WO2013118376A1 - 電力供給システムおよびそれに用いられる充放電用パワーコンディショナ - Google Patents

電力供給システムおよびそれに用いられる充放電用パワーコンディショナ Download PDF

Info

Publication number
WO2013118376A1
WO2013118376A1 PCT/JP2012/081261 JP2012081261W WO2013118376A1 WO 2013118376 A1 WO2013118376 A1 WO 2013118376A1 JP 2012081261 W JP2012081261 W JP 2012081261W WO 2013118376 A1 WO2013118376 A1 WO 2013118376A1
Authority
WO
WIPO (PCT)
Prior art keywords
power
charge
conditioner
output voltage
voltage
Prior art date
Application number
PCT/JP2012/081261
Other languages
English (en)
French (fr)
Inventor
和憲 木寺
Original Assignee
パナソニック株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by パナソニック株式会社 filed Critical パナソニック株式会社
Publication of WO2013118376A1 publication Critical patent/WO2013118376A1/ja

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/22The renewable source being solar energy
    • H02J2300/24The renewable source being solar energy of photovoltaic origin
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/50The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads
    • H02J2310/56The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads characterised by the condition upon which the selective controlling is based
    • H02J2310/58The condition being electrical
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E70/00Other energy conversion or management systems reducing GHG emissions
    • Y02E70/30Systems combining energy storage with energy generation of non-fossil origin
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Definitions

  • the present invention relates to a power supply system for supplying power to a load and a charge / discharge power conditioner used therefor.
  • a solar power generation system including a solar cell and a solar cell power conditioner is known (see, for example, Japanese Patent Application Laid-Open No. 9-135577).
  • the solar cell power conditioner used in the solar power generation system can perform an interconnected operation linked to the commercial power system, and can perform a self-sustaining operation independent of the commercial power system when the commercial power system fails. .
  • the solar cell power conditioner can supply power to the load even when the commercial power grid fails.
  • the solar battery power conditioner connects the load which wants to supply electric power at the time of the interconnected operation, and the load which wants to supply electric power at the independent operation. And a free standing output terminal for connection.
  • the interconnection output terminal and the stand-alone output terminal are separate terminals, and in order to switch from the interconnection operation mode to the stand-alone operation mode when a power failure of the commercial power system occurs.
  • the required manual operation was required. That is, without the above-mentioned manual operation, the conventional solar cell power conditioner can not start the self-sustaining operation independent of the commercial power system, and can not effectively use the electric power generated by the solar cell.
  • the power supply system includes a power conditioner for controlling power generation of a power generation device, a power conditioner for charging and discharging for controlling charge and discharge of a storage battery, and a commercial feed path for feeding power from a commercial power system to a load. And a detection unit for detecting recovery of the commercial power system, wherein the power conditioner for generating power is supplied from the power conditioner for power generation and the power conditioner for charging and discharging to the load.
  • the function of outputting power to the feed path when a predetermined voltage is applied to the feed path for feeding, and stopping the power output to the feed path when the predetermined voltage is not applied to the feed path The switching unit electrically disconnects the commercial power feed line when the commercial power system fails, and the detection unit restores the commercial power system.
  • the charge / discharge power conditioner detects a power failure of the commercial power system, an output control unit that controls power output to the feed line, and And a power failure detection unit, wherein the output control unit detects the power failure of the commercial power system by the power failure detection unit, and the power feeding path is electrically disconnected by the switching unit.
  • the effective value of the output voltage output from the charge / discharge power conditioner toward the feed path side is changed so that the voltage of the path becomes the predetermined voltage.
  • the power conditioner for power generation has a function of suppressing the power output to the feed path when the effective value of the voltage of the feed path is larger than a predetermined threshold value
  • the output control unit of the charge / discharge power conditioner may When charging satisfies the normal condition, the effective value of the output voltage is set to the threshold or less, and when the charging of the storage battery does not satisfy the normal condition, the effective value of the output voltage is made larger than the threshold Is preferred.
  • the charge / discharge power conditioner includes a calculation unit that calculates charge power when charging the storage battery, and the output control unit is configured to calculate the charge power calculated by the calculation unit.
  • the effective value of the output voltage is increased at a predetermined first rate of increase, the charging power is higher than the specified power, and the effective value of the output voltage is higher than the threshold
  • the large second threshold is exceeded, the effective value of the output voltage is increased at a second increase rate that is greater than or equal to zero and lower than the first increase rate, and the effective value of the output voltage is greater than the second increase rate. It is preferable to reduce the effective value of the output voltage when the charging power is less than the specified power in a state larger than a threshold value.
  • the charge / discharge power conditioner has a power change detection unit that detects a change direction of increase or decrease of the charge power, and the output control unit is configured to set the charge power to a level equal to or higher than the specified power.
  • the effective value of the output voltage is maintained at the value at the point of detection when it is detected by the power change detection unit that the charge power is in the decreasing direction.
  • the charge / discharge power conditioner calculates a charge power at the time of charging the storage battery, and the charge power calculated by the calculation unit is greater than a predetermined change rate. It is preferable to have a stop control unit that stops the power output from the power conditioner for power generation to the power conditioner for charge and discharge when the power is increased to become the specified power or more.
  • the power supply system includes a power generation switching unit inserted between the power generation power conditioner and the power feeding path, and the stop control unit of the charge / discharge power conditioner changes the charge power as the change. It is preferable to control the power generation switching unit so as to electrically cut off the power conditioner for power generation and the power feeding path when the power increases by a rate or more and becomes equal to or more than the specified power.
  • the power conditioner for power generation has a function of stopping the power output when the effective value of the voltage of the power feeding path exceeds a predetermined abnormal stop value, and the power for charging and discharging
  • the stop control unit of the conditioner is configured to make the effective value of the output voltage larger than the abnormal stop value when the charging power increases by the change rate or more and becomes the specified power or more. It is preferable to control
  • the output control unit of the charge / discharge power conditioner preferably changes the amplitude of the output voltage.
  • the output control unit of the charge / discharge power conditioner sets a waveform equivalent to a waveform obtained by superimposing a wave whose instantaneous value becomes zero at a peak point of the sine wave on the sine wave. It is preferable to change the effective value of the output voltage by changing the waveform.
  • the output control unit of the charge / discharge power conditioner changes the waveform of the output voltage to a waveform equivalent to a waveform in which a double harmonic is superimposed on the fundamental wave as the sine wave.
  • the effective value of the output voltage is changed.
  • the output control unit of the charge / discharge power conditioner changes the waveform of the output voltage to a waveform equivalent to a waveform obtained by amplifying a sine wave with a gain different depending on the phase of the sine wave.
  • the effective value of the output voltage is changed.
  • the power conditioner for charge and discharge of the present invention is used in a power supply system.
  • the power conditioner for communication regardless of whether or not the power conditioner for communication has a communication function, it is possible to use the power from the power generation device without the need for manual operation at the time of power failure of the commercial power system.
  • FIG. 1 is a schematic view showing a configuration of a power supply system according to a first embodiment.
  • FIG. 1 is a circuit diagram showing the configuration of the main part of a power supply system according to a first embodiment.
  • FIG. 6 is an explanatory diagram for explaining the operation of the power supply system according to the first embodiment.
  • FIG. 6 is an explanatory diagram for explaining the operation of the power supply system according to the first embodiment.
  • FIG. 6 is an explanatory diagram for explaining the operation of the power supply system according to the first embodiment.
  • FIG. 6 is an explanatory diagram for explaining the operation of the power supply system according to the first embodiment.
  • FIG. 5 is a flowchart showing an operation of the power supply system according to the first embodiment.
  • 5 is a flowchart showing an operation of the power supply system according to the first embodiment.
  • FIG. 8 is an explanatory view for explaining the operation of the power supply system according to the second embodiment.
  • 7 is a flowchart showing the operation of the power supply system according to the second embodiment.
  • FIG. 13 is a circuit diagram showing the configuration of the main part of a power supply system according to a third embodiment.
  • FIG. 13 is an explanatory diagram for explaining the operation of the power supply system according to the third embodiment.
  • 7 is a flowchart showing the operation of the power supply system according to the third embodiment.
  • FIG. 14 is an explanatory view illustrating an operation of the power supply system according to the fourth embodiment.
  • 15 is a flowchart showing the operation of the power supply system according to the fourth embodiment.
  • the power supply system 1 includes a solar cell power conditioner (power conditioner for power generation) 2 that controls power generation of a solar cell (power generator) 21, and a fuel cell (power generator). And a fuel cell power conditioner (power conditioner for power generation) 3 for controlling the power generation in the above.
  • the power supply system 1 also includes a charge / discharge power conditioner 4 that controls charge / discharge of the storage battery 41. Further, the power supply system 1 distributes the power to the load 8 and the switch board 5 including the first switch (switching unit) 51 inserted in the commercial power feeding path 91 for supplying power from the commercial power system 7 to the load 8.
  • the distribution board 6 to be The solar cell power conditioner 2, the fuel cell power conditioner 3 and the charge / discharge power conditioner 4 are electrically connected to the distribution board 6 and the commercial power system 7 via the switching board 5.
  • the power supply system 1 is operated by the charge / discharge power conditioner 4 after the solar cell power conditioner 2, the fuel cell power conditioner 3, and the charge / discharge power conditioner 4 are temporarily stopped at the time of a power failure of the commercial power system 7.
  • This is a system for reactivating the solar cell power conditioner 2 and the fuel cell power conditioner 3.
  • the load 8 includes, for example, a plurality of (four in FIG. 1) load devices 81, 81... Installed in a house.
  • Each load device 81 is, for example, a home appliance such as a television, a microwave, a refrigerator, or a lighting fixture.
  • Each load device 81 is directly connected to the distribution board 6 or connected to the distribution board 6 via an outlet (not shown).
  • the distribution board 6 includes a main breaker and a plurality of branch breakers.
  • the distribution board 6 distributes AC power to the load devices 81, 81,.
  • the master breaker distributes AC power from the solar cell power conditioner 2, the fuel cell power conditioner 3, the charge / discharge power conditioner 4, and the commercial power system 7 to each branch breaker.
  • the branch breaker supplies power from the master breaker to load devices 81 connected to the branch breaker.
  • the solar cell 21 is installed, for example, on the roof of a dwelling unit and performs solar power generation. That is, the solar cell 21 generates direct current power using solar energy.
  • the solar cell not only a single cell solar cell (solar cell) but also a solar cell module in which a plurality of solar cells are arranged in series or in parallel, a plurality of solar cells Also included are solar cell arrays in which modules are arranged in series or in parallel.
  • a solar cell is a configuration of a minimum unit having a solar cell function.
  • the solar cell module has a configuration in which a plurality of solar cells are arranged and covered with tempered glass or the like.
  • the solar cell array has a configuration in which a plurality of solar cell modules are arranged on a mount provided on a roof or the like.
  • the solar cell power conditioner 2 includes a power conversion unit 22, a control unit 23, and a pair of switches 24 and 24. Further, the solar cell power conditioner 2 includes a voltage detection unit 251, a current detection unit 252, and a pair of output terminal units 26, 26.
  • This solar cell power conditioner 2 is AC power (for example, 100 V or 200 V) adapted to grid interconnection with DC power (for example, DC 100 V to 250 V) generated by the solar cell 21 with the commercial power system 7 (see FIG. 1). , And outputs this AC power to the distribution board 6 (see FIG. 1).
  • the solar cell power conditioner 2 also controls the generated power of the solar cell 21.
  • the power conversion unit 22 includes a DC / DC conversion unit 27 and a DC / AC conversion unit 28.
  • the power conversion unit 22 operates in accordance with an instruction of the control unit 23.
  • the DC / DC conversion unit 27 includes an inductor 271, a switching element 272, a diode 273, a capacitor 274, and a diode 275.
  • the switching element 272 is, for example, an insulated gate bipolar transistor (hereinafter referred to as "IGBT"), and is switched on and off in accordance with a control signal from the control unit 23.
  • IGBT insulated gate bipolar transistor
  • the DC / DC conversion unit 27 converts the DC voltage input from the solar cell 21 into a DC voltage suitable for the DC / AC conversion unit 28. Specifically, first, when the switching element 272 is turned on by the control signal from the control unit 23, the path of the direct current from the solar cell 21 becomes the path of the inductor 271 and the switching element 272. At this time, electromagnetic energy is stored in the inductor 271. Thereafter, when the switching element 272 is turned off by the control signal from the control unit 23, a back electromotive force is generated in the inductor 271, and the back electromotive force is added to the DC voltage from the solar cell 21. The DC voltage from the solar cell 21 A larger DC voltage is output to the capacitor 274 side. The DC / DC conversion unit 27 outputs the DC voltage smoothed by the capacitor 274 to the DC / AC conversion unit 28.
  • the DC / AC conversion unit 28 includes a switching circuit 281 and a filter circuit 282.
  • the DC / AC conversion unit 28 converts the DC voltage from the DC / DC conversion unit 27 into an AC voltage in the switching circuit 281, and smoothes the AC voltage from the switching circuit 281 in the filter circuit 282.
  • the switching circuit 281 includes four switching elements 291 to 294 and four diodes 295, 295,.
  • the switching circuit 281 is a full bridge circuit configured of four switching elements 291 to 294.
  • the switching elements 291 to 294 are, for example, IGBTs, and switch on and off according to a control signal from the control unit 23.
  • the switching circuit 281 converts the DC voltage from the DC / DC converter 27 into an AC voltage by switching the switching elements 291 to 294 on and off.
  • the alternating voltage is output to the filter circuit 282.
  • the filter circuit 282 includes an inductor 296, a capacitor 297, and an inductor 298.
  • the control unit 23 has a CPU (microprocessor (MPU: Micro Processing Unit)) mounted on a computer as a main component, and operates according to a program to operate the DC / DC conversion unit 27 and the DC / AC of the power conversion unit 22.
  • the conversion unit 28 is controlled. At this time, the control unit 23 performs cooperative control with the commercial power system 7.
  • Control unit 23 supplies power to feed path 92 when a predetermined voltage is applied to feed path 92 for feeding power from solar cell power conditioner 2 and charge / discharge power conditioner 4 to load 8 (see FIG. 1). Power output function to output Further, the control unit 23 has a power failure detection function of detecting a power failure of the commercial power system 7 when a predetermined voltage is not applied to the power feeding path 92. Furthermore, the control unit 23 has a solitary operation preventing function of stopping the power output to the power feeding path 92 when a power failure of the commercial power system 7 is detected by the power failure detection function.
  • the power failure detection function of the control unit 23 is an islanding operation detection function that detects that the solar battery power conditioner 2 is operating alone at the time of a power failure of the commercial power grid 7.
  • a detection method used for the islanding operation detection function there are a passive method and an active method.
  • a passive system there are a voltage phase jump detection system, a third harmonic voltage distortion surge detection system, a frequency change rate detection system, and the like.
  • Active methods include frequency shift method, slip mode frequency shift method, active power variation method, reactive power variation method, load variation method and the like.
  • the solar cell power conditioner 2 stores the program for the control part 23 (computer) to perform various functions.
  • the program is stored in advance in the solar battery power conditioner 2 when the solar battery power conditioner 2 is shipped.
  • a method using a computer readable recording medium having the program recorded thereon is an example of a method for the solar battery power conditioner 2 to acquire the program.
  • the solar cell power conditioner 2 may be provided with a reading device (not shown) for reading data of the recording medium. Examples of the recording medium include an optical disc (CD-ROM, DVD-ROM) and a memory card.
  • Examples of the reading device include a drive device that reads information of an optical disk, and a memory card reader that reads information of a memory card.
  • the solar battery power conditioner 2 may have a communication function (not shown) for communicating with another device using a network.
  • the solar cell power conditioner 2 is not limited to the circuit configuration shown in FIG. 2 and may be another known circuit configuration.
  • the fuel cell power conditioner 3 shown in FIG. 1 controls the power generation of a fuel cell (not shown), that is, the generated power of the fuel cell. Further, the fuel cell power conditioner 3 converts the DC power generated by the fuel cell into AC power (for example, 100 V or 200 V) compatible with the grid connection with the commercial power system 7, and this AC power is distributed Output to 6 Like the solar cell power conditioner 2, the fuel cell power conditioner 3 has a power output function of outputting power to the power feeding path 92 when a predetermined voltage is applied to the power feeding path 92. Further, the fuel cell power conditioner 3 has a power failure detection function of detecting a power failure of the commercial power system 7 when a predetermined voltage is not applied to the power feeding path 92.
  • the fuel cell power conditioner 3 has an islanding operation preventing function of stopping the power output to the power feeding path 92 when a power failure of the commercial power system 7 is detected by the power failure detecting function.
  • the power failure detection function of the fuel cell power conditioner 3 is an islanding operation detection function that detects that the fuel cell power conditioner 3 is operating alone at the time of a power failure of the commercial power system 7.
  • the detection method used for the isolated operation detection function of the fuel cell power conditioner 3 can adopt the same method as the solar cell power conditioner 2, but the same method as the solar cell power conditioner 2 needs to be used. Absent.
  • the switchboard 5 includes a first switch (switching unit) 51 inserted in the commercial power feeding path 91 and a detection unit 54 that detects a power return of the commercial power grid 7.
  • switching board 5 has a second switch (power generation switching unit) 52 inserted between solar cell power conditioner 2 and feed path 92, and between fuel cell power conditioner 3 and feed path 92.
  • a third switch (power generation switching unit) 53 inserted therein.
  • the detection unit 54 is provided on the commercial power feed path 91 between the commercial power grid 7 and the first switch 51, and measures the power recovery of the commercial power grid 7 by measuring the voltage of the commercial power feed path 91. To detect.
  • the first switch 51 is turned off and electrically disconnects the commercial power feeding path 91 when the commercial power grid 7 fails.
  • the first switch 51 is turned on to electrically connect the commercial feed path 91. That is, while the first switch 51 is in the on state at normal times (during non-power failure), it is turned off at the time of power failure.
  • the second switch 52 is inserted between the solar cell power conditioner 2 and the feed path 92 and provided. When the commercial power system 7 loses power, the second switch 52 is turned off to electrically disconnect between the solar cell power conditioner 2 and the feeding path 92. That is, while the second switch 52 is in the on state at normal times (during a non-power failure), it is turned off at the time of a power failure.
  • the third switch 53 is inserted between the fuel cell power conditioner 3 and the feed path 92 and provided. When the commercial power grid 7 fails, the third switch 53 is turned off to electrically disconnect between the fuel cell power conditioner 3 and the feed path 92. That is, while the third switch 53 is in the on state at normal times (during a non-power failure), it is turned off at the time of a power failure.
  • the storage battery 41 is, for example, a nickel hydrogen battery, a lithium ion battery, a lead storage battery, etc., and can store the generated power of the solar cell 21, the generated power of the fuel cell, and the commercial power of the commercial power system 7.
  • the charge / discharge power conditioner 4 includes a power conversion unit 42, a control unit 43, a pair of switches 44, 44, and a pair of output terminal portions 45, 45.
  • the charge / discharge power conditioner 4 also includes a full charge detection unit 461, a current detection unit 462, and an output voltage detection unit 463.
  • this charge / discharge power conditioner 4 converts an AC voltage from the side of distribution board 6 (see FIG. 1) into a DC voltage compatible with storage battery 41, and this DC voltage is stored in storage battery 41.
  • the power conditioner 4 for charging and discharging converts the DC voltage of the storage battery 41 into an AC voltage suitable for grid interconnection with the commercial power grid 7 (see FIG. 1).
  • the voltage is output to distribution board 6.
  • the power conversion unit 42 includes a DC / DC bidirectional conversion unit 47 and a DC / AC bidirectional conversion unit 48.
  • the power conversion unit 42 operates in accordance with an instruction of the control unit 43.
  • the DC / DC bidirectional conversion unit 47 includes an inductor 471, two switching elements 472 and 473, two diodes 474 and 475, and a capacitor 476.
  • the switching elements 472 and 473 are, for example, IGBTs, and are switched on and off in accordance with a control signal from the control unit 43.
  • the DC / AC bidirectional conversion unit 48 includes a switching circuit 481 and a filter circuit 482.
  • the switching circuit 481 includes four switching elements 491 to 494 and four diodes 495, 495,.
  • the filter circuit 482 includes an inductor 496, a capacitor 497, and an inductor 498.
  • the switching elements 491 to 494 are, for example, IGBTs, and switch on and off in accordance with a control signal from the control unit 43.
  • the DC / AC bidirectional conversion unit 48 converts the DC voltage from the DC / DC bidirectional conversion unit 47 into an AC voltage in the switching circuit 481 according to the instruction of the control unit 43 at the time of discharge, and the filter circuit 482 The alternating voltage from the switching circuit 481 is smoothed.
  • the DC / AC bidirectional conversion unit 48 converts the AC voltage from the feed path 92 side into a DC voltage in the switching circuit 481 according to the instruction of the control unit 43.
  • the control unit 43 has a CPU (microprocessor) mounted on the computer as a main component, and operates according to a program to function as a power failure detection unit, an output control unit, and a switching control unit described later. That is, the control unit 43 controls the DC / DC bidirectional conversion unit 47 and the DC / AC bidirectional conversion unit 48.
  • a CPU microprocessor
  • the power failure detection unit detects a power failure of the commercial power system 7 when a predetermined voltage is not applied to the power feeding path 92.
  • the output control unit controls the power output to the feed line 92. Further, the output control unit has an islanding operation detecting function of detecting that the charging / discharging power conditioner 4 is operating alone when the commercial power grid 7 fails. Thereby, the output control unit stops the power output from the charge / discharge power conditioner 4 to the power feeding path 92 when the power failure detection unit detects a power failure of the commercial power grid 7.
  • the detection method used for the isolated operation detection function of the output control unit can adopt the same method as the solar battery power conditioner 2, but the same method as the solar battery power conditioner 2 or the fuel cell power conditioner 3 It does not have to be.
  • the output control unit when the power failure detection unit detects a power failure of the commercial power system 7 and the first power supply line 91 is electrically disconnected by the first switch 51, the power output is temporarily stopped, The effective value of the output voltage V1 on the side of the feed line 92 is changed so that the voltage V2 applied thereto (hereinafter referred to as "feed line voltage") becomes a predetermined voltage. That is, the output control unit performs current control at the time of charge and discharge of storage battery 41 in a state of being interconnected with commercial power system 7 (see FIG.
  • the voltage control is performed by changing the effective value of the output voltage V1 in accordance with at least one of the charge amount of the storage battery 41 and the charge / discharge power.
  • the output voltage V1 is not a voltage output from the charge / discharge power conditioner 4 toward the storage battery 41 for charging, but a voltage output toward the power feeding path 92 for discharging.
  • the switching control unit controls the first switch 51 by outputting an off signal to the first switch 51 when the power failure detection unit detects a power failure of the commercial power grid 7 to electrically connect the commercial power feeding path 91. Make it cut.
  • the switching control unit controls the first switch 51 by outputting an ON signal to the first switch 51 to electrically connect the commercial power feeding path 91. To connect.
  • the charge / discharge power conditioner 4 stores a program for the control unit 43 (computer) to execute various functions. That is, the charge / discharge power conditioner 4 stores a program for causing the control unit 43 to function as an output control unit and a switching control unit.
  • the program is stored in advance in the charge / discharge power conditioner 4 when the charge / discharge power conditioner 4 is shipped.
  • a computer readable recording medium having the program recorded thereon is an example of a method for the charge / discharge power conditioner 4 to acquire the program. There is a method to use. In the case of the method using a recording medium, the power conditioner 4 for charging and discharging may be provided with a reading device (not shown) for reading data of the recording medium.
  • Examples of the recording medium include an optical disc (CD-ROM, DVD-ROM) and a memory card.
  • Examples of the reading device include a drive device that reads information of an optical disk, and a memory card reader that reads information of a memory card.
  • the power conditioner 4 for charge / discharge to acquire the program there is a method for downloading the program from another device (for example, a server) using a network.
  • the charge / discharge power conditioner 4 may have a communication function (not shown) for communicating with another device using a network.
  • the charge / discharge power conditioner 4 When the sum of the output power of the solar cell power conditioner 2 and the output power of the fuel cell power conditioner 3 is smaller than the power consumption of the load 8, the charge / discharge power conditioner 4 is a difference between the power consumption and the sum. Discharge. On the other hand, when the sum is larger than the power consumption, the charge / discharge power conditioner 4 charges the difference between the sum and the power consumption.
  • the output power of the solar cell power conditioner 2 changes. Further, when the power consumption of the load 8 is small, the charging power of the charge / discharge power conditioner 4 becomes large. For this reason, the output power of the solar battery power conditioner 2 is specified power so that the storage battery 41 is not charged in a state where the charge power of the power conditioner 4 for charge and discharge is larger than the specified power (including full charge). You need to:
  • the power output of the solar cell power conditioner 2 and the fuel cell power conditioner 3 can be suppressed on the charge / discharge power conditioner 4 side.
  • the solar cell power conditioner 2 is demonstrated, the same may be said of the fuel cell power conditioner 3.
  • the power conditioner 4 for charging and discharging controls the power output of the solar battery power conditioner 2 using the output suppression function of the solar battery power conditioner 2.
  • the solar cell power conditioner 2 detects the effective value of the feed line voltage V2 and the effective value of the feed line voltage V2 rises above the suppression start voltage V12 (see FIG. 3)
  • the solar cell power conditioner Control the output power of the The suppression start voltage V12 is a predetermined value. That is, when the effective value of the feed line voltage V2 exceeds the suppression start voltage V12, the solar cell power conditioner 2 performs the suppression control to suppress the power generation of the solar cell 21.
  • an overvoltage abnormal voltage V13 (see FIG. 3) which is a voltage higher than the suppression start voltage V12 and at which the power output of the solar cell power conditioner 2 is stopped is set.
  • control unit 43 of the charge / discharge power conditioner 4 detects a power failure of the commercial power system 7 by the power failure detection unit, and the commercial power supply path 91 is electrically disconnected by the first switch 51. In this case, when the charge of the storage battery 41 satisfies the normal condition, the effective value of the output voltage V1 is set to the suppression start voltage V12 or less. On the other hand, when charging of storage battery 41 does not satisfy the normal condition, control unit 43 sets the effective value of output voltage V1 larger than suppression start voltage V12 in order to suppress the power output of solar battery power conditioner 2.
  • “When the charge of the storage battery 41 satisfies the normal condition” is when the charge amount of the storage battery 41 is smaller than the prescribed charge amount or when the charge power charged in the storage battery 41 is smaller than the prescribed power.
  • “when the charge of the storage battery 41 does not satisfy the normal condition” is when the charge amount of the storage battery 41 is equal to or greater than the specified charge amount or when the charge power charged to the storage battery 41 is equal to or greater than the specified power is there.
  • control unit 43 of the charge / discharge power conditioner 4 functions as a calculation unit that calculates charging power when charging the storage battery 41.
  • the calculation unit uses the detection results of the current detection unit 462 and the output voltage detection unit 463 to calculate the charging power at the time of charging the storage battery 41.
  • the output control unit performs voltage control so that the effective value of the output voltage V1 is increased at a predetermined first rate of increase when the charging power calculated by the calculating unit becomes equal to or higher than the specified power. Further, when the charging power is equal to or higher than the specified power and the effective value of the output voltage V1 exceeds the switching voltage (second threshold) V14 larger than the suppression start voltage V12, the output control unit performs an effective operation of the output voltage V1. Voltage control is performed to increase the value at a second rate of increase. The second rate of increase is preset to a value that is greater than or equal to zero and less than the first rate of increase. Furthermore, when the charging power is less than the specified power in a state where the effective value of the output voltage V1 is larger than the switching voltage V14, the output control unit performs voltage control so as to reduce the effective value of the output voltage V1.
  • the power conditioner 4 for charging and discharging In order to suppress the power output of the power conditioner 2, the effective value of the output voltage V1 of the charging / discharging power conditioner 4 is increased at a first rate of increase.
  • the effective value of the output voltage V1 reaches the suppression start voltage V12 as it rises (time t2, t10).
  • the solar cell power conditioner 2 starts suppression of the power output with a fixed delay time (suppression start delay T2) (time t4, t12).
  • compression start delay T2 time t4, t12
  • the output voltage increase time T1 should be as short as possible. For this reason, it is preferable that the first increase rate be set as high as possible.
  • the time from when the effective value of output voltage V1 exceeds suppression start voltage V12 to when solar cell power conditioner 2 starts suppression of the power output (suppression start delay T2) is for each solar cell power conditioner 2
  • the variation is large. Therefore, when the power conditioner 4 for charge and discharge continues to increase the effective value of the output voltage V1 at the first rate of increase, the power for charge and discharge before the solar cell power conditioner 2 starts suppressing the power output.
  • the effective value of the output voltage V1 of the conditioner 4 reaches the overvoltage abnormal voltage V13 of the solar battery power conditioner 2, and the solar battery power conditioner 2 stops the power output.
  • the switching voltage (second threshold) V14 is set in advance between the suppression start voltage V12 and the overvoltage abnormal voltage V13.
  • the power conditioner 4 for charging and discharging determines the effective value of the output voltage V1 at a second rising rate lower than the first rising rate. Raise it.
  • the switching voltage V14 is set in consideration of the variation of the suppression start voltage V12. Further, the first increase rate and the second increase rate are set so that the effective value of the output voltage V1 does not become the overvoltage abnormal voltage V13.
  • the solar battery power conditioner 2 suppresses the power output and the generated power P1 of the solar battery 21 becomes equal to or less than the load power P11 (time t5), the charge and discharge is performed so that the effective value of the output voltage V1 becomes the rated voltage V11.
  • the power conditioner 4 gradually lowers the effective value of the output voltage V1 (time t5 to t8).
  • the charge / discharge power conditioner 4 decreases the effective value of the output voltage V1 at a first falling rate until the effective value of the output voltage V1 reaches the switching voltage V14 (time t5 to t6).
  • the charge / discharge power conditioner 4 decreases the effective value of the output voltage V1 at a second falling rate higher than the first falling rate. (Time t6 to t7). At time t8, the solar cell power conditioner 2 ends the suppression of the power output with the suppression end delay T3.
  • the output control unit of the charge / discharge power conditioner 4 changes the effective value of the output voltage V1 by changing the amplitude of the output voltage V1.
  • the output control unit can change the amplitude of the output voltage V1 by adjusting the pulse width of the on time of the switching elements 491 to 494 of the DC / AC bidirectional conversion unit.
  • the output control unit sets the on time of the switching elements 472 and 473 of the DC / DC bidirectional conversion unit 47 so that the output voltage of the DC / DC bidirectional conversion unit 47 becomes higher than the instantaneous value of the output voltage V1. Adjust the pulse width.
  • the broken line in FIG. 4 indicates the output voltage V1 before change, and the solid line in FIG. 4 indicates the output voltage V1 after change.
  • FIG. 5 there is a method of changing the effective value of the output voltage V1 without changing the peak value of the output voltage V1 before and after the change.
  • the peak value of the output voltage V1 after the change is high because the amplitude is increased from the waveform of the broken line in FIG.
  • problems relating to the withstand voltage of the load 8 occur. Therefore, it is necessary not to connect the load device 81 having a withstand voltage lower than the peak value of the output voltage V1 after change.
  • the output control unit of the charge / discharge power conditioner 4 is a sine wave (broken line in FIG. 5) that has an instantaneous value of zero at the peak point of the sine wave (one-dot chain line in FIG. V.
  • the effective value of the output voltage V1 is changed by changing the waveform of the output voltage V1 to a waveform equivalent to the waveform (solid line in FIG. 5) in which the. That is, the waveform of the solid line in FIG. 5 is created by combining the harmonics of the dashed dotted line in FIG. 5 with the sine wave in dashed line in FIG.
  • the output control unit adjusts the pulse width of the on time of the switching elements 491 to 494 of the DC / AC bidirectional conversion unit 48 to make the waveform of the output voltage V1 the waveform of the solid line in FIG. be able to.
  • the output control unit adjusts the pulse width of the on time of the switching elements 491 to 494 of the DC / AC bidirectional conversion unit 48 to make the waveform of the output voltage V1 the waveform of the solid line in FIG. be able to.
  • the two waveforms of the dashed dotted line to be superimposed are also positive waveforms, and the base sine wave
  • the two superimposed dashed-dotted waveforms also have negative waveforms.
  • the output control unit of the charge / discharge power conditioner 4 changes the waveform of the output voltage V1 into a waveform equivalent to a waveform in which the second harmonic is superimposed on the fundamental wave as a sine wave.
  • FIG. 6 there is a method of changing the effective value by applying a gain G which is different depending on the phase of the sine wave to the sine wave to generate a voltage of a waveform generated.
  • the output control unit of the charge / discharge power conditioner 4 has a waveform equivalent to a waveform (solid line in FIG. 6) obtained by amplifying the sine wave (dotted line in FIG. 6) with a gain G different depending on the phase of the sine wave.
  • the effective value of the output voltage V1 is changed by changing the waveform of the output voltage V1.
  • the output control unit adjusts the pulse width of the on time of the switching elements 491 to 494 of the DC / AC bidirectional conversion unit 48 to make the waveform of the output voltage V1 the waveform of the solid line in FIG. be able to.
  • the output control unit adjusts the pulse width of the on time of the switching elements 491 to 494 of the DC / AC bidirectional conversion unit 48 to make the waveform of the output voltage V1 the waveform of the solid line in FIG. be able to.
  • the power supply system 1 performs an interconnection operation with the commercial power system 7 at a normal time when the commercial power system 7 supplies commercial power (S1).
  • the power supply system 1 continues the interconnection operation unless a power failure of the commercial power system 7 is detected (S2).
  • the solar battery power conditioner 2, the fuel cell power conditioner 3, and the charge / discharge power conditioner 4 detect a power failure of the commercial power system 7 by the power failure detection function System operation (power output) is stopped (S3).
  • the first switch 51 is turned off to electrically disconnect the commercial power feeding path 91 by the off signal from the charge / discharge power conditioner 4, and the power supply system 1 is switched to the stand-alone operation mode (S4), The independent operation is performed (S5).
  • the power conditioner 4 for charging and discharging outputs an AC voltage of the same frequency and amplitude as the AC voltage of the commercial power system 7 at the normal time.
  • the solar cell power conditioner 2 and the fuel cell power conditioner 3 resume the operation as in the normal state.
  • the power supply system 1 performs suppression control according to the charge state of the storage battery 41 (S6).
  • step S7 the power supply system 1 stops the independent operation (electric power output) (S8), and switches from the independent operation to the grid-connected operation (S9).
  • step S7 the process returns to step S6 to continue suppression control.
  • step S6 when the charge power of the storage battery 41 exceeds the set value (S21), until the effective value of the output voltage V1 of the charge / discharge power conditioner 4 reaches the switching voltage V14 (S22), the charge / discharge power conditioner 4 raises the effective value of the output voltage V1 at the first rate of increase (S23). When the effective value of the output voltage V1 exceeds the switching voltage V14 (S22), the effective value of the output voltage V1 is increased at a second increase rate ( ⁇ first increase rate) (S24).
  • step S21 when the charge power is equal to or less than the set value in step S21, when the effective value of output voltage V1 of charge / discharge power conditioner 4 is larger than rated voltage V11 and switching voltage V14 (S25, S26) The conditioner 4 lowers the effective value of the output voltage V1 at the first rate of decrease (S27). If the effective value of the output voltage V1 is less than or equal to the switching voltage V14 in step S26, the effective value of the output voltage V1 is decreased at a second decrease rate (> first decrease rate) (S28). If the effective value of the output voltage V1 is less than or equal to the rated voltage V11 in step S25, the operation of the suppression control is ended.
  • the power conditioner 4 for charge and discharge in the present embodiment described above controls the output voltage V1 on the feed path 92 side so that the feed path voltage V2 becomes a predetermined voltage when the commercial power grid 7 fails.
  • the power conditioner (the solar battery power conditioner 2 and the fuel cell power conditioner 3) for power generation is supplied with the power feeding path 92 as in the case where the commercial power system 7 does not have a power failure. Power can be output.
  • the power generation device (solar cell does not need to be operated manually at the time of power failure of the commercial power system 7. 21, the power of the fuel cell can be used.
  • the power conditioner 4 for charge and discharge suppresses the effective value of the output voltage V1 and suppresses the start voltage (threshold value) V12. Make it bigger.
  • the effective value of the feed line voltage V2 can be made larger than the suppression start voltage V12, so the output power of the power conditioner for power generation can be made smaller.
  • Charging of the storage battery 41 can be performed under normal conditions.
  • the effective value of the output voltage V1 of the charging / discharging power conditioner 4 exceeds the switching voltage (second threshold) V14, the effective value of the output voltage V1 Lower the rate of rise of
  • the effective value of the feed line voltage V2 is power generation It is possible to reduce the output power of the power conditioner for power generation without reaching the over voltage abnormal voltage (abnormal stop value) V13 of the power conditioner.
  • the power supply system 1 of the present embodiment by changing the amplitude of the output voltage V1 of the charge / discharge power conditioner 4, the effective value of the output voltage V1 can be easily changed.
  • the waveform of the output voltage V1 is changed to a waveform equivalent to a waveform obtained by superimposing a wave whose instantaneous value becomes zero at a peak point of the sine wave on a sine wave.
  • the effective value of the output voltage V1 can be increased while keeping the peak value of the output voltage V1 constant.
  • the output voltage V1 can be obtained while keeping the peak value of the output voltage V1 constant. Only the effective value can be increased.
  • the waveform of the output voltage V1 is changed to a waveform equivalent to a waveform obtained by amplifying a sine wave with a gain G which varies depending on the phase of the sine wave.
  • the power supply system 1 according to the second embodiment relates to the first embodiment in that voltage control is performed without changing the effective value of the output voltage V1 when the charge power is greater than the specified power and the change direction is negative. It differs from the power supply system 1.
  • symbol is attached
  • the control unit 43 of the charge / discharge power conditioner 4 of the present embodiment functions as a power change detection unit that detects the change direction of the increase and decrease of the charge power. Further, the control unit 43 according to the present embodiment functions as an output control unit when the charge power is detected to be decreasing by the power change detection unit when the charge power is equal to or higher than the specified power. Is maintained at the detection point value. Description of functions similar to those of the control unit 43 of the first embodiment will be omitted.
  • the speed of output suppression of the solar cell power conditioner 2 is greatly different for each product. For this reason, even if the solar battery power conditioner 2 starts suppression so that the output power of the solar battery power conditioner 2 becomes equal to or less than the load power P11, the time until suppression is applied (suppression start delay T2) varies widely . Thus, it is conceivable that the charge / discharge power conditioner 4 raises the effective value of the output voltage V1 to the overvoltage abnormal voltage V13 at the suppression start delay T2.
  • the power conditioner 4 for charging and discharging changes the rate of increase of the effective value of the output voltage V1.
  • An example of the rate of increase of the effective value of the output voltage V1 of the charge / discharge power conditioner 4 will be shown below.
  • the solar cell power conditioner 2 is demonstrated, the same may be said of the fuel cell power conditioner 3.
  • the output power of the solar battery power conditioner 2 (generated power P1 of the solar battery 21) is larger than the load power P11, and the generated power P1 is increasing, ie, the charging power of the storage battery 41 is increasing.
  • the switching voltage V14 is smaller than the switching voltage V14 (time t21 to t23 and t28 to t30 in FIG. 9)
  • the effective value of the output voltage V1 is set as the first increase rate.
  • the charging power is increasing and the effective value of the output voltage V1 is larger than the switching voltage V14 (time t23 to t24, t30 to t31 And the effective value of the output voltage V1 is a second rate of increase.
  • the generated power P1 is larger than the load power P11 and the generated power P1 is decreasing, ie, the charging power is decreasing and the effective value of the output voltage V1 is larger than the switching voltage V14 (time t24 to t25, t31 to t32 And the effective value of the output voltage V1 is the third rate of increase.
  • the effective value of the output voltage is increased by a fourth Rate.
  • the solar battery power conditioner 2 suppresses the power output and the generated power P1 of the solar battery 21 becomes equal to or less than the load power P11 (time t25, t32), charging is performed so that the effective value of the output voltage V1 becomes the rated voltage V11.
  • the discharge power conditioner 4 gradually lowers the effective value of the output voltage V1 (time t25 to t27).
  • the charge / discharge power conditioner 4 decreases the effective value of the output voltage V1 at a first falling rate until the effective value of the output voltage V1 becomes the switching voltage V14 (time t25 to t26, t32 to t33).
  • power conditioner 4 for charging and discharging determines the effective value of output voltage V1 at a second falling rate higher than the first falling rate. It is lowered (at time t26 to t27). At time t27, the solar cell power conditioner 2 ends the suppression of the power output with the suppression end delay T3.
  • the power conditioner 4 for charging and discharging The effective value of the output voltage V1 is lowered at a falling rate (S51).
  • the charge / discharge power conditioner 4 decreases the effective value of the output voltage V1 at the second decrease rate (S52). If the effective value of the output voltage V1 is less than or equal to the rated voltage V11 in step S49, the operation of the suppression control is ended.
  • the power conditioner the solar battery power conditioner 2 or the fuel cell power conditioner 3 for power generation has started output suppression is determined by the charge / discharge power conditioner. It is possible for the driver 4 to make judgment in the change direction of the charging power, and to make the effective value of the output voltage V1 constant according to the judgment result. As a result, in the power supply system 1 of the present embodiment, the probability that the feed line voltage V2 reaches the overvoltage abnormal voltage (abnormal stop value) V13 can be reduced.
  • the control unit 43 of the charge / discharge power conditioner 4 of the present embodiment functions as a calculation unit and a stop control unit described later.
  • the calculation unit and the stop control unit will be described below with reference to FIGS.
  • the calculation unit calculates charging power P2 when charging storage battery 41.
  • the stop control unit charges / discharges from the solar cell power conditioner 2 and the fuel cell power conditioner 3 Power output to the power conditioner 4 is stopped.
  • the stop control unit electrically connects the solar cell power conditioner 2, the fuel cell power conditioner 3, and the feeding path 92 when the charging power P2 increases above the change rate and becomes the specified power or more.
  • the second switch 52 and the third switch 53 are controlled to disconnect.
  • the change in output power due to sunshine of the solar battery power conditioner 2 is a relatively gradual output change.
  • the rise in output power depends on the change in sunshine and the tracking speed of the maximum power tracking control (MPPT control) of the solar battery power conditioner 2. It is possible to control the charging power P2 of the
  • the fluctuation of the load device 81 causes a very sharp fluctuation of the charging power P2 of the charging / discharging power conditioner 4 (time t41 to t44).
  • the charging power P2 of the charge / discharge power conditioner 4 suddenly increases by 1 kW (time t43). Even if the output suppression function of the solar cell power conditioner 2 is operated in this state, the charge / discharge power conditioner 4 will be in the overcharged state until the suppression of 1 kW works.
  • the power conditioner 4 for charging and discharging detects the steep charging power P 2, and when the charging power P 2 exceeds the allowable charging power P 21, the second to disconnect the solar battery power conditioner 2 from the feed path 92 promptly.
  • the off signal is output to the switch 52 of (1) (time t42 to t45).
  • step S63 If the increase speed of the charging power P2 exceeds the set value in step S63, the second switch 52 for disconnecting the solar cell 21 is turned off (S67).
  • the charge / discharge power conditioner 4 sets the third rate of increase ( ⁇ second The effective value of the output voltage V1 is increased at a rising rate) (S69).
  • the charge / discharge power conditioner 4 raises the effective value of the output voltage V1 at the fourth rate of increase ( ⁇ the first rate of increase). (S70).
  • the charge / discharge power conditioner 4 sets the first value when the effective value of the output voltage V1 is greater than the rated voltage V11 and the switching voltage V14 (S71, S72). The effective value of the output voltage V1 is lowered at a falling rate of (S73). When the effective value of the output voltage V1 is equal to or less than the switching voltage V14 (S72), the charge / discharge power conditioner 4 decreases the effective value of the output voltage V1 at the second decrease rate (S74). If the effective value of the output voltage V1 is less than or equal to the rated voltage V11 in step S71, the operation of the suppression control is ended.
  • the power conditioner 4 for charge and discharge detects the sharp charge power P2 when the sharp change of the charge power P2 occurs, and the power for power generation is promptly generated. It is possible to stop the power output from the conditioner (solar cell power conditioner 2, fuel cell power conditioner 3) to the charge / discharge power conditioner 4.
  • the charging / discharging power conditioner 4 functions as a power generation switching unit (second switch By controlling the second switch 52 and the third switch 53), the power output from the power conditioner for power generation to the power conditioner 4 for charging and discharging can be reliably and easily stopped.
  • the solar cell power conditioner 2 and the fuel cell power conditioner 3 of the present embodiment stop the power output when the effective value of the feed line voltage V2 exceeds the predetermined overvoltage abnormal voltage (abnormal stop value) V13. It has an abnormal stop function. Descriptions of functions similar to those of the solar cell power conditioner 2 and the fuel cell power conditioner 3 according to the third embodiment will be omitted.
  • the stop control unit of the control unit 43 of the power conditioner 4 for charge and discharge according to the present embodiment, when the charge power P2 increases by a predetermined change rate or more and becomes equal to or more than the allowable charge power (specified power) P21,
  • the output control unit is controlled to make the effective value of the output voltage V1 larger than the overvoltage abnormal voltage V13.
  • the power output from the solar cell power conditioner 2 and the fuel cell power conditioner 3 is stopped.
  • description is abbreviate
  • the change in output power due to sunshine of the solar battery power conditioner 2 is a relatively gradual output change.
  • the rise in output power depends on the change in sunshine and the tracking speed of the maximum power tracking control (MPPT control) of the solar battery power conditioner 2. It is possible to control the charging power P2 of the
  • the fluctuation of the load device 81 causes a very sharp fluctuation of the charging power P2 of the charging / discharging power conditioner 4 (time t61 to t63).
  • the charging power P2 of the charge / discharge power conditioner 4 suddenly increases by 1 kW (time t62). Even if the output suppression function of the solar cell power conditioner 2 is operated in this state, the charge / discharge power conditioner 4 will be in the overcharged state until the suppression of 1 kW works.
  • the power conditioner 4 for charging and discharging detects the steep charging power P2, and when the charging power P2 exceeds the allowable charging power P21, the power for charging and discharging is used to stop the solar battery power conditioner 2 promptly.
  • the effective value of the output voltage V1 of the conditioner 4 is raised to the overvoltage abnormal voltage V13 (time t61 to t62). At time t64 after time t63, the output voltage V1 is returned to the rated voltage V11.
  • FIGS. First, the case where the charge power P2 exceeds the set value (S81) and the charge power P2 is increasing (S82) and the increase speed of the charge power P2 is equal to or less than the set value (S83) will be described.
  • the charge / discharge power conditioner 4 raises the effective value of the output voltage V1 at the first rate of increase (S85).
  • the charge / discharge power conditioner 4 increases the effective value of the output voltage V1 at a second rate of increase ( ⁇ first rate of increase) S86).
  • step S83 If the increase speed of the charging power P2 exceeds the set value in step S83, the process proceeds to step S85.
  • the charge / discharge power conditioner 4 If the charging power P2 is not increasing at step S82, and the effective value of the output voltage V1 is larger than the switching voltage V14 (S87), the charge / discharge power conditioner 4 generates the third rising rate ( ⁇ second The effective value of the output voltage V1 is increased at a rising rate) (S88). When the effective value of the output voltage V1 is equal to or less than the switching voltage V14 (S87), the charge / discharge power conditioner 4 raises the effective value of the output voltage V1 at the fourth rate of increase ( ⁇ first rate of increase). (S89).
  • the charging / discharging power conditioner 4 sets the first value when the effective value of the output voltage V1 is larger than the rated voltage V11 and the switching voltage V14 (S90, S91).
  • the effective value of the output voltage V1 is lowered at the rate of decrease of (S92).
  • the charge / discharge power conditioner 4 decreases the effective value of the output voltage V1 at the second decrease rate (S93). If the effective value of the output voltage V1 is less than or equal to the rated voltage V11 in step S90, the operation of the suppression control is ended.
  • the effective value of the output voltage V1 of the charge / discharge power conditioner 4 is used as a power conditioner for generating power (solar battery power conditioner 2. Make it larger than the overvoltage abnormal voltage (abnormal stop value) V13 of the fuel cell power conditioner 3).
  • the effective value of the feed line voltage V2 can be made larger than the overvoltage abnormal voltage V13, so that the power output of the power conditioner for power generation can be stopped reliably and easily. it can.
  • the first switch (switching unit) 51, the second switch (power generation switching unit) 52, and the third switch (power generation switching unit) 53 are the same as in each embodiment. It may be provided collectively in one switch board 5, and may be provided separately.
  • the power generation device and the power conditioner for power generation may be single or plural. Also, there may be a plurality of types of power generation devices.
  • the distribution board 6 is located in front of the load 8 on the feed path 92, but the power conditioner for generating power (solar cell power conditioner 2, fuel cell power conditioner 3) and charging / discharging power
  • the conditioner 4 may be directly connected to the distribution board 6 or may be connected to the distribution board 6 via the switching board 5.

Abstract

 発電用パワーコンディショナが通信機能を有するか否かにかかわらず、商用電力系統の停電時において手動操作を必要とせずに発電装置からの電力を利用する。電力供給システムは、太陽電池パワーコンディショナと、充放電用パワーコンディショナと、第1のスイッチと、検出部とを備える。太陽電池パワーコンディショナは、給電路に所定電圧が印加されている場合、給電路へ電力を出力し、給電路に所定電圧が印加されていない場合、給電路への電力出力を停止する。第1のスイッチは、商用電力系統が停電した場合、商用給電路を電気的に切断する。充放電用パワーコンディショナの制御部は、第1のスイッチにより商用給電路が電気的に切断された場合に、給電路の電圧が所定電圧になるように充放電用パワーコンディショナから放電用に給電路側に向かって出力される出力電圧の実効値を変化させる。

Description

電力供給システムおよびそれに用いられる充放電用パワーコンディショナ
 本発明は、負荷に電力を供給する電力供給システムおよびそれに用いられる充放電用パワーコンディショナに関する。
 従来から、太陽電池と太陽電池パワーコンディショナとを備える太陽光発電システムが知られている(例えば日本国特許公開9-135577号公報参照)。
 この太陽光発電システムに用いられる太陽電池パワーコンディショナは、商用電力系統と連系した連系運転を行う一方、商用電力系統が停電したときには、商用電力系統から独立した自立運転を行うことができる。これにより、太陽電池パワーコンディショナは、商用電力系統が停電したときであっても、負荷に電力を供給することができる。
 上記のような連系運転と自立運転とを行うために、太陽電池パワーコンディショナは、連系運転時に電力供給したい負荷を接続するための連系出力端子と、自立運転時に電力供給したい負荷を接続するための自立出力端子とを備えている。
 しかしながら、従来の太陽電池パワーコンディショナは、連系出力端子と自立出力端子とが別個の端子であり、商用電力系統の停電が発生した際に、連系運転モードから自立運転モードへ切り替えるために所定の手動操作が必要であった。すなわち、上記の手動操作がなければ、従来の太陽電池パワーコンディショナでは、商用電力系統から独立した自立運転を開始することができず、太陽電池で発電された電力を有効利用することができなかった。
 このような問題を解決するために、外部から通信によって太陽電池パワーコンディショナの電力出力を制御することが考えられる。
 ところが、外部から太陽電池パワーコンディショナと通信する場合、通信機能を有する太陽電池パワーコンディショナにしか対応することができない。
 そこで、本発明の目的は、発電用パワーコンディショナが通信機能を有するか否かにかかわらず、商用電力系統の停電時において手動操作を必要とせずに発電装置からの電力を利用することができる電力供給システムおよびそれに用いられる充放電用パワーコンディショナを提供することにある。
 本発明の電力供給システムは、発電装置の発電を制御する発電用パワーコンディショナと、蓄電池の充放電を制御する充放電用パワーコンディショナと、商用電力系統から負荷へ給電するための商用給電路に挿入された切替部と、前記商用電力系統の復電を検出する検出部とを備え、前記発電用パワーコンディショナは、当該発電用パワーコンディショナおよび前記充放電用パワーコンディショナから前記負荷へ給電するための給電路に所定電圧が印加されている場合に前記給電路へ電力を出力する機能と、前記給電路に前記所定電圧が印加されていない場合に前記給電路への電力出力を停止する機能とを有し、前記切替部は、前記商用電力系統が停電した場合に前記商用給電路を電気的に切断し、前記検出部により前記商用電力系統の復電が検出された場合に前記商用給電路を電気的に接続し、前記充放電用パワーコンディショナは、前記給電路への電力出力を制御する出力制御部と、前記商用電力系統の停電を検出する停電検出部とを有し、前記出力制御部は、前記停電検出部により前記商用電力系統の停電が検出されて、前記切替部により前記商用給電路が電気的に切断された場合に、前記給電路の電圧が前記所定電圧になるように前記充放電用パワーコンディショナから放電用に前記給電路側に向かって出力される出力電圧の実効値を変化させることを特徴とする。
 この電力供給システムにおいて、前記発電用パワーコンディショナは、前記給電路の電圧の実効値が予め決められたしきい値より大きい場合に、前記給電路への電力出力を抑制する機能を有し、前記充放電用パワーコンディショナの前記出力制御部は、前記停電検出部により前記商用電力系統の停電が検出されて、前記切替部により前記商用給電路が電気的に切断された場合、前記蓄電池の充電が正常な条件を満たすとき、前記出力電圧の実効値を前記しきい値以下とし、前記蓄電池の充電が正常な条件を満たさないとき、前記出力電圧の実効値を前記しきい値より大きくすることが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナは、前記蓄電池を充電する際の充電電力を算出する算出部を有し、前記出力制御部は、前記算出部で算出された前記充電電力が規定電力以上になると、前記出力電圧の実効値を予め決められた第1の上昇率で上昇させ、前記充電電力が前記規定電力以上であって、前記出力電圧の実効値が前記しきい値より大きい第2のしきい値を超えると、前記出力電圧の実効値をゼロ以上かつ前記第1の上昇率より低い第2の上昇率で上昇させ、前記出力電圧の実効値が前記第2のしきい値より大きい状態で前記充電電力が前記規定電力未満になると、前記出力電圧の実効値を減少させることが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナは、前記充電電力の増減の変化方向を検出する電力変化検出部を有し、前記出力制御部は、前記充電電力が前記規定電力以上の状態で、前記電力変化検出部により前記充電電力が減少方向であると検出された場合、前記出力電圧の実効値を検出時点の値に維持することが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナは、前記蓄電池を充電する際の充電電力を算出する算出部と、前記算出部で算出された前記充電電力が予め決められた変化率以上で増加して規定電力以上になった場合に前記発電用パワーコンディショナから前記充放電用パワーコンディショナへの電力出力を停止させる停止制御部とを有することが好ましい。
 この電力供給システムにおいて、前記発電用パワーコンディショナと前記給電路との間に挿入された発電用切替部を備え、前記充放電用パワーコンディショナの前記停止制御部は、前記充電電力が前記変化率以上で増加して前記規定電力以上になった場合、前記発電用パワーコンディショナと前記給電路とを電気的に切断するように前記発電用切替部を制御することが好ましい。
 この電力供給システムにおいて、前記発電用パワーコンディショナは、前記給電路の電圧の実効値が予め決められた異常停止値を超えた場合に電力出力を停止する機能を有し、前記充放電用パワーコンディショナの前記停止制御部は、前記充電電力が前記変化率以上で増加して前記規定電力以上になった場合、前記出力電圧の実効値を前記異常停止値より大きくするように前記出力制御部を制御することが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナの前記出力制御部は、前記出力電圧の振幅を変化させることが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナの前記出力制御部は、正弦波に当該正弦波のピーク点で瞬時値がゼロになる波を重畳した波形と等価な波形に前記出力電圧の波形を変化させることによって、前記出力電圧の実効値を変化させることが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナの前記出力制御部は、前記正弦波としての基本波に2倍高調波を重畳した波形と等価な波形に前記出力電圧の波形を変化させることによって、前記出力電圧の実効値を変化させることが好ましい。
 この電力供給システムにおいて、前記充放電用パワーコンディショナの前記出力制御部は、正弦波を当該正弦波の位相によって異なるゲインで増幅した波形と等価な波形に前記出力電圧の波形を変化させることによって、前記出力電圧の実効値を変化させることが好ましい。
 本発明の充放電用パワーコンディショナは、電力供給システムに用いられる。
 本発明によれば、発電用パワーコンディショナが通信機能を有するか否かにかかわらず、商用電力系統の停電時において、手動操作を必要とせずに発電装置からの電力を利用することができる。
 本発明の好ましい実施形態をさらに詳細に記述する。本発明の他の特徴および利点は、以下の詳細な記述および添付図面に関連して一層良く理解されるものである。
実施形態1に係る電力供給システムの構成を示す概略図である。 実施形態1に係る電力供給システムの要部の構成を示す回路図である。 実施形態1に係る電力供給システムの動作を説明する説明図である。 実施形態1に係る電力供給システムの動作を説明する説明図である。 実施形態1に係る電力供給システムの動作を説明する説明図である。 実施形態1に係る電力供給システムの動作を説明する説明図である。 実施形態1に係る電力供給システムの動作を示すフローチャートである。 実施形態1に係る電力供給システムの動作を示すフローチャートである。 実施形態2に係る電力供給システムの動作を説明する説明図である。 実施形態2に係る電力供給システムの動作を示すフローチャートである。 実施形態3に係る電力供給システムの要部の構成を示す回路図である。 実施形態3に係る電力供給システムの動作を説明する説明図である。 実施形態3に係る電力供給システムの動作を示すフローチャートである。 実施形態4に係る電力供給システムの動作を説明する説明図である。 実施形態4に係る電力供給システムの動作を示すフローチャートである。
 (実施形態1)
 実施形態1に係る電力供給システム1は、図1に示すように、太陽電池(発電装置)21の発電を制御する太陽電池パワーコンディショナ(発電用パワーコンディショナ)2と、燃料電池(発電装置)の発電を制御する燃料電池パワーコンディショナ(発電用パワーコンディショナ)3とを備えている。また、電力供給システム1は、蓄電池41の充放電を制御する充放電用パワーコンディショナ4を備えている。さらに、電力供給システム1は、商用電力系統7から負荷8へ給電するための商用給電路91に挿入された第1のスイッチ(切替部)51を含む切替盤5と、電力を負荷8に分配する分電盤6とを備えている。太陽電池パワーコンディショナ2、燃料電池パワーコンディショナ3および充放電用パワーコンディショナ4は、切替盤5を介して分電盤6および商用電力系統7に電気的に接続されている。
 この電力供給システム1は、商用電力系統7の停電時に太陽電池パワーコンディショナ2と燃料電池パワーコンディショナ3と充放電用パワーコンディショナ4とが一旦停止した後、充放電用パワーコンディショナ4によって太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3を再稼動させるシステムである。
 負荷8は、例えば住宅内に設置された複数(図1では4台)の負荷機器81,81……から構成されている。各負荷機器81は、例えばテレビや電子レンジ、冷蔵庫、照明器具などの家電機器である。各負荷機器81は、分電盤6に直接接続されていたり、コンセント(図示せず)を介して分電盤6に接続されていたりする。
 分電盤6は、図示しないが、主幹ブレーカと、複数台の分岐ブレーカとを備えている。この分電盤6は、負荷機器81,81,……に交流電力を分配する。主幹ブレーカは、太陽電池パワーコンディショナ2と燃料電池パワーコンディショナ3と充放電用パワーコンディショナ4と商用電力系統7とからの交流電力を各分岐ブレーカに分配する。分岐ブレーカは、自己に接続されている負荷機器81へ主幹ブレーカからの電力を供給する。
 太陽電池21は、例えば住戸の屋根などに設置されており、太陽光発電を行う。すなわち、太陽電池21は、太陽光エネルギーを利用して直流電力を生成する。なお、本実施形態の「太陽電池」には、単一セルの太陽電池(太陽電池セル)だけではなく、複数の太陽電池セルが直列または並列に配列された太陽電池モジュールや、複数の太陽電池モジュールが直列または並列に配列された太陽電池アレイも含まれる。太陽電池セルは、太陽電池の機能を持つ最小単位の構成である。太陽電池モジュールは、複数の太陽電池セルが配列された状態で強化ガラスなどによって覆われてパッケージ化された構成である。太陽電池アレイは、屋根などに設けられた架台に複数の太陽電池モジュールが配列された構成である。
 太陽電池パワーコンディショナ2は、図2に示すように、電力変換部22と、制御部23と、一対の開閉器24,24とを備えている。また、太陽電池パワーコンディショナ2は、電圧検出部251と、電流検出部252と、一対の出力端子部26,26とを備えている。この太陽電池パワーコンディショナ2は、太陽電池21で生成された直流電力(例えばDC100V~250V)を商用電力系統7(図1参照)との系統連系に適合した交流電力(例えば100Vまたは200V)に変換し、この交流電力を分電盤6(図1参照)へ出力する。また、太陽電池パワーコンディショナ2は、太陽電池21の発電電力を制御する。
 電力変換部22は、DC/DC変換部27と、DC/AC変換部28とを備えている。この電力変換部22は、制御部23の指示に従って動作する。
 DC/DC変換部27は、インダクタ271と、スイッチング素子272と、ダイオード273と、コンデンサ274と、ダイオード275とを備えている。スイッチング素子272は、例えば絶縁ゲート型バイポーラトランジスタ(Insulated Gate Bipolar Transistor:IGBT、以下「IGBT」という)であり、制御部23からの制御信号に従ってオンオフを切り替えている。
 DC/DC変換部27は、太陽電池21から入力される直流電圧を、DC/AC変換部28に適する直流電圧に変換する。具体的には、まず、制御部23からの制御信号によってスイッチング素子272がオンになると、太陽電池21からの直流電流の経路は、インダクタ271、スイッチング素子272の経路となる。このとき、インダクタ271に電磁エネルギーが蓄えられる。その後、制御部23からの制御信号によってスイッチング素子272がオフになると、インダクタ271に逆起電力が発生し、太陽電池21からの直流電圧に上記逆起電力が加わり、太陽電池21からの直流電圧より大きな直流電圧をコンデンサ274側へ出力する。DC/DC変換部27は、コンデンサ274により平滑化された直流電圧をDC/AC変換部28に出力する。
 DC/AC変換部28は、スイッチング回路281と、フィルタ回路282とを備えている。このDC/AC変換部28は、スイッチング回路281にてDC/DC変換部27からの直流電圧を交流電圧に変換し、フィルタ回路282にてスイッチング回路281からの交流電圧を平滑化する。
 スイッチング回路281は、4つのスイッチング素子291~294と、4つのダイオード295,295,……とを備えている。スイッチング回路281は、4つのスイッチング素子291~294で構成されるフルブリッジ回路である。スイッチング素子291~294は、例えばIGBTであり、制御部23からの制御信号に従ってオンオフを切り替える。スイッチング回路281は、スイッチング素子291~294のオンオフの切替によって、DC/DC変換部27からの直流電圧を交流電圧に変換する。上記交流電圧はフィルタ回路282に出力される。
 フィルタ回路282は、インダクタ296と、コンデンサ297と、インダクタ298とを備えている。
 制御部23は、コンピュータに搭載されたCPU(マイクロプロセッサ(MPU:Micro Processing Unit))を主構成要素とし、プログラムに従って動作することによって、電力変換部22のDC/DC変換部27およびDC/AC変換部28を制御する。この際、制御部23は、商用電力系統7との協調制御を行う。
 制御部23は、太陽電池パワーコンディショナ2および充放電用パワーコンディショナ4から負荷8(図1参照)へ給電するための給電路92に所定電圧が印加されている場合に給電路92へ電力を出力する電力出力機能を有している。また、制御部23は、給電路92に所定電圧が印加されていない場合に商用電力系統7の停電を検出する停電検出機能を有している。さらに、制御部23は、停電検出機能により商用電力系統7の停電が検出された場合に給電路92への電力出力を停止する単独運転防止機能を有している。
 制御部23の停電検出機能は、商用電力系統7の停電時に太陽電池パワーコンディショナ2が単独で運転していることを検出する単独運転検出機能である。単独運転検出機能に用いられる検出方式としては、受動的方式と能動的方式とがある。受動的方式としては、電圧位相跳躍検出方式や3次高調波電圧歪急増検出方式、周波数変化率検出方式などがある。能動的方式としては、周波数シフト方式やスリップモード周波数シフト方式、有効電力変動方式、無効電力変動方式、負荷変動方式などがある。
 なお、太陽電池パワーコンディショナ2は、制御部23(コンピュータ)が各種の機能を実行するためのプログラムを格納している。上記プログラムは、太陽電池パワーコンディショナ2の出荷時に太陽電池パワーコンディショナ2に予め格納されている。ただし、太陽電池パワーコンディショナ2が上記プログラムを出荷後に取得する場合、太陽電池パワーコンディショナ2が上記プログラムを取得する手法の一例としては、上記プログラムを記録したコンピュータ読み取り可能な記録媒体を用いる手法がある。記録媒体を用いる手法の場合、太陽電池パワーコンディショナ2は、記録媒体のデータを読み取るための読取装置(図示せず)を備えていればよい。記録媒体としては、例えば光ディスク(CD-ROM、DVD-ROM)やメモリカードなどがある。読取装置としては、光ディスクの情報を読み出すドライブ装置や、メモリカードの情報を読み出すメモリカードリーダなどがある。また、太陽電池パワーコンディショナ2が上記プログラムを取得する他の手法としては、ネットワークを用いて上記プログラムを他の装置(例えばサーバ)からダウンロードする手法がある。上記プログラムをダウンロードする手法の場合、太陽電池パワーコンディショナ2は、ネットワークを用いて他の装置と通信するための通信機能(図示せず)を有していればよい。
 また、太陽電池パワーコンディショナ2は、図2に示す回路構成に限らず、他の周知な回路構成であってもよい。
 図1に示す燃料電池パワーコンディショナ3は、燃料電池(図示せず)の発電すなわち燃料電池の発電電力を制御する。また、燃料電池パワーコンディショナ3は、燃料電池で生成された直流電力を商用電力系統7との系統連系に適合した交流電力(例えば100Vまたは200V)に変換し、この交流電力を分電盤6へ出力する。燃料電池パワーコンディショナ3は、太陽電池パワーコンディショナ2と同様に、給電路92に所定電圧が印加されている場合に給電路92へ電力を出力する電力出力機能を有している。また、燃料電池パワーコンディショナ3は、給電路92に所定電圧が印加されていない場合に商用電力系統7の停電を検出する停電検出機能を有している。さらに、燃料電池パワーコンディショナ3は、停電検出機能により商用電力系統7の停電が検出された場合に給電路92への電力出力を停止する単独運転防止機能を有している。なお、燃料電池パワーコンディショナ3は、周知の構成であるから、説明を省略する。また、燃料電池パワーコンディショナ3の停電検出機能は、商用電力系統7の停電時に燃料電池パワーコンディショナ3が単独で運転していることを検出する単独運転検出機能である。燃料電池パワーコンディショナ3の単独運転検出機能に用いられる検出方式は、太陽電池パワーコンディショナ2と同様の方式を採用することができるが、太陽電池パワーコンディショナ2と同一の方式である必要はない。
 切替盤5は、商用給電路91に挿入された第1のスイッチ(切替部)51と、商用電力系統7の復電を検出する検出部54とを備えている。また、切替盤5は、太陽電池パワーコンディショナ2と給電路92との間に挿入された第2のスイッチ(発電用切替部)52と、燃料電池パワーコンディショナ3と給電路92との間に挿入された第3のスイッチ(発電用切替部)53とを備えている。
 検出部54は、商用電力系統7と第1のスイッチ51との間の商用給電路91上に設けられており、商用給電路91の電圧を計測することによって、商用電力系統7の復電を検出する。
 第1のスイッチ51は、商用電力系統7が停電した場合、オフになって商用給電路91を電気的に切断する。一方、検出部54により商用電力系統7の復電が検出された場合、第1のスイッチ51は、オンになって商用給電路91を電気的に接続する。すなわち、第1のスイッチ51は、通常時(非停電時)にオン状態である一方、停電時にはオフ状態になる。
 第2のスイッチ52は、太陽電池パワーコンディショナ2と給電路92との間に挿入されて設けられている。商用電力系統7が停電した場合、第2のスイッチ52は、オフになって太陽電池パワーコンディショナ2と給電路92との間を電気的に切断する。すなわち、第2のスイッチ52は、通常時(非停電時)にオン状態である一方、停電時にはオフ状態になる。
 第3のスイッチ53は、燃料電池パワーコンディショナ3と給電路92との間に挿入されて設けられている。商用電力系統7が停電した場合、第3のスイッチ53は、オフになって燃料電池パワーコンディショナ3と給電路92との間を電気的に切断する。すなわち、第3のスイッチ53は、通常時(非停電時)にオン状態である一方、停電時にはオフ状態になる。
 蓄電池41は、例えばニッケル水素電池やリチウムイオン電池、鉛蓄電池などであり、太陽電池21の発電電力、燃料電池の発電電力および商用電力系統7の商用電力を蓄電することができる。
 充放電用パワーコンディショナ4は、図2に示すように、電力変換部42と、制御部43と、一対の開閉器44,44と、一対の出力端子部45,45とを備えている。また、充放電用パワーコンディショナ4は、満充電検出部461と、電流検出部462と、出力電圧検出部463とを備えている。この充放電用パワーコンディショナ4は、蓄電池41の充電時では、分電盤6(図1参照)側からの交流電圧を、蓄電池41に適合した直流電圧に変換し、この直流電圧を蓄電池41へ出力する。一方、蓄電池41の放電時では、充放電用パワーコンディショナ4は、蓄電池41の直流電圧を、商用電力系統7(図1参照)との系統連系に適合した交流電圧に変換し、この交流電圧を分電盤6へ出力する。
 電力変換部42は、DC/DC双方向変換部47と、DC/AC双方向変換部48とを備えている。この電力変換部42は、制御部43の指示に従って動作する。
 DC/DC双方向変換部47は、インダクタ471と、2つのスイッチング素子472,473と、2つのダイオード474,475と、コンデンサ476とを備えている。スイッチング素子472,473は、例えばIGBTであり、制御部43からの制御信号に従ってオンオフを切り替えている。
 DC/AC双方向変換部48は、スイッチング回路481と、フィルタ回路482とを備えている。スイッチング回路481は、4つのスイッチング素子491~494と、4つのダイオード495,495,……とを備えている。フィルタ回路482は、インダクタ496と、コンデンサ497と、インダクタ498とを備えている。スイッチング素子491~494は、例えばIGBTであり、制御部43からの制御信号に従ってオンオフを切り替える。
 DC/AC双方向変換部48は、放電時において、制御部43の指示に従って、スイッチング回路481にてDC/DC双方向変換部47からの直流電圧を交流電圧に変換し、フィルタ回路482にてスイッチング回路481からの交流電圧を平滑化する。一方、充電時においては、DC/AC双方向変換部48は、制御部43の指示に従って、スイッチング回路481にて給電路92側からの交流電圧を直流電圧に変換する。
 制御部43は、コンピュータに搭載されたCPU(マイクロプロセッサ)を主構成要素とし、プログラムに従って動作することによって、後述の停電検出部、出力制御部および切替制御部として機能する。すなわち、制御部43は、DC/DC双方向変換部47およびDC/AC双方向変換部48を制御する。
 停電検出部は、給電路92に所定電圧が印加されていない場合に商用電力系統7の停電を検出する。
 出力制御部は、給電路92への電力出力を制御する。また、出力制御部は、商用電力系統7の停電時に充放電用パワーコンディショナ4が単独で運転していることを検出する単独運転検出機能を有している。これにより、出力制御部は、停電検出部により商用電力系統7の停電が検出された場合に充放電用パワーコンディショナ4から給電路92への電力出力を停止する。出力制御部の単独運転検出機能に用いられる検出方式は、太陽電池パワーコンディショナ2と同様の方式を採用することができるが、太陽電池パワーコンディショナ2や燃料電池パワーコンディショナ3と同一の方式である必要はない。
 出力制御部は、停電検出部により商用電力系統7の停電が検出されて、第1のスイッチ51により商用給電路91が電気的に切断された場合、一旦電力出力を停止した後、給電路92に印加されている電圧(以下「給電路電圧」という)V2が所定電圧になるように給電路92側の出力電圧V1の実効値を変化させる。すなわち、出力制御部は、商用電力系統7(図1参照)と連系した状態で、蓄電池41の充放電の際に電流制御を行い、停電検出部により商用電力系統7の停電が検出された場合、蓄電池41の充電量または充放電電力の少なくとも一方に応じて出力電圧V1の実効値を変化させて電圧制御にて運転を行う。
 なお、出力電圧V1とは、充放電用パワーコンディショナ4から充電用に蓄電池41に向かって出力される電圧ではなく、放電用に給電路92側に向かって出力される電圧を意味する。
 切替制御部は、停電検出部により商用電力系統7の停電が検出された場合、第1のスイッチ51にオフ信号を出力することによって第1のスイッチ51を制御して商用給電路91を電気的に切断させる。検出部54により商用電力系統7の復電が検出された場合、切替制御部は、第1のスイッチ51にオン信号を出力することによって第1のスイッチ51を制御して商用給電路91を電気的に接続させる。
 なお、充放電用パワーコンディショナ4は、制御部43(コンピュータ)が各種の機能を実行するためのプログラムを格納している。すなわち、充放電用パワーコンディショナ4は、制御部43を出力制御部および切替制御部として機能させるためのプログラムを格納している。上記プログラムは、充放電用パワーコンディショナ4の出荷時に充放電用パワーコンディショナ4に予め格納されている。ただし、充放電用パワーコンディショナ4が上記プログラムを出荷後に取得する場合、充放電用パワーコンディショナ4が上記プログラムを取得する手法の一例としては、上記プログラムを記録したコンピュータ読み取り可能な記録媒体を用いる手法がある。記録媒体を用いる手法の場合、充放電用パワーコンディショナ4は、記録媒体のデータを読み取るための読取装置(図示せず)を備えていればよい。記録媒体としては、例えば光ディスク(CD-ROM、DVD-ROM)やメモリカードなどがある。読取装置としては、光ディスクの情報を読み出すドライブ装置や、メモリカードの情報を読み出すメモリカードリーダなどがある。また、充放電用パワーコンディショナ4が上記プログラムを取得する他の手法としては、ネットワークを用いて上記プログラムを他の装置(例えばサーバ)からダウンロードする手法がある。上記プログラムをダウンロードする手法の場合、充放電用パワーコンディショナ4は、ネットワークを用いて他の装置と通信するための通信機能(図示せず)を有していればよい。
 充放電用パワーコンディショナ4は、太陽電池パワーコンディショナ2の出力電力と燃料電池パワーコンディショナ3の出力電力との総和が負荷8の消費電力より小さい場合、上記消費電力と上記総和との差分を放電する。一方、上記総和が上記消費電力より大きい場合、充放電用パワーコンディショナ4は、上記総和と上記消費電力との差分を充電する。
 ところで、本実施形態の電力供給システム1において、太陽電池21の発電電力P1(図3参照)が日照量により変化するから、太陽電池パワーコンディショナ2の出力電力は変化する。また、負荷8の消費電力が小さい場合に、充放電用パワーコンディショナ4の充電電力が大きくなる。このため、充放電用パワーコンディショナ4の充電電力が規定電力より大きな電力である状態(フル充電状態を含む)で蓄電池41を充電させないように、太陽電池パワーコンディショナ2の出力電力を規定電力以下にする必要がある。
 そこで、本実施形態の電力供給システム1は、充放電用パワーコンディショナ4側で太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3の電力出力を抑制することができる。以下、太陽電池パワーコンディショナ2について説明するが、燃料電池パワーコンディショナ3についても同様である。
 本実施形態の電力供給システム1では、太陽電池パワーコンディショナ2の出力抑制機能を利用して、太陽電池パワーコンディショナ2の電力出力を充放電用パワーコンディショナ4が制御する。出力抑制機能とは、太陽電池パワーコンディショナ2が給電路電圧V2の実効値を検出し、給電路電圧V2の実効値が抑制開始電圧V12(図3参照)以上に上昇すると、太陽電池パワーコンディショナ2の出力電力を抑制する機能である。抑制開始電圧V12は、予め決められた値である。すなわち、給電路電圧V2の実効値が抑制開始電圧V12を超えると、太陽電池パワーコンディショナ2は、太陽電池21の発電を抑制させる抑制制御を行う。また、太陽電池パワーコンディショナ2には、抑制開始電圧V12よりもさらに高い電圧であって太陽電池パワーコンディショナ2の電力出力が停止する過電圧異常電圧V13(図3参照)が設定されている。
 充放電用パワーコンディショナ4の制御部43は、出力制御部として、停電検出部により商用電力系統7の停電が検出されて、第1のスイッチ51により商用給電路91が電気的に切断された場合、蓄電池41の充電が正常な条件を満たすとき、出力電圧V1の実効値を抑制開始電圧V12以下とする。一方、蓄電池41の充電が正常な条件を満たさないとき、制御部43は、太陽電池パワーコンディショナ2の電力出力を抑制するために、出力電圧V1の実効値を抑制開始電圧V12より大きくする。「蓄電池41の充電が正常な条件を満たすとき」とは、蓄電池41の充電量が規定充電量より少ないときか、蓄電池41に充電される充電電力が規定電力より少ないときである。一方、「蓄電池41の充電が正常な条件を満たさないとき」とは、蓄電池41の充電量が規定充電量以上であるときか、蓄電池41に充電される充電電力が規定電力以上であるときである。
 また、充放電用パワーコンディショナ4の制御部43は、蓄電池41を充電する際の充電電力を算出する算出部として機能する。算出部は、電流検出部462および出力電圧検出部463の検出結果を用いて、蓄電池41を充電する際の充電電力を算出する。
 出力制御部は、算出部で算出された充電電力が規定電力以上になると、出力電圧V1の実効値を予め決められた第1の上昇率で上昇させるように電圧制御を行う。また、充電電力が規定電力以上であって、出力電圧V1の実効値が抑制開始電圧V12より大きい切替電圧(第2のしきい値)V14を超えると、出力制御部は、出力電圧V1の実効値を第2の上昇率で上昇させるように電圧制御を行う。第2の上昇率は、ゼロ以上かつ第1の上昇率より低い値に予め設定されている。さらに、出力電圧V1の実効値が切替電圧V14より大きい状態で充電電力が規定電力未満になると、出力制御部は、出力電圧V1の実効値を減少させるように電圧制御を行う。
 太陽電池パワーコンディショナ2の電力出力を充放電用パワーコンディショナ4が制御する方法について図3を用いて説明する。
 太陽電池パワーコンディショナ2の出力電力(太陽電池21の発電電力P1)が予め設定された負荷電力P11以上になると(図3の時刻t1,t9)、充放電用パワーコンディショナ4は、太陽電池パワーコンディショナ2の電力出力を抑制するために、充放電用パワーコンディショナ4の出力電圧V1の実効値を第1の上昇率で上昇させる。
 出力電圧V1の実効値は、上昇していくと抑制開始電圧V12に達する(時刻t2,t10)。出力電圧V1の実効値が抑制開始電圧V12に達すると、太陽電池パワーコンディショナ2は一定の遅延時間(抑制開始遅延T2)を持って電力出力の抑制を開始する(時刻t4,t12)。時刻t4,t12において、発電電力P1はピーク電力P12となる。
 充放電用パワーコンディショナ4が出力電圧V1の実効値を上昇させて、出力電圧V1の実効値が抑制開始電圧V12に到達するまでの時間を出力電圧上昇時間T1とすると、この出力電圧上昇時間T1はできるだけ短いほうがよい。このため、第1の上昇率は、できるだけ高く設定されているほうが好ましい。しかし、出力電圧V1の実効値が抑制開始電圧V12を超えてから太陽電池パワーコンディショナ2が電力出力の抑制を開始するまでの時間(抑制開始遅延T2)は、太陽電池パワーコンディショナ2ごとにばらつきが大きい。このため、充放電用パワーコンディショナ4が出力電圧V1の実効値を第1の上昇率で上昇させ続けると、太陽電池パワーコンディショナ2が電力出力の抑制を開始する前に、充放電用パワーコンディショナ4の出力電圧V1の実効値が太陽電池パワーコンディショナ2の過電圧異常電圧V13に達し、太陽電池パワーコンディショナ2が電力出力を停止してしまう。
 そこで、本実施形態では、抑制開始電圧V12と過電圧異常電圧V13との間に切替電圧(第2のしきい値)V14が予め設定されている。出力電圧V1の実効値が切替電圧V14に達すると(時刻t3,t11)、充放電用パワーコンディショナ4は、出力電圧V1の実効値を第1の上昇率よりも低い第2の上昇率で上昇させる。なお、抑制開始電圧V12のばらつきを考慮して、切替電圧V14は設定されている。また、出力電圧V1の実効値が過電圧異常電圧V13にならないように第1の上昇率および第2の上昇率は設定されている。
 これにより、太陽電池パワーコンディショナ2の抑制開始遅延T2がばらついていても、充放電用パワーコンディショナ4の出力電圧V1の実効値が過電圧異常電圧V13に達することなく太陽電池パワーコンディショナ2に電力出力の抑制をかけることができる。
 太陽電池パワーコンディショナ2が電力出力を抑制し、太陽電池21の発電電力P1が負荷電力P11以下になると(時刻t5)、出力電圧V1の実効値が定格電圧V11になるように、充放電用パワーコンディショナ4は、出力電圧V1の実効値を徐々に下降させていく(時刻t5~t8)。この際、出力電圧V1の実効値が切替電圧V14になるまでは、充放電用パワーコンディショナ4は、出力電圧V1の実効値を第1の下降率で下降させていく(時刻t5~t6)。出力電圧V1の実効値が切替電圧V14以下になると(時刻t6)、充放電用パワーコンディショナ4は、出力電圧V1の実効値を第1の下降率よりも高い第2の下降率で下降させていく(時刻t6~t7)。時刻t8において、太陽電池パワーコンディショナ2は、抑制終了遅延T3を持って電力出力の抑制を終了する。
 ところで、充放電用パワーコンディショナ4の出力電圧V1の実効値を変化させる方法の一例として、以下に示す3つの方法がある。いずれの方法を採用してもよく、用途に応じて適宜選択される。
 まず、第1の方法として、図4に示すように、交流電圧である出力電圧V1の振幅を変化させることにより、実効値を変化させる方法がある。この方法では、充放電用パワーコンディショナ4の出力制御部は、出力電圧V1の振幅を変化させることによって、出力電圧V1の実効値を変化させる。具体的には、出力制御部は、DC/AC双方向変換部48のスイッチング素子491~494のオン時間のパルス幅を調整することによって、出力電圧V1の振幅を変化させることができる。このとき、DC/DC双方向変換部47の出力電圧が出力電圧V1の瞬時値より高くなるように、出力制御部は、DC/DC双方向変換部47のスイッチング素子472,473のオン時間のパルス幅を調整する。図4の破線は変化前の出力電圧V1を示し、図4の実線は変化後の出力電圧V1を示す。
 続いて、第2の方法として、図5に示すように、変化前と変化後とで出力電圧V1のピーク値を変化させずに出力電圧V1の実効値を変化させる方法がある。第1の方法のような振幅増幅型の場合、上述の通り、図4の破線の波形から振幅を増加させて図4の実線の波形を作るため、変化後の出力電圧V1のピーク値が高くなり、負荷8の耐圧に関する問題が発生する。このため、変化後の出力電圧V1のピーク値より低い耐圧の負荷機器81を接続しないようにする必要がある。
 そこで、第2の方法では、充放電用パワーコンディショナ4の出力制御部は、正弦波(図5の破線)に上記正弦波のピーク点で瞬時値がゼロになる波(図5の一点鎖線)を重畳した波形(図5の実線)と等価な波形に出力電圧V1の波形を変化させることによって、出力電圧V1の実効値を変化させる。すなわち、図5の破線の正弦波に図5の一点鎖線の高調波を合わせ込むことで図5の実線の波形を作る。具体的には、出力制御部は、DC/AC双方向変換部48のスイッチング素子491~494のオン時間のパルス幅を調整することによって、出力電圧V1の波形を図5の実線の波形にすることができる。これにより、簡単な演算で出力電圧V1のピーク値を高くしないで出力電圧V1の実効値だけを大きくすることができる。
 ただし、第2の方法では、図5に示すように、基の正弦波のうち正の波形部分に対しては、重畳される一点鎖線の2つの波形も正の波形であり、基の正弦波のうち負の波形部分に対しては、重畳される一点鎖線の2つの波形も負の波形であることが望まれる。
 特に、充放電用パワーコンディショナ4の出力制御部は、図5に示すように、正弦波としての基本波に2倍高調波を重畳した波形と等価な波形に出力電圧V1の波形を変化させることによって、出力電圧V1の実効値を変化させることが好ましい。
 続いて、第3の方法として、図6に示すように、正弦波に、上記正弦波の位相によって異なるゲインGをかけて生成した波形の電圧とすることで、実効値を変化させる方法がある。この方法では、充放電用パワーコンディショナ4の出力制御部は、正弦波(図6の破線)を上記正弦波の位相によって異なるゲインGで増幅した波形(図6の実線)と等価な波形に出力電圧V1の波形を変化させることによって、出力電圧V1の実効値を変化させる。具体的には、出力制御部は、DC/AC双方向変換部48のスイッチング素子491~494のオン時間のパルス幅を調整することによって、出力電圧V1の波形を図6の実線の波形にすることができる。これにより、簡単な演算で出力電圧V1のピーク値を高くしないで出力電圧V1の実効値だけを大きくすることができる。
 次に、本実施形態に係る電力供給システム1の動作について図7を用いて説明する。なお、符号は図1を参照する。まず、電力供給システム1は、商用電力系統7が商用電力を供給している通常時において、商用電力系統7と連系運転を行う(S1)。電力供給システム1は、商用電力系統7の停電が検出されない限り、連系運転を継続して行う(S2)。一方、商用電力系統7が停電した場合、太陽電池パワーコンディショナ2と燃料電池パワーコンディショナ3と充放電用パワーコンディショナ4とは、停電検出機能により商用電力系統7の停電を検出して連系運転(電力出力)を停止する(S3)。その後、充放電用パワーコンディショナ4からのオフ信号によって、第1のスイッチ51がオフになって商用給電路91を電気的に切断し、電力供給システム1は自立運転モードに切り替わり(S4)、自立運転を行う(S5)。この際、充放電用パワーコンディショナ4は、通常時の商用電力系統7の交流電圧と同じ周波数および振幅の交流電圧を出力する。これにより、太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3は、通常時と同じように動作を再開する。その後、蓄電池41の充電状態に応じて、電力供給システム1は抑制制御を行う(S6)。その後、商用電力系統7の復電が検出されると(S7)、電力供給システム1は自立運転(電力出力)を停止し(S8)、自立運転から系統連系運転に切り替わる(S9)。一方、ステップS7において、商用電力系統7の復電が検出されない場合、ステップS6に戻って抑制制御を継続する。
 続いて、ステップS6における抑制制御の動作について図8を用いて説明する。なお、符号は図1,3を参照する。まず、蓄電池41の充電電力が設定値を超えた場合(S21)、充放電用パワーコンディショナ4の出力電圧V1の実効値が切替電圧V14に達するまでは(S22)、充放電用パワーコンディショナ4は、第1の上昇率で出力電圧V1の実効値を上昇させる(S23)。出力電圧V1の実効値が切替電圧V14を超えると(S22)、第2の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S24)。
 一方、ステップS21において充電電力が設定値以下である場合、充放電用パワーコンディショナ4の出力電圧V1の実効値が定格電圧V11および切替電圧V14より大きいとき(S25,S26)、充放電用パワーコンディショナ4は、第1の下降率で出力電圧V1の実効値を下降させる(S27)。ステップS26において出力電圧V1の実効値が切替電圧V14以下である場合、第2の下降率(>第1の下降率)で出力電圧V1の実効値を下降させる(S28)。ステップS25において出力電圧V1の実効値が定格電圧V11以下である場合、抑制制御の動作を終了する。
 以上説明した本実施形態における充放電用パワーコンディショナ4は、商用電力系統7の停電時に、給電路電圧V2が所定電圧になるように給電路92側の出力電圧V1を制御する。これにより、本実施形態の電力供給システム1では、商用電力系統7が停電していない場合と同様に発電用パワーコンディショナ(太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3)が給電路92へ電力を出力することができる。その結果、本実施形態の電力供給システム1では、発電用パワーコンディショナが通信機能を有していなくても、商用電力系統7の停電時において、手動操作を必要とせずに発電装置(太陽電池21、燃料電池)の電力を利用することができる。
 また、本実施形態の電力供給システム1では、蓄電池41の充電が正常な条件を満たさないときに、充放電用パワーコンディショナ4が出力電圧V1の実効値を抑制開始電圧(しきい値)V12より大きくする。これにより、本実施形態の電力供給システム1では、給電路電圧V2の実効値を抑制開始電圧V12より大きくすることができるので、発電用パワーコンディショナの出力電力を小さくすることができ、その結果、蓄電池41の充電を正常な条件で行うことができる。
 さらに、本実施形態の電力供給システム1によれば、充放電用パワーコンディショナ4の出力電圧V1の実効値が切替電圧(第2のしきい値)V14を超えると、出力電圧V1の実効値の上昇率を低くする。これにより、本実施形態の電力供給システム1では、発電用パワーコンディショナの間で電力出力を抑制する機能の開始(抑制開始遅延T2)がばらついていても、給電路電圧V2の実効値が発電用パワーコンディショナの過電圧異常電圧(異常停止値)V13に達することなく、発電用パワーコンディショナの出力電力を小さくすることができる。
 また、本実施形態の電力供給システム1によれば、充放電用パワーコンディショナ4の出力電圧V1の振幅を変化させることによって、出力電圧V1の実効値を簡単に変化させることができる。
 本実施形態の電力供給システム1では、正弦波に上記正弦波のピーク点で瞬時値がゼロになる波を重畳した波形と等価な波形に出力電圧V1の波形を変化させる。これにより、出力電圧V1のピーク値を一定にしたまま出力電圧V1の実効値だけを大きくすることができる。特に、基本波に2倍の高調波を重畳した波形と等価な波形に出力電圧V1の波形を変化させることによって、簡単な演算で、出力電圧V1のピーク値を一定にしたまま出力電圧V1の実効値だけを大きくすることができる。
 本実施形態の電力供給システム1では、正弦波を上記正弦波の位相によって異なるゲインGで増幅した波形と等価な波形に出力電圧V1の波形を変化させる。これにより、簡単な演算で、出力電圧V1のピーク値を一定にしたまま出力電圧V1の実効値だけを大きくすることができる。
 (実施形態2)
 実施形態2に係る電力供給システム1は、充電電力が規定電力以上の状態で変化方向が負の場合、出力電圧V1の実効値を変化させずに電圧制御を行う点で、実施形態1に係る電力供給システム1と相違する。なお、実施形態1の電力供給システム1と同様の構成要素については、同一の符号を付して説明を省略する。
 本実施形態の充放電用パワーコンディショナ4の制御部43は、充電電力の増減の変化方向を検出する電力変化検出部として機能する。また、本実施形態の制御部43は、出力制御部として、充電電力が規定電力以上の状態で、電力変化検出部により充電電力が減少方向であると検出された場合、出力電圧V1の実効値を検出時点の値に維持する。なお、実施形態1の制御部43と同様の機能については説明を省略する。
 次に、本実施形態に係る電力供給システム1の動作の一例について図9を用いて説明する。太陽電池パワーコンディショナ2の出力抑制のスピードは製品ごとに各々大きく異なっている。このため、太陽電池パワーコンディショナ2の出力電力が負荷電力P11以下になるように太陽電池パワーコンディショナ2が抑制を開始しても、抑制がかかるまでの時間(抑制開始遅延T2)が大きくばらつく。これにより、充放電用パワーコンディショナ4は、抑制開始遅延T2で、出力電圧V1の実効値を過電圧異常電圧V13まで上昇させてしまうことが考えられる。
 そこで、充放電用パワーコンディショナ4側で充電電力が増加しているか減少しているかを判断して、これにより、太陽電池パワーコンディショナ2が抑制を開始したか否かの判断を行う。この判断結果に応じて、充放電用パワーコンディショナ4は、出力電圧V1の実効値の上昇率を変更する。以下に充放電用パワーコンディショナ4の出力電圧V1の実効値の上昇率の一例を示す。以下、太陽電池パワーコンディショナ2について説明するが、燃料電池パワーコンディショナ3についても同様である。
 太陽電池パワーコンディショナ2の出力電力(太陽電池21の発電電力P1)が負荷電力P11より大きく、発電電力P1が増加中すなわち蓄電池41の充電電力が増加中であって、出力電圧V1の実効値が切替電圧V14より小さい場合(図9の時刻t21~t23,t28~t30)、出力電圧V1の実効値を第1の上昇率とする。また、発電電力P1が負荷電力P11より大きく、発電電力P1が増加中すなわち充電電力が増加中であって、出力電圧V1の実効値が切替電圧V14より大きい場合(時刻t23~t24,t30~t31)、出力電圧V1の実効値を第2の上昇率とする。一方、発電電力P1が負荷電力P11より大きく、発電電力P1が減少中すなわち充電電力が減少中であって、出力電圧V1の実効値が切替電圧V14より大きい場合(時刻t24~t25,t31~t32)、出力電圧V1の実効値を第3の上昇率とする。また、図示しないが、発電電力P1が負荷電力P11より大きく、発電電力P1が減少中であって、出力電圧V1の実効値が切替電圧V14より小さい場合、出力電圧の実効値を第4の上昇率とする。なお、第1の上昇率>第2の上昇率>第3の上昇率・第4の上昇率≧0である。また、第3の上昇率および第4の上昇率が0である場合、図9に示すように、出力電圧V1の実効値は、第2の上昇率になってから一定(第3の上昇率=0)になり、場合によっては第1の上昇率からいきなり一定(第4の上昇率=0)になる。
 太陽電池パワーコンディショナ2が電力出力を抑制し、太陽電池21の発電電力P1が負荷電力P11以下になると(時刻t25,t32)、出力電圧V1の実効値が定格電圧V11になるように、充放電用パワーコンディショナ4は、出力電圧V1の実効値を徐々に下降させていく(時刻t25~t27)。この際、出力電圧V1の実効値が切替電圧V14になるまでは、充放電用パワーコンディショナ4は、出力電圧V1の実効値を第1の下降率で下降させていく(時刻t25~t26,t32~t33)。出力電圧V1の実効値が切替電圧V14以下になると(時刻t26,t33)、充放電用パワーコンディショナ4は、出力電圧V1の実効値を第1の下降率よりも高い第2の下降率で下降させていく(時刻t26~t27)。時刻t27において、太陽電池パワーコンディショナ2は、抑制終了遅延T3を持って電力出力の抑制を終了する。
 次に、本実施形態に係る電力供給システム1の抑制制御の動作について図10を用いて説明する。なお、符号は図1,9を参照する。まず、蓄電池41の充電電力が設定値を超えた場合(S41)、充電電力が増加中であって(S42)、充放電用パワーコンディショナ4の出力電圧V1の実効値が切替電圧V14に達するまでは(S43)、充放電用パワーコンディショナ4は、第1の上昇率で出力電圧V1の実効値を上昇させる(S44)。出力電圧V1の実効値が切替電圧V14を超えると(S43)、充放電用パワーコンディショナ4は、第2の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S45)。
 ステップS42において充電電力が増加中ではない場合、出力電圧V1の実効値が切替電圧V14より大きいときは(S46)、充放電用パワーコンディショナ4は、第3の上昇率(<第2の上昇率)で出力電圧V1の実効値を上昇させる(S47)。第3の上昇率=0の場合、出力電圧V1の実効値を維持する。出力電圧V1の実効値が切替電圧V14を超えると(S46)、充放電用パワーコンディショナ4は、第4の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S48)。第4の上昇率=0の場合、出力電圧V1の実効値を維持する。
 一方、ステップS41において充電電力が設定値以下である場合、出力電圧V1の実効値が定格電圧V11および切替電圧V14より大きいとき(S49,S50)、充放電用パワーコンディショナ4は、第1の下降率で出力電圧V1の実効値を下降させる(S51)。出力電圧V1の実効値が切替電圧V14以下である場合(S50)、充放電用パワーコンディショナ4は、第2の下降率で出力電圧V1の実効値を下降させる(S52)。ステップS49において出力電圧V1の実効値が定格電圧V11以下である場合、抑制制御の動作を終了する。
 以上説明した本実施形態の電力供給システム1によれば、発電用パワーコンディショナ(太陽電池パワーコンディショナ2、燃料電池パワーコンディショナ3)が出力抑制を開始したか否かを充放電用パワーコンディショナ4が充電電力の変化方向で判断し、判断結果に応じて出力電圧V1の実効値を一定にすることができる。これにより、本実施形態の電力供給システム1では、給電路電圧V2が過電圧異常電圧(異常停止値)V13に達する確率を低減させることができる。
 (実施形態3)
 実施形態3に係る電力供給システム1は、図12に示すように充電電力P2が急激に増加すると、図1,11に示す発電用切替部(第2のスイッチ52、第3のスイッチ53)を制御して発電用パワーコンディショナ(太陽電池パワーコンディショナ2、燃料電池パワーコンディショナ3)からの電力出力を停止させる点で、実施形態2に係る電力供給システム1と相違する。なお、実施形態2の電力供給システム1と同様の構成要素については、同一の符号を付して説明を省略する。
 本実施形態の充放電用パワーコンディショナ4の制御部43は、後述の算出部と停止制御部として機能する。以下、算出部および停止制御部について図11,12を用いて説明する。
 算出部は、蓄電池41を充電する際の充電電力P2を算出する。
 停止制御部は、算出部で算出された充電電力P2が予め決められた変化率以上で増加して規定電力以上になった場合、太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3から充放電用パワーコンディショナ4への電力出力を停止させる。
 本実施形態の停止制御部は、充電電力P2が上記変化率以上で増加して規定電力以上になった場合、太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3と給電路92とを電気的に切断するように第2のスイッチ52および第3のスイッチ53を制御する。
 次に、本実施形態に係る電力供給システム1の動作の一例について図12を用いて説明する。まず、太陽電池パワーコンディショナ2の日照による出力電力の変化は比較的緩やかな出力変動である。特に出力電力の上昇は日照の変化と太陽電池パワーコンディショナ2の最大電力追従制御(MPPT制御)の追従スピードとに依存するため、緩やかな変化で出力抑制機能により、充放電用パワーコンディショナ4の充電電力P2をコントロールすることが可能である。一方、負荷機器81の変動は、充放電用パワーコンディショナ4の充電電力P2の極めて急峻な変動を発生させる(時刻t41~t44)。例えば1kWの負荷機器81がオンからオフになった場合(時刻t41)、充放電用パワーコンディショナ4の充電電力P2は急に1kW増加することになる(時刻t43)。この状態で太陽電池パワーコンディショナ2の出力抑制機能を動作させても、1kW分の抑制が働くまで充放電用パワーコンディショナ4は過充電状態になってしまう。
 そこで、充放電用パワーコンディショナ4は急峻な充電電力P2を検出し、充電電力P2が許容充電電力P21を超えた場合、速やかに太陽電池パワーコンディショナ2を給電路92から切り離すために第2のスイッチ52へオフ信号を出力する(時刻t42~t45)。
 次に、本実施形態に係る電力供給システム1の抑制制御の動作について図13を用いて説明する。なお、符号は図1,9,12を参照する。まず、充電電力P2が設定値を超えて(S61)、充電電力P2が増加中であって(S62)、充電電力P2の増加スピードが設定値以下である場合(S63)について説明する。出力電圧V1の実効値が切替電圧V14に達するまでは(S64)、充放電用パワーコンディショナ4は、第1の上昇率で出力電圧V1の実効値を上昇させる(S65)。出力電圧V1の実効値が切替電圧V14を超えると(S64)、充放電用パワーコンディショナ4は、第2の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S66)。
 ステップS63において充電電力P2の増加スピードが設定値を超える場合、太陽電池21を解列するための第2のスイッチ52をオフにする(S67)。
 ステップS62において充電電力P2が増加中ではない場合、出力電圧V1の実効値が切替電圧V14より大きいときは(S68)、充放電用パワーコンディショナ4は、第3の上昇率(<第2の上昇率)で出力電圧V1の実効値を上昇させる(S69)。出力電圧V1の実効値が切替電圧V14以下であると(S68)、充放電用パワーコンディショナ4は、第4の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S70)。
 一方、ステップS61において充電電力P2が設定値以下である場合、出力電圧V1の実効値が定格電圧V11および切替電圧V14より大きいとき(S71,S72)、充放電用パワーコンディショナ4は、第1の下降率で出力電圧V1の実効値を下降させる(S73)。出力電圧V1の実効値が切替電圧V14以下である場合(S72)、充放電用パワーコンディショナ4は、第2の下降率で出力電圧V1の実効値を下降させる(S74)。ステップS71において出力電圧V1の実効値が定格電圧V11以下である場合、抑制制御の動作を終了する。
 以上説明した本実施形態の電力供給システム1によれば、充電電力P2の急峻な変動が発生した場合に、充放電用パワーコンディショナ4が急峻な充電電力P2を検出し、速やかに発電用パワーコンディショナ(太陽電池パワーコンディショナ2、燃料電池パワーコンディショナ3)から充放電用パワーコンディショナ4への電力出力を停止することができる。
 特に、本実施形態の電力供給システム1では、充放電用パワーコンディショナ4の充電電力P2の急峻な変動が発生した場合に、充放電用パワーコンディショナ4が発電用切替部(第2のスイッチ52、第3のスイッチ53)を制御することによって、確実かつ簡単に発電用パワーコンディショナから充放電用パワーコンディショナ4への電力出力を停止させることができる。
 (実施形態4)
 実施形態4に係る電力供給システム1は、図14に示すように、充電電力P2が急激に増加すると、出力電圧V1の実効値を過電圧異常電圧V13以上にして太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3からの電力出力を停止させる点で、実施形態3に係る電力供給システム1と相違する。なお、実施形態3の電力供給システム1と同様の構成要素については、同一の符号を付して説明を省略する。
 本実施形態の太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3は、給電路電圧V2の実効値が予め決められた過電圧異常電圧(異常停止値)V13を超えた場合に電力出力を停止する異常停止機能を有している。なお、実施形態3の太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3と同様の機能については説明を省略する。
 本実施形態の充放電用パワーコンディショナ4の制御部43の停止制御部は、充電電力P2が予め決められた変化率以上で増加して許容充電電力(規定電力)P21以上になった場合、出力電圧V1の実効値を過電圧異常電圧V13より大きくするように出力制御部を制御する。これにより、太陽電池パワーコンディショナ2および燃料電池パワーコンディショナ3からの電力出力を停止させる。なお、実施形態3の充放電用パワーコンディショナ4と同様の機能については説明を省略する。
 次に、本実施形態に係る電力供給システム1の動作の一例について図14を用いて説明する。まず、太陽電池パワーコンディショナ2の日照による出力電力の変化は比較的緩やかな出力変動である。特に出力電力の上昇は日照の変化と太陽電池パワーコンディショナ2の最大電力追従制御(MPPT制御)の追従スピードとに依存するため、緩やかな変化で出力抑制機能により、充放電用パワーコンディショナ4の充電電力P2をコントロールすることが可能である。一方、負荷機器81の変動は、充放電用パワーコンディショナ4の充電電力P2の極めて急峻な変動を発生させる(時刻t61~t63)。例えば1kWの負荷機器81がオンからオフになった場合(時刻t61)、充放電用パワーコンディショナ4の充電電力P2は急に1kW増加することになる(時刻t62)。この状態で太陽電池パワーコンディショナ2の出力抑制機能を動作させても、1kW分の抑制が働くまで充放電用パワーコンディショナ4は過充電状態になってしまう。
 そこで、充放電用パワーコンディショナ4は急峻な充電電力P2を検出し、充電電力P2が許容充電電力P21を超えた場合、速やかに太陽電池パワーコンディショナ2を停止させるために、充放電用パワーコンディショナ4の出力電圧V1の実効値を過電圧異常電圧V13まで上昇させる(時刻t61~t62)。時刻t63の後の時刻t64で出力電圧V1を定格電圧V11に戻す。
 次に、本実施形態に係る電力供給システム1の抑制制御の動作について図15を用いて説明する。なお、符号は図1,14を参照する。まず、充電電力P2が設定値を超えて(S81)、充電電力P2が増加中であって(S82)、充電電力P2の増加スピードが設定値以下である場合(S83)について説明する。出力電圧V1の実効値が切替電圧V14に達するまでは(S84)、充放電用パワーコンディショナ4は、第1の上昇率で出力電圧V1の実効値を上昇させる(S85)。出力電圧V1の実効値が切替電圧V14を超えると(S84)、充放電用パワーコンディショナ4は、第2の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S86)。
 ステップS83において充電電力P2の増加スピードが設定値を超える場合、ステップS85に進む。
 ステップS82において充電電力P2が増加中ではない場合、出力電圧V1の実効値が切替電圧V14より大きいときは(S87)、充放電用パワーコンディショナ4は、第3の上昇率(<第2の上昇率)で出力電圧V1の実効値を上昇させる(S88)。出力電圧V1の実効値が切替電圧V14以下であると(S87)、充放電用パワーコンディショナ4は、第4の上昇率(<第1の上昇率)で出力電圧V1の実効値を上昇させる(S89)。
 一方、ステップS81において充電電力P2が設定値以下である場合、出力電圧V1の実効値が定格電圧V11および切替電圧V14より大きいとき(S90,S91)、充放電用パワーコンディショナ4は、第1の下降率で出力電圧V1の実効値を下降させる(S92)。出力電圧V1の実効値が切替電圧V14以下である場合(S91)、充放電用パワーコンディショナ4は、第2の下降率で出力電圧V1の実効値を下降させる(S93)。ステップS90において出力電圧V1の実効値が定格電圧V11以下である場合、抑制制御の動作を終了する。
 以上説明した本実施形態の電力供給システム1では、充電電力P2が急激に増加した場合に、充放電用パワーコンディショナ4の出力電圧V1の実効値を発電用パワーコンディショナ(太陽電池パワーコンディショナ2、燃料電池パワーコンディショナ3)の過電圧異常電圧(異常停止値)V13より大きくする。これにより、本実施形態の電力供給システム1では、給電路電圧V2の実効値を過電圧異常電圧V13より大きくすることができるので、確実かつ簡単に発電用パワーコンディショナの電力出力を停止させることができる。
 なお、各実施形態において、第1のスイッチ(切替部)51と第2のスイッチ(発電用切替部)52と第3のスイッチ(発電用切替部)53とは、各実施形態のように1つの切替盤5にまとめて設けられていてもよいし、別個に設けられていてもよい。
 また、各実施形態において、発電装置および発電用パワーコンディショナは、単数であっても、複数であってもよい。また、発電装置は複数種類あってもよい。
 さらに、各実施形態では、給電路92上の負荷8の手前に分電盤6があるが、発電用パワーコンディショナ(太陽電池パワーコンディショナ2、燃料電池パワーコンディショナ3)および充放電用パワーコンディショナ4は、分電盤6に直接接続されていてもよいし、切替盤5を介して分電盤6に接続されていてもよい。
 本発明を幾つかの好ましい実施形態について記述したが、この発明の本来の精神および範囲、即ち請求の範囲を逸脱することなく、当業者によって様々な修正および変形が可能である。

Claims (13)

  1.  発電装置の発電を制御する発電用パワーコンディショナと、蓄電池の充放電を制御する充放電用パワーコンディショナと、商用電力系統から負荷へ給電するための商用給電路に挿入された切替部と、前記商用電力系統の復電を検出する検出部とを備え、
     前記発電用パワーコンディショナは、当該発電用パワーコンディショナおよび前記充放電用パワーコンディショナから前記負荷へ給電するための給電路に所定電圧が印加されている場合に前記給電路へ電力を出力する機能と、前記給電路に前記所定電圧が印加されていない場合に前記給電路への電力出力を停止する機能とを有し、
     前記切替部は、前記商用電力系統が停電した場合に前記商用給電路を電気的に切断し、前記検出部により前記商用電力系統の復電が検出された場合に前記商用給電路を電気的に接続し、
     前記充放電用パワーコンディショナは、前記給電路への電力出力を制御する出力制御部と、前記商用電力系統の停電を検出する停電検出部とを有し、
     前記出力制御部は、前記停電検出部により前記商用電力系統の停電が検出されて、前記切替部により前記商用給電路が電気的に切断された場合に、前記給電路の電圧が前記所定電圧になるように前記充放電用パワーコンディショナから放電用に前記給電路側に向かって出力される出力電圧の実効値を変化させる
     ことを特徴とする電力供給システム。
  2.  前記発電用パワーコンディショナは、前記給電路の電圧の実効値が予め決められたしきい値より大きい場合に、前記給電路への電力出力を抑制する機能を有し、
     前記充放電用パワーコンディショナの前記出力制御部は、前記停電検出部により前記商用電力系統の停電が検出されて、前記切替部により前記商用給電路が電気的に切断された場合、前記蓄電池の充電が正常な条件を満たすとき、前記出力電圧の実効値を前記しきい値以下とし、前記蓄電池の充電が正常な条件を満たさないとき、前記出力電圧の実効値を前記しきい値より大きくする
     ことを特徴とする請求項1記載の電力供給システム。
  3.  前記充放電用パワーコンディショナは、前記蓄電池を充電する際の充電電力を算出する算出部を有し、
     前記出力制御部は、前記算出部で算出された前記充電電力が規定電力以上になると、前記出力電圧の実効値を予め決められた第1の上昇率で上昇させ、前記充電電力が前記規定電力以上であって、前記出力電圧の実効値が前記しきい値より大きい第2のしきい値を超えると、前記出力電圧の実効値をゼロ以上かつ前記第1の上昇率より低い第2の上昇率で上昇させ、前記出力電圧の実効値が前記第2のしきい値より大きい状態で前記充電電力が前記規定電力未満になると、前記出力電圧の実効値を減少させる
     ことを特徴とする請求項2記載の電力供給システム。
  4.  前記充放電用パワーコンディショナは、前記充電電力の増減の変化方向を検出する電力変化検出部を有し、
     前記出力制御部は、前記充電電力が前記規定電力以上の状態で、前記電力変化検出部により前記充電電力が減少方向であると検出された場合、前記出力電圧の実効値を検出時点の値に維持する
     ことを特徴とする請求項3記載の電力供給システム。
  5.  前記充放電用パワーコンディショナは、
     前記蓄電池を充電する際の充電電力を算出する算出部と、
     前記算出部で算出された前記充電電力が予め決められた変化率以上で増加して規定電力以上になった場合に前記発電用パワーコンディショナから前記充放電用パワーコンディショナへの電力出力を停止させる停止制御部と
     を有することを特徴とする請求項1または2記載の電力供給システム。
  6.  前記充放電用パワーコンディショナは、前記算出部で算出された前記充電電力が予め決められた変化率以上で増加して規定電力以上になった場合に前記発電用パワーコンディショナから前記充放電用パワーコンディショナへの電力出力を停止させる停止制御部を有することを特徴とする請求項3または4記載の電力供給システム。
  7.  前記発電用パワーコンディショナと前記給電路との間に挿入された発電用切替部を備え、
     前記充放電用パワーコンディショナの前記停止制御部は、前記充電電力が前記変化率以上で増加して前記規定電力以上になった場合、前記発電用パワーコンディショナと前記給電路とを電気的に切断するように前記発電用切替部を制御する
     ことを特徴とする請求項5または6記載の電力供給システム。
  8.  前記発電用パワーコンディショナは、前記給電路の電圧の実効値が予め決められた異常停止値を超えた場合に電力出力を停止する機能を有し、
     前記充放電用パワーコンディショナの前記停止制御部は、前記充電電力が前記変化率以上で増加して前記規定電力以上になった場合、前記出力電圧の実効値を前記異常停止値より大きくするように前記出力制御部を制御する
     ことを特徴とする請求項5または6記載の電力供給システム。
  9.  前記充放電用パワーコンディショナの前記出力制御部は、前記出力電圧の振幅を変化させることによって、前記出力電圧の実効値を変化させることを特徴とする請求項1~8のいずれか1項に記載の電力供給システム。
  10.  前記充放電用パワーコンディショナの前記出力制御部は、正弦波に当該正弦波のピーク点で瞬時値がゼロになる波を重畳した波形と等価な波形に前記出力電圧の波形を変化させることによって、前記出力電圧の実効値を変化させることを特徴とする請求項1~8のいずれか1項に記載の電力供給システム。
  11.  前記充放電用パワーコンディショナの前記出力制御部は、前記正弦波としての基本波に2倍高調波を重畳した波形と等価な波形に前記出力電圧の波形を変化させることによって、前記出力電圧の実効値を変化させることを特徴とする請求項10記載の電力供給システム。
  12.  前記充放電用パワーコンディショナの前記出力制御部は、正弦波を当該正弦波の位相によって異なるゲインで増幅した波形と等価な波形に前記出力電圧の波形を変化させることによって、前記出力電圧の実効値を変化させることを特徴とする請求項1~8のいずれか1項に記載の電力供給システム。
  13.  請求項1~12のいずれか1項に記載の電力供給システムに用いられる充放電用パワーコンディショナ。
PCT/JP2012/081261 2012-02-10 2012-12-03 電力供給システムおよびそれに用いられる充放電用パワーコンディショナ WO2013118376A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2012027444 2012-02-10
JP2012-027444 2012-02-10

Publications (1)

Publication Number Publication Date
WO2013118376A1 true WO2013118376A1 (ja) 2013-08-15

Family

ID=48947163

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2012/081261 WO2013118376A1 (ja) 2012-02-10 2012-12-03 電力供給システムおよびそれに用いられる充放電用パワーコンディショナ

Country Status (2)

Country Link
JP (1) JPWO2013118376A1 (ja)
WO (1) WO2013118376A1 (ja)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015057022A (ja) * 2013-09-13 2015-03-23 パナソニック株式会社 分散電源装置、電力切替装置及び電力供給システム
CN104713176A (zh) * 2013-12-11 2015-06-17 珠海格力电器股份有限公司 光伏空调系统及其控制方法
JP2015144531A (ja) * 2014-01-31 2015-08-06 シャープ株式会社 電力変換器、負荷装置、及び、制御方法
JP2015226439A (ja) * 2014-05-29 2015-12-14 三菱電機株式会社 電力供給システム及びパワーコンディショナ
JP2016007095A (ja) * 2014-06-20 2016-01-14 台達電子工業股▲ふん▼有限公司 ハイブリッドエネルギーシステム及びその制御方法
JP2016025813A (ja) * 2014-07-24 2016-02-08 三菱電機株式会社 自立運転対応分散型電源及び自立運転システム
JP2016039759A (ja) * 2014-08-11 2016-03-22 株式会社椿本チエイン 電力供給システム及び電力変換装置
JP2016096659A (ja) * 2014-11-14 2016-05-26 シャープ株式会社 パワーコンディショナの制御装置、パワーコンディショナ、その制御方法および電力システム
JP2016127708A (ja) * 2015-01-05 2016-07-11 積水化学工業株式会社 充放電システム
JP2016171633A (ja) * 2015-03-11 2016-09-23 積水化学工業株式会社 充放電システム
JP2016178808A (ja) * 2015-03-20 2016-10-06 積水化学工業株式会社 充放電システム
JP2017011800A (ja) * 2015-06-17 2017-01-12 シャープ株式会社 パワーコンディショナ、およびその制御方法
JP2018162591A (ja) * 2017-03-27 2018-10-18 有限会社ワタナベエレクトロニクス 電化住宅
JP2021065008A (ja) * 2019-10-11 2021-04-22 住友電気工業株式会社 自立電源システム、電源装置、及び、自立電源システムの制御方法
EP3996240A4 (en) * 2019-07-03 2023-04-05 Toshiba Mitsubishi-Electric Industrial Systems Corporation POWER SUPPLY SYSTEM

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008017652A (ja) * 2006-07-07 2008-01-24 Mitsubishi Electric Corp 電力供給システム
JP2011188607A (ja) * 2010-03-08 2011-09-22 Seiko Electric Co Ltd 電力供給システム、電力供給方法及び制御装置

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008017652A (ja) * 2006-07-07 2008-01-24 Mitsubishi Electric Corp 電力供給システム
JP2011188607A (ja) * 2010-03-08 2011-09-22 Seiko Electric Co Ltd 電力供給システム、電力供給方法及び制御装置

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015057022A (ja) * 2013-09-13 2015-03-23 パナソニック株式会社 分散電源装置、電力切替装置及び電力供給システム
CN104713176B (zh) * 2013-12-11 2018-05-22 珠海格力电器股份有限公司 光伏空调系统及其控制方法
CN104713176A (zh) * 2013-12-11 2015-06-17 珠海格力电器股份有限公司 光伏空调系统及其控制方法
JP2015144531A (ja) * 2014-01-31 2015-08-06 シャープ株式会社 電力変換器、負荷装置、及び、制御方法
JP2015226439A (ja) * 2014-05-29 2015-12-14 三菱電機株式会社 電力供給システム及びパワーコンディショナ
JP2016007095A (ja) * 2014-06-20 2016-01-14 台達電子工業股▲ふん▼有限公司 ハイブリッドエネルギーシステム及びその制御方法
JP2016025813A (ja) * 2014-07-24 2016-02-08 三菱電機株式会社 自立運転対応分散型電源及び自立運転システム
JP2016039759A (ja) * 2014-08-11 2016-03-22 株式会社椿本チエイン 電力供給システム及び電力変換装置
JP2016096659A (ja) * 2014-11-14 2016-05-26 シャープ株式会社 パワーコンディショナの制御装置、パワーコンディショナ、その制御方法および電力システム
JP2016127708A (ja) * 2015-01-05 2016-07-11 積水化学工業株式会社 充放電システム
JP2016171633A (ja) * 2015-03-11 2016-09-23 積水化学工業株式会社 充放電システム
JP2016178808A (ja) * 2015-03-20 2016-10-06 積水化学工業株式会社 充放電システム
JP2017011800A (ja) * 2015-06-17 2017-01-12 シャープ株式会社 パワーコンディショナ、およびその制御方法
JP2018162591A (ja) * 2017-03-27 2018-10-18 有限会社ワタナベエレクトロニクス 電化住宅
EP3996240A4 (en) * 2019-07-03 2023-04-05 Toshiba Mitsubishi-Electric Industrial Systems Corporation POWER SUPPLY SYSTEM
JP2021065008A (ja) * 2019-10-11 2021-04-22 住友電気工業株式会社 自立電源システム、電源装置、及び、自立電源システムの制御方法

Also Published As

Publication number Publication date
JPWO2013118376A1 (ja) 2015-05-11

Similar Documents

Publication Publication Date Title
WO2013118376A1 (ja) 電力供給システムおよびそれに用いられる充放電用パワーコンディショナ
US10305285B2 (en) Photovoltaic voltage regulation
JP5717172B2 (ja) 電力供給システム
JP5800919B2 (ja) 電力変換装置
US8937824B2 (en) Photovoltaic system and method of controlling same
US10790769B2 (en) Control method and control system for enhancing endurance to anomalous voltage for doubly-fed induction generator
JP5882845B2 (ja) 電力貯蔵型太陽光発電システム
US9893550B2 (en) Energy storage system and starting method thereof
CN112994105A (zh) 一种光伏发电系统、功率控制装置及储能系统
JP5325507B2 (ja) 系統連系インバータ
JP2005269843A (ja) 系統連系装置
US20230063475A1 (en) Power supply system
JP4123006B2 (ja) 太陽光発電システム
US11329488B2 (en) Power conversion system, method for controlling converter circuit, and program
US20240014664A1 (en) Power supply system and method for controlling output voltage of direct current combiner box
US11967840B2 (en) Power supply system
US20150295409A1 (en) Micro-grid operation system with smart energy management
JP7255408B2 (ja) 電力変換装置及び発電システム
JP5806544B2 (ja) 制御装置
CN116670991A (zh) 直流/直流转换器及其控制方法
JP2021136861A (ja) 電力変換装置を制御するための方法および制御装置
US11916511B1 (en) Solar-battery integrated DC system
FI128564B (en) Controller and method for controlling a power converter
JP7259416B2 (ja) パワーコンディショナ及び制御装置
JP2024018293A (ja) ハイブリッド型蓄電システム

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 12867940

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2013557373

Country of ref document: JP

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 12867940

Country of ref document: EP

Kind code of ref document: A1