KR100531385B1 - 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법 - Google Patents
매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법 Download PDFInfo
- Publication number
- KR100531385B1 KR100531385B1 KR1020040074752A KR20040074752A KR100531385B1 KR 100531385 B1 KR100531385 B1 KR 100531385B1 KR 1020040074752 A KR1020040074752 A KR 1020040074752A KR 20040074752 A KR20040074752 A KR 20040074752A KR 100531385 B1 KR100531385 B1 KR 100531385B1
- Authority
- KR
- South Korea
- Prior art keywords
- construction
- underground
- steel frame
- slab
- basement
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 92
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 83
- 239000010959 steel Substances 0.000 title claims abstract description 83
- 239000004567 concrete Substances 0.000 title claims abstract description 42
- 230000000694 effects Effects 0.000 title abstract description 11
- 238000009412 basement excavation Methods 0.000 claims description 11
- 239000002689 soil Substances 0.000 claims description 10
- 229910052571 earthenware Inorganic materials 0.000 claims description 5
- 238000007796 conventional method Methods 0.000 claims description 2
- 238000005304 joining Methods 0.000 claims description 2
- 230000000149 penetrating Effects 0.000 claims description 2
- 238000011068 load Methods 0.000 abstract description 9
- 238000005266 casting Methods 0.000 abstract description 2
- 238000009430 construction management Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 13
- 238000009434 installation Methods 0.000 description 12
- 239000011150 reinforced concrete Substances 0.000 description 6
- 239000002002 slurry Substances 0.000 description 5
- 238000005553 drilling Methods 0.000 description 4
- 238000004080 punching Methods 0.000 description 4
- 238000009415 formwork Methods 0.000 description 3
- 239000004035 construction material Substances 0.000 description 2
- RYGMFSIKBFXOCR-UHFFFAOYSA-N copper Chemical compound data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 2
- 229910052802 copper Inorganic materials 0.000 description 2
- 239000010949 copper Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000004904 shortening Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances data:image/svg+xml;base64,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 data:image/svg+xml;base64,PD94bWwgdmVyc2lvbj0nMS4wJyBlbmNvZGluZz0naXNvLTg4NTktMSc/Pgo8c3ZnIHZlcnNpb249JzEuMScgYmFzZVByb2ZpbGU9J2Z1bGwnCiAgICAgICAgICAgICAgeG1sbnM9J2h0dHA6Ly93d3cudzMub3JnLzIwMDAvc3ZnJwogICAgICAgICAgICAgICAgICAgICAgeG1sbnM6cmRraXQ9J2h0dHA6Ly93d3cucmRraXQub3JnL3htbCcKICAgICAgICAgICAgICAgICAgICAgIHhtbG5zOnhsaW5rPSdodHRwOi8vd3d3LnczLm9yZy8xOTk5L3hsaW5rJwogICAgICAgICAgICAgICAgICB4bWw6c3BhY2U9J3ByZXNlcnZlJwp3aWR0aD0nODVweCcgaGVpZ2h0PSc4NXB4JyB2aWV3Qm94PScwIDAgODUgODUnPgo8IS0tIEVORCBPRiBIRUFERVIgLS0+CjxyZWN0IHN0eWxlPSdvcGFjaXR5OjEuMDtmaWxsOiNGRkZGRkY7c3Ryb2tlOm5vbmUnIHdpZHRoPSc4NScgaGVpZ2h0PSc4NScgeD0nMCcgeT0nMCc+IDwvcmVjdD4KPHRleHQgeD0nMTMuMzEyOCcgeT0nNTMuNTkwOScgY2xhc3M9J2F0b20tMCcgc3R5bGU9J2ZvbnQtc2l6ZToyM3B4O2ZvbnQtc3R5bGU6bm9ybWFsO2ZvbnQtd2VpZ2h0Om5vcm1hbDtmaWxsLW9wYWNpdHk6MTtzdHJva2U6bm9uZTtmb250LWZhbWlseTpzYW5zLXNlcmlmO3RleHQtYW5jaG9yOnN0YXJ0O2ZpbGw6I0U4NDIzNScgPkg8L3RleHQ+Cjx0ZXh0IHg9JzI4LjE1NjknIHk9JzYyLjg2MzYnIGNsYXNzPSdhdG9tLTAnIHN0eWxlPSdmb250LXNpemU6MTVweDtmb250LXN0eWxlOm5vcm1hbDtmb250LXdlaWdodDpub3JtYWw7ZmlsbC1vcGFjaXR5OjE7c3Ryb2tlOm5vbmU7Zm9udC1mYW1pbHk6c2Fucy1zZXJpZjt0ZXh0LWFuY2hvcjpzdGFydDtmaWxsOiNFODQyMzUnID4yPC90ZXh0Pgo8dGV4dCB4PSczNS4wNDU1JyB5PSc1My41OTA5JyBjbGFzcz0nYXRvbS0wJyBzdHlsZT0nZm9udC1zaXplOjIzcHg7Zm9udC1zdHlsZTpub3JtYWw7Zm9udC13ZWlnaHQ6bm9ybWFsO2ZpbGwtb3BhY2l0eToxO3N0cm9rZTpub25lO2ZvbnQtZmFtaWx5OnNhbnMtc2VyaWY7dGV4dC1hbmNob3I6c3RhcnQ7ZmlsbDojRTg0MjM1JyA+TzwvdGV4dD4KPC9zdmc+Cg== O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 210000001503 Joints Anatomy 0.000 description 1
- 241000237502 Ostreidae Species 0.000 description 1
- 210000003660 Reticulum Anatomy 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000000875 corresponding Effects 0.000 description 1
- 230000003111 delayed Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000007429 general method Methods 0.000 description 1
- 235000020636 oyster Nutrition 0.000 description 1
- 230000003014 reinforcing Effects 0.000 description 1
- 230000003252 repetitive Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000007665 sagging Methods 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/04—Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
Abstract
Description
Claims (3)
- 흙막이용 가설 스트러트를 설치하지 않고 건물의 영구 구조부재를 흙막이 벽체에 대한 버팀대로서 활용하는 지하 구조물 구축 공법에 있어서,(a) 통상의 방법에 의해 지중에 가설 흙막이 벽체를 구축하는 단계;(b) 건축물의 본 기둥이 설치되어야 할 위치에 철골기둥을 지상으로부터 수직으로 박아 설치하고 상기 철골기둥의 하단에 기초부를 형성시키는 단계;(c) 상기 가설 흙막이 벽체의 내측을 소정 깊이로 굴토하여 터파기 작업을 수행하고 상기 터파기 작업에 의해 노출된 가설 흙막이 벽체의 측면에 철골좌대를 설치하는 단계;(d) 상기 철골좌대의 상부에 매립형 철골띠장을 수평으로 설치하는 단계;(e) 건축물의 본 보부재가 설치되어야 할 위치에 내부 수평보를 설치하고, 상기 내부 수평보의 단부를 상기 매립형 철골띠장의 측면에 일체로 접합하는 단계;(f) 상기 (e)단계에서 설치된 내부 수평보의 상부에 콘크리트 슬래브를 타설 시공하되, 상기 콘크리트 슬래브는 그 외곽 경계선이 이후 시공될 지하 외벽의 내측면 경계선보다 최소한 일치하거나 더욱 내측으로 위치할 수 있도록 상기 가설 흙막이 벽체로부터 소정 거리만큼을 제외하고 타설 시공하는 단계;(g) 상기 (c)단계에서 (f)단계의 공정을 기초 레벨까지 반복하여 수행하는 단계; 및,(h) 상기 가설 흙막이 벽체의 내측으로 지하외벽을 지상까지 연속적으로 타설하여 지하외벽을 구축 시공하는 단계;를 포함하여 이루어지는 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법.
- 제1항에 있어서,상기 (e)단계에서 내부 수평보를 설치한 다음, 상기 내부 수평보의 상부에 스터드 볼트를 부착 설치하는 단계를 더욱 포함하는 것을 특징으로 하는 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법.
- 제1항 또는 제2항에 있어서,상기 매립형 철골띠장에는 상하로 관통하는 관통공이 소정 간격으로 다수개가 형성되어 있는 것을 특징으로 하는 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020040074752A KR100531385B1 (ko) | 2004-09-17 | 2004-09-17 | 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020040074752A KR100531385B1 (ko) | 2004-09-17 | 2004-09-17 | 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법 |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100531385B1 true KR100531385B1 (ko) | 2005-11-29 |
Family
ID=37306308
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020040074752A KR100531385B1 (ko) | 2004-09-17 | 2004-09-17 | 매립형 철골띠장과 슬래브 강막작용을 이용하여 지하외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100531385B1 (ko) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100634726B1 (ko) | 2005-04-19 | 2006-10-16 | (주)한국건설공법 | 지하구조물의 슬래브 구축용 구조체와 이를 이용한테두리보가 생략된 슬래브 및 지하옹벽 시공방법 |
KR100766956B1 (ko) | 2005-04-11 | 2007-10-15 | (주)에스피에스 | 지하 흙막이벽의 지지구조 및 이를 적용한 건축물 지하 합벽의 구축공법 |
KR100910576B1 (ko) | 2007-11-02 | 2009-08-04 | 쌍용건설 주식회사 | 매입 앵커 및 이를 이용한 지하외벽의 합성옹벽 시공방법 |
KR100938916B1 (ko) | 2009-06-29 | 2010-01-27 | (주)하이탑 | 선단확공을 통한 역타공법 |
KR100999410B1 (ko) * | 2008-05-07 | 2010-12-09 | 한국건설기술연구원 | 유공 성형보와 조립식 슬리브를 사용한 조립식 띠장 및그를 이용하여 지하 옹벽의 연속시공이 가능한 지하 구조물시공방법 |
KR101054696B1 (ko) * | 2007-08-23 | 2011-08-08 | 주식회사 한화건설 | 슬러리 월에서 슬래브 강막작용을 이용하여 토압 지지가이루어지도록 한 지하구조물의 역타 구축 공법 |
KR101066198B1 (ko) | 2009-03-18 | 2011-09-20 | (주)네오크로스구조엔지니어링 | 슬러리 월을 이용한 지하구조물 역타 시공 방법 |
KR101221970B1 (ko) * | 2010-05-04 | 2013-01-15 | 양숙경 | 무가시설 지하구조물 시공방법 |
KR101230986B1 (ko) | 2010-06-16 | 2013-02-15 | 주식회사 한빛구조엔지니어링 | 역류방지형 콘크리트 타설구 및 바이브레이터 근입구가 구비된 거푸집을 이용한 지하외벽 선시공 공법 |
KR101267565B1 (ko) | 2012-02-13 | 2013-05-24 | 주식회사 한빛구조엔지니어링 | 지하 역타 시공시 코어부 구조물 시공 방법 |
KR101401057B1 (ko) | 2013-02-28 | 2014-05-29 | (주)바로건설기술 | 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법 |
KR20160110699A (ko) | 2015-03-11 | 2016-09-22 | (주)대우건설 | 무띠장 흙막이 벽체 직접 연결 구조 |
KR20160133705A (ko) * | 2015-05-13 | 2016-11-23 | 최완규 | 측압지지보 겸용 데크 지지프레임 |
CN107476338A (zh) * | 2017-08-21 | 2017-12-15 | 中铁六局集团有限公司 | 预制纵梁拼装方法 |
KR101827619B1 (ko) * | 2016-01-14 | 2018-02-08 | 이병희 | 흙막이 벽체 토압 지지공법 |
KR102123543B1 (ko) * | 2019-11-20 | 2020-06-16 | (주)에스앤피이엔씨 | 중앙 철골기둥을 이용한 탑다운 공법 |
-
2004
- 2004-09-17 KR KR1020040074752A patent/KR100531385B1/ko not_active IP Right Cessation
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100766956B1 (ko) | 2005-04-11 | 2007-10-15 | (주)에스피에스 | 지하 흙막이벽의 지지구조 및 이를 적용한 건축물 지하 합벽의 구축공법 |
KR100634726B1 (ko) | 2005-04-19 | 2006-10-16 | (주)한국건설공법 | 지하구조물의 슬래브 구축용 구조체와 이를 이용한테두리보가 생략된 슬래브 및 지하옹벽 시공방법 |
KR101054696B1 (ko) * | 2007-08-23 | 2011-08-08 | 주식회사 한화건설 | 슬러리 월에서 슬래브 강막작용을 이용하여 토압 지지가이루어지도록 한 지하구조물의 역타 구축 공법 |
KR100910576B1 (ko) | 2007-11-02 | 2009-08-04 | 쌍용건설 주식회사 | 매입 앵커 및 이를 이용한 지하외벽의 합성옹벽 시공방법 |
KR100999410B1 (ko) * | 2008-05-07 | 2010-12-09 | 한국건설기술연구원 | 유공 성형보와 조립식 슬리브를 사용한 조립식 띠장 및그를 이용하여 지하 옹벽의 연속시공이 가능한 지하 구조물시공방법 |
KR101066198B1 (ko) | 2009-03-18 | 2011-09-20 | (주)네오크로스구조엔지니어링 | 슬러리 월을 이용한 지하구조물 역타 시공 방법 |
KR100938916B1 (ko) | 2009-06-29 | 2010-01-27 | (주)하이탑 | 선단확공을 통한 역타공법 |
KR101221970B1 (ko) * | 2010-05-04 | 2013-01-15 | 양숙경 | 무가시설 지하구조물 시공방법 |
KR101230986B1 (ko) | 2010-06-16 | 2013-02-15 | 주식회사 한빛구조엔지니어링 | 역류방지형 콘크리트 타설구 및 바이브레이터 근입구가 구비된 거푸집을 이용한 지하외벽 선시공 공법 |
KR101267565B1 (ko) | 2012-02-13 | 2013-05-24 | 주식회사 한빛구조엔지니어링 | 지하 역타 시공시 코어부 구조물 시공 방법 |
KR101401057B1 (ko) | 2013-02-28 | 2014-05-29 | (주)바로건설기술 | 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법 |
KR20160110699A (ko) | 2015-03-11 | 2016-09-22 | (주)대우건설 | 무띠장 흙막이 벽체 직접 연결 구조 |
KR20160133705A (ko) * | 2015-05-13 | 2016-11-23 | 최완규 | 측압지지보 겸용 데크 지지프레임 |
KR101692151B1 (ko) * | 2015-05-13 | 2017-01-02 | 최완규 | 측압지지보 겸용 데크 지지프레임 |
KR101827619B1 (ko) * | 2016-01-14 | 2018-02-08 | 이병희 | 흙막이 벽체 토압 지지공법 |
CN107476338A (zh) * | 2017-08-21 | 2017-12-15 | 中铁六局集团有限公司 | 预制纵梁拼装方法 |
KR102123543B1 (ko) * | 2019-11-20 | 2020-06-16 | (주)에스앤피이엔씨 | 중앙 철골기둥을 이용한 탑다운 공법 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3828153B2 (ja) | トンネル、地下通路、地下駐車場などを構築する地下構造物、及びその構築方法、並びにその構造のためのプレハブ部材 | |
US20160340855A1 (en) | Modular construction mold apparatus and method for constructing concrete buildings and structures | |
CN101397852B (zh) | 一种对历史建筑增建多层地下室的施工方法 | |
KR100866162B1 (ko) | 의자형 자립식 흙막이벽의 시공방법 | |
JP4793634B2 (ja) | 仮締め切り工法 | |
KR101014796B1 (ko) | 기성 콘크리트 기둥부재를 이용한 탑다운 시공방법 | |
JP4698491B2 (ja) | 水中構造物の仮締切工法及び構造 | |
KR100884289B1 (ko) | 복합형 강가시설 및 그 시공방법 | |
KR101274974B1 (ko) | 흙막이 겸용 옹벽 및 이의 시공방법 | |
US20100325819A1 (en) | Bridge approach and abutment construction and method | |
WO2010134731A9 (ko) | 지하외벽의 연속시공을 위해 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법 | |
KR101363878B1 (ko) | 가설구조와 본구조의 합벽식 공법을 이용한 지하도로 시공방법 | |
KR100634726B1 (ko) | 지하구조물의 슬래브 구축용 구조체와 이를 이용한테두리보가 생략된 슬래브 및 지하옹벽 시공방법 | |
CA1319261C (fr) | Structures cellulaires pour murs de soutenement | |
RU2220258C1 (ru) | Способ возведения многоэтажного подземного сооружения (варианты) | |
KR100951097B1 (ko) | 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 받침브라켓 | |
KR101331261B1 (ko) | 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조 및 이의 시공 방법 | |
KR200372315Y1 (ko) | 역타설 시스템의 이동 조립식 지지 브라켓 구조 | |
US7500807B2 (en) | Method of construction using sheet piling sections | |
JP2002256573A (ja) | 既設基礎補強型鉄塔用基礎及びその構築工法 | |
KR101107567B1 (ko) | Rc 구조물 역타 공법을 위한 보구조체와 수직 강재부재의 접합장치, 전용지지틀 및 이를 이용한 시공방법 | |
JP3327191B2 (ja) | 地下構造物およびその構築工法 | |
KR100984898B1 (ko) | 지하구조물 하강 시공공법 | |
KR101344063B1 (ko) | 강합성 지하차도 시공 공법 | |
KR101973565B1 (ko) | 종방향 플레이트가 부착된 phc 말뚝에 차수용 플레이트를 용접으로 접합하여 흙막이 벽체와 차수벽을 동시에 조성하는 흙막이 공법 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
J204 | Invalidation trial for patent | ||
J301 | Trial decision |
Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20090617 Effective date: 20101029 |
|
J2X1 | Appeal (before the patent court) |
Free format text: INVALIDATION |
|
J302 | Written judgement (patent court) |
Free format text: JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20101202 Effective date: 20110624 |
|
J2X2 | Appeal (before the supreme court) |
Free format text: APPEAL BEFORE THE SUPREME COURT FOR INVALIDATION |
|
J202 | Request for trial for correction [limitation] | ||
EXTG | Extinguishment | ||
J301 | Trial decision |
Free format text: TRIAL DECISION FOR CORRECTION REQUESTED 20110819 Effective date: 20111123 |
|
J303 | Written judgement (supreme court) |
Free format text: JUDGMENT (SUPREME COURT) FOR INVALIDATION REQUESTED 20110719 Effective date: 20111110 |