KR19990007580A - Underground retaining wall construction method using temporary retaining wall as a permanent structure - Google Patents

Underground retaining wall construction method using temporary retaining wall as a permanent structure Download PDF

Info

Publication number
KR19990007580A
KR19990007580A KR1019980042252A KR19980042252A KR19990007580A KR 19990007580 A KR19990007580 A KR 19990007580A KR 1019980042252 A KR1019980042252 A KR 1019980042252A KR 19980042252 A KR19980042252 A KR 19980042252A KR 19990007580 A KR19990007580 A KR 19990007580A
Authority
KR
South Korea
Prior art keywords
wall
retaining wall
temporary
underground
building
Prior art date
Application number
KR1019980042252A
Other languages
Korean (ko)
Other versions
KR100327547B1 (en
Inventor
홍원기
Original Assignee
홍원기
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 홍원기 filed Critical 홍원기
Priority to KR1019980042252A priority Critical patent/KR100327547B1/en
Publication of KR19990007580A publication Critical patent/KR19990007580A/en
Application granted granted Critical
Publication of KR100327547B1 publication Critical patent/KR100327547B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 건축물의 지하 구조물을 설치하기 위한 지하 터파기 공사 때 임시 시설물로써 설치한 흙막이 벽을 건축 지하 옹벽 영구구조 부재의 일부로 활용하여 경제적으로 건축물 지하 부분의 옹벽을 구축하는 방법에 관한 것이다.The present invention relates to a method for economically constructing a retaining wall of an underground part of a building by utilizing the retaining wall installed as a temporary facility during the construction of an underground trench for installing an underground structure of a building as a part of a building underground retaining wall permanent structural member.

본 발명은 건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정한 후 오거 드릴 등 토공장비로 구멍을 뚫어 H형재를 박고 토류판을 설치하여 가설 흙막이 벽을 설치하여 터파기하고, 터파기가 완료되면 H형재에 정착전단연결수단을 설치하고, 지하 옹벽 부분에는 보강 철근을 배치하고, 지하 옹벽의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생하여 완성하는 단계로 공사한다. 상기 가설 흙막이 벽은 현장 상황에 따라 현장타설 콘크리트 말뚝, 소일 시멘트 월, 강재 시트 파일 등 다양하게 채택될 수 있으며 이런 다양한 종류의 가설 흙막이 벽에 본 방법이 적용된다.The present invention is determined in consideration of the outline of the building to install the temporary mud wall, and then drilled a hole with earthwork equipment, such as auger drill H-shaped material and install the earth plate to install the temporary mud wall, when the trench is completed, H Settlement shear connection means are installed in the section, reinforcing bars are placed in the base retaining wall, the mold is installed in the inner side of the base retaining wall, and concrete is cured and completed. The temporary wall can be adopted in various ways, such as cast concrete piles, soil cement wall, steel sheet pile according to the site situation, the method is applied to this various types of temporary wall walls.

본 발명으로 건축물의 지하 구조물용 터파기를 위하여 임시로 설치하는 가설 흙막이 벽체를 영구 시설물의 일부로 활용하는 방법을 제공하여 한번 사용하고 철거하거나 매립하여야 가설 흙막이 벽을 영구 구조물의 일부로 활용함으로서 한정된 자원을 효율적으로 사용하고 공사비를 절감할 수 있게 되었다.The present invention provides a method of utilizing temporary temporary wall for temporarily discharging the underground structure of a building as part of a permanent facility, and once used and dismantled or buried, the temporary limited wall is used as part of the permanent structure to efficiently utilize limited resources. It can be used to reduce construction costs.

Description

가설 흙막이 벽을 영구 구조물로 활용하는 지하옹벽 구축방법(Composite Retaining Wall Construction Method)Composite Retaining Wall Construction Method Using Temporary Walls As Permanent Structures

본 발명은 건축물의 지하옹벽 구축방법에 관한 것이다. 더욱 구체적으로 임시 시설물로서 설치한 흙막이 벽을 건축물 영구구조 부재의 일부로 활용하여 경제적으로 건축물 지하 부분의 옹벽을 구축하는 방법에 관한 것이다.The present invention relates to a method for constructing an underground retaining wall of a building. More specifically, the present invention relates to a method of economically constructing a retaining wall in an underground part of a building by using a retaining wall installed as a temporary facility as part of a permanent structural member.

도심지에서는 한정된 토지를 효율적으로 활용하기 위하여 지하 굴착 심도가 깊어지고 있다. 지하 굴착할 때 인접 건물, 도로 등 기존 시설물을 파손하지 않기 위하여 흙막이 벽의 설치가 요구된1다. 흙막이 벽을 설치하기 위하여 많은 공사비가 소요되지만 흙막이 벽체는 단지 가설용 시설로 인식하고 설계, 시공되고 있다. 흙막이 벽체는 토압, 수압, 상재 하중 등을 단지 건물 구조체가 완성될 때까지만 견딜 수 있으면 되고, 건물 구조체가 완성되면 그대로 사장하거나 극히 일부 공사현장의 경우 해체, 철거하여 건물 지하 옹벽 구조체와는 전혀 별개의 구조체로 취급되고 있는 실정이다. 그렇게 사용하기 때문에 건물 구조체의 지하 옹벽도 같은 기능을 할 수 있는 데도 가설 흙막이와 건물 지하 옹벽을 따로 따로 설계, 시공함으로 낭비 요소를 안고 있다. 그리고 가설 흙막이의 설계 및 시공과정에서도 가장 경제적으로 설계해야 할 강박감을 갖게 되어 상대적으로 안전율이 부족할 우려가 많아 예기치 못한 하중에 대하여 붕괴 등 안전사고가 발생할 가능성도 높았다.In urban areas, the depth of underground excavation is deepening in order to utilize limited land efficiently. When excavating underground, it is required to install a wall of mud to prevent damage to existing facilities such as adjacent buildings and roads. Although a lot of construction costs are required for installing the wall, the wall is only recognized as a temporary installation and is designed and constructed. The wall must be able to withstand earth pressure, water pressure, and floor load only until the building structure is completed.If the building structure is completed, it is left as it is, or in some construction sites, it is dismantled and dismantled. It is treated as a structure of. Because of this use, even though the base retaining wall of the building structure can perform the same function, the temporary retaining wall and the retaining wall of the building are separately designed and constructed, which causes waste. In addition, the design and construction of temporary earthquakes have a compulsion to be most economically designed, so there is a concern that the safety factor may be insufficient. Therefore, there is a high possibility of a safety accident such as collapse for an unexpected load.

지하에 구조물을 설치할 터파기를 하기 위하여 사용하는 가설 흙막이 벽은 여러 종류가 있다. 지하 터파기 심도가 깊을 경우 통상 채택하는 흙막이 벽은 H 형재 말뚝을 박고 H 형재 말뚝 사이에 토류판을 끼우는 방법, 소일 시멘트 월(Soil Cement Wall, SCW)공법, 현장타설 콘크리트 말뚝(Cast-in-place concrete pile, CIP)공법 등이 있다. 이들 공법은 토압, 수압 등 외력을 견딜 수 있도록 지중에 벽체를 형성한 후 내부에서 버팀대(strut)로 지지하거나 어스앵커(earth anchor)로서 당긴다. 버팀대나 어스앵커의 축력은 시간이 지날수록 재료의 피로현상이 발생하여 구조적 결함이 발생할 수 있기 때문에 가시설로 분류한다. 그러나 땅속에 박혀있는 H형재, SCW, CIP 등은 건축물의 외부 옹벽과 결합하여 영구 구조물의 일부로 재활용할 수 있는데도 매립, 사장해 버리는 실정이었다.There are several types of temporary wall walls used for trenches to install structures underground. In case of deep underground excavation depth, the commonly used retaining wall is to insert H-shape piles and insert earth plate between H-shape piles, Soil Cement Wall (SCW) method, and cast-in-place concrete piles. concrete pile (CIP) method. These methods form walls in the ground to withstand external forces such as earth pressure and water pressure, and then support them with struts or pull them as earth anchors. The axial force of braces or earth anchors is classified as temporary because over time the fatigue phenomenon of the material may cause structural defects. However, H-shaped members, SCW, CIP, etc. embedded in the ground were buried and died even though they could be recycled as part of the permanent structure in combination with the external retaining wall of the building.

가시설로서 흙막이 벽을 설치할 때는 지하 옹벽을 구축하기 위한 작업공간이 필요하므로 흙막이 벽 선이 작업공간을 확보할 만큼 외곽 쪽으로 후퇴해야 하고 후퇴한 선 만큼 터파기 량이 많아지고 되메우기 량 역시 많아지는 낭비요소도 있었다.When installing the retaining wall as a temporary facility, a work space for constructing the base retaining wall is required. Therefore, the retaining wall line must be retracted to the outside enough to secure the working space, and the waste factor that increases the amount of trenching and refilling is also increased. there was.

종래의 가설 흙막이 공법에서 안고 있는 문제점을 해결하기 위하여 발명자는 임시로 설치하여 일정 기간이 지난 뒤 해체하거나 매립해 버리는 가설 흙막이 벽체를 지하 구조물 옹벽의 일부로서 영구히 활용할 수 있는 지하옹벽 구축 방법을 개발하게 되었다.In order to solve the problems in the conventional temporary block construction method, the inventors have developed a method for constructing a basement retaining wall that can permanently utilize the temporary block walls that are temporarily installed and then dismantled or buried as part of the underground structure retaining wall. It became.

본 발명의 목적은 건축물의 지하 구조물용 터파기를 위하여 임시로 설치하는 가설 흙막이 벽체를 영구 시설물의 일부로 활용하는 방법을 제공하기 위한 것이다.It is an object of the present invention to provide a method of utilizing temporary temporary walls installed as temporary parts for excavation of underground structures of buildings as part of permanent facilities.

본 발명의 다른 목적은 한번 사용하고 매립, 사장하여야 가설 흙막이 벽을 영구 구조물의 일부로 활용함으로서 한정된 자원을 효율적으로 사용하고 공사비를 절감하는 방법을 제공하기 위한 것이다.Another object of the present invention is to provide a method of efficiently using limited resources and reducing construction costs by using a temporary barrier wall as part of a permanent structure.

본 발명의 또 다른 목적은 건축물의 지하 부분을 설치하기 위한 터파기 량과 되메우기 량을 줄일 수 있는 방법을 제공하기 위한 것이다.Still another object of the present invention is to provide a method for reducing the amount of burrow and backfill for installing an underground part of a building.

제1도는 종래 지하옹벽을 구축하는 방법을 보인 평단면도와 입면도이다.1 is a plan sectional view and elevation view showing a conventional method for constructing an underground retaining wall.

제2도는 본 발명의 지하옹벽 구축방법의 개념을 보인 평면도와 그 단면도이다.2 is a plan view and a cross-sectional view showing the concept of the underground retaining wall construction method of the present invention.

제3도는 가설 흙막이 벽과 지하옹벽을 일체화시키기 위하여 사용하는 전달연결수단으로서 전단연결재의 예이다.3 is an example of a shear connector as a transmission connecting means used to integrate the temporary retaining wall and the underground retaining wall.

제4도는 H형재를 엄지말뚝으로 사용하고 토류판을 끼운 가설 흙막이 시설을 영구시설로 활용한 구체예이다.FIG. 4 is a specific example of using the H-shape as the thumb pile and using the temporary earthquake facility with the earth plate as a permanent facility.

제5도는 본 발명의 철근 배근 개념도이다.5 is a conceptual diagram of the reinforcement of the present invention.

제6도는 제5도에서 유효 폭 구간의 철근 배근 개념도이다.FIG. 6 is a conceptual view of reinforcing bar in the effective width section in FIG. 5.

제7도는 소일 시멘트 월(SCW)을 가설 흙막이로 설치하는 경우 이를 영구 구조물로 활용하는 구체예이다.FIG. 7 is a specific example of using a cement cement wall (SCW) as a temporary structure.

제8도는 현장타설 콘크리트 말뚝 (Cast-in-place concrete pile, CIP) 가설 흙막이 벽을 영구 구조물로 활용하는 것을 보이는 구체예이다.FIG. 8 is an embodiment showing the use of cast-in-place concrete pile (CIP) temporary walls as a permanent structure.

제9도는 현장타설 콘크리트 말뚝 가설 흙막이 벽에서 H형재를 보강한 흙막이 벽을 영구 구조물로 활용하는 것을 보이는 구체예이다.FIG. 9 is a specific example showing the use of an earthquake wall reinforced with an H-shape as a permanent structure in a cast-in-place concrete piling wall.

* 도면의 주요부호에 대한 설명 *Explanation of the main symbols in the drawings

1: 지반 2: 지하 옹벽1: ground 2: underground retaining wall

3a, 3b: 수직철근 4a,4b: 수평철근3a, 3b: vertical rebar 4a, 4b: horizontal rebar

5: 하중(토압+수압) 6: 지지점5: Load (earth pressure + hydraulic pressure) 6: Support point

11: 정착전단연결수단 20: 가설 흙막이 벽11: settling shear connection means 20: temporary wall

21: H형재 22: 소일 시멘트 월(SCW)21: H shape 22: Soil cement wall (SCW)

23:현장타설 콘크리트 말뚝 흙막이 벽23: cast-in-place concrete pile walls

24:H형재 보강 현장 콘크리트 말뚝 흙막이 벽24: H-shape reinforcement site concrete pile piling wall

26: LW 차수벽 27: 보강철근26: LW lining 27: Rebar

제1도는 종래 지하옹벽을 구축하는 방법을 보인 평단면도(a)와 배근 입면도(b)이다.1 is a plan sectional view (a) and a back elevation (b) showing a conventional method of constructing an underground retaining wall.

건물의 지하 터파기를 위하여 가설 흙막이 벽(도시하지 않음)을 설치하고 터파기 후 건조물의 지하옹벽(2)을 설치하고 지하옹벽 외부에 있는 가설 흙막이 벽을 철거하거나 땅속에 매립하고 지반(1)을 다져 완성한다.Install a temporary retaining wall (not shown) for the underground excavation of the building, install the underground retaining wall (2) of the building after the excavation, remove the temporary retaining wall outside the underground retaining wall, or bury the ground (1). Chop and finish.

종래의 방법대로 공사할 경우 가설 흙막이 벽체는 단순히 지하 터파기를 위한 용도로만 사용되므로 지하 터파기가 완료된 뒤에는 그대로 매립하거나 철거해야 한다. 그러나 현실적으로 철거비용이 많이 들거나, 철거할 경우 주변 지반이 침하하여 인접 건물에 피해를 줄 수 있거나, 철거 작업이 어려운 곳이 많아 아예 땅속에 매립해 버리는 경우가 많아 아까운 자원을 땅속에 버리는 결과가 되었다.In case of construction according to the conventional method, since the temporary wall is used only for the purpose of underground excavation, it must be reclaimed or removed as it is after the underground excavation is completed. In reality, however, the cost of demolition is high, or if the ground is subsided, the surrounding ground may sink and damage adjacent buildings, or the demolition work is difficult, and it is often buried in the ground, resulting in the disposal of unnecessary resources. .

지반(1)을 다진 다음에는 하중(5)이 직접 지하 옹벽(2)에 작용하므로 지하 옹벽은 하중을 견딜 수 있도록 구조설계가 되어야 하므로 하중의 크기에 따라 철근(3a, 3b, 4a, 4b)을 배치하는 방법으로 공사를 하였다.After the ground (1) is chopped, the load (5) acts directly on the underground retaining wall (2). Therefore, the underground retaining wall must be structurally designed to withstand the load. Therefore, the reinforcing bars (3a, 3b, 4a, 4b) are required depending on the size of the load. The construction was done by placing the method.

제2도는 본 발명의 지하 옹벽 구축방법의 개념을 보인 평면도(a)와 그 단면도(b)이다.2 is a plan view (a) and a cross-sectional view (b) illustrating the concept of a method for constructing an underground retaining wall of the present invention.

본 발명은 가설 흙막이 벽(20)과 지하 옹벽(2)을 전단열결재(11)로서 결합시켜 일체 거동하도록 함으로서 강성을 키운 것이다(도면에서 가설 흙막이 벽(20)은 편의상 H형재를 도시하였다). 철거하거나 매립해야 할 가설 흙막이 벽을 지하 옹벽(2)과 일체화하여 영구 벽체로 활용하는 기본 개념으로 제시하였다.The present invention is to increase the rigidity by combining the temporary retaining wall 20 and the base retaining wall (2) as a shear thermal binder (11) so as to be integrated (in the drawing, the temporary retaining wall (20) shows an H-shaped for convenience). . The temporary conception wall to be demolished or reclaimed is presented as a basic concept that integrates the underground retaining wall (2) and utilizes it as a permanent wall.

제3도는 가설 흙막이 벽과 지하 옹벽을 연결하는 정착전단연결수단(11)으로서 전단연결재를 예시한 것이다.Figure 3 illustrates a shear connector as the anchoring shear connecting means 11 for connecting the temporary retaining wall and the underground retaining wall.

전단연결재(shear connector)는 부재 단면에 생기는 전단 흐름에 저항하기 위한 것으로, 제3도에서는 대표적인 것으로서 스터드 볼트(stud bolt), ㄷ형강, 나선근을 예시하였다. 전단연결재는 반드시 예시한 형태에 한정되지 않는다. 즉 가설 흙막이 벽과 지하 옹벽을 일체로 결합시키는 수단, 예를 들면 접착제, 거친 면으로 만들어 결합을 강화시키기 위한 샌드 블라스팅(sand blasting), 전단 요철(shear key) 등도 정착전단연결수단으로 활용할 수 있다.Shear connector (shear connector) is to resist the shear flow generated in the cross-section of the member, as a representative in Figure 3, the stud bolt (stud bolt), c-shaped steel, helix. Shear connector is not necessarily limited to the illustrated form. In other words, a means of integrally combining the temporary retaining wall and the base retaining wall, for example, an adhesive, a rough surface, sand blasting, shear key, etc., for strengthening the bond, may also be used as a fixing shear connection means. .

제4도는 엄지 말뚝으로 H형재(21)에 토류판을 끼워 가설 흙막이 벽을 형성한 흙막이 벽을 영구 구조물로 활용한 구체예이다.FIG. 4 is a specific example of using a retaining wall formed with a temporary retaining wall by inserting a earth plate into the H-shaped member 21 with a thumb pile as a permanent structure.

H형재(21)에 정착전단연결수단(11)을 소정의 간격으로 고정시키고 내부 쪽으로 지하 옹벽(2)을 형성시켜 일체화시킨 것이다. 이렇게 일체화시키면 H형재(21)가 있는 부분은 종래 방법으로 지하 옹벽(2)을 형성하게 되며, 이 경우에는 B x h1의 단면을 가진 단위 보로 해석되지만 정착전단연결수단(11)에 의해 일체화되면 B x h의 단면을 가진 단위 보로 해석된다. 따라서 단면 2차 모멘트는 [h/h1]3즉 [1+h2/h1]3만큼 커지므로 하중에 대한 저항 능력이 커진다.The fixing shear connecting means 11 is fixed to the H-shape 21 at predetermined intervals, and the base retaining wall 2 is formed toward the inside to be integrated. In this case, the portion having the H-shape 21 forms the base retaining wall 2 by a conventional method. Interpreted as a unit beam with a cross section of B xh. Accordingly, the cross-sectional secondary moment is increased by [h / h1] 3, that is, [1 + h2 / h1] 3 , thereby increasing the resistance to load.

한편 H형재(21)가 있는 곳에는 저항 능력이 대단히 향상되므로 H형재(21)가 있는 곳에 실내측 쪽으로 수직 철근(3a)을 보강하여 보의 기능을 수행하고 H형재가 있는 곳과 다른 H형재(21)가 있는 곳의 사이의 지하 옹벽(2)은 단지 하중을 받아 H형재(21)가 있는 곳으로 전달하는 기능만 하도록 설계할 수 있다. 이 경우 하중이 흐르는 방향을 살펴보면 지하 옹벽에 걸린 하중은 H형재가 있는 곳으로 흘러가(도면에서 화살표 참조) H형재가 있는 곳의 단면이 하둥에 저항하게 된다. 따라서 제5도에 보인 바와 같이 H형재가 있는 곳의 주 보강철근은 내부 쪽 수직 철근(3a)이고 H형재 있는 곳의 사이에 있는 지하옹벽(2)의 주철근은 내부 쪽 수평철근(4a)이다. H형재 있는 곳의 사이에 있는 지하옹벽(2)의 수직철근은 더 이상 필요하지 않으므로 최소 철근비 정도만 보강하면 된다.On the other hand, since the resistance capability is greatly improved where the H-shaped 21 is located, the vertical reinforcing bar 3a is reinforced to the interior side where the H-shaped 21 is located to perform the function of a beam, and the H-shaped member different from the H-shaped member. The base retaining wall 2 between the places where the 21 is located can be designed to function only to transfer the load to the place where the H-shaped material 21 is located. In this case, when the load flows, the load on the underground retaining wall flows to the H-shaped section (see arrow in the drawing) and the cross section of the H-shaped section is resisted to the bottom. Thus, as shown in FIG. 5, the main reinforcing bar where the H-shaped members are located is the inner vertical rebar 3a, and the main reinforcing bar of the basement retaining wall 2 between the H-shaped members is the inner horizontal reinforcing bar 4a. . Since the vertical reinforcement of the basement retaining wall 2 between the H-shaped sections is no longer needed, only the minimum reinforcement ratio needs to be reinforced.

제6도는 제5도의 B-B 단면으로 H형재 있는 곳의 단면의 철근 배근 개념도이다.6 is a conceptual view of the reinforcement of the cross section where the H-shaped section is located in the B-B cross section of FIG.

가설 흙막이 벽(여기서는 H형재+토류판으로 된 것을 도시하였다)과 지하 옹벽(2)이 일체로 되어 지하 구조물의 슬래브(5)로 지지된 연속보로 이해할 수 있다. 지지점(6)에서는 H형재에 부모멘트가 생기고 이 부모멘트는 H형재가 부담한다. 지지점(6) 사이 중간 부분에는 정모멘트가 생기고 이 정모멘트는 수직 철근(3a)을 배근하여 견디도록 한다. 수직 철근(3a)은 정모멘트에 견디면 되므로 반드시 연속될 필요는 없다. 따라서 일정 규격으로 외부에서 제작하여 조립하는 방식으로 공사하면 공기 단축과 품질의 향상을 기대할 수 있다. 도면에서 전단응력도는 도시하지 않았지만 지지점 부근에서 전단 응력도가 최대가 되고 지지점 사이 중간 부분에서 최소가 되므로 정착전단연결수단(11)은 지지점(6) 부근에서 촘촘히 배치하고 지지점(6) 사이 중간 부분으로 갈수록 성기게 배치한다.It can be understood as a continuous beam that is supported by the slab (5) of the underground structure in which the temporary retaining wall (shown here as H-shaped plate + earth plate) and the base retaining wall (2) are integrated. At the support point 6, the parent section is formed in the H-shaped member, and the parent member bears the parental member. In the middle part between the support points 6, a static moment arises and this static moment is made to withstand the vertical rebar 3a. Since the vertical reinforcing bars 3a withstand the constant moment, they do not necessarily have to be continuous. Therefore, if the construction is made by assembling from the outside to a certain standard can be expected to shorten the air and improve the quality. Although the shear stress is not shown in the figure, the shear stress in the vicinity of the support point is maximum and the minimum in the middle part between the support points, so that the anchoring shear connecting means 11 is closely arranged near the support point 6 and is moved to the middle part between the support points 6. Lay out gradually.

본 발명에서는 정착전단연결수단(11)에 의해 지하 옹벽과 일체가 된 H형강(21)이 제1도의 종래 지하 옹벽에서 주근으로 인식되는 수직철근(3b)을 대신하여 설치되기 때문에 제1도의 철근(3b)는 더 이상 필요하지 않게 된다. 또한 같은 이유로 수평철근(4b)도 더 이상 필요없게 된다. 따라서 본 발명의 경우 토압측 철근 배근은 제4도의 일부 수평철근(4a)의 일부를 제외하고는 전혀 필요없다. 따라서 최소 철근비 정도만 보강할 수 있고 또는 용접철망과 같이 기성제품을 재단하여 사용하면 편리하다. 즉 프리패브화(prefabrication)가 가능하다.In the present invention, since the H-shaped steel 21 integrated with the underground retaining wall by the anchoring shear connecting means 11 is installed in place of the vertical reinforcing bar 3b which is recognized as the main bar in the conventional underground retaining wall of FIG. (3b) is no longer needed. For the same reason, the horizontal bar 4b is no longer needed. Therefore, in the case of the present invention, the earth pressure side reinforcement is not necessary at all except for a part of the horizontal rebar 4a of FIG. Therefore, only the minimum reinforcement ratio can be reinforced or it is convenient to cut and use ready-made products such as welded wire mesh. That is, prefabrication is possible.

제7도는 소일 시멘트 월 가설 흙막이 벽(22)을 설치한 경우를 보인 구체예이다. 소일 시멘트 월은 흙에 시멘트를 혼합하여 주열식으로 형성하여 흙막이 벽을 만드는 방법이다. 벽의 강성을 높이기 위하여 소정 간격으로 H형재를 넣는다.7 is a specific example showing the case where the soil cement wall temporary barrier wall 22 is installed. Soil cement wall is a method of creating a wall of mud walls by mixing cement with soil to form a column. In order to increase the rigidity of the wall, H-shaped members are inserted at predetermined intervals.

전반적인 작용과 구성은 제4도 H형재+토류판 흙막이 벽과 유사하다.The overall action and construction is similar to that of Figure 4, H-shape + earth plate wall.

본 발명의 방법은 소일 시멘트 주열이 1열로 된 것(제7a도), 제1열 뒤쪽에 소일 시멘트 월을 1열 더 보강하여 2열로 된 것(제7b도), 또는 제1열 뒤쪽에 소일 시멘트 월을 2열 더 보강하여 3열(제7c도) 어느 경우든 적용된다.The method of the present invention comprises one row of cement cement rows (figure 7a), two rows of reinforcing soil cement walls one row behind column one (figure 7b), or a single row behind column one Two additional rows of cement walls are applied in any of the three rows (Figure 7c).

제8도는 가설 흙막이 벽으로 현장 타설 콘크리트 말뚝(cast-in-place concrete pile)을 사용한 경우를 나타낸 구체예이다. 현장 타설 콘크리트(CIP) 콘크리트 말뚝은 소요 위치에 구멍을 뚫고 구멍 속에 보강철근(27)을 넣어 형성한 말뚝이다. 이 말뚝을 주열식으로 형성하면 현장타설 콘크리트 말뚝 흙막이 벽(23)으로 된다. 이 말뚝의 보강 철근(27)에 전단연결재를 고정하여 지하옹벽(2)과 일체화시킨다. 현장타설 콘크리트 말뚝 뒤쪽에는 차수를 위하여 물 유리를 주입한 LW 차수벽(26)을 시공할 수 있다.FIG. 8 is a specific example showing the case of using a cast-in-place concrete pile as a temporary barrier wall. Cast-in-place concrete (CIP) concrete pile is a pile formed by drilling a hole in the required position and put the reinforcing bar (27) in the hole. When the pile is formed in a columnar manner, it becomes a cast-in-place concrete pile wall 23. The shear connector is fixed to the reinforcing bar 27 of the pile and integrated with the basement retaining wall 2. Behind the cast-in-place concrete piles can be constructed LW order wall 26 infused with water glass for the order.

본 발명의 방법은 보강 철근(27)을 넣은 현장타설 콘크리트 말뚝 흙막이 벽 주열이 1열로 된 것(제8a도), 제1열 뒤쪽에 무근 또는 보강 철근을 넣은 현장타설 콘크리트 말뚝 흙막이 벽 1열 더 보강하여 2열로 된 것(제8b도), 또는 제1열 뒤쪽에 무근 또는 보강 철근을 넣은 현장타설 콘크리트 말뚝 흙막이 벽 1열 더 보강하여 3열(제8c도) 어느 경우든 적용된다.The method of the present invention is that the cast-in-place concrete pile wall walls with reinforcing bars 27 are arranged in one row (Fig. 8a), the cast-in-place concrete pile walls with one column or reinforcing bars in the rear of the first row are one more row. Either reinforcement in two rows (Fig. 8b), or one row of cast-in-place concrete pile retaining walls with reinforcement or reinforcing bars at the back of column 1, reinforcement in three rows (Fig. 8c).

제9도는 제8도에서 보강철근(27)을 넣은 현장타설 콘크리트 말뚝 대신에 현장 타설 콘크리트 말뚝에 H형재를 소정 간격으로 보강한 H형재 보강 현장 콘크리트 말뚝 흙막이 벽(24)인 경우의 구체예이다.FIG. 9 is a concrete example of the case of the H-shaped reinforcement site concrete pile wall 24 in which the H-shaped material is reinforced at a predetermined interval in place of the cast-in-place concrete pile in which the reinforcing bar 27 is inserted in FIG. 8. .

본 발명의 방법은 H형재로 보강한 현장타설 콘크리트 말뚝 흙막이 벽 주열이 1열로 된 것(제9a도), 제1열 뒤쪽에 무근 또는 보강 철근을 넣은 현장타설 콘크리트 말뚝 흙막이 벽 1열 더 보강하여 2열로 된 것(제9b도), 또는 제1열 뒤쪽에 무근 또는 보강 철근을 넣은 현장타설 콘크리트 말뚝 흙막이 벽 1열 더 보강하여 3열(제9c도) 어느 경우든 적용된다.According to the method of the present invention, the cast-in-place concrete pile wall wall column reinforced with H-shape is one row (Fig. 9a), and the cast-in-place concrete pile wall wall with reinforcement or reinforcing bar is further reinforced by the first row. Either two rows (Figure 9b), or one row of cast-in-place concrete pile walls with reinforced or reinforcing bars at the back of Column 1, will be applied in any of the three columns (Figure 9c).

제4도를 참조하여 본 발명의 공사방법을 설명한다.Referring to Figure 4 describes the construction method of the present invention.

건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 H형재(21)를 박고 토류판을 설치하여 가설 흙막이 벽을 설치하고 터파기한다. 터파기가 완료되면 H형재(21)에 정착전단연결수단(11)을 소정의 간격으로 설치한다. 지하 옹벽 부분에는 보강 철근을 배치한다. 즉 지하 옹벽(2) 부분 중 H형재(21) 부분에 주 수직 철근(3a)을 배근하고, 지하 옹벽(2) 부분 중 H형재(21) 사이 부분에는 수평 철근(4a)을 배근한다.In consideration of the outline of the building, it decides the position to install the temporary mud walls, drills holes with earthwork equipment such as auger drills, embeds H-shaped members 21 and installs the earth plate to install the temporary mud walls. When the excavation is completed, the fixing shear connecting means 11 is installed in the H-shaped member 21 at predetermined intervals. Reinforcing bars are placed in the basement retaining wall. That is, the main vertical reinforcing bars 3a are placed in the H-shaped member 21 of the base retaining wall 2, and the horizontal reinforcing bars 4a are placed in the portion between the H-shaped members 21 in the underground retaining wall 2.

지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생한다.The mold is installed on the inner side of the base retaining wall 2, and the concrete is poured and cured.

종래의 방법과 비교해 볼 때 종래에는 가설 흙막이 벽을 설치하고 지하 옹벽을 별도로 설치해야 하기 때문에 지하 옹벽을 설치할 작업공간이 더 필요하므로 가설 흙막이 벽체가 더 외부 쪽에 위치해야 한다. 따라서 터파기해야 할 용적이 커지고 해당 공간에 되메우기 해야 할 토량이 많아져 발생할 공사비를 절감할 수 있는 요인이 되기도 한다.Compared with the conventional method, since the temporary retaining wall needs to be installed separately and the underground retaining wall needs to be installed, the temporary retaining wall needs to be located at the outer side because more work space is needed to install the retaining wall. As a result, the volume to be dug up and the amount of soil to be refilled are increased, which may be a factor to reduce construction costs.

제7도를 참조하여 본 발명의 다른 구체예의 공사방법을 설명한다.A construction method of another embodiment of the present invention will be described with reference to FIG.

건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 H형재를 박고 소일 시멘트 월(22)을 가설 흙막이 벽으로 형성하고 터파기한다. 터파기가 완료되면 소일 시멘트 월(22)의 H형재 주변을 파취하여 정착전단연결수단(11)을 소정의 간격으로 설치한다. 지하 옹벽(2) 부분에는 보강 철근을 배근한다. 즉 지하 옹벽(2) 부분 중 H형재 부분에 주 수직 철근(3a)을 배근하고, 지하 옹벽(2) 부분 중 H형재 사이 부분에는 수평 철근(4a)을 배근한다.In consideration of the outline of the building, determine the location of the temporary wall to be installed, drill the hole with earthwork equipment, such as auger drill, put the H-shaped material, and form the soil cement wall (22) as a temporary wall of wall and break. When the excavation is completed, the periphery of the H-shape of the soil cement wall 22 is excavated to install the fixing shear connection means 11 at predetermined intervals. Reinforcing bars are placed in the base retaining wall 2. That is, the main vertical reinforcing bar 3a is placed in the H-shaped part of the base retaining wall 2, and the horizontal reinforcing bar 4a is placed in the part between the H-shaped part of the underground retaining wall 2 part.

지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생한다. 지하 옹벽(2) 부분 중 H형재 사이 부분에는 필요에 따라 구멍을 뚫고 다우월 바(dowel bar)를 박아 지하 옹벽(2) 부분 중 H형재 사이 부분에서도 소일 시멘트 월(22)과 일체화 시켜 더욱 구조성능을 높일 수 있다.The mold is installed on the inner side of the base retaining wall 2, and the concrete is poured and cured. In the part of the base retaining wall (2), the hole between the H-shape is drilled as needed, and the dowel bar is embedded in the part of the base retaining wall (2). It can improve performance.

제8도를 참조하여 본 발명의 또 다른 구체예의 공사방법을 설명한다.Referring to Figure 8 describes a construction method of another embodiment of the present invention.

건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 보강 철근(27)을 넣고 현장타설 콘크리트 말뚝 흙막이 벽(23)을 형성하고 터파기한다. 터파기가 완료되면 현장타설 콘크리트 말뚝 흙막이 벽(23)의 보강 철근(27) 주변을 파취하여 보강 철근(27)에 정착전단연결수단(11)을 소정의 간격으로 설치한다. 지하 옹벽(2) 부분에 수직 철근(3a)과 수평 철근(4a)을 배근한다.In consideration of the outline of the building to determine the location of the temporary mud wall to be installed by drilling a hole with earthwork equipment such as auger drill reinforcement reinforcing bar (27) and put the cast concrete pile wall (23) to form and break. When the trench is completed, the perimeter of the reinforcement steel 27 of the cast-in-place concrete piling wall 23 is excavated to install the fixing shear connecting means 11 at the predetermined intervals in the reinforcement steel 27. The vertical reinforcing bars 3a and the horizontal reinforcing bars 4a are disposed in the base retaining wall 2.

지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생한다. 경우에 따라 현장 타설 콘크리트 말뚝 흙막이 벽(23)에 구멍을 뚫고 다우월 바(dowel bar)를 박아 지하 옹벽(2)과 현장타설 콘크리트 말뚝 흙막이 벽(23)을 일체화시킬 수 있다.The mold is installed on the inner side of the base retaining wall 2, and the concrete is poured and cured. In some cases, a hole may be drilled in the cast-in-place concrete piling wall 23 and a dowel bar may be integrated to integrate the base retaining wall 2 and the cast-in-place concrete piling wall 23.

제9도를 참조하여 본 발명의 또 다른 구체예의 공사방법을 설명한다.A construction method of another embodiment of the present invention will be described with reference to FIG.

건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 소정의 간격으로 H형재을 넣고 현장타설 콘크리트 말뚝 흙막이 벽(24)을 형성하고 터파기한다. 터파기가 완료되면 현장타설 H형재 보강 현장 콘크리트 말뚝 흙막이 벽(24)의 H형재 주변을 파취하여 H형재에 정착전단연결수단(11)을 소정의 간격으로 설치한다. 지하 옹벽(2) 부분에 수직 철근(3a)과 수평 철근(4a)을 배근한다.In consideration of the outline of the building, determine the location to install the temporary mud wall, drill holes with earthwork equipment such as auger drill, insert the H-shaped at predetermined intervals, form a cast-in-place concrete pile mud wall (24) and break it. When the trench is completed, the cast-in-place H-shaped reinforcement site is piled around the H-shaped concrete pile wall 24 to install the fixing shear connecting means 11 in the H-shaped at a predetermined interval. The vertical reinforcing bars 3a and the horizontal reinforcing bars 4a are disposed in the base retaining wall 2.

지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생한다. 경우에 따라 철근이 보강된 부분의 현장 콘크리트 말뚝 흙막이 벽에 구멍을 뚫고 다우월 바(dowel bar)를 박아 지하 옹벽(2)과 현장타설 콘크리트 말뚝 흙막이 벽을 일체화시킬 수 있다.The mold is installed on the inner side of the base retaining wall 2, and the concrete is poured and cured. In some cases, it is possible to integrate the underground retaining wall 2 and the cast-in-place concrete piling wall by drilling a hole in the on-site concrete pile piling wall of the reinforcement part and inserting a dowel bar.

이상에서 설명한 방법외에 도면으로 표시하지 않았지만 강재 시트 파일(steel sheet pile)을 가설 흙막이 벽으로 사용한 경우에도 강재 시트 파일을 영구 구조물의 일부로 활용할 수 있다. 공사 방법은 건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 강재 시트 파일을 항타하여 가설 시트 파일 흙막이 벽을 형성하고, 상기 가설 시트 파일 흙막이 벽 내부를 터파기하고, 상기 가설 시트 파일에 정착전단연결수단(11)을 설치하고, 지하 옹벽(2) 부분에 수직 철근(3a)과 수평 철근(4a)을 배근하고, 상기 지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생하여 공사한다.Although not shown in the drawings other than the method described above, even when the steel sheet pile (steel sheet pile) is used as a temporary barrier wall, the steel sheet pile may be used as part of the permanent structure. The construction method is to determine the position to install the temporary mud wall in consideration of the outline of the building to drive the steel sheet pile to form a temporary sheet pile mud wall, to excavate the inside of the temporary sheet pile mud wall, to the temporary sheet pile The anchoring shear connecting means 11 is installed, the vertical reinforcing bars 3a and the horizontal reinforcing bars 4a are disposed on the base retaining wall 2, the mold is installed on the inner side of the base retaining wall 2, and the concrete is poured. Curing and constructing

본 발명으로 건축물의 지하 구조물용 터파기를 위하여 임시로 설치하는 가설 흙막이 벽체를 영구 시설물의 일부로 활용하는 방법을 제공하여 한번 사용하고 철거하거나 매립하여야 가설 흙막이 벽을 영구 구조물의 일부로 활용함으로서 한정된 자원을 효율적으로 사용하고 공사비를 절감할 수 있게 되었다.The present invention provides a method of utilizing temporary temporary wall for temporarily discharging the underground structure of a building as part of a permanent facility, and once used and dismantled or buried, the temporary limited wall is used as part of the permanent structure to efficiently utilize limited resources. It can be used to reduce construction costs.

Claims (9)

건축물의 지하 부분 외곽선을 감안하여 가설흙막이 벽(20)을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 H형재(21)를 박고 토류판을 설치하여 가설 흙막이를 설치하는 단계;Determining a location to install the temporary mud wall (20) in consideration of the underground portion of the building, and drilling the hole with earthwork equipment such as an auger drill to insert the H-shaped member 21 and installing a soil plate to install the temporary mud wall; 상기 가설 흙막이 벽(20) 내부에서 터파기하는 단계;Digging in the temporary soil wall (20); 상기 터파기가 완료되면 상기 H형재(21)에 정착전단연결수단(11)을 설치하는 단계;Installing the fixing shear connecting means (11) on the H-shaped member (21) when the trench is completed; 상기 지하 옹벽(2) 부분에 철근(3a, 4a)을 배근하고;Reinforcing bars (3a, 4a) to the base retaining wall (2); 상기 지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생하여 상기 지하 옹벽(2)을 완성하는 단계;Installing a mold on the inner side of the base retaining wall (2), and placing and curing concrete to complete the base retaining wall (2); 로 공사하는 것을 특징으로 하는 지하 옹벽 구축 방법.Underground retaining wall construction method characterized in that the construction. 건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 H형재를 박고 소일 시멘트 월(22)을 가설 흙막이 벽으로 형성하고;Determine the location to install the temporary mud wall in consideration of the outline of the building to drill holes with earthwork equipment such as auger drill to form H-shaped material and form a soil cement wall 22 as a temporary mud wall; 상기 가설 흙막이 벽 내부를 터파기하고;Excavating the inside of the temporary soil wall; 상기 소일 시멘트 월(22)의 상기 H형재 주변을 파취하여 상기 H형재에 정착전단연결수단(11)을 설치하고;Digging around the H-shaped member of the soil cement wall 22 and installing fixing shear connecting means 11 to the H-shaped member; 상기 지하 옹벽(2) 부분에 철근(3a, 4a)을 배근하고;Reinforcing bars (3a, 4a) to the base retaining wall (2); 상기 지하 옹벽(2)의 내부 쪽에 형틀을 설치하고;A mold is installed on an inner side of the base retaining wall (2); 상기 지하 옹벽(2) 콘크리트를 타설하여 양생하는 단계;Pouring and curing the concrete retaining wall (2); 로 공사하는 것을 특징으로 하는 지하 옹벽 구축 방법.Underground retaining wall construction method characterized in that the construction. 제2항에서, 상기 지하 옹벽(2) 부분 중 H형재가 있는 곳과 인접한 다른 H형재가 있는 사이 부분의 상기 소일 시멘트 월(22)에 구멍을 뚫고 다우월 바(dowel bar)를 박는 단계를 더 포함하는 것을 특징으로 하는 지하 옹벽 구축 방법.The method of claim 2, wherein a hole in the soil cement wall 22 between the H-shaped portion and the adjacent H-shaped portion of the portion of the base retaining wall 2 is drilled and a dowel bar is driven. Underground retaining wall construction method further comprising. 건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 보강 철근(27)을 넣고 현장타설 콘크리트 말뚝 흙막이 벽(23)을 형성하고;Determine the location to install the temporary mud wall in consideration of the outline of the building to drill holes with earthwork equipment such as auger drill to put reinforcement reinforcing bar (27) to form a cast-in-place concrete pile mud wall (23); 상기 현장타설 콘크리트 말뚝 흙막이 벽(23) 내부를 터파기하고;Digging the inside of the cast-in-place concrete piling wall (23); 상기 현장타설 콘크리트 말뚝 흙막이 벽(23)의 상기 보강 철근(27) 주변을 파취하여 상기 보강 철근(27)에 정착전단연결수단(11)을 설치하고;Digging around the reinforcing reinforcement 27 of the cast-in-place concrete piling wall 23 and installing the fixing shear connecting means 11 to the reinforcing reinforcement 27; 지하 옹벽(2) 부분에 수직 철근(3a)과 수평 철근(4a)을 배근하고;Vertical reinforcing bars 3a and horizontal reinforcing bars 4a are disposed in the portion of the base retaining wall 2; 상기 지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생하는 단계;Installing a mold on the inner side of the base retaining wall (2), and placing and curing concrete; 로 공사하는 것을 특징으로 하는 지하 옹벽 구축 방법.Underground retaining wall construction method characterized in that the construction. 제4항에서, 상기 지하 옹벽(2) 부분 중 상기 보강 철근(27)에 정착전단연결수단(11)을 설치한 곳과 인접한 다른 상기 보강 철근(27)에 정착전단연결수단(11)을 설치한 곳 사이 부분의 상기 현장타설 콘크리트 말뚝 흙막이 벽(23)에 구멍을 뚫고 다우월 바(dowel bar)를 박는 단계를 더 포함하는 것을 특징으로 하는 지하 옹벽 구축 방법.5. The fixing shear connecting means (11) is installed in the other reinforcing bar (27) adjacent to the place where the anchoring shear connecting means (11) is installed in the reinforcing bar (27). A method for building an underground retaining wall further comprising drilling a dowel bar and drilling a hole in the cast-in-place concrete piling wall of a portion between one part. 건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 오거 드릴 등 토공장비로 구멍을 뚫어 소정의 간격으로 H형재로 보강한 현장타설 콘크리트 말뚝 흙막이 벽(24)을 형성하고;Determine the location to install the temporary mud wall in consideration of the outline of the building to form a cast-in-place concrete pile mud wall (24) reinforced with H-shape at a predetermined interval by drilling holes with earthwork equipment such as auger drill; 상기 H형재 보강 현장타설 콘크리트 말뚝 흙막이 벽(24) 내부를 터파기하고;Digging the inside of the H-shaped reinforcement cast-in-place concrete piling wall 24; 상기 H형재로 보강 현장타설 콘크리트 말뚝 흙막이 벽(24)의 상기 H형재 주변을 파취하여 상기 H형재에 정착전단연결수단(11)을 설치하고;Digging the H-shaped periphery of the reinforced concrete pile retaining wall (24) with the H-shape and installing the fixing shear connecting means (11) to the H-shaped; 지하 옹벽(2) 부분에 수직 철근(3a)과 수평 철근(4a)을 배근하고;Vertical reinforcing bars 3a and horizontal reinforcing bars 4a are disposed in the portion of the base retaining wall 2; 상기 지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생하는 단계;Installing a mold on the inner side of the base retaining wall (2), and placing and curing concrete; 로 공사하는 것을 특징으로 하는 지하 옹벽 구축 방법.Underground retaining wall construction method characterized in that the construction. 제6항에서, 상기 지하 옹벽(2) 부분 중 상기 H형재에 정착전단연결수단(11)을 설치한 곳과 인접한 다른 상기 H형재에에 정착전단연결수단(11)을 설치한 곳 사이 부분의 상기 H형재 보강 현장타설 콘크리트 말뚝 흙막이 벽(24)에 구멍을 뚫고 다우월 바(dowel bar)를 박는 단계를 더 포함하는 것을 특징으로 하는 지하 옹벽 구축 방법.The method of claim 6, wherein the portion between the portion of the base retaining wall (2) between the place where the anchorage shear connection means 11 is installed in the H-shaped member and the other place where the anchorage shear connection means (11) is installed in the other H-shaped adjacent to And drilling a dowel bar and drilling a hole in the H-shaped reinforcement cast-in-place concrete piling wall (24). 건축물의 외곽선을 감안하여 가설흙막이 벽을 설치할 위치를 결정하여 강재 시트 파일을 항타하여 가설 시트 파일 흙막이 벽을 형성하고;Determining a location to install the temporary wall, considering the outline of the building, and driving the steel sheet pile to form the temporary sheet pile wall; 상기 가설 시트 파일 흙막이 벽 내부를 터파기하고;Digging the inside of the temporary sheet pile soil wall; 상기 가설 시트 파일에 정착전단연결수단(11)을 설치하고;Installing a fixing shear connecting means (11) in the temporary sheet pile; 지하 옹벽(2) 부분에 수직 철근(3a)과 수평 철근(4a)을 배근하고;Vertical reinforcing bars 3a and horizontal reinforcing bars 4a are disposed in the portion of the base retaining wall 2; 상기 지하 옹벽(2)의 내부 쪽에 형틀을 설치하고, 콘크리트를 타설하여 양생하는 단계;Installing a mold on the inner side of the base retaining wall (2), and placing and curing concrete; 로 공사하는 것을 특징으로 하는 지하 옹벽 구축 방법.Underground retaining wall construction method characterized in that the construction. 제1항, 제2항, 제4항, 제6항, 제7항, 또는 제8항에서, 상기 정착전단연결수단(11)은 전단연결재(shear connector), 접착제 도포, 샌드 블라스팅, 또는 전단요철(shear key)에 의한 수단인 것을 특징으로 하는 지하 옹벽 구축방법.The method of claim 1, 2, 4, 6, 7, or 8, wherein the anchoring shear connecting means 11 is a shear connector, adhesive application, sand blasting, or shear A method for building an underground retaining wall, characterized in that it is a means by means of irregularities.
KR1019980042252A 1998-10-09 1998-10-09 Composite retaining wall construction method KR100327547B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019980042252A KR100327547B1 (en) 1998-10-09 1998-10-09 Composite retaining wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019980042252A KR100327547B1 (en) 1998-10-09 1998-10-09 Composite retaining wall construction method

Publications (2)

Publication Number Publication Date
KR19990007580A true KR19990007580A (en) 1999-01-25
KR100327547B1 KR100327547B1 (en) 2002-11-04

Family

ID=37478423

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019980042252A KR100327547B1 (en) 1998-10-09 1998-10-09 Composite retaining wall construction method

Country Status (1)

Country Link
KR (1) KR100327547B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100401330B1 (en) * 2001-05-04 2003-10-17 주식회사 정진종합엔지니어링건축사사무소 A method of construction for earth-protection walls of building
KR20040023915A (en) * 2002-09-12 2004-03-20 (주)한빛하이테크엔지니어링 Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method and construction method thereof
KR100444838B1 (en) * 2001-07-27 2004-08-25 정란 A fiber reinforced earth retaining wall, a constructing method thereof, and a composite underground wall structure using thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101296856B1 (en) 2011-08-24 2013-08-14 주식회사 세진에스씨엠 Reinforcement structure for wall of underground structure and construction method of underground structure using the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3062909B2 (en) * 1993-08-25 2000-07-12 株式会社竹中工務店 Construction method of composite underground wall using soil cement column wall

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100401330B1 (en) * 2001-05-04 2003-10-17 주식회사 정진종합엔지니어링건축사사무소 A method of construction for earth-protection walls of building
KR100444838B1 (en) * 2001-07-27 2004-08-25 정란 A fiber reinforced earth retaining wall, a constructing method thereof, and a composite underground wall structure using thereof
KR20040023915A (en) * 2002-09-12 2004-03-20 (주)한빛하이테크엔지니어링 Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method and construction method thereof

Also Published As

Publication number Publication date
KR100327547B1 (en) 2002-11-04

Similar Documents

Publication Publication Date Title
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
KR20130081971A (en) Precast concrete wall and method for constructing underground permanent wall using the precast concrete wall
KR100415809B1 (en) precast pile for braced wall and the method using the same
KR100832490B1 (en) A foundation method of continuous and cut off wall by overlap casing
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR100313721B1 (en) Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
KR102223856B1 (en) Foundation structure of waste landfill site and construction method thereof
KR20200029080A (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
KR100376589B1 (en) Underground construction method using permanent reinforced concrete girders as temporary struts
JP2000352296A (en) Method o constructing passage just under underground structure
JP4485006B2 (en) Construction method for underground structures
KR100327547B1 (en) Composite retaining wall construction method
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
KR102103831B1 (en) Construction method of underground structures using auger apparatus with guide bit
KR100493516B1 (en) Micro pile and assembly foundation reinforcement structure member and its method for pier
KR102195496B1 (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
KR100401330B1 (en) A method of construction for earth-protection walls of building
KR100317906B1 (en) Building Anchoring Method by friction and its design method
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
KR100429283B1 (en) Construction Method using Precast Concrete for Diaphragm Wall
KR20200088659A (en) Top-down type underground structure construction method using earth support plate
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
N231 Notification of change of applicant
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
J201 Request for trial against refusal decision
AMND Amendment
B701 Decision to grant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20100217

Year of fee payment: 9

LAPS Lapse due to unpaid annual fee