WO2021009873A1 - 掘削軌道生成方法、システム、及び掘削軌道生成装置 - Google Patents

掘削軌道生成方法、システム、及び掘削軌道生成装置 Download PDF

Info

Publication number
WO2021009873A1
WO2021009873A1 PCT/JP2019/028107 JP2019028107W WO2021009873A1 WO 2021009873 A1 WO2021009873 A1 WO 2021009873A1 JP 2019028107 W JP2019028107 W JP 2019028107W WO 2021009873 A1 WO2021009873 A1 WO 2021009873A1
Authority
WO
WIPO (PCT)
Prior art keywords
excavation
track
point
information
height information
Prior art date
Application number
PCT/JP2019/028107
Other languages
English (en)
French (fr)
Inventor
達也 吉本
裕志 吉田
Original Assignee
日本電気株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本電気株式会社 filed Critical 日本電気株式会社
Priority to PCT/JP2019/028107 priority Critical patent/WO2021009873A1/ja
Priority to JP2021532619A priority patent/JP7248122B2/ja
Priority to US17/624,923 priority patent/US20220275606A1/en
Publication of WO2021009873A1 publication Critical patent/WO2021009873A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/435Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like
    • E02F3/437Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like providing automatic sequences of movements, e.g. linear excavation, keeping dipper angle constant
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/26Indicating devices
    • E02F9/261Surveying the work-site to be treated
    • E02F9/262Surveying the work-site to be treated with follow-up actions to control the work tool, e.g. controller
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05DSYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
    • G05D1/00Control of position, course, altitude or attitude of land, water, air or space vehicles, e.g. using automatic pilots
    • G05D1/02Control of position or course in two dimensions
    • G05D1/021Control of position or course in two dimensions specially adapted to land vehicles
    • G05D1/0212Control of position or course in two dimensions specially adapted to land vehicles with means for defining a desired trajectory
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2025Particular purposes of control systems not otherwise provided for
    • E02F9/205Remotely operated machines, e.g. unmanned vehicles

Definitions

  • the present invention relates to an excavation track generation method, a system, and an excavation track generation device that generate a track for an excavator to excavate an object.
  • a drilling start point is determined so that a track that does not put a load on the bucket, in other words, the bucket is not overloaded.
  • a trajectory generator for generating a trajectory for this purpose is disclosed.
  • each excavation site is searched in the order of excavation order, and the cost function is optimized based on performance criteria such as excavation amount, energy consumption and time, thereby determining the position of the bucket of the excavator.
  • the earthwork work planning method for determining the orientation is disclosed.
  • Patent Documents 1 and 2 and the like disclose that an excavation track is generated, a track that can be efficiently excavated in consideration of the accumulation state of the excavation target such as the amount of deposition and the shape of the object Is desired to be generated.
  • An object of the present invention is to provide a track generation method, a system, and an excavation track generation device that can efficiently generate a track capable of excavating an object.
  • the track generation method of the present invention obtains information about an excavation point for excavating an object, information on the deposition height of the excavation point, the object at the excavation point, and excavation for excavating the object. Includes, based on the excavation range of the device, that the excavator creates a track for excavating the object.
  • the system of the present invention includes an excavation device for excavating an object and an excavation track generation device for generating a track for the excavation device to excavate the object, and the excavation track generation device excavates the object.
  • the excavation device Based on the acquisition unit that acquires information about the excavation point, the excavation point, the deposit height information of the object at the excavation point, and the excavation movable range of the excavation device, the excavation device is described above. It has a generator that generates a track for excavating an object and a control unit that instructs the excavator to excavate the object along the track, and the excavator has the excavator along the track. Excavate the above object.
  • the excavation track generator of the present invention excavates the object, the acquisition unit that acquires the information about the excavation point for excavating the object, the excavation point, the deposit height information of the object at the excavation point, and the object. Based on the excavation movable range of the excavation device, the excavation device includes a generation unit that generates a track for excavating the object.
  • FIG. 1 is an explanatory diagram showing an example of a schematic configuration of a system according to an embodiment of the present invention.
  • FIG. 2 is a block diagram showing an example of the hardware configuration of the excavation track generator 4 according to the first embodiment.
  • FIG. 3 is a block diagram showing an example of a configuration realized by the excavation track generation device 4 and the position detection device 5 in the system 1 according to the first embodiment.
  • FIG. 4 is an explanatory diagram for explaining an example of a calculation process of an excavation point from the main body of the excavation device 3.
  • FIG. 5 is an explanatory diagram for explaining an example of a process for calculating the amount of sediment.
  • FIG. 6 is a diagram for explaining each parameter calculated by the excavation track generation device 4 (parameter calculation unit 120).
  • FIG. 7 is a diagram for explaining the calculation process of GRAD.
  • FIG. 8 is a diagram showing a calculation algorithm for calculating DRAG and GRADavg.
  • FIG. 9 is a diagram for explaining the calculation process of the average gradient GRADavg of the object 2.
  • FIG. 10 is an explanatory diagram for explaining the calculation process of the excavated sediment amount VOL expected from DRAG and GRADavg.
  • FIG. 11 is an explanatory diagram for explaining a process of generating an excavation track according to the excavation track generation algorithm.
  • FIG. 12 is a diagram showing a screen example of the excavation track displayed on the display device 46. It is a flowchart for demonstrating the example of the schematic flow of the excavation track generation processing which concerns on 1st Embodiment.
  • FIG. 16 is a block diagram showing an example of a schematic configuration of the excavation track generation device 4 according to the second embodiment.
  • automation of the drilling rig is realized by performing the following processes such as recognition, judgment, and control.
  • a recognition process the state of the drilling rig (backhoe) and the environment (earth and sand pits, dumps, etc.) is observed by the sensor network, and the observation information is collected in the automatic control system.
  • a judgment process the excavation position, excavation amount, track, and the like are determined.
  • a control process the drilling rig is controlled based on the determined track.
  • FIG. 1 is an explanatory diagram showing an example of a schematic configuration of a system 1 according to an embodiment of the present invention.
  • the system 1 includes an excavation device 3 for excavating an object 2 such as earth and sand deposited in a sediment pit, and an excavation track generation device for generating a track for the excavation device 3 to excavate the object 2. 4 and a position detecting device 5 for detecting the position of the object 2.
  • the drilling track generator 4 is arranged at a location remote from the drilling device 3 and communicates with the drilling device 3 via the network 6.
  • the drilling track generator 4 can remotely control the drilling device 3.
  • the excavation track generation device 4 may be able to communicate with the position detection device 5 via the network 6.
  • the network 6 is a wired network (for example, LAN (Local Area Network), optical fiber, etc.) or a wireless network (for example, LTE (Long Term Evolution), WiFi (registered trademark) or local 5G).
  • the position detection device 5 detects information about the object 2 at the excavation site, and transmits information about the detection result to the excavation track generation device 4 via, for example, the network 6.
  • the position detection device 5 is, for example, a three-dimensional sensor (3D sensor) such as a 3D lidar (3D LiDAR), a stereo camera, or a TOF (Time of Flight) camera, but is not limited thereto.
  • 3D sensor such as a 3D lidar (3D LiDAR), a stereo camera, or a TOF (Time of Flight) camera
  • the information acquired as an example may be the three-dimensional coordinate information of the object 2.
  • the position detection device 5 is a stereo camera
  • the information acquired as an example may be a three-dimensional captured image of the object 2.
  • the information of the object 2 to be acquired is not limited to these two examples.
  • a backhoe whose working surface of the excavator (bucket) attached to the tip of the arm is on the front side will be described as a specific example of the drilling rig 3.
  • the drilling device 3 is not limited to the backhoe, and may be, for example, a power excavator in which the working surface of the excavator (bucket) faces forward.
  • FIG. 2 is a block diagram showing an example of the hardware configuration of the excavation track generator 4 according to the first embodiment.
  • the excavation track generator 4 includes a communication interface 41, an input / output unit 42, an arithmetic processing unit 43, a main memory 44, and a storage unit 45.
  • the communication interface 41 transmits / receives data to / from an external device.
  • the communication interface 41 communicates with an external device via a wired communication path or a wireless communication path.
  • the arithmetic processing unit 43 is, for example, a CPU (Central Processing Unit), a GPU (Graphics Processing Unit), or the like.
  • the main memory 44 is, for example, a RAM (Random Access Memory), a ROM (Read Only Memory), or the like.
  • the storage unit 45 is, for example, an HDD (Hard Disk Drive), an SSD (Solid State Drive), a memory card, or the like. Further, the storage unit 45 may be a memory such as a RAM or a ROM.
  • the excavation track generation device 4 for example, by reading the excavation track generation program stored in the storage unit 45 into the main memory 44 and executing it by the arithmetic processing unit 43, the functional unit as shown in FIG. 3 is realized. These programs may be read onto the main memory 44 and then executed, or may be executed without being read onto the main memory 44. In addition, the main memory 44 and the storage unit 45 also play a role of storing information and data held by the components included in the excavation track generation device 4.
  • Non-temporary computer-readable media include various types of tangible storage media.
  • Examples of non-temporary computer-readable media include magnetic recording media (eg, flexible disks, magnetic tapes, hard disk drives), opto-magnetic recording media (eg, opto-magnetic disks), CD-ROMs (Compact Disc-ROMs), CDs. -R (CD-Recordable), CD-R / W (CD-ReWritable), semiconductor memory (for example, mask ROM, PROM (Programmable ROM), EPROM (Erasable PROM), flash ROM, RAM.
  • the program also includes.
  • the computer-readable medium can supply the program to the computer via a wired communication path such as an electric wire and an optical fiber, or a wireless communication path.
  • the display device 46 is a device that displays a screen corresponding to drawing data processed by the arithmetic processing unit 43, such as an LCD (Liquid Crystal Display), a CRT (Cathode Ray Tube) display, and a monitor.
  • LCD Liquid Crystal Display
  • CRT Cathode Ray Tube
  • FIG. 3 is a block diagram showing an example of a configuration realized by the excavation track generation device 4 and the position detection device 5 in the system 1 according to the first embodiment.
  • the excavation track generation device 4 includes an excavation point acquisition unit 110, a parameter calculation unit 120, an excavation sediment amount acquisition unit 130, an excavation track generation unit 140, a control unit 150, and a display unit 160.
  • the excavation track generator 4 (excavation point acquisition unit 110) acquires information on the excavation point for excavating the object 2. Then, the excavation track generation device 4 (excavation track generation unit 140) generates a track for the excavation device 3 to excavate the object 2.
  • the excavation track generator 4 is based on, for example, the excavation point, the deposit height information of the object 2 at the excavation point, and the excavation movable range of the excavation device 3 for excavating the object 2. 3 creates a track for excavating object 2.
  • the deposit height information of the object 2 at the excavation point is, for example, information represented by the depth of the object from the excavation point to the ground plane of the excavation device.
  • the drilling movable range of the drilling rig 3 is determined by, for example, the pulling width of the bucket (hereinafter, also referred to as the bucket pulling width) included in the drilling rig 3.
  • the depth of the object 2 and the bucket pulling width of the drilling device 3 are calculated by, for example, the parameter calculation unit 120.
  • the excavation point acquisition unit 110 includes an excavation area limiting unit 111, a sediment amount calculation unit 112, and an excavation position selection unit 113, as shown in FIG. 3, in order to acquire information on the excavation point.
  • the excavation point acquisition unit 110 (excavation area restriction unit 111) specifies the range in which the excavation device 3 can excavate.
  • the excavation area limiting unit 111 calculates, for example, the distance from the main body of the excavation device 3 to the excavation point, and specifies an area where excavation is possible based on the distance from the main body of the excavation device 3 to the excavation point.
  • FIG. 4 is an explanatory diagram for explaining an example of calculation processing of the target point 400 from the main body 31 of the drilling rig 3.
  • the drilling rig 3 includes a main body 31, a boom 32, an arm 33, and a bucket 34.
  • R is, for example, the horizontal distance from the position of the main body 31 (for example, the turning axis of the main body 31) to the target point 400.
  • D is a vertical distance from the ground plane of the drilling rig 3 to the target point 400.
  • H is a vertical distance from the ground contact surface of the drilling rig 3 to the position of the main body 31 (for example, the swivel axis of the main body 31).
  • both D and H have a positive value on the vertical axis Z shown in FIG.
  • the distance L from the main body 31 of the drilling rig 3 to the target point 400 can be calculated by the following formula.
  • the excavation point acquisition unit 110 limits the excavable area to a target point satisfying the following conditions based on the distance L calculated above.
  • the upper and lower limit values (boundary values) of D and L may be determined according to the size of the drilling rig 3 and the size of the object 2 (specifically, the earth and sand pit).
  • the excavation point acquisition unit 110 may acquire the information regarding the excavation point by determining the excavation point based on the accumulated amount of the object 2.
  • the excavation point acquisition unit 110 calculates the earth and sand amount according to the excavation reference point and the bucket passage area in the excavation area specified by the excavation area limiting unit 111.
  • the drilling reference point is a point where the drilling rig 3 starts drilling, and more specifically, a point where the bucket provided by the drilling rig 3 enters the earth and sand (object 2).
  • the bucket passage area is an area through which the bucket is moved by the pulling width from the excavation reference point (specifically, the point where the bucket enters the earth and sand).
  • FIG. 5 is an explanatory diagram for explaining an example of the process of calculating the amount of sediment.
  • the bucket passage area is determined by the multiplication value of the bucket pull width D and the bucket width W.
  • the sediment amount calculation area is determined by the section from each excavation reference point A, B, C in the excavation area to the bucket pulling width D.
  • the amount of earth and sand VOL (deposited amount of the object 2) excavated from the excavation reference point A is calculated by the following formula.
  • (x, y) are the position coordinates in the horizontal direction.
  • the function z (x, y) is a function representing the depth of the object from the surface of the earth and sand (object 2) to the ground plane of the drilling rig.
  • the depth represented by the function z (x, y) is calculated based on, for example, the information acquired by the position detecting device 5.
  • the excavation point acquisition unit 110 (sediment amount calculation unit 112) can calculate the sediment amount (deposition amount of the object 2) for each of the excavation reference points A, B, and C.
  • the excavation point acquisition unit 110 selects the excavation reference point as the excavation point based on the calculated amount of earth and sand. For example, the excavation point acquisition unit 110 (excavation position selection unit 113) selects the excavation reference point having the maximum calculated amount of earth and sand as the excavation point. For example, in the example shown in FIG. 5B, the excavation reference point A is selected as the excavation point. That is, the excavation reference point A is determined as the excavation point. In this way, the earth and sand (object 2) can be excavated from the point where more earth and sand (object 2) is deposited.
  • the excavation point to be selected is not limited to the above-mentioned excavation reference point where the amount of earth and sand is maximum, and for example, the excavation point where the bucket can be loaded most may be set.
  • the excavation point acquisition unit 110 (sediment amount calculation unit 112) determines the amount of earth and sand that can be loaded on the bucket when excavated from the excavation reference point so that the point that can be most loaded on the bucket can be selected as the excavation point. calculate. Then, the excavation point acquisition unit 110 (excavation position selection unit 113) selects the excavation reference point that can be most loaded in the bucket as the excavation point based on the calculated amount of earth and sand.
  • the excavation track generator 4 (parameter calculation unit 120) includes a distance calculation unit 121, a depth calculation unit 122, a gradient calculation unit 123, and a bucket pull width calculation unit 124. It includes an average gradient calculation unit 125 and a parameter determination unit 126.
  • FIG. 6 is a diagram for explaining each parameter calculated by the excavation track generator 4 (parameter calculation unit 120).
  • RANGE is, for example, a horizontal distance from the position of the main body of the drilling device 3 (for example, the turning axis Z of the main body) to the drilling point.
  • DEPTH is the depth of the object 2 at the excavation point.
  • GRAD is the slope of the excavation point.
  • DRAG is the width of the bucket during excavation.
  • GRADavg is the average gradient of the excavated area.
  • RANGE and DEPTH are used to determine the trajectory to the excavation point.
  • GRAD is also used to determine the bucket insertion angle during excavation.
  • DRAG is also used to determine the bucket passage range during excavation.
  • GRADavg is also used to determine the slope of the excavation track.
  • Parameter calculation unit 120 calculates RANGE.
  • the parameter calculation unit 120 calculates RANGE from the relative distance from the position of the main body of the excavation device 3 (for example, the turning axis Z of the main body) to the excavation point.
  • the parameter calculation unit 120 (depth calculation unit 122) sets the depth of the object from the excavation point to the ground plane of the excavation device as DEPTH, for example, based on the detection result by the position detection device 5. calculate.
  • FIG. 7 is a diagram for explaining the GRAD calculation process.
  • the gradient calculation unit 123 calculates the gradient of the excavation point 701 as GRAD based on the depth error between the excavation point 701 and the peripheral points 702 and 703.
  • FIG. 8 is a diagram showing an example of a calculation algorithm for calculating DRAG and GRADavg. That is, with reference to FIG. 8, DRAG and GRADavg are calculated according to an algorithm as shown in FIG. 8, for example.
  • the parameter calculation unit 120 determines the minimum bucket pull width (DRAGmin) required to excavate a predetermined amount of earth and sand from the determined excavation point in DRAG.
  • the predetermined amount of sediment is acquired by, for example, the excavated sediment amount acquisition unit 130, and the excavated sediment amount acquisition unit 130 notifies the bucket pulling width calculation unit 124.
  • the parameter calculation unit 120 calculates the average gradient GRADavg of the object 2 deposited at the excavation point.
  • the parameter calculation unit 120 (average gradient calculation unit 125) is deposited at the excavation point based on the depth of the object 2, the excavation point, and the pulling width DRAG (excavation movable range) of the bucket.
  • the average gradient GRADavg of the object 2 is calculated.
  • FIG. 9 is a diagram for explaining the calculation process of the average gradient GRADavg of the object 2. With reference to FIG. 9, the average gradient GRADavg is calculated by dividing the integral value of the depth of the object 2 in the excavation area by the bucket pulling width D, as shown in the following equation.
  • H is the height from the ground plane of the drilling device 3 to the drilling point.
  • the DRAG calculated by the bucket pulling width calculation unit 124 is input to the bucket pulling width D.
  • the parameter calculation unit 120 calculates the excavated sediment amount VOL expected from the DRAG and GRADavg calculated as described above.
  • FIG. 10 is an explanatory diagram for explaining the calculation process of the excavated sediment amount VOL expected from DRAG and GRADavg.
  • the parameter calculation unit 120 calculates the amount of sediment VOL on the baseline whose slope is GRADavg, starting from the excavation point, by using the following formula.
  • H is the height from the ground plane of the excavator 3 to the excavation point.
  • L is the depth at which the bucket is inserted from the excavation point, that is, the bucket length.
  • the DRAG calculated by the bucket pulling width calculation unit 124 is input to D.
  • R is a distance in the estimated direction from the turning axis Z of the drilling rig 3 to the target point.
  • W is the width of the bucket.
  • the function z (x, y) is a function representing the depth of the object from the surface of the earth and sand (object 2) to the ground plane of the drilling rig. The depth represented by the function z (x, y) is calculated based on, for example, the information acquired by the position detecting device 5.
  • the parameter calculation unit 120 determines whether or not the VOL calculated by the above formula exceeds the predetermined sediment volume VOLth that can be loaded based on the bucket capacity. When the VOL exceeds the desired sediment volume VOLth, the current DRAG and GRADavg are sent to the excavation track generation unit 140.
  • the parameter calculation unit 120 (bucket pull width calculation unit 124) updates the current bucket pull width DRAG (minimum bucket pull width DRAGmin) to DRAG + ⁇ DRAG. , It is determined whether or not the updated DRAG exceeds the maximum bucket pull width DRAGmax. When the updated DRAG exceeds the maximum bucket pulling width DRAGmax, the current DRAG and GRADavg are sent to the excavation track generation unit 140. On the other hand, when the updated DRAG does not exceed the maximum bucket pulling width DRAGmax, the parameter calculation unit 120 (average gradient calculation unit 125) calculates GRADavg again according to the updated DRAG.
  • DRAG minimum bucket pull width DRAGmin
  • the parameter calculation unit 120 calculates RANGE, DEPTH, GRAD, DRAG, and GRADavg, and notifies the excavation track generation unit 140 of the calculated five parameters.
  • the excavation track generation device 4 (excavation track generation unit 140) generates a track for the excavation device 3 to excavate the object 2 based on the parameters received from the parameter calculation unit 120. Specifically, the excavation track generation device 4 (excavation track generation unit 140) starts with the depth of the object 2 at the excavation point, the excavation movable range (bucket pulling width) of the excavation device 3, and the excavation device 3. The track is generated based on the distance to the excavation point and the slope of the object 2 deposited at the excavation point.
  • the excavation track generation unit 140 generates an excavation track according to the following excavation track generation algorithm.
  • FIG. 11 is an explanatory diagram for explaining a process of generating an excavation track according to the excavation track generation algorithm.
  • the excavation track generation unit 140 calculates the upper point A'of the excavation point A according to the distance RANGE and the depth DEPTH, and calculates the linear path from the initial posture P to A'.
  • the excavation track generation unit 140 calculates a straight path from the A'point to the A point.
  • the excavation track generation unit 140 calculates the point B at which the bucket is inserted to the depth L in the direction orthogonal to the gradient GRAD at the point A, and calculates the linear path from A to B.
  • the excavation track generation unit 140 calculates the point C of the length of the pull width DRAG on a straight line inclined by the average gradient GRADavg from the point B, and calculates the straight line path from B to C.
  • the excavation track generation unit 140 calculates the point D above the point C, and calculates the linear path from C to D. In this way, the excavation track generation unit 140 can generate an excavation track connected by a straight line in the order of A', A, B, C, and D.
  • the excavation track generation device 4 (control unit 150) instructs the excavation device 3 to excavate the object 2 along the excavation track generated by the excavation track generation unit 140.
  • FIG. 12 is a diagram showing a screen example 1200 of the excavation track displayed on the display device 46.
  • the screen example 1200 shown in FIG. 12 mainly includes three display areas 1201, 1202, 1203.
  • the display device 46 displays, for example, the behavior of the drilling device 3 that changes according to the drilling track (display area 1201).
  • the display device 46 may indicate, for example, the excavation location, the position of the excavation device 3, and the excavation status.
  • the display device 46 may display, for example, the behavior of the excavation device 3 that changes according to the excavation track by arranging a plurality of images side by side, or by displaying the plurality of images continuously, the excavation device like a moving image.
  • the behavior of 3 may be displayed.
  • the display device 46 may display, for example, the track of the drilling device 3 generated by the drilling track generating unit 140.
  • the display device 46 displays, for example, numerical values of various state parameters that change according to the excavation track and information on the behavior of the bucket, boom, arm, and the like according to the excavation track (display area 1202).
  • the display device 46 includes, for example, Bucket (for example, the angle formed by the line segment between the bucket and the bucket cutting edge axis and the line segment between the bucket and the arm axis), Arm (for example, the line segment between the bucket and the arm axis). (Angle formed by the arm and boom axis line segment), Boom (for example, the angle formed by the arm and boom axis line segment and the horizon), Turn (for example, a turning angle with the front surface of the excavator 3 as 0 degree).
  • Status eg, the stage of operation such as excavation, loading, turning, or leveling).
  • the display device 46 may display, for example, the positions of the drilling device 3 and the object 2 in coordinates or drawings (display area 1203). Specifically, the display device 46 sets the turning angle of the drilling rig 3 as a reference angle (for example, 0 degrees) with a predetermined reference direction of the drilling rig 3 (for example, the front direction of the drilling rig 3 at the start of drilling) as a reference angle (for example, 0 degree). May be displayed.
  • a reference angle for example, 0 degrees
  • a predetermined reference direction of the drilling rig 3 for example, the front direction of the drilling rig 3 at the start of drilling
  • a reference angle for example, 0 degree
  • the display device 46 may display the information of the object 2 based on the information detected by the position detection device 5, for example. Specifically, the display device 46 is deposited based on, for example, the relative distance from the drilling device 3 to the object 2, the coordinates indicating the position of the object 2, and the information acquired by the position detection device 5. The shape of the object 2 may be displayed.
  • FIGS. 13 to 15 are flowcharts for explaining an example of a schematic flow of the excavation track generation process according to the first embodiment.
  • step S1301 the position detection device 5 detects the position of the drilling device 3 (for example, the position of the turning shaft). Further, in step S1302, the position detecting device 5 detects the position of the earth and sand area (object 2). Then, the process proceeds to step S1303.
  • the position of the drilling rig 3 may be detected by the drilling rig 3 itself using a positioning system such as GPS (Global Positioning System) or GNSS (Global Navigation Satellite System). Further, the position of the earth and sand area (object 2) is not limited to the case where it is detected by the position detecting device 5, and may be specified in advance.
  • step S1303 the excavation track generator 4 (excavation area limiting unit 111) calculates a candidate area to be the target of the excavation point from the earth and sand area (the area where the object 2 is deposited), and proceeds to step S1304.
  • step S1304 the excavation track generator 4 (earth and sand amount calculation unit 112) calculates the amount of earth and sand in the excavation bucket passage area from each point in the excavation candidate area, and proceeds to step S1305.
  • step S1305 the excavation track generator 4 (excavation position selection unit 113) selects a point in the bucket passage region where the amount of sediment is maximum as the excavation point, and proceeds to step S1401 shown in FIG.
  • step S1401 the excavation track generator 4 (distance calculation unit 121) calculates the distance from the position of the excavation device 3 (for example, the position of the turning shaft) to the excavation point, and proceeds to step S1402.
  • step S1402 the excavation track generator 4 (depth calculation unit 122) calculates the depth of the excavation point and proceeds to step S1403.
  • step S1403 the excavation track generator 4 (gradient calculation unit 123) calculates the gradient at the excavation point and proceeds to step S1404.
  • step S1404 the excavation track generator 4 (excavation sediment amount acquisition unit 130) acquires a predetermined excavation sediment amount set in response to an operation input by the operator, and proceeds to step S1405.
  • step S1405 the excavation track generator 4 (bucket pulling width calculation unit 124) calculates the minimum bucket pulling width required for excavating the predetermined excavated sediment amount, and proceeds to step S1406.
  • step S1406 the excavation track generator 4 (average gradient calculation unit 125) calculates the average gradient in the excavation area based on the bucket pull width, and proceeds to step S1501 shown in FIG.
  • step S1501 the excavation track generation device 4 (excavation track generation unit 140) generates a target excavation track based on the excavation track generation parameters calculated in steps S1401 to S1406, and proceeds to step S1502.
  • step S1502 the drilling track generator 4 (control unit 150) automatically controls the drilling device so as to follow the target drilling track, and ends the processes shown in FIGS. 13 to 15.
  • an appropriate amount of earth and sand is taken into consideration in consideration of the accumulation state of the excavation object such as the amount of earth and sand (object 2) deposited in the earth and sand pit and its shape. It is possible to generate a track that can be excavated efficiently so that it can be excavated.
  • FIG. 16 is a block diagram showing an example of a schematic configuration of the excavation track generation device 4 according to the second embodiment.
  • the excavation track generation device 4 includes an acquisition unit 510 and a generation unit 520.
  • the acquisition unit 510 and the generation unit 520 may be implemented by one or more processors, a memory (for example, a non-volatile memory and / or a volatile memory), and / or a hard disk.
  • the acquisition unit 510 and the generation unit 520 may be implemented by the same processor, or may be separately implemented by different processors.
  • the memory may be contained in the one or more processors, or may be outside the one or more processors.
  • the excavation track generator 4 acquires information on the excavation point where the object is excavated. Then, the excavation track generation device 4 (generation unit 520) is based on the excavation point, the deposit height information of the object at the excavation point, and the excavation movable range of the excavation device for excavating the object. The excavator creates a track for excavating the object.
  • the acquisition unit 510 and the generation unit 520 of the second embodiment operate the excavation point acquisition unit 110 and the excavation track generation unit 140 of the first embodiment, respectively. You may. In this case, the description of the first embodiment may also be applied to the second embodiment.
  • the second embodiment is not limited to this example.
  • the second embodiment has been described above. According to the second embodiment, for example, it is possible to efficiently generate a track capable of excavating an object.
  • the above-mentioned drilling track generator is not limited to the case where it is arranged remotely from the drilling rig, and may be provided inside the drilling rig, for example.
  • the steps in the processes described herein do not necessarily have to be performed in chronological order in the order described in the sequence diagram.
  • the steps in the process may be executed in an order different from the order described in the sequence diagram, or may be executed in parallel.
  • a part of the steps in the process may be deleted, and additional steps may be added to the process.
  • a plurality of devices including the components of the excavation track generation device described in the present specification (for example, an excavation point acquisition unit, a parameter calculation unit, and / or an excavation track generation unit).
  • One or more devices (or units) of the devices (or units), or modules for one of the plurality of devices (or units) described above) may be provided.
  • a method including the processing of the above-mentioned components may be provided, and a program for causing the processor to execute the processing of the above-mentioned components may be provided.
  • a non-transitory computer readable medium may be provided that can be read by the computer on which the program is recorded.
  • such devices, modules, methods, programs, and computer-readable non-temporary recording media are also included in the present invention.
  • Appendix 2 The excavation track generation method according to Appendix 1, wherein in the acquisition of the information regarding the excavation point, the excavation point is determined based on the accumulated amount of the object.
  • Appendix 3 The drilling track generation method according to Appendix 1 or 2, further comprising instructing the drilling rig to drill the object along the track.
  • Appendix 4 In the generation of the track, the deposit height information of the object, the excavation movable range of the excavation device, the distance from the excavation device to the excavation point, and the object to be deposited at the excavation point.
  • Appendix 5 The excavation track according to any one of Appendix 1 to 4, wherein the deposit height information of the object is information represented by the depth of the object from the excavation point to the ground plane of the excavation device. Generation method.
  • the excavation device includes an excavation track generator that generates a track for excavating the object.
  • the excavation track generator is An acquisition unit that acquires information about the excavation point where the object is excavated, and Based on the excavation point, the deposit height information of the object at the excavation point, and the excavation movable range of the excavation device, a generation unit that generates a track for the excavation device to excavate the object. , It has a control unit that instructs the excavator to excavate the object along the track.
  • the drilling rig is a system that drills the object along the track.
  • Appendix 10 The system according to Appendix 9, wherein the acquisition unit acquires the information about the excavation point by determining the excavation point based on the accumulated amount of the object.
  • the generation unit includes the deposit height information of the object, the excavation movable range of the excavation device, the distance from the excavation device to the excavation point, and the gradient of the object deposited at the excavation point.
  • Appendix 12 The system according to any one of Appendix 9 to 11, wherein the deposit height information of the object is information represented by the depth of the object from the excavation point to the ground plane of the excavator.
  • a position detecting device for detecting the position of the object is further provided.
  • the excavation track generator is Further, there is a calculation unit for calculating the average gradient of the object deposited at the excavation point based on the deposit height information of the object, the excavation point, and the excavation movable range of the excavation device. And Of the appendices 9 to 14, the generation unit generates the track based on the deposit height information of the object, the excavation movable range of the excavation device, and the average gradient of the object. , Any one of the systems described in item 1.
  • the acquisition department that acquires information about the excavation point where the object is excavated, Based on the excavation point, the deposit height information of the object at the excavation point, and the excavation movable range of the excavation device for excavating the object, the orbit at which the excavation device excavates the object is determined.
  • the generator to generate and A drilling track generator equipped with.
  • Appendix 18 The drilling track generating device according to Appendix 16 or 17, further comprising a control unit instructing the drilling device to drill the object along the track.
  • the generation unit includes the deposit height information of the object, the excavation movable range of the excavation device, the distance from the excavation device to the excavation point, and the gradient of the object deposited at the excavation point.
  • the excavation track generator according to any one of Supplementary note 16 to 18, which generates the track based on the above.
  • Appendix 21 The excavation track generation device according to Appendix 20, further comprising a depth calculation unit that calculates the depth of the object based on the detection result of the position detection device that detects the position of the object.
  • An average gradient calculation unit that calculates the average gradient of the object deposited at the excavation point based on the deposit height information of the object, the excavation point, and the excavation movable range of the excavation device. Further prepare Of the appendices 16 to 22, the generator generates the track based on the deposit height information of the object, the excavation movable range of the excavator, and the average gradient of the object. , The excavation track generator according to any one of the items.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

【課題】効率良く対象物を掘削可能な軌道を生成すること。 【解決手段】掘削軌道生成装置4は、対象物2を掘削する掘削地点に関する情報を取得する掘削地点取得部110と、掘削軌道を生成するために用いられるパラメータを算出するパラメータ算出部120と、上記掘削地点と、上記掘削地点での対象物2の堆積高さ情報と、対象物2を掘削する掘削装置3の掘削可動範囲と、に基づいて、掘削装置3が対象物2を掘削する軌道を生成する掘削軌道生成部140と、を備える。

Description

掘削軌道生成方法、システム、及び掘削軌道生成装置
 本発明は、掘削装置が対象物を掘削する軌道を生成する掘削軌道生成方法、システム、及び掘削軌道生成装置に関する。
 作業人員削減による低コスト化、及び無人化による安全性向上などの観点から、バックホウなどの掘削装置を用いた土砂搬出作業の自動化するための取り組みがなされている。
 掘削装置を自動制御するにあたり、掘削装置の軌道を生成する方法として、例えば、特許文献1には、掘削開始点を決定し、バケットに負荷がかからない軌道、言い換えればバケットに積載し過ぎないようにするための軌道を生成する軌道生成装置が開示されている。
 また、特許文献2には、掘削順序の順番に各掘削部位を探索し、掘削量、消費エネルギー及び時間などの性能基準に基づいて費用関数を最適化することにより、掘削機のバケットの位置と向きを決定する土工作業計画方法が開示されている。
特開2016-160718号公報 特開平11-247230号公報
 上述した特許文献1及び2などには掘削軌道を生成することが開示されているが、例えば堆積量や対象物の形状など、掘削対象物の堆積状況を考慮して、効率良く掘削可能な軌道を生成することが望まれる。
 本発明の目的は、効率良く対象物を掘削可能な軌道を生成することを可能にする軌道生成方法、システム、及び掘削軌道生成装置を提供することにある。
 本発明の軌道生成方法は、対象物を掘削する掘削地点に関する情報を取得することと、上記掘削地点と、上記掘削地点での上記対象物の堆積高さ情報と、上記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、上記掘削装置が上記対象物を掘削する軌道を生成することと、を含む。
 本発明のシステムは、対象物を掘削する掘削装置と、上記掘削装置が上記対象物を掘削する軌道を生成する掘削軌道生成装置と、を備え、上記掘削軌道生成装置は、上記対象物を掘削する掘削地点に関する情報を取得する取得部と、上記掘削地点と、上記掘削地点での上記対象物の堆積高さ情報と、上記掘削装置の掘削可動範囲と、に基づいて、上記掘削装置が上記対象物を掘削する軌道を生成する生成部と、上記軌道に沿って上記対象物を掘削することを上記掘削装置に指示する制御部と、を有し、上記掘削装置は、上記軌道に沿って上記対象物を掘削する。
 本発明の掘削軌道生成装置は、対象物を掘削する掘削地点に関する情報を取得する取得部と、上記掘削地点と、上記掘削地点での上記対象物の堆積高さ情報と、上記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、上記掘削装置が上記対象物を掘削する軌道を生成する生成部と、を備える。
 本発明によれば、効率良く対象物を掘削可能な軌道を生成することが可能になる。なお、本発明により、当該効果の代わりに、又は当該効果とともに、他の効果が奏されてもよい。
図1は、本発明の実施形態に係るシステムの概略的な構成の一例を示す説明図である。 図2は、第1の実施形態に係る掘削軌道生成装置4のハードウェア構成の例を示すブロック図である。 図3は、第1の実施形態に係るシステム1において、掘削軌道生成装置4及び位置検出装置5により実現される構成の例を示すブロック図である。 図4は、掘削装置3の本体部から掘削地点の算出処理の例を説明するための説明図である。 図5は、土砂量を算出する処理の例を説明するための説明図である。 図6は、掘削軌道生成装置4(パラメータ算出部120)により算出される各パラメータを説明するための図である。 図7は、GRADの算出処理を説明するための図である。 図8は、DRAGおよびGRADavgを算出するための計算アルゴリズムを示す図である。 図9は、対象物2の平均勾配GRADavgの算出処理を説明するための図である。 図10は、DRAGとGRADavgから見込まれる掘削土砂量VOLの算出処理を説明するための説明図である。 図11は、掘削軌道生成アルゴリズムに従って掘削軌道を生成する処理を説明するための説明図である。 図12は、表示装置46に表示される掘削軌道の画面例を示す図である。 第1の実施形態に係る掘削軌道生成処理の概略的な流れの例を説明するためのフローチャートである。 第1の実施形態に係る掘削軌道生成処理の概略的な流れの例を説明するためのフローチャートである。 第1の実施形態に係る掘削軌道生成処理の概略的な流れの例を説明するためのフローチャートである。 図16は、第2の実施形態に係る掘削軌道生成装置4の概略的な構成の例を示すブロック図である。
 以下、添付の図面を参照して本発明の実施形態を詳細に説明する。なお、本明細書及び図面において、同様に説明されることが可能な要素については、同一の符号を付することにより重複説明が省略され得る。
 説明は、以下の順序で行われる。
 1.本発明の実施形態の概要
 2.システムの構成
 3.第1の実施形態
  3.1.掘削軌道生成装置4の構成
  3.2.技術的特徴
 4.第2の実施形態
  4.1.掘削軌道生成装置4の構成
  4.2.技術的特徴
 5.他の実施形態
 <<1.本発明の実施形態の概要>>
 まず、本発明の実施形態の概要を説明する。
 (1)技術的課題
 作業人員削減による低コスト化、及び無人化による安全性向上などの観点から、バックホウなどの掘削装置を用いた土砂搬出作業の自動化するための取り組みがなされている。
 例えば以下のような、認識、判断、及び制御などの処理を行うことにより、掘削装置の自動化が実現される。まず、認識処理として、センサネットワークにより掘削装置(バックホウ)や環境(土砂ピット、ダンプなど)の状態を観測して、その観測情報を自動制御システムに収集する。次に、判断処理として、掘削位置、掘削量、及び軌道などを決定する。次に、制御処理として、上記決定された軌道に基づいて掘削装置を制御する。
 ここで、例えば堆積量や対象物の形状など、掘削対象物の堆積状況を考慮して、効率良く掘削可能な軌道を生成することが望まれる。そこで、本実施形態では、効率良く対象物を掘削可能な軌道を生成することを目的とする。
 (2)技術的特徴
 本発明の実施形態では、例えば、対象物を掘削する掘削地点に関する情報を取得し、上記掘削地点と、上記掘削地点での上記対象物の堆積高さ情報と、上記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、上記掘削装置が上記対象物を掘削する軌道を生成する。
 これにより、例えば、効率良く対象物を掘削可能な軌道を生成することが可能になる。なお、上述した技術的特徴は本発明の実施形態の具体的な一例であり、当然ながら、本発明の実施形態は上述した技術的特徴に限定されない。
 <<2.システムの構成>>
 図1を参照して、本発明の実施形態に係るシステム1の構成の例を説明する。図1は、本発明の実施形態に係るシステム1の概略的な構成の一例を示す説明図である。図1を参照すると、システム1は、例えば土砂ピットに堆積されている土砂などの対象物2を掘削する掘削装置3と、掘削装置3が対象物2を掘削する軌道を生成する掘削軌道生成装置4と、対象物2の位置を検出する位置検出装置5と、を含む。
 以上のような構成のシステム1では、例えば、掘削軌道生成装置4は、掘削装置3から遠隔した場所に配置され、ネットワーク6を介して掘削装置3との間で通信を行う。これにより、掘削軌道生成装置4は、掘削装置3を遠隔制御することができる。また、例えば、掘削軌道生成装置4は、ネットワーク6を介して位置検出装置5との間で通信可能であってもよい。ネットワーク6は、有線のネットワーク(例えば、LAN(Local Area Network)、光ファイバ等)、又は無線のネットワーク(例えば、LTE(Long Term Evolution)、WiFi(登録商標)又はローカル5G)である。
 位置検出装置5は、掘削場所における対象物2に関する情報を検出し、例えばネットワーク6を介して検出結果に関する情報を掘削軌道生成装置4に送信する。位置検出装置5は、例えば、3Dライダ(3D LiDAR)、ステレオカメラ、又はTOF(Time of Flight)カメラ等の3次元センサ(3Dセンサ)であるが、これに限定されない。位置検出装置5が上記3Dライダである場合、一例として取得される情報は対象物2の3次元座標情報であり得る。また、位置検出装置5がステレオカメラである場合、一例として取得される情報は対象物2の3次元撮像画像であり得る。なお、取得される対象物2の情報は、これら2つの例に限定されない。
 また、本実施形態では、アームの先端に取り付けたショベル(バケット)の作用面が手前側であるバックホウを、掘削装置3の具体例として説明する。なお、掘削装置3は、バックホウに限定されず、例えば、ショベル(バケット)の作用面が前方を向いているパワーショベルなどであってもよい。
 <<3.第1の実施形態>>
 続いて、図2~図15を参照して、第1の実施形態に係る掘削軌道生成装置4を説明する。
 <3.1.掘削軌道生成装置4の構成>
図2は、第1の実施形態に係る掘削軌道生成装置4のハードウェア構成の例を示すブロック図である。図2を参照すると、掘削軌道生成装置4は、通信インタフェース41、入出力部42、演算処理部43、メインメモリ44、及び記憶部45を備える。
 通信インタフェース41は、外部の装置との間でデータを送受信する。例えば、通信インタフェース41は、有線通信路または無線通信路を介して外部装置と通信する。 
演算処理部43は、例えばCPU(Central Processing Unit)やGPU(Graphics Processing Unit)等である。メインメモリ44は、例えばRAM(Random Access Memory)やROM(Read Only Memory)等である。記憶部45は、例えばHDD(Hard Disk Drive)、SSD(Solid State Drive)、またはメモリカード等である。また、記憶部45は、RAMやROM等のメモリであってもよい。 
掘削軌道生成装置4では、例えば記憶部45に記憶された掘削軌道生成用プログラムをメインメモリ44に読み出して演算処理部43により実行することにより、図3に示すような機能部が実現される。これらのプログラムをメインメモリ44上に読み出してから実行してもよいし、メインメモリ44上に読み出さずに実行してもよい。また、メインメモリ44や記憶部45は、掘削軌道生成装置4が備える構成要素が保持する情報やデータを記憶する役割も果たす。 
また、上述したプログラムは、様々なタイプの非一時的なコンピュータ可読媒体(non-transitory computer readable medium)を用いて格納され、コンピュータに供給することができる。非一時的なコンピュータ可読媒体は、様々なタイプの実体のある記録媒体(tangible storage medium)を含む。非一時的なコンピュータ可読媒体の例は、磁気記録媒体(例えば、フレキシブルディスク、磁気テープ、ハードディスクドライブ)、光磁気記録媒体(例えば、光磁気ディスク)、CD-ROM(Compact Disc-ROM)、CD-R(CD-Recordable)、CD-R/W(CD-ReWritable)、半導体メモリ(例えば、マスクROM、PROM(Programmable ROM)、EPROM(Erasable PROM)、フラッシュROM、RAMを含む。また、プログラムは、様々なタイプの一時的なコンピュータ可読媒体(transitory computer readable medium)によってコンピュータに供給されてもよい。一時的なコンピュータ可読媒体の例は、電気信号、光信号、及び電磁波を含む。一時的なコンピュータ可読媒体は、電線及び光ファイバ等の有線通信路、又は無線通信路を介して、プログラムをコンピュータに供給できる。 
表示装置46は、LCD(Liquid Crystal Display)、CRT(Cathode Ray Tube)ディスプレイ、モニターのような、演算処理部43により処理された描画データに対応する画面を表示する装置である。
 図3は、第1の実施形態に係るシステム1において、掘削軌道生成装置4及び位置検出装置5により実現される構成の例を示すブロック図である。図3を参照すると、掘削軌道生成装置4は、掘削地点取得部110、パラメータ算出部120、掘削土砂量取得部130、掘削軌道生成部140、制御部150、及び表示部160を備える。
 <3.2.技術的特徴>
 次に、図2~15を参照して、第1の実施形態の技術的特徴を説明する。
 第1の実施形態によれば、掘削軌道生成装置4(掘削地点取得部110)は、対象物2を掘削する掘削地点に関する情報を取得する。そして、掘削軌道生成装置4(掘削軌道生成部140)は、掘削装置3が対象物2を掘削する軌道を生成する。掘削軌道生成装置4は、例えば、上記掘削地点と、上記掘削地点での対象物2の堆積高さ情報と、対象物2を掘削する掘削装置3の掘削可動範囲と、に基づいて、掘削装置3が対象物2を掘削する軌道を生成する。
 ここで、上記掘削地点での対象物2の堆積高さ情報は、例えば、上記掘削地点から上記掘削装置の接地面までの前記対象物の深度によって表される情報である。また、上記掘削装置3の上記掘削可動範囲は、例えば掘削装置3が備えるバケットの引き幅(以下、バケット引き幅ともいう。)によって決まる。上記対象物2の上記深度、及び上記掘削装置3の上記バケット引き幅などは、例えばパラメータ算出部120により算出される。
 (1)掘削地点の取得
 具体的に、掘削地点取得部110は、上記掘削地点に関する情報を取得するため、図3に示すように、掘削領域制限部111、土砂量算出部112、及び掘削位置選択部113を備える。
 -掘削可能領域の絞り込み
 掘削地点取得部110(掘削領域制限部111)は、掘削装置3が掘削可能な範囲を特定する。掘削領域制限部111は、例えば、掘削装置3の本体部から掘削地点までの距離を算出して、掘削装置3の本体部から掘削地点までの距離に基づいて掘削可能となる領域を特定する。
 図4は、掘削装置3の本体部31から対象地点400の算出処理の例を説明するための説明図である。図4を参照すると、掘削装置3は、本体部31、ブーム32、アーム33、及びバケット34を備える。
 Rは、例えば、本体部31の位置(例えば、本体部31の旋回軸)から対象地点400までの水平方向の距離である。また、Dは、掘削装置3の接地面から対象地点400までの垂直方向の距離である。また、Hは、掘削装置3の接地面から本体部31の位置(例えば、本体部31の旋回軸)までの垂直方向の距離である。ここで、D及びHは、両方とも、図4に示す垂直軸Zを正の値とする。
 このように、R、D、Hの値を定義すると、掘削装置3の本体部31から対象地点400までの距離Lは、下記式により算出することができる。
Figure JPOXMLDOC01-appb-M000001
 掘削地点取得部110(掘削領域制限部111)は、上述して算出された距離Lに基づいて、掘削可能領域を、以下の条件を満たす対象地点に制限する。
Figure JPOXMLDOC01-appb-M000002
Figure JPOXMLDOC01-appb-M000003
 なお、上記のDおよびLの上下限値(境界値)は、掘削装置3のサイズ、対象物2(具体的には土砂ピット)のサイズなどに応じて決定されてもよい。
 -土砂量による掘削地点選択
 掘削地点取得部110は、対象物2の堆積量に基づいて上記掘削地点を決定することにより、上記掘削地点に関する前記情報を取得してもよい。
 具体的には、掘削地点取得部110(土砂量算出部112)は、掘削領域制限部111により特定された掘削領域内の掘削基準地点、及びバケット通過領域に応じて、土砂量を算出する。ここで、上記掘削基準地点は、掘削装置3が掘削を開始する地点、より具体的には、掘削装置3が備えるバケットが土砂(対象物2)に入る地点である。また、上記バケット通過領域は、上記掘削基準地点(具体的には、バケットが土砂に入る地点)からバケットを引き幅分移動させるまでに通過する領域である。
 図5は、土砂量を算出する処理の例を説明するための説明図である。図5(A)を参照すると、バケット通過領域は、バケット引き幅D、及びバケット横幅Wの乗算値によって決まる。また、図5(B)を参照すると、土砂量算出領域は、掘削領域内の各々の掘削基準地点A、B、Cからバケット引き幅Dまでの区間によって決まる。
 したがって、図5(B)に示す例では、掘削基準地点Aから掘削される土砂量VOL(対象物2の堆積量)が、下記式により算出される。
Figure JPOXMLDOC01-appb-M000004
 ここで、(x,y)は、水平方向の位置座標である。また、関数z(x,y)は、土砂(対象物2)の表面から上記掘削装置の接地面までの前記対象物の深度を表す関数である。関数z(x,y)により表される深度は、例えば、位置検出装置5により取得される情報に基づいて算出される。
 このようにして、掘削地点取得部110(土砂量算出部112)は、掘削基準地点A、B、Cのそれぞれについて土砂量(対象物2の堆積量)を算出することができる。
 なお、図5(B)に示す例において、掘削基準地点Cから土砂(対象物2)を掘削する場合には土留めがあるため、土留めのサイズに応じてバケット引き幅Dが制限されてもよい。
 掘削地点取得部110(掘削位置選択部113)は、算出した土砂量に基づいて、掘削基準地点を掘削地点として選択する。例えば、掘削地点取得部110(掘削位置選択部113)は、算出した土砂量が最大となる掘削基準地点を掘削地点として選択する。例えば、図5(B)に示す例では、掘削基準地点Aが、上記掘削地点として選択される。つまり、掘削基準地点Aが上記掘削地点として決定される。このようにして、土砂(対象物2)がより多く堆積された地点から土砂(対象物2)を掘削することができる。
 なお、選択対象となる掘削地点は、上述した土砂量が最大となる掘削基準地点に限らず、例えば、最もバケットに積載できる地点を掘削地点としてもよい。この場合、掘削地点取得部110(土砂量算出部112)は、最もバケットに積載できる地点を掘削地点として選択できるようにするために,掘削基準地点から掘削した場合にバケットに積載できる土砂量を算出する。そして、掘削地点取得部110(掘削位置選択部113)は、算出した土砂量に基づいて、最もバケットに積載できる掘削基準地点を掘削地点として選択する。
 (2)パラメータの算出
 掘削軌道生成装置4(パラメータ算出部120)は、例えば、図3に示すように、距離算出部121、深度算出部122、勾配算出部123、バケット引き幅算出部124、平均勾配算出部125、及びパラメータ決定部126を備える。
 -パラメータの定義
 図6は、掘削軌道生成装置4(パラメータ算出部120)により算出される各パラメータを説明するための図である。
 RANGEは、例えば掘削装置3の本体部の位置(例えば本体部の旋回軸Z)から掘削地点までの水平距離である。DEPTHは、掘削地点での対象物2の深度である。GRADは、掘削地点の勾配である。DRAGは、掘削時のバケット引き幅である。GRADavgは掘削領域の平均勾配である。
 例えば、RANGE及びDEPTHは、掘削地点までの軌道を決定するために用いられる。また、GRADは、掘削時のバケット挿入角度を決定するために用いられる。また、DRAGは、掘削時のバケット通過範囲を決定するのに用いられる。また、GRADavgは、掘削軌道の傾斜度を決定するために用いられる。
 -RANGEの算出
 パラメータ算出部120(距離算出部121)は、RANGEを算出する。例えば、パラメータ算出部120(距離算出部121)は、掘削装置3の本体部の位置(例えば本体部の旋回軸Z)から掘削地点までの相対距離により、RANGEを算出する。
 -DEPTHの算出
 パラメータ算出部120(深度算出部122)は、例えば、位置検出装置5による検出結果に基づいて、上記掘削地点から上記掘削装置の接地面までの前記対象物の深度を、DEPTHとして算出する。
 -GRADの算出
 図7は、GRADの算出処理を説明するための図である。勾配算出部123は、例えば図7に示すように、掘削地点701と周辺地点702、703の深度誤差に基づいて、掘削地点701の勾配をGRADとして算出する。
 -DRAGおよびGRADavgの算出
 図8は、DRAGおよびGRADavgを算出するための計算アルゴリズムの例を示す図である。すなわち、図8を参照すると、DRAGおよびGRADavgは、例えば図8に示すようなアルゴリズムに従って算出される。
 まず、パラメータ算出部120(バケット引き幅算出部124)は、決定した掘削地点から所定の土砂量を掘削するのに必要となる最小バケット引き幅(DRAGmin)をDRAGに決定する。ここで、上記所定の土砂量は、例えば掘削土砂量取得部130により取得され、掘削土砂量取得部130からバケット引き幅算出部124へ通知される。
 次に、パラメータ算出部120(平均勾配算出部125)は、上記掘削地点に堆積される対象物2の平均勾配GRADavgを算出する。例えば、パラメータ算出部120(平均勾配算出部125)は、対象物2の深度と、上記掘削地点と、バケットの引き幅DRAG(上記掘削可動範囲)とに基づいて、上記掘削地点に堆積される対象物2の平均勾配GRADavgを算出する。図9は、対象物2の平均勾配GRADavgの算出処理を説明するための図である。図9を参照すると、平均勾配GRADavgは、下記式に示すように、掘削領域内の対象物2の深度の積分値をバケット引き幅Dで除算することにより算出される。
Figure JPOXMLDOC01-appb-M000005
 ここで、Hは、掘削装置3の接地面から掘削地点までの高さである。また、バケット引き幅Dには、バケット引き幅算出部124により算出されたDRAGが入力される。
 次に、パラメータ算出部120(パラメータ決定部126)は、上記のように算出されたDRAGとGRADavgから見込まれる掘削土砂量VOLを算出する。図10は、DRAGとGRADavgから見込まれる掘削土砂量VOLの算出処理を説明するための説明図である。具体的には、パラメータ算出部120(パラメータ決定部126)は、下記式を用いることにより、掘削地点を起点として、傾斜度がGRADavgであるベースライン上の土砂量VOLを算出する。
Figure JPOXMLDOC01-appb-M000006
 ここで、Hは掘削装置3の接地面から掘削地点までの高さである。Lは、掘削地点からバケットが挿入される深さ、すなわちバケット長さである。また、Dにはバケット引き幅算出部124により算出されたDRAGが入力される。また、Rは、掘削装置3の旋回軸Zから対象地点までの推定方向の距離である。Wはバケット横幅である。関数z(x,y)は、土砂(対象物2)の表面から上記掘削装置の接地面までの前記対象物の深度を表す関数である。関数z(x,y)により表される深度は、例えば、位置検出装置5により取得される情報に基づいて算出される。
 パラメータ算出部120(パラメータ決定部126)は、上記式により算出されたVOLが、バケット容量に基づき積載可能な所定の土砂体積VOLthを越えているか否かを判断する。VOLが所望の土砂体積VOLthを越えている場合には、現在のDRAGとGRADavgが掘削軌道生成部140に送られる。
 一方、VOLが所定の土砂体積VOLthを越えていない場合には、パラメータ算出部120(バケット引き幅算出部124)は、現在のバケット引き幅DRAG(最小バケット引き幅DRAGmin)を、DRAG+ΔDRAGに更新し、更新後のDRAGが最大バケット引き幅DRAGmaxを越えているか否かを判断する。更新後のDRAGが上記最大バケット引き幅DRAGmaxを越えている場合には、現在のDRAGとGRADavgが掘削軌道生成部140に送られる。一方、更新後のDRAGが最大バケット引き幅DRAGmaxを越えていない場合には、パラメータ算出部120(平均勾配算出部125)により、更新後のDRAGに応じてGRADavgが再び算出される。
 (まとめ)
 以上のようにして、パラメータ算出部120は、RANGE、DEPTH、GRAD、DRAG、及びGRADavgを算出して、算出した5つのパラメータを掘削軌道生成部140に通知する。
 (3)掘削軌道の生成
 掘削軌道生成装置4(掘削軌道生成部140)は、パラメータ算出部120から受信したパラメータに基づいて、掘削装置3が対象物2を掘削する軌道を生成する。具体的には、掘削軌道生成装置4(掘削軌道生成部140)は、上記掘削地点での対象物2の深度と、掘削装置3の上記掘削可動範囲(バケット引き幅)と、掘削装置3から上記掘削地点までの距離と、掘削地点に堆積される対象物2の勾配とに基づいて、上記軌道を生成する。
 例えば、掘削軌道生成部140は、次のような掘削軌道生成アルゴリズムに従って、掘削軌道を生成する。図11は、掘削軌道生成アルゴリズムに従って掘削軌道を生成する処理を説明するための説明図である。
 まず、掘削軌道生成部140は、距離RANGEと深さDEPTHとに応じて掘削地点Aの上方地点A’を算出し,初期姿勢PからA’までの直線経路を算出する。次に、掘削軌道生成部140は、A’地点からA地点への直線経路を算出する。次に、掘削軌道生成部140は、A地点の勾配GRADに対して直交な方向で、深さLまでバケットを挿入する地点Bを算出し、AからBへの直線経路を算出する。次に、掘削軌道生成部140は、B地点から平均勾配GRADavgだけ傾けた直線上で引き幅DRAGの長さの地点Cを算出し、BからCへの直線経路を算出する。次に、掘削軌道生成部140は、C地点の上方地点Dを算出し、CからDまでの直線経路を算出する。このようにして、掘削軌道生成部140は、A’、A、B、C、Dの順番に直線で結ぶ掘削軌道を生成することができる。
 (4)掘削軌道に基づく制御
 掘削軌道生成装置4(制御部150)は、掘削軌道生成部140により生成された掘削軌道に沿って対象物2を掘削することを、掘削装置3に指示する。
 (5)掘削軌道の表示
 掘削軌道生成装置4(表示部160)は、掘削軌道生成部140により生成された掘削軌道を表示装置46に表示する。図12は、表示装置46に表示される掘削軌道の画面例1200を示す図である。例えば、図12に示す画面例1200は、主に、3つの表示領域1201、1202、1203を含む。
 図12に示すように、表示装置46は、例えば、掘削軌道に応じて変化する掘削装置3の挙動を表示する(表示領域1201)。表示装置46は、例えば、掘削箇所と掘削装置3の位置と掘削状況とを示すようにしてもよい。表示装置46は、例えば、掘削軌道に応じて変化する掘削装置3の挙動を複数の画像を並べて表示してもよいし、複数の画像を連続して表示することで、動画のように掘削装置3の挙動を表示してもよい。表示装置46は、例えば、掘削軌道生成部140によって生成された掘削装置3の軌道を表示してもよい。
 表示装置46は、例えば、掘削軌道に応じて変化する各種状態パラメータの数値や掘削軌道に応じたバケット、ブーム、及びアームなどの挙動に関する情報を表示する(表示領域1202)。具体的には、表示装置46は、例えば、Bucket(例えば、バケット及びバケット刃先軸間の線分とバケット及びアーム軸間線分とがなす角度)、Arm(例えば、バケット及びアーム軸間線分とアーム及びブーム軸間線分とがなす角度)、Boom(例えば、アーム及びブーム軸間線分と水平線とがなす角度)、Turn(例えば、掘削装置3の正面を0度とする旋回角度)、Status(例えば、掘削、積込、旋回、又は均し等の動作の段階)を表示する。
 表示装置46は、例えば、掘削装置3や対象物2の位置を座標や図面で表示してもよい(表示領域1203)。具体的には、表示装置46は、掘削装置3における所定の基準方向(例えば、掘削開始時点での掘削装置3の正面方向)を基準角度(例えば、0度)として、掘削装置3の旋回角度を表示してもよい。
  表示装置46は、例えば、位置検出装置5が検出した情報に基づいて、対象物2の情報を表示してもよい。具体的には、表示装置46は、例えば、掘削装置3から対象物2までの相対距離、対象物2の位置を示す座標、及び位置検出装置5の取得した情報に基づいて算出された堆積した対象物2の形状などを表示してもよい。
 (6)処理の流れ
 図13から図15を参照して、第1の実施形態に係る掘削軌道を生成する処理の例を説明する。図13、図14、及び図15は、第1の実施形態に係る掘削軌道生成処理の概略的な流れの例を説明するためのフローチャートである。
 ステップS1301において、位置検出装置5は、掘削装置3の位置(例えば旋回軸の位置)を検出する。またステップS1302において、位置検出装置5は、土砂エリア(対象物2)の位置を検出する。次いで、ステップS1303に進む。なお、掘削装置3の位置は、掘削装置3自身がGPS(Global Positioning System)又はGNSS(Global Navigation Satellite System)などの測位システムを利用することにより、検出されてもよい。また、土砂エリア(対象物2)の位置は、位置検出装置5により検出される場合に限らず、予め特定されていてもよい。
 ステップS1303において、掘削軌道生成装置4(掘削領域制限部111)は、土砂エリア(対象物2が堆積した領域)から掘削地点の対象となる候補領域を算出して、ステップS1304に進む。
 ステップS1304において、掘削軌道生成装置4(土砂量算出部112)は、掘削候補領域内の各地点から掘削時バケット通過領域内の土砂量を算出して、ステップS1305に進む。
 ステップS1305において、掘削軌道生成装置4(掘削位置選択部113)は、バケット通過領域内の土砂量が最大となる地点を掘削地点として選択して、図14に示すステップS1401に進む。
 ステップS1401において、掘削軌道生成装置4(距離算出部121)は、掘削装置3の位置(例えば旋回軸の位置)から掘削地点までの距離を算出して、ステップS1402に進む。
 ステップS1402において、掘削軌道生成装置4(深度算出部122)は、掘削地点の深度を算出して、ステップS1403に進む。
 ステップS1403において、掘削軌道生成装置4(勾配算出部123)は、掘削地点における勾配を算出して、ステップS1404に進む。
 ステップS1404において、掘削軌道生成装置4(掘削土砂量取得部130)が、例えばオペレータによる操作入力に応じて設定される所定の掘削土砂量を取得して、ステップS1405に進む。
 ステップS1405において、掘削軌道生成装置4(バケット引き幅算出部124)は、上記所定の掘削土砂量を掘削するのに必要となる最小バケット引き幅を算出して、ステップS1406に進む。
 ステップS1406において、掘削軌道生成装置4(平均勾配算出部125)は、バケット引き幅に基づく掘削領域内の平均勾配を算出して、図15に示すステップS1501に進む。
 ステップS1501において、掘削軌道生成装置4(掘削軌道生成部140)は、ステップS1401~S1406により算出された掘削軌道生成用パラメータに基づき目標掘削軌道を生成して、ステップS1502に進む。
 ステップS1502において、掘削軌道生成装置4(制御部150)は、目標掘削軌道に追従するように、掘削装置を自動制御して、図13から図15に示す処理を終了する。
 上記図13から図15に示す処理によれば、土砂ピットに積載された土砂(対象物2)の堆積量やその形状など、掘削対象物の堆積状況を考慮して、例えば、適切な土砂量を掘削できるように効率良く掘削可能な軌道を生成することができる。
 <<4.第2の実施形態>>
 続いて、図16を参照して、本発明の第2の実施形態を説明する。上述した第1の実施形態は、具体的な実施形態であるが、第2の実施形態は、より一般化された実施形態である。
 <4.1.掘削軌道生成装置4の構成>
 図16は、第2の実施形態に係る掘削軌道生成装置4の概略的な構成の例を示すブロック図である。図16を参照すると、掘削軌道生成装置4は、取得部510、及び生成部520を備える。
 取得部510、及び生成部520は、1つ以上のプロセッサと、メモリ(例えば、不揮発性メモリ及び/若しくは揮発性メモリ)並びに/又はハードディスクとにより実装されてもよい。取得部510、及び生成部520は、同一のプロセッサにより実装されてもよく、別々に異なるプロセッサにより実装されてもよい。上記メモリは、上記1つ以上のプロセッサ内に含まれていてもよく、又は、上記1つ以上のプロセッサ外にあってもよい。
 <4.2.技術的特徴>
 第2の実施形態に係る技術的特徴を説明する。
 第2の実施形態によれば、掘削軌道生成装置4(取得部510)は、対象物を掘削する掘削地点に関する情報を取得する。そして、掘削軌道生成装置4(生成部520)は、上記掘削地点と、上記掘削地点での対象物の堆積高さ情報と、対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、掘削装置が対象物を掘削する軌道を生成する。
 -第1の実施形態との関係
 一例として、第2の実施形態の取得部510及び生成部520は、それぞれ、第1の実施形態の掘削地点取得部110及び掘削軌道生成部140の動作を行ってもよい。この場合に、第1の実施形態についての説明は、第2の実施形態にも適用されうる。
 なお、第2の実施形態は、この例に限定されない。
 以上、第2の実施形態を説明した。第2の実施形態によれば、例えば、効率良く対象物を掘削可能な軌道を生成することが可能になる。
 <<5.他の実施形態>>
 以上、本発明の実施形態を説明したが、本発明はこれらの実施形態に限定されるものではない。これらの実施形態は例示にすぎないということ、及び、本発明のスコープ及び精神から逸脱することなく様々な変形が可能であるということは、当業者に理解されるであろう。
 例えば、上述した掘削軌道生成装置は、掘削装置と遠隔して配置される場合に限らず、例えば掘削装置内部に設けられてもよい。また、本明細書に記載されている処理におけるステップは、必ずしもシーケンス図に記載された順序に沿って時系列に実行されなくてよい。例えば、処理におけるステップは、シーケンス図として記載した順序と異なる順序で実行されても、並列的に実行されてもよい。また、処理におけるステップの一部が削除されてもよく、さらなるステップが処理に追加されてもよい。
 また、本明細書において説明した掘削軌道生成装置の構成要素(例えば、掘削地点取得部、パラメータ算出部、及び/又は掘削軌道生成部)を備える装置(例えば、掘削軌道生成装置を構成する複数の装置(又はユニット)のうちの1つ以上の装置(又はユニット)、又は上記複数の装置(又はユニット)のうちの1つのためのモジュール)が提供されてもよい。また、上記構成要素の処理を含む方法が提供されてもよく、上記構成要素の処理をプロセッサに実行させるためのプログラムが提供されてもよい。また、当該プログラムを記録したコンピュータに読み取り可能な非一時的記録媒体(Non-transitory computer readable medium)が提供されてもよい。当然ながら、このような装置、モジュール、方法、プログラム、及びコンピュータに読み取り可能な非一時的記録媒体も本発明に含まれる。
 上記実施形態の一部又は全部は、以下の付記のようにも記載され得るが、以下には限られない。
(付記1)
 対象物を掘削する掘削地点に関する情報を取得することと、
 前記掘削地点と、前記掘削地点での前記対象物の堆積高さ情報と、前記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、前記掘削装置が前記対象物を掘削する軌道を生成することと、
 を含む、掘削軌道生成方法。
(付記2)
 前記掘削地点に関する前記情報の取得では、前記対象物の堆積量に基づいて前記掘削地点を決定する、付記1記載の掘削軌道生成方法。
(付記3)
 前記軌道に沿って前記対象物を掘削することを前記掘削装置に指示することを、更に含む、付記1又は2記載の掘削軌道生成方法。
(付記4)
 前記軌道の生成では、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記掘削装置から前記掘削地点までの距離と、前記掘削地点に堆積される前記対象物の勾配とに基づいて、前記軌道を生成する、付記1乃至3のうち何れか1項記載の掘削軌道生成方法。
(付記5)
 前記対象物の前記堆積高さ情報は、前記掘削地点から前記掘削装置の接地面までの前記対象物の深度によって表される情報である、付記1乃至4のうち何れか1項記載の掘削軌道生成方法。
(付記6)
 前記対象物の位置を検出する位置検出装置による検出結果に基づいて、前記対象物の前記深度を算出することを、更に含む、付記5記載の掘削軌道生成方法。
(付記7)
 前記軌道を表示装置に表示することを、更に含む付記1乃至6のうち何れか1項記載の掘削軌道生成方法。
(付記8)
 前記対象物の前記堆積高さ情報と、前記掘削地点と、前記掘削装置の掘削可動範囲とに基づいて、前記掘削地点に堆積される前記対象物の平均勾配を算出することを、更に含み、
 前記軌道の生成では、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記対象物の前記平均勾配とに基づいて、前記軌道を生成する、付記1乃至7のうち、何れか1項記載の掘削軌道生成方法。
(付記9)
 対象物を掘削する掘削装置と、
 前記掘削装置が前記対象物を掘削する軌道を生成する掘削軌道生成装置と、を備え、
 前記掘削軌道生成装置は、
  前記対象物を掘削する掘削地点に関する情報を取得する取得部と、
  前記掘削地点と、前記掘削地点での前記対象物の堆積高さ情報と、前記掘削装置の掘削可動範囲と、に基づいて、前記掘削装置が前記対象物を掘削する軌道を生成する生成部と、
  前記軌道に沿って前記対象物を掘削することを前記掘削装置に指示する制御部と、を有し、
 前記掘削装置は、前記軌道に沿って前記対象物を掘削する、システム。
(付記10)
 前記取得部は、前記対象物の堆積量に基づいて前記掘削地点を決定することにより、前記掘削地点に関する前記情報を取得する、付記9記載のシステム。
(付記11)
 前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記掘削装置から前記掘削地点までの距離と、前記掘削地点に堆積される前記対象物の勾配とに基づいて、前記軌道を生成する、付記9又は10記載のシステム。
(付記12)
 前記対象物の前記堆積高さ情報は、前記掘削地点から前記掘削装置の接地面までの前記対象物の深度によって表される情報である、付記9乃至11のうち何れか1項記載のシステム。
(付記13)
 前記対象物の位置を検出する位置検出装置を更に備え、
 前記掘削軌道生成装置は、前記位置検出装置による検出結果に基づいて、前記対象物の前記深度を算出する深度算出部を、更に有する、付記12記載のシステム。
(付記14)
 前記軌道を表示する表示装置を更に備える付記9乃至13のうち何れか1項記載のシステム。
(付記15)
 前記掘削軌道生成装置は、
  前記対象物の前記堆積高さ情報と、前記掘削地点と、前記掘削装置の掘削可動範囲とに基づいて、前記掘削地点に堆積される前記対象物の平均勾配を算出する算出部を、更に有し、
 前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記対象物の前記平均勾配とに基づいて、前記軌道を生成する、付記9乃至14のうち、何れか1項記載のシステム。
(付記16)
 対象物を掘削する掘削地点に関する情報を取得する取得部と、
 前記掘削地点と、前記掘削地点での前記対象物の堆積高さ情報と、前記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、前記掘削装置が前記対象物を掘削する軌道を生成する生成部と、
 を備える、掘削軌道生成装置。
(付記17)
 前記取得部は、前記対象物の堆積量に基づいて前記掘削地点を決定することにより、前記掘削地点に関する前記情報を取得する、付記16記載の掘削軌道生成装置。
(付記18)
 前記軌道に沿って前記対象物を掘削することを前記掘削装置に指示する制御部を、更に備える、付記16又は17記載の掘削軌道生成装置。
(付記19)
 前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記掘削装置から前記掘削地点までの距離と、前記掘削地点に堆積される前記対象物の勾配とに基づいて、前記軌道を生成する、付記16乃至18のうち何れか1項記載の掘削軌道生成装置。
(付記20)
 前記対象物の前記堆積高さ情報は、前記掘削地点から前記掘削装置の接地面までの前記対象物の深度によって表される情報である、付記16乃至19のうち何れか1項記載の掘削軌道生成装置。
(付記21)
 前記対象物の位置を検出する位置検出装置による検出結果に基づいて、前記対象物の前記深度を算出する深度算出部を、更に備える、付記20記載の掘削軌道生成装置。
(付記22)
 前記軌道を表示装置に表示する表示部を、更に備える付記16乃至21のうち何れか1項記載の掘削軌道生成装置。
(付記23)
 前記対象物の前記堆積高さ情報と、前記掘削地点と、前記掘削装置の掘削可動範囲とに基づいて、前記掘削地点に堆積される前記対象物の平均勾配を算出する平均勾配算出部を、更に備え、
 前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記対象物の前記平均勾配とに基づいて、前記軌道を生成する、付記16乃至22のうち、何れか1項記載の掘削軌道生成装置。
 土砂などの対象物を掘削装置により掘削するシステムにおいて、効率良く対象物を掘削可能な軌道を生成することができる。
 1 システム
 2 対象物
 3 掘削装置
 4 掘削軌道生成装置
 5 位置検出装置
 6 ネットワーク
 110 掘削地点取得部
 120 パラメータ算出部
 130 掘削土砂量取得部
 140 掘削軌道生成部
 150 制御部
 160 表示部
 510 取得部
 520 生成部

 

Claims (20)

  1.  対象物を掘削する掘削地点に関する情報を取得することと、
     前記掘削地点と、前記掘削地点での前記対象物の堆積高さ情報と、前記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、前記掘削装置が前記対象物を掘削する軌道を生成することと、
     を含む、掘削軌道生成方法。
  2.  前記掘削地点に関する前記情報の取得では、前記対象物の堆積量に基づいて前記掘削地点を決定する、請求項1記載の掘削軌道生成方法。
  3.  前記軌道に沿って前記対象物を掘削することを前記掘削装置に指示することを、更に含む、請求項1又は2記載の掘削軌道生成方法。
  4.  前記軌道の生成では、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記掘削装置から前記掘削地点までの距離と、前記掘削地点に堆積される前記対象物の勾配とに基づいて、前記軌道を生成する、請求項1乃至3のうち何れか1項記載の掘削軌道生成方法。
  5.  前記対象物の前記堆積高さ情報は、前記掘削地点から前記掘削装置の接地面までの前記対象物の深度によって表される情報である、請求項1乃至4のうち何れか1項記載の掘削軌道生成方法。
  6.  前記対象物の位置を検出する位置検出装置による検出結果に基づいて、前記対象物の前記深度を算出することを、更に含む、請求項5記載の掘削軌道生成方法。
  7.  前記軌道を表示装置に表示することを、更に含む請求項1乃至6のうち何れか1項記載の掘削軌道生成方法。
  8.  前記対象物の前記堆積高さ情報と、前記掘削地点と、前記掘削装置の掘削可動範囲とに基づいて、前記掘削地点に堆積される前記対象物の平均勾配を算出することを、更に含み、
     前記軌道の生成では、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記対象物の前記平均勾配とに基づいて、前記軌道を生成する、請求項1乃至7のうち、何れか1項記載の掘削軌道生成方法。
  9.  対象物を掘削する掘削装置と、
     前記掘削装置が前記対象物を掘削する軌道を生成する掘削軌道生成装置と、を備え、
     前記掘削軌道生成装置は、
      前記対象物を掘削する掘削地点に関する情報を取得する取得部と、
      前記掘削地点と、前記掘削地点での前記対象物の堆積高さ情報と、前記掘削装置の掘削可動範囲と、に基づいて、前記掘削装置が前記対象物を掘削する軌道を生成する生成部と、
      前記軌道に沿って前記対象物を掘削することを前記掘削装置に指示する制御部と、を有し、
     前記掘削装置は、前記軌道に沿って前記対象物を掘削する、システム。
  10.  前記取得部は、前記対象物の堆積量に基づいて前記掘削地点を決定することにより、前記掘削地点に関する前記情報を取得する、請求項9記載のシステム。
  11.  前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記掘削装置から前記掘削地点までの距離と、前記掘削地点に堆積される前記対象物の勾配とに基づいて、前記軌道を生成する、請求項9又は10記載のシステム。
  12.  前記対象物の前記堆積高さ情報は、前記掘削地点から前記掘削装置の接地面までの前記対象物の深度によって表される情報である、請求項9乃至11のうち何れか1項記載のシステム。
  13.  前記対象物の位置を検出する位置検出装置を更に備え、
     前記掘削軌道生成装置は、前記位置検出装置による検出結果に基づいて、前記対象物の前記深度を算出する深度算出部を、更に有する、請求項12記載のシステム。
  14.  前記軌道を表示する表示装置を更に備える請求項9乃至13のうち何れか1項記載のシステム。
  15.  前記掘削軌道生成装置は、
      前記対象物の前記堆積高さ情報と、前記掘削地点と、前記掘削装置の掘削可動範囲とに基づいて、前記掘削地点に堆積される前記対象物の平均勾配を算出する算出部を、更に有し、
     前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記対象物の前記平均勾配とに基づいて、前記軌道を生成する、請求項9乃至14のうち、何れか1項記載のシステム。
  16.  対象物を掘削する掘削地点に関する情報を取得する取得部と、
     前記掘削地点と、前記掘削地点での前記対象物の堆積高さ情報と、前記対象物を掘削する掘削装置の掘削可動範囲と、に基づいて、前記掘削装置が前記対象物を掘削する軌道を生成する生成部と、
     を備える、掘削軌道生成装置。
  17.  前記取得部は、前記対象物の堆積量に基づいて前記掘削地点を決定することにより、前記掘削地点に関する前記情報を取得する、請求項16記載の掘削軌道生成装置。
  18.  前記軌道に沿って前記対象物を掘削することを前記掘削装置に指示する制御部を、更に備える、請求項16又は17記載の掘削軌道生成装置。
  19.  前記生成部は、前記対象物の前記堆積高さ情報と、前記掘削装置の前記掘削可動範囲と、前記掘削装置から前記掘削地点までの距離と、前記掘削地点に堆積される前記対象物の勾配とに基づいて、前記軌道を生成する、請求項16乃至18のうち何れか1項記載の掘削軌道生成装置。
  20.  前記対象物の前記堆積高さ情報は、前記掘削地点から前記掘削装置の接地面までの前記対象物の深度によって表される情報である、請求項16乃至19のうち何れか1項記載の掘削軌道生成装置。

     
PCT/JP2019/028107 2019-07-17 2019-07-17 掘削軌道生成方法、システム、及び掘削軌道生成装置 WO2021009873A1 (ja)

Priority Applications (3)

Application Number Priority Date Filing Date Title
PCT/JP2019/028107 WO2021009873A1 (ja) 2019-07-17 2019-07-17 掘削軌道生成方法、システム、及び掘削軌道生成装置
JP2021532619A JP7248122B2 (ja) 2019-07-17 2019-07-17 掘削軌道生成方法、システム、及び掘削軌道生成装置
US17/624,923 US20220275606A1 (en) 2019-07-17 2019-07-17 Method for generating excavation trajectory, system, and excavation trajectory generation apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2019/028107 WO2021009873A1 (ja) 2019-07-17 2019-07-17 掘削軌道生成方法、システム、及び掘削軌道生成装置

Publications (1)

Publication Number Publication Date
WO2021009873A1 true WO2021009873A1 (ja) 2021-01-21

Family

ID=74209777

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2019/028107 WO2021009873A1 (ja) 2019-07-17 2019-07-17 掘削軌道生成方法、システム、及び掘削軌道生成装置

Country Status (3)

Country Link
US (1) US20220275606A1 (ja)
JP (1) JP7248122B2 (ja)
WO (1) WO2021009873A1 (ja)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3770334B1 (en) * 2018-03-23 2024-03-13 Sumitomo Heavy Industries, Ltd. Shovel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63194032A (ja) * 1987-02-04 1988-08-11 Komatsu Ltd パワ−シヨベルの作業機制御装置
JPH06298374A (ja) * 1993-04-12 1994-10-25 Komatsu Ltd 材料移載システムにおける材料投下高さ位置制御装置
JP2013002058A (ja) * 2011-06-13 2013-01-07 Sumitomo Heavy Ind Ltd ショベル
US20150046044A1 (en) * 2011-09-23 2015-02-12 Volvo Construction Equipment Ab Method for selecting an attack pose for a working machine having a bucket
JP2016089559A (ja) * 2014-11-10 2016-05-23 日立建機株式会社 建設機械
US20160258129A1 (en) * 2015-03-05 2016-09-08 Caterpillar Inc. Systems and Methods for Adjusting Pass Depth In View of Excess Materials
WO2017159744A1 (ja) * 2016-03-16 2017-09-21 住友重機械工業株式会社 ショベル

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6298374B2 (ja) 2014-07-11 2018-03-20 株式会社東芝 Pwm制御装置
CN107532400A (zh) * 2015-03-19 2018-01-02 住友建机株式会社 挖土机
US10761537B1 (en) * 2017-06-02 2020-09-01 Built Robotics Inc. Obstacle detection and manipulation by a vehicle within a dig site
CN109801366A (zh) * 2019-01-25 2019-05-24 北京百度网讯科技有限公司 用于选取目标挖掘点的方法和装置

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63194032A (ja) * 1987-02-04 1988-08-11 Komatsu Ltd パワ−シヨベルの作業機制御装置
JPH06298374A (ja) * 1993-04-12 1994-10-25 Komatsu Ltd 材料移載システムにおける材料投下高さ位置制御装置
JP2013002058A (ja) * 2011-06-13 2013-01-07 Sumitomo Heavy Ind Ltd ショベル
US20150046044A1 (en) * 2011-09-23 2015-02-12 Volvo Construction Equipment Ab Method for selecting an attack pose for a working machine having a bucket
JP2016089559A (ja) * 2014-11-10 2016-05-23 日立建機株式会社 建設機械
US20160258129A1 (en) * 2015-03-05 2016-09-08 Caterpillar Inc. Systems and Methods for Adjusting Pass Depth In View of Excess Materials
WO2017159744A1 (ja) * 2016-03-16 2017-09-21 住友重機械工業株式会社 ショベル

Also Published As

Publication number Publication date
JPWO2021009873A1 (ja) 2021-01-21
US20220275606A1 (en) 2022-09-01
JP7248122B2 (ja) 2023-03-29

Similar Documents

Publication Publication Date Title
US11934192B2 (en) Obstacle detection and manipulation by a vehicle within a dig site
CA2989984C (en) Work assist system for work machine
US11512448B2 (en) Excavating earth from a dig site using an excavation vehicle
AU2016336321A1 (en) Construction management system, construction management method and management device
JP6974217B2 (ja) 施工管理装置
US11680384B2 (en) Autonomous operation by earth-moving vehicle based on triggering conditions
US11543080B2 (en) Automated pipeline construction modelling
US20220120060A1 (en) Graphical user interface for real-time management of an earth shaping vehicle
JP2016103301A (ja) ショベル、ショベル管理システム、及び携帯通信端末
JP6954002B2 (ja) シールド掘進機の方向制御システム
US20220070611A1 (en) Graphical user interface for dynamically updating a geofence
KR20200092855A (ko) 타겟 굴착점 선택 방법 및 장치
WO2022046388A1 (en) Graphical user interface for real-time management of an earth shaping vehicle
WO2021009873A1 (ja) 掘削軌道生成方法、システム、及び掘削軌道生成装置
US11939742B2 (en) Control device and control method
KR102637524B1 (ko) 작업 기계
JP7294013B2 (ja) ジャッキパターンの選択支援方法及びシールド掘進機の方向制御システム
JP2017145686A (ja) ショベル
JP7107792B2 (ja) 建設機械
JP7317926B2 (ja) 施工管理装置、表示装置および施工管理方法
JP2019101697A (ja) 施工管理装置および施工管理方法
JP7165599B2 (ja) 施工管理装置、施工管理システム、作業機械、施工管理方法及びプログラム
CN112652012A (zh) 挖掘机智能控制方法、装置、设备、存储介质和挖掘机

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19937924

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2021532619

Country of ref document: JP

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 19937924

Country of ref document: EP

Kind code of ref document: A1