WO2021103895A1 - 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 - Google Patents
预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 Download PDFInfo
- Publication number
- WO2021103895A1 WO2021103895A1 PCT/CN2020/123928 CN2020123928W WO2021103895A1 WO 2021103895 A1 WO2021103895 A1 WO 2021103895A1 CN 2020123928 W CN2020123928 W CN 2020123928W WO 2021103895 A1 WO2021103895 A1 WO 2021103895A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- expansion joint
- suspension
- embedded
- positioning system
- installation
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/06—Arrangement, construction or bridging of expansion joints
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Definitions
- the invention relates to the field of bridge engineering, and mainly relates to a pre-embedded assembly type expansion joint super-long installation suspension leveling positioning system and a construction method.
- the expansion joints of prestressed cast-in-place box girder are constructed using the "post-embedded method", that is, when the main structure of the concrete box girder is constructed, expansion joints are reserved at the end of each header girder, and after the asphalt paving on the bridge deck is completed Construction is carried out by reverse cutting, and the installation height and smoothness of the expansion joint can be adjusted according to the asphalt finish surface.
- the expansion joint is installed before the bridge deck asphalt paving to complete the pre-embedded component installation, the installation process can overcome the traditional "post-embedded method" construction period long and temporary measures Many, waste of resources, etc., but the pre-embedded components require high installation accuracy, and it is difficult to install and level over long lengths.
- the purpose of the present invention is to solve the need for ultra-long installation of pre-embedded expansion joint pre-embedded components with high precision, difficult to locate and adjust, and meet the high-quality requirements for installation of expansion joints, and is an ultra-long assembled expansion joint pre-embedded component
- High-precision leveling and fixing provide a suspension leveling positioning system and construction method.
- the expansion joint embedded component is fixed under the main beam through the handle suspension rod.
- the handle suspension rod can be rotated to adjust the height and position of the embedded component, which is convenient for the overall precise positioning of the ultra-long embedded component, the installation is firm, and it is not easy to deform, and meets the requirements of the embedded component.
- the installation of components requires high precision to improve the smoothness and durability of the installation of expansion joints.
- the pre-embedded assembly type expansion joint super-long installation suspension leveling and positioning system including the main beam of section steel, four handle suspension rods, six horizontal casters, two bases, and suspension rod nuts. It is characterized by: both ends of the main beam of section steel They are respectively fixed on two bases; each base is equipped with three horizontal casters; the middle of the section steel main beam is provided with two unconnected hollow chutes, and each chute is equipped with two handle suspension rods, and each handle is suspended A suspension nut is arranged at the lower end of the rod, and the suspension nut is connected with the expansion joint embedded component; each horizontal caster uses a concrete beam as a fulcrum.
- the distance between the two hollow chutes is 10cm.
- the section steel main beam is made of channel steel, and the length is 1.5m.
- the handle suspension rod is a handle bolt.
- the base is made of steel plate.
- each suspension leveling and positioning system is arranged above the expansion joint pre-embedded assembly along the bridge transverse joint at a certain interval, and is connected to the expansion joint through the handle suspension rod.
- the suspension rod nut fixed on the inner side of the expansion joint pre-embedded assembly is connected.
- the elevation of the expansion joint pre-embedded assembly is adjusted by rotating the handle suspension rod, and its smoothness and cross slope are adjusted by the horizontal casters fixed at both ends of the steel main beam.
- the suspension leveling and positioning system is installed above the expansion joint pre-embedded assembly along the transverse joint of the bridge at a distance of 2m, and the suspension nut fixed on the expansion joint pre-embedded assembly Align, connect the handle suspension rod with the suspension rod nut fixed on the inner side of the expansion joint embedded component, so that the suspension leveling and positioning system and the expansion joint embedded component form a whole; adjust the height of the expansion joint embedded component by rotating the handle suspension rod, Adjust the smoothness and cross slope of the pre-embedded components of expansion joints by moving the horizontal casters on the concrete beam, and double-check the height and smoothness of the pre-embedded components of expansion joints to ensure that the installation error of the pre-embedded components of expansion joints is ⁇ 2mm;
- the present invention performs positioning and leveling installation by suspending the embedded components, creating conditions for the overall precise installation of the ultra-long embedded components, realizing convenient positioning of the embedded components, firm installation, and resistance to deformation, and meeting the requirements for the installation height of the ultra-long embedded components. Accuracy requirements, improve the smoothness and durability of the expansion joint installation, and ensure the installation quality of the expansion joint.
- Figure 1 is a schematic cross-sectional view of the present invention.
- Figure 2 is a schematic plan view of the present invention.
- the present invention includes a profile steel main beam 1, four handle suspension rods 2, handle bolts 3, six horizontal casters 4, two bases 5, and suspension rod nuts 6, which are characterized by: profile steel
- the two ends of the main beam 1 are respectively fixed on the two bases 5 by handle bolts 3; each base 5 is provided with three horizontal casters 4; the middle of the section steel main beam 1 is provided with two disconnected hollow chutes, two hollows A 10cm partition is reserved between the chutes.
- Two handle suspension rods 2 are installed in each chute, and a suspension nut 6 is set at the lower end of each handle suspension rod 2, and the suspension nut 6 is connected to the expansion joint embedded assembly 8;
- the horizontal casters 4 take the concrete beam 7 as the fulcrum.
- the main beam of the section steel adopts Q235A 10# channel steel with a length of 1.5m
- the handle suspension is an M12 ⁇ 100 handle bolt
- the handle bolt is an M12 ⁇ 60 bolt
- the horizontal caster is 10# horizontal adjustment Wheel
- the suspension nut is an M12 long hole nut
- the base is made of 2mm thick Q235 steel plate.
- the section steel main beam 1 uses Q235A 10# channel steel with a length of 1.5m.
- a M12 screw hole is set 15cm away from the two ends of the section steel main beam 1, and two unconnected hollow slides are set in the middle of the section steel main beam 1. Slot, a 10cm partition is reserved between the two hollow chutes.
- the base 5 is made of a 2mm thick Q235 steel plate into an equilateral triangle with a side length of 15cm.
- a M12 screw hole is set at the center of the triangle, and a horizontal caster 4 is set at each of the three corners of the base 5.
- the profiled steel main beam 1 and the base 5 are connected by M12 handle bolts 3.
- the handle suspension rod 2 uses a 10cm long M12 handle screw, and the suspension nut 6 uses a 10cm long M12 nut; the handle suspension rod 2 is installed in the hollow chute of the steel main beam 1, and each chute is installed two.
- the pre-embedded assembly type expansion joint pre-embedded assembly 8 made by processing the pre-embedded U-shaped steel bar 9 and the expansion joint positioning rib 10, the expansion joint pre-embedded assembly 8 is hoisted to the expansion joint installation slot as a whole, and the plane of the expansion joint pre-embedded assembly 8 is checked Position, ensure that its error is ⁇ 2mm.
- Two suspension rod nuts 6 are symmetrically fixed every 2m along the inner side of the expansion joint embedded component 8.
- the suspension rod nut 6 inside the expansion joint embedded component 8 is connected, and the suspension leveling and positioning system is integrated with the expansion joint embedded component 8; the height of the expansion joint embedded component 8 is adjusted by rotating the handle suspension rod 2, and the horizontal caster 4 Move on the concrete beam 7 to adjust the smoothness and cross-slope of the expansion joint embedded components 8, and double-check the elevation and smoothness of the expansion joint embedded components to ensure that the installation error of the expansion joint embedded components is ⁇ 2mm.
- the handle suspension rod 2 is rotated to release the suspension leveling positioning system and the expansion joint embedded component 8 to complete the positioning and installation of the expansion joint embedded component.
Abstract
Description
Claims (6)
- 预埋装配式伸缩缝超长安装悬吊调平定位系统,包括型钢主梁、四根手柄悬杆、六个水平脚轮、两个基座、悬杆螺母,其特征在于:型钢主梁两端分别固定在两个基座上;每个基座上设置三个水平脚轮;型钢主梁中部设置两条不连通的镂空滑槽,每个滑槽内安装两根手柄悬杆,每个手柄悬杆下端设置一个悬吊螺母,悬吊螺母与伸缩缝预埋组件连接;每个水平脚轮以混凝土梁为支点。
- 根据权利要求1所述的预埋装配式伸缩缝超长安装悬吊调平定位系统,其特征在于:两个镂空滑槽间为10cm。
- 根据权利要求1或2所述的预埋装配式伸缩缝超长安装悬吊调平定位系统,其特征在于:所述型钢主梁采用槽钢制作而成,长度为1.5m。
- 根据权利要求1或2所述的预埋装配式伸缩缝超长安装悬吊调平定位系统,其特征在于:所述手柄悬杆为手柄螺栓。
- 根据权利要求1或2所述的预埋装配式伸缩缝超长安装悬吊调平定位系统,其特征在于:所述基座采用钢板制作而成。
- 利用权利要求1所述的预埋装配式伸缩缝超长安装悬吊调平定位系统的施工方法,其特征在于按以下步骤进行:一、伸缩缝预埋组件安装:将伸缩缝预埋组件整体吊装至伸缩缝安装槽口,核对伸缩缝预埋组件平面位置,并沿伸缩缝预埋组件内侧每2m对称固定两个悬杆螺母;二、悬吊调平定位系统安装:将所述的悬吊调平定位系统按照2m间距沿桥梁横向跨缝设置于伸缩缝预埋组件上方,与固定在伸缩缝预埋组件上的悬杆螺母对齐,将手柄悬杆与固定在伸缩缝预埋组件内侧的悬杆螺母连接,使悬吊调平定位系统与伸缩缝预埋组件形成整体;通过手柄悬杆旋转调整伸缩缝预埋组件高程,通过水平脚轮在混凝土梁上移动调整伸缩缝预埋组件平顺度及横坡,二次复核伸缩缝预埋组件高程及平顺度,确保伸缩缝预埋组件安装误差≤2mm;三、混凝土浇筑:采用C50钢纤维混凝土浇筑箱梁预留伸缩缝槽口,倾倒混凝土,并用30型振捣棒将混凝土振捣密实;混凝土浇筑完毕后,完成表面收光,用塑料薄膜覆盖,并在人孔四周设置警示标志,避免人员踩踏;四、悬吊调平定位系统解除:混凝土初凝后旋转手柄悬杆,解除悬吊调平定位系统与伸缩缝预埋组件连接,完成伸缩缝预埋组件定位安装。
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922106653.9U CN211522857U (zh) | 2019-11-29 | 2019-11-29 | 预埋装配式伸缩缝超长安装悬吊调平定位系统 |
CN201922106653.9 | 2019-11-29 | ||
CN201911206426.1 | 2019-11-29 | ||
CN201911206426.1A CN110777650A (zh) | 2019-11-29 | 2019-11-29 | 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2021103895A1 true WO2021103895A1 (zh) | 2021-06-03 |
Family
ID=76128781
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2020/123928 WO2021103895A1 (zh) | 2019-11-29 | 2020-10-27 | 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 |
Country Status (1)
Country | Link |
---|---|
WO (1) | WO2021103895A1 (zh) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104652324A (zh) * | 2015-02-12 | 2015-05-27 | 汪蔚 | 一种移动式可更换执行头的桥梁缝隙残渣清除装置 |
CN106150055A (zh) * | 2016-08-23 | 2016-11-23 | 天津二建建筑工程有限公司 | 混凝土预埋件精平吊挂安装工作台架及预埋件的安装方法 |
KR20180017844A (ko) * | 2016-08-11 | 2018-02-21 | 김용성 | 신축이음장치 |
CN207347916U (zh) * | 2017-07-06 | 2018-05-11 | 陕西恒宇工程材料有限公司 | 一种托架工装及具有托架安装工装的梳齿型桥梁伸缩装置 |
CN108385515A (zh) * | 2018-03-23 | 2018-08-10 | 刘力源 | 一种装配式多向变位梳齿板桥梁伸缩装置及安装方法 |
CN110016859A (zh) * | 2019-05-05 | 2019-07-16 | 中交德利(广州)控股有限公司 | 一种装配式多向变位桥梁伸缩装置及安装方法 |
CN110777650A (zh) * | 2019-11-29 | 2020-02-11 | 中建三局第二建设工程有限责任公司 | 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 |
-
2020
- 2020-10-27 WO PCT/CN2020/123928 patent/WO2021103895A1/zh active Application Filing
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104652324A (zh) * | 2015-02-12 | 2015-05-27 | 汪蔚 | 一种移动式可更换执行头的桥梁缝隙残渣清除装置 |
KR20180017844A (ko) * | 2016-08-11 | 2018-02-21 | 김용성 | 신축이음장치 |
CN106150055A (zh) * | 2016-08-23 | 2016-11-23 | 天津二建建筑工程有限公司 | 混凝土预埋件精平吊挂安装工作台架及预埋件的安装方法 |
CN207347916U (zh) * | 2017-07-06 | 2018-05-11 | 陕西恒宇工程材料有限公司 | 一种托架工装及具有托架安装工装的梳齿型桥梁伸缩装置 |
CN108385515A (zh) * | 2018-03-23 | 2018-08-10 | 刘力源 | 一种装配式多向变位梳齿板桥梁伸缩装置及安装方法 |
CN110016859A (zh) * | 2019-05-05 | 2019-07-16 | 中交德利(广州)控股有限公司 | 一种装配式多向变位桥梁伸缩装置及安装方法 |
CN110777650A (zh) * | 2019-11-29 | 2020-02-11 | 中建三局第二建设工程有限责任公司 | 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103255717A (zh) | 一种防撞墙的施工方法 | |
CN104631232A (zh) | 一种针对轨道柱式检查坑扣件系统安装的一体化浇筑装置 | |
CN104863060A (zh) | 斜塔模板系统及采用斜塔模板系统的施工方法 | |
CN110777650A (zh) | 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 | |
CN203403438U (zh) | 一种设有保护性施工模圈的检查井盖 | |
CN209723607U (zh) | 可调式整体楼梯踏步模板 | |
CN112012373A (zh) | 一种轻钢龙骨纸面石膏板隔墙及施工方法 | |
WO2021103895A1 (zh) | 预埋装配式伸缩缝超长安装悬吊调平定位系统及施工方法 | |
CN110847464B (zh) | 确保现浇结构顶板水平度的施工和测量方法 | |
CN110863652A (zh) | 预制拼装双节立柱精定位安装方法 | |
CN203795264U (zh) | 一种汽车安全碰撞试验室用牵引跑道 | |
KR20090070852A (ko) | 보차도 경계석 시공방법 및 장치 | |
CN210134654U (zh) | 一种可调节式楼地面控制装置 | |
CN212052342U (zh) | 可伸缩调节的预应力混凝土t梁横向加宽施工辅助工具 | |
CN111502264B (zh) | 一种土木建筑工程施工用的浇筑框架固定模板结构 | |
CN212866842U (zh) | 一种框构式建筑脚手架 | |
CN211522857U (zh) | 预埋装配式伸缩缝超长安装悬吊调平定位系统 | |
CN108625262B (zh) | 一种螺柱及其路面模板微调升降高度施工方法 | |
CN113047111B (zh) | 一种机场跑道角钢装配式道面板结构 | |
CN110107091A (zh) | 一种可调节式楼地面控制装置及使用方法 | |
CN211898503U (zh) | 一种用于塔机的固定节安装的调平工装 | |
CN214195592U (zh) | 一种装配式建筑叠合楼板找平装置 | |
CN212199898U (zh) | 道床底施工模具 | |
CN115419190B (zh) | 一种叠合墙现浇混凝土结合结构的施工方法 | |
CN105463947B (zh) | 无砟轨道板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 20892289 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20892289 Country of ref document: EP Kind code of ref document: A1 |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20892289 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 17.01.2023) |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20892289 Country of ref document: EP Kind code of ref document: A1 |