WO2006123009A1 - Sealing of a piling - Google Patents

Sealing of a piling Download PDF

Info

Publication number
WO2006123009A1
WO2006123009A1 PCT/FI2005/000234 FI2005000234W WO2006123009A1 WO 2006123009 A1 WO2006123009 A1 WO 2006123009A1 FI 2005000234 W FI2005000234 W FI 2005000234W WO 2006123009 A1 WO2006123009 A1 WO 2006123009A1
Authority
WO
WIPO (PCT)
Prior art keywords
tongue
groove element
soil
groove
broaching tool
Prior art date
Application number
PCT/FI2005/000234
Other languages
English (en)
French (fr)
Other versions
WO2006123009B1 (en
Inventor
Jouko Lehtonen
Jari Laaksonen
Original Assignee
Turun Ammattikorkeakoulu
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Turun Ammattikorkeakoulu filed Critical Turun Ammattikorkeakoulu
Priority to PCT/FI2005/000234 priority Critical patent/WO2006123009A1/en
Priority to EP05742489.7A priority patent/EP1888847B1/de
Publication of WO2006123009A1 publication Critical patent/WO2006123009A1/en
Publication of WO2006123009B1 publication Critical patent/WO2006123009B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles

Definitions

  • the invention relates to a method for forming a sealed piling in soil of at least two tongue-and-groove elements, at least one of which comprises a broaching tool.
  • the broaching tool is fastened to the tongue- and-groove element at a distance from the first corner of the tongue-and- groove element, the distance being 0 - 20 % of the length of the first edge of the tongue-and-groove element.
  • a sealing medium feeding device is fastened to the tongue-and-groove element and the tongue-and-groove element is arranged in the soil and sealing medium is fed by means of the sealing medium feeding device in the cavity created by arranging the broaching tool in the soil.
  • the invention also relates to a tongue-and-groove element for the piling, the tongue-and-groove element comprising a broaching tool, which can be arranged to form a cavity in the soil.
  • the invention further relates to a sealed piling.
  • the invention also relates to a method for isolating contaminated soil.
  • Pilings are used for many different purposes.
  • the use of a piling in the form of a support wall is known for instance in waterfront structures such as piers, banks, dams, riverbanks and other corresponding target areas, in which the purpose of the wall is usually to support the soil.
  • the soil on the other side thereof normally forms a load, which the wall has to bear, whereas the other side of the wall can at least partly be open.
  • pilings are used for example as underground impounding walls for separating the contaminated soil-area from clean soil and thus for preventing polluted water from flowing, whereby the tightness of the sealing is understandably an important feature.
  • both supporting the load of the soil as well as watertightness are required of a piling.
  • the features required of a piling depend on the application of use.
  • the production material of the piling is selected according to the application of use and need.
  • Known materials are e.g. steel, concrete, wood, aluminium, plastics and glass fibre.
  • the soil quality of the construction site affects the choice of piling solution.
  • the soil can be for instance clay, sand or gravel. It can be soft or hard, wet or dry.
  • the granular size of the soil is of importance as well as how tightly the soil is packed i.e. what the compactness of the soil is like.
  • the location can also be a waste disposal site, where the soil is often comprised of degradable waste.
  • the problem commonly related to pilings is that they are not tight and watertight enough but water can flow through the piling, usually at the joint of two tongue-and-groove elements.
  • the piling is formed in soil from a group of metal tongue-and- groove elements, which comprise a tubular tongue closed at the lower end by a tip element and a tubular groove showing a longitudinal slot in its housing as well as a web connecting the tongues-and-grooves.
  • a pile shoe which is comprised of an elon- gated tip element and a collar having a diameter larger than the outer diameter of the tongue.
  • the tongue has above its collar flow apertures through which the mortar or corresponding hardening substance fed through the upper end of the pipe inside the tubular tongue the substance is transferred around the tongue in the cavity created by the pile shoe in the soil.
  • the groove is embedded around the tongue along the tongue in the hardening substance, whereby the substance remains between the tongue and groove as sealing and surrounds the groove as well.
  • the aim of the invention is to achieve a solution which reduces or at least partly eliminates the disadvantages of the prior art mentioned above.
  • the aim of the invention is to provide a method, in which the amount of valuable pipe material could be reduced in the joints between tongue-and-groove elements sealed with a sealing medium and thereby achieving an improved tightness in the joints with less costs than by using known techniques. It also an aim of the invention to achieve a tongue-and-groove element, a sealed piling as well as a method for isolating contaminated soil.
  • a sealed piling is formed in soil of at least two tongue-and-groove elements, at least one of which com- prises a broaching tool.
  • the broaching tool is fastened to the tongue-and-groove element at a distance from the first corner of the tongue- and-groove element, the distance being 0 - 20 % of the length of the first edge of the tongue-and-groove element.
  • a sealing medium feeding device is fastened to the tongue-and-groove element and the tongue-and-groove element is arranged in the soil and sealing medium is fed by means of the sealing medium feeding device in the cavity created by arranging the broaching tool in the soil.
  • the sealing medium feeding device is fastened to the tongue-and-groove element by means of an openable fastening device. It is further characteristic for a method according to the invention that the fastening device is released and the sealing medium feeding device is disconnected from the tongue-and-groove element after the tongue-and-groove element has been arranged at a desired depth inside the soil.
  • the invention also relates to a tongue-and-groove element for the piling, the tongue-and-groove element comprising a broaching tool, which can be arranged to form a cavity in the soil. It is typically characteristic for a tongue- and-groove element according to the invention that the tongue-and-groove element has a fastening tool, to which the sealing medium feeding device can detachably be fastened.
  • a further aim of the invention is a sealed piling, which is characterised in that it has been formed by using a method according to the present invention for forming a sealed piling. It can also be characteristic for a sealed piling related to the invention that it is comprised of tongue-and-groove ele- ments related to the invention.
  • the invention further relates to a method for isolating contaminated soil, which method is characterised in that the isolating is performed with a sealed piling according to the invention.
  • Fig. 1 shows a tongue-and-groove element according to the first embodiment of the invention
  • Fig. 2 shows a sealed piling according to a second embodiment of the invention
  • Fig. 3 shows the sealed piling according to a third embodiment of the invention as a cross section in the direction of the ground level
  • Fig. 4 shows a broaching tool according to a fourth embodiment of the invention
  • Fig. 5 shows the broaching tool according to a fifth embodiment of the invention
  • Fig. 6 shows the broaching tool according to a sixth embodiment of the invention
  • Fig. 7 shows the broaching tool according to a seventh embodiment of the invention
  • Fig. 8 shows the broaching tool according to an eighth embodiment of the invention
  • Fig. 9 shows an additional flange according to a ninth embodiment of the invention
  • Fig. 10 shows a solution according to a tenth embodiment of the invention
  • Fig. 11 shows a solution according to an eleventh embodiment of the invention.
  • a sealed piling is formed in soil of at least two tongue-and-groove elements, at least one of which comprises a broaching tool.
  • the broaching tool is fastened to the tongue-and-groove element at a distance from the first corner of the tongue- and-groove element, the distance being 0 - 20 % of the length of the first edge of the tongue-and-groove element.
  • a sealing medium feeding device is fastened to the tongue-and-groove element and the tongue-and-groove element is arranged in the soil and sealing medium is fed by means of the sealing medium feeding device in the cavity created by arranging the broaching tool in the soil.
  • the sealing medium feeding device is fastened to the tongue-and-groove element by means of an openable fastening device. It is further characteristic for the method according to the invention that the fastening device is released and the sealing medium feeding device is disconnected from the tongue-and-groove element after the tongue-and-groove element is arranged at a desired depth inside the soil.
  • the tongue-and-groove elements can typically be plate-like or pile-formed pieces made of steel, concrete, wood, aluminium, plastic or glass fibre. At least two tongue-and-groove elements are needed to form a sealed piling according to the invention. It is obvious to someone skilled in the art that a required amount of tongue-and-groove elements will be used, such as 3, 4, 5, 7, 10, 15 or 37.
  • the soil can for example be gravel, sand, clay, topsoil, waste from a waste disposal site or mixture of some of these constituents.
  • the task of the broaching tool is to form a cavity in the soil when the broaching tool is arranged in the soil with the tongue-and-groove element, the broaching tool being fastened to the tongue-and-groove element.
  • the purpose of the cavity is to be filled by the sealing medium and thus to seal the seam between two tongue-and-groove elements to be substantially liq- uidtight.
  • the broaching tool is described in more detail below.
  • the first edge of the tongue-and-groove element refers to that edge of the tongue-and-groove element, to a lock element of which the next tongue- and-groove element is fastened.
  • the first edge is one of those edges in the direction of which the tongue-and-groove element is arranged in the soil. In a typical tongue-and-groove element this first edge is a vertical edge.
  • the second edge of the tongue-and-groove element is an opposing edge in relation to the first edge and advantageously substantially parallel thereto.
  • the third edge of the tongue-and-groove element is that which normally remains on the surface of the soil or closest to the soil. The force required to arrange the element in the soil is mainly directed at the third edge.
  • the fourth edge of the tongue-and-groove element refers to that edge which leads when the tongue-and-groove element is arranged in the soil and which advantageously is substantially parallel to the third edge.
  • the first corner of the tongue-and-groove element refers to the corner between the first and fourth edge.
  • the broaching tool is fastened to the tongue- and-groove element at a distance from the first corner of the tongue-and- groove element, the distance being advantageously 0 - 20 % of the length of the tongue-and-groove element's first edge, more advantageously 0 - 15 %, very advantageously 0 - 10 %, still very advantageously 0 - 5 % of said distance.
  • the tongue-and-groove element can be arranged in the soil for example by beating, ramming, vibrating, pushing or by otherwise directing a suitable force at the third edge of the element. Arranging the tongue-and-groove element in the soil can also be referred to as installing, driving or sinking.
  • the tongue-and-groove elements are generally arranged in the soil vertically or substantially in a vertical position, however, the elements can also be arranged in the soil obliquely, whereby the angle between the tongue-and-groove element and the "surface" of the soil can be in the range of 0 - 180°.
  • the elements can thus be arranged in the soil for example horizontally.
  • the cavity created by the broaching tool is filled with sealing medium.
  • Ad- vantageously sealing medium is fed according to the sinking speed of the tongue-and-groove element so that the cavity created by the broaching tool medium can be used as sealing medium, which hardens in the cavity created by the broaching tool or an non-hardening sealing medium which substantially does not harden.
  • the sealing medium can be selected for example from the group comprising hydraulically hardening binding media, concrete, cement, blast furnace slag, bentonite and two-component plastics, for example two-component plastics of the resin type, as well as mixtures thereof.
  • the sealing medium is fed to the cavity by means of a sealing medium feeding device at least partly in an unhardened form, meaning that the sealing medium is sufficiently elastic and fluid in order to be fed by means of a feeding device.
  • the sealing medium fills the cavity and surrounds the first edge of the tongue-and-groove element arranged in the soil.
  • the sealing medium feeding device can be a pipe or a hose, for example, and its feeding head refers to that head of the feeding device through which the sealing medium exits the feeding device into the cavity created by the broaching tool.
  • the sealing medium feeding device is fastened to the tongue-and-groove element by means of an openable fastening device, which can be for example a wire, rope, string or other device suitable for fastening.
  • the fastening device is released and the sealing medium feeding device is disconnected from the tongue-and-groove element and pulled away from connection with the cavity filled with sealing medium after the tongue-and-groove element has been arranged at the desired depth inside the soil.
  • a first tongue- and-groove element When beginning to form a piling according to the invention, a first tongue- and-groove element has to be installed in the soil so, that there are no previously installed elements in the soil, to the immediate connection of which the first tongue-and-groove element could be installed.
  • the first tongue-and-groove element is thus installed in the soil without being able to fasten its second edge to a lock tool of another tongue-and-groove element and to the soft sealing medium surrounding it, as this other tongue- and-groove element has not been arranged in the soil in the situation in question.
  • a starting situation of this type occurs if a hardening sealing me- dium is used and if such a long time has passed after the previous tongue- and-groove element was installed that the sealing medium surrounding the first edge thereof has had time to substantially harden and the next tongue- and-groove element can not be arranged in the lock tool of the tongue-and- groove element previously installed in the soil.
  • the second tongue-and-groove element to be arranged in the soil is fitted in the lock tool of the first tongue- and-groove element previously arranged in the soil, which lock tool and the first edge of the first tongue-and-groove element previously arranged in the soil are surrounded by at least partly unhardened sealing medium.
  • the sec- ond edge of the second tongue-and-groove element thus substantially meets the first edge of the first tongue-and-groove element.
  • the lock tool may be typically a folding, rail or tubular tool equipped with a longitudinal slot in the edge of the tongue-and-groove element, in which the counterpart of the lock tool arranged in the next tongue-and-groove element can be arranged.
  • the tongue or the groove part can be discontinuous, for example so that the tongue part of the lock tool is a continuous pipe and the pipe of the groove part is discontinuous or so that the groove part is continuous and the tongue part is discontinuous.
  • the method according to the invention naturally also such tongue-and-groove elements can be used which do not have a lock tool.
  • the openable fastening device of the sealing medium feeding device is released and the sealing medium feeding device is disconnected from the tongue-and-groove element, whereafter the feeding device can be pulled away from the connection with the tongue-and-groove element arranged in the soil.
  • the sealing medium is allowed to harden in the " cavity so that is surrounds and seals the joint between two adjacent tongue- and-groove elements arranged in the soil.
  • non-hardening sealing medium can be used for sealing, which surrounds and seals the joint between two adjacent tongue-and-groove elements arranged in the soil.
  • a sealed piling a piling is meant, in which the joints between the tongue-and-groove elements are according to this example surrounded by and sealed with hardening or unhardened sealing medium.
  • sealing medium which does not harden, for example bentonite.
  • non-hardening sealing medium for sealing
  • the tongue-and-groove elements can be removed from the soil when they no longer are needed.
  • the method according to this em- bodiment can be used for example for forming a temporary piling or temporary impounding wall. After a usage according to this method the tongue- and-groove elements can be recycled and re-used for forming another piling.
  • the invention also relates to a tongue-and-groove element for the piling, the tongue-and-groove element comprising a broaching tool, which can be arranged to form a cavity in the soil. It is typically characteristic for a tongue- and-groove element according to the invention that the tongue-and-groove element comprises a fastening tool, to which the sealing medium feeding device can detachably be fastened.
  • the fastening tool can be for example a hook or a loop.
  • the sealing medium feeding device can detachably be fastened to the fastening tool, which entails that the fastening can easily be opened.
  • the fastening of the sealing medium feeding device to the fastening tool can advantageously be opened at ground level af- ter the tongue-and-groove element together with its broaching tool as well as the feeding device together with its fastening tool are arranged at a desired depth in the soil.
  • a wire can be used as an advantageous fastening device of the sealing medium feeding device, which wire can be pulled away from the connection with the fastening tool, whereby fastening of the sealing medium feeding device is released and the feeding device can be pulled away from the cavity and be re-used for filling the next cavity.
  • a lock tool can be used, which is openable at ground level by means of a bar or wire.
  • Such a tongue-and-groove element according to the invention is advanta- geously intended to be used together with the method according to the invention for forming a sealed piling. It is naturally also possible to use the tongue-and-groove element with methods of other types.
  • the fastening tool in the tongue-and-groove element is arranged in the broaching tool.
  • the fastening tool in which the sealing medium feeding device can detachably be arranged, is arranged in the broaching tool, advantageously inside the walls of the broaching tool, the feeding head of the sealing medium feeding device is easily arranged to be protected by the walls of the broaching tool, so that the soil can not get mixed with the sealing medium at the same time as the sealing medium exits the feeding head of the feeding device.
  • the fastening tool can advantageously be arranged in the immediate vicinity of the broaching tool, so that the feeding head of the sealing medium feeding device to be fastened to the fastening tool is at least partly protected by the walls of the broaching tool or substantially close to the broaching tool.
  • the feeding head of the sealing medium feeding device can be further away from the broaching tool so that the feeding head is not protected by the walls of the broaching tool, for example in the case of argillaceous soil which does not crumble in the cavity but the cavity substantially retains its original structure created by the broaching tool.
  • the sealing medium feeding device can detachably be fastened to the fastening tool by a fastening device.
  • the broaching tool is shaped like a box having one side open so that the walls of the broaching tool protect the feeding head of the sealing medium feeding device.
  • the open side of the boxlike broaching tool is most advantageously that side which is opposite to the bottom of the broaching tool and is limited to the walls of the broaching tool. In a typical operating situation, this open side is the upper side of the broaching tool.
  • the bottom of the broaching tool refers to that side of the broaching tool which leads when arranging the broaching tool in the soil.
  • the broaching tool can advantageously be boxlike or cylindrical and with regard to its walls the perpendicular cross section can be for example shaped like a quadrangle, triangle, pentagon or some other polygon or a circle, oval or ellips.
  • the bottom of the broaching tool can be regarding the walls of the broaching tool and the tongue-and-groove element substantially perpendicular or oblique.
  • the bottom can be advantageously even, more advantageously cone-shaped.
  • the bottom can be tapered towards its end or sharp, whereby when installing the tongue-and- groove element in the soil the friction forming between the broaching tool and the soil is remarkably reduced.
  • the broaching tool is ar- ranged in the first corner of the tongue-and-groove element and in the second corner of the tongue-and-groove element a notch corresponding to the size of the broaching tool is arranged.
  • the notch has advantageously substantially the shape and size of the broaching tool so that the tongue-and- groove element can easily be arranged in connection with the previously installed tongue-and-groove element and at the same depth therewith inside the soil.
  • the second corner of the tongue-and-groove element refers to the corner between the second and fourth edge of the element.
  • the broaching tool has a fastening pin for fastening the broaching tool to the tongue-and- groove element.
  • the fastening pin can be rail-formed or can resemble the lock of the tongue-and-groove element.
  • the fastening pin can also be a split pipe to be arranged around the lock of the tongue-and-groove element. With the aid of the fastening pin the broaching tool can be firmly fastened to the tongue-and-groove element.
  • an additional flange is arranged in the tongue-and-groove element for balancing the arranging of the tongue-and- groove element in the soil.
  • the additional flange can be made for example of steel plate by breaking and cutting-off and it can advantageously be fastened to the fourth edge of the tongue-and-groove element which typically is the lower edge of the tongue-and-groove element.
  • a resistance is formed between the fourth edge and the soil as well as the bottom of the broaching tool and the soil.
  • the purpose of the additional flange is to create a substantially equal resistance as the broaching tool creates in the first corner of the tongue- and-groove element.
  • the additional flange is advantageously fastened to the fourth edge of the tongue-and-groove element at a point which typically is closer to the second comer than the first corner. It is obvious to someone skilled in the art that the size and shape of the flange can be altered if necessary and the fastening point of the flange on the fourth edge of the tongue-and-groove element can be chosen on a case-specific basis de- pending on the characteristics of the soil, for example.
  • a tongue-and-groove element according to the invention can be made of a material selected from the group comprising steel, wood, concrete, aluminium, plastic, glass fibre and mixtures thereof.
  • a further aim of the invention is a sealed piling, which is characterised in that it has been formed by using a method according to the present invention for forming a sealed piling. It can also be characteristic for a sealed piling related to the invention that it is comprised of tongue-and-groove elements related to the invention.
  • the invention further relates to a method for isolating contaminated soil, which method is characterised in that the isolating is performed with a sealed piling according to the invention.
  • the flowing of liquid in the contaminated soil can remarkably well be prevented to flow outside the contaminated area as the sealed piling according to the invention is liquidtight and does not allow liquids flowing in the soil to penetrate.
  • Contaminated soil can be found for example in waste disposal sites, service station areas or factory areas.
  • Figure 1 shows a tongue-and-groove element 1 according to a first embodiment of the invention, in a first corner 9 of which element a broaching tool 2a, according to a fourth embodiment of the invention, is fastened, which broaching tool is shown in Figure 4 in more detail.
  • a broaching tool 2a according to a fourth embodiment of the invention
  • an additional flange 4 according to a ninth embodiment of the invention is fastened, which edge in the example according to the Figure is the lower edge of the element, and which flange is shown in more detail in Figure 9 serving the purpose of balancing the installing of the tongue-and-groove element 1 in the soil.
  • a notch 5 is arranged substantially having the shape and size of the broaching tool 2a, whereby the tongue-and-groove element 1 in question can easily be installed at the same depth as the corresponding tongue-and-groove element previously installed inside the soil so that the second corner of the tongue- and-groove element does not hit the broaching tool fastened to the previously installed element.
  • the Figure also shows a first edge 8 of the tongue- and-groove element.
  • Figure 2 shows a sealed piling according to a second embodiment of the invention.
  • Several tongue-and-groove elements 6a, 6b, 6c and 6d are installed in the soil and the joints between the elements are surrounded by a sealing medium 7.
  • the installation of one element 6e is not finished.
  • the second edge 12 of the element 6e to be installed is arranged in a lock tool of the adjacent element 6d previously installed in the soil, whereby the element 6e to be installed can be installed in the close vicinity of the adjacent element 6d previously installed in the soil.
  • the sealing medium 7 surrounding the first edge 11 of the adjacent element 6d previously installed in the soil has not had time to harden in the situation shown in the Figure and the second edge 12 of the element 6e to be installed is also covered by the sealing medium 7.
  • the sealing medium feeding device 13 is detachably fastened to the broaching tool 2a by the fastening device.
  • the feeding head of the sealing medium feeding device 13 is protected by the walls of the broaching tool 2a, wherefore the soil does not get mixed with fresh sealing medium 7.
  • the Figure also shows the third edge 16 of the tongue-and-groove element 6e to be installed, which edge in the situation of the Figure is the upper edge of the element, and by directing a suitable force at which edge the tongue-and-groove element can be in- stalled in the soil.
  • the tongue-and-groove element 6e in the soil sealing medium 7 is fed in the cavity created by the broaching tool 2a so that the cavity is the entire time substantially filled with sealing medium 7 up to the ground level 17.
  • Figure 3 shows a sealed piling according to a third embodiment of the in- vention as a cross section in the direction of the ground level.
  • the adjacent tongue-and-groove elements 18 are fastened to each other by means of the lock tools 22.
  • the seams between the adjacent elements 18 are surrounded by sealing medium 23.
  • FIG. 4 shows a broaching tool 2a according to a fourth embodiment of the invention, the cross section and bottom 24 of which are substantially quadrangle in shape and the bottom is substantially flat and perpendicular to the walls 25 of the broaching tool.
  • the Figure also shows the fastening tool 26 in the broaching tool, to which fastening tool the sealing medium feeding device can detachably be fastened by means of the fastening device.
  • the broaching tool 2a has a fastening pin 27, by means of which the broaching tool 2a can be fastened to the tongue-and-groove element.
  • There is a slot 10 in the wall 25 of the broaching tool 2a making it possible for the broaching tool 2a to be fitted on the level of the fourth edge of the tongue-and-groove element.
  • the broaching tool 2a is fastened ad- vantageously to the first corner of the tongue-and-groove element or substantially close to the corner so that the first corner of the tongue-and- groove element comes through the slot 10 inside the broaching tool 2a and the corner of the tongue-and-groove element can be fastened to the fastening pin 27 in the broaching tool 2a.
  • the fastening can take place by means of a friction joint, click joint, by welding or connecting to a fitting piece in the broaching tool. It is obvious, that also other known fastening means, such as nails, screws, pins, pop rivets or lock pins can be used for fastening.
  • the broaching tool 2a according to this embodiment is shown in Figure 1 installed in a tongue-and-groove element.
  • a broaching tool 2b according to a fifth embodiment of the inven- tion is shown, the cross section and bottom 29 of which are circular in shape and the bottom 29 is substantially flat and perpendicular to the wall 30 of the broaching tool.
  • the Figure also shows the fastening tool 26, the fastening pin 27 and the slot 31 in the wall of the broaching tool.
  • FIG. 6 shows a broaching tool 2c according to a sixth embodiment of the invention, the cross section of which is quadrangle in shape and the bottom 32 is oblique compared to the level, which is perpendicular to the walls 33 of the broaching tool.
  • Figure 7 shows a broaching tool 2d according to a seventh embodiment of the invention, the cross section of which is circular in shape and the bottom 35 is oblique compared to the level, which is perpendicular to the wall 36 of the broaching tool.
  • FIG. 8 shows a broaching tool 2e according to an eighth embodiment of the invention, wherein the sealing medium feeding device 13 is fastened to the fastening tool 26 of the broaching tool by means of a fastening device
  • the bottom 38 of the broaching tool is cone shaped which serves the purpose of reducing the friction between the soil and the broaching tool when installing the tongue-and-groove element and the broaching tool in the soil.
  • Figure 9 shows an additional flange 4 according to a ninth embodiment of the invention, which comprises wings 39, a tip element 40 and a slot 41 , in which the fourth edge of the tongue-and-groove element is fitted.
  • the additional flange according to this embodiment is shown in Figure 1 installed in a tongue-and-groove element.
  • Figure 10 shows a solution according to a tenth embodiment of the invention.
  • the Figure shows a wall 42 of the broaching tool being circular in shape in cross section and a fastening tool 26 for fastening the sealing medium feeding device.
  • the broaching tool is fastened to the tongue-and- groove element 43 by means of a fastening pin 44 resembling the lock of the tongue-and-groove element.
  • FIG 11 shows a solution according to an eleventh embodiment of the invention.
  • the Figure shows a wall 42 of a broaching tool being circular in shape in cross section and a fastening tool 26.
  • the broaching tool is fastened to the tongue-and-groove element 43 by a fastening pin 45, which is a split pipe to be arranged around the lock of the tongue-and-groove element.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Processing Of Solid Wastes (AREA)
PCT/FI2005/000234 2005-05-20 2005-05-20 Sealing of a piling WO2006123009A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
PCT/FI2005/000234 WO2006123009A1 (en) 2005-05-20 2005-05-20 Sealing of a piling
EP05742489.7A EP1888847B1 (de) 2005-05-20 2005-05-20 Abdichtung einer spundwand

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/FI2005/000234 WO2006123009A1 (en) 2005-05-20 2005-05-20 Sealing of a piling

Publications (2)

Publication Number Publication Date
WO2006123009A1 true WO2006123009A1 (en) 2006-11-23
WO2006123009B1 WO2006123009B1 (en) 2007-02-15

Family

ID=36699135

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/FI2005/000234 WO2006123009A1 (en) 2005-05-20 2005-05-20 Sealing of a piling

Country Status (2)

Country Link
EP (1) EP1888847B1 (de)
WO (1) WO2006123009A1 (de)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE608309C (de) * 1927-11-01 1935-01-21 Cie Intle Des Pieux Armes Fran Vorrichtung zur Herstellung von Ortpfaehlen aus Beton
GB518727A (en) 1938-08-29 1940-03-06 Harley Hugh Dalrymple Hay Improvements in or relating to interlocking sheet metal piling
GB570784A (en) * 1944-02-10 1945-07-23 Andrew Hood Improvements in or relating to concrete piling wall units
JPS56111717A (en) * 1980-10-20 1981-09-03 Sumitomo Metal Ind Ltd Joint of steel-pipe sheet pile
JPH09158173A (ja) * 1995-12-05 1997-06-17 Kubota Corp 鋼管柱列土留壁におけるアンカ−の施工方法
US5938375A (en) * 1997-12-17 1999-08-17 Sevonson Environmental Services, Inc. Method of sealing joints between adjacent sheet piling sections to form a continuous barrier and barriers formed using said method
FI990594A (fi) 1999-03-17 2000-09-18 Rautaruukki Oyj Ponttiseinä ja sen tiivistys
DE10337127A1 (de) * 2003-04-16 2004-10-28 Harald Gollwitzer Gmbh Pfahl zum Einbringen in einen Untergrund oder Baugrund

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE608309C (de) * 1927-11-01 1935-01-21 Cie Intle Des Pieux Armes Fran Vorrichtung zur Herstellung von Ortpfaehlen aus Beton
GB518727A (en) 1938-08-29 1940-03-06 Harley Hugh Dalrymple Hay Improvements in or relating to interlocking sheet metal piling
GB570784A (en) * 1944-02-10 1945-07-23 Andrew Hood Improvements in or relating to concrete piling wall units
JPS56111717A (en) * 1980-10-20 1981-09-03 Sumitomo Metal Ind Ltd Joint of steel-pipe sheet pile
JPH09158173A (ja) * 1995-12-05 1997-06-17 Kubota Corp 鋼管柱列土留壁におけるアンカ−の施工方法
US5938375A (en) * 1997-12-17 1999-08-17 Sevonson Environmental Services, Inc. Method of sealing joints between adjacent sheet piling sections to form a continuous barrier and barriers formed using said method
FI990594A (fi) 1999-03-17 2000-09-18 Rautaruukki Oyj Ponttiseinä ja sen tiivistys
WO2000055433A1 (en) 1999-03-17 2000-09-21 Rautaruukki Oyj Method for forming a bulkhead sealed with mortar and the bulkhead manufactured thereby and the tongue-and-groove element for the bulkhead
DE10337127A1 (de) * 2003-04-16 2004-10-28 Harald Gollwitzer Gmbh Pfahl zum Einbringen in einen Untergrund oder Baugrund

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 005, no. 190 (M - 100) 4 December 1981 (1981-12-04) *
PATENT ABSTRACTS OF JAPAN vol. 1997, no. 10 31 October 1997 (1997-10-31) *

Also Published As

Publication number Publication date
EP1888847A1 (de) 2008-02-20
WO2006123009B1 (en) 2007-02-15
EP1888847B1 (de) 2015-11-04

Similar Documents

Publication Publication Date Title
CN110130363A (zh) 装配式植入基坑围护桩与桩墙合一结构及其施工方法
WO2021105569A1 (en) Method for forming a pile wall in ground and a corresponding pile wall
JP6015751B2 (ja) 鋼製壁および鋼製壁の施工方法
KR101613039B1 (ko) 현장타설 콘크리트 말뚝과 소일 시멘트 말뚝을 이용한 차수 흙막이 벽체 시공방법 및 차수 흙막이 벽체
JP4882096B2 (ja) 遮水壁材の継手充填用注入材及び該注入材を使用した遮水壁の施工方法
EP1888847B1 (de) Abdichtung einer spundwand
JP4485006B2 (ja) 地下構造物の施工法
JP6940709B1 (ja) 擁壁及びその築造方法
WO2022200692A1 (en) Method for forming a wall structure in the ground by drilling and wall structure formed by drilling
JPH0613770B2 (ja) 親杭を有する山止め壁の造成方法
JP4623577B2 (ja) 場所打ち杭の構築方法
JPH01142121A (ja) コンクリート擁壁形成用矢板およびそれを使用したコンクリート擁壁の形成方法
KR200373276Y1 (ko) 강관파일의 지지력 확장구조
US20220282443A1 (en) Method for forming a pile wall in ground and a corresponding pile wall
JP2007231600A (ja) 門型カルバート
Pettit et al. Jet grouting: the pace quickens
JPH0470422A (ja) オープンケーソン工法
CN215669468U (zh) 一种扩底混凝土phc劲性桩
JP2003328357A (ja) 鋼管矢板工法
KR102103831B1 (ko) 가이드비트가 구비된 오거장치를 이용한 지중구조물의 시공방법
KR200373275Y1 (ko) 강관파일의 지지력 확장구조
JPH1088592A (ja) コンクリ−ト擁壁
JP2006265827A (ja) 地中貫入体の施工方法及びそのための鋼殻エレメント
JP2001064970A (ja) 埋込み杭施工装置
KR0167035B1 (ko) 흄관 매설공법

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application
DPE2 Request for preliminary examination filed before expiration of 19th month from priority date (pct application filed from 20040101)
NENP Non-entry into the national phase

Ref country code: DE

WWW Wipo information: withdrawn in national office

Country of ref document: DE

WWE Wipo information: entry into national phase

Ref document number: 2005742489

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: RU

WWW Wipo information: withdrawn in national office

Country of ref document: RU

WWP Wipo information: published in national office

Ref document number: 2005742489

Country of ref document: EP