CN112921905A - Construction method of novel initial dam suitable for upstream type tailing pond - Google Patents

Construction method of novel initial dam suitable for upstream type tailing pond Download PDF

Info

Publication number
CN112921905A
CN112921905A CN202110109027.4A CN202110109027A CN112921905A CN 112921905 A CN112921905 A CN 112921905A CN 202110109027 A CN202110109027 A CN 202110109027A CN 112921905 A CN112921905 A CN 112921905A
Authority
CN
China
Prior art keywords
layer
dam
initial dam
drainage
initial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110109027.4A
Other languages
Chinese (zh)
Other versions
CN112921905B (en
Inventor
许传华
段蔚平
毛志远
邱宇
杨强胜
田伟虎
倪强
藕明江
翁金红
吴光富
曹金海
鲁立胜
汪明海
林启祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Sinosteel Maanshan Institute Of Mining Research Engineering Investigation And Design Co ltd
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Maanshan Institute Of Mining Research Engineering Investigation And Design Co ltd, Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd, Sinosteel Maanshan General Institute of Mining Research Co Ltd filed Critical Sinosteel Maanshan Institute Of Mining Research Engineering Investigation And Design Co ltd
Priority to CN202110109027.4A priority Critical patent/CN112921905B/en
Publication of CN112921905A publication Critical patent/CN112921905A/en
Priority to PCT/CN2021/116002 priority patent/WO2022160713A1/en
Application granted granted Critical
Publication of CN112921905B publication Critical patent/CN112921905B/en
Priority to ZA2022/04722A priority patent/ZA202204722B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • E03F3/046Open sewage channels

Abstract

The invention discloses a novel construction method of an initial dam suitable for an upstream tailing pond, which comprises the steps of laying an impermeable layer at the bottom of an initial dam body, and respectively arranging an upstream seepage drainage ridge (1) and a downstream seepage drainage ridge (1) of the initial dam on the upstream and the downstream of the initial dam) An initial dam drainage mattress (2) is laid on an impermeable layer at the bottom of the initial dam body, and the lower end of the vertical drainage blind ditch pipe (3) is communicated with the initial dam drainage mattress (2); embedding an oblique drainage blind ditch at the contact part of the initial dam and the mountain, and embedding a transverse blind ditch at the contact part of the initial dam and the mountain; and (3) piling up the initial dam layer by layer from bottom to top, compacting the initial dam layer by layer, and constructing an anti-seepage slope protection layer (5) on the upstream slope of the initial dam. The invention has the advantages of low construction cost, small stone usage amount and good water permeable effect, and the soil dam reaches the water permeable dam by designing the drainage facility in the initial soil damThe requirements of (1).

Description

Construction method of novel initial dam suitable for upstream type tailing pond
Technical Field
The invention relates to a tailing discharging and stockpiling facility, in particular to an initial dam of a tailing pond, which is particularly suitable for being applied to the construction of an upstream tailing pond under the conditions that stone resources are insufficient at the place where the tailing pond is planned to be constructed, a permeable rock-fill dam is difficult to construct and the traffic is inconvenient, and can effectively reduce the seepage line of a dam body.
Background
The initial dam is built by non-tailing materials, and the main function of the initial dam is to lay a foundation for the later tailing accumulation dam, namely the foundation dam. Two types of non-permeable dams and permeable dams can be classified according to whether water is drained or not.
In the process of the upstream type tailing pond operation, the initial dam type generally adopts a permeable rock-fill dam in consideration of stable permeation at the initial stage and the later stage of the tailing pond operation. The permeable dam is a dam type which performs organized drainage in a dam body and allows organized and planned water seepage. The drainage system of the utility model has different functions and functions from the drainage system of the impermeable dam. A drainage system is also arranged in the impervious dam, and the purpose of the drainage system is to discharge seepage water in the impervious body organically, protect the impervious body and the initial dam and prevent seepage deformation. The water draining system of permeable dam is to eliminate the water leakage from the dam in organized mode and has the main function of controlling the position of the infiltration line inside the accumulated dam. The main dam type of the permeable dam is that reverse filtering bodies are additionally arranged on the upstream slope of various rockfill dams, and drainage facilities can also be additionally arranged in the impermeable dam, so that the infiltration line of a tailing fill dam can be reduced. The permeable dam is the most basic dam type in the initial dam, and is also an ideal dam type.
The dam shape of the initial dam is selected according to the specific conditions of the body, the local conditions are thoroughly met, the materials are locally obtained, and the principle of material design is adopted. The earth-rock dam has the lowest requirement on the topographic and geological conditions and has the strongest adaptability. If the local stone is not enough to build the permeable rock-fill dam, a drainage facility can be added on the basis of the homogeneous dam to realize water permeability.
In the article of 'the upstream type tailing pond is a new initial dam type seepage calculation analysis' published in 2 months 2020 of science and technology wind of Chinese journal, a new initial dam type is provided, and a part of soil and rock mixture (about 1/4 initial dam height) is filled in an upstream side partition of a conventional rockfill dam, so that tailing 'muddy' at the initial operation stage of the tailing pond is reduced, and the stable seepage of the rockfill dam is ensured. However, the initial dam belongs to a permeable dam, a large amount of stone resources are needed in construction, and the construction cost is high; moreover, after a part of soil and stone mixture is filled in the upstream side of the conventional rockfill dam in a partition mode, the water permeability is greatly reduced.
The invention discloses a design method for enabling an earth dam to meet the requirements of a permeable dam according to site conditions of a tailing pond and characteristics of dam building materials.
Disclosure of Invention
The method for constructing the initial dam of the upstream type tailing pond is low in construction cost, small in stone usage amount and good in water permeability, the designed initial dam can meet the water permeability requirement of the permeable dam, and when the site stone is not enough to construct the initial rock-fill dam and the cost for transporting stone is high, the cost can be effectively reduced, and the initial dam can meet the use requirement of the permeable dam.
In order to achieve the purpose, the construction method of the novel initial dam suitable for the upstream type tailing pond is realized by adopting the following technical scheme:
the invention relates to a novel construction method of an initial dam suitable for an upstream tailing pond, which is characterized in that dam abutment intercepting ditches are arranged on hills on two sides of the initial dam, dam foot drainage ditches are arranged at dam feet of the initial dam, the water outlet ends of the dam abutment intercepting ditches are communicated with the dam foot drainage ditches, and the following technical scheme is adopted:
1) impermeable layer at bottom of dam body at initial laying stage
Clearing the foundation of the initial dam, and paving a fine soil layer, a composite geomembrane, a coarse sand layer, a rock block layer and a sand-gravel layer from bottom to top respectively to form an impermeable layer at the bottom of the initial dam body after clearing the foundation;
the mass percentage of 0-0.1 mm grain fraction in the fine grain soil layer is more than or equal to 95%, the mass percentage of 2-13 mm grain fraction in the coarse sand layer is more than or equal to 95%, the mass percentage of 76-200 mm grain fraction in the stone layer is more than or equal to 95%, and the mass percentage of 13-76 mm grain fraction in the sand gravel layer is more than or equal to 95%; wherein: the thickness of the fine-grain soil layer is 0.17-0.23 m, the thickness of the coarse sand layer is 0.18-0.24 m, the thickness of the lump stone layer is 1.3-1.8 m, and the thickness of the sand gravel layer is 0.18-0.25 m.
2) An upstream drainage ridge and a downstream drainage ridge of the initial dam are respectively arranged at the upstream and the downstream of the initial dam, an initial dam drainage mattress is paved on an impermeable layer at the bottom of the initial dam between the upstream drainage ridge and the downstream drainage ridge of the initial dam, and the upstream drainage ridge and the downstream drainage ridge of the initial dam are communicated with the initial dam drainage mattress; the stone material for stacking the seepage drainage arrises is required to be a good permeable material, the content of the stone material with the granularity smaller than 2mm is not more than 5 percent, the maximum diameter of the stone material is not more than 0.5m, the stone material is required to be fresh, hard, weather-resistant and abrasion-resistant, weatherproof stone is not used, the wet compressive strength is not less than 40Mpa, and the softening coefficient is not less than 0.80; the seepage drainage prism and the seepage drainage mattress are both wrapped by double-layer geotextile.
3) Pre-burying a vertical drainage blind ditch pipe on a drainage mattress of the initial dam in the initial dam, wherein the lower end of the vertical drainage blind ditch pipe is communicated with the drainage mattress of the initial dam; the vertical seepage elimination blind ditch pipe is wrapped by geotextile and is symmetrically arranged in the initial dam.
4) Embedding an inclined drainage blind ditch at the contact part of the initial dam and the mountain, embedding a transverse blind ditch at the contact part of the initial dam and the mountain, wherein the upper water inlet of the inclined drainage blind ditch is communicated with the transverse drainage blind ditch, and the lower water outlet of the inclined drainage blind ditch is communicated with the drainage mattress of the initial dam; the blind ditch is formed by wrapping rubble stones by double-layer geotextile, the rubble stones are compact and have good water permeability, and the aim is to increase the drainage capacity of the contact part of the initial dam and a mountain and further reduce the seepage line of the dam.
5) Initial dam construction
In the space formed between the upstream seepage drainage arris body of the initial dam, the downstream seepage drainage arris body of the initial dam and the mountain bodies at two sides of the initial dam, the initial dam is built layer by layer from bottom to top and is compacted in a layering way, and after the upstream seepage drainage arris body height of the initial dam is compacted, the method is implemented according to the following steps:
step 1: adopting cohesive soil to pile and compact the first layer of the initial dam, and constructing an anti-seepage slope protection layer on the upstream slope of the first layer of the initial dam;
step 2: adopting cohesive soil to pile and compact the second layer of the initial dam above the first layer of the initial dam, and constructing an anti-seepage slope protection layer on the upstream slope of the second layer of the initial dam;
section 3: adopting cohesive soil to pile and compact the third layer of the initial dam on the second layer of the initial dam, and constructing an anti-seepage slope protection layer on the upstream slope of the third layer of the initial dam;
and 4, step n: and the rest can be done by analogy until the building height reaches the design height.
And paving a geomembrane on the surface of the dam crest of the initial dam, and paving a broken stone protective layer and a dry block stone protective layer on the geomembrane. The dry stone has a specification, the ratio of long to short sides is not more than 4, the content of the dry stone is less than 5 percent and the dry stone has proper gradation.
Furthermore, the anti-seepage slope protection layer is respectively a sand-gravel layer, a rock block layer, a sand-gravel layer, a coarse sand layer, a composite geomembrane and a coarse sand layer from inside to outside; the composite geomembrane is formed by sandwiching a geomembrane between two layers of geotextiles; in the anti-seepage slope protection layer, the mass of 13-76 mm grain size fraction in the sand-gravel layer is more than or equal to 95%, the mass of 76-200 mm grain size fraction in the rock block layer is more than or equal to 95%, and the mass of 2-13 mm grain size fraction in the coarse sand layer is more than or equal to 95%; in the anti-seepage slope protection layer, the thickness of the coarse sand layer is 0.18-0.24 m, the thickness of the stone layer is 1.3-1.8 m, and the thickness of the sand gravel layer is 0.18-0.25 m.
Further, in the step 5), the height of each layer of stacking from bottom to top is 2.2-2.8 m, the thickness of the layered compaction is not more than 0.8m, after the layers are rolled by a vibratory roller, each layer of sampling is used for measuring the porosity, the number of the sampling and the technical requirement of the porosity measurement are implemented according to the specification requirement, and the porosity of the dam body after the compaction is required to be not more than 22%. The cautions and technical requirements of the cohesive soil pile must comply with the technical Specification for construction of rolled earth-rock dam DL/5129-2001 and GBJ201-83 Specification for construction and acceptance of earthwork and blasting engineering, so as to achieve the expected filling quality.
Further, the stability of the tailing dam is analyzed by a Bishop method; and analyzing the seepage field of the tailing dam by using a finite element method, calculating a node water head, and outputting a water level line by using a computer.
The construction method of the novel initial dam suitable for the upstream type tailing pond has the following effects after the technical scheme is adopted:
(1) when the existing stones in the field are not enough to build a rock-fill dam and the cost for transporting stones is too high, the method can obviously reduce the cost;
(2) the drainage of the cohesive soil initial dam can be realized through a drainage facility main body formed by the upstream and downstream drainage arrises and the drainage mattress;
(3) the dam body infiltration line can be further reduced when the infiltration line in the initial dam is higher through the vertical drainage blind ditch pipe pre-buried in the initial dam;
(4) the oblique drainage blind ditches are embedded in the contact part of the initial dam and the mountain, and the transverse blind ditches are embedded in the contact part of the initial dam and the mountain, so that the drainage effect can be improved, and the dam body infiltration line is further reduced;
(5) the method is simple in construction, the designed drainage facility mostly uses stones, geomembranes and geotextiles, and construction materials are convenient to obtain.
Drawings
Fig. 1 is a schematic cross-sectional structure diagram of a novel initial dam system suitable for an upstream tailings pond constructed by the method of the present invention;
fig. 2 is a schematic diagram of a longitudinal section structure of a novel initial dam system suitable for an upstream tailings pond constructed by the method.
The reference signs are: 1-drainage prism at upstream of initial dam; 1' -drainage arrises at the downstream of the initial dam; 2-draining seepage mattress of initial dam; 3-vertical drainage blind ditch pipe; 4-a dam foot drainage ditch; 5-seepage-proofing slope protection layer; 6-late tailing dam; 7-oblique drainage blind ditches; 8-horizontal drainage blind ditches; 9-impermeable layer at the bottom of the dam body at the initial stage.
Detailed Description
The method for constructing the novel initial dam suitable for the upstream-type tailing pond is further described in detail with reference to the accompanying drawings and examples.
The invention is shown in figure 1 and is suitable for the new initial dam system cross section structure sketch map of the upstream type tailings storehouse and combines figure 2 to see, the invention is suitable for the new initial dam construction method of the upstream type tailings storehouse, set up the dam abutment intercepting ditch on the massif of both sides of the initial dam, set up the foot drain ditch 4 of dam in the foot of dam of the initial dam, the said outlet end of the intercepting ditch of the shoulder is communicated with foot drain ditch 4 of dam, and adopt the following technical scheme:
1) impermeable layer at bottom of dam body at initial laying stage
Clearing the foundation of the initial dam, and paving a fine soil layer, a composite geomembrane, a coarse sand layer, a rock block layer and a sand-gravel layer from bottom to top respectively to form an impermeable layer 9 at the bottom of the initial dam body after clearing the foundation; the mass percentage of 0-0.1 mm grain fraction in the fine grain soil layer is more than or equal to 95%, the mass percentage of 2-13 mm grain fraction in the coarse sand layer is more than or equal to 95%, the mass percentage of 76-200 mm grain fraction in the lump stone layer is more than or equal to 95%, and the mass percentage of 13-76 mm grain fraction in the sand gravel layer is more than or equal to 95%; the thickness of the fine-grained soil layer is 0.2m, the thickness of the coarse sand layer is 0.2m, the thickness of the stone layer is 1.5m, and the thickness of the sand-gravel layer is 0.2 m.
2) An upstream drainage and seepage prism 1 and a downstream drainage and seepage prism 1 ' of the initial dam are respectively arranged at the upstream and the downstream of the initial dam, an initial dam drainage and seepage mattress 2 is laid on an impermeable layer 9 at the bottom of the initial dam between the upstream drainage and seepage prism 1 and the downstream drainage and seepage prism 1 ', and the upstream drainage and seepage prism 1 and the downstream drainage and seepage prism 1 ' of the initial dam are communicated with the initial dam drainage and seepage mattress 2;
3) a vertical drainage blind ditch pipe 3 is pre-buried above a drainage mattress 2 of the initial dam in the initial dam, and the lower end of the vertical drainage blind ditch pipe 3 is communicated with the drainage mattress 2 of the initial dam;
4) an inclined drainage blind ditch 7 is pre-buried at the contact part of the initial dam and the mountain, a transverse blind ditch 8 is pre-buried at the contact part of the initial dam and the mountain, an upper water inlet of the inclined drainage blind ditch 7 is communicated with the transverse drainage blind ditch 8, and a lower water outlet of the inclined drainage blind ditch 7 is communicated with the drainage mattress 2 of the initial dam;
5) initial dam construction
In the space formed by the upstream seepage drainage arris body 1 of the initial dam, the downstream seepage drainage arris body 1' of the initial dam and the mountains at two sides of the initial dam, the initial dam is built layer by layer from bottom to top and is compacted in layers, and after the upstream seepage drainage arris body 1 of the initial dam is compacted to the height, the method is implemented according to the following steps:
step 1: adopting cohesive soil to pile and compact the first layer of the initial dam, and constructing an anti-seepage slope protection layer 5 on the upstream slope of the first layer of the initial dam;
step 2: adopting cohesive soil to pile and compact the second layer of the initial dam above the first layer of the initial dam, and constructing an anti-seepage slope protection layer 5 on the upstream slope of the second layer of the initial dam;
section 3: adopting cohesive soil to pile and compact the third layer of the initial dam on the second layer of the initial dam, and constructing an anti-seepage slope protection layer 5 on the upstream slope of the third layer of the initial dam;
and 4, step n: and the rest can be done by analogy until the building height reaches the design height.
The anti-seepage slope protection layer 5 is respectively a sand-gravel layer, a rock block layer, a sand-gravel layer, a coarse sand layer, a composite geomembrane and a coarse sand layer from inside to outside; the mass percentage of 13-76 mm grain size fraction in the sand-gravel layer is more than or equal to 95%, the mass percentage of 76-200 mm grain size fraction in the stone layer is more than or equal to 95%, and the mass percentage of 2-13 mm grain size fraction in the coarse sand layer is more than or equal to 95%; in the anti-seepage slope protection layer 5, the thickness of the coarse sand layer is 0.2m, the thickness of the stone layer is 1.5m, and the thickness of the sand gravel layer is 0.2 m.
The composite geomembrane adopted by the invention is formed by sandwiching a layer of geomembrane between two layers of geotextile, and the specification of the geotextile is 300-600 g/m2(ii) a Wherein: the composite geomembrane in the step 1) adopts 300g/m2Geotextile, the composite geomembrane of the step 5) adopts 600g/m2The geotextile is non-woven, and the geomembrane is an HDPE film.
In the step 5), the height of each layer of pile from bottom to top is 2.5m, and the thickness of the layered compaction is not more than 0.8 m.
After the initial dam is built to the designed height, a geomembrane is laid on the surface of the top of the initial dam, and a broken stone protective layer and a dry block stone protective layer are laid on the geomembrane.
After the initial dam is built and tailings are discharged to the level, the construction of the sub-dam 6 is started, and the construction sequence of the sub-dam 6 is as follows:
first, the base layer is leveledConstructing a fine soil layer, a composite geomembrane and a coarse tailings protective layer on the foundation layer from bottom to top respectively to form a first-stage sub-dam; after the first-stage sub-dam construction is finished and tailings are discharged to the level, the second-stage sub-dam construction is carried out after the first-stage sub-dam construction is finished; the construction sequence of the second-stage sub-dam is also flat foundation layer → fine soil layer → composite geomembrane → coarse tailings protective layer, and so on. The mass ratio of 0-0.1 mm grain fraction in the fine grain soil layer is more than or equal to 95%, the mass ratio of 2-13 mm grain fraction in the coarse sand layer is more than or equal to 95%, and the thickness of the fine grain soil layer is 0.2 m; the coarse tailings protective layer is dug and transported from an old tailings pond, and the thickness of the coarse tailings protective layer is 0.2 m; the composite geomembrane is formed by sandwiching a layer of geomembrane between two layers of geotextile, and the specification of the geotextile is 300g/m2The geomembrane is a 1.5mm HDPE membrane.
The stability of the tailing dam is analyzed by adopting a Bishop method; and analyzing the seepage field of the tailing dam by using a finite element method, calculating a node water head, and outputting a water level line by using a computer.

Claims (8)

1. The utility model provides a construction method that is suitable for novel initial dam of upper reaches formula tailing storehouse, sets up dam abutment intercepting ditch on the massif of initial dam both sides, sets up dam foot escape canal (4) at the dam toe of initial dam, the play water end of dam intercepting ditch and dam foot escape canal (4) intercommunication, its characterized in that still adopts following technical scheme:
1) impermeable layer at bottom of dam body at initial laying stage
Clearing the foundation of the initial dam, and paving a fine soil layer, a composite geomembrane, a coarse sand layer, a rock block layer and a sand-gravel layer from bottom to top respectively to form an impermeable layer (9) at the bottom of the initial dam body after clearing the foundation;
2) an upstream drainage and seepage prism (1) and a downstream drainage and seepage prism (1 ') of the initial dam are respectively arranged at the upstream and the downstream of the initial dam, an initial dam drainage and seepage mattress (2) is laid on an impermeable layer (9) at the bottom of the initial dam between the upstream drainage and seepage prism (1) and the downstream drainage and seepage prism (1 ') of the initial dam, and the upstream drainage and seepage prism (1) and the downstream drainage and seepage prism (1 ') of the initial dam are communicated with the initial dam drainage and seepage mattress (2);
3) a vertical drainage blind ditch pipe (3) is pre-buried above the drainage mattress (2) of the initial dam in the initial dam, and the lower end of the vertical drainage blind ditch pipe (3) is communicated with the drainage mattress (2) of the initial dam;
4) an inclined drainage blind ditch (7) is pre-buried at the contact part of the initial dam and the mountain, a transverse blind ditch (8) is pre-buried at the contact part of the initial dam and the mountain, an upper water inlet of the inclined drainage blind ditch (7) is communicated with the transverse drainage blind ditch (8), and a lower water outlet of the inclined drainage blind ditch (7) is communicated with the drainage mattress (2) of the initial dam;
5) initial dam construction
In the space formed by the upstream seepage drainage arris body (1) of the initial dam, the downstream seepage drainage arris body (1') of the initial dam and the mountains at two sides of the initial dam, the initial dam is built layer by layer from bottom to top and is compacted in layers, and after the upstream seepage drainage arris body (1) of the initial dam is compacted to the height, the construction is carried out according to the following steps:
step 1: adopting cohesive soil to pile and compact the first layer of the initial dam, and constructing an anti-seepage slope protection layer (5) on the upstream slope of the first layer of the initial dam;
step 2: adopting cohesive soil to pile and compact the second layer of the initial dam above the first layer of the initial dam, and constructing an anti-seepage slope protection layer (5) on the upstream slope of the second layer of the initial dam;
section 3: adopting cohesive soil to pile and compact the third layer of the initial dam on the second layer of the initial dam, and constructing an anti-seepage slope protection layer (5) on the upstream slope of the third layer of the initial dam;
and 4, step n: and so on.
2. The method for constructing a novel initial dam suitable for the upstream tailings pond as claimed in claim 1, wherein: the mass percentage of 0-0.1 mm grain fraction in the fine grain soil layer in the step 1) is more than or equal to 95%, the mass percentage of 2-13 mm grain fraction in the coarse sand layer is more than or equal to 95%, the mass percentage of 76-200 mm grain fraction in the stone layer is more than or equal to 95%, and the mass percentage of 13-76 mm grain fraction in the sand-gravel layer is more than or equal to 95%.
3. The method for constructing a novel initial dam suitable for the upstream tailings pond as claimed in claim 2, wherein: the anti-seepage slope protection layer (5) is respectively a sand-gravel layer, a rock block layer, a sand-gravel layer, a coarse sand layer, a composite geomembrane and a coarse sand layer from inside to outside; the composite geomembrane is formed by sandwiching a geomembrane between two layers of geotextiles.
4. A method for constructing a novel initial dam for an upstream tailings pond as claimed in claim 3, wherein: in the anti-seepage slope protection layer (5), the mass of 13-76 mm grain fraction in the sand-gravel layer is more than or equal to 95%, the mass of 76-200 mm grain fraction in the rock block layer is more than or equal to 95%, and the mass of 2-13 mm grain fraction in the coarse sand layer is more than or equal to 95%.
5. The method for constructing the novel initial dam suitable for the upstream tailings pond as claimed in claim 4, wherein: in the step 1), the thickness of the fine-grain soil layer is 0.17-0.23 m, the thickness of the coarse sand layer is 0.18-0.24 m, the thickness of the block stone layer is 1.3-1.8 m, and the thickness of the sand gravel layer is 0.18-0.25 m.
6. The method for constructing a novel initial dam suitable for the upstream tailings pond as claimed in claim 5, wherein: in the anti-seepage slope protection layer (5), the thickness of the coarse sand layer is 0.18-0.24 m, the thickness of the stone layer is 1.3-1.8 m, and the thickness of the sand gravel layer is 0.18-0.25 m.
7. A method for constructing a novel initial dam for an upstream tailings pond as claimed in claim 1, 2, 3, 4, 5 or 6, wherein: in the step 5), the height of each layer of piles from bottom to top is 2.2-2.8 m, and the thickness of the layers of piles is not more than 0.8 m.
8. The method for constructing a novel initial dam suitable for the upstream tailings pond of claim 7, wherein: analyzing the stability of the tailing dam by using a Bishop method; and analyzing the seepage field of the tailing dam by using a finite element method, calculating a node water head, and outputting a water level line by using a computer.
CN202110109027.4A 2021-01-27 2021-01-27 Construction method of initial dam suitable for upstream type tailing pond Active CN112921905B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN202110109027.4A CN112921905B (en) 2021-01-27 2021-01-27 Construction method of initial dam suitable for upstream type tailing pond
PCT/CN2021/116002 WO2022160713A1 (en) 2021-01-27 2021-09-01 Method for constructing novel starter dam suitable for upstream tailings pond
ZA2022/04722A ZA202204722B (en) 2021-01-27 2022-04-28 Construction method of new type of starter dam suitable for upstream tailings pond

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110109027.4A CN112921905B (en) 2021-01-27 2021-01-27 Construction method of initial dam suitable for upstream type tailing pond

Publications (2)

Publication Number Publication Date
CN112921905A true CN112921905A (en) 2021-06-08
CN112921905B CN112921905B (en) 2022-03-15

Family

ID=76166808

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110109027.4A Active CN112921905B (en) 2021-01-27 2021-01-27 Construction method of initial dam suitable for upstream type tailing pond

Country Status (3)

Country Link
CN (1) CN112921905B (en)
WO (1) WO2022160713A1 (en)
ZA (1) ZA202204722B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113882491A (en) * 2021-10-14 2022-01-04 中钢集团马鞍山矿山研究总院股份有限公司 Method for reducing infiltration line of tailing pond or phosphogypsum pond
CN114439090A (en) * 2021-10-14 2022-05-06 中钢集团马鞍山矿山研究总院股份有限公司 Interception, drainage and seepage structure for reducing seepage line of tailing pond or phosphogypsum pond
WO2022160713A1 (en) * 2021-01-27 2022-08-04 中钢集团马鞍山矿山研究总院股份有限公司 Method for constructing novel starter dam suitable for upstream tailings pond
CN114892681A (en) * 2022-06-17 2022-08-12 中国恩菲工程技术有限公司 Sand dam, tailing dam and medium-line tailing damming method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115492131B (en) * 2022-08-23 2023-06-13 攀钢集团矿业有限公司 Weak beach embankment earth covering method and device for tail part of tailing pond
CN116432273A (en) * 2023-02-28 2023-07-14 中国电建集团成都勘测设计研究院有限公司 Suspension type seepage-proof design method for foundation dam with strong water permeability and deep coverage layer
CN116090080B (en) * 2023-04-07 2023-10-24 兰州有色冶金设计研究院有限公司 Design method for stepped steeping structure of full-section infiltration line of tailing dam
CN117161636B (en) * 2023-11-03 2024-01-19 矿冶科技集团有限公司 Arrange and ooze nest of tubes system of processing

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1782280A3 (en) * 1989-11-13 1992-12-15 Чepeпobeцkoe Пpoизboдctbehhoe Oб'eдиhehиe "Ammoфoc" Method of clearing slurry sump from pyrite cinders
CN202081409U (en) * 2011-05-31 2011-12-21 内蒙古电力勘测设计院 Initial dam structure of ash storage field built of ash and slag
CN202117155U (en) * 2011-06-11 2012-01-18 昆明有色冶金设计研究院股份公司 Efficient leakage drainage device for inner slope of initial dam of tailing pond
CN104631425A (en) * 2014-12-18 2015-05-20 河南省电力勘测设计院 Method for accelerating seepage eliminating and solidification of coal ash
CN104652492A (en) * 2015-01-09 2015-05-27 中钢集团马鞍山矿山研究院有限公司 Seepage draining system of tailing pond cohesive soil initial dam
CN110656629A (en) * 2019-10-22 2020-01-07 中国恩菲工程技术有限公司 Initial dam of upstream method damming tailings pond
CN111305210A (en) * 2020-03-05 2020-06-19 中钢集团马鞍山矿山研究总院股份有限公司 Ultra-fine grain tailing pond heightening and expanding heap-discharging structure adopting midline method for one-time dam building

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100879917B1 (en) * 2008-06-04 2009-02-26 (주)시엠씨 Tailing stability method of river at mine district
CN104480974B (en) * 2014-12-15 2017-02-01 中冶长天国际工程有限责任公司 Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN105926576B (en) * 2016-04-29 2019-06-18 铜陵有色金属集团股份有限公司冬瓜山铜矿 A method of it builds a dam for upper reaches method tailings alluviation and accelerates Tailings Slurry dewatering and coagulating
CN210946842U (en) * 2019-10-17 2020-07-07 西京学院 Grid beam slope protection device for initial dam of tailing pond
CN112921905B (en) * 2021-01-27 2022-03-15 中钢集团马鞍山矿山研究总院股份有限公司 Construction method of initial dam suitable for upstream type tailing pond

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1782280A3 (en) * 1989-11-13 1992-12-15 Чepeпobeцkoe Пpoизboдctbehhoe Oб'eдиhehиe "Ammoфoc" Method of clearing slurry sump from pyrite cinders
CN202081409U (en) * 2011-05-31 2011-12-21 内蒙古电力勘测设计院 Initial dam structure of ash storage field built of ash and slag
CN202117155U (en) * 2011-06-11 2012-01-18 昆明有色冶金设计研究院股份公司 Efficient leakage drainage device for inner slope of initial dam of tailing pond
CN104631425A (en) * 2014-12-18 2015-05-20 河南省电力勘测设计院 Method for accelerating seepage eliminating and solidification of coal ash
CN104652492A (en) * 2015-01-09 2015-05-27 中钢集团马鞍山矿山研究院有限公司 Seepage draining system of tailing pond cohesive soil initial dam
CN110656629A (en) * 2019-10-22 2020-01-07 中国恩菲工程技术有限公司 Initial dam of upstream method damming tailings pond
CN111305210A (en) * 2020-03-05 2020-06-19 中钢集团马鞍山矿山研究总院股份有限公司 Ultra-fine grain tailing pond heightening and expanding heap-discharging structure adopting midline method for one-time dam building

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张云理: "内坡反滤层式均质土尾矿初期坝", 《工业建筑》 *
谢定松等: "青石壁贮灰场主坝坝面渗水原因分析及加固方案研究", 《水利水电技术》 *
陈星等: "尾矿库土石初期坝坡面沼泽化治理措施", 《长江科学院院报》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022160713A1 (en) * 2021-01-27 2022-08-04 中钢集团马鞍山矿山研究总院股份有限公司 Method for constructing novel starter dam suitable for upstream tailings pond
CN113882491A (en) * 2021-10-14 2022-01-04 中钢集团马鞍山矿山研究总院股份有限公司 Method for reducing infiltration line of tailing pond or phosphogypsum pond
CN114439090A (en) * 2021-10-14 2022-05-06 中钢集团马鞍山矿山研究总院股份有限公司 Interception, drainage and seepage structure for reducing seepage line of tailing pond or phosphogypsum pond
CN114892681A (en) * 2022-06-17 2022-08-12 中国恩菲工程技术有限公司 Sand dam, tailing dam and medium-line tailing damming method

Also Published As

Publication number Publication date
WO2022160713A1 (en) 2022-08-04
CN112921905B (en) 2022-03-15
ZA202204722B (en) 2022-06-29

Similar Documents

Publication Publication Date Title
CN112921905B (en) Construction method of initial dam suitable for upstream type tailing pond
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN207846349U (en) A kind of water blocking earth dam
CN101758058B (en) Method for piling tails without building tails reservoir
CN101021068A (en) Low-level prepressing drainage dynamic consolidating soft soil foundation processing method
CN111593742B (en) Construction method for rectifying and improving tailing pond based on rubble silt squeezing method
CN111441211A (en) Composite roadbed structure made of carbon soft rock and geosynthetic material
CN108060655A (en) A kind of construction and its construction method of the face coombe hydroenergy storage station upper storage reservoir that is ringed on three sides by mountains
CN112921904B (en) A clay initial dam structure for upstream formula tailing storehouse
CN110820720A (en) Water-blocking and drainage-resisting anti-floating construction structure and method
CN113502836A (en) Drainage geogrid and supporting structure and method
CN112195965A (en) Expansive soil cutting retaining wall
CN111827152A (en) Internal drainage structure of edge-covered roadbed and implementation method thereof
CN209338948U (en) A kind of water-permeable pavement structure
CN111648383A (en) Internal drainage method for loess high-fill side slope
CN116856435A (en) Reinforced soil slope structure and construction method thereof
CN216238618U (en) A bridge bearing structure on slope for unstable side slope
CN109653240B (en) Urban residual soil heaping body in ecological restoration engineering and construction method thereof
CN210262542U (en) Road structure for sponge city construction
CN111236269B (en) Layered laying and combining reinforcement method for geotechnical material in airport high slope area
CN108487331B (en) Underground structure anti-floating system integrating gallery drainage and fertilizer groove seepage prevention
CN114000475A (en) Farmland soil drainage system for ditch treatment and land reclamation of loess plateau and construction method thereof
CN210049321U (en) Rainwater regulation instrument suitable for in park mountain forest environment
CN112012170A (en) Combined auxiliary dam of tailing pond and construction method thereof
CN114293421B (en) Carbonaceous shale embankment and filling construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221102

Address after: 243000 No. 666 Xitang Road, Ma'anshan Economic Development Zone, Anhui Province

Patentee after: MAANSHAN Mine Research Institute Co.,Ltd.

Patentee after: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Address before: 243000 No. 666 Xitang Road, Ma'anshan Economic Development Zone, Anhui Province

Patentee before: MAANSHAN Mine Research Institute Co.,Ltd.

Patentee before: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Patentee before: SINOSTEEL MAANSHAN INSTITUTE OF MINING RESEARCH, ENGINEERING INVESTIGATION AND DESIGN Co.,Ltd.