WO2012121378A1 - 生産効率化装置、生産効率化方法、コンピュータプログラム - Google Patents
生産効率化装置、生産効率化方法、コンピュータプログラム Download PDFInfo
- Publication number
- WO2012121378A1 WO2012121378A1 PCT/JP2012/056144 JP2012056144W WO2012121378A1 WO 2012121378 A1 WO2012121378 A1 WO 2012121378A1 JP 2012056144 W JP2012056144 W JP 2012056144W WO 2012121378 A1 WO2012121378 A1 WO 2012121378A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- processing
- information
- processed
- time
- production efficiency
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Program-control systems
- G05B19/02—Program-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B19/4189—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by the transport system
-
- H—ELECTRICITY
- H10—SEMICONDUCTOR DEVICES; ELECTRIC SOLID-STATE DEVICES NOT OTHERWISE PROVIDED FOR
- H10P—GENERIC PROCESSES OR APPARATUS FOR THE MANUFACTURE OR TREATMENT OF DEVICES COVERED BY CLASS H10
- H10P72/00—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof
- H10P72/30—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof for conveying, e.g. between different workstations
- H10P72/33—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof for conveying, e.g. between different workstations into and out of processing chamber
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Program-control systems
- G05B19/02—Program-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B19/41865—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
-
- H—ELECTRICITY
- H10—SEMICONDUCTOR DEVICES; ELECTRIC SOLID-STATE DEVICES NOT OTHERWISE PROVIDED FOR
- H10P—GENERIC PROCESSES OR APPARATUS FOR THE MANUFACTURE OR TREATMENT OF DEVICES COVERED BY CLASS H10
- H10P72/00—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof
- H10P72/30—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof for conveying, e.g. between different workstations
- H10P72/32—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof for conveying, e.g. between different workstations between different workstations
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/30—Nc systems
- G05B2219/31—From computer integrated manufacturing till monitoring
- G05B2219/31372—Mes manufacturing execution system
-
- H—ELECTRICITY
- H10—SEMICONDUCTOR DEVICES; ELECTRIC SOLID-STATE DEVICES NOT OTHERWISE PROVIDED FOR
- H10P—GENERIC PROCESSES OR APPARATUS FOR THE MANUFACTURE OR TREATMENT OF DEVICES COVERED BY CLASS H10
- H10P72/00—Handling or holding of wafers, substrates or devices during manufacture or treatment thereof
- H10P72/06—Apparatus for monitoring, sorting, marking, testing or measuring
- H10P72/0612—Production flow monitoring, e.g. for increasing throughput
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Definitions
- the present invention relates to a production efficiency improvement device and a production efficiency improvement method for improving the efficiency of conveyance and processing of an object to be processed in a production processing system for conveying an object to be processed between a plurality of processing apparatuses and processing the object to be processed. And a computer program for operating a computer as the production efficiency improving apparatus.
- a plurality of processing devices for processing a target object a plurality of transport devices for transporting a target object between the plurality of processing devices, a transport control device for controlling operations of the plurality of transport devices, and a target object
- a production apparatus including a production execution control device that determines a processing apparatus to be processed, instructs a collection destination and a conveyance destination of the object to be processed to the transfer control apparatus, and instructs a processing content of the object to be processed to the processing apparatus;
- Patent Document 1 communicates with a plurality of processing apparatuses that process a target object and a plurality of transfer apparatuses that transfer the target object from any of the processing apparatuses to any of the processing apparatuses.
- Software having at least one of a procedure and a process instruction procedure for instructing the processing apparatus to execute a process using the information is disclosed.
- Non-Patent Document 1 also describes a factory production management system MES (Manufacturing Execute System) and a transport control device MCS (Material Control System) that receives various instructions from the MES and controls the transport device (OHT: Overhead Hoist Transfer). ) And sharing information such as the factory layout, it is disclosed that transportation efficiency can be improved. Also, a buffer that can directly transfer the object to be transported from the OHT carriage, for example, OHB (Over Head Buffer: shelf under the OHT rail) is provided, and if the next process device group is known in advance, without using a stocker It is disclosed that the object to be processed can be transported to the target apparatus in a short time by carrying the object to be processed in advance to the buffer of the corresponding bay.
- MES Manufacturing Execute System
- MCS Machine Control System
- OHT Overhead Hoist Transfer
- the processing device reports the completion to the production management system MES, and the production management system receiving this reports the collection and delivery of the object to be processed in the transport control device. Is instructing.
- the processing apparatus informs the production management system MES that the load port is available and the object to be processed next can be received.
- the production management system that has received the report designates the object to be processed next in the processing apparatus and instructs the transport control apparatus to deliver to the processing apparatus. In the system configured as described above, it takes a long time for the object to be processed to be collected by the transfer apparatus after the processing of the object to be processed in the processing apparatus is completed.
- This invention is made
- a production efficiency improving apparatus includes a first communication unit that communicates information with a plurality of processing apparatuses that process a target object, and a transport apparatus that transports the target object to the plurality of processing apparatuses. Based on the information communicated by the first communication means with the second communication means that communicates control information related to the control of the conveyance apparatus with the conveyance system, the processing apparatus that is the communication destination of the information is processed.
- a transport time predicting unit that predicts a transport time that requires transport of the body, and a control to the transport system so that the transport device arrives at the processing device that is the communication destination of the information at the transport time predicted by the transport time predicting unit And generating means for generating information.
- the production efficiency improving apparatus is characterized in that the control information includes an instruction to move a transfer apparatus not equipped with an object to be processed to a processing apparatus that is a communication source of the information.
- the production efficiency improving apparatus is characterized in that the control information includes an instruction to move a transfer device on which an object to be processed is mounted to a processing device that is a communication source of the information.
- the transfer system includes a plurality of transfer devices, and the control information is compared with a region where there are few processing devices in which processing on an object to be processed is completed within a predetermined period. , Including an instruction to move the transport device so that the transport device is unevenly distributed in an area where there are many processing devices in which the processing ends within the period.
- the generating means instructs the transport apparatus to wait when the transport apparatus arrives at the processing apparatus before the processing of the object to be processed is completed by the processing apparatus.
- Control information including an instruction to circulate the transport apparatus around the processing apparatus or an instruction to move the transport apparatus to a predetermined location is generated.
- control information includes a transfer device that is not mounted with a target object and a transfer device that is mounted with a target object to be processed by the processing device in this order. It includes an instruction to move each transport device so as to arrive at the device.
- the production efficiency improving apparatus includes means for directly or indirectly communicating production execution control information transmitted from a production execution control apparatus that controls operations of the processing apparatus and the transfer apparatus, and the production execution It is characterized in that the contents of the production execution control information transmitted from the control device and the contents of the control information generated by the generating means do not contradict each other.
- the production efficiency improving apparatus further comprises means for predicting a required travel time, which is a time required for the transport device to arrive at the processing device that is the communication source of the information at the transport time, and the control information includes: It has a movement start time which is a time to start the movement of the transfer device, and the movement start time is a time before the required movement time from the transfer time.
- the transport time is when the processing in the processing apparatus is completed and the processing object can be taken out by the transport apparatus, and the unprocessed target to be processed in the processing apparatus. It is characterized by including a time when the processing body is lost or a time between each time.
- the processing apparatus is configured to provide information on the remaining processing time of the target object that has been input to the processing apparatus, and the target object to be processed next in order to continue processing. It is configured to communicate with information related to calculation of the required time, and processing of the object to be processed put into each processing device is completed based on the information communicated with a plurality of the processing devices.
- the production efficiency improving apparatus includes means for communicating the actual time actually required for processing on the object to be processed by the processing device or the actual end time when the processing is actually ended, the expected end timing, the actual time or Means for associating and storing the actual end time and information used for predicting the end prediction timing, wherein the generation means generates control information using the stored information.
- the production efficiency improving apparatus is characterized in that the information communicated by the first communication means includes information indicating that the processing for the object to be processed is in a specific processing step.
- the information communicated by the first communication means includes information indicating a time required for processing the object to be processed by the processing device or a scheduled time when the processing ends. To do.
- the production efficiency improving apparatus is characterized in that the information communicated by the first communication means includes information indicating that the processing apparatus is in a specific state.
- the information communicated by the first communication means includes information related to an actual time required for past processing in the processing apparatus or an actual time when the processing is completed. .
- the production efficiency improving apparatus is characterized in that the first communication means receives information transmitted when the processing on the object to be processed is in a specific processing step in the processing apparatus. To do.
- the production efficiency improving apparatus includes means for requesting the processing apparatus information necessary for the processing apparatus to predict a transport timing that requires transport of an object to be processed. Information transmitted from the processing device is received in response to a request.
- the production efficiency improving apparatus includes means for requesting the processing apparatus to set a timing for transmitting information for predicting a transport timing when the processing apparatus needs to transport the workpiece. .
- the production efficiency improving method communicates information with a plurality of processing apparatuses that process an object to be processed, and a transfer system having a transfer apparatus that transfers the object to be processed to the plurality of processing apparatuses. Then, the control information related to the control of the transport device is communicated, and based on the communicated information, the unloading time required for unloading the object to be processed or the unloading of the object to be processed by the processing device to which the information is communicated is completed. And the control information to the transport system is generated so that the transport device arrives at the processing device that is the communication destination of the information at a time according to the predicted transport time or the transport time. And
- a computer program includes: a first communication unit that communicates information with a plurality of processing devices that process a target object; and a transport device that transports the target object to the plurality of processing units. And a second communication unit that communicates control information related to the control of the transport apparatus with the transport system having the information processing apparatus, and a processing apparatus that is a communication destination of the information is based on the information communicated by the first communication unit. Means for predicting the unloading time required for unloading the processing body or the unloading time required for loading, and the transport device arrives at the processing device to which the information is communicated at a time corresponding to the unloading time or the loading time predicted by the means. As described above, it functions as generation means for generating control information for the transport system.
- the information transmitted from the processing device is received, and the processing device predicts the transport time required to transport the object to be processed using the received information. And the control information which moves a conveying apparatus to the said processing apparatus is produced
- the transfer device not mounted with the object to be processed is moved to the processing device.
- the transfer device collects the processed object from the processing device.
- the transfer device carrying the object to be processed is moved to the processing device. That is, the transfer device carrying the object to be processed next in the processing device is moved to the processing device.
- a processing apparatus processes the to-be-processed object conveyed by the conveying apparatus.
- the conveying device is unevenly distributed in an area where there are many processing devices that complete processing within a predetermined period. Therefore, it is possible to efficiently convey the object to be processed to the processing apparatus.
- the transfer device waits. Moreover, you may make a conveyance apparatus circulate around a processing apparatus. Furthermore, you may move a conveying apparatus to a predetermined location, for example, a garage. Therefore, it is possible to efficiently collect the processed object to be processed from the processing apparatus and to convey the next necessary object to be processed to the processing apparatus while avoiding the congestion of the conveying apparatus.
- the transfer device that does not have the object to be processed is moved to the processing device, and the processed object to be processed is recovered from the processing device. Then, the transfer device carrying the object to be processed next is moved to the processing apparatus, and the object to be processed is processed by the processing apparatus.
- the production execution control information transmitted from the production execution control device is received directly or indirectly.
- the production execution control device is a device that positively controls the operations of the processing device and the transfer system.
- the production efficiency improvement device is a device that speculatively controls the operation of the transfer device at a stage before the control contents for the transfer device and the processing device are determined in order to improve the transfer and processing of the object to be processed.
- the production efficiency improving apparatus matches the control information generated by itself with the production execution control information transmitted from the production execution control apparatus so as not to contradict each other. Therefore, the control information generated by the production efficiency improving device does not hinder the operation such as malfunction of the transport system.
- the travel time required for the transport device to arrive at the processing device is predicted at the predicted transport time. And the time before the said movement required time from the said conveyance time is made into the movement start time.
- the control information includes information related to the movement start timing.
- an unprocessed processing target to be processed in the processing device is included in the transporting time. Includes the time to disappear, or the time between each time.
- the processing apparatus includes information related to the remaining processing time of the object to be processed that has been input to the processing apparatus, and the time required for the next object to be continuously processed. Communicates information related to the calculation of. Based on the information communicated with a plurality of the processing devices, an end time at which the processing of the processing object put in each processing device ends, and a starting time at which each processing device requires the next processing target Based on the calculated end time and start time, the priority order of the processing devices to which the transport device is to be moved is determined.
- the predicted processing time, the actual time actually required for processing the object to be processed by the processing device, or the actual end time when the processing is actually ended, and the information used for prediction of the predicted processing time are stored in association with each other, and the transport timing is predicted using the stored information. Accordingly, the accuracy of the conveyance time is improved.
- the processing apparatus transmits information indicating that the processing for the object to be processed is in a specific processing step.
- the production efficiency improving apparatus receives the information transmitted from the processing apparatus, and predicts the conveyance timing using the information.
- the processing device transmits information indicating a scheduled time at which processing on the object to be processed is completed in the processing device.
- the production efficiency improving apparatus receives the information transmitted from the processing apparatus, and predicts the conveyance timing using the information.
- the information indicating that the processing apparatus is in a specific state other than the processing of the object to be processed is transmitted.
- the production efficiency improving apparatus receives the information transmitted from the processing apparatus, and predicts the conveyance timing using the information.
- the processing device transmits information related to the past processing end time, and the production efficiency improvement device predicts the processing end time using the information.
- the processing device transmits information used for prediction of the transport timing when processing on the object to be processed enters a specific processing step in the processing device.
- the production efficiency improvement device requests information necessary for prediction of the transport timing to the processing device, and the processing device transmits the information to the production efficiency improvement device in response to the request.
- the production efficiency improving apparatus sets the timing for transmitting information necessary for prediction of the conveyance timing in the processing apparatus.
- the processing device transmits the information to the production efficiency improving device at the set time.
- the present invention it is possible to improve the production efficiency by predicting the processing end time of the object to be processed in the processing apparatus and moving the transfer apparatus speculatively.
- 10 is a flowchart showing a processing procedure related to production efficiency improvement in Modification 1.
- 10 is a timing chart showing arrival timings of an empty transport device and a transport device mounted with an object to be processed according to Modification 2.
- 10 is a flowchart showing a processing order related to production efficiency improvement in Modification 4.
- FIG. 10 is a block diagram illustrating a configuration example of a production processing system according to Modification Example 5. It is the block diagram which showed the example of 1 structure of the production processing system which concerns on the modification 6.
- FIG. 12 is a flowchart showing a processing order related to production efficiency improvement in Modification 7.
- 12 is a flowchart showing a processing order related to production efficiency improvement in Modification 7.
- FIG. 1 is a block diagram showing a configuration example of a production processing system having a production efficiency improving apparatus according to the present embodiment.
- the production processing system according to the embodiment of the present invention includes a plurality of processing devices 2, a transport system 3 having a plurality of transport devices 32 and a transport control device 31 that controls the operation of the transport device 32, the processing device 2, It has a production execution control device 4 that gives control instructions to the transfer system 3 and controls the operation of each device, and a production efficiency improvement device 1 that communicates between the plurality of processing devices 2 and the transfer system 3.
- the production execution control device 4 constitutes a so-called MES, and the object to be processed should be processed according to the scheduler module that creates a production plan according to the type, specification, etc. of the product to be manufactured, and the created production plan.
- This is a computer having a dispatcher module and the like for specifying the processing device 2 and performing processing for instructing the processing content and the transport control content for the object to be processed to the processing device 2 and the transport system 3, respectively.
- the information transmitted from the production execution control device 4 to the processing device 2 and the transport system 3 to control the operations of the processing device 2 and the transport system 3 will be referred to as production execution control information.
- the processing apparatus 2 is a substrate processing apparatus such as a plasma CVD apparatus, a plasma etching apparatus, or a sputtering apparatus that processes an object to be processed such as a glass substrate for manufacturing an organic EL device or a silicon wafer for manufacturing a semiconductor device or the like. Further, the processing apparatus 2 has a function of transmitting information for predicting the end time of the process to the production efficiency improving apparatus 1 before the process on the object to be processed is completed. Note that, in this embodiment, an example in which various times related to transport control are processed using time is described, but processing may be performed using time based on an arbitrary time point. Further, the processing device 2 has a function of transmitting processing end information indicating that the processing on the object to be processed has ended to the production execution control device 4.
- a substrate processing apparatus such as a plasma CVD apparatus, a plasma etching apparatus, or a sputtering apparatus that processes an object to be processed such as a glass substrate for manufacturing an organic EL device or a silicon wafer for manufacturing a semiconductor
- FIG. 2 is a block diagram illustrating a configuration example of the processing device 2.
- the processing apparatus 2 is, for example, a multi-chamber type substrate processing system.
- the processing device 2 includes first and second load ports 21a and 21b (LP: Load Port) on which the FOUP is placed to deliver a FOUP (FOUP: Front Open Unified Pod) that accommodates the workpiece W.
- the provided load module 22 is provided.
- a transfer module 24 (TM: Transfer ⁇ ⁇ ⁇ ⁇ Module) is connected to the load module 22 via loadlock modules 23a and 23b (LLM: Load Lock Module).
- the vacuum robot included in the transfer module 24 transports the workpiece W carried through the load lock modules 23a and 23b to the process modules 25a, 25b, 25c, and 25d (PM: Process Module).
- the process modules 25a, 25b, 25c, and 25d perform predetermined processing on the workpiece W according to the recipe.
- the processed workpiece W follows the reverse path, is collected in the FOUP placed on the first or second load port 21a, 21b, and is carried out from the load port 21a, 21b in units of FOUP.
- the transport device 32 is, for example, a transport shuttle that travels on a track installed on a ceiling or a floor, an automatic guided vehicle that travels on a predetermined route, and the like, and transports a FOUP.
- the transport device 32 moves between the plurality of processing devices 2 and the stocker storing the FOUP in accordance with an instruction given from the transport control device 31, and transports the object to be processed accommodated in the FOUP.
- the conveyance control device 31 constitutes a so-called MCS, and in accordance with one or both of production execution control information given from the production execution control device 4 and control information given from the production efficiency improving device 1 described later, the conveyance device It is a computer which controls operation
- FIG. 3 is a block diagram showing a configuration example of the production efficiency improving apparatus 1 according to the present embodiment.
- the production efficiency improving device 1 communicates information with the processing device 2, and based on the information acquired by the communication, the processing device 2 that is the transmission source of the information finishes the processing on the object to be processed (hereinafter, referred to as the processing efficiency improvement device 1).
- a function for predicting the processing end time), a function for setting the content of information from the processing device 2 and a communication timing and instructing the processing device 2, and a processing device that is the transmission source of the information according to the predicted processing end time 2 is a computer having a function of generating instruction information for starting the movement so that the transport device 32 arrives at 2.
- the instruction information is one piece of control information related to the control of the transport device 32.
- the production efficiency improvement apparatus 1 is a computer that includes a control unit 11 that controls the operation of each component of the production efficiency improvement apparatus 1, for example, a CPU (Central Processing Unit).
- the control unit 11 includes an internal storage device 13 such as a ROM or a RAM connected via a bus, a hard disk drive, a solid state drive, a CD-ROM that is a device that can read data from a portable recording medium.
- An external storage device 12 such as a ROM drive, first to third communication units 14, 15, 16 and a clock unit 17 are connected.
- the ROM is a non-volatile memory such as a mask ROM or EEPROM that stores a control program necessary for the operation of the computer.
- the RAM is a volatile memory such as a DRAM or SRAM that temporarily stores various data generated when executing the arithmetic processing of the control unit 11 and a control program necessary for the operation of the computer.
- the first to third communication units 14, 15, and 16 are interfaces for transmitting and receiving information to and from the processing device 2, the conveyance control device 31, and the production execution control device 4, respectively. The transmission / reception of various information by the first to third communication units 14, 15, 16 is controlled by the control unit 11.
- the computer program 5a is a portable medium recorded in a computer-readable manner, such as a recording medium 5 such as a CD (Compact Disc) -ROM, a DVD (Digital Versatile Disc) -ROM, a BD (Blu-ray Disc), or a hard disk drive. Recorded on a solid state drive.
- the control unit 11 reads the computer program 5a from a portable medium or a hard disk drive in which the computer program 5a is recorded, and stores it in the internal storage device 13.
- the optical disk and the optical disk drive are examples of the recording medium 5 and the external storage device 12, and the computer program 5a is recorded on a flexible disk, a magnetic optical disk, an external hard disk, a semiconductor memory, or the like in a computer-readable manner.
- the external storage device 12 may be configured to read.
- the computer program 5a according to the present invention may be downloaded from an external computer (not shown) connected to the communication network.
- FIG. 4 and 5 are flowcharts showing the processing procedure of the production efficiency improving device 1.
- FIG. ⁇ Basic production efficiency flow> The processing device 2 executing the process on the object to be processed transmits information necessary for predicting the time when the process on the object to be processed is completed to the production efficiency improving device 1 (step S11).
- FIG. 6 is a flowchart illustrating an example of an information transmission procedure in the processing device 2.
- the processing device 2 starts processing on the object to be processed (step S51). And the processing apparatus 2 determines whether the process with respect to a to-be-processed object exists in the set specific process process (step S52). When it determines with it being in a specific processing process (step S52: YES), the processing apparatus 2 transmits the information which shows that the process with respect to a to-be-processed object exists in a specific processing process to the production efficiency improvement apparatus 1 (step S53). ). This information is information for reporting that the processing sequence in the processing device 2 has passed a specific processing step.
- step S53 determines whether the process for the object to be processed has been completed (step S54). . If it is determined that the process has not been completed (step S54: NO), the processing device 2 returns the process to step S52 and continues the process on the object to be processed. If it is determined that the process has been completed (step S54: YES), the processing device 2 transmits end information to the production execution control device 4 (step S55), and the process ends.
- the set specific processing step is that the number of unprocessed objects accommodated in each FOUP is predetermined for each FOUP arranged in the first and second load ports 21a and 21b.
- the processing apparatus 2 is set as a process that has become less than the number, and the processing apparatus 2 performs a timing at which the number of unprocessed objects accommodated in the FOUP becomes less than a predetermined number for each FOUP placed on the load ports 21a and 21b.
- the set specific processing step is, for example, three steps before the end step of the processing sequence being executed. These are processing steps set as predetermined processing steps.
- FIG. 7 is a flowchart showing another example of the information transmission procedure in the processing device 2.
- the processing device 2 starts processing on the object to be processed (step S71). And the processing apparatus 2 determines whether the process with respect to a to-be-processed object exists in a specific process process (step S72). When it determines with it being in a specific process process (step S72: YES), the processing apparatus 2 transmits the information containing the scheduled completion
- the scheduled processing end time is an example, and may be replaced with information indicating a scheduled timing when the processing ends.
- the scheduled end time transmitted from the processing device 2 may be calculated by a predetermined arithmetic expression based on the recipe information, or may be calculated statistically from the past processing end time.
- the processing device 2 determines whether or not the process on the object to be processed has been completed (step S74). . If it is determined that the process has not ended (step S74: NO), the processing device 2 returns the process to step S72 and continues the process on the object to be processed. If it is determined that the process has been completed (step S74: YES), the processing device 2 transmits end information to the production execution control device 4 (step S75), and the process ends.
- the production efficiency improving device 1 predicts the processing end time based on the information transmitted from the processing device 2 according to the above-described processing procedure. Note that the time indicated by the information transmitted from the processing device 2 may be directly handled as the processing end time.
- FIG. 8 is a flowchart showing another example of the information transmission procedure in the processing device 2.
- the processing device 2 starts processing on the object to be processed (step S91). And the processing apparatus 2 determines whether the process with respect to a to-be-processed object exists in a specific process process (step S92). When it determines with it being in a specific process process (step S92: YES), the processing apparatus 2 transmits the information which concerns on the performance of the past process end time when the process with respect to a to-be-processed object is complete
- the information related to the results is, for example, information related to the actual time required for the past processing in the processing device 2 or the actual time when the processing is completed.
- step S94 determines whether the process for the object to be processed has been completed. . If it is determined that the process has not been completed (step S94: NO), the processing device 2 returns the process to step S92 and continues the process on the object to be processed. If it is determined that the process has ended (step S94: YES), the processing device 2 stores the processing end time (step S95), transmits the end information to the production execution control device 4 (step S96), and ends the process. .
- the production efficiency improvement device 1 statistically processes the information transmitted from the processing device 2 according to the above-described processing procedure, and predicts the processing end time. For example, the processing end time is predicted based on the average value, variance, maximum value, minimum value, median value, mode value, etc. of the time required for processing.
- the information related to the past processing end time results may be appropriately processed on the processing device 2 side and transmitted to the production efficiency improving device 1, or the raw data of the processing end time recorded by the processing device 2 may be used. You may transmit to the production efficiency improvement apparatus 1.
- FIG. 9 is a flowchart illustrating another example of the information transmission procedure in the processing device 2.
- the process module 25a of the processing apparatus 2 starts a process that does not use an object to be processed such as a dry cleaning process for maintenance (step S111). Then, the processing device 2 determines whether or not the processing device 2 is in a specific state (step S112). When it determines with it being in a specific state (step S112: YES), the processing apparatus 2 transmits the information which shows that it is in a specific state to the production efficiency improvement apparatus 1 (step S113).
- step S113 When the process of step S113 is completed, or when it is determined that the processing apparatus 2 is not in a specific state (step S112: NO), the processing apparatus 2 determines whether the process has been completed (step S114). . If it is determined that the process has not ended (step S114: NO), the processing device 2 returns the process to step S112 and continues the process. When it determines with complete
- the production efficiency improving device 1 predicts the time at which this processing ends based on the information indicating that it is in this specific state, and directs the object to be processed next to the processing device 2 in accordance with the time.
- the object to be processed next to the processing device 2 in accordance with the time at which the predicted processing ends is transmitted to the transport control device 31 and the object to be processed is delivered to the processing device 2. It is possible to reduce the time from the end of the process without using the object to be processed in the process module 25a of the apparatus 2 until the start of the process to the object to be processed, which contributes to the production in the process module 25a.
- the degree of processing can be increased and the processing efficiency can be increased.
- the statistical value of the time required to deliver the object to be processed next to the processing device 2 is the time before the statistical value obtained from the timing when the process not using the object is completed. More preferably, the timing is set as a specific state.
- FIG. 10 is a flowchart illustrating another example of the information transmission procedure in the processing device 2.
- the control unit 11 of the production efficiency improving apparatus 1 transmits request information for requesting information necessary for predicting the end of processing for the object to be processed to the processing apparatus 2 (step S131).
- the processing device 2 receives the request information transmitted from the production efficiency improving device 1 (step S132). Then, the processing device 2 provides the production efficiency improvement device 1 with information necessary for predicting the end of processing, such as the processing steps for the target object when requested, the state of the processing device 2, the processing recipe for the target object, and the like. Transmit (step S133), and the process ends.
- FIG. 11 is a flowchart relating to the setting of the transmission timing of information necessary for processing end prediction in the processing device 2.
- the control unit 11 of the production efficiency improvement apparatus 1 accepts the setting of the timing for transmitting information necessary for predicting the end of processing to the production efficiency improvement apparatus 1 using an input device (not shown) (step S151). And the control part 11 transmits the setting information which requests
- the processing device 2 receives the setting information transmitted from the production efficiency improving device 1 (step S153). Then, the processing device 2 sets the information transmission timing according to the content of the setting information received in step S153 (step S154). If the transmission timing has already been set, it is changed to a new setting timing. Thereafter, the processing device 2 transmits information necessary for processing end prediction to the production efficiency improving device 1 at the timing set in step S154.
- a setting may be changed automatically.
- the setting is changed so that the information transmission timing is advanced.
- the speculative movement instruction refers to an instruction to start movement so that the transport device 32 arrives at the processing device 2 that is the transmission source of the information at a time according to the predicted processing end time.
- the setting is changed so as to delay the information transmission timing.
- the control unit 11 of the production efficiency improving device 1 receives the information transmitted from the processing device 2 at the first communication unit 14 (step S12), and based on the received information, the processing device that is the transmission source of the information
- the process end time at which 2 finishes the process is predicted (step S13).
- the processing end time is, for example, that processing in the processing apparatus 2 is completed, and the processed object is collected in the FOUP placed on the load port, and the FOUP can be carried out. It is time of.
- the control unit 11 generates speculative instruction information for starting the movement of the transport device 32 to the processing device 2 that is the transmission source of the information at a timing according to the predicted processing end time based on the predicted processing end time.
- the generated speculative instruction information is transmitted to the transport control device 31 by the second communication unit 15 (Step S15).
- the speculative instruction information is an example of control information related to the control of the transport device 32.
- the production efficiency improving apparatus 1 uses the information for instructing the processing apparatus 2 to prepare the object to be collected from the processing apparatus 2 at the scheduled arrival time of the transport apparatus 32. You may comprise so that it may transmit to the processing apparatus 2.
- FIG. When the processing device 2 receives the information transmitted from the production efficiency improving device 1, the processing device 2 executes a preparation process for delivering the object to be processed to the transport device 32.
- the timing for transmitting speculative instruction information for starting the movement of the transfer device 32 is the time required for the transfer device 32 to move to the processing device 2 and the processing in the processing device 2 is completed. It is determined based on the scheduled time at which the finished object to be processed can be taken out. For example, the movement of the transfer device 32 may be instructed so that the transfer device 32 arrives at the processing device 2 in accordance with the time when the object to be processed can be taken out from the processing device 2. In addition, when there is a low possibility of the traffic jam in the transport apparatus 32, the transport apparatus 32 may arrive before the time when the object to be processed can be taken out from the processing apparatus 2.
- the transport device 32 is delayed from the scheduled time at which the object to be processed can be taken out from the processing device 2 in order to avoid the traffic jam caused by the movement of the transport device. May arrive at the processing device 2.
- Other suitable movement instruction timings will be described in a later-described modification.
- the time required for the transfer device 32 to move to the processing device 2 takes into account the distance between the transfer device 32 and the processing device 2, the moving speed of the transfer device 32, the transfer route, the traffic jam situation, and other conditions. Is calculated. For example, the time required for movement may be recorded and statistically calculated based on the recorded time, or an internal simulation may be performed based on the position, conveyance path, and movement speed of the conveyance device 32. It may be calculated by performing, or may be calculated by simulating the movement schedule of each of the plurality of transfer apparatuses 32 and the congestion status of the transfer path based on the movement schedule.
- the conveying device 32 is unevenly distributed in a region where there are a large number of processing devices 2 whose processing ends within the period compared to a region where there are few processing devices 2 where processing for the object to be processed ends within a predetermined period.
- the instruction information may be included in the instruction information. Insignificant congestion and depopulation of the transport device 32 can be prevented, and the transport device 32 can be moved to the processing device 2 more efficiently.
- the conveyance control device 31 receives the speculative instruction information transmitted from the production efficiency improving device 1 (step S16). Then, based on the received speculative instruction information, the transport control device 31 executes the vehicle allocation scheduling of the transport device 32 and the standby process of the transport device 32 (step S17), and transmits a movement instruction to the empty transport device 32. (Step S18).
- the instruction given in step S18 is an instruction related to speculative preparation that is performed prior to the definitive control instruction transmitted from the production execution control device 4.
- the collection instruction may be transmitted at the same time as the movement instruction is transmitted to the conveying device 32 (step S18).
- the conveyance device 32 receives the movement instruction from the conveyance control device 31 (step S19). Then, the empty transfer device 32 moves to the vicinity of the instructed processing device 2 in accordance with the received instruction (step S20). That is, the transport device 32 for collecting the object to be processed processed by the processing device 2 has moved to the processing device 2 prior to an instruction from the production execution control device 4.
- the conveyance device 32 mounted on the object to be processed in the vicinity of the instructed processing device 2 (hereinafter referred to as the first processing device 2), specifically, the object to be processed next in the first processing device 2. Is moved (step S21).
- the processing apparatus 2 in the process immediately before the first processing apparatus 2 (hereinafter referred to as the second processing apparatus 2).
- the stocker stores the object to be processed next in the second processing apparatus 2 or in the processing apparatus 2.
- the empty transfer device 32 is moved to (not shown), and the workpiece to be processed next is mounted, and then the transfer device 32 is moved to the designated first processing device 2.
- the processing apparatus 2 finishes the process on the object to be processed (step S22), and transmits end information indicating that the process is completed to the production execution control apparatus 4 (step S23).
- the production execution control device 4 receives the end information from the processing device 2 (step S24), and transmits definite conveyance instruction information to the production efficiency improving device 1 (step S25).
- the conveyance instruction information is one piece of production execution control information.
- the control unit 11 of the production efficiency improving device 1 receives the conveyance instruction information transmitted from the production execution control device 4 by the third communication unit 16 (step S26). Then, the control unit 11 matches the contents of the speculative instruction information generated in step S14 with the contents of the conveyance instruction information received in step S26 (step S27), and the matched conveyance instruction information is transferred to the conveyance control device 31. (Step S28).
- the processing apparatus 2 finishes the processing to the production execution control apparatus 4 and can carry it out.
- Send information When the production execution control device 4 receives information indicating that the processing is completed and can be carried out, the production execution control device 4 conveys an instruction to the conveyance control device 31 to collect the object to be processed from the processing device 2.
- Send instruction information When the conveyance control apparatus 31 receives the conveyance instruction information, the conveyance control apparatus 31 moves the conveyance apparatus 32 to the processing apparatus 2 according to the conveyance instruction information, and collects the object to be processed.
- the production efficiency improvement apparatus 1 issues a process end report from the processing apparatus 2 in order to eliminate the need for major changes to such an existing sequence.
- the transport device 32 is moved so that the transport device 32 reaches the processing device 2 based on the predicted timing of the end of processing, and the transport device 32 corresponds to the destination processing device 2.
- the transfer device 32 stays at a position corresponding to the processing device 2 and waits. What is necessary is just to comprise so that the vicinity may be made to go around.
- the conveyance control device 31 receives an instruction to collect the object to be processed from the production execution control device 4, the object to be processed from the processing device 2 by the conveyance device 32 in response to the reception. To collect.
- speculative instruction information for instructing speculative conveyance to the conveyance device 32 and conveyance instruction information for instructing collection or delivery of the object to be processed from the processing device 2 to the conveyance device 32 are matched with the control sequence of the existing transfer execution control device 4 so as to wait for an instruction from the production execution control device 4.
- the conveyance device 32 waits for an instruction from the production execution control device 4 and collects the object to be processed.
- the conveyance device 32 When the sequence is allowed to be changed and the production efficiency is further improved, the collection of the object to be processed after completion of the processing is performed even before the conveyance instruction information is transmitted from the production execution control device 4.
- the processing device 2 are executed as soon as the workpiece can be collected, and if the next transport destination processing device is not instructed by the production execution control device, it is transported to a nearby buffer or stocker and stored. By doing so, it is possible to make it possible to respond as soon as it is instructed to carry in the object to be processed by the apparatus, or to increase the production efficiency of the instruction relating to the conveyance destination to which the object is next conveyed Device 1 or Requests the conveyance control unit production execution control apparatus than 31 may take a matching so as to convey the ⁇ processed in the next processing device or stocker based on the obtained instruction.
- the conveyance device 32 may collect the object to be processed from the processing device 2 or place the FOUP on the processing device 2. .
- the conveyance control device 31 transmits information indicating the processing content of the conveyance device 32 to the production execution control device 4, and the production execution control device 4 performs the subsequent processing device 2 and conveyance device 32 based on the information. It is preferable to correct the control content for.
- the transport control device 31 receives the matched transport instruction information transmitted from the production efficiency improving device 1 (step S29). Then, the conveyance control device 31 transmits a collection instruction for instructing collection of the object to be processed and a conveyance instruction for conveying the processed object to be processed to another processing apparatus 2 or a stocker (not shown). (Step S30).
- the empty conveyance device 32 receives the collection instruction and the conveyance instruction transmitted from the conveyance control device 31 (step S31), moves to the designated processing device 2 according to the received collection instruction, and collects the object to be processed. (Step S32).
- the conveyance device 32 on which the collected object to be processed is loaded conveys the object to be processed to the processing device 2 or the stocker (step S33).
- the movement of the empty transfer device is instructed before the transfer of the transfer device mounted with the object to be processed is shown.
- the movement of the transfer device may be started first, and then the movement of the empty transfer device may be instructed.
- the transfer device mounted with a target object requires more time to move, It may be instructed to move the transfer device mounted on the processing body.
- FIG. 12 is a flowchart illustrating a processing procedure when the speculative instruction to the transport device 32 is not correct.
- the conveyance control device 31 monitors the state of the conveyance device 32 and the production execution control information transmitted from the production execution control device 4, and the conveyance device 32 arrives before the processing of the object to be processed in the processing device 2 is completed. I can recognize that.
- the conveyance control device 31 transmits a speculative movement failure notification to the production efficiency improvement device 1 when the conveyance device 32 arrives before the processing of the object to be processed in the processing device 2 is completed (step S171).
- the control unit 11 of the production efficiency improving device 1 receives standby or patrol of the transport device 32 or instruction information for moving the transport device 32 to the garage. Generate (step S173). And the control part 11 transmits the instruction information produced
- the conveyance control device 31 When the conveyance control device 31 receives the instruction information transmitted from the production efficiency improvement device 1 (step S175), the conveyance control device 31 waits for the conveyance device 32 that has arrived at the processing device 2 or goes around, or moves the conveyance device 32 to a predetermined garage. An instruction to move is transmitted to the transport device 32 (step S176).
- the transport device 32 waits around the processing device 2 according to the instruction of the transport control device 31, circulates around the periphery, or moves to a predetermined garage (step S177).
- the processing end time of the object to be processed in the processing apparatus 2 is predicted and the object to be processed is speculatively transferred, thereby shortening the transfer time of the transfer apparatus 32 and processing on the object to be processed.
- Efficiency can be improved and production efficiency can be improved.
- the operation status of the processing device 2 is transmitted to the production execution control device 4 having a high processing load even in the current state and the prediction processing is executed, the processing load of the production execution control device 4 further increases, and the transport device 2 and the processing As a result, the control of the apparatus 2 is delayed, and the production efficiency may be deteriorated.
- the conveyance device 32 can be moved speculatively under the control of the production efficiency improving device 1, so that the production efficiency can be improved while avoiding such a problem.
- the example in which the time at which the processing of the object to be processed in the processing device 2 is predicted is predicted and the transport device 32 is moved to the vicinity of the processing device 2 has been described. You may comprise so that speculative movement of the conveying apparatus 32 may be instruct
- an event signal is output from the processing apparatus 2 at a specific timing, and when the production efficiency improving apparatus 1 receives the event signal output from the processing apparatus 2, the production apparatus 1 immediately processes the transport apparatus 32. You may comprise so that it may move to the apparatus 2.
- the content and output timing of the event signal are not particularly limited. Specifically, the event signal is output from the processing device 2, a signal output when the processing on the object to be processed enters a specific process, a signal output when the processing device 2 is in a specific state, or the processing device 2. A signal having processing end time information.
- the production efficiency improving device 1 when receiving the event signal output from the processing device 2, is configured to move the transfer device 32 to the processing device 2 after a predetermined time from receiving the event signal. May be.
- the production efficiency improving apparatus 1 may transmit an instruction to move the transport apparatus 32 to the transport control apparatus 31.
- the processing device 2 is configured to transmit the processing status to the production execution control device 4 and cause the production execution control device 4 to execute the prediction process, the processing load of the production execution control device 4 is still high at present.
- the processing load increases, and the control of the transfer device 32 and the processing device 2 is delayed, which may deteriorate the production efficiency.
- an increase in the processing load of the production execution device 4 can be minimized by providing the production efficiency improvement device 1 separately from the transport control device 31 and the production efficiency improvement device 1. .
- the production execution device 4, the conveyance control device 31, and the production efficiency improvement device 1 are individually provided.
- the functions of the production efficiency improvement device 1 and the conveyance control device 31 are combined into one computer. It may be constructed.
- FIG. 13 is a flowchart illustrating a processing procedure related to production efficiency improvement in the first modification.
- the control unit 11 of the processing apparatus 2 and the production efficiency improving apparatus 1 performs transmission / reception of information (steps S191 and 192) and predicts processing end for the object to be processed in the processing apparatus 2 (steps S11 to S12 in FIG. 4) ( Step S193).
- the processing device 2 that has finished the process on the object to be processed transmits the actual end time when the process on the object to be processed has actually been finished to the production efficiency improving device 1 (step S194).
- the actual end time actually required to finish the process on the object to be processed may be transmitted, and the following process may be executed using the actual end time.
- the control unit 11 of the production efficiency improving device 1 receives the actual end time transmitted from the processing device 2 (step S195), and uses the predicted end time, the actual end time transmitted from the processing device 2, and the process end prediction.
- the information used is associated with and stored in the internal storage device 13 (step S196).
- the information associated with the processing end time and the actual end time includes, for example, an ID for identifying the processing device 2, a recipe, and the like.
- the end prediction time, the actual end time, and the information used for the end prediction are stored in association with each other. Information related to the process end prediction stored in the internal storage device 13 is used for the process end prediction.
- the production efficiency improving device 1 Receives the information (step S198), and uses the received information and the information stored in the internal storage device 13 to predict the time at which the processing device 2 that is the transmission source of the processing ends (Ste S199).
- the statistical calculation method for predicting the end of processing is not particularly limited.
- the processing end time is calculated by calculating the maximum value, minimum value, average value, mode value, variance, and the like of the processing end time based on the information stored in the internal storage device 13. Thereafter, the same processing as the processing after step S14 in FIG. 4 is executed.
- the processing end time is statistically calculated, it is possible to speculatively instruct the movement of the transport device 32 at a more appropriate timing. Further, production efficiency can be improved.
- FIG. 14 is a timing chart showing the arrival timings of the empty transport device and the transport device mounted with the object to be processed according to the second modification.
- 14A is a probability distribution of arrival timings of a transport device mounted on an object to be processed
- FIG. 14B is a probability distribution of arrival timings of empty transport devices
- FIGS. 14C and 14D are first and second load ports 21a, The timing with which the process with respect to the to-be-processed object mounted in 21b is performed is shown.
- the production efficiency improving apparatus 1 requires a time required for the transport apparatus 32 to move to the processing apparatus 2 and a target object placed on the first load port 21a in the processing apparatus 2.
- the processing is completed, and the processing for the processing object placed on the second load port 21b and the first time at which the processing object for which the processing has been completed can be taken out are scheduled to end.
- the movement of the transfer device 32 is instructed at a timing at which the transfer device 32 can arrive between the first time and the second time.
- the control unit 11 of the production efficiency improving apparatus 1 determines the probability distribution of the time when an empty transfer device arrives at the processing device 2 and the probability distribution of the time when the transfer device mounted on the object to be processed arrives at the processing device 2.
- Each probability distribution calculated is distributed between the first time and the second time, and the probability distribution related to the arrival time of the empty transport device is the probability related to the arrival time of the transport device mounted on the workpiece.
- the movement of each transport device 32 is instructed to be distributed closer to the first time than the distribution. More preferably, the movement of the transport device 32 may be instructed so that the probability distributions do not overlap, that is, the ratio of the overlapping portions of the probability distributions is less than a predetermined value.
- the first and second times can be predicted based on the load port switching time, the number of objects to be processed, the recipe, and the like.
- the object to be processed placed on the first load port 21 a when the object to be processed placed on the first load port 21 a is being processed, the object to be processed is based on the information transmitted from the processing device 2.
- the first time at which the process on the body is completed and the object to be processed on which the process is completed can be taken out is predicted.
- the process is executed on the object to be processed placed on the second load port 21b.
- the control unit 11 performs all the processes on the object to be processed. A second time to end is predicted using the recipe. Then, the control unit 11 estimates the time required for the transfer device 32 to move to the processing device 2, and between the first time and the second time, The transfer device 32 is instructed to move at a timing at which the transfer device mounted on the processing body can arrive in this order.
- the production efficiency improving device 1 According to the production efficiency improving device 1 according to the second modification, it is possible to speculatively instruct the movement of the transport device 32 at an appropriate timing, and to further improve the production efficiency.
- Modification 3 Priority scheduling
- the production efficiency improving device 1 predicts the processing end time, thereby enabling the unloading from the processing device, and the timing at which the processing device 2 no longer has an object to be processed. Ask for.
- the processing apparatus 2 even when the FOUP containing the object to be processed that can be unloaded from the processing apparatus 2 after the processing is completed is on one load port, the processing apparatus 2.
- the process module There is a grace period before it reaches a state where it cannot be processed by the body.
- the information concerned is placed on the other load port starting from the time when the processing of the object to be processed contained in the FOUP placed on at least one load port is completed and can be collected by the transfer device.
- the transport control device 31 may control so that the transport device 32 arrives at the processing device 2 between the start point and the end point of the transport-necessary timing.
- the transport control device 31 has the time width. In consideration of the transport priority at 31, it becomes easy to schedule movement of the transport device 32 in which congestion of the transport device 32 in the transport path is reduced.
- processing on the object to be processed in the processing device 2 is completed, and a report that the processing is completed is sent from the processing device 2 to the production execution control device 4, and the processing device is sent from the production execution control device 4 to the transfer control device 31.
- the conveyance control device 31 determines the positions and movement states of the plurality of conveyance devices. In consideration of the above, it may be constructed so as to move without delay in response to the collection instruction from the production execution control device 4 so that congestion does not occur.
- the process module Since the processing can be continued continuously, high production efficiency of the processing apparatus 2 can be maintained.
- FIG. 15 is a flowchart showing a processing order related to production efficiency improvement in the fourth modification.
- transfer instruction information is transmitted from the production execution control device 4 (step S211), and the production efficiency improving device 1 receives the transfer instruction information (step S212), the production efficiency
- the control unit 11 of the processing apparatus 1 requests the processing apparatus 2 for a recipe in which the switching time of the load ports 21a and 21b and the processing contents for the currently processed object are described (step S213).
- the processing device 2 When the processing device 2 receives the switching time of the load ports 21a and 21b and a recipe request from the production efficiency improving device 1 (step S214), the processing device 2 performs the latest load port switching time and the processing contents for the currently processed object. Is transmitted to the production efficiency improving device 1 (step S215).
- the control unit 11 of the production efficiency improving device 1 receives the load port switching time and the recipe transmitted from the processing device 2 (step S216). Based on the current time, the load port switching time, and the recipe, the control unit 11 calculates a time (hereinafter referred to as “remaining process time”) until the current process is completed (step S217). ). Then, when there are a plurality of processing apparatuses 2 that need to transport the object to be processed, the control unit 11 determines the priority order of the processing apparatuses 2 that should arrange the transport apparatus 32 (step S218). The priority is determined so as to be higher as the remaining processing time is shorter.
- control part 11 transmits the collection
- the transport apparatus 32 can be preferentially moved to the processing apparatus 2 that is likely to wait for arrival of the object to be processed.
- FIG. 16 is a block diagram illustrating a configuration example of a production processing system according to the fifth modification.
- the production efficiency improving device 1 includes the first to third communication units 14, 15, and 16 that communicate information with the processing device 2, the conveyance control device 31, and the production execution control device 4.
- the information may be received indirectly from the production execution control device 4.
- you may comprise so that the information transmitted from the production execution control apparatus 4 may be received via the conveyance control apparatus 31.
- an interface for transmitting and receiving information to and from the production execution control apparatus 4 is unnecessary, and a communication system can be constructed at low cost.
- FIG. 17 is a block diagram illustrating a configuration example of a production processing system according to the sixth modification.
- the production efficiency improving device 1 is configured to receive information transmitted from the processing device 2 by using a communication line 33 that transmits and receives information between the transport control device 31 and the transport device 32.
- the communication line 33 is laid along the conveyance path of the conveyance apparatus 32 which comprises the conveyance system 3, for example.
- a communication line with the processing apparatus 2 is located near a stop point for the transfer device 32 that transfers the substrate to be processed included in the transfer system 3 to the processing apparatus 2 via the communication line 33. You may comprise so that the access point (station) which connects may be arrange
- a dedicated line for transmitting and receiving information to and from the processing device 2 is unnecessary, and a communication system can be constructed at a low cost.
- FIG. 18 and FIG. 19 are flowcharts showing a processing order related to the production efficiency improvement in Modification 7.
- the production efficiency improving apparatus 1 according to the modified example 7 uses the information from the production execution control apparatus 4 to give a more accurate speculative movement instruction for the transfer apparatus mounted on the workpiece.
- the processing apparatus 2 that is executing the process on the object to be processed transmits information necessary for predicting the time when the process on the object to be processed is completed to the production efficiency improving apparatus 1 (step S231).
- the control unit 11 of the production efficiency improving device 1 receives the information transmitted from the processing device 2 by the first communication unit 14 (step S232), and based on the received information, the processing device that is the transmission source of the information The process end time at which 2 finishes the process is predicted (step S233).
- control unit 11 generates speculative instruction information for an empty transport device based on the predicted processing end time (step S234), and the speculative instruction information for the generated empty transport device is generated by the second communication unit 15. To the transport control device 31 (step S235).
- the conveyance control device 31 receives the speculative instruction information of the empty conveyance device transmitted from the production efficiency improvement device 1 (step S236). Then, based on the received speculative instruction information, the conveyance control device 31 instructs the allocation and movement of the conveyance device 32, that is, scheduling of dispatch, and standby of the conveyance device 32 (step S237), and the movement of the empty conveyance device. An instruction is transmitted (step S238).
- the transport device 32 receives an instruction from the transport control device 31 (step S239). Then, the transport apparatus 32 that has received the instruction moves to the vicinity of the instructed processing apparatus 2 in accordance with the received instruction (step S240). That is, the transport device 32 for collecting the object to be processed processed by the processing device 2 has moved to the processing device 2 prior to an instruction from the production execution control device 4.
- control unit 11 requests the production execution control device 4 for information related to the next processing, such as the lot number of the object to be processed next in the processing device 2 that is the information transmission source (step S241).
- the production execution control device 4 When the production execution control device 4 receives a request for information related to the next process from the production efficiency improving device 1 (step S242), the production execution control device 4 specifies the designation information of the target object related to the next process or the target object related to the next process. Information for this is transmitted to the production efficiency improvement apparatus 1 (step S243).
- the control unit 11 of the production efficiency improving apparatus 1 receives the information transmitted from the production execution control apparatus 4 (step S244), and generates speculative instruction information for conveying the object to be processed based on the information (step S245).
- the generated speculative instruction information for conveying the object to be processed is transmitted to the conveyance control device 31 by the second communication unit 15 (step S246).
- the conveyance control device 31 receives the speculative instruction information for conveying the workpiece transmitted from the production efficiency improving device 1 (step S247). Then, based on the received speculative instruction information, the transfer control device 31 identifies the transfer device 32 on which the specified object is mounted, executes dispatching, and executes standby processing of the transfer device 32. (Step S248), a movement instruction is transmitted (Step S249).
- the instruction performed in step S248 is an instruction related to speculative preparation that is performed prior to the definitive control instruction transmitted from the production execution control device 4, as will be described later.
- the conveying control apparatus 31 determines the current object of the designated to-be-treated object. It is only necessary to specify the storage location, allocate the transfer device 32 for mounting the object to be processed, schedule the mounting and movement of the object to be processed, and wait processing for the transfer device 32.
- the transport device 32 receives an instruction from the transport control device 31 (step S250). And according to the received instruction
- the production efficiency improving device 1 According to the production efficiency improving device 1 according to the modified example 7, it is possible to accurately instruct speculative movement of the transfer device mounted on the object to be processed, and to improve the production efficiency.
- the embodiment disclosed this time has been described as an example in which the object to be processed is transported using a FOUP that is a sealed container having a lid that can be opened and closed on the side surface.
- the SMIF pod can be applied to an open cassette that is an open storage container that is not hermetically sealed, the number of objects to be processed accommodated in the storage container may be one, The form which moves the to-be-processed object itself, without putting in a container may be sufficient.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Automation & Control Theory (AREA)
- General Factory Administration (AREA)
- Container, Conveyance, Adherence, Positioning, Of Wafer (AREA)
- Control Of Position, Course, Altitude, Or Attitude Of Moving Bodies (AREA)
Abstract
Description
図1は、本実施の形態に係る生産効率化装置を有する生産処理システムの一構成例を示したブロック図である。本発明の実施の形態に係る生産処理システムは、複数の処理装置2と、複数の搬送装置32及び該搬送装置32の動作を制御する搬送制御装置31を有する搬送システム3と、処理装置2及び搬送システム3へ制御指示を与え、各装置の動作を制御する生産実行制御装置4と、前記複数の処理装置2及び搬送システム3の間で通信する生産効率化装置1とを有する。
具体的には、生産効率化装置1は、該生産効率化装置1の各構成部の動作を制御する制御部11、例えばCPU(Central Processing Unit)を備えたコンピュータである。制御部11には、バスを介して接続されたROM、又はRAMなどの内部記憶装置13、ハードディスクドライブや、ソリッドステートドライブや、可搬式記録メディアからのデータの読み出しが可能な装置であるCD-ROMドライブなどの外部記憶装置12、第1乃至第3通信部14,15,16、及び時計部17が接続されている。
RAMは、制御部11の演算処理を実行する際に生ずる各種データやコンピュータの動作に必要な制御プログラムを一時記憶するDRAM、SRAM等の揮発性メモリである。
第1乃至第3通信部14,15,16は、夫々処理装置2、搬送制御装置31及び生産実行制御装置4との間で情報を送受信するためのインタフェースである。第1乃至第3通信部14,15,16による各種情報の送受信は制御部11によって制御される。
コンピュータプログラム5aは、コンピュータ読み取り可能に記録された可搬式メディアであるCD(Compact Disc)-ROM、DVD(Digital Versatile Disc)-ROM、BD(Blu-ray Disc)等の記録媒体5或いはハードディスクドライブやソリッドステートドライブに記録されている。制御部11はこれらコンピュータプログラム5aが記録された可搬式メディアやハードディスクドライブなどから、コンピュータプログラム5aを読み出し、内部記憶装置13に記憶させる。また、言うまでもなく、光ディスク及び光ディスクドライブは、記録媒体5及び外部記憶装置12の一例であり、フレキシブルディスク、磁気光ディスク、外付けハードディスク、半導体メモリ等にコンピュータプログラム5aをコンピュータ読み取り可能に記録し、前記外部記憶装置12にて読み出すように構成しても良い。また、通信網に接続されている図示しない外部コンピュータから本発明に係るコンピュータプログラム5aをダウンロードするようにしても良い。
<生産効率化基本フロー>
被処理体に対して処理を実行している処理装置2は、被処理体に対する処理が終了する時刻を予測するために必要な情報を生産効率化装置1へ送信する(ステップS11)。
図6は、処理装置2における情報送信手順の一例を示したフローチャートである。処理装置2は、被処理体に対する処理を開始する(ステップS51)。そして、処理装置2は、被処理体に対する処理が、設定された特定の処理工程にあるか否かを判定する(ステップS52)。特定の処理工程にあると判定した場合(ステップS52:YES)、処理装置2は、被処理体に対する処理が特定の処理工程にあることを示す情報を生産効率化装置1へ送信する(ステップS53)。該情報は、処理装置2における処理シーケンスが特定の処理ステップを通過したことを報告する情報である。ステップS53の処理を終えた場合、又は特定の処理工程にないと判定した場合(ステップS52:NO)、処理装置2は、被処理体に対する処理を終了したか否かを判定する(ステップS54)。処理を終了していないと判定した場合(ステップS54:NO)、処理装置2は処理をステップS52へ戻し、被処理体に対する処理を続行する。処理を終了したと判定した場合(ステップS54:YES)、処理装置2は、終了情報を生産実行制御装置4へ送信し(ステップS55)、処理を終える。
また例えば、前記設定された特定の処理工程とは、処理装置2が複数の被処理体を同時に処理するバッチ式の熱処理装置である場合、実行している処理シーケンスの終了ステップの例えば3ステップ手前など所定の処理ステップとして設定された処理ステップである。
図7は、処理装置2における情報送信手順の他の例を示したフローチャートである。処理装置2は、被処理体に対する処理を開始する(ステップS71)。そして、処理装置2は、被処理体に対する処理が特定の処理工程にあるか否かを判定する(ステップS72)。特定の処理工程にあると判定した場合(ステップS72:YES)、処理装置2は、被処理体に対する処理が終了する終了予定時刻を含む情報を生産効率化装置1へ送信する(ステップS73)。なお、処理終了予定時刻は一例であり、処理が終了する予定時機を示した情報に代えても良い。処理装置2から送信される終了予定時刻は、レシピの情報に基づいて所定の演算式で算出しても良いし、過去の処理終了時刻から統計的に算出しても良い。ステップS73の処理を終えた場合、又は特定の処理工程にないと判定した場合(ステップS72:NO)、処理装置2は、被処理体に対する処理を終了したか否かを判定する(ステップS74)。処理を終了していないと判定した場合(ステップS74:NO)、処理装置2は処理をステップS72へ戻し、被処理体に対する処理を続行する。処理を終了したと判定した場合(ステップS74:YES)、処理装置2は、終了情報を生産実行制御装置4へ送信し(ステップS75)、処理を終える。
生産効率化装置1は、上述の処理手順に従って処理装置2から送信された情報に基づいて、処理終了時刻を予測する。なお、処理装置2から送信された情報が示す時刻を、そのまま処理終了時刻として取り扱っても良い。
図8は、処理装置2における情報送信手順の他の例を示したフローチャートである。処理装置2は、被処理体に対する処理を開始する(ステップS91)。そして、処理装置2は、被処理体に対する処理が特定の処理工程にあるか否かを判定する(ステップS92)。特定の処理工程にあると判定した場合(ステップS92:YES)、処理装置2は、被処理体に対する処理が終了する過去の処理終了時刻の実績に係る情報を生産効率化装置1へ送信する(ステップS93)。該実績に係る情報は、例えば、処理装置2における過去の処理に要した実績時間又は処理が終了した実績時刻に係る情報である。ステップS93の処理を終えた場合、又は特定の処理工程にないと判定した場合(ステップS92:NO)、処理装置2は、被処理体に対する処理を終了したか否かを判定する(ステップS94)。処理を終了していないと判定した場合(ステップS94:NO)、処理装置2は処理をステップS92へ戻し、被処理体に対する処理を続行する。処理を終了したと判定した場合(ステップS94:YES)、処理装置2は、処理終了時刻を記憶し(ステップS95)、終了情報を生産実行制御装置4へ送信し(ステップS96)、処理を終える。
生産効率化装置1は、上述の処理手順に従って処理装置2から送信された情報を統計的に処理し、処理終了時刻を予測する。例えば、処理に要した時間の平均値、分散、最大値、最小値、中央値、最頻値等に基づいて、処理終了時刻を予測する。
図9は、処理装置2における情報送信手順の他の例を示したフローチャートである。処理装置2のプロセスモジュール25aは、メンテナンスのためのドライクリーニング処理などの被処理体を用いない処理を開始する(ステップS111)。そして、処理装置2は、処理装置2が特定の状態にあるか否かを判定する(ステップS112)。特定の状態にあると判定した場合(ステップS112:YES)、処理装置2は、自身が特定の状態にあることを示した情報を生産効率化装置1へ送信する(ステップS113)。ステップS113の処理を終えた場合、又は処理装置2が特定の状態に無いと判定した場合(ステップS112:NO)、処理装置2は、該処理を終了したか否かを判定する(ステップS114)。処理を終了していないと判定した場合(ステップS114:NO)、処理装置2は処理をステップS112へ戻し、該処理を続行する。処理を終了すると判定した場合(ステップS114:YES)、処理装置2は、終了情報を生産実行制御装置4へ送信し(ステップS115)、処理を終える。 生産効率化装置1は、この特定の状態にあることを示した情報を元にこの処理が終了する時刻を予測し、前記時刻にあわせて次に処理すべき被処理体を処理装置2へ向けて移動する準備を行う。この予測した処理が終了する時刻に合わせて次に処理すべき被処理体を処理装置2へ動かす指示情報を搬送制御装置31へ送信し、被処理体を処理装置2へ配達することで、処理装置2のプロセスモジュール25aにおける被処理体を用いない処理が終了してから、被処理体への処理の開始ができるようになるまでの時間を短縮することができ、プロセスモジュール25aにおける生産に寄与する度合いを高め、処理効率を高めることができる。
このため、次に処理すべき被処理体を処理装置2へ配達するのに要する時間の統計値により、被処理体を用いない処理が終了するタイミングよりも求められた統計値の時間分手前のタイミングを特定の状態として設定することがより好ましい。
図10は、処理装置2における情報送信手順の他の例を示したフローチャートである。生産効率化装置1の制御部11は、被処理体に対する処理の終了予測に必要な情報を要求する要求情報を処理装置2へ送信する(ステップS131)。
図11は、処理装置2における処理終了予測に必要な情報の送信タイミングの設定に係るフローチャートである。生産効率化装置1の制御部11は、処理の終了予測に必要な情報を生産効率化装置1へ送信するタイミングの設定を、図示しない入力装置にて受け付ける(ステップS151)。そして、制御部11は、情報の送信タイミングの設定を要求する設定情報を処理装置2へ送信する(ステップS152)。
生産効率化装置1の制御部11は、処理装置2から送信された情報を、第1通信部14にて受信し(ステップS12)、受信した情報に基づいて、該情報の送信元の処理装置2が処理を終える処理終了時刻を予測する(ステップS13)。該処理終了時刻は、例えば、処理装置2における処理が終了し、該処理が終了した被処理体がロードポートに載置されたFOUPに回収されて、該FOUPを搬出することが可能になる予定の時刻である。
図12は、搬送装置32への投機的指示が的中しなかった場合の処理手順を示したフローチャートである。搬送制御装置31は、搬送装置32の状態及び生産実行制御装置4から送信される生産実行制御情報を監視しており、処理装置2における被処理体の処理が終了する前に搬送装置32が到着したことを認識することができる。搬送制御装置31は、処理装置2における被処理体の処理が終了する前に搬送装置32が到着した場合、投機的移動失敗通知を生産効率化装置1へ送信する(ステップS171)。
また、現状でも処理負荷が高い生産実行制御装置4へ処理装置2の動作状況を送信し、予測処理を実行させた場合、生産実行制御装置4の処理負荷が更に増大し、搬送装置2及び処理装置2に対する制御が遅延することになり、却って生産効率が悪化するおそれがあった。しかし、本実施の形態によれば、生産効率化装置1の制御によって、搬送装置32を投機的に移動させることができるため、かかる問題を回避しつつ、生産効率を向上させることができる。
例えば、処理装置2から特定のタイミングでイベント信号が出力されるように構成し、生産効率化装置1は、処理装置2から出力されたイベント信号を受信した場合、直ちに、搬送装置32を該処理装置2へ移動させるように構成しても良い。イベント信号の内容及び出力タイミングは特に限定されるものでは無い。具体的には、イベント信号は、被処理体に対する処理が特定の工程に入った場合に出力される信号、処理装置2が特定の状態にある場合に出力される信号、処理装置2から出力された処理終了時刻情報を有する信号などである。
図13は、変形例1における生産効率化に係る処理手順を示したフローチャートである。処理装置2及び生産効率化装置1の制御部11は、図4のステップS11~ステップS12と同様、情報の送受信(ステップS191,192)、処理装置2における被処理体に対する処理終了予測を行う(ステップS193)。
その後、被処理体に対する処理を終えた処理装置2は、被処理体に対する処理を実際に終えた実終了時刻を生産効率化装置1へ送信する(ステップS194)。なお、実終了時刻に代えて、被処理体に対する処理を終えるのに実際に要した実終了時間を送信し、実終了時間を用いて以下の処理を実行するように構成しても良い。
図14は、変形例2に係る空の搬送装置及び被処理体搭載の搬送装置の到着タイミングを示したタイミングチャートである。図14Aは、被処理体搭載の搬送装置の到着タイミングの確率分布、図14Bは、空の搬送装置の到着タイミングの確率分布、図14C及び図14Dは、第1及び第2のロードポート21a、21bに載置された被処理体に対する処理が行われるタイミングを示している。
次に本発明にかかわる変形例3を説明する。
本変形例3では、生産効率化装置1は、処理終了時刻を予測することにより、処理装置からの搬出が可能になるタイミングと、処理装置2においてこれから処理すべき被処理体が無くなってしまうタイミングを求める。
これにより、搬送制御装置31は、搬送必要時機の始点から終点の間に搬送装置32が処理装置2に到着するように制御すればよく、このように時間幅を有しているので搬送制御装置31において搬送の優先度を考慮し、搬送路における搬送装置32の混雑を低減させた搬送装置32の移動スケジューリングがしやすくなる。更に例えば処理装置2における被処理体への処理が終了し、処理装置2から生産実行制御装置4へ処理が終了した旨の報告がなされ、生産実行制御装置4から搬送制御装置31へ該処理装置からの被処理体の回収の指示がだされたあとであっても、前記搬送必要時機の終点までに時間的余裕があるのであれば、搬送制御装置31は複数の搬送装置の位置や移動状態を考慮し、混雑が発生しないように前記生産実行制御装置4からの回収指示に即応せずに、遅れて移動させるように構築してもよい。
このように、処理装置2において、処理が終了し搬出することが可能になった被処理体が発生しても、処理すべき未処理の被処理体が無いという状態にならなければ、プロセスモジュールは連続的に処理を続けることができるので、処理装置2の高い生産効率を維持することが可能となる。
図15は、変形例4における生産効率化に係る処理順を示したフローチャートである。投機的に搬送装置32を移動させた後、生産実行制御装置4から搬送指示情報が送信され(ステップS211)、該搬送指示情報を生産効率化装置1が受信した場合(ステップS212)、生産効率化装置1の制御部11は、ロードポート21a,21bの切替時刻、及び現在行っている被処理体に対する処理内容が記述されたレシピを処理装置2に要求する(ステップS213)。
図16は、変形例5に係る生産処理システムの一構成例を示したブロック図である。上述の実施の形態では生産効率化装置1が、処理装置2、搬送制御装置31、生産実行制御装置4との間で情報の通信を行う第1乃至第3通信部14,15,16を備えている例を説明したが、生産実行制御装置4からの情報を間接的に受信するように構成しても良い。例えば、生産実行制御装置4から送信される情報を搬送制御装置31を介して受信するように構成しても良い。
図17は、変形例6に係る生産処理システムの一構成例を示したブロック図である。これまでに説明した本発明における形態では、変形例6生産効率化装置1が処理装置2と通信するための専用線を有する例を説明したが、これに限るものでは無く、変形例6に係る生産効率化装置1は、搬送制御装置31と、搬送装置32との間で情報を送受信する通信線路33を流用して、処理装置2から送信される情報を受信するように構成されている。通信線路33は、例えば、搬送システム3を構成する搬送装置32の搬送路に沿って敷設されている。
また、通信線路33を経由し、搬送システム3が有する被処理基板を搬送する搬送装置32が処理装置2への被処理基板の受け渡しをするための停止点近傍に、処理装置2との通信線路を接続するアクセスポイント(局)が配置されるように構成しても良い。
図18及び図19は、変形例7における生産効率化に係る処理順を示したフローチャートである。変形例7に係る生産効率化装置1は、生産実行制御装置4からの情報を利用して被処理体搭載の搬送装置のより的確な投機的移動指示を行うものである。
2 処理装置
3 搬送システム
4 生産実行制御装置
5 記録媒体
5a コンピュータプログラム
11 制御部
12 外部記憶装置
13 内部記憶装置
14 第1通信部
15 第2通信部
16 第3通信部
17 時計部
21a 第1のロードポート
21b 第2のロードポート
22 ロードモジュール
23a、23b ロードロックモジュール
24 トランスファーモジュール
25a、25b、25c、25d プロセスモジュール
31 搬送制御装置
32 搬送装置
Claims (20)
- 被処理体を処理する複数の処理装置との間で情報を通信する第1通信手段と、
前記複数の処理装置に被処理体を搬送する搬送装置を有する搬送システムとの間で、該搬送装置の制御に係る制御情報を通信する第2通信手段と、
前記第1通信手段にて通信した情報に基づいて、該情報の通信先の処理装置が被処理体の搬送を要する搬送時機を予測する搬送時機予測手段と、
該搬送時機予測手段が予測した搬送時機に前記情報の通信先の処理装置へ前記搬送装置が到着するように前記搬送システムへの制御情報を生成する生成手段と
を備える生産効率化装置。 - 前記制御情報は、
被処理体を搭載していない搬送装置を前記情報の通信元の処理装置へ移動させる指示を含む
請求項1に記載の生産効率化装置。 - 前記制御情報は、
被処理体を搭載している搬送装置を前記情報の通信元の処理装置へ移動させる指示を含む
請求項1又は請求項2に記載の生産効率化装置。 - 前記搬送システムは複数の搬送装置を有しており、
前記制御情報は、
被処理体に対する処理が所定の期間内に終了する処理装置が少ない領域に比べて、処理が前記期間内に終了する処理装置が多く存在する領域に前記搬送装置を偏在させるように前記搬送装置を移動させる指示を含む
請求項1乃至請求項3のいずれか一つに記載の生産効率化装置。 - 前記生成手段は、
前記処理装置で被処理体の処理が終了する前に、前記搬送装置が該処理装置に到着した場合、該搬送装置を待機させる指示、前記搬送装置を前記処理装置の周辺で巡回させる指示、又は所定箇所に前記搬送装置を移動させる指示を含む制御情報を生成するようにしてある請求項2乃至請求項4のいずれか一つに記載の生産効率化装置。 - 前記制御情報は、
被処理体を搭載していない搬送装置と、前記処理装置で処理されるべき被処理体を搭載した搬送装置とがこの順で前記処理装置に到着するように各搬送装置を移動させる指示を含む
請求項1乃至5に記載の生産効率化装置。 - 前記処理装置及び前記搬送装置の動作を制御する生産実行制御装置から送信された生産実行制御情報を直接的又は間接的に通信する手段を備え、
前記生産実行制御装置から送信された生産実行制御情報の内容と、生成手段が生成した制御情報の内容とが矛盾しないようにしてある請求項1乃至請求項6のいずれか一つに記載の生産効率化装置。 - 前記搬送時機に搬送装置が前記情報の通信元の処理装置へ到着するために要する時間である移動所要時間を予測する手段を更に備え、
前記制御情報は、前記搬送装置の移動を開始させる時機である移動開始時機を有し、前記移動開始時機は前記搬送時機より前記移動所要時間前の時機である
請求項1乃至7のいずれか一つに記載の生産効率化装置。 - 前記搬送時機は、
前記処理装置における処理が終了し、前記搬送装置による被処理体の取り出しが可能になる時機、該処理装置において処理すべき未処理の被処理体が無くなる時機、又は各時機の間の時機を含む
請求項1乃至8のいずれか一つに記載の生産効率化装置。 - 前記処理装置は、該処理装置に投入されている被処理体の残処理時間に係る情報と、連続して処理を継続する為に次に被処理体が必要になる時間の算出に係る情報とを通信するように構成してあり、
複数の前記処理装置と通信した前記情報に基づいて、各処理装置に投入されている被処理体の処理が終了する終了時機、及び各処理装置が次の被処理体を必要とする開始時機を算出する手段と、
算出された終了時機及び開始時機に基づいて、前記搬送装置を移動させるべき処理装置の優先順位を決定する手段と
を備える請求項1乃至請求項9のいずれか一つに記載の生産効率化装置。 - 前記処理装置で被処理体に対する処理に実際に要した実績時間又は処理を実際に終了した実終了時刻を通信する手段と、
終了予測時機と、実績時間又は実終了時刻と、終了予測時機の予測に用いた情報とを対応付けて蓄積する手段と
を備え、
前記生成手段は、
蓄積された情報を用いて制御情報を生成するようにしてある
請求項1乃至請求項10のいずれか一つに記載の生産効率化装置。 - 前記第1通信手段が通信する情報は、
被処理体に対する処理が特定の処理工程にあることを示す情報を含む
請求項1乃至請求項11のいずれか一つに記載の生産効率化装置。 - 前記第1通信手段が通信する情報は、
前記処理装置で被処理体に対する処理に要する時間又は処理が終了する予定時機を示した情報を含む
請求項1乃至請求項12のいずれか一つに記載の生産効率化装置。 - 前記第1通信手段が通信する情報は、
前記処理装置の自身の状態が特定の状態にあることを示す情報を含む
請求項1乃至請求項13のいずれか一つに記載の生産効率化装置。 - 前記第1通信手段が通信する情報は、
前記処理装置における過去の処理に要した実績時間又は処理が終了した実績時刻に係る情報を含む
請求項1乃至請求項14のいずれか一つに記載の生産効率化装置。 - 前記第1通信手段は、
前記処理装置で被処理体に対する処理が特定の処理工程にある場合に送信された情報を受信するようにしてある
請求項1乃至請求項15のいずれか一つに記載の生産効率化装置。 - 前記処理装置が被処理体の搬送を要する搬送時機を予測するために必要な情報を前記処理装置へ要求する手段を備え、
前記第1通信手段は、
前記要求に応じて前記処理装置から送信された情報を受信するようにしてある
請求項1乃至請求項16のいずれか一つに記載の生産効率化装置。 - 前記処理装置が被処理体の搬送を要する搬送時機を予測するための情報を送信する時機の設定を前記処理装置に要求する手段を備える
請求項1乃至請求項17のいずれか一つに記載の生産効率化装置。 - 被処理体を処理する複数の処理装置との間で情報を通信し、
前記複数の処理装置に被処理体を搬送する搬送装置を有する搬送システムとの間で、該搬送装置の制御に係る制御情報を通信し、
通信した情報に基づいて、該情報の通信先の処理装置が処理を終了した被処理体の搬出を要する搬出時間又は被処理体の搬入を要する搬入時間を予測し、
予測した搬出時間又は搬入時間に応じた時機に前記情報の通信先の処理装置へ前記搬送装置が到着するように前記搬送システムへの制御情報を生成する
生産効率化方法。 - コンピュータを、
被処理体を処理する複数の処理装置との間で情報を通信する第1通信手段と、
前記複数の処理装置に被処理体を搬送する搬送装置を有する搬送システムとの間で、該搬送装置の制御に係る制御情報を通信する第2通信手段と、
前記第1通信手段にて通信した情報に基づいて、該情報の通信先の処理装置が被処理体の搬出を要する搬出時間又は搬入を要する搬入時間を予測する手段と、
該手段が予測した搬出時間又は搬入時間に応じた時機に前記情報の通信先の処理装置へ前記搬送装置が到着するように前記搬送システムへの制御情報を生成する生成手段と
して機能させるコンピュータプログラム。
Priority Applications (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| US14/004,120 US9268328B2 (en) | 2011-03-10 | 2012-03-09 | Production efficiency improving apparatus, production efficiency improving method, and computer program |
| DE112012001172T DE112012001172T5 (de) | 2011-03-10 | 2012-03-09 | Produktionseffizienzverbesserungsvorrichtung,Produktionseffizienzverbesserungsverfahren und Computerprogramm |
| KR1020137023564A KR101865984B1 (ko) | 2011-03-10 | 2012-03-09 | 생산 효율화 장치, 생산 효율화 방법, 및 컴퓨터 프로그램 |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2011053590A JP5797913B2 (ja) | 2011-03-10 | 2011-03-10 | 生産効率化装置、生産効率化方法、コンピュータプログラム |
| JP2011-053590 | 2011-03-10 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2012121378A1 true WO2012121378A1 (ja) | 2012-09-13 |
Family
ID=46798329
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP2012/056144 Ceased WO2012121378A1 (ja) | 2011-03-10 | 2012-03-09 | 生産効率化装置、生産効率化方法、コンピュータプログラム |
Country Status (6)
| Country | Link |
|---|---|
| US (1) | US9268328B2 (ja) |
| JP (1) | JP5797913B2 (ja) |
| KR (1) | KR101865984B1 (ja) |
| DE (1) | DE112012001172T5 (ja) |
| TW (1) | TWI501345B (ja) |
| WO (1) | WO2012121378A1 (ja) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110471202A (zh) * | 2019-08-22 | 2019-11-19 | 中电九天智能科技有限公司 | 一种基于mes的液晶面板半板补片生产方法 |
| US12019455B2 (en) | 2018-02-08 | 2024-06-25 | Nec Corporation | Transport operation control device, transport system, transport operation control method, and recording medium |
Families Citing this family (18)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2733558B1 (en) * | 2011-07-15 | 2020-03-18 | Tokyo Electron Limited | Processing indicating device, processing indicating method, computer program and processing device |
| US10520932B2 (en) | 2014-07-03 | 2019-12-31 | Taiwan Semiconductor Manufacturing Co., Ltd | Transport system and method |
| US10382312B2 (en) | 2016-03-02 | 2019-08-13 | Fisher-Rosemount Systems, Inc. | Detecting and locating process control communication line faults from a handheld maintenance tool |
| US11605037B2 (en) | 2016-07-20 | 2023-03-14 | Fisher-Rosemount Systems, Inc. | Fleet management system for portable maintenance tools |
| US10554644B2 (en) | 2016-07-20 | 2020-02-04 | Fisher-Rosemount Systems, Inc. | Two-factor authentication for user interface devices in a process plant |
| US10270853B2 (en) | 2016-07-22 | 2019-04-23 | Fisher-Rosemount Systems, Inc. | Process control communication between a portable field maintenance tool and an asset management system |
| US10374873B2 (en) | 2016-07-22 | 2019-08-06 | Fisher-Rosemount Systems, Inc. | Process control communication between a portable field maintenance tool and a process control instrument |
| US10585422B2 (en) | 2016-07-22 | 2020-03-10 | Fisher-Rosemount Systems, Inc. | Portable field maintenance tool system having interchangeable functional modules |
| US10375162B2 (en) | 2016-07-22 | 2019-08-06 | Fisher-Rosemount Systems, Inc. | Process control communication architecture |
| US10599134B2 (en) | 2016-07-22 | 2020-03-24 | Fisher-Rosemount Systems, Inc. | Portable field maintenance tool configured for multiple process control communication protocols |
| US10481627B2 (en) | 2016-07-25 | 2019-11-19 | Fisher-Rosemount Systems, Inc. | Connection check in field maintenance tool |
| US10505585B2 (en) | 2016-07-25 | 2019-12-10 | Fisher-Rosemount Systems, Inc. | Portable field maintenance tool with a bus for powering and communicating with a field device |
| US10764083B2 (en) | 2016-07-25 | 2020-09-01 | Fisher-Rosemount Systems, Inc. | Portable field maintenance tool with resistor network for intrinsically safe operation |
| CN108529868B (zh) * | 2018-05-18 | 2021-01-12 | 河北南玻玻璃有限公司 | 一种玻璃落板控制方法、系统、存储介质和玻璃生产设备 |
| JP7215490B2 (ja) * | 2018-11-13 | 2023-01-31 | 日本電気株式会社 | 搬送作業制御装置、方法およびプログラム |
| JP6816176B2 (ja) * | 2019-01-11 | 2021-01-20 | 本田技研工業株式会社 | 測定システム |
| US12373744B2 (en) * | 2019-02-28 | 2025-07-29 | Nec Corporation | Conveyance route design device, conveyance route design method, and a recording medium |
| KR20240046392A (ko) * | 2022-09-30 | 2024-04-09 | 삼성디스플레이 주식회사 | 표시 장치의 제조장치 및 표시 장치의 제조방법 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004134778A (ja) * | 2003-09-16 | 2004-04-30 | Oki Electric Ind Co Ltd | 半導体装置製造工程の搬送方法 |
| JP2008310467A (ja) * | 2007-06-13 | 2008-12-25 | Panasonic Corp | 搬送制御装置および搬送制御方法 |
| JP2009076495A (ja) * | 2007-09-18 | 2009-04-09 | Hitachi High-Technologies Corp | 真空処理装置 |
| JP2009135275A (ja) * | 2007-11-30 | 2009-06-18 | Panasonic Corp | 搬送システム及びその制御方法 |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH1159829A (ja) * | 1997-08-08 | 1999-03-02 | Mitsubishi Electric Corp | 半導体ウェハカセット搬送装置、半導体ウェハカセット搬送装置で用いられるストッカ、ならびに半導体ウェハカセット搬送装置で用いられるストッカ入庫作業制御方法、ストッカ出庫作業制御方法、自動搬送車制御方法、およびストッカ在庫照合方法 |
| JP2005208891A (ja) | 2004-01-22 | 2005-08-04 | Semiconductor Leading Edge Technologies Inc | 制御装置及び処理システム |
| JP2005239288A (ja) * | 2004-02-24 | 2005-09-08 | Meidensha Corp | 搬送設備の渋滞予測方法とその装置 |
| US20090118842A1 (en) * | 2007-11-06 | 2009-05-07 | David Everton Norman | Manufacturing prediction server |
-
2011
- 2011-03-10 JP JP2011053590A patent/JP5797913B2/ja active Active
-
2012
- 2012-03-09 US US14/004,120 patent/US9268328B2/en active Active
- 2012-03-09 KR KR1020137023564A patent/KR101865984B1/ko active Active
- 2012-03-09 TW TW101108164A patent/TWI501345B/zh active
- 2012-03-09 DE DE112012001172T patent/DE112012001172T5/de active Pending
- 2012-03-09 WO PCT/JP2012/056144 patent/WO2012121378A1/ja not_active Ceased
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004134778A (ja) * | 2003-09-16 | 2004-04-30 | Oki Electric Ind Co Ltd | 半導体装置製造工程の搬送方法 |
| JP2008310467A (ja) * | 2007-06-13 | 2008-12-25 | Panasonic Corp | 搬送制御装置および搬送制御方法 |
| JP2009076495A (ja) * | 2007-09-18 | 2009-04-09 | Hitachi High-Technologies Corp | 真空処理装置 |
| JP2009135275A (ja) * | 2007-11-30 | 2009-06-18 | Panasonic Corp | 搬送システム及びその制御方法 |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US12019455B2 (en) | 2018-02-08 | 2024-06-25 | Nec Corporation | Transport operation control device, transport system, transport operation control method, and recording medium |
| CN110471202A (zh) * | 2019-08-22 | 2019-11-19 | 中电九天智能科技有限公司 | 一种基于mes的液晶面板半板补片生产方法 |
| CN110471202B (zh) * | 2019-08-22 | 2021-12-07 | 中电九天智能科技有限公司 | 一种基于mes的液晶面板半板补片生产方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| TW201243989A (en) | 2012-11-01 |
| DE112012001172T5 (de) | 2013-12-24 |
| TWI501345B (zh) | 2015-09-21 |
| JP2012190285A (ja) | 2012-10-04 |
| US20140018955A1 (en) | 2014-01-16 |
| KR101865984B1 (ko) | 2018-06-08 |
| JP5797913B2 (ja) | 2015-10-21 |
| US9268328B2 (en) | 2016-02-23 |
| KR20140027105A (ko) | 2014-03-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5797913B2 (ja) | 生産効率化装置、生産効率化方法、コンピュータプログラム | |
| EP2733558B1 (en) | Processing indicating device, processing indicating method, computer program and processing device | |
| US9748088B2 (en) | Method, storage medium and system for controlling the processing of lots of workpieces | |
| EP4488777A1 (en) | Wafer transfer supervision control method and system, computer device and storage medium | |
| US11599115B2 (en) | Transport control device | |
| US20140257546A1 (en) | Processing device group controller, manufacturing process system, processing device group control method, manufacturing optimization system, manufacturing optimization device, and manufacturing optimization method | |
| US20060190118A1 (en) | Methods and apparatus for enhanced operation of substrate carrier handlers | |
| JP6017134B2 (ja) | 生産効率化システム、生産効率化装置および生産効率化方法 | |
| TWI557524B (zh) | A production processing system, a control device for production processing, a control method for production processing, and a control program for production processing | |
| US7809466B2 (en) | Transportation system and transportation method | |
| US7505828B2 (en) | Carrier transportation management system and method for internal buffer process tools | |
| CN101273312B (zh) | 增强衬底载具搬运器操作的方法和装置 | |
| JP2018093131A (ja) | 搬送システム | |
| WO2026060659A1 (zh) | 用于机器人故障后任务分配的方法、装置、设备和产品 | |
| JP2013114328A (ja) | 処理装置群コントローラ、生産処理システム、処理装置群制御方法、及びプログラム | |
| JP2011077136A (ja) | 基板処理システム及びその制御方法 | |
| JP2017017342A (ja) | 生産処理システムおよび生産効率化方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12754657 Country of ref document: EP Kind code of ref document: A1 |
|
| ENP | Entry into the national phase |
Ref document number: 20137023564 Country of ref document: KR Kind code of ref document: A |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 1120120011724 Country of ref document: DE Ref document number: 112012001172 Country of ref document: DE |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 14004120 Country of ref document: US |
|
| 122 | Ep: pct application non-entry in european phase |
Ref document number: 12754657 Country of ref document: EP Kind code of ref document: A1 |