WO2022160713A1 - Method for constructing novel starter dam suitable for upstream tailings pond - Google Patents

Method for constructing novel starter dam suitable for upstream tailings pond Download PDF

Info

Publication number
WO2022160713A1
WO2022160713A1 PCT/CN2021/116002 CN2021116002W WO2022160713A1 WO 2022160713 A1 WO2022160713 A1 WO 2022160713A1 CN 2021116002 W CN2021116002 W CN 2021116002W WO 2022160713 A1 WO2022160713 A1 WO 2022160713A1
Authority
WO
WIPO (PCT)
Prior art keywords
dam
layer
seepage
initial
initial dam
Prior art date
Application number
PCT/CN2021/116002
Other languages
French (fr)
Chinese (zh)
Inventor
许传华
段蔚平
毛志远
邱宇
杨强胜
田伟虎
倪强
藕明江
翁金红
吴光富
曹金海
鲁立胜
汪明海
林启祥
Original Assignee
中钢集团马鞍山矿山研究总院股份有限公司
华唯金属矿产资源高效循环利用国家工程研究中心有限公司
中钢集团马鞍山矿院工程勘察设计有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中钢集团马鞍山矿山研究总院股份有限公司, 华唯金属矿产资源高效循环利用国家工程研究中心有限公司, 中钢集团马鞍山矿院工程勘察设计有限公司 filed Critical 中钢集团马鞍山矿山研究总院股份有限公司
Publication of WO2022160713A1 publication Critical patent/WO2022160713A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • E03F3/046Open sewage channels

Definitions

  • the invention relates to a tailings discharge and stockpiling facility, in particular to an initial dam of a tailings pond, which is especially suitable for the upstream of the proposed tailings pond where there is a lack of stone resources, it is difficult to build a permeable rockfill dam and the traffic is inconvenient
  • the application in the construction of tailings pond can effectively reduce the wetting line of the dam body.
  • the initial dam was built with materials other than tailings, and its main function was to lay the foundation for the subsequent tailings accumulation dam, also known as the foundation dam. According to whether the drainage can be divided into two types: impervious dam and permeable dam.
  • the initial dam type is usually a permeable rockfill dam.
  • a permeable dam is a dam type that conducts organized drainage in the dam body and allows organized and planned water seepage. Its drainage system differs from the drainage system of an impervious dam in function and role. There is also a drainage system in the impermeable dam, the purpose of which is to discharge the seepage water in the anti-seepage body in an organized manner, protect the anti-seepage body and the initial dam, and prevent seepage deformation.
  • the drainage system of the permeable dam is to remove the seepage water through the dam body in an organized manner, and its main function is to control the position of the infiltration line in the accumulation dam.
  • the main dam type of the permeable dam is to add a reverse filter on the upstream slope of various rockfill dams, or to add drainage facilities in the impervious dam to reduce the infiltration line of the tailings accumulation dam.
  • the permeable dam is the most basic dam type in the initial dam, and it is also an ideal dam type.
  • the dam type selection of the initial dam should be based on the specific conditions of the body, and implement the principles of adapting measures to local conditions, using local materials, and designing according to materials.
  • Earth-rock dams have the lowest requirements on topographic and geological conditions and the strongest adaptability. If the local stone is not enough to build a permeable rockfill dam, drainage facilities can be added on the basis of the homogeneous dam to achieve permeation.
  • the invention innovates a design method to make the earth dam meet the requirements of the permeable dam, and design the drainage facilities inside the initial earth dam to make the earth dam meet the requirements of the permeable dam.
  • a kind of construction method of the novel initial stage dam suitable for the upstream tailings pond of the present invention adopts the following technical scheme to realize:
  • the present invention is a construction method of a new type of initial dam suitable for an upstream tailings pond.
  • a shoulder intercepting ditch is arranged on the mountain bodies on both sides of the initial dam, and a dam toe drainage ditch is arranged at the dam foot of the initial dam.
  • the outlet end of the ditch is connected to the drainage ditch at the foot of the dam, and the following technical solutions are adopted:
  • the foundation of the initial dam is cleaned, and after the foundation is cleaned, the fine-grained soil layer, the composite geomembrane, the coarse sand layer, the rock layer and the sand and pebble layer are laid from bottom to top to form the anti-seepage layer at the bottom of the initial dam body;
  • the mass proportion of the 0-0.1mm grain size is ⁇ 95%
  • the 2-13mm grain size in the coarse sand layer is ⁇ 95%
  • the 76-200mm grain size in the boulder layer is ⁇ 95%.
  • the mass proportion of the 13-76mm grain size in the sand and pebble layer is ⁇ 95%; among which: the thickness of the fine-grained soil layer is 0.17-0.23m, the thickness of the coarse sand layer is 0.18-0.24m, and the thickness of the rock layer is 1.3 ⁇ 1.8m, the thickness of the sand and pebble layer is 0.18 ⁇ 0.25m.
  • the initial dam drainage cushion is laid on the seepage layer, and the upstream seepage drainage prism of the initial dam and the downstream seepage prism of the initial dam are connected with the initial dam drainage cushion;
  • the stones used to build the seepage drainage prism must be good permeable materials , the content of the stone particle size less than 2mm should not be greater than 5%, the maximum diameter of the stone should not exceed 0.5m, the stone should be fresh, hard, weathering and abrasion resistant, no weathered stone should be used, wet compressive strength ⁇ 40Mpa, softening coefficient ⁇ 0.80;
  • the drainage prism and the drainage mattress are wrapped with double-layer geotextiles.
  • a vertical seepage drainage blind ditch pipe is pre-buried on the initial dam seepage drainage mattress in the initial dam, and the lower end of the vertical seepage drainage blind ditch pipe is communicated with the initial dam seepage drainage mattress; the vertical seepage drainage blind ditch pipe
  • the ditch pipes are made of plastic blind ditch pipes and wrapped with geotextiles, and the vertical seepage drainage blind ditch pipes are symmetrically arranged in the initial dam.
  • the upper water inlet of the oblique drainage blind ditch is connected with the horizontal drainage blind ditch
  • the lower water outlet of the ditch is connected to the initial dam drainage pad;
  • the blind ditch is to wrap the rubble with double-layer geotextile, and the rubble should be dense and have good water permeability.
  • the purpose is to increase the contact area between the initial dam and the mountain.
  • the drainage capacity of the dam further reduces the infiltration line of the dam body.
  • the initial dam In the space formed by the upstream seepage drainage prism of the initial dam, the downstream seepage prism of the initial dam and the mountains on both sides of the initial dam, the initial dam is stacked layer by layer from bottom to top, and compacted in layers. After the initial dam upstream seepage drainage prism height, follow the steps below:
  • Step 1 Use cohesive soil to build and compact the first layer of the initial dam, and construct an anti-seepage slope protection layer on the upstream slope of the first layer of the initial dam;
  • Step 2 Use cohesive soil to build and compact the second layer of the initial dam on the first layer of the initial dam, and construct an anti-seepage protection slope on the upstream slope of the second layer of the initial dam;
  • Part 3 Build and compact the third layer of the initial dam with cohesive soil above the second layer of the initial dam, and construct an anti-seepage protection slope on the upstream slope of the third layer of the initial dam;
  • Steps 4 to n By analogy, until the stacking reaches the design height.
  • a geomembrane is laid on the top surface of the initial dam, and a protective layer of crushed stone and dry block stone is laid on the geomembrane.
  • the ratio of long and short sides is not more than 4, the content of less than 20mm is less than 5%, and there is an appropriate gradation.
  • the anti-seepage slope protection layers are respectively a sand pebble layer, a block stone layer, a sand pebble layer, a coarse sand layer, a composite geomembrane, and a coarse sand layer from the inside to the outside;
  • the composite geomembrane is the middle of the two layers of geotextiles.
  • the mass ratio of ⁇ 13mm grain size is ⁇ 95%; in the anti-seepage protection layer, the thickness of the coarse sand layer is 0.18-0.24m, the thickness of the boulder layer is 1.3-1.8m, and the thickness of the sand and pebble layer is 0.18-0.25m .
  • the stacking height of each layer from bottom to top is 2.2-2.8m, and the thickness of layered compaction is not more than 0.8m.
  • the number of samples and the technical requirements for porosity determination shall be implemented in accordance with the requirements of the specification, and the porosity of the dam body after compaction shall not be greater than 22%.
  • the precautions and technical requirements for cohesive soil piling must follow the "Technical Specifications for Roller Compacted Earth-rock Dam Construction" DL/5129-2001 and GBJ201-83 "Code for Construction and Acceptance of Earthwork and Blasting Engineering", so that the filling quality can achieve the expected purpose .
  • the present invention adopts the Bishop method to analyze the stability of the tailings dam; uses the finite element method to analyze the seepage field of the tailings dam, calculates the node water head, and uses the computer to output the water level line.
  • a construction method of a novel initial dam suitable for an upstream tailings pond of the present invention has the following effects:
  • the seepage drainage facility main body composed of the upstream and downstream seepage drainage prisms and the seepage drainage mattress can realize the seepage drainage of the cohesive soil initial dam;
  • the infiltration line of the dam body can be further reduced when the infiltration line in the initial dam is relatively high through the pre-buried vertical seepage drainage blind trench pipe in the initial dam;
  • Fig. 1 is a kind of new-type initial stage dam system cross-sectional structural schematic diagram suitable for upstream type tailings pond constructed by the method of the present invention
  • FIG. 2 is a schematic diagram of the longitudinal section structure of a new type of initial dam system suitable for upstream tailings ponds constructed by the method of the present invention.
  • the reference signs are: 1 - upstream seepage drainage prism of the initial dam; 1' - seepage drainage prism downstream of the initial dam; 2 - initial dam seepage drainage cushion; 3 - vertical seepage drainage blind ditch pipe; 4 - dam foot drainage ditch; 5- anti-seepage slope protection layer; 6- late tailings sub-dam; 7- oblique drainage blind ditch; 8- lateral drainage blind ditch; 9- anti-seepage layer at the bottom of the initial dam body.
  • FIG. 1 The cross-sectional structural schematic diagram of a new type of initial dam system suitable for upstream tailings ponds constructed by the method of the present invention shown in FIG. 1 and combined with FIG.
  • the construction method of the dam is to set the dam abutment intercepting ditch on the mountains on both sides of the initial dam, and set the dam toe drainage ditch 4 at the dam toe of the initial dam, and the outlet end of the shoulder intercepting ditch is communicated with the dam toe drainage ditch 4, And adopt the following technical solutions:
  • the foundation of the initial dam is cleaned, and after the cleaning is completed, the fine-grained soil layer, the composite geomembrane, the coarse sand layer, the rock layer, and the sand and pebble layer are laid from bottom to top to form the anti-seepage layer 9 at the bottom of the initial dam body;
  • the mass proportion of 0-0.1mm grain size is ⁇ 95%
  • the mass proportion of 2-13mm grain size is ⁇ 95%
  • the mass proportion of 76-200mm grain size in the boulder layer is ⁇ 95%.
  • the mass proportion of the 13-76mm grain size is ⁇ 95%; the thickness of the fine-grained soil layer is 0.2m, the thickness of the coarse sand layer is 0.2m, the thickness of the boulder layer is 1.5m, and the thickness of the sand and pebble layer is 0.2m.
  • the initial dam is built layer by layer from bottom to top, and the layers are compacted. After compaction to the height of the seepage-draining prism 1 upstream of the initial dam, follow the steps below:
  • Step 1 Use cohesive soil to build and compact the first layer of the initial dam, and construct the anti-seepage slope protection layer 5 on the upstream slope of the first layer of the initial dam;
  • Step 2 Use cohesive soil to build and compact the second layer of the initial dam on the first layer of the initial dam, and construct the anti-seepage protection slope layer 5 on the upstream slope of the second layer of the initial dam;
  • Part 3 Build and compact the third layer of the initial dam with cohesive soil above the second layer of the initial dam, and construct an anti-seepage protection slope layer 5 on the upstream slope of the third layer of the initial dam;
  • Steps 4 to n By analogy, until the stacking reaches the design height.
  • the anti-seepage slope protection layer 5 is, from the inside to the outside, a sand and pebble layer, a block stone layer, a sand and pebble layer, a coarse sand layer, a composite geomembrane, and a coarse sand layer. %, the mass proportion of 76-200mm grain size in the boulder layer is ⁇ 95%, and the mass proportion of 2-13mm grain size in the coarse sand layer is ⁇ 95%; in the anti-seepage slope protection layer 5, the thickness of the coarse sand layer is 0.2m , the thickness of the block stone layer is 1.5m, and the thickness of the sand pebble layer is 0.2m.
  • the composite geomembrane used in the present invention is a layer of geomembrane sandwiched between two layers of geotextiles, and the specifications of the geotextiles are 300-600 g/m 2 ; wherein: the composite geomembrane in step 1) adopts 300 g/m 2 geotextiles. 5) The composite geomembrane adopts 600g/m 2 non-woven geotextile, and the geomembrane adopts HDPE membrane.
  • step 5 the stacking height of each layer from bottom to top is 2.5m, and the thickness of layered compaction does not exceed 0.8m.
  • a geomembrane is laid on the top surface of the initial dam, and a protective layer of crushed stone and dry block stone is laid on the geomembrane.
  • the construction sequence of the sub-dam 6 is as follows:
  • the base layer is first leveled, and the fine-grained soil layer, composite geomembrane, and coarse tailings protective layer are constructed from bottom to top on the base layer to form the first-level sub-dam; after the construction of the first-level sub-dam is completed, the tailings are discharged After reaching this level, the second-level sub-dam will be built backward; the construction sequence of the second-level sub-dam is also leveling the base layer ⁇ fine-grained soil layer ⁇ composite geomembrane ⁇ coarse tailings protective layer, and so on.
  • the mass proportion of the 0-0.1mm grain size is ⁇ 95%
  • the mass proportion of the 2-13mm grain size is ⁇ 95%
  • the thickness of the fine-grained soil layer is 0.2m
  • the old tailings pond was excavated and transported, with a thickness of 0.2m
  • the composite geomembrane is a layer of geomembrane sandwiched between two layers of geotextiles.
  • the invention adopts the Bishop method to analyze the stability of the tailings dam; uses the finite element method to analyze the seepage field of the tailings dam, calculates the node water head, and uses the computer to output the water level line.

Abstract

Disclosed is a method for constructing a novel starter dam suitable for an upstream tailings pond, comprising: laying a starter dam body bottom anti-seepage layer; providing a starter dam upstream seepage drainage prism body (1) and a starter dam downstream seepage drainage prism body (1,) respectively on the upstream and downstream of the starter dam, and laying a starter dam seepage drainage mattress (2) on the starter dam body bottom anti-seepage layer, lower ends of vertical seepage drainage blind ditch pipe (3) being in communication with the starter dam seepage drainage mattress (2); pre-embedding inclined drainage blind ditches at positions where the starter dam contacts mountain bodies, and pre-embedding transverse blind ditches at positions where the starter dam contacts the mountain bodies; and building the starter dam layer by layer from bottom to top, and compacting same in a layered manner, and constructing an anti-seepage protective slope layer (5) on an upstream slope surface of the starter dam. The present invention has advantages of low construction cost, small amount of stones used, and good water-permeable effect. By designing a drainage facility inside a starter earth dam, the earth dam meets the requirement of a water-permeable dam.

Description

一种适于上游式尾矿库的新型初期坝的建设方法A new type of initial dam construction method suitable for upstream tailings pond 技术领域technical field
本发明涉及一种尾矿排放、堆存设施,具体涉及一种尾矿库的初期坝,尤其适合在拟建尾矿库所在地石料资源缺乏、难以建设透水堆石坝且交通不便情况下的上游式尾矿库建设中应用,可以有效降低坝体浸润线。The invention relates to a tailings discharge and stockpiling facility, in particular to an initial dam of a tailings pond, which is especially suitable for the upstream of the proposed tailings pond where there is a lack of stone resources, it is difficult to build a permeable rockfill dam and the traffic is inconvenient The application in the construction of tailings pond can effectively reduce the wetting line of the dam body.
背景技术Background technique
初期坝是用非尾矿的材料筑成,其主要作用是为以后的尾矿堆积坝打基础,也称基础坝。按是否排水可以分为不透水坝和透水坝两种类型。The initial dam was built with materials other than tailings, and its main function was to lay the foundation for the subsequent tailings accumulation dam, also known as the foundation dam. According to whether the drainage can be divided into two types: impervious dam and permeable dam.
上游式尾矿库运行过程中,考虑到尾矿库运行初期和后期渗透稳定,初期坝坝型通常采用透水堆石坝。透水坝是一种在坝体内进行有组织地排水,允许有组织、有计划地渗水的坝型。它的排水系统和不透水坝的排水系统的功能和作用不同。在不透水坝内也有排水系统,其目的是将防渗体中的渗漏水有组织地排出,保护防渗体和初期坝,防止发生渗透变形。透水坝的排水系统是将通过坝体的渗漏水有组织地排除,其主要作用是控制堆积坝内浸润线位置。透水坝的主要坝型是各种堆石坝的上游坡加设反滤体,也可以用不透水坝内加设排水设施,使其能降低尾矿堆积坝的浸润线。透水坝是初期坝中最基本的坝型,也是理想的一种坝型。During the operation of the upstream tailings pond, considering the stability of infiltration in the initial and later stages of the operation of the tailings pond, the initial dam type is usually a permeable rockfill dam. A permeable dam is a dam type that conducts organized drainage in the dam body and allows organized and planned water seepage. Its drainage system differs from the drainage system of an impervious dam in function and role. There is also a drainage system in the impermeable dam, the purpose of which is to discharge the seepage water in the anti-seepage body in an organized manner, protect the anti-seepage body and the initial dam, and prevent seepage deformation. The drainage system of the permeable dam is to remove the seepage water through the dam body in an organized manner, and its main function is to control the position of the infiltration line in the accumulation dam. The main dam type of the permeable dam is to add a reverse filter on the upstream slope of various rockfill dams, or to add drainage facilities in the impervious dam to reduce the infiltration line of the tailings accumulation dam. The permeable dam is the most basic dam type in the initial dam, and it is also an ideal dam type.
初期坝的坝型选择应该根据当体具体条件,贯彻因地制宜,就地取材,因材设计的原则。土石坝对地形地质条件要求最低,适应性最强。若当地石料不足以筑建透水堆石坝时,则可以在均质坝的基础上增加排水设施来实现透水。The dam type selection of the initial dam should be based on the specific conditions of the body, and implement the principles of adapting measures to local conditions, using local materials, and designing according to materials. Earth-rock dams have the lowest requirements on topographic and geological conditions and the strongest adaptability. If the local stone is not enough to build a permeable rockfill dam, drainage facilities can be added on the basis of the homogeneous dam to achieve permeation.
中文期刊《科技风》2020年2月发表的“上游式尾矿库一种新的初期坝型式的渗流计算分析”的一文中,提出一种新的初期坝型, 在常规堆石坝的上游侧分区填筑一部分土石混合料(约1/4初期坝高),既减少尾矿库运行初期的尾矿“跑浑”,又能保证堆积坝渗透稳定。但该初期坝属于透水坝,建设中需要大量石块资源,建设成本高;而且,在常规堆石坝的上游侧分区填筑一部分土石混合料后,透水性能大大降低。In the article "Seepage Calculation Analysis of a New Initial Dam Type for Upstream Tailings Ponds" published in the Chinese journal "Science and Technology Wind" in February 2020, a new initial dam type was proposed, which is upstream of conventional rockfill dams. Filling a part of earth-rock mixture in the side zone (about 1/4 of the initial dam height) can not only reduce the tailings "running muddy" in the early stage of operation of the tailings pond, but also ensure the stability of the seepage of the accumulation dam. However, the initial dam is a permeable dam, which requires a lot of rock resources and high construction cost. Moreover, after filling a part of the earth-rock mixture in the upstream side of the conventional rockfill dam, the water permeability is greatly reduced.
本发明根据尾矿库现场场地条件及筑坝材料特点,创新了一种使土坝达到透水坝要求的设计方法,通过在初期土坝内部设计排水设施使土坝达到透水坝的要求。According to the site conditions of the tailings pond and the characteristics of the dam-building materials, the invention innovates a design method to make the earth dam meet the requirements of the permeable dam, and design the drainage facilities inside the initial earth dam to make the earth dam meet the requirements of the permeable dam.
发明内容SUMMARY OF THE INVENTION
为了克服现有尾矿库透水坝建设中需要消耗大量的石料资源、建设成本高以及土石坝透水性能差的问题,而提供一种建设成本低、石料使用量小、透水效果好的适于上游式尾矿库的新型初期坝的建设方法,设计的初期土坝可以达到透水坝的透水要求,当场地石料不足以构建初期堆石坝并且运输石料成本较高时,使用本发明方法可以有效地降低成本,并且使初期土坝达到透水坝的使用要求。In order to overcome the problems of consuming a large amount of stone resources, high construction cost and poor water permeability of earth-rock dams in the construction of permeable dams in existing tailings ponds, a new method with low construction cost, small amount of stone materials and good water permeability is provided, which is suitable for upstream The new initial dam construction method of the type tailings pond, the designed initial earth dam can meet the water permeability requirements of the permeable dam, and when the site stone is not enough to build the initial rockfill dam and the cost of transporting the stone is high, the method of the invention can be used effectively. Reduce costs, and make the initial earth dam meet the use requirements of permeable dams.
为实现本发明的上述目的,本发明一种适于上游式尾矿库的新型初期坝的建设方法采用以下技术方案实现:In order to realize the above-mentioned purpose of the present invention, a kind of construction method of the novel initial stage dam suitable for the upstream tailings pond of the present invention adopts the following technical scheme to realize:
本发明一种适于上游式尾矿库的新型初期坝的建设方法,在初期坝两侧山体上设置坝肩截水沟,在初期坝的坝脚设置坝脚排水沟,所述的肩截水沟的出水端与坝脚排水沟连通,并采用以下技术方案:The present invention is a construction method of a new type of initial dam suitable for an upstream tailings pond. A shoulder intercepting ditch is arranged on the mountain bodies on both sides of the initial dam, and a dam toe drainage ditch is arranged at the dam foot of the initial dam. The outlet end of the ditch is connected to the drainage ditch at the foot of the dam, and the following technical solutions are adopted:
1)铺设初期坝体底部防渗层1) The anti-seepage layer at the bottom of the dam body at the initial stage of laying
对初期坝基底进行清基,清基结束后,自下而上分别铺设细粒土层、复合土工膜、粗砂层、块石层、砂卵石层共同构成初期坝体底部防渗层;The foundation of the initial dam is cleaned, and after the foundation is cleaned, the fine-grained soil layer, the composite geomembrane, the coarse sand layer, the rock layer and the sand and pebble layer are laid from bottom to top to form the anti-seepage layer at the bottom of the initial dam body;
所述细粒土层中0~0.1mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%,块石层中76~200mm粒级质量占比≥95%,砂卵石层中13~76mm粒级质量占比≥95%;其中:细粒土层的厚度为 0.17~0.23m,粗砂层的厚度为0.18~0.24m,块石层的厚度为1.3~1.8m,砂卵石层的厚度为0.18~0.25m。In the fine-grained soil layer, the mass proportion of the 0-0.1mm grain size is ≥95%, the 2-13mm grain size in the coarse sand layer is ≥95%, and the 76-200mm grain size in the boulder layer is ≥95%. %, the mass proportion of the 13-76mm grain size in the sand and pebble layer is ≥95%; among which: the thickness of the fine-grained soil layer is 0.17-0.23m, the thickness of the coarse sand layer is 0.18-0.24m, and the thickness of the rock layer is 1.3 ~1.8m, the thickness of the sand and pebble layer is 0.18~0.25m.
2)在初期坝上、下游分别设置初期坝上游排渗棱体、初期坝下游排渗棱体,在初期坝上游排渗棱体、初期坝下游排渗棱体之间的初期坝体底部防渗层上铺设初期坝排渗褥垫,初期坝上游排渗棱体、初期坝下游排渗棱体与初期坝排渗褥垫连通;堆筑排渗棱体的石料必须是很好的透水材料,石料粒度小于2mm的含量不得大于5%,石料最大直径不宜超过0.5m,石料要求新鲜、坚硬、耐风化、耐磨蚀,不得使用风化石,湿抗压强度≥40Mpa,软化系数≥0.80;排渗棱体和排渗褥垫均用双层土工布包裹。2) Set upstream seepage drainage prisms of the initial dam and downstream seepage prisms of the initial dam respectively on the upstream and downstream of the initial dam, and prevent the bottom of the initial dam body between the upstream seepage drainage prisms of the initial dam and the downstream seepage prisms of the initial dam. The initial dam drainage cushion is laid on the seepage layer, and the upstream seepage drainage prism of the initial dam and the downstream seepage prism of the initial dam are connected with the initial dam drainage cushion; the stones used to build the seepage drainage prism must be good permeable materials , the content of the stone particle size less than 2mm should not be greater than 5%, the maximum diameter of the stone should not exceed 0.5m, the stone should be fresh, hard, weathering and abrasion resistant, no weathered stone should be used, wet compressive strength ≥ 40Mpa, softening coefficient ≥ 0.80; The drainage prism and the drainage mattress are wrapped with double-layer geotextiles.
3)在初期坝内之初期坝排渗褥垫之上预埋竖向排渗盲沟管,竖向排渗盲沟管的下端与初期坝排渗褥垫连通;所述竖向排渗盲沟管采用塑料盲沟管,并用土工布包裹,竖向排渗盲沟管在初期坝内对称布置。3) A vertical seepage drainage blind ditch pipe is pre-buried on the initial dam seepage drainage mattress in the initial dam, and the lower end of the vertical seepage drainage blind ditch pipe is communicated with the initial dam seepage drainage mattress; the vertical seepage drainage blind ditch pipe The ditch pipes are made of plastic blind ditch pipes and wrapped with geotextiles, and the vertical seepage drainage blind ditch pipes are symmetrically arranged in the initial dam.
4)在初期坝与山体接触部位预埋斜向排水盲沟,在初期坝与山体接触部位预埋横向盲沟,斜向排水盲沟的上部进水口与横向排水盲沟连通,斜向排水盲沟的下部出水口与初期坝排渗褥垫连通;盲沟是用双层土工布包裹毛石,毛石体之间应该密实并具有良好的透水性,其目的是增加初期坝与山体接触部位的排水能力,进一步降低坝体浸润线。4) Pre-buried oblique drainage blind ditch at the contact part between the initial dam and the mountain, and pre-embedded the horizontal blind ditch in the initial contact part of the dam and the mountain. The upper water inlet of the oblique drainage blind ditch is connected with the horizontal drainage blind ditch The lower water outlet of the ditch is connected to the initial dam drainage pad; the blind ditch is to wrap the rubble with double-layer geotextile, and the rubble should be dense and have good water permeability. The purpose is to increase the contact area between the initial dam and the mountain. The drainage capacity of the dam further reduces the infiltration line of the dam body.
5)初期坝施工5) Initial dam construction
在初期坝上游排渗棱体、初期坝下游排渗棱体及初期坝两侧山体之间构成的空间内,自下而上逐层堆筑初期坝,并分层压实,当压实到初期坝上游排渗棱体高度后,按照以下步骤实施:In the space formed by the upstream seepage drainage prism of the initial dam, the downstream seepage prism of the initial dam and the mountains on both sides of the initial dam, the initial dam is stacked layer by layer from bottom to top, and compacted in layers. After the initial dam upstream seepage drainage prism height, follow the steps below:
第1步:采用粘性土堆筑、压实初期坝第一层,在初期坝第一层上游坡面上施工防渗护坡层;Step 1: Use cohesive soil to build and compact the first layer of the initial dam, and construct an anti-seepage slope protection layer on the upstream slope of the first layer of the initial dam;
第2步:在初期坝第一层之上采用粘性土堆筑、压实初期坝第 二层,在初期坝第二层上游坡面上施工防渗护坡层;Step 2: Use cohesive soil to build and compact the second layer of the initial dam on the first layer of the initial dam, and construct an anti-seepage protection slope on the upstream slope of the second layer of the initial dam;
第3部:在初期坝第二层之上采用粘性土堆筑、压实初期坝第三层,在初期坝第三层上游坡面上施工防渗护坡层;Part 3: Build and compact the third layer of the initial dam with cohesive soil above the second layer of the initial dam, and construct an anti-seepage protection slope on the upstream slope of the third layer of the initial dam;
第4~n步:以此类推,直至堆筑至设计高度。 Steps 4 to n: By analogy, until the stacking reaches the design height.
在初期坝的坝顶表面铺设土工膜,在土工膜上铺设碎石保护层、干砌块石块保护层。干砌石块规格,长短边之比不大于4,小于20mm的含量<5%,有适当的级配。A geomembrane is laid on the top surface of the initial dam, and a protective layer of crushed stone and dry block stone is laid on the geomembrane. For dry-laid stone specifications, the ratio of long and short sides is not more than 4, the content of less than 20mm is less than 5%, and there is an appropriate gradation.
进一步地,所述防渗护坡层自内向外分别是砂卵石层、块石层、砂卵石层、粗砂层、复合土工膜、粗砂层;所述的复合土工膜为两层土工布中间夹一层土工膜;在防渗护坡层中,砂卵石层中13~76mm粒级质量占比≥95%,块石层中76~200mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%;在防渗护坡层中,粗砂层的厚度为0.18~0.24m,块石层的厚度为1.3~1.8m,砂卵石层的厚度为0.18~0.25m。Further, the anti-seepage slope protection layers are respectively a sand pebble layer, a block stone layer, a sand pebble layer, a coarse sand layer, a composite geomembrane, and a coarse sand layer from the inside to the outside; the composite geomembrane is the middle of the two layers of geotextiles. Sandwich a layer of geomembrane; in the anti-seepage protection layer, the 13-76mm grain size in the sand and pebble layer accounts for ≥95% of the mass, the 76-200mm grain size in the cobblestone layer accounts for ≥95% of the mass, and 2 in the coarse sand layer. The mass ratio of ~13mm grain size is ≥95%; in the anti-seepage protection layer, the thickness of the coarse sand layer is 0.18-0.24m, the thickness of the boulder layer is 1.3-1.8m, and the thickness of the sand and pebble layer is 0.18-0.25m .
进一步地,在步骤5)中,自下而上每层堆筑的高度为2.2~2.8m,分层压实的厚度不超过0.8m,要求用振动压路机碾压后,每层取样测定孔隙率,取样的个数和孔隙率测定的技术要求按规范要求执行,要求压实后坝体的孔隙率不得大于22%。粘性土堆筑的注意事项及技术要求必须遵循《碾压式土石坝施工技术规范》DL/5129-2001和GBJ201-83《土方与爆破工程施工及验收规范》,使填筑质量达到预期的目的。Further, in step 5), the stacking height of each layer from bottom to top is 2.2-2.8m, and the thickness of layered compaction is not more than 0.8m. , the number of samples and the technical requirements for porosity determination shall be implemented in accordance with the requirements of the specification, and the porosity of the dam body after compaction shall not be greater than 22%. The precautions and technical requirements for cohesive soil piling must follow the "Technical Specifications for Roller Compacted Earth-rock Dam Construction" DL/5129-2001 and GBJ201-83 "Code for Construction and Acceptance of Earthwork and Blasting Engineering", so that the filling quality can achieve the expected purpose .
进一步地,本发明采用Bishop法对尾矿坝稳定性进行分析;用有限元法对尾矿坝渗流场进行分析,计算出结点水头,并用计算机输出水位线。Further, the present invention adopts the Bishop method to analyze the stability of the tailings dam; uses the finite element method to analyze the seepage field of the tailings dam, calculates the node water head, and uses the computer to output the water level line.
本发明一种适于上游式尾矿库的新型初期坝的建设方法采用以上技术方案后,具有以下效果:After adopting the above technical scheme, a construction method of a novel initial dam suitable for an upstream tailings pond of the present invention has the following effects:
(1)在场地现有石料不足以建成堆石坝并且运输石料成本过高 时,用此方法可以显著地降低成本;(1) When the existing stone materials on the site are insufficient to build a rockfill dam and the cost of transporting the stone materials is too high, this method can significantly reduce the cost;
(2)通过上下游排渗棱体与排渗褥垫构成的排渗设施主体可以实现粘性土初期坝的排渗;(2) The seepage drainage facility main body composed of the upstream and downstream seepage drainage prisms and the seepage drainage mattress can realize the seepage drainage of the cohesive soil initial dam;
(3)通过初期坝内预埋的竖向排渗盲沟管可以在初期坝内浸润线较高时进一步降低坝体浸润线;(3) The infiltration line of the dam body can be further reduced when the infiltration line in the initial dam is relatively high through the pre-buried vertical seepage drainage blind trench pipe in the initial dam;
(4)在初期坝与山体接触部位预埋斜向排水盲沟,在初期坝与山体接触部位预埋横向盲沟,可以增加排水效果,进一步降低坝体浸润线;(4) Pre-buried oblique drainage blind ditch at the initial contact part of the dam and the mountain, and pre-embedded the horizontal blind ditch at the initial contact part of the dam and the mountain, which can increase the drainage effect and further reduce the wetting line of the dam body;
(5)通过此方法施工简单,设计的排水设施多使用石料、土工膜、土工布,施工材料便于获得。(5) The construction is simple by this method, and the designed drainage facilities mostly use stone, geomembrane and geotextile, and the construction materials are easy to obtain.
附图说明Description of drawings
图1为本发明方法建设的一种适于上游式尾矿库的新型初期坝系统横剖面结构示意图;Fig. 1 is a kind of new-type initial stage dam system cross-sectional structural schematic diagram suitable for upstream type tailings pond constructed by the method of the present invention;
图2为本发明方法建设的一种适于上游式尾矿库的新型初期坝系统纵剖面结构示意图。FIG. 2 is a schematic diagram of the longitudinal section structure of a new type of initial dam system suitable for upstream tailings ponds constructed by the method of the present invention.
附图标记为:1-初期坝上游排渗棱体;1’-初期坝下游排渗棱体;2-初期坝排渗褥垫;3-竖向排渗盲沟管;4-坝脚排水沟;5-防渗护坡层;6-后期尾砂子坝;7-斜向排水盲沟;8-横向排水盲沟;9-初期坝体底部防渗层。The reference signs are: 1 - upstream seepage drainage prism of the initial dam; 1' - seepage drainage prism downstream of the initial dam; 2 - initial dam seepage drainage cushion; 3 - vertical seepage drainage blind ditch pipe; 4 - dam foot drainage ditch; 5- anti-seepage slope protection layer; 6- late tailings sub-dam; 7- oblique drainage blind ditch; 8- lateral drainage blind ditch; 9- anti-seepage layer at the bottom of the initial dam body.
具体实施方式Detailed ways
下面结合附图和实施例对本发明一种适于上游式尾矿库的新型初期坝的建设方法做进一步详细说明。The construction method of a novel initial dam suitable for an upstream tailings pond of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments.
由图1所示的本发明方法建设的一种适于上游式尾矿库的新型初期坝系统横剖面结构示意图并结合图2看出,本发明一种适于上游式尾矿库的新型初期坝的建设方法,在初期坝两侧山体上设置坝肩截水沟,在初期坝的坝脚设置坝脚排水沟4,所述的肩截水沟的出水端与坝脚排水沟4连通,并采用以下技术方案:The cross-sectional structural schematic diagram of a new type of initial dam system suitable for upstream tailings ponds constructed by the method of the present invention shown in FIG. 1 and combined with FIG. The construction method of the dam is to set the dam abutment intercepting ditch on the mountains on both sides of the initial dam, and set the dam toe drainage ditch 4 at the dam toe of the initial dam, and the outlet end of the shoulder intercepting ditch is communicated with the dam toe drainage ditch 4, And adopt the following technical solutions:
1)铺设初期坝体底部防渗层1) The anti-seepage layer at the bottom of the dam body at the initial stage of laying
对初期坝基底进行清基,清基结束后,自下而上分别铺设细粒土层、复合土工膜、粗砂层、块石层、砂卵石层共同构成初期坝体底部防渗层9;细粒土层中0~0.1mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%,块石层中76~200mm粒级质量占比≥95%,砂卵石层中13~76mm粒级质量占比≥95%;细粒土层的厚度为0.2m,粗砂层的厚度为0.2m,块石层的厚度为1.5m,砂卵石层的厚度为0.2m。The foundation of the initial dam is cleaned, and after the cleaning is completed, the fine-grained soil layer, the composite geomembrane, the coarse sand layer, the rock layer, and the sand and pebble layer are laid from bottom to top to form the anti-seepage layer 9 at the bottom of the initial dam body; In the fine-grained soil layer, the mass proportion of 0-0.1mm grain size is ≥95%, in the coarse sand layer, the mass proportion of 2-13mm grain size is ≥95%, and the mass proportion of 76-200mm grain size in the boulder layer is ≥95%. In the sand and pebble layer, the mass proportion of the 13-76mm grain size is ≥95%; the thickness of the fine-grained soil layer is 0.2m, the thickness of the coarse sand layer is 0.2m, the thickness of the boulder layer is 1.5m, and the thickness of the sand and pebble layer is 0.2m.
2)在初期坝上、下游分别设置初期坝上游排渗棱体1、初期坝下游排渗棱体1’,在初期坝上游排渗棱体1、初期坝下游排渗棱体1’之间的初期坝体底部防渗层9上铺设初期坝排渗褥垫2,初期坝上游排渗棱体1、初期坝下游排渗棱体1’与初期坝排渗褥垫2连通;2) On the upstream and downstream of the initial dam, respectively set the upstream seepage drainage prism 1 of the initial dam and the downstream seepage prism 1' of the initial dam, between the upstream seepage prism 1 of the initial dam and the seepage prism 1' downstream of the initial dam The initial dam seepage drainage cushion 2 is laid on the bottom anti-seepage layer 9 of the initial dam body, and the upstream seepage drainage prism 1 of the initial dam and the downstream seepage prism 1' of the initial dam are communicated with the initial dam seepage drainage cushion 2;
3)在初期坝内之初期坝排渗褥垫2之上预埋竖向排渗盲沟管3,竖向排渗盲沟管3的下端与初期坝排渗褥垫2连通;3) The vertical seepage drainage blind ditch pipe 3 is pre-buried on the initial dam seepage drainage mattress 2 in the initial dam, and the lower end of the vertical seepage drainage blind ditch pipe 3 is communicated with the initial dam seepage drainage mattress 2;
4)在初期坝与山体接触部位预埋斜向排水盲沟7,在初期坝与山体接触部位预埋横向盲沟8,斜向排水盲沟7的上部进水口与横向排水盲沟8连通,斜向排水盲沟7的下部出水口与初期坝排渗褥垫2连通;4) Pre-buried oblique drainage blind ditch 7 at the contact position between the initial dam and the mountain body, pre-embedded lateral blind ditch 8 at the initial contact position of the dam and the mountain body, and the upper water inlet of the oblique drainage blind ditch 7 is communicated with the horizontal drainage blind ditch 8, The lower water outlet of the oblique drainage blind ditch 7 is communicated with the initial dam drainage cushion 2;
5)初期坝施工5) Initial dam construction
在初期坝上游排渗棱体1、初期坝下游排渗棱体1’及初期坝两侧山体之间构成的空间内,自下而上逐层堆筑初期坝,并分层压实,当压实到初期坝上游排渗棱体1高度后,按照以下步骤实施:In the space formed by the upstream seepage drainage prism 1 of the initial dam, the downstream seepage prism 1' of the initial dam, and the mountains on both sides of the initial dam, the initial dam is built layer by layer from bottom to top, and the layers are compacted. After compaction to the height of the seepage-draining prism 1 upstream of the initial dam, follow the steps below:
第1步:采用粘性土堆筑、压实初期坝第一层,在初期坝第一层上游坡面上施工防渗护坡层5;Step 1: Use cohesive soil to build and compact the first layer of the initial dam, and construct the anti-seepage slope protection layer 5 on the upstream slope of the first layer of the initial dam;
第2步:在初期坝第一层之上采用粘性土堆筑、压实初期坝第二层,在初期坝第二层上游坡面上施工防渗护坡层5;Step 2: Use cohesive soil to build and compact the second layer of the initial dam on the first layer of the initial dam, and construct the anti-seepage protection slope layer 5 on the upstream slope of the second layer of the initial dam;
第3部:在初期坝第二层之上采用粘性土堆筑、压实初期坝第 三层,在初期坝第三层上游坡面上施工防渗护坡层5;Part 3: Build and compact the third layer of the initial dam with cohesive soil above the second layer of the initial dam, and construct an anti-seepage protection slope layer 5 on the upstream slope of the third layer of the initial dam;
第4~n步:以此类推,直至堆筑至设计高度。 Steps 4 to n: By analogy, until the stacking reaches the design height.
所述防渗护坡层5自内向外分别是砂卵石层、块石层、砂卵石层、粗砂层、复合土工膜、粗砂层;砂卵石层中13~76mm粒级质量占比≥95%,块石层中76~200mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%;在防渗护坡层5中,粗砂层的厚度为0.2m,块石层的厚度为1.5m,砂卵石层的厚度为0.2m。The anti-seepage slope protection layer 5 is, from the inside to the outside, a sand and pebble layer, a block stone layer, a sand and pebble layer, a coarse sand layer, a composite geomembrane, and a coarse sand layer. %, the mass proportion of 76-200mm grain size in the boulder layer is ≥95%, and the mass proportion of 2-13mm grain size in the coarse sand layer is ≥95%; in the anti-seepage slope protection layer 5, the thickness of the coarse sand layer is 0.2m , the thickness of the block stone layer is 1.5m, and the thickness of the sand pebble layer is 0.2m.
本发明采用的复合土工膜为两层土工布中间夹一层土工膜,土工布的规格为300~600g/m 2;其中:步骤1)中之复合土工膜采用300g/m 2土工布,步骤5)之复合土工膜采用600g/m 2无纺织土工布,土工膜采用HDPE膜。 The composite geomembrane used in the present invention is a layer of geomembrane sandwiched between two layers of geotextiles, and the specifications of the geotextiles are 300-600 g/m 2 ; wherein: the composite geomembrane in step 1) adopts 300 g/m 2 geotextiles. 5) The composite geomembrane adopts 600g/m 2 non-woven geotextile, and the geomembrane adopts HDPE membrane.
在步骤5)中,自下而上每层堆筑的高度为2.5m,分层压实的厚度不超过0.8m。In step 5), the stacking height of each layer from bottom to top is 2.5m, and the thickness of layered compaction does not exceed 0.8m.
在初期坝堆筑至设计高度后,在初期坝的坝顶表面铺设土工膜,在土工膜上铺设碎石保护层、干砌块石块保护层。After the initial dam is built to the design height, a geomembrane is laid on the top surface of the initial dam, and a protective layer of crushed stone and dry block stone is laid on the geomembrane.
在初期坝堆筑完成并排放尾矿至该水平后,开始进行子坝6的施工,子坝6施工顺序为:After the initial dam construction is completed and the tailings are discharged to this level, the construction of the sub-dam 6 begins. The construction sequence of the sub-dam 6 is as follows:
先平整基础层,在基础层之上自下而上分别施工细粒土层、复合土工膜、粗尾砂保护层,形成第一级子坝;在第一级子坝施工完成并排放尾矿至该水平后,再退后施工第二级子坝;第二级子坝的施工顺序也为平整基础层→细粒土层→复合土工膜→粗尾砂保护层,以此类推。细粒土层中0~0.1mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%,细粒土层的厚度为0.2m;粗尾砂保护层从旧尾矿库挖运过来,厚度为0.2m;复合土工膜为两层土工布中间夹一层土工膜,土工布的规格为300g/m 2,土工膜为1.5mm的HDPE膜。 The base layer is first leveled, and the fine-grained soil layer, composite geomembrane, and coarse tailings protective layer are constructed from bottom to top on the base layer to form the first-level sub-dam; after the construction of the first-level sub-dam is completed, the tailings are discharged After reaching this level, the second-level sub-dam will be built backward; the construction sequence of the second-level sub-dam is also leveling the base layer→fine-grained soil layer→composite geomembrane→coarse tailings protective layer, and so on. In the fine-grained soil layer, the mass proportion of the 0-0.1mm grain size is ≥95%, and in the coarse sand layer, the mass proportion of the 2-13mm grain size is ≥95%, and the thickness of the fine-grained soil layer is 0.2m; The old tailings pond was excavated and transported, with a thickness of 0.2m; the composite geomembrane is a layer of geomembrane sandwiched between two layers of geotextiles.
本发明采用Bishop法对尾矿坝稳定性进行分析;用有限元法对 尾矿坝渗流场进行分析,计算出结点水头,并用计算机输出水位线。The invention adopts the Bishop method to analyze the stability of the tailings dam; uses the finite element method to analyze the seepage field of the tailings dam, calculates the node water head, and uses the computer to output the water level line.

Claims (8)

  1. 一种适于上游式尾矿库的新型初期坝的建设方法,在初期坝两侧山体上设置坝肩截水沟,在初期坝的坝脚设置坝脚排水沟(4),所述的肩截水沟的出水端与坝脚排水沟(4)连通,其特征在于还采用以下技术方案:A method for constructing a new type of initial dam suitable for an upstream tailings pond. A dam abutment intercepting ditch is arranged on the mountain bodies on both sides of the initial dam, and a dam toe drainage ditch (4) is arranged at the dam foot of the initial dam. The outlet end of the intercepting ditch is communicated with the drainage ditch (4) at the foot of the dam, and is characterized in that the following technical solutions are also adopted:
    1)铺设初期坝体底部防渗层1) The anti-seepage layer at the bottom of the dam body at the initial stage of laying
    对初期坝基底进行清基,清基结束后,自下而上分别铺设细粒土层、复合土工膜、粗砂层、块石层、砂卵石层共同构成初期坝体底部防渗层(9);The foundation of the initial dam is cleaned. After the foundation is cleaned, the fine-grained soil layer, the composite geomembrane, the coarse sand layer, the rock layer and the sand and pebble layer are laid from bottom to top to form the anti-seepage layer at the bottom of the initial dam body (9 );
    2)在初期坝上、下游分别设置初期坝上游排渗棱体(1)、初期坝下游排渗棱体(1’),在初期坝上游排渗棱体(1)、初期坝下游排渗棱体(1’)之间的初期坝体底部防渗层(9)上铺设初期坝排渗褥垫(2),初期坝上游排渗棱体(1)、初期坝下游排渗棱体(1’)与初期坝排渗褥垫(2)连通;2) Set up seepage drainage prisms (1) upstream of the initial dam and downstream seepage prisms (1') on the upstream and downstream of the initial dam, respectively, and seepage drainage prisms (1) upstream of the initial dam and seepage drainage downstream of the initial dam The initial dam seepage drainage cushion (2) is laid on the anti-seepage layer (9) at the bottom of the initial dam body between the prisms (1'), the seepage drainage prism (1) upstream of the initial dam, and the seepage drainage prism downstream of the initial dam ( 1') is communicated with the initial dam drainage mattress (2);
    3)在初期坝内之初期坝排渗褥垫(2)之上预埋竖向排渗盲沟管(3),竖向排渗盲沟管(3)的下端与初期坝排渗褥垫(2)连通;3) The vertical seepage drainage blind ditch pipe (3) is pre-buried on the initial dam seepage drainage mattress (2) in the initial dam, and the lower end of the vertical seepage drainage blind ditch pipe (3) and the initial dam seepage drainage mattress (2) Connectivity;
    4)在初期坝与山体接触部位预埋斜向排水盲沟(7),在初期坝与山体接触部位预埋横向盲沟(8),斜向排水盲沟(7)的上部进水口与横向排水盲沟(8)连通,斜向排水盲沟(7)的下部出水口与初期坝排渗褥垫(2)连通;4) Pre-buried oblique drainage blind ditch (7) at the initial contact position between the dam and the mountain, pre-embedded lateral blind ditch (8) at the initial contact position between the dam and the mountain, and the upper water inlet of the oblique drainage blind ditch (7) and the horizontal The blind drainage ditch (8) is communicated, and the lower water outlet of the oblique drainage blind ditch (7) is communicated with the initial dam drainage cushion (2);
    5)初期坝施工5) Initial dam construction
    在初期坝上游排渗棱体(1)、初期坝下游排渗棱体(1’)及初期坝两侧山体之间构成的空间内,自下而上逐层堆筑初期坝,并分层压实,当压实到初期坝上游排渗棱体(1)高度后,按照以下步骤实施:In the space formed between the upstream seepage drainage prism (1) of the initial dam, the downstream seepage prism (1') of the initial dam, and the mountains on both sides of the initial dam, the initial dam is built layer by layer from bottom to top, and the layers are layered. Compaction, when compacted to the height of the upstream seepage prism (1) of the initial dam, follow the steps below:
    第1步:采用粘性土堆筑、压实初期坝第一层,在初期坝第一层上游坡面上施工防渗护坡层(5);Step 1: Use cohesive soil to build and compact the first layer of the initial dam, and construct an anti-seepage slope protection layer (5) on the upstream slope of the first layer of the initial dam;
    第2步:在初期坝第一层之上采用粘性土堆筑、压实初期坝第二层,在初期坝第二层上游坡面上施工防渗护坡层(5);Step 2: Use cohesive soil to build and compact the second layer of the initial dam on the first layer of the initial dam, and construct the anti-seepage slope protection layer (5) on the upstream slope of the second layer of the initial dam;
    第3部:在初期坝第二层之上采用粘性土堆筑、压实初期坝第三层,在初期坝第三层上游坡面上施工防渗护坡层(5);Part 3: Use cohesive soil to build and compact the third layer of the initial dam on the second layer of the initial dam, and construct the anti-seepage slope protection layer (5) on the upstream slope of the third layer of the initial dam;
    第4~n步:以此类推。Steps 4 to n: and so on.
  2. 如权利要求1所述的一种适于上游式尾矿库的新型初期坝的建设方法,其特征在于:步骤1)所述细粒土层中0~0.1mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%,块石层中76~200mm粒级质量占比≥95%,砂卵石层中13~76mm粒级质量占比≥95%。The construction method of a new type of initial dam suitable for an upstream tailings pond according to claim 1, characterized in that: in step 1) the fine-grained soil layer in the fine-grained soil layer accounts for ≥ 95% by mass , the mass proportion of 2-13mm grain size in the coarse sand layer is ≥95%, the mass proportion of 76-200mm grain size in the boulder layer is ≥95%, and the mass proportion of 13-76mm grain size in the sand and pebble layer is ≥95%.
  3. 如权利要求2所述的一种适于上游式尾矿库的新型初期坝的建设方法,其特征在于:防渗护坡层(5)自内向外分别是砂卵石层、块石层、砂卵石层、粗砂层、复合土工膜、粗砂层;所述的复合土工膜为两层土工布中间夹一层土工膜。The construction method of a novel initial dam suitable for an upstream tailings pond according to claim 2, characterized in that: the anti-seepage slope protection layer (5) from the inside to the outside is a sand and pebble layer, a block stone layer, and a sand and pebble layer, respectively. layer, coarse sand layer, composite geomembrane, and coarse sand layer; the composite geomembrane is a layer of geomembrane sandwiched between two layers of geotextiles.
  4. 如权利要求3所述的一种适于上游式尾矿库的新型初期坝的建设方法,其特征在于:在防渗护坡层(5)中,砂卵石层中13~76mm粒级质量占比≥95%,块石层中76~200mm粒级质量占比≥95%,粗砂层中2~13mm粒级质量占比≥95%。The construction method of a new type of initial dam suitable for an upstream tailings pond according to claim 3, characterized in that: in the anti-seepage slope protection layer (5), the mass proportion of 13-76 mm grain size in the sand and pebble layer ≥95%, the mass proportion of 76-200mm in the rock layer is ≥95%, and the mass of 2-13mm in the coarse sand layer is ≥95%.
  5. 如权利要求4所述的一种适于上游式尾矿库的新型初期坝的建设方法,其特征在于:步骤1)中,细粒土层的厚度为0.17~0.23m,粗砂层的厚度为0.18~0.24m,块石层的厚度为1.3~1.8m,砂卵石层的厚度为0.18~0.25m。The construction method of a new type of initial dam suitable for an upstream tailings pond according to claim 4, characterized in that: in step 1), the thickness of the fine-grained soil layer is 0.17-0.23 m, and the thickness of the coarse sand layer is 0.17-0.23 m. It is 0.18-0.24m, the thickness of the rock layer is 1.3-1.8m, and the thickness of the sand and pebble layer is 0.18-0.25m.
  6. 如权利要求5所述的一种适于上游式尾矿库的新型初期坝的建设方法,其特征在于:防渗护坡层(5)中,粗砂层的厚度为0.18~0.24m,块石层的厚度为1.3~1.8m,砂卵石层的厚度为0.18~0.25m。A method for constructing a new type of initial dam suitable for an upstream tailings pond according to claim 5, characterized in that: in the anti-seepage slope protection layer (5), the thickness of the coarse sand layer is 0.18-0.24m, the The thickness of the layer is 1.3 to 1.8m, and the thickness of the sand and pebble layer is 0.18 to 0.25m.
  7. 如权利要求1、2、3、4、5或6所述的一种适于上游式尾矿 库的新型初期坝的建设方法,其特征在于:步骤5)中,自下而上每层堆筑的高度为2.2~2.8m,分层压实的厚度不超过0.8m。The construction method of a novel initial dam suitable for an upstream tailings pond according to claim 1, 2, 3, 4, 5 or 6, characterized in that: in step 5), each layer is stacked from bottom to top The height of the building is 2.2 ~ 2.8m, and the thickness of the layered compaction does not exceed 0.8m.
  8. 如权利要求7所述的一种适于上游式尾矿库的新型初期坝的建设方法,其特征在于:用Bishop法对尾矿坝稳定性进行分析;用有限元法对尾矿坝渗流场进行分析,计算出结点水头,并用计算机输出水位线。The construction method of a new type of initial dam suitable for an upstream tailings pond as claimed in claim 7, characterized in that: the stability of the tailings dam is analyzed by the Bishop method; the seepage field of the tailings dam is analyzed by the finite element method. The analysis is carried out, the node water head is calculated, and the water level line is output by the computer.
PCT/CN2021/116002 2021-01-27 2021-09-01 Method for constructing novel starter dam suitable for upstream tailings pond WO2022160713A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110109027.4 2021-01-27
CN202110109027.4A CN112921905B (en) 2021-01-27 2021-01-27 Construction method of initial dam suitable for upstream type tailing pond

Publications (1)

Publication Number Publication Date
WO2022160713A1 true WO2022160713A1 (en) 2022-08-04

Family

ID=76166808

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/116002 WO2022160713A1 (en) 2021-01-27 2021-09-01 Method for constructing novel starter dam suitable for upstream tailings pond

Country Status (3)

Country Link
CN (1) CN112921905B (en)
WO (1) WO2022160713A1 (en)
ZA (1) ZA202204722B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116090080A (en) * 2023-04-07 2023-05-09 兰州有色冶金设计研究院有限公司 Design method for stepped steeping structure of full-section infiltration line of tailing dam
CN116432273A (en) * 2023-02-28 2023-07-14 中国电建集团成都勘测设计研究院有限公司 Suspension type seepage-proof design method for foundation dam with strong water permeability and deep coverage layer
CN117161636A (en) * 2023-11-03 2023-12-05 矿冶科技集团有限公司 Arrange and ooze nest of tubes system of processing

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112921905B (en) * 2021-01-27 2022-03-15 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of initial dam suitable for upstream type tailing pond
CN113882491A (en) * 2021-10-14 2022-01-04 中钢集团马鞍山矿山研究总院股份有限公司 Method for reducing infiltration line of tailing pond or phosphogypsum pond
CN114439090A (en) * 2021-10-14 2022-05-06 中钢集团马鞍山矿山研究总院股份有限公司 Interception, drainage and seepage structure for reducing seepage line of tailing pond or phosphogypsum pond
CN114892681A (en) * 2022-06-17 2022-08-12 中国恩菲工程技术有限公司 Sand dam, tailing dam and medium-line tailing damming method
CN115492131B (en) * 2022-08-23 2023-06-13 攀钢集团矿业有限公司 Weak beach embankment earth covering method and device for tail part of tailing pond

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100879917B1 (en) * 2008-06-04 2009-02-26 (주)시엠씨 Tailing stability method of river at mine district
CN202081409U (en) * 2011-05-31 2011-12-21 内蒙古电力勘测设计院 Initial dam structure of ash storage field built of ash and slag
CN104480974A (en) * 2014-12-15 2015-04-01 中冶长天国际工程有限责任公司 Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN105926576A (en) * 2016-04-29 2016-09-07 铜陵有色金属集团股份有限公司冬瓜山铜矿 Method for accelerating tailing pulp dewatering and consolidating in upstream method milltailing alluviation dam building
CN110656629A (en) * 2019-10-22 2020-01-07 中国恩菲工程技术有限公司 Initial dam of upstream method damming tailings pond
CN210946842U (en) * 2019-10-17 2020-07-07 西京学院 Grid beam slope protection device for initial dam of tailing pond
CN112921905A (en) * 2021-01-27 2021-06-08 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of novel initial dam suitable for upstream type tailing pond

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1782280A3 (en) * 1989-11-13 1992-12-15 Чepeпobeцkoe Пpoизboдctbehhoe Oб'eдиhehиe "Ammoфoc" Method of clearing slurry sump from pyrite cinders
CN202117155U (en) * 2011-06-11 2012-01-18 昆明有色冶金设计研究院股份公司 Efficient leakage drainage device for inner slope of initial dam of tailing pond
CN104631425B (en) * 2014-12-18 2016-08-17 河南省电力勘测设计院 A kind of flyash of accelerating arranges the method oozing consolidation
CN104652492B (en) * 2015-01-09 2016-07-06 中钢集团马鞍山矿山研究院有限公司 The row of a kind of Tailings Dam cohesive soil initial dam oozes system
CN111305210B (en) * 2020-03-05 2021-05-25 中钢集团马鞍山矿山研究总院股份有限公司 Ultra-fine grain tailing pond heightening and expanding heap-discharging structure adopting midline method for one-time dam building

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100879917B1 (en) * 2008-06-04 2009-02-26 (주)시엠씨 Tailing stability method of river at mine district
CN202081409U (en) * 2011-05-31 2011-12-21 内蒙古电力勘测设计院 Initial dam structure of ash storage field built of ash and slag
CN104480974A (en) * 2014-12-15 2015-04-01 中冶长天国际工程有限责任公司 Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN105926576A (en) * 2016-04-29 2016-09-07 铜陵有色金属集团股份有限公司冬瓜山铜矿 Method for accelerating tailing pulp dewatering and consolidating in upstream method milltailing alluviation dam building
CN210946842U (en) * 2019-10-17 2020-07-07 西京学院 Grid beam slope protection device for initial dam of tailing pond
CN110656629A (en) * 2019-10-22 2020-01-07 中国恩菲工程技术有限公司 Initial dam of upstream method damming tailings pond
CN112921905A (en) * 2021-01-27 2021-06-08 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of novel initial dam suitable for upstream type tailing pond

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116432273A (en) * 2023-02-28 2023-07-14 中国电建集团成都勘测设计研究院有限公司 Suspension type seepage-proof design method for foundation dam with strong water permeability and deep coverage layer
CN116090080A (en) * 2023-04-07 2023-05-09 兰州有色冶金设计研究院有限公司 Design method for stepped steeping structure of full-section infiltration line of tailing dam
CN116090080B (en) * 2023-04-07 2023-10-24 兰州有色冶金设计研究院有限公司 Design method for stepped steeping structure of full-section infiltration line of tailing dam
CN117161636A (en) * 2023-11-03 2023-12-05 矿冶科技集团有限公司 Arrange and ooze nest of tubes system of processing
CN117161636B (en) * 2023-11-03 2024-01-19 矿冶科技集团有限公司 Arrange and ooze nest of tubes system of processing

Also Published As

Publication number Publication date
CN112921905B (en) 2022-03-15
ZA202204722B (en) 2022-06-29
CN112921905A (en) 2021-06-08

Similar Documents

Publication Publication Date Title
WO2022160713A1 (en) Method for constructing novel starter dam suitable for upstream tailings pond
CN101758058B (en) Method for piling tails without building tails reservoir
CN103953008A (en) Modified mixed dam applicable to tailings ponds
CN111691438A (en) Anti-skidding-drainage comprehensive treatment method for landslide of large-scale accumulation body
CN112392127B (en) Dendritic embedded type flexible ecological slope drainage ditch and construction method
CN110820720A (en) Water-blocking and drainage-resisting anti-floating construction structure and method
CN110847124A (en) Concrete panel rock-fill dam with multiple anti-seepage structures and construction method thereof
CN101021068A (en) Low-level prepressing drainage dynamic consolidating soft soil foundation processing method
CN111648383A (en) Internal drainage method for loess high-fill side slope
CN113502836A (en) Drainage geogrid and supporting structure and method
CN207079438U (en) For sponge urban water-through mat formation it is lower improvement permeability rate device
CN112921904B (en) A clay initial dam structure for upstream formula tailing storehouse
CN112854144A (en) Construction structure of earth-rock dam on deep sludge layer and construction method thereof
CN112195965A (en) Expansive soil cutting retaining wall
CN108532543B (en) Auxiliary anti-seepage layer-paving structure for foundation pit on upstream of dam
CN111827152A (en) Internal drainage structure of edge-covered roadbed and implementation method thereof
CN210262542U (en) Road structure for sponge city construction
CN108487331B (en) Underground structure anti-floating system integrating gallery drainage and fertilizer groove seepage prevention
CN213358505U (en) Seepage-proofing reinforcing heightening structure for existing diseased river levee
CN213867883U (en) Sand filling pipe bag cofferdam suitable for coastal area
CN109653240B (en) Urban residual soil heaping body in ecological restoration engineering and construction method thereof
CN210368867U (en) Superimposed structure of homogeneity earth dam and rock-fill dam
CN209338948U (en) A kind of water-permeable pavement structure
CN111335290A (en) Offshore artificial island structure suitable for silt foundation and construction method
CN218060376U (en) Self-dewatering balanced decompression underground anti-floating structure

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21922308

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21922308

Country of ref document: EP

Kind code of ref document: A1