WO2021093751A1 - Construction method for tunnel in transverse semi-soft and semi-hard section stratum - Google Patents

Construction method for tunnel in transverse semi-soft and semi-hard section stratum Download PDF

Info

Publication number
WO2021093751A1
WO2021093751A1 PCT/CN2020/127977 CN2020127977W WO2021093751A1 WO 2021093751 A1 WO2021093751 A1 WO 2021093751A1 CN 2020127977 W CN2020127977 W CN 2020127977W WO 2021093751 A1 WO2021093751 A1 WO 2021093751A1
Authority
WO
WIPO (PCT)
Prior art keywords
tunnel
construction
section
area
construction area
Prior art date
Application number
PCT/CN2020/127977
Other languages
French (fr)
Chinese (zh)
Inventor
寇海军
宋新海
于建
阎明东
Original Assignee
中铁十九局集团第五工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁十九局集团第五工程有限公司 filed Critical 中铁十九局集团第五工程有限公司
Publication of WO2021093751A1 publication Critical patent/WO2021093751A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Definitions

  • This application relates to the technical field of tunnel construction, and in particular to a tunnel construction method used in transverse semi-soft and semi-hard section stratum.
  • the design must traverse the stratum with large differences in weathering of surrounding rock, especially along the longitudinal direction of the pre-construction tunnel, the surrounding rock on the left and right half of the tunnel face They are Devonian extremely soft carbonaceous slate and weakly weathered dolomitic limestone.
  • the rock formation in the construction area indicated by the left half section 1 is Devonian extremely soft carbonaceous slate
  • the rock formation in the construction area indicated by the right half section 2 is weakly weathered dolomitic limestone.
  • the Devonian ultra-soft carbonaceous slate is a thin-layered and medium-thick layered structure, and its interlayer bonding is poor.
  • the surrounding rock corresponding to the left half of section 1 of the construction site is extremely water-rich and presents a strand-like burst.
  • the strand-shaped water outlet points are shown as A, B, C, and D in the figure.
  • the purpose of this application is to provide a tunnel construction method used in transverse semi-soft and semi-hard section stratum, to solve the current problem of using upper and lower heading pits to reserve core soil method for tunnel construction in transverse semi-soft and semi-hard section stratum.
  • This application During construction, serious landslides occurred, which not only affected the construction work, but also seriously threatened the safety of the construction site.
  • the present application provides a tunnel construction method used in transverse semi-soft and semi-hard section stratum, including:
  • the application further includes: before step S1, performing drainage treatment on the area where water gushing occurs on the palm face, and temporarily supporting the construction area on the back side of the palm face.
  • step S1 in this application further includes:
  • the steel pipe in the pre-embedded advanced pipe shed is used as a drill pipe for drilling.
  • the head end of the steel pipe is connected to the guide plate drill bit, and the tail end of the steel pipe is connected to the drilling rig.
  • the two sections of steel pipes are alternately connected, and the second section of steel pipes are provided with overflow holes;
  • the initial pressure of the grouting pump is controlled to be 0.5 ⁇ 1.0MPa and the final pressure is 2.0 ⁇ 3.0MPa during grouting, so that the spreading radius of the slurry is greater than 45cm .
  • the size of the central angle of the pre-embedded advanced tube roof in this application is 90° ⁇ 120°, and the symmetrical center line of the embedded advanced tube roof deviates from the tunnel toward the left half of the tunnel.
  • the angle of the vertical centerline is 10°-20°; the extrapolation angle of the steel pipe is 10°-30°, and the slurry injected into the steel pipe is a glass double slurry.
  • step S2 in this application further includes:
  • step S21 in this application includes: dividing the left half-section into a first construction area and a second construction area from top to bottom; step S22 includes: adopting the third construction area corresponding to the right half-section
  • the two-step bench construction method excavates the pilot tunnel.
  • step S3 in the present application further includes: the fourth construction area and the fifth construction area between the temporary invert at the lower part of step S2 and the pre-constructed invert.
  • the fourth construction area and the fifth construction area are correspondingly distributed on the left half-section and the right half-section respectively, and the lower side of the fourth construction area and the fifth construction area is the sixth construction of pre-inverted arch area.
  • the pilot tunnel excavated in the second construction area described in this application lags behind the pilot tunnel excavated in the first construction area by a first preset distance; the pilot tunnel excavated in the third construction area A second preset distance behind the pilot tunnel excavated in the second construction area; the pilot tunnel excavated in the fourth construction area lags behind the pilot tunnel excavated in the third construction area by a third preset distance; The pilot tunnel excavated in the fifth construction area lags behind the pilot tunnel excavated in the fourth construction area by a fourth preset distance.
  • both the temporary intermediate wall support and the permanent support arch are inserted with retraction anchor pipes.
  • step S2 of the present application the horizontal distance between the tunnel face and the closed section of the inverted arch along the longitudinal direction of the tunnel is less than 35 meters; in step S3, when the inverted arch is excavated once, the horizontal distance along the longitudinal direction of the tunnel is Less than 3m.
  • the tunnel construction method provided by this application when constructing the stratum with the Devonian extremely soft carbonaceous slate and weakly weathered dolomitic limestone on the left and right half of the cross-section respectively, the pre-embedded pipe shed is used in advance. Reinforce the water bulging, soft rock, and mud outburst on the left side of the tunnel face to ensure the stability of the stratum in front of the tunnel face. During the construction, the left half section and the right half section were carried out in turn by the middle partition method.
  • Construction and establishment of a temporary closed support structure, and finally an inverted arch which effectively avoids the collapse of the surrounding rock caused by the concentration of bias stress or the water softening of the surrounding rock, and can effectively resist the settlement and convergent deformation of the weak surrounding rock, thereby ensuring The normal progress of the construction work and the safety of the construction site.
  • Figure 1 is a schematic diagram of the surrounding rock distribution on the face of the tunnel currently facing during tunnel construction
  • FIG. 2 is a schematic diagram of a cross-sectional structure of a tunnel excavated according to an embodiment of the application
  • FIG. 3 is a schematic diagram of a top view structure of a tunnel excavation shown in an embodiment of the application;
  • FIG. 4 is a flowchart of a tunnel construction method shown in an embodiment of the application.
  • Fig. 5 is a flowchart of further construction of step S1 shown in an embodiment of the application.
  • Fig. 6 is a flowchart of further construction of step S2 shown in an embodiment of the application.
  • connection should be understood in a broad sense, unless otherwise clearly specified and limited.
  • it can be a fixed connection or a detachable connection.
  • Connected or integrally connected it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication between two components.
  • connection should be understood in a broad sense, unless otherwise clearly specified and limited.
  • it can be a fixed connection or a detachable connection.
  • Connected or integrally connected it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication between two components.
  • the specific meanings of the above-mentioned terms in this application can be understood under specific circumstances.
  • an embodiment of the present application provides a tunnel construction method used in transverse semi-soft and semi-hard section stratum, including:
  • the tunnel construction method shown in this embodiment is composed of Devonian extremely soft carbonaceous slate and weakly weathered dolomitic limestone in the left half and right half of the cross-section 1, respectively.
  • the pre-embedded advanced pipe shed 13 is used to reinforce the water, soft rock, and mud bursting parts on the left side of the tunnel face in advance to ensure the stability of the stratum in front of the tunnel face, and the construction is in progress.
  • the middle partition method to construct the left half-section 1 and the right half-section 2 respectively, and establish a temporary closed support structure, which can ensure the stability of the initial support structure, and can be further used for permanent construction at the bottom of the tunnel.
  • Supporting arch frame and composite lining which effectively avoids the problem of collapse caused by the concentration of bias stress or the softening of the surrounding rock in contact with water, and can effectively resist the settlement and convergence deformation of the weak surrounding rock, thereby ensuring the normal progress of construction operations And the safety of the construction site.
  • this embodiment further includes: before step S1, performing drainage treatment on the area where water gushing occurs on the palm face, and temporarily supporting the construction area on the back side of the palm face.
  • the drainage treatment on the area where water gushing occurs on the tunnel face is mainly aimed at the water gushing on the left half section 1. Due to the serious collapse and water gushing in the left half of the section 1, firstly, the face of the face was closed with plain sprayed C25 concrete, and the muck was back-pressured to backfill the arch toe of the excavation and support section behind the face, and only the arch foot was reserved. The space for excavation and construction, the purpose of this move is to prevent the collapse from continuing to expand.
  • the construction method of the temporary support is as follows: the temporary invert and the hoop arch are aligned and arranged so that they can be closed into a ring and jointly bear the stress of the surrounding rock of the vault.
  • the temporary invert is made of I20a steel. , Arranged in sequence along the longitudinal direction of the tunnel, with an interval of 1.2m.
  • step S1 in this embodiment further includes:
  • the steel pipe embedded in the advanced pipe shed is used as a drill pipe for drilling.
  • the head end of the steel pipe is connected to the guide plate drill bit, and the tail end of the steel pipe is connected to the drilling rig.
  • the steel pipe is drilled from the first section of the steel pipe to the second section.
  • the steel pipes are alternately connected, and there is an overflow hole on the second section of the steel pipe;
  • the initial pressure of the grouting pump is controlled to be 0.5 ⁇ 1.0MPa and the final pressure is 2.0 ⁇ 3.0MPa during grouting, so that the spreading radius of the slurry is greater than 45cm .
  • the diameter of the steel pipe is 108mm
  • the wall thickness is 6mm
  • the 4m long first section of steel pipe is alternately connected with the 6m long second section of steel pipe.
  • the first section of steel pipe and the second section of steel pipe are connected by a thread.
  • grouting is injected into the alternately connected steel pipes, which can form an advanced supporting rigid body in the corresponding stratum.
  • the injected grout is a grout that is easy to set and harden.
  • the vertical centerline of the tunnel is set to K1
  • the symmetrical centerline of the embedded advanced tube shed 13 is K2
  • the size of the central angle ⁇ of the embedded advanced tube shed 13 is It is 90° ⁇ 120°
  • the angle ⁇ of the symmetrical center line K2 of the pre-embedded leading pipe shed 13 from the vertical center line K1 of the tunnel towards the left half section 1 is 10° ⁇ 20°
  • the extrapolation angle of the steel pipe is 10° ⁇
  • the slurry injected into the steel pipe is preferably a glass double slurry.
  • the pre-embedded advanced pipe shed 13 is formed by arranging 45 steel pipes along the vault (circumferential direction) of the tunnel.
  • the length of the steel pipes is 30m, and the circumferential spacing of the steel pipes is 30cm; in actual drilling
  • the extrapolation angle of the steel pipe is 10° ⁇ 30°
  • the YZB-5 type double-slurry grouting pump is used to fill the steel pipe with double-glass grout.
  • step S2 in this embodiment further includes:
  • the full-section tunnel face is divided into the first construction area, the second construction area, the third construction area, the fourth construction area, the fifth construction area, and the sixth construction area.
  • the corresponding numbers of the six construction areas are 1, 2, 3, 4, 5 and 6.
  • the second construction area for mechanical excavation and construction of the pilot tunnel, spray 8cm thick concrete to close the corresponding tunnel face in this area, and install steel mesh on the corresponding arch in the middle left after the slag is discharged
  • the first permanent support arch 3 is butted along the axial direction with the second permanent support arch 6, the second temporary intermediate wall support 8 and the first temporary intermediate wall support 5 are butted in the vertical direction, and then the first temporary invert 4 is removed.
  • the first permanent support arch 3, the second permanent support arch 6, the second temporary invert 7, the second temporary intermediate wall support 8 and the first temporary intermediate wall support 5 constitute a closed support structure.
  • the pilot tunnel is excavated in layers by dividing multiple construction areas, and immediately after excavation, a closed ring supporting structure is constructed, which further effectively avoids the stress due to bias.
  • this embodiment uses a two-step step construction method to excavate the pilot tunnel for the third construction area (upper right).
  • the weak blasting method can be used to excavate the pilot tunnel when the two-step construction is carried out.
  • Install the third permanent support arch 9 on the corresponding arch on the upper right the first spray is closed, and the first temporary intermediate wall support 5 and the second temporary intermediate wall support 8 are removed, facing the second temporary invert 7
  • the right half section 2 is extended so that the first permanent supporting arch 3, the second permanent supporting arch 6, the second temporary invert 7 and the third permanent supporting arch 9 form a closed supporting structure, Even if the supporting arch frame of the upper half of the entire tunnel is closed into a ring with the second temporary invert 7, the stability of the initial support is ensured.
  • the selection is also selected
  • the fourth construction area (lower left) is micro-blasted, the pilot tunnel is excavated, and after the slag is discharged, the fourth permanent support arch 10 is installed, and the first spray is closed; then, the fifth construction area (lower right) is selected for micro-blasting. After blasting, excavating the pilot tunnel, and after the slag is discharged, the fifth permanent support arch 11 is installed, and the first spray is closed.
  • the fourth construction area and the fifth construction area are located at the temporary elevation when the overall closed support structure is initially established. The underside of the arch.
  • the sixth construction area (lower bottom) is selected for micro-blasting and excavation.
  • the sixth permanent supporting arch 12 is installed, so as to complete the full-section arch closed into a ring, and first spray closed.
  • the excavation guide shall be carried out in a staggered manner. After excavation, spray 8cm thick concrete to seal the face of the corresponding area.
  • the pilot tunnel excavated in the second construction area in this embodiment lags behind the pilot tunnel excavated in the first construction area by the first preset distance, and the first preset distance can be set to 3m; third The pilot tunnel excavated in the construction area lags behind the second preset distance of the pilot tunnel excavated in the second construction area, and the second preset distance can be set to 5m; the pilot tunnel excavated in the fourth construction area lags behind the third construction area
  • the third preset distance of the excavated pilot tunnel, the third preset distance can be set to 20m;
  • the pilot tunnel excavated in the fifth construction area lags behind the fourth preset distance of the pilot tunnel excavated in the fourth construction area, and the fourth preset distance
  • the preset distance can be set to 3m, the pilot tunnel excavated in the sixth construction area lags the fifth preset distance of the pilot tunnel excavated in the fifth construction area, and the fifth preset distance can be set to 4m.
  • the anchor pipes with reduced feet are inserted at the temporary intermediate wall supporting and each permanent supporting arch.
  • this embodiment takes into account that the tunnel design adopts an elliptical force-bearing section, and the part above the center of the tunnel is in the best force. Therefore, the bottom surface of the middle step obtained from the construction of the left middle part is set on the horizontal axis of the center of the circle. Maximize the stability of the primary support structure. In order to meet the requirements of mechanized construction, it is determined that the height of the upper step obtained by the construction of the upper left part of the left half section 1 is set to 3.8m, the height of the middle step is set to 2.6m, and the right half section 2 is set to the height of the upper step during the two-step construction.
  • the closed invert section refers to the section where the full-section arch frame is initially closed into a ring.

Abstract

A construction method for a tunnel in a transverse semi-soft and semi-hard section stratum, comprising: S1, constructing a pre-buried advanced pipe shed (13) in the area on a tunnel face corresponding to a tunnel arch portion; S2, constructing a soft-rock-distribution left half section (1) and a hard-rock-distribution right half section (2) in sequence by using a center diaphragm method, after excavation is completed, dismantling temporary center diaphragm supports (5, 8), and ensuring that permanent support arch frames (3, 6, 9) respectively constructed on the upper portions of the left half section (1) and the right half section (2) along an arc roof and temporary inverts (7) on the lower portions form a closed support structure; and S3, performing invert excavation, constructing permanent support arch frames (10, 11, 12) at the bottom of the tunnel, dismantling the temporary inverts (7), and constructing a composite lining. The construction method is simple, effectively solves the problem of proneness to collapse during semi-soft and semi-hard section stratum construction, and ensures the normal progress of construction operations and the safety of the construction site.

Description

一种用于横向半软半硬断面地层中的隧道施工方法Tunnel construction method used in transverse semi-soft and semi-hard section stratum
相关申请的交叉引用Cross-references to related applications
本申请要求于2019年11月11日提交的申请号为201911097059.6,发明名称为“一种用于横向半软半硬断面地层中的隧道施工方法”的中国专利申请的优先权,其通过引用方式全部并入本文。This application claims the priority of the Chinese patent application filed on November 11, 2019 with the application number 201911097059.6 and the title of the invention "A tunnel construction method for transverse semi-soft and semi-hard section stratum", which is by reference All are incorporated into this article.
技术领域Technical field
本申请涉及隧道施工技术领域,尤其涉及一种用于横向半软半硬断面地层中的隧道施工方法。This application relates to the technical field of tunnel construction, and in particular to a tunnel construction method used in transverse semi-soft and semi-hard section stratum.
背景技术Background technique
在隧道施工时,由于受到施工条件及施工成本的限制,在设计上必须穿越围岩风化差异性较大的地层,尤其是顺着预施工的隧道纵向,掌子面左、右半边的围岩分别为泥盆系极软炭质板岩和弱风化白云质灰岩。参见图1,左半断面1示意的施工区域的岩层为泥盆系极软炭质板岩,右半断面2示意的施工区域的岩层为弱风化白云质灰岩。泥盆系极软炭质板岩为薄层状和中厚层状构造,其层间结合性差,并在施工现场左半断面1对应的围岩极为富水,并呈现股状突涌,其股状出水点分别如图中的A、B、C、D所示。During the tunnel construction, due to the constraints of construction conditions and construction costs, the design must traverse the stratum with large differences in weathering of surrounding rock, especially along the longitudinal direction of the pre-construction tunnel, the surrounding rock on the left and right half of the tunnel face They are Devonian extremely soft carbonaceous slate and weakly weathered dolomitic limestone. Referring to Figure 1, the rock formation in the construction area indicated by the left half section 1 is Devonian extremely soft carbonaceous slate, and the rock formation in the construction area indicated by the right half section 2 is weakly weathered dolomitic limestone. The Devonian ultra-soft carbonaceous slate is a thin-layered and medium-thick layered structure, and its interlayer bonding is poor. The surrounding rock corresponding to the left half of section 1 of the construction site is extremely water-rich and presents a strand-like burst. The strand-shaped water outlet points are shown as A, B, C, and D in the figure.
当前,在上述地层中进行隧道施工时,采用上、下导坑预留核心土法开挖,但该施工方法导致上台阶凌空面过大,左侧泥盆系炭质板岩遇水软化失稳,掌子面掉块、滑塌现象十分严重,其中,涂泥滑塌位置如图1中的P处所示。这不仅难以确保正常地进行施工作业,还严重威胁到施工现场的安全。At present, when tunnel construction is carried out in the above-mentioned strata, the upper and lower pilot pits are used to excavate the core soil method, but this construction method causes the upper step volley surface to be too large, and the Devonian carbonaceous slate on the left is softened by water. It is stable, and the phenomenon of block-dropping and slumping of the tunnel face is very serious. Among them, the position of the slippage of the smear is shown at P in Figure 1. This is not only difficult to ensure normal construction operations, but also seriously threatens the safety of the construction site.
发明内容Summary of the invention
(一)要解决的技术问题(1) Technical problems to be solved
本申请的目的是提供一种用于横向半软半硬断面地层中的隧道施工方法,用以解决当前在横向半软半硬断面地层中,采用上、下导坑预留核心土法进行隧道施工时,出现严重的滑塌现象,不仅影响到施工作业,还 严重威胁到施工现场安全的问题。The purpose of this application is to provide a tunnel construction method used in transverse semi-soft and semi-hard section stratum, to solve the current problem of using upper and lower heading pits to reserve core soil method for tunnel construction in transverse semi-soft and semi-hard section stratum. During construction, serious landslides occurred, which not only affected the construction work, but also seriously threatened the safety of the construction site.
(二)技术方案(2) Technical solution
为了解决上述技术问题,本申请提供了一种用于横向半软半硬断面地层中的隧道施工方法,包括:In order to solve the above technical problems, the present application provides a tunnel construction method used in transverse semi-soft and semi-hard section stratum, including:
S1,对掌子面上对应隧道拱部区域施作预埋超前管棚;S1, pre-embedded and advanced pipe sheds are applied to the tunnel arch area corresponding to the tunnel face;
S2,采用中隔壁法依次对软岩分布的左半断面和硬岩分布的右半断面进行施工,开挖完成后,拆除临时中隔壁支护,并确保在左半断面、右半断面的上部分别沿拱顶施作的永久支护拱架与下部的临时仰拱构成封闭支护结构;S2. Use the middle partition method to construct the soft rock distribution on the left half of the section and the hard rock distribution on the right half of the section in turn. After the excavation is completed, remove the temporary middle partition support, and ensure that the upper part of the left half section and the right half section The permanent supporting arch frame constructed along the vault and the temporary invert at the lower part form a closed supporting structure;
S3,进行仰拱开挖,施作隧道底部的永久支护拱架,拆除临时仰拱,并施作复合式衬砌。S3. Carry out invert excavation, construct permanent arch support at the bottom of the tunnel, remove temporary invert, and construct composite lining.
在一个实施例中,本申请中还包括:在步骤S1之前,对掌子面上发生涌水的区域进行排水处理,并对掌子面后侧的施工区域施作临时支撑。In one embodiment, the application further includes: before step S1, performing drainage treatment on the area where water gushing occurs on the palm face, and temporarily supporting the construction area on the back side of the palm face.
在一个实施例中,本申请中步骤S1进一步包括:In an embodiment, step S1 in this application further includes:
S11,将所述预埋超前管棚中的钢管作为钻杆进行钻进,钢管的首端连接导向板钻头,钢管的尾端连接钻机,其中,钢管在钻进时由第一段钢管与第二段钢管交替连接,第二段钢管上设有溢浆孔;S11, the steel pipe in the pre-embedded advanced pipe shed is used as a drill pipe for drilling. The head end of the steel pipe is connected to the guide plate drill bit, and the tail end of the steel pipe is connected to the drilling rig. The two sections of steel pipes are alternately connected, and the second section of steel pipes are provided with overflow holes;
S12,拆除钻机,并将注浆泵与钢管的尾端相连接,注浆泵在注浆时控制初压为0.5~1.0MPa,终压为2.0~3.0MPa,以使得浆液的扩散半径大于45cm。S12. Remove the drilling rig and connect the grouting pump to the end of the steel pipe. The initial pressure of the grouting pump is controlled to be 0.5~1.0MPa and the final pressure is 2.0~3.0MPa during grouting, so that the spreading radius of the slurry is greater than 45cm .
在一个实施例中,本申请中所述预埋超前管棚施作的圆心角的大小为90°~120°,所述预埋超前管棚的对称中心线朝向所述左半断面偏离隧道的竖直中心线的角度为10°~20°;所述钢管的外插角度为10°~30°,所述钢管中加注的浆液为玻璃双浆液。In one embodiment, the size of the central angle of the pre-embedded advanced tube roof in this application is 90°~120°, and the symmetrical center line of the embedded advanced tube roof deviates from the tunnel toward the left half of the tunnel. The angle of the vertical centerline is 10°-20°; the extrapolation angle of the steel pipe is 10°-30°, and the slurry injected into the steel pipe is a glass double slurry.
在一个实施例中,本申请中步骤S2进一步包括:In an embodiment, step S2 in this application further includes:
S21,将所述左半断面从上往下划分为多层施工区域,并按照划分的施工区域逐层向下开挖导洞,每层导洞出渣后,设置对应构成封闭支护结构的永久支护拱架、临时仰拱和临时中隔壁支护;S21: Divide the left half-section from top to bottom into multi-layer construction areas, and excavate pilot tunnels layer by layer according to the divided construction areas. After the slag is discharged from the pilot tunnels on each layer, a corresponding closed supporting structure is installed. Permanent support arch, temporary invert and temporary intermediate wall support;
S22,采用台阶施工法对右半断面对应的区域开挖导洞。S22, using the step construction method to excavate a pilot tunnel in the area corresponding to the right half of the section.
在一个实施例中,本申请中步骤S21包括:将所述左半断面从上往下 划分为第一施工区域和第二施工区域;步骤S22包括:在右半断面对应的第三施工区域采用两台阶的台阶施工法开挖导洞。In one embodiment, step S21 in this application includes: dividing the left half-section into a first construction area and a second construction area from top to bottom; step S22 includes: adopting the third construction area corresponding to the right half-section The two-step bench construction method excavates the pilot tunnel.
在一个实施例中,本申请中步骤S3还包括:对位于步骤S2中位于下部的临时仰拱与预施作的仰拱之间的第四施工区域和第五施工区域,以前后交错施工的方式开挖导洞,并在出渣后,设置相应的永久支护拱架;In one embodiment, step S3 in the present application further includes: the fourth construction area and the fifth construction area between the temporary invert at the lower part of step S2 and the pre-constructed invert. Excavate the pilot tunnel in a way, and install the corresponding permanent support arch after the slag is discharged;
所述第四施工区域、所述第五施工区域分别对应分布在左半断面和右半断面上,所述第四施工区域、所述第五施工区域的下侧为预施作仰拱的第六施工区域。The fourth construction area and the fifth construction area are correspondingly distributed on the left half-section and the right half-section respectively, and the lower side of the fourth construction area and the fifth construction area is the sixth construction of pre-inverted arch area.
在一个实施例中,本申请中所述第二施工区域开挖的导洞滞后于所述第一施工区域开挖的导洞第一预设距离;所述第三施工区域开挖的导洞滞后于所述第二施工区域开挖的导洞第二预设距离;所述第四施工区域开挖的导洞滞后于所述第三施工区域开挖的导洞第三预设距离;所述第五施工区域开挖的导洞滞后于所述第四施工区域开挖的导洞第四预设距离。In one embodiment, the pilot tunnel excavated in the second construction area described in this application lags behind the pilot tunnel excavated in the first construction area by a first preset distance; the pilot tunnel excavated in the third construction area A second preset distance behind the pilot tunnel excavated in the second construction area; the pilot tunnel excavated in the fourth construction area lags behind the pilot tunnel excavated in the third construction area by a third preset distance; The pilot tunnel excavated in the fifth construction area lags behind the pilot tunnel excavated in the fourth construction area by a fourth preset distance.
在一个实施例中,本申请中在所述临时中隔壁支护与所述永久支护拱架处均插装有缩脚锚管。In one embodiment, in the present application, both the temporary intermediate wall support and the permanent support arch are inserted with retraction anchor pipes.
在一个实施例中,本申请中步骤S2中,掌子面距离仰拱封闭段沿隧道纵向的水平距离小于35米;步骤S3中,在对仰拱一次开挖时,沿隧道纵向的水平距离小于3m。In one embodiment, in step S2 of the present application, the horizontal distance between the tunnel face and the closed section of the inverted arch along the longitudinal direction of the tunnel is less than 35 meters; in step S3, when the inverted arch is excavated once, the horizontal distance along the longitudinal direction of the tunnel is Less than 3m.
(三)技术效果(3) Technical effects
本申请提供的隧道施工方法,在对左、右半断面分别为泥盆系极软炭质板岩和弱风化白云质灰岩的地层进行施工时,通过施作预埋超前管棚的方式提前对掌子面左侧鼓水、软岩、突泥部位进行加固,确保了掌子面前方地层的稳定性,并在进行施工时,采用中隔壁法依次对左半断面和右半断面分别进行施工,并建立临时封闭支护结构,最后再施作仰拱,如此有效避免了因偏压应力集中或围岩遇水软化导致的坍塌问题,且能有效抵抗软弱围岩的沉降和收敛变形,从而确保了施工作业的正常进行及施工现场的安全性。The tunnel construction method provided by this application, when constructing the stratum with the Devonian extremely soft carbonaceous slate and weakly weathered dolomitic limestone on the left and right half of the cross-section respectively, the pre-embedded pipe shed is used in advance. Reinforce the water bulging, soft rock, and mud outburst on the left side of the tunnel face to ensure the stability of the stratum in front of the tunnel face. During the construction, the left half section and the right half section were carried out in turn by the middle partition method. Construction and establishment of a temporary closed support structure, and finally an inverted arch, which effectively avoids the collapse of the surrounding rock caused by the concentration of bias stress or the water softening of the surrounding rock, and can effectively resist the settlement and convergent deformation of the weak surrounding rock, thereby ensuring The normal progress of the construction work and the safety of the construction site.
附图说明Description of the drawings
为了更清楚地说明本申请的实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地, 下面描述中的附图是本申请的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly describe the embodiments of the present application or the technical solutions in the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the drawings in the following description These are some embodiments of the present application. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative work.
图1为当前在隧道施工时所面临的掌子面围岩分布的示意图;Figure 1 is a schematic diagram of the surrounding rock distribution on the face of the tunnel currently facing during tunnel construction;
图2为本申请实施例所示的隧道开挖的断面结构示意图;2 is a schematic diagram of a cross-sectional structure of a tunnel excavated according to an embodiment of the application;
图3为本申请实施例所示的隧道开挖的俯视结构示意图;FIG. 3 is a schematic diagram of a top view structure of a tunnel excavation shown in an embodiment of the application;
图4为本申请实施例所示的隧道施工方法的流程图;FIG. 4 is a flowchart of a tunnel construction method shown in an embodiment of the application;
图5为本申请实施例所示的步骤S1进一步施工的流程图;Fig. 5 is a flowchart of further construction of step S1 shown in an embodiment of the application;
图6为本申请实施例所示的步骤S2进一步施工的流程图。Fig. 6 is a flowchart of further construction of step S2 shown in an embodiment of the application.
图中:1、左半断面;2、右半断面;3、第一永久支护拱架;4、第一临时仰拱;5、第一临时中隔壁支护;6、第二永久支护拱架;7、第二临时仰拱;8、第二临时中隔壁支护;9、第三永久支护拱架;10、第四永久支护拱架;11、第五永久支护拱架;12、第六永久支护拱架;13、预埋超前管棚;14、缩脚锚管。In the figure: 1. Left half section; 2. Right half section; 3. First permanent support arch; 4. First temporary inverted arch; 5. First temporary intermediate wall support; 6. Second permanent support Arch; 7. The second temporary invert; 8. The second temporary intermediate wall support; 9. The third permanent support arch; 10. The fourth permanent support arch; 11. The fifth permanent support arch ; 12. The sixth permanent support arch; 13. The pre-embedded advanced pipe shed; 14. The anchor pipe with reduced foot.
具体实施方式Detailed ways
为使本申请实施例的目的、技术方案和优点更加清楚,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本申请一部分实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本申请保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be described clearly and completely in conjunction with the accompanying drawings in the embodiments of the present application. Obviously, the described embodiments It is a part of the embodiments of the present application, but not all of the embodiments. Based on the embodiments in this application, all other embodiments obtained by a person of ordinary skill in the art without creative work shall fall within the protection scope of this application.
在本申请的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本申请中的具体含义。In the description of this application, it should be noted that the terms "installation", "connection", and "connection" should be understood in a broad sense, unless otherwise clearly specified and limited. For example, it can be a fixed connection or a detachable connection. Connected or integrally connected; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal communication between two components. For those of ordinary skill in the art, the specific meanings of the above-mentioned terms in this application can be understood under specific circumstances.
参见图4,本申请实施例提供了一种用于横向半软半硬断面地层中的隧道施工方法,包括:Referring to Fig. 4, an embodiment of the present application provides a tunnel construction method used in transverse semi-soft and semi-hard section stratum, including:
S1,对掌子面上对应隧道拱部区域施作预埋超前管棚;S1, pre-embedded and advanced pipe sheds are applied to the tunnel arch area corresponding to the tunnel face;
S2,采用中隔壁法依次对软岩分布的左半断面和硬岩分布的右半断面进行施工,开挖完成后,拆除临时中隔壁支护,并确保在左半断面、右半 断面的上部分别沿拱顶施作的永久支护拱架与下部的临时仰拱构成封闭支护结构;S2. Use the middle partition method to construct the soft rock distribution on the left half of the section and the hard rock distribution on the right half of the section in turn. After the excavation is completed, remove the temporary middle partition support, and ensure that the upper part of the left half section and the right half section The permanent supporting arch frame constructed along the vault and the temporary invert at the lower part form a closed supporting structure;
S3,进行仰拱开挖,施作隧道底部的永久支护拱架,拆除临时仰拱,并施作复合式衬砌。S3. Carry out invert excavation, construct permanent arch support at the bottom of the tunnel, remove temporary invert, and construct composite lining.
具体的,参见图1至图2,本实施例所示的隧道施工方法,在对左半断面1、右半断面2分别为泥盆系极软炭质板岩和弱风化白云质灰岩的地层进行施工时,通过施作预埋超前管棚13的方式提前对掌子面左侧鼓水、软岩、突泥部位进行加固,确保了掌子面前方地层的稳定性,并在进行施工时,采用中隔壁法依次对左半断面1和右半断面2分别进行施工,并建立临时封闭支护结构,这可确保初期支护结构的稳定性,从可进一步再施作隧道底部的永久支护拱架和复合式衬砌,如此有效避免了因偏压应力集中或围岩遇水软化导致的坍塌问题,且能有效抵抗软弱围岩的沉降和收敛变形,从而确保了施工作业的正常进行及施工现场的安全性。Specifically, referring to Figures 1 to 2, the tunnel construction method shown in this embodiment is composed of Devonian extremely soft carbonaceous slate and weakly weathered dolomitic limestone in the left half and right half of the cross-section 1, respectively. When the stratum is being constructed, the pre-embedded advanced pipe shed 13 is used to reinforce the water, soft rock, and mud bursting parts on the left side of the tunnel face in advance to ensure the stability of the stratum in front of the tunnel face, and the construction is in progress. When using the middle partition method to construct the left half-section 1 and the right half-section 2 respectively, and establish a temporary closed support structure, which can ensure the stability of the initial support structure, and can be further used for permanent construction at the bottom of the tunnel. Supporting arch frame and composite lining, which effectively avoids the problem of collapse caused by the concentration of bias stress or the softening of the surrounding rock in contact with water, and can effectively resist the settlement and convergence deformation of the weak surrounding rock, thereby ensuring the normal progress of construction operations And the safety of the construction site.
进一步的,本实施例中还包括:在步骤S1之前,对掌子面上发生涌水的区域进行排水处理,并对掌子面后侧的施工区域施作临时支撑。Further, this embodiment further includes: before step S1, performing drainage treatment on the area where water gushing occurs on the palm face, and temporarily supporting the construction area on the back side of the palm face.
具体的,对掌子面上发生涌水的区域进行排水处理主要针对的是左半断面1发生的涌水。左半断面1由于塌方、涌水严重,首先采用素喷型号为C25混凝土封闭掌子面,并拉渣土反压回填掌子面后方已经完成开挖、支护段落的拱脚,只预留将进行开挖施工的空间,此举的目的是防止坍塌继续扩大。Specifically, the drainage treatment on the area where water gushing occurs on the tunnel face is mainly aimed at the water gushing on the left half section 1. Due to the serious collapse and water gushing in the left half of the section 1, firstly, the face of the face was closed with plain sprayed C25 concrete, and the muck was back-pressured to backfill the arch toe of the excavation and support section behind the face, and only the arch foot was reserved. The space for excavation and construction, the purpose of this move is to prevent the collapse from continuing to expand.
另外,临时支撑的施作方式为:采用临时仰拱与环向套拱对齐布设,使其能够闭合成环,共同承受拱顶围岩的受力,其中,临时仰拱采用I20a工字钢制作,沿隧道纵向依次排布,其排布的间距为1.2m。In addition, the construction method of the temporary support is as follows: the temporary invert and the hoop arch are aligned and arranged so that they can be closed into a ring and jointly bear the stress of the surrounding rock of the vault. Among them, the temporary invert is made of I20a steel. , Arranged in sequence along the longitudinal direction of the tunnel, with an interval of 1.2m.
进一步的,参见图5,本实施例中步骤S1进一步包括:Further, referring to FIG. 5, step S1 in this embodiment further includes:
S11,将预埋超前管棚中的钢管作为钻杆进行钻进,钢管的首端连接导向板钻头,钢管的尾端连接钻机,其中,钢管在钻进时由第一段钢管与第二段钢管交替连接,第二段钢管上设有溢浆孔;S11, the steel pipe embedded in the advanced pipe shed is used as a drill pipe for drilling. The head end of the steel pipe is connected to the guide plate drill bit, and the tail end of the steel pipe is connected to the drilling rig. The steel pipe is drilled from the first section of the steel pipe to the second section. The steel pipes are alternately connected, and there is an overflow hole on the second section of the steel pipe;
S12,拆除钻机,并将注浆泵与钢管的尾端相连接,注浆泵在注浆时控制初压为0.5~1.0MPa,终压为2.0~3.0MPa,以使得浆液的扩散半径大于45cm。S12. Remove the drilling rig and connect the grouting pump to the end of the steel pipe. The initial pressure of the grouting pump is controlled to be 0.5~1.0MPa and the final pressure is 2.0~3.0MPa during grouting, so that the spreading radius of the slurry is greater than 45cm .
具体的,本实施例在对预埋超前管棚13进行施工时,采用钢管的直径为108mm,壁厚为6mm,并采用4m长的第一段钢管与6m长的第二段钢管交替连接钻进,并且第一段钢管与第二段钢管之间通过丝扣相连接。Specifically, in this embodiment, when the pre-embedded advanced pipe shed 13 is constructed, the diameter of the steel pipe is 108mm, the wall thickness is 6mm, and the 4m long first section of steel pipe is alternately connected with the 6m long second section of steel pipe. In addition, the first section of steel pipe and the second section of steel pipe are connected by a thread.
由于在第二段钢管上设有溢浆孔,则向交替连接的钢管内注浆,可在相应的地层形成超前支护刚性体,通过对注浆泵的注浆压力进行控制,在浆液的扩散半径大于45cm时,可确保预埋超前管棚13进行交错注浆的饱满度符合标准,并且还可通过第二段钢管上的溢浆孔进行二次补注浆,其中,向钢管内加注的浆液为易于凝结硬化的浆液。Since there is an overflow hole on the second section of the steel pipe, grouting is injected into the alternately connected steel pipes, which can form an advanced supporting rigid body in the corresponding stratum. By controlling the grouting pressure of the grouting pump, the When the diffusion radius is greater than 45cm, it can ensure that the fullness of the embedded advanced pipe shed 13 for staggered grouting meets the standard, and it can also be used for secondary grouting through the overflow hole on the second section of the steel pipe. The injected grout is a grout that is easy to set and harden.
进一步的,参见图2,本实施例中设定隧道的竖直中心线为K1,预埋超前管棚13的对称中心线为K2,则预埋超前管棚13施作的圆心角α的大小为90°~120°,预埋超前管棚13的对称中心线K2朝向左半断面1偏离隧道的竖直中心线K1的角度β为10°~20°;钢管的外插角度为10°~30°,钢管中加注的浆液优选为玻璃双浆液。Further, referring to FIG. 2, in this embodiment, the vertical centerline of the tunnel is set to K1, and the symmetrical centerline of the embedded advanced tube shed 13 is K2, then the size of the central angle α of the embedded advanced tube shed 13 is It is 90°~120°, the angle β of the symmetrical center line K2 of the pre-embedded leading pipe shed 13 from the vertical center line K1 of the tunnel towards the left half section 1 is 10°~20°; the extrapolation angle of the steel pipe is 10°~ At 30°, the slurry injected into the steel pipe is preferably a glass double slurry.
具体的,本实施例中优选预埋超前管棚13由45根钢管沿隧道的拱顶(环向)布置而成,钢管的长度为30m,并且钢管的环向间距为30cm;在实际钻进时,采用导向仪控制钢管的外插角精度,以使得钢管的外插角度为10°~30°,并且采用YZB-5型双液浆注浆泵钢管中加注玻璃双浆液,并在对钢管注浆时,按照先下后上,先稀后浓,隔孔注浆的原则进行,必要时可采用间歇式注浆法施工。Specifically, in this embodiment, it is preferable that the pre-embedded advanced pipe shed 13 is formed by arranging 45 steel pipes along the vault (circumferential direction) of the tunnel. The length of the steel pipes is 30m, and the circumferential spacing of the steel pipes is 30cm; in actual drilling When using a guide instrument to control the accuracy of the extrapolation angle of the steel pipe, so that the extrapolation angle of the steel pipe is 10°~30°, and the YZB-5 type double-slurry grouting pump is used to fill the steel pipe with double-glass grout. When grouting steel pipes, follow the principle of down first and then up, first thinning and then thickening, and grouting with separate holes. If necessary, intermittent grouting can be used for construction.
进一步的,参见图6,本实施例中步骤S2进一步包括:Further, referring to FIG. 6, step S2 in this embodiment further includes:
S21,将左半断面从上往下划分为多层施工区域,并按照划分的施工区域逐层向下开挖导洞,每层导洞出渣后,设置对应构成封闭支护结构的永久支护拱架、临时仰拱和临时中隔壁支护;S21: Divide the left half of the cross-section into multi-layer construction areas from top to bottom, and excavate pilot tunnels layer by layer according to the divided construction areas. After the slag is discharged from the pilot tunnels on each layer, a permanent support corresponding to the closed supporting structure is installed. Arch retaining frame, temporary invert and temporary intermediate wall support;
S22,采用台阶施工法对右半断面对应的区域开挖导洞。S22, using the step construction method to excavate a pilot tunnel in the area corresponding to the right half of the cross-section.
具体的,参见图2与图3,将隧道全断面掌子面划分为第一施工区域、第二施工区域、第三施工区域、第四施工区域、第五施工区域和第六施工区域,这六个施工区域对应编号为①、②、③、④、⑤和⑥。Specifically, referring to Figures 2 and 3, the full-section tunnel face is divided into the first construction area, the second construction area, the third construction area, the fourth construction area, the fifth construction area, and the sixth construction area. The corresponding numbers of the six construction areas are ①, ②, ③, ④, ⑤ and ⑥.
在实际施工时,首先,选定第一施工区域(左上部)进行机械开挖施工导洞,喷8cm厚的混凝土封闭该区域对应的掌子面,并在出渣后,在左上部对应的拱部安装钢筋网片和第一永久支护拱架3,在对应右半断面2 的竖直壁面铺挂网片,初喷封闭,然后,安装第一临时中隔壁支护5,接着,在水平位置安装第一临时仰拱4,并使得第一永久支护拱架3、第一临时仰拱4和第一临时中隔壁支护5构成封闭支护结构。In the actual construction, first, select the first construction area (upper left) for mechanical excavation and construction of the pilot tunnel, spray 8cm thick concrete to close the corresponding tunnel face in this area, and after the slag is discharged, the corresponding hole in the upper left Install the steel mesh and the first permanent support arch 3 on the arch, lay the mesh on the vertical wall corresponding to the right half of the section 2, and seal it with initial spraying. Then, install the first temporary intermediate wall support 5, and then The first temporary invert 4 is installed in a horizontal position, and the first permanent support arch 3, the first temporary invert 4 and the first temporary intermediate wall support 5 form a closed support structure.
其次,选定第二施工区域(左中部)进行机械开挖施工导洞,喷8cm厚的混凝土封闭该区域对应的掌子面,并在出渣后,在左中部对应的拱部安装钢筋网片和第二永久支护拱架6,并按照上述操作,在水平位置安装第二临时仰拱7,在竖直壁面安装第二临时中隔壁支护8,其中,第一永久支护拱架3与第二永久支护拱架6沿轴向对接,第二临时中隔壁支护8与第一临时中隔壁支护5沿竖直方向对接,再拆除第一临时仰拱4,此时,第一永久支护拱架3、第二永久支护拱架6、第二临时仰拱7、第二临时中隔壁支护8和第一临时中隔壁支护5构成封闭支护结构。Secondly, select the second construction area (middle left) for mechanical excavation and construction of the pilot tunnel, spray 8cm thick concrete to close the corresponding tunnel face in this area, and install steel mesh on the corresponding arch in the middle left after the slag is discharged According to the above operation, install the second temporary invert 7 in the horizontal position and install the second temporary intermediate wall support 8 on the vertical wall according to the above operation. Among them, the first permanent support arch 3 is butted along the axial direction with the second permanent support arch 6, the second temporary intermediate wall support 8 and the first temporary intermediate wall support 5 are butted in the vertical direction, and then the first temporary invert 4 is removed. At this time, The first permanent support arch 3, the second permanent support arch 6, the second temporary invert 7, the second temporary intermediate wall support 8 and the first temporary intermediate wall support 5 constitute a closed support structure.
由此可见,对于左半断面1的施工而言,通过划分多个施工区域分层开挖导洞,并在挖掘后立即施做封闭成环的支护结构,进一步有效避免了因偏压应力集中或围岩遇水软化导致的坍塌,且可有效抵抗软弱围岩的沉降和收敛变形。It can be seen that for the construction of the left half section 1, the pilot tunnel is excavated in layers by dividing multiple construction areas, and immediately after excavation, a closed ring supporting structure is constructed, which further effectively avoids the stress due to bias. The collapse of concentrated or surrounding rock caused by water softening, and can effectively resist the settlement and convergence deformation of weak surrounding rock.
另外,本实施例对第三施工区域(右上部)采用两台阶的台阶施工法开挖导洞。In addition, this embodiment uses a two-step step construction method to excavate the pilot tunnel for the third construction area (upper right).
具体的,由于右半断面2围岩夹杂白云质灰岩,块状构造,围岩稳定性尚可,则可在进行两台阶施工时,具体采用弱爆破的方式开挖导洞,出渣后,在右上部对应的拱部安装第三永久支护拱架9,初喷封闭,并拆除第一临时中隔壁支护5与第二临时中隔壁支护8,对第二临时仰拱7朝向右半断面2进行接长,以使得第一永久支护拱架3、第二永久支护拱架6、第二临时仰拱7和第三永久支护拱架9构成封闭式支护结构,即使得整个隧道上半面的支护拱架与第二临时仰拱7闭合成环,从而确保了初期支护的稳定性。Specifically, since the surrounding rock of the right half section 2 is mixed with dolomitic limestone, the block structure, and the stability of the surrounding rock is acceptable, the weak blasting method can be used to excavate the pilot tunnel when the two-step construction is carried out. After the slag is discharged , Install the third permanent support arch 9 on the corresponding arch on the upper right, the first spray is closed, and the first temporary intermediate wall support 5 and the second temporary intermediate wall support 8 are removed, facing the second temporary invert 7 The right half section 2 is extended so that the first permanent supporting arch 3, the second permanent supporting arch 6, the second temporary invert 7 and the third permanent supporting arch 9 form a closed supporting structure, Even if the supporting arch frame of the upper half of the entire tunnel is closed into a ring with the second temporary invert 7, the stability of the initial support is ensured.
进一步的,本实施例在具体施工时,在左半断面、右半断面分别沿拱顶施作的永久支护拱架与下部的临时仰拱初步建立整体的封闭支护结构时,还选定第四施工区域(左下部)进行微爆破,开挖导洞,出渣后,安装第四永久支护拱架10,并初喷封闭;接着,选定第五施工区域(右下部)进行微爆破,开挖导洞,出渣后,安装第五永久支护拱架11,并初喷封闭, 其中,第四施工区域与第五施工区域位于初步建立整体的封闭支护结构时的临时仰拱的下侧。Further, in the concrete construction of this embodiment, when the permanent supporting arch frame and the temporary invert at the lower part of the left half section and the right half section are respectively constructed along the vault to initially establish an integrated closed support structure, the selection is also selected The fourth construction area (lower left) is micro-blasted, the pilot tunnel is excavated, and after the slag is discharged, the fourth permanent support arch 10 is installed, and the first spray is closed; then, the fifth construction area (lower right) is selected for micro-blasting. After blasting, excavating the pilot tunnel, and after the slag is discharged, the fifth permanent support arch 11 is installed, and the first spray is closed. Among them, the fourth construction area and the fifth construction area are located at the temporary elevation when the overall closed support structure is initially established. The underside of the arch.
另外,还选定第六施工区域(下底部)进行微爆破开挖,出渣后,安装第六永久支护拱架12,从而完成全断面的拱架封闭成环,并初喷封闭。In addition, the sixth construction area (lower bottom) is selected for micro-blasting and excavation. After the slag is discharged, the sixth permanent supporting arch 12 is installed, so as to complete the full-section arch closed into a ring, and first spray closed.
在此应当指出的是,为了确保上断面左、右侧的各个永久支护拱架不同时悬空,在对第四施工区域和第五施工区域进行施工时,以前后交错施工的方式开挖导洞,并在开挖后,喷8cm厚的混凝土封闭相应区域的掌子面。It should be pointed out here that in order to ensure that the permanent supporting arches on the left and right sides of the upper section are not suspended at the same time, when the fourth and fifth construction areas are constructed, the excavation guide shall be carried out in a staggered manner. After excavation, spray 8cm thick concrete to seal the face of the corresponding area.
进一步的,参见图3,本实施例中第二施工区域开挖的导洞滞后于第一施工区域开挖的导洞第一预设距离,第一预设距离可设定为3m;第三施工区域开挖的导洞滞后于第二施工区域开挖的导洞第二预设距离,第二预设距离可设定为5m;第四施工区域开挖的导洞滞后于第三施工区域开挖的导洞第三预设距离,第三预设距离可设定为20m;第五施工区域开挖的导洞滞后于第四施工区域开挖的导洞第四预设距离,第四预设距离可设定为3m,第六施工区域开挖的导洞滞后于第五施工区域开挖的导洞第五预设距离,第五预设距离可设定为4m。Further, referring to FIG. 3, the pilot tunnel excavated in the second construction area in this embodiment lags behind the pilot tunnel excavated in the first construction area by the first preset distance, and the first preset distance can be set to 3m; third The pilot tunnel excavated in the construction area lags behind the second preset distance of the pilot tunnel excavated in the second construction area, and the second preset distance can be set to 5m; the pilot tunnel excavated in the fourth construction area lags behind the third construction area The third preset distance of the excavated pilot tunnel, the third preset distance can be set to 20m; the pilot tunnel excavated in the fifth construction area lags behind the fourth preset distance of the pilot tunnel excavated in the fourth construction area, and the fourth preset distance The preset distance can be set to 3m, the pilot tunnel excavated in the sixth construction area lags the fifth preset distance of the pilot tunnel excavated in the fifth construction area, and the fifth preset distance can be set to 4m.
进一步的,为了确保支护结构的稳定性,并抵抗围岩变形对支护结构的影响,本实施例在临时中隔壁支护与各个永久支护拱架处均插装有缩脚锚管。Further, in order to ensure the stability of the supporting structure and resist the influence of the deformation of the surrounding rock on the supporting structure, in this embodiment, the anchor pipes with reduced feet are inserted at the temporary intermediate wall supporting and each permanent supporting arch.
在此应当指出的是,本实施例考虑到隧道设计采用椭圆形受力截面,其圆心以上部分受力情况最好,从而将左中部施工得到的中台阶底面设置在圆心水平轴线上,这样能够最大限度增强初支支护结构的稳定性。为了满足机械化施工要求,确定左半断面1的左上部施工得到的上台阶高度设定为3.8m、中台阶高度设定为2.6m,右半断面2在进行二台阶施工时,上台阶高度设定为6.4m,整个断面下台阶高度设定为1.9m、仰拱开挖深度为1.8m。另外,由于该地层围岩极不稳定,为确保施工期间绝对安全,设定掌子面距离仰拱封闭段沿隧道纵向的水平距离小于35米,仰拱一次开挖距离不得大于3m,其中,仰拱封闭段指的是初步完成全断面的拱架封闭成环的断面。It should be pointed out here that this embodiment takes into account that the tunnel design adopts an elliptical force-bearing section, and the part above the center of the tunnel is in the best force. Therefore, the bottom surface of the middle step obtained from the construction of the left middle part is set on the horizontal axis of the center of the circle. Maximize the stability of the primary support structure. In order to meet the requirements of mechanized construction, it is determined that the height of the upper step obtained by the construction of the upper left part of the left half section 1 is set to 3.8m, the height of the middle step is set to 2.6m, and the right half section 2 is set to the height of the upper step during the two-step construction. It is set at 6.4m, the height of the steps under the entire section is set at 1.9m, and the invert excavation depth is set at 1.8m. In addition, because the surrounding rock of the formation is extremely unstable, in order to ensure absolute safety during construction, the horizontal distance between the tunnel face and the closed section of the inverted arch along the longitudinal direction of the tunnel is set to be less than 35 meters, and the excavation distance of the inverted arch shall not be greater than 3m. The closed invert section refers to the section where the full-section arch frame is initially closed into a ring.
最后应说明的是:以上实施例仅用以说明本申请的技术方案,而非对 其限制;尽管参照前述实施例对本申请进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本申请各实施例技术方案的精神和范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the application, not to limit them; although the application has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: The technical solutions recorded in the foregoing embodiments are modified, or some of the technical features are equivalently replaced; these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present application.

Claims (10)

  1. 一种用于横向半软半硬断面地层中的隧道施工方法,其特征在于,包括:A tunnel construction method used in transverse semi-soft and semi-hard section stratum, which is characterized in that it comprises:
    S1,对掌子面上对应隧道拱部区域施作预埋超前管棚;S1, pre-embedded and advanced pipe sheds are applied to the tunnel arch area corresponding to the tunnel face;
    S2,采用中隔壁法依次对软岩分布的左半断面和硬岩分布的右半断面进行施工,开挖完成后,拆除临时中隔壁支护,并确保在左半断面、右半断面的上部分别沿拱顶施作的永久支护拱架与下部的临时仰拱构成封闭支护结构;S2. Use the middle partition method to construct the soft rock distribution on the left half of the section and the hard rock distribution on the right half of the section in turn. After the excavation is completed, remove the temporary middle partition support, and ensure that the upper part of the left half section and the right half section The permanent supporting arch frame constructed along the vault and the temporary invert at the lower part form a closed supporting structure;
    S3,进行仰拱开挖,施作隧道底部的永久支护拱架,拆除临时仰拱,并施作复合式衬砌。S3. Carry out invert excavation, construct permanent arch support at the bottom of the tunnel, remove temporary invert, and construct composite lining.
  2. 根据权利要求1所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 1, wherein:
    还包括:在步骤S1之前,对掌子面上发生涌水的区域进行排水处理,并对掌子面后侧的施工区域施作临时支撑。It also includes: prior to step S1, performing drainage treatment on the area where water gushing occurs on the tunnel face, and temporarily supporting the construction area on the back side of the tunnel face.
  3. 根据权利要求1所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 1, wherein:
    步骤S1进一步包括:Step S1 further includes:
    S11,将所述预埋超前管棚中的钢管作为钻杆进行钻进,钢管的首端连接导向板钻头,钢管的尾端连接钻机,其中,钢管在钻进时由第一段钢管与第二段钢管交替连接,第二段钢管上设有溢浆孔;S11, the steel pipe in the pre-embedded advanced pipe shed is used as a drill pipe for drilling. The head end of the steel pipe is connected to the guide plate drill bit, and the tail end of the steel pipe is connected to the drilling rig. The two sections of steel pipes are alternately connected, and the second section of steel pipes are provided with overflow holes;
    S12,拆除钻机,并将注浆泵与钢管的尾端相连接,注浆泵在注浆时控制初压为0.5~1.0MPa,终压为2.0~3.0MPa,以使得浆液的扩散半径大于45cm。S12. Remove the drilling rig and connect the grouting pump to the end of the steel pipe. The initial pressure of the grouting pump is controlled to be 0.5~1.0MPa and the final pressure is 2.0~3.0MPa during grouting, so that the spreading radius of the slurry is greater than 45cm .
  4. 根据权利要求3所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 3, wherein:
    所述预埋超前管棚施作的圆心角的大小为90°~120°,所述预埋超前管棚的对称中心线朝向所述左半断面偏离隧道的竖直中心线的角度为10°~20°;所述钢管的外插角度为10°~30°,所述钢管中加注的浆液为玻璃双浆液。The central angle of the pre-embedded advanced tube roof is 90°~120°, and the symmetrical center line of the embedded advanced tube roof deviates from the vertical center line of the tunnel by 10° toward the left half section. ~20°; the extrapolation angle of the steel pipe is 10°-30°, and the slurry injected into the steel pipe is a glass double slurry.
  5. 根据权利要求1所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 1, wherein:
    步骤S2进一步包括:Step S2 further includes:
    S21,将所述左半断面从上往下划分为多层施工区域,并按照划分的施工区域逐层向下开挖导洞,每层导洞出渣后,设置对应构成封闭支护结 构的永久支护拱架、临时仰拱和临时中隔壁支护;S21: Divide the left half-section from top to bottom into multi-layer construction areas, and excavate pilot tunnels layer by layer according to the divided construction areas. After the slag is discharged from the pilot tunnels on each layer, a corresponding closed supporting structure is installed. Permanent support arch, temporary invert and temporary intermediate wall support;
    S22,采用台阶施工法对右半断面对应的区域开挖导洞。S22, using the step construction method to excavate a pilot tunnel in the area corresponding to the right half of the section.
  6. 根据权利要求5所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 5, wherein:
    步骤S21包括:将所述左半断面从上往下划分为第一施工区域和第二施工区域;Step S21 includes: dividing the left half section into a first construction area and a second construction area from top to bottom;
    步骤S22包括:在右半断面对应的第三施工区域采用两台阶的台阶施工法开挖导洞。Step S22 includes: excavating a pilot tunnel with a two-step step construction method in the third construction area corresponding to the right half of the cross-section.
  7. 根据权利要求6所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 6, wherein:
    步骤S3还包括:对位于步骤S2中位于下部的临时仰拱与预施作的仰拱之间的第四施工区域和第五施工区域,以前后交错施工的方式开挖导洞,并在出渣后,设置相应的永久支护拱架;Step S3 also includes: for the fourth construction area and the fifth construction area between the temporary invert at the lower part of step S2 and the pre-constructed invert, the pilot tunnel is excavated in a staggered construction method, and the exit After the slag, set the corresponding permanent support arch;
    所述第四施工区域、所述第五施工区域分别对应分布在左半断面和右半断面上,所述第四施工区域、所述第五施工区域的下侧为预施作仰拱的第六施工区域。The fourth construction area and the fifth construction area are correspondingly distributed on the left half-section and the right half-section respectively, and the lower side of the fourth construction area and the fifth construction area is the sixth construction of pre-inverted arch area.
  8. 根据权利要求7所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 7, wherein:
    所述第二施工区域开挖的导洞滞后于所述第一施工区域开挖的导洞第一预设距离;The pilot tunnel excavated in the second construction area lags behind the pilot tunnel excavated in the first construction area by a first preset distance;
    所述第三施工区域开挖的导洞滞后于所述第二施工区域开挖的导洞第二预设距离;The pilot tunnel excavated in the third construction area lags behind the pilot tunnel excavated in the second construction area by a second preset distance;
    所述第四施工区域开挖的导洞滞后于所述第三施工区域开挖的导洞第三预设距离;The pilot tunnel excavated in the fourth construction area lags behind the pilot tunnel excavated in the third construction area by a third preset distance;
    所述第五施工区域开挖的导洞滞后于所述第四施工区域开挖的导洞第四预设距离。The pilot tunnel excavated in the fifth construction area lags behind the pilot tunnel excavated in the fourth construction area by a fourth preset distance.
  9. 根据权利要求1所述的隧道施工方法,其特征在于,The tunnel construction method according to claim 1, wherein:
    在所述临时中隔壁支护与所述永久支护拱架处均插装有缩脚锚管。Retractable anchor pipes are inserted at the temporary intermediate wall support and the permanent support arch.
  10. 根据权利要求1-9中任意一项所述的隧道施工方法,其特征在于,The tunnel construction method according to any one of claims 1-9, characterized in that:
    步骤S2中,掌子面距离仰拱封闭段沿隧道纵向的水平距离小于35米;In step S2, the horizontal distance between the tunnel face and the closed section of the inverted arch along the longitudinal direction of the tunnel is less than 35 meters;
    步骤S3中,在对仰拱一次开挖时,沿隧道纵向的水平距离小于3m。In step S3, when the invert is excavated once, the horizontal distance along the longitudinal direction of the tunnel is less than 3m.
PCT/CN2020/127977 2019-11-11 2020-11-11 Construction method for tunnel in transverse semi-soft and semi-hard section stratum WO2021093751A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201911097059.6 2019-11-11
CN201911097059.6A CN110985002B (en) 2019-11-11 2019-11-11 Tunnel construction method for horizontal semi-soft semi-hard section stratum

Publications (1)

Publication Number Publication Date
WO2021093751A1 true WO2021093751A1 (en) 2021-05-20

Family

ID=70083779

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/127977 WO2021093751A1 (en) 2019-11-11 2020-11-11 Construction method for tunnel in transverse semi-soft and semi-hard section stratum

Country Status (2)

Country Link
CN (1) CN110985002B (en)
WO (1) WO2021093751A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110985002B (en) * 2019-11-11 2021-03-23 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN112431599B (en) * 2020-10-20 2022-10-28 中铁十九局集团第五工程有限公司 Tunnel excavation method for upper soft and lower hard stratum

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07229386A (en) * 1994-02-22 1995-08-29 Shigeki Nagatomo Excavation method for tunnel of flat and large cross section
CN107060825A (en) * 2017-05-04 2017-08-18 山东省交通规划设计院 Construction method is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
CN109594991A (en) * 2018-12-29 2019-04-09 中铁隧道集团二处有限公司 Shallow Buried Soft Rock Super-large-section tunnel CD method combines rapid constructing method with benching tunnelling method
CN110985002A (en) * 2019-11-11 2020-04-10 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725358A (en) * 2008-10-31 2010-06-09 中铁四局集团有限公司 Excavation construction method of ultra-shallow buried uneven weathered stratum of tunnel
CN106321106B (en) * 2015-06-30 2018-05-15 中交二公局第六工程有限公司 A kind of tunnel weak surrounding rock, hazy bias location hole abutment start tunneling method
CN205117356U (en) * 2015-11-21 2016-03-30 中铁二十局集团第二工程有限公司 Self -drilling spiral pipe canopy
CN106638509A (en) * 2017-01-04 2017-05-10 中国电建集团贵阳勘测设计研究院有限公司 Tunnel structure capable of reducing slope excavation and construction method thereof
KR101819494B1 (en) * 2017-01-18 2018-01-18 쌍용건설 주식회사 Tunnel construction method with support walls
CN107859523A (en) * 2017-12-12 2018-03-30 吉林大学 A kind of asymmetric supporting construction of Unevenly-pressured shallow tunnel and construction method
CN108316931A (en) * 2018-03-05 2018-07-24 北京市政建设集团有限责任公司 A kind of branch-cut bridge section tunnel CRD method construction methods
CN109139046A (en) * 2018-08-23 2019-01-04 洛阳恒诺锚固技术有限公司 Segmenting slip casting self-drilling type barrel vault advanced support method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07229386A (en) * 1994-02-22 1995-08-29 Shigeki Nagatomo Excavation method for tunnel of flat and large cross section
CN107060825A (en) * 2017-05-04 2017-08-18 山东省交通规划设计院 Construction method is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
CN109594991A (en) * 2018-12-29 2019-04-09 中铁隧道集团二处有限公司 Shallow Buried Soft Rock Super-large-section tunnel CD method combines rapid constructing method with benching tunnelling method
CN110985002A (en) * 2019-11-11 2020-04-10 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LI SHIJUN: "Study on Construction Optimization of Highway Tunnel in Asymmetric Surrounding Rock", CHINESE MASTER'S THESES FULL-TEXT DATABASE, no. 7, 15 July 2013 (2013-07-15), CN, pages 1 - 92, XP055812183, ISSN: 1674-0246 *
ZHANG QUANFENG , WANG SONGQING , XU YING , YANG MING , WANG HAIBO , SHEN WUNGANG , YANG XINWEN: "On Subway Tunnel Rapid Construction Technology of Large-span Mining Method", JOURNAL OF ANHUI UNIVERSITY OF SCIENCE AND TECHNOLOGY(NATURAL SCIENCE), vol. 39, no. 5, 30 September 2019 (2019-09-30), pages 7 - 12, XP055812199, ISSN: 1672-1098 *

Also Published As

Publication number Publication date
CN110985002A (en) 2020-04-10
CN110985002B (en) 2021-03-23

Similar Documents

Publication Publication Date Title
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN110905530B (en) Stability control construction method for water-rich soft rock tunnel penetrating fault fracture zone
WO2022083096A1 (en) Tunnel excavation method for upper-soft and lower-hard stratum
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
WO2021093751A1 (en) Construction method for tunnel in transverse semi-soft and semi-hard section stratum
CN105863648B (en) A kind of tunneling is shallow to cover large-section tunnel construction method
CN105351001B (en) A kind of method based on gob side entry retaining region reinforcement gas pumping
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN107762533A (en) A kind of front pre-grouting method of high-pressure water-enriched weak surrounding rock mountain tunnel
CN110924959B (en) Construction method of water-rich weak surrounding rock tunnel penetrating fault fracture zone
CN211258623U (en) Water-rich weak surrounding rock tunnel supporting system crossing fault fracture zone
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN111997624A (en) Shallow-buried large-section underground excavation rectangular tunnel construction method
WO2022100346A1 (en) Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN105370289A (en) Ultra-long shallow-buried excavation construction method for existing pipeline in complex environment
CN108798702A (en) A kind of method for protecting support of big cross section large-deformation tunnel in soft rock
CN108252719A (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN109944600A (en) Shield receiving end reinforced construction method
CN109139018A (en) The method for tunnel construction and system that deep hole sleeve valve barrel grouting is combined with horizontal jet grouting
CN106013078A (en) Construction method for strong permeable ground layer strengthened curtain structure
CN108915702B (en) Shield receiving method in circular small-section tunnel
CN115839251A (en) Up-down overlapping tunnel construction method based on advanced pre-reinforcement

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20886373

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20886373

Country of ref document: EP

Kind code of ref document: A1