WO2019000031A1 - Système de construction de haut en bas - Google Patents

Système de construction de haut en bas Download PDF

Info

Publication number
WO2019000031A1
WO2019000031A1 PCT/AU2018/050647 AU2018050647W WO2019000031A1 WO 2019000031 A1 WO2019000031 A1 WO 2019000031A1 AU 2018050647 W AU2018050647 W AU 2018050647W WO 2019000031 A1 WO2019000031 A1 WO 2019000031A1
Authority
WO
WIPO (PCT)
Prior art keywords
pile
mandrel
hollow
ground
nesting
Prior art date
Application number
PCT/AU2018/050647
Other languages
English (en)
Inventor
John Jarvie
Gregory Paul Mullane
Original Assignee
Armour Wall Group Pty Limited
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2017902464A external-priority patent/AU2017902464A0/en
Application filed by Armour Wall Group Pty Limited filed Critical Armour Wall Group Pty Limited
Priority to EP18822765.6A priority Critical patent/EP3645795A4/fr
Priority to CN201880043236.XA priority patent/CN110869563A/zh
Priority to NZ759839A priority patent/NZ759839A/en
Priority to AU2018293555A priority patent/AU2018293555A1/en
Priority to US16/620,840 priority patent/US20200149240A1/en
Publication of WO2019000031A1 publication Critical patent/WO2019000031A1/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0283Retaining or protecting walls characterised by constructional features of mixed type
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/28Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0032Steel; Iron in sheet form, i.e. bent or deformed plate-material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0045Composites
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Definitions

  • the following disclosure relates to a construction methodology that employs a series of piles such as sheet piles used for retaining walls.
  • Underground basements, car parks, cellars, etc. are usually built from the bottom up.
  • the site is first excavated, prior to driving into the ground and supporting thereat interlocking panels that form a continuous barrier/retaining wall at the perimeter of the site.
  • the resultant continuous barrier/retaining wall enables permanent works to proceed within the excavated space.
  • a plurality of elongated, vertically oriented, optionally interlocking panels are driven into the earth to a depth sufficient to support the panels in an upright attitude, although typically some bracing, anchoring or tieback at the panel upper ends is required.
  • the panels may take the form of extruded structural panels that are provided with male and female opposed edges so that similar panels can be locked together at their adjacent side edges to form a continuous barrier/retaining wall.
  • the nesting element for use in a hollow pile.
  • the nesting element is configured to be retained at an opening defined in a wall of the pile.
  • the nesting element comprises a surface that is configured such that, in use, the surface substantially conforms to an internal profile at a transverse cross-section of the pile.
  • the opening may be defined in a side wall of the pile and the nesting element may be inserted into the pile (e.g. via the side wall opening or slid through from an open end of the pile hollow cross-section) to locate and be retained adjacent to the opening (e.g. with the surface at an in-use location that is at or just above the side wall opening).
  • Such a nesting element can allow a hollow pile to be employed in a top-to- bottom construction methodology, as will be described hereafter.
  • the surface of the nesting element may be spaced from the pile internal surface but be sufficiently close so as not to allow cementitious material (e.g. concrete) that is poured into the pile from above the nesting element to pass through to a lower section of the pile.
  • cementitious material e.g. concrete
  • the nesting element may comprise a flange.
  • the nesting element surface may extend generally orthogonally from the flange.
  • the flange may be configured to be arranged against an interior or exterior surface of the hollow pile to be retained thereat in use. The flange may thus help to support the surface in the pile.
  • the flange may be riveted to the interior or exterior surface of the pile adjacent the opening.
  • the flange may be affixed to the interior or exterior surface of the hollow pile, such that weight of cementitious material on the surface is resisted and borne by the flange.
  • a means other than a flange may be employed to retain the surface at the pile wall opening.
  • the nesting element may be configured to be affixed, such as by one or more fasteners, adhesive, etc.
  • the nesting element may further comprise at least one side wall that extends from the surface in a direction opposite to the flange.
  • the at least one side wall may be configured to locate adjacent to an interior surface of the hollow pile in use.
  • the at least one side wall can increase the structural rigidity of the nesting element such that it is better able to support the
  • cementitious material that impinges and weighs upon the surface when poured into the pile from above the nesting element.
  • the nesting element may be configured to support one or more reinforcing bars that, in-use, extend vertically through the pile.
  • the surface may be provided with one or more holes therethrough, each sized for a respective one of the one or more reinforcing bars.
  • the nesting element may thus support the rods at the surface, and may maintain a spacing between adjacent rods (i.e. as cementitious material flows into the pile). Where the pile has multiple nesting elements, these may work together to support the rods and maintain a spacing between adjacent rods along the length of the pile.
  • the nesting element as disclosed herein may be used with a hollow pile that takes the form of a sheet pile.
  • the sheet pile may have a rectangular box section that extends for a length of the sheet pile. Accordingly, the nesting element may be correspondingly dimensioned to nest in the rectangular box section (i.e. that is shaped to closely face the interior surfaces of the box section). Forming the nesting element as a prism can provide it with a high degree of structural integrity. Such a shape is also easy to mass produce.
  • the sheet pile and corresponding nesting element may have a substantially square cross-section.
  • the surface of the nesting element that blocks or restricts the flow of cementitious material through the hollow pile may define an in-use upper surface of the nesting element.
  • the nesting element may further comprise two opposing side walls that each extend downwardly in use from respective opposing side edges of the upper surface.
  • the nesting element may additionally comprise a rear wall that extends downwardly in use from a rear edge of the upper surface.
  • Each of the side walls and rear wall may closely face or abut a corresponding surface of the box section of the hollow pile, to better support the nesting element within the box section.
  • the nesting element may be open at at least two sides or "faces" thereof. These two “faces” may be adjacent to one another.
  • a first of the two open faces may be arranged to open outwardly of the sheet pile at the wall opening in use.
  • a second of the two open faces may be arranged to face arranged to open downwardly in the sheet pile in use.
  • the first open face can allow cementitious material to flow into the hollow pile, whereas the second open face can allow cementitious material to flow down into the hollow pile.
  • the flow of cementitious material into the hollow pile may occur, for example, when an adjacent floor slab is being poured at the construction site. In this way, the floor slab can become "keyed" to the retaining wall.
  • the nesting element may be supported in use at the sheet pile side wall opening by a flange that surrounds a perimeter of the second open face.
  • the flange may extend generally orthogonally out from each of the upper surface and side walls.
  • the pile system comprises a hollow pile that has at least one opening defined in a wall of the pile.
  • the pile system also comprises a nesting element that is as defined above.
  • the nesting element can be configured such that it is able to be inserted into the pile via the opening or through the hollow cross-section and retained adjacent to the at least one opening of the hollow pile.
  • the pile system can allow each such hollow pile to be employed in a top- to-bottom construction methodology, as will be described hereafter.
  • the pile system can be used to construct a retaining wall to be located at a perimeter of a construction site such as an underground basement, car park, cellar, etc.
  • the pile system may comprise a plurality of hollow piles and associated nesting elements, which may be pre-assembled (e.g. prior to being brought to site).
  • the hollow pile may have a plurality of openings defined in and spaced out along the side wall of the pile. Each opening may be located to correspond to an adjacent floor level in use of the pile (e.g. each opening may correspond to an adjacent floor slab of e.g. the underground construction).
  • a nesting element may be provided for each pile side wall opening.
  • the hollow pile may comprise a sheet pile having a rectangular box section extending for its length.
  • the nesting element may be correspondingly dimensioned to nest in the rectangular box section (e.g. having the features as set forth above).
  • the system may comprise a plurality of hollow piles.
  • each of the hollow piles may be configured to be connected to each other along their length. In such an embodiment, when the hollow piles are connected together, they may thereby form a substantially self- supporting wall.
  • each of the hollow piles may comprise at least one male clutch and at least one corresponding female clutch.
  • the male clutch can project from a side wall of the hollow pile to extend longitudinally along the length of the side wall.
  • the female clutch can be formed at a side wall of the hollow pile to extend longitudinally along the length of the side wall.
  • the male and female clutches may be aligned on adjacent piles so as to form a substantially smooth face along the wall when the hollow piles are connected together in-use via their clutches.
  • the male clutch may be formed to project from an intermediate location along the side wall or along a distal end of the side wall.
  • a female clutch can be respectively formed within the side wall at an intermediate location along the side wall or along a distal end of the side wall.
  • a rebate may be provided within and along the length of the or each female clutch such that, in use, a sealing bead may be inserted into the rebate in use.
  • the system when the hollow piles have been connected together to form the wall, the system may be configured to have a cementitious material poured into the connected piles at an open upper end of each of the hollow piles.
  • the system prior to pouring the cementitious material into the open upper end of each of the hollow piles, the system may be configured to receive reinforcing vertically through each of the hollow piles.
  • the system may further comprise a plurality of king piles.
  • Each king pile may take the form of a cylindrical (e.g. tube) pile.
  • each hollow pile may have a king pile arranged along either side thereof.
  • a retaining wall may be constructed that has alternating hollow (e.g. sheet) piles and king piles.
  • each of the hollow piles and king piles may be configured along respective sides thereof to be connected to each other along their length.
  • the hollow and king piles when connected together, they may form a substantially self-supporting wall.
  • the sheet and king piles may be as set forth in WO 2017/063021, the relevant contents of which are incorporated herein by reference.
  • the system when the hollow and king piles have been connected together to form the wall, the system may have a cementitious material (e.g. concrete) poured into the piles at an open upper end of each of the hollow and king piles.
  • a cementitious material e.g. concrete
  • the system can also act as formwork for the cementitious material when e.g. forming the retaining wall.
  • reinforcing e.g. one or more reinforcing bars
  • the reinforcing bars may extend longitudinally through each pile.
  • the reinforced piles may be pre-assembled (e.g. prior to being brought to site).
  • the installation system comprises a first mandrel with an elongate tubular internal profile that is correspondingly dimensioned to an external profile of the hollow pile.
  • the first mandrel can be formed (e.g. of a thick and/or toughened steel, etc.) to be pile-driven into the ground, rather than driving the hollow pile into the ground.
  • the installation system may further comprise a second mandrel.
  • the second mandrel can also be formed to be pile-driven into the ground, rather than driving a further hollow pile into the ground.
  • the second mandrel may have an elongate channel with opposing elongate side walls that are connected to one another by a rear wall.
  • Each opposing elongate side wall may be configured to connect with a side wall of an adjacent first mandrel or a rear or side wall of an adjacent and further second mandrel.
  • the connection between mandrels may be configured such that, in use, when the first mandrel has been driven into the ground, the first mandrel is able to guide the second mandrel whilst it is driven into the ground.
  • the first and second mandrels can be configured to work together.
  • each side wall of the second mandrel may comprise a female clutch that, in use, may be configured to engage a corresponding and respective male clutch (or clutches) that project from one of:
  • each of the first and second mandrels may comprise a flange that projects substantially perpendicularly away from a side wall thereof.
  • the flange may be configured to facilitate gripping of the mandrel by a pile driving mechanism.
  • the flange may also act as a spine to prevent deflection and buckling of the mandrels in use during pile-driving.
  • the installation system may be reusable. Typically all components thereof may be fabricated from strong, tough materials (e.g. treated metals such as toughened/strengthened steel, etc.).
  • strong, tough materials e.g. treated metals such as toughened/strengthened steel, etc.
  • the drive system may be used for driving into the ground a pile system as set forth above.
  • the drive system may comprise a mandrel that is configured for location with respect to an open in-use upper end of the hollow pile.
  • the mandrel may be operated at height from e.g. a crane or other like vehicle on a construction site and may thus act as a pile driver.
  • the mandrel may comprise a head that is configured so as to act on the hollow pile upper end to cause an in-use lower end of the hollow pile to be driven into the ground.
  • the head may be dimensioned to effectively close the open upper end during pile driving.
  • the hollow pile may be of a type that comprises a hollow section having two sets of flanges that extend out from opposite sides of the hollow section.
  • the mandrel may be configured to comprise two spaced elongate pin members that each extend from the mandrel head to locate and extend between a respective one of the sets of flanges. In this way, the mandrel can be suited to better engage with the hollow pile during pile driving. After pile driving, the mandrel can be withdrawn from the hollow pile.
  • each pin member may be configured to extend beyond the hollow pile lower end in use.
  • Each pin member may further comprise a pointed end to facilitate its insertion into the ground.
  • the hollow pile may be of a type that comprises a hollow section in the form of a box section.
  • the box section may have opposing side walls.
  • One of the sets of flanges may extend in a first direction as a continuation of the box section side walls.
  • the other of the sets of flanges may extend in a second opposite direction as a continuation of the box section side walls.
  • the hollow pile may, in this regard, be take the form of sheet pile, and may be as set forth in WO 2017/063021, the relevant contents of which are incorporated herein by reference.
  • the mandrel can be shaped accordingly to suit such a hollow pile.
  • the drive system may further comprise at least one attachment for location at an in-use open lower end of the hollow pile.
  • the attachment may be force-fit into the pile lower end, to be secured thereto during pile driving.
  • the attachment may remain in place after pile driving.
  • the attachment may be configured to prevent ground matter from entering the hollow pile during driving of the hollow pile lower end into the ground.
  • the attachment may protrude to a pointed end to facilitate its insertion into the ground.
  • the drive system may further comprise at least one detachable cover for each nesting element when the latter is located at the hollow pile side wall opening.
  • the cover may be releasably secured to the nesting element at the side wall opening (i.e. for subsequent removal during a
  • the cover may be configured to prevent ground matter from entering the hollow pile during driving of the pile into the ground.
  • Also disclosed herein is a method of constructing a retaining wall.
  • the method comprises driving into ground a first mandrel as described above, then removing ground from within an interior of the first mandrel.
  • the method may further comprise driving into the ground a second mandrel as defined above, such that the side walls of the second mandrel connect with the first mandrel to be guided thereby. Ground from within an interior of the second mandrel may then be removed.
  • the method may further comprise driving into the ground a further second mandrel, such that the side walls of the second mandrel may connect with the second mandrel existing in the ground to be guided thereby. Ground from within an interior of the further second mandrel may then be removed.
  • the method may further comprise locating a hollow pile as defined above within the first mandrel.
  • the method may further comprise removing the first mandrel from the ground.
  • a hollow pile as defined above may then be located within the second mandrel such that the hollow pile can connect to the adjacent hollow pile that was located within the first mandrel.
  • the ground within the second mandrel may then be removed.
  • the method may further comprise locating a hollow pile as defined above within a further second mandrel such that the hollow pile can connect to the adjacent hollow pile that was located within the second mandrel. Ground from within an interior of the further second mandrel may then be removed.
  • the method may further comprise arranging one or more elongate reinforcing bars to extend vertically through and for a length of each hollow pile.
  • each elongate reinforcing bar may extend vertically through one or more nesting elements arranged in each hollow pile.
  • the method may further comprise pouring a cementitious material into the hollow pile at an in-use open upper end thereof.
  • the cementitious material may flow down inside the pile until it reaches a surface of an in-use uppermost nesting element located at a respective wall opening.
  • the method may further comprise driving a pile system into the ground.
  • the pile system may comprise a hollow pile having at least one opening defined in a wall thereof.
  • the pile can be as set forth above.
  • the at least one wall opening can have a nesting element retained thereat.
  • the nesting element can be as set forth above and can be inserted in the opening.
  • One mode of implementing the method is as a top-to-bottom construction methodology, as further described hereafter.
  • the method can also allow for underground and above ground construction to take place simultaneously.
  • a plurality of hollow piles may be driven into the ground to form the retaining wall.
  • the plurality of hollow piles may be interconnected so as to form the retaining wall.
  • each hollow pile may be interconnected to an adjacent hollow pile via an intermediate, optionally hollow, king pile.
  • Each king pile may be driven into the ground so as to form part of the retaining wall.
  • the hollow and king piles may be driven into the ground in sequence moving along a line of the retaining wall.
  • each hollow pile and each king pile may be interconnected along respective adjacent longitudinal sides thereof.
  • the manner of interconnection may be by way of complementary male and female clutches, such as those as set forth in WO 2017/063021, the relevant contents of which are incorporated herein by reference.
  • each hollow pile and each king pile may have one or more elongate reinforcing bars arranged to extend vertically therein for a length of the pile. These may be pre-assembled in each pile (e.g. prior to being brought to site).
  • the method may further comprise pouring a cementitious material into each hollow pile at the in-use open upper end thereof. The cementitious material can flow down inside the pile until it reaches a surface of an in-use uppermost nesting element located at a respective wall opening.
  • the cementitious material can flow down to a base thereof.
  • the king piles can support a remainder of the retaining wall, whereby top-to-bottom construction of the site can now commence.
  • the retaining wall may be constructed along a perimeter of a construction site (i.e. to surround the site).
  • a slab of cementitious material may be formed at the ground within the construction site perimeter (i.e. as defined by the retaining wall).
  • one or more slab support columns may first be formed into the ground spaced discretely within the construction site. These slab support columns may extend for the full depth of the construction site.
  • ground under the slab may now be excavated down to a level that aligns with a (first) line of nesting elements arranged in the hollow piles of the retaining wall at the site perimeter, the line of nesting elements being at a level that corresponds to a next floor slab.
  • the cementitious material for the next floor slab may be poured at the excavated ground level within the construction site perimeter.
  • This next floor slab may optionally make use of (e.g. be connected to so as to be supported by) the one or more slab support columns.
  • a cover at each pile wall opening at each of a line of nesting elements may be removed prior to pouring the next slab at the excavated ground level.
  • the cementitious material can also flow in through each of the pile wall and nesting element openings and into the respective hollow pile, so as to fill up the pile, either to a surface of a next lower nesting element, or to a base of the hollow pile (i.e. depending on how long each pile is, how many nesting elements it has, and how many underground floors are being formed).
  • ground under the next floor slab may now by excavated down to a further level that aligns with an additional lower (second) line of nesting elements in the hollow piles in the retaining wall, the additional line of nesting elements being at a level that corresponds to a further floor slab.
  • a further floor slab may now be formed on ground at the excavated further level. Then, the further steps similar to those as set forth above may be performed.
  • ground under the further floor slab may be excavated and a yet further floor slab may be poured. Then, the further steps similar to those as set forth above may be repeated until, eventually, a final base floor slab is formed at a lowermost level corresponding to a base of the retaining wall. This can complete this mode of implementing the top-to- bottom construction method.
  • Figure 1 shows an axonometric projection of a first nesting element embodiment in the form of a stopper element.
  • Figure 2 shows an axonometric projection of the stopper element of Fig. 1 with optional reinforcement rods inserted therethrough.
  • Figure 3 shows an axonometric projection of the stopper element of Fig. 1 retained in an opening in a wall of a hollow pile in the form of a sheet pile.
  • Figures 4a, 4b and 4c each show an axonometric projection of the sheet pile, with: Fig. 4a showing the sheet pile prior to the pouring of cementitious material thereinto; Fig. 4b showing the sheet pile post the pouring of cementitious material into the top of the sheet pile; and Fig. 4c showing the sheet pile post the pouring of cementitious material into the pile system via an opening through the stopper element.
  • Figure 5 shows an axonometric projection of a hollow king pile for use with the sheet pile of Figs. 3 and 4, as part of a pile system.
  • Figure 6 shows a plan view of the king pile of Fig. 5 when attached at a corner to two sheet piles of Fig. 4, each filled with a cementitious material.
  • Figure 7 shows an axonometric projection of a pile system comprising a plurality of alternating sheet and king piles, with a stopper element retained in an opening in a side wall of each sheet pile.
  • Figures 8a and 8b respectively show an axonometric projection (Fig. 8a) and side view (Fig. 8b) of a pile system akin to Figs. 6 & 7, with a floor slab formed at the level of each of a horizontal line of stopper elements, as well as showing a basement level floor slab, and ground level floor slab (Fig. 8a).
  • Figures 9a, 9b and 9c respectively show axonometric projections of components of a pile drive system, with: Fig. 9a showing a pile driving mandrel that comprises a head and two pins that are configured to protrude through flanges of the sheet pile; Fig. 9b showing the sheet pile prepared for installation with a detachable cover over the stopper element; and Fig. 9c showing the sheet pile prepared for installation through the fitting of a wedge attachment at a lower open end of a box section of the sheet pile.
  • Figures 10a to lOe respectively show side schematic cross-sectional views of one mode of the sequence/stages of constructing a top-to-bottom underground construction.
  • Figure 11 shows an axonometric projection of a second nesting element embodiment, also in the form of a stopper element.
  • Figure 12 shows an axonometric projection of an alternative hollow pile embodiment in the form of a square box-section sheet pile.
  • Figure 13 shows, in axonometric projection, an elongate form of the square box- section sheet pile of Figure 12, and illustrating an opening for the stopper element of Figure 11.
  • Figure 14 shows, in axonometric projection, a series/sequence of elongate square box-section sheet piles of Figure 13, being joined together to form a retaining wall.
  • Figures 15A, 15B and 15C show, in axonometric projection, three different mandrel types that can be used for driving into the ground to enable the elongate square box-section sheet piles of Figure 13 to be inserted therein.
  • Figure 16 shows, in axonometric projection, two of those three mandrel types joined together as they would be after being driven into the ground by a pile- driving apparatus.
  • Figure 17 shows, in axonometric projection, one of the mandrel types after having been driven into the ground and then excavated, with a square box-section sheet pile of Figure 13 inserted therein.
  • Figure 18 shows a schematic plan of a number of (four different) mandrel types as they would be arranged to define a retaining wall having a rectangular perimeter.
  • the method of construction as described herein can be deployed in a so-called "top-to-bottom” construction methodology.
  • the method can make use of a sheet pile such as those used for retaining walls, but modified for the top-to- bottom construction methodology.
  • the disclosure relates to the formation of a retaining wall structure at the perimeter of a construction site such as an underground basement, car park, cellar, etc. and upon which e.g. a multistory construction may be erected.
  • a nesting element in the form of a stopper element one or more of which can be used to modify each sheet pile, to make the sheet pile suitable for a stage-wise pouring thereinto of a cementitious material such as concrete.
  • the stopper elements can enable floor slabs of the underground construction to key into each modified sheet pile as part of the top-to-bottom construction methodology.
  • components of a pile driving system which enable each modified sheet pile to be driven into the ground to form the retaining wall.
  • the top-to-bottom construction methodology described herein can reduce time and construction costs, as well as simplifying existing underground construction techniques.
  • a nesting element is shown in the form of a stopper element (100).
  • the stopper element (100) is configured for use in a hollow pile in the form of a generally rectangular sheet pile (200) as best shown in Figure 3.
  • the stopper element (100) is configured such that it is able to be retained at or adjacent to an opening (230) defined in a wall of the sheet pile (200). This modifies the sheet pile (200), the effect of which will be explained hereafter.
  • the stopper element (100) is depicted as a rectangular prism in Figure 1, as will also be explained hereafter, the stopper element (100) can take a number of other forms.
  • the opening (230) is defined in a side wall (240) of the sheet pile (200) to open into an elongate box section (201) of the sheet pile that extends generally centrally through the pile and provides a main structural "spine" thereof.
  • the stopper element ( 100) is inserted into this side wall opening to locate and be retained adjacent to opening (230); e.g. an in-use upper surface (102) of the stopper element assumes an in-use location that is located at (or may locate just above) an upper part of the side wall opening.
  • an in-use upper surface (102) of the stopper element assumes an in-use location that is located at (or may locate just above) an upper part of the side wall opening.
  • the stopper element (100) takes other forms it may, for example, be inserted into the pile via an open upper end of the box section (201).
  • the stopper element (100) can allow the sheet pile (200) to be employed in a top-to-bottom construction methodology.
  • the upper surface (102) of the stopper element (100) can stop the flow of a pour of concrete down through the box section (201), which has a number of benefits in the top-to- bottom methodology, as will also be described hereafter.
  • the upper surface (102) of the stopper element (100) is also configured such that, when the stopper element is located at the opening (230), surface (102) substantially conforms to an internal profile at a transverse cross-section of the box section (201). This substantial conformity does not exclude the upper surface (102) being spaced from an internal surface (210) of the sheet pile (200), but it does require the surface (102) to be sufficiently close to surface (210) so as not to allow concrete (150) that is poured into an open upper end of the box section (201) to pass through to a lower section of the pile.
  • this "concrete-stop” feature enables the sheet pile to be "tied” to a floor slab as the top-to-bottom construction method proceeds. This in turn means that construction is able to continue above and below the pile level presently under construction, i.e. once the concrete ( 150) has cured at a given level. This may be advantageous in improving the efficiency of the construction, potentially reducing construction times and associated costs.
  • the stopper element (100) can enables each sheet pile to "key” to and thus support a floor slab ( Figure 8a, 410), such that the pile retaining wall substantially supports the floor slab. Usually, however, separate slab support columns are provided to support each floor slab as each is constructed.
  • the stopper element (100) takes the form of a rectangular prism that is readily fabricated (e.g. welded from plate, moulded from tough plastic, etc.).
  • the stopper element (100) comprises at least one, and in this case two side walls (20) that each extend downwardly in use from respective opposing side edges (21, 22) of the surface (102).
  • the stopper element (100) additionally comprises a rear wall (25) that extends downwardly in use from a rear edge (23) of the surface (102).
  • each of the side walls (20) and rear wall (25) may closely face or abut a corresponding surface of the box section (201) of the sheet pile (200), to better support the stopper element (100) within the box section.
  • the side walls (20) and rear wall (25) increase the structural rigidity of the stopper element (100) such that it is better able to support concrete (150) that impinges and weighs upon the surface (102) when poured into the box section (201) of the sheet pile (200) from above.
  • the stopper element (100) comprises a flange in the form of a peripheral retention lip (30) that surrounds a front face of the stopper element (100), with the lip (30) being connected to each of the surface (102) and side walls (20) and extending generally orthogonally therefrom.
  • the lip (30) is configured to be arranged against an exterior surface of the sheet pile (200) and retains the stopper element (100) at the opening (230).
  • the lip (30) helps to support the stopper element (100), such that the weight of concrete (150) on the surface is resisted and generally borne by the lip (30).
  • the lip (30) may be affixed to the exterior surface of the sheet pile (e.g. bolted, screwed, adhered, etc.). Whilst the flange is shown in the form of a peripheral lip, it may simply comprise one or more tabs, etc. that can enable the stopper element (100) to be retained (e.g. affixed) at the opening (230).
  • the stopper element (100) can be reshaped accordingly, such as by assuming the shape as depicted in the embodiment of the stopper element (100') shown in Figure 1 1.
  • the stopper element is shaped to sufficiently correspond to the pile transverse cross-section so as not to allow concrete that is poured into the pile to pass therethrough into a lower section of the pile.
  • stopper element (100') As shown in Figure 1 1, it is shaped and configured to suit to a hollow pile (200').
  • reference numerals that are denoted by an apostrophe correspond to the described elements as referred to previously and hereafter.
  • the hollow pile (200') can have a cross-sectional profile wherein a pair of female clutches (220a') are formed within two of the side walls (240') at an intermediate location along each respective side wall (240').
  • a pair of male clutches (220b') are formed to project from an intermediate location along a different side wall (240') to that of the female clutches. It is understood that a single side wall could have any number of either male or female clutches, or alternatively could have both male and female clutches, as suitable, to resist the tensile or torsional force loading on the clutches in use.
  • the sheet pile (200') has an opening (230') that is defined in a side wall (240') of the pile (200') at which the stopper element shown in Figure 1 1 (100') can be aligned.
  • the stopper element (100') shown in Figure 11 is configured such that it can be slid through the hollow cross section of the pile (200') and retained (e.g. rivetted) adjacent to the opening (230'), such that the in-use upper surface ( 102') of the stopper element (100') assumes an in-use location that is located at (or it may locate just above) an upper part of the side wall opening (230').
  • the stopper element (100') comprises a flange in the form of a peripheral retention lip (30') that projects orthogonally upwards in use from a front face of the stopper element (100'), with the lip (30') being adapted such that it can be riveted to the inside of the hollow pile (200').
  • the stopper element (100) is open at two adjacent points
  • the second face (50) is arranged to face downwardly in the box section (201) of sheet pile (200) in use.
  • the first open face (70) is arranged to face outwardly at the sheet pile wall opening (230).
  • the openings (50, 70) an allow concrete (150) to flow into the sheet pile and then down into the box section (201).
  • This flow of concrete occurs when, for example, an adjacent floor slab (e.g. slab 410 to 430 in Figs. 8a & 8b) is being poured at the construction site. In this way, the floor slab can become "keyed" to the retaining wall.
  • the stopper element (100) can be configured to support one or more optional reinforcing bars/rods (1 10) that extend vertically in use through the box section (201) of the sheet pile (200).
  • the surface (102) can be provided with one or more holes (40) therethrough, each sized for a respective one of the reinforcing bars/rods (1 10).
  • the stopper element (100) supports the reinforcing bars/rods (1 10) at the surface (102), and maintains a spacing between adjacent reinforcing bars/rods as concrete (150) flows into the sheet pile.
  • the sheet pile (200) has multiple stopper elements (100) spaced out along its length, these work together to evenly support the reinforcing bars/rods (1 10) through the box section (201), maintaining a spacing between adjacent reinforcing bars/rods along the length of the sheet pile (200).
  • a plurality of sheet piles (200) with associated stopper elements (100) are pre-assembled (e.g. prior to being brought to a construction site).
  • Each sheet pile may (Fig. 4a) or may not (Fig. 3) be pre-assembled with the reinforcing bars/rods (110) extending through the box section (201).
  • the plurality of sheet piles (200) can be joined to each other, as described below.
  • the sheet piles (200) are deployed in conjunction with a plurality of king piles (300) - see Figs. 5-7.
  • Each king pile (300) takes the form of a cylindrical (e.g. tube) pile.
  • each sheet pile (200) has a king pile (300) arranged and connected along either side thereof, such as depicted in Figures 6 & 7.
  • the retaining wall (W) is constructed with alternating sheet piles (200) and king piles (300), including at the corners thereof (Fig. 6).
  • each sheet pile (200) has a plurality of openings (230) defined in and spaced out along the side wall (240) of the pile (200).
  • three intermediate openings (230) can be provided at 3 meter intervals along its length.
  • Each opening (230) is located to correspond to an adjacent floor level in use of the pile (200). For example, as shown in Fig. 8, and moving down from a ground level floor slab (400), a first opening (230) corresponds to an adjacent first underground floor slab (410), a second opening (230') corresponds to an adjacent second lower underground floor slab (420), and a third opening (230") corresponds to an adjacent third lower underground floor slab (430). Each of these slabs is spaced above a base level floor slab (450). The base slab (450) may also be keyed into respective base openings defined in each sheet pile side wall (240) - not shown, but as indicated in Fig. 8a. A stopper element (100) is provided at each of these side wall openings (230, 230', 230", etc.).
  • Each of the sheet piles (200) and king piles (300) are configured along respective sides thereof to be connected to each other along their length, such as depicted by Figure 7.
  • the hollow (200) and king (300) piles are connected together, they are able to form a substantially self-supporting wall.
  • the sheet piles (200) and king piles (300) may be as set forth in WO
  • each sheet pile (200) has two sets of flanges (220) that extend out from opposite sides of the box section (201).
  • One set of flanges comprises male clutches (220b) along a distal edge thereof, and the other set of flanges comprises female clutches (220a) along a distal edge thereof.
  • male clutches (320b) and female clutches (320a) are interconnected between sheet piles, or between each sheet pile and a respective king pile.
  • the sheet pile (200) and king pile (300) are thus interconnected along respective adjacent longitudinal sides thereof such as depicted in Figure 6 corner or Figure 7 (wall section).
  • concrete (150) is poured into the piles at an open upper end of each of each pile such as that depicted in Figures 4b, 4c and 6.
  • the pile system can also act as form work for the concrete when forming the retaining wall.
  • each hollow sheet pile (200') can be located adjacent to another hollow sheet pile (200'), without requiring the use of king piles.
  • adjacent hollow sheet piles (200') are connected by sliding together longitudinally along complementary male (220b') and female (220a') clutches.
  • not every sheet pile (200') need have openings (230') for respective stopper elements (100').
  • every second or third pile (200') may have openings (230') pre-cut therein, or in some embodiments, openings may be cut in piles that are a predetermined distance apart from one another (e.g. 1 metre). Such spacings have been observed to provide sufficient load bearing connections from a floor through to the pile.
  • the sheet piles and stopper elements can be manufactured from plastics or composite materials. In other embodiments, the sheet piles and stopper elements can be manufactured from steel.
  • the pile driving installation system comprise a mandrel (500).
  • the mandrel (500) comprises a head (550) that is configured to impact on the sheet pile (200) upper end to cause an in-use lower end of the sheet pile to be driven into the ground.
  • the head (550) is dimensioned to effectively extend over the entire upper end and thereby close the sheet pile at this end during pile driving.
  • the mandrel (500) is operated at height from e.g. a crane or other like vehicle on a construction site to act as the pile driver.
  • the mandrel (500) further comprises two spaced elongate pin members (510) that each extend from the mandrel head (550) to locate and extend between a respective one of the sets of sheet pile flanges (220). In this way, the mandrel (500) better engages with the sheet pile (200) during pile driving. After pile driving, the pin members (510) can be slidingly withdrawn from the sheet pile (200). Each pin member (510) is configured to extend beyond the sheet pile (200) lower end in use as shown. Each pin member (510) further comprises a pointed end (520) to facilitate its insertion into the ground.
  • the drive installation system further comprises an attachment in the form of a wedge (530) for location at an in-use open lower end of the sheet pile (200) as depicted in Figure 9c.
  • the wedge (530) may be force-fit into the pile (200) lower end, to be secured thereto during pile driving.
  • the wedge (530) remains in place after pile driving.
  • the wedge (530) is configured to prevent ground matter (earth) from entering the sheet pile (200) during pile driving.
  • the wedge (530) protrudes to a pointed end (531) to facilitate its insertion into the ground.
  • the drive installation system further comprises a detachable cover plate (560) for each stopper element (100), when the latter is located in the sheet pile (200) side wall opening (230).
  • the cover plate (560) is releasably secured to the stopper element (100) at the side wall opening (230) (i.e. for subsequent removal during a construction phase - i.e. to allow for the inflow of concrete into the sheet pile).
  • the cover plate (560) is also configured to prevent ground matter (earth) from entering the hollow pile during driving of the sheet pile into the ground.
  • box section mandrels can be used instead of driving the individual sheet piles.
  • This alternative installation system comprises a first box section mandrel (600) as shown in Figure 15 A.
  • the first box section mandrel (600) has an elongate tubular internal profile that is correspondingly dimensioned to an external profile of the hollow pile (200).
  • the first mandrel (600) is driven into the ground (e.g. by a suitable pile-driving installation mechanism).
  • the ground e.g. earth
  • a sheet pile (200) can then be located within the hollow first mandrel (600).
  • a second mandrel (610), as illustrated in Figures 15B and 15C can be driven into the ground adjacent the first mandrel (600), as shown in Figure 16.
  • the second mandrel (610) can be driven either prior to or after drilling of the ground from within the first mandrel (600).
  • first mandrel (600) and multiple second mandrels (610) may be advantageous to drive the first mandrel (600) and multiple second mandrels (610) prior to drilling, and then to drill out each thereafter.
  • the second mandrel can generally take the form of elongate channel having opposing elongate side walls (640) that are connected to one another by a rear wall (630).
  • Each side wall (640) has a female clutch (622) proximal the distal ends of the side wall (64), the female clutch (622) being configured to engage a corresponding and respective male clutch (620) of an adjacent mandrel.
  • the corresponding and respective male clutch (620) may project from one of either; the opposing sides walls (640A or 640B) of an adjacent first mandrel (600), the opposing side walls (640) of an adjacent second mandrel (61 OA) or the same side wall of an adjacent second mandrel (6 IOC).
  • the second mandrel can have multiple different configurations (such as 610A-D) to enable the mandrel system to turn corners or forms other angles and shapes as needed.
  • Figure 15C shows a mandrel wherein the rear wall (630) of the second mandrel (610B) has a pair of female clutches (624) formed within the rear wall (630) at an intermediate location thereon.
  • Figure 18 shows a mandrel (610D) that replaces one of the female clutches with a channel clutch (61 1).
  • the channel clutch is shaped and sized (i.e. it is sufficiently wide) to receive laterally therein an adjacent female clutch of the mandrel (6 IOC).
  • connection of male and female clutches between mandrels enables the guided driving of a subsequent "second" mandrel (either after a first or a second mandrel) into the ground.
  • the pile driving installation system where box section mandrels are used, can be advantageous in that the clutches of the sheet piles are not exposed to contamination with dirt nor are they subjected to shear and other damaging impact forces during the driving process.
  • the first (600) and second (610) mandrels can be provided with a flange (650) that projects substantially perpendicularly away from a side wall so as to facilitate gripping of the mandrel by a pile driving mechanism.
  • Figures 16 and 18 each depict an array of mandrels that can be arranged to create different configurations of retaining wall, such as a straight wall as depicted in Figure 14, or a wall having a rectangular perimeter as depicted in Figure 18.
  • a first mandrel (600) is driven into the ground, and a second mandrel (610) is driven adjacent to the first mandrel (600).
  • the first (600) and second (610) mandrels are aligned to connect along their clutches, and the second mandrel (610) is thus guided into the correct alignment alongside the first mandrel (600) during driving.
  • additional second mandrels (610) can then be driven into the ground alongside either the first (600), second (610), etc. mandrels as required.
  • the ground within an interior of the first mandrel (600) and second mandrel (61) is then removed (such as by drilling, etc.).
  • a sheet pile (200') can then be located within the hollow first mandrel (600). Once the first mandrel (600) is removed from the ground, a second sheet pile (200') can then be located within the hollow second mandrel (610) that sits adjacent the sheet pile (200') by sliding the second sheet pile along the clutches (i.e. as shown in Figure 14). The second mandrel (610) is then removed from the ground and the process repeated until the retaining wall is constructed.
  • the sheet piles (200') can have a series of discretely spaced reinforcing bars/rods arranged to extend vertically therein. Thereafter, concrete in-pouring can commence, and the top-to-bottom construction of the site can take place.
  • Figure 10 depicts an embodiment of a method of constructing a retaining wall such as those depicted in Figures 7 or 8.
  • the method first comprises driving the pre-prepared king (300) and sheet (200) piles into the ground to form a retaining wall perimeter at the construction site.
  • the sheet (200) and king (300) piles are driven into the ground to be interconnected in sequence moving along a line of the retaining wall, until the perimeter wall is completed.
  • the method then comprises pouring concrete (150) into each pile (200, 300) at the in-use open upper end thereof.
  • Each may be reinforced as set forth above.
  • each sheet pile The concrete flows down inside each sheet pile until it reaches a surface (102) of the uppermost stopper element (100) located at a respective wall opening (230) such as depicted in Figure 4b.
  • a king pile (300) and between the sheet pile flanges (220) the concrete flows down to a pile bottom thereof.
  • the filled king piles (300) and filled flanges (220) thus support a remainder of the retaining wall, whereby top-to-bottom construction of the site can now commence.
  • the method also comprises forming a number of slab support columns (290) deep into the ground (i.e. beyond the retaining wall) and spaced discretely within the construction site perimeter.
  • the method next comprises surface excavation and the forming of the ground level floor slab (400) over the slab support columns (290).
  • top-to-bottom construction methodology to be implemented will be described hereafter with further reference to Figures 10c to lOe. It should be noted that this method can also allow for underground and above ground construction to take place simultaneously.
  • the method next comprises excavating ground under the slab (400) down to a level that aligns with a second line of nesting elements (100) arranged at openings (230') in the sheet piles (200), i.e. at the level that corresponds to the floor slab (420) - Fig. 8b & 10c.
  • the exposed cover plates (560) are then removed, and formwork and reinforcing for the floor slab are then constructed.
  • the floor slab (420) is then poured with concrete, with the floor slab connecting to so as to be supported by the slab support columns (290).
  • the method next comprises excavating ground under the slab (420) down to a level that aligns with a bottom line of stopper elements (100) arranged at lowermost openings in the sheet piles (200), i.e. at the level that corresponds to the base level floor slab (450).
  • the exposed cover plates (560) are removed, and formwork and reinforcing for the base level floor slab is constructed.
  • the floor slab (450) is then poured with concrete, with the floor slab connecting to so as to be supported by the slab support columns (290).
  • the concrete also flows into the sheet pile via each open stopper element (100) at opening (230), then flowing into the box section (201) of the respective sheet pile (200), so as to fill it up down to each wedge (530).
  • the method now comprises building formwork for each of the floor slabs (410 and 430).
  • This formwork can simply be erected on the already poured (and sufficiently cured) floor slabs (420 and 450) respectively.
  • the exposed cover plates (560) are removed at each of the levels for floor slabs (410 and 430).
  • Each floor slab (410 and 430) is then poured with concrete, with each floor slab connecting to so as to be supported by the slab support columns (290).
  • the concrete also flows into the sheet pile via each open stopper element (100) at opening (230), and then flows into the box section (201) of the respective sheet pile (200), so as to fill it up down to each now concreted stopper element located at floor slabs (420 and 450) respectively.
  • each floor slab (410, 420, 430, 450) may be formed in sequence, moving down floor-by-floor from the ground level floor slab (400).
  • each level is excavated is sequence.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

L'invention concerne un élément d'emboîtement utilisable dans un pieu creux. L'élément d'emboîtement est conçu pour être retenu au niveau d'une ouverture définie dans une paroi du pieu. L'élément d'emboîtement comprend une surface conçue de sorte que, pendant l'utilisation, la surface épouse sensiblement la forme d'un profilé intérieur au niveau d'une section transversale du pieu. L'invention concerne également un système de pieux qui utilise un ou plusieurs éléments d'emboîtement dans un ou plusieurs pieux respectifs, et un système d'installation pour installer le système de pieux dans le sol. L'invention concerne en outre un procédé de construction d'un mur de soutènement à l'aide du système de pieux et du système d'installation.
PCT/AU2018/050647 2017-06-26 2018-06-26 Système de construction de haut en bas WO2019000031A1 (fr)

Priority Applications (5)

Application Number Priority Date Filing Date Title
EP18822765.6A EP3645795A4 (fr) 2017-06-26 2018-06-26 Système de construction de haut en bas
CN201880043236.XA CN110869563A (zh) 2017-06-26 2018-06-26 自上而下的建筑系统
NZ759839A NZ759839A (en) 2017-06-26 2018-06-26 Top-to-bottom construction system
AU2018293555A AU2018293555A1 (en) 2017-06-26 2018-06-26 Top-to-bottom construction system
US16/620,840 US20200149240A1 (en) 2017-06-26 2018-06-26 Top-to-bottom construction system

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AU2017902464A AU2017902464A0 (en) 2017-06-26 Top-to-bottom construction system
AU2017902464 2017-06-26

Publications (1)

Publication Number Publication Date
WO2019000031A1 true WO2019000031A1 (fr) 2019-01-03

Family

ID=64740742

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/AU2018/050647 WO2019000031A1 (fr) 2017-06-26 2018-06-26 Système de construction de haut en bas

Country Status (6)

Country Link
US (1) US20200149240A1 (fr)
EP (1) EP3645795A4 (fr)
CN (1) CN110869563A (fr)
AU (1) AU2018293555A1 (fr)
NZ (1) NZ759839A (fr)
WO (1) WO2019000031A1 (fr)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20190080352A1 (en) * 2017-09-11 2019-03-14 Adobe Systems Incorporated Segment Extension Based on Lookalike Selection
CN110258528A (zh) * 2019-06-04 2019-09-20 广州穗岩土木科技股份有限公司 一种可装配插入自卡式预制空心地下连续墙及其施工方法
CN110306532A (zh) * 2019-07-05 2019-10-08 广州穗岩土木科技股份有限公司 一种连锁预制桩地下连续墙
FR3118468A1 (fr) * 2020-12-30 2022-07-01 Soletanche Freyssinet Procédé de fabrication d’une paroi de soutènement

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11371243B2 (en) * 2016-11-26 2022-06-28 Armour Wall Group Pty Limited Building panel
GB2571097B (en) * 2018-02-15 2021-08-25 Ccmj Systems Ltd Shear key former apparatus and method(s)
US11021845B1 (en) * 2019-12-02 2021-06-01 Cmi Limited Co. Sheet piling filler-corner
CN114508092A (zh) * 2022-03-03 2022-05-17 河海大学 一种预制玻璃钢瓦楞夹心板桩及其组装方式
CN114855824A (zh) * 2022-06-08 2022-08-05 浙江国进建设有限公司 一种基坑拉森钢板桩施工方法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB552928A (en) * 1941-10-28 1943-04-30 Braithwaite And Company Engine Improvements in and relating to screw piles and cylinders
US3187513A (en) * 1962-08-24 1965-06-08 Shell Oil Co Method of driving piles
JPS63161217A (ja) * 1986-12-23 1988-07-04 Sakutaka Okuda 掘削工法
US5501550A (en) * 1994-07-11 1996-03-26 Calabrese; Salvatore J. Pile assembly and method employing external mandrel
KR20110012704A (ko) * 2009-07-31 2011-02-09 손정희 변위조절용 파일을 이용한 지중벽체 시공방법
WO2011105703A2 (fr) * 2010-02-26 2011-09-01 Song Gi-Yong Procédé pour construire un pieu composite en tube d'acier/béton dans lequel le tube d'acier est entièrement noyé avec du substratum rocheux, et construction de pieu
US8322115B2 (en) * 2002-10-18 2012-12-04 Polyone Corporation Insert panel for concrete fillable formwork wall
AU2014265045A1 (en) * 2014-05-19 2015-12-03 Paul Bekker Engineers Pty Limited Earthquake Resistant Building Slab
KR20160130113A (ko) * 2015-05-01 2016-11-10 임병균 원컷팅 공법이 적용된 콘크리트 파일의 항두막이 장치
WO2017063021A1 (fr) * 2015-10-13 2017-04-20 Comtec Industries Pty Ltd Améliorations de digues, de murs de soutènement et de structures similaires à l'aide de micro-pieux

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3638664C2 (de) * 1986-11-12 1995-08-17 Holzmann Philipp Ag Verfahren zum Herstellen einer Spundwand
GB9107672D0 (en) * 1991-04-11 1991-05-29 Roxbury Ltd Improvements in or relating to piles
US8043028B2 (en) * 2004-10-27 2011-10-25 Geopier Foundation Company, Inc. Apparatus for providing a support column
CN201080606Y (zh) * 2007-07-12 2008-07-02 陆见华 一种中空塑料t形桩
FR3025815B1 (fr) * 2015-07-07 2016-12-30 Terre Armee Int Insert de moulage et bloc de parement avec un tel insert

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB552928A (en) * 1941-10-28 1943-04-30 Braithwaite And Company Engine Improvements in and relating to screw piles and cylinders
US3187513A (en) * 1962-08-24 1965-06-08 Shell Oil Co Method of driving piles
JPS63161217A (ja) * 1986-12-23 1988-07-04 Sakutaka Okuda 掘削工法
US5501550A (en) * 1994-07-11 1996-03-26 Calabrese; Salvatore J. Pile assembly and method employing external mandrel
US8322115B2 (en) * 2002-10-18 2012-12-04 Polyone Corporation Insert panel for concrete fillable formwork wall
KR20110012704A (ko) * 2009-07-31 2011-02-09 손정희 변위조절용 파일을 이용한 지중벽체 시공방법
WO2011105703A2 (fr) * 2010-02-26 2011-09-01 Song Gi-Yong Procédé pour construire un pieu composite en tube d'acier/béton dans lequel le tube d'acier est entièrement noyé avec du substratum rocheux, et construction de pieu
AU2014265045A1 (en) * 2014-05-19 2015-12-03 Paul Bekker Engineers Pty Limited Earthquake Resistant Building Slab
KR20160130113A (ko) * 2015-05-01 2016-11-10 임병균 원컷팅 공법이 적용된 콘크리트 파일의 항두막이 장치
WO2017063021A1 (fr) * 2015-10-13 2017-04-20 Comtec Industries Pty Ltd Améliorations de digues, de murs de soutènement et de structures similaires à l'aide de micro-pieux

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20190080352A1 (en) * 2017-09-11 2019-03-14 Adobe Systems Incorporated Segment Extension Based on Lookalike Selection
CN110258528A (zh) * 2019-06-04 2019-09-20 广州穗岩土木科技股份有限公司 一种可装配插入自卡式预制空心地下连续墙及其施工方法
CN110258528B (zh) * 2019-06-04 2021-06-15 广州穗岩土木科技股份有限公司 一种可装配插入自卡式预制空心地下连续墙及其施工方法
CN110306532A (zh) * 2019-07-05 2019-10-08 广州穗岩土木科技股份有限公司 一种连锁预制桩地下连续墙
FR3118468A1 (fr) * 2020-12-30 2022-07-01 Soletanche Freyssinet Procédé de fabrication d’une paroi de soutènement
WO2022144162A1 (fr) * 2020-12-30 2022-07-07 Soletanche Freyssinet Procede de fabrication d'une paroi de soutenement

Also Published As

Publication number Publication date
NZ759839A (en) 2021-12-24
CN110869563A (zh) 2020-03-06
AU2018293555A1 (en) 2020-01-02
US20200149240A1 (en) 2020-05-14
EP3645795A4 (fr) 2021-03-31
EP3645795A1 (fr) 2020-05-06

Similar Documents

Publication Publication Date Title
US20200149240A1 (en) Top-to-bottom construction system
US4452028A (en) Structure and method for reinforcing a wall
AU7524194A (en) Concrete building frame construction method
KR20210148031A (ko) 터널 수직갱 굴착에 따른 구조 및 시공방법
KR102243718B1 (ko) 굽힘모멘트의 변위를 최소화하기 위한 흙막이 장치 시공방법
KR100531385B1 (ko) 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법
US20130008125A1 (en) Construction method for new underground structure
CN211257007U (zh) 一种用于建筑基坑施工的支护结构
KR101677236B1 (ko) 2중 강판 토류벽 구조 및 이를 이용한 가시설 흙막이 공법
CN111519634B (zh) 一种临时换撑结构的拆换撑施工方法
CN113293708B (zh) 水中现浇梁支架采用贯穿式钢管桩基础的安装拆除方法
CN110359488A (zh) 一种装配式地下结构的围护构件及其与拱形板的连接构造
KR102482690B1 (ko) 거푸집 일체화 pc 패널을 이용한 하부기초 시공방법
CN111206602B (zh) 一种局部垮塌高边坡格构梁模板体系及施工方法
EP1486618A1 (fr) Méthode et moyens pour construire une cave
WO2018053592A1 (fr) Procédé de construction de mur porteur
CN113513026A (zh) 一种软土地基深基坑桩端后锚固组合钢板桩及其施工方法
KR20220065461A (ko) 지하 연속벽체 겹이음을 위한 철근구조물, 이를 이용한 지하 연속벽체 및 지하 연속벽체 시공방법
AU649629B2 (en) Demountable and relocatable interlocking building hoarding partitions and temporary security fencing
KR102464866B1 (ko) 방음벽 기초의 시공방법 및 그에 의해 시공된 방음벽 기초
KR20210013888A (ko) 지장구조물이 있는 경우의 탑다운공법
KR102276810B1 (ko) 흙막이 구조물, 토류판 및 이의 시공방법
JP3133598B2 (ja) 地下階のある中小規模建物の構築工法
CN108442406B (zh) 一种半逆作法基坑内支撑结构及其施工方法
CN115627781B (zh) 一种用于既有边坡滑塌快速处治的边坡加固结构及施工方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18822765

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2018293555

Country of ref document: AU

Date of ref document: 20180626

Kind code of ref document: A

ENP Entry into the national phase

Ref document number: 2018822765

Country of ref document: EP

Effective date: 20200127