WO2018198771A1 - Dispositif de production d'énergie hydroélectrique et système de production d'énergie - Google Patents

Dispositif de production d'énergie hydroélectrique et système de production d'énergie Download PDF

Info

Publication number
WO2018198771A1
WO2018198771A1 PCT/JP2018/015191 JP2018015191W WO2018198771A1 WO 2018198771 A1 WO2018198771 A1 WO 2018198771A1 JP 2018015191 W JP2018015191 W JP 2018015191W WO 2018198771 A1 WO2018198771 A1 WO 2018198771A1
Authority
WO
WIPO (PCT)
Prior art keywords
braking
generator
power
braking device
power generation
Prior art date
Application number
PCT/JP2018/015191
Other languages
English (en)
Japanese (ja)
Inventor
智哉 川合
Original Assignee
Ntn株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ntn株式会社 filed Critical Ntn株式会社
Publication of WO2018198771A1 publication Critical patent/WO2018198771A1/fr

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/08Tide or wave power plants
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B11/00Parts or details not provided for in, or of interest apart from, the preceding groups, e.g. wear-protection couplings, between turbine and generator
    • F03B11/08Parts or details not provided for in, or of interest apart from, the preceding groups, e.g. wear-protection couplings, between turbine and generator for removing foreign matter, e.g. mud
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B15/00Controlling
    • F03B15/02Controlling by varying liquid flow
    • F03B15/04Controlling by varying liquid flow of turbines
    • F03B15/06Regulating, i.e. acting automatically
    • F03B15/18Regulating, i.e. acting automatically for safety purposes, e.g. preventing overspeed
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Definitions

  • the present invention relates to a hydroelectric generator and a power generation system, and more particularly to control of a small hydroelectric generator.
  • Hydropower generator is a system that uses the kinetic energy of running water for power generation.
  • the hydroelectric generator includes, as main components, a water turbine that rotates by receiving a flow of water, a generator that is connected to the water turbine and converts rotational energy into electric energy, and a controller that controls the output of the generator and the water turbine. . Since the optimum power to be extracted from the generator varies depending on the flow velocity, the control device measures the flow velocity, the rotation speed of the water turbine, or the generated voltage of the generator, determines the optimum power to be extracted from the generator, and determines the power amount of the generator. And the generator are controlled so that the optimum values match.
  • Patent Document 1 Japanese Patent Application Laid-Open No. 2013-189837 (Patent Document 1) and Japanese Patent Application Laid-Open No. 2014-202093 (Patent Document 2) disclose techniques for measures against dust generated by hydroelectric power generation.
  • Patent Document 1 discloses an example in which a dust removal facility for removing foreign substances is installed in a water channel upstream from a water turbine installation location.
  • a dust removal facility for removing foreign substances is installed in a water channel upstream from a water turbine installation location.
  • a simple dust remover such as a comb filter in the small hydroelectric generator.
  • Patent Document 2 proposes a method of crushing and removing dust by using a water turbine blade as a crushing blade for crushing foreign matter by using a generator as a motor. With such a measure, dust can be removed without a significant increase in cost.
  • the small hydroelectric generator disclosed in Japanese Patent Application Laid-Open No. 2014-202093 (Patent Document 2) has the following two problems.
  • the control device in order to drive the generator as an electric motor, the control device must have an inverter function. Since a general generator control device has only functions of a rectifier circuit and a DC / DC converter, it is difficult to easily add such functions. Second, using an inverter to make a generator function as an electric motor is not power generation, which is the original purpose, but power consumption. The functioning of the generator as an electric motor that consumes electric power is an operation opposite to the original target power generation, and is not a desired operation. Furthermore, it is necessary to secure a power supply when functioning as an electric motor.
  • the present invention is for solving the above-described problems, and an object thereof is to provide a small-sized hydroelectric generator that is easy to maintain against dust and foreign matter while suppressing cost.
  • the present disclosure relates to a hydroelectric power generation apparatus.
  • the hydroelectric power generator includes a water turbine, an electric or mechanical braking device that operates a braking force on a rotating shaft that is linked to the water wheel, and a control device that repeatedly operates and releases the braking device so that the braking force increases or decreases.
  • the control device When the amount of decrease from the power corresponding to the flow rate of the generated power of the hydroelectric generator is the first value, the control device operates the brake device a first time, and the amount of decrease in the generated power is the first value. If the second value is greater than the second value, the braking device is operated a second number of times greater than the first number of times.
  • a hydroelectric generator of another aspect disclosed in the present disclosure includes a water turbine, an electric or mechanical braking device that operates a braking force on a rotating shaft that is linked to the water turbine, and a braking device that increases or decreases the braking force. And a control device that repeats operation and release.
  • the control device operates the braking device so that the braking force exhibits the first increase / decrease pattern when the generated power decreases from the power corresponding to the flow velocity, and when the recovery of the generated power is insufficient, the first
  • the braking device is operated with a second increase / decrease pattern having a larger deceleration than the increase / decrease pattern.
  • the braking device includes a brake that applies a frictional force to a member fixed to the rotating shaft, and the control device increases or decreases the braking force by changing the frictional force.
  • the braking device includes a generator that generates electric power by rotating the water wheel, and the control device increases or decreases the braking force by increasing or decreasing the electric power extracted from the generator.
  • control device repeats the operation and release of the braking device after increasing the rotational speed of the water turbine by reducing the power generated by the hydroelectric power generation device.
  • the water wheel has a horizontal axis type propeller rotor blade.
  • the water turbine has a vertical axis type rotor blade.
  • the present disclosure also discloses a power generation system that performs ocean current power generation or tidal power generation that converts kinetic energy of flowing water into electric power using any of the above-described hydroelectric power generation apparatuses.
  • the present invention in a small hydroelectric generator, it is possible to remove dust and the like adhering to the water turbine while suppressing an increase in cost, and it is possible to prevent a decrease in power generation amount.
  • dust and grass are less likely to get entangled in the turbine blade, eliminating the need for a dust remover to remove dust installed in the water channel upstream from the water turbine installation location, or reducing the number of dust removal operations of the dust remover. It is possible to reduce the introduction cost or running cost of the entire hydroelectric power generation system. In addition, the risk of causing damage such as overflow is reduced because the water flow in the channel is not hindered.
  • FIG. 3 It is a front view which shows the structure of the hydraulic power unit which concerns on this Embodiment. It is a side view which shows the structure of the hydraulic power unit which concerns on this Embodiment. It is a block diagram which shows the structure of the hydraulic power unit which concerns on this Embodiment. 4 is a flowchart for explaining control executed by a control unit in the configuration example of FIG. 3. It is a figure which shows the relationship between the generated electric power before a brake, and the generated electric power after a brake recovered
  • FIG. 6 is a front view showing a schematic shape of a hydroelectric generator according to Embodiment 3.
  • FIG. 1 is a front view showing the configuration of the hydroelectric generator according to the present embodiment.
  • FIG. 2 is a side view showing the configuration of the hydroelectric generator according to the present embodiment.
  • the hydroelectric power generation device shown in FIGS. 1 and 2 uses a kinetic energy of a water flow for power generation, and is a small and lightweight hydroelectric power generation that can be installed in a water channel that distributes existing agricultural water, tap water, or industrial water. System.
  • the hydroelectric power generation device includes a water turbine 1, a speed increaser 2, a power generator 3, and a support portion 40.
  • the water turbine 1 has a propeller-type rotor blade having a horizontal axis as a rotation center. The water turbine 1 rotates in response to the force of water flow in the water channel.
  • the gearbox 2 is connected to the water turbine 1.
  • the speed increaser 2 increases the rotation speed of the water turbine 1 by a predetermined gear ratio, and converts the rotation of the horizontal axis into the rotation of the vertical axis and transmits the rotation to the generator 3.
  • the generator 3 is, for example, a three-phase synchronous generator.
  • the generator 3 is connected to the water turbine 1 through the speed increaser 2.
  • the generator 3 includes a rotor and a stator (both not shown).
  • the generator 3 generates AC power when the rotor rotates as the water turbine 1 rotates.
  • the power generated by the generator 3 is controlled by the control device 100 (see FIG. 3).
  • the support unit 40 supports the water turbine 1, the speed increaser 2, and the generator 3.
  • the support portion 40 includes two beams 40a and 40b, a gantry 40c, a support column 40d, and a base plate 40e.
  • the two beams 40a and 40b are arranged so as to have a parallel positional relationship.
  • a gantry 40c is provided so as to be placed on top of both of the two beams 40a and 40b.
  • the two struts 40d are disposed at one end and the other end of the gantry 40c, respectively.
  • a base plate 40e is disposed so as to connect the upper portions of the two columns 40d.
  • the generator 3 is disposed between the gantry 40c and the base plate 40e, and is fixed to the base plate 40e.
  • a column for fixing the position of the water turbine 1 and the gearbox 2 with respect to the position of the gantry 40c is provided below the gantry 40c.
  • a rotating shaft that connects the speed increaser 2 and the generator 3 is accommodated inside the column.
  • FIG. 3 is a block diagram showing a configuration of the hydroelectric generator according to the present embodiment.
  • the hydroelectric power generation device includes a water turbine 1, a speed increaser 2, a power generator 3, a rotation speed detector 6, a braking device 12, a current meter 14, Control device 100.
  • Control device 100 includes a control unit 7, a rectifier circuit 4, and a DC / AC converter 10.
  • the control unit 7 controls the braking device 12 as well as the rectifier circuit 4 and the DC / AC converter 10.
  • the water wheel 1 is rotated by the power of running water.
  • a generator 3 is connected to the water turbine 1 via a speed increaser 2.
  • the generator 3 generates power as the water turbine 1 rotates.
  • the generator 3 is a three-phase synchronous generator, and its output is output as a three-phase alternating current.
  • the three-phase AC output of the generator 3 is converted into a DC output by the rectifier circuit 4, and the DC output is output to the subsequent DC / AC converter 10.
  • the generator 3 is a three-phase synchronous generator
  • the type of the generator is not limited to this, and an arbitrary type such as a three-phase induction generator or a DC generator may be used.
  • the generator can be used in combination with a control device corresponding to the generator type.
  • a mechanical brake that converts kinetic energy into heat by friction can be used.
  • a mechanical brake electromagnettic brake, disc brake, etc.
  • a fluid brake can be used as the braking device 12.
  • the rotational speed of the water turbine 1 can be increased or decreased or the rotation can be stopped.
  • the control unit 7 measures the state of the generator 3 while measuring the state of the water flow with the velocimeter 14.
  • the control device 100 can observe that the rotational speed of the water turbine 1 has decreased or the amount of power generation has decreased even though the flow rate is sufficient.
  • the control device 100 controls the braking device 12 to repeat braking (decrease in rotational speed) and release (increase in rotational speed). Garbage and aquatic plants entangled with the water turbine blades float from the water turbine 1 when the rotation speed of the water turbine 1 decreases and the water pressure and centrifugal force due to the rotation of the water turbine blades are weakened.
  • the above control may be performed every time a certain time has elapsed.
  • FIG. 4 is a flowchart for explaining the control executed by the control unit in the configuration example of FIG. The process of this flowchart is called and executed at regular intervals from the main routine for generator control. Referring to FIGS. 3 and 4, in step S ⁇ b> 1, control unit 7 determines whether or not the dust removal operation condition is satisfied.
  • the dust removal operation condition is established when the possibility that dust has adhered to the water turbine 1 increases. For example, when any one of the following conditions (1) to (4) is satisfied, the control unit 7 determines that the dust removal operation condition is satisfied. Note that the control unit 7 may determine that the dust removal operation condition is satisfied when a combination of two or more of the conditions (1) to (4) is satisfied.
  • Condition (1) The average generated power of the hydroelectric generator at a certain time has decreased below the threshold value.
  • Condition (2) The average rotation speed of the water turbine 1 at a certain time has decreased to fall below a threshold value.
  • Condition (3) The average generated voltage of the hydroelectric generator at a certain time has decreased below a threshold value.
  • Condition (4) A predetermined time has elapsed since the last time the dust removal operation condition was satisfied (or released).
  • the operating conditions may be determined based on the amount of decrease in average generated power, the average current, the average rotational torque, and the like.
  • step S1 When it is determined in step S1 that the dust removal operation condition is not satisfied (NO in S1), the control unit 7 advances the process to step S10. In this case, control is returned to the main routine.
  • step S1 when it is determined in step S1 that the dust removal operation condition is satisfied (YES in S1), the control unit 7 executes the dust removal operation shown in steps S2 to S9.
  • the control unit 7 increases or decreases the braking force of the braking device 12. For example, the control unit 7 outputs a command signal to the braking device 12 so that the braking force repeats the maximum value and zero when the rotational speed detector 6 detects a decrease in the rotational speed of the generator 3. , The deceleration and acceleration of the water wheel 1 are repeated.
  • the control unit 7 sets a counter upper limit value corresponding to the amount of decrease in generated power.
  • FIG. 5 is a diagram showing the relationship between the generated power before the dust removal operation and the generated power recovered after the dust removal operation.
  • the generated power recovers to 90%. Further, if the dust removal operation is performed in a state where the generated power before the dust removal operation is 60% or more, the generated power is recovered to 100%.
  • the above conditions (1) to (3) should be set to threshold values for the respective conditions so as to correspond to the generated power of 50%, preferably 60%.
  • FIG. 6 is a graph for examining the number of times of braking by the brake.
  • the vertical axis represents the generated power (%) after braking
  • the horizontal axis represents the number of braking times
  • the generated power (%) before braking is 20%, 30%, 40%, 50%, 70%, 90 % Data are plotted.
  • FIG. 6 shows that when the pre-brake generated power is 20% and 30%, the generated power does not increase and dust is not removed no matter how many times the brake is operated. When the generated power before braking is 40%, the generated power recovers somewhat when the brake is operated, but does not increase more than 60%.
  • the generated power before braking is 50%
  • the generated power increases and recovers up to 4 times when the brake is operated, but it does not increase more than 90% even if it is operated 4 times or more.
  • the generated power before braking is 70%
  • the generated power increases and recovers up to 3 times when the brake is operated, and reaches 100% after 3 times.
  • the generated power before braking is 90%
  • the brake is operated the generated power increases and recovers up to twice, and becomes 100% after two times.
  • the operation frequency should be set appropriately to balance the recovery of generated power and the maintenance of the brake life. Is desired. Therefore, in the present embodiment, the brake operation frequency is changed according to the decrease rate of the generated power.
  • FIG. 7 is a diagram showing the relationship between the power generated before braking and the number of brake operations in the dust removal operation.
  • the dust removal operation is executed when the generated power is 50% or more in order to effectively recover the power.
  • the number of times of brake operation is three, and when the generated power before the dust removal operation is 70%.
  • the brake operation frequency is set to 4 times, and when the generated power before the dust removal operation is 50%, the brake operation frequency is set to 6 times.
  • the number of brake actuations is increased as the generated power before the dust removal operation decreases.
  • step S ⁇ b> 2 the control unit 7 determines a counter upper limit value (the number of brakes) as a numerical value corresponding to the amount of decrease in generated power based on the number of removal operations shown in the relationship shown in FIG. Subsequently, in step S3, the control unit 7 clears the built-in counter. This counter is a counter for measuring the number of repetitions. Subsequently, in step S4, the control unit 7 sets the command signal SB so that the braking device 12 generates a braking force (brake ON). Thereafter, in step S5, the control unit 7 waits until a set time (for example, 1 to 10 seconds) elapses in the brake-on state.
  • a set time for example, 1 to 10 seconds
  • step S6 the control unit 7 sets the command signal SB so that the braking device 12 does not generate a braking force (brake OFF). Thereafter, in step S7, the control unit 7 waits until a set time (for example, 1 to 10 seconds) elapses in the brake OFF state.
  • a set time for example, 1 to 10 seconds
  • control unit 7 increments the counter in step S8, and in step S9, determines whether or not the count value of the counter has reached an upper limit value (set number of repetitions of increase / decrease). In step S9, if the count value has not yet reached the upper limit value, the control unit 7 returns the process to step S4 and turns on the brake again.
  • step S9 if the count value reaches the upper limit value in step S9, the process proceeds to step S10, and the dust removal operation per time is completed.
  • the braking device 12 is installed on the rotating shaft that connects the speed increaser 2 and the generator 3 of the hydroelectric power generation device, and the braking device 12 is repeatedly turned on and off. Thereby, the rotational speed of the water turbine 1 is changed.
  • the foreign matter adhering to the water wheel 1 can be removed by applying a force during acceleration, floating up when decelerating, and flowing downstream with the force of water flow. Therefore, there is an effect of recovering the power generation amount that is reduced due to the foreign matter.
  • the set time in S5 and the set time in S7 are fixed values while being repeated up to the upper limit value of the counter.
  • the set time may be changed.
  • FIG. 8 is a block diagram showing a modification of the configuration of the hydroelectric generator.
  • the modified hydroelectric generator includes a water turbine 1, a speed increaser 2, a generator 3, a rotational speed detector 6, a flow meter 14, and a control device 100 ⁇ / b> A.
  • the control device 100A includes a control unit 7A, a rectifier circuit 4, a DC / DC converter 9, and a DC / AC converter 10. Since water turbine 1, generator 3, rectifier circuit 4, and rotational speed detector 6 are the same as those shown in FIG. 3, the description thereof will not be repeated.
  • the control unit 7A outputs a current command signal SA to the DC / DC converter 9.
  • the DC / DC converter 9 takes out power from the output of the rectifier circuit 4 in accordance with the command of the current command signal SA, and outputs a current as commanded to the DC / AC converter 10. Along with this, the output voltage of the DC / DC converter 9 rises.
  • the DC / AC converter 10 outputs power to the subsequent stage.
  • the DC / AC converter 10 is configured to suppress an increase in the output voltage of the DC / DC converter 9 by outputting more power to the subsequent stage.
  • the optimum power that can be extracted from the water turbine 1 is determined by the flow rate of water received by the water turbine 1.
  • the flow rate and the number of rotations of the generator 3 are substantially proportional.
  • the optimum power can be determined. If the electric power that is larger than the optimum electric power is taken out from the generator 3, the rotational speed of the generator 3 is lowered. At this time, the rotational speed of the water turbine 1 connected to the generator 3 also decreases. On the contrary, when the electric power taken out from the generator 3 is less than the optimum value, for example, zero, the rotation speed of the generator increases and increases similarly to the rotation speed of the water turbine 1 connected to the generator 3.
  • the rotational speed of the water turbine 1 can be increased or decreased by increasing or decreasing the electric power extracted from the generator 3.
  • FIG. 9 is a flowchart for explaining control for removing dust adhering to the water wheel in the configuration of FIG. 8 and 9, in step S11, control unit 7A determines whether or not the dust removal operation condition is satisfied.
  • the dust removal operation condition is established when the possibility that dust has adhered to the water turbine 1 increases.
  • conditions (1) to (4) or combinations thereof those already described can be applied, and therefore description thereof will not be repeated here.
  • step S11 If it is determined in step S11 that the dust removal operation condition is not satisfied (NO in S11), the control unit 7A advances the process to step S20. In this case, control is returned to the main routine.
  • step S11 when it is determined in step S11 that the dust removal operation condition is satisfied (YES in S11), the control unit 7A executes the dust removal operation shown in steps S12 to S19.
  • step S12 the control unit 7A determines the counter upper limit value to a numerical value corresponding to the amount of decrease in generated power based on the number of removal operations shown in the relationship shown in FIG. Subsequently, the control unit 7A increases or decreases the current command value to the DC / DC converter 9 as the dust removal operation. For example, when the control unit 7A detects a decrease in the rotational speed of the generator 3 from the rotational speed detector 6, the control unit 7A outputs the current command signal SA so that the output current repeats the maximum value and zero. Repeat the deceleration and acceleration.
  • step S13 the control unit 7A clears the built-in counter. This counter is a counter for measuring the number of repetitions. Subsequently, in step S14, the control unit 7A sets the current command signal SA so that the DC / DC converter 9 maximizes the output current, and then in step S15, the control unit 7A sets the set time (for example, 1 to Wait 3 seconds). While the output current of the DC / DC converter 9 is maximized, a large amount of electric power is consumed and a large braking force is generated in the generator 3.
  • step S14 the control unit 7A sets the current command signal SA so that the DC / DC converter 9 maximizes the output current
  • step S15 the control unit 7A sets the set time (for example, 1 to Wait 3 seconds). While the output current of the DC / DC converter 9 is maximized, a large amount of electric power is consumed and a large braking force is generated in the generator 3.
  • step S16 the control unit 7A sets the current command signal SA so that the DC / DC converter 9 sets the output current to zero, and then in step S17, the control unit 7A sets the set time (for example, 1 to 3). Wait). In this case, since the load on the generator 3 is lighter than when the current command signal SA is set to the maximum current, the rotational speed of the generator 3 increases.
  • control unit 7A increments the counter in step S18, and determines in step S19 whether or not the count value of the counter has reached the upper limit value (set number of repetitions of increase / decrease). In step S19, if the count value has not yet reached the upper limit value, control unit 7A returns the process to step S14, and sets current command signal SA to maximize the output current again.
  • step S19 when the count value reaches the upper limit value in step S19, the process proceeds to step S20, and the dust removal operation per time is completed.
  • the load of the generator 3 that is linked to the water turbine 1 of the hydroelectric generator is varied by increasing or decreasing the current command value of the DC / DC converter 9.
  • the rotational speed of the generator 3 is changed, and the rotational speed of the water turbine 1 interlocked with the generator 3 is changed.
  • the foreign matter adhering to the water wheel 1 can be removed by applying a force during acceleration, floating up when decelerating, and flowing downstream with the force of water flow. Therefore, there is an effect of recovering the power generation amount that is reduced due to the foreign matter.
  • the brake life is extended while effectively removing dust by determining the number of times of increase / decrease in braking force corresponding to the amount of decrease in generated power.
  • the pattern for applying the braking force is changed.
  • FIG. 10 is a flowchart for explaining control executed by the control unit in the hydroelectric generator of the second embodiment. The process of this flowchart is called and executed at regular intervals from the main routine for generator control.
  • step S51 the control unit 7 determines whether or not the dust removal operation condition is satisfied.
  • the dust removal operation condition is established when the possibility that dust has adhered to the water turbine 1 increases.
  • conditions (1) to (4) or combinations thereof those already described can be applied, and therefore description thereof will not be repeated here.
  • step S51 If it is determined in step S51 that the dust removal operation condition is not satisfied (NO in S51), the control unit 7 advances the process to step S55. In this case, control is returned to the main routine.
  • step S51 when it is determined in step S51 that the dust removal operation condition is satisfied (YES in S51), the control unit 7 executes the dust removal operation shown in steps S52 to S54.
  • step S52 control is performed to decelerate the water turbine 1 with the first braking pattern.
  • the first braking pattern is a braking pattern in which the load on the braking device 12 is relatively small.
  • step S54 control is returned to the main routine.
  • the second braking pattern is a braking pattern in which the load on the braking device is larger than that of the first braking pattern.
  • FIG. 11 is a waveform diagram showing a first example of the first braking pattern.
  • FIG. 12 is a waveform diagram showing a second example of the first braking pattern.
  • FIG. 13 is a waveform diagram showing a third example of the first braking pattern.
  • FIG. 14 is a waveform diagram showing a fourth example of the first braking pattern.
  • FIG. 15 is a waveform diagram showing an example of the second braking pattern.
  • the second braking pattern shown in FIG. 15 is a control in which a sudden braking is applied to the rotating water wheel 1 to temporarily stop the rotation and then the brake is released.
  • the brake is applied more slowly than in FIG. 15, or the brake is released before reaching the stop.
  • the control unit 7 tries to remove dust with the first braking pattern with a light load on the braking device 12, and when the electric power still does not recover, the second braking pattern is applied.
  • the first braking pattern can be considered and will be described with reference to FIGS.
  • the degree of deceleration at time t1 is not different from that in FIG. 15, but when the rotational speed decreases from N1 to N2, the braking force is maintained and released at time t2.
  • the degree of deceleration at times t11 to t12 is slower than that in FIG. 15, and the braking torque of the braking device 12 can be small.
  • the deceleration degree from time t21 to t22 is slower than that in FIG. 15, and the braking device 12 is released immediately at time t22, so that the amount of power generation can be reduced little.
  • FIG. 16 is a front view showing a schematic shape of the hydroelectric generator according to the third embodiment.
  • the hydraulic power generation apparatus according to Embodiment 4 includes a water turbine 1 ⁇ / b> A and a generator 3.
  • the water turbine 1 ⁇ / b> A has a vertical axis type rotary blade and rotates by a water flow.
  • the generator 3 is connected to the rotating shaft of the water turbine 1A. When the water wheel 1A rotates, the rotating shaft of the generator 3 also rotates.
  • FIGS. 3 to 15 can be used in combination in the same manner for the water turbine 1A shown in FIG. Since the control device, flowchart, and braking pattern shown in FIGS. 3 to 15 have been described in the first and second embodiments, description thereof will not be repeated here.
  • the vertical axis type water turbine 1 ⁇ / b> A is a straight wing type and exemplifies a configuration in which the upper and lower ends of the wing are bent toward the rotation axis, but is not particularly limited thereto.
  • other types such as a Darius type, a gyromill type, a Savonius type, a cross flow type, a paddle type, and an S-type rotor type may be used.
  • the rotational speed of the generator 3 can be changed, and the rotational speed of the water turbine 1A connected to the generator 3 can be changed.
  • the foreign matter attached to the water turbine 1A can be removed by applying a force during acceleration, floating up when decelerating, and flowing downstream with the force of water flow. Therefore, there is an effect of recovering the power generation amount that is reduced due to the foreign matter.
  • the hydroelectric generator of the present embodiment includes a hydraulic turbine 1, an electric or mechanical braking device 12 that operates a braking force on a rotating shaft that is linked to the hydraulic turbine 1, and an operation of the braking device 12 so that the braking force increases or decreases. And a control device 100 that repeats release. As shown in FIG. 7, when the amount of decrease from the power corresponding to the flow rate of the generated power of the generator 3 is the first value, the control device 100 operates the braking device 12 a first number of times (for example, If the electric power corresponding to the flow rate is 100% and then 90% is reduced by 10%, the operation is performed three times).
  • the device 12 is activated a second number of times that is greater than the first number of times (eg, activated 4 times for 70% reduced by 30%, and activated 6 times for reduced 50%).
  • the rotational speed of the turbine blade is changed by installing the rotational braking device connected to the hydraulic turbine of the hydroelectric generator and repeating the braking (decreasing rotational speed) and releasing (increasing rotational speed) on the turbine blade.
  • Garbage and grass entangled with the turbine blades are lifted from the turbine blades by the inertial force because the water pressure and centrifugal force due to the rotation of the turbine blades are weakened when the rotation speed of the turbine wheels decreases.
  • braking and releasing are repeated, it becomes easy to float, and the force that pushes downstream by the water flow acts and flows downstream.
  • the reduction amount ⁇ P of the generated power may be expressed as a percentage (%) or may be expressed as electric power (W).
  • the braking device 12 includes a brake (mechanical friction brake) that applies a frictional force to a member fixed to the rotating shaft of the water turbine.
  • the control device 100 increases or decreases the braking force by changing the frictional force.
  • the braking device includes a generator 3 that generates power by the rotation of the water wheel.
  • the control device 100A increases or decreases the braking force by increasing or decreasing the electric power extracted from the generator.
  • the speed fluctuation range of the water turbine 1 is sufficiently obtained by repeatedly increasing / decreasing the braking force from the predetermined rotational speed.
  • the flow rate of water received by the water turbine 1 varies greatly in the long term, and may be greatly reduced in a season with little rainfall. Accordingly, the rotational speed of the water turbine 1 also decreases, and even when the braking force increase / decrease operation is repeated from the state in which the rotational speed of the water turbine 1 decreases, the fluctuation range of the rotational speed of the water turbine 1 is small, and predetermined dust removal The effect may not be obtained.
  • the water turbine has a horizontal axis type propeller rotor blade.
  • the water turbine has a vertical axis type rotor blade.
  • the hydroelectric generator of another aspect disclosed in the present disclosure includes a water turbine 1, an electric or mechanical brake device 12 that operates a braking force on a rotating shaft that operates in conjunction with the water turbine, and braking so that the braking force increases or decreases.
  • a control device 100 that repeats the operation and release of the device 12 is provided. As shown in FIG. 10, when the generated power is lower than the power corresponding to the flow velocity, the control device 100 performs braking so that the braking force shows the first increase / decrease pattern (any one of FIGS. 12 to 14). When the device 12 is operated and recovery of the generated power is insufficient, the braking device is operated with a second increase / decrease pattern (FIG. 15) having a deceleration larger than that of the first increase / decrease pattern.
  • the present disclosure also discloses a power generation system that performs ocean current power generation or tidal power generation that converts kinetic energy of flowing water into electric power using any of the above-described hydroelectric power generation apparatuses.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Hydraulic Turbines (AREA)
  • Control Of Water Turbines (AREA)

Abstract

L'invention concerne un dispositif de production d'énergie hydroélectrique comprenant : une turbine à eau (1); un dispositif de freinage électrique ou mécanique (12) pour amener une force de freinage à agir sur un arbre de rotation qui se verrouille avec la turbine à eau (1); et un dispositif de commande (100) pour répéter l'opération et la libération du dispositif de freinage (12) de façon à augmenter ou à diminuer la force de freinage. Le dispositif de commande (100) actionne le dispositif de freinage (12) pour un premier nombre de fois où une quantité de réduction de puissance générée d'un générateur (3) à partir de la puissance correspondant à la vitesse d'écoulement atteint une première valeur (par exemple, le dispositif de freinage est actionné trois fois lorsque la puissance générée est de 90% après une réduction de 10%), et actionne le dispositif de freinage (12) pour un second nombre de fois supérieur au premier nombre de fois lorsque la quantité de réduction de la puissance générée est une seconde valeur plus grande que la première valeur (par exemple, le dispositif de freinage est actionné quatre fois lorsque la puissance générée est de 70% après une réduction de 30%, et est actionné six fois lorsque la puissance générée diminue de 50%). Par conséquent, un dispositif de production d'énergie hydroélectrique compact avec une maintenance facile contre la poussière et les matières étrangères peut être fourni tout en réduisant le coût.
PCT/JP2018/015191 2017-04-28 2018-04-11 Dispositif de production d'énergie hydroélectrique et système de production d'énergie WO2018198771A1 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2017-089698 2017-04-28
JP2017089698A JP6885778B2 (ja) 2017-04-28 2017-04-28 水力発電装置および発電システム

Publications (1)

Publication Number Publication Date
WO2018198771A1 true WO2018198771A1 (fr) 2018-11-01

Family

ID=63918338

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2018/015191 WO2018198771A1 (fr) 2017-04-28 2018-04-11 Dispositif de production d'énergie hydroélectrique et système de production d'énergie

Country Status (2)

Country Link
JP (1) JP6885778B2 (fr)
WO (1) WO2018198771A1 (fr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180223792A1 (en) * 2015-11-02 2018-08-09 Ntn Corporation Hydroelectric power generation apparatus and power generation system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5484220A (en) * 1977-12-17 1979-07-05 Meidensha Electric Mfg Co Ltd Hydraulic power plant device
JPH0730373U (ja) * 1992-11-11 1995-06-06 東芝エンジニアリング株式会社 小容量水車の制御装置
JP2008261327A (ja) * 2007-03-19 2008-10-30 Kawasaki Heavy Ind Ltd シャフトレス水車起動装置
JP2012197703A (ja) * 2011-03-18 2012-10-18 Tokyo Electric Power Co Inc:The 水車監視制御装置及び水車監視制御方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5484220A (en) * 1977-12-17 1979-07-05 Meidensha Electric Mfg Co Ltd Hydraulic power plant device
JPH0730373U (ja) * 1992-11-11 1995-06-06 東芝エンジニアリング株式会社 小容量水車の制御装置
JP2008261327A (ja) * 2007-03-19 2008-10-30 Kawasaki Heavy Ind Ltd シャフトレス水車起動装置
JP2012197703A (ja) * 2011-03-18 2012-10-18 Tokyo Electric Power Co Inc:The 水車監視制御装置及び水車監視制御方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180223792A1 (en) * 2015-11-02 2018-08-09 Ntn Corporation Hydroelectric power generation apparatus and power generation system
US10677214B2 (en) * 2015-11-02 2020-06-09 Ntn Corporation Hydroelectric power generation apparatus and power generation system

Also Published As

Publication number Publication date
JP6885778B2 (ja) 2021-06-16
JP2018188981A (ja) 2018-11-29

Similar Documents

Publication Publication Date Title
KR102577355B1 (ko) 수력 발전 장치 및 발전 시스템
CN102312778B (zh) 用于监视风力涡轮机的操作的方法和系统
JP5092017B2 (ja) 風力発電装置及びナセル旋回方法
EP2466126B1 (fr) Appareil et procédé de fonctionnement d'une éolienne en mer
WO2011011358A2 (fr) Système et procédé pour délivrer une sortie constante à partir d'une entrée à écoulement variable
CN112585348B (zh) 水力发电装置和发电系统
EP2966297A1 (fr) Système de génération d'énergie éolienne
CN104791176A (zh) 一种排列式漂浮流水发电装置
CN104612896A (zh) 海上风电抗台风控制系统
WO2013073559A1 (fr) Dispositif et procédé de génération d'énergie éolienne et programme associé
WO2018198771A1 (fr) Dispositif de production d'énergie hydroélectrique et système de production d'énergie
US20190162162A1 (en) Hydroelectric power generation apparatus and power generation system
EP2963286A1 (fr) Éolienne et procédé pour l'arrêter
JP2018040306A (ja) 風水力発電装置
WO2019181474A1 (fr) Dispositif de production d'énergie hydroélectrique, et système de production d'énergie
CN104047796A (zh) 一种利用自然流动的河水进行发电的装置
WO2011155278A1 (fr) Dispositif de génération d'énergie par fluide, et procédé de commande du dispositif de génération d'énergie par fluide
WO2017077799A1 (fr) Dispositif de production d'énergie hydroélectrique et système de production d'énergie
WO2018021000A1 (fr) Dispositif générateur d'énergie hydraulique et système générateur d'énergie
JP4299767B2 (ja) 水車発電システム及びインバータ
JP2020090892A (ja) 水力発電装置および発電システム
CN203867780U (zh) 一种全负荷无刹车轮式风力发电装置
JP2024048515A (ja) 発電装置および発電方法
JP2007032468A (ja) 風力発電装置
RU2297549C2 (ru) Способ максимального извлечения кинетической энергии из турбулизированного воздушного потока и преобразования ее в электрическую энергию и устройство для его осуществления

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18791134

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18791134

Country of ref document: EP

Kind code of ref document: A1