CN100451295C - 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法 - Google Patents

一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法 Download PDF

Info

Publication number
CN100451295C
CN100451295C CNB2007101392274A CN200710139227A CN100451295C CN 100451295 C CN100451295 C CN 100451295C CN B2007101392274 A CNB2007101392274 A CN B2007101392274A CN 200710139227 A CN200710139227 A CN 200710139227A CN 100451295 C CN100451295 C CN 100451295C
Authority
CN
China
Prior art keywords
excavation
tunnel
preliminary bracing
inverted arch
digging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2007101392274A
Other languages
English (en)
Other versions
CN101105131A (zh
Inventor
霍玉华
高治双
祁玺剑
张金柱
徐家定
黄直久
王毅东
彭斌
鲍海荣
赵华锋
吴波
赵香萍
商崇伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CNB2007101392274A priority Critical patent/CN100451295C/zh
Publication of CN101105131A publication Critical patent/CN101105131A/zh
Application granted granted Critical
Publication of CN100451295C publication Critical patent/CN100451295C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及铁路隧道施工技术领域,具体为一种适用于铁路大断面Ⅳ、Ⅴ级围岩隧道的开挖方法,解决现有铁路隧道开挖方法存在作业空间狭小、工效低,施工方法不灵活、进度不稳定,围岩易变形以及操作不便等问题,包括超前支护,开挖弧形导坑并预留核心土;交错开挖中台阶左右边墙并预留核心土;交错开挖下台阶左右边墙并预留核心土;依次开挖上、中、下台阶预留核心土;开挖仰拱并施作初期支护等步骤,本发明施工空间大,可以多作业面平行作业,工效较高;在地质条件发生变化时,便于灵活、及时转换其他施工方法;预留核心土,保持左右错位开挖,利于开挖工作面稳定;当围岩变形较大时,在保证安全和满足净空断面的前提下,可尽快调整闭合时间。

Description

一种适用于铁路大断面Ⅳ、Ⅴ级围岩隧道的开挖方法
技术领域
本发明涉及铁路隧道施工技术领域,具体为一种适用于铁路大断面IV、V级围岩隧道的开挖方法。
背景技术
公知,铁路小断面软弱围岩隧道的开挖方法主要有环形开挖预留核心土法和台阶法等,当这两种方法用于铁路大断面IV、V级围岩隧道开挖时,其中环形开挖预留核心土法存在的问题有:(1)作业空间狭小,不利于大型机械的施工,工效低,围岩暴露时间长;(2)地质条件发生变化时,不能灵活、及时地转换施工方法,进度不稳定;(3)上台阶太高,施工不便;台阶法存在的问题有:(1)不适应于IV、V级围岩大断面铁路隧道,不能有效抑制围岩的变形;(2)地质条件发生变化时,不能灵活、及时地转换施工方法,进度不稳定;(3)上台阶太高,未预留核心土,围岩易失稳;(4)上台阶支护施作需加工作业平台,操作不便。
发明内容
本发明为了解决现有铁路隧道开挖方法用于IV、V级围岩大断面隧道时存在作业空间狭小、工效低,施工方法不灵活、进度不稳定,围岩易变形、不稳定以及施工操作不便等问题,提供一种适用于铁路大断面IV、V级围岩隧道的开挖方法。
本发明是采用如下技术方案实现的:一种适用于铁路大断面IV、V级(一般为100-180平方米)围岩隧道的开挖方法,首先按照隧道跨度和高度要求,将围岩挖成具有下台阶和中台阶的阶梯状,然后包括以下步骤:A、施作超前支护后,沿开挖轮廓线环向开挖拱部弧形导坑,弧形导坑的高度为3.0-4.0m,开挖后立即喷射3-5cm厚的混凝土封闭,并在中间预留上台阶核心土,同时施作拱部初期支护,核心土沿隧道纵向长度为3-5m,宽度为隧道开挖跨度的1/3-1/2,高度为1.5-2.5m,根据初期支护钢架间的距离确定开挖循环进尺,为保证隧道开挖安全,防止围岩松弛,按设计要求做好超前支护,特别在断层、破碎带、浅埋段等自稳性较差和富水地层中,应加强超前支护;B、在拱部支护的保护下,交错开挖中台阶左右边墙并预留核心土,同时施作初期支护,开挖循环进尺应根据初期支护钢架间距确定,开挖过程中保持左右错开2-3m;C、交错开挖下台阶左右边墙并预留核心土,同时施作初期支护,开挖进尺应根据初期支护钢架间距确定,开挖过程中保持左右错开2-3m,此距离如果太长,当地质条件发生变化时,不能及时、灵活的闭合,以构成稳固的支护体系;该距离如果太短,易发生左右拱同时悬空,产生掉拱现象,极不安全;D、依次开挖上、中、下台阶预留的核心土;E、开挖仰拱并施作初期支护,使支护体系封闭成环;按照上述步骤不断循环,实现隧道的开挖。
所述的开挖前按照隧道跨度和高度要求,将围岩挖成具有下台阶和中台阶的阶梯状,这是本领域的技术人员很容易实现的,然后按照上述工法循环开挖;上述步骤中预留核心土的目的是防止正面土体往外挤压,造成塌方;上述作为上台阶的核心土的大小是该申请人在受力结构的理论分析基础上,经过长期实践经验总结出来的。
所述初期支护的施工步骤为:a.初喷混凝土以封闭岩面;b.施作系统锚杆,挂设钢筋网;c.安装钢架;d.二次喷射混凝土。
所述仰拱施工步骤为:a.隧底开挖:采用全幅分段施工,上面铺设仰拱栈桥,每循环开挖长度控制在2~3米;b.仰拱初期支护:隧底开挖后,及时清除虚碴、杂物、泥浆、积水,立即初喷3~5cm厚混凝土封闭岩面,然后安装仰拱钢架并喷射混凝土,使初期支护及时闭合成环;c.仰拱混凝土浇筑:每循环浇筑长度为4~6m,仰拱成型采用浮放模板支架;d.仰拱填充混凝土浇筑:浇筑前应清除仰拱表面的杂物和积水,待仰拱混凝土终凝后连续浇筑,一次成型,填充混凝土强度达到5MPa后允许行人通行,达到设计强度的100%后允许车辆通行,仰拱填充表面坡度应符合设计要求,应平顺、排水通畅、不积水。
所述中台阶和下台阶的开挖高度为隧道总开挖高度减去上台阶开挖高度后平均分配得到,一般为3.0-3.5m。
根据初期支护钢架间的距离,确定上述各步骤的开挖循环进尺一般为不大于1.5m,当围岩较稳定、牢固时,支护钢架间的距离较大,开挖循环进尺较大;当围岩较松动、易变形时,支护钢架间的距离短,支护较密,开挖循环进尺较小。
与现有技术相比,本发明具有以下优点:
(1)施工空间大,方便机械化施工,可以多作业面平行作业,部分软岩或土质地段可以采用挖掘机直接开挖,工效较高;
(2)在地质条件发生变化时,便于灵活、及时转换其他施工方法;
(3)适应不同跨度和多种断面形式,尤其适用于IV、V级断面围岩的隧道开挖,而且初期支护工序操作简便;
(4)在台阶法开挖的基础上,预留核心土,并保持左右错位开挖,利于开挖工作面稳定;
(5)当围岩变形较大时,在保证安全和满足净空断面的前提下,可尽快调整闭合时间。
附图说明
图1为本发明的开挖透视图
图2为本发明施工工序正面示意图
图3为本发明施工工序纵断面示意图
图4为本发明施工工序俯视图
图5为本发明监控量测过程中净空变化测点布置示意图
图中:1-上台阶  2-弧形导坑  3-中台阶  4-核心土  5-下台阶  6-核心土  7-仰拱  8-超前支护  9-初期支护
具体实施方式
一种适用于铁路大断面IV、V级围岩隧道的开挖方法,首先按照隧道跨度和高度要求,将围岩挖成具有下台阶5和中台阶3的阶梯状,然后包括以下步骤:A、施作超前支护后,沿开挖轮廓线环向开挖拱部弧形导坑2,弧形导坑2的高度为3.0-4.0m,开挖后立即喷射3-5cm厚的混凝土封闭,并在中间预留作为上台阶1的核心土,同时施作拱部初期支护,核心土沿隧道纵向长度为3-5m,宽度为隧道开挖跨度的1/3-1/2,高度为1.5-2.5m,根据初期支护钢架间的距离确定开挖循环进尺;B、在拱部支护的保护下,交错开挖中台阶3左右边墙并预留核心土4,同时施作初期支护,开挖循环进尺应根据初期支护钢架间距确定,开挖过程中保持左右错开2-3m;C、交错开挖下台阶5左右边墙并预留核心土6,同时施作初期支护,开挖进尺应根据初期支护钢架间距确定,开挖过程中保持左右错开2-3m;D、依次开挖上、中、下台阶预留的核心土;E、开挖仰拱7并施作初期支护,使支护体系封闭成环;按照上述步骤不断循环,实现隧道的开挖。上述各步骤的开挖循环进尺一般为不大于1.5m。所述中台阶3和下台阶5的开挖高度为隧道总开挖高度减去上台阶1开挖高度后平均分配得到,一般为3.0-3.5m。
所述初期支护的施工步骤为:a.初喷混凝土以封闭岩面;b.施作系统锚杆,挂设钢筋网;c.安装钢架;d.二次喷射混凝土。所述仰拱施工步骤为:a.隧底开挖:采用全幅分段施工,上面铺设仰拱栈桥,每循环开挖长度控制在2~3米;b.仰拱初期支护:隧底开挖后,及时清除虚碴、杂物、泥浆、积水,立即初喷3~5cm厚混凝土封闭岩面,然后安装仰拱钢架并喷射混凝土,使初期支护及时闭合成环;c.仰拱混凝土浇筑:每循环浇筑长度为4~6m,仰拱成型采用浮放模板支架;d.仰拱填充混凝土浇筑:浇筑前应清除仰拱表面的杂物和积水,待仰拱混凝土终凝后连续浇筑,一次成型。
在上述工艺过程中,监控测量工作必须紧跟开挖、支护作业进行布点和监测,量测数据运用工程类比法及时分析、反馈,调整支护参数,以保证施工和结构安全。
1、量测项目,见表1
表1监控量测项目
  序号   监测项目   测量方法和仪表   测量精度   备注
  1   洞内、外观察   现场观察,地质罗盘
2   初期支护拱(墙)脚净空   米用非接触无尺量测法,全站仪 0.1mm
  3   初期支护拱顶净空   采用非接触无尺量测法,全站仪 0.1mm
4 地表观测点 水准测量的方法,水准仪 1mm  浅埋隧道(H<sub>0</sub>≤2b)、洞口段、下穿高速公路(建筑物)段必测
  5   仰拱观测点   水准测量的方法,水准仪   1mm
注:H0-隧道埋深;b-隧道最大开挖宽度。
2、净空变化测点布置,如图5所示:其中A为拱顶观测点,E为仰拱观测点,
(1)上部弧形导坑开挖并施作拱部初期支护后,布设拱顶下沉A点和第一条净空量测基线B-B’,在3~6h内取得初读数;
(2)中台阶开挖并施作墙部初期支护后,布设第二条净空量测基线C-C’,在3~6h内取得初读数;
(3)下台阶开挖并施作墙部初期支护后,布设第三条净空量测基线D-D’,在3~6h内取得初读数;
(4)仰拱开挖并施作初期支护后布设仰拱观测点E;
(5)其它量测项目应在开挖后12h内取得初读数,最迟不得超过24h,且在下一循环开挖前完成;
(6)拱(墙)脚净空变化、拱顶和仰拱观测点应布设在同一断面,便于分析、比较。
3、量测频率
各测点取得初读数据后,量测频率按照“位移速度”和“量测断面距开挖面距离”要求进行控制,量测频率见表2。当变形突变时,应加大量测频率。
表2量测频率
Figure C20071013922700091
注:b-隧道开挖跨度。
4、量测数据分析、整理,绘制位移-时态曲线
(1)一般情况下开挖中台阶时,A点和B-B’基线会发生突变,中台阶墙部初期支护施作完成后,变形趋于平缓;开挖下台阶时,A点和C-C’基线会发生突变,下台阶墙部初期支护施作完成后,变形趋于平缓;隧底开挖时,A点和D-D’基线会发生突变,仰拱初期支护施作完成,支护全环闭合后,变形趋于平缓。
(2)绘制位移-时间变化曲线
获取现场量测数据后,及时绘制位移~时间关系曲线,通过回归分析预测最终位移值和各阶段的位移速率。
5、监控量测管理
围岩稳定性的综合判别,应根据量测结果按以下方式进行。
(1)按变形管理等级指导施工,见表3。
表3
Figure C20071013922700101
(2)根据位移变化速度判别
①净空变化速度大于5mm/d时,为变形突变,应加强支护;
②拱(墙)脚处净空变化速度小于0.2mm/d,拱顶下沉速度小于0.15mm/d,围岩基本稳定。
(3)根据位移时态曲线的形态来判别
①当位移速率不断下降时(du2/d2t<0),趋于稳定状态;
②当位移速率保持不变时(du2/d2t=0),不稳定,应加强支护;
③当位移速率不断上升时(du2/d2t>0),危险状态,应立即停止开挖,加强支护。

Claims (5)

1、一种适用于铁路大断面IV、V级围岩隧道的开挖方法,其特征是首先按照隧道跨度和高度要求,将围岩挖成具有下台阶(5)和中台阶(3)的阶梯状,然后包括以下步骤:
A、施作超前支护后,沿开挖轮廓线环向开挖拱部弧形导坑(2),弧形导坑(2)的高度为3.0-4.0m,开挖后立即喷射3-5cm厚的混凝土封闭,并在中间预留作为上台阶(1)的核心土,同时施作拱部初期支护,核心土沿隧道纵向长度为3-5m,宽度为隧道开挖跨度的1/3-1/2,高度为1.5-2.5m,根据初期支护钢架间的距离确定开挖循环进尺;
B、在拱部支护的保护下,交错开挖中台阶(3)左右边墙并预留核心土(4),同时施作初期支护,开挖循环进尺应根据初期支护钢架间距确定,开挖过程中保持左右错开2-3m;
C、交错开挖下台阶(5)左右边墙并预留核心土(6),同时施作初期支护,开挖进尺应根据初期支护钢架间距确定,开挖过程中保持左右错开2-3m;
D、依次开挖上、中、下台阶预留的核心土;
E、开挖仰拱(7)并施作初期支护,使支护体系封闭成环;按照上述步骤不断循环,实现隧道的开挖。
2、根据权利要求1所述的一种适用于铁路大断面IV、V级围岩隧道的开挖方法,其特征是所述初期支护的施工步骤为:
a.初喷混凝土以封闭岩面;
b.施作系统锚杆,挂设钢筋网;
c.安装钢架;
d.二次喷射混凝土。
3、根据权利要求1或2所述的一种适用于铁路大断面IV、V级围岩隧道的开挖方法,其特征是所述仰拱施工步骤为:
a.隧底开挖:采用全幅分段施工,上面铺设仰拱栈桥,每循环开挖长度控制在2~3米;
b.仰拱初期支护:隧底开挖后,及时清除虚碴、杂物、泥浆、积水,立即初喷3~5cm厚混凝土封闭岩面,然后安装仰拱钢架并喷射混凝土,使初期支护及时闭合成环;
c.仰拱混凝土浇筑:每循环浇筑长度为4~6m,仰拱成型采用浮放模板支架;
d.仰拱填充混凝土浇筑:浇筑前应清除仰拱表面的杂物和积水,待仰拱混凝土终凝后连续浇筑,一次成型。
4、根据权利要求1或2所述的一种适用于铁路大断面IV、V级围岩隧道的开挖方法,其特征是所述中台阶(3)和下台阶(5)的开挖高度为隧道总开挖高度减去上台阶(1)开挖高度后平均分配得到。
5、根据权利要求1或2所述的一种适用于铁路大断面IV、V级围岩隧道的开挖方法,其特征是上述各步骤的开挖循环进尺为不大于1.5m。
CNB2007101392274A 2007-08-17 2007-08-17 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法 Active CN100451295C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007101392274A CN100451295C (zh) 2007-08-17 2007-08-17 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007101392274A CN100451295C (zh) 2007-08-17 2007-08-17 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法

Publications (2)

Publication Number Publication Date
CN101105131A CN101105131A (zh) 2008-01-16
CN100451295C true CN100451295C (zh) 2009-01-14

Family

ID=38999188

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007101392274A Active CN100451295C (zh) 2007-08-17 2007-08-17 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法

Country Status (1)

Country Link
CN (1) CN100451295C (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121661A (zh) * 2016-08-08 2016-11-16 中铁二局集团有限公司 一种隧道洞身通过黄土分界面富水地层施工方法

Families Citing this family (61)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101638989B (zh) * 2009-07-30 2012-01-18 中铁二局股份有限公司 海底隧道断层破碎带铣挖支护施工方法
CN101864963B (zh) * 2010-05-26 2013-04-10 中铁二十三局集团第三工程有限公司 一种大断面黄土隧道施工方法
CN102287194B (zh) * 2010-06-21 2013-07-03 福建省信通工程建设有限公司 一种多跨平拱隧道的施工方法
CN102042019B (zh) * 2010-11-11 2012-12-19 中铁十三局集团第四工程有限公司 浅埋大跨软塑粘土隧道两台阶五步开挖的施工方法
CN102134998B (zh) * 2011-04-27 2012-11-07 中铁二局股份有限公司 一种风积沙隧道的施工方法
CN102226399A (zh) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 软岩四线大跨隧道三台阶以索代撑开挖施工方法
CN102312672A (zh) * 2011-09-23 2012-01-11 中南大学 一种适应复杂多变地质条件的大断面隧道快速施工方法
CN102392651B (zh) * 2011-11-30 2014-10-22 中铁五局(集团)有限公司 全风化花岗岩隧道开挖施工方法
CN102562074A (zh) * 2012-02-03 2012-07-11 中铁四局集团第二工程有限公司 大断面隧道上硬下软复合地层的施工方法
CN102606162B (zh) * 2012-02-08 2014-09-17 中铁四局集团第二工程有限公司 隧道软弱围岩浅埋易坍塌区快速施工方法
CN102587924A (zh) * 2012-03-26 2012-07-18 中铁十三局集团第四工程有限公司 浅埋高含水量粘性土隧道施工方法
CN102650210B (zh) * 2012-05-11 2014-07-09 中铁十二局集团有限公司 下半断面为干燥粉细砂层隧道的施工方法
CN102808627A (zh) * 2012-09-07 2012-12-05 中国建筑第八工程局有限公司 钢管棚暗挖施工方法
CN102953737B (zh) * 2012-10-22 2015-05-13 中铁三局集团有限公司 Ⅵ级富水围岩隧道仰拱施工方法
CN102926758A (zh) * 2012-11-19 2013-02-13 沐俊卫 综炮联合台阶法巷道掘进施工方法
CN103234403B (zh) * 2013-04-24 2014-11-19 中国科学院武汉岩土力学研究所 一种公路隧道静态爆破施工方法
CN103277106B (zh) * 2013-06-21 2015-07-01 云南云岭高速公路建设集团有限公司 公路隧道三台阶五步开挖施工方法
CN103291309B (zh) * 2013-06-28 2015-03-25 中铁隧道集团一处有限公司 水封洞库主洞室轴线一侧存在不良地质体的处理方法
CN103628890A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 软弱千枚岩隧道开挖变形控制方法
CN103628889A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 千枚岩地层隧道开挖快速封闭方法
CN104500079A (zh) * 2014-11-26 2015-04-08 中国电建集团成都勘测设计研究院有限公司 浅埋偏压倾倒变形散体及强卸荷岩石结构中的隧道开挖法
CN104653187B (zh) * 2014-12-11 2017-06-06 中铁十九局集团有限公司 富水砂层地质大断面隧道开挖方法
CN104775830B (zh) * 2014-12-12 2017-08-04 中铁十九局集团有限公司 一种膨胀土隧道拱墙初期支护施工方法
CN104405411B (zh) * 2014-12-15 2017-05-10 中铁第四勘察设计院集团有限公司 超大变断面隧道支护结构
CN104612698B (zh) * 2015-01-24 2018-01-16 杭州天恒投资建设管理有限公司 一种浅埋暗挖隧道上台阶中隔壁施工方法
CN104790978B (zh) * 2015-03-10 2017-03-08 中铁九局集团有限公司 小净距立体交叉隧道环形导坑施工方法
CN104963689A (zh) * 2015-07-07 2015-10-07 中铁十九局集团第二工程有限公司 隧道三台阶七步开挖方法
CN105888696A (zh) * 2016-06-30 2016-08-24 中铁四局集团第四工程有限公司 大截面隧道的施工方法
CN106246201A (zh) * 2016-08-22 2016-12-21 北京市市政工程研究院 小型溶洞位于开挖隧道四周时隧道的开挖与溶洞处理方法
CN106246192A (zh) * 2016-08-22 2016-12-21 北京市政路桥股份有限公司 一种隧道基础及底板下的大型溶洞处理及隧道开挖方法
CN107152281A (zh) * 2017-05-04 2017-09-12 中铁二院工程集团有限责任公司 破碎岩石隧道下穿陡坡高桥墩的施工方法
CN106979021B (zh) * 2017-05-05 2019-01-11 中铁十二局集团有限公司 大断面黄土隧道开挖及初期支护快速封闭成环方法
CN107013222A (zh) * 2017-05-28 2017-08-04 中铁五局集团有限公司 一种紧邻既有铁路的滇中红层隧道铣挖施工方法
CN107288653B (zh) * 2017-06-27 2023-04-14 中铁十一局集团第四工程有限公司 一种软弱围岩大断面隧道双侧壁导坑三台阶法开挖支护结构及施工方法
CN107560510A (zh) * 2017-08-25 2018-01-09 中铁十二局集团有限公司 一种隧道大断面段施工方法及其断面爆破布置
CN107387096A (zh) * 2017-09-21 2017-11-24 中铁四局集团有限公司 大断面黄土隧道三台阶拉中槽开挖作业面及其施工方法
CN107829748B (zh) * 2017-11-10 2019-07-02 长安大学 一种适用于漂卵石地层大断面隧道的互补循环式开挖方法
CN108286442B (zh) * 2018-01-08 2020-01-31 中铁十二局集团有限公司 适用于软弱围岩隧道两台阶一次快速封闭成环的开挖方法
CN108343035A (zh) * 2018-02-11 2018-07-31 中铁十二局集团有限公司 浅埋隧道下穿河流施工方法
CN108756894B8 (zh) * 2018-04-23 2019-12-24 中铁二十五局集团第一工程有限公司 隧道微三台阶上部核心土施工工法
CN109162720A (zh) * 2018-08-24 2019-01-08 中铁十六局集团第三工程有限公司 一种双跨简支仰拱栈桥施工方法
CN109026029A (zh) * 2018-10-09 2018-12-18 中建地下空间有限公司 一种适用于破碎围岩隧道开挖支护的施工方法
CN109339798B (zh) * 2018-10-19 2021-05-04 重庆大学 一种用于改进隧道双侧壁导坑法施工中核心土解除方法
CN109488313B (zh) * 2018-12-10 2020-07-10 中交一公局桥隧工程有限公司 一种ⅴ级围岩微台阶法开挖施工工艺
CN109882185A (zh) * 2019-03-25 2019-06-14 中铁十六局集团第二工程有限公司 一种高地应力条件下岩质软硬不均隧道的施工方法
CN110043269B (zh) * 2019-05-05 2020-07-03 中交第三航务工程局有限公司 一种高速公路隧道洞身的开挖施工工艺
CN110030000B (zh) * 2019-05-29 2020-06-16 西南交通大学 一种用于小断面隧道的一步距一回头施工方法
CN110230496A (zh) * 2019-06-14 2019-09-13 中国铁建大桥工程局集团有限公司 一种大断面软弱地层隧道三台阶四步交错施工方法
CN110778320A (zh) * 2019-11-27 2020-02-11 中铁五局集团有限公司 一种软弱围岩隧道三台阶带仰拱同步开挖支护施工方法
CN111322090B (zh) * 2020-02-28 2021-12-03 中铁五局集团第一工程有限责任公司 一种用于控制高地应力硬质岩隧道围岩变形的支护方法
CN111456743A (zh) * 2020-03-12 2020-07-28 中铁四局集团有限公司 一种大断面黄土隧道微台阶开挖方法及其台阶结构
CN111677530B (zh) * 2020-06-04 2022-04-26 中铁六局集团太原铁路建设有限公司 隧道贯通段三台阶临时仰拱安全施工工法
CN112963155B (zh) * 2021-03-05 2023-05-23 北京城建设计发展集团股份有限公司 土岩复合地层大断面隧道拱部开挖琵琶工法
CN113279786B (zh) * 2021-06-10 2023-03-10 中国十七冶集团有限公司 一种提高隧道作业面核心土稳定性的装置
CN113586068B (zh) * 2021-09-09 2022-12-06 中国水利水电第四工程局有限公司 一种等高隧洞交岔口开挖支护施工方法
CN113818887A (zh) * 2021-09-10 2021-12-21 中国有色金属工业昆明勘察设计研究院有限公司 一种复杂地质条件的超大断面隧道施工工艺
CN114282287A (zh) * 2021-11-19 2022-04-05 中交一公局桥隧工程有限公司 V级围岩隧道台阶法施工初支变形分级控制标准确定方法
CN114183172A (zh) * 2021-11-22 2022-03-15 中铁十六局集团第三工程有限公司 一种基于安全步距的大变形隧道施工方法
CN114233297A (zh) * 2021-12-09 2022-03-25 中建八局南方建设有限公司 一种大跨度小净距浅埋隧道开挖施工方法
CN114278313B (zh) * 2021-12-31 2024-07-30 北京住总集团有限责任公司 一种基于区间不同开挖工法转换的支护体系及施工方法
CN114320317A (zh) * 2022-01-21 2022-04-12 中交四航局第一工程有限公司 短台阶超大断面隧道软弱围岩段施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3996751A (en) * 1973-07-30 1976-12-14 Tore Jerker Hallenius Method of blasting and reinforcing rock cavities
CN1873187A (zh) * 2006-06-23 2006-12-06 董淑练 隧道施工的开挖方法
CN1952350A (zh) * 2006-10-27 2007-04-25 中铁四局集团有限公司 小断面突变至大断面隧道快速施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3996751A (en) * 1973-07-30 1976-12-14 Tore Jerker Hallenius Method of blasting and reinforcing rock cavities
CN1873187A (zh) * 2006-06-23 2006-12-06 董淑练 隧道施工的开挖方法
CN1952350A (zh) * 2006-10-27 2007-04-25 中铁四局集团有限公司 小断面突变至大断面隧道快速施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
七步流水作业法在道南黄土隧道施工中的应用. 帅建兵.公路隧道,第4期. 2006
七步流水作业法在道南黄土隧道施工中的应用. 帅建兵.公路隧道,第4期. 2006 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106121661A (zh) * 2016-08-08 2016-11-16 中铁二局集团有限公司 一种隧道洞身通过黄土分界面富水地层施工方法

Also Published As

Publication number Publication date
CN101105131A (zh) 2008-01-16

Similar Documents

Publication Publication Date Title
CN100451295C (zh) 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN104612698B (zh) 一种浅埋暗挖隧道上台阶中隔壁施工方法
CN106194196B (zh) 一种横穿隧道洞身的大型溶洞处理与开挖方法
CN104500077B (zh) 一种浅埋暗挖隧道穿越平房区施工方法
CN102606162B (zh) 隧道软弱围岩浅埋易坍塌区快速施工方法
CN101994513B (zh) 上半断面完成全断面帷幕注浆隧道施工方法
CN105443132A (zh) 浅埋暗挖十字横撑隧道施工方法
CN105781571A (zh) 一种软岩变形隧道衬砌支护拆换拱施工方法
CN110617072B (zh) 一种极小净距斜下穿既有运营隧道的隧道开挖施工方法
CN103410524B (zh) 一种软岩隧道施工方法
CN110130927A (zh) 一种炭质板岩隧道大变形控制施工方法
CN102312672A (zh) 一种适应复杂多变地质条件的大断面隧道快速施工方法
CN106246192A (zh) 一种隧道基础及底板下的大型溶洞处理及隧道开挖方法
CN102996133A (zh) 适用于软弱围岩隧道斜井与正洞交汇处的施工方法
CN106121675A (zh) 小型溶洞位于开挖隧道仰拱底时隧道开挖与溶洞处理方法
CN101798930A (zh) 一种隧道高压富水断层带的快速施工方法
CN105781573A (zh) 铁路下穿公路隧道双层套管加筋双管棚跟管钻进施工方法
CN104389610A (zh) 一种穿越运营高速公路隧道超短台阶施工方法
CN106246191B (zh) 一种洞体深浚、充填丰满的大型溶洞处理及隧道开挖方法
CN204941545U (zh) 车站暗挖施工系统
CN106968691A (zh) 一种高寒地区粉质粘土隧道改良cd法施工方法
CN105971611A (zh) 地铁隧道近距离下穿既有铁路干线路基沉降控制方法
CN109113757A (zh) 隧道交叉口快速施工方法
CN108643940A (zh) 超大断面浅埋软弱围岩隧道井字形双侧壁支护体系及隧道施工方法
CN103410522A (zh) 浅埋暗挖法连续近距离下穿铁路桥的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20090605

Address after: No 130, West Mining street, Taiyuan City, Shanxi Province: 030024

Co-patentee after: THE 2ND ENGINEERING CO.,LTD. OF CHINA RAILWAY 12TH BUREAU GROUP

Patentee after: CHINA RAILWAY 12TH BUREAU GROUP Co.,Ltd.

Address before: No 130, West Mining street, Taiyuan City, Shanxi Province: 030024

Patentee before: CHINA RAILWAY 12TH BUREAU GROUP Co.,Ltd.