CH152167A - Flooring and method of making same. - Google Patents

Flooring and method of making same.

Info

Publication number
CH152167A
CH152167A CH152167DA CH152167A CH 152167 A CH152167 A CH 152167A CH 152167D A CH152167D A CH 152167DA CH 152167 A CH152167 A CH 152167A
Authority
CH
Switzerland
Prior art keywords
asphalt
layer
sand
macadam
emulsion
Prior art date
Application number
Other languages
German (de)
Inventor
Bertschinger Walo
Original Assignee
Bertschinger Walo
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bertschinger Walo filed Critical Bertschinger Walo
Publication of CH152167A publication Critical patent/CH152167A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Description

  

      Fussboden    und     Verfahren    zur Herstellung desselben.    Bei den bisher bekannten Fussbodenkon  struktionen mit fugenloser Deckschicht auf  der     .Bodenunterlage        wird        auf    die Eisenbeton  oder     Ziegeltragschieht    .der     Bodenunterlage     eine     Estrichschicht    aus Gips oder Zement  mit Sand oder Bims     und    Wasser aufge  bracht und auf .dieselbe     ,

  dann    der     eigentliche     Bodenbelag aus     Linoleum        etc.    Diese     Kon-          struktion    hat den     Nachteil,    dass es     einige          \Vochen        dauert,    bis die     Estrichschicht    voll  kommen trocken ist und der Belag     verlegt     werden kann.  



  Um .diese Wartezeit abzukürzen, ist be  reits vorgeschlagen worden, die Deckschicht  aus     Teermakadam    herzustellen. Aber dem  Verfahren zur     Herstellung    von     Fussböden,    mit       Teermakadam    als fugenlose Deckschicht  haften ebenfalls Nachteile an, die darin     be-          4ehen,    dass der     Teermakadam    nicht an Ort  und     Stelle    hergestellt, sondern in besonderen  Werken und nach     ,der    Baustelle transportiert  wird.

   Zur rascheren     Erhärtung    wird dem  Teer ein gewisser Prozentsatz Asphalt     tbeige-          fitgt.    Ist nun die Einbaustelle vom Teer-         makadamwerk    zu weit entfernt, so verteuert  sich der Belag infolge der Transportkosten       und        unter        Umständen    erhärtet der     Makadam     schon während des     Transportes.    Ausserdem  verflüchtigen sich die im Teer enthaltenen.

    leichten Öle auch nach dem Einbau,     können     in die Betonunterlage einsickern und können  sich in der     darunterliegenden    Decke bemerk  bar     -machen.     



  Diese Nachteile werden bei .dem Fuss  boden nach vorliegender Erfindung vermie  den. Gemäss der Erfindung besteht die     Deck-          schicht    aus     Asphaltmakadam.    Auf diesen  wird     zweckmässigerweise    noch eine glättende  Schicht angebracht.  



  Gemäss dem Verfahren nach der Erfin  dung bereitet man den     Asphaltmakadam    an  der Baustelle, indem man einer Asphaltemul  sion Sand zusetzt, bringt den     Makadam    auf  .die Bodenunterlage als Schicht auf und glät  tet die Oberfläche der Schicht, beispiels  weise mit Zement, Sand, Wasserglas, As  phaltsand oder mit Sägespänen und Leim,      oder mit einer Mischung einiger oder aller  dieser     Mittel.     



  Das Verfahren kann beispielsweise so aus  geführt werden,     dass    man eine Asphaltemul  sion, welche 50 bis<B>60%</B> Asphalt in 50 bis       40%    Wasser     suspendiert    enthält, herstellt  und diese Emulsion mit. feinem Sand, grobem  Sand und noch Steinsplitt bis 15 mm Korn  grösse vermischt und so einen     Aspha@tmak:i-          dam    herstellt. Letzterer wird auf die Boden  unterlage, die zum Beispiel aus     Eisenbeton     bestehen kann, als Schicht aufgebracht. Diese  Schicht kann eine Dicke von 2 bis 15 cm auf  weisen.

   Die Oberfläche .der Schicht wird mit  Zement, Sand oder Wasserglas oder Asphalt  sand, oder     mit    einer Mischung einiger oder  aller dieser Stoffe     abgqglättet.     



  Der     Asphaltmakadam    kann auch auf der  Bodenunterlage     selbst    und ohne Zugabe von  Steinsplitt     hergestellt    werden, oder man kann  der Emulsion auch *Schlacken in Sandform  zum Beispiel     Schlackengrus    zusetzen.  



  Diese so erhaltene fugenlose     Deckschicht     wirkt schalldämpfend, sie zersetzt sich nicht.  Die Asphaltemulsion kann im Werk herge  stellt werden, und in Fässern zur Baustelle  transportiert werden, wo dann die Herstel  lung des     Makadams    erfolgt.. Im     Gegensatz     zum     Teermakadam    sind die     Transportkosten     ab Werk erheblich verringert, da Sand und  Steinsplitt nicht     mittransportiert    werden  müssen. Ausserdem fällt die Wärmebehand  lung fort.



      Flooring and method of making same. In the previously known flooring constructions with a seamless top layer on the .Bodenunterlage a screed layer of plaster of paris or cement with sand or pumice and water is applied to the reinforced concrete or brick support layer.

  then the actual floor covering made of linoleum etc. This construction has the disadvantage that it takes a few weeks before the screed layer is completely dry and the covering can be laid.



  In order to shorten this waiting time, it has already been proposed to produce the top layer from tar macadam. But the process of making floors, with the tar macadam as a jointless top layer, also has disadvantages, which consist in the fact that the tar macadam is not produced on the spot, but is transported to the construction site in special plants.

   A certain percentage of asphalt is added to the tar to harden it more quickly. If the installation site is too far away from the tar macadam plant, the cost of the topping increases as a result of the transport costs and under certain circumstances the macadam already hardens during transport. In addition, those contained in the tar evaporate.

    Light oils, even after installation, can seep into the concrete base and can be noticeable in the ceiling below.



  These disadvantages are avoided in .dem floor according to the present invention. According to the invention, the top layer consists of asphalt macadam. A smoothing layer is expediently applied to this.



  According to the method according to the invention, the asphalt macadam is prepared at the construction site by adding sand to an asphalt emulsion, applying the macadam as a layer and smoothing the surface of the layer, for example with cement, sand, water glass, Asphalt sand, or with sawdust and glue, or with a mixture of some or all of these.



  The method can, for example, be carried out in such a way that an asphalt emulsion which contains 50 to 60% asphalt suspended in 50 to 40% water is produced and this emulsion is produced with it. fine sand, coarse sand and stone chippings up to 15 mm in size are mixed to produce an Aspha @ tmak: i-dam. The latter is applied as a layer to the ground underlay, which can consist of reinforced concrete, for example. This layer can have a thickness of 2 to 15 cm.

   The surface of the layer is sanded with cement, sand or water glass or asphalt, or with a mixture of some or all of these substances.



  The asphalt macadam can also be made on the ground itself and without adding stone chippings, or you can also add slag in sand form, for example slag gravel, to the emulsion.



  The seamless top layer obtained in this way has a sound-absorbing effect, it does not decompose. The asphalt emulsion can be produced in the factory and transported in barrels to the construction site, where the macadam is then manufactured. In contrast to the tar macadam, the transport costs ex works are considerably reduced, as sand and stone chippings do not have to be transported. In addition, there is no heat treatment.

 

Claims (1)

PATENTANSPRÜCHE: I. Fussboden mit fugenloser Deckschicht auf der Bodenunterlage, auf welcher Deek- schicht der Bodenbelag angebracht ist, dadurch gekennzeichnet, dass die Deck s chicht aus Asphaltmakadam besteht. PATENT CLAIMS: I. Floor with seamless top layer on the floor underlay, on which the floor covering is attached, characterized in that the top layer consists of asphalt macadam. 1I. Verfahren zur Herstellung des Fuss bodens nach Patentanspruch I, dadurch gekennzeichnet, dass man .den AsphaIt- maka.dam an der Baustelle bereitet, in .dem man einer Asphaltemulsion Sand zu setzt, und den Makadam auf die Boden unterlage als Schicht aufbringt. und die Oberfläche der Schicht glättet. UNTERANSPRÜCHE 1. 1I. Process for the production of the floor according to claim I, characterized in that the asphalt maka.dam is prepared at the construction site by adding sand to an asphalt emulsion and applying the macadam as a layer to the floor. and smooths the surface of the layer. SUBCLAIMS 1. Verfahren nach Patentanspruch II, da durch gekennzeichnet, dass man den Makadam aus.. einer Asphaltemulsion her stellt, welche 50 bis 60% Asphalt und 50 bis. 40 % Wasser :enthält, und der Emulsion feinen Sand, groben Sand und Steinsplitt zumischt. 2. Verfahren nach Patentanspruch II, 3a durch gekennzeichnet, dass man den Na kadam aus einer Asphaltemulsion her stellt, welche 50 bis<B>60%</B> Asphalt and 50 bis 40% Wasser enthält, und der Emulsion Schlackengrus zumischt. 3. Method according to claim II, characterized in that the macadam is made from .. an asphalt emulsion which contains 50 to 60% asphalt and 50 to. 40% water: contains and mixes fine sand, coarse sand and stone chippings with the emulsion. 2. The method according to claim II, 3a, characterized in that the Na kadam is made from an asphalt emulsion which contains 50 to <B> 60% </B> asphalt and 50 to 40% water, and slag powder is added to the emulsion. 3. Verfahren nach Patentanspruch II, da durch gekennzeichnet, dass man die Glät- tung der Oberfläche der Deckschicht mit- telst Zement und Sand ausführt. 4. Verfahren nach Patentanspruch II, da durch gekennzeichnet, dass man die Glät- tung der Oberfläche-der Deckschicht mit- telst Wasserglas ausführt. 5. Method according to patent claim II, characterized in that the surface of the cover layer is smoothed with cement and sand. 4. The method according to claim II, characterized in that the surface - the cover layer - is smoothed with water glass. 5. Verfahren nach Patentanspruch II, da durch gekennzeichnet, dass man die Glä.t- tungder Oberfläche der Deckschicht mit- telst Asphaltsänd ausführt. 6. Verfahren nach Patentanspruch II, da durch gekennzeichnet., dass man die Glät- tung der Oberfläche der Deckschicht mit- telst Sägespänen und Leim ausführt. Method according to patent claim II, characterized in that the surface of the surface layer is smoothed using asphalt sand. 6. The method according to patent claim II, characterized in that the surface of the cover layer is smoothed with sawdust and glue.
CH152167D 1930-11-01 1930-11-01 Flooring and method of making same. CH152167A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH152167T 1930-11-01

Publications (1)

Publication Number Publication Date
CH152167A true CH152167A (en) 1932-01-31

Family

ID=4407310

Family Applications (1)

Application Number Title Priority Date Filing Date
CH152167D CH152167A (en) 1930-11-01 1930-11-01 Flooring and method of making same.

Country Status (1)

Country Link
CH (1) CH152167A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE958332C (en) * 1953-01-13 1957-02-14 Hartwig Volbehr Process for the production of a smooth, preferably colored asphalt or similar floor by treating its surface with substances that have been enriched with asphalt or the like
DE1153873B (en) * 1954-04-17 1963-09-05 Kurt Herold Process for smoothing mastic asphalt floor coverings

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE958332C (en) * 1953-01-13 1957-02-14 Hartwig Volbehr Process for the production of a smooth, preferably colored asphalt or similar floor by treating its surface with substances that have been enriched with asphalt or the like
DE1153873B (en) * 1954-04-17 1963-09-05 Kurt Herold Process for smoothing mastic asphalt floor coverings

Similar Documents

Publication Publication Date Title
CH152167A (en) Flooring and method of making same.
DE511883C (en) Process for the production of a covering for floors, walls u. like
DE19848927A1 (en) Process for the production of a mastic asphalt screed with terrazzo elements
CH711468B1 (en) Floor covering system, in particular for mineral floor slabs, for preventing moisture stains and discoloration and method for constructing a floor covering system.
DE806348C (en) Process for the production of fibrous boards provided with a hard covering to increase the stability
DE1659938A1 (en) Process for producing floors or other covering layers
DE563163C (en) Method of making a pumice concrete screed with a Sorell cement spread
CH157867A (en) Process for the production of seamless flooring.
DE2319535A1 (en) Crack-bridging, insulating flooring system
US2014700A (en) Asphalt terrazzo composition and method of laying the same
DE732109C (en) Process for the production of a waterproof, fireproof and dust-free floor covering, e.g. as a base for linoleum
DE867000C (en) Seamless roof covering made from several layers of paper or fabric
DE1102376B (en) Method of making a screed
CH300853A (en) Plastering and filling compounds for building purposes.
DE199280C (en)
AT134079B (en) Insulating covering.
DE561848C (en) Seamless floor screed
DE381657C (en) Construction method
DE1659929A1 (en) Underlay and process for its manufacture
DE652247C (en) Procedure for applying chemical-resistant coatings to substrates
CH154691A (en) Process for the production of seamless insulating and underlay floors and ready-to-walk floor coverings.
CH141469A (en) Process for the production of seamless insulating and underlay floors and ready-to-walk floor coverings.
DE537735C (en) Process for the production of an artificial stone mass
CH186197A (en) Process for the production of water-permeable surfaces for tennis, gymnastics and playgrounds.
CH147130A (en) Cork layer for floor and wall coverings or the like and process for their production.