CN105971611A - 地铁隧道近距离下穿既有铁路干线路基沉降控制方法 - Google Patents
地铁隧道近距离下穿既有铁路干线路基沉降控制方法 Download PDFInfo
- Publication number
- CN105971611A CN105971611A CN201610353430.0A CN201610353430A CN105971611A CN 105971611 A CN105971611 A CN 105971611A CN 201610353430 A CN201610353430 A CN 201610353430A CN 105971611 A CN105971611 A CN 105971611A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- railway
- construction
- train
- roadbed settlement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/003—Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/001—Improving soil or rock, e.g. by freezing; Injections
Abstract
本发明公开了一种地铁隧道近距离下穿既有铁路干线路基沉降控制方法,包括地质勘察→超前物探→理论计算→隧道施工→列车限速→监控量测→优化隧道施工共七个步骤,构成一套完整的地铁隧道近距离下穿既有铁路干线路基沉降控制体系。在施工前先要掌握前方地质构造情况,再依据理论计算,精确掌握最大允许下沉量,从而有针对性的采用施工措施,达到施工人员与机械最优配置,同时通过计算机模拟方法,分析上行列车车速产生的动载荷对路基沉降量的影响,提出列车限速要求,最后进行铁路路基下沉量监测,依据监测数据,及时优化施工工艺。优化资源配置,提高工效,保证安全质量,降低施工成本,减小上行列车行驶产生的动荷载对铁路路基下沉量不良影响。
Description
技术领域
本发明涉及工程施工技术领域,具体涉及一种在既有铁路干线下方近距离新建地铁隧道的路基沉降控制方法。
背景技术
目前,地铁隧道下穿既有铁路干线的路基沉降控制方法多采用地表注浆对既有铁路线进行预加固处理,采用大管棚、中管棚和小导管对隧道进行超前注浆支护,再对隧道进行各种浅埋暗挖施工。该方法仅仅停留在具体加固地表和稳定隧道开挖层面上,具有如下不足:
(1)施工方法仅适用典型工程,通用性差;
(2)未重视前期地质勘察的重要性,较少涉及超前地质物探,无法提前获取局部地质异常信息并采取对应施工措施;
(3)未精确计算现场铁路线路基理论最大允许下沉量;
(4)未考虑上行列车动荷载对铁路线路基沉降值的影响。
发明内容
本发明旨在建立一套近距离下穿既有铁路干线路基沉降控制技术体系,全面、及时、准确地掌握工作面前方地质构造特征,从而优化资源配置,提高工效;科学计算典型铁路线路基最大允许下沉量,在确保安全质量的前提下,最大程度节约施工成本;限制上行列车行驶速度,减小动荷载对铁路路基下沉量的影响。
为此,本发明所采用的技术方案为:一种地铁隧道近距离下穿既有铁路干线路基沉降控制方法,包括以下步骤:
第一步:地质勘察;
第二步:超前物探::在常规地质勘察的基础上,辅助以工作面超前物探方法,达到全方位、无死角地掌握工作面前方的地质构造信息;
第三步:理论计算:计算既有铁路干线路基最大允许沉降量,计算公式为[Smax]=W[δ]/L,其中[δ]为铁路轨道允许10m弦量测的最大矢度值,L为量测弦长,W为沉降槽宽度,W=5i,i为地表沉降槽宽度系数,即沉降槽曲线反弯点至隧道中心线的水平距离,D为隧道直径;Z0为隧道中心至地表深度;将计算出的最大允许沉降量与铁路路基下沉量不超过±3mm的行业标准进行对比,当计算出的最大允许沉降量大于等于行业标准允许的下沉量时,以行业标准允许的下沉量为准,当计算出的最大允许沉降量小于行业标准允许的下沉量时,以计算出的最大允许沉降量为准;
第四步:隧道施工:
(a)地表加固处理:隧道施工前,采用地表注浆对既有铁路线进行预加固处理;
(b)超前支护:首先采用大管棚结合小导管对将开挖隧道进行超前注浆支护,再根据现场地质情况,采用匹配的浅埋暗挖法对隧道进行开挖,在开挖隧道内采用地纵梁将隧道上方的铁路架空;
(c)隧道支护:首先采用锚网喷技术对开挖隧道进行初期支护,再进行补充注浆,最后再进行二次衬砌施工;
第五步:列车限速:基于计算机数值仿真技术,对上行列车行驶过程中由动载荷引发路基沉降量进行计算,确定列车最大通过时速;
第六步:监控量测:对铁路路基下沉量实时进行监控量测;
第七步:优化隧道施工:根据监控量测的下沉数据,及时优化隧道施工。
作为上述方案的优选,所述第二步中的超前物探方法为电阻率法、瞬变电磁法或地质雷达法,均为常用的超前物探法。
进一步,所述第四步中(b)的超前支护,大管棚在待开挖隧道拱部环向间隔设置,在地铁隧道与既有铁路干线交叉点前后10m范围内,大管棚环向间距缩短,通过加密方式加强支护效果。
所述第四步中(c)的隧道支护,在进行二次衬砌施工前,采用地质雷达扫描法对注浆效果和初期支护背后进行检测,保证质量,有效控制铁路路基后期沉降。
本发明的有益效果:建立了一种近距离下穿既有铁路干线路基沉降控制的通用性技术体系;可以优化资源配置,提高工效;既保证安全质量,又能够最大程度降低施工成本;减小上行列车行驶产生的动荷载对铁路路基下沉量不良影响。
附图说明
图1是本发明进行第四步的超前支护后的效果图。
图2是本发明进行第四步的隧道支护后的效果图(省略小导管)。
图3是本发明进行第三步理论计算时沉降槽宽度中各参数的示意图。
具体实施方式
下面通过实施例并结合附图,对本发明作进一步说明:
一种地铁隧道近距离下穿既有铁路干线路基沉降控制方法,依次包括地质勘察→超前物探→理论计算→隧道施工→列车限速→监控量测→优化隧道施工共七个步骤,构成一套完整的地铁隧道近距离下穿既有铁路干线路基沉降控制体系。在施工前先要掌握前方地质构造情况,再依据理论计算,精确掌握最大允许下沉量,从而有针对性的采用施工措施,达到施工人员与机械最优配置,同时通过计算机模拟方法,分析上行列车车速产生的动载荷对路基沉降量的影响,提出列车限速要求,最后进行铁路路基下沉量监测,依据监测数据,及时优化施工工艺。
第一步:地质勘察:沿待勘察路线间隔一定距离钻孔并进行地质勘察,为常规的地质勘察方法,在大范围内对地质构造信息进行一个相对粗略的了解。
第二步:超前物探:以地质勘察的钻孔为中心,进行一定半径范围内的超前物探。在常规地质勘察的基础上,辅助以工作面超前物探方法,达到全方位、无死角地掌握工作面前方的地质构造信息达到全方位、无死角地掌握工作面前方的地质构造信息。超前物探相比资质勘察,由于在小范围内进行,探测地质构造信息更精确,既保证安全施工,又可以合理调配资源。常规地质勘察都是间隔一定距离进行钻孔,勘察精度与施工精度存在一定差距,采用超前物探手段可以很好的弥补该方面的不足。地铁隧道沿途差异性很大,如出现断层、裂隙、水和有害气体瓦斯等异常地质情况,仅依靠地质勘察无法准确掌握待开挖路段的地质构造信息。假设不进行超前物探,在隧道施工过程中出现漏水等异常现象,再返回进行地质勘察,既浪费时间,又增加了施工成本。超前物探方法为电阻率法、瞬变电磁法或地质雷达法等。
第三步:理论计算:计算既有铁路干线路基最大允许沉降量,计算公式为[Smax]=W[δ]/L,其中[δ]为铁路轨道允许10m弦量测的最大矢度值,L为量测弦长,W为沉降槽宽度,W=5i,i为地表沉降槽宽度系数,即沉降槽曲线反弯点至隧道中心线的水平距离,D为隧道直径;Z0为隧道中心至地表深度。W中各参数的获取如图3所示。《铁路线路维修规则》中规定,列车时速小于等于120Km/h时,正线到发线的线路轨道前后高低差用L=10m弦量测,最大矢度值[δ]不应超过4mm。
现目前,铁路路基下沉量采用不超过±3mm的行业标准进行,鉴于该数值有时与现场实际差异较大,因此,将计算出的最大允许沉降量与铁路路基下沉量不超过±3mm的行业标准进行对比,当计算出的最大允许沉降量大于等于行业标准允许的下沉量时,以行业标准允许的下沉量为准,当计算出的最大允许沉降量小于行业标准允许的下沉量时,以计算出的最大允许沉降量为准。
第四步:隧道施工:
(a)地表加固处理:隧道施工前,采用地表注浆对既有铁路线进行预加固处理。
(b)超前支护:首先采用大管棚1结合小导管2对将开挖隧道进行超前注浆支护,再根据现场地质情况,采用匹配的浅埋暗挖法对隧道进行开挖,在开挖隧道内采用地纵梁3将隧道上方的铁路架空(如图1所示)。超前支护采用大管棚结合小导管对将开挖隧道进行超前注浆支护,并采用匹配的浅埋暗挖法对隧道进行开挖,是隧道施工中常用的超前支护方法,在此不再赘述。最好是,大管棚在待开挖隧道拱部环向间隔设置,在地铁隧道与既有铁路干线交叉点前后10m范围内,大管棚环向间距缩短,大管棚设置得更加密集,通过加密方式加强支护效果。
(c)隧道支护:首先采用锚网喷技术对开挖隧道进行初期支护4,再进行补充注浆,最后再进行二次衬砌5施工(如图2所示)。新建隧道初期采用工字钢、砂浆锚杆6、喷射混凝土、钢筋网片相结合的方式进行初期支护,统称为锚网喷技术,属于现有技术;初期支护完成1-2环后,应立即进行补充注浆,避免初支后有空隙或不密实现象。最好是,在进行二次衬砌施工前,采用地质雷达扫描法对注浆效果和初期支护背后进行检测,保证质量,有效控制铁路路基后期沉降。图2中,保留大管棚1,省略图1的小导管2,是为了避免小导管2影响砂浆锚杆6的展示效果。
第五步:列车限速:基于计算机数值仿真技术,对上行列车行驶过程中由动载荷引发路基沉降量进行计算,确定列车最大通过时速,该技术为成熟技术,可以购买仿真分析软件获得列车最大通过时速。
第六步:监控量测:对铁路路基下沉量实时进行监控量测。
第七步:优化隧道施工:根据监控量测的下沉数据,及时优化隧道施工。
Claims (4)
1.一种地铁隧道近距离下穿既有铁路干线路基沉降控制方法,其特征在于,包括以下步骤:
第一步:地质勘察;
第二步:超前物探:在常规地质勘察的基础上,辅助以工作面超前物探方法,达到全方位、无死角地掌握工作面前方的地质构造信息;
第三步:理论计算:计算既有铁路干线路基最大允许沉降量,计算公式为[Smax]=W[δ]/L,其中[δ]为铁路轨道允许10m弦量测的最大矢度值,L为量测弦长,W为沉降槽宽度,W=5i,i为地表沉降槽宽度系数,即沉降槽曲线反弯点至隧道中心线的水平距离,D为隧道直径;Z0为隧道中心至地表深度;将计算出的最大允许沉降量与铁路路基下沉量不超过±3mm的行业标准进行对比,当计算出的最大允许沉降量大于等于行业标准允许的下沉量时,以行业标准允许的下沉量为准,当计算出的最大允许沉降量小于行业标准允许的下沉量时,以计算出的最大允许沉降量为准;
第四步:隧道施工:
(a)地表加固处理:隧道施工前,采用地表注浆对既有铁路线进行预加固处理;
(b)超前支护:首先采用大管棚结合小导管对将开挖隧道进行超前注浆支护,再根据现场地质情况,采用匹配的浅埋暗挖法对隧道进行开挖,在开挖隧道内采用地纵梁将隧道上方的铁路架空;
(c)隧道支护:首先采用锚网喷技术对开挖隧道进行初期支护,再进行补充注浆,最后再进行二次衬砌施工;
第五步:列车限速:基于计算机数值仿真技术,对上行列车行驶过程中由动载荷引发路基沉降量进行计算,确定列车最大通过时速;
第六步:监控量测:对铁路路基下沉量实时进行监控量测;
第七步:优化隧道施工:根据监控量测的下沉数据,及时优化隧道施工。
2.按照权利要求1所述的地铁隧道近距离下穿既有铁路干线路基沉降控制方法,其特征在于:所述第二步中的超前物探方法为电阻率法、瞬变电磁法或地质雷达法。
3.按照权利要求1所述的地铁隧道近距离下穿既有铁路干线路基沉降控制方法,其特征在于:所述第四步中(b)的超前支护,大管棚在待开挖隧道拱部环向间隔设置,在地铁隧道与既有铁路干线交叉点前后10m范围内,大管棚环向间距缩短,通过加密方式加强支护效果。
4.按照权利要求1所述的地铁隧道近距离下穿既有铁路干线路基沉降控制方法,其特征在于:所述第四步中(c)的隧道支护,在进行二次衬砌施工前,采用地质雷达扫描法对注浆效果和初期支护背后进行检测。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610353430.0A CN105971611A (zh) | 2016-05-25 | 2016-05-25 | 地铁隧道近距离下穿既有铁路干线路基沉降控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610353430.0A CN105971611A (zh) | 2016-05-25 | 2016-05-25 | 地铁隧道近距离下穿既有铁路干线路基沉降控制方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105971611A true CN105971611A (zh) | 2016-09-28 |
Family
ID=56956234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610353430.0A Pending CN105971611A (zh) | 2016-05-25 | 2016-05-25 | 地铁隧道近距离下穿既有铁路干线路基沉降控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105971611A (zh) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798718A (zh) * | 2018-07-09 | 2018-11-13 | 中铁十七局集团第四工程有限公司 | 隧道前承后继注浆方法 |
CN108868820A (zh) * | 2018-09-30 | 2018-11-23 | 西南石油大学 | 一种软土地基盾构隧道沉降控制结构及使用方法 |
CN109139019A (zh) * | 2018-09-04 | 2019-01-04 | 中铁十二局集团有限公司 | 潜埋暗挖隧道下穿地铁既有线路的监测方法及监测装置 |
CN109653749A (zh) * | 2018-11-30 | 2019-04-19 | 中铁二局第五工程有限公司 | 一种高海拔地区浅埋松散坡积碎石土段隧道开挖施工方法 |
CN109653755A (zh) * | 2019-01-03 | 2019-04-19 | 中铁隧道集团二处有限公司 | 一种大直径泥水盾构零沉降穿越无砟轨道路基的施工方法 |
CN110173269A (zh) * | 2019-06-26 | 2019-08-27 | 中铁二十三局集团第三工程有限公司 | 一种浅埋隧道下穿既有铁路施工控制方法 |
CN110220743A (zh) * | 2019-06-28 | 2019-09-10 | 苏州中车建设工程有限公司 | 一种便携式取水装置 |
CN110220742A (zh) * | 2019-06-28 | 2019-09-10 | 苏州中车建设工程有限公司 | 一种野外定深快速取水方法 |
CN111539052A (zh) * | 2020-03-23 | 2020-08-14 | 中铁隧道集团二处有限公司 | 地铁盾构区间近距离下穿顶管隧道沉降控制标准制定方法 |
CN112923129A (zh) * | 2021-01-21 | 2021-06-08 | 四川石油天然气建设工程有限责任公司 | 油气管道对接式拖管施工工艺及系统 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101598026A (zh) * | 2009-06-29 | 2009-12-09 | 中铁二院工程集团有限责任公司 | 浅埋下穿高速公路黄土地层超大断面隧道的初期支护构造 |
CN102345460A (zh) * | 2011-06-21 | 2012-02-08 | 北京交通大学 | 一种浅埋大断面黄土隧道沉降控制方法 |
KR101437882B1 (ko) * | 2013-10-25 | 2014-09-04 | 최진원 | 각종 단면 형상을 갖는 터널 굴진 공법 |
CN104295304A (zh) * | 2014-08-13 | 2015-01-21 | 北京城建集团有限责任公司 | 一种实现不同沉降分布保证率的地铁隧道沉降槽生成方法 |
-
2016
- 2016-05-25 CN CN201610353430.0A patent/CN105971611A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101598026A (zh) * | 2009-06-29 | 2009-12-09 | 中铁二院工程集团有限责任公司 | 浅埋下穿高速公路黄土地层超大断面隧道的初期支护构造 |
CN102345460A (zh) * | 2011-06-21 | 2012-02-08 | 北京交通大学 | 一种浅埋大断面黄土隧道沉降控制方法 |
KR101437882B1 (ko) * | 2013-10-25 | 2014-09-04 | 최진원 | 각종 단면 형상을 갖는 터널 굴진 공법 |
CN104295304A (zh) * | 2014-08-13 | 2015-01-21 | 北京城建集团有限责任公司 | 一种实现不同沉降分布保证率的地铁隧道沉降槽生成方法 |
Non-Patent Citations (2)
Title |
---|
冀文有等: "《近距离下穿既有铁路线路基沉降控制和规律研究》", 《山西建筑》 * |
孙文文等: "《地铁隧道的下穿施工对上部路基沉降影响分析》", 《隧道建设》 * |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798718A (zh) * | 2018-07-09 | 2018-11-13 | 中铁十七局集团第四工程有限公司 | 隧道前承后继注浆方法 |
CN109139019A (zh) * | 2018-09-04 | 2019-01-04 | 中铁十二局集团有限公司 | 潜埋暗挖隧道下穿地铁既有线路的监测方法及监测装置 |
CN108868820A (zh) * | 2018-09-30 | 2018-11-23 | 西南石油大学 | 一种软土地基盾构隧道沉降控制结构及使用方法 |
CN109653749A (zh) * | 2018-11-30 | 2019-04-19 | 中铁二局第五工程有限公司 | 一种高海拔地区浅埋松散坡积碎石土段隧道开挖施工方法 |
CN109653755A (zh) * | 2019-01-03 | 2019-04-19 | 中铁隧道集团二处有限公司 | 一种大直径泥水盾构零沉降穿越无砟轨道路基的施工方法 |
CN110173269B (zh) * | 2019-06-26 | 2020-08-04 | 中铁二十三局集团第三工程有限公司 | 一种浅埋隧道下穿既有铁路施工控制方法 |
CN110173269A (zh) * | 2019-06-26 | 2019-08-27 | 中铁二十三局集团第三工程有限公司 | 一种浅埋隧道下穿既有铁路施工控制方法 |
CN110220743A (zh) * | 2019-06-28 | 2019-09-10 | 苏州中车建设工程有限公司 | 一种便携式取水装置 |
CN110220742A (zh) * | 2019-06-28 | 2019-09-10 | 苏州中车建设工程有限公司 | 一种野外定深快速取水方法 |
CN110220742B (zh) * | 2019-06-28 | 2021-06-15 | 苏州中车建设工程有限公司 | 一种野外定深快速取水方法 |
CN110220743B (zh) * | 2019-06-28 | 2021-06-15 | 苏州中车建设工程有限公司 | 一种便携式取水装置 |
CN111539052A (zh) * | 2020-03-23 | 2020-08-14 | 中铁隧道集团二处有限公司 | 地铁盾构区间近距离下穿顶管隧道沉降控制标准制定方法 |
CN111539052B (zh) * | 2020-03-23 | 2022-08-26 | 中铁隧道集团二处有限公司 | 地铁盾构区间近距离下穿顶管隧道沉降控制标准制定方法 |
CN112923129A (zh) * | 2021-01-21 | 2021-06-08 | 四川石油天然气建设工程有限责任公司 | 油气管道对接式拖管施工工艺及系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105971611A (zh) | 地铁隧道近距离下穿既有铁路干线路基沉降控制方法 | |
CN111058855B (zh) | 一种盾构下穿的结构物的形变控制方法及评估系统 | |
CN109653755B (zh) | 一种大直径泥水盾构零沉降穿越无砟轨道路基的施工方法 | |
Luo et al. | Deformation rule and mechanical characteristics of temporary support in soil tunnel constructed by sequential excavation method | |
CN105443132A (zh) | 浅埋暗挖十字横撑隧道施工方法 | |
CN103437341A (zh) | 上覆砂土微风化石灰岩中地下连续墙的有效成槽施工方法 | |
CN102733812B (zh) | 城市江底分岔段小净距隧道侧壁扩挖的隧道施工方法 | |
CN108978676A (zh) | 一种基坑群和基础桩群的施工方法 | |
CN112576265A (zh) | 一种盾构下穿老旧村庄沉降控制方法 | |
Li et al. | Cause Analysis of Soft and Hard Rock Tunnel Collapse and Information Management. | |
Mei et al. | Experimental study of the comprehensive technology of grouting and suspension under an operating railway in the cobble stratum | |
CN110245426B (zh) | 一种用于管廊结构顶管施工的有限元精细化模拟方法 | |
Cao et al. | Control of strata deformation in subway interval tunnels crossing a high-speed rail shield tunnel at a short distance | |
Konukhov et al. | Ensuring the safety of the existing buildings during the construction of the underground in Moscow | |
CN206129278U (zh) | 土压平衡盾构机近距离侧穿初支暗挖隧道的施工结构 | |
Insam et al. | Brenner Base Tunnel–interaction between underground structures, complex challenges and strategies | |
CN114483054A (zh) | 上软下硬地层导洞非爆开挖施工方法 | |
CN108492030B (zh) | 一种估算深埋隧道掌子面爆发突涌灾害危险程度的方法 | |
Bilotta et al. | Ground movements induced by tunnel boring in Naples | |
Guo et al. | Grouting reinforcement of large building foundation over old gob areas: a case study in Huaibei mining area, China | |
Jing et al. | Instability mechanism and key control technology of deep soft rock roadway under long-term water immersion | |
Yan et al. | Deformation and Long-term Stability of Bridge in Mining with Filling | |
Yang et al. | Investigation on the Height of Fracture Zone in Goaf of Steep Coal Seam Based on Microseismic Monitoring | |
Xu et al. | Deformation control strategies for shield tunnel underpassing viaduct of high-speed railway: A case study | |
Liu et al. | Numerical simulation analysis of the effect of pipe shed support for underpassing existing tunnels |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160928 |