WO2008119798A1 - Mât distributeur notamment pour pompe à béton - Google Patents
Mât distributeur notamment pour pompe à béton Download PDFInfo
- Publication number
- WO2008119798A1 WO2008119798A1 PCT/EP2008/053865 EP2008053865W WO2008119798A1 WO 2008119798 A1 WO2008119798 A1 WO 2008119798A1 EP 2008053865 W EP2008053865 W EP 2008053865W WO 2008119798 A1 WO2008119798 A1 WO 2008119798A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- arm
- mast
- distribution boom
- boom according
- last
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
- E04G21/04—Devices for both conveying and distributing
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
- E04G21/04—Devices for both conveying and distributing
- E04G21/0418—Devices for both conveying and distributing with distribution hose
- E04G21/0427—Devices for both conveying and distributing with distribution hose on a static support, e.g. crane
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
- E04G21/04—Devices for both conveying and distributing
- E04G21/0418—Devices for both conveying and distributing with distribution hose
- E04G21/0436—Devices for both conveying and distributing with distribution hose on a mobile support, e.g. truck
Definitions
- the invention relates to a distribution boom, in particular for a concrete pump, which is composed of at least three mutually parallel axes against each other and with respect to a mast block by means of a respective power unit pivotable mast arms, and acted upon by a pressurized liquid or liquid concrete, partially guided over the mast arms of the distribution mast conveyor line , which ends on the output side in a arranged on the last boom arm discharge element.
- Known distribution booms of this type which are intended for stationary or mobile concrete pumps, usually have a discharge hose as the discharge element, into which the delivery line opens with its last line section and which hangs pendulum-like down on the free mast tip of the last mast arm.
- the end hose can be swiveled by the operator in a limited radius to the concreting point, while the pump driver operates the concrete pump and thereby moves the articulated mast for the Endschlauchbediener.
- the operation of the articulated mast and the concrete pump is preferably carried out via a radio link using a remote control.
- distribution booms are also suitable for discharging shotcrete.
- special Spritzbetoniermaschinen be used, which may also have a bucking mast, which carries on its last mast arm via the delivery line with shotcrete sprayed spray nozzle.
- the object of the invention is to improve the known distributor boom of the type specified at the outset. that it can be used both for concreting surfaces and formwork as well as for discharging shotcrete.
- the solution according to the invention consists essentially in that the last mast arm of the distributor mast is composed of two arm parts rigidly connected to one another at a separation point, wherein the first power unit connected to the penultimate mast arm acts on a first arm unit directly articulated on the penultimate mast arm and at least two different, modularly interchangeable second Armtei- Ie are provided which can be equipped with different, connectable to the delivery line discharge elements.
- the separation point is designed as a flange connection.
- a preferred embodiment of the invention provides that the arranged on the second arm portion different discharge elements from the group spray nozzle, end hose and / or tailpipe can be selected.
- one of the second arm parts has a discharge element designed as a spray nozzle, it is advantageous if it is connected via a flexible connecting hose to the end of the delivery line section arranged on the second last boom arm.
- a flexible connecting hose to the end of the delivery line section arranged on the second last boom arm.
- a preferably designed as a spring coil the sphtzdüsen workede end of the flexible connecting hose comprehensive cuff is arranged at the input end of the spray nozzle, which serves as kink protection for the hose.
- a nozzle which carries the spray nozzle and which is arranged to rotate with respect to the second arm part about a parallel and / or transversely to the longitudinal extent extending axis of the motor drive shaft is arranged.
- the drive head expediently has at least two hydraulic motors or electric motors whose output shafts are aligned perpendicular or parallel offset from one another.
- the hydraulic or electric cables connected to the drive head can be guided via the boom arms of the distributor boom.
- the drive head is controlled via a remote control, which is expediently combined with the remote control for the articulated mast.
- the spray nozzle For the operation of the spray nozzle is also advantageous if a preferably guided over the mast arms, acted upon with a binder for thick materials binder line is connected to the spray nozzle. Furthermore, a compressed-air line, which is preferably guided via the mast arms, can be provided on the spray nozzle. According to an advantageous embodiment of the invention, the delivery line section of the second last arm section connected to the spray nozzle via the flexible hose has a reducing piece converging towards its exit side.
- a further preferred embodiment of the invention provides that the exchangeable second arm part carries a discharge element designed as an end hose or tailpipe, which is connected on the output side to the delivery line section of the last boom arm and hangs from the same downwards.
- the invention further relates to a slurry pump, in particular a truck-mounted concrete pump with a pump unit for thick materials, in particular for liquid concrete.
- the slurry pump according to the invention is characterized in that it has a distributor boom according to the invention described above, whose delivery line is connected on the input side to a pressure outlet of the pump unit.
- An advantageous embodiment of the invention provides that a responsive to an output signal of the Codierschalters control device for controlling the pump unit and any other drive units for a binding agent or compressed air is provided.
- Figure 1 is a side view of a truck-mounted concrete pump with a distribution boom designed as articulated mast in the operating position.
- FIG. 2 shows a detail of the distributor boom in the region of the penultimate and the last boom arm without discharge element in perspective view
- 3 shows a section of the distributor mast with the second mast arm attached to the last mast arm and the discharge element formed as an end hose or tailpipe in a perspective view
- Fig. 4 shows a detail of the distribution boom with attached to the last mast arm second arm and trained as a spray discharge element in perspective view.
- the truck-mounted concrete pump shown in FIG. 1 comprises a transport vehicle 11, a pump unit, not shown, for example designed as a two-cylinder piston pump for liquid concrete, and a distribution mast 10 as a carrier for a delivery line 16 (FIGS. 2 to 4). Via the delivery line 16, liquid concrete is conveyed to a concreting location 18 remote from the location of the vehicle 11.
- the distributor boom 10 consists of a pivotable about a vehicle-mounted vertical axis 13 mast bracket 21 and a pivotable on this articulated boom 22, which in the illustrated embodiment of five articulated mast arms 23 to 27, which run parallel to each other and at right angles to the vertical axis 13 of the mast bracket 21 Axles 28 to 32 are pivotable.
- the buckling angle ranges ⁇ 1 to ⁇ 5 of the articulated joints formed by the joint axes 26 to 32 and their arrangement with respect to one another are coordinated with one another such that the distribution boom 10 can be deposited on the vehicle 11 with a space-saving transport configuration.
- drive units 34 which are individually assigned to the articulated axes 28 to 32, the articulated boom is deployable at different distances and / or height differences between the concreting location 18 and the vehicle location (FIG. 1).
- the pump driver controls, for example by means of a radio remote control, the mast movements through which the mast tip 33 with the end shown in FIG. hose 43 is passed over the area to be concreted away.
- the end hose 43 has a typical length of 3 to 4 m and, because of its articulated suspension in the area of the mast top and due to its inherent flexibility with its discharge end, can be kept in the most favorable position for the concreting site 18 by a final hose operator.
- the last mast arm 27 is composed of two arm parts 27 ', 27 "rigidly connected to one another as a flange connection 40.
- the first arm part 27' is articulated directly on the penultimate mast arm 26 via the bending axis 32
- the drive unit 34 designed as a hydraulic cylinder, which is connected to the penultimate mast arm 26, engages directly on the first arm part 27 '.
- different second arm parts 27' are provided, which are modularly opposed to one another. are exchangeable.
- the second arm parts 27 "are equipped with different discharge elements which can be connected to the delivery line 16, of which the discharge element shown in FIG. 3 is designed as end hose 43 or tail pipe, while the discharge element shown in FIG. 4 forms a spray nozzle 45.
- the second arm part 27 "forms an extension of the first arm part 27 ', along which the feed line 16 is guided and opens into the pendulum-like downwardly hanging end hose 43.
- the second arm part 27 "according to FIG. 3 can be exchanged for the second arm part 27" according to FIG. 4, which carries the spray nozzle 45.
- the spray nozzle 45 is connected via a flexible connecting hose 46 to the outlet-side end 47 of the conveying line section 16 arranged on the second last boom arm 26.
- the delivery line section of the second-last mast arm 26 has a connection to its output side 47. vergernden reducer 48 on.
- a spray nozzle 45 carrying, and this is arranged opposite the second arm to parallel and / or transverse to the longitudinal axis axes by means of motors 49,50,51 twisting drive head 52 is arranged.
- a binder line 53 and a compressed air line 54 are connected to the spray nozzle 45. The actuation of the spray nozzle 45 and the drive head 52 as well as the mast arms 23 to 27 via a remote control.
- the sphtzdüsen worne end of the flexible connecting hose 46 comprehensive cuff 55 is arranged, which serves as kink protection.
- the invention relates to a distribution boom, which is intended for a stationary or mobile concrete pump.
- the distributor boom 10 has at least three axes parallel to each other 28 to 32 against each other or against a mast block 21 by means of a respective drive unit 34 pivotable mast arms 23 to 27 and an input side acted upon with liquid concrete, partially guided over the mast arms conveyor line 16, the output side in an am last mast arm 27 disposed discharge element 43,45 opens.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
L'invention concerne un mât distributeur qui est conçu pour une pompe à béton fixe ou mobile. Le mât distributeur (10) présente au moins trois bras (23 à 27) pouvant pivoter autour d'axes (28 à 32) parallèles, les uns par rapport aux autres ou par rapport à un chevalet (21) de mât, dans chaque cas, au moyen d'un groupe d'entraînement (34), ainsi qu'une conduite de refoulement (16) alimentée en béton liquide au niveau d'une entrée et guidée par sections par les bras de mât, et qui débouche côté sortie dans un élément de sortie (43, 45) disposé sur le dernier bras de mât (27). Conformément à l'invention, le dernier bras de mât (27) se compose de deux parties (27', 27'') reliées entre elles de manière rigide en un point de séparation (40) et le groupe d'entraînement (34) qui est relié avec l'avant-dernier bras de mât (26) vient en contact avec une première partie de bras (27') aarticulée directement sur l'avant-dernier bras de mât (26). Toujours selon l'invention, il est prévu au moins deux deuxièmes parties de bras (27'') différentes et interchangeables de manière modulaire pouvant être équipées de différents éléments de sortie (43, 45) qui peuvent être raccordés à la conduite de refoulement (16).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP08735639A EP2129845A1 (fr) | 2007-04-03 | 2008-04-01 | Mât distributeur notamment pour pompe à béton |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102007016354.3 | 2007-04-03 | ||
DE102007016354A DE102007016354A1 (de) | 2007-04-03 | 2007-04-03 | Verteilermast, insbesondere für eine Betonpumpe |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2008119798A1 true WO2008119798A1 (fr) | 2008-10-09 |
Family
ID=39559290
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/EP2008/053865 WO2008119798A1 (fr) | 2007-04-03 | 2008-04-01 | Mât distributeur notamment pour pompe à béton |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP2129845A1 (fr) |
DE (1) | DE102007016354A1 (fr) |
WO (1) | WO2008119798A1 (fr) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704689A (zh) * | 2012-06-18 | 2012-10-03 | 三一重工股份有限公司 | 臂架装置及工程机械 |
WO2013007039A1 (fr) * | 2011-07-14 | 2013-01-17 | 长沙中联重工科技发展股份有限公司 | Procédé et dispositif de commande de bras mécanique et engin de chantier |
WO2013078920A1 (fr) * | 2011-11-30 | 2013-06-06 | 中联重科股份有限公司 | Dispositif de pompage de béton, son mécanisme de tige de liaison à courbure et procédé de fabrication pour mécanisme de tige de liaison à courbure |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7762271B2 (en) * | 2007-03-07 | 2010-07-27 | Putzmeister, Inc. | Material delivery support device for boom and method of use |
CN101793092B (zh) * | 2010-02-05 | 2011-07-06 | 三一重工股份有限公司 | 一种混凝土泵车及其臂架装置 |
FI122722B (fi) * | 2010-04-14 | 2012-06-15 | Bronto Skylift Oy Ab | Henkilönostin ja menetelmä henkilönostimen käyttämiseksi |
DE102012215469A1 (de) | 2012-08-31 | 2014-03-06 | Putzmeister Engineering Gmbh | Betonverteilermast |
CN114670324B (zh) * | 2022-04-06 | 2023-08-22 | 中铁上海工程局集团有限公司 | 基于微方量混凝土精准布料的智能布料装置及其布料方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB222092A (en) * | 1923-09-19 | 1925-11-19 | Georges Joseph Michel Leicknam | Improvements in processes and apparatus for depositing concrete and the like under pressure |
US3221772A (en) * | 1963-03-11 | 1965-12-07 | Mississippi Valley Structural | Articulated conduit boom assembly |
US3707990A (en) * | 1971-01-11 | 1973-01-02 | Case Co J I | Concrete placement apparatus |
US3918749A (en) * | 1974-08-07 | 1975-11-11 | Forms Const | Concrete hose and coupling |
DE3409757A1 (de) * | 1983-06-07 | 1984-12-13 | Epítögépgyártó Vállalat, Budapest | Rohrweiche und flexible rohrleitung |
DE4436247A1 (de) * | 1994-10-11 | 1996-04-18 | Putzmeister Maschf | Anordnung zum Reinigen von Dickstoff-Förderrohren |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SE378436B (fr) * | 1967-07-03 | 1975-09-01 | Skanska Cementgjuteriet Ab | |
SE399733B (sv) * | 1976-06-01 | 1978-02-27 | Stabilator Ab | Sett och anordning for betongsprutning |
GB1535385A (en) * | 1976-07-16 | 1978-12-13 | Lancaster F | Guns for dispensing streams of liquid cement and fibre reinforcement |
DE3409474C2 (de) * | 1984-03-15 | 1986-11-27 | Maschinenfabrik Walter Scheele GmbH & Co KG, 4750 Unna-Massen | Zusammenfaltbare Betonverteilereinrichtung |
DE3601256A1 (de) * | 1986-01-17 | 1987-07-23 | Bernhard Ladwein | Vorrichtung zum foerdern von baustoffen |
DE3909212C2 (de) * | 1989-03-21 | 1998-09-24 | Putzmeister Ag | Einrichtung zum Einbringen von Beton in Tunnelschalungen |
DE4233171A1 (de) * | 1992-10-02 | 1994-04-07 | Putzmeister Maschf | Betonverteilermast |
-
2007
- 2007-04-03 DE DE102007016354A patent/DE102007016354A1/de not_active Withdrawn
-
2008
- 2008-04-01 EP EP08735639A patent/EP2129845A1/fr not_active Withdrawn
- 2008-04-01 WO PCT/EP2008/053865 patent/WO2008119798A1/fr active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB222092A (en) * | 1923-09-19 | 1925-11-19 | Georges Joseph Michel Leicknam | Improvements in processes and apparatus for depositing concrete and the like under pressure |
US3221772A (en) * | 1963-03-11 | 1965-12-07 | Mississippi Valley Structural | Articulated conduit boom assembly |
US3707990A (en) * | 1971-01-11 | 1973-01-02 | Case Co J I | Concrete placement apparatus |
US3918749A (en) * | 1974-08-07 | 1975-11-11 | Forms Const | Concrete hose and coupling |
DE3409757A1 (de) * | 1983-06-07 | 1984-12-13 | Epítögépgyártó Vállalat, Budapest | Rohrweiche und flexible rohrleitung |
DE4436247A1 (de) * | 1994-10-11 | 1996-04-18 | Putzmeister Maschf | Anordnung zum Reinigen von Dickstoff-Förderrohren |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2013007039A1 (fr) * | 2011-07-14 | 2013-01-17 | 长沙中联重工科技发展股份有限公司 | Procédé et dispositif de commande de bras mécanique et engin de chantier |
WO2013078920A1 (fr) * | 2011-11-30 | 2013-06-06 | 中联重科股份有限公司 | Dispositif de pompage de béton, son mécanisme de tige de liaison à courbure et procédé de fabrication pour mécanisme de tige de liaison à courbure |
CN102704689A (zh) * | 2012-06-18 | 2012-10-03 | 三一重工股份有限公司 | 臂架装置及工程机械 |
CN102704689B (zh) * | 2012-06-18 | 2014-10-15 | 三一汽车制造有限公司 | 臂架装置及工程机械 |
Also Published As
Publication number | Publication date |
---|---|
DE102007016354A1 (de) | 2008-10-09 |
EP2129845A1 (fr) | 2009-12-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2008119798A1 (fr) | Mât distributeur notamment pour pompe à béton | |
EP1360387B1 (fr) | Dispositif de repartition de matieres epaisses, notamment de beton | |
EP2729645B1 (fr) | Mât distributeur pour des pompes à béton | |
DE19849747C5 (de) | Verteilervorrichtung für Dickstoffe, insbesondere für Beton | |
DE102019107833A1 (de) | Vorrichtung für das Ausbringen eines fluiden Prozesswerkstoffs | |
EP0838562B1 (fr) | Bras de distribution pour pompes à béton | |
EP2079889B1 (fr) | Repartiteur circulaire pour substances epaisses et en particulier pour beton liquide | |
EP1290292B1 (fr) | Dispositif distributeur pour matieres epaisses | |
WO2009074395A1 (fr) | Cadre rapporté pour pompes à béton mobiles | |
WO2006063670A1 (fr) | Tuyau d'extremite pour evacuer des matieres epaisses | |
DE102012224529A1 (de) | Arbeitsgerät mit Drehkopf-Trennstelle | |
DE3409474C2 (de) | Zusammenfaltbare Betonverteilereinrichtung | |
EP0838563B1 (fr) | Bras de distribution pour pompes à béton | |
WO2013004508A1 (fr) | Mât de distribution pour pompes à béton | |
EP1951972B1 (fr) | Mat articule pour installation de transport de matieres denses | |
WO2014016022A1 (fr) | Distributeur tournant pour substances épaisses | |
EP0893392B1 (fr) | Grue télescopique avec flechette relevable | |
DE102012216243A1 (de) | Umlenkhebel eines Antriebs- und Koppelgetriebes für den Einsatz in einem Betonverteilermast | |
DE102017208032A1 (de) | Verteilermast für mobile Betonpumpen mit Gelenken für nebeneinanderliegende Arme und mobile Betonpumpe | |
DE4225716C2 (de) | Vorrichtung zum Auftragen von Mörtel | |
WO2006136286A1 (fr) | Dispositif antiderapant | |
EP1664459A1 (fr) | Dispositif de distribution de beton frais | |
DE102008027233A1 (de) | Gelenkbolzen als Bestandteil einer Dickstoff-Leitung | |
DE102007045158A1 (de) | Rundverteiler für Dickstoffe, insbesondere für Flüssigbeton | |
WO2003080959A2 (fr) | Pompe a beton automatique |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 08735639 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2008735639 Country of ref document: EP |
|
NENP | Non-entry into the national phase |
Ref country code: DE |