KR102601694B1 - Method for demolishing underground building - Google Patents
Method for demolishing underground building Download PDFInfo
- Publication number
- KR102601694B1 KR102601694B1 KR1020220000435A KR20220000435A KR102601694B1 KR 102601694 B1 KR102601694 B1 KR 102601694B1 KR 1020220000435 A KR1020220000435 A KR 1020220000435A KR 20220000435 A KR20220000435 A KR 20220000435A KR 102601694 B1 KR102601694 B1 KR 102601694B1
- Authority
- KR
- South Korea
- Prior art keywords
- underground
- demolition
- foundation
- wall
- anchoring
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 90
- 238000004873 anchoring Methods 0.000 claims abstract description 38
- 239000002689 soil Substances 0.000 claims description 25
- 239000004568 cement Substances 0.000 claims description 12
- 239000008267 milk Substances 0.000 claims description 12
- 210000004080 milk Anatomy 0.000 claims description 12
- 235000013336 milk Nutrition 0.000 claims description 12
- 238000009792 diffusion process Methods 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 5
- 239000010959 steel Substances 0.000 claims description 5
- 230000001174 ascending effect Effects 0.000 claims description 3
- 238000005336 cracking Methods 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 230000000694 effects Effects 0.000 description 10
- 239000002699 waste material Substances 0.000 description 7
- 238000009694 cold isostatic pressing Methods 0.000 description 5
- 208000037584 hereditary sensory and autonomic neuropathy Diseases 0.000 description 5
- 238000011900 installation process Methods 0.000 description 5
- 239000007787 solid Substances 0.000 description 4
- 238000005452 bending Methods 0.000 description 3
- 238000004891 communication Methods 0.000 description 3
- 230000002787 reinforcement Effects 0.000 description 3
- 239000010865 sewage Substances 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000005056 compaction Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/08—Wrecking of buildings
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/40—Miscellaneous comprising stabilising elements
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본 발명은 지하 2/10 높이 내지 4/10 높이에 이르러 토사벽체(B)를 피어싱(Piercing)하여 앵커링리버(Anchoring Lebar; 70)를 끼움과 동시에 띠장(64)에 결합시키면서 앵커링리버(70)로 하여금 토사벽체(B)의 하향토압을 온전히 받아 띠장(64)과 함께하는 지지력으로 토사벽체(B)의 붕괴토압을 저지할 수 있도록 한 지하건축물 신속 철거방법에 관한 발명이다.The present invention pierces the earthen wall (B) at a height of 2/10 to 4/10 underground, inserts an anchoring lever (70), and simultaneously connects the anchoring lever (70) to the wale (64). This is an invention regarding a method of rapid demolition of an underground building, which allows a person to completely receive the downward earth pressure of the earthen wall (B) and prevent the collapse earth pressure of the earthen wall (B) with the bearing capacity of the wale (64).
Description
본 발명은 지하건축물 신속 철거방법에 관한 것으로, 더욱 상세하게는 토사벽체에 등간격의 H-빔과 더불어 CIP가 파일링됨과 동시에 지하지반 위에 지하기초가 마련되면서 지하벽체, 슬래브 및 기둥을 지닌 오래된 지하건축물을 신속, 용이 및 안전하게 철거하여 토목업체에 인계할 수 있도록 한 지하건축물 신속 철거방법에 관한 것이다.The present invention relates to a method of rapid demolition of an underground building. More specifically, the present invention relates to a method for rapid demolition of an underground building. More specifically, the CIP is piled on the earthen wall along with H-beams at equal intervals, and at the same time, an underground foundation is prepared on the underground ground, and an old underground structure with basement walls, slabs and pillars is prepared. This relates to a rapid demolition method for underground buildings that allows the building to be quickly, easily and safely demolished and handed over to a civil engineering company.
일반적으로 오래된 지하건축물을 철거할 경우 주변건물 및 주변도로로의 영향을 최소화시킬 수 있어야 하며, 이에 대한 선행기술문헌으로서 상향식 순차제거 및 순차매립공법이 공지되어 있다.In general, when demolishing an old underground building, the impact on surrounding buildings and surrounding roads must be minimized, and bottom-up sequential removal and sequential reclamation methods are known as prior art literature.
도 1a는 선행기술문헌(대한민국 공개특허공보 제2006-0103309호)에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법을 설명함에 있어서 레이커파일 및 레이커 설치공정을 나타내는 단면도이고, 도 1b는 선행기술문헌에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법을 설명함에 있어서 레이커파일 및 레이커 설치공정을 나타내는 사시도이며, 도 1c는 선행기술문헌에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법을 설명함에 있어서 토사되메움이 진행되어 더 이상 옹벽지지의 필요가 없게 된 하단측 레이커를 제거하는 한편 옹벽의 제거가 완료된 부분에 대해서는 그 옹벽을 지지하는데 사용되었던 레이커파일을 인발하는 개념을 도시한 단면도이다.Figure 1a is a cross-sectional view showing the raker pile and raker installation process in explaining the bottom-up sequential removal and sequential reclamation method for removing underground retaining walls according to the prior art document (Korean Patent Publication No. 2006-0103309), and Figure 1b is a cross-sectional view showing the raker pile and raker installation process. In explaining the bottom-up sequential removal and sequential reclamation method for removing underground retaining walls according to prior art literature, it is a perspective view showing the raker pile and raker installation process, and Figure 1c is a bottom-up sequential removal for removing underground retaining walls according to prior art literature. In explaining the sequential reclamation method, the lower raker, which no longer needs retaining wall support due to soil backfilling, is removed, and the raker piles used to support the retaining wall are pulled out from the part where the removal of the retaining wall has been completed. This is a cross-sectional view showing the concept.
선행기술문헌에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법은 도 1a 내지 도 1c에 도시된 바와 같이 지하가 깊지 않은 철거에 맞도록 제안된 것으로 지하2층의 구간에서 이미 철거된 공간 내부 지중에 레이커파일(30)을 박은 후 경사를 달리한 레이커(32)로 하여금 지하옹벽(10)을 경사지게 지지하도록 레이커파일(30)에 고정되는 구조로 설계되어 있다.The bottom-up sequential removal and sequential reclamation method for removing underground retaining walls according to prior art literature is proposed to suit demolition where the basement is not deep, as shown in Figures 1a to 1c, and is a space that has already been demolished in the section of the second basement level. It is designed to be fixed to the raker pile (30) so that the raker pile (30) is driven into the internal ground and then the raker (32) with different inclinations is inclined to support the underground retaining wall (10).
경사를 달리한 레이커(32)를 적용한다는 것은 이미 철거된 공간 내부가 있어야 한다는 의미이고, 이 점은 레이커파일(30) 및 레이커(32)의 설치 직전의 상태가 지하옹벽(10)으로 막고 있는 토압이 언제든지 무너질 수 있는 공법이어서 지하의 깊이가 깊을 경우 매우 위험스러운 상황에 노출될 수밖에 없어, 결국, 지하 층이 깊은 경우의 철거는 실현할 수 없는 한계를 안고 있다.Applying a raker (32) with a different slope means that there must be an interior of the space that has already been demolished, and this means that the state just before installation of the raker pile (30) and raker (32) is blocked by the underground retaining wall (10). Since this is a construction method in which the earth pressure can collapse at any time, it is bound to be exposed to a very dangerous situation if the underground depth is deep. Ultimately, demolition in deep underground layers has limitations that cannot be realized.
그리고, 토사되메우기 공정 역시 도 1b와 같이 레이커(32)의 기울기 때문에[레이커(32)의 철거를 대비하여] 토사를 경사지게 되메우기를 할 수밖에 없어 작업이 불편[공사기간 연장]할 뿐만 아니라 지하옹벽(10)에 가해지는 토압에 의해 토사가 언제 무너질지 모르는 위험에 거듭 노출되어 있고, 나아가 레이커파일(30)에 가해지는 토사되메우기에 의한 토압이 상당하여 레이커파일(30)의 한쪽방향으로의 휨이나 꺾임 현상이 나타날 수 있을 뿐만 아니라, 이를 극복하기 위하여 레이커파일(30)의 지지력을 위한 두께 또는 깊이 등을 더 고려해야만 하는 단점을 안고 있다.In addition, in the soil backfilling process, as shown in FIG. 1b, due to the slope of the raker 32 (in preparation for the demolition of the raker 32), the soil backfill has to be sloped, which not only makes the work inconvenient (extends the construction period), but also creates an underground retaining wall ( 10), it is repeatedly exposed to the risk that the soil may collapse at any time due to the earth pressure applied to the raker pile (30), and the earth pressure due to soil backfill applied to the raker pile (30) is significant, causing the raker pile (30) to bend in one direction or Not only may a bending phenomenon occur, but in order to overcome this, it has the disadvantage of having to further consider the thickness or depth for the bearing capacity of the raker pile (30).
결국, 선행기술문헌의 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법은 지하가 깊지 않는 곳에 적합하도록 설계되어 있고, 특히 이미 철거된 공간 내부가 있어야 하는 전제가 필요하며, 경사를 달리한 레이커(32)로 인하여 레이커파일(30)의 휨이나 꺾임 나아가 토사되메우기의 힘듦 및 위험성 등과 같은 다수의 문제점이 안고 있음을 확인할 수 있는 것이다.In the end, the bottom-up sequential removal and sequential reclamation method for removing the underground retaining wall in the prior art literature is designed to be suitable for places where the underground is not deep, and in particular, it requires the premise that there must be an inside of the space that has already been demolished, and a raker with a different slope is required. Due to (32), it can be confirmed that there are a number of problems such as bending or bending of the raker pile (30), and the difficulty and risk of soil backfilling.
본 발명의 목적은 토사벽체에 등간격의 H-빔과 더불어 CIP가 파일링됨과 동시에 지하지반 위에 지하기초가 마련되면서 지하벽체, 슬래브 및 기둥을 지닌 오래된 지하건축물을 신속, 용이 및 안전하게 철거하여 토목업체에 인계할 수 있도록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to quickly, easily and safely demolish old underground buildings with underground walls, slabs and columns by piling CIPs with H-beams at equal intervals on the earthen wall and at the same time providing an underground foundation on the underground ground. The goal is to provide a method of rapid demolition of underground buildings that can be handed over to .
본 발명의 목적은 지하 2/10 높이 내지 4/10 높이에서부터 지하기초에 이르기까지 충분히 확보된 기초철거공간을 활용하여 지하기초를 거침없이 철거토록 하여 안정성과 더불어 신속성을 더불어 보장케 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to demolish the underground foundation without hesitation by utilizing the sufficiently secured demolition space from 2/10th to 4/10th of the underground height to the underground foundation, thereby ensuring speed and stability of the underground building. It provides a method of demolition.
본 발명의 목적은 기초철거공간, 즉 지하기초에서 구동되는 중장비의 작업높이[예를 들어 포크레인 등과 같은 중장비의 작업시 버팀보에 부딪히지 않도록 하는 작업높이]를 확보하여 지하기초 철거시 중장비의 운동범위를 보장할 수 있도록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to secure the foundation demolition space, that is, the working height of heavy equipment driven in the underground foundation (for example, a working height that prevents heavy equipment such as an excavator from colliding with the brace when working on the foundation) to ensure the range of movement of heavy equipment during demolition of the underground foundation. The goal is to provide a method of rapid demolition of underground buildings that can be guaranteed.
본 발명의 목적은 지하 각 층의 내림순서로 슬래브, 기둥, 지하벽체 및 CIP의 철거와 함께 H-빔에 달라붙은 콘크리트의 파쇄 및 반출할 때 구동되는 중장비의 하부에 슬래브의 급격한 크랙[중장비의 제자리 회전 등의 하중 및 압력에 따른 슬래브의 급격한 파손에 의한 예기치 못한 무너짐 초래]을 방지토록 받침철판을 더 위치시켜 중장비의 견고한 받침으로 더욱 안전한 철거작업을 가능케 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to demolish slabs, columns, basement walls, and CIPs in descending order of each underground floor, and to prevent rapid cracks in the slab at the bottom of heavy equipment driven when crushing and transporting concrete adhering to H-beams [of heavy equipment]. We provide a rapid demolition method for underground buildings that enables safer demolition work with a solid support for heavy equipment by further positioning the supporting steel plates to prevent unexpected collapse due to sudden damage to the slab due to load and pressure such as rotation in place. .
본 발명의 목적은 지하기초의 철거시 중장비의 원활한 운동범위를 보장함과 동시에 토사벽체의 붕괴토압을 극복할 수 있도록 지하 2/10 높이 내지 4/10 높이에 이르러 토사벽체를 피어싱하면서 앵커링리버를 끼움과 동시에 띠장에 결합시켜 앵커링리버로 하여금 토사벽체의 하향토압을 온전히 받아 띠장과 함께하는 지지력으로 토사벽체의 붕괴토압을 저지토록 하여 대형사고를 미연에 방지케 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to provide an anchoring river while piercing the earthen wall at a height of 2/10 to 4/10th underground so as to ensure a smooth range of motion of heavy equipment during the demolition of the underground foundation and at the same time overcome the earth pressure of the collapsed earthen wall. It provides a method of rapid demolition of underground buildings by attaching it to the wale at the same time and allowing the anchoring river to fully receive the downward earth pressure of the earthen wall and prevent the collapse earth pressure of the earthen wall with the bearing power of the earthen wall, thus preventing a major accident. .
본 발명의 목적은 앵커링리버로 하여금 지지력확산판과 함께 띠장에 고정되도록 하여 토사벽체의 하향토압을 온전히 받으면서 하향되려는 힘을 지지력확산판으로 띠장에 확산시켜 붕괴토압의 저지력을 더욱 극대화시킬 수 있도록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to allow the anchoring river to be fixed to the wale together with the bearing force diffusion plate so that the downward force of the earthen wall can be fully received and the downward force can be spread to the wale by the bearing force diffusion plate to further maximize the stopping power of the collapsing earth pressure. It provides a method for rapid demolition of underground buildings.
본 발명의 목적은 지하건축물 주변에 상하수도관이나 통신케이블 또는 이웃하는 다른 건축물이 존재하여 앵커링리버를 토사벽체에 박을 수 없을 경우 지하건축물의 코너에서 H-빔을 사선방향으로 잇는 코너버팀보를 더 설치하여 기초철거공간의 확보와 더불어 토사벽체의 붕괴토압을 동시에 해소할 수 있도록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to add a corner brace connecting the H-beam in a diagonal direction at the corner of the underground building when the anchoring river cannot be driven into the earthen wall due to the presence of water and sewage pipes, communication cables, or other neighboring buildings around the underground building. The aim is to provide a rapid demolition method for underground buildings that can secure foundation demolition space and simultaneously relieve the earth pressure of collapsed earthen walls.
본 발명의 목적은 앵커링리버를 박을 때 토사벽체 속으로 피어싱 주입되는 시멘트밀크와 함께 경화되도록 하여 토사벽체의 하향토압을 온전히 받을 수 있도록 하고, 토사벽체 속으로 끼워지는 3∼5개의 종형지지철근들과, 이 종형지지철근들을 등간격으로 고정시키는 횡형고정철근들로 이루어질 수 있도록 하며, 종형지지철근들 및 횡형고정철근들을 감싸면서 시멘트밀크를 수용하는 플렉시블튜브를 포함토록 하여, 플렉시블튜브로서 종형지지철근들 및 횡형고정철근들과 함께 시멘트밀크를 신속 견고하게 밀집 경화시켜 견고한 지지력과 해체시의 용이함을 더불어 보장할 수 있도록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to allow the anchoring river to be hardened together with the cement milk that is pierced and injected into the soil wall when driving the anchoring river, so that it can fully receive the downward earth pressure of the soil wall, and to install 3 to 5 vertical support bars inserted into the soil wall. and horizontal fixed bars that fix the vertical support bars at equal intervals, and include a flexible tube that accommodates cement milk while surrounding the vertical support bars and the horizontal fixed bars, forming a vertical tube as a flexible tube. The aim is to provide a method of rapid demolition of underground buildings that ensures solid bearing capacity and ease of dismantling by quickly and tightly hardening cement milk together with support bars and horizontal fixing bars.
본 발명의 목적은 지하 2/10 높이 내지 4/10 높이에서부터 지하기초에 이르기까지 내림순서로 슬래브, 기둥, 지하벽체, 잭서포트 및 CIP의 철거와 함께 H-빔에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 H-빔 사이에 토류판을 끼우면서 기초철거공간을 확보토록 하여 지하기초를 해체하기 위한 중장비의 원활한 운동범위를 충분히 확보토록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to demolish slabs, columns, basement walls, jack supports, and CIPs in descending order from 2/10th to 4/10th of the underground height to the basement foundation, as well as crushing and transporting the concrete attached to the H-beam. Next, we provide a rapid demolition method for underground buildings that secures foundation demolition space by inserting earthen plates between neighboring H-beams to ensure sufficient range of smooth movement for heavy equipment to dismantle the underground foundation.
본 발명의 목적은 토류판 및 토사벽체 사이에 폐콘크리트를 채워 주변건물과 주변도로에 의해 토압을 받고 있는 토사벽체의 초기미동을 폐콘크리트의 채움으로 지지할 수 있도록 하여 CIP의 공백에 따른 토사벽체의 밀림현상이나 무너짐현상을 미리서 제압할 수 있도록 한 지하건축물 신속 철거방법을 제공함에 있다.The purpose of the present invention is to fill the space between the earth plate and the earth wall with waste concrete so that the initial slight movement of the earth wall under earth pressure from surrounding buildings and surrounding roads can be supported by filling the waste concrete, thereby supporting the filling of the earth wall according to the space in the CIP. The goal is to provide a method of rapid demolition of underground buildings that can suppress crowding or collapse in advance.
상기 목적을 달성하기 위한 본 발명은,The present invention to achieve the above object,
토사벽체에 등간격의 H-빔과 더불어 CIP가 파일링됨과 동시에 지하지반 위에 지하기초가 마련되면서 지하벽체, 슬래브 및 기둥을 지닌 지하건축물을 철거하는 지하건축물 신속 철거방법에 있어서,In the method of rapid demolition of an underground building in which an underground building with underground walls, slabs and columns is demolished while CIP is piled on the earthen wall along with equally spaced H-beams and an underground foundation is prepared on the underground ground,
지하 각 층의 상기 슬래브에 쓰루홀을 뚫어 포스트파일을 끼우면서 상기 지하기초에 지지되도록 함과 동시에 상기 슬래브 사이에 잭서포트를 설치하는 제1공정과,A first step of drilling through holes in the slabs of each underground floor to insert post piles so that they are supported on the basement foundation, and installing jack supports between the slabs;
지하 2/10 높이 내지 4/10 높이에 이르기까지 내림순서로 상기 슬래브, 기둥, 지하벽체, 잭서포트 및 CIP의 철거와 함께 상기 H-빔에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 상기 H-빔 사이에 토류판을 끼우고 띠장을 두르면서 상기 포스트파일과 더불어 상기 H-빔을 잇는 버팀보를 설치하는 제2공정과,Following the demolition of the slab, column, basement wall, jack support, and CIP in descending order from 2/10th to 4/10th of the height underground, crushing and removal of the concrete attached to the H-beam, the neighboring H -A second process of installing a brace connecting the H-beam with the post pile by inserting an earth plate between the beams and wrapping a strip,
지하 2/10 높이 내지 4/10 높이에 이르러 상기 토사벽체를 피어싱하여 앵커링리버를 끼움과 동시에 상기 띠장에 결합시키면서 상기 앵커링리버로 하여금 상기 토사벽체의 하향토압을 온전히 받아 상기 띠장과 함께하는 지지력으로 상기 토사벽체의 붕괴토압을 저지시키는 제3공정과,When reaching a height of 2/10 to 4/10 of the underground level, the earthen wall is pierced and the anchoring river is inserted and coupled to the wale, thereby allowing the anchoring river to completely receive the downward earth pressure of the earthen wall and provide a supporting force with the wale. A third process of preventing the collapse earth pressure of the earthen wall,
지하 2/10 높이 내지 4/10 높이에서부터 상기 지하기초에 이르기까지 내림순서로 상기 슬래브, 기둥, 지하벽체, 잭서포트 및 CIP의 철거와 함께 상기 H-빔에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 상기 H-빔 사이에 토류판을 끼우면서 기초철거공간을 확보하는 제4공정과,Following the demolition of the slab, column, basement wall, jack support and CIP in descending order from 2/10th to 4/10th of the height of the basement to the basement foundation, crushing and removal of the concrete attached to the H-beam A fourth process of securing foundation demolition space by inserting an earthen plate between the adjacent H-beams,
지하 2/10 높이 내지 4/10 높이에서부터 상기 지하기초에 이르기까지 확보된 상기 기초철거공간을 활용하여 상기 지하기초를 철거하는 제5공정과, A fifth process of demolishing the underground foundation using the foundation demolition space secured from 2/10 to 4/10 the height underground to the underground foundation,
지하 각 층의 올림순서로 상기 지하지반에서부터 토사되메우기 및 다짐을 하면서 상기 앵커링리버, 버팀보 및 띠장을 해체하는 제6공정과,A sixth process of dismantling the anchoring river, braces, and strips while backfilling and compacting soil from the underground ground in the ascending order of each underground floor,
상기 포스트파일 및 H-빔을 인발하는 제7공정을 포함하는 것을 그 기술적 방법상의 기본 특징으로 한다.A basic feature of the technical method is that it includes a seventh process of drawing the post pile and H-beam.
본 발명은 토사벽체에 등간격의 H-빔과 더불어 CIP가 파일링됨과 동시에 지하지반 위에 지하기초가 마련되면서 지하벽체, 슬래브 및 기둥을 지닌 오래된 지하건축물을 신속, 용이 및 안전하게 철거하여 토목업체에 인계할 수 있도록 하는 효과가 있다.The present invention is to quickly, easily and safely demolish old underground buildings with underground walls, slabs and columns by piling CIP with H-beams at equal intervals on the earthen wall and at the same time providing an underground foundation on the underground foundation, and handing it over to a civil engineering company. It has the effect of allowing you to do it.
본 발명은 지하 2/10 높이 내지 4/10 높이에서부터 지하기초에 이르기까지 확보된 기초철거공간을 활용하여 지하기초를 거침없이 철거토록 하여 안정성과 더불어 신속성을 더불어 보장케 하는 효과가 있다.The present invention has the effect of ensuring stability and speed by demolishing the underground foundation without hesitation by utilizing the foundation demolition space secured from 2/10 to 4/10 the height of the underground to the underground foundation.
본 발명은 기초철거공간, 즉 지하기초에서 구동되는 중장비의 작업높이[예를 들어 포크레인 등과 같은 중장비의 작업시 버팀보에 부딪히지 않도록 하는 작업높이]를 확보하여 지하기초 철거시 중장비의 운동범위를 보장할 수 있는 효과가 있다.The present invention secures the working height of heavy equipment driven in the foundation demolition space, that is, the underground foundation (for example, a working height that prevents heavy equipment such as an excavator from colliding with the brace when working) to ensure the range of motion of the heavy equipment when demolishing the underground foundation. There is a possible effect.
본 발명은 지하 각 층의 내림순서로 슬래브, 기둥, 지하벽체 및 CIP의 철거와 함께 H-빔에 달라붙은 콘크리트의 파쇄 및 반출할 때 구동되는 중장비의 하부에 슬래브의 급격한 크랙[중장비의 제자리 회전 등의 하중 및 압력에 따른 슬래브의 급격한 파손에 의한 예기치 못한 무너짐 초래]을 방지토록 받침철판을 더 위치시켜 중장비의 견고한 받침으로 더욱 안전한 철거작업을 가능케 하는 효과가 있다.The present invention deals with the demolition of slabs, columns, basement walls, and CIPs in descending order of each underground floor, as well as the sudden cracking of the slab at the bottom of the driven heavy equipment when crushing and transporting the concrete stuck to the H-beam [in-place rotation of heavy equipment]. To prevent unexpected collapse due to rapid damage to the slab due to load and pressure, etc., the support steel plates are positioned further, which has the effect of enabling safer demolition work with a sturdy support for heavy equipment.
본 발명은 지하기초의 철거시 중장비의 원활한 운동범위를 보장함과 동시에 토사벽체의 붕괴토압을 극복할 수 있도록 지하 2/10 높이 내지 4/10 높이에 이르러 토사벽체를 피어싱하면서 앵커링리버를 끼움과 동시에 띠장에 결합시켜 앵커링리버로 하여금 토사벽체의 하향토압을 온전히 받아 띠장과 함께하는 지지력으로 토사벽체의 붕괴토압을 저지토록 하여 대형사고를 미연에 방지케 하는 효과가 있다.The present invention involves inserting an anchoring river while piercing the earthen wall at a height of 2/10 to 4/10th underground to ensure a smooth range of motion of heavy equipment during demolition of the underground foundation and at the same time overcome the earth pressure of the collapsed earthen wall. At the same time, by combining it with the wale, the anchoring river completely receives the downward earth pressure of the earthen wall and prevents the earth pressure from collapsing the earthen wall with the supporting force with the wale, which has the effect of preventing large-scale accidents in advance.
본 발명은 앵커링리버로 하여금 지지력확산판과 함께 띠장에 고정되도록 하여 토사벽체의 하향토압을 온전히 받으면서 하향되려는 힘을 지지력확산판으로 띠장에 확산시켜 붕괴토압의 저지력을 더욱 극대화시킬 수 있도록 하는 효과가 있다.The present invention has the effect of allowing the anchoring river to be fixed to the wale together with the bearing force diffusion plate to fully receive the downward earth pressure of the earthen wall and to spread the downward force to the wale with the bearing force diffusion plate to further maximize the stopping power of the collapsing earth pressure. there is.
본 발명은 지하건축물 주변에 상하수도관이나 통신케이블 또는 이웃하는 다른 건축물이 존재하여 앵커링리버를 토사벽체에 박을 수 없을 경우 지하건축물의 코너에서 H-빔을 사선방향으로 잇는 코너버팀보를 더 설치하여 기초철거공간의 확보와 더불어 토사벽체의 붕괴토압을 동시에 해소할 수 있도록 하는 효과가 있다.In the present invention, when the anchoring river cannot be driven into the earthen wall due to the presence of water and sewage pipes, communication cables, or other neighboring buildings around the underground building, a corner brace connecting the H-beam in a diagonal direction is installed at the corner of the underground building. It has the effect of securing space for foundation demolition and simultaneously relieving the earth pressure of the collapsed earthen wall.
본 발명은 앵커링리버를 박을 때 토사벽체 속으로 피어싱 주입되는 시멘트밀크와 함께 경화되도록 하여 토사벽체의 하향토압을 온전히 받을 수 있도록 하고, 토사벽체 속으로 끼워지는 3∼5개의 종형지지철근들과, 이 종형지지철근들을 등간격으로 고정시키는 횡형고정철근들로 이루어질 수 있도록 하며, 종형지지철근들 및 횡형고정철근들을 감싸면서 시멘트밀크를 수용하는 플렉시블튜브를 포함토록 하여, 플렉시블튜브로서 종형지지철근들 및 횡형고정철근들과 함께 시멘트밀크를 신속 견고하게 밀집 경화시켜 견고한 지지력과 더불어 해체시의 용이함을 보장할 수 있도록 하는 효과가 있다.The present invention allows the anchoring river to be hardened together with the cement milk that is pierced and injected into the soil wall to fully receive the downward earth pressure of the soil wall, and includes 3 to 5 vertical support bars inserted into the soil wall and , It is made up of horizontal fixed bars that fix the vertical support bars at equal intervals, and includes a flexible tube that accommodates cement milk while surrounding the vertical support bars and the horizontal fixed bars, forming the vertical support bars as a flexible tube. It has the effect of quickly and firmly hardening the cement milk together with the vertical and horizontal fixing rebars to ensure solid support and ease of disassembly.
본 발명은 지하 2/10 높이 내지 4/10 높이에서부터 지하기초에 이르기까지 내림순서로 슬래브, 기둥, 지하벽체, 잭서포트 및 CIP의 철거와 함께 H-빔에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 H-빔 사이에 토류판을 끼우면서 기초철거공간을 확보토록 하여 지하기초를 해체하기 위한 중장비의 원활한 운동범위를 충분히 확보토록 하는 효과가 있다.The present invention involves the demolition of slabs, columns, basement walls, jack supports, and CIPs in descending order from 2/10th to 4/10th of the underground height to the basement foundation, followed by crushing and removal of the concrete attached to the H-beam. By inserting an earth plate between neighboring H-beams, space for foundation demolition is secured, which has the effect of ensuring a sufficient range of smooth movement for heavy equipment to dismantle the underground foundation.
본 발명은 토류판 및 토사벽체 사이에 폐콘크리트를 채워 주변건물과 주변도로에 의해 토압을 받고 있는 토사벽체의 초기미동을 폐콘크리트의 채움으로 지지할 수 있도록 하여 CIP의 공백에 따른 토사벽체의 밀림현상이나 무너짐현상을 미리서 제압할 수 있도록 하는 효과가 있다.The present invention fills the space between the earth plate and the earth wall with waste concrete, so that the initial slight movement of the earth wall under earth pressure from surrounding buildings and surrounding roads can be supported by filling the waste concrete, thereby preventing the phenomenon of the earth wall being pushed due to the space in the CIP. It has the effect of suppressing the collapse phenomenon in advance.
도 1a는 선행기술문헌에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법을 설명함에 있어서 레이커파일 및 레이커 설치공정을 나타내는 단면도.
도 1b는 선행기술문헌에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법을 설명함에 있어서 레이커파일 및 레이커 설치공정을 나타내는 사시도.
도 1c는 선행기술문헌에 따른 지하옹벽을 제거하기 위한 상향식 순차제거 및 순차매립공법을 설명함에 있어서 토사되메움이 진행되어 더 이상 옹벽지지의 필요가 없게 된 하단측 레이커를 제거하는 한편 옹벽의 제거가 완료된 부분에 대해서는 그 옹벽을 지지하는데 사용되었던 레이커파일을 인발하는 개념을 도시한 단면도.
도 2a는 본 발명에 따른 지하건축물 신속 철거방법을 설명하기 위한 오래된 지하건축물을 개략적으로 보여주는 평면도.
도 2b는 본 발명에 따른 지하건축물 신속 철거방법을 설명하기 위한 오래된 지하건축물을 개략적으로 보여주는 종단면도.
도 3a 내지 도 3j는 본 발명에 따른 지하건축물 신속 철거방법을 나타내는 공정도.Figure 1a is a cross-sectional view showing the raker pile and raker installation process in explaining the bottom-up sequential removal and sequential reclamation method for removing underground retaining walls according to prior art literature.
Figure 1b is a perspective view showing the raker pile and raker installation process in explaining the bottom-up sequential removal and sequential reclamation method for removing underground retaining walls according to prior art literature.
Figure 1c illustrates the bottom-up sequential removal and sequential reclamation method to remove the underground retaining wall according to the prior art literature, removing the lower raker, which no longer needs retaining wall support due to soil backfilling, and removing the retaining wall. A cross-sectional view showing the concept of pulling out the raker piles that were used to support the retaining wall for the completed portion.
Figure 2a is a plan view schematically showing an old underground building to illustrate the method for rapid demolition of an underground building according to the present invention.
Figure 2b is a longitudinal cross-sectional view schematically showing an old underground building to explain the method for rapid demolition of an underground building according to the present invention.
Figures 3a to 3j are process diagrams showing a method for rapid demolition of an underground building according to the present invention.
본 발명에 따른 지하건축물 신속 철거방법의 바람직한 실시예를 도면을 참조하면서 설명하기로 하고, 그 실시예로는 다수 개가 존재할 수 있으며, 이러한 실시예를 통하여 본 발명의 목적, 특징 및 이점들을 더욱 잘 이해할 수 있게 된다.A preferred embodiment of the method for rapid demolition of an underground building according to the present invention will be described with reference to the drawings. There may be a plurality of embodiments, and through these embodiments, the purpose, features and advantages of the present invention can be better understood. become understandable.
도 2a는 본 발명에 따른 지하건축물 신속 철거방법을 설명하기 위한 오래된 지하건축물(50)을 개략적으로 보여주는 평면도이고, 도 2b는 본 발명에 따른 지하건축물 신속 철거방법을 설명하기 위한 오래된 지하건축물(50)을 개략적으로 부여주는 종단면도이다.Figure 2a is a plan view schematically showing an old underground building 50 for explaining the rapid demolition method of an underground building according to the present invention, and Figure 2b is a plan view schematically showing an old underground building 50 for explaining the rapid demolition method of an underground building according to the present invention. ) is a longitudinal cross-sectional view that schematically gives.
본 발명에 따른 지하건축물 신속 철거방법은 도 2a 및 도 2b에 도시된 바와 같이 토사벽체(B)에 등간격의 H-빔(H)과 더불어 CIP(Cast Injected concretPile; C)가 파일링됨과 동시에 지하지반(J) 위에 지하기초(51)가 마련되면서 지하벽체(52), 슬래브(53) 및 기둥(54)을 지닌 오래된 지하건축물(50)을 신속, 용이 및 안전하게 철거하여 토목업체에 인계할 수 있도록 한다.As shown in Figures 2a and 2b, the method for rapid demolition of an underground building according to the present invention involves piling H-beams (H) at equal intervals and CIP (Cast Injected Concret Pile; C) on the earthen wall (B) while simultaneously piling the underground building. As the underground foundation (51) is prepared on the ground (J), the old underground building (50) with the underground wall (52), slab (53), and pillar (54) can be quickly, easily and safely demolished and handed over to a civil engineering company. Let it happen.
도 3a 내지 도 3j는 본 발명에 따른 지하건축물 신속 철거방법을 나타내는 공정도이다.Figures 3a to 3j are process diagrams showing a method for rapid demolition of an underground building according to the present invention.
본 발명에 따른 지하건축물 신속 철거방법은 도 2a 내지 도 3j에 도시된 바와 같이 지하 각 층의 슬래브(53)에 쓰루홀(53a)을 뚫어 포스트파일(61)을 끼우면서 지하기초(51)에 지지되도록 함과 동시에 슬래브(53) 사이에 잭서포트(62)를 설치하는 제1공정과, 지하 2/10 높이 내지 4/10 높이에 이르기까지 내림순서로 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)의 철거와 함께 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 H-빔(H) 사이에 토류판(63)을 끼우고 띠장(64)을 두르면서 포스트파일(61)과 더불어 H-빔(H)을 잇는 버팀보(65)를 설치하는 제2공정과, 지하 2/10 높이 내지 4/10 높이에 이르러 토사벽체(B)를 피어싱하여 앵커링리버(70)를 끼움과 동시에 띠장(64)에 결합시키면서 앵커링리버(70)로 하여금 토사벽체(B)의 하향토압을 온전히 받아 띠장(64)과 함께하는 지지력으로 토사벽체(B)의 붕괴토압을 저지시키는 제3공정과, 지하 2/10 높이 내지 4/10 높이에서부터 지하기초(51)에 이르기까지 내림순서로 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)의 철거와 함께 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 H-빔(H) 사이에 토류판(63)을 끼우면서 기초철거공간(G)을 확보하는 제4공정과, 지하 2/10 높이 내지 4/10 높이에서부터 지하기초(51)에 이르기까지 확보된 기초철거공간(G)을 활용하여 지하기초(51)를 거침없이 철거하는 제5공정과, 지하 각 층의 올림순서로 지하지반(J)에서부터 토사되메우기(T) 및 다짐을 하면서 앵커링리버(70), 버팀보(65) 및 띠장(64)을 해체하는 제6공정과, 포스트파일(61) 및 H-빔(H)을 인발하는 제7공정을 포함한다.The method for rapid demolition of an underground building according to the present invention is to drill a through hole (53a) in the slab (53) of each underground floor and insert a post pile (61) into the basement foundation (51), as shown in FIGS. 2A to 3J. A first process of installing a jack support 62 between the slabs 53 to ensure support, and a slab 53, a column 54, in descending order from 2/10 to 4/10 of the underground height. Following the demolition of the basement wall (52), jack support (62), and CIP (C), the crushing and removal of the concrete stuck to the H-beam (H), and the earth plate (63) between neighboring H-beams (H). A second process of installing a brace (65) connecting the H-beam (H) along with the post pile (61) while wrapping a wale (64), and soil and sand at a height of 2/10 to 4/10 of the underground level. By piercing the wall (B), the anchoring river (70) is inserted and coupled to the wale (64), allowing the anchoring river (70) to completely receive the downward earth pressure of the earth wall (B) and use the support force with the wale (64) to move the soil. The third process of preventing the collapse earth pressure of the wall (B), and the slab (53), column (54), and basement wall ( 52), following the removal of the jack support (62) and CIP (C), crushing and removal of the concrete stuck to the H-beam (H), and inserting the earth plate (63) between the neighboring H-beams (H). The fourth process of securing the foundation demolition space (G), and the underground foundation (51) using the foundation demolition space (G) secured from 2/10th to 4/10th of the underground height to the underground foundation (51). The 5th process of demolition without hesitation, and the process of dismantling the anchoring river (70), brace (65), and wale (64) while backfilling and compacting soil from the basement (J) in the order of raising each underground floor. It includes a 6th process and a 7th process of drawing the post pile 61 and the H-beam (H).
더욱 구체적으로, 본 발명에 따른 지하건축물 신속 철거방법을 설명하면 다음과 같다.More specifically, the method for rapid demolition of an underground building according to the present invention is described as follows.
제1공정은 도 3a에 도시된 바와 같이 지하 각 층의 슬래브(53)에 쓰루홀(53a)을 뚫어 포스트파일(61)을 끼우면서 지하기초(51)에 지지되도록 함[지하기초(51)를 경유하여 지하지반(J)에 미 도시의 마이크로파일을 박은 후 포스트파일(61)을 이어지도록 할 수도 있음]과 동시에 슬래브(53) 사이에 구조계산의 설계에 따라 잭서포트(62)를 설치한다.As shown in Figure 3a, the first process involves drilling a through hole (53a) in the slab (53) of each underground floor and inserting a post pile (61) so that it is supported on the basement foundation (51) [Underground foundation (51) [It is also possible to connect the post piles (61) after driving the micropiles of the US city into the underground ground (J) via] and at the same time install the jack support (62) between the slabs (53) according to the design of the structural calculation. do.
제2공정은 도 3b 및 도 3c에 도시된 바와 같이 지하 2/10 높이 내지 4/10 높이에 이르기까지 내림순서로 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)의 철거와 함께 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 H-빔(H) 사이에 토류판(63)을 끼우고 띠장(64)을 두르면서 포스트파일(61)과 더불어 H-빔(H)을 잇는 버팀보(65)를 설치한다. As shown in Figures 3b and 3c, the second process includes the slab (53), column (54), basement wall (52), and jack support (62) in descending order from 2/10 to 4/10 of the underground height. ) and CIP (C) are demolished, and the concrete stuck to the H-beam (H) is crushed and taken out, followed by inserting an earthen plate (63) between neighboring H-beams (H) and wrapping a strip (64). In addition to the post pile (61), install the brace (65) connecting the H-beam (H).
지하 각 층의 내림순서로 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)를 철거할 경우 주변건물 및 주변도로가 점유하는 토압에 의해 토사벽체(B)가 쉽게 무너질 수 있으므로 지하건축물(50)의 철거 전에 미리 H-빔(H) 사이에 토류판(63)을 끼우고 띠장(64)을 두르면서 포스트파일(61)과 더불어 H-빔(H)을 버팀보(65)로 이어 안전을 도모토록 한다. 이때, 제2공정에서 지하 2/10 높이 내지 4/10 높이에 이르기까지의 공정은 후술되는 제3공정에서의 기초철거공간(G), 즉 지하기초(51)에서 구동되는 중장비의 작업높이[예를 들어 포크레인 등과 같은 중장비의 작업시 버팀보(65)에 부딪히지 않도록 하는 작업높이 - 지하 깊이가 깊을 경우 지하 2/10 높이만으로도 중장비의 작업높이가 확보될 수 있고 지하 깊이가 얕을 경우 지하 4/10 높이로서 중장비의 작업높이를 확보될 수 있도록 함]를 충분히 확보할 수 있는 지하 2/10 높이 내지 4/10 높이에 이르기까지의 공정에 해당될 수 있다. When demolishing the slab (53), column (54), basement wall (52), jack support (62), and CIP (C) in descending order of each underground floor, the earth wall is damaged by the earth pressure occupied by the surrounding buildings and surrounding roads. Since (B) can easily collapse, before demolition of the underground building (50), insert an earthen plate (63) between the H-beams (H) and wrap a strip (64) around the post pile (61) and the H-beam ( Connect H) with a brace (65) to ensure safety. At this time, the process from 2/10 to 4/10 of the underground height in the second process is the foundation demolition space (G) in the third process described later, that is, the working height of heavy equipment driven in the underground foundation 51 [ For example, the working height to prevent hitting the brace (65) when working with heavy equipment such as an excavator - if the underground depth is deep, the working height of heavy equipment can be secured with only 2/10 of the underground height, and if the underground depth is shallow, the working height of the heavy equipment can be secured by 4/10 underground. It can be applied to a process ranging from 2/10 height to 4/10 height underground, which can sufficiently secure the working height of heavy equipment (10 height).
나아가, 제2공정은 토류판(63) 및 토사벽체(B) 사이에 폐콘크리트(P)를 채워 주변건물과 주변도로에 의해 붕괴토압을 받고 있는 토사벽체(B)의 초기미동을 폐콘크리트(P)의 채움으로 지지할 수 있도록 하여 CIP(C)의 공백에 따른 토사벽체(B)의 밀림현상이나 무너짐현상을 미리서 제압할 수 있도록 한다.Furthermore, in the second process, waste concrete (P) is filled between the earth plate (63) and the earth wall (B) to prevent the initial slight movement of the earth wall (B), which is under collapsing earth pressure from surrounding buildings and surrounding roads, with waste concrete (P). ) so that it can be supported by filling, so that the pushing or collapsing phenomenon of the earthen wall (B) due to the gap in the CIP (C) can be suppressed in advance.
한편, 제2공정에서 지하 각 층의 내림순서로 슬래브(53), 기둥(54), 지하벽체(52) 및 CIP(C)의 철거와 함께 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출할 때 구동되는 중장비의 하부에 슬래브(53)의 급격한 크랙[중장비의 제자리 회전 등의 하중 및 압력에 따른 슬래브(53)의 급격한 파손에 의한 예기치 못한 무너짐 초래]을 방지토록 받침철판(80)을 더 위치시켜 중장비의 견고한 받침으로 더욱 안전한 철거작업을 가능케 한다.Meanwhile, in the second process, the slab (53), column (54), basement wall (52), and CIP (C) are demolished in descending order of each underground floor, and the concrete attached to the H-beam (H) is crushed and A support steel plate (80) is installed at the bottom of the driven heavy equipment to prevent sudden cracking of the slab (53) (causing unexpected collapse due to sudden damage to the slab (53) due to load and pressure such as rotation of heavy equipment in place). By positioning it further, safer demolition work is possible with a sturdy support for heavy equipment.
제3공정은 도 3d 및 도 3e에 도시된 바와 같이 지하 2/10 높이 내지 4/10 높이에 이르러 토사벽체(B)를 피어싱(Piercing)하여 앵커링리버(Anchoring Lebar; 70)를 끼움과 동시에 띠장(64)에 결합시키면서 앵커링리버(70)로 하여금 토사벽체(B)의 하향토압을 온전히 받아 띠장(64)과 함께하는 지지력으로 토사벽체(B)의 붕괴토압을 저지할 수 있도록 한다.As shown in Figures 3d and 3e, the third process pierces the earthen wall (B) at a height of 2/10 to 4/10 underground, inserts an anchoring lever (70), and simultaneously attaches a strip. While coupled to (64), the anchoring river (70) fully receives the downward earth pressure of the earthen wall (B) and prevents the collapse earth pressure of the earthen wall (B) with the supporting force of the wale (64).
예를 들어, 제2공정을 지하기초(51)에 이르기까지, 즉 지하 끝까지 실행할 경우 기초철거공간(G)의 미확보로 인하여 버팀보(65)의 낮은 높이에 따른 중장비의 운동범위가 극히 제한될 수밖에 없고[작업성이 현저히 떨어짐], 이에 반하여 중장비의 움직임을 보장하기 위하여 제2공정을 지하 2/10 높이 내지 4/10 높이에 이르기까지 수행한 후 더 이상 버팀보(65)를 설치하지 않을 경우 붕괴토압에 의해 토사벽체(B)가 순식간에 무너져 지하기초(51)의 철거시 큰 인명사고를 초래할 수밖에 없다.For example, if the second process is carried out up to the underground foundation (51), that is, to the end of the underground, the range of movement of heavy equipment due to the low height of the brace (65) will be extremely limited due to the unsecured foundation demolition space (G). There is no [workability is significantly reduced], and on the other hand, in order to ensure the movement of heavy equipment, if the second process is performed to 2/10 to 4/10 the height underground and the brace 65 is no longer installed, it will collapse. The earthen wall (B) collapses instantly due to earth pressure, which inevitably results in a serious casualty accident during the demolition of the underground foundation (51).
이에 따라, 본 발명에서는 지하기초(51)의 철거시 중장비의 원활한 운동범위를 보장함과 동시에 토사벽체(B)의 붕괴토압을 극복할 수 있도록 제3공정에서 지하 2/10 높이 내지 4/10 높이에 이르러 토사벽체(B)를 피어싱하면서 앵커링리버(70)를 끼움과 동시에 띠장(64)에 결합시킬 수 있도록 한 것이고, 바로 이 앵커링리버(70)로 하여금 토사벽체(B)의 하향토압을 온전히 받아 띠장(64)과 함께하는 지지력으로 토사벽체(B)의 붕괴토압을 저지토록 하여 대형사고를 미연에 방지케 한 것이다.Accordingly, in the present invention, in the third process, the height of 2/10 to 4/10 of the underground level is increased to ensure a smooth range of movement of heavy equipment when demolishing the underground foundation (51) and at the same time overcome the collapse earth pressure of the earthen wall (B). By piercing the earthen wall (B) when the height has been reached, the anchoring river (70) can be inserted and connected to the wale (64), and this anchoring river (70) can be used to maintain the downward earth pressure of the earthen wall (B). This is to prevent a major accident in advance by preventing the collapsing earth pressure of the earthen wall (B) with the support force provided by the wale (64).
이때, 앵커링리버(70)는 지지력확산판(70a)과 함께 띠장(64)에 고정되도록 하여 토사벽체(B)의 하향토압을 온전히 받으면서 하향되려는 힘을 지지력확산판(70a)으로 띠장(64)에 확산시켜 붕괴토압의 저지력을 더욱 극대화시킬 수 있도록 하고, 나아가 앵커링리버(70)는 토사벽체(B)를 향하여 하향 경사지게 박히도록 하여 토사벽체(B)의 하향토압을 붕괴토압의 저지력으로 전환시켜 인명피해를 미연에 방지토록 한다.At this time, the anchoring river 70 is fixed to the wale 64 together with the bearing force diffusion plate 70a so as to fully receive the downward earth pressure of the earthen wall (B) and direct the downward force to the wale 64 with the bearing force diffusion plate 70a. It is possible to further maximize the stopping power of the collapsing earth pressure by spreading it across the earth, and further, the anchoring river 70 is driven in a downward slope toward the earthen wall (B) to convert the downward earth pressure of the earthen wall (B) into the stopping power of the collapsing earth pressure. Prevent casualties in advance.
한편, 제3공정은 지하건축물(50) 주변에 상하수도관이나 통신케이블 또는 이웃하는 다른 건축물이 존재하여 앵커링리버(70)를 토사벽체(B)에 박을 수 없을 경우 도 3e에 도시된 바와 같이 지하건축물(50)의 코너에서 H-빔(H)을 사선방향으로 잇는 코너버팀보(65)를 더 설치하여 기초철거공간(G)의 확보와 더불어 토사벽체(B)의 붕괴토압을 동시에 해소할 수 있도록 한다.On the other hand, in the third process, when the anchoring river 70 cannot be driven into the earthen wall (B) due to the presence of water and sewage pipes, communication cables, or other neighboring buildings around the underground building 50, as shown in Figure 3e. By additionally installing a corner brace (65) connecting the H-beam (H) in a diagonal direction at the corner of the underground building (50), it is possible to secure the foundation demolition space (G) and simultaneously relieve the collapse earth pressure of the earthen wall (B). make it possible
더욱 구체적으로, 앵커링리버(70)는 토사벽체(B) 속으로 피어싱 주입되는 시멘트밀크(Cement Milk; 71)와 함께 경화되도록 하여 토사벽체(B)의 하향토압을 온전히 받을 수 있도록 하고, 나아가 앵커링리버(70)는 토사벽체(B) 속으로 끼워지는 3∼5개의 종형지지철근(72)들과, 이 종형지지철근(72)들을 등간격으로 고정시키는 횡형고정철근(73)들로 이루어질 수 있도록 하며, 더 나아가 종형지지철근(72)들 및 횡형고정철근(73)들을 감싸면서 시멘트밀크(71)를 수용하는 플렉시블튜브(74)를 포함토록 하여, 플렉시블튜브(74)로서 종형지지철근(72)들 및 횡형고정철근(73)들과 함께 시멘트밀크(71)를 신속 견고하게 밀집 경화시켜 견고한 지지력과 더불어 해체시의 용이함을 보장토록 한다.More specifically, the anchoring river 70 is hardened together with the cement milk (71) that is pierced and injected into the earthen wall (B) to fully receive the downward earth pressure of the earthen wall (B), and furthermore, anchoring The river 70 may be composed of 3 to 5 vertical support bars 72 inserted into the soil wall (B) and horizontal fixing bars 73 that fix the vertical support bars 72 at equal intervals. and further includes a flexible tube 74 that accommodates the cement milk 71 while surrounding the vertical support reinforcement bars 72 and the horizontal fixed reinforcement bars 73, so that the vertical support reinforcement bars (74) are formed as the flexible tube 74. 72) and the horizontal fixing bars 73, the cement milk 71 is quickly and firmly hardened to ensure solid support and ease of disassembly.
제4공정은 도 3f에 도시된 바와 같이 지하 2/10 높이 내지 4/10 높이에서부터 지하기초(51)에 이르기까지 내림순서로 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)의 철거와 함께 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 H-빔(H) 사이에 토류판(63)을 끼우면서 기초철거공간(G)을 확보토록 하여 지하기초(51)를 해체하기 위한 중장비의 원활한 운동범위를 충분히 보장한다.As shown in Figure 3f, the fourth process is a slab (53), a column (54), an underground wall (52), and a jack in descending order from the height of 2/10 to 4/10 of the underground level to the underground foundation (51). Following the demolition of the support (62) and CIP (C), the crushing and removal of the concrete stuck to the H-beam (H), the earth plate (63) is inserted between the neighboring H-beams (H), and the foundation demolition space ( G) is secured to ensure a sufficient range of smooth movement of heavy equipment to dismantle the underground foundation (51).
제5공정은 지하 2/10 높이 내지 4/10 높이에서부터 지하기초(51)에 이르기까지 확보된 기초철거공간(G)을 활용하여 지하기초(51)를 거침없이 철거토록 하여 안정성과 더불어 신속성을 더불어 보장케 하고, 이때 지하기초(51)의 철거시 포스트파일(61)을 지지할 수 있는 영역만 남겨두고 지하기초(51)를 철거토록 한다[다른 한편으로 미 도시의 마이크로파일이 지하지반(J)에 파일링되어 포스트파일(61)이 이어지도록 한 경우에는 마이크로파일만 남겨두고 지하기초(51) 모두를 철거토록 할 수 있음은 물론이다].The 5th process uses the foundation demolition space (G) secured from 2/10th to 4/10th of the underground height to the underground foundation (51) to demolish the underground foundation (51) without hesitation, ensuring stability and speed. In addition, it is guaranteed, and at this time, when the underground foundation (51) is demolished, the underground foundation (51) is demolished leaving only the area that can support the post pile (61). [On the other hand, the micropiles in American cities are underground ( Of course, if it is piled at J) and the post piles (61) are connected, all of the underground foundations (51) can be demolished, leaving only the micro piles].
제6공정은 도 3h 및 도 3i에 도시된 바와 같이 지하 각 층의 올림순서로 지하지반(J)에서부터 토사되메우기(T) 및 다짐을 하면서 앵커링리버(70), 버팀보(65) 및 띠장(64)을 해체하여 토사되메우기(T) 및 다짐에 의해 토사벽체(B)와의 토압의 균형을 실현한다.As shown in FIGS. 3h and 3i, the sixth process includes soil backfill (T) and compaction from the underground base (J) in the ascending order of each underground floor, while anchoring river 70, brace 65, and strip 64. ) is dismantled and the soil pressure is balanced with the soil wall (B) through soil backfill (T) and compaction.
제7공정은 도 3j에 도시된 바와 같이 포스트파일(61)[또는 미 도시의 마이크로파일과 함께하는 포스트파일(61)] 및 H-빔(H)을 인발하여 최종 토목업체에 안전하게 인계할 수 있도록 한다.In the 7th process, as shown in Figure 3j, the post pile 61 (or the post pile 61 with a micropile not shown) and the H-beam (H) are drawn so that they can be safely handed over to the final civil engineering company. do.
본 발명은 오래된 지하건축물을 신속, 용이 및 안전하게 철거하는 산업분야에 이용가능하다.The present invention can be used in the industrial field of demolishing old underground buildings quickly, easily, and safely.
B : 토사벽체 J: 지하지반
H : H-빔 C : CIP
50 : 지하건축물 51 : 지하기초
52 : 지하벽체 53 : 슬래브
53a : 쓰루홀 54 : 기둥
61 : 포스트파일 62 : 잭서포트
63 : 토류판 64 : 띠장
65 : 버팀보 66 : 코너버팀보
70 : 앵커링리버 70a : 지지력확산판
71 : 시멘트밀크 72 : 종형지지철근
73 : 횡형고정철근 74 : 플렉시블튜브
80 : 받침철판 G : 기초철거공간
T : 토사되메우기 P : 폐콘크리트B: Soil wall J: Basement ground
H: H-Beam C: CIP
50: Underground building 51: Underground foundation
52: Basement wall 53: Slab
53a: Through hole 54: Pillar
61: Post file 62: Jack support
63: Earth plate 64: Strip
65: brace 66: corner brace
70: Anchoring river 70a: Bearing force diffusion plate
71: Cement milk 72: Vertical support rebar
73: Horizontal fixed rebar 74: Flexible tube
80: Support steel plate G: Foundation demolition space
T: Soil backfill P: Waste concrete
Claims (8)
지하 각 층의 상기 슬래브(53)에 쓰루홀(53a)을 뚫어 포스트파일(61)을 끼우면서 상기 지하기초(51)에 지지되도록 함과 동시에 상기 슬래브(53) 사이에 잭서포트(62)를 설치하는 제1공정과,
지하 2/10 높이 내지 4/10 높이에 이르기까지 내림순서로 상기 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)의 철거와 함께 상기 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 상기 H-빔(H) 사이에 토류판(63)을 끼우고 띠장(64)을 두르면서 상기 포스트파일(61)과 더불어 상기 H-빔(H)을 잇는 버팀보(65)를 설치하는 제2공정과,
지하 2/10 높이 내지 4/10 높이에 이르러 상기 토사벽체(B)를 피어싱하여 앵커링리버(70)를 끼움과 동시에 상기 띠장(64)에 결합시키면서 상기 앵커링리버(70)로 하여금 상기 토사벽체(B)의 하향토압을 온전히 받아 상기 띠장(64)과 함께하는 지지력으로 상기 토사벽체(B)의 붕괴토압을 저지시키는 제3공정과,
지하 2/10 높이 내지 4/10 높이에서부터 상기 지하기초(51)에 이르기까지 내림순서로 상기 슬래브(53), 기둥(54), 지하벽체(52), 잭서포트(62) 및 CIP(C)의 철거와 함께 상기 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출에 이어 이웃하는 상기 H-빔(H) 사이에 토류판(63)을 끼우면서 기초철거공간(G)을 확보하는 제4공정과,
지하 2/10 높이 내지 4/10 높이에서부터 상기 지하기초(51)에 이르기까지 확보된 상기 기초철거공간(G)을 활용하여 상기 지하기초(51)를 철거하는 제5공정과,
지하 각 층의 올림순서로 상기 지하지반(J)에서부터 토사되메우기(T) 및 다짐을 하면서 상기 앵커링리버(70), 버팀보(65) 및 띠장(64)을 해체하는 제6공정과,
상기 포스트파일(61) 및 H-빔(H)을 인발하는 제7공정을 포함하는 것을 특징으로 하는 지하건축물 신속 철거방법.CIP (C) along with H-beams (H) at equal intervals are piled on the earthen wall (B), and at the same time, an underground foundation (51) is prepared on the underground ground (J), thereby forming the basement wall (52), slab (53) and In the method of quickly demolishing an underground building (50) having a pillar (54),
A through hole (53a) is drilled in the slab (53) of each underground floor, and a post pile (61) is inserted so that it is supported on the basement foundation (51) and a jack support (62) is provided between the slabs (53). The first process of installing,
With the demolition of the slab (53), column (54), basement wall (52), jack support (62) and CIP (C) in descending order from 2/10th to 4/10th of the height underground, the H- Following the crushing and removal of the concrete stuck to the beam (H), an earth plate (63) is inserted between the neighboring H-beams (H) and a band (64) is wrapped around the post pile (61) and the H- A second process of installing a brace (65) connecting the beam (H),
When reaching a height of 2/10 to 4/10 underground, the earthen wall (B) is pierced and the anchoring river 70 is inserted, and at the same time, the anchoring river 70 is connected to the wale 64 to pierce the earthen wall (B). A third process of completely receiving the downward earth pressure of B) and preventing the collapse earth pressure of the earthen wall (B) with the supporting force of the wale 64,
The slab (53), column (54), basement wall (52), jack support (62), and CIP (C) in descending order from 2/10th to 4/10th of the height underground to the basement foundation (51). Following the demolition of the H-beam (H), crushing and removal of the concrete stuck to the H-beam (H), an earth plate (63) is inserted between the neighboring H-beams (H) to secure the foundation demolition space (G). process,
A fifth process of demolishing the underground foundation (51) using the foundation demolition space (G) secured from a height of 2/10 to 4/10 underground to the underground foundation (51),
A sixth process of dismantling the anchoring river (70), braces (65), and strips (64) while backfilling (T) and compacting soil from the underground ground (J) in the ascending order of each underground floor,
A rapid demolition method for an underground building, comprising a seventh process of pulling out the post pile (61) and the H-beam (H).
상기 제3공정에서 상기 앵커링리버(70)는 지지력확산판(70a)과 함께 상기 띠장(64)에 고정되는 것을 특징으로 하는 지하건축물 신속 철거방법.According to paragraph 1,
In the third process, the anchoring river (70) is fixed to the wale (64) together with the bearing force diffusion plate (70a).
상기 제3공정에서 상기 앵커링리버(70)는 상기 토사벽체(B)를 향하여 하향 경사지게 박히는 것을 특징으로 하는 지하건축물 신속 철거방법.According to paragraph 1,
In the third process, the anchoring river (70) is driven in a downward slope toward the earthen wall (B).
상기 제3공정은 상기 지하건축물(50)의 코너에서 상기 H-빔(H)을 사선방향으로 잇는 코너버팀보(65)를 더 설치하는 것을 포함하는 것을 특징으로 하는 지하건축물 신속 철거방법.According to paragraph 1,
The third process is a method of rapidly demolishing an underground building, characterized in that it further includes installing a corner brace (65) connecting the H-beam (H) in a diagonal direction at a corner of the underground building (50).
상기 제3공정에서 상기 앵커링리버(70)는 상기 토사벽체(B) 속으로 피어싱 주입되는 시멘트밀크(71)와 함께 경화되는 것을 특징으로 하는 지하건축물 신속 철거방법.According to any one of claims 1 to 4,
In the third process, the anchoring river (70) is hardened together with the cement milk (71) that is pierced and injected into the earthen wall (B).
상기 제3공정에서 상기 앵커링리버(70)는 상기 토사벽체(B) 속으로 끼워지는 3∼5개의 종형지지철근(72)들과, 상기 종형지지철근(72)들을 등간격으로 고정시키는 횡형고정철근(73)들로 이루어지는 것을 특징으로 하는 지하건축물 신속 철거방법.According to clause 5,
In the third process, the anchoring river 70 is a horizontal fixer for fixing 3 to 5 vertical support bars 72 inserted into the earthen wall B, and the vertical support bars 72 at equal intervals. A method of rapid demolition of an underground building, characterized in that it consists of reinforcing bars (73).
상기 제3공정에서 상기 앵커링리버(70)는 상기 종형지지철근(72)들 및 횡형고정철근(73)들을 감싸면서 상기 시멘트밀크(71)를 수용하는 플렉시블튜브(74)를 더 포함하는 것을 특징으로 하는 지하건축물 신속 철거방법.According to clause 6,
In the third process, the anchoring river 70 further includes a flexible tube 74 that accommodates the cement milk 71 while surrounding the vertical support bars 72 and the horizontal fixing bars 73. A method of rapid demolition of underground buildings.
상기 제2공정은 지하 각 층의 내림순서로 상기 슬래브(53), 기둥(54), 지하벽체(52) 및 CIP(C)의 철거와 함께 상기 H-빔(H)에 달라붙은 콘크리트의 파쇄 및 반출할 때 구동되는 중장비의 하부에 상기 슬래브(53)의 급격한 크랙을 방지토록 받침철판(80)을 위치시키는 것을 더 포함하는 것을 특징으로 하는 지하건축물 신속 철거방법.
According to any one of claims 1 to 4,
The second process involves demolition of the slab 53, column 54, basement wall 52, and CIP (C) in descending order of each underground floor, and crushing of the concrete attached to the H-beam (H). And a method for rapid demolition of an underground building, further comprising positioning a support steel plate (80) at the bottom of the heavy equipment driven during unloading to prevent rapid cracking of the slab (53).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020220000435A KR102601694B1 (en) | 2022-01-03 | 2022-01-03 | Method for demolishing underground building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020220000435A KR102601694B1 (en) | 2022-01-03 | 2022-01-03 | Method for demolishing underground building |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20230105190A KR20230105190A (en) | 2023-07-11 |
KR102601694B1 true KR102601694B1 (en) | 2023-11-14 |
Family
ID=87159555
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020220000435A KR102601694B1 (en) | 2022-01-03 | 2022-01-03 | Method for demolishing underground building |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102601694B1 (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007070815A (en) | 2005-09-05 | 2007-03-22 | Takenaka Komuten Co Ltd | Rebuilding method of existing building |
JP2012107430A (en) | 2010-11-17 | 2012-06-07 | Shimizu Corp | Construction method of underground structure |
KR101410471B1 (en) | 2014-01-16 | 2014-06-23 | 주식회사 백산이앤티건설 | Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100736241B1 (en) | 2006-09-07 | 2007-07-06 | 주식회사 백산종합개발 | Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall |
-
2022
- 2022-01-03 KR KR1020220000435A patent/KR102601694B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007070815A (en) | 2005-09-05 | 2007-03-22 | Takenaka Komuten Co Ltd | Rebuilding method of existing building |
JP2012107430A (en) | 2010-11-17 | 2012-06-07 | Shimizu Corp | Construction method of underground structure |
KR101410471B1 (en) | 2014-01-16 | 2014-06-23 | 주식회사 백산이앤티건설 | Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building |
Also Published As
Publication number | Publication date |
---|---|
KR20230105190A (en) | 2023-07-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100866162B1 (en) | Chair-type self-supported earth retaining wall constructing method | |
KR100736241B1 (en) | Gradual Bottom-up Slice and Gradual Infilling Method for Removing Underground Retaining Wall | |
KR101410471B1 (en) | Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building | |
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
KR102400229B1 (en) | Method for demolishing underground building | |
KR101205783B1 (en) | The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously | |
KR100713787B1 (en) | The underground structure assembly and the underground structure building method which it uses | |
KR100794609B1 (en) | Construction method of underground structure using concrete filled pipe roof and concrete wall | |
KR100967497B1 (en) | Method for constructing an underground structure | |
JP2012107479A (en) | Method for constructing underground and aboveground structure | |
JP4013182B2 (en) | Self-supporting mountain retaining wall method and self-supporting mountain retaining wall | |
KR100877974B1 (en) | Reverse removing method of underground retaining wall using bottom-up cut and gradual land infilling with struts | |
KR20070076553A (en) | Construction method of underground structure using concrete filled pipe roof and concrete wall | |
WO2004033843A2 (en) | Subterranean structures and methods for constructing subterranean structures | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
JP7386095B2 (en) | Underground structure construction method | |
JP3002126B2 (en) | Temporary receiving method for structures | |
KR102601694B1 (en) | Method for demolishing underground building | |
CN111472363A (en) | Construction method of foundation pit enclosure structure located in underground space of existing building | |
JP3248458B2 (en) | Shoring construction underground construction method | |
KR102497458B1 (en) | Cip Retaining Reinforcing Structure and Method Constructing the Same | |
KR102021496B1 (en) | Retaining wall construction method and retaining wall structure by the method | |
KR101128955B1 (en) | The Construction Method of Pressing Underground Structure | |
KR100397958B1 (en) | The structure timbering of cut with separating wale and the construction method thereof | |
KR101256311B1 (en) | Structual deepening method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |