WO2022083096A1 - Tunnel excavation method for upper-soft and lower-hard stratum - Google Patents

Tunnel excavation method for upper-soft and lower-hard stratum Download PDF

Info

Publication number
WO2022083096A1
WO2022083096A1 PCT/CN2021/090852 CN2021090852W WO2022083096A1 WO 2022083096 A1 WO2022083096 A1 WO 2022083096A1 CN 2021090852 W CN2021090852 W CN 2021090852W WO 2022083096 A1 WO2022083096 A1 WO 2022083096A1
Authority
WO
WIPO (PCT)
Prior art keywords
tunnel
support
blasting
arch
lower step
Prior art date
Application number
PCT/CN2021/090852
Other languages
French (fr)
Chinese (zh)
Inventor
张帅
王建辉
阳凯
宋新海
于建
王纪伟
Original Assignee
中铁十九局集团第五工程有限公司
中铁十九局集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁十九局集团第五工程有限公司, 中铁十九局集团有限公司 filed Critical 中铁十九局集团第五工程有限公司
Publication of WO2022083096A1 publication Critical patent/WO2022083096A1/en
Priority to ZA2023/05430A priority Critical patent/ZA202305430B/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D19/00Provisional protective covers for working space
    • E21D19/04Provisional protective covers for working space for use in drifting galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Definitions

  • the present application relates to the technical field of tunnel construction, and in particular, to a tunnel excavation method for upper soft and lower hard strata.
  • the excavation section of the undercut tunnel often has a composite stratum with soft upper and lower hard layers, that is, the upper part of the tunnel section is a soft soil layer, and the lower part is a relatively hard soil layer or rock.
  • the section of a subway tunnel is generally buried at a depth of about 20m.
  • the main pipelines include rainwater, water supply, sewage, natural gas and culverts.
  • the embodiment of the present application provides a tunnel excavation method for upper soft and lower hard strata, which is used to solve safety accidents such as collapse and water inrush and mud inrush when the traditional tunnel excavation method is easily excavated in the upper soft and lower hard stratum. The problem.
  • the embodiment of the present application provides a tunnel excavation method for upper and lower hard strata, the tunnel section is divided into upper and lower parts, and the excavation step comprises:
  • the lower section of the tunnel is excavated by means of multiple cycle footage blasting; wherein, after each cycle footage blasting is completed, the initial support of the lower step and the temporary arch of the lower step are used as temporary support. support;
  • the upper section of the tunnel is excavated by means of multiple cycle footage blasting; wherein, before each cycle footage blasting, the temporary support corresponding to the cycle footage blasting length is removed; After the cyclic footage blasting, the initial support for the upper step is applied and closed to form a ring with the initial support for the lower step.
  • the initial support for the lower step and the temporary support for the temporary arch of the lower step are performed, specifically include:
  • An I-beam is arranged on the temporary arch of the lower step, and both ends of the I-beam are respectively supported and fixedly connected to the lower step grille at the side wall;
  • the bottom surface and side walls of the lower steps are sprayed concrete for sealing.
  • the method further includes: respectively placing side walls on both sides of the lower step.
  • the lower step grille support at the place is set up with locking foot anchor pipes and grouted.
  • the temporary support corresponding to the cyclic footage blasting length is removed, specifically comprising: removing the engineering
  • the connecting bolts between the steel beam and the lower step grille support at the side wall are cut off or the I-beam is cut off from the root.
  • the S1 specifically includes:
  • a water-stop curtain is installed in the stratum within the set range of the tunnel vault, and grouting reinforcement is performed in the area surrounded by the water-stop curtain; or, from the inside of the tunnel, the tunnel vault is Apply half-section curtain grouting reinforcement in the stratum within the set range;
  • the advanced middle pipe shed support is applied along the excavation outline of the tunnel.
  • the performing initial support for upper steps includes:
  • An upper step grille support is applied to the arch of the upper step and is fixedly connected with the lower step grille support;
  • the arches of the upper steps are sprayed concrete for sealing.
  • the tunnel excavation method for upper soft and lower hard strata further includes applying advanced small conduit support to the arch of the tunnel after completing one or more cycles of footage blasting;
  • the PVC pipe is pre-buried in the initial support of the upper step; after the arch of the upper step is sealed by spraying concrete, Drill holes are drilled in the PVC pipe, and a small lead pipe is arranged in the hole.
  • the steel arches supported by the upper step grid and/or the steel arches supported by the lower step grid are Use socket connection.
  • the cyclic footage blasting of the lower step adopts an electronic detonator water pressure control blasting method
  • the cyclic footage blasting of the upper step adopts the electronic detonator layer-by-layer peeling control. blasting method.
  • the diameter of the part of the middle pipe shelter intruding into the contour line of the initial support of the upper step is smaller than the diameter of the part of the middle pipe shelter intruding into the stratum .
  • the tunnel excavation method for the upper soft and lower hard stratum is a reverse step construction method of excavating the lower step first, and then performing the upper step excavation, and both the lower step and the upper step are adopted.
  • Multiple cycle footage blasting After each blasting of the lower steps, the initial support of the lower steps and the temporary support of the temporary arch of the lower steps shall be applied. The corresponding temporary supports shall be removed before each blasting of the upper steps so that the The force is released to the excavated lower steps, thereby greatly reducing the reaction force on the tunnel arch when the upper steps are blasted, reducing the risk of collapse and water and mud inrush, and improving the safety of construction.
  • Fig. 1 is the schematic flow chart of the tunnel excavation method of upper soft and lower hard strata in the embodiment of the present application;
  • FIG. 2 is a schematic cross-sectional view of a tunnel excavation method for upper soft and lower hard strata in the embodiment of the present application
  • FIG 3 is a schematic longitudinal cross-sectional view of a tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application.
  • the terms “installed”, “connected” and “connected” should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection, Or integrally connected; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal communication between the two components.
  • installed should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection, Or integrally connected; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal communication between the two components.
  • FIG. 1 it is a schematic flow chart of a tunnel excavation method for upper soft and lower hard strata in the embodiment of the application.
  • the tunnel section is divided into upper and lower parts, and the lower step 1 is excavated first and then the upper step is excavated. 2 way cycle excavation.
  • FIG. 2 is a schematic cross-sectional view of the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application
  • FIG. 3 is a longitudinal cross-sectional schematic diagram of the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application.
  • the excavation steps include:
  • the lower section of the tunnel is excavated by the method of multiple cycle footage blasting; wherein, after each cycle footage blasting is completed, the initial support of the lower step and the temporary support of the temporary arch 11 of the lower step 1 are applied. protect.
  • the lower bench 1 is excavated by means of cyclic footage blasting at the lower section of the tunnel, and the length of one excavation of the lower bench 1 can be determined according to the length of the advance support. For example, if the length of the middle pipe shed 3 used for the advanced support is 10m, and the longitudinal overlap is 4m, the length of one excavation of the lower step 1 is about 6m. If the footage is blasted 1m per cycle, it will take 6 blasts to complete the excavation of the next step 1. After each blasting, a temporary arch 11 with a length of 1 m will be formed on the top of the lower step 1 . After each cycle footage blasting is completed, the initial support of the descending steps and the temporary support of the temporary arch 11 are completed in time. In order to further improve the safety of construction, vertical I-beams such as I18 I-beams may also be arranged between the temporary arch 11 and the bottom surface of the lower step as a temporary support roof.
  • I18 I-beams may also be arranged between the temporary arch 11 and the bottom
  • the cyclic footage blasting of the lower step 1 adopts the electronic detonator hydraulic blasting method.
  • the electronic detonator can freely set the delayed initiation time (such as 50 milliseconds), which can realize precise blasting control and control of construction noise and blasting vibration.
  • Each cycle footage blasting of the lower step 1 adopts the blasting method of 2 holes and 1 stage, and the middle hole is blasted first to reduce the reaction force of the subsequent blasting on the arch. Hydraulic blasting is used for control, the utilization rate of explosives is improved, the amount of single-shot blasting charges is reduced, the degree of blasting and crushing is uniform, and the on-site dust removal is faster.
  • a corresponding number of water bags are added to the blast hole according to the design requirements, and the blast hole is sealed with the blast mud.
  • the upper step 2 is excavated by means of multiple cycle footage blasting. Among them, before each cycle footage blasting, the temporary support corresponding to the cycle footage blasting length is removed first; after each cycle footage blasting is completed, the upper step initial support is applied and closed with the lower step initial support. .
  • the cyclic footage blasting of the upper step 2 adopts the electronic detonator layer-by-layer stripping blasting method.
  • each cycle footage is 0.5m
  • the excavation length of the upper step 2 and the lower step 1 is the same. If the excavation length of the upper step 2 is 6m, 12 blasts are required to complete the excavation of the upper step 2.
  • Each cycle footage blasting of the upper step 2 adopts a single-hole single-stage blasting method, and the middle hole is blasted first to reduce the reaction force of the subsequent blasting on the arch.
  • the tunnel excavation method for the upper soft and lower hard stratum is a reverse step construction method of excavating the lower step first, and then performing the upper step excavation, and both the lower step and the upper step are adopted.
  • Multiple cycle footage blasting After each blasting of the lower steps, the initial support of the lower steps and the temporary support of the temporary arch of the lower steps shall be applied. The corresponding temporary supports shall be removed before each blasting of the upper steps so that the The force is released to the excavated lower steps, thereby greatly reducing the reaction force on the tunnel arch when the upper steps are blasted, reducing the risk of collapse and water and mud inrush, and improving the safety of construction.
  • performing advance support on the arch of the tunnel in S1 includes the steps:
  • the method of applying advanced support from the ground is adopted, that is, a water-stop curtain is installed from the ground in the stratum of the set range of the tunnel vault, and the water-stop curtain is surrounded by the water-stop curtain.
  • Grouting reinforcement is carried out in the designated area.
  • the water-stop curtains of the rotary jet piles and the stirring jet piles are applied within the set range along the width direction and length direction of the tunnel to form a water-stop body such as a mouth-shaped, a sun-shaped or a mesh-shaped water body.
  • a range is set on the outside to form a continuous water stop coaxial with the tunnel.
  • the method of applying advanced support from the tunnel is adopted, that is, the half-section is applied from the stratum within the set range of the tunnel vault within the tunnel.
  • curtain grouting reinforcement For example, the grouting pipe extends from the upper section of the tunnel to the outside of the tunnel excavation outline, and grouting is performed outside the excavation outline and within the set range along the length of the tunnel, so as to form a continuous stop coaxial with the tunnel. Water body.
  • the drilling position is released on the working face (the upper section of the tunnel) and calibrated with paint.
  • the orifice pipe is buried at the calibration position, and the orifice pipe is tightly consolidated with the installation surface to ensure no leakage or stringing of slurry.
  • the burying method is as follows: use a drilling rig to drill at the calibrated drilling position, insert the orifice tube with the orifice flange and expose it for 20-30cm after the hole is formed, and wrap the outer wall of the orifice tube with geotextile.
  • the drilling rig pushes the orifice pipe into the borehole, pours the double-liquid slurry, and finally completes the burial of the orifice pipe.
  • the diameter of the borehole is 115mm and the length is about 4m.
  • the orifice pipe is made of seamless steel pipe with a diameter of 108mm and a length of 3m.
  • the thickness of the geotextile is about 1-3cm and the length is about 30cm. match.
  • the orifice pipe After the orifice pipe is all buried, replace the drill bit, drill the hole in the orifice pipe to the design depth, insert the grouting pipe into the hole and connect it with the orifice flange of the orifice pipe to complete the orifice pipe and grouting system Connection. Then, the tightness of the pipeline of the grouting pipe is detected by the pressurized water, and the cracks in the rock are flushed, the slurry passage is enlarged, and the compactness of the slurry flushing is increased. After the hole is cleared, the grouting construction is started. For example, make sure that the final hole diameter of the drilled hole is not less than 75mm.
  • the grouting pipe adopts a PVC pipe with a diameter of 42 mm, wherein the grouting pipe is provided with grouting ports with a plum-shaped distribution at intervals of 50 cm along the length direction of the grouting pipe, and the diameter of the grouting port is 10 mm.
  • the grouting pressure of the pressure sand layer is 0.5-1.0MPa.
  • the grouting sequence is: the outer ring is injected first, the inner ring is injected later, and the same ring is applied at intervals from bottom to top. In this way, the subsequent holes can check the grouting effect of the previous holes.
  • the middle pipe shed 3 is made of steel pipes with a diameter of 89 mm, a length of 10 m, and a thickness of 5 mm.
  • the middle pipe shed 3 is symmetrically arranged along the excavation contour with a circumferential spacing of 0.25 m within the range of the tunnel arch not less than 150°.
  • the length of advance support is determined by the length of curtain grouting and mid-pipe shed advance support construction. For example, if the length of the middle pipe shed 3 is 10m, and the longitudinal overlap is 4m along the length of the tunnel, the length of the primary support of the middle pipe shed is about 6m. In the case that the length of one curtain grouting should not be less than 6m, and the length of one advance support reaches 6m, then the length of one excavation lower step 1 and one excavation upper step 2 are both 6m.
  • step S2 after each cycle footage blasting is completed, the initial support of the lower step and the temporary support of the temporary arch 11 of the lower step 1 are applied, specifically including:
  • the lower step grid support 121 is applied to the bottom surface and side walls of the lower step 1.
  • an I-beam 112 is provided on the temporary arch 11 of the lower step 1, and the I-beam 112 is fixedly connected to the lower step grille support 121 at the side wall.
  • the temporary arch 11 is immediately sprayed with concrete 111 to reinforce the temporary arch and ensure construction safety.
  • the thickness of the shotcrete 111 is 150 mm.
  • the I-beam 112 is connected with the lower step grille support 121 at the side wall through a connecting plate and bolts. During construction, ensure that the I-beam 113 is firmly connected to the grille arch, and is closely attached to the temporary arch 11, and the non-compact places are sealed and compacted with shotcrete.
  • I-beam 112 adopts I18 I-beam.
  • the longitudinal spacing of the I-beams 112 is 1m along the excavation footage direction of the tunnel. If the cyclic footage of each blasting is 1m, then after each cycle footage is blasted, an I-beam is installed in the temporary arch 11 .
  • the thickness of sprayed concrete is 250mm on the bottom surface and side wall of the lower step 1.
  • the temporary support corresponding to the cycle footage blasting length specifically including: cutting off the connecting bolts between the I-beam 112 and the lower step grille support 121 at the side wall Or cut the I-beam 112 from the root.
  • the shotcrete at the connection plate between the I-beam 112 and the lower step grille support 121 at the side wall is cleaned by hand and a breaking hammer.
  • the lower step 1 after the bottom surface and side walls of the lower step 1 are sealed with sprayed concrete, it also includes setting up locking foot anchor pipes 122 on the lower step grid supports 121 at the side walls on both sides of the lower step 1 and grouting.
  • the length of the foot-locking anchor pipe 122 is 3.5 m
  • two foot-locking anchor pipes 122 are erected on each side
  • the grouting pressure is 0.5-1.0 MPa.
  • step S3 the initial support for the upper steps is performed, which specifically includes:
  • the upper step grille support 211 is applied to the arch of the upper step 2 and fixedly connected to the lower step grille support.
  • the upper step grid and the lower step grid are connected by connecting plates, so that the upper step grid and the lower step grid are closed into a ring.
  • the thickness of shotcrete in the arch 21 of the upper step 2 is 250 mm, wherein the arch of the upper step 2 includes a vault and side walls connected to the vault on both sides of the upper step 2 .
  • step S3 also includes:
  • a small advanced duct support is applied to the arch of the tunnel.
  • the number of leading small pipes 4 is 34 and the length is 3.5m, it will take about 4 hours from drilling to the end of grouting.
  • the overlying rock of the tunnel arch itself is thin, and the sand layer above it needs to be closed as soon as possible. Therefore, when the arch of the upper step 2 is used as the upper step grille support 211, according to the design position and angle of the advanced small conduit 4, the PVC pipe is pre-buried in the initial support of the upper step, and the arch of the upper step 2 is pre-buried.
  • a hole is drilled in the PVC pipe, and the drilled hole is used to set the leading small conduit 4 . This can reduce the risk of collapse caused by the exposure of surrounding rock for too long, and ensure the safety of the project.
  • the length of the leading small ducts 4 is 3.5m
  • the circumferential spacing is 0.25m
  • the leading small ducts 4 are arranged in the range of not less than 150° on the dome of the upper step 2
  • the number of the leading small ducts 4 is determined according to the actual size of the tunnel.
  • the longitudinal overlap is 2m, that is, the longitudinal distance is 1.5m. If the blasting length of one cycle footage is 0.5m, it can be blasted three times and then applied to the leading small conduit 4. Of course, in order to increase the safety of construction, the longitudinal distance of the leading small duct 4 can also be shortened to 0.5m or 1 m. After completing one or two cycle footage blasting and initial support of the steps, the leading small duct 4 is applied. support.
  • the grid support is formed by connecting and fixing a plurality of steel arches arranged along the tunnel excavation direction by connecting steel bars.
  • the adjacent steel arches are connected by single-sided welding connecting steel bars, and the welding length needs to be reserved for the next circulating connecting steel bars, and the welding length is at least 10 times the diameter of the connecting steel bars. This will lead to a long blasting footage and a long distance between the last grille and the face of the tunnel. The rock mass of this reserved length is in a state of being in the air and unsupported, which brings safety hazards to the construction.
  • the steel arches of the upper step grille support 211 and the steel arches of the lower step grille support are connected by sleeves.
  • two adjacent steel arches are fixedly connected by two steel bars and a sleeve, one end of the connecting steel bars is provided with an external thread, and the sleeve is provided with an internal thread.
  • first stand up the first steel arch weld the unthreaded end of the connecting steel bar to the first steel arch, and screw the sleeve to the threaded end of the connecting steel bar.
  • the other connecting bar is screwed to the sleeve at the end of the previous connecting bar.
  • the other connecting bar is connected to the second steel arch.
  • the arches are welded accordingly, so that the two steel arches are welded and fixed in the longitudinal direction by two steel bars and a sleeve. Among them, welding and fixing are carried out at intervals of 1m on the steel arch ring upward.
  • the sleeve After the last steel arch is erected in each blasting footage, the sleeve is installed on the connecting steel bar, and it is buried in the initial support when spraying concrete. Therefore, it is not necessary to reserve a long single-sided welding length of the lower circulation connecting steel bar, but only a short length of the sleeve needs to be reserved, thereby reducing the welding length of the longitudinal connecting steel bar, thereby reducing a single excavation.
  • the length of the grid arch is as close as possible to the face of the tunnel, reducing the length of the unsupported rock mass facing the tunnel, and enhancing the engineering safety factor.
  • the diameter of the part where the middle pipe shelter 3 intrudes into the initial support contour of the upper step is smaller than the diameter of the part where the middle pipe shelter 3 penetrates into the formation.
  • the tail of the middle pipe shed 3 with a diameter of 89mm needs to be replaced by a steel pipe with a diameter of 42mm and a length of 1.5m.
  • the two sections are welded together by open steel plates, so as to facilitate the cutting of the intrusion-limiting steel pipe in the later construction, thereby promoting the The upper step 2 is quickly and effectively closed into a loop to reduce engineering risks.
  • connection between the grid arches in the embodiment of the present application are all made of steel plates and high-strength bolts, and the parts that need to be welded are fully welded with 50 electrodes on one side.
  • the tunnel excavation method for the upper soft and lower hard stratum provided by the embodiment of the present application, through the reverse step construction method of excavating the lower step first and then excavating the upper step, so that most of the energy during blasting of the upper step is directed to the excavated lower step.
  • the direction release greatly reduces the disturbance of the blasting operation to the tunnel arch and reduces the risk of water inrush and mud inrush; through the precise control of the blasting control technology, the blasting noise and blasting vibration speed are reduced, and the surrounding environment and the surrounding road surface are effectively controlled and pipeline settlement; hydraulic blasting is adopted to reduce the impact of construction dust and toxic and harmful gases on the health of workers; small-diameter steel pipes are installed in the encroachment section of the middle pipe shed, and steel grids are used between the arches.
  • Sleeve connection is simple and easy to operate, and can shorten the construction time, so as to quickly complete the initial support and sealing, and realize the efficient and safe excavation of the tunnel that goes through the soft and hard stratum below.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A tunnel excavation method for an upper-soft and lower-hard stratum. The section of a tunnel is divided into an upper portion and a lower portion. The excavation step comprises: S1, constructing advanced support on an arch portion of the tunnel; S2, excavating a lower step (1) on the lower section of the tunnel in a multi-time cyclic footage blasting manner, wherein a lower step primary support and a temporary support of a temporary arch portion (11) of the lower step (1) are constructed after each time of cyclic footage blasting is completed; and S3, excavating an upper step (2) on the upper section of the tunnel in the multi-time cyclic footage blasting manner, wherein the corresponding temporary support is removed before each time of cyclic footage blasting, an upper step primary support is constructed after each time of cyclic footage blasting is completed, and the upper step primary supports and the lower step primary supports are closed to form rings.

Description

上软下硬地层的隧道开挖方法Tunnel excavation method for upper soft and lower hard stratum
相关申请的交叉引用CROSS-REFERENCE TO RELATED APPLICATIONS
本申请要求于2020年10月20日提交的申请号为202011125816.9,发明名称为“上软下硬地层的隧道开挖方法”的中国专利申请的优先权,其通过引用方式全部并入本文。This application claims the priority of the Chinese patent application with the application number 202011125816.9, filed on October 20, 2020, and the invention titled "Tunnel Excavation Method for Upper Soft and Lower Hard Ground", which is incorporated herein by reference in its entirety.
技术领域technical field
本申请涉及隧道施工技术领域,尤其涉及一种上软下硬地层的隧道开挖方法。The present application relates to the technical field of tunnel construction, and in particular, to a tunnel excavation method for upper soft and lower hard strata.
背景技术Background technique
在隧道施工时,会采用各种不同的隧道开挖方法。以在合适的工程造价和施工速度的基础上控制因施工对周边环境、人员、地面管线和建筑物沉降的影响。其中,暗挖隧道的开挖断面较多的出现上软下硬的复合地层的情况,即隧道断面上部是软土层,而下部是较硬的土层或岩石。例如,地铁隧道断面一般埋深约20m,加上道路下方管线较多,主要管线有雨水、给水、污水、天然气和暗渠等,道路两侧存在多层住宅楼、临街商铺和办公楼等,隧道上方存在较厚的富水砂层,地质条件极为复杂,拱部覆岩薄且破碎。然而,若按照传统的台阶法或CD法进行开挖,极易发生坍塌和突水突泥等安全事故,后果十分严重。During tunnel construction, various tunnel excavation methods are used. In order to control the impact of construction on the surrounding environment, personnel, ground pipelines and building settlement on the basis of appropriate project cost and construction speed. Among them, the excavation section of the undercut tunnel often has a composite stratum with soft upper and lower hard layers, that is, the upper part of the tunnel section is a soft soil layer, and the lower part is a relatively hard soil layer or rock. For example, the section of a subway tunnel is generally buried at a depth of about 20m. In addition, there are many pipelines under the road. The main pipelines include rainwater, water supply, sewage, natural gas and culverts. There are multi-storey residential buildings, street-facing shops and office buildings on both sides of the road. There is a thick water-rich sand layer above, the geological conditions are extremely complex, and the overlying rock in the arch is thin and broken. However, if the excavation is carried out according to the traditional step method or CD method, safety accidents such as collapse and water and mud inrush are very likely to occur, and the consequences are very serious.
发明内容SUMMARY OF THE INVENTION
本申请实施例提供一种上软下硬地层的隧道开挖方法,用以解决传统的隧道开挖方法在对上软下硬地层进行隧道开挖时易发生坍塌和突水突泥等安全事故的问题。The embodiment of the present application provides a tunnel excavation method for upper soft and lower hard strata, which is used to solve safety accidents such as collapse and water inrush and mud inrush when the traditional tunnel excavation method is easily excavated in the upper soft and lower hard stratum. The problem.
本申请实施例提供一种上软下硬地层的隧道开挖方法,将隧道断面分为上下两个部分,开挖步骤包括:The embodiment of the present application provides a tunnel excavation method for upper and lower hard strata, the tunnel section is divided into upper and lower parts, and the excavation step comprises:
S1,在所述隧道的拱部施作超前支护;S1, perform advanced support on the arch of the tunnel;
S2,在所述隧道的下断面采用多次循环进尺爆破的方式开挖下台阶;其中,每完成一次循环进尺爆破后,施作下台阶初期支护以及所述下台阶 的临时拱部的临时支护;S2, the lower section of the tunnel is excavated by means of multiple cycle footage blasting; wherein, after each cycle footage blasting is completed, the initial support of the lower step and the temporary arch of the lower step are used as temporary support. support;
S3,在所述隧道的上断面采用多次循环进尺爆破的方式开挖上台阶;其中,在每一次循环进尺爆破之前,先拆除该循环进尺爆破长度对应的所述临时支护;每完成一次循环进尺爆破后,施作上台阶初期支护并与所述下台阶初期支护封闭成环。S3, the upper section of the tunnel is excavated by means of multiple cycle footage blasting; wherein, before each cycle footage blasting, the temporary support corresponding to the cycle footage blasting length is removed; After the cyclic footage blasting, the initial support for the upper step is applied and closed to form a ring with the initial support for the lower step.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述每完成一次循环进尺爆破后,施作下台阶初期支护以及所述下台阶的临时拱部的临时支护,具体包括:According to the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application, after each cycle footage blasting is completed, the initial support for the lower step and the temporary support for the temporary arch of the lower step are performed, specifically include:
在所述下台阶的临时拱部喷射混凝土;shotcrete at the temporary arch of the lower steps;
在所述下台阶的底面和侧墙施作下台阶格栅支护;Apply lower step grille support on the bottom surface and side wall of the lower step;
在所述下台阶的临时拱部设置工字钢,所述工字钢的两端分别与所述侧墙处的所述下台阶格栅支护固定连接;An I-beam is arranged on the temporary arch of the lower step, and both ends of the I-beam are respectively supported and fixedly connected to the lower step grille at the side wall;
在所述下台阶的底面和侧墙喷射混凝土进行封闭。The bottom surface and side walls of the lower steps are sprayed concrete for sealing.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述在所述下台阶的底面和侧墙喷射混凝土进行封闭后,还包括,分别在所述下台阶的两侧侧墙处的所述下台阶格栅支护搭设锁脚锚管并进行注浆。According to an embodiment of the tunnel excavation method for upper soft and lower hard strata, after the bottom surface and side walls of the lower step are sealed by spraying concrete, the method further includes: respectively placing side walls on both sides of the lower step. The lower step grille support at the place is set up with locking foot anchor pipes and grouted.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述在每一次循环进尺爆破之前,先拆除该循环进尺爆破长度对应的所述临时支护,具体包括:将所述工字钢与所述侧墙处的所述下台阶格栅支护之间的连接螺栓割除或将所述工字钢从根部割断。According to the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application, before each cyclic footage blasting, the temporary support corresponding to the cyclic footage blasting length is removed, specifically comprising: removing the engineering The connecting bolts between the steel beam and the lower step grille support at the side wall are cut off or the I-beam is cut off from the root.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述S1具体包括:According to the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application, the S1 specifically includes:
从地面在隧道拱顶的设定范围的地层内施作止水帷幕,并在所述止水帷幕所围设的区域内进行注浆加固;或者,从所述隧道内在所述隧道拱顶的设定范围的地层内施作半断面帷幕注浆加固;From the ground, a water-stop curtain is installed in the stratum within the set range of the tunnel vault, and grouting reinforcement is performed in the area surrounded by the water-stop curtain; or, from the inside of the tunnel, the tunnel vault is Apply half-section curtain grouting reinforcement in the stratum within the set range;
沿所述隧道的开挖轮廓线施作超前中管棚支护。The advanced middle pipe shed support is applied along the excavation outline of the tunnel.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述施作上台阶初期支护,包括:According to the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application, the performing initial support for upper steps includes:
在所述上台阶的拱部施作上台阶格栅支护并与所述下台阶格栅支护固定连接;An upper step grille support is applied to the arch of the upper step and is fixedly connected with the lower step grille support;
在所述上台阶的拱部喷射混凝土进行封闭。The arches of the upper steps are sprayed concrete for sealing.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,还包括每完成一次或多次循环进尺爆破后,在所述隧道的拱部施作超前小导管支护;According to an embodiment of the present application, the tunnel excavation method for upper soft and lower hard strata further includes applying advanced small conduit support to the arch of the tunnel after completing one or more cycles of footage blasting;
其中,在所述上台阶的拱部施作上台阶格栅支护的同时,在所述上台阶初期支护内预埋PVC管;在所述上台阶的拱部喷射混凝土进行封闭后,在所述PVC管内钻孔,在所述孔内设置超前小导管。Wherein, while the arch of the upper step is supported by the upper step grid, the PVC pipe is pre-buried in the initial support of the upper step; after the arch of the upper step is sealed by spraying concrete, Drill holes are drilled in the PVC pipe, and a small lead pipe is arranged in the hole.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述上台阶格栅支护的钢拱架之间和/或所述下台阶格栅支护的钢拱架之间均采用套筒连接。According to the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application, the steel arches supported by the upper step grid and/or the steel arches supported by the lower step grid are Use socket connection.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述下台阶的循环进尺爆破采用电子雷管水压控制爆破方式,所述上台阶的循环进尺爆破采用电子雷管逐层剥离控制爆破方式。According to an embodiment of the tunnel excavation method for upper soft and lower hard strata, the cyclic footage blasting of the lower step adopts an electronic detonator water pressure control blasting method, and the cyclic footage blasting of the upper step adopts the electronic detonator layer-by-layer peeling control. blasting method.
根据本申请一个实施例的上软下硬地层的隧道开挖方法,所述中管棚侵入所述上台阶初期支护的轮廓线的部分的直径小于所述中管棚侵入地层的部分的直径。According to the tunnel excavation method for upper soft and lower hard formations according to an embodiment of the present application, the diameter of the part of the middle pipe shelter intruding into the contour line of the initial support of the upper step is smaller than the diameter of the part of the middle pipe shelter intruding into the stratum .
本申请实施例提供的本申请实施例提供的上软下硬地层的隧道开挖方法,通过先进行下台阶开挖,再进行上台阶开挖的反台阶施工法,下台阶和上台阶均采用多次循环进尺爆破,下台阶每次爆破完成后施作下台阶初期支护和下台阶临时拱部的临时支护,上台阶每次爆破前先拆除对应的临时支护,使上台阶爆破时的作用力向已开挖的下台阶释放,从而较大程度的减轻了上台阶爆破时对隧道拱部的反作用力,降低了坍塌和突水突泥的风险,提高了施工的安全性。The tunnel excavation method for the upper soft and lower hard stratum provided by the embodiment of the present application is a reverse step construction method of excavating the lower step first, and then performing the upper step excavation, and both the lower step and the upper step are adopted. Multiple cycle footage blasting. After each blasting of the lower steps, the initial support of the lower steps and the temporary support of the temporary arch of the lower steps shall be applied. The corresponding temporary supports shall be removed before each blasting of the upper steps so that the The force is released to the excavated lower steps, thereby greatly reducing the reaction force on the tunnel arch when the upper steps are blasted, reducing the risk of collapse and water and mud inrush, and improving the safety of construction.
附图说明Description of drawings
为了更清楚地说明本申请实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作一简单地介绍,显而易见地,下面描述中的附图是本申请的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the following will briefly introduce the accompanying drawings used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are some embodiments of the present application. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without any creative effort.
图1是本申请实施例上软下硬地层的隧道开挖方法的流程示意图;Fig. 1 is the schematic flow chart of the tunnel excavation method of upper soft and lower hard strata in the embodiment of the present application;
图2是本申请实施例上软下硬地层的隧道开挖方法的断面示意图;2 is a schematic cross-sectional view of a tunnel excavation method for upper soft and lower hard strata in the embodiment of the present application;
图3是本申请实施例上软下硬地层的隧道开挖方法的纵向剖面示意图。3 is a schematic longitudinal cross-sectional view of a tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application.
附图标记:Reference number:
1、下台阶;2、上台阶;121、下台阶格栅支护;122、锁脚锚管;111、混凝土;11、临时拱部;3、中管棚;4、超前小导管;211、上台阶格栅支护;112、工字钢;5、防水层;6、二次衬砌。1. Lower steps; 2. Upper steps; 121. Lower steps grid support; 122. Locking anchors; 111. Concrete; 11. Temporary arches; 3. Middle pipe shed; 4. Leading small pipes; 211. Upper step grille support; 112, I-beam; 5, waterproof layer; 6, secondary lining.
具体实施方式Detailed ways
为使本申请实施例的目的、技术方案和优点更加清楚,下面将结合本申请实施例中的附图,对本申请实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本申请一部分实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本申请保护的范围。In order to make the purposes, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be described clearly and completely below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments It is a part of the embodiments of the present application, but not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present application.
在本申请实施例的描述中,需要说明的是,除非另有明确的规定和限定,术语“第一”“第二”是为了清楚说明产品部件进行的编号,不代表任何实质性区别。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本申请实施例中的具体含义。In the description of the embodiments of the present application, it should be noted that, unless otherwise expressly specified and limited, the terms "first" and "second" are used to clearly describe the numbering of product components and do not represent any substantial difference. Those of ordinary skill in the art can understand the specific meanings of the above terms in the embodiments of the present application according to specific situations.
在本申请的描述中,需要说明的是,除非另有明确的规定和限定,术语“安装”“相连”“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本申请中的具体含义。In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection, Or integrally connected; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal communication between the two components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood in specific situations.
下面结合图1~图3描述本申请实施例提供的上软下硬地层的隧道开挖方法。The following describes the tunnel excavation method for upper soft and lower hard strata provided by the embodiments of the present application with reference to FIGS. 1 to 3 .
如图1所示为本申请实施例上软下硬地层的隧道开挖方法的流程示意图,本申请实施例将隧道断面分为上下两个部分,采用先开挖下台阶1后开挖上台阶2的方式循环开挖。如图2所示为本申请实施例上软下硬地层的隧道开挖方法的断面示意图,如图3所示为本申请实施例上软下硬地层的隧道开挖方法的纵向剖面示意图。开挖步骤包括:As shown in FIG. 1 , it is a schematic flow chart of a tunnel excavation method for upper soft and lower hard strata in the embodiment of the application. In the embodiment of the application, the tunnel section is divided into upper and lower parts, and the lower step 1 is excavated first and then the upper step is excavated. 2 way cycle excavation. FIG. 2 is a schematic cross-sectional view of the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application, and FIG. 3 is a longitudinal cross-sectional schematic diagram of the tunnel excavation method for upper soft and lower hard strata according to an embodiment of the present application. The excavation steps include:
S1,在隧道的拱部施作超前支护。S1, implement advance support on the arch of the tunnel.
S2,在隧道的下断面采用多次循环进尺爆破的方式开挖下台阶1;其中,每完成一次循环进尺爆破后,施作下台阶初期支护以及下台阶1的临 时拱部11的临时支护。S2, the lower section of the tunnel is excavated by the method of multiple cycle footage blasting; wherein, after each cycle footage blasting is completed, the initial support of the lower step and the temporary support of the temporary arch 11 of the lower step 1 are applied. protect.
具体的,在隧道的下断面采用循环进尺爆破的方式开挖下台阶1,下台阶1的一次开挖长度可根据超前支护的长度确定。例如,超前支护采用的中管棚3的长度为10m,纵向搭接4m,则下台阶1的一次开挖长度约为6m。若每次循环进尺爆破1m,则需要经过6次爆破完成下台阶1的开挖。每次爆破完成后,会在下台阶1顶部形成长度为1m的临时拱部11。在每完成一次循环进尺爆破后,及时完成下台阶初期支护和临时拱部11的临时支护。为了进一步提高施工的安全性,临时拱部11与下台阶的底面之间还可以设置竖直方向的工字钢如I18工字钢,作为临时支顶。Specifically, the lower bench 1 is excavated by means of cyclic footage blasting at the lower section of the tunnel, and the length of one excavation of the lower bench 1 can be determined according to the length of the advance support. For example, if the length of the middle pipe shed 3 used for the advanced support is 10m, and the longitudinal overlap is 4m, the length of one excavation of the lower step 1 is about 6m. If the footage is blasted 1m per cycle, it will take 6 blasts to complete the excavation of the next step 1. After each blasting, a temporary arch 11 with a length of 1 m will be formed on the top of the lower step 1 . After each cycle footage blasting is completed, the initial support of the descending steps and the temporary support of the temporary arch 11 are completed in time. In order to further improve the safety of construction, vertical I-beams such as I18 I-beams may also be arranged between the temporary arch 11 and the bottom surface of the lower step as a temporary support roof.
其中,下台阶1的循环进尺爆破采用电子雷管水压爆破方式。电子雷管可自由设定延时起爆时间(如50毫秒),可实现精准爆破控制和对施工噪声和爆破振动的控制。下台阶1的每一次循环进尺爆破采用2孔1段位的爆破方式,且中间孔先爆,以减少后续爆破对拱部的反作用力。采用水压爆破进行控制,炸药利用率得到提高,单次起爆药量得以减少,爆破碎石块度均匀,且现场降尘较快。本申请实施例中,炮孔按照设计要求增加相应数量的水袋,并用炮泥对炮孔做好封堵。Among them, the cyclic footage blasting of the lower step 1 adopts the electronic detonator hydraulic blasting method. The electronic detonator can freely set the delayed initiation time (such as 50 milliseconds), which can realize precise blasting control and control of construction noise and blasting vibration. Each cycle footage blasting of the lower step 1 adopts the blasting method of 2 holes and 1 stage, and the middle hole is blasted first to reduce the reaction force of the subsequent blasting on the arch. Hydraulic blasting is used for control, the utilization rate of explosives is improved, the amount of single-shot blasting charges is reduced, the degree of blasting and crushing is uniform, and the on-site dust removal is faster. In the embodiment of the present application, a corresponding number of water bags are added to the blast hole according to the design requirements, and the blast hole is sealed with the blast mud.
S3,在隧道的上断面采用多次循环进尺爆破的方式开挖上台阶2。其中,在每次循环进尺爆破之前,先拆除该循环进尺爆破长度对应的临时支护;每完成一次循环进尺爆破后,施作上台阶初期支护并与所述下台阶初期支护封闭成环。S3, on the upper section of the tunnel, the upper step 2 is excavated by means of multiple cycle footage blasting. Among them, before each cycle footage blasting, the temporary support corresponding to the cycle footage blasting length is removed first; after each cycle footage blasting is completed, the upper step initial support is applied and closed with the lower step initial support. .
具体的,由于上台阶2处于较软地层中,且拱部覆岩十分薄弱,为了尽可能降低爆破风险,本申请实施例中,上台阶2的循环进尺爆破采用电子雷管逐层剥离爆破方式,例如,每次循环进尺0.5m,上台阶2与下台阶1的开挖长度相同,若上台阶2一次开挖长度为6m,则需要经过12次爆破以完成上台阶2的开挖。上台阶2的每一次循环进尺爆破采用单孔单段爆破方式,且中间孔先爆,以减少后续爆破对拱部的反作用力。在每一次循环进尺爆破之前,先拆除该进尺0.5m范围内的临时拱部的临时支护,使上台阶2爆破时的大部分能量向已开挖的下台阶1的方向释放,能够较大程度的减轻爆破对拱部的反作用力。每完成一次循环进尺爆破后,及时完成上台阶初期支护并与所述下台阶初期支护封闭成环。Specifically, since the upper step 2 is in a relatively soft stratum, and the overlying rock of the arch is very weak, in order to reduce the blasting risk as much as possible, in the embodiment of the present application, the cyclic footage blasting of the upper step 2 adopts the electronic detonator layer-by-layer stripping blasting method. For example, each cycle footage is 0.5m, and the excavation length of the upper step 2 and the lower step 1 is the same. If the excavation length of the upper step 2 is 6m, 12 blasts are required to complete the excavation of the upper step 2. Each cycle footage blasting of the upper step 2 adopts a single-hole single-stage blasting method, and the middle hole is blasted first to reduce the reaction force of the subsequent blasting on the arch. Before each cycle shot blasting, remove the temporary support of the temporary arch within the range of 0.5m, so that most of the energy during blasting of the upper step 2 is released in the direction of the excavated lower step 1, which can be larger The degree of reduction of the blasting reaction force on the arch. After each cycle footage blasting is completed, the initial support for the upper step is completed in time and the initial support for the lower step is closed into a ring.
以单次开挖台阶的长度为6m为例,先在隧道的下断面开挖6m长的下台阶1,再在隧道的上断面开挖6m的上台阶2,视为完成一次隧道的开挖循环,根据需要开挖的隧道长度,进行多次开挖循环。进一步的,在完成上述步骤S1-S3后,还要对后方已开挖的隧道敷设防水层5和浇注二次衬砌6。Taking the length of a single excavation step as an example of 6m, first excavate a 6m-long lower step 1 on the lower section of the tunnel, and then excavate a 6m-long upper step 2 on the upper section of the tunnel, which is regarded as the completion of one tunnel excavation. Cycle, perform multiple excavation cycles according to the length of the tunnel to be excavated. Further, after the above steps S1-S3 are completed, a waterproof layer 5 and a secondary lining 6 are also laid on the tunnel that has been excavated at the rear.
本申请实施例提供的本申请实施例提供的上软下硬地层的隧道开挖方法,通过先进行下台阶开挖,再进行上台阶开挖的反台阶施工法,下台阶和上台阶均采用多次循环进尺爆破,下台阶每次爆破完成后施作下台阶初期支护和下台阶临时拱部的临时支护,上台阶每次爆破前先拆除对应的临时支护,使上台阶爆破时的作用力向已开挖的下台阶释放,从而较大程度的减轻了上台阶爆破时对隧道拱部的反作用力,降低了坍塌和突水突泥的风险,提高了施工的安全性。The tunnel excavation method for the upper soft and lower hard stratum provided by the embodiment of the present application is a reverse step construction method of excavating the lower step first, and then performing the upper step excavation, and both the lower step and the upper step are adopted. Multiple cycle footage blasting. After each blasting of the lower steps, the initial support of the lower steps and the temporary support of the temporary arch of the lower steps shall be applied. The corresponding temporary supports shall be removed before each blasting of the upper steps so that the The force is released to the excavated lower steps, thereby greatly reducing the reaction force on the tunnel arch when the upper steps are blasted, reducing the risk of collapse and water and mud inrush, and improving the safety of construction.
本申请实施例中,S1中在隧道的拱部施作超前支护,包括步骤:In the embodiment of the present application, performing advance support on the arch of the tunnel in S1 includes the steps:
S11,当隧道上方地面存在施作空间时,采用从地面施作超前支护的方式,即从地面在隧道拱顶的设定范围的地层内施作止水帷幕,并在止水帷幕所围设的区域内进行注浆加固。具体的,在隧道上方对应的地面上,沿隧道宽度方向和长度方向的设定范围内施作旋喷桩、搅喷桩止水帷幕,形成口字形或日字形或目字形等止水体。然后,根据设计图孔位、钻孔参数,在止水帷幕所围设的区域内钻孔,并在孔内进行单液水泥浆注浆加固,注浆加固区域覆盖环绕隧道的开挖轮廓线外侧设定范围,从而形成与隧道同轴的连续止水体。具体的,根据设计图孔位、钻孔参数,在隧道上方对应的地面上直接钻孔,然后在孔内进行注浆。S11, when there is a working space on the ground above the tunnel, the method of applying advanced support from the ground is adopted, that is, a water-stop curtain is installed from the ground in the stratum of the set range of the tunnel vault, and the water-stop curtain is surrounded by the water-stop curtain. Grouting reinforcement is carried out in the designated area. Specifically, on the corresponding ground above the tunnel, the water-stop curtains of the rotary jet piles and the stirring jet piles are applied within the set range along the width direction and length direction of the tunnel to form a water-stop body such as a mouth-shaped, a sun-shaped or a mesh-shaped water body. Then, according to the hole position and drilling parameters in the design drawing, drill holes in the area enclosed by the water-stop curtain, and perform single-liquid cement grouting reinforcement in the hole, and the grouting reinforcement area covers the excavation contour line surrounding the tunnel. A range is set on the outside to form a continuous water stop coaxial with the tunnel. Specifically, according to the hole position and drilling parameters in the design drawing, drill holes directly on the corresponding ground above the tunnel, and then grouting is carried out in the holes.
当隧道上方地面不适合施工时,例如道路上方为公路或建筑物时,则采用从隧道内施作超前支护的方式,即从隧道内在隧道拱顶的设定范围的地层内施作半断面帷幕注浆加固。例如,使注浆管从隧道的上断面伸入隧道开挖轮廓线外侧,在开挖轮廓线外侧和沿隧道长度方向的设定范围内进行注浆加固,从而形成与隧道同轴的连续止水体。When the ground above the tunnel is not suitable for construction, such as when there is a road or a building above the road, the method of applying advanced support from the tunnel is adopted, that is, the half-section is applied from the stratum within the set range of the tunnel vault within the tunnel. Curtain grouting reinforcement. For example, the grouting pipe extends from the upper section of the tunnel to the outside of the tunnel excavation outline, and grouting is performed outside the excavation outline and within the set range along the length of the tunnel, so as to form a continuous stop coaxial with the tunnel. Water body.
具体的,根据设计图孔位、钻孔参数,在工作面(隧道上断面)上放出钻孔位置,并用油漆标定。在标定位置埋设孔口管,孔口管与安装面密实固结,以保证不漏浆、不串浆。其埋设方法为:利用钻机在标定的钻孔 位置进行钻孔,成孔完成后将带有孔口法兰的孔口管插入并外露20-30cm,在孔口管外壁缠裹土工布后采用钻机将孔口管顶入钻孔,灌注双液浆,最终完成孔口管的埋设。例如,钻孔直径为115mm,长度4m左右,孔口管采用直径108mm、长3m的无缝钢管,土工布厚度1-3cm左右,长度30cm左右,孔口法兰与直径42mm的注浆管相匹配。Specifically, according to the hole position and drilling parameters in the design drawing, the drilling position is released on the working face (the upper section of the tunnel) and calibrated with paint. The orifice pipe is buried at the calibration position, and the orifice pipe is tightly consolidated with the installation surface to ensure no leakage or stringing of slurry. The burying method is as follows: use a drilling rig to drill at the calibrated drilling position, insert the orifice tube with the orifice flange and expose it for 20-30cm after the hole is formed, and wrap the outer wall of the orifice tube with geotextile. The drilling rig pushes the orifice pipe into the borehole, pours the double-liquid slurry, and finally completes the burial of the orifice pipe. For example, the diameter of the borehole is 115mm and the length is about 4m. The orifice pipe is made of seamless steel pipe with a diameter of 108mm and a length of 3m. The thickness of the geotextile is about 1-3cm and the length is about 30cm. match.
孔口管全部埋设完成后,更换钻机钻头,在孔口管内钻孔至设计深度,将注浆管插入该孔并与孔口管的孔口法兰连接,从而完成孔口管与注浆系统的连接。然后,通过压水检测注浆管的管路的密封性,同时冲洗岩石裂隙,扩大浆液通路,增加浆液冲塞的密实性,清孔完毕后开始进行注浆施工。例如,确保钻孔的终孔直径不小于75mm。注浆管采用直径42mm的PVC管,其中,注浆管沿其长度方向间隔50cm的设置梅花形分布的注浆口,注浆口直径10mm。压力砂层注浆压力为0.5-1.0MPa,现场遇到岩层注浆时,选择1.0~1.5MPa。注浆顺序为:先注外圈,后注内圈,同一圈由下而上间隔施作。这样后序孔可检查前序孔的注浆效果。After the orifice pipe is all buried, replace the drill bit, drill the hole in the orifice pipe to the design depth, insert the grouting pipe into the hole and connect it with the orifice flange of the orifice pipe to complete the orifice pipe and grouting system Connection. Then, the tightness of the pipeline of the grouting pipe is detected by the pressurized water, and the cracks in the rock are flushed, the slurry passage is enlarged, and the compactness of the slurry flushing is increased. After the hole is cleared, the grouting construction is started. For example, make sure that the final hole diameter of the drilled hole is not less than 75mm. The grouting pipe adopts a PVC pipe with a diameter of 42 mm, wherein the grouting pipe is provided with grouting ports with a plum-shaped distribution at intervals of 50 cm along the length direction of the grouting pipe, and the diameter of the grouting port is 10 mm. The grouting pressure of the pressure sand layer is 0.5-1.0MPa. When the rock layer is grouted on site, choose 1.0-1.5MPa. The grouting sequence is: the outer ring is injected first, the inner ring is injected later, and the same ring is applied at intervals from bottom to top. In this way, the subsequent holes can check the grouting effect of the previous holes.
S12,沿隧道的开挖轮廓线施作超前中管棚支护。帷幕注浆完成之后施作中管棚支护。例如,中管棚3采用直径89mm、长10m、厚5mm的钢管,在隧道拱部不小于150°的范围内,沿开挖轮廓线以环向间距0.25m对称布置中管棚3。S12, implement advanced middle pipe shed support along the excavation outline of the tunnel. After the curtain grouting is completed, the middle pipe shed support is applied. For example, the middle pipe shed 3 is made of steel pipes with a diameter of 89 mm, a length of 10 m, and a thickness of 5 mm. The middle pipe shed 3 is symmetrically arranged along the excavation contour with a circumferential spacing of 0.25 m within the range of the tunnel arch not less than 150°.
当超前支护采用帷幕注浆和超前中管棚支护时,超前支护的长度由帷幕注浆和中管棚超前支护施工的长度决定。例如,中管棚3长度10m,沿隧道长度方向纵向搭接4m,则一次中管棚支护的长度约为6m。在一次帷幕注浆的长度应不小于6m的情况下,一次超前支护的长度达到6m,则一次开挖下台阶1和一次开挖上台阶2的长度均为6m。When curtain grouting and advanced mid-pipe shed support are used for advance support, the length of advance support is determined by the length of curtain grouting and mid-pipe shed advance support construction. For example, if the length of the middle pipe shed 3 is 10m, and the longitudinal overlap is 4m along the length of the tunnel, the length of the primary support of the middle pipe shed is about 6m. In the case that the length of one curtain grouting should not be less than 6m, and the length of one advance support reaches 6m, then the length of one excavation lower step 1 and one excavation upper step 2 are both 6m.
本申请实施例中,步骤S2中,每完成一次循环进尺爆破后,施作下台阶初期支护以及下台阶1的临时拱部11的临时支护,具体包括:In the embodiment of the present application, in step S2, after each cycle footage blasting is completed, the initial support of the lower step and the temporary support of the temporary arch 11 of the lower step 1 are applied, specifically including:
S21,在下台阶1的临时拱部11喷射混凝土111。S21 , spraying concrete 111 on the temporary arch 11 of the lower step 1 .
S22,在下台阶1的底面和侧墙施作下台阶格栅支护121。S22, the lower step grid support 121 is applied to the bottom surface and side walls of the lower step 1.
S23,在下台阶1的临时拱部11设置工字钢112,工字钢112与侧墙处的下台阶格栅支护121固定连接。S23, an I-beam 112 is provided on the temporary arch 11 of the lower step 1, and the I-beam 112 is fixedly connected to the lower step grille support 121 at the side wall.
S24,在下台阶1的底面和侧墙喷射混凝土进行封闭。S24, spraying concrete on the bottom surface and side wall of the lower step 1 for sealing.
其中,每次完成一次循环进尺爆破后,立即对临时拱部11喷射混凝土111处理,以加固临时拱部,保证施工安全性。例如,喷射混凝土111的厚度为150mm。工字钢112与侧墙处的下台阶格栅支护121通过连接板和螺栓固定连接连接。施工时确保工字钢113与格栅拱架连接牢固,且与临时拱部11密贴,不密实处采用喷射混凝土封闭密实。例如,工字钢112采用I18工字钢。工字钢112沿隧道的开挖进尺方向纵向间距1m,若每次爆破的循环进尺为1m,则每次循环进尺爆破后,在临时拱部11设置一个工字钢。在下台阶1的底面和侧墙喷射混凝土厚度250mm。Wherein, after each completion of one cycle footage blasting, the temporary arch 11 is immediately sprayed with concrete 111 to reinforce the temporary arch and ensure construction safety. For example, the thickness of the shotcrete 111 is 150 mm. The I-beam 112 is connected with the lower step grille support 121 at the side wall through a connecting plate and bolts. During construction, ensure that the I-beam 113 is firmly connected to the grille arch, and is closely attached to the temporary arch 11, and the non-compact places are sealed and compacted with shotcrete. For example, I-beam 112 adopts I18 I-beam. The longitudinal spacing of the I-beams 112 is 1m along the excavation footage direction of the tunnel. If the cyclic footage of each blasting is 1m, then after each cycle footage is blasted, an I-beam is installed in the temporary arch 11 . The thickness of sprayed concrete is 250mm on the bottom surface and side wall of the lower step 1.
在下台阶1的每一次循环进尺爆破之前,先拆除该循环进尺爆破长度对应的临时支护,具体包括:将工字钢112与侧墙处的下台阶格栅支护121之间的连接螺栓割除或将工字钢112从根部割断。其中,在拆除工字钢112之前,先采用人工和破碎锤将工字钢112与侧墙处的下台阶格栅支护121的连接板处的喷射混凝土清理干净。Before each cycle footage blasting of the lower step 1, first remove the temporary support corresponding to the cycle footage blasting length, specifically including: cutting off the connecting bolts between the I-beam 112 and the lower step grille support 121 at the side wall Or cut the I-beam 112 from the root. Wherein, before removing the I-beam 112, the shotcrete at the connection plate between the I-beam 112 and the lower step grille support 121 at the side wall is cleaned by hand and a breaking hammer.
进一步的,在下台阶1的底面和侧墙喷射混凝土进行封闭后,还包括,分别在下台阶1的两侧侧墙处的下台阶格栅支护121搭设锁脚锚管122并进行注浆。例如,锁脚锚管122的长度为3.5m,每侧搭设两根锁脚锚管122,注浆压力为0.5-1.0MPa。Further, after the bottom surface and side walls of the lower step 1 are sealed with sprayed concrete, it also includes setting up locking foot anchor pipes 122 on the lower step grid supports 121 at the side walls on both sides of the lower step 1 and grouting. For example, the length of the foot-locking anchor pipe 122 is 3.5 m, two foot-locking anchor pipes 122 are erected on each side, and the grouting pressure is 0.5-1.0 MPa.
在上述实施例的基础上,步骤S3中,施作上台阶初期支护,具体包括:On the basis of the above embodiment, in step S3, the initial support for the upper steps is performed, which specifically includes:
S31,在上台阶2的拱部施作上台阶格栅支护211并与所述下台阶格栅支护固定连接。例如上台阶格栅与下台阶格栅之间通过连接板连接,使上台阶格栅与下台阶格栅封闭成环。S31, the upper step grille support 211 is applied to the arch of the upper step 2 and fixedly connected to the lower step grille support. For example, the upper step grid and the lower step grid are connected by connecting plates, so that the upper step grid and the lower step grid are closed into a ring.
S32,在上台阶2的拱部喷射混凝土进行封闭。例如,在上台阶的拱部21喷射混凝土厚度250mm,其中,上台阶2的拱部包括拱顶和上台阶2两侧与拱顶相连的侧墙。S32, spraying concrete on the arch of the upper step 2 for sealing. For example, the thickness of shotcrete in the arch 21 of the upper step 2 is 250 mm, wherein the arch of the upper step 2 includes a vault and side walls connected to the vault on both sides of the upper step 2 .
进一步的,步骤S3还包括:Further, step S3 also includes:
S33,每完成一次或多次循环进尺爆破后,在隧道的拱部施作超前小导管支护。其中,若按超前小导管4数量为34根,长度为3.5m,从钻孔至注浆结束,需要4小时左右。然而,隧道拱部本身覆岩薄,其上为砂层,需要尽快封闭。因此,在上台阶2的拱部施作上台阶格栅支护211的同时, 按照超前小导管4的设计位置和角度,在上台阶初期支护内预埋PVC管,在上台阶2的拱部喷射混凝土进行封闭后,在PVC管内钻孔,该钻孔用于设置超前小导管4。这样可以减少围岩暴露时间过长而导致坍塌的风险,确保工程安全。S33, after each completion of one or more cycles of footage blasting, a small advanced duct support is applied to the arch of the tunnel. Among them, if the number of leading small pipes 4 is 34 and the length is 3.5m, it will take about 4 hours from drilling to the end of grouting. However, the overlying rock of the tunnel arch itself is thin, and the sand layer above it needs to be closed as soon as possible. Therefore, when the arch of the upper step 2 is used as the upper step grille support 211, according to the design position and angle of the advanced small conduit 4, the PVC pipe is pre-buried in the initial support of the upper step, and the arch of the upper step 2 is pre-buried. After the part of the sprayed concrete is sealed, a hole is drilled in the PVC pipe, and the drilled hole is used to set the leading small conduit 4 . This can reduce the risk of collapse caused by the exposure of surrounding rock for too long, and ensure the safety of the project.
例如,超前小导管4的长度为3.5m,环向间距0.25m,在上台阶2的拱顶不小于150°的范围布置超前小导管4,超前小导管4的数量根据隧道的实际尺寸确定。纵向搭接2m,即纵距1.5m,若一次循环进尺爆破长度为0.5m,则可爆破三次之后施作超前小导管4。当然,为了增加施工的安全性,也可以将超前小导管4的纵距缩短至0.5m或1m,在每完成一次或两次循环进尺爆破和上台阶初期支护后,即施作超前小导管支护。For example, the length of the leading small ducts 4 is 3.5m, the circumferential spacing is 0.25m, the leading small ducts 4 are arranged in the range of not less than 150° on the dome of the upper step 2, and the number of the leading small ducts 4 is determined according to the actual size of the tunnel. The longitudinal overlap is 2m, that is, the longitudinal distance is 1.5m. If the blasting length of one cycle footage is 0.5m, it can be blasted three times and then applied to the leading small conduit 4. Of course, in order to increase the safety of construction, the longitudinal distance of the leading small duct 4 can also be shortened to 0.5m or 1 m. After completing one or two cycle footage blasting and initial support of the steps, the leading small duct 4 is applied. support.
格栅支护由沿隧道开挖方向设置的多个钢拱架通过连接钢筋连接固定而形成。一般通过单面焊接连接钢筋的方式连接相邻的钢拱架,需要给下一循环连接钢筋预留焊接长度,该焊接长度至少为连接钢筋直径的10倍。这样会导致一次爆破进尺较长,且最后一榀格栅与掌子面距离较远,这一段预留长度的岩体处于临空未支护状态,给施工带来安全隐患。The grid support is formed by connecting and fixing a plurality of steel arches arranged along the tunnel excavation direction by connecting steel bars. Generally, the adjacent steel arches are connected by single-sided welding connecting steel bars, and the welding length needs to be reserved for the next circulating connecting steel bars, and the welding length is at least 10 times the diameter of the connecting steel bars. This will lead to a long blasting footage and a long distance between the last grille and the face of the tunnel. The rock mass of this reserved length is in a state of being in the air and unsupported, which brings safety hazards to the construction.
对此,本申请实施例中,上台阶格栅支护211的钢拱架之间以及下台阶格栅支护的钢拱架之间均采用套筒连接。具体的,相邻两个钢拱架之间通过两根钢筋和一个套筒固定连接,连接钢筋的一端设有外螺纹,套筒内设有内螺纹。In this regard, in the embodiment of the present application, the steel arches of the upper step grille support 211 and the steel arches of the lower step grille support are connected by sleeves. Specifically, two adjacent steel arches are fixedly connected by two steel bars and a sleeve, one end of the connecting steel bars is provided with an external thread, and the sleeve is provided with an internal thread.
安装时,例如,先支立第一钢拱架,将连接钢筋没有螺纹的一端焊接于第一钢拱架,并将套筒螺接于连接钢筋的螺纹端。然后,在支立第二钢拱架之前,先将另一连接钢筋与前一连接钢筋端部的套筒螺接,支立第二钢拱架后,再将另一连接钢筋与第二钢拱架对应焊接,从而在纵向上通过两根钢筋和一个套筒完成两个钢拱架的焊接固定。其中,在钢拱架环向上每间隔1m进行一次焊接固定。在每次爆破进尺内支立最后一个钢拱架后,将套筒安装在连接钢筋上,喷射混凝土时将其埋设在初期支护中。从而不需要预留较长的下循环连接钢筋的单面焊接长度,而只需要将套筒预留出较短的长度即可,从而减少了纵向连接钢筋的焊接长度,从而减少单次开挖长度,使格栅拱架尽量靠近掌子面,减少掌子面临空未支护的岩体长度,增强了工程安全系数。During installation, for example, first stand up the first steel arch, weld the unthreaded end of the connecting steel bar to the first steel arch, and screw the sleeve to the threaded end of the connecting steel bar. Then, before the second steel arch is erected, the other connecting bar is screwed to the sleeve at the end of the previous connecting bar. After the second steel arch is erected, the other connecting bar is connected to the second steel arch. The arches are welded accordingly, so that the two steel arches are welded and fixed in the longitudinal direction by two steel bars and a sleeve. Among them, welding and fixing are carried out at intervals of 1m on the steel arch ring upward. After the last steel arch is erected in each blasting footage, the sleeve is installed on the connecting steel bar, and it is buried in the initial support when spraying concrete. Therefore, it is not necessary to reserve a long single-sided welding length of the lower circulation connecting steel bar, but only a short length of the sleeve needs to be reserved, thereby reducing the welding length of the longitudinal connecting steel bar, thereby reducing a single excavation. The length of the grid arch is as close as possible to the face of the tunnel, reducing the length of the unsupported rock mass facing the tunnel, and enhancing the engineering safety factor.
上台阶2爆破完成后,因部分中管棚3侵入上台阶初期支护轮廓线内,开挖过程中需要对其进行割除。然而因中管棚3口径较大,割除困难,导致作业周期长,不利于上台阶2的快速封闭。因此,在上述实施例的基础上,中管棚3侵入上台阶初期支护轮廓线的部分的直径小于中管棚3侵入地层的部分的直径。例如,直径89mm的中管棚3的尾部需要割除段采用直径为42mm的钢管代替,长度为1.5m,两段通过开口钢板焊接在一起,以利于后期施工时对侵限钢管的割除,从而促进快速有效的对上台阶2进行封闭成环,减少工程风险。After the blasting of the upper step 2 is completed, because part of the middle pipe shed 3 intrudes into the initial support outline of the upper step, it needs to be cut off during the excavation process. However, due to the large diameter of the middle tube shed 3, it is difficult to cut it, resulting in a long operation cycle, which is not conducive to the rapid sealing of the upper step 2. Therefore, on the basis of the above-mentioned embodiment, the diameter of the part where the middle pipe shelter 3 intrudes into the initial support contour of the upper step is smaller than the diameter of the part where the middle pipe shelter 3 penetrates into the formation. For example, the tail of the middle pipe shed 3 with a diameter of 89mm needs to be replaced by a steel pipe with a diameter of 42mm and a length of 1.5m. The two sections are welded together by open steel plates, so as to facilitate the cutting of the intrusion-limiting steel pipe in the later construction, thereby promoting the The upper step 2 is quickly and effectively closed into a loop to reduce engineering risks.
本申请实施例中的格栅拱架之间的连接,包括下台阶初期支护和工字钢112的连接,均采用钢板和高强螺栓,需要焊接的部位,采用50焊条单面满焊。The connection between the grid arches in the embodiment of the present application, including the initial support of the lower step and the connection of the I-beam 112, are all made of steel plates and high-strength bolts, and the parts that need to be welded are fully welded with 50 electrodes on one side.
本申请实施例提供的上软下硬地层的隧道开挖方法,通过先开挖下台阶后开挖上台阶的反台阶施工方法,使上台阶爆破时的能量大部分向已开挖的下台阶方向释放,较大程度的减轻了爆破作业对隧道拱部的扰动,降低突水突泥的风险;通过精准控制爆破控制技术降低了爆破噪声和爆破振速,有效控制了周边环境和周边道路地表及管线沉降;采用水压爆破方式,降低了施工粉尘、有毒有害气体对作业人员健康的影响;通过在中管棚的侵限段设置小管径的钢管,以及格栅钢拱架之间采用套筒连接,工艺简便、便于操作,能够缩施工时间,以快速完成初期支护和封闭,实现了高效、安全地对下穿上软下硬地层的隧道的开挖作业。The tunnel excavation method for the upper soft and lower hard stratum provided by the embodiment of the present application, through the reverse step construction method of excavating the lower step first and then excavating the upper step, so that most of the energy during blasting of the upper step is directed to the excavated lower step. The direction release greatly reduces the disturbance of the blasting operation to the tunnel arch and reduces the risk of water inrush and mud inrush; through the precise control of the blasting control technology, the blasting noise and blasting vibration speed are reduced, and the surrounding environment and the surrounding road surface are effectively controlled and pipeline settlement; hydraulic blasting is adopted to reduce the impact of construction dust and toxic and harmful gases on the health of workers; small-diameter steel pipes are installed in the encroachment section of the middle pipe shed, and steel grids are used between the arches. Sleeve connection is simple and easy to operate, and can shorten the construction time, so as to quickly complete the initial support and sealing, and realize the efficient and safe excavation of the tunnel that goes through the soft and hard stratum below.
最后应说明的是:以上实施例仅用以说明本申请的技术方案,而非对其限制;尽管参照前述实施例对本申请进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本申请各实施例技术方案的精神和范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, but not to limit them; although the present application has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: it can still be The technical solutions described in the foregoing embodiments are modified, or some technical features thereof are equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions in the embodiments of the present application.

Claims (10)

  1. 一种上软下硬地层的隧道开挖方法,其特征在于,将隧道断面分为上下两个部分,开挖步骤包括:A tunnel excavation method for upper soft and lower hard stratum is characterized in that, the tunnel section is divided into upper and lower parts, and the excavation step comprises:
    S1,在所述隧道的拱部施作超前支护;S1, perform advanced support on the arch of the tunnel;
    S2,在所述隧道的下断面采用多次循环进尺爆破的方式开挖下台阶;其中,每完成一次循环进尺爆破后,施作下台阶初期支护以及所述下台阶的临时拱部的临时支护;S2, the lower section of the tunnel is excavated by means of multiple cycle footage blasting; wherein, after each cycle footage blasting is completed, the initial support of the lower step and the temporary arch of the lower step are used as temporary support. support;
    S3,在所述隧道的上断面采用多次循环进尺爆破的方式开挖上台阶;其中,在每一次循环进尺爆破之前,先拆除该循环进尺爆破长度对应的所述临时支护;每完成一次循环进尺爆破后,施作上台阶初期支护并与所述下台阶初期支护封闭成环。S3, the upper section of the tunnel is excavated by means of multiple cycle footage blasting; wherein, before each cycle footage blasting, the temporary support corresponding to the cycle footage blasting length is removed; After the cyclic footage blasting, the initial support for the upper step is applied and closed to form a ring with the initial support for the lower step.
  2. 根据权利要求1所述的上软下硬地层的隧道开挖方法,其特征在于,所述每完成一次循环进尺爆破后,施作下台阶初期支护以及所述下台阶的临时拱部的临时支护,具体包括:The tunnel excavation method for upper soft and lower hard strata according to claim 1, characterized in that, after each completion of one cycle footage blasting, the initial support of the lower step and the temporary support of the temporary arch of the lower step are applied. Support, including:
    在所述下台阶的临时拱部喷射混凝土;shotcrete at the temporary arch of the lower steps;
    在所述下台阶的底面和侧墙施作下台阶格栅支护;Apply lower step grille support on the bottom surface and side wall of the lower step;
    在所述下台阶的临时拱部设置工字钢,所述工字钢的两端分别与所述侧墙处的所述下台阶格栅支护固定连接;An I-beam is arranged on the temporary arch of the lower step, and both ends of the I-beam are respectively supported and fixedly connected to the lower step grille at the side wall;
    在所述下台阶的底面和侧墙喷射混凝土进行封闭。The bottom surface and side walls of the lower steps are sprayed concrete for sealing.
  3. 根据权利要求2所述的上软下硬地层的隧道开挖方法,其特征在于,所述在所述下台阶的底面和侧墙喷射混凝土进行封闭后,还包括,分别在所述下台阶的两侧侧墙处的所述下台阶格栅支护搭设锁脚锚管并进行注浆。The tunnel excavation method for upper soft and lower hard strata according to claim 2, characterized in that, after the bottom surface of the lower step and the side walls are sprayed with concrete, the method further comprises: The lower step grille support at the side walls on both sides is provided with locking foot anchor pipes and grouting.
  4. 根据权利要求2所述的上软下硬地层的隧道开挖方法,其特征在于,所述在每一次循环进尺爆破之前,先拆除该循环进尺爆破长度对应的所述临时支护,具体包括:将所述工字钢与所述侧墙处的所述下台阶格栅支护之间的连接螺栓割除或将所述工字钢从根部割断。The tunnel excavation method for upper soft and lower hard strata according to claim 2, characterized in that, before each cyclic footage blasting, the temporary support corresponding to the cyclic footage blasting length is removed, specifically including: The connecting bolts between the I-beam and the lower step grille support at the side wall are cut off or the I-beam is cut from the root.
  5. 根据权利要求1所述的上软下硬地层的隧道开挖方法,其特征在于,所述S1具体包括:The tunnel excavation method for upper soft and lower hard strata according to claim 1, wherein the S1 specifically includes:
    从地面在隧道拱顶的设定范围的地层内施作止水帷幕,并在所述止水 帷幕所围设的区域内进行注浆加固;或者,从所述隧道内在所述隧道拱顶的设定范围的地层内施作半断面帷幕注浆加固;From the ground, a water-stop curtain is installed in the stratum within the set range of the tunnel vault, and grouting reinforcement is performed in the area surrounded by the water-stop curtain; or, from the inside of the tunnel, the tunnel vault is Apply half-section curtain grouting reinforcement in the stratum within the set range;
    沿所述隧道的开挖轮廓线施作超前中管棚支护。The advanced middle pipe shed support is applied along the excavation outline of the tunnel.
  6. 根据权利要求2~5任一项所述的上软下硬地层的隧道开挖方法,其特征在于,所述施作上台阶初期支护,包括:The tunnel excavation method for upper soft and lower hard strata according to any one of claims 2 to 5, wherein the performing initial support for the upper step comprises:
    在所述上台阶的拱部施作上台阶格栅支护并与所述下台阶格栅支护固定连接;An upper step grille support is applied to the arch of the upper step and is fixedly connected with the lower step grille support;
    在所述上台阶的拱部喷射混凝土进行封闭。The arches of the upper steps are sprayed concrete for sealing.
  7. 根据权利要求6所述的上软下硬地层的隧道开挖方法,其特征在于,还包括:每完成一次或多次循环进尺爆破后,在所述隧道的拱部施作超前小导管支护;The tunnel excavation method for upper soft and lower hard strata according to claim 6, further comprising: after completing one or more cycles of footage blasting, applying an advanced small conduit support to the arch of the tunnel ;
    其中,在所述上台阶的拱部施作上台阶格栅支护的同时,在所述上台阶初期支护内预埋PVC管;在所述上台阶的拱部喷射混凝土进行封闭后,在所述PVC管内钻孔,在所述孔内设置超前小导管。Wherein, while the arch of the upper step is supported by the upper step grid, the PVC pipe is pre-buried in the initial support of the upper step; after the arch of the upper step is sealed by spraying concrete, Drill holes are drilled in the PVC pipe, and a small lead pipe is arranged in the hole.
  8. 根据权利要求6所述的上软下硬地层的隧道开挖方法,其特征在于,所述上台阶格栅支护的钢拱架之间和/或所述下台阶格栅支护的钢拱架之间均采用套筒连接。The tunnel excavation method for upper soft and lower hard strata according to claim 6, characterized in that, between the steel arches supported by the upper step grille and/or the steel arches supported by the lower step grille The frames are connected by sleeves.
  9. 根据权利要求1所述的上软下硬地层的隧道开挖方法,其特征在于,所述下台阶的循环进尺爆破采用电子雷管水压控制爆破方式,所述上台阶的循环进尺爆破采用电子雷管逐层剥离控制爆破方式。The tunnel excavation method for upper soft and lower hard strata according to claim 1, wherein the cyclic footage blasting of the lower step adopts an electronic detonator water pressure control blasting method, and the cyclic footage blasting of the upper step adopts an electronic detonator Layer-by-layer peeling and controlled blasting.
  10. 根据权利要求1所述的上软下硬地层的隧道开挖方法,其特征在于,所述中管棚侵入所述上台阶初期支护的轮廓线的部分的直径小于所述中管棚侵入地层的部分的直径。The tunnel excavation method for upper soft and lower hard strata according to claim 1, wherein the diameter of the part of the middle pipe shed intruding into the contour line of the initial support of the upper step is smaller than the diameter of the middle pipe shed intruding into the stratum the diameter of the part.
PCT/CN2021/090852 2020-10-20 2021-04-29 Tunnel excavation method for upper-soft and lower-hard stratum WO2022083096A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
ZA2023/05430A ZA202305430B (en) 2020-10-20 2023-05-18 Tunnel excavation method for upper-soft and lower-hard stratum

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202011125816.9 2020-10-20
CN202011125816.9A CN112431599B (en) 2020-10-20 2020-10-20 Tunnel excavation method for upper soft and lower hard stratum

Publications (1)

Publication Number Publication Date
WO2022083096A1 true WO2022083096A1 (en) 2022-04-28

Family

ID=74695740

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/090852 WO2022083096A1 (en) 2020-10-20 2021-04-29 Tunnel excavation method for upper-soft and lower-hard stratum

Country Status (3)

Country Link
CN (1) CN112431599B (en)
WO (1) WO2022083096A1 (en)
ZA (1) ZA202305430B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914898A (en) * 2021-09-30 2022-01-11 中铁三局集团有限公司 Advance support construction method before underground excavation ingate enters tunnel
CN114855809A (en) * 2022-06-17 2022-08-05 山东曼凯机械化工程有限公司 Hard rock excavation method
CN116816362A (en) * 2023-08-31 2023-09-29 北京交通大学 Supporting and reinforcing method for intersection of positive tunnel and transverse channel of ultra-large buried soft rock tunnel
WO2024139800A1 (en) * 2022-12-29 2024-07-04 中海建筑有限公司 Construction method for gas partition system of gas outburst tunnel

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112431599B (en) * 2020-10-20 2022-10-28 中铁十九局集团第五工程有限公司 Tunnel excavation method for upper soft and lower hard stratum
CN113006802A (en) * 2021-03-26 2021-06-22 北京城建设计发展集团股份有限公司 Tunnel reverse step excavation construction method suitable for thin overburden stratum
CN113153375B (en) * 2021-04-08 2022-12-02 济南城建集团有限公司 Construction method of soft foundation ultra-small clear distance tunnel primary support anti-drop support settlement-reducing support system
CN114151091B (en) * 2021-12-17 2023-10-31 中铁二院昆明勘察设计研究院有限责任公司 CRD construction method and structure suitable for blasting excavation of upper soft and lower hard stratum
CN114483054A (en) * 2022-03-07 2022-05-13 中铁隧道局集团有限公司 Non-explosive excavation construction method for pilot tunnel in upper soft and lower hard stratum

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000345794A (en) * 1999-06-03 2000-12-12 Mitsui Eng & Shipbuild Co Ltd Shield drive machine
CN104895575A (en) * 2015-06-03 2015-09-09 福建工程学院 High-efficiency rapid construction method for upper-soft lower-hard formation large-section tunnels
CN205063959U (en) * 2015-08-28 2016-03-02 大连海事大学 Tunnel supporting construction suitable for last soft hard ground layer down
CN106321106A (en) * 2015-06-30 2017-01-11 中交二公局第六工程有限公司 Construction method for tunnel-entering of tunnel weak surrounding rock and semi-open and semi-underground bias section portal abutment
CN112431599A (en) * 2020-10-20 2021-03-02 中铁十九局集团第五工程有限公司 Tunnel excavation method for upper soft and lower hard stratum

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444407B (en) * 2011-12-12 2015-06-03 中铁二局股份有限公司 Construction deformation control method for lower step of high crustal stress weak surrounding rock tunnel
CN105926406B (en) * 2016-04-29 2018-11-02 中交一公局第一工程有限公司 A kind of joining method and structure on old road new in reorganization and expansion pavement construction
CN109372517A (en) * 2018-09-28 2019-02-22 北京交通大学 One kind is suitable for wearing water supplying pipe construction method under upper soft lower hard compound stratum tunnel
CN110985002B (en) * 2019-11-11 2021-03-23 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN111043926B (en) * 2020-01-03 2020-12-29 重庆中环建设有限公司 400m is realized based on electron detonator2Blasting excavation method for tunnel with large cross section
CN111441802A (en) * 2020-04-17 2020-07-24 济南城建集团有限公司 Temporary inverted arch dismantling replacement structure and process in tunnel constructed by CRD method
CN111734455A (en) * 2020-06-24 2020-10-02 高军 Rapid construction method for synchronous excavation of two step inverted arches of soft rock large deformation tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000345794A (en) * 1999-06-03 2000-12-12 Mitsui Eng & Shipbuild Co Ltd Shield drive machine
CN104895575A (en) * 2015-06-03 2015-09-09 福建工程学院 High-efficiency rapid construction method for upper-soft lower-hard formation large-section tunnels
CN106321106A (en) * 2015-06-30 2017-01-11 中交二公局第六工程有限公司 Construction method for tunnel-entering of tunnel weak surrounding rock and semi-open and semi-underground bias section portal abutment
CN205063959U (en) * 2015-08-28 2016-03-02 大连海事大学 Tunnel supporting construction suitable for last soft hard ground layer down
CN112431599A (en) * 2020-10-20 2021-03-02 中铁十九局集团第五工程有限公司 Tunnel excavation method for upper soft and lower hard stratum

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JIN QIANGGUO: "Discussion on the Invert Benched Excavation Method for Qingshan Tunnel", TUNNEL CONSTRUCTION, no. 3, 15 August 2000 (2000-08-15), pages 55 - 58, XP055923533, ISSN: 2096-4498 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914898A (en) * 2021-09-30 2022-01-11 中铁三局集团有限公司 Advance support construction method before underground excavation ingate enters tunnel
CN113914898B (en) * 2021-09-30 2023-09-29 中铁三局集团有限公司 Advanced support construction method before underground excavation of horsehead door entering tunnel
CN114855809A (en) * 2022-06-17 2022-08-05 山东曼凯机械化工程有限公司 Hard rock excavation method
WO2024139800A1 (en) * 2022-12-29 2024-07-04 中海建筑有限公司 Construction method for gas partition system of gas outburst tunnel
CN116816362A (en) * 2023-08-31 2023-09-29 北京交通大学 Supporting and reinforcing method for intersection of positive tunnel and transverse channel of ultra-large buried soft rock tunnel
CN116816362B (en) * 2023-08-31 2023-10-31 北京交通大学 Supporting and reinforcing method for intersection of positive tunnel and transverse channel of ultra-large buried soft rock tunnel

Also Published As

Publication number Publication date
CN112431599A (en) 2021-03-02
ZA202305430B (en) 2024-01-31
CN112431599B (en) 2022-10-28

Similar Documents

Publication Publication Date Title
WO2022083096A1 (en) Tunnel excavation method for upper-soft and lower-hard stratum
WO2020173100A1 (en) Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN108952732B (en) Excavation construction method suitable for large-section tunnel of water-rich fault fracture zone
CN106050266A (en) Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
CN110735653A (en) deep-hole retreating type grouting water plugging construction method for igneous rock water-rich fault
CN115182737B (en) Vertical orthogonal ejection type air duct structure of deeply buried subway station and construction method
CN106703814A (en) Mined metro station hole pile construction method
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN113006825B (en) Arch changing construction method for tunnel collapse position
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN102518470A (en) Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN107905796A (en) A kind of tunnels in soil Guan Peng operating rooms construction method
CN110905536A (en) Construction method for receiving complex stratum earth pressure shield in underground excavation tunnel
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN105134254B (en) A kind of tunnel surface drilling sleeve pipe sealing device and its operating procedure
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
JP2022553449A (en) External expansion pipe construction method for drilling in the mining zone
CN113107501A (en) Initial tunneling construction method for portal extension steel ring
CN113404517B (en) Construction method for tunnel mud bursting and water flushing
CN109695453A (en) Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
CN214997645U (en) Be applicable to subway station goes out inlet pipe curtain construction pipe curtain structure
CN112443331B (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN211058801U (en) Piece flows stratum tunnel excavation construction structures

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21881520

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21881520

Country of ref document: EP

Kind code of ref document: A1