JP2023077832A - Construction method of underground structure - Google Patents

Construction method of underground structure Download PDF

Info

Publication number
JP2023077832A
JP2023077832A JP2021191301A JP2021191301A JP2023077832A JP 2023077832 A JP2023077832 A JP 2023077832A JP 2021191301 A JP2021191301 A JP 2021191301A JP 2021191301 A JP2021191301 A JP 2021191301A JP 2023077832 A JP2023077832 A JP 2023077832A
Authority
JP
Japan
Prior art keywords
underground
new
floor
constructing
underground structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2021191301A
Other languages
Japanese (ja)
Inventor
恵吾 松田
Keigo Matsuda
了 岸田
Satoru Kishida
健一 眞下
Kenichi Mashita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2021191301A priority Critical patent/JP2023077832A/en
Publication of JP2023077832A publication Critical patent/JP2023077832A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

To provide a construction method of a structure allowing a new underground structure to be additionally constructed with efficiency as removing an existing underground structure even in a narrow land.SOLUTION: A construction method of an underground structure comprises steps of: constructing earth-retaining walls 3 on a circumference of an existing underground structure 2; removing existing underground floors with the first predetermined number of floors below a first floor of the existing underground structure 2; installing first temporary earth-retaining timbering supporting the earth-retaining walls 3 from a first foundation surface appearing after removing the existing underground floors to a level of the first floor; constructing a plurality of underground piles columns 6 downward from the first foundation surface to a first determined depth; constructing a new underground floor surface on the first foundation surface; sequentially constructing new underground structures with the first predetermined number of the floors to a new first floor surface 7 upward from the new underground floor surface; excavating the foundation downward from the new underground floor surface 7 to a second foundation surface 12; constructing the foundation on the second foundation surface 12; installing second temporary earth-retaining timbering 13; and sequentially constructing additional new underground structures with the second predetermined number of the floors.SELECTED DRAWING: Figure 7

Description

本発明は、既存の構造物を撤去して地下構造物を増設する地下構造物の構築方法に関する。 The present invention relates to an underground structure construction method for removing an existing structure and adding an underground structure.

例えば、特許文献1には、既存の地下構造物を撤去して地下構造物を新設する地下構造物の構築方法が記載されている。この地下構造物の構築工法によれば、地盤を掘削しながら地下構造物を構築する逆打ち工法に基づいて、既存の地下構造物を解体しながら、新たに地下構造物を構築している。この地下構造物の構築工法は、以下の各工程を備えている。 For example, Patent Literature 1 describes a method of constructing an underground structure in which an existing underground structure is removed and a new underground structure is constructed. According to this underground structure construction method, a new underground structure is constructed while dismantling the existing underground structure based on the reverse construction method in which the underground structure is constructed while excavating the ground. This underground structure construction method includes the following steps.

既存地下構造物の外周に山留め壁を構築する。次に、既存地下構造物の地下躯体を貫通して仮支柱となる構真柱を設置する。次に、既存躯体の地下上部階を解体し、既存基礎下を掘削する。次に、構真柱および山留め壁に仮受材を取付け、仮受材にて既存躯体全体を支持し、1階先行床を構築する。次に、既存躯体下方では掘削をすすめ、床付け完了後、新築基礎を構築する。以後、既存地下躯体の解体と、新築地下躯体の構築と、新築地上躯体の構築とを適宜並行して行う。 A retaining wall will be constructed around the perimeter of the existing underground structure. Next, install structural pillars that will serve as temporary pillars through the underground skeleton of the existing underground structure. Next, the upper underground floor of the existing frame will be dismantled and the existing foundation will be excavated. Next, temporary supporting materials are attached to the structure pillars and retaining walls, and the entire existing frame is supported by the temporary supporting materials to construct the first floor preceding floor. Next, excavation will be carried out below the existing frame, and after the flooring is complete, the new foundation will be constructed. Thereafter, dismantle the existing underground skeleton, construct a new underground skeleton, and construct a new above-ground skeleton as appropriate in parallel.

特開2001-262595号公報JP-A-2001-262595

特許文献1に記載された地下構造物の構築方法等の逆打ち工法においては、例えば、大深度工事で、近接した公共交通機関がある場合、困難性が生じる可能性がある。例えば、逆打ち工法において施工対象領域の外周部に斜路スロープが設けられる場合、柱のような鉛直部材の下部からコンクリートをポンプで圧入して打設する圧入工法を用いたコンクリート打設が困難となる可能性がある。特許文献1に記載された地下構造物の構築方法等の逆打ち工法においては、例えば、精度確保の為、構真柱を地上において組み立てた後(以下、地組ともいう)、構真柱を地下に構築する。しかしながら、施工対象が狭小敷地である場合、1階に先行床を構築してから、構真柱を地下に構築しようとすると、敷地に比して構真柱が長くなり地組するためのスペースを確保できなくなる可能性がある。 In the reverse construction method such as the method for constructing an underground structure described in Patent Literature 1, for example, difficulties may arise in deep-deep construction in the presence of nearby public transportation. For example, when a sloped road is provided on the outer periphery of a construction target area in the reverse casting method, it is difficult to place concrete using the press-in method, in which concrete is pressed in from the bottom of a vertical member such as a pillar using a pump. may become. In the reverse construction method such as the underground structure construction method described in Patent Document 1, for example, in order to ensure accuracy, after assembling the structural column on the ground (hereinafter also referred to as ground assembly), the structural column is assembled. Build underground. However, when the construction target is a narrow site, if the preceding floor is constructed on the first floor and then the structural column is constructed underground, the structural column will be longer than the site and the space for ground assembly will be lost. may not be ensured.

特許文献1に記載された地下構造物の構築方法等の逆打ち工法においては、仮設した開口に搬出土や解体ガラを集積して搬出を行う際に、仮設した開口の下部にこれらを集積しないとならず、重機の移動や操作が困難となる可能性がある。 In the reverse construction method such as the method for constructing an underground structure described in Patent Document 1, when excavated soil and dismantled waste are accumulated in a temporary opening and carried out, they are not accumulated under the temporary opening. Otherwise, it may become difficult to move and operate heavy machinery.

本発明は、狭小地であっても効率的に既存地下構造物を撤去しながら新規の地下構造物を増築可能な構造物の構築方法を提供することを目的とする。 SUMMARY OF THE INVENTION It is an object of the present invention to provide a method of constructing a structure capable of constructing a new underground structure while efficiently removing the existing underground structure even in a narrow space.

本発明の一態様は、既存地下構造物の外周に山留め壁を構築する工程と、既存地下構造物の1階から下方の第1所定階数の既存地下構造物を撤去する工程と、前記地下階を撤去して現れた第1地盤面から前記1階の高さまで前記山留め壁を支持する第1仮設土留め支保工を設置する工程と、前記第1地盤面から下方の第1所定深さまで複数の構真柱を構築する工程と、前記第1地盤面に新規地下床面を構築する工程と、前記新規地下床面から上方に第1所定階数の新規地下構造物を順次構築し新規1階床面まで構築する工程と、前記新規1階床面から上方の新規地上階を順次構築すると共に、前記新規地下床面から下方の地盤を、前記第1所定深さに比して浅い第2所定深さの第2地盤面まで掘削する工程と、前記第2地盤面に基礎を構築する工程と、前記基礎から前記新規地下床面の高さまで前記山留め壁を支持する第2仮設土留め支保工を設置する工程と、前記基礎から上方に第2所定階数分の追加新規地下構造物を順次構築する工程と、を備えることを特徴とする地下構造物の構築方法である。 One aspect of the present invention includes the steps of constructing an earth retaining wall around the perimeter of an existing underground structure, removing a first predetermined number of existing underground structures below the first floor of the existing underground structure, and A step of installing a first temporary earth retaining shoring that supports the earth retaining wall from the first ground surface revealed by removing the above to the height of the first floor; A step of constructing a structural column of, a step of constructing a new underground floor surface on the first ground surface, and sequentially constructing a new underground structure with a first predetermined number of floors upward from the new underground floor surface to create a new first floor A step of constructing up to the floor surface, sequentially constructing a new ground floor above the new first floor floor surface, and lowering the ground below the new underground floor surface to a second depth shallower than the first predetermined depth a step of excavating to a second ground surface of a predetermined depth; a step of constructing a foundation on the second ground surface; and a second temporary earth retaining support that supports the earth retaining wall from the foundation to the height of the new underground floor surface. and sequentially constructing additional new underground structures for a second predetermined number of floors upward from the foundation.

本発明によれば、構真柱を構築する際、構真柱の柱頭を第1地盤面までとすることができるため、構真柱を短くすることができる。構真柱を短くすることにより、施工対象範囲1が狭小地であっても構真柱を地組することができる等の利点がある。本発明によれば、既設地下構造物まで撤去し、第1地盤面に新規地下床面を構築しその上方に新規地下構造物を順打ち工法に基づいて構築するため、新規地下構造物を安定的に構築することができる。 According to the present invention, when constructing a framing pillar, the capital of the framing pillar can be extended to the first ground surface, so that the framing pillar can be shortened. By shortening the framing column, there is an advantage that the framing column can be assembled even if the construction target area 1 is a narrow land. According to the present invention, the existing underground structure is removed, the new underground floor is constructed on the first ground surface, and the new underground structure is constructed above it based on the sequential construction method, so that the new underground structure is stabilized. can be constructed systematically.

また、本発明の前記第1地盤面は、地下水位に比して浅い深さ方向の高さであってもよい。 Further, the first ground surface of the present invention may have a height in the depth direction that is shallower than the groundwater level.

本発明によれば、地下水位に比して浅い位置において新規地下構造物を構築するため、新規地下構造物を安定的に構築することができる。 According to the present invention, since a new underground structure is constructed at a position shallower than the groundwater level, the new underground structure can be constructed stably.

また、本発明は、前記第1所定階数の前記新規地下構造物と前記新規1階床面とを繋ぐ地下スロープを構築する工程を備えていてもよい。 Moreover, the present invention may comprise the step of constructing an underground slope connecting the new underground structure of the first predetermined number of floors and the new first floor floor surface.

本発明によれば、地下スロープを順打ち工法に基づいて安定した品質に基づいて構築することができる。 ADVANTAGE OF THE INVENTION According to this invention, an underground slope can be constructed based on the stable quality based on a sequential construction method.

また、本発明は前記基礎から上方に追加地下スロープを構築する工程を備えていてもよい。 The invention may also comprise the step of constructing additional underground ramps upwardly from said foundation.

本発明によれば、追加地下スロープを順打ち工法に基づいて安定した品質に基づいて構築することができる。 ADVANTAGE OF THE INVENTION According to this invention, an additional underground slope can be constructed on the basis of stable quality based on a sequential construction method.

また、本発明は、前記新規地下構造物の構築及び前記追加新規地下構造物の構築において前記地下スロープ及び前記追加地下スロープを備える場合には、前記地下スロープ及び前記追加地下スロープを用いて撤去物を搬出すると共に、搬入物を搬入する工程を備えていてもよい。 Further, in the present invention, when the underground slope and the additional underground slope are provided in the construction of the new underground structure and the construction of the additional new underground structure, the object to be removed using the underground slope and the additional underground slope It may be provided with a step of carrying out and carrying in a carried-in object.

本発明によれば、地下スロープ及び追加地下スロープを構築することにより、撤去物や搬入物を車両により容易に運搬することができる。 According to the present invention, by constructing an underground slope and an additional underground slope, it is possible to easily transport objects to be removed and items to be brought in by vehicle.

本発明によれば、狭小地であっても効率的に既存地下構造物を撤去しながら新規の地下構造物を増築可能とすることができる。 According to the present invention, it is possible to efficiently remove an existing underground structure and extend a new underground structure even in a narrow space.

本発明の実施形態に係る地下構造物の施工対象範囲を示す平面図である。1 is a plan view showing a construction target range of an underground structure according to an embodiment of the present invention; FIG. 地下構造物の構築方法の地中連続壁を構築する工程を示す図である。It is a figure which shows the process of constructing a diaphragm wall of the constructing method of an underground structure. 地下構造物の構築方法の既存地下構造物の一部を撤去し、構真柱を構築する工程を示す図である。It is a figure which shows the process of removing a part of existing underground structure of the construction method of an underground structure, and constructing a structural column. 地下構造物の構築方法の第1仮設土留め支保工を設置する工程を示す図である。It is a figure which shows the process of installing the 1st temporary earth retaining shoring of the construction method of an underground structure. 地下構造物の構築方法の新規地下構造物を構築する工程を示す図である。It is a figure which shows the process of constructing a new underground structure of the construction method of an underground structure. 地下構造物の構築方法の新規地下構造物構築した後を示す図である。It is a figure which shows after constructing a new underground structure of the constructing method of an underground structure. 地下構造物の構築方法の地下スロープを構築する工程を示す図である。It is a figure which shows the process of constructing|constructing an underground slope of the constructing method of an underground structure. 地下構造物の構築方法の新規地下構造物の下方の地盤を掘削する工程を示す図である。It is a figure which shows the process of excavating the ground under the new underground structure of the construction method of an underground structure. 地下構造物の構築方法の新規地下構造物の下方に追加新規地下構造物構築した後を示す図である。FIG. 10 is a diagram showing a state after construction of an additional new underground structure below the new underground structure in the construction method of the underground structure; 地下構造物の構築方法の追加新規地下スロープを構築する工程を示す図である。FIG. 4 is a diagram showing a step of constructing an additional new underground slope in the method of constructing an underground structure;

以下、図面を参照しつつ、本発明に係る地下構造物の構築方法の実施形態に係る各工程について説明する。 Hereinafter, each process according to an embodiment of the method for constructing an underground structure according to the present invention will be described with reference to the drawings.

図1及び図2に示されるように、新規建物が構築される施工対象範囲1は、例えば、狭小地である。施工対象範囲1は、例えば、近隣に幹線道路、公共交通機関、他の建物等が密集している。施工対象範囲1は、例えば、既設の建物の地上階が撤去され、1階床面から下方に第1所定階数の既設地下構造物2が残置されている。本実施形態においては、第1所定階数は既設地下構造物2の階数であり、例えば、地下2階分である。既設地下構造物2の床面に比して低い位置には、地下水位面Wが存在している。施工対象範囲1には、大深度工事が行われ、既設地下構造物2に比して更に深い地中に新規地下構造物(後述)が増設される。 As shown in FIGS. 1 and 2, a construction target area 1 where a new building is to be constructed is, for example, a narrow lot. In the construction target range 1, for example, a highway, public transportation, other buildings, etc. are densely located nearby. In the construction target range 1, for example, the ground floor of the existing building has been removed, and the existing underground structure 2 of the first predetermined number of floors is left below the floor surface of the first floor. In this embodiment, the first predetermined number of floors is the number of floors of the existing underground structure 2, for example, two underground floors. A groundwater level W exists at a position lower than the floor of the existing underground structure 2 . In the construction target range 1, deep construction is carried out, and a new underground structure (described later) is added in the deeper ground than the existing underground structure 2.

先ず、既設地下構造物2の外周に地山の崩落を防止するための山留め壁3が構築される。山留め壁3は、例えば、地中連続壁工法に基づいて構築される。地中連続壁工法は、例えば、壁状の溝孔を掘削しつつ安定液を溝孔に注入して掘削壁面の崩壊を防ぎながら地下に掘り進め、溝孔にコンクリートを打設し、無筋或いは鉄筋コンクリートなどの連続した地中連続壁(山留め壁3は、)を地中に構築する工法である。地中連続壁はSMW (Soil. Mixing Wall:ソイルセメント工法)に基づいて、構築される。地中連続壁は、溝孔にセメントミルクと土を混合・撹拌して止水壁を形成し、H形鋼を挿入して連続した山留め壁3により形成される。 First, an earth retaining wall 3 is constructed around the outer circumference of the existing underground structure 2 to prevent the ground from collapsing. The retaining wall 3 is constructed based on, for example, a diaphragm wall construction method. In the diaphragm wall construction method, for example, a wall-shaped ditch is excavated and a stabilizing liquid is injected into the ditch to prevent the excavated wall surface from collapsing. Alternatively, it is a method of constructing a continuous underground continuous wall (retaining wall 3) made of reinforced concrete or the like in the ground. The diaphragm wall is constructed based on SMW (Soil. Mixing Wall: soil cement construction method). A diaphragm wall is formed by mixing and agitating cement milk and soil in a groove to form a water stop wall, and inserting H-shaped steel to form a continuous earth retaining wall 3 .

溝孔は、例えば、柱状の掘削孔を連続して形成される。掘削孔には、孔壁崩壊防止と掘り屑であるスライムが沈降することを防止するために安定液が注入され、掘削孔の壁面を保持する。安定液は、例えば、ベントナイト溶液であり、比重、粘性、砂分、pHなどに基づく品質が管理される。山留め壁3は、シートパイルを用いる等他の工法により構築されてもよい。既設地下構造物2は、1階の床面から順次撤去される。このとき既設地下構造物2の内部空間2Sには、埋め戻し土2Bが充填される。埋め戻し土2Bは、例えば、流動化処理土である。埋め戻し土2Bは、地上面から充填される。埋め戻し土2Bは、既設地下構造物2の撤去状態に応じて掘削される。 The slot is formed, for example, by continuously drilling a columnar bore. A stabilizing liquid is injected into the borehole to hold the wall surface of the borehole in order to prevent the borehole wall from collapsing and to prevent the slime, which is excavation debris, from settling down. The stabilizing liquid is, for example, a bentonite solution, and quality is controlled based on specific gravity, viscosity, sand content, pH, and the like. The mountain retaining wall 3 may be constructed by other construction methods such as using sheet piles. The existing underground structure 2 is removed sequentially from the floor surface of the first floor. At this time, the internal space 2S of the existing underground structure 2 is filled with backfill soil 2B. The backfill soil 2B is, for example, fluidized soil. The backfill soil 2B is filled from the ground surface. The backfill soil 2B is excavated according to the state of removal of the existing underground structure 2 .

図3に示されるように、既設地下構造物2の1階床面が撤去された後に現れた開口には、仮設の床面となる構台Fが構築される。構台Fは、1階の全面ではなく一部を覆うように構築される。構台Fは、平面視して矩形に構築される。構台Fの設置に並行して、構台Fの下方には、構台Fを支持するために仮設される複数の構台杭F2が設置される。構台杭F2は、例えば、H鋼により形成される。構台杭F2は、例えば、後述の新規地下構造物8を支持する第2地盤面12(図7参照)に比して下方の位置まで根入れされる。構台杭F2は、H鋼を適宜継ぎ足して構成される。これにより、構台Fから下方の撤去物Tを搬出可能となる。構台Fには、クレーン等の重機や車両が載置される。構台Fから下方において残置された既設地下構造物2を破砕したコンクリート塊や埋め戻し土2Bは、上方から順次撤去される。既設地下構造物2は、上方から順次撤去され、第1地盤面5が露出する。 As shown in FIG. 3, a gantry F that serves as a temporary floor is constructed in the opening that appears after the first floor of the existing underground structure 2 is removed. The gantry F is constructed to cover a portion of the ground floor rather than the entire surface. The gantry F is constructed in a rectangular shape in plan view. In parallel with the installation of the gantry F, a plurality of gantry piles F2 temporarily installed to support the gantry F are installed below the gantry F. The gantry pile F2 is made of H steel, for example. The gantry pile F2 is embedded, for example, to a lower position than the second ground surface 12 (see FIG. 7) that supports the new underground structure 8, which will be described later. The gantry pile F2 is constructed by appropriately adding H steel. As a result, it becomes possible to carry out the object to be removed T below from the gantry F. A heavy machine such as a crane or a vehicle is placed on the gantry F. Concrete blocks and backfill soil 2B left behind by crushing the existing underground structure 2 below the gantry F are sequentially removed from above. The existing underground structure 2 is removed sequentially from above, and the first ground surface 5 is exposed.

第1地盤面5から下方の第1所定深さまで複数の構真柱6を構築する。構真柱6は、逆打ち工法において先に構築される先行床を支持するための支持柱である。構真柱6は、例えば、H鋼等の鋼材の周囲がコンクリートにより覆われて形成される柱体である。構真柱6は、基礎杭6Aと一体に構築され、構造物の一部の部材として用いられる。構真柱6の構築において、例えば、既設地下構造物2或いは、第1地盤面5から下方に杭孔を掘削しながら杭孔に安定液を注入し、杭孔の安定を保持しつつ杭孔を下方に掘り進め縦穴状の空間を掘削する。縦穴状の空間は、例えば、下部がテーパ形状に拡径された拡径空間が形成される。拡径空間は、例えば、拡径装置(不図示)等を用いて形成される。 A plurality of structural columns 6 are constructed from the first ground surface 5 to a first predetermined depth below. The structure column 6 is a support column for supporting the preceding floor that is constructed first in the reverse construction method. The structural column 6 is a column body formed by covering a steel material such as H-steel with concrete, for example. The structure column 6 is constructed integrally with the foundation pile 6A and used as a part of the structure. In the construction of the structural column 6, for example, while excavating a pile hole downward from the existing underground structure 2 or the first ground surface 5, a stabilizing liquid is injected into the pile hole, and the pile hole is opened while maintaining the stability of the pile hole. is dug downward to excavate a vertical hole-like space. The vertical hole-shaped space is formed, for example, as a diameter-expanded space with a tapered lower portion. The diameter expansion space is formed using, for example, a diameter expansion device (not shown) or the like.

拡径空間には、鉄筋により形成された鉄筋籠(不図示)が建て込まれる。縦穴には、コンクリートが打設される基礎杭6Aが形成される。コンクリートの硬化前に基礎杭の上方には、構真柱6が位置決めされ、建て込まれる。縦穴状の空間には、H鋼により地組された構真柱6が挿入され、コンクリート内に構真柱6が埋め込まれ、コンクリートの硬化後に構真柱6と基礎杭とが一体に形成される。 A reinforcing bar cage (not shown) formed of reinforcing bars is erected in the expanding space. A foundation pile 6A into which concrete is placed is formed in the vertical hole. A structural column 6 is positioned and erected above the foundation pile before the concrete hardens. Into the vertical hole-shaped space, a structural column 6 assembled with H steel is inserted, the structural column 6 is embedded in the concrete, and after the concrete hardens, the structural column 6 and the foundation pile are integrally formed. be.

上記工程によれば、第1地盤面5から構真柱6を構築することにより、構真柱6は、1階床面を先行床として構築する逆打ち工法の場合に比して短く構築することができる。第1地盤面5から構真柱6を構築することにより、構真柱6の地組を可能にできる。 According to the above process, by constructing the structure column 6 from the first ground surface 5, the structure column 6 is constructed shorter than in the case of the reverse construction method in which the floor surface of the first floor is used as the preceding floor. be able to. By constructing the framing column 6 from the first ground surface 5, ground framing of the framing column 6 can be made possible.

拡径空間にコンクリートが充填され構真柱6が構築されると、構真柱6は、地上構造物の荷重を支持すると共に、地上構造物に加わるモーメントに基づく上方への引っ張り力に対抗可能な基礎杭となる。構真柱6の縦穴状の空間には、例えば、柱状に組まれた鉄筋が挿入される。その後、構真柱6の縦穴状の空間にコンクリートが打設され、構真柱6が構築される。 When the expanded space is filled with concrete and the structure column 6 is constructed, the structure column 6 can support the load of the aboveground structure and resist the upward pulling force based on the moment applied to the aboveground structure. foundation piles. For example, a column-shaped reinforcing bar is inserted into the vertical hole-shaped space of the structural column 6 . After that, concrete is placed in the vertical hole-shaped space of the structural column 6, and the structural column 6 is constructed.

図4に示されるように、対向する山留め壁3の間には、第1仮設土留め支保工4が設置される。第1仮設土留め支保工4は、例えば、H鋼等の部材を組み合わせた枠体に構築される。第1仮設土留め支保工4の端部と山留め壁3との間には、山留め壁3の表面の水平方向に沿ってH鋼が配置される。第1仮設土留め支保工4は、例えば、対向する山留め壁3を軸力方向に支持し、山留め壁3が土圧を受けて内側に膨出することを防止する。第1仮設土留め支保工4の間を用いて、地上面からクレーン装置K等を用いて既設地下構造物2を解体したガラや搬出土等の撤去物Tが搬出される。第1地盤面5は、例えば、地下水位に比して浅い深さ方向の高さである。 As shown in FIG. 4 , a first temporary earth retaining shoring 4 is installed between the opposing earth retaining walls 3 . The first temporary earth retaining shoring 4 is constructed, for example, in a frame that combines members such as H steel. Between the end portion of the first temporary earth retaining shoring 4 and the earth retaining wall 3 , an H-beam is arranged along the horizontal direction of the surface of the earth retaining wall 3 . The first temporary earth retaining shoring 4 supports, for example, the facing earth retaining wall 3 in the axial direction, and prevents the earth retaining wall 3 from bulging inward due to earth pressure. Using the space between the first temporary earth retaining shorings 4, removed objects T such as scraps and unloaded soil obtained by demolishing the existing underground structure 2 are carried out from the ground surface using a crane device K or the like. The first ground surface 5 has, for example, a height in the depth direction that is shallower than the groundwater level.

図5に示されるように、次に、第1地盤面5から上方には、新規地下床面7が構築される。新規地下床面7は、例えば、第1地盤面5上であり且つ構真柱6の上部に支持されるように構築される。新規地下床面7は、例えば、鉄筋コンクリート造にて構築され、第1地盤面5の下方に後述の追加新規地下構造物15を構築するための逆打ち工法における先行床として利用することができる。新規地下床面7の構築の際に、第1地盤面5から上方の構台杭F3が撤去される。撤去された構台杭F3は、後述の第2仮設土留め支保工13として利用することができる。新規地下床面7から上方には、第1所定階数の新規地下構造物8が順打ち工法に基づいて順次構築される。新規地下構造物8は、新規1階床面9まで構築される。このとき、順次、第1仮設土留め支保工4が撤去される。撤去された第1仮設土留め支保工4は、後述の第2仮設土留め支保工13として利用することができる。 As shown in FIG. 5, a new subsurface 7 is then constructed above the first subsurface 5 . A new subsurface 7 is constructed, for example, on the first subsurface 5 and supported on top of the framing columns 6 . The new underground floor surface 7 is constructed of, for example, reinforced concrete, and can be used as a preceding floor in a reverse construction method for constructing an additional new underground structure 15 below the first ground surface 5 . During the construction of the new subterranean floor 7, the gantry pile F3 above from the first subsurface 5 is removed. The removed gantry pile F3 can be used as a second temporary earth retaining shoring 13, which will be described later. Above the new underground floor surface 7, a new underground structure 8 having a first predetermined number of floors is sequentially constructed based on the sequential construction method. A new underground structure 8 is constructed up to a new first floor floor 9 . At this time, the first temporary earth retaining shoring 4 is removed sequentially. The removed first temporary earth retaining shoring 4 can be used as a second temporary earth retaining shoring 13 which will be described later.

新規地下構造物8は、例えば、コンクリートの圧入工法を用いて形成され、上下方向に貫通する複数の仮設開口Hが適宜設けられる。仮設開口Hは、例えば、クレーン装置等を用いて撤去物を搬出し、或いは新規地下床面7の下方の後述の追加新規地下構造物15を構築するための資材を搬入し、コンクリートを打設するためのホースを出し入れするために用いられる。新規1階床面9は、例えば、鉄筋コンクリート造に基づいて構築される。新規1階床面9には、上下方向に貫通する複数の仮設開口Hが適宜設けられる。仮設開口Hは、例えば、新規地下床面に設けられた仮設開口Hの上下方向に沿った位置に設けられる。 The new underground structure 8 is formed using, for example, a concrete press-in method, and is appropriately provided with a plurality of temporary openings H penetrating vertically. For the temporary opening H, for example, a crane device is used to carry out the removed objects, or carry in materials for constructing an additional new underground structure 15 below the new underground floor surface 7, and pour concrete. Used to insert and remove hoses for The new first floor floor 9 is constructed based on, for example, reinforced concrete construction. A plurality of temporary openings H penetrating vertically are appropriately provided on the new first floor floor 9 . The temporary opening H is provided, for example, at a position along the vertical direction of the temporary opening H provided in the new underground floor surface.

仮設開口Hは、例えば、クレーン装置K等を用いて既存地下階を解体したガラや搬出土、構台杭の一部等の撤去物を搬出し、或いは新規地下構造物8を構築するための資材を搬入し、コンクリートを打設するためのホースを出し入れするために用いられる。 For example, the temporary opening H is used to carry out scraps from the dismantling of the existing underground floor using a crane device K or the like, unloaded soil, removed items such as part of the gantry pile, or materials for constructing a new underground structure 8. It is used for loading and unloading hoses for placing concrete.

本実施形態においては、新規地下構造物8は、例えば、地下2階分である。新規地下構造物8は、上述したように地下水位に比して上方において施工されるため、地下水が出ない状態において品質を確保した躯体を構築できる。また、地下水が出ない状態とすることで、地中連続壁を構築するSMWが建物内側方向に受ける荷重の増加を防ぎ、SMWの安定を計ることが出来る。 In this embodiment, the new underground structure 8 is, for example, two floors underground. Since the new underground structure 8 is constructed above the groundwater level, as described above, it is possible to construct a framework that ensures quality in a state where groundwater does not flow. In addition, by preventing groundwater from flowing out, it is possible to prevent an increase in the load received by the SMW constructing the diaphragm wall in the direction of the inside of the building, thereby stabilizing the SMW.

図6Aに示されるように、次に、新規地下構造物8が構築される。新規地下構造物8は、順打ち工法にて構築されるため、コンクリートの品質を安定的に確保することができる。仮設開口Hは、必要に応じて閉塞してもよい。 A new underground structure 8 is then constructed, as shown in FIG. 6A. Since the new underground structure 8 is constructed by the forward casting method, it is possible to stably ensure the quality of the concrete. Temporary opening H may be closed if necessary.

図6Bに示されるように、新規地下構造物8の一部には、新規地下床面7と新規1階床面9とを繋ぐ地下スロープ10を設けてもよい。地下スロープ10は、例えば、鉄筋コンクリート造にて、順打ち工法にて構築されるが、後に撤去される仮設構造部であってもよく、H鋼等を用いて解体可能に組み立てられてもよい。 As shown in FIG. 6B, part of the new underground structure 8 may be provided with an underground slope 10 that connects the new underground floor surface 7 and the new first floor floor surface 9 . The underground slope 10 is, for example, made of reinforced concrete and constructed by the forward casting method, but it may be a temporary structure that is removed later, or it may be assembled so as to be dismantled using H steel or the like.

地下スロープ10は、例えば、新規地下構造物8の各階毎に構築されてもよいし、新規地下床面7と新規1階床面9とを繋ぐように構築されてもよい。地下スロープ10は、既存地下階を解体したガラや搬出土等の撤去物を搬出したり、新規地下構造物8を構築するための資材を搬入したりする車両用通路として利用することができる。 For example, the underground slope 10 may be constructed for each floor of the new underground structure 8 or may be constructed so as to connect the new underground floor surface 7 and the new first floor floor surface 9 . The underground slope 10 can be used as a passageway for vehicles to carry out removed objects such as scraps and excavated earth from the dismantled existing underground floor, and to carry in materials for constructing a new underground structure 8. - 特許庁

図7に示されるように、新規1階床面9の構築後、新規1階床面9から上方では、新規地上階11が順次構築される。新規地上階11の構築と同時進行して、新規地下床面7から下方の地盤が掘削される。このとき、地盤は、構真柱6の下端が設けられた第1所定深さに比して浅い第2所定深さの第2地盤面12まで掘削される。新規地下床面7と第2地盤面12との間には、地下空間が形成され、新規地下床面7は、露出した複数の構真柱6に支持される。 As shown in FIG. 7 , after the construction of the new first floor floor 9 , new ground floors 11 are sequentially constructed above the new first floor floor 9 . Simultaneously with construction of the new ground floor 11, the ground below the new underground floor surface 7 is excavated. At this time, the ground is excavated to a second ground surface 12 of a second predetermined depth shallower than the first predetermined depth at which the lower ends of the structural columns 6 are provided. An underground space is formed between the new underground floor surface 7 and the second ground surface 12 , and the new underground floor surface 7 is supported by a plurality of exposed structural columns 6 .

このとき、仮設開口Hは、例えば、クレーン装置等を用いて、地盤を掘削して生じた掘削土等を搬出し、新規地下構造物8を構築するための資材を搬入し、構台杭F2として利用していた部材の一部を第2仮設土留め支保工13の部材として供するために搬入し、コンクリートを打設するためのホースを出し入れするために用いられる。また、地盤の掘削深さに応じて構台杭F2が順次撤去される。 At this time, the temporary opening H is used, for example, by using a crane device or the like to carry out the excavated soil or the like generated by excavating the ground, and the materials for constructing the new underground structure 8 are carried in and used as the gantry pile F2. Some of the members that have been used are brought in to serve as members of the second temporary earth retaining shoring 13, and are used to take in and out hoses for placing concrete. Moreover, the gantry pile F2 is removed one by one according to the excavation depth of the ground.

対向する山留め壁3の間には、第2仮設土留め支保工13が設置される。第2仮設土留め支保工13は、例えば、第1仮設土留め支保工4や、構台杭F2の部材を利用した枠体に構築される。第2仮設土留め支保工13の端部と山留め壁3との間には、山留め壁3の表面の水平方向に沿ってH鋼が配置される。第2仮設土留め支保工13は、第1仮設土留め支保工4と同様に、対向する山留め壁3を軸力方向に支持し、山留め壁3が土圧を受けて内側に膨出することを防止する。 A second temporary earth retaining shoring 13 is installed between the opposing earth retaining walls 3 . The second temporary earth retaining shoring 13 is constructed in a frame using the members of the first temporary earth retaining shoring 4 and the gantry pile F2, for example. Between the end portion of the second temporary earth retaining shoring 13 and the earth retaining wall 3 , an H-beam is arranged along the horizontal direction of the surface of the earth retaining wall 3 . Like the first temporary earth retaining shoring 4, the second temporary earth retaining shoring 13 supports the opposing earth retaining wall 3 in the axial direction, and the earth retaining wall 3 bulges inward under the earth pressure. to prevent

地下スロープ10を設ける場合は、地盤を掘削して生じた掘削土等を、仮設開口Hを通じて新規地下構造物8まで搬出された後に、地下スロープ10を用いて車両や重機により搬出してもよい。 When the underground slope 10 is provided, excavated soil or the like generated by excavating the ground may be carried out by a vehicle or heavy machinery using the underground slope 10 after being carried out to the new underground structure 8 through the temporary opening H. .

図8に示されるように、第2地盤面12は、基礎杭6Aの上端と略同一の高さに掘削される。第2地盤面12の上部には、新規追加地下床面14が構築される。新規追加地下床面14から上方には、第2所定階数分の追加新規地下構造物15が順打ち工法に基づいて順次構築される。本実施形態においては、第2所定階数は、2階分である。即ち、本実施形態においては、追加新規地下構造物15は、地下3階及び地下4階である。追加新規地下構造物15は、例えば、コンクリートの圧入工法などの方法で鉄筋コンクリート造にて構築される。構真柱6は、追加新規地下構造物15の一部の構造体となり一体化される。基礎杭6Aは、追加新規地下構造物15及び新規地下構造物8を支持する。 As shown in FIG. 8, the second ground surface 12 is excavated to substantially the same height as the upper ends of the foundation piles 6A. A newly added underground floor 14 is constructed on top of the second ground surface 12 . Above the newly added underground floor surface 14, additional new underground structures 15 for the second predetermined number of floors are successively constructed based on the sequential construction method. In this embodiment, the second predetermined number of floors is two floors. That is, in this embodiment, the additional new underground structure 15 is the 3rd basement floor and the 4th basement floor. The additional new underground structure 15 is constructed of reinforced concrete by a method such as a concrete press-in method. The structure pillar 6 becomes a part of structure of the additional new underground structure 15 and is integrated. The foundation piles 6A support the additional new underground structure 15 and the new underground structure 8.

また、図9に示されるように、追加新規地下構造物15の一部に追加地下スロープ16が構築されてもよい。追加地下スロープ16は、例えば、追加新規地下構造物15毎に構築されてもよく、新規追加地下床面14から新規地下床面7まで構築されてもよい。追加地下スロープ16は、例えば、鉄筋コンクリート造にて構築されるが、後に撤去される仮設構造部であってもよく、H鋼等を用いて解体可能に組み立てられてもよい。 Also, as shown in FIG. 9, an additional underground slope 16 may be constructed on a portion of the additional new underground structure 15 . The additional underground slope 16 may be constructed, for example, for each additional new underground structure 15 , or may be constructed from the newly added underground floor surface 14 to the new underground floor surface 7 . The additional underground slope 16 is constructed of reinforced concrete, for example, but it may be a temporary structure that will be removed later, or it may be assembled using H-steel or the like so that it can be dismantled.

追加地下スロープ16からは、ガラ等の搬出物が搬出されると共に、資材等の搬入物が搬入される。上記工程に基づいて、新規追加地下床面14と新規地下床面7との間に追加新規地下構造物15が構築される。クレーン装置等を用いて搬出物が搬出された後、各仮設開口Hが閉塞される。各仮設開口Hは、閉塞が必要でない場合は、残置され追加新規地下構造物15の一部として利用される。 Through the additional underground slope 16, items to be carried out, such as waste, are carried out, and items to be carried in, such as materials, are carried in. Based on the above steps, the additional new underground structure 15 is constructed between the newly added underground floor surface 14 and the new underground floor surface 7 . Each temporary opening H is closed after the load is carried out using a crane device or the like. Each temporary opening H is left in place and utilized as part of the additional new underground structure 15 when closure is not required.

上述した地下構造物の構築方法によれば、逆打ち工法において構真柱6を構築する際、構真柱6の柱頭を第1地盤面5までとすることができるため、構真柱6の長さを短くすることができる。構真柱を短くすることにより、施工対象範囲1が狭小地であっても構真柱を地組することができる等の利点がある。 According to the construction method of the underground structure described above, when constructing the structural column 6 by the reverse construction method, the capital of the structural column 6 can be set up to the first ground surface 5. length can be shortened. By shortening the framing column, there is an advantage that the framing column can be assembled even if the construction target area 1 is a narrow land.

上述した地下構造物の構築方法によれば、地下水位に比して上方の第1地盤面5から新規地下構造物を順打ち工法に基づいて構築するため、新規地下構造物の構築を安定的に行うことができる。また、新規1階床面、追加新規地下構造物に仮設開口Hを設けることにより、搬出物及び搬入物を重機により容易に運搬することができる。また、新規地下構造物の一部や、追加新規地下階の一部に追加地下スロープを構築する場合には、搬出物及び搬入物を車両や重機を用いて容易に運搬することができる。 According to the underground structure construction method described above, since the new underground structure is constructed based on the sequential construction method from the first ground surface 5 above the groundwater level, the new underground structure can be constructed stably. can be done. In addition, by providing a temporary opening H in the new first floor floor and additional new underground structure, it is possible to easily transport carry-out and carry-in items by heavy machinery. In addition, when constructing an additional underground slope in a part of a new underground structure or in a part of an additional new underground floor, it is possible to easily transport items to be carried out and items to be brought in using vehicles and heavy machinery.

以上、本発明の一実施形態について説明したが、本発明は上記の一実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。例えば、地下スロープ10及び追加地下スロープ16は、例えば、設計上の構造物であってもよいし、後に撤去される仮設構造部であってもよい。 An embodiment of the present invention has been described above, but the present invention is not limited to the above-described embodiment, and can be modified as appropriate without departing from the scope of the invention. For example, underground ramp 10 and additional underground ramp 16 may be, for example, designed structures or temporary structures that are later removed.

1 施工対象範囲
2 既設地下構造物
3 山留め壁
4 第1仮設土留め支保工
5 第1地盤面
6 構真柱
7 新規地下床面
8 新規地下構造物
9 新規1階床面
10 地下スロープ
11 新規地上階
12 第2地盤面
13 第2仮設土留め支保工
14 新規追加地下床面
15 追加新規地下構造物
16 追加地下スロープ
F 構台
1 Construction target area 2 Existing underground structure 3 Earth retaining wall 4 First temporary earth retaining shoring 5 First ground surface 6 Structural column 7 New underground floor surface 8 New underground structure 9 New 1st floor floor surface 10 Underground slope 11 New Ground floor 12 Second ground surface 13 Second temporary earth retaining shoring 14 Newly added underground floor surface 15 Additional new underground structure 16 Additional underground slope F Gantry

Claims (5)

既存地下構造物の外周に山留め壁を構築する工程と、
既存地下構造物の1階から下方の第1所定階数の既存地下階を撤去する工程と、
前記既存地下階を撤去して現れた第1地盤面から前記1階の高さまで前記山留め壁を支持する第1仮設土留め支保工を設置する工程と、
前記第1地盤面から下方の第1所定深さまで複数の構真柱を構築する工程と、
前記第1地盤面に新規地下床面を構築する工程と、
前記新規地下床面から上方に第1所定階数の新規地下構造物を順次構築し新規1階床面まで構築する工程と、
前記新規1階床面から上方の新規地上構造物を順次構築すると共に、前記新規地下床面から下方の地盤を、前記第1所定深さに比して浅い第2所定深さの第2地盤面まで掘削する工程と、
前記第2地盤面に基礎を構築する工程と、
前記基礎から前記新規地下床面の高さまで前記山留め壁を支持する第2仮設土留め支保工を設置する工程と、
前記基礎から上方に第2所定階数分の追加新規地下構造物を順次構築する工程と、
を備えることを特徴とする、地下構造物の構築方法。
A process of constructing a retaining wall around the perimeter of the existing underground structure;
removing a first predetermined number of existing underground floors below the first floor of the existing underground structure;
A step of installing a first temporary earth retaining shoring for supporting the earth retaining wall from the first ground level revealed by removing the existing basement floor to the height of the first floor;
constructing a plurality of structural columns to a first predetermined depth below the first ground surface;
constructing a new subsurface on said first toposurface;
a step of sequentially constructing a new underground structure having a first predetermined number of floors upward from the new underground floor surface to a new first floor floor surface;
While sequentially constructing a new above-ground structure above the new first floor floor, the ground below the new underground floor is a second ground having a second predetermined depth shallower than the first predetermined depth. a step of drilling to the surface;
building a foundation on the second toposurface;
installing a second temporary earth retaining shoring that supports the earth retaining wall from the foundation to the height of the new underground floor;
a step of sequentially constructing an additional new underground structure for a second predetermined number of floors above the foundation;
A method for constructing an underground structure, comprising:
前記第1地盤面は、地下水位に比して浅い深さ方向の高さである、
請求項1に記載の地下構造物の構築方法。
The first ground surface has a height in the depth direction that is shallower than the groundwater level,
The method for constructing an underground structure according to claim 1.
前記第1所定階数の前記新規地下構造物と前記新規1階床面とを繋ぐ地下スロープを構築する工程を備える、
請求項1または2に記載の地下構造物の構築方法。
A step of constructing an underground slope that connects the new underground structure of the first predetermined floor and the new first floor floor surface,
The method for constructing an underground structure according to claim 1 or 2.
前記基礎から上方に追加地下スロープを構築する工程を備える、
請求項3に記載の地下構造物の構築方法。
constructing an additional underground slope upwards from the foundation;
A method for constructing an underground structure according to claim 3.
前記新規地下構造物の構築及び前記追加新規地下構造物の構築において前記地下スロープ及び前記追加地下スロープを備える場合には、前記地下スロープ及び前記追加地下スロープを用いて撤去物を搬出すると共に、搬入物を搬入する工程を備える、
請求項4に記載の地下構造物の構築方法。
When the underground slope and the additional underground slope are provided in the construction of the new underground structure and the construction of the additional new underground structure, the underground slope and the additional underground slope are used to carry out and carry in the objects to be removed. Equipped with a process of importing things,
The method for constructing an underground structure according to claim 4.
JP2021191301A 2021-11-25 2021-11-25 Construction method of underground structure Pending JP2023077832A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021191301A JP2023077832A (en) 2021-11-25 2021-11-25 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021191301A JP2023077832A (en) 2021-11-25 2021-11-25 Construction method of underground structure

Publications (1)

Publication Number Publication Date
JP2023077832A true JP2023077832A (en) 2023-06-06

Family

ID=86622359

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021191301A Pending JP2023077832A (en) 2021-11-25 2021-11-25 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JP2023077832A (en)

Similar Documents

Publication Publication Date Title
US7500807B2 (en) Method of construction using sheet piling sections
US20220098817A1 (en) Method for constructing structure
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
KR20140055639A (en) A execution method of architecture beam
US6616380B1 (en) Subterranean structures and methods for constructing subterranean structures
JP2012112121A (en) Excavation method of ground under spread foundation and base-isolating method of existing building
JP2000352296A (en) Method o constructing passage just under underground structure
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR100625115B1 (en) downward reinforced-concrete underground structure using temporary assistant columns
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
JP2023077832A (en) Construction method of underground structure
EP1348812A1 (en) Building methods and apparatus
JPH0559728A (en) Sheathing work above underground structure
JP7193994B2 (en) Strut construction method
KR102579002B1 (en) Method of demolition of underground exterior walls
KR100515971B1 (en) Soil retaining method using H-pile having large section
JP4146250B2 (en) Open caisson bottom plate construction method
KR101128955B1 (en) The Construction Method of Pressing Underground Structure
KR102601694B1 (en) Method for demolishing underground building
KR101079188B1 (en) The Method for Construction Walls of Underground Structure
KR102118636B1 (en) Method for construction for underground tunnel
JP6851180B2 (en) How to rebuild the building
JP6920039B2 (en) How to dismantle the existing underground skeleton
KR19990007580A (en) Underground retaining wall construction method using temporary retaining wall as a permanent structure