WO2006010759A1 - Method for mounting and installing a gate and ready-to-be-installed gate - Google Patents

Method for mounting and installing a gate and ready-to-be-installed gate Download PDF

Info

Publication number
WO2006010759A1
WO2006010759A1 PCT/EP2005/053641 EP2005053641W WO2006010759A1 WO 2006010759 A1 WO2006010759 A1 WO 2006010759A1 EP 2005053641 W EP2005053641 W EP 2005053641W WO 2006010759 A1 WO2006010759 A1 WO 2006010759A1
Authority
WO
WIPO (PCT)
Prior art keywords
gate
leaf
supporting
self
members
Prior art date
Application number
PCT/EP2005/053641
Other languages
French (fr)
Inventor
Frédéric MORENA
François TISSOT
Original Assignee
Prokodis Snc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Prokodis Snc filed Critical Prokodis Snc
Priority to EP05769859A priority Critical patent/EP1781887B1/en
Priority to AT05769859T priority patent/ATE538283T1/en
Publication of WO2006010759A1 publication Critical patent/WO2006010759A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B11/00Means for allowing passage through fences, barriers or the like, e.g. stiles
    • E06B11/02Gates; Doors
    • E06B11/04Gates; Doors characterised by the kind of suspension
    • E06B11/045Gates; Doors characterised by the kind of suspension exclusively for horizontally sliding gates
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B7/00Special arrangements or measures in connection with doors or windows

Definitions

  • the present invention relates to a method for mounting and installing a portal.
  • the invention also relates to a gate ready for installation, that is to say a complete gate mounted in the factory with almost all or all its accessories.
  • Known gates are usually installed as follows: [0004] Two metal or masonry posts are attached to the ground and are connected to each other by a concrete beam (with sill) cast in a trench.
  • the cast-in-place concrete beam is extended on one side so as to support the leaf in the open position as well as the guide rail for sliding the leaf.
  • the portal is equipped with its security devices and mo ⁇ torisation devices. Possibly a telephone porter is realized or other means according to the specific requests of the customers.
  • the object of the invention is to overcome the disadvantages of the state of the art, by proposing a method for mounting and installing a portal and a portal ready for installation, which not only facilitate the installation, in realizing a saving of labor, but which, moreover, make it possible to obtain a precision and a quality of pose clearly improved.
  • the method for mounting and installing a gate is characterized by the following steps: a complete gate is prepared in the factory, ready to be laid ready for use, comprising a self-supporting lower beam on which is fixed at least two posts a motorization box, at least one leaf that can be moved between a position in which the leaf closes the space between the two posts and a position in which the leaf releases this space,
  • said adjustment members are constituted by at least two spaced crosspieces slidably and removably fixed to the beam, each carrying at their ends a vertical adjustment screw that can bear on the ground .
  • the gate comprises a leaf that can slide between a closed position and an open position, the lower beam au ⁇ toportante having a length at least equal to the distance between the two poles added by the sliding stroke of the leaf to the open position.
  • the self-supporting lower beam supports the guide rail of the leaf; the leaf is kept open until the concrete is fully cured; the self-supporting lower beam comprises a rear portion secured to the site.
  • the self-supporting beam is a hollow metal beam in which electrical cables supply power of the portal actuators, passage detection, telephone door and other;
  • the factory-fitted complete gate is transported from its place of assembly to a trailer, then from this trailer to the trench by means of a hoist.
  • the gate ready for installation is characterized in that it comprises a self-supporting lower beam supporting at least two posts, at least one movable leaf, at least one box containing electrical organs motorization of the gate and the electrical cables necessary to supply said electrical components, the assembly being transportable by a hoist and that the self-supporting beam comprises members to facilitate the installation of the gate allowing to maintain the gate resting on the ground and to adjust its position relative to the ground level and relative to a vertical plane, these bodies can be removed from the beam after the installation of the gate.
  • the gate is such that:
  • One of the posts comprises an interior volume enclosing detection members
  • One of the poles comprises a receiving volume forming a vertical box containing a telephone doorphone, passage detection and lighting means.
  • the post comprises a receiving volume forming a vertical box enclosing a telephone doorphone, passage detection members
  • the adjustment members are reusable because integral to the beam by bolting.
  • FIG. 1 is an exploded perspective view of the self-supporting beam of the gate according to the invention
  • Figure 2 is an exploded elevational view of the sliding leaf of the gate according to the invention
  • Figure 3 is a top view of the leaf; represented in FIG.
  • FIG. 4 is a perspective view of the gate completely mounted on the self-supporting beam with the option of a door
  • FIG. 5 is a perspective view showing the gate carried by a forklift towards the trailer of a truck
  • FIG. 6 is a perspective view showing the portal placed in a trench by means of a crane
  • FIG. 7 is a view in elevation and in longitudinal section of the ground, showing the gate placed in the trench,
  • FIG. 8 is a view from above of the gate shown in FIG. 7,
  • FIG. 9 is a view along arrow F of FIG. 7,
  • FIG. 10 is a side view of an adjustment member for laying the gate
  • FIG. 11 is a side view on a larger scale of the member shown in FIG. 10
  • FIG. 12 is a top view of FIG. the member according to FIG.
  • FIG. 13 is a perspective view of the beam laid in the trench showing the flow water flow bypassing this beam
  • FIG. 14 is an elevational view of another embodiment of a portal ready for laying
  • FIG. 15 is a view from above of FIG. 14.
  • the method for mounting and installing a gate comprises the following steps:
  • a complete gate is produced at the factory, as represented for example in FIG. 4, ready to be laid ready for use, comprising a self-supporting lower beam 1 (see FIG. 1) on which at least two posts are fixed. 2, 3, a box 12, at least one leaf 4 (see Figures 2 and 3) movable between a position in which the leaf 4 closes the space between the two posts 2, 3 and a position in which the leaf 4 frees this space.
  • the lower beam 1 and the leaf 4 may consist of several parts assembled with each other.
  • a trench 5 is dug (see FIGS. 6, 7, 8 and 9) able to receive the lower beam of the gate.
  • the gate Before sealing the beam 1, it adjusts the position of the gate so that the upper edge of the beam 1 is horizontal and located at the desired level relative to the self and that the posts 2, 3 are located in a vertical plane.
  • the latter is equipped on site with removable adjusting members 6, which can bear against the ground, which is removed after dur ⁇ curing the sealing concrete.
  • the elements 6 are used to maintain the gate in a vertical plane.
  • the adjusting members 6 are constituted by at least two and preferably three cross members 6 spaced slidably and removably fixed to the beam 1.
  • Each crosspiece 6 carries at its ends a vertical adjusting screw 7 which can bear on the ground 8 via a shim 9 (see Figure 9).
  • the gate comprises a leaf 4 slidable between a closed position and an open position (see Figure 7) and the self-supporting lower beam 1 has a length L at least equal to the distance between the two posts 2, 3 added by the sliding stroke of the leaf 4 to the open position.
  • the self-supporting lower beam 1 supports on its upper face the guide rail
  • the leaf 4 is held in the open position shown in Figure 7 until complete hardening of the concrete poured into the trench 5, which allows to free the passage, knowing that the assembly is immobilized by the bodies 6.
  • the self-supporting lower beam 1 further supports a vertical box 12 having the structure of a hollow pole enclosing portal mo ⁇ torisation and passage detection members, for example infrared cells.
  • the post 2 may also be hollow so as to achieve, by its internal volume, a vertical box 13 enclosing a telephone doorphone, passage detection members (infrared cells) and lighting.
  • the self-supporting beam 1 is, in the example shown, a hollow metal beam of rectangular section in two parts (see Figure 1), in which the electric cables supply power of the drive members of the gate, pass detection, doorphone and others that are housed in the boxes
  • the cabinet 12 and also the posts 2, 3 are based on ho ⁇ rizal plates 14, 15, 16, 17 (see Figure 1) located in the plane of the upper face of the beam 1. These plates 14 to 17 each comprise an opening through which one can pass a power supply cable organs housed in the boxes 12, 13.
  • Figure 5 shows that the complete gate mounted at the factory can be transported from its place of assembly to the trailer 18 of a truck, by means of a forklift 19 whose forks bear under the beam 1.
  • the second element of the beam is not mounted, to reduce the size of the portal.
  • the gate is placed in the trench 5 (see Figure 6) by means of a crane 20 whose cables are fixed to the beam 1.
  • the gate further comprises a gate 21 which is pivotally mounted to a pole 22 which is fixed at one end of the beam 1.
  • the self-supporting lower beam 1 supports a series of posts 3, 22, 23 of boxes 12, 13, a sliding leaf 4, a gate 21, a large element fixed gate 24 which covers the sliding leaf 4 when it is in the open position, a small fixed gate element 25 located next to the pole 22 and the gate 21.
  • the gate In the case where the gate must be placed on a sloping path 26 (see Figure 13), drainage is provided to promote the flow of water 27. This drainage bypasses the beam 1 so that it does not no dam vis-à-vis the flow of water.

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Barrages (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forklifts And Lifting Vehicles (AREA)
  • Devices For Checking Fares Or Tickets At Control Points (AREA)
  • Automobile Manufacture Line, Endless Track Vehicle, Trailer (AREA)

Abstract

The invention concerns a method for mounting and installing a gate, characterized by the following steps: producing in factory a complete gate, ready to be installed and ready for use, comprising a self-supporting lower beam (1) whereon are fixed two posts (2, 3), a motoring housing (12), at least one leaf (4) mobile between a position wherein the leaf (4) closes the space included between the two posts (2, 3) and a position wherein the leaf (4) clears said space, on the site where the gate is to be installed, digging a trench (5) for receiving the lower beam (1) of the gate, transporting the complete factory-built gate to the site of installation, setting the lower beam (1) supporting the rest of the gate in the trench (5), and sealing, with concrete, said beam (1) in said trench.

Description

Description Description
« Procédé pour monter et installer un portail et portail prêt à la pose »"Method for mounting and installing a gate and portal ready for installation"
[0001] La présente invention concerne un procédé pour monter et installer un portail. [0002] L'invention concerne également un portail prêt à la pose, c'est-à-dire un portail complet monté en usine avec la quasi-totalité, voire tous ses accessoires. [0003] Les portails connus sont habituellement installés de façon suivante : [0004] On fixe au sol deux poteaux métalliques ou en maçonnerie qui sont reliés entre eux par une poutre en béton (avec longrine) coulé dans une tranchée.The present invention relates to a method for mounting and installing a portal. The invention also relates to a gate ready for installation, that is to say a complete gate mounted in the factory with almost all or all its accessories. Known gates are usually installed as follows: [0004] Two metal or masonry posts are attached to the ground and are connected to each other by a concrete beam (with sill) cast in a trench.
[0005] Puis on place entre les deux poteaux, un vantail mobile. Dans le cas d'un vantail coulissant, la poutre en béton coulé sur place est prolongée sur un des côtés pour pouvoir supporter le vantail en position ouverte ainsi que le rail de guidage du cou- lissement du vantail.Then placed between the two poles, a mobile leaf. In the case of a sliding leaf, the cast-in-place concrete beam is extended on one side so as to support the leaf in the open position as well as the guide rail for sliding the leaf.
[0006] En fin d'installation, on équipe le portail de ses sécurités et d'organes de mo¬ torisation. Eventuellement un portier téléphonique est réalisé ou autre moyen en fonction des demandes spécifiques des clients..[0006] At the end of the installation, the portal is equipped with its security devices and mo¬ torisation devices. Possibly a telephone porter is realized or other means according to the specific requests of the customers.
[0007] Toutes ces opérations sont complexes, longues et coûteuses en main d' œuvre. [0008] Les documents DE 19856042, EP 1338742, WO 01/96700, EP 0590578 et EP 1096084 décrivent des portails à vantail coulissant. Ces portails sont composés de diverses parties qui sont assemblées et montées sur place, c'est-à-dire sur le lieu de pose du portail.All these operations are complex, long and expensive in manpower. DE 19856042, EP 1338742, WO 01/96700, EP 0590578 and EP 1096084 disclose sliding leaf gates. These portals are composed of various parts that are assembled and mounted on site, that is to say on the place of installation of the portal.
[0009] Le but de l'invention est de remédier aux inconvénients de l'état de la technique, en proposant un procédé pour monter et installer un portail ainsi qu'un portail prêt à la pose, qui non seulement facilitent la pose, en réalisant une économie de main d' œuvre, mais qui en outre, permettent d'obtenir une précision et une qualité de pose nettement améliorées.The object of the invention is to overcome the disadvantages of the state of the art, by proposing a method for mounting and installing a portal and a portal ready for installation, which not only facilitate the installation, in realizing a saving of labor, but which, moreover, make it possible to obtain a precision and a quality of pose clearly improved.
[0010] Suivant l'invention, le procédé pour monter et installer un portail est caractérisé par les étapes suivantes : on réalise en usine un portail complet, prêt à être posé prêt à l'emploi, comprenant une poutre inférieure autoportante sur laquelle on fixe au moins deux poteaux un coffret de motorisation, au moins un vantail pouvant être déplacé entre une position dans laquelle le vantail ferme l'espace compris entre les deux poteaux et une position dans laquelle le vantail libère cet espace,According to the invention, the method for mounting and installing a gate is characterized by the following steps: a complete gate is prepared in the factory, ready to be laid ready for use, comprising a self-supporting lower beam on which is fixed at least two posts a motorization box, at least one leaf that can be moved between a position in which the leaf closes the space between the two posts and a position in which the leaf releases this space,
- sur le lieu de pose du portail, on creuse une tranchée apte à recevoir la poutre inférieure du portail, - on transporte le portail complet réalisé en usine vers le lieu de pose, on pose la poutre inférieure supportant le reste du portail dans la tranchée et,- on the place of installation of the portal, one digs a trench able to receive the lower beam of the portal, the complete gate made in the factory is transported to the installation site, the lower beam supporting the rest of the gate is placed in the trench and,
- on scelle, au moyen de béton, ladite poutre dans ladite tranchée pour ajuster la position du portail, ce dernier est équipé en usine d'organes de réglage amovibles, pouvant venir en appui sur le sol, que l'on enlève après durcissement du béton de scellement.- Sealing, by means of concrete, said beam in said trench to adjust the position of the gate, the latter is factory equipped with removable adjustment members, which can bear on the ground, which is removed after hardening of the sealing concrete.
[0011] Le fait que l'ensemble du portail tout équipé soit supporté sur une poutre au¬ toportante permet de transporter et de poser l'ensemble dans la tranchée, en une seule opération, ce qui permet de réaliser une économie de main d' œuvre considérable et une pose extrêmement précise.The fact that the entire gate is fully supported on a beam au¬ toportante allows to transport and put the whole in the trench, in one operation, which allows for a saving of hand of considerable work and extremely precise laying.
[0012] Dans une version préférée de l'invention, lesdits organes de réglage sont constitués par au moins deux traverses espacées fixées de façon coulissante et amovible à la poutre, portant chacune à leurs extrémités une vis verticale de réglage pouvant prendre appui sur le sol.In a preferred version of the invention, said adjustment members are constituted by at least two spaced crosspieces slidably and removably fixed to the beam, each carrying at their ends a vertical adjustment screw that can bear on the ground .
[0013] On utilise avantageusement trois traverses et on place l'une des traverses sen¬ siblement au milieu de la longueur de la poutre.It is advantageous to use three sleepers and place one of the sleepers sen¬ sibly in the middle of the length of the beam.
[0014] Dans une application préférée de l'invention, le portail comporte un vantail pouvant coulisser entre une position fermée et une position ouverte, la poutre inférieure au¬ toportante ayant une longueur au moins égale à la distance comprise entre les deux poteaux additionnée par la course de coulissement du vantail vers la position ouverte.In a preferred application of the invention, the gate comprises a leaf that can slide between a closed position and an open position, the lower beam au¬ toportante having a length at least equal to the distance between the two poles added by the sliding stroke of the leaf to the open position.
[0015] Selon d'autres particularités de l'invention :According to other features of the invention:
- la poutre inférieure autoportante supporte le rail de guidage du vantail ; le vantail est maintenu en position ouverte jusqu'au durcissement complet du béton ; la poutre inférieure autoportante comprend une partie arrière solidarisée sur le chantier. la poutre autoportante est une poutre métallique creuse dans laquelle s'étendent des câbles électriques d'alimentation des organes de motorisation du portail, de détection de passage, du portier téléphonique et autres ;- The self-supporting lower beam supports the guide rail of the leaf; the leaf is kept open until the concrete is fully cured; the self-supporting lower beam comprises a rear portion secured to the site. the self-supporting beam is a hollow metal beam in which electrical cables supply power of the portal actuators, passage detection, telephone door and other;
- le portail complet monté en usine est transporté depuis son lieu de montage vers une remorque, puis de cette remorque vers la tranchée au moyen d'un engin de levage.- the factory-fitted complete gate is transported from its place of assembly to a trailer, then from this trailer to the trench by means of a hoist.
[0016] Selon un autre aspect de l'invention, le portail prêt à la pose est caractérisé en ce qu'il comprend une poutre inférieure autoportante supportant au moins deux poteaux, au moins un vantail mobile, au moins un coffret renfermant des organes électriques de motorisation du portail et les câbles électriques nécessaires pour alimenter lesdits organes électriques, l'ensemble étant transportable par un engin de levage et que la poutre autoportante comprend des organes pour faciliter la pose du portail permettant de maintenir ce portail en appui sur le sol et de régler sa position par rapport au niveau du sol et par rapport à un plan vertical, ces organes pouvant êtres enlevés de la poutre après la pose du portail.. [0017] Avantageusement, le portail est tel que :According to another aspect of the invention, the gate ready for installation is characterized in that it comprises a self-supporting lower beam supporting at least two posts, at least one movable leaf, at least one box containing electrical organs motorization of the gate and the electrical cables necessary to supply said electrical components, the assembly being transportable by a hoist and that the self-supporting beam comprises members to facilitate the installation of the gate allowing to maintain the gate resting on the ground and to adjust its position relative to the ground level and relative to a vertical plane, these bodies can be removed from the beam after the installation of the gate. Advantageously, the gate is such that:
- Il comporte un portillon monté pivotant à un poteau fixé à l'une des extrémités de la poutre inférieure autoportante,- It comprises a gate pivotally mounted to a pole fixed at one end of the self-supporting lower beam,
- L'un des poteaux comprend un volume intérieur renfermant des organes de détection,One of the posts comprises an interior volume enclosing detection members,
- L'un des poteaux comporte un volume de réception formant un coffret vertical renfermant un portier téléphonique, des organes de détection de passage et d'éclairage.- One of the poles comprises a receiving volume forming a vertical box containing a telephone doorphone, passage detection and lighting means.
Le poteau comporte un volume de réception formant un coffret vertical renfermant un portier téléphonique, des organes de détection de passage Les organes de réglage sont réutilisables car solidaires à la poutre par boulonnage.The post comprises a receiving volume forming a vertical box enclosing a telephone doorphone, passage detection members The adjustment members are reusable because integral to the beam by bolting.
[0018] D'autres particularités et avantages de l'invention apparaîtront encore dans la description ci-après.Other features and advantages of the invention will become apparent in the description below.
[0019] Aux dessins annexés, donnés à titre d'exemples non limitatifs :In the accompanying drawings, given as non-limiting examples:
- la figure 1 est une vue en perspective éclatée de la poutre autoportante du portail selon l'invention, la figure 2 est une vue en élévation éclatée du vantail coulissant du portail selon l'invention, la figure 3 est une vue de dessus du vantail représenté sur la figure 2,- Figure 1 is an exploded perspective view of the self-supporting beam of the gate according to the invention, Figure 2 is an exploded elevational view of the sliding leaf of the gate according to the invention, Figure 3 is a top view of the leaf; represented in FIG.
- la figure 4 est une vue en perspective du portail complètement monté sur la poutre autoportante avec l'option d'un portillon,- Figure 4 is a perspective view of the gate completely mounted on the self-supporting beam with the option of a door,
- la figure 5 est une vue en perspective montrant le portail transporté par un chariot élévateur vers la remorque d'un camion,FIG. 5 is a perspective view showing the gate carried by a forklift towards the trailer of a truck,
- la figure 6 est une vue en perspective montrant le portail posé dans une tranchée au moyen d'une grue,FIG. 6 is a perspective view showing the portal placed in a trench by means of a crane,
- la figure 7 est une vue en élévation et en coupe longitudinale du sol, montrant le portail posé dans la tranchée,FIG. 7 is a view in elevation and in longitudinal section of the ground, showing the gate placed in the trench,
- la figure 8 est une vue de dessus du portail représenté sur la figure 7, la figure 9 est une vue suivant la flèche F de la figure 7,FIG. 8 is a view from above of the gate shown in FIG. 7, FIG. 9 is a view along arrow F of FIG. 7,
- la figure 10 est une vue latérale d'un organe de réglage de la pose du portail, la figure 11 est une vue latérale à plus grande échelle de l'organe représenté sur la figure 10, la figure 12 est une vue de dessus de l'organe selon la figure 11,FIG. 10 is a side view of an adjustment member for laying the gate, FIG. 11 is a side view on a larger scale of the member shown in FIG. 10, FIG. 12 is a top view of FIG. the member according to FIG.
- la figure 13 est une vue en perspective de la poutre posée dans la tranchée montrant la trajectoire des eaux d'écoulement contournant cette poutre, la figure 14 est une vue en élévation d'une autre réalisation d'un portail prêt à la pose, la figure 15 est une vue de dessus de la figure 14.FIG. 13 is a perspective view of the beam laid in the trench showing the flow water flow bypassing this beam, FIG. 14 is an elevational view of another embodiment of a portal ready for laying, FIG. 15 is a view from above of FIG. 14.
[0020] Comme montré par les figures annexées, le procédé pour monter et installer un portail comprend les étapes suivantes :As shown in the accompanying figures, the method for mounting and installing a gate comprises the following steps:
[0021] On réalise en usine un portail complet, tel que représenté par exemple sur la figure 4, prêt à être posé prêt à l'emploi, comprenant une poutre inférieure autoportante 1 (voir figure 1) sur laquelle on fixe au moins deux poteaux 2, 3, un coffret 12, au moins un vantail 4 (voir figures 2 et 3) pouvant être déplacé entre une position dans laquelle le vantail 4 ferme l'espace compris entre les deux poteaux 2, 3 et une position dans laquelle le vantail 4 libère cet espace.A complete gate is produced at the factory, as represented for example in FIG. 4, ready to be laid ready for use, comprising a self-supporting lower beam 1 (see FIG. 1) on which at least two posts are fixed. 2, 3, a box 12, at least one leaf 4 (see Figures 2 and 3) movable between a position in which the leaf 4 closes the space between the two posts 2, 3 and a position in which the leaf 4 frees this space.
[0022] La poutre inférieure 1 et le vantail 4 peuvent être constitués de plusieurs parties assemblées les unes avec les autres. Sur le lieu de pose du portail, on creuse une tranchée 5 (voir figures 6, 7, 8 et 9) apte à recevoir la poutre inférieure du portail.The lower beam 1 and the leaf 4 may consist of several parts assembled with each other. At the place where the gate is laid, a trench 5 is dug (see FIGS. 6, 7, 8 and 9) able to receive the lower beam of the gate.
[0023] On transporte le portail complet réalisé en usine vers le lieu de pose, comme montré par les figures 5 et 6.We carry the complete gate made in the factory to the place of installation, as shown in Figures 5 and 6.
[0024] On pose (voir figure 6) la poutre inférieure 1 supportant le reste du portail dans la tranchée 5, on lui assemble la partie arrière la par boulonnage et on scelle, au moyen de béton, la poutre 1 dans la tranchée 5.It is laid (see Figure 6) the lower beam 1 supporting the rest of the gate in the trench 5, it assembles the rear part by bolting and sealed, by means of concrete, the beam 1 in the trench 5.
[0025] Avant de sceller la poutre 1, on ajuste la position du portail pour que le bord supérieur de la poutre 1 soit horizontal et situé au niveau désiré par rapport au soi et que les poteaux 2, 3 soient situés dans un plan vertical.Before sealing the beam 1, it adjusts the position of the gate so that the upper edge of the beam 1 is horizontal and located at the desired level relative to the self and that the posts 2, 3 are located in a vertical plane.
[0026] Pour ajuster la position du portail, ce dernier est équipé sur site d'organes de réglage amovibles 6, pouvant venir en appui sur le sol, que l'on enlève après dur¬ cissement du béton de scellement.To adjust the position of the gate, the latter is equipped on site with removable adjusting members 6, which can bear against the ground, which is removed after dur¬ curing the sealing concrete.
[0027] Lors de la pose du portail, de la coulée du béton dans la tranchée 5 et avant dur¬ cissement du béton, les éléments 6 servent à maintenir le portail dans un plan vertical.When laying the gate, pouring concrete in the trench 5 and before dur¬ curing concrete, the elements 6 are used to maintain the gate in a vertical plane.
[0028] Dans l'exemple représenté sur les figures 6, 7, 8, 9, 10, 11 et 12, les organes de réglage 6 sont constitués par au moins deux et de préférence trois traverses 6 espacées fixées de façon coulissante et amovible à la poutre 1. Chaque traverse 6 porte à ses extrémités une vis 7 verticale de réglage pouvant prendre appui sur le sol 8 par l'intermédiaire d'une cale 9 (voir figure 9).In the example shown in Figures 6, 7, 8, 9, 10, 11 and 12, the adjusting members 6 are constituted by at least two and preferably three cross members 6 spaced slidably and removably fixed to the beam 1. Each crosspiece 6 carries at its ends a vertical adjusting screw 7 which can bear on the ground 8 via a shim 9 (see Figure 9).
[0029] Dans l'exemple représenté sur les figures 4 à 9, le portail comporte un vantail 4 pouvant coulisser entre une position fermée et une position ouverte (voir figure 7) et la poutre inférieure autoportante 1 a une longueur L au moins égale à la distance comprise entre les deux poteaux 2, 3 additionnée par la course de coulissement du vantail 4 vers la position ouverte. [0030] La poutre inférieure autoportante 1 supporte sur sa face supérieure le rail de guidageIn the example shown in Figures 4 to 9, the gate comprises a leaf 4 slidable between a closed position and an open position (see Figure 7) and the self-supporting lower beam 1 has a length L at least equal to the distance between the two posts 2, 3 added by the sliding stroke of the leaf 4 to the open position. The self-supporting lower beam 1 supports on its upper face the guide rail
11 des galets inférieurs 10 du vantail 4, comme montré par exemple sur les figures 2 et 7.11 lower rollers 10 of the leaf 4, as shown for example in Figures 2 and 7.
[0031] Le vantail 4 est maintenu dans la position ouverte montrée par la figure 7 jusqu'au durcissement complet du béton coulé dans la tranchée 5, ce qui permet de libérer le passage, sachant que l'ensemble est immobilisé par les organes 6.The leaf 4 is held in the open position shown in Figure 7 until complete hardening of the concrete poured into the trench 5, which allows to free the passage, knowing that the assembly is immobilized by the bodies 6.
[0032] Dans l'exemple représenté, la poutre inférieure autoportante 1 supporte en outre un coffret vertical 12 ayant la structure d'un poteau creux renfermant des organes de mo¬ torisation du portail et de détection de passage, par exemple des cellules infrarouges.In the example shown, the self-supporting lower beam 1 further supports a vertical box 12 having the structure of a hollow pole enclosing portal mo¬ torisation and passage detection members, for example infrared cells.
[0033] Le poteau 2 peut par ailleurs être creux de sorte à réaliser, par son volume interne, un coffret vertical 13 renfermant un portier téléphonique, des organes de détection de passage (cellules infrarouges) et d'éclairage.The post 2 may also be hollow so as to achieve, by its internal volume, a vertical box 13 enclosing a telephone doorphone, passage detection members (infrared cells) and lighting.
[0034] La poutre autoportante 1 est, dans l'exemple représenté, une poutre métallique creuse de section rectangulaire en deux parties (voir figure 1), dans laquelle s'étendent des câbles électriques d'alimentation des organes de motorisation du portail, de détection de passage, du portier téléphonique et autres qui sont logés dans les coffretsThe self-supporting beam 1 is, in the example shown, a hollow metal beam of rectangular section in two parts (see Figure 1), in which the electric cables supply power of the drive members of the gate, pass detection, doorphone and others that are housed in the boxes
12 et 13.12 and 13.
[0035] Le coffret 12 ainsi que d'ailleurs les poteaux 2, 3 reposent sur des plaques ho¬ rizontales 14, 15, 16, 17 (voir figure 1) situées dans le plan de la face supérieure de la poutre 1. Ces plaques 14 à 17 comportent chacune une ouverture par laquelle on peut faire passer un câble d'alimentation électrique des organes logés dans les coffrets 12, 13.The cabinet 12 and also the posts 2, 3 are based on ho¬ rizal plates 14, 15, 16, 17 (see Figure 1) located in the plane of the upper face of the beam 1. These plates 14 to 17 each comprise an opening through which one can pass a power supply cable organs housed in the boxes 12, 13.
[0036] De même pour tout ajout de poteau, il y aura une plaque (idem 14 à 17) sup¬ plémentaire qui sera au travers de la poutre communicante avec les autres.Similarly for any addition of post, there will be a plate (idem 14 to 17) sup¬ supplemental which will be through the communicating beam with the others.
[0037] La figure 5 montre que le portail complet monté en usine peut être transporté depuis son lieu de montage vers la remorque 18 d'un camion, au moyen d'un chariot élévateur 19 dont les fourches prennent appui sous la poutre 1. Lors de ce transport, le second élément la de la poutre n'est pas monté, afin de diminuer l'encombrement du portail.Figure 5 shows that the complete gate mounted at the factory can be transported from its place of assembly to the trailer 18 of a truck, by means of a forklift 19 whose forks bear under the beam 1. When this transport, the second element of the beam is not mounted, to reduce the size of the portal.
[0038] Sur le lieu de pose, le portail est mis en place dans la tranchée 5 (voir figure 6) au moyen d'une grue 20 dont les câbles sont fixés à la poutre 1.At the place of installation, the gate is placed in the trench 5 (see Figure 6) by means of a crane 20 whose cables are fixed to the beam 1.
[0039] Dans l'exemple représenté sur les figures 4, 5 et 6, le portail comprend en outre un portillon 21 qui est monté pivotant à un poteau 22 qui est fixé à l'une des extrémités de la poutre 1.In the example shown in Figures 4, 5 and 6, the gate further comprises a gate 21 which is pivotally mounted to a pole 22 which is fixed at one end of the beam 1.
[0040] Dans l'exemple du portail représenté sur les figures 14 et 15, la poutre inférieure autoportante 1 supporte une série de poteaux 3, 22, 23 des coffrets 12, 13, un vantail coulissant 4, un portillon 21, un grand élément de grille 24 fixe qui recouvre le vantail coulissant 4 lorsque celui-ci est en position ouverte, un petit élément de grille 25 fixe situé à côté du poteau 22 et du portillon 21. [0041] Dans le cas où le portail doit être posé sur un chemin en pente 26 (voir figure 13), un drainage est réalisé pour favoriser l'écoulement des eaux 27. Ce drainage contourne la poutre 1 afin que celle-ci ne fasse pas barrage vis-à-vis de l'écoulement des eaux.In the example of the gate shown in FIGS. 14 and 15, the self-supporting lower beam 1 supports a series of posts 3, 22, 23 of boxes 12, 13, a sliding leaf 4, a gate 21, a large element fixed gate 24 which covers the sliding leaf 4 when it is in the open position, a small fixed gate element 25 located next to the pole 22 and the gate 21. In the case where the gate must be placed on a sloping path 26 (see Figure 13), drainage is provided to promote the flow of water 27. This drainage bypasses the beam 1 so that it does not no dam vis-à-vis the flow of water.
[0042] REFERENCESREFERENCES
1. Poutre1. Beam
[0043] la. Partie arrièreThe. Rear part
1. Poteau1. Post
2. Poteau2. Post
3. Vantail3. Leaf
4. Tranchée4. Trench
5. Organe5. Body
6. Vis6. Screw
7. Sol7. Ground
8. Cale8. Wedge
9. Galet9. Roller
10. Rail de guidage10. Guide rail
11. Coffret11. Box
12. Coffret12. Box
13. Plaque13. Plate
14. Plaque14. Plate
15. Plaque15. Plate
16. Plaque16. Plate
17. Remorque17. Trailer
18. Chariot élévateur18. Forklift
19. Grue19. Crane
20. Portillon20. Gate
21. Poteau21. Post
22. Poteau22. Post
23. Elément de grille23. Grid element
24. Elément de grille24. Grid element
25. Chemin en pente25. Sloping path
26. Ecoulement eau 26. Water flow

Claims

Revendications claims
[0001] Procédé pour monter et installer un portail, caractérisé par les étapes suivantes : on réalise en usine un portail complet, prêt à être posé prêt à l'emploi, comprenant une poutre inférieure autoportante (1) sur laquelle on fixe au moins deux poteaux (2, 3) un coffret (12) de motorisation, au moins un vantail (4) pouvant être déplacé entre une position dans laquelle le vantail (4) ferme l'espace compris entre les deux poteaux (2, 3) et une position dans laquelle le vantail (4) libère cet espace, sur le lieu de pose du portail, on creuse une tranchée[0001] A method for mounting and installing a gate, characterized by the following steps: a complete gate ready for use is prepared at the factory, comprising a self-supporting lower beam (1) on which at least two posts (2, 3) a casing (12) motorization, at least one leaf (4) can be moved between a position in which the leaf (4) closes the space between the two posts (2, 3) and a position in which the leaf (4) releases this space, on the place of installation of the portal, one digs a trench
(5) apte à recevoir la poutre inférieure (1) du portail, on transporte le portail complet prêt à l'emploi réalisé en usine vers le lieu de pose, on pose la poutre inférieure (1) supportant le reste du portail dans la tranchée (5) et, on scelle, au moyen de béton, ladite poutre (1) dans ladite tranchée (5) pour ajuster la position du portail, ce dernier est équipé en usine d'organes de réglage (6) amovibles, pouvant venir en appui sur le sol, que l'on enlève après durcissement du béton de scellement.(5) suitable for receiving the lower beam (1) of the gate, the complete ready-to-use gate is transported from the factory to the laying site, the lower beam (1) supporting the rest of the gate is placed in the trench (5) and, said concrete, said beam (1) is sealed in said trench (5) to adjust the position of the gate, the latter is equipped at the factory with removable adjustment members (6), which can come into operation support on the ground, which is removed after hardening of the concrete.
[0002] Procédé selon la revendication 1, caractérisé en ce que lesdits organes de réglageMethod according to claim 1, characterized in that said adjusting members
(6) sont constitués par au moins deux traverses espacées fixées de façon coulissante et amovible à la poutre (1), portant chacune à leurs extrémités une vis verticale (7) de réglage pouvant prendre appui sur le sol.(6) are constituted by at least two spaced crosspieces slidably and removably fixed to the beam (1), each carrying at their ends a vertical screw (7) for adjustment that can bear on the ground.
[0003] Procédé selon la revendication 2, caractérisé en ce qu'on utilise trois traverses et on place l'une des traverses sensiblement au milieu de la longueur de la poutreMethod according to Claim 2, characterized in that three sleepers are used and one of the sleepers is placed substantially in the middle of the length of the beam.
(1).(1).
[0004] Procédé selon l'une quelconque des revendications 1 à 3, caractérisé en ce que le portail comporte un vantail (4) pouvant coulisser entre une position fermée et une position ouverte, la poutre inférieure autoportante (1) ayant une longueur au moins égale à la distance comprise entre les deux poteaux (2, 3) additionnée par la course de coulissement du vantail (4) vers la position ouverte.Method according to any one of claims 1 to 3, characterized in that the gate comprises a leaf (4) slidable between a closed position and an open position, the self-supporting lower beam (1) having a length at least equal to the distance between the two posts (2, 3) added by the sliding stroke of the leaf (4) to the open position.
[0005] Procédé selon la revendication 4, caractérisé en ce que la poutre inférieure au¬ toportante (1) supporte le rail de guidage (11) du vantail (4).Method according to claim 4, characterized in that the lower beam au¬ toportante (1) supports the guide rail (11) of the leaf (4).
[0006] Procédé selon l'une quelconque des revendications 4 ou 5, caractérisé en ce que le vantail (4) est maintenu en position ouverte jusqu'au durcissement complet du béton.Method according to any one of claims 4 or 5, characterized in that the leaf (4) is held in the open position until complete hardening of the concrete.
[0007] Procédé selon l'une quelconque des revendications 1 à 6, caractérisé par le fait que la poutre inférieure autoportante (1) comprend une partie arrière (la) so¬ lidarisée sur le chantier.Method according to any one of claims 1 to 6, characterized in that the self-supporting lower beam (1) comprises a rear part (la) so¬ lidarisée on site.
[0008] Procédé selon l'une quelconque des revendications 1 à 7, caractérisé en ce que la poutre autoportante (1) est une poutre métallique creuse dans laquelle s'étendent des câbles électriques d'alimentation des organes de motorisation du portail, de détection de passage, du portier téléphonique et autres.Method according to any one of claims 1 to 7, characterized in that the self-supporting beam (1) is a hollow metal beam in which extend electrical power supply cables of the gate operator, pass detection, telephone doorphone and others.
[0009] Procédé selon l'une quelconque des revendications 1 à 8, caractérisé en ce que le portail complet monté en usine est transporté depuis son lieu de montage vers une remorque (18), puis de cette remorque vers la tranchée (5) au moyen d'un engin de levage (19, 20).A method according to any one of claims 1 to 8, characterized in that the complete gate mounted at the factory is transported from its place of assembly to a trailer (18), then this trailer to the trench (5) at means of a hoist (19, 20).
[0010] Portail prêt à la pose caractérisé en ce qu'il comprend une poutre inférieure au¬ toportante (1) supportant au moins deux poteaux (2, 3), au moins un vantail mobile (4), au moins un coffret (12, 13) renfermant des organes électriques de motorisation du portail et les câbles électriques nécessaires pour alimenter lesdits organes électriques, l'ensemble étant transportable par un engin de levage (19, 20)., et que la poutre autoportante (1) comprend des organes (6) pour faciliter la pose du portail permettant de maintenir ce portail en appui sur le sol et de régler sa position par rapport au niveau du sol et par rapport à un plan vertical, ces organes (6) pouvant êtres enlevés de la poutre (1) après la pose du portail.Portal ready for installation characterized in that it comprises a lower au¬ toportante beam (1) supporting at least two posts (2, 3), at least one movable leaf (4), at least one cabinet (12). , 13) enclosing electric actuator members of the gate and the electric cables necessary for supplying said electric members, the assembly being transportable by a lifting apparatus (19, 20)., And that the self-supporting beam (1) comprises members (6) to facilitate the installation of the gate to maintain the gate resting on the ground and to adjust its position relative to the ground level and relative to a vertical plane, these bodies (6) can be removed from the beam ( 1) after the installation of the gate.
[0011] Portail selon la revendication 10, caractérisé en ce qu'il comporte un portillonGate according to claim 10, characterized in that it comprises a gate
(21) monté pivotant à un poteau (22) fixé à l'une des extrémités de la poutre inférieure autoportante (1).(21) pivotally mounted to a pole (22) attached to one end of the self-supporting lower beam (1).
[0012] Portail selon l'une quelconque des revendications 10 ou 11, caractérisé en ce que le poteau (3) comprend un volume intérieur renfermant des organes de détection.Gate according to any one of claims 10 or 11, characterized in that the pole (3) comprises an interior volume enclosing detection members.
[0013] Portail selon l'une quelconque des revendications 10 à 12, caractérisé en ce que le poteau (2) comporte un volume de réception formant un coffret vertical (13) renfermant un portier téléphonique, des organes de détection de passage et d'éclairage.Gate according to any one of claims 10 to 12, characterized in that the pole (2) comprises a receiving volume forming a vertical box (13) enclosing a telephone doorphone, passage detection members and lighting.
[0014] Portail selon l'une quelconque des revendications 10 à 13, caractérisé en ce que le poteau (3) comporte un volume de réception formant un coffret vertical renfermant un portier téléphonique, des organes de détection de passage. Gate according to any one of claims 10 to 13, characterized in that the pole (3) comprises a receiving volume forming a vertical box containing a telephone doorphone, passage detection members.
PCT/EP2005/053641 2004-07-27 2005-07-26 Method for mounting and installing a gate and ready-to-be-installed gate WO2006010759A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
EP05769859A EP1781887B1 (en) 2004-07-27 2005-07-26 Method for mounting and installing a gate and ready-to-be-installed gate
AT05769859T ATE538283T1 (en) 2004-07-27 2005-07-26 METHOD FOR ATTACHING AND INSTALLING A GATE AND READY TO INSTALL GATE

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR0451673 2004-07-27
FR0451673A FR2873743B1 (en) 2004-07-27 2004-07-27 METHOD FOR MOUNTING AND INSTALLING A PORTAL AND PORTAL READY TO INSTALL

Publications (1)

Publication Number Publication Date
WO2006010759A1 true WO2006010759A1 (en) 2006-02-02

Family

ID=34947575

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/EP2005/053641 WO2006010759A1 (en) 2004-07-27 2005-07-26 Method for mounting and installing a gate and ready-to-be-installed gate

Country Status (4)

Country Link
EP (1) EP1781887B1 (en)
AT (1) ATE538283T1 (en)
FR (1) FR2873743B1 (en)
WO (1) WO2006010759A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2446645A (en) * 2007-02-15 2008-08-20 Barkers Engineering Ltd Security gate
US11649675B2 (en) 2021-03-17 2023-05-16 Troy Hinojosa Gate opener assembly

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3055143B1 (en) * 2016-08-18 2021-02-26 Etablissements Roy PILLAR FOR RECEIVING A LEAF, READY-TO-INSTALL LEAF AND PROCESS FOR INSTALLING SUCH A READY-TO-INSTALL LEAF
RU2694376C1 (en) * 2018-12-24 2019-07-12 Закрытое акционерное общество "Центр специальных инженерных сооружений научно-исследовательского и конструкторского института радиоэлектронной техники" (ЗАО "ЦеСИС НИКИРЭТ") Anti-rammer sliding gates
RU188758U1 (en) * 2018-12-24 2019-04-23 Закрытое акционерное общество "Центр специальных инженерных сооружений научно-исследовательского и конструкторского института радиоэлектронной техники" (ЗАО "ЦеСИС НИКИРЭТ") Anti ram sliding gates

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3228679A (en) * 1963-08-08 1966-01-11 Kansas Sheet Metal Co Inc Apparatus for supporting conduits in trenches
DE8405078U1 (en) * 1984-02-20 1984-07-12 Schmitt, geb. Rustler, Heidemarie, 8072 Manching GATE, LIKE GARDEN GATE OR THE LIKE.

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2313545A1 (en) * 1975-06-02 1976-12-31 Reimbert Andre Prefabricated gate unit unit for private estate entrances - having sill and posts cast in one piece and incorporating hinge pins
FR2648507B1 (en) * 1989-06-19 1994-03-04 Massa Gerard REUSABLE MONOBLOCK PORTAL SUPPORT
FR2686936B1 (en) * 1992-02-04 1995-02-10 Jacques Daum AUTOMATIC FENCE DOOR ASSEMBLY.
DE4232411A1 (en) 1992-09-28 1994-03-31 Hans Lechtenboehmer Sliding gate system
DE19856042C2 (en) 1998-12-04 2003-05-28 Dorma Gmbh & Co Kg Light metal frame profile system with floor guide
DE29914065U1 (en) * 1999-08-12 2000-02-17 Mvs Miete Vertrieb Service Ag Entrance sliding gate with floor guide outside the clear passage
BE1012951A3 (en) 1999-10-29 2001-06-05 Bekaert Sa Nv Sliding gate.
BE1013551A3 (en) 2000-06-13 2002-03-05 Bekaert Sa Nv Cantilever sliding gate.
ES2278822T3 (en) 2002-02-22 2007-08-16 Hautau Gmbh ADJUSTMENT OF THE MOUNTING HEIGHT OF A SLIDING SLIDING BRIDGE ON A BEARING DEVICE.

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3228679A (en) * 1963-08-08 1966-01-11 Kansas Sheet Metal Co Inc Apparatus for supporting conduits in trenches
DE8405078U1 (en) * 1984-02-20 1984-07-12 Schmitt, geb. Rustler, Heidemarie, 8072 Manching GATE, LIKE GARDEN GATE OR THE LIKE.

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2446645A (en) * 2007-02-15 2008-08-20 Barkers Engineering Ltd Security gate
GB2446645B (en) * 2007-02-15 2012-01-11 Barkers Engineering Ltd Security gate apparatus
US11649675B2 (en) 2021-03-17 2023-05-16 Troy Hinojosa Gate opener assembly

Also Published As

Publication number Publication date
EP1781887B1 (en) 2011-12-21
EP1781887A1 (en) 2007-05-09
FR2873743B1 (en) 2008-12-05
FR2873743A1 (en) 2006-02-03
ATE538283T1 (en) 2012-01-15

Similar Documents

Publication Publication Date Title
EP1781887B1 (en) Method for mounting and installing a gate and ready-to-be-installed gate
FR2928951A1 (en) MOBILE BACKGROUND DEVICE FOR SWIMMING POOL
EP2642046A1 (en) Fencing system
FR2521118A1 (en) IMPROVED ROLLING BRIDGE FOR ENERGY GENERATING GAS TURBINE BAYS
FR3009572A1 (en) SHADOW FOR PARKING AREA OF VEHICLE.
FR2968326A1 (en) SHELTER FOR ACCREDITATION BASINS
EP3280852B1 (en) Mobile-bottom device for swimming pools or hollow cavities
FR3033584B1 (en) MODULAR CONSTRUCTION FROM PREFABRICATED ELEMENTS
FR2964133A1 (en) Device for maintaining fixed vertical mast on vertical pillar managed on flat frame placed on building terrace, has piled elements on arm sides determined such that assembly constitutes ballasting mass sufficient to ensure mast stability
FR2919659A1 (en) Construction installation for lift-up garage door, has chamber allowing extended positioning of lintel, reception of motor unit formed by reversible moto-reducer, and insertion of transmission control unit to allow lifting of apron of door
FR2745842A1 (en) Retractable self-supporting cover for swimming pool
FR3009725A1 (en) ANCHORING DEVICE FOR MECHANICAL UPPERWORKING FOUNDATIONS, AND METHOD FOR MANUFACTURING SUCH A DEVICE
EP1528207A1 (en) Sliding gate for uneven terrain
EP3189200A1 (en) Gate slidable at the front and self-supporting at the rear
FR2876140A1 (en) Gate, has unitary structure ready to be installed in earthwork effectuated at reception location and comprising end columns, casements disposed on columns to which sealing units are associated, and beam connecting sealing units
FR2467816A1 (en) Hoist for lifting articles in window - has adjustable supports in window and horizontal sliding beam fixed inboard to vertical support
FR2942636A1 (en) Mobile floor for e.g. swimming pool, has covering structure comprising side rails constituted of plastic casing, and beam housed in casing, where beam is made of concrete that is cast and reinforced with metallic frame
FR2648507A1 (en) Reusable monobloc gate support
FR3048713A1 (en) PRE-ASSEMBLE BATH BASIN FORMING SPA, SWIMMING SPA OR SWIMMING POOL
FR2986808A1 (en) MOBILE SEALED BUILDING CONSISTING OF MULTIPLE TRONCONS
FR2531118A1 (en) Hydraulic barrage element and processes for installing it.
FR2934291A1 (en) TILE FORMWORK DEVICE AND VERTICAL MAT FOR RAISING SLAB FORMWORK
EP3099882A1 (en) Template for fitting a doorway, portal frame or the like
FR3046429A1 (en) STATIONARY SHELTER FOR STORING AT LEAST ONE ELECTRIC ENERGY STORAGE UNIT
FR3108354A1 (en) GATE THRESHOLD BLOCK AND GATE INCLUDING IT

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KM KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NA NG NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SM SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LT LU LV MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 2005769859

Country of ref document: EP

121 Ep: the epo has been informed by wipo that ep was designated in this application
WWP Wipo information: published in national office

Ref document number: 2005769859

Country of ref document: EP