WO2021109932A1 - Dispositif équipé d'un contrepoids pour levage rapide de panneau de mur en bp - Google Patents

Dispositif équipé d'un contrepoids pour levage rapide de panneau de mur en bp Download PDF

Info

Publication number
WO2021109932A1
WO2021109932A1 PCT/CN2020/132177 CN2020132177W WO2021109932A1 WO 2021109932 A1 WO2021109932 A1 WO 2021109932A1 CN 2020132177 W CN2020132177 W CN 2020132177W WO 2021109932 A1 WO2021109932 A1 WO 2021109932A1
Authority
WO
WIPO (PCT)
Prior art keywords
steel
counterweight
hoisting
lifting
wall panel
Prior art date
Application number
PCT/CN2020/132177
Other languages
English (en)
Chinese (zh)
Inventor
王佳蓓
张宏
梁熊
代保明
陈文玉
吴云孝
冯苛钊
Original Assignee
中建三局第二建设工程有限责任公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from CN201911213445.7A external-priority patent/CN110759222A/zh
Priority claimed from CN201922122929.2U external-priority patent/CN211169496U/zh
Application filed by 中建三局第二建设工程有限责任公司 filed Critical 中建三局第二建设工程有限责任公司
Publication of WO2021109932A1 publication Critical patent/WO2021109932A1/fr

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus

Definitions

  • the invention belongs to the field of construction engineering, and in particular relates to a fast lifting device for PC wall panels with counterweights.
  • Precast concrete structures have the advantages of improving construction efficiency, improving construction quality of construction projects, and reducing environmental pollution, so they have broad development prospects in my country.
  • the hoisting of prefabricated components is the lifeline of on-site construction, and it is also an important factor affecting the construction progress.
  • the purpose of the present invention is to overcome the above-mentioned problems and defects in the prior art and provide a fast lifting device for PC wall panels with counterweights.
  • the device of the present invention solves the difficult problem of prefabricated wall panel hoisting under the cantilevered structure.
  • the hoisting tool is directly hoisted and installed, the hoisting speed is fast on site, and the excavation of the floor slab is avoided.
  • a fast lifting device for PC wall panels with counterweights including I-beams, balanced main steel beams, counterweight steel beams, two steel lifting lugs I, two steel lifting lugs II, counterweights, four A steel wire rope is characterized in that the two ends of the balance main steel beam are welded with an I-beam and a counterweight steel beam, and the two sides of the middle part above the balance main steel beam are symmetrically welded with steel lifting lugs I, and the balance main steel beam is located above The steel lifting lugs II are symmetrically welded on both sides of the end of the counterweight steel beam. A lifting hole is provided on the steel lifting lug II.
  • the counterweight is installed under the counterweight steel beam; the four steel wire ropes are connected to two The steel lifting lugs I and the two steel lifting lugs II are connected together and connected to an external car crane.
  • the I-beam is provided with a plurality of holes for lifting, and it is convenient to select suitable holes as lifting points according to the size of the PC wallboard.
  • the steel lifting lug I is provided with a plurality of holes for lifting, so that it is convenient to select suitable holes for the steel lifting lug I as the lifting point according to the actual situation of the site.
  • the counterweight is a steel counterweight.
  • the invention uses the lever principle (similar to the lifting balance principle of a tower crane) to design a balance lifting device.
  • One end of the hoisting device is an I-beam, which is used to hoist the PC wall.
  • the counterweight is based on the heaviest weight of the PC wall. Whether the total length is conducive to the construction and consider its weight.
  • the car crane is connected with the steel wire rope, and it can be successfully lifted and installed to the PC wall panel installation place of the cantilever structure at one time.
  • the present invention directly adopts mechanical hoisting, the personnel only adjusts the wall panel, no secondary hoisting installation is required, and there is no need to open the second floor slab, and the whole installation process, all loads are directly Acting on the crane, it does not have any impact on the second floor slab, eliminating the risk of cracking and collapse of the floor slab.
  • Figure 1 is a schematic elevation view of the present invention.
  • Figure 2 is a plan view of the present invention.
  • Figure 3 is a schematic diagram of the installation of the present invention.
  • Figure 4 is a schematic diagram of the use of the present invention.
  • the present invention includes I-beam 1, balance main steel beam 2, counterweight steel beam 3, two steel lifting lugs I4, two steel lifting lugs II5, steel
  • the balance weight 6 and the four steel wire ropes 7 are prepared, and the two ends of the balance main steel beam 2 are welded with the I-beam 1 and the counterweight steel beam 3 respectively.
  • the I-beam 1 is provided with a plurality of lifting holes for balance
  • the two sides of the upper middle part of the main steel beam 2 are symmetrically welded with steel lifting lugs I4.
  • the steel lifting lugs I4 are provided with multiple lifting holes.
  • the upper part of the balance main steel beam 2 is located at the end of the counterweight steel beam 3
  • the two sides are symmetrically welded with steel lifting lugs II5.
  • the steel lifting lugs II5 are provided with a lifting hole.
  • the steel counterweight 6 is installed under the counterweight steel beam 3; the four wire ropes 7 are connected to the two steel The lifting lugs I4 and the two steel lifting lugs II5 are connected together and connected to an external car crane.
  • the construction staff can hold the wall panel to control the falling direction of the wall panel and prefabricate it.
  • the hanging board slowly descends here. When it is 20mm away from the top of the pre-embedded steel bar, use the reflector to align the steel bar and the reserved corrugated blind hole. After the corrugated blind hole at the bottom of the prefabricated hanging plate is aligned with the position of the embedded steel bar on the ground, slowly lower the wall panel to make It is in place smoothly. After the prefabricated PC wall panel is in place, install the bolts on the PC steel beam without pre-tightening. According to the previous control line, adjust the horizontal, vertical and elevation of the prefabricated components, and tighten the bolts to the design requirements after all adjustments are within the error range, and then tighten the bolts to the design requirements.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Selon l'invention, un dispositif équipé d'un contrepoids pour le levage rapide d'un panneau de mur en BP présente la structure suivante: une poutre (1) en acier en forme de H et une poutre (3) en acier de contrepoids sont respectivement soudées à deux extrémités d'une poutre principale équilibrée (2) en acier. Des premières pattes (4) de levage en acier sont respectivement soudées symétriquement à deux côtés d'une partie médiane sur la poutre principale équilibrée (2) en acier. Des secondes pattes (5) de levage en acier sont respectivement soudées symétriquement à deux côtés d'une partie d'extrémité de la poutre (3) en acier de contrepoids sur la poutre principale équilibrée (2) en acier. Un trou servant au levage est pratiqué sur la seconde patte (5) de levage en acier. Un contrepoids (6) est monté au-dessous de la poutre (3) en acier de contrepoids. Quatre câbles (7) en acier sont reliés respectivement aux deux premières pattes (4) de levage en acier et aux deux secondes pattes (5) de levage en acier, sont ensuite reliés l'un à l'autre en un ensemble, et sont reliés à une grue externe sur camion. Le panneau de mur en BP est fixé à un point de levage de la poutre (1) en acier en forme de H, et est relié à la section de contrepoids et à la patte de levage sur la section médiane de la poutre principale équilibrée (2) en acier au moyen du câble (7) en acier. La grue sur camion est reliée au câble (7) en acier, soulève des panneaux de mur en BP à un moment donné, et monte le panneau de mur en BP dans une position de montage de panneau de mur en BP présentant une structure en porte-à-faux. Le dispositif de levage facilite la construction, est sûr et fiable, et surmonte efficacement la difficulté de montage d'un panneau de mur en BP sur une structure en porte-à-faux.
PCT/CN2020/132177 2019-12-02 2020-11-27 Dispositif équipé d'un contrepoids pour levage rapide de panneau de mur en bp WO2021109932A1 (fr)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN201911213445.7A CN110759222A (zh) 2019-12-02 2019-12-02 一种带配重的pc墙板快速吊装装置
CN201922122929.2U CN211169496U (zh) 2019-12-02 2019-12-02 一种带配重的pc墙板快速吊装装置
CN201922122929.2 2019-12-02
CN201911213445.7 2019-12-02

Publications (1)

Publication Number Publication Date
WO2021109932A1 true WO2021109932A1 (fr) 2021-06-10

Family

ID=76221423

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/132177 WO2021109932A1 (fr) 2019-12-02 2020-11-27 Dispositif équipé d'un contrepoids pour levage rapide de panneau de mur en bp

Country Status (1)

Country Link
WO (1) WO2021109932A1 (fr)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3675961A (en) * 1970-06-24 1972-07-11 Charles B Wheeler Horizontal load positioner
CN203545437U (zh) * 2013-10-19 2014-04-16 甘肃酒钢集团宏兴钢铁股份有限公司 一种不锈钢冷轧张力辊平衡吊具
CN104140037A (zh) * 2014-07-29 2014-11-12 南京奥捷墙体材料有限公司 墙板吊装系统
CN204265214U (zh) * 2014-11-13 2015-04-15 甘肃酒钢集团宏兴钢铁股份有限公司 一种冷轧抛丸机螺旋输送器检修吊具
CN107879239A (zh) * 2017-11-24 2018-04-06 常德远大建筑工业有限公司 一种外挂墙板吊装方法
CN110759222A (zh) * 2019-12-02 2020-02-07 中建三局第二建设工程有限责任公司 一种带配重的pc墙板快速吊装装置
CN211169496U (zh) * 2019-12-02 2020-08-04 中建三局第二建设工程有限责任公司 一种带配重的pc墙板快速吊装装置

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3675961A (en) * 1970-06-24 1972-07-11 Charles B Wheeler Horizontal load positioner
CN203545437U (zh) * 2013-10-19 2014-04-16 甘肃酒钢集团宏兴钢铁股份有限公司 一种不锈钢冷轧张力辊平衡吊具
CN104140037A (zh) * 2014-07-29 2014-11-12 南京奥捷墙体材料有限公司 墙板吊装系统
CN204265214U (zh) * 2014-11-13 2015-04-15 甘肃酒钢集团宏兴钢铁股份有限公司 一种冷轧抛丸机螺旋输送器检修吊具
CN107879239A (zh) * 2017-11-24 2018-04-06 常德远大建筑工业有限公司 一种外挂墙板吊装方法
CN110759222A (zh) * 2019-12-02 2020-02-07 中建三局第二建设工程有限责任公司 一种带配重的pc墙板快速吊装装置
CN211169496U (zh) * 2019-12-02 2020-08-04 中建三局第二建设工程有限责任公司 一种带配重的pc墙板快速吊装装置

Similar Documents

Publication Publication Date Title
CN110759222A (zh) 一种带配重的pc墙板快速吊装装置
CN201411900Y (zh) 烟囱液压提模装置
CN106193618A (zh) 一种大跨径空中钢结构桁架施工工法
CN110562868B (zh) 超高层建筑单元式玻璃幕墙吊装施工方法
CN105692470A (zh) 内爬式塔吊及其操作方法
CN111395641A (zh) 一种预制混凝土外挂墙板及其施工方法
CN203654702U (zh) 一种钢筋混凝土烟囱施工操作平台
CN114215170A (zh) 一种超高空巨型吊挂多层连体结构提升方法
CN114232805B (zh) 一种超高度大跨度钢混凝土梁吊挂结构的施工方法
CN110905261A (zh) 用于多台堆取料机的超大跨度密闭料场结构及其施工方法
CN112627550A (zh) 超高型单层门型架钢结构吊装建造方法
CN211169496U (zh) 一种带配重的pc墙板快速吊装装置
WO2021109932A1 (fr) Dispositif équipé d'un contrepoids pour levage rapide de panneau de mur en bp
CN107419907A (zh) 一种炼钢塔楼钢结构平台的交错安装焊接方法
CN107675792A (zh) 钢结构悬挑连廊结构及施工方法
CN108894509B (zh) 钢结构装配式住宅预制夹心保温外墙板无外架施工方法
CN109594697B (zh) 超高层内嵌入式单元玻璃幕墙施工方法及其结构
CN214653269U (zh) 一种简易alc墙板吊装设备
CN114382015A (zh) 斜拉桥异形钢主塔竖向转体施工工法
CN108862002B (zh) 一种塔吊盲区超薄钢板剪力墙起吊装置及其吊装方法
CN111188273A (zh) 大跨钢-混组合桥大节段钢桁梁架设系统及施工方法
CN218757009U (zh) 栈桥下低净空的钢换撑结构
CN205346600U (zh) 一种大板梁吊装专用工具
CN215249037U (zh) 装配式外墙吊装和固定机构
CN215331380U (zh) 一种轨道式悬吊平台

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20896250

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20896250

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 20896250

Country of ref document: EP

Kind code of ref document: A1

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established