WO2023015711A1 - 装配式地铁车站施工方法 - Google Patents

装配式地铁车站施工方法 Download PDF

Info

Publication number
WO2023015711A1
WO2023015711A1 PCT/CN2021/123000 CN2021123000W WO2023015711A1 WO 2023015711 A1 WO2023015711 A1 WO 2023015711A1 CN 2021123000 W CN2021123000 W CN 2021123000W WO 2023015711 A1 WO2023015711 A1 WO 2023015711A1
Authority
WO
WIPO (PCT)
Prior art keywords
assembly
component
rings
assembled
level
Prior art date
Application number
PCT/CN2021/123000
Other languages
English (en)
French (fr)
Inventor
罗璞
黄超
张准
马文彬
程凤
舒俊
饶烺
郑锃
陈垚学
李楠
Original Assignee
中铁工程机械研究设计院有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁工程机械研究设计院有限公司 filed Critical 中铁工程机械研究设计院有限公司
Publication of WO2023015711A1 publication Critical patent/WO2023015711A1/zh

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof

Definitions

  • the invention relates to the technical field of subway station construction, in particular to a method for constructing a prefabricated subway station.
  • the subway is the travel method that many people choose.
  • the construction of the subway takes a long period, and the construction speed has always been a problem to be solved.
  • more and more subways now choose prefabricated construction methods.
  • the existing prefabricated construction methods usually use gantry cranes to assemble layer by layer or assemble them into rings one by one.
  • the above assembly methods are usually efficient Low, seriously affecting the construction period and use requirements.
  • the problem solved by the invention is how to improve the construction efficiency of the prefabricated subway station.
  • the present invention provides a construction method for a prefabricated subway station.
  • the prefabricated subway station includes a bottom-level component, a middle-level component and a top-level component, and the bottom-level component is connected to the top-level component through the middle-level component; the assembly
  • the construction methods of type subway stations include:
  • the assembly of the middle-level components of the predetermined number of rings is completed, the assembly of the top-level components is started on the middle-level components.
  • the bottom-level components, the middle-level components and the top-level components are arranged in steps and Simultaneously assemble.
  • the construction method of the prefabricated subway station described in the present invention can start the assembly of the middle-level components after the bottom-level components are assembled to the predetermined number of rings, and then start the assembly of the top-level components after the middle-level components are assembled to the predetermined number of rings, and then Bottom-level components, middle-level components and top-level components are assembled simultaneously in a stepwise manner until all bottom-level components, middle-level components and top-level components are fully assembled, which improves assembly efficiency and shortens the construction period.
  • the bottom assembly includes a bottom component and two bottom corner components, and the two bottom corner components are respectively arranged at both ends of the bottom component;
  • the assembly of the bottom component includes:
  • the bottom component is fixed on the bottom surface of the foundation pit by a gantry crane, and the two bottom corner components are respectively fixed on both ends of the bottom component, so as to assemble the bottom layer assembly of the first ring.
  • the accuracy and stability of the assembly of the bottom layer components of the first ring are guaranteed, and the bottom layer components of the first ring are used as a benchmark to ensure the accuracy of subsequent assembly.
  • the assembly of the underlying components also includes:
  • the bottom layer components of the first ring are assembled, the bottom layer components of the remaining rings are assembled by a bottom layer assembly machine, and each ring is longitudinally compressed by the bottom layer assembly machine.
  • the bottom assembly machine automatically assembles the bottom components and compresses each ring, which improves the assembly efficiency and the stability of the bottom components after assembly.
  • the assembly of the remaining rings using the bottom assembly machine includes:
  • the bottom component is fixed on the bottom surface of the foundation pit by using the bottom assembly machine, and the two bottom corner components are respectively fixed at both ends of the bottom component.
  • the assembly of one ring bottom layer assembly can be completed only by fixing the two bottom corner members to the two ends of the bottom member respectively, and the assembly of all ring bottom layer assemblies can be completed repeatedly in sequence.
  • the construction method of the prefabricated subway station also includes:
  • the fertilizer tank of the bottom-level components is backfilled, and when the assembly of the middle-level components of the predetermined number of rings is completed, the fertilizer tank of the middle-level components is backfilled, When the assembly of the top-level components of a predetermined number of rings is completed, the fertilizer tank of the top-level components is backfilled.
  • the middle layer assembly includes a middle plate member and two side plate members, the bottom ends of the two side plate members are respectively fixedly connected with the top ends of the two bottom corner members, and the two side plate members of the middle plate member ends are respectively fixedly connected with the two side plate members;
  • the assembly of the middle layer assembly includes:
  • the two side plate components are respectively fixed on the two bottom corner components by using a middle layer assembly machine, and the middle plate component is fixed between the two side plate components.
  • the roof assembly includes two corner components and a top plate component, one ends of the two corner components are respectively fixedly connected to the top ends of the two side plate components, and the two ends of the top plate component are respectively connected to The other ends of the two side plate members are fixedly connected;
  • the assembly of the top floor assembly includes:
  • the two corner components are respectively fixed on the top ends of the two side plate components by using a roof assembly machine, and the top plate component is fixed between the two corner components.
  • the assembly of the underlying components includes:
  • a base track is laid on the bottom of the foundation pit, a gantry crane is used to place a base assembly machine on the base track, and the base assembly is assembled by the base assembly machine.
  • the assembly of the middle layer components includes:
  • the assembly of the top-level components includes:
  • middle-level components After the middle-level components are assembled to a predetermined number of rings, start to lay the middle-level track on the assembled middle-level components, use the gantry crane to place the top-level assembly machine on the middle-level track, and use the top-level assembly machine to assemble The top-level component.
  • Fig. 1 is the flow chart of the prefabricated subway station construction method of the embodiment of the present invention.
  • Fig. 2 is the schematic diagram of the construction method of the assembled subway station of the embodiment of the present invention.
  • Fig. 3 is a schematic structural view of a prefabricated subway station according to an embodiment of the present invention.
  • a coordinate system XYZ is set, wherein the positive direction of the X-axis represents the front, the reverse direction of the X-axis represents the rear, the positive direction of the Y-axis represents the right, and the reverse direction of the Y-axis represents the left.
  • the positive direction of the Z axis represents the upward direction, and the negative direction of the Z axis represents the downward direction.
  • a construction method of a prefabricated subway station As shown in FIG. 1 and FIG. 2, a construction method of a prefabricated subway station according to an embodiment of the present invention, wherein the prefabricated subway station includes a bottom assembly 1, a middle assembly 2 and a top assembly 3, and the bottom assembly 1 passes through the middle assembly 2 and The top floor components 3 are connected to each other; the construction method of the prefabricated subway station includes:
  • middle layer assembly 2 When finishing the assembling of the middle layer assembly 2 of predetermined number of rings, begin to carry out the assembly of top layer assembly 3 on middle layer assembly 2, this moment, bottom layer assembly 1, middle layer assembly 2 and top layer assembly 3 were arranged in steps and assembled simultaneously.
  • the bottom assembly 1 is assembled first, and after the bottom assembly 1 is assembled to a predetermined number of rings, the bottom assembly 1 is started. Assembling the middle component 2, the bottom component 1 and the middle component 2 are being assembled at the same time. When the assembly progress of the middle-level component 2 reaches the predetermined number of rings, the assembly of the top-level component 3 starts on the middle-level component 2. When the assembly of the top-level component 3 and the middle-level component 2 is completed, a complete ring can be formed. At this time, the bottom component 1 1. The middle-level component 2 and the top-level component 3 are assembled simultaneously in a stepwise manner.
  • the middle assembly 2 has completed the assembly of the second predetermined number of rings
  • the bottom assembly 1 has completed the assembly of the third predetermined number of rings.
  • Component 1 always completes a predetermined number of loops more than the middle component 2, and at the same time, the middle component 2 always completes a predetermined number of loops more than the top component 3, so that the bottom component 1, the middle component 2 and the top component 3 can be assembled at the same time.
  • the working efficiency is further improved.
  • the bottom component 1 when the middle component 2 starts to assemble, the bottom component 1 does not stop assembling. At this time, the bottom component 1 and the middle component 2 are assembled at the same time.
  • the middle assembly 2 starts to assemble
  • the bottom assembly 1 has reached the predetermined number of rings for the second time. the number of rings.
  • the assembly of the middle-level component 2 After the assembly of the middle-level component 2 reaches the predetermined number of rings for the first time, the assembly of the top-level component 3 starts, and the assembly of the bottom-level component 1 and the middle-level component 2 does not stop, and then the bottom-level component 1, middle-level component 2 and top-level component 3 are assembled at the same time .
  • the middle-level assembly 2 After the assembly of the top-level assembly 3 reaches the predetermined number of rings for the first time, the middle-level assembly 2 has reached the predetermined number of rings for the second time, and the bottom-level assembly 1 has reached the predetermined number of rings for the third time.
  • the component 2 and the top-level component 3 can be continuously assembled in a stepwise manner until the assembly is completed.
  • the number of rings refers to the number of bottom-level components 1 , middle-level components 2 or top-level components 3 arranged along the direction of subway travel.
  • the middle-level component 2 can be assembled on the bottom-level component 1, and after all the middle-level components 2 are assembled, the middle-level component 2 can be finally assembled Top level component3.
  • the bottom assembly 1 includes a bottom member 11 and two bottom corner members 12, and the two bottom corner members 12 are respectively arranged at both ends of the bottom member 11.
  • the first ring floor assembly 1 is assembled by a gantry crane, and the bottom member 11 is fixed on the bottom surface of the foundation pit by the gantry crane, and then the two bottom corner members 12 are respectively fixed on the two ends of the bottom member 11 to complete the first ring floor assembly 1 assembly.
  • the first ring is assembled by the gantry crane, which ensures the accuracy of the initial assembly.
  • the assembly of the bottom assembly 1 also includes: using the bottom assembly machine 4 to assemble the remaining ring bottom assembly 1, and using the bottom assembly machine 4 to longitudinally compress each ring to ensure the stability of the bottom of the bottom assembly 1 .
  • longitudinal compression refers to the compression in the direction perpendicular to the ground, and each ring is compressed in the direction perpendicular to the ground by the bottom assembly machine 4 to ensure the stability after assembly.
  • using the bottom assembly machine 4 to assemble the remaining ring bottom layer components 1 includes: using the bottom assembly machine 4 to fix the bottom member 11 on the bottom surface of the foundation pit, and fixing the two bottom corner members 12 on the two sides of the bottom member 11 respectively. end.
  • the base assembly 1 includes a bottom member 11 and two bottom corner members 12, and the bottom assembly machine 4 needs to fix the bottom member 11 on the bottom surface of the foundation pit, and then install the two bottom corner members 12 on The two ends of the bottom member 11 are used to complete the assembly of a ring of bottom components 1 , and the bottom component 11 is assembled with two bottom corner components 12 repeatedly until the assembly of all bottom components 1 is completed.
  • the construction method of the subway station further includes: when completing the assembly of the bottom assembly 1 of a predetermined number of rings, backfilling the fertilizer tank of the bottom assembly 1, every time the assembly of the bottom assembly 1 of a predetermined number of rings is completed, When the middle module 2 is assembled, the fertilizer groove of the middle module 2 is backfilled, and when a predetermined number of rings of the top module 3 is assembled, the fertilizer groove of the top module 3 is backfilled.
  • the fertilizer tank of the bottom component 1 within the first predetermined number of cycles is backfilled.
  • the middle layer component 2 completes the first predetermined number of cycles at this time, for the bottom layer component 1 in the second predetermined cycle number and the middle layer component 2 in the first predetermined cycle number
  • the manure tank is backfilled.
  • the middle layer component 2 completes the second predetermined cycle number
  • the top layer component 3 completes the first predetermined cycle number, and the bottom layer component 1 in the third predetermined cycle number 1.
  • the middle layer assembly 2 includes a middle plate member 21 and two side plate members 22, the bottom ends of the two side plate members 22 are connected to the top ends of the two bottom corner members 12 respectively. Fixed connection, the two ends of the middle plate member 21 are respectively fixedly connected with the two side plate members 22; after the bottom assembly 1 is assembled to a predetermined number of rings, the middle layer assembly machine 5 is used to fix the two side plate members 22 respectively on the bottom layer On the two bottom corner components 12 of the component 1 , the middle plate component 21 is fixed between the two side plate components 22 , so as to complete the assembly of the middle component 2 on the bottom component 1 .
  • the roof assembly 3 includes two corner members 32 and a top plate member 31, one end of the two corner members 32 is fixedly connected to the top ends of the two side plate members 22 respectively, and the two ends of the top plate member 31 The ends are respectively fixedly connected with the other ends of the two side plate members 22.
  • the top layer assembly machine 6 is used to fix the two top corner members 32 respectively on the two ends of the middle layer assembly 2.
  • the top plate member 31 is fixed between the two corner members 32 , so as to complete the assembly between the middle layer assembly 2 and the top layer assembly 3 .
  • the track is laid before the bottom assembly 1, the middle assembly 2 and the top assembly 3 are assembled, and the bottom assembly 1, the middle assembly 2 and The top layer assembly 3 is assembled.
  • the base track has been completely laid at the bottom of the foundation pit from the beginning, and the gantry crane can continue to assemble the base component 1 by placing the base assembly machine 4 on the base track.
  • the base track and the middle track are scheduled as the components are completed The number of rings increases accordingly.
  • the bottom track is laid on the bottom assembly 1 within the predetermined number of rings for the first time, and the middle layer assembly machine 5 is placed on the bottom track by a gantry crane Above, the middle layer assembly machine 5 moves on the bottom track, so that the middle layer assembly 2 of the first predetermined number of rings is assembled on the bottom layer assembly 1 that has completed the first predetermined number of rings.
  • the bottom layer assembly machine 4 Working at the same time as the middle assembly machine 5, after the middle assembly 2 completes the assembly of the predetermined number of rings for the first time, the bottom assembly 1 has completed the second assembly of the predetermined number of rings.
  • the laying of the first section of the middle track is carried out on the middle component 2 that has completed the first predetermined number of rings.
  • the second section of the bottom track is laid on the bottom assembly 1 that has completed the second predetermined number of rings.
  • the top floor assembly machine 6 is placed in the first section by a gantry crane. On the middle track, the bottom assembly machine 4, the middle assembly machine 5 and the top assembly machine 6 are started simultaneously at the same time, and the bottom assembly 1, the middle assembly 2 and the top assembly 3 are assembled for the next predetermined number of rings respectively.
  • the assembly of the next predetermined number of rings at this time means that the bottom assembly 1 completes the assembly of the third predetermined number of rings, the middle assembly 2 completes the assembly of the second predetermined number of rings, and the top layer assembly 3 completes the first assembly. Assembly of a predetermined number of rings.
  • the assembly of the next predetermined number of rings is carried out again, it is necessary to lay the third section of the bottom track on the bottom assembly 1 of the third predetermined number of rings and lay the second section on the middle layer assembly 2 of the second predetermined number of rings.
  • the construction method of a prefabricated subway station includes the following steps:
  • the transverse direction refers to the assembly direction of the bottom corner member 12 and the bottom member 11 .
  • the bottom assembly 1 is assembled by the bottom assembly machine 4 and each ring is longitudinally compressed by the bottom assembly machine 4. After the first flow section is completed, the bottom fertilizer tank of the bottom assembly 1 that has completed the flow section is backfilled.
  • the pipeline section refers to the number of loops included in one section when it is completed in multiple sections, and the number of loops in a pipeline section can be selected according to actual needs.
  • the bottom track is laid on the bottom assembly 1 in the first flow section, the middle assembly machine 5 is installed on the bottom track with a gantry crane, and the middle plate member 21 and the side plate member 22 are assembled to complete the bottom assembly 1 and Assembly between middle level components 2.
  • the middle assembly machine 5 and the bottom assembly machine 4 carry out the assembly operation at the same time.
  • the bottom assembly 1 has completed the assembly of the second flow section.
  • the bottom fertilizer tank in the section and the middle layer fertilizer tank in the first flow section of the middle module 2 are backfilled.
  • the roof assembly machine 6 is used to assemble the roof member 31 and the corner member 32, so as to assemble the roof assembly 3 on the middle assembly 2 in the first flow section.
  • the bottom assembly machine 4, the middle assembly machine 5 and the top assembly machine 6 are assembled simultaneously in a stepwise manner, that is, when the top assembly 3 completes the assembly of the first flow section, the middle assembly 2 has completed the assembly of the second flow section , the bottom component 1 has completed the assembly of the third pipeline segment.

Abstract

一种装配式地铁车站施工方法,包括:开挖基坑;装配底层组件(1),当完成预定环数的所述底层组件(1)的装配时,开始在所述底层组件(1)上进行中层组件(2)的装配;当完成预定环数的中层组件(2)的装配时,开始在所述中层组件(2)上进行顶层组件(3)的装配。该施工方法在底层组件(1)装配至预定环数后开始中层组件(2)的装配,接着在中层组件(2)装配至预定环数后开始顶层组件(3)的装配,之后底层组件(1)、中层组件(2)和顶层组件(3)呈阶梯式同时进行装配,直至将所有底层组件(1)、中层组件(2)和顶层组件(3)全部装配完成以形成地铁车站,提高了装配的效率,缩短了工期。

Description

装配式地铁车站施工方法 技术领域
本发明涉及地铁车站施工技术领域,具体而言,涉及一种装配式地铁车站施工方法。
背景技术
随着城市人口的增加,人们的出行可供选择的方式越来越多,地铁是很多人选择的出行方式,而建造地铁需要较长的周期,施工速度是一直有待解决的问题。为了解决地铁施工速度的问题,现在越来越多的地铁选择装配式施工方法,现有的装配式施工方法通常采用龙门吊逐层装配或者逐个依次装配成环的方法进行装配,上述装配方法通常效率较低,严重影响施工周期与使用需求。
发明内容
本发明解决的问题是如何提高装配式地铁车站的施工效率。
为解决上述问题,本发明提供一种装配式地铁车站施工方法,装配式地铁车站包括底层组件、中层组件和顶层组件,所述底层组件通过所述中层组件与所述顶层组件连接;所述装配式地铁车站施工方法包括:
开挖基坑;
装配所述底层组件,当完成预定环数的所述底层组件的装配时,开始在所述底层组件上进行所述中层组件的装配;
当完成预定环数的所述中层组件的装配时,开始在所述中层组件上进行所述顶层组件的装配,此时所述底层组件、所述中层组件和所述顶层组件呈阶梯式设置且同时进行装配。
相对于现有技术,本发明所述的装配式地铁车站施工方法可以在底层组件装配至预定环数后开始中层组件的装配,接着在中层组件装配至预定环数后开始顶层组件的装配,之后底层组件、中层组件和顶层组件呈阶梯式同时进行装配,直至将所有底层组件、中层组件和顶层组件全部装配完成,提高了装配的效率,缩短了工期。
可选地,所述底层组件包括底部构件和两个底角构件,两个所述底角构件分别设置在所述底部构件的两端;所述底层组件的装配包括:
利用龙门吊将所述底部构件固定在所述基坑底面,将两个所述底角构件分别固定在所述底部构件的两端,以对第一环所述底层组件进行装配。
由此,保证第一环底层组件装配的准确性和稳定性,后面以第一环底层组件为基准,保证后续装配的精度。
可选地,所述底层组件的装配还包括:
在第一环底层组件装配后,利用底层拼装机装配其余环所述底层组件,并利用所述底层拼装机对每一环进行纵向压紧。
由此,后续通过底层拼装机对底层组件进行自动装配以及对每一环进行压紧,提高了装配效率和装配后底层组件的稳固性。
可选地,所述利用底层拼装机装配其余环所述底层组件包括:
利用所述底层拼装机将所述底部构件固定在所述基坑底面,并将两个所述底角构件分别固定在所述底部构件的两端。
由此,只需将两个底角构件分别固定在底部构件的两端就可完成一环底层组件的装配,依次重复完成全部环底层组件的装配。
可选地,装配式地铁车站施工方法还包括:
每完成预定环数的所述底层组件的装配时,对所述底层组件的肥槽进行回填,每完成预定环数的所述中层组件的装配时,对所述中层组件的肥槽进行回填,每完成预定环数的所述顶层组件的装配时,对所述顶层组件的肥槽进行回填。
由此,保证底层组件、中层组件和顶层组件装配时的结构强度。
可选地,所述中层组件包括中板构件和两个侧板构件,两个所述侧板构件的底端分别与两个所述底角构件的顶端固定连接,所述中板构件的两端分别与两个所述侧板构件固定连接;所述中层组件的装配包括:
利用中层拼装机将两个所述侧板构件分别固定在两个所述底角构件上,并将所述中板构件固定在两个所述侧板构件之间。
由此,持续在底层组件上进行中层组件的装配。
可选地,所述顶层组件包括两个顶角构件和顶板构件,两个所述顶角构件的一端分别与两个所述侧板构件的顶端固定连接,所述顶板构件的两端分别与两个所述侧板构件的另一端固定连接;所述顶层组件的装配包括:
利用顶层拼装机将两个所述顶角构件分别固定在两个所述侧板构件的顶端,并将所述顶板构件固定在两个所述顶角构件之间。
由此,持续在中层组件上进行顶层组件的装配。
可选地,所述底层组件的装配包括:
在所述基坑底部铺设基层轨道,利用龙门吊将底层拼装机放置在所述基层轨道上,通过所述底层拼装机装配所述底层组件。
由此,便于底层拼装机在基层轨道上移动,以完成全部底层组件的装配。
可选地,所述中层组件的装配包括:
当所述底层组件装配至预定环数后,开始在已装配完成的所述底层组件上铺设底层轨道,利用所述龙门吊将中层拼装机放置在所述底层轨道上,通过所述中层拼装机装配所述中层组件。
由此,便于中层拼装机在底层轨道上移动,以完成全部中层组件的装配。
可选地,所述顶层组件的装配包括:
当所述中层组件装配至预定环数后,开始在已装配完成的所述中层组件上铺设中层轨道,利用所述龙门吊将顶层拼装机放置在所述中层轨道上,通过所述顶层拼装机装配所述顶层组件。
由此,便于顶层拼装机在中层轨道上移动,以完成全部顶层组件的装配。
附图说明
图1为本发明实施例的装配式地铁车站施工方法的流程图;
图2为本发明实施例的装配式地铁车站施工方法示意图;
图3为本发明实施例的装配式地铁车站的结构示意图。
附图标记说明:
1-底层组件,11-底部构件,12-底角构件,2-中层组件,21-中板构件,22-侧板构件,3-顶层组件,31-顶板构件,32-顶角构件,4-底层拼装机,5-中层拼装机,6-顶层拼装机,7-第一钢支撑,8-第二钢支撑。
具体实施方式
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。通常 在此处附图中描述和示出的本发明实施例的组件可以以各种不同的配置来布置和设计。
因此,以下对附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
在本发明的描述中,需要说明的是,术语“上”、“下”、“左”、“右”、“内”、“外”、“前”、“后”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。本发明的实施例的附图中设置有坐标系XYZ,其中X轴的正向代表前方,X轴的反向代表后方,Y轴的正向代表右方,Y轴的反向代表左方,Z轴的正向代表上方,Z轴的反向代表下方。
以下结合附图对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。
结合图1和图2所示,本发明实施例的一种装配式地铁车站施工方法,其中,装配式地铁车站包括底层组件1、中层组件2和顶层组件3,底层组件1通过中层组件2与顶层组件3相互连接;所述装配式地铁车站施工方法包括:
开挖基坑;
装配底层组件1,当完成预定环数的底层组件1的装配时,开始在底层组件1上进行中层组件2的装配;
当完成预定环数的中层组件2的装配时,开始在中层组件2上进行顶层组件3的装配,此时底层组件1、中层组件2和顶层组件3呈阶梯式设置且同时进行装配。
结合图2所示,具体地,在本实施例中,在基坑开挖完成后,先进行底层组件1的装配,将底层组件1装配至预定的环数后,开始在底层组件1上进行中层组件2的装配,此时底层组件1和中层组件2同时在进行装配。 当中层组件2装配进度达到预定的环数时,开始在中层组件2上进行顶层组件3的装配,待顶层组件3与中层组件2装配完成时便可形成一个完整的环,此时底层组件1、中层组件2和顶层组件3呈阶梯式同时进行装配。应当理解的是,当顶层组件3完成一个预定环数的装配时,此时中层组件2已完成第二个预定环数的装配,底层组件1已完成第三个预定环数的装配,即底层组件1始终比中层组件2多完成一个预定环数,同时中层组件2始终比顶层组件3多完成一个预定环数,由此底层组件1、中层组件2和顶层组件3可以实现同时进行装配,与依次成环或者在所有底层组件1完成装配后,再装配中层组件2,最后装配顶层组件3相比,进一步提高了工作效率。
需要说明的是,底层组件1装配至预定环数后,中层组件2开始装配时,底层组件1并未停止装配,此时底层组件1和中层组件2同时进行装配。由此,在底层组件1的装配第一次达到预定的环数后,中层组件2开始装配,待中层组件2的装配第一次达到预定的环数后,底层组件1已第二次达到预定的环数。当中层组件2的装配第一次达到预定的环数后,顶层组件3开始装配,底层组件1、中层组件2也并未停止装配,之后底层组件1、中层组件2和顶层组件3同时进行装配。由此,在顶层组件3的装配第一次达到预定的环数后,中层组件2已第二次达到预定的环数,底层组件1已第三次达到预定的环数,底层组件1、中层组件2和顶层组件3便可以呈现阶梯式持续同时装配,直至装配完成。
应当理解的是,环数是指底层组件1、中层组件2或顶层组件3沿地铁行驶方向上排列的个数。
需要说明的是,在本实施例中,也可在所有底层组件1装配完成后,在底层组件1上进行中层组件2的装配,等所有中层组件2装配完成后,最后在中层组件2上装配顶层组件3。
结合图2和图3所示,优选地,底层组件1包括底部构件11和两个底角构件12,两个底角构件12分别设置在底部构件11的两端,在装配底层组件1时,其中第一环底层组件1通过龙门吊进行装配,通过龙门吊将底部构件11固定在基坑底面,之后将两个底角构件12分别固定在底部构件11的两端,以完成第一环底层组件1的装配。
由此,在进行底层组件1装配时,第一环通过龙门吊装配,保证了一开始装配时的精度。
优选地,底层组件1的装配还包括:利用底层拼装机4装配其余环底层组件1,并利用所述底层拼装机4对每一环进行纵向压紧,保证底层组件1底部的稳固性。
应当理解的是,纵向压紧是指向垂直于地面方向压紧,通过底层拼装机4对每一环向垂直于地面方向进行压紧,保证了装配后的稳定性。
在本实施例中,利用底层拼装机4装配其余环底层组件1包括:利用底层拼装机4将底部构件11固定在基坑底面,并将两个底角构件12分别固定在底部构件11的两端。
结合图3所示,具体地,底层组件1包括底部构件11和两个底角构件12,底层拼装机4需要将底部构件11固定在基坑的底面,接着将两个底角构件12安装至底部构件11的两端,以此完成一环底层组件1的装配,重复将底部构件11与两个底角构件12进行装配,直至完成所有底层组件1的装配。
在本实施例中,该地铁车站施工方法还包括:每完成一个预定环数的所述底层组件1的装配时,对所述底层组件1的肥槽进行回填,每完成一个预定环数的所述中层组件2的装配时,对所述中层组件2的肥槽进行回填,每完成一个预定环数的所述顶层组件3的装配时,对所述顶层组件3的肥槽进行回填。
在一个具体实施方式中,当底层组件1完成第一个预定环数后,对第一个预定环数内的底层组件1的肥槽进行回填。当底层组件1完成第二个预定环数后,此时中层组件2完成第一个预定环数,对第二个预定环数内的底层组件1以及第一个预定环数内的中层组件2的肥槽进行回填。当底层组件1完成第三个预定环数后,此时中层组件2完成第二个预定环数,以及顶层组件3完成第一个预定环数,对第三个预定环数内的底层组件1、第二个预定环数内的中层组件2以及第一个预定环数内的顶层组件3的肥槽进行回填,保证施工过程中的结构强度。以此类推,直至对底层组件1、中层组件2以及顶层组件3的所有肥槽进行回填。
结合图2和图3所示,在本实施例中,中层组件2包括中板构件21和两个侧板构件22,两个侧板构件22的底端分别与两个底角构件12的顶端固定连接,中板构件21的两端分别与两个侧板构件22固定连接;底层组件1装配至预定环数后,此时开始利用中层拼装机5将两个侧板构件22分别固定在底层组件1的两个底角构件12上,将中板构件21固定在两个侧板构件22之间,以此完成在底层组件1上装配中层组件2。
结合图3所示,优选地,顶层组件3包括两个顶角构件32和顶板构件31,两个顶角构件32的一端分别与两个侧板构件22的顶端固定连接,顶板构件31的两端分别与两个侧板构件22的另一端固定连接,当中层组件2装配至预定环数后,此时开始利用顶层拼装机6将两个顶角构件32分别固定在中层组件2的两个侧板构件22的顶端,同时将顶板构件31固定在两个顶角构件32之间,以此完成中层组件2与顶层组件3之间的装配。
作为一个优选地实施方式,在底层组件1、中层组件2和顶层组件3装配之前铺设轨道,通过在各个所述轨道上设置对应的拼装机分别对所述底层组件1、所述中层组件2和所述顶层组件3进行装配。
具体地,在通过龙门吊完成第一环底层组件1的装配后,先在基坑底部铺设基层轨道,之后利用龙门吊将底层拼装机4放置在基层轨道上,通过底层拼装机4在基层轨道上移动,实现对多环底层组件1的持续装配。
需要说明的是,基层轨道一开始就已在基坑底部全部铺设完成,龙门吊将底层拼装机4放置在基层轨道上就可以持续对底层组件1进行装配,底层轨道和中层轨道随着组件完成预定环数的次数而相应增加铺设。
结合图2所示,具体地,当底层组件1装配至预定环数后,开始在第一次完成预定环数内的底层组件1上铺设底层轨道,通过龙门吊将中层拼装机5放置在底层轨道上,通过中层拼装机5在底层轨道上移动,从而在已完成第一次预定环数的底层组件1上进行相应的第一次预定环数的中层组件2的装配,此时底层拼装机4和中层拼装机5同时工作,当中层组件2完成第一次预定环数的装配后,此时的底层组件1已经完成第二次预定环数的装配。
当中层组件2完成第一次预定环数的装配,底层组件1完成第二次预定环数的装配后,在完成第一次预定环数的中层组件2上进行第一段中层轨道 的铺设,同时在完成第二次预定环数的底层组件1上进行第二段底层轨道的铺设,第一段中层轨道和第二段底层轨道铺设完成后,通过龙门吊将顶层拼装机6放置在第一段中层轨道上,此时同时开启底层拼装机4、中层拼装机5和顶层拼装机6,分别对底层组件1、中层组件2和顶层组件3下一个预定环数进行装配。应当理解的是,此时的下一个预定环数的装配是指,底层组件1完成第三个预定环数的装配、中层组件2完成第二个预定环数的装配以及顶层组件3完成第一个预定环数的装配。当再次进行下一个预定环数的装配时,需要再次在第三个预定环数的底层组件1上铺设第三段的底层轨道和在第二个预定环数的中层组件2上铺设第二段的中层轨道,之后再次同时启动底层拼装机4、中层拼装机5和顶层拼装机6同时进行装配,从而呈阶梯式完成底层组件1的第四个预定环数、中层组件2第三个预定环数以及顶层组件3第二个预定环数的装配。以此类推,完成全部底层组件1、中层组件2和顶层组件3的装配。
下面通过一个具体的实施例对本发明进行详细说明。
示例性地,装配式地铁车站施工方法包括如下步骤:
开挖基坑。
在基层铺设轨道,用龙门吊将底层组件1的第一环进行装配,底角构件12与底部构件11横向固定。应当理解的是,横向是指底角构件12与底部构件11的装配方向。
在基坑底部铺设基层轨道,用龙门吊将底层拼装机4放在基层轨道上。
通过底层拼装机4对底层组件1进行装配并用底层拼装机4对每一环进行纵向压紧,当完成第一个流水段后,对已完成流水段的底层组件1的底层肥槽进行回填。需要说明的是,流水段是指分多段完成时其中一段中所包括的环数,可以根据实际需求选择一个流水段内的环数。
当回填强度达到要求以后,拆除第一流水段底层范围内的第二钢支撑8。
拆除完成后在第一流水段内的底层组件1上铺设底层轨道,用龙门吊将中层拼装机5安装在底层轨道上,对中板构件21及侧板构件22进行装配,以完成底层组件1与中层组件2之间的装配。
此时中层拼装机5与底层拼装机4同时进行装配作业,当中层组件2 完成第一个流水段装配后,此时底层组件1已完成第二个流水段装配,对底层组件1第二流水段内的底层肥槽及中层组件2第一流水段内的中层肥槽进行回填。
当回填强度达到要求以后,拆除底层组件1第二流水段内的第二钢支撑8,同时拆除中层组件2第一流水段内的第一钢支撑7。应当理解的是,第一钢支撑7和第二钢支撑8随着底层组件1和中层组件2依次完成的流水段而相应依次拆除,保证基坑的结构强度,防止坍塌。
拆除钢支撑以后,再次在第二个流水段内的底层组件1铺设底层轨道以及第一个流水段内的中层组件2铺设中层轨道,铺设完成后,用龙门吊将顶层拼装机6安装在中层轨道上,用顶层拼装机6对顶板构件31和顶角构件32进行装配,以在第一个流水段内中层组件2上进行顶层组件3的装配。
此时底层拼装机4、中层拼装机5和顶层拼装机6分别呈阶梯式同时进行装配,即当顶层组件3完成第一个流水段装配时,中层组件2已完成第二个流水段的装配,底层组件1已完成第三个流水段的装配。
重复上述步骤,直至整个地铁车站完成装配。
在本说明书的描述中,参考术语“实施例”、“一个实施例”和“一个实施方式”等的描述意指结合该实施例或实施方式描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或实施方式中。在本说明书中,对上述术语的示意性表述不一定指的是相同的实施例或实施方式。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或实施方式以合适的方式结合。
最后应说明的是,以上各实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。

Claims (10)

  1. 一种装配式地铁车站施工方法,其特征在于,装配式地铁车站包括底层组件(1)、中层组件(2)和顶层组件(3),所述底层组件(1)通过所述中层组件(2)与所述顶层组件(3)连接;所述装配式地铁车站施工方法包括:
    开挖基坑;
    装配所述底层组件(1),当完成预定环数的所述底层组件(1)的装配时,开始在所述底层组件(1)上进行所述中层组件(2)的装配;
    当完成预定环数的所述中层组件(2)的装配时,开始在所述中层组件(2)上进行所述顶层组件(3)的装配,此时所述底层组件(1)、所述中层组件(2)和所述顶层组件(3)呈阶梯式设置且同时进行装配。
  2. 根据权利要求1所述的装配式地铁车站施工方法,其特征在于,所述底层组件(1)包括底部构件(11)和两个底角构件(12),两个所述底角构件(12)分别设置在所述底部构件(11)的两端;所述底层组件(1)的装配包括:
    利用龙门吊将所述底部构件(11)固定在所述基坑底面,将两个所述底角构件(12)分别固定在所述底部构件(11)的两端,以对第一环所述底层组件(1)进行装配。
  3. 根据权利要求2所述的装配式地铁车站施工方法,其特征在于,所述底层组件(1)的装配还包括:
    在第一环所述底层组件(1)装配后,利用底层拼装机(4)装配其余环所述底层组件(1),并利用所述底层拼装机(4)对每一环进行纵向压紧。
  4. 根据权利要求3所述的装配式地铁车站施工方法,其特征在于,所述利用底层拼装机(4)装配其余环所述底层组件(1)包括:
    利用所述底层拼装机(4)将所述底部构件(11)固定在所述基坑底面,并将两个所述底角构件(12)分别固定在所述底部构件(11)的两端。
  5. 根据权利要求1所述的装配式地铁车站施工方法,其特征在于,还包括:
    每完成预定环数的所述底层组件(1)的装配时,对所述底层组件(1)的肥槽进行回填,每完成预定环数的所述中层组件(2)的装配时,对所述中层组件(2)的肥槽进行回填,每完成预定环数的所述顶层组件(3)的装配时,对所 述顶层组件(3)的肥槽进行回填。
  6. 根据权利要求2所述的装配式地铁车站施工方法,其特征在于,所述中层组件(2)包括中板构件(21)和两个侧板构件(22),两个所述侧板构件(22)的底端分别与两个所述底角构件(12)的顶端固定连接,所述中板构件(21)的两端分别与两个所述侧板构件(22)固定连接;所述中层组件(2)的装配包括:
    利用中层拼装机(5)将两个所述侧板构件(22)分别固定在两个所述底角构件(12)上,并将所述中板构件(21)固定在两个所述侧板构件(22)之间。
  7. 根据权利要求6所述的装配式地铁车站施工方法,其特征在于,所述顶层组件(3)包括两个顶角构件(32)和顶板构件(31),两个所述顶角构件(32)的一端分别与两个所述侧板构件(22)的顶端固定连接,所述顶板构件(31)的两端分别与两个所述侧板构件(22)的另一端固定连接;所述顶层组件(3)的装配包括:
    利用顶层拼装机(6)将两个所述顶角构件(32)分别固定在两个所述侧板构件(22)的顶端,并将所述顶板构件(31)固定在两个所述顶角构件(32)之间。
  8. 根据权利要求1所述的装配式地铁车站施工方法,其特征在于,所述底层组件(1)的装配包括:
    在所述基坑底部铺设基层轨道,利用龙门吊将底层拼装机(4)放置在所述基层轨道上,通过所述底层拼装机(4)装配所述底层组件(1)。
  9. 根据权利要求8所述的装配式地铁车站施工方法,其特征在于,所述中层组件(2)的装配包括:
    当所述底层组件(1)装配至预定环数后,开始在已装配完成的所述底层组件(1)上铺设底层轨道,利用所述龙门吊将中层拼装机(5)放置在所述底层轨道上,通过所述中层拼装机(5)装配所述中层组件(2)。
  10. 根据权利要求9所述的装配式地铁车站施工方法,其特征在于,所述顶层组件(3)的装配包括:
    当所述中层组件(2)装配至预定环数后,开始在已装配完成的所述中层组件(2)上铺设中层轨道,利用所述龙门吊将顶层拼装机(6)放置在所述中层轨道上,通过所述顶层拼装机(6)装配所述顶层组件(3)。
PCT/CN2021/123000 2021-08-11 2021-10-11 装配式地铁车站施工方法 WO2023015711A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110920255.X 2021-08-11
CN202110920255.XA CN113622461A (zh) 2021-08-11 2021-08-11 一种装配式地铁车站施工方法

Publications (1)

Publication Number Publication Date
WO2023015711A1 true WO2023015711A1 (zh) 2023-02-16

Family

ID=78384591

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/123000 WO2023015711A1 (zh) 2021-08-11 2021-10-11 装配式地铁车站施工方法

Country Status (2)

Country Link
CN (1) CN113622461A (zh)
WO (1) WO2023015711A1 (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115110575A (zh) * 2022-06-13 2022-09-27 中电建南方建设投资有限公司 一种用于装配式车站构件拼装方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003213706A (ja) * 2002-01-16 2003-07-30 Tekken Constr Co Ltd 鉄道線路敷地上空に構築される構造物のための下部工及びその構築方法
CN111733875A (zh) * 2020-06-10 2020-10-02 广州地铁设计研究院股份有限公司 装配式地铁车站中层组件的拼装设备
CN111733874A (zh) * 2020-06-10 2020-10-02 广州地铁设计研究院股份有限公司 装配式地铁车站顶层组件的拼装设备
CN111827347A (zh) * 2020-06-10 2020-10-27 广州地铁设计研究院股份有限公司 装配式地铁车站底层组件的拼装设备
CN112281918A (zh) * 2020-11-13 2021-01-29 广州地铁设计研究院股份有限公司 一种装配式地铁车站及其施工方法
CN112502186A (zh) * 2020-11-04 2021-03-16 中国铁路设计集团有限公司 建筑空间结构一体化的装配式地铁车站结构

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107130629B (zh) * 2017-05-03 2019-05-17 中铁十六局集团地铁工程有限公司 一种采用锚索和钢支撑围护结构的装配式车站施工方法
CN111794273A (zh) * 2020-06-10 2020-10-20 广州地铁设计研究院股份有限公司 装配式地铁车站
CN111733873A (zh) * 2020-06-10 2020-10-02 广州地铁设计研究院股份有限公司 装配式地铁车站的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003213706A (ja) * 2002-01-16 2003-07-30 Tekken Constr Co Ltd 鉄道線路敷地上空に構築される構造物のための下部工及びその構築方法
CN111733875A (zh) * 2020-06-10 2020-10-02 广州地铁设计研究院股份有限公司 装配式地铁车站中层组件的拼装设备
CN111733874A (zh) * 2020-06-10 2020-10-02 广州地铁设计研究院股份有限公司 装配式地铁车站顶层组件的拼装设备
CN111827347A (zh) * 2020-06-10 2020-10-27 广州地铁设计研究院股份有限公司 装配式地铁车站底层组件的拼装设备
CN112502186A (zh) * 2020-11-04 2021-03-16 中国铁路设计集团有限公司 建筑空间结构一体化的装配式地铁车站结构
CN112281918A (zh) * 2020-11-13 2021-01-29 广州地铁设计研究院股份有限公司 一种装配式地铁车站及其施工方法

Also Published As

Publication number Publication date
CN113622461A (zh) 2021-11-09

Similar Documents

Publication Publication Date Title
WO2023015711A1 (zh) 装配式地铁车站施工方法
CN105839667A (zh) 全预制叠合装配式地下综合管廊的施工制作工艺
CN105952474A (zh) 一种大断面隧道约束混凝土初期支护快速施工方法
CN102587363A (zh) 自升式钻井平台桁架式桩腿的合拢方法
CN207420596U (zh) 隧道用拱架预拼装台车
CN110080289A (zh) 一种装配式平顶大跨无柱地下结构的明挖施工方法
CN106760940A (zh) 一种预制复合纤维水泥空心围墙构件及施工方法
CN105672638A (zh) 一种带支撑滑移的脚手架及网架安装方法
CN202733214U (zh) Pe缠绕结构壁管
CN208685450U (zh) 钢桁架桥拼装支架体系
CN208415303U (zh) 一种用于支撑连接混凝土浇筑钢筋笼与模板的支模件
CN108518008B (zh) 柔性拉索结构上的刚性屋盖结构及其安装方法
CN206693470U (zh) 一种现浇次梁t形楼板
CN106245765A (zh) 注浆连接钢管装置结构及连接方法
CN207017653U (zh) 一种箱型卸载专用支墩及其卸载结构
CN206418775U (zh) 一种臂架及混凝土湿喷机
CN109339105A (zh) 一种方拱形管廊安装支座及管廊系统和管廊系统安装方法
CN204676560U (zh) 基坑中隔墙的换撑结构
CN208455660U (zh) 一种填土边坡装配式挡土墙
CN209555972U (zh) 一种方拱形管廊安装支座及管廊系统
CN205088653U (zh) 压力钢管拖运安装组合轨道
CN206554613U (zh) 一种预制复合纤维水泥空心围墙构件
CN110258359A (zh) 通过吊推支架施工的变高度钢梁施工方法
CN217517654U (zh) 一种预制骑马井
CN213329123U (zh) 基坑逆作法施工时预埋于复合墙内的钢构件

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21953317

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE