WO2022100346A1 - Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method - Google Patents

Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method Download PDF

Info

Publication number
WO2022100346A1
WO2022100346A1 PCT/CN2021/123555 CN2021123555W WO2022100346A1 WO 2022100346 A1 WO2022100346 A1 WO 2022100346A1 CN 2021123555 W CN2021123555 W CN 2021123555W WO 2022100346 A1 WO2022100346 A1 WO 2022100346A1
Authority
WO
WIPO (PCT)
Prior art keywords
underground diaphragm
pipe jacking
diaphragm wall
well
reinforcement
Prior art date
Application number
PCT/CN2021/123555
Other languages
French (fr)
Chinese (zh)
Inventor
杨俊峰
安刚建
余世祥
袁正璞
曹广勇
杨祖兵
林键
詹杰
沃云舟
王伟超
邓文杰
张挺
Original Assignee
中铁四局集团第四工程有限公司
中铁四局集团有限公司
安徽建筑大学
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁四局集团第四工程有限公司, 中铁四局集团有限公司, 安徽建筑大学 filed Critical 中铁四局集团第四工程有限公司
Publication of WO2022100346A1 publication Critical patent/WO2022100346A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Definitions

  • the invention relates to the technical field of multi-row pipe jacking construction, in particular to a reinforcement structure and a construction method for the entry and exit holes of large-diameter pipe jacking groups in a water-rich sand layer.
  • Pipe jacking construction in water-rich sand layer areas often causes seepage, piping, and soil flow at the entrance and exit of the tunnel. In severe cases, it may even cause soil instability and collapse of foundation pits. Reinforcement is an important part of the pipe jacking initiation and receiving technology, which refers to the reinforcement of the stratum where the pipe jacking machine enters and exits the working well.
  • the main purposes of reinforcement are: to improve the soil strength in the working well area, to control the surface subsidence; to prevent piping and soil flow caused by seepage; to improve the bearing capacity of the soil at the end of the tunnel.
  • reinforcement techniques such as deep stirring piles and freezing methods are often used. When the geological conditions are complex, the conventional stirring pile reinforcement technology is difficult to form piles under complex geological conditions; the construction cost of the freezing method is too high, the construction is difficult and the construction period is long.
  • the creator of the present invention finally obtained the present invention after a long period of research and practice.
  • the technical solution adopted in the present invention is to provide a reinforcement structure for the entrance and exit of the large-diameter pipe jacking group in the water-rich sand layer, including an underground diaphragm wall and a high-pressure rotary jet pile, and the underground diaphragm wall is arranged at the starting point.
  • the depth of the underground diaphragm wall is below the bottom elevation of the pipe jacking machine, and a bored cast-in-place pile is arranged in the middle of the inner side of the originating well and the receiving well, and the bored cast-in-place pile is connected with all the boreholes.
  • the underground diaphragm walls are of the same depth, and cross braces are used between the underground diaphragm walls; the cross braces are fixedly connected to the bored cast-in-place piles;
  • the high-pressure jetting piles are arranged in two rows of plum-like occlusion, which are arranged in parallel with the underground continuous wall, and are spaced from the underground continuous wall, and the depth of the high-pressure jetting piles exceeds the jacking pipe.
  • the bottom of the machine the width along the underground diaphragm wall beyond the pipe jacking machine.
  • the thickness of the underground diaphragm wall is 0.8m.
  • the surface soil layer in front of the inlet and outlet holes of the pipe jacking group is reinforced and hardened, and a dewatering well is evenly arranged on the outside of the high-pressure jetting pile and the underground diaphragm wall.
  • the buried depth of the underground diaphragm wall exceeds the elevation of the bottom of the pipe jacking machine group by 10m.
  • the width of the high-pressure jetting pile group exceeds half the width of the pipe jacking machine, and the depth of the high-pressure jetting pile is 5m beyond the bottom of the pipe jacking machine.
  • the height of the high-pressure jetting pile exceeds twice the elevation of the pipe jacking machine, and the distance from the underground diaphragm wall is 0.5m.
  • a construction method for the reinforcement structure of the entry and exit holes of the large-diameter pipe jacking group in the water-rich sand layer comprising the steps of:
  • the dewatering wells are evenly and symmetrically arranged along the groundwater flow potential at the edge of the field area, and the depth of the dewatering wells is 2m below the bottom of the tunnel where the pipe jacking machine is jacked.
  • the surface is leveled, the field area is cleaned and the surface is grouted and hardened for reinforcement, and the grouting adopts cement single grout.
  • step S3 the construction of the underground diaphragm wall is carried out on the outer edge of the working well, and after the construction of the underground diaphragm wall is completed, the bored piles are symmetrically constructed in the center of the interior of the working well, and the drilling
  • the cast-in-place pile is made of mud wall to form holes, and then the excavation of the working well is carried out in the way of three-sequence formation of grooves.
  • the horizontal brace is constructed, and the bottom plate of the working well is constructed.
  • a water stop ring is set at the entrance of the inlet and outlet holes of the jacking pipe group, and the water stop ring is embedded in the lining structure and the enclosure structure, and the enclosure structure is an underground continuous wall, so
  • the inner lining structure is a concrete reinforcement structure extending from the underground diaphragm wall to the working well;
  • the water stop ring includes a pre-embedded steel ring, a pressure plate, a rubber ring and an installation steel ring, and the pressure plate and the rubber ring are arranged on the pre-buried steel ring.
  • the embedded steel ring is pre-embedded.
  • the inner diameter of the ring is the same size as the reserved hole; an annular reinforced concrete protection ring is arranged in the embedded steel ring, the rubber ring is arranged on one side of the working well, and the rubber ring is pressed by the pressing plate .
  • the beneficial effects of the present invention are as follows: the present invention performs reinforcement treatment on the inlet and outlet holes of the large-diameter pipe jacking group, which not only improves the reinforcement efficiency of the inlet and outlet holes, simplifies the processing steps, but also greatly improves the quality of the stratum reinforcement and the construction. The difficulty and construction cost are reduced, which ensures the construction period, quality and economy of the project.
  • Fig. 1 is the structural view of described water-rich sand layer large diameter pipe jacking group in and out hole reinforcement structure
  • Figure 2 is a structural view of the originating well
  • Fig. 3 is the plum-blossom occlusal structure diagram of described high-pressure rotary jet pile
  • Fig. 4 is the reinforcement structure diagram of the pipe jacking inlet and outlet holes
  • FIG. 5 is a flow chart of the construction method for the reinforcement structure of the large diameter pipe jacking group in and out of the water-rich sand layer.
  • the reinforcement structure for the inlet and outlet holes of the large-diameter pipe jacking group in the water-rich sand layer according to the present invention includes an underground diaphragm wall and a high-pressure rotary jet pile.
  • the thickness of the wall is 0.8m
  • the depth of the underground diaphragm wall is 10m below the bottom elevation of the pipe jacking machine, so as to effectively form a water-stop curtain
  • the corresponding underground diaphragm wall is supported by transverse braces.
  • a row of two C30 bored cast-in-place piles with a diameter of 0.6 m are arranged in the middle of the inner side of the originating well and the receiving well, and the bored cast-in-place piles are at the same depth as the underground diaphragm wall, both of which are in the same depth.
  • the cross brace is fixedly connected with the bored pile, so that the cross brace in the support well is reinforced by the bored pile.
  • the high-pressure jetting piles are arranged at the entrance and exit holes of the pipe jacking group and the outside of the underground continuous wall.
  • the diameter of a single high-pressure jetting pile is 0.6m, and is generally arranged in two rows of plum blossoms, which are continuous with the underground.
  • the walls are arranged in parallel, and the distance from the underground diaphragm wall is set to 0.5m, the depth of the high-pressure rotary jet pile is 5m beyond the bottom of the pipe jacking machine, and the width is 2m beyond the pipe jacking machine along the underground diaphragm wall.
  • the surface soil layer in front of the inlet and outlet holes of the pipe jacking group is reinforced and hardened, and a dewatering well with a diameter of 1.6m is evenly arranged on the outside of the high-pressure jetted pile and the underground diaphragm wall for drainage and foundation pits.
  • the excavation depth is 12m.
  • the depth of the dewatering well is 10m beyond the bottom of the pit.
  • the reinforcement structure of the large diameter pipe jacking group in and out of the water-rich sand layer according to the invention is a kind of pipe jacking construction tunnel suitable for the water-rich sand layer.
  • the front end of the originating well and the rear outer edge of the receiving well are reinforced through the high-pressure rotary jet clinching pile and the enclosure structure of the working well to form a dense, continuous and rigid support system, and a dewatering well is used as an enclosure.
  • a dewatering well is used as an enclosure.
  • the high-pressure rotary jet occlusal piles added on the outside can effectively make up for the problems of soil erosion and stratum instability caused by the pipe jacking machine group during the opening and jacking process.
  • the diameter of the pipe jacking machine is 3.5m, and it penetrates the water-rich sand layer.
  • the method of the invention not only improves the reinforcement efficiency of the entrance and exit holes, simplifies the processing steps, but also greatly improves the quality of formation reinforcement, construction safety, construction difficulty and construction. The cost is reduced, and it can meet the construction of pipe jacking machine groups in different strata.
  • Fig. 1 is a structural view of the reinforcement structure of the inlet and outlet holes of the large-diameter pipe jacking group in the water-rich sand layer; this embodiment is explained by an actual case;
  • the three pipe jacking machines are assembled in the starting shaft 9, and are respectively jacked from the first inlet 6, the second inlet 7, and the third inlet 8 from left to right, and then the first outlet 61, the second inlet 8 The outlet 71 and the third outlet 81 reach the receiving well.
  • Fig. 2 is a structural view of the originating well;
  • the soil layer is reinforced, and the support 3 and the bored cast-in-place pile 4 are applied to the working well, namely the originating well 9 and the receiving well 10, to reinforce the underground diaphragm wall 2 in the well.
  • a working well bottom plate 11 is provided at the bottom of the underground diaphragm wall 2 , and the underground diaphragm wall 2 , the high-pressure rotary jetting pile 5 and the bored cast-in-place pile 4 are all deep below the working well bottom plate 11 .
  • the diameter of the dewatering well 1 is 1.6m, and it is evenly arranged along the working well.
  • Fig. 3 is a plum-shaped occlusal structure diagram of the high-pressure rotary jetting pile; 2.
  • the top entrances are arranged side by side, and the distance between a row of high-pressure rotary jet piles 5 close to the underground diaphragm wall 2 is 0.5m.
  • the grouting material is ordinary silicon 42.5 cement, cement slurry (single liquid), and the water-cement ratio is 1:1 impermeable slurry, so that the entire formation can be effectively reinforced, forming a compact whole with the underground diaphragm wall 2 to prevent piping and seepage when the originating well 9 and the receiving well 10 are broken.
  • the cement dosage of the high-pressure rotary jet pile 5 is controlled to be less than the cement dosage of the underground diaphragm wall 2, so as to ensure that the strength of the reinforced soil is between 1.2 MPa and 1.5 MPa, which can ensure the normal jacking of the pipe jacking machine group and avoid the top It is difficult to break the pile into the cutter head.
  • the depth of the underground diaphragm wall 2 is twice the elevation of the bottom of the pipe jacking machine group, which can well form a water-stop curtain and prevent the base from surging.
  • the cross braces 3 in the originating well 9 and the receiving well 10 are reinforced concrete structures, which play a supporting role for the underground diaphragm wall and resist the earth pressure.
  • the cross braces 3 are mainly poured from the borehole.
  • the pile 4 is used for load bearing and stability maintenance, and its combined support system can also be used for the lifting and installation of the pipe jacking equipment.
  • Dewatering wells 1 are arranged in the outer edge soil layers of the originating well 9 and the receiving well 10 along the direction of groundwater flow potential to conduct well point dewatering, enhance soil strength, and improve the airtightness of the cave door.
  • an underground diaphragm wall method is used to form the enclosure structure.
  • the thickness of the underground diaphragm wall 2 is 0.8m, and the depth of soil penetration is twice the elevation of the bottom of the pipe jacking machine group.
  • the water-stop curtain effectively prevents water and soil seepage from entering the originating well 9 and the receiving well 10 .
  • a ring beam with a section size of 1m*0.8m is made on the top of the diaphragm wall, so that the diaphragm wall can form a whole.
  • the joint form of underground diaphragm wall adopts rigid joint cross steel plate for joint.
  • the internal cross braces 3 and bored cast-in-place piles 4 are constructed.
  • the cross braces 3 are used to maintain the stability of the working well and prevent external
  • the underground diaphragm wall 2 caused by the earth pressure is deformed inward to prevent collapse.
  • the diameter of the bored pile 4 is 0.6m, and ordinary Portland cement above grade 42.5 and C30 concrete are used for the load-bearing of the cross braces and the lifting equipment in the originating well 9 and the receiving well 10 .
  • the soil layer between the front end of the originating well 9, that is, the side where the pipe jacking machine group exits the hole, and the front end of the receiving well 10, that is, the side where the pipe jacking machine group enters the hole, is reinforced.
  • the surface of the reinforcement area is hardened, and the high-pressure rotary jet pile method is used for formation reinforcement and water isolation. Ordinary Portland cement of grade 42.5 or above is used, and the grade is C20.
  • the high-pressure jetting piles are separated by 0.5m from the underground diaphragm wall on the exit side of the originating well and the underground diaphragm wall on the entrance side of the receiving well.
  • the depth of the jetting pile group exceeds twice the elevation of the pipe jacking machine, and can pass through the permeable layer. During the construction of the high-pressure jetting pile, it can effectively form a dense whole with the underground diaphragm wall.
  • FIG. 4 is a reinforcement structure diagram of the inlet and outlet holes of the jacking pipe, the hole 12 is provided with a water stop ring, and the hole 12 is the hole of the inlet and outlet holes of the jacking pipe group.
  • the enclosure structure 14 is an underground diaphragm wall, and the inner lining structure 13 is a concrete reinforcement structure extending from the underground diaphragm wall to the working well.
  • the reinforced soil body 17 in the figure may be the high-pressure jetted pile 5 .
  • the water stop ring includes a pre-embedded steel ring 15, a pressure plate 19, a rubber ring 20 and an installation steel ring 18.
  • the pressure plate 19 and the rubber ring 20 are arranged on the pre-embedded steel ring 15 and the installation steel ring 18.
  • the pre-embedded steel ring 15 is pre-embedded, and a reserved hole is formed after the inside of the pre-embedded steel ring 15 is chiseled, and the inner diameter of the pre-embedded steel ring is the same as the reserved hole.
  • the hole is the same size.
  • annular reinforced concrete protection ring 16 may also be arranged in the embedded steel ring 15, and the annular reinforced concrete protection ring 16 is used to replace part of the rubber ring 20.
  • the rubber ring 20 is arranged on one side of the working well, and the rubber ring 20 is pressed by the pressing plate 19 to ensure a good sealing effect between the embedded steel ring 15 and the installation steel ring 18 .
  • a clamping structure is provided at the connection position of the rubber ring 20 and the annular reinforced concrete protection ring 16 , and the connection between the rubber ring 20 and the annular reinforced concrete protection ring 16 is realized through the clamping structure.
  • the rubber ring 20 is placed at the door of the hole, and due to its elastic expansion characteristics, it can better seal the pipe joint and the upper structure to prevent water seepage.
  • Figure 5 is a flowchart of the construction method of the water-rich sand layer large-diameter pipe jacking group in-out hole reinforcement structure; the construction of the water-rich sand layer large-diameter pipe group in-out hole reinforcement structure method, including the following steps:
  • the local layer is a water-rich sand layer.
  • the measured groundwater depth is 1.3 to 7.6 meters, and the water level elevation is 4.5 to 20.0 meters.
  • the permeability coefficient of artificial plain filled soil is less than or equal to 1.00 ⁇ 10-5cm/s, which belongs to the medium water permeability level, so the surface of the stratum needs only simple grouting and hardening treatment.
  • the bottom silt, medium sand, strongly weathered basalt and coarse sand layers have a permeability coefficient k of 1.10 ⁇ 10-2cm/s ⁇ k ⁇ 1.08 ⁇ 10-3cm/s, which are highly permeable layers with poor hydraulic properties.
  • Seepage deformation stability is a relatively unstable soil layer, which is prone to seepage deformation, so the reinforcement requirements are higher, and the soil should form a dense and continuous soil layer without flow-plastic phenomenon. Determine the stratum reinforcement requirements according to the design requirements to ensure the stability of the stratum.
  • the diameter of the pipe jacking machine is 3.5m.
  • the excavation design of the working well is as follows: the working well is 24.1m long and 11.4m wide. area reinforcement.
  • a dewatering well with a diameter of 1.6m is set up uniformly and symmetrically along the groundwater flow potential at the edge of the field area.
  • the design standard value only needs to dewater the pit bottom to less than 0.5m.
  • the depth of the dewatering well is 10m below the bottom of the tunnel where the pipe jacking machine is jacked.
  • the surface is leveled, and the field area is cleaned and hardened by grouting on the surface for reinforcement.
  • the grouting adopts cement single grout, and the field materials and access equipment are provided according to the design requirements.
  • the working well is 24.1m long and 11.4m wide.
  • the enclosure structure adopts the underground diaphragm wall + 1.0m ⁇ 0.8m reinforced concrete internal support system, the diaphragm wall is 80cm wide, 8 standard "one" sections, 4 special-shaped “L” sections, the standard section width is 6m, and the special-shaped section width is 5.75m,
  • the outer edge of the working well adopts a 0.8m thick underground diaphragm wall.
  • the construction of the underground diaphragm wall includes measuring and positioning according to the design drawings, lofting and drawing lines, excavation of the top foundation groove, construction of guide walls, mud wall protection system, deep trench excavation, Lower the steel cage to pour concrete and pull out the conduit.
  • a ring beam with a section size of 1m*0.8m is made on the top of the diaphragm wall, so that the diaphragm wall can form a whole.
  • the joint form of underground diaphragm wall adopts rigid joint cross steel plate for joint.
  • the mud system adopts a mud circulation system made of bentonite, and is equipped with a mud pool.
  • the drilling is made by percussion drilling.
  • the excavation adopts step-by-step excavation, and the excavation is symmetrical from both sides to the middle.
  • the three-sequence trough is adopted.
  • the reinforced concrete horizontal transverse bracing and horizontal longitudinal bracing are arranged at m, and the supports in this project are all permanent supports and do not involve the replacement and dismantling process.
  • the base plate structure is constructed, and the back cover is covered with a plain concrete cushion, and the pouring is completed at one time, and then the base plate is constructed with a reinforced concrete structure, and the construction joint is located 1.2m above the side wall of the base plate.
  • the end of the pipe jacking inlet and outlet holes is reinforced by high-pressure jetting piles.
  • the diameter and spacing of the high-pressure jetting piles are designed.
  • the single-pipe method is used for the rotary jetting piles.
  • the diameter of the pile is 0.6 ⁇ 1.0m, considering its economic rationality and the continuity of mutual overlap, the pile diameter is 0.6m, and two rows of grouting holes are used;
  • the design value of the distance is 0.75R, so the row distance is 0.45m.
  • Ordinary silicate 42.5 cement is used, and the water-cement ratio of cement single slurry is 1:1 to carry out synchronous grouting and follow-up grouting process, and control the grouting rate and uniformity;
  • the plum-shaped double-row occlusal arrangement is adopted on the outside of the exit hole of the originating well and the outside of the entry hole of the receiving well.
  • the specific arrangement is arranged according to the "Z" shape in Figure 3, and the lap joint according to the construction sequence of "a-b-c-d-e-f-g" in the figure, the occlusal lap joint can be Effectively form an overall lap;
  • the construction of high-pressure rotary jetting piles includes measuring and laying out lines, determining hole positions, drilling holes, cleaning holes, and spraying.
  • step S4 before constructing the high-pressure jetting pile, a technical test of the high-pressure jetting pile should be carried out. Parameter basis, so as to ensure the construction quality of high-pressure rotary jetting piles.
  • the water stop ring at the entrance is mainly composed of a pre-embedded steel ring, a pressure plate, a rubber ring and an installation steel ring.
  • the inner diameter of the embedded steel ring is the same size as the reserved hole; the installation of the steel ring is Welded on the embedded steel ring, several bolts are welded on the installation steel ring to install the rubber ring and the pressure plate.
  • the installation position should be adjusted according to the axis position of the exit hole. Since the jacking pipe will inevitably deviate from the axis position of the exit hole, the water stop ring allows the machine head to have a 2cm axis position. If the deviation of the machine head exceeds 2cm, the water stop ring The installation position must be adjusted according to the actual deviation.
  • the diameter of the machine head is generally 2cm larger than the outer diameter of the pipe, so that there is a gap of 2cm between the pipe and the hole, which is easy to form a mud sleeve, which is convenient to reduce the frictional resistance between the pipe wall and the soil.
  • the length of the pipe ring is 2.6m, so that after the first pipe ring is fully jacked, its section is at the column section in the reinforced area of the rotary jet pile.
  • the thickness of the underground diaphragm wall is 0.8m
  • the diameter of the rotary jetting pile is 0.6m
  • the spacing of the second row is 0.45m
  • the length of the pipe ring is 2.6m, so that the first pipe ring is completely After jacking in, its section is at the column section in the reinforced area of the rotary jet pile.
  • the buried depth of the underground diaphragm wall is 10m higher than the elevation of the bottom of the pipe jacking machine group, which can effectively form a water-stop curtain.
  • the width of the high-pressure jetting pile group exceeds half of the width of the pipe jacking machine.
  • the height of the high-pressure jetting pile is twice the elevation of the pipe jacking machine, and the distance from the underground diaphragm wall is 0.5m, which can be effectively combined with it to reinforce the soil layer in front of the hole.
  • the material used for the high-pressure rotary spray pile is cement slurry.
  • the cement slurry is sprayed into the soil layer and mixed with the soil by high pressure through the rotating nozzle to form cement-soil solids, which overlap each other to form piles for retaining soil and water, reducing the The process of erecting temporary supports. Improve the efficiency of the pipe jacking machine entering and exiting the hole, and reduce the cost of entering and exiting the hole.
  • the method of the invention is used to reinforce the inlet and outlet holes of the large-diameter pipe jacking group, which not only improves the reinforcement efficiency of the inlet and outlet holes, simplifies the processing steps, but also greatly improves the quality of the stratum reinforcement, reduces the construction difficulty and construction cost, and ensures the safety of the project. Duration, quality and economy.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A reinforcement structure for entry and exit of a large-diameter jacking pipe group in a water-rich sand stratum, and a construction method. The structure comprises underground diaphragm walls (2) and high-pressure jet grouting piles (5); the underground diaphragm walls (2) are arranged at edge positions of a launch shaft (9) and a reception shaft (10); the depths of the underground diaphragm walls (2) are below a bottom elevation of a pipe jacking machine; bored piles (4) are provided at the middles on the insides of the launch shaft (9) and the reception shaft (10); the depths of the bored piles (4) are the same as those of the underground diaphragm walls (2); cross braces (3) are used between the underground diaphragm walls (2) for support; the cross braces (3) are fixedly connected to the bored piles (4); the high-pressure jet grouting piles (5) are provided at the entry and exit of a jacking pipe group and the outside of the underground diaphragm walls (2); the high-pressure jet grouting piles (5) are arranged in row-shaped structure engaged in a quincuncial manner, and are arranged in parallel with the underground diaphragm walls (2). By performing reinforcement treatment on the entry and exit of a large-diameter jacking pipe group, the reinforcement efficiency of entry and exit openings is improved, machining process steps are simplified, and the quality of stratum reinforcement is improved, and construction difficulty and construction costs are reduced.

Description

一种富水砂层大直径顶管群进出洞加固结构及施工方法A kind of reinforcement structure and construction method of large-diameter pipe jacking group inlet and outlet holes in water-rich sand layer 技术领域technical field
本发明涉及多排顶管施工技术领域,具体涉及一种富水砂层大直径顶管群进出洞加固结构及施工方法。The invention relates to the technical field of multi-row pipe jacking construction, in particular to a reinforcement structure and a construction method for the entry and exit holes of large-diameter pipe jacking groups in a water-rich sand layer.
背景技术Background technique
随着城市化的不断进行,顶管施工在城市管网中的应用越来越广泛和系统化,对于富水砂层地区,大直径顶管群在顶管进出洞过程中经常会出现工程质量缺陷等问题。富水砂层作为一种力学不稳定地层,其地层流动性大,容易造成大范围的地层扰动,在施工时,地表沉降不易控制,大直径顶管群在进出洞口时,是施工风险较大的关键过程。因此,大直径顶管群进出洞加固是工程的难点之一,进出洞加固方法显得尤为重要。With the continuous progress of urbanization, the application of pipe jacking in the urban pipe network is becoming more and more extensive and systematic. For areas with water-rich sand layers, large-diameter pipe jacking groups often experience engineering quality problems during the process of pipe jacking in and out of the hole. defects, etc. As a mechanically unstable stratum, the water-rich sand layer has high stratum fluidity and is easy to cause large-scale stratum disturbance. During construction, the surface subsidence is not easy to control. When the large diameter pipe jacking group enters and exits the tunnel, the construction risk is high. key process. Therefore, the reinforcement of the entry and exit holes of the large diameter pipe jacking group is one of the difficulties in the project, and the reinforcement method of the entry and exit holes is particularly important.
在富水砂层地区顶管施工,常在出进出洞口发生渗流、管涌、流土,严重时,甚至造成土体失稳、基坑的坍塌等现象。加固是顶管始发、接收技术的一个重要组成部分,是指对顶管机进出工作井部位的地层加固。加固的主要目的是:提高工作井区土体强度,控制地表沉降;防止由渗流引发的管涌、流土;提高洞口端头土体的承载能力。在一般的软土地层中,多采用深层搅拌桩、冻结法等加固技术。当地质条件为复杂时,常规搅拌桩加固技术在复杂地质条件下难以成桩;冷冻法施工成本过高、施工难度大且工期长。Pipe jacking construction in water-rich sand layer areas often causes seepage, piping, and soil flow at the entrance and exit of the tunnel. In severe cases, it may even cause soil instability and collapse of foundation pits. Reinforcement is an important part of the pipe jacking initiation and receiving technology, which refers to the reinforcement of the stratum where the pipe jacking machine enters and exits the working well. The main purposes of reinforcement are: to improve the soil strength in the working well area, to control the surface subsidence; to prevent piping and soil flow caused by seepage; to improve the bearing capacity of the soil at the end of the tunnel. In general soft soil layers, reinforcement techniques such as deep stirring piles and freezing methods are often used. When the geological conditions are complex, the conventional stirring pile reinforcement technology is difficult to form piles under complex geological conditions; the construction cost of the freezing method is too high, the construction is difficult and the construction period is long.
鉴于上述缺陷,本发明创作者经过长时间的研究和实践终于获得了本发明。In view of the above-mentioned defects, the creator of the present invention finally obtained the present invention after a long period of research and practice.
发明内容SUMMARY OF THE INVENTION
为解决上述技术缺陷,本发明采用的技术方案在于,提供一种富水砂层大直径顶管群进出洞加固结构,包括地下连续墙、高压旋喷桩,所述地下连续墙设置在始发井和接收井的边缘位置处,所述地下连续墙深度至顶管机底部标高以下,在所述始发井和所述接收井内侧中部设置钻孔灌注桩,所述钻孔灌注桩与所述地下连续墙同深度,所述地下连续墙之间采用横撑支撑;所述横撑和所述钻孔灌注桩固定连接;所述高压旋喷桩设置在顶管群进出洞及所述地下连续墙外侧,所述高压旋喷桩设置为梅花式咬合的两排,与所述地下连续墙并行布置,且与所述地下连续墙之间设置间距,所述高压旋喷桩深度超出顶管机底部,宽度沿所述地下连续墙超出顶管机。In order to solve the above-mentioned technical defects, the technical solution adopted in the present invention is to provide a reinforcement structure for the entrance and exit of the large-diameter pipe jacking group in the water-rich sand layer, including an underground diaphragm wall and a high-pressure rotary jet pile, and the underground diaphragm wall is arranged at the starting point. At the edge positions of the well and the receiving well, the depth of the underground diaphragm wall is below the bottom elevation of the pipe jacking machine, and a bored cast-in-place pile is arranged in the middle of the inner side of the originating well and the receiving well, and the bored cast-in-place pile is connected with all the boreholes. The underground diaphragm walls are of the same depth, and cross braces are used between the underground diaphragm walls; the cross braces are fixedly connected to the bored cast-in-place piles; On the outer side of the diaphragm wall, the high-pressure jetting piles are arranged in two rows of plum-like occlusion, which are arranged in parallel with the underground continuous wall, and are spaced from the underground continuous wall, and the depth of the high-pressure jetting piles exceeds the jacking pipe. The bottom of the machine, the width along the underground diaphragm wall beyond the pipe jacking machine.
较佳的,所述地下连续墙厚度为0.8m。Preferably, the thickness of the underground diaphragm wall is 0.8m.
较佳的,所述顶管群进出洞前方地表土层进行加固硬化处理,并在所述高压旋喷桩及所 述地下连续墙外侧均匀设置降水井。Preferably, the surface soil layer in front of the inlet and outlet holes of the pipe jacking group is reinforced and hardened, and a dewatering well is evenly arranged on the outside of the high-pressure jetting pile and the underground diaphragm wall.
较佳的,所述地下连续墙的埋深超出顶管机群底部标高的10m。Preferably, the buried depth of the underground diaphragm wall exceeds the elevation of the bottom of the pipe jacking machine group by 10m.
较佳的,所述高压旋喷桩群的宽度超出顶管机宽度的一半,所述高压旋喷桩深度超出顶管机底部5m。Preferably, the width of the high-pressure jetting pile group exceeds half the width of the pipe jacking machine, and the depth of the high-pressure jetting pile is 5m beyond the bottom of the pipe jacking machine.
较佳的,所述高压旋喷桩高度超出顶管机标高的一倍,与所述地下连续墙的间距为0.5m。Preferably, the height of the high-pressure jetting pile exceeds twice the elevation of the pipe jacking machine, and the distance from the underground diaphragm wall is 0.5m.
较佳的,一种所述富水砂层大直径顶管群进出洞加固结构的施工方法,包括步骤:Preferably, a construction method for the reinforcement structure of the entry and exit holes of the large-diameter pipe jacking group in the water-rich sand layer, comprising the steps of:
S1,确定加固要求及区域;S1, determine the reinforcement requirements and areas;
S2,地表加固处理;S2, surface reinforcement treatment;
S3,工作井内加固处理;S3, reinforcement treatment in the working well;
S4,顶管进出洞端头加固。S4, the end of the jacking pipe inlet and outlet holes is reinforced.
S5,顶管进出质量控制。S5, pipe jacking in and out quality control.
较佳的,在步骤S2中,在场区边缘沿着地下水流势走向均匀对称设置所述降水井,所述降水井深度为顶管机顶进隧道底部以下2m。Preferably, in step S2, the dewatering wells are evenly and symmetrically arranged along the groundwater flow potential at the edge of the field area, and the depth of the dewatering wells is 2m below the bottom of the tunnel where the pipe jacking machine is jacked.
较佳的,所述降水井设置完成后进行地表整平,加固采用对场区清理并对地表注浆硬化处理,注浆采用水泥单浆液。Preferably, after the dewatering well is installed, the surface is leveled, the field area is cleaned and the surface is grouted and hardened for reinforcement, and the grouting adopts cement single grout.
较佳的,在步骤S3中,在工作井外缘进行所述地下连续墙施工,所述地下连续墙施工完成后,在所述工作井内部中心对称施工所述钻孔灌注桩,所述钻孔灌注桩采用泥浆护壁成孔,后采用三序成槽的方式进行所述工作井的开挖,开挖采用分步开挖,由两边向中间对称开挖,,在开挖设计标高后设置所述横撑,并施工所述工作井底板。Preferably, in step S3, the construction of the underground diaphragm wall is carried out on the outer edge of the working well, and after the construction of the underground diaphragm wall is completed, the bored piles are symmetrically constructed in the center of the interior of the working well, and the drilling The cast-in-place pile is made of mud wall to form holes, and then the excavation of the working well is carried out in the way of three-sequence formation of grooves. The horizontal brace is constructed, and the bottom plate of the working well is constructed.
较佳的,在步骤S5中,所述顶管群进出洞的洞口设置止水圈,所述止水圈内嵌在内衬结构和围护结构,所述围护结构为地下连续墙,所述内衬结构为地下连续墙向工作井延伸的混凝土加固结构;所述止水圈包括预埋钢环、压板、橡胶圈和安装钢环,所述压板和所述橡胶圈设置在所述预埋钢环和所述安装钢环之间,在设置所述围护结构时,预埋所述预埋钢环,所述预埋钢环内部凿除后形成预留洞口,所述预埋钢环的内径同预留洞口一样大小;所述预埋钢环内设置环形钢筋混凝土保护圈,所述橡胶圈设置在所述工作井一侧,并通过所述压板对所述橡胶圈进行压紧。Preferably, in step S5, a water stop ring is set at the entrance of the inlet and outlet holes of the jacking pipe group, and the water stop ring is embedded in the lining structure and the enclosure structure, and the enclosure structure is an underground continuous wall, so The inner lining structure is a concrete reinforcement structure extending from the underground diaphragm wall to the working well; the water stop ring includes a pre-embedded steel ring, a pressure plate, a rubber ring and an installation steel ring, and the pressure plate and the rubber ring are arranged on the pre-buried steel ring. Between the embedded steel ring and the installation steel ring, when the enclosure structure is set, the embedded steel ring is pre-embedded. The inner diameter of the ring is the same size as the reserved hole; an annular reinforced concrete protection ring is arranged in the embedded steel ring, the rubber ring is arranged on one side of the working well, and the rubber ring is pressed by the pressing plate .
与现有技术比较本发明的有益效果在于:本发明对大直径顶管群进出洞进行加固处理,不但提高了进出洞口的加固效率,简化加工工艺步骤,而且大大提高了地层加固的质量,施工难度和施工成本降低,保证了工程的工期、质量性和经济性。Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention performs reinforcement treatment on the inlet and outlet holes of the large-diameter pipe jacking group, which not only improves the reinforcement efficiency of the inlet and outlet holes, simplifies the processing steps, but also greatly improves the quality of the stratum reinforcement and the construction. The difficulty and construction cost are reduced, which ensures the construction period, quality and economy of the project.
附图说明Description of drawings
图1为所述富水砂层大直径顶管群进出洞加固结构的结构视图;Fig. 1 is the structural view of described water-rich sand layer large diameter pipe jacking group in and out hole reinforcement structure;
图2为所述始发井的结构视图;Figure 2 is a structural view of the originating well;
图3为所述高压旋喷桩的梅花式咬合结构图;Fig. 3 is the plum-blossom occlusal structure diagram of described high-pressure rotary jet pile;
图4为顶管进出洞加固构造图;Fig. 4 is the reinforcement structure diagram of the pipe jacking inlet and outlet holes;
图5为所述富水砂层大直径顶管群进出洞加固结构的施工方法的流程图。FIG. 5 is a flow chart of the construction method for the reinforcement structure of the large diameter pipe jacking group in and out of the water-rich sand layer.
图中数字表示:The numbers in the figure represent:
1-降水井;2-地下连续墙;3-横撑;4-钻孔灌注桩;5-高压旋喷桩;6-第一进洞口;7-第二进洞口;8-第三进洞口;9-始发井;10-接收井;11-工作井底板;12-洞口处;13-内衬结构;14-围护结构;15-预埋钢环;16-环形钢筋混凝土保护圈;17-经加固的土体;18-安装钢环;19-压板;20-橡胶圈;61-第一出洞口;71-第二出洞口;81-第三出洞口。1- Dewatering well; 2- Underground diaphragm wall; 3- Cross brace; 4- Bored cast-in-place pile; 5- High pressure rotary jetting pile; 6- The first entrance; ; 9- originating well; 10- receiving well; 11- bottom plate of working well; 12- opening; 13- lining structure; 14- enclosure structure; 15- embedded steel ring; 16- annular reinforced concrete protection ring; 17-Reinforced soil; 18-Installation steel ring; 19-Press plate; 20-Rubber ring; 61-The first outlet; 71-The second outlet; 81-The third outlet.
具体实施方式Detailed ways
以下结合附图,对本发明上述的和另外的技术特征和优点作更详细的说明。The above and other technical features and advantages of the present invention will be described in more detail below with reference to the accompanying drawings.
实施例一Example 1
本发明所述富水砂层大直径顶管群进出洞加固结构包括地下连续墙、高压旋喷桩,所述地下连续墙设置在始发井和接收井的边缘位置处,且所述地下连续墙厚度为0.8m,所述地下连续墙深度至顶管机底部标高以下10m,从而有效的形成止水帷幕,相对的所述地下连续墙采用横撑支撑。The reinforcement structure for the inlet and outlet holes of the large-diameter pipe jacking group in the water-rich sand layer according to the present invention includes an underground diaphragm wall and a high-pressure rotary jet pile. The thickness of the wall is 0.8m, the depth of the underground diaphragm wall is 10m below the bottom elevation of the pipe jacking machine, so as to effectively form a water-stop curtain, and the corresponding underground diaphragm wall is supported by transverse braces.
较佳的,在所述始发井和所述接收井内侧中部设置一排两根直径为0.6m的C30钻孔灌注桩,所述钻孔灌注桩与所述地下连续墙同深度,均为顶管机底部标高以下10m,所述横撑和所述钻孔灌注桩固定连接,从而通过所述钻孔灌注桩加固支撑井内的所述横撑。Preferably, a row of two C30 bored cast-in-place piles with a diameter of 0.6 m are arranged in the middle of the inner side of the originating well and the receiving well, and the bored cast-in-place piles are at the same depth as the underground diaphragm wall, both of which are in the same depth. Below the elevation of the bottom of the pipe jacking machine is 10m, the cross brace is fixedly connected with the bored pile, so that the cross brace in the support well is reinforced by the bored pile.
所述高压旋喷桩设置在顶管群进出洞及所述地下连续墙外侧,单根所述高压旋喷桩的直径为0.6m,一般设置为梅花式咬合的两排,与所述地下连续墙并行布置,且与所述地下连续墙之间的距离设置为0.5m,所述高压旋喷桩深度超出顶管机底部5m,宽度沿所述地下连续墙超出顶管机2m。The high-pressure jetting piles are arranged at the entrance and exit holes of the pipe jacking group and the outside of the underground continuous wall. The diameter of a single high-pressure jetting pile is 0.6m, and is generally arranged in two rows of plum blossoms, which are continuous with the underground. The walls are arranged in parallel, and the distance from the underground diaphragm wall is set to 0.5m, the depth of the high-pressure rotary jet pile is 5m beyond the bottom of the pipe jacking machine, and the width is 2m beyond the pipe jacking machine along the underground diaphragm wall.
较佳的,所述顶管群进出洞前方地表土层进行加固硬化处理,并在所述高压旋喷桩及所述地下连续墙外侧均匀设置直径1.6m的降水井,用以降排水,基坑开挖深12m,为有效达到富水砂层降水效果,降水井深度超出坑底10m。Preferably, the surface soil layer in front of the inlet and outlet holes of the pipe jacking group is reinforced and hardened, and a dewatering well with a diameter of 1.6m is evenly arranged on the outside of the high-pressure jetted pile and the underground diaphragm wall for drainage and foundation pits. The excavation depth is 12m. In order to effectively achieve the dewatering effect of the water-rich sand layer, the depth of the dewatering well is 10m beyond the bottom of the pit.
本发明所述富水砂层大直径顶管群进出洞加固结构是一种适用于富水砂层顶管施工隧道。主要利用降水井、高压旋喷咬合桩、地下连续墙等体系,对顶管始发井和接收井区间内的土 体进行加固,来实现顶管机群在富水砂层进出洞的加固方法。通过高压旋喷咬合桩和工作井的围护结构,对始发井的前端和接收井的后端外缘土体进行加固,形成致密连续和刚性的支护体系,并配以降水井起到围护和止水的作用。外侧增设的高压旋喷咬合桩,可以有效地弥补因顶管机群开洞顶进过程中所造成的水土流失、地层不稳问题。本顶管机直径3.5m,下穿富水砂层,采用此发明方法不但提高了进出洞口的加固效率,简化加工工艺步骤,而且大大提高了地层加固的质量和施工安全性,施工难度和施工成本降低,能满足不同地层的顶管机群施工。The reinforcement structure of the large diameter pipe jacking group in and out of the water-rich sand layer according to the invention is a kind of pipe jacking construction tunnel suitable for the water-rich sand layer. Mainly use dewatering wells, high-pressure rotary jet engagement piles, underground diaphragm walls and other systems to reinforce the soil in the interval between the pipe-jacking originating well and the receiving well, so as to realize the reinforcement method of the pipe-jacking machine group entering and exiting the hole in the water-rich sand layer. The front end of the originating well and the rear outer edge of the receiving well are reinforced through the high-pressure rotary jet clinching pile and the enclosure structure of the working well to form a dense, continuous and rigid support system, and a dewatering well is used as an enclosure. Protects and stops water. The high-pressure rotary jet occlusal piles added on the outside can effectively make up for the problems of soil erosion and stratum instability caused by the pipe jacking machine group during the opening and jacking process. The diameter of the pipe jacking machine is 3.5m, and it penetrates the water-rich sand layer. The method of the invention not only improves the reinforcement efficiency of the entrance and exit holes, simplifies the processing steps, but also greatly improves the quality of formation reinforcement, construction safety, construction difficulty and construction. The cost is reduced, and it can meet the construction of pipe jacking machine groups in different strata.
实施例二 Embodiment 2
如图1所示,图1为所述富水砂层大直径顶管群进出洞加固结构的结构视图;本实施例通过实际案例进行解释说明;As shown in Fig. 1, Fig. 1 is a structural view of the reinforcement structure of the inlet and outlet holes of the large-diameter pipe jacking group in the water-rich sand layer; this embodiment is explained by an actual case;
三台顶管机在始发井9内进行拼装,分别由第一进洞口6、第二进洞口7、第三进洞口8从左向右顶进,再由第一出洞口61、第二出洞口71、第三出洞口81到达接收井。The three pipe jacking machines are assembled in the starting shaft 9, and are respectively jacked from the first inlet 6, the second inlet 7, and the third inlet 8 from left to right, and then the first outlet 61, the second inlet 8 The outlet 71 and the third outlet 81 reach the receiving well.
顶管机群取出所述始发井9称为出洞,顶管机群进入所述接收井10称为进洞,如此就完成了一个循环。When the pipe jacking machine group takes out the originating well 9, it is called the exit hole, and when the pipe jacking machine group enters the receiving well 10, it is called the entrance hole, thus completing a cycle.
如图2所示,图2为所述始发井的结构视图;本发明富水砂层大直径顶管群进出洞加固结构主要是对所述始发井9和所述接收井10之间土层进行土层加固,另对工作井即所述始发井9和所述接收井10内施做所述支撑3和所述钻孔灌注桩4对所述地下连续墙2进行井内加固。所述地下连续墙2底部设置工作井底板11,所述地下连续墙2、所述高压旋喷桩5和所述钻孔灌注桩4均深入所述工作井底板11以下。As shown in Fig. 2, Fig. 2 is a structural view of the originating well; The soil layer is reinforced, and the support 3 and the bored cast-in-place pile 4 are applied to the working well, namely the originating well 9 and the receiving well 10, to reinforce the underground diaphragm wall 2 in the well. A working well bottom plate 11 is provided at the bottom of the underground diaphragm wall 2 , and the underground diaphragm wall 2 , the high-pressure rotary jetting pile 5 and the bored cast-in-place pile 4 are all deep below the working well bottom plate 11 .
所述降水井1直径为1.6m,沿工作井均匀布置。The diameter of the dewatering well 1 is 1.6m, and it is evenly arranged along the working well.
如图3所示,图3为所述高压旋喷桩的梅花式咬合结构图;所述高压旋喷桩5直径为0.6m,采用梅花式两排并列咬合成桩,与所述地下连续墙2顶进洞口并列设置,靠近所述地下连续墙2的一排高压旋喷桩5的排间距离为0.5m,注浆材料为普硅42.5水泥,水泥浆(单液),水灰比为1∶1的抗渗浆液,如此整个地层可以得到有效加固,与所述地下连续墙2形成一个致密整体,防止所述始发井9和所述接收井10破洞时的管涌和渗流。As shown in Fig. 3, Fig. 3 is a plum-shaped occlusal structure diagram of the high-pressure rotary jetting pile; 2. The top entrances are arranged side by side, and the distance between a row of high-pressure rotary jet piles 5 close to the underground diaphragm wall 2 is 0.5m. The grouting material is ordinary silicon 42.5 cement, cement slurry (single liquid), and the water-cement ratio is 1:1 impermeable slurry, so that the entire formation can be effectively reinforced, forming a compact whole with the underground diaphragm wall 2 to prevent piping and seepage when the originating well 9 and the receiving well 10 are broken.
同时控制所述高压旋喷桩5的水泥用量少于所述地下连续墙2的水泥用量,确保加固的土体强度在1.2MPa~1.5MPa,可以确保顶管机群的正常顶进,避免顶进刀盘难以破桩。At the same time, the cement dosage of the high-pressure rotary jet pile 5 is controlled to be less than the cement dosage of the underground diaphragm wall 2, so as to ensure that the strength of the reinforced soil is between 1.2 MPa and 1.5 MPa, which can ensure the normal jacking of the pipe jacking machine group and avoid the top It is difficult to break the pile into the cutter head.
所述地下连续墙2入土深度是顶管机群底部标高的两倍,可以很好的形成止水帷幕,防止基底涌起。The depth of the underground diaphragm wall 2 is twice the elevation of the bottom of the pipe jacking machine group, which can well form a water-stop curtain and prevent the base from surging.
所述始发井9和所述接收井10的井内横撑3为钢筋混凝土结构,起着对所述地下连续墙 的支撑作用,抵抗土压力,所述横撑3主要由所述钻孔灌注桩4来承重、维稳,其组合支撑体系也可用于顶管设备的吊运和安装。The cross braces 3 in the originating well 9 and the receiving well 10 are reinforced concrete structures, which play a supporting role for the underground diaphragm wall and resist the earth pressure. The cross braces 3 are mainly poured from the borehole. The pile 4 is used for load bearing and stability maintenance, and its combined support system can also be used for the lifting and installation of the pipe jacking equipment.
在所述始发井9和所述接收井10外缘土层,沿着地下水流势方向设置降水井1,进行井点降水,增强土体强度,提高洞门的密闭性。Dewatering wells 1 are arranged in the outer edge soil layers of the originating well 9 and the receiving well 10 along the direction of groundwater flow potential to conduct well point dewatering, enhance soil strength, and improve the airtightness of the cave door.
在所述始发井9和所述接收井10的边缘采用地下连续墙工法形成围护结构,所述地下连续墙2厚为0.8m,入土深度是顶管机群底部标高的两倍,可以形成止水帷幕,有效的防止水土渗流进入所述始发井9和所述接收井10。地下连续墙顶部制作截面尺寸为1m*0.8m的圈梁,使地下连续墙形成整体。地下连续墙接头形式采用刚性接头十字钢板进行接缝。On the edges of the originating well 9 and the receiving well 10, an underground diaphragm wall method is used to form the enclosure structure. The thickness of the underground diaphragm wall 2 is 0.8m, and the depth of soil penetration is twice the elevation of the bottom of the pipe jacking machine group. The water-stop curtain effectively prevents water and soil seepage from entering the originating well 9 and the receiving well 10 . A ring beam with a section size of 1m*0.8m is made on the top of the diaphragm wall, so that the diaphragm wall can form a whole. The joint form of underground diaphragm wall adopts rigid joint cross steel plate for joint.
在所述始发井9和所述接收井10的周边地下连续墙施工完成后,施工内部横撑3和钻孔灌注桩4,所述横撑3用于维持工作井的稳定,阻止由外部土压力所造成的地下连续墙2向内变形,防止坍塌。所述钻孔灌注桩4直径为0.6m,采用42.5级以上普通硅酸盐水泥,C30混凝土,用以所述始发井9和所述接收井10内横撑和吊运设备的承重。After the construction of the surrounding underground diaphragm walls of the originating well 9 and the receiving well 10 is completed, the internal cross braces 3 and bored cast-in-place piles 4 are constructed. The cross braces 3 are used to maintain the stability of the working well and prevent external The underground diaphragm wall 2 caused by the earth pressure is deformed inward to prevent collapse. The diameter of the bored pile 4 is 0.6m, and ordinary Portland cement above grade 42.5 and C30 concrete are used for the load-bearing of the cross braces and the lifting equipment in the originating well 9 and the receiving well 10 .
在始发井9的前端即顶管机群出洞的一侧,接收井10的前端即顶管机群进洞的一侧间的土层进行加固。在加固区域地表进行硬化处理,采用高压旋喷桩法进行地层加固和隔水,采用42.5级以上普通硅酸盐水泥,等级为C20,采用梅花式间隔咬合布置,直径为0.6m。所述高压旋喷桩与始发井出洞一侧地下连续墙和接收井进洞一侧地下连续墙间隔0.5m,所述高压旋喷桩群超出宽度是顶管及直径的一半,所述高压旋喷桩群深度超出顶管机标高的一倍,并能穿过透水层,在高压旋喷桩施工时,可有效与地下连续墙形成一个致密整体。The soil layer between the front end of the originating well 9, that is, the side where the pipe jacking machine group exits the hole, and the front end of the receiving well 10, that is, the side where the pipe jacking machine group enters the hole, is reinforced. The surface of the reinforcement area is hardened, and the high-pressure rotary jet pile method is used for formation reinforcement and water isolation. Ordinary Portland cement of grade 42.5 or above is used, and the grade is C20. The high-pressure jetting piles are separated by 0.5m from the underground diaphragm wall on the exit side of the originating well and the underground diaphragm wall on the entrance side of the receiving well. The depth of the jetting pile group exceeds twice the elevation of the pipe jacking machine, and can pass through the permeable layer. During the construction of the high-pressure jetting pile, it can effectively form a dense whole with the underground diaphragm wall.
实施例三 Embodiment 3
如图4所示,图4为所述顶管进出洞加固构造图,所述洞口12设置有止水圈,所述洞口12为所述顶管群进出洞的洞口,所述止水圈内嵌在内衬结构13和围护结构14,所述围护结构14为地下连续墙,所述内衬结构13为地下连续墙向工作井延伸的混凝土加固结构。图中经加固的土体17可以为所述高压旋喷桩5。As shown in FIG. 4, FIG. 4 is a reinforcement structure diagram of the inlet and outlet holes of the jacking pipe, the hole 12 is provided with a water stop ring, and the hole 12 is the hole of the inlet and outlet holes of the jacking pipe group. Embedded in an inner lining structure 13 and an enclosure structure 14, the enclosure structure 14 is an underground diaphragm wall, and the inner lining structure 13 is a concrete reinforcement structure extending from the underground diaphragm wall to the working well. The reinforced soil body 17 in the figure may be the high-pressure jetted pile 5 .
所述止水圈包括预埋钢环15、压板19、橡胶圈20和安装钢环18,所述压板19和所述橡胶圈20设置在所述预埋钢环15和所述安装钢环18之间,在设置所述围护结构14时,预埋所述预埋钢环15,所述预埋钢环15内部凿除后形成预留洞口,所述预埋钢环的内径同预留洞口一样大小。在所述止水圈长度较长的情况下,所述预埋钢环15内还可设置环形钢筋混凝土保护圈16,采用所述环形钢筋混凝土保护圈16替代部分所述橡胶圈20,所述橡胶圈20设置在所述工作井一侧,并通过所述压板19对所述橡胶圈20进行压紧,从而保证所述预埋钢环15和所述安装钢环18之间密封效果良好。The water stop ring includes a pre-embedded steel ring 15, a pressure plate 19, a rubber ring 20 and an installation steel ring 18. The pressure plate 19 and the rubber ring 20 are arranged on the pre-embedded steel ring 15 and the installation steel ring 18. In between, when the enclosure structure 14 is set, the pre-embedded steel ring 15 is pre-embedded, and a reserved hole is formed after the inside of the pre-embedded steel ring 15 is chiseled, and the inner diameter of the pre-embedded steel ring is the same as the reserved hole. The hole is the same size. When the length of the water stop ring is long, an annular reinforced concrete protection ring 16 may also be arranged in the embedded steel ring 15, and the annular reinforced concrete protection ring 16 is used to replace part of the rubber ring 20. The rubber ring 20 is arranged on one side of the working well, and the rubber ring 20 is pressed by the pressing plate 19 to ensure a good sealing effect between the embedded steel ring 15 and the installation steel ring 18 .
为了使所述预埋钢环15能牢固地预埋在洞口井壁上,在它与混凝土接触的一面焊接数根开叉的锚杆,主要是方便顶管机出洞时凿除地连墙洞门,稳固地连续墙上部结构,不使其他部位受到洞门凿除的影响;在所述安装钢环18上焊数根螺栓用来安装所述橡胶圈20和所述压板19,所述压板19用来固定所述橡胶圈20的位置,防止其发生变形移位。In order to make the pre-embedded steel ring 15 firmly pre-embedded on the wall of the hole, several split anchor rods are welded on the side where it is in contact with the concrete, which is mainly to facilitate the removal of the ground connecting wall when the pipe jacking machine exits the hole. The hole door is firmly connected to the upper structure of the wall, so that other parts are not affected by the removal of the hole door; several bolts are welded on the installation steel ring 18 to install the rubber ring 20 and the pressure plate 19. The pressing plate 19 is used to fix the position of the rubber ring 20 to prevent it from being deformed and displaced.
较佳的,所述橡胶圈20和所述环形钢筋混凝土保护圈16连接位置处设置卡接结构,通过所述卡接结构实现所述橡胶圈20和所述环形钢筋混凝土保护圈16之间的咬合,形成柔性和刚性搭接,所述橡胶圈20置于洞门口处,由其弹性膨胀特性,可以更好的密封管节与上部结构,防止渗水。Preferably, a clamping structure is provided at the connection position of the rubber ring 20 and the annular reinforced concrete protection ring 16 , and the connection between the rubber ring 20 and the annular reinforced concrete protection ring 16 is realized through the clamping structure. The rubber ring 20 is placed at the door of the hole, and due to its elastic expansion characteristics, it can better seal the pipe joint and the upper structure to prevent water seepage.
实施例四 Embodiment 4
如图5所示,图5为所述富水砂层大直径顶管群进出洞加固结构的施工方法的流程图;本发明所述富水砂层大直径顶管群进出洞加固结构的施工方法,包括以下步骤:As shown in Figure 5, Figure 5 is a flowchart of the construction method of the water-rich sand layer large-diameter pipe jacking group in-out hole reinforcement structure; the construction of the water-rich sand layer large-diameter pipe group in-out hole reinforcement structure method, including the following steps:
S1,确定加固要求及区域;S1, determine the reinforcement requirements and areas;
本地层为富水砂层,测得地下水位埋深1.3~7.6米,水位标高4.5~20.0米。人工素填土土体渗透系数≤1.00×10-5cm/s,属于中等透水等级,故地层表面只需简单注浆硬化处理。底部粉砂、中砂、强风化玄武岩和粗砂层,其渗透系数k,1.10×10-2cm/s≤k≤1.08×10-3cm/s,属强透水层,水理性质较差,存在渗透变形稳定问题,属于较不稳定土层,易于发生渗透变形,故加固要求较高,要使土体形成致密连续土层,不发生流塑现象。根据设计要求确定地层加固要求,保证地层的稳定性。The local layer is a water-rich sand layer. The measured groundwater depth is 1.3 to 7.6 meters, and the water level elevation is 4.5 to 20.0 meters. The permeability coefficient of artificial plain filled soil is less than or equal to 1.00×10-5cm/s, which belongs to the medium water permeability level, so the surface of the stratum needs only simple grouting and hardening treatment. The bottom silt, medium sand, strongly weathered basalt and coarse sand layers have a permeability coefficient k of 1.10×10-2cm/s≤k≤1.08×10-3cm/s, which are highly permeable layers with poor hydraulic properties. Seepage deformation stability is a relatively unstable soil layer, which is prone to seepage deformation, so the reinforcement requirements are higher, and the soil should form a dense and continuous soil layer without flow-plastic phenomenon. Determine the stratum reinforcement requirements according to the design requirements to ensure the stability of the stratum.
本顶管机直径为3.5m,考虑到顶管机群设备的吊运安装和顶进后背的制作,设置工作井的开挖设计为:工作井长24.1m,宽11.4m,以此来确定场区加固区域。The diameter of the pipe jacking machine is 3.5m. Considering the hoisting and installation of the pipe jacking machine group and the production of the jacking back, the excavation design of the working well is as follows: the working well is 24.1m long and 11.4m wide. area reinforcement.
S2,地表加固处理;S2, surface reinforcement treatment;
首先在场区边缘沿着地下水流势走向均匀对称设置直径1.6m的降水井,设计标准值只需将坑底降水,降到坑底0.5m以下,本工程考虑到土层主要为粉砂、中砂、粗砂、粉质粘土和强风化玄武岩,降水井深度为顶管机顶进隧道底部以下10m。First of all, a dewatering well with a diameter of 1.6m is set up uniformly and symmetrically along the groundwater flow potential at the edge of the field area. The design standard value only needs to dewater the pit bottom to less than 0.5m. For sand, coarse sand, silty clay and strongly weathered basalt, the depth of the dewatering well is 10m below the bottom of the tunnel where the pipe jacking machine is jacked.
然后进行地表整平,加固采用对场区清理并对地表注浆硬化处理,注浆采用水泥单浆液,按设计要求提供场区材料、进场设备。Then, the surface is leveled, and the field area is cleaned and hardened by grouting on the surface for reinforcement. The grouting adopts cement single grout, and the field materials and access equipment are provided according to the design requirements.
S3,工作井内加固处理;S3, reinforcement treatment in the working well;
工作井长24.1m,宽11.4m。围护结构采用地下连续墙+1.0m×0.8m钢筋混凝土内支撑体系,连续墙宽80cm,8幅标准“一”段,4幅异型“L”段,标准段宽度为6m,异型段宽度为5.75m,The working well is 24.1m long and 11.4m wide. The enclosure structure adopts the underground diaphragm wall + 1.0m×0.8m reinforced concrete internal support system, the diaphragm wall is 80cm wide, 8 standard "one" sections, 4 special-shaped "L" sections, the standard section width is 6m, and the special-shaped section width is 5.75m,
工作井外缘采用0.8m厚的地下连续墙,地下连续墙的施工包括按设计图纸测量定位、放样画线、顶部基槽开挖、施做导墙、泥浆护壁系统、深层沟槽开挖、下放钢筋笼浇筑混凝土、拔出导管。地下连续墙顶部制作截面尺寸为1m*0.8m的圈梁,使地下连续墙形成整体。地下连续墙接头形式采用刚性接头十字钢板进行接缝。The outer edge of the working well adopts a 0.8m thick underground diaphragm wall. The construction of the underground diaphragm wall includes measuring and positioning according to the design drawings, lofting and drawing lines, excavation of the top foundation groove, construction of guide walls, mud wall protection system, deep trench excavation, Lower the steel cage to pour concrete and pull out the conduit. A ring beam with a section size of 1m*0.8m is made on the top of the diaphragm wall, so that the diaphragm wall can form a whole. The joint form of underground diaphragm wall adopts rigid joint cross steel plate for joint.
接着在工作井内部中心对称施工一排两根间距6m的C30钻孔灌注桩,采用泥浆护壁成孔,直径0.6m。泥浆系统采用膨润土制备的泥浆循环系统,配以泥浆池,钻孔采用冲击钻成孔。然后进行工作井的开挖,开挖采用分步开挖,由两边向中间对称开挖,采用三序成槽的方式,开挖过程中实时监测、随偏随纠,然后在开挖标高9.5m处设置钢筋混凝土水平横撑和水平纵向支撑,本工程支撑均为永久支撑,不涉及换拆撑工艺。接着施工底板结构,采用素混凝土垫层封底,一次性浇筑完成,紧接着用钢筋混凝土结构施做底板,施工缝位于底板侧墙上方1.2m处。Then, a row of two C30 bored piles with a spacing of 6m are constructed symmetrically in the center of the working well, and the mud wall is used to form holes with a diameter of 0.6m. The mud system adopts a mud circulation system made of bentonite, and is equipped with a mud pool. The drilling is made by percussion drilling. Then carry out the excavation of the working well. The excavation adopts step-by-step excavation, and the excavation is symmetrical from both sides to the middle. The three-sequence trough is adopted. The reinforced concrete horizontal transverse bracing and horizontal longitudinal bracing are arranged at m, and the supports in this project are all permanent supports and do not involve the replacement and dismantling process. Next, the base plate structure is constructed, and the back cover is covered with a plain concrete cushion, and the pouring is completed at one time, and then the base plate is constructed with a reinforced concrete structure, and the construction joint is located 1.2m above the side wall of the base plate.
S4,顶管进出洞端头加固;S4, the end of the jacking pipe inlet and outlet holes is reinforced;
所述顶管进出洞端头加固采用高压旋喷桩加固,根据富水砂层特性,设计高压旋喷桩的直径和间距,旋喷桩采用单管法,在砂土中单管法设计直径为0.6~1.0m,考虑其经济合理性和相互搭接连续性,桩径采用0.6m,采用二排注浆孔;孔距标准设计值为0.866R,故桩间孔距取0.5m;排距设计值为0.75R,故排距取0.45m,采用普通硅酸盐42.5水泥,水泥单浆液水灰比1∶1,进行同步注浆和跟进补浆过程,控制注浆速率和均匀程度;在始发井出洞外侧和接收井进洞外侧采用梅花式双排咬合布置,其具体布置方式按图3中“Z”型布置,按图中“a-b-c-d-e-f-g”施工顺序搭接咬合,咬合搭接可以有效地形成整体搭接;高压旋喷桩施工包括测量放线、确定孔位、钻机造孔、清孔、喷浆作业。The end of the pipe jacking inlet and outlet holes is reinforced by high-pressure jetting piles. According to the characteristics of the water-rich sand layer, the diameter and spacing of the high-pressure jetting piles are designed. The single-pipe method is used for the rotary jetting piles. The diameter of the pile is 0.6~1.0m, considering its economic rationality and the continuity of mutual overlap, the pile diameter is 0.6m, and two rows of grouting holes are used; The design value of the distance is 0.75R, so the row distance is 0.45m. Ordinary silicate 42.5 cement is used, and the water-cement ratio of cement single slurry is 1:1 to carry out synchronous grouting and follow-up grouting process, and control the grouting rate and uniformity; The plum-shaped double-row occlusal arrangement is adopted on the outside of the exit hole of the originating well and the outside of the entry hole of the receiving well. The specific arrangement is arranged according to the "Z" shape in Figure 3, and the lap joint according to the construction sequence of "a-b-c-d-e-f-g" in the figure, the occlusal lap joint can be Effectively form an overall lap; the construction of high-pressure rotary jetting piles includes measuring and laying out lines, determining hole positions, drilling holes, cleaning holes, and spraying.
在步骤S4中,施工高压旋喷桩之前应先进行高压旋喷桩工艺性试桩试验,根据高压旋喷桩工艺性试验确定了高压旋喷施工技术参数,作为项目高压旋喷桩施工的技术参数依据,从而保证高压旋喷桩的施工质量。In step S4, before constructing the high-pressure jetting pile, a technical test of the high-pressure jetting pile should be carried out. Parameter basis, so as to ensure the construction quality of high-pressure rotary jetting piles.
S5,在洞口安装止水圈,洞口止水圈主要由预埋钢环、压板、橡胶圈和安装钢环组成。为了使预埋钢环能牢固地预埋在洞口井壁上,在它与混凝土接触的一面焊接数根开叉的锚杆,预埋钢环的内径同预留洞口一样大小;安装钢环是焊在预埋钢环上的,在安装钢环上焊数根螺栓用来安装橡胶圈和压板。S5, install a water stop ring at the entrance of the hole. The water stop ring at the entrance is mainly composed of a pre-embedded steel ring, a pressure plate, a rubber ring and an installation steel ring. In order to make the embedded steel ring firmly embedded on the hole wall, several split anchors are welded on the side it contacts with the concrete. The inner diameter of the embedded steel ring is the same size as the reserved hole; the installation of the steel ring is Welded on the embedded steel ring, several bolts are welded on the installation steel ring to install the rubber ring and the pressure plate.
安装位置要根据出洞轴心位置进行调整,由于顶管出洞时不可避免有一定偏离出洞轴线位置,止水圈允许机头有2cm轴线位置,若机头偏差超过2cm,止水圈的安装位置必须根据实际偏差进行调整。The installation position should be adjusted according to the axis position of the exit hole. Since the jacking pipe will inevitably deviate from the axis position of the exit hole, the water stop ring allows the machine head to have a 2cm axis position. If the deviation of the machine head exceeds 2cm, the water stop ring The installation position must be adjusted according to the actual deviation.
机头的直径一般比管外径大2cm,使得管与洞之间有2cm的空隙,容易形成泥浆套,便 于减少管壁与土之间的摩擦阻力。管环长度采用2.6m,使首节管环完全顶进后,其断面处在旋喷桩加固区柱断面处。The diameter of the machine head is generally 2cm larger than the outer diameter of the pipe, so that there is a gap of 2cm between the pipe and the hole, which is easy to form a mud sleeve, which is convenient to reduce the frictional resistance between the pipe wall and the soil. The length of the pipe ring is 2.6m, so that after the first pipe ring is fully jacked, its section is at the column section in the reinforced area of the rotary jet pile.
考虑到地下连续墙厚0.8m,旋喷桩直径0.6m,二排排距0.45m,为防止首管破洞顶进出现洞口流土现象,管环长度采用2.6m,使首节管环完全顶进后,其断面处在旋喷桩加固区柱断面处。Considering that the thickness of the underground diaphragm wall is 0.8m, the diameter of the rotary jetting pile is 0.6m, and the spacing of the second row is 0.45m, in order to prevent the phenomenon of soil flow at the entrance of the first pipe when the first pipe is broken into the hole, the length of the pipe ring is 2.6m, so that the first pipe ring is completely After jacking in, its section is at the column section in the reinforced area of the rotary jet pile.
较佳的,所述地下连续墙的埋深超出顶管机群底部标高的10m,可以有效形成止水帷幕。Preferably, the buried depth of the underground diaphragm wall is 10m higher than the elevation of the bottom of the pipe jacking machine group, which can effectively form a water-stop curtain.
较佳的,所述高压旋喷桩群的宽度超出顶管机宽度的一半。Preferably, the width of the high-pressure jetting pile group exceeds half of the width of the pipe jacking machine.
较佳的,所述高压旋喷桩高度超出顶管机标高一倍,与所述地下连续墙的间距为0.5m,可以与之有效结合加固洞口前方土层。Preferably, the height of the high-pressure jetting pile is twice the elevation of the pipe jacking machine, and the distance from the underground diaphragm wall is 0.5m, which can be effectively combined with it to reinforce the soil layer in front of the hole.
高压旋喷桩所用的材料为水泥浆,利用高压经过旋转的喷嘴将水泥浆喷入土层与土体混合形成水泥土加固体,相互搭接形成排桩,用来挡土和止水,减少了架设临时支护这一工序。提高顶管机进出洞的效率,降低进出洞的成本。The material used for the high-pressure rotary spray pile is cement slurry. The cement slurry is sprayed into the soil layer and mixed with the soil by high pressure through the rotating nozzle to form cement-soil solids, which overlap each other to form piles for retaining soil and water, reducing the The process of erecting temporary supports. Improve the efficiency of the pipe jacking machine entering and exiting the hole, and reduce the cost of entering and exiting the hole.
通过本发明方法对大直径顶管群进出洞进行加固处理,不但提高了进出洞口的加固效率,简化加工工艺步骤,而且大大提高了地层加固的质量,施工难度和施工成本降低,保证了工程的工期、质量性和经济性。The method of the invention is used to reinforce the inlet and outlet holes of the large-diameter pipe jacking group, which not only improves the reinforcement efficiency of the inlet and outlet holes, simplifies the processing steps, but also greatly improves the quality of the stratum reinforcement, reduces the construction difficulty and construction cost, and ensures the safety of the project. Duration, quality and economy.
以上所述仅为本发明的较佳实施例,对本发明而言仅仅是说明性的,而非限制性的。本专业技术人员理解,在本发明权利要求所限定的精神和范围内可对其进行许多改变,修改,甚至等效,但都将落入本发明的保护范围内。The above descriptions are only preferred embodiments of the present invention, which are merely illustrative rather than limiting for the present invention. Those skilled in the art understand that many changes, modifications and even equivalents can be made within the spirit and scope defined by the claims of the present invention, but all fall within the protection scope of the present invention.

Claims (10)

  1. 一种富水砂层大直径顶管群进出洞加固结构,其特征在于,包括地下连续墙、高压旋喷桩,所述地下连续墙设置在始发井和接收井的边缘位置处,所述地下连续墙深度至顶管机底部标高以下;在所述始发井和所述接收井内侧中部设置钻孔灌注桩,所述钻孔灌注桩与所述地下连续墙同深度,所述地下连续墙之间采用横撑支撑,所述横撑和所述钻孔灌注桩固定连接;所述高压旋喷桩设置在顶管群进出洞及所述地下连续墙外侧,所述高压旋喷桩设置为梅花式咬合的排状结构,与所述地下连续墙并行布置,且与所述地下连续墙之间设置间距,所述高压旋喷桩深度超出顶管机底部,宽度沿所述地下连续墙超出顶管机。A large-diameter pipe jacking in-out hole reinforcement structure in a water-rich sand layer is characterized in that it includes an underground diaphragm wall and a high-pressure rotary jet pile, the underground diaphragm wall is arranged at the edge positions of the originating well and the receiving well, and the The depth of the underground diaphragm wall is below the bottom elevation of the pipe jacking machine; bored cast-in-place piles are arranged in the middle of the inner side of the originating well and the receiving well, and the bored cast-in-place piles are at the same depth as the underground diaphragm wall, and the underground continuous The walls are supported by cross braces, and the cross braces are fixedly connected with the bored cast-in-place piles; the high-pressure jetting piles are arranged at the inlet and outlet holes of the pipe jacking group and the outside of the underground continuous wall, and the high-pressure jetting piles are arranged It is a row-like structure with a plum-like occlusion, which is arranged in parallel with the underground diaphragm wall, and is spaced from the underground diaphragm wall. Beyond the pipe jacking machine.
  2. 如权利要求1所述的富水砂层大直径顶管群进出洞加固结构,其特征在于,所述地下连续墙厚度为0.6m~1m。The large-diameter jacking pipe group access hole reinforcement structure of claim 1, wherein the thickness of the underground diaphragm wall is 0.6m to 1m.
  3. 如权利要求1所述的富水砂层大直径顶管群进出洞加固结构,其特征在于,所述顶管群进出洞前方地表土层进行加固硬化处理,并在所述高压旋喷桩及所述地下连续墙外侧均匀设置降水井。The large-diameter pipe jacking group entry and exit hole reinforcement structure in a water-rich sand layer according to claim 1, wherein the surface soil layer in front of the pipe jacking group entrance and exit holes is reinforced and hardened, and the high-pressure rotary jetting pile and the surface soil layer are reinforced and hardened. Dewatering wells are evenly arranged on the outer side of the underground continuous wall.
  4. 如权利要求1所述的富水砂层大直径顶管群进出洞加固结构,其特征在于,所述地下连续墙的埋深超出顶管机群底部标高的10m。The large-diameter pipe jacking group entry and exit hole reinforcement structure in a water-rich sand layer according to claim 1, wherein the buried depth of the underground diaphragm wall is 10m beyond the bottom elevation of the pipe jacking machine group.
  5. 如权利要求1所述的富水砂层大直径顶管群进出洞加固结构,其特征在于,所述高压旋喷桩群的宽度超出顶管机宽度的一半,所述高压旋喷桩深度超出顶管机底部5m。The large-diameter pipe jacking hole reinforcement structure of claim 1, wherein the width of the high-pressure jetting pile group exceeds half the width of the pipe jacking machine, and the high-pressure jetting pile depth exceeds The bottom of the pipe jacking machine is 5m.
  6. 如权利要求1所述的富水砂层大直径顶管群进出洞加固结构,其特征在于,所述高压旋喷桩高度超出顶管机标高的一倍,与所述地下连续墙的间距为0.5m。The large-diameter pipe jacking hole reinforcement structure of water-rich sand layer according to claim 1, characterized in that, the height of the high-pressure jetting pile exceeds twice the elevation of the pipe jacking machine, and the distance from the underground diaphragm wall is 0.5m.
  7. 一种如权利要求1-6中仍一项所述的富水砂层大直径顶管群进出洞加固结构的施工方法,其特征在于,包括步骤:A construction method for the reinforcement structure of the large diameter pipe jacking group in and out of the water-rich sand layer as described in one of claims 1-6, characterized in that, comprising the steps of:
    S1,确定加固要求及区域;S1, determine the reinforcement requirements and areas;
    S2,地表加固处理;S2, surface reinforcement treatment;
    S3,工作井内加固处理;S3, reinforcement treatment in the working well;
    S4,顶管进出洞端头加固。S4, the end of the jacking pipe inlet and outlet holes is reinforced.
    S5,顶管进出质量控制。S5, pipe jacking in and out quality control.
  8. 如权利要求7所述的施工方法,其特征在于,在步骤S2中,在场区边缘沿着地下水流势走向均匀对称设置所述降水井,所述降水井深度为顶管机顶进隧道底部以下10m;所述降水井设置完成后进行地表整平,加固采用对场区清理并对地表注浆硬化处理,注浆采用水泥单浆液。The construction method according to claim 7, characterized in that, in step S2, the dewatering wells are evenly and symmetrically arranged along the groundwater flow potential at the edge of the site, and the dewatering well depth is below the bottom of the tunnel where the pipe jacking machine is jacked. 10m; after the dewatering well is installed, the surface is leveled, and the field area is cleaned and the surface is grouted and hardened for reinforcement, and the grouting adopts cement single grout.
  9. 如权利要求7所述的施工方法,其特征在于,在步骤S3中,在工作井外缘进行所述地下连续墙施工,所述地下连续墙施工完成后,在所述工作井内部中心对称施工所述钻孔灌 注桩,所述钻孔灌注桩采用泥浆护壁成孔,后采用三序成槽的方式进行所述工作井的开挖,开挖采用分步开挖,由两边向中间对称开挖,在开挖设计标高后设置所述横撑,并施工工作井底板。The construction method according to claim 7, characterized in that, in step S3, the construction of the underground diaphragm wall is performed on the outer edge of the working well, and after the construction of the underground diaphragm wall is completed, the construction is performed centrally symmetrically inside the working well. The bored cast-in-place piles are formed by mud retaining walls to form holes, and then the excavation of the working well is carried out by means of three-sequence formation of grooves. Excavate, set up the horizontal brace after excavating the design elevation, and construct the bottom plate of the working well.
  10. 如权利要求7所述的施工方法,其特征在于,在步骤S5中,所述顶管群进出洞的洞口设置止水圈,所述止水圈内嵌在内衬结构和围护结构,所述围护结构为地下连续墙,所述内衬结构为地下连续墙向工作井延伸的混凝土加固结构;所述止水圈包括预埋钢环、压板、橡胶圈和安装钢环,所述压板和所述橡胶圈设置在所述预埋钢环和所述安装钢环之间,在设置所述围护结构时,预埋所述预埋钢环,所述预埋钢环内部凿除后形成预留洞口,所述预埋钢环的内径同预留洞口一样大小;所述预埋钢环内设置环形钢筋混凝土保护圈,所述橡胶圈设置在所述工作井一侧,并通过所述压板对所述橡胶圈进行压紧。The construction method according to claim 7, characterized in that, in step S5, a water stop ring is set at the entrance of the inlet and outlet holes of the jacking pipe group, and the water stop ring is embedded in the lining structure and the enclosure structure, so The enclosure structure is an underground diaphragm wall, and the lining structure is a concrete reinforcement structure extending from the underground diaphragm wall to the working well; the water stop ring includes a pre-embedded steel ring, a pressure plate, a rubber ring and an installation steel ring, the pressure plate and the rubber ring is arranged between the pre-embedded steel ring and the installation steel ring, when the enclosure structure is set, the pre-embedded steel ring is pre-embedded, and after the inside of the pre-embedded steel ring is chiseled A reserved hole is formed, and the inner diameter of the embedded steel ring is the same size as the reserved hole; an annular reinforced concrete protection ring is arranged in the embedded steel ring, and the rubber ring is arranged on one side of the working well and passes through all the holes. The pressing plate presses the rubber ring.
PCT/CN2021/123555 2020-11-10 2021-10-13 Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method WO2022100346A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202011251544.7A CN112253162B (en) 2020-11-10 2020-11-10 Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method
CN202011251544.7 2020-11-10

Publications (1)

Publication Number Publication Date
WO2022100346A1 true WO2022100346A1 (en) 2022-05-19

Family

ID=74265194

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/123555 WO2022100346A1 (en) 2020-11-10 2021-10-13 Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method

Country Status (2)

Country Link
CN (1) CN112253162B (en)
WO (1) WO2022100346A1 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112253162B (en) * 2020-11-10 2022-11-08 中铁四局集团有限公司 Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method
CN113338947B (en) * 2021-04-14 2024-04-09 浙江交工集团股份有限公司 Water-rich sand layer anti-flowing sand water-surge working well and construction method thereof
CN113464150A (en) * 2021-08-13 2021-10-01 中国建设基础设施有限公司 Shield end reinforcing structure and reinforcing construction method
CN114060040A (en) * 2021-11-11 2022-02-18 上海市基础工程集团有限公司 Horizontal T-joint construction method for directly jacking pipe into shield tunnel
CN115288113A (en) * 2022-07-20 2022-11-04 中国一冶集团有限公司 Reinforced structure for jacking and withdrawing of jacking pipe and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030065963A (en) * 2002-02-02 2003-08-09 백상현 A method of constrution method for tunnel of structure pipe
JP2012162877A (en) * 2011-02-04 2012-08-30 Taisei Corp Construction method for underground structure, and the underground structure
CN105041322A (en) * 2015-06-08 2015-11-11 上海隧道工程有限公司 Method and system for reinforcing hole for push bench to go in and out
CN108612106A (en) * 2016-12-10 2018-10-02 中铁十二局集团有限公司 Subway layer of sand open-cut foundation ditch construction method
CN110206339A (en) * 2019-06-14 2019-09-06 北京翔鲲水务建设有限公司 A kind of push pipe passes through construction method of underground continuous wall
CN111794780A (en) * 2020-03-31 2020-10-20 中铁十六局集团北京轨道交通工程建设有限公司 Shield tunneling machine in-out hole safety guarantee method for water-rich round gravel stratum
CN111810176A (en) * 2020-08-12 2020-10-23 通州建总集团有限公司 Subway station end reinforcement construction method for water-rich sand layer shield construction
CN112253162A (en) * 2020-11-10 2021-01-22 中铁四局集团有限公司 Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101781991B (en) * 2010-02-10 2012-05-30 中铁三局集团有限公司 Double-well type reinforcement method of shield arrival or starting end and double-well type shield arrival method
CN106609508A (en) * 2015-10-22 2017-05-03 中铁十四局集团有限公司 Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain
CN106050244A (en) * 2016-08-01 2016-10-26 中铁第勘察设计院集团有限公司 Water-rich sand-cobble stratum shield entry and exit reinforcing system and construction method thereof
CN106285693B (en) * 2016-08-31 2018-10-19 中铁十六局集团北京轨道交通工程建设有限公司 A kind of closed reception construction method of shield steel bushing
CN106759380A (en) * 2017-02-27 2017-05-31 中铁第勘察设计院集团有限公司 The foundation pit enclosure structure of multiple tracks diaphram wall combination stratum consolidation and precipitation
CN206529779U (en) * 2017-02-27 2017-09-29 中铁第一勘察设计院集团有限公司 A kind of foundation pit enclosure structure of multiple tracks diaphram wall combination stratum consolidation and precipitation
CN107676097B (en) * 2017-08-27 2019-09-13 中铁十二局集团有限公司 A kind of high hydraulic pressure soft soil layer HFE composite shield originating method
CN111706342A (en) * 2020-06-30 2020-09-25 北京市市政工程设计研究总院有限公司 Shield end reinforcing method based on closed stratum in water-rich sandy gravel stratum

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030065963A (en) * 2002-02-02 2003-08-09 백상현 A method of constrution method for tunnel of structure pipe
JP2012162877A (en) * 2011-02-04 2012-08-30 Taisei Corp Construction method for underground structure, and the underground structure
CN105041322A (en) * 2015-06-08 2015-11-11 上海隧道工程有限公司 Method and system for reinforcing hole for push bench to go in and out
CN108612106A (en) * 2016-12-10 2018-10-02 中铁十二局集团有限公司 Subway layer of sand open-cut foundation ditch construction method
CN110206339A (en) * 2019-06-14 2019-09-06 北京翔鲲水务建设有限公司 A kind of push pipe passes through construction method of underground continuous wall
CN111794780A (en) * 2020-03-31 2020-10-20 中铁十六局集团北京轨道交通工程建设有限公司 Shield tunneling machine in-out hole safety guarantee method for water-rich round gravel stratum
CN111810176A (en) * 2020-08-12 2020-10-23 通州建总集团有限公司 Subway station end reinforcement construction method for water-rich sand layer shield construction
CN112253162A (en) * 2020-11-10 2021-01-22 中铁四局集团有限公司 Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method

Also Published As

Publication number Publication date
CN112253162A (en) 2021-01-22
CN112253162B (en) 2022-11-08

Similar Documents

Publication Publication Date Title
WO2022100346A1 (en) Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN205742213U (en) Foundation pit supporting construction
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN110541721A (en) Support system and construction method for fully weathered surrounding rock tunnel in water-rich quicksand stratum
CN111997624A (en) Shallow-buried large-section underground excavation rectangular tunnel construction method
CN103321246A (en) Underground diaphragm wall based foundation pit construction method
CN110397057A (en) A kind of soft soil area Self-sinking type steel open caisson support system and method
CN106638643A (en) Water-stopping-curtain construction device and method
CN110700280A (en) Narrow zone foundation pit supporting construction flow guide device and construction method
CN111364532B (en) Existing pile foundation reinforcement method based on slurry control
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN110777775A (en) Foundation pit structure and construction method thereof
CN207659986U (en) A kind of building or structures foundation stabilization underpin pier
CN114109442A (en) Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method
CN110500119B (en) Waterproof consolidation structure construction method for penetrating through debris flow accumulation body tunnel
CN114541408B (en) Front upper part wind-containing well structure of underground station end well and underpass construction method thereof
CN205804366U (en) A kind of slag runner structure
CN113914909A (en) Tunnel water inrush point emergency rescue plugging structure and construction method thereof
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area
CN113464150A (en) Shield end reinforcing structure and reinforcing construction method
CN106013168A (en) Slag trough structure and construction method for same
CN213867843U (en) Deep foundation pit supporting structure for deep sludge layer
CN117702815B (en) Symmetrical extension construction method for lateral open cut of existing underground space
CN218204422U (en) Foundation pit supporting structure of PRC tubular pile and prestressed anchorage cable combination

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21890873

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21890873

Country of ref document: EP

Kind code of ref document: A1

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 17/10/2023)