WO2024104449A1 - 核岛反应堆厂房施工装备集成平台及其爬升方法 - Google Patents

核岛反应堆厂房施工装备集成平台及其爬升方法 Download PDF

Info

Publication number
WO2024104449A1
WO2024104449A1 PCT/CN2023/132188 CN2023132188W WO2024104449A1 WO 2024104449 A1 WO2024104449 A1 WO 2024104449A1 CN 2023132188 W CN2023132188 W CN 2023132188W WO 2024104449 A1 WO2024104449 A1 WO 2024104449A1
Authority
WO
WIPO (PCT)
Prior art keywords
platform
steel
nuclear island
reactor building
construction
Prior art date
Application number
PCT/CN2023/132188
Other languages
English (en)
French (fr)
Inventor
张琨
王开强
王东
杨亚璋
孙庆
赵葳
刘威
陈李华
黄雷
黄阁
董晓刚
崔健
姚涛
魏伟
丁志新
熊猛
刘文杰
刘永波
叶贞
严宗宇
Original Assignee
中建三局集团有限公司
中广核工程有限公司
中建三局第一建设工程有限责任公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中建三局集团有限公司, 中广核工程有限公司, 中建三局第一建设工程有限责任公司 filed Critical 中建三局集团有限公司
Publication of WO2024104449A1 publication Critical patent/WO2024104449A1/zh

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin

Definitions

  • the invention relates to the technical field of nuclear island plant construction in nuclear power plants, and in particular to a nuclear island reactor plant construction equipment integrated platform and a climbing method thereof.
  • the construction formwork for the inner and outer shells of nuclear island reactor buildings is mainly based on the arc-shaped large formwork system with triangular hangers.
  • the cantilevered tripod of the inner shell blocks the construction of the outer shell structure in the vertical space, thus forming a "step-by-step" construction process for the inner shell, outer shell, and surrounding plant, which prolongs the total construction period.
  • the load-bearing capacity of the template triangular hanger is low, and construction materials can only be arranged outside the surrounding plant, which limits the layout of the yard;
  • the template must be transported upward with the help of an external tower crane, which seriously occupies the tower crane's transportation capacity.
  • the material transportation, installation of embedded parts and through-pieces all rely on external tower cranes, resulting in low vertical transportation efficiency.
  • the main purpose of the present invention is to provide a nuclear island reactor building construction equipment integrated platform and a climbing method thereof, aiming to solve the problem of the total construction period being restricted by the "ladder-type" process of the inner shell, outer shell and surrounding buildings in the existing construction of the nuclear island reactor building.
  • the present invention provides a nuclear island reactor plant construction equipment integrated platform, including a steel platform system, a support and jacking system, a rack and template system and construction integrated equipment, wherein:
  • the support and jacking system is installed on the side of the nuclear island reactor building, the support and jacking system is located below the steel platform system to support it to climb relative to the nuclear island reactor building, and the rack and template system is installed below the steel platform system;
  • the steel platform system includes an annular steel truss, a radial main steel truss and a radial secondary steel truss.
  • the two ends of the radial main steel truss are respectively connected to the innermost and outermost annular steel trusses.
  • the radial secondary steel truss is disconnected above the shell of the nuclear island reactor building to facilitate the hanging of shell construction materials downwards.
  • the integrated construction equipment includes a crane with a retractable boom, a placing machine, and a climbing work vehicle fixed on a steel platform, a circular track installed at the bottom of the hanger and formwork system, a ring crane slidably connected to the circular track, and a top-sectioned downward-extending transport device connected to the steel platform.
  • the support and jacking system includes load-bearing parts, support parts, climbing parts, steel columns and hydraulic components, wherein the load-bearing parts can be detachably installed on the side of the nuclear island reactor building, the top of the steel column is fixedly connected to the steel platform system, and the bottom is fixedly connected to the support part, the bottom of the hydraulic component is fixed inside the climbing part and the top is connected to the support part to support its climbing.
  • the supporting member, the climbing member and the load-bearing member are detachably connected via hooks or pins.
  • a crane is fixed on the steel platform system, the crane column is fixedly connected to the steel platform, and the crane boom is retractable.
  • a concrete placing boom is fixed on the steel platform system.
  • an annular working track is installed above the steel platform system, and the aerial work vehicle is slidably installed on the annular working track, and the aerial work vehicle can be raised and lowered.
  • the steel platform system is connected to a plurality of top-sectioned downward-extending transport devices.
  • the nuclear island reactor building construction equipment integrated platform also includes a construction elevator located on both sides of the buttress columns, the construction elevator including a construction elevator standard section that can be detachably installed on the side of the nuclear island reactor building and a ladder cage installed on the construction elevator standard section and movable up and down relative to the construction elevator standard section.
  • a construction elevator located on both sides of the buttress columns, the construction elevator including a construction elevator standard section that can be detachably installed on the side of the nuclear island reactor building and a ladder cage installed on the construction elevator standard section and movable up and down relative to the construction elevator standard section.
  • the steel platform system includes an outer cantilever platform and an inner cantilever platform that are detachably connected.
  • the outer cantilever platform is attached to the outer side of the outer shell of the nuclear island reactor building through the outer cantilever platform fulcrum
  • the inner cantilever platform is attached to the outer side of the inner shell of the nuclear island reactor building through the inner cantilever platform fulcrum; an operating frame and prestressed tensioning equipment are arranged on the top of the inner cantilever platform.
  • the present invention further proposes a climbing method based on the above-mentioned nuclear island reactor building construction equipment integrated platform, comprising the following steps:
  • the oil cylinder of the hydraulic assembly extends to drive the support to drive the steel column, steel platform system, hanging frame and formwork system and other auxiliary construction equipment and facilities to climb as a whole;
  • the climbing member After the climbing member is climbed to the right position, the climbing member is connected to the load-bearing member at the corresponding position.
  • the integrated platform is supported on the inner and outer shell walls, and the inner and outer shells are multi-layered and flow-lined through multi-layer racks, avoiding interference with existing template technology, achieving synchronous construction of the inner and outer shells, and decoupling the construction of surrounding plants from the outer shell.
  • the steel platform system is composed of multiple radial and annular space trusses, with high overall bearing capacity and high rigidity. It can provide a loading platform for the construction of reactor buildings. At the same time, heavy equipment such as cranes, concrete placing machines, elevators, etc. can be directly arranged on the steel platform and climb synchronously with the platform in coordination with the formwork, effectively improving the vertical transportation efficiency and eliminating the need for large construction equipment to be lifted separately and the plane position changed;
  • the steel platform system can be modified to adapt to the multi-stage construction of the reactor building, reduce the additional measures required for structural construction, and save construction time and costs.
  • FIG1 is a schematic cross-sectional view of the integrated platform for construction equipment of a nuclear island reactor plant of the present invention
  • FIG2 is a schematic diagram of the structure of the steel platform system in the integrated platform for construction equipment of the nuclear island reactor building of the present invention
  • FIG3 is a schematic structural diagram of the support and jacking system in the integrated platform for construction equipment of a nuclear island reactor building of the present invention
  • FIG4 is a schematic structural diagram of the ring corridor hoisting equipment in the nuclear island reactor plant construction equipment integrated platform of the present invention.
  • FIG5 is a schematic diagram of the plan structure of a crane in the integrated platform for construction equipment of a nuclear island reactor plant of the present invention.
  • FIG6 is a schematic diagram of the elevation structure of a crane in the integrated platform for construction equipment of a nuclear island reactor plant of the present invention.
  • FIG7 is a schematic structural diagram of a concrete placing machine in the integrated platform for construction equipment of a nuclear island reactor building of the present invention.
  • FIG8 is a schematic structural diagram of a high-altitude operation vehicle in the integrated platform for nuclear island reactor building construction equipment of the present invention.
  • FIG9 is a schematic structural diagram of a top-sectioned downwardly extending transport device in an integrated platform for construction equipment of a nuclear island reactor plant of the present invention.
  • FIG10 is a schematic diagram of the plan layout of the construction elevator in the nuclear island reactor plant construction equipment integrated platform of the present invention.
  • FIG11 is a schematic diagram of the elevation layout of the construction elevator in the nuclear island reactor plant construction equipment integrated platform of the present invention.
  • FIG. 12 is a schematic diagram of the structure of the nuclear island reactor building construction equipment integrated platform after transformation according to the present invention.
  • the present invention provides a nuclear island reactor building construction equipment integration platform.
  • a nuclear island reactor plant construction equipment integrated platform includes a steel platform system 4 (providing layout space for various equipment and facilities), a support and jacking system 5, a rack and template system 6 and construction integrated equipment 7, wherein:
  • the support and jacking system 5 is installed on the side of the nuclear island reactor building (can be selectively attached to the outer side of the inner shell 2, the inner side of the outer shell 1 or the outer side of the outer shell 1), the support and jacking system 5 is located below the steel platform system 4 to support it to climb relative to the nuclear island reactor building, and the hanger and template system 6 is suspended and installed below the steel platform system 4;
  • the steel platform system 4 includes an annular steel truss 4.1, a radial main steel truss 4.2 and a radial secondary steel truss 4.3.
  • the two ends of the radial main steel truss 4.2 are respectively connected to the innermost annular steel truss 4.1 and the outermost annular steel truss 4.1.
  • the radial secondary steel truss 4.3 is disconnected above the shell 1 of the nuclear island reactor building to facilitate the downward lifting of the shell 1 construction materials.
  • the construction integrated equipment 7 comprises a circular track 7.1 installed at the bottom of the hanger and template system 6 and a ring hanger 7.2 (a plurality of ring hangers) slidably connected to the circular track 7.1.
  • the circular track 7.1 is located between the outer shell 1 and the inner shell 2 of the nuclear island reactor building.
  • the bracket and formwork system 6 is connected to the bottom of the steel platform system 4 and arranged on both sides of the outer shell to meet the simultaneous construction of multiple layers. It can also provide a working platform for shell reinforcement binding, embedded parts installation, formwork support, concrete pouring, concrete maintenance, etc. An inclined ladder is installed in the bracket to facilitate personnel to go up and down on each floor.
  • the steel platform system 4 has a ring-shaped structure in plane and is arranged above the inner shell 2 and the outer shell 1. Equipment facilities and operation rooms are integrated on the steel platform system 4.
  • the steel platform system 4 is composed of at least three radial and at least two annular space trusses. It has a high overall bearing capacity and high rigidity, and can provide a loading platform for reactor construction. At the same time, heavy equipment such as cranes, concrete placing machines, elevators, etc. can be directly arranged on the steel platform system 4, and climb synchronously with the platform in coordination with the formwork, etc., effectively improving the vertical transportation efficiency and eliminating the need for large construction equipment to be lifted separately and the plane position changed.
  • the construction components of the ring corridor are hoisted to the completed ring corridor platform between the inner shell 2 and the outer shell 1 by an external tower crane, and then the ring crane 7.2 hoists the materials to the corresponding position for installation.
  • the installed ring corridor platform can also be used as a loading platform for the construction materials of the upper ring corridor.
  • the supporting and jacking system 5 includes a load-bearing member 5.1, a support member 5.2, a climbing member 5.3, a steel column 5.4 and a hydraulic component 5.5, wherein the load-bearing member 5.1 is detachably installed on the side of the nuclear island reactor building, the top of the steel column 5.4 is fixedly connected to the steel platform system 4, and the bottom is fixedly connected to the support member 5.2, and the bottom of the hydraulic component 5.5 is fixed inside the climbing member 5.3 and the top is connected to the support member 5.2 to support its climbing.
  • the support member 5.2, the climbing member 5.3 and the load-bearing member 5.1 are detachably connected through hooks or pins.
  • corresponding hooks are provided on the support member 5.2 and the climbing member 5.3, and a plurality of mounts cooperating with the hooks are provided in the height direction of the load-bearing member 5.1 (two rows of mounts can be provided vertically), and the hooks and mounts are connected by snapping.
  • a mount is provided on the support member, and a hook is provided on the load-bearing member.
  • the load-bearing member 5.1 can be selectively attached to the outer side of the inner shell 2, the inner side of the outer shell 1 or the outer side of the outer shell 1, to transfer all the loads of the platform to the factory shell, and drive the platform to climb or descend as a whole.
  • the climbing member 5.3 can adopt a frame structure, and a plurality of hooks are installed on both side surfaces of the frame structure.
  • the climbing member 5.3 When the climbing member 5.3 is climbed to the right position, the climbing member 5.3 is connected to the load-bearing member 5.1 at the corresponding position.
  • a crane 8 (multiple cranes may be arranged) is fixed on the steel platform system 4, the column 8.2 of the crane 8 is fixedly connected to the steel platform, and the crane boom 8.2 is retractable.
  • the crane boom 8.2 may be at different elevation angles with the column 8.2.
  • the crane 8 serves the inner shell 2, the outer shell 1, the steel lining, and even the internal structural materials for transportation and hoisting.
  • a concrete placing machine 9 is fixed on the steel platform system 4. During the construction phase of the dome of the inner shell 2, the concrete placing machine 9 can be extended to the center of the plane of the reactor building, thereby completing the concrete pouring of the dome of the inner shell 2.
  • a circular working track 10.1 is installed above the steel platform system 4, and a climbing working vehicle 10.2 is slidably installed on the circular working track 10.1, and the climbing working vehicle 10.2 can be raised and lowered.
  • the climbing working vehicle 10.2 can be raised and lowered, so as to be used for operations such as welding of steel linings 3 at different heights and installation of penetration parts.
  • the steel platform system 4 is connected to a plurality of top-sectioned downwardly extending transport devices 11 (the structure in the prior art can be used).
  • the top-sectioned downwardly extending transport devices 11 are fixedly connected to the steel platform system 4 and are not connected to the surrounding factory buildings 12.
  • the top-sectioned downwardly extending transport devices 11 are raised as the steel platform system 4 is lifted, and then a standard elevator section is added to the top and extended downward.
  • the nuclear island reactor building construction equipment integrated platform also includes a construction elevator 13 located on both sides of the buttress column 14, the construction elevator 13 includes a construction elevator standard section 13.1 that can be detachably installed on the side of the nuclear island reactor building, and a ladder cage 13.2 installed on the construction elevator standard section 13.1 and movable up and down relative to it.
  • construction workers By setting up a construction elevator 13, construction workers can ascend from the inner and outer shells to the hanger and enter the steel platform for work.
  • the ladder cage 13.2 can be loaded with prestressed steel bar tensioning workers and equipment to move up and down along the construction elevator standard section 13.1 to the designated position to perform horizontal prestressing on the side of the buttress column 14.
  • the working process of the construction elevator 13 is as follows:
  • the rack and formwork system 6 rises with the lifting of the integrated platform
  • the steel platform system 4 includes a detachably connected outer cantilever platform 15.1 and an inner cantilever platform 16.1.
  • the outer cantilever platform 15.1 is attached to the outer side of the nuclear island reactor building shell 1 through the outer cantilever platform fulcrum 15.2
  • the inner cantilever platform 16.1 is attached to the outer side of the nuclear island reactor building inner shell 2 through the inner cantilever platform fulcrum 16.2; an operating frame and prestressed tensioning equipment are arranged on the top of the inner cantilever platform 16.1.
  • Both the outer cantilever platform 15.1 and the inner cantilever platform 16.1 are steel truss structures.
  • the outer cantilever platform 15.1 is attached to the outer side of the outer shell 1 and serves as the construction support for the bottom plate of the ASP water tank;
  • the inner cantilever platform 16.1 is attached to the outer side of the inner shell 2 and serves as the ring beam, the Gamma prestressed tendon tensioning construction platform and the rainproof platform.
  • An outer cantilever platform fulcrum 15.2 and an inner cantilever platform fulcrum 16.2 are respectively installed on the outer side of the outer shell 1 and the outer side of the inner shell 2;
  • the inner cantilever platform 16.1 is attached to the outer side of the inner shell 2 through the inner cantilever platform fulcrum 16.2, and the outer cantilever platform 15.1 is attached to the outer side of the outer shell 1 through the support and jacking system 5;
  • the external cantilever platform 15.1 is lowered by the support and jacking system 5, and the external cantilever platform 15.1 reaches the height of the external cantilever platform fulcrum 15.2;
  • the integrated platform is supported on the wall of the inner and outer shell 1, and the multi-layer assembly line operation of the inner and outer shell 1 is realized through multi-layer hangers, avoiding the interference of the existing process mold turning frame, realizing the synchronous construction of the inner shell 2 and the outer shell 1, and decoupling the construction of the surrounding plant 12 from the outer shell 1, solving the problem of the "step-by-step” process of the inner shell 2, the outer shell 1, and the surrounding plant 12 restricting the total construction period in the existing construction of the nuclear island reactor plant;
  • the steel platform system 4 is composed of multiple radial and annular space trusses, with high overall bearing capacity and high rigidity, and can provide a loading platform for reactor construction.
  • heavy equipment such as cranes 8, concrete placing machines 9, elevators, etc. can be directly arranged on the steel platform, and climb synchronously with the platform in coordination with the formwork, etc., effectively improving the vertical transportation efficiency and eliminating the need for large construction equipment to be lifted separately and the plane position changed;
  • the steel platform system 4 can be adapted to the multi-stage construction of the reactor building through modification, reducing the need for additional measures for structural construction, saving construction time and costs.
  • the present invention further proposes a climbing method for a nuclear island reactor building construction equipment integrated platform.
  • a climbing method based on the above-mentioned nuclear island reactor building construction equipment integrated platform includes the following steps:
  • Step S10 connecting the climbing member 5.3 to the load-bearing member 5.1, and releasing the connection between the supporting member 5.2 and the load-bearing member 5.1;
  • Step S20 the oil cylinder of the hydraulic assembly 5.5 is extended to drive the support member 5.2 to drive the steel column 5.4, the steel platform system 4, the hanger and formwork system 6 and other auxiliary construction equipment and facilities to climb as a whole;
  • Step S30 when the integrated platform is lifted to the right position, the support member 5.2 is connected to the corresponding position load-bearing member 5.1;
  • Step S40 the connection between the climbing member 5.3 and the load-bearing member 5.1 is released, and the oil cylinder of the hydraulic assembly 5.5 is recovered, driving the climbing member 5.3 to climb upward;
  • Step S50 after the climbing member 5.3 has climbed to its proper position, the climbing member 5.3 is connected to the load-bearing member 5.1 at the corresponding position.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Jib Cranes (AREA)

Abstract

本发明公开了一种核岛反应堆厂房施工装备集成平台及其爬升方法。本核岛反应堆厂房施工装备集成平台包括钢平台系统、支承及顶升系统、挂架及模板系统和施工集成装备,支承及顶升系统安装于核岛反应堆厂房的侧面上,支承及顶升系统位于钢平台系统的下方,挂架及模板系统安装于钢平台系统下方;钢平台系统包括环向钢桁架、径向主钢桁架以及径向次钢桁架,施工集成装备包括安装于挂架及模板系统底部的环形轨道以及与环形轨道滑动连接的环吊。本核岛反应堆厂房施工装备集成平台,解决了核岛反应堆厂房现有施工中内壳、外壳、周边厂房"阶梯式"工艺制约总工期的问题。

Description

核岛反应堆厂房施工装备集成平台及其爬升方法 技术领域
本发明涉及核电站核岛厂房施工技术领域,涉及一种核岛反应堆厂房施工装备集成平台及其爬升方法。
背景技术
目前,核岛反应堆厂房内外壳施工模架以带三角挂架的弧形大模板系统为主。采用该系统存下以下问题:
第一、内壳悬挑式三角架竖向空间上阻挡外壳结构施工,从而形成内壳、外壳、周边厂房“阶梯式”施工工序,延长总工期。第二、模板三角挂架架体承载力低,施工材料只能布置于周边厂房外侧,堆场布置受限;第三、模板须借助外部塔吊向上转运,严重占用塔吊运力,同时材料转运、预埋件和贯穿件的安装就位等均依靠外部塔吊,导致垂直运输效率低。第四、现有工艺下,反应堆厂房ASP水箱、环廊、预应力筋等结构施工时须额外搭设落地支撑架和相关作业平台,施工技术措施复杂,既影响工期也显著增加施工成本。
发明内容
本发明的主要目的在于提供一种核岛反应堆厂房施工装备集成平台及其爬升方法,旨在解决核岛反应堆厂房现有施工中内壳、外壳、周边厂房“阶梯式”工艺制约总工期的问题。
为实现上述目的,本发明提供一种核岛反应堆厂房施工装备集成平台,包括钢平台系统、支承及顶升系统、挂架及模板系统和施工集成装备,其中,
所述支承及顶升系统安装于核岛反应堆厂房的侧面上,支承及顶升系统位于钢平台系统的下方以支撑将其相对于核岛反应堆厂房爬升,挂架及模板系统安装于钢平台系统下方;
所述钢平台系统包括环向钢桁架、径向主钢桁架以及径向次钢桁架,径向主钢桁架的两端分别与最内侧和最外侧环向钢桁架连接,径向次钢桁架在核岛反应堆厂房外壳上方断开以便于外壳施工材料向下吊入;
所述施工集成装备包括固定在钢平台上的吊臂可伸缩式吊机、布料机、登高作业车,安装于挂架及模板系统底部的环形轨道以及与环形轨道滑动连接的环吊,与钢平台连接的顶部加节向下延伸式运输装置等。
优选地,所述支承及顶升系统包括承力件、支撑件、爬升件、钢立柱以及液压组件,其中,所述承力件可拆卸安装于核岛反应堆厂房的侧面上,钢立柱的顶端与钢平台系统固定连接,底端与支撑件固定连接,液压组件的底部固定于爬升件内部且顶部与支撑件连接以支撑其爬升。
优选地,所述支撑件、爬升件与承力件通过挂爪或销轴实现可拆卸连接。
优选地,所述钢平台系统上固定有吊机,吊机立柱与钢平台固定连接,吊机大臂为可伸缩式。
优选地,所述钢平台系统上固定有混凝土布料机。
优选地,所述钢平台系统上方安装有环形作业轨道,登高作业车滑动安装于环形作业轨道上,登高作业车可升降。
优选地,所述钢平台系统连接有多台顶部加节向下延伸式运输装置。
优选地,所述核岛反应堆厂房施工装备集成平台还包括位于扶壁柱两侧的施工电梯,施工电梯包括可拆卸安装于核岛反应堆厂房的侧面上的施工电梯标准节以及安装于施工电梯标准节上且相对其可上下移动的梯笼。
优选地,所述钢平台系统包括可拆卸连接的外悬挑平台和内悬挑平台,拆卸外悬挑平台和内悬挑平台连接杆件后,外悬挑平台通过外悬挑平台支点附着于核岛反应堆厂房外壳外侧,内悬挑平台通过内悬挑平台支点附着于核岛反应堆厂房内壳外侧;所述内悬挑平台顶部布置有操作架和预应力张拉设备。
本发明进一步提出一种基于上述的核岛反应堆厂房施工装备集成平台的爬升方法,包括以下步骤:
将爬升件与承力件连接,解除支撑件和承力件之间的连接;
通过液压组件的油缸伸出,驱使支撑件带动钢立柱、钢平台系统、挂架及模板系统及其他附属施工设备设施整体爬升;
当集成平台爬升到位后,连接支撑件与相应位置承力件;
解除爬升件与承力件的连接,液压组件的油缸回收,带动爬升件向上爬升;
爬升件爬升到位后,连接爬升件与相应位置的承力件。
本发明提出的核岛反应堆厂房施工装备集成平台,具有以下有益效果:
1、因集成平台支撑在内外壳墙体上,并通过多层挂架实现内外壳多层流水作业,避免现有模板工艺的干涉,实现内壳、外壳等标高同步施工,周边厂房与外壳施工解耦,解决了核岛反应堆厂房现有施工中内壳、外壳、周边厂房“阶梯式”工艺制约总工期的问题;
2、钢平台系统由多道径向和环形空间桁架构成,整体承载力高、刚度大,能为反应堆厂房施工提供堆载平台,同时吊机、混凝土布料机、电梯等重型设备可直接布置在钢平台上,并协同模板等与平台同步爬升,有效提高垂直运输效率,并免除大型施工设备单独顶升、平面位置变更作业;
3、钢平台系统通过改造可适应反应堆厂房多阶段施工,减少结构施工所需的额外措施搭设,节省工期和成本。
附图说明
图1为本发明核岛反应堆厂房施工装备集成平台的剖面结构示意图;
图2为本发明核岛反应堆厂房施工装备集成平台中钢平台系统的结构示意图;
图3为本发明核岛反应堆厂房施工装备集成平台中支承及顶升系统的结构示意图;
图4为本发明核岛反应堆厂房施工装备集成平台中环廊吊装设备的结构示意图;
图5为本发明核岛反应堆厂房施工装备集成平台中吊机的平面结构示意图;
图6为本发明核岛反应堆厂房施工装备集成平台中吊机的立面结构示意图;
图7为本发明核岛反应堆厂房施工装备集成平台中混凝土布料机的结构示意图;
图8为本发明核岛反应堆厂房施工装备集成平台中登高作业车的结构示意图;
图9为本发明核岛反应堆厂房施工装备集成平台中顶部加节向下延伸式运输装置的结构示意图;
图10为本发明核岛反应堆厂房施工装备集成平台中施工电梯的平面布置示意图;
图11为本发明核岛反应堆厂房施工装备集成平台中施工电梯的立面布置示意图;
图12为本发明核岛反应堆厂房施工装备集成平台在改造后的结构示意图。
图中:1-外壳、2-内壳、3-钢衬里、4-钢平台系统、4.1-环向钢桁架、4.2-径向主钢桁架、4.3-径向次钢桁架、5-支承及顶升系统、5.1-承力件、5.2-支撑件、5.3-爬升件、5.4-钢立柱、5.5-液压组件、6-挂架及模板系统、7-施工集成装备、7.1-环形轨道、7.2-环吊、8-吊机、8.1-吊机大臂、8.2-立柱、9-混凝土布料机、10.1-环形作业轨道、10.2-登高作业车、11-顶部加节向下延伸式运输装置、12-周边厂房、13-施工电梯、13.1-施工电梯标准节、13.2-梯笼、14-扶壁柱、15.1-外悬挑平台、15.2-外悬挑平台支点、16.1-内悬挑平台、16.2-内悬挑平台支点、17-环梁。
本发明目的的实现、功能特点及优点将结合实施例,参照附图做进一步说明。
具体实施方式
应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
需要说明的是,在本发明的描述中,术语“横向”、“纵向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,并不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。此外,术语“第一”、“第二”等仅用于描述目的,而不能理解为指示或暗示相对重要性。
本发明提出一种核岛反应堆厂房施工装备集成平台。
参照图1至图11,本优选实施例中,一种核岛反应堆厂房施工装备集成平台,包括钢平台系统4(为各类设备设施提供布置空间)、支承及顶升系统5、挂架及模板系统6和施工集成装备7,其中,
支承及顶升系统5安装于核岛反应堆厂房的侧面上(可选择性地附着于内壳2外侧、外壳1的内侧或外壳1外侧),支承及顶升系统5位于钢平台系统4的下方以支撑将其相对于核岛反应堆厂房进行爬升,挂架及模板系统6悬挂安装于钢平台系统4下方;
钢平台系统4包括环向钢桁架4.1、径向主钢桁架4.2以及径向次钢桁架4.3,径向主钢桁架4.2的两端分别与最内侧的环向钢桁架4.1和最外侧的环向钢桁架4.1连接,径向次钢桁架4.3在核岛反应堆厂房外壳1上方断开以便于外壳1施工材料向下吊入;
施工集成装备7包括安装于挂架及模板系统6底部的环形轨道7.1以及与环形轨道7.1滑动连接的环吊7.2(设置有多个)。环形轨道7.1位于核岛反应堆厂房的外壳1和内壳2之间。
挂架及模板系统6连接于钢平台系统4下方,布置于外壳两侧,满足多层同时施工,可同时为壳体钢筋绑扎、预埋件安装、模板支设、混凝土浇筑、混凝土养护等提供作业平台,挂架内设斜梯,便于人员在各层上下通行。
钢平台系统4其平面呈环形结构,布置于内壳2和外壳1的上方。钢平台系统4上集成有设备设施与作业室。
钢平台系统4由至少三道径向和至少两道环形空间桁架构成,其整体承载力高、刚度大,能为反应堆施工提供堆载平台,同时吊机、混凝土布料机、电梯等重型设备可直接布置在钢平台系统4上,并协同模板等与平台同步爬升,有效提高垂直运输效率,并免除大型施工设备单独顶升、平面位置变更作业。
环廊施工构件通过外部塔吊吊运至内壳2和外壳1之间已完成的环廊平台上,再由环吊7.2将材料吊运至相应位置安装,安装好的环廊平台又可作为上一层环廊施工材料堆载平台。
具体地,参照图3,本实施例在此提出一支承及顶升系统5的具体结构:支承及顶升系统5包括承力件5.1、支撑件5.2、爬升件5.3、钢立柱5.4以及液压组件5.5,其中,承力件5.1可拆卸安装于核岛反应堆厂房的侧面上,钢立柱5.4的顶端与钢平台系统4固定连接,底端与支撑件5.2固定连接,液压组件5.5的底部固定于爬升件5.3内部且顶部与支撑件5.2连接以支撑其爬升。
具体地,支撑件5.2、爬升件5.3与承力件5.1通过挂爪或销轴实现可拆卸连接。如支撑件5.2和爬升件5.3上设置相应挂爪,承力件5.1高度方向上设置多个与挂爪配合的挂座(竖向上可设置两排挂座),挂爪和挂座卡合连接。或支撑件上设置挂座,承力件上设置挂爪。承力件5.1可选择性附着于内壳2外侧、外壳1内侧或外壳1外侧,将平台全部荷载传递至厂房壳体,并驱动平台进行整体爬升或下降。爬升件5.3可采用框架结构,框架结构的两侧面上安装有多个挂爪。
本支承及顶升系统5的工作过程如下:
1、将爬升件5.3与承力件5.1连接,解除支撑件5.2与承力件5.1连接;
2、控制液压组件5.5的油缸伸出,从而驱使支撑件5.2带动钢立柱5.4、钢平台系统4、挂架及模板系统6及其他附属施工设备设施整体爬升;
3、当集成平台爬升到位后,连接支撑件5.2与相应位置的承力件5.1;
4、解除爬升件5.3与承力件5.1的连接,控制液压组件5.5的油缸回收,从而带动爬升件5.3向上爬升;
5、当爬升件5.3爬升到位后,连接爬升件5.3与相应位置的承力件5.1。
进一步地,参照图5和图6,钢平台系统4上固定有吊机8(可布置多台),吊机8的立柱8.2与钢平台固定连接,吊机大臂8.2为可伸缩式。吊机大臂8.2可与立柱8.2成不同仰角。吊机8服务于内壳2、外壳1、钢衬里,乃至内部结构材料转运、吊装。
进一步地,参照图7,钢平台系统4上固定有混凝土布料机9。在内壳2穹顶施工阶段,混凝土布料机9可伸至反应堆厂房平面中心处,从而完成内壳2穹顶混凝土浇筑。
进一步地,参照图8,钢平台系统4上方安装有环形作业轨道10.1,登高作业车10.2滑动安装于环形作业轨道10.1上,登高作业车10.2可升降。登高作业车10.2可升降,从而用于不同高度钢衬里3焊接、贯穿件安装等作业。
进一步地,参照图9,钢平台系统4连接有多台顶部加节向下延伸式运输装置11(采用现有技术中结构即可)。顶部加节向下延伸式运输装置11与钢平台系统4固定连接,并与周边厂房12不连接。顶部加节向下延伸式运输装置11随钢平台系统4的顶升而升高,再后顶部加装电梯标准节并向下延伸。 通过设置顶部加节向下延伸式运输装置11,从而保证施工人员从周边厂房12顶部进出集成平台。
进一步地,参照图10和图11,本核岛反应堆厂房施工装备集成平台还包括位于扶壁柱14两侧的施工电梯13,施工电梯13包括可拆卸安装于核岛反应堆厂房的侧面上的施工电梯标准节13.1、以及安装于施工电梯标准节13.1上且相对其可上下移动的梯笼13.2。
通过设置施工电梯13,从而使施工人员从内外壳间上升至挂架并进入钢平台作业。梯笼13.2可装载预应力钢筋张拉作业人员及设备沿施工电梯标准节13.1上下运行至指定位置,进行扶壁柱14侧面的水平预应力张拉作业。
施工电梯13的工作过程如下:
1、解除施工电梯标准节13.1与挂架及模板系统6之间的连接;
2、挂架及模板系统6随集成平台顶升而升高;
3、施工电梯标准节13.1吊入,并进行加节作业;
4、重新连接施工电梯标准节13.1与挂架及模板系统6,梯笼13.2可运行至挂架及模板系统6底部。
进一步地,参照图12,钢平台系统4包括可拆卸连接的外悬挑平台15.1和内悬挑平台16.1,拆卸外悬挑平台15.1和内悬挑平台16.1连接杆件后,外悬挑平台15.1通过外悬挑平台支点15.2附着于核岛反应堆厂房外壳1外侧,内悬挑平台16.1通过内悬挑平台支点16.2附着于核岛反应堆厂房内壳2外侧;内悬挑平台16.1顶部布置有操作架和预应力张拉设备。外悬挑平台15.1和内悬挑平台16.1均为钢桁架结构。
外悬挑平台15.1附着于外壳1外侧,作为ASP水箱底板施工支撑;内悬挑平台16.1附着于内壳2外侧,兼做环梁、Gamma预应力筋张拉施工平台与防雨平台。
本集成平台的拆改施工过程如下:
1、在外壳1的外侧和内壳2外侧分别安装外悬挑平台支点15.2和内悬挑平台支点16.2;
2、拆除钢平台系统4顶部的集成设备和作业室;
3、将钢平台系统4与内悬挑平台支点16.2连接;
4、拆除外壳1上部钢平台系统4的部分钢桁架,使钢平台系统4一分为 二,内悬挑平台16.1通过内悬挑平台支点16.2附着于内壳2外侧,外悬挑平台15.1通过支承及顶升系统5附着于外壳1外侧;
5、外悬挑平台15.1通过支承及顶升系统5下降,外悬挑平台15.1到达外悬挑平台支点15.2高度处;
6、连接外悬挑平台15.1与外悬挑平台支点15.2,外悬挑平台15.1支座转换;
7、拆除支承及顶升系统5。
本发明提出的核岛反应堆厂房施工装备集成平台,具有以下有益效果:
1、因集成平台支撑在内外壳1墙体上,并通过多层挂架实现内外壳1的多层流水作业,避免现有工艺翻模架体的干涉,实现内壳2、外壳1标高同步施工,周边厂房12与外壳1施工解耦,解决了核岛反应堆厂房现有施工中内壳2、外壳1、周边厂房12“阶梯式”工艺制约总工期的问题;
2、钢平台系统4由多道径向和环形空间桁架构成,整体承载力高、刚度大,能为反应堆施工提供堆载平台,同时吊机8、混凝土布料机9、电梯等重型设备可直接布置在钢平台上,并协同模板等与平台同步爬升,有效提高垂直运输效率,并免除大型施工设备单独顶升、平面位置变更作业;
3、钢平台系统4通过改造可适应反应堆厂房多阶段施工,减少结构施工所需的额外措施搭设,节省工期和成本。
本发明进一步提出一种核岛反应堆厂房施工装备集成平台的爬升方法。
本优选实施例中,一种基于上述核岛反应堆厂房施工装备集成平台的爬升方法,包括以下步骤:
步骤S10,将爬升件5.3与承力件5.1连接,解除支撑件5.2和承力件5.1之间的连接;
步骤S20,通过液压组件5.5的油缸伸出,驱使支撑件5.2带动钢立柱5.4、钢平台系统4、挂架及模板系统6及其他附属施工设备设施整体爬升;
步骤S30,当集成平台爬升到位后,连接支撑件5.2与相应位置承力件5.1;
步骤S40,解除爬升件5.3与承力件5.1的连接,液压组件5.5的油缸回收,带动爬升件5.3向上爬升;
步骤S50,爬升件5.3爬升到位后,连接爬升件5.3与相应位置的承力件5.1。
以上仅为本发明的优选实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。

Claims (10)

  1. 一种核岛反应堆厂房施工装备集成平台,其特征在于,包括钢平台系统、支承及顶升系统、挂架及模板系统和施工集成装备,其中,
    所述支承及顶升系统安装于核岛反应堆厂房的侧面上,支承及顶升系统位于钢平台系统的下方以支撑将其相对于核岛反应堆厂房爬升,挂架及模板系统安装于钢平台系统下方;
    所述钢平台系统包括环向钢桁架、径向主钢桁架以及径向次钢桁架,径向主钢桁架的两端分别与最内侧和最外侧环向钢桁架连接,径向次钢桁架在核岛反应堆厂房外壳上方断开以便于外壳施工材料向下吊入;
    所述施工集成装备包括固定在钢平台上的吊臂可伸缩式吊机、布料机、登高作业车,安装于挂架及模板系统底部的环形轨道以及与环形轨道滑动连接的环吊,与钢平台连接的顶部加节向下延伸式运输装置等。
  2. 如权利要求1所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述支承及顶升系统包括承力件、支撑件、爬升件、钢立柱以及液压组件,其中,所述承力件可拆卸安装于核岛反应堆厂房的侧面上,钢立柱的顶端与钢平台系统固定连接,底端与支撑件固定连接,液压组件的底部固定于爬升件内部且顶部与支撑件连接以支撑其爬升。
  3. 如权利要求2所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述支撑件、爬升件与承力件通过挂爪或销轴实现可拆卸连接。
  4. 如权利要求2所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述钢平台系统上固定有吊机,吊机立柱与钢平台固定连接,吊机大臂为可伸缩式。
  5. 如权利要求2所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述钢平台系统上固定有混凝土布料机。
  6. 如权利要求2所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述钢平台系统上方安装有环形作业轨道,登高作业车滑动安装于环形作业轨道上,登高作业车可升降。
  7. 如权利要求2所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述钢平台系统连接有多台顶部加节向下延伸式运输装置。
  8. 如权利要求2所述的核岛反应堆厂房施工装备集成平台,其特征在于, 还包括位于扶壁柱两侧的施工电梯,施工电梯包括可拆卸安装于核岛反应堆厂房的侧面上的施工电梯标准节以及安装于施工电梯标准节上且相对其可上下移动的梯笼。
  9. 如权利要求2至8中任意一项所述的核岛反应堆厂房施工装备集成平台,其特征在于,所述钢平台系统包括可拆卸连接的外悬挑平台和内悬挑平台,拆卸外悬挑平台和内悬挑平台连接杆件后,外悬挑平台通过外悬挑平台支点附着于核岛反应堆厂房外壳外侧,内悬挑平台通过内悬挑平台支点附着于核岛反应堆厂房内壳外侧;所述内悬挑平台顶部布置有操作架和预应力张拉设备。
  10. 一种基于权利要求2至9中任意一项所述的核岛反应堆厂房施工装备集成平台的爬升方法,其特征在于,包括以下步骤:
    将爬升件与承力件连接,解除支撑件和承力件之间的连接;
    通过液压组件的油缸伸出,驱使支撑件带动钢立柱、钢平台系统、挂架及模板系统及其他附属施工设备设施整体爬升;
    当集成平台爬升到位后,连接支撑件与相应位置承力件;
    解除爬升件与承力件的连接,液压组件的油缸回收,带动爬升件向上爬升;
    爬升件爬升到位后,连接爬升件与相应位置的承力件。
PCT/CN2023/132188 2022-11-18 2023-11-17 核岛反应堆厂房施工装备集成平台及其爬升方法 WO2024104449A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202211445529.5A CN115680286A (zh) 2022-11-18 2022-11-18 核岛反应堆厂房施工装备集成平台及其爬升方法
CN202211445529.5 2022-11-18

Publications (1)

Publication Number Publication Date
WO2024104449A1 true WO2024104449A1 (zh) 2024-05-23

Family

ID=85053224

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2023/132188 WO2024104449A1 (zh) 2022-11-18 2023-11-17 核岛反应堆厂房施工装备集成平台及其爬升方法

Country Status (2)

Country Link
CN (1) CN115680286A (zh)
WO (1) WO2024104449A1 (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115680286A (zh) * 2022-11-18 2023-02-03 中建三局集团有限公司 核岛反应堆厂房施工装备集成平台及其爬升方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10111378A (ja) * 1996-10-07 1998-04-28 Hitachi Ltd 円筒構造物の据付方法
CN102155089A (zh) * 2011-01-30 2011-08-17 中建三局建设工程股份有限公司 一种集垂直运输设备及模架为一体的自顶升施工平台
CN106703401A (zh) * 2015-07-30 2017-05-24 中国核工业第二二建设有限公司 Ap1000核岛屏蔽墙模板及施工操作平台
CN111894272A (zh) * 2020-08-19 2020-11-06 张前进 一种智能型施工平台及其安装工艺和施工工艺
CN115680286A (zh) * 2022-11-18 2023-02-03 中建三局集团有限公司 核岛反应堆厂房施工装备集成平台及其爬升方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10111378A (ja) * 1996-10-07 1998-04-28 Hitachi Ltd 円筒構造物の据付方法
CN102155089A (zh) * 2011-01-30 2011-08-17 中建三局建设工程股份有限公司 一种集垂直运输设备及模架为一体的自顶升施工平台
CN106703401A (zh) * 2015-07-30 2017-05-24 中国核工业第二二建设有限公司 Ap1000核岛屏蔽墙模板及施工操作平台
CN111894272A (zh) * 2020-08-19 2020-11-06 张前进 一种智能型施工平台及其安装工艺和施工工艺
CN115680286A (zh) * 2022-11-18 2023-02-03 中建三局集团有限公司 核岛反应堆厂房施工装备集成平台及其爬升方法

Also Published As

Publication number Publication date
CN115680286A (zh) 2023-02-03

Similar Documents

Publication Publication Date Title
CN101886468B (zh) 高位连体结构悬挂式模板支撑施工方法
WO2024104449A1 (zh) 核岛反应堆厂房施工装备集成平台及其爬升方法
CN101191382A (zh) 钢柱支撑式整体自升钢平台脚手模板系统及其施工方法
CN113090014A (zh) 一种高层装配式建筑整体作业平台及其施工方法与应用
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
CN111894272A (zh) 一种智能型施工平台及其安装工艺和施工工艺
CN115538792A (zh) 一种住宅造楼机安装施工方法及结构
JP3579816B2 (ja) 躯体構築用多目的ステージ
JP4247851B2 (ja) クライミングクレーンの使用方法
JPH08311818A (ja) 建造物のクライミング式リフトアップ工法およびその装置
CN208152583U (zh) 一种高层建筑施工辅助设备
CN216810895U (zh) 一种电梯井作业平台
CN114988310A (zh) 一种爬模下核心筒内部钢梁倒运安装系统及其施工方法
CN111196566A (zh) 超高层内爬塔吊的施工结构及施工方法
JP3220397B2 (ja) 昇降式足場
Zhang et al. Significant progress in construction equipment of super high-rise building
CN206220484U (zh) 一种钢平台的模板吊点承重梁
CN116335398B (zh) 一种多层快速施工方法
CN116181041B (zh) 一种多层快速施工的造楼机
JP2003120037A (ja) 高層建物の建設揚重システム
CN219100670U (zh) 一种低位顶升爬升施工平台
CN217299872U (zh) 一种井筒液压综合布料平台
CN218114742U (zh) 扁担梁吊装系统和扁担梁吊装体系
CN215564411U (zh) 一种用于高耸筒状建筑物的滑移施工装置
CN215055166U (zh) 一种高效高层装配式建筑作业平台