WO2022016720A1 - 基于深基坑内支撑结构的临时通道施工方法 - Google Patents
基于深基坑内支撑结构的临时通道施工方法 Download PDFInfo
- Publication number
- WO2022016720A1 WO2022016720A1 PCT/CN2020/123774 CN2020123774W WO2022016720A1 WO 2022016720 A1 WO2022016720 A1 WO 2022016720A1 CN 2020123774 W CN2020123774 W CN 2020123774W WO 2022016720 A1 WO2022016720 A1 WO 2022016720A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- support
- foundation pit
- temporary
- layer
- ramp
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 49
- 238000009412 basement excavation Methods 0.000 claims abstract description 15
- 239000011150 reinforced concrete Substances 0.000 claims description 11
- 238000005266 casting Methods 0.000 claims description 3
- 239000011378 shotcrete Substances 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 2
- 239000002689 soil Substances 0.000 description 7
- 238000003860 storage Methods 0.000 description 4
- 239000004567 concrete Substances 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G27/00—Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps
Definitions
- the patent of the present invention relates to the technical field of building foundation pit support and earthwork excavation, in particular, to a temporary channel construction method based on a support structure in a deep foundation pit.
- the inner support beam is mainly made of reinforced concrete material, the section size is generally 800mm ⁇ 800mm to 1000mm ⁇ 1000mm, the horizontal spacing is generally 8-16m, and the vertical spacing is generally 4-6m.
- a temporary ramp is usually set to pass the dump truck.
- internal support is used for foundation pit support
- the criss-crossing internal support beams of the multi-channel support system divide the internal space of the foundation pit into small pieces.
- the temporary soil ramp needs to cross the support beam or cross the upper support. Beams are often affected by the location and size distribution of supporting beams and columns. It is difficult to set temporary excavated ramps. Over-excavation and insufficient support are often encountered, which poses a greater safety hazard.
- the slope needs to be adjusted repeatedly, and the position of the temporary ramp needs to be changed according to different excavation areas; during the excavation of the foundation pit in the rainy season, the ramp needs to be repeatedly paved with bricks, slag and stones. , to ensure normal passage, and increase the cost of procurement and transportation.
- the support in the slope closing stage of the ramp, it is necessary to use grading and sub-platform relay excavation at the entrance of the ramp, which requires multiple transfers, or long-arm excavators are used to transfer to the top of the foundation pit, or grab buckets are used for hoisting. It often leads to low efficiency of the entire foundation pit support and earthwork excavation, long construction period and high comprehensive cost.
- the purpose of the present invention is to provide a temporary earthwork passage system based on the support structure in the foundation pit, which aims to solve the problems of low foundation pit support and earthwork excavation efficiency, long construction period and high comprehensive cost in the prior art.
- the present invention is achieved in this way, a temporary channel construction method based on a support structure in a deep foundation pit, comprising the following steps:
- a supporting plate is cast between the supporting beams supported in the first layer to form the inner support in the first layer.
- the support plate includes a transverse support plate, a longitudinal support plate and a surrounding support plate, the surrounding support plate is arranged around the inner side wall of the foundation pit, the transverse support plate and the longitudinal support plate are arranged in a staggered manner, and Both ends of the lateral support plate or the longitudinal support plate are connected to the surrounding support plate.
- a sinking ramp is constructed, the sinking ramp is connected with the entrance and exit of the sinking ramp and the entrance and exit of the top of the foundation pit, and the sinking ramp is used to communicate with the first-level temporary ramp.
- a first-level temporary ramp is constructed on the column pile, and the first-level temporary ramp is a reinforced concrete structure obtained by pouring;
- the first layer of earthwork is excavated to the bottom of the inner support of the second layer, and the excavated earthwork is loaded and transported out through the first-level temporary ramp.
- step S13
- a first-grade slope-changing platform is poured between the support beams supported in the second layer, the first-grade slope-changing platform is a reinforced concrete structure, and the first-grade slope-changing platform is connected to the support plate supported in the second layer. , and the first-grade slope-changing platform is connected to the first-grade temporary ramp.
- the first-level temporary ramp is located above the support beam supported in the second layer.
- the ramp connected to the bottom of the foundation pit is a temporary ramp at the bottom of the foundation pit
- the temporary ramp at the bottom of the foundation pit is a soil slope
- the slope surface of the soil slope is sprayed with concrete protective surface.
- the slope ratio of the first-level temporary ramp and the second-level temporary ramp is not greater than 1:6.
- the width of the first-level temporary ramp, the first-level slope-changing platform, the second-level temporary ramp, and the second-level slope-changing platform is not less than 6m.
- the temporary channel construction method based on the support structure in the deep foundation pit enables large-scale machinery such as muck trucks and dump trucks to be safely Exercise freely in the foundation pit, excavate the foundation pit in sequence, and transport the earth out through the temporary ramp and the variable slope platform, which speeds up the construction progress, and the muck truck can drive through the variable slope platform and the temporary slope.
- the earthwork at the bottom of the foundation pit is directly and quickly transferred to the designated muck storage point, without the need for multiple transfers, saving a lot of time, manpower and financial resources. It solves the problems of low efficiency of foundation pit support and earthwork excavation, long construction period and high comprehensive cost in the prior art.
- FIG. 1 is a schematic flowchart of a temporary channel construction method based on a support structure in a deep foundation pit provided by the present invention
- FIG. 2 is a schematic top view of a temporary channel construction method based on a support structure in a deep foundation pit provided in Embodiment 1 of the present invention
- FIG. 3 is a schematic side view of a temporary channel construction method based on a support structure in a deep foundation pit provided in Embodiment 1 of the present invention
- FIG. 4 is a schematic structural diagram of the inner support of the first layer of the temporary channel construction method based on the inner support structure of the deep foundation pit provided by the present invention.
- FIG. 1 to FIG. 4 it is a preferred embodiment provided by the present invention.
- a temporary channel construction method based on a support 31 structure in a deep foundation pit comprising the following steps:
- the temporary ramp 11 of each level adopts a reinforced concrete structure to ensure its stable bearing; the slope ratio of the temporary ramp 11 of each level is not greater than 1:6 to ensure the smooth running of the dump truck; and , the width of the temporary ramp 11 and the slope-changing platform 21 of each level is not less than 6m.
- the width of the temporary ramp 11 of each level is 7m ⁇ 8m, so as to ensure that two vehicles can pass in one direction or partially in two directions;
- the surface of the temporary ramp 11 is provided with anti-skid measures, such as grooves arranged at intervals on the upper surface of each level of the temporary ramp 11 .
- the temporary ramp 11 and the variable slope platform 21 of each level are made of reinforced concrete structure to ensure their stable bearing. .
- the reinforcement satisfies the structural calculation to ensure that two dump trucks can pass safely when they are fully loaded, and a certain safety reserve is reserved.
- the roads are all cast-in-place reinforced concrete structures. The road conditions are good, the traffic is smooth, and it is not affected by the weather. It is to speed up the unearthed speed of the dump truck.
- the corresponding numerical ordering given in the present invention is only for the convenience of description and to make the structure clear.
- the ordering and the corresponding ordering may be different.
- a transfer platform is provided between the inner support 31 of the second layer and the inner support 31 of the third layer, which will lead to the change of the numerical order, but does not affect the overall structural change of the present invention.
- the temporary ramp 11 and the slope-changing platform 21 are arranged in sequence, so that large-scale machinery such as muck trucks and dump trucks can safely run freely in the foundation pit, and excavate the foundation pit in sequence.
- the earthwork is transported out through the temporary ramp 11 and the slope-changing platform 21, which speeds up the construction progress, and the muck truck can travel to the foundation pit bottom 24 through the slope-changing platform 21 and the temporary ramp 11, and then the foundation pit bottom 24 can be transported.
- the earthwork is directly and quickly transferred to the designated muck storage point, without the need for multiple transfers, saving a lot of time, manpower and financial resources.
- FIG. 2 and FIG. 3 Please refer to FIG. 2 and FIG. 3 in combination, in an embodiment of the present invention, before S11:
- a support plate is cast between the support beams of the inner support 31 of the first layer to form the inner support 31 of the first layer.
- the column piles are used to support the inner support 31 of the first layer and the subsequent inner support 31 of the second layer, etc., to ensure the stable support of the inner support 31 of the first layer and the inner support 31 of the second layer to the side wall of the foundation pit, and to support the support
- the beam was replaced with a support plate, and the original small-section support beam was converted into a large-area bearing plate, which was used as the inner support 31 structure of the foundation pit support, which played a role in strengthening the inner support 31 and improved the foundation pit support. security.
- the support plate includes a lateral support plate 312, a longitudinal support plate 313 and a surrounding support plate 311.
- the surrounding support plate 311 is arranged around the inner side wall of the foundation pit. 312 or both ends of the longitudinal support plate 313 are connected to the surrounding support plate 311 .
- the inner support 31 of the first layer is located at the top of the foundation pit.
- the support plate of the inner support 31 of the first layer can be used as a material storage yard, a processing yard, a finished product storage yard, etc. during the construction of the underground structure, and is used for the site without temporary facilities around the project.
- the project provides a lot of space.
- the surrounding support plate 311 is connected to the top of the foundation pit. Converting the support beam into the inner support 31 plate greatly increases the rigidity of the inner support 31 structure, makes the deformation of the foundation pit within a controllable range, and improves the safety of the foundation pit support project.
- FIG. 1 to FIG. 4 Please refer to FIG. 1 to FIG. 4 in combination, in an embodiment of the present invention, before S12:
- the sinking ramp is connected to the entrance and exit of the sinking ramp and the entrance and exit of the top of the foundation pit, and the sinking ramp is used to connect the first-level temporary ramp 11.
- the first-level temporary ramp 11 In order to meet the slope rate requirements, there are cases where the first-level temporary ramp 11 needs to be extended. However, due to the limited width of the foundation pit, in this case, the entrance of the sinking ramp needs to be opened, and the sinking ramp is used as the first-level temporary ramp. 1111 extension so that its slope meets the requirements. Of course, if the width of the foundation pit is sufficient, there is no need to set the above-mentioned subsidence ramp.
- a first-level temporary ramp 11 is constructed on the column pile, and the first-level temporary ramp 11 is a reinforced concrete structure obtained by pouring;
- the first layer of earthwork is excavated to the bottom of the inner support 31 of the second layer, and the excavated earthwork is loaded and transported out through the first-level temporary ramp 11 .
- the column piles are set under the first-level temporary ramp 11 to ensure stable support for the first-level temporary ramp 11 .
- the first-level temporary ramp 11 is a reinforced concrete structure to ensure safe passage of vehicles.
- reference may be made to the first-level temporary ramp 11 which will not be repeated here.
- step S13
- a first-grade slope-changing platform 21 is poured between the support beams of the inner support 31 in the second layer, the first-grade slope-changing platform 21 is a reinforced concrete structure, and the first-grade slope-changing platform 21 is connected to the support plate of the second layer inner support 31, and, The first-level slope changing platform 21 is connected to the first-level temporary ramp 11 .
- the inner support 31 of the second layer is also provided with a support plate at the corresponding position of the support plate of the inner support 31 of the first layer, so as to support the foundation pit stably.
- the plate 313 is convenient for construction personnel to walk.
- the first-level temporary ramp 11 is located above the support beams of the inner support 31 on the second floor.
- the above-mentioned column piles below the first-level temporary ramp 11 are worn through the support beams of the inner support 31 in the second layer, and the stability of the first-level temporary ramp 11 can be achieved through the support beams of the inner support 31 in the second layer and combined with the column piles. support.
- the structure and construction method of the inner support 31 of the second layer and the inner support 31 of each subsequent layer can be referred to the inner support 31 of the second layer, and will not be repeated here.
- the ramp connected to the foundation pit bottom 24 is the temporary ramp 11 at the foundation pit bottom 24, the temporary ramp 11 at the foundation pit bottom 24 is an earth slope, and the slope surface of the earth slope is sprayed with concrete.
- the stability of its structure can be ensured by directly adopting the form of soil slope, and the surface of the temporary ramp 11 at the bottom of the foundation pit 24 can be sprayed with concrete protective surface , which not only maintains the normal traffic of vehicles, but also saves costs.
- a foundation pit is constructed in a rectangular shape with a perimeter of about 452 m, an excavation area of 11400 m 2 , and an excavation depth of 27 m.
- the lithology of the stratum is mainly filled soil layer, silty soil and sandy cohesive soil layer, and a maximum of four temporary channels are used.
- the construction steps are as follows:
- the third-level slope-changing platform 21 is set on the inner support 31 on the third layer; the second-level slope-changing platform 21 is set between the second-layer inner support 31 and the third-layer inner support 31, 21 is set on the side wall of the foundation pit.
- the secondary slope changing platform 21 needs to be used as a transfer platform, so that the vehicle can run smoothly.
- the second-grade slope changing platform 21, the second-grade temporary ramp 11 and the third-grade temporary ramp 11 described here can be regarded as the second-grade temporary ramp 11 described above, and the third-grade slope changing platform 21 can be regarded as the second-grade temporary ramp 11 described above. Step-by-step ramps.
- a three-level temporary ramp 11 is provided on the side wall of the foundation pit. That is, the third-level temporary ramp 11 is inclined and extended against the side wall of the foundation pit. Combined with the above-mentioned use of the second-level slope changing platform 21 as a transfer platform, the slope rate of the temporary ramp 11 is reduced, and the temporary ramp 11 is increased. length.
- three-level temporary ramps 11 extend on both sides of the second-level slope-changing platform 21 against the side walls of the foundation pit respectively, and the three-level temporary ramps 11 on both sides extend to two third-level temporary ramps 11 on the inner support 31 of the third layer.
- the slope-changing platform 21 is connected to the foundation pit bottom 24 through two four-stage slope-changing platforms 21. In this way, by setting two roads, both sides can be driven as vehicles at the same time, or both sides can be driven as one-way roads respectively, which is convenient for transfer. .
- a transfer platform is not used, and a slope-changing platform 21 is provided for the inner support 31 of each layer.
- the ramp 11 extends in a straight line, which is convenient for the rapid transportation of vehicles.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (10)
- 一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,包括以下步骤:S11,施工第一层内支撑;S12,施工一级临时坡道,同时开挖第一层土方至第二层内支撑底部;S13,施工第二层内支撑,并在第二层内支撑的支撑梁之间浇筑一级变坡平台,所述一级变坡平台连通所述一级临时坡道;S14,施工二级临时坡道,同时开挖第二层土方至第三层内支撑底部;S15,施工第三层内支撑,并在第三层内支撑的支撑梁之间浇筑二级变坡平台,所述二级变坡平台连通所述二级临时坡道;S16,依照S12至S15类推,在基坑内朝下施工,直至开挖至基坑底部。
- 如权利要求1所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,在S11中:在基坑内施工立柱桩;施工第一层内支撑的支撑梁;在所述第一层内支撑的支撑梁之间浇筑支撑板,构成所述第一层内支撑。
- 如权利要求2所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,所述支撑板包括横向支撑板、纵向支撑板以及环绕支撑板,所述环绕支撑板环设于基坑的内侧壁,所述横向支撑板与所述纵向支撑板交错布置,且所述横向支撑板或所述纵向支撑板的两端连接于所述环绕支撑板。
- 如权利要求1至3任意一项所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,在S12之前:在基坑的侧壁设置下沉通道出入口;施工下沉坡道,所述下沉坡道连通所述下沉坡道出入口和基坑顶出入口,所述下沉坡道用于连通所述一级临时坡道。
- 如权利要求1至3任意一项所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,在S12中:在基坑内施工立柱桩;在所述立柱桩上施工一级临时坡道,所述一级临时坡道为通过浇筑得到的钢筋混凝土结构;开挖第一层土方至第二层内支撑底部,通过一级临时坡道将开挖的土方装车外运。
- 如权利要求1至3任意一项所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,S13步骤中:施工第二层内内支撑的支撑梁;在所述第二层内支撑的支撑梁之间浇筑支撑板;在所述第二层内支撑的支撑梁之间浇筑一级变坡平台,所述一级变坡平台为钢筋混凝土结构,所述一级变坡平台连通所述第二层内支撑的支撑板,并且,所述一级变坡平台连通所述一级临时坡道。
- 如权利要求6所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,所述一级临时坡道位于所述第二层内支撑的支撑梁上方。
- 如权利要求1至3任意一项所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,连接至基坑底的坡道为基坑底临时坡道,所述基坑底临时坡道为土坡,土坡的坡面喷射混凝土护面。
- 如权利要求1至3任意一项所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,所述一级临时坡道和所述二级临时坡道的坡率不大于1:6。
- 如权利要求1至3任意一项所述的一种基于深基坑内支撑结构的临时通道施工方法,其特征在于,所述一级临时坡道、所述一级变坡平台、所述二级临时坡道以及所述二级变坡平台的宽度不小于6m。
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010708264.8 | 2020-07-22 | ||
CN202010708264.8A CN111851509A (zh) | 2020-07-22 | 2020-07-22 | 基于深基坑内支撑结构的临时通道施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2022016720A1 true WO2022016720A1 (zh) | 2022-01-27 |
Family
ID=73001913
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2020/123774 WO2022016720A1 (zh) | 2020-07-22 | 2020-10-26 | 基于深基坑内支撑结构的临时通道施工方法 |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN111851509A (zh) |
WO (1) | WO2022016720A1 (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114997072A (zh) * | 2022-07-27 | 2022-09-02 | 中建五局第三建设有限公司 | 基坑水平支撑布置方案确定方法、装置、设备及存储介质 |
CN115162345A (zh) * | 2022-06-27 | 2022-10-11 | 中建八局第三建设有限公司 | 一种长江漫滩超大深基坑土方开挖组织及施工方法 |
CN115262567A (zh) * | 2022-08-02 | 2022-11-01 | 中建市政工程有限公司 | 一种超窄全硬岩深基坑开挖方法 |
CN115387347A (zh) * | 2022-06-06 | 2022-11-25 | 中煤江南建设发展集团有限公司 | 一种基于受限空间的深基坑支护方法 |
CN116717112A (zh) * | 2023-08-11 | 2023-09-08 | 华侨大学 | 一种基于基坑冠梁的施工坡道支撑辅助结构 |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114032910B (zh) * | 2021-07-28 | 2023-10-03 | 中建一局集团华南建设有限公司 | 一种狭小基坑坡道结构及利用该结构的出土方法 |
CN113668548B (zh) * | 2021-07-28 | 2023-01-03 | 中国建筑一局(集团)有限公司 | 狭小基坑坡道支撑结构及施工方法 |
CN114961342A (zh) * | 2022-06-14 | 2022-08-30 | 浙江大学建筑设计研究院有限公司 | 一种利用基坑内已有对撑的出土通道结构 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101647340B1 (ko) * | 2016-02-17 | 2016-08-11 | (주)다원아이티 | 원형 흙막이 구조물 시공 방법 |
WO2019122118A1 (de) * | 2017-12-22 | 2019-06-27 | Meier + Jäggi Ag | Polygonales spriesssystem mit knotenpunkten zur aussteifung von baugruben |
CN110004936A (zh) * | 2019-05-20 | 2019-07-12 | 中建四局土木工程有限公司 | 一种基于深基坑支护结构的出土坡道及施工方法 |
CN110206034A (zh) * | 2019-06-06 | 2019-09-06 | 深圳市工勘岩土集团有限公司 | 环形深基坑开挖施工方法 |
CN110872841A (zh) * | 2019-11-29 | 2020-03-10 | 深圳宏业基岩土科技股份有限公司 | 内支撑基坑土方运输坡道的施工方法 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203846796U (zh) * | 2014-05-27 | 2014-09-24 | 中国建筑第四工程局有限公司 | 一种地下室逆作施工所用的临时出土坡道 |
CN104480944B (zh) * | 2014-11-27 | 2016-04-06 | 中建一局集团第五建筑有限公司 | 出土坡道结构及其施工方法 |
CN106907024A (zh) * | 2017-04-13 | 2017-06-30 | 北京市第三建筑工程有限公司 | 混凝土栈桥与基坑连接结点构造及其施工方法 |
CN110593080A (zh) * | 2019-09-26 | 2019-12-20 | 中建钢构有限公司 | 一种与内支撑体系结合的撑间栈桥系统及施工方法 |
-
2020
- 2020-07-22 CN CN202010708264.8A patent/CN111851509A/zh active Pending
- 2020-10-26 WO PCT/CN2020/123774 patent/WO2022016720A1/zh active Application Filing
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101647340B1 (ko) * | 2016-02-17 | 2016-08-11 | (주)다원아이티 | 원형 흙막이 구조물 시공 방법 |
WO2019122118A1 (de) * | 2017-12-22 | 2019-06-27 | Meier + Jäggi Ag | Polygonales spriesssystem mit knotenpunkten zur aussteifung von baugruben |
CN110004936A (zh) * | 2019-05-20 | 2019-07-12 | 中建四局土木工程有限公司 | 一种基于深基坑支护结构的出土坡道及施工方法 |
CN110206034A (zh) * | 2019-06-06 | 2019-09-06 | 深圳市工勘岩土集团有限公司 | 环形深基坑开挖施工方法 |
CN110872841A (zh) * | 2019-11-29 | 2020-03-10 | 深圳宏业基岩土科技股份有限公司 | 内支撑基坑土方运输坡道的施工方法 |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115387347A (zh) * | 2022-06-06 | 2022-11-25 | 中煤江南建设发展集团有限公司 | 一种基于受限空间的深基坑支护方法 |
CN115162345A (zh) * | 2022-06-27 | 2022-10-11 | 中建八局第三建设有限公司 | 一种长江漫滩超大深基坑土方开挖组织及施工方法 |
CN115162345B (zh) * | 2022-06-27 | 2024-03-01 | 中建八局第三建设有限公司 | 一种长江漫滩超大深基坑土方开挖组织及施工方法 |
CN114997072A (zh) * | 2022-07-27 | 2022-09-02 | 中建五局第三建设有限公司 | 基坑水平支撑布置方案确定方法、装置、设备及存储介质 |
CN115262567A (zh) * | 2022-08-02 | 2022-11-01 | 中建市政工程有限公司 | 一种超窄全硬岩深基坑开挖方法 |
CN116717112A (zh) * | 2023-08-11 | 2023-09-08 | 华侨大学 | 一种基于基坑冠梁的施工坡道支撑辅助结构 |
CN116717112B (zh) * | 2023-08-11 | 2023-12-01 | 华侨大学 | 一种基于基坑冠梁的施工坡道支撑辅助结构 |
Also Published As
Publication number | Publication date |
---|---|
CN111851509A (zh) | 2020-10-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2022016720A1 (zh) | 基于深基坑内支撑结构的临时通道施工方法 | |
CN107558494B (zh) | 一种轨道交通地下车站结构及其建造方法 | |
CN105236275B (zh) | 一种狭窄区域建筑深基坑施工的提土系统及提土方法 | |
CN107059667A (zh) | 门形装配式钢筋混凝土箱型涵洞及其施工方法 | |
CN102995659B (zh) | 超大型地下工程的先中心区结合周边的施工方法 | |
CN113502824B (zh) | 利用栈桥结合深基坑内环状道路快速出土施工方法 | |
CN108611985A (zh) | 特殊地质超重框架桥顶进施工方法 | |
CN107740588B (zh) | 一种城市内狭小地段建筑施工材料的吊装运输方法 | |
CN110206034A (zh) | 环形深基坑开挖施工方法 | |
CN206635599U (zh) | 一种塌方道路的路面抢险支固装置 | |
CN206495233U (zh) | 门形装配式钢筋混凝土箱型涵洞 | |
CN213038380U (zh) | 基于基坑内支撑结构的土方临时通道系统 | |
CN109267749A (zh) | 一种应用于厚淤泥层的混凝土预制模板施工工艺 | |
CN210737607U (zh) | 一种用于逆作法梁板施工的悬挂支撑体系 | |
CN112177042A (zh) | 一种不影响地面交通的轨道交通车站施工方法 | |
NL2031687B1 (en) | Ramp Supporting Structure and Construction Method of Narrow Foundation Pit | |
CN114032910B (zh) | 一种狭小基坑坡道结构及利用该结构的出土方法 | |
CN111608429B (zh) | 装配式超深基坑坡道系统及其施工方法 | |
CN111827705A (zh) | 既有地下车库内扩建井桶状地下车库的方法 | |
CN115506382A (zh) | 一种用于筑岛平台桩板墙的施工方法 | |
CN105298147A (zh) | 超深基坑螺旋下降物料快速运输通道及其施工方法 | |
CN114961335A (zh) | 一种大跨度钢筋混凝土支撑梁的拆除施工方法 | |
CN210797573U (zh) | 一种基于板下滑槽的地下结构内部运输系统 | |
CN112796325A (zh) | 一种双层栈桥式逆作法施工方法 | |
CN207295774U (zh) | 一种轨道交通地下车站结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 20946410 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20946410 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 14.06.2023) |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20946410 Country of ref document: EP Kind code of ref document: A1 |