CN102808627A - 钢管棚暗挖施工方法 - Google Patents

钢管棚暗挖施工方法 Download PDF

Info

Publication number
CN102808627A
CN102808627A CN2012103308388A CN201210330838A CN102808627A CN 102808627 A CN102808627 A CN 102808627A CN 2012103308388 A CN2012103308388 A CN 2012103308388A CN 201210330838 A CN201210330838 A CN 201210330838A CN 102808627 A CN102808627 A CN 102808627A
Authority
CN
China
Prior art keywords
excavation
steel pipe
pipe
tunneling
canopy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103308388A
Other languages
English (en)
Inventor
万伟民
王智
徐聪聪
王荣涛
郭青松
王大迎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN2012103308388A priority Critical patent/CN102808627A/zh
Publication of CN102808627A publication Critical patent/CN102808627A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种钢管棚暗挖施工方法,包括以下步骤:a.根据地下管沟开挖面的形状确定所述开挖面管棚的形状以及所述管棚的钢管的布置方式;b.先对所述管沟的第一侧进行土石方开挖,开挖达到一预设标高时,按1:0.5进行放坡;c.待开挖至所述管沟下方时,进行暗挖段开挖,并在所述暗挖段的土层岩体上按自上而下的顺序进行钻孔,每钻完一个孔便在孔中插入一根钢管,开挖的同时对所述管棚进行支护以及加固处理;d.最后对所述管沟的第二侧进行土石方开挖,开挖至所述预设标高。本发明的钢管棚暗挖施工方法,利用管棚支撑其上建筑物,使地下工程暗挖部位与上面建筑物分离,防止土层坍塌和地表下沉,有效保护上面建筑物,同时保证地下结构施工的顺利进行。

Description

钢管棚暗挖施工方法
技术领域
本发明关于一种地下建筑施工,尤其是指一种钢管棚暗挖施工方法。
背景技术
隧道及地下建筑工程施工时,须先开挖出相应的空间,然后在其中修筑衬砌。施工方法的选择,应以地质、地形及环境条件以及埋置深度为主要依据,其中对施工方法有决定性影响的是埋置深度。埋置较浅的工程,施工时先从地面挖基坑或堑壕,修筑衬砌之后再回填,这就是明挖法。当埋深超过一定限度后,明挖法不再适用,而要改用暗挖法,即不挖开地面,采用在地下挖洞的方式施工。现如今越来越多的工程需要在地下松散层甚至含水松散层的土层岩体进行施工,而且施工区域还有可能与现有市政公用基础设施相冲突,如此一来,在建筑物密集、交通繁忙的城市中心地区,采用明挖法施工地下工程必须拆迁大量的地层管网和地面建筑物,这就对地下综合管沟的施工技术提出了全新的要求。
发明内容
有鉴于上述问题,本发明提供了一种钢管棚暗挖施工方法,包括以下步骤:
a.根据地下管沟开挖面的形状确定所述开挖面管棚的形状以及所述管棚的钢管的布置方式;
b.先对所述管沟的第一侧进行土石方开挖,开挖达到一预设标高时,按1:0.5进行放坡;
c.待开挖至所述管沟下方时,进行暗挖段开挖,并在所述暗挖段的土层岩体上按自上而下的顺序进行钻孔,每钻完一个孔便在孔中插入一根钢管,开挖的同时对所述管棚进行支护以及加固处理;
d.最后对所述管沟的第二侧进行土石方开挖,开挖至所述预设标高。
进一步的,对所述管沟的第一侧的土石方按1:0.5进行放坡时,坡面用素混凝土进行保护。
进一步的,采用潜孔钻进再扩孔的方法进行钻孔。
进一步的,当钻孔向下偏斜时,在偏斜部分填充水泥砂浆,等水泥砂浆凝固后再从偏斜开始处继续钻进;当钻孔向上偏斜时,采用合金钻头进行再次钻进。
进一步的,对所述管棚进行支护时,在所述钢管内采用后退式分段注浆法注入水泥砂浆,注浆时待孔口返浆后,在孔口用湿粘土和碎皮进行封堵,严密捣实后,需提高灌浆压力并稳定数分钟后,再结束灌浆。
进一步的,进行暗挖段开挖时,采用上下台阶法进行施工,在进行上台阶开挖时,预留有核心土,所述预留的核心土面积不少于上台阶开挖面积的一半。
进一步的,利用所述管沟的第二侧开挖的基坑作为水平降水基坑,用抽水机将基坑内水排出。
进一步的,在进行上台阶开挖时,在所述开挖面的上半断面增设临时仰拱作为初期支护。
进一步的,在所述暗挖段的土层岩体上,根据所述开挖面的形状,在所述管棚的周边架设工字钢支撑抵靠于各所述钢管的内侧。
本发明的钢管棚暗挖施工方法,利用管棚支撑其上建筑物,使地下工程暗挖部位与上面建筑物分离,可以防止土层坍塌和地表下沉,能有效保护上面建筑物,同时保证地下结构施工的顺利进行。
附图说明
图1是本发明钢管棚暗挖施工方法的流程图。
图2是本发明钢管棚暗挖施工方法的管棚的结构示意图。
图3是本发明钢管棚暗挖施工方法的钢管的布置示意图。
图4是本发明钢管棚暗挖施工方法的上台阶开挖时的结构示意图。
图5是本发明钢管棚暗挖施工方法的下台阶开挖时的结构示意图。
具体实施方式
下面配合附图以及具体实施例对本发明作详细说明。
配合参看图1所示,为本发明的钢管棚暗挖施工方法的流程图,包括以下步骤:
S1根据地下管沟开挖面的形状确定所述开挖面管棚的形状以及所述管棚的钢管的布置方式;
配合参看图2所示,某市政交通项目临江大道隧道工程为双层隧道工程,临江大道的部分施工段与下穿的市政污水渠箱10发生冲突,该工程在与下穿的市政污水渠箱10发生冲突的综合管沟施工段采用本发明的钢管棚暗挖施工方法,其中,该工程为拱形直墙,管棚20的形状和管棚20的钢管30的布置方式根据地下管沟开挖面的形状进行确定。
S2先对所述管沟的第一侧进行土石方开挖,开挖达到一预设标高时,按1:0.5进行放坡;
该工程首先完成南侧管沟的土石方开挖,开挖时在靠近暗挖段-2.00标高开始,按1:0.5放坡,坡面用素混凝土保护,以防止因雨水冲刷,避免泥水流下坑底影响主体工程的施工,挖掘过程严格控制管棚线路精确,确保管棚与结构的关系。
S3待开挖至所述管沟下方时,进行暗挖段开挖,并在所述暗挖段的土层岩体上按自上而下的顺序进行钻孔,每钻完一个孔便在孔中插入一根钢管,开挖的同时对所述管棚进行支护以及加固处理;
由于该工程下伏地层为泥质粉沙岩,进入风化带后往往是呈软硬互层,在强风化中通常夹中微风化岩,给压水钻进成孔造成困难,故采用潜孔钻进再扩孔的办法进行成孔。
配合参看图3所示,钻孔时,做好每个孔详细的钻孔记录,按设计要求孔间距为40cm。每钻完一孔便插入一根长钢管30。钻孔顺序自上而下,首先施工顶部拱部管棚21,而后施工顶部水平管棚22。为增加管棚20的刚度,待钢管30插入后,可在钢管30内压入混凝土或设置钢筋笼。
其中,钻孔的偏斜可由每隔5m测定钻孔的偏斜而知。当钻孔向下偏斜过大时,在偏斜部分填充水泥砂浆,等水泥砂浆凝固后再从偏斜开始处继续钻进;当钻孔向上偏斜时,采用合金钻头进行再次钻进。
配合参看图4以及图5所示,进行暗挖段开挖时,采用上下台阶法进行施工。
结合图4所示,在进行上台阶开挖时,预留有核心土40,所述预留的核心土40的面积不少于上台阶开挖面积的一半,并根据所述开挖面的形状,在所述管棚20的周边架设工字钢50支撑抵靠于各所述钢管30的内侧。由于从拱部开挖至底部仰拱历时较长,不利掌子面的稳定,易造成拱顶及地表沉降,故遵循浅埋暗挖及时封闭步步成环的原则,在所述开挖面的上半断面增设临时仰拱,使上半断面及时封闭,完成初期支护。为增加管棚20的刚度,可在钢管30内采用后退式分段注浆法注入水泥砂浆,注浆时待孔口返浆后,在孔口用湿粘土和碎皮进行封堵,严密捣实后,稍作提高灌浆压力,稳定数分钟后,灌浆才能结束。
结合图5所示,待上台阶开挖完毕并且支护以及加固处理完毕后,再进行下台阶开挖。为了防止拱脚23下沉,在拱脚23处先初喷5cm混凝土,再放置钢板60并设置锁脚砂浆锚杆、挂钢筋网,再终喷5cm混凝土。
S4最后对所述管沟的第二侧进行土石方开挖,开挖至所述预设标高。
最后采用明挖法进行北侧管沟土石方的开挖,开挖标高至-2.00,北侧明挖段基坑作为暗挖段施工竖井。
利用北侧明挖段基坑作为水平降水基坑,在水平降水基坑内用水平钻机成孔,埋设水平降水管,超前将地下管沟施工范围内地下水降至地下管沟底部仰拱以下1.0m左右,采用抽水机将基坑内水及时排出,保证后续开挖初支在无水条件下施工。
除了上述步骤外,整个施工过程还应遵循以下要求:
(1)严格控制开挖进度,每次开挖一榀,并留核心土,严禁多榀一次开挖。
(2)遇到管棚20上方存在人工杂填土,开挖过程出现不良地址情况及时对开挖面进行网喷封闭,进行加固处理后再施工。
(3)严格控制钢管30的间距,注意“标高、中线、前倾后仰、左高右低、左前右后”等各个方位的位置偏差,钢管30保护层临土侧50mm,背土侧30mm。钢管30的安装允许误差见下表1。
Figure BDA00002111218700041
表1
(4)施工过程中,加强量测频率,及时反馈量测结果,以便根据量测结果及时修正支护参数,确保安全。
以上所述仅是本发明的较佳实施例而已,并非对本发明做任何形式上的限制,虽然本发明已以较佳实施例揭露如上,然而并非用以限定本发明,任何熟悉本专业的技术人员,在不脱离本发明技术方案的范围内,当可利用上述揭示的技术内容作出些许更动或修饰为等同变化的等效实施例,但凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。

Claims (9)

1.一种钢管棚暗挖施工方法,其特征在于包括以下步骤:
a.根据地下管沟开挖面的形状确定所述开挖面管棚的形状以及所述管棚的钢管的布置方式;
b.先对所述管沟的第一侧进行土石方开挖,开挖达到一预设标高时,按1:0.5进行放坡;
c.待开挖至所述管沟下方时,进行暗挖段开挖,并在所述暗挖段的土层岩体上按自上而下的顺序进行钻孔,每钻完一个孔便在孔中插入一根钢管,开挖的同时对所述管棚进行支护以及加固处理;
d.最后对所述管沟的第二侧进行土石方开挖,开挖至所述预设标高。
2.如权利要求1所述的钢管棚暗挖施工方法,其特征在于对所述管沟的第一侧的土石方按1:0.5进行放坡时,坡面用素混凝土进行保护。
3.如权利要求1所述的钢管棚暗挖施工方法,其特征在于采用潜孔钻进再扩孔的方法进行钻孔。
4.如权利要求1或3所述的钢管棚暗挖施工方法,其特征在于当钻孔向下偏斜时,在偏斜部分填充水泥砂浆,等水泥砂浆凝固后再从偏斜开始处继续钻进;当钻孔向上偏斜时,采用合金钻头进行再次钻进。
5.如权利要求1所述的钢管棚暗挖施工方法,其特征在于对所述管棚进行支护时,在所述钢管内采用后退式分段注浆法注入水泥砂浆,注浆时待孔口返浆后,在孔口用湿粘土和碎皮进行封堵,严密捣实后,需提高灌浆压力并稳定数分钟后,再结束灌浆。
6.如权利要求1所述的钢管棚暗挖施工方法,其特征在于进行暗挖段开挖时,采用上下台阶法进行施工,在进行上台阶开挖时,预留有核心土,所述预留的核心土面积不少于上台阶开挖面积的一半。
7.如权利要求1所述的钢管棚暗挖施工方法,其特征在于利用所述管沟的第二侧开挖的基坑作为水平降水基坑,用抽水机将基坑内水排出。
8.如权利要求6所述的钢管棚暗挖施工方法,其特征在于在进行上台阶开挖时,在所述开挖面的上半断面增设临时仰拱作为初期支护。
9.如权利要求1所述的钢管棚暗挖施工方法,其特征在于在所述暗挖段的土层岩体上,根据所述开挖面的形状,在所述管棚的周边架设工字钢支撑抵靠于各所述钢管的内侧。
CN2012103308388A 2012-09-07 2012-09-07 钢管棚暗挖施工方法 Pending CN102808627A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103308388A CN102808627A (zh) 2012-09-07 2012-09-07 钢管棚暗挖施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103308388A CN102808627A (zh) 2012-09-07 2012-09-07 钢管棚暗挖施工方法

Publications (1)

Publication Number Publication Date
CN102808627A true CN102808627A (zh) 2012-12-05

Family

ID=47232478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103308388A Pending CN102808627A (zh) 2012-09-07 2012-09-07 钢管棚暗挖施工方法

Country Status (1)

Country Link
CN (1) CN102808627A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926758A (zh) * 2012-11-19 2013-02-13 沐俊卫 综炮联合台阶法巷道掘进施工方法
CN103147773A (zh) * 2013-03-27 2013-06-12 李海广 老防空洞扩展空间的施工工艺
CN106194223A (zh) * 2016-07-21 2016-12-07 中国水利水电第十四工程局有限公司 一种复杂地质条件下大型尾水调压室穹顶的开挖方法
CN108590668A (zh) * 2018-04-27 2018-09-28 中国电建市政建设集团有限公司 一种暗挖车站超长管棚拉管法
CN108952765A (zh) * 2018-07-18 2018-12-07 中铁十二局集团第二工程有限公司 超大管棚在富水砂层超前支护的施工方法
CN109537630A (zh) * 2019-01-25 2019-03-29 中国矿业大学 一种钢管棚与冻土协同作用的加固方法
CN109915173A (zh) * 2019-03-22 2019-06-21 北京城建集团有限责任公司 一种地下管幕支撑结构和导洞蓄水系统

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000352296A (ja) * 1999-06-11 2000-12-19 Maeda Corp 地下構造物直下の通路の形成方法
JP2005273376A (ja) * 2004-03-26 2005-10-06 Makoto Uemura 地下構造物構築方法における切羽安定方法
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101196118A (zh) * 2008-01-07 2008-06-11 北京市政建设集团有限责任公司 超前双排注浆小导管施工工艺
JP2009235831A (ja) * 2008-03-28 2009-10-15 Fujita Corp 地中内構造物の構造、およびその施工方法
CN101929340A (zh) * 2009-12-31 2010-12-29 平煤建工集团有限公司 煤矿井下平斜巷管棚预注浆超前支护施工工艺

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000352296A (ja) * 1999-06-11 2000-12-19 Maeda Corp 地下構造物直下の通路の形成方法
JP2005273376A (ja) * 2004-03-26 2005-10-06 Makoto Uemura 地下構造物構築方法における切羽安定方法
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101196118A (zh) * 2008-01-07 2008-06-11 北京市政建设集团有限责任公司 超前双排注浆小导管施工工艺
JP2009235831A (ja) * 2008-03-28 2009-10-15 Fujita Corp 地中内構造物の構造、およびその施工方法
CN101929340A (zh) * 2009-12-31 2010-12-29 平煤建工集团有限公司 煤矿井下平斜巷管棚预注浆超前支护施工工艺

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
中国公路学会隧道工程分会等: "《2007年全国公路隧道学术会议论文集》", 31 October 2007 *
侯瑜京等编著: "《甘肃昌马水库坝址右岸山体稳定研究及加固处理》", 30 April 2005 *
北京建工京精大房工程建设监理公司编著: "《城市轨道交通工程土建监理工作手册》", 31 January 2011 *
杨晓东主编: "《锚固与注浆技术手册》", 31 January 2010 *
苏钧等: "长管棚技术在广州地铁区间隧道中的应用", 《铁道建筑》 *
陶龙光等: "《城市地下工程》", 31 December 1996, 科学出版社 *
高谦等: "《地下工程系统分析与设计》", 31 May 2011, 中国建材工业出版社 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926758A (zh) * 2012-11-19 2013-02-13 沐俊卫 综炮联合台阶法巷道掘进施工方法
CN103147773A (zh) * 2013-03-27 2013-06-12 李海广 老防空洞扩展空间的施工工艺
CN103147773B (zh) * 2013-03-27 2015-07-22 李海广 老防空洞扩展空间的施工工艺
CN106194223A (zh) * 2016-07-21 2016-12-07 中国水利水电第十四工程局有限公司 一种复杂地质条件下大型尾水调压室穹顶的开挖方法
CN108590668A (zh) * 2018-04-27 2018-09-28 中国电建市政建设集团有限公司 一种暗挖车站超长管棚拉管法
CN108952765A (zh) * 2018-07-18 2018-12-07 中铁十二局集团第二工程有限公司 超大管棚在富水砂层超前支护的施工方法
CN109537630A (zh) * 2019-01-25 2019-03-29 中国矿业大学 一种钢管棚与冻土协同作用的加固方法
CN109537630B (zh) * 2019-01-25 2019-12-17 中国矿业大学 一种钢管棚与冻土协同作用的加固方法
CN109915173A (zh) * 2019-03-22 2019-06-21 北京城建集团有限责任公司 一种地下管幕支撑结构和导洞蓄水系统
CN109915173B (zh) * 2019-03-22 2023-11-21 北京城建集团有限责任公司 一种地下管幕支撑结构和导洞蓄水系统

Similar Documents

Publication Publication Date Title
CN105839643A (zh) 一种采用基坑支护的隧道进洞施工方法
CN102808627A (zh) 钢管棚暗挖施工方法
CN102704957A (zh) 一种用于浅埋大型地下结构建造的棚架法
CN106930775B (zh) 浅埋山区公路隧道门式排桩刚构围护结构及其施工方法
CN104847362B (zh) 硬岩地层大跨地铁车站暗挖施工方法
CN108547639B (zh) 隧道临近既有构筑物的超前同孔多导管分层注浆施工方法
CN104763433A (zh) 上软下硬地层大跨地铁车站暗挖施工方法
CN106703044B (zh) 一种流塑状冲填土软弱地层放坡组合支护方法
CN102748040A (zh) 地铁大跨度车站主体结构及其柱拱法施工方法
Bell Methods of treatment of unstable ground
CN111101540B (zh) 一种明挖隧道上穿既有电力隧道施工方法
CN109736827A (zh) 城市地铁硬岩地层联络通道高压气体膨胀致裂开挖的方法
CN108797618A (zh) 一种用于城市地下综合管廊基坑排水结构及其施工方法
CN106812150A (zh) 一种山区陡坡地段公路桥梁桩基施工方法
CN106088099A (zh) 一种地铁基坑锚索处理方法
CN110284885A (zh) 盾构检修井施工方法
CN110259490A (zh) 一种地铁暗挖车站施工方法
CN102839980A (zh) 公路隧道结构及其施工方法
CN113931637A (zh) 一种浅埋富水较软岩隧道施工方法
CN112983461A (zh) 坡积体中偏压隧道洞口的施工方法
Tsuji et al. Extraordinary Inundation Accidents in the Seikan Undersea Tunnel.(paper Presented at 13TH International Conference on Soil Mechanics & Foundation Engineering in New Delhi in 1994).
CN1419020A (zh) 导洞一隔离桩墙法防护邻近构造物沉降的方法和结构
Davis et al. Groundwater control and stability in an excavation in Magnesian Limestone near Sunderland, NE England
CN109611114B (zh) 一种土岩复合地层下卧既有隧道的地下空间开挖方法
CN108019211B (zh) 一种富水砂卵石地层的导洞内截水帷幕及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121205