US3685301A - Process and apparatus for the installation of jack piles - Google Patents

Process and apparatus for the installation of jack piles Download PDF

Info

Publication number
US3685301A
US3685301A US92375A US3685301DA US3685301A US 3685301 A US3685301 A US 3685301A US 92375 A US92375 A US 92375A US 3685301D A US3685301D A US 3685301DA US 3685301 A US3685301 A US 3685301A
Authority
US
United States
Prior art keywords
frame
jack
casing
footing
tunneling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US92375A
Inventor
Russel L Heacox
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
P AND Z CO Inc
Original Assignee
P AND Z CO Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by P AND Z CO Inc filed Critical P AND Z CO Inc
Application granted granted Critical
Publication of US3685301A publication Critical patent/US3685301A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/48Foundations inserted underneath existing buildings or constructions

Definitions

  • ABSTRACT Apparatus is illustrated for the placement of jack piles underneath footings of existing buildings, Typically, tunneling is provided to expose a segment of the building;
  • the jack pile apparatus of this invention is erected under the exposed footing. Once erected, the apparatus is jacked to securely rest on the bottom surface of the tunneling at its lower end and to support the exposed portion of the footing at its upper end.
  • the jack pile casing is jacked or crowded from the ap paratus in discrete sequential segments. Simultaneously with this jacking the earth from the center of the jack pile casing is removed with a continuous flight auger, Once the casing is inserted, concrete is used to fill the casing and support the exposed footing.
  • RUSSEL L. HEACOX ATTORNEYS l l I l l I l l IHHHHHH PROCESS AND APPARATUS FOR THE INSTALLATION OF JACK PILES This invention relates to forming piles in the ground. More particularly, this relates to jack piles which are commonly crowded in the ground underneath existing building footings and thereafter formed to support building footings.
  • a tunneling underneath the footing of a building is first made. This tunneling exposes typically a small part and less than all of the under surface of the building footing. Thereafter, a hollow casing having the outer diameter of the jack pile is forced or crowded into the ground. Typically, this forcing or crowding is done by placing a jack against the exposed portion of the building footing at its upper end and against the upward and exposed portion of the pile casing at its lower end. When the jack is expanded, the pile casing is driven or crowded into the ground.
  • a hand-supported and rotated auger is inserted interior of the casing.
  • these augers consist of a series of rods having at their bottommost portion an auger of one, two or three flights.
  • the auger is revolved by hand to loosen small quantities of soil (approximately 6 or 8 inches). When such a small quantity of soil is loosened, the auger is brought to the surface, and the loose soil removed. The auger is then reinserted into the earth and the sequence repeated.
  • An object of this invention is to disclose an apparatus for the placement of jack pile casings into the ground. Accordingly, a frame structure is disclosed which bears on the bottom of the tunneling on one hand and on the exposed under portion of the building footing on the other hand.
  • the jack pile casing, in the form of a pipe is crowded into the ground by a press table jacked from the framing. Simultaneously, a continuous flight auger within the jack pile casing is rotated by hydraulic motors; evacuation of earth from the center of the casing simultaneously occurs.
  • An advantage of this apparatus is that installation of jack pile casings is much faster; a crew of threemen working within the confines of a tunnel can install 60 feet of pile per 8-hour shift.
  • An additional advantage of this invention is that the mechanism is capable of supporting and rotating a continuous flight auger. Dirt can be continuously evacuated from the interior of a jack pile casing without periodic removal of the auger.
  • a further object of this invention is to securely brace both the mechanism for crowding the jack pile segments into the ground as well as the mechanism for supporting and rotating the auger. This is accomplished by securely jacking the frame of the apparatus in the invention between the bottom of the tunneling on one hand and the exposed portion of the building footing on the other hand.
  • An advantage of this bracing is that the building footing can be submitted to substantially constant loading.
  • the loading of the building is transmitted through the machine framing onto the exposed earth at the bottom of the tunneling.
  • the loading of the building footing shifts from the framing onto the jack pile segment being crowded into the ground.
  • a further advantage of the bracing of the machine framing is that true linearity of the jack pile and auger can be maintained during insertion of the jack pile.
  • a further object of this invention is to control the depth of penetration of the auger with respect to the depth of penetration of the jack pile casing. Accordingly, the auger motor and supported auger can be retarded with respect to the jack pile casing as they are both advanced into the ground.
  • An advantage of this adjustability of the auger with respect to the jack pile is that where jack pile casings are inserted below an existing water table, a plug of earth can be maintained at the bottom of the jack pile casing sufficient to prevent the percolation of water into the interior of the jack pile casing.
  • a further advantage of this invention is that the auger can be fixed with respect to the table which crowds the jack pile casing into the earth. With this adjustment, the auger can also be crowded into the earth.
  • a further object of this invention is to disclose an auger and motor for supporting and rotating the auger through which earth entrained in water from a flooded jack pile casing can be removed. Such removal of earth in water can be made without flooding the confines of the narrow tunneling under the building footing.
  • Yet another advantage of this invention is to provide for the erection and removal of the apparatus in discrete segments which can be conveniently handled in the narrow confines of a tunnel.
  • FIG. 2 is a perspective view similar to FIG. 1 but taken from a different angle showing the jack pile apparatus, press table, auger motor and footing jack with rnost of the frame not shown to facilitate understandmg;
  • FIG. 3 is a perspective view of a jack pile casing segment being crowded into the ground by a pressure plate with the auger segment being rotated interior of the casing segment;
  • FIG. 4 illustrates the jack pile segment of the casing of FIG. 3 completely crowded into the earth with an ad ditional jack pile segment and auger segment being placed for subsequent overlying and sequential insertion;
  • FIG. 5 shows the placed jack pile and auger segment immediately before further insertion of the jack pile casing into the ground.
  • the jack pile apparatus of this invention is shown in perspective during the installation of the jack pile.
  • the apparatus includes a frame A with a footing jack B mounted at the upper portion thereof. Typically, tunneling is made to expose a portion of a preexisting footing l4. Thereafter, frame A is assembled, underlying the footing. The footing jack B is then actuated so as to bear against the exposed portion of footing l4. Secure bracing of frame A and partial support of footing 14 results.
  • a jack pile casing segment C is shown being crowded into the ground by a pressure table D.
  • Pressure table D is in turn forced downwardly and onto jack pile casing segment C by hydraulic cylinders E braced within frame A.
  • a hydraulic motor F supported in a vertically movable cage G powers a continuous flight auger H.
  • continuous flight auger H serves to evacuate earth from the center of the casing segment C.
  • Jack pile segments C and continuous flight auger segments H are inserted into the ground in the sequence illustrated in FIGS. 3 through 5. Once insertion of the casing to the desired depth has completely occurred, auger H is withdrawn and the casing segments C are allowed to remain in place. Thereafter, the interior of easing segment C is filled with concrete, as by tremmie pouring or other techniques, and thereafter allowed to cure and harden. Subsequently, the jack pile apparatus is removed, the poured and cured jack pile connected to the underside of the exposed footing 14, and the tunnel filled. The result is that footing 14 at its exposed portion is completely underpinned.
  • a pile foundation can be provided for an existing building structure.
  • Frame A consists of three discrete segments. These segments are bottom frame segment 16, intermediate frame segment 18 and top frame segment 20.
  • All three frame segments have two features in common.
  • the frame sections are provided with l-beam segments 22 on either side.
  • I-beam segments 22 are each aligned with their front flanges 24 and their rear flanges 26 in parallel planes.
  • the webs 27 of each I- beam segment 22 are parallel and spaced apart.
  • each frame segment is placed in overlying relation and define opposed U-section channels.
  • These opposed U-section channels provide opposed U-sectioned tracks by which the press table D and auger motor supporting frame G can subsequently ride vertically up and down during insertion of the jack pile segment C interior of the ground.
  • the second feature that the frame segments have in common is that they each define an overlying and corresponding horizontal U-shaped section when viewed in plan.
  • This U-shaped section provides an interval in which the press table D, auger motor F, and auger motor supporting frame G can be moved upwardly and downwardly during insertion of the jack piles into the earth.
  • Bottom frame section 16 bears against the bottom of the tunneling at footing bars 30.
  • Footing bars 30 underlie each I-beam segment 22 at the two sides of the U- cross section of the frame A.
  • a transverse footing bar 32 extends across the frame interconnecting footing bars 30 on either side thereof. It can thus be seen that the two footing bars 30 and the transverse footing bar 32 together define the U-section'at the bottom of seg ment 16 of frame A.
  • each vertical beam 34 extendends upward the full length of frame segment 16.
  • two horizontal beams 36 are placed.
  • Horizontal beams 36 interconnect the top of each I- beam segment 22 of frame segment 16 with the top of each beam 34 defining the sides of the U-sectioned frame segment 16 at its upper end. Similarily, the top of the respective vertical beams 34 is connected by a horizontal beam (obstructed in the view here shown). This horizontal beam defines the bottom of the U-sectioned frame segment 16 at its upper end.
  • suitable cross bracing 38 can be provided in bottom frame segment 22 as required.
  • Middle frame segment 18 is constructed in a manner analogous to and complementary to bottom frame segment 16.
  • This section includes overlying I-beam segments 22, overlying'vertical beams 40, and beams and bracing interconnecting the vertical beams and I-beam' segments which are analogous to the bracing illustrated with respect to the bottom frame segment 16.
  • Top frame segment 20 is analogous to frame segments 16 and 18. This frame segment includes its own I-beam segments 22, its own vertical beams 42 and beams and bracing interconnecting the I-beam segments and vertical beams.
  • Frame A is designed primarily for vertical loading. This vertical loading is passed through the respective vertically aligned I-beam segments 22 and the vertical beams 34, 40 and 42 from the top of frame A to the bottom of frame A. Thus the load of the building exerted on the frame by footing jack B is passed through the frame to the bottom of the tunneling underlying the footing 14.
  • Top frame segment A has affixed rigidly thereto footing jack B.
  • the attachment of jack B to this portion of upper frame segment 20 can be best illustrated with respect to FIG. 2.
  • top portion of frame segment 20 accommodates interior of its U-shaped section four steel plates welded together in a rectangular section as viewed in plan.
  • Plates 45 and 46 form the side edges of the rectangle parallel to the side edges of the U-shaped section of frame A.
  • Plate 47 interconnects the inward ends of plates 45 and 46 and extends parallel to the bottom section of the U-shaped frame segment 20.
  • plate 48 closes the front portion of the rectangle across the forward ends of plates 45 and 46.
  • the rectangular frame consisting of plates 45 through 48 is rigidly welded and secured to frame segment 20 at its upper end. This rigid securing is necessary as substantially all of the ,vertical loading of the frame through footing jack B is transmitted through the rectangular frame of plates 45 through 48 to the frame A
  • Three horizontal plates are welded to the frame of plates 45-48.
  • a first bottom and central plate 50 is welded between rear plate 47 at one hand and forward plate 48 at the other end. Typically, the plate 50 is welded at the bottom medial portion of plates 47 and 48.
  • Plate 50 supports the end of a hydraulic cylinder 52.
  • Hydraulic cylinder 52 has an enclosed piston (not shown) and a rod 54 extending upwardly and concentrically from cylinder 52.
  • Rod 54 in turn attaches to a bearing plate 56 at its upward end.
  • Press table D includes a rectangular plate 62 and floor border plates 64, 65, 66 and 67.
  • Border plates 64-67 are typically welded at the edges of erectangular plate 62, extend above the upper surface and together form a boundary which enables the upper surface of the table to retain earth before it is removed. It will be noted that the overall rectangular section of plate 62 and framing plates 64-67 is such that the press table D will fit interior of the U-shaped cross section of frame A.
  • each set of paired and parallel bars 69, 70 are spaced apart so as to receive therebetween the rods 71 and 72 extending from the pistons interior of hydraulic cylinders E.
  • Bar sets 69 and and the ends of the respective piston rods 71 and 72 between the bars of each set are cross bored and pinned toaffix the press table D to the ends of the hydraulic piston rods.
  • Plates 64 and 65 have afiixed thereto U-shaped channels 74 and 75, respectively. These U-shaped channels 74 and 75 have U shape which is complementary to the opposed U-sectioned channels defined by lbeam segments 22. It will be immediately seen that hydraulic piston rods 71 and 72 are moved towards and away from hydraulic cylinders E, the press table in following such movement will be guided by U-shaped channels 74 and 75 riding in the opposed U-shaped channels of l-beam sections 22. With the alignment of the U-shaped channels 74, 75 within the opposed U- sectioned channels of l-bearn segments 22, the horizontal alignment of the press table D during movement towards and away from the bottom of the tunneling is assured.
  • Plate 62 is provided with a concentric bore 79.
  • bore 79 has a diameter which is slightly less than the diameter of the jack pile casing segment C. It can be seen that when the jack pile segment C is placed in centered abutment below the press table D, its periphery will contact press table D immediately adjacent the borders at aperture 78. The hollow interior of the segment C-will be exposed for removal of dirt.
  • auger motors F While press table functions to crowd casing segment C into the ground, auger motors F as supported by motor frames G serve to support and rotate continuous flight auger H.
  • paired hydraulic motors F mounted in coaxial relation each drive a hollow drive shaft 78. Motors F are each secured to plates 80 and 81 which are in turn fixed to a frame G.
  • Frame G is rectangular in plan having a cross section which fits interior of frame A.
  • This frame G typically constructed from angle bars, has U section channels 84, 85 affixed to either side thereof.
  • U-sectioned channels 84, 85 function in a manner analogous to the channels 74, 75 on press table D.
  • these U-sectioned channels ride interior of the opposing U-sections of l-beam segments 22 and provide horizontal alignment to the frame G and motors F during their sliding vertical movement interior of frame Unlike press table'D, hydraulic motors F and frame G are free to vertically move with respect to frame A.
  • the continuous flight auger normally will be crowded downwardly into the ground by its own weight, the weight of hydraulic motors F and the weight of frame G.
  • a second advantage of the free floating arrangement of the frame G and hydraulic motors F with respect to press table D is that where crowding of the auger into the earth is desired, frame G can be secured to press table D. This securing can occur by cables, can be adjusted to any particular interval, and is conveniently actuated by lowering press table D.
  • press table D when press table D is raised, frame G and its supported hydraulic motors F will also be raised.
  • the press table D can be used to raise and lower the auger where required.
  • continuous flight auger H this auger is of conventional construction save and except for a hollow bore 87 interior thereof.
  • hydraulic motors F at their drive shaft 79 are of conventional construction save and except for a ho]- low bore 88 therein. Bores 87 and 88 overlie one another, form a fluid-tight seal when motors F are conjoined to continuous flight auger H and can be used for the removal of drilling slurry removed by the auger when the jack pile casing is flooded.
  • the pile casing becomes flooded with water, earth removed from the center of the pile casing can no longer work its way up the continuous auger flights.
  • the earth forms a slurry with the ambient water and must be removed by pumping.
  • each jack pile casing segment C can be easily understood.
  • the jack pile segments C comprise a hollow steel pipe 100 having an inside diameter equal to the desired outside diameter of the poured and cured concrete portion of the jack pile.
  • Pipe typically extends for most of the length of each jack pile casing segment C and is surrounded at its upper portion by a welded sleeve 102.
  • Sleeve 102 typically has an inside diameter equal to the outside diameter of pipe 100. This sleeve has half its longitudinal lengths fastened to the upper portion of pipe 100. The remaining half of its longitudinal length protrudes upwardly and above the top of pipe 100.
  • sleeve 102 permits the lower ends of jack pile segments C at their respective pipes 100 to be freely received, centered and aligned when one casing segment C is placed on top of a lower casing segment C.
  • the placement of the jack pile casing segments is easily facilitated by the sleeves 102.
  • continuous flight auger H Theconstruction of continuous flight auger H is also easily understood.
  • the continuous flight auger H comes in segments, each segment being of a length equal to the length of the jack pile casing segment C.
  • the outer diameter of the continuous flight auger H is complementary to but slightly less than the inner diameter of pipe 100 of casing segment C. This permits the auger to evacuate substantially all of the earth interior of the casing segment C and additionally centers the auger H with respect to the pile casing as the pile casing is crowded into the earth.
  • a first jack pile segment C is shown being crowded into the earth. It will be noted that press table D is in contact with the upper portion of sleeve 102 and that the respective hydraulic piston rods 71, 72 from hydraulic cylinders E are pushing press table downwardly. At the same time, shaft 79 powered by hydraulic motors F is causing the continuous flight auger H to rotate.
  • the jack pile casing segments C each have a complementary section of auger H inserted within them.
  • This section of auger H is suspended by a hook which passes through the upper portion of the auger shaft at one end and drapes over the upper lip of sleeve 102 at the other end.
  • this retaining hook is of S-shape and of such a length so that the segment of the auger H is supported at a level well below the lower end of pipe 100 of easing segment C.
  • frame A is provided with a small hydraulic winch 108 at the forward end thereof.
  • cable 109 from this winch is passed around the outside surface of the casing segment C and its contained auger segment H and lifted to a position where the casing segment and auger segment can be swung into place overlying previously installed pile casing segments and auger flights already in the earth.
  • hook 105 will permit the lower end of auger segment H to protrude downwardly and below the lower portion of pipe 100.
  • the jack pile apparatus and process of this invention will admit of a number of variations.
  • the frame structure A can be constructed of numerous configurations so long as it permits the sliding movement of apparatus for crowding the casing segment C into the ground and additionally centers the apparatus for supporting and rotating the continuous flight auger H.
  • numerous drilling apparatuses could be used.
  • jetting could be used.
  • other modifications may be made to the disclosed invention without departing from the spirit and scope thereof.
  • Apparatus for installing a jack pile casing downwardly into the earth under a footing partially exposed by tunneling comprising: a vertical frame for placement on the bottom of said tunneling underneath said exposed footing; a jack resting on said frame at one'end and expansible to transmit the downward loading from said exposed footing through said frame between said exposed portion of said footing at the top and said tunneling at the bottom; 'a press table attached to said frame for vertical up and down movement, said press table defining a surface for contacting the upwardly exposed portion of said jack pile casing upon downward movement of said table; means for jacking attached between said frame and said table for urging said table vertically downward with said jack pile casing into the ground whereby downward loading from said footing to said frame at least partially shifts from said frame at said tunneling to said jack pile casing to crowd said casing into the earth while maintaining substantially constant upward loading at said footmg.
  • a process of installing a jack pile casing comprising: tunneling underneath an existing footing to expose a part but not all of said footing; providing and placing a frame having a vertical dimension slightly less than the vertical distance between said exposed footing at the top and said tunneling at the bottom; providing and expanding an expansible jack member to brace said frame between said exposed footing at the top and said tunneling at the bottom to support at least a portion of the downward load of said footing through said frame from the bottom of said tunneling; jacking said jack pile casing downwardly into the ground from a point on said frame whereby at least a portion of the load from said footing is shifted from said frame on the bottom of said tunneling to said casing being jacked.
  • Apparatus for installing jack pile casings underneath a portion of a foundation exposed by a tunneling comprising: a frame extending substantially between the bottom of said tunneling on one hand and the exposed portion of said foundation on the other hand; a horizontal press table attached to said frame; means for moving said press table vertically on said frame and maintaining said press table horizontal during said vertical movement; means for jacking said press table downwardly from a point of said frame; said press table configured at the lower surface for abutting the upper portion of a jack pile casing and crowding said casing into the ground; said press table further defining an aperture for permitting earth interior of said casing to be removed through said press table to the exterior of said casing; a continuous flight auger dependingly supported from a point on said frame through said aperture interior of said casing; and, means for rotating said auger attached to said auger and frame for removing earth from said jack pile casing segment as it is crowded into the ground.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

Apparatus is illustrated for the placement of jack piles underneath footings of existing buildings. Typically, tunneling is provided to expose a segment of the building. The jack pile apparatus of this invention is erected under the exposed footing. Once erected, the apparatus is jacked to securely rest on the bottom surface of the tunneling at its lower end and to support the exposed portion of the footing at its upper end. The jack pile casing is jacked or crowded from the apparatus in discrete sequential segments. Simultaneously with this jacking the earth from the center of the jack pile casing is removed with a continuous flight auger. Once the casing is inserted, concrete is used to fill the casing and support the exposed footing.

Description

United States Patent Heacox [72] Inventor: Russel L. Heacox, Santa Rosa, Calif. [73] Assignee: P & Z Company, Inc., South San Francisco, Calif.
[22] Filed: Nov. 24, 1970 [21] App1.No.: 92,375
.[52] U.S.C1 ..6l/5l,61/53.5 [51] Int. Cl. ..E02d 27/48 [58] Field of Search ..61/51, 50, 53.5, 63, 45 A, 61/45, 45 D [56] References Cited UNITED STATES PATENTS 435,472 9/1890 Friestedt ..61/51 131,746 10/1872 Du Bois ..307/155 1,217,128 2/1917 White ..61/51 1,181,212 5/1916- Clark ..61/51 Rl3,532 2/1913 Breuchaud ..61/51 [151 3,685,301 [451 Aug. 22, 1972 FOREIGN PATENTS OR APPLICATIONS 985,351 1965 Great Britain ..6l/5l Primary Examiner-Jacob Shapiro Attorney-Townsend and Townsend [57] ABSTRACT Apparatus is illustrated for the placement of jack piles underneath footings of existing buildings, Typically, tunneling is provided to expose a segment of the building; The jack pile apparatus of this invention is erected under the exposed footing. Once erected, the apparatus is jacked to securely rest on the bottom surface of the tunneling at its lower end and to support the exposed portion of the footing at its upper end. The jack pile casing is jacked or crowded from the ap paratus in discrete sequential segments. Simultaneously with this jacking the earth from the center of the jack pile casing is removed with a continuous flight auger, Once the casing is inserted, concrete is used to fill the casing and support the exposed footing.
5 Claims, 5 Drawing Figures PNENTEDwszz I972 SHEET 1 0F 3 RUSSEL L. HEACOX FIG .1
- ATTORNEYS I PATENTED M1822 m2 SHEET 2 OF 3 v 1 INVENTOR; v
RUSSEL HEACOX I ATTORNEYS PATENT ED M1822 1912 SHEET 3 OF 3 I N VE NTOR. RUSSEL L. HEACOX ATTORNEYS l l I l l I l l IHHHHHH PROCESS AND APPARATUS FOR THE INSTALLATION OF JACK PILES This invention relates to forming piles in the ground. More particularly, this relates to jack piles which are commonly crowded in the ground underneath existing building footings and thereafter formed to support building footings.
Many buildings are commonly supported on large concrete blocks or pads. These blocks or pads rest against the soil underlying the building at their bottom surface and have the columns or other vertical supporting members of the building bearing on their upper surface.
After the building has been installed, it is frequently necessary to underpin and support such footings. This is necessity for additional support can arise when the building settles, when earth immediately adjacent the building is excavated, or when additional loadings are being placed within the building and on footings. Jack piles are commonly used to provide such underpinning.
In the conventional installation of jack piles, a tunneling underneath the footing of a building is first made. This tunneling exposes typically a small part and less than all of the under surface of the building footing. Thereafter, a hollow casing having the outer diameter of the jack pile is forced or crowded into the ground. Typically, this forcing or crowding is done by placing a jack against the exposed portion of the building footing at its upper end and against the upward and exposed portion of the pile casing at its lower end. When the jack is expanded, the pile casing is driven or crowded into the ground.
Simultaneously with such crowding or forcing of the pile easing into the ground, a hand-supported and rotated auger is inserted interior of the casing. Typically, these augers consist of a series of rods having at their bottommost portion an auger of one, two or three flights. As the jack pile casing is crowded into the ground, the auger is revolved by hand to loosen small quantities of soil (approximately 6 or 8 inches). When such a small quantity of soil is loosened, the auger is brought to the surface, and the loose soil removed. The auger is then reinserted into the earth and the sequence repeated.
The process of inserting jack piles heretofore known has several serious disadvantages. First, the insertion, rotation and removal of an auger by hand is laborious. Secondly, when jacking or crowding of a segment of jack pile casing into the ground occurs, the building footing is loaded vertically upward; when such jacking ceases, the building footing is not loaded. lacking the jack pile segments into the ground results in fluctuating loads on the building footing. Such a fluctuating loading on the building footings may not be desired, especially where the structure is old or extremely fragile. Finally, the process is slow; crews of four men are often limited to installing only feet of casing for an 8-hour shift in adverse soil conditions.
An object of this invention is to disclose an apparatus for the placement of jack pile casings into the ground. Accordingly, a frame structure is disclosed which bears on the bottom of the tunneling on one hand and on the exposed under portion of the building footing on the other hand. The jack pile casing, in the form of a pipe is crowded into the ground by a press table jacked from the framing. Simultaneously, a continuous flight auger within the jack pile casing is rotated by hydraulic motors; evacuation of earth from the center of the casing simultaneously occurs.
An advantage of this apparatus is that installation of jack pile casings is much faster; a crew of threemen working within the confines of a tunnel can install 60 feet of pile per 8-hour shift.
An additional advantage of this invention is that the mechanism is capable of supporting and rotating a continuous flight auger. Dirt can be continuously evacuated from the interior of a jack pile casing without periodic removal of the auger.
A further object of this invention is to securely brace both the mechanism for crowding the jack pile segments into the ground as well as the mechanism for supporting and rotating the auger. This is accomplished by securely jacking the frame of the apparatus in the invention between the bottom of the tunneling on one hand and the exposed portion of the building footing on the other hand.
An advantage of this bracing is that the building footing can be submitted to substantially constant loading. When the pile segments are not being jacked into the ground, the loading of the building is transmitted through the machine framing onto the exposed earth at the bottom of the tunneling. When a pile is being jacked into the ground, the loading of the building footing shifts from the framing onto the jack pile segment being crowded into the ground.
A further advantage of the bracing of the machine framing is that true linearity of the jack pile and auger can be maintained during insertion of the jack pile.
A further object of this invention is to control the depth of penetration of the auger with respect to the depth of penetration of the jack pile casing. Accordingly, the auger motor and supported auger can be retarded with respect to the jack pile casing as they are both advanced into the ground.
An advantage of this adjustability of the auger with respect to the jack pile is that where jack pile casings are inserted below an existing water table, a plug of earth can be maintained at the bottom of the jack pile casing sufficient to prevent the percolation of water into the interior of the jack pile casing.
A further advantage of this invention is that the auger can be fixed with respect to the table which crowds the jack pile casing into the earth. With this adjustment, the auger can also be crowded into the earth.
A further object of this invention is to disclose an auger and motor for supporting and rotating the auger through which earth entrained in water from a flooded jack pile casing can be removed. Such removal of earth in water can be made without flooding the confines of the narrow tunneling under the building footing.
Yet another advantage of this invention is to provide for the erection and removal of the apparatus in discrete segments which can be conveniently handled in the narrow confines of a tunnel.
Other objects, features and advantages of this inven- FIG. 2 is a perspective view similar to FIG. 1 but taken from a different angle showing the jack pile apparatus, press table, auger motor and footing jack with rnost of the frame not shown to facilitate understandmg;
FIG. 3 is a perspective view of a jack pile casing segment being crowded into the ground by a pressure plate with the auger segment being rotated interior of the casing segment;
FIG. 4 illustrates the jack pile segment of the casing of FIG. 3 completely crowded into the earth with an ad ditional jack pile segment and auger segment being placed for subsequent overlying and sequential insertion; and,
FIG. 5 shows the placed jack pile and auger segment immediately before further insertion of the jack pile casing into the ground.
Referring to FIG. 1, the jack pile apparatus of this invention is shown in perspective during the installation of the jack pile..The apparatus includes a frame A with a footing jack B mounted at the upper portion thereof. Typically, tunneling is made to expose a portion of a preexisting footing l4. Thereafter, frame A is assembled, underlying the footing. The footing jack B is then actuated so as to bear against the exposed portion of footing l4. Secure bracing of frame A and partial support of footing 14 results.
A jack pile casing segment C is shown being crowded into the ground by a pressure table D. Pressure table D is in turn forced downwardly and onto jack pile casing segment C by hydraulic cylinders E braced within frame A.
A hydraulic motor F supported in a vertically movable cage G powers a continuous flight auger H. During insertion of jack pile segment C into the ground, continuous flight auger H serves to evacuate earth from the center of the casing segment C.
Jack pile segments C and continuous flight auger segments H are inserted into the ground in the sequence illustrated in FIGS. 3 through 5. Once insertion of the casing to the desired depth has completely occurred, auger H is withdrawn and the casing segments C are allowed to remain in place. Thereafter, the interior of easing segment C is filled with concrete, as by tremmie pouring or other techniques, and thereafter allowed to cure and harden. Subsequently, the jack pile apparatus is removed, the poured and cured jack pile connected to the underside of the exposed footing 14, and the tunnel filled. The result is that footing 14 at its exposed portion is completely underpinned.
By the expedient of tunneling under and inserting jack piles at other portions of the building footing or footings, a pile foundation can be provided for an existing building structure.
Frame A consists of three discrete segments. These segments are bottom frame segment 16, intermediate frame segment 18 and top frame segment 20.
All three frame segments have two features in common. First, the frame sections are provided with l-beam segments 22 on either side. I-beam segments 22 are each aligned with their front flanges 24 and their rear flanges 26 in parallel planes. The webs 27 of each I- beam segment 22 are parallel and spaced apart.
The I-beam segments on opposite sides of each frame segment are placed in overlying relation and define opposed U-section channels. These opposed U-section channels provide opposed U-sectioned tracks by which the press table D and auger motor supporting frame G can subsequently ride vertically up and down during insertion of the jack pile segment C interior of the ground.
The second feature that the frame segments have in common is that they each define an overlying and corresponding horizontal U-shaped section when viewed in plan. This U-shaped section provides an interval in which the press table D, auger motor F, and auger motor supporting frame G can be moved upwardly and downwardly during insertion of the jack piles into the earth.
Bottom frame section 16 bears against the bottom of the tunneling at footing bars 30. Footing bars 30 underlie each I-beam segment 22 at the two sides of the U- cross section of the frame A. A transverse footing bar 32 extends across the frame interconnecting footing bars 30 on either side thereof. It can thus be seen that the two footing bars 30 and the transverse footing bar 32 together define the U-section'at the bottom of seg ment 16 of frame A.
At the two junctures of footing bars 30 and transverse footing bar 32, two vertical beams 34 are placed. Each vertical beam 34'extends upward the full length of frame segment 16. At the upper end of the vertical beams 34, two horizontal beams 36 are placed. Horizontal beams 36 interconnect the top of each I- beam segment 22 of frame segment 16 with the top of each beam 34 defining the sides of the U-sectioned frame segment 16 at its upper end. Similarily, the top of the respective vertical beams 34 is connected by a horizontal beam (obstructed in the view here shown). This horizontal beam defines the bottom of the U-sectioned frame segment 16 at its upper end. As is apparent, suitable cross bracing 38 can be provided in bottom frame segment 22 as required.
Middle frame segment 18 is constructed in a manner analogous to and complementary to bottom frame segment 16. This section includes overlying I-beam segments 22, overlying'vertical beams 40, and beams and bracing interconnecting the vertical beams and I-beam' segments which are analogous to the bracing illustrated with respect to the bottom frame segment 16.
Top frame segment 20 is analogous to frame segments 16 and 18. This frame segment includes its own I-beam segments 22, its own vertical beams 42 and beams and bracing interconnecting the I-beam segments and vertical beams.
Frame A is designed primarily for vertical loading. This vertical loading is passed through the respective vertically aligned I-beam segments 22 and the vertical beams 34, 40 and 42 from the top of frame A to the bottom of frame A. Thus the load of the building exerted on the frame by footing jack B is passed through the frame to the bottom of the tunneling underlying the footing 14.
Top frame segment A has affixed rigidly thereto footing jack B. The attachment of jack B to this portion of upper frame segment 20 can be best illustrated with respect to FIG. 2.
Referring to FIG. 2, it will be seen that the top portion of frame segment 20 accommodates interior of its U-shaped section four steel plates welded together in a rectangular section as viewed in plan. Plates 45 and 46 form the side edges of the rectangle parallel to the side edges of the U-shaped section of frame A. Plate 47 interconnects the inward ends of plates 45 and 46 and extends parallel to the bottom section of the U-shaped frame segment 20. Similarly, plate 48 closes the front portion of the rectangle across the forward ends of plates 45 and 46.
The rectangular frame consisting of plates 45 through 48 is rigidly welded and secured to frame segment 20 at its upper end. This rigid securing is necessary as substantially all of the ,vertical loading of the frame through footing jack B is transmitted through the rectangular frame of plates 45 through 48 to the frame A Three horizontal plates are welded to the frame of plates 45-48. A first bottom and central plate 50 is welded between rear plate 47 at one hand and forward plate 48 at the other end. Typically, the plate 50 is welded at the bottom medial portion of plates 47 and 48.
Plate 50 supports the end of a hydraulic cylinder 52. Hydraulic cylinder 52 has an enclosed piston (not shown) and a rod 54 extending upwardly and concentrically from cylinder 52. Rod 54 in turn attaches to a bearing plate 56 at its upward end.
It can thus be seen that when frame A is assembled underlying an exposed portion of a footing 14, the upward hydraulic movement of the rod 54 and bearing plate 56 will accomplish two objectives. First, plate 56 will contact and impart support to the footing. Secondly, plate 56 will load frame A through plates 50 and then plates 47 and 48 to compressively brace the frame A of the apparatus of this invention in place. The apparatus of this invention will thus be rigidly secured interior of the tunneling. As will become more fully apparent hereafter, the loading of footing jack B will be Shifted between the bottom of frame A and the jack pile casing segment C as the segments C are crowded into the earth.
In addition to supporting plates 50 thereacross, the
' frame of the plates 4548 supports at each end plates 58 and 60. Plates 58 and 60 are attached in spaced apart relation at either end of the plates 47 and 48 at their upper edges. These plates define between them an interval sufficient to accommodate hydraulic cylinder 52. Additionally, the plates each have a width sufficient to form a rest and support point for each of the hydraulic cylinders E.
Press table D includes a rectangular plate 62 and floor border plates 64, 65, 66 and 67. Border plates 64-67 are typically welded at the edges of erectangular plate 62, extend above the upper surface and together form a boundary which enables the upper surface of the table to retain earth before it is removed. It will be noted that the overall rectangular section of plate 62 and framing plates 64-67 is such that the press table D will fit interior of the U-shaped cross section of frame A.
Extending between framing plates 66 and 67 are two sets of parallel bars 69 and 70. These bars fasten plates 66 and 67 at either end, and to the rectangular plate 62 at their lower surface.
Typically, each set of paired and parallel bars 69, 70 are spaced apart so as to receive therebetween the rods 71 and 72 extending from the pistons interior of hydraulic cylinders E. Bar sets 69 and and the ends of the respective piston rods 71 and 72 between the bars of each set are cross bored and pinned toaffix the press table D to the ends of the hydraulic piston rods.
Plates 64 and 65 have afiixed thereto U-shaped channels 74 and 75, respectively. These U-shaped channels 74 and 75 have U shape which is complementary to the opposed U-sectioned channels defined by lbeam segments 22. It will be immediately seen that hydraulic piston rods 71 and 72 are moved towards and away from hydraulic cylinders E, the press table in following such movement will be guided by U-shaped channels 74 and 75 riding in the opposed U-shaped channels of l-beam sections 22. With the alignment of the U-shaped channels 74, 75 within the opposed U- sectioned channels of l-bearn segments 22, the horizontal alignment of the press table D during movement towards and away from the bottom of the tunneling is assured.
Plate 62 is provided with a concentric bore 79. Typically bore 79 has a diameter which is slightly less than the diameter of the jack pile casing segment C. It can be seen that when the jack pile segment C is placed in centered abutment below the press table D, its periphery will contact press table D immediately adjacent the borders at aperture 78. The hollow interior of the segment C-will be exposed for removal of dirt.
It will be remembered that when hydraulic motor F supports and rotates continuous flight auger H during crowding of the casing segment C into the ground, earth will be continuously discharged from the top of the continuous auger flight. This discharge of earth will occur through aperture 79 and onto the upper surface of plate 62 of press table D. Here the earth can be conveniently removed by shovel or other means.
While press table functions to crowd casing segment C into the ground, auger motors F as supported by motor frames G serve to support and rotate continuous flight auger H. With reference to FIG. 2, it will be seen that paired hydraulic motors F mounted in coaxial relation each drive a hollow drive shaft 78. Motors F are each secured to plates 80 and 81 which are in turn fixed to a frame G.
Frame G is rectangular in plan having a cross section which fits interior of frame A. This frame G, typically constructed from angle bars, has U section channels 84, 85 affixed to either side thereof.
U-sectioned channels 84, 85 function in a manner analogous to the channels 74, 75 on press table D. Typically, these U-sectioned channels ride interior of the opposing U-sections of l-beam segments 22 and provide horizontal alignment to the frame G and motors F during their sliding vertical movement interior of frame Unlike press table'D, hydraulic motors F and frame G are free to vertically move with respect to frame A. Thus, it will be seen that the continuous flight auger normally will be crowded downwardly into the ground by its own weight, the weight of hydraulic motors F and the weight of frame G.
This free floating arrangement of motors F and frame G relative to press table D furnishes several advantages. First, it is often desired to progressively retard auger flight F with respect to the pile casing segment C being crowded into the earth. Typically, where the pile casing segments are being placed below an ambient water table, a plug of earth must be maintained at the bottom of the casing C. Without such plug of earth being maintained, water will frequently percolate interior of the casing C, flood it in the entirety, and make the earth removal by the auger difficult or impossible to transport up the auger flights.
As is apparent, by the expedient of inserting wedges between the lower portion of frame G on one hand and the upper portion of press table D on the other hand, the relation between the advancement of the lowest auger segment H and the advancement of the lowest pile casing segment C can be easily controlled.
A second advantage of the free floating arrangement of the frame G and hydraulic motors F with respect to press table D is that where crowding of the auger into the earth is desired, frame G can be secured to press table D. This securing can occur by cables, can be adjusted to any particular interval, and is conveniently actuated by lowering press table D.
Thirdly, it will be observed that when press table D is raised, frame G and its supported hydraulic motors F will also be raised. Thus, the press table D can be used to raise and lower the auger where required.
Referring to continuous flight auger H, it will be noted that this auger is of conventional construction save and except for a hollow bore 87 interior thereof. Similarly, hydraulic motors F at their drive shaft 79 are of conventional construction save and except for a ho]- low bore 88 therein. Bores 87 and 88 overlie one another, form a fluid-tight seal when motors F are conjoined to continuous flight auger H and can be used for the removal of drilling slurry removed by the auger when the jack pile casing is flooded.
It will be remembered that the apparatus of this invention is used at the end of tunneling underneath the exposed footing of a building. Where piles are inserted below an existing water table, it sometimes is inevitable that the pile casing when inserted in the ground becomes flooded with water from the ambient water table. This is especially true where the jack piles are being placed in porous soils.
Once the pile casing becomes flooded with water, earth removed from the center of the pile casing can no longer work its way up the continuous auger flights. Typically, the earth forms a slurry with the ambient water and must be removed by pumping.
With the continuous flight auger H here shown, fluid is removed through the center aperture 87 in the auger and the center aperture 88 in the hydraulic motors F and pumped out through a hose connection 90 to the exterior of the tunnel. This removal of slurry prevents the spillage of water in the tunneling where such water could produce intolerable working conditions, and possibly cause undesired building settlement due to hydraulic mining. In the event that water must be placed into the jack pile casing segment C to replace the water being withdrawn, it can conveniently be poured through aperture 78 to pass down the auger flights for entraining displaced earth.
Referring to FIG. 3, the construction of each jack pile casing segment C can be easily understood. Typically, the jack pile segments C comprise a hollow steel pipe 100 having an inside diameter equal to the desired outside diameter of the poured and cured concrete portion of the jack pile. Pipe typically extends for most of the length of each jack pile casing segment C and is surrounded at its upper portion by a welded sleeve 102. Sleeve 102, typically has an inside diameter equal to the outside diameter of pipe 100. This sleeve has half its longitudinal lengths fastened to the upper portion of pipe 100. The remaining half of its longitudinal length protrudes upwardly and above the top of pipe 100.
As can be seen from FIGS. 4 and 5, sleeve 102 permits the lower ends of jack pile segments C at their respective pipes 100 to be freely received, centered and aligned when one casing segment C is placed on top of a lower casing segment C. Thus, the placement of the jack pile casing segments is easily facilitated by the sleeves 102.
Theconstruction of continuous flight auger H is also easily understood. Typically, the continuous flight auger H comes in segments, each segment being of a length equal to the length of the jack pile casing segment C.
The outer diameter of the continuous flight auger H is complementary to but slightly less than the inner diameter of pipe 100 of casing segment C. This permits the auger to evacuate substantially all of the earth interior of the casing segment C and additionally centers the auger H with respect to the pile casing as the pile casing is crowded into the earth.
Referring to FIG. '3, a first jack pile segment C is shown being crowded into the earth. It will be noted that press table D is in contact with the upper portion of sleeve 102 and that the respective hydraulic piston rods 71, 72 from hydraulic cylinders E are pushing press table downwardly. At the same time, shaft 79 powered by hydraulic motors F is causing the continuous flight auger H to rotate.
It will be noted at the lower end of the auger H that a plug of earth has been maintained between the lower edge of the casing segment C and the-lower end of the auger H. This will prevent flooding of the pile casing. Consequently, dirt will pass up the continuous flight auger and out through the aperture 78 in press table D.
It will be noted in FIG. 3 that the jack pile casing segment C is shown crowded almost to its full depth of penetration interior of the earth. Typically, when this occurs, shaft 79 will be disconnected from continuous flight auger H andpress table D retracted upwardly relative to frame A by the hydraulic retraction of piston rods 71, 72 into their respective hydraulic cylinders E. Once press table D has moved upwardly and towards the top of frame A, it will move with it hydraulic motors F and their supporting frame G. An interval will exist between the top of the jack pile casing segment C and the bottom of the press table D sufficient for the insertion of another jack pile casing segment C.
Referring to FIG. 4, the insertion of a jack pile casing segment C can be easily understood. Typically, the jack pile casing segments C each have a complementary section of auger H inserted within them. This section of auger H is suspended by a hook which passes through the upper portion of the auger shaft at one end and drapes over the upper lip of sleeve 102 at the other end. Typically, this retaining hook is of S-shape and of such a length so that the segment of the auger H is supported at a level well below the lower end of pipe 100 of easing segment C.
The casing segment C and its contained auger segment H are usually of considerable weight. Therefore, frame A is provided with a small hydraulic winch 108 at the forward end thereof. Typically, cable 109 from this winch is passed around the outside surface of the casing segment C and its contained auger segment H and lifted to a position where the casing segment and auger segment can be swung into place overlying previously installed pile casing segments and auger flights already in the earth.
As can be clearly viewed in FIG. 4, once casing segment C is raised, hook 105 will permit the lower end of auger segment H to protrude downwardly and below the lower portion of pipe 100. When the casing segment C is placed overlying a previously installed casing segment C, it will be seen that the coupling for the continuous flight auger H can be easily made without interference from the sidewalls of the pipe 100.
Once connection has been made between the two overlying continuous flight auger segments, cable 109 and the supported casing segment C will be lowered. Typically, the lower end of pipe 100 will fit concentrically interior of the upper sleeve 102. With such a fit, hook 105 will no longer be needed and will be removed as illustrated in FIG. 5. Once cable 109 is detached, press table D and shaft 79 will be engaged with the casing segment C and the auger segment H, respectively, and the insertion of the jack pile casing continued.
It will be understood, that the jack pile apparatus and process of this invention will admit of a number of variations. For example, the frame structure A can be constructed of numerous configurations so long as it permits the sliding movement of apparatus for crowding the casing segment C into the ground and additionally centers the apparatus for supporting and rotating the continuous flight auger H. Further, numerous drilling apparatuses could be used. For example, jetting could be used. Likewise, other modifications may be made to the disclosed invention without departing from the spirit and scope thereof.
What is claimed is:
1. Apparatus for installing a jack pile casing downwardly into the earth under a footing partially exposed by tunneling, said apparatus comprising: a vertical frame for placement on the bottom of said tunneling underneath said exposed footing; a jack resting on said frame at one'end and expansible to transmit the downward loading from said exposed footing through said frame between said exposed portion of said footing at the top and said tunneling at the bottom; 'a press table attached to said frame for vertical up and down movement, said press table defining a surface for contacting the upwardly exposed portion of said jack pile casing upon downward movement of said table; means for jacking attached between said frame and said table for urging said table vertically downward with said jack pile casing into the ground whereby downward loading from said footing to said frame at least partially shifts from said frame at said tunneling to said jack pile casing to crowd said casing into the earth while maintaining substantially constant upward loading at said footmg.
2. The apparatus of claim 1 and wherein said frame is fabricated in a plurality discrete and overlying segy me ts of co es horizon cross section an said press table s a comp ementary honzonta cross section to permit vertical movement of said press table over and between said discrete frame sections.
3. A process of installing a jack pile casing comprising: tunneling underneath an existing footing to expose a part but not all of said footing; providing and placing a frame having a vertical dimension slightly less than the vertical distance between said exposed footing at the top and said tunneling at the bottom; providing and expanding an expansible jack member to brace said frame between said exposed footing at the top and said tunneling at the bottom to support at least a portion of the downward load of said footing through said frame from the bottom of said tunneling; jacking said jack pile casing downwardly into the ground from a point on said frame whereby at least a portion of the load from said footing is shifted from said frame on the bottom of said tunneling to said casing being jacked.
4. Apparatus for installing jack pile casings underneath a portion of a foundation exposed by a tunneling comprising: a frame extending substantially between the bottom of said tunneling on one hand and the exposed portion of said foundation on the other hand; a horizontal press table attached to said frame; means for moving said press table vertically on said frame and maintaining said press table horizontal during said vertical movement; means for jacking said press table downwardly from a point of said frame; said press table configured at the lower surface for abutting the upper portion of a jack pile casing and crowding said casing into the ground; said press table further defining an aperture for permitting earth interior of said casing to be removed through said press table to the exterior of said casing; a continuous flight auger dependingly supported from a point on said frame through said aperture interior of said casing; and, means for rotating said auger attached to said auger and frame for removing earth from said jack pile casing segment as it is crowded into the ground.
5. The process of claim 3 and including the step of excavating the interior of said jack pile casing simultaneously with said jacking step by excavating with a first continuous auger flight when said first segment of said jack pile casing is jacked into the ground; disconnecting said first continuous auger flight, placing a second continuous auger flight section within said second jack pile casing segment; connecting said second continuous auger flight section to said first continuous auger flight section and simultaneously with said jacking of said first and second jack pile casings into the ground utilizing said first and second auger flights to excavate said interior of said jack pile casings.

Claims (5)

1. Apparatus for installing a jack pile casing downwardly into the earth under a footing partially exposed by tunneling, said apparatus comprising: a vertical frame for placement on the bottom of said tunneling underneath said exposed footing; a jack resting on said frame at one end and expansible to transmit the downward loading from said exposed footing through said frame between said exposed portion of said footing at the top and said tunneling at the bottom; a press table attached to said frame for vertical up and down movement, said press table defining a surface for contacting the upwardly exposed portion of said jack pile casing upon downward movement of said table; means for jacking attached between said frame and said table for urging said table vertically downward with said jack pile casing into the ground whereby downward loading from said footing to said frame at least partially shifts from said frame at said tunneling to said jack pile casing to crowd said casing into the earth while maintaining substantially constant upward loading at said footing.
2. The apparatus of claim 1 and wherein said frame is fabricated in a plurality discrete and overlying segments of corresponding horizontal cross section and said press table includes a complementary horizontal cross section to permit vertical movement of said press table over and between said discrete frame sections.
3. A process of installing a jack pile casing comprising: tunneling underneath an existing footing to expose a part but not all of said footing; providing and placing a frame having a vertical diMension slightly less than the vertical distance between said exposed footing at the top and said tunneling at the bottom; providing and expanding an expansible jack member to brace said frame between said exposed footing at the top and said tunneling at the bottom to support at least a portion of the downward load of said footing through said frame from the bottom of said tunneling; jacking said jack pile casing downwardly into the ground from a point on said frame whereby at least a portion of the load from said footing is shifted from said frame on the bottom of said tunneling to said casing being jacked.
4. Apparatus for installing jack pile casings underneath a portion of a foundation exposed by a tunneling comprising: a frame extending substantially between the bottom of said tunneling on one hand and the exposed portion of said foundation on the other hand; a horizontal press table attached to said frame; means for moving said press table vertically on said frame and maintaining said press table horizontal during said vertical movement; means for jacking said press table downwardly from a point of said frame; said press table configured at the lower surface for abutting the upper portion of a jack pile casing and crowding said casing into the ground; said press table further defining an aperture for permitting earth interior of said casing to be removed through said press table to the exterior of said casing; a continuous flight auger dependingly supported from a point on said frame through said aperture interior of said casing; and, means for rotating said auger attached to said auger and frame for removing earth from said jack pile casing segment as it is crowded into the ground.
5. The process of claim 3 and including the step of excavating the interior of said jack pile casing simultaneously with said jacking step by excavating with a first continuous auger flight when said first segment of said jack pile casing is jacked into the ground; disconnecting said first continuous auger flight, placing a second continuous auger flight section within said second jack pile casing segment; connecting said second continuous auger flight section to said first continuous auger flight section and simultaneously with said jacking of said first and second jack pile casings into the ground utilizing said first and second auger flights to excavate said interior of said jack pile casings.
US92375A 1970-11-24 1970-11-24 Process and apparatus for the installation of jack piles Expired - Lifetime US3685301A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US9237570A 1970-11-24 1970-11-24

Publications (1)

Publication Number Publication Date
US3685301A true US3685301A (en) 1972-08-22

Family

ID=22232913

Family Applications (1)

Application Number Title Priority Date Filing Date
US92375A Expired - Lifetime US3685301A (en) 1970-11-24 1970-11-24 Process and apparatus for the installation of jack piles

Country Status (1)

Country Link
US (1) US3685301A (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3796055A (en) * 1972-05-19 1974-03-12 R Mahony Method and apparatus for underpinning and raising a building foundation
US3869003A (en) * 1971-12-25 1975-03-04 Sanwa Kizai Co Ltd Pile drivers
JPS5256705A (en) * 1975-11-05 1977-05-10 Yutaka Mizutani Method of building direct support pile for builttup structure
US4626138A (en) * 1985-05-10 1986-12-02 Atlas Hydropiling Ltd. Non-impacting pile driver
US4634319A (en) * 1985-03-28 1987-01-06 Donald R. May Method and apparatus for lifting and supporting structures
US4800700A (en) * 1987-05-07 1989-01-31 Atlas System, Inc. Method and apparatus for lifting and supporting slabs
US4854782A (en) * 1987-11-25 1989-08-08 Sandra L. May Apparatus for lifting structures
US4923338A (en) * 1988-02-01 1990-05-08 Alfred Kunz Gmbh & Co. Process for lowering building structures
US5213448A (en) * 1992-12-11 1993-05-25 A. B. Chance Company Underpinning bracket for uplift and settlement loading
US5234290A (en) * 1991-11-04 1993-08-10 Rodney B. Stewart Prestressed caisson bearing pier and structural foundation device
US5269630A (en) * 1993-02-02 1993-12-14 Power Lift Foundation Repair Slab lifter
US5800094A (en) * 1997-02-05 1998-09-01 Jones; Robert L. Apparatus for lifting and supporting structures
US5980160A (en) * 1997-02-19 1999-11-09 Vanderklaauw; Peter M. Apparatus and method for a modular lifting and shoring system
US20050074298A1 (en) * 2003-10-06 2005-04-07 Jones Robert L. Modular tubular helical piering system
US7621098B2 (en) 2001-11-20 2009-11-24 Mfpf, Inc. Segmented foundation installation apparatus and method
US20100065331A1 (en) * 2008-09-11 2010-03-18 Harrison Stuart Ronald Auger boring machine
SE1830018A1 (en) * 2018-01-17 2019-07-18 Berg & Betongfoerstaerkning Ab Procedure for piling, piling rig for carrying out the procedure and pile for use in connection therewith
US20200385946A1 (en) * 2017-12-07 2020-12-10 Ihc Holland Ie B.V. A coupling system, an assembly of a vessel and a coupling system, and an assembly of a coupling system, jacket pile and foundation pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US13532A (en) * 1855-09-04 Ghaut-separator
US131746A (en) * 1872-10-01 Improvement in sinking metallic piles
US435472A (en) * 1890-09-02 Sand-band for vehicles
US1181212A (en) * 1905-07-08 1916-05-02 Amasa B Clark Method of constructing pile foundations.
US1217128A (en) * 1916-03-10 1917-02-20 Lazarus White Method of providing substructures for structures.
GB985351A (en) * 1963-01-29 1965-03-10 Ludwig Muller Method of and means for underpinning buildings

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US13532A (en) * 1855-09-04 Ghaut-separator
US131746A (en) * 1872-10-01 Improvement in sinking metallic piles
US435472A (en) * 1890-09-02 Sand-band for vehicles
US1181212A (en) * 1905-07-08 1916-05-02 Amasa B Clark Method of constructing pile foundations.
US1217128A (en) * 1916-03-10 1917-02-20 Lazarus White Method of providing substructures for structures.
GB985351A (en) * 1963-01-29 1965-03-10 Ludwig Muller Method of and means for underpinning buildings

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3869003A (en) * 1971-12-25 1975-03-04 Sanwa Kizai Co Ltd Pile drivers
US3796055A (en) * 1972-05-19 1974-03-12 R Mahony Method and apparatus for underpinning and raising a building foundation
JPS5256705A (en) * 1975-11-05 1977-05-10 Yutaka Mizutani Method of building direct support pile for builttup structure
JPS6026892B2 (en) * 1975-11-05 1985-06-26 裕 水谷 Method for creating direct support piles for existing structures
US4634319A (en) * 1985-03-28 1987-01-06 Donald R. May Method and apparatus for lifting and supporting structures
US4626138A (en) * 1985-05-10 1986-12-02 Atlas Hydropiling Ltd. Non-impacting pile driver
US4800700A (en) * 1987-05-07 1989-01-31 Atlas System, Inc. Method and apparatus for lifting and supporting slabs
US4854782A (en) * 1987-11-25 1989-08-08 Sandra L. May Apparatus for lifting structures
US4923338A (en) * 1988-02-01 1990-05-08 Alfred Kunz Gmbh & Co. Process for lowering building structures
US5234290A (en) * 1991-11-04 1993-08-10 Rodney B. Stewart Prestressed caisson bearing pier and structural foundation device
US5213448A (en) * 1992-12-11 1993-05-25 A. B. Chance Company Underpinning bracket for uplift and settlement loading
US5269630A (en) * 1993-02-02 1993-12-14 Power Lift Foundation Repair Slab lifter
US5800094A (en) * 1997-02-05 1998-09-01 Jones; Robert L. Apparatus for lifting and supporting structures
US5980160A (en) * 1997-02-19 1999-11-09 Vanderklaauw; Peter M. Apparatus and method for a modular lifting and shoring system
US6379085B1 (en) * 1997-02-19 2002-04-30 Peter M. Vanderklaauw Method and apparatus for relocating a structure from a first elevation to a second elevation
US7621098B2 (en) 2001-11-20 2009-11-24 Mfpf, Inc. Segmented foundation installation apparatus and method
US20050074298A1 (en) * 2003-10-06 2005-04-07 Jones Robert L. Modular tubular helical piering system
US7037045B2 (en) 2003-10-06 2006-05-02 Jones Robert L Modular tubular helical piering system
US20100065331A1 (en) * 2008-09-11 2010-03-18 Harrison Stuart Ronald Auger boring machine
US8424618B2 (en) 2008-09-11 2013-04-23 Vermeer Manufacturing Company Auger boring machine
US20200385946A1 (en) * 2017-12-07 2020-12-10 Ihc Holland Ie B.V. A coupling system, an assembly of a vessel and a coupling system, and an assembly of a coupling system, jacket pile and foundation pile
SE1830018A1 (en) * 2018-01-17 2019-07-18 Berg & Betongfoerstaerkning Ab Procedure for piling, piling rig for carrying out the procedure and pile for use in connection therewith

Similar Documents

Publication Publication Date Title
US3685301A (en) Process and apparatus for the installation of jack piles
US5123209A (en) Earth engineering apparatus and method
US3195312A (en) Method for erecting precast retaining wall
US3866425A (en) Method of and apparatus for the driving and extractor of sheet piles
US3820345A (en) Apparatus for laying pipe
US3250075A (en) Method of retaining wall construction and anchoring
US1943800A (en) Sectional wall and method of erecting it
US4146348A (en) Method for executing impermeable construction joints for diaphragm walls
US3606757A (en) Method for laying pipe
US3668874A (en) Shoring apparatus
US3496727A (en) Apparatus for laying pipe
US3969904A (en) Method of laying a pipeline in a trench
JP3782180B2 (en) Support structure using sheet piles for earth retaining bells
CN114875925B (en) Construction method of oversized deep foundation pit of subway tunnel adjacent to sea-filling stratum
US1751835A (en) Cofferdam and method of construction
CN217734010U (en) Bearing diagonal construction equipment for foundation ditch
JP3440661B2 (en) Tunnel protection method
JP4755361B2 (en) Vertical shaft construction method
JP2745083B2 (en) Tunnel construction method
JPH01304217A (en) Jack method of pile and jack device thereof
KR200315933Y1 (en) Excavating apparatus
JP2876525B2 (en) Soft ground consolidation equipment
JPH0466998B2 (en)
JP2023077832A (en) Construction method of underground structure
CN104131569A (en) Ultra-large ultra-deep kidney-shaped manually-excavated pile supporting structure and construction method