US20220243418A1 - Method for alternately constructing underground vertical members using top-down construction method - Google Patents

Method for alternately constructing underground vertical members using top-down construction method Download PDF

Info

Publication number
US20220243418A1
US20220243418A1 US17/623,168 US201917623168A US2022243418A1 US 20220243418 A1 US20220243418 A1 US 20220243418A1 US 201917623168 A US201917623168 A US 201917623168A US 2022243418 A1 US2022243418 A1 US 2022243418A1
Authority
US
United States
Prior art keywords
underground
level
construction
constructed
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
US17/623,168
Other languages
English (en)
Inventor
Kyeongok YANG
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of US20220243418A1 publication Critical patent/US20220243418A1/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Definitions

  • the present invention is provided to shorten a period of underground frame construction in top-down construction method, and more specifically, provides a construction method for alternately constructing underground vertical members downward to lower levels and then constructing remaining vertical members during the same time period after mat and foundation construction, thus making it possible to shorten a construction period of the vertical members and an overall construction period.
  • the top-down construction method is a construction method for shortening the construction period by constructing frames on the above-ground levels while forming the frames downward to the underground levels.
  • the general order of the top-down construction method for the underground level includes installing an earth retaining wall and pillars, excavating each level, and then constructing the last lowest foundation or mat while constructing a slab downward to have a depth of 4th to 7th underground levels.
  • the piles are constructed at an initial stage of construction, a core part of one underground level is constructed for the frame construction of the above-ground level (superstructure), and the remaining vertical members are constructed in order (from a lower level to an upper level) after placing the foundation or the mat.
  • the frame construction of the above-ground level is constructed during the same time period with the underground level, the number of levels that go up before the foundation and mat construction, and the number of levels that go up until the completion of the construction of the underground vertical members are structurally limited.
  • construction constraint conditions are given in which construction of the slab only up to the 8th level is allowed until the foundation and the mat are placed, construction of the slab only up to the 15th level is allowed until construction of the underground vertical members is completed, and construction of the roof level is allowed without restrictions after construction of the underground vertical members is completed.
  • the above-ground level frame has to be constructed only up to the 8th or 15th level, and then the construction stops and waits. Conversely, if the frame construction of the underground level is accelerated, the frame construction of the above-ground level will also be accelerated, so that the overall construction period is greatly affected by the underground level work.
  • the above-ground level frame it takes 6 to 7 days for one level to construct one reference level, so that more than four levels are constructed in one month, but for the construction of the underground level frame, it takes 1.5 or 2 months for one level, so that a construction speed of the underground level is relatively slow.
  • the conventional construction order of the underground construction includes constructing the earth retaining wall, the post, excavation of each level down, slab construction of each level, foundation or mat construction of the lowest level, and the construction of the underground vertical members upward in a sequence.
  • the underground vertical member has a feature that it proceeds in a sequence (construction from the lower level to the upper level) after the foundation or the mat is placed.
  • the construction period of the underground vertical members takes 20 to 25 days for one level, so that it takes 4 to 5 months for the six underground levels.
  • the underground vertical members are constructed in a sequence (down-top) after the foundation or the mat is placed. Since the above-ground level can continue to go up after the underground vertical members are completed, the underground vertical member is a critical path that determines the construction period.
  • the construction speed of the construction of the above-ground level frame is fast, with a cycle of 6 to 7 days for one level, while the number of levels that can go up to the time point of placing of the underground level mat (for example, the 8th above-ground level) and the number of levels that can go up to the completion time point (15th above-ground level) of the underground vertical member is limited. Therefore, construction stops and construction waiting occurs at an inflection point of the 8th and 15th above-ground levels.
  • the top-down construction method has an advantage of shortening the construction period by constructing the above-ground level while constructing the underground level.
  • the construction period is greatly affected by the construction of the underground level frame.
  • the present invention was created to solve the problems of the prior art as described above, and an object thereof is to shorten the construction period of the underground vertical members using a top-down construction method so that the above-ground level frame construction can be continuously carried out. Accordingly, the overall construction period is shortened.
  • a method for alternately constructing underground vertical members according to the present invention includes alternately constructing underground vertical members downward, and thereafter, constructing the remaining vertical members during the same time period by being distributed between the previously constructed vertical members.
  • the construction period is shortened by pre-constructing a number of underground vertical members on the overall process table and excluding them from the main process line (critical path) that determines the construction period.
  • a buckling length of the pillar is shortened, allowing more above-ground levels to be constructed, thereby shortening the overall construction period.
  • the remaining portions which are constructed upward can be constructed during the same time period, thereby shortening the overall construction period.
  • the underground vertical members can be constructed early after the construction of the corresponding level slab, there is less room for construction delay and thereby the overall construction period is not delayed.
  • the construction period can be further shortened by constructing only the reinforcing bar assembly first and placing concrete during the same time period.
  • the 6th underground level vertical member is constructed, and then the 5th underground level, the 4th underground level, the third underground level, and the second underground level are constructed in a sequence. Accordingly, in the prior art, it took a total of 125 days to construct 5 levels in a sequence in a case of 25 days per level. However, according to the present invention it takes only 25 days by constructing the 6th underground level, the 4th underground level, and the second underground level during the same time period which are the even-numbered levels after the mat is constructed because the odd-numbered levels have already been completed before the mat is placed. As a result, in the prior art, it took 125 days after the mat is placed, but according to the present invention, it takes 25 days, so that as a result, about 100 days are shortened.
  • the present invention exhibits an effect of shortening the construction period of about 3 months (about 8% of the total construction period) for 36 months compared to 39 months in an office building with 6 underground levels and 39 above-ground levels.
  • the reduction of the overall construction period in the office and officetel buildings, and the like reduces construction costs such as construction management costs and on-site expenses from the construction company side, and has a high economic effect that early sales, rental income, additional sales (25% of annual sales), and the like from the building owner's side.
  • FIG. 1 is an overall flow chart of a method for alternately constructing underground vertical members according to the present invention.
  • FIGS. 2 and 3 are examples of process tables of an office building of the 39th level in a method for alternately constructing underground vertical members according to the present invention.
  • FIG. 4 is an enlarged process table of an underground vertical member process of FIG. 2 according to the present invention.
  • FIG. 5 is an example of a process table of the latest start point of construction of the underground vertical members which are alternately constructed according to the present invention.
  • FIG. 6 is a comparison process table of the earliest start point and the latest start point of construction of the underground vertical members which are alternately constructed according to the present invention.
  • FIG. 7 is an overall flow chart of a method for constructing underground vertical members of a conventional construction method.
  • FIGS. 8 and 9 are examples of process tables of an office building of the 39th level to which the conventional construction method is applied.
  • FIG. 10 is an enlarged process table of the underground vertical member process of the conventional construction method of FIG. 8 .
  • FIG. 11 is a comparison process table in which the conventional construction method is compared with the process of the underground vertical members alternately constructed according to the present invention.
  • FIGS. 12 and 13 are comparison tables of a schedule difference in which the overall process table ( FIGS. 8 and 9 ) of the conventional construction method is compared with the overall process table ( FIGS. 2 and 3 ) of the underground vertical members alternately constructed according to the present invention.
  • FIG. 14 is a process comparison graph in which the overall process table of the conventional construction method ( FIGS. 8 and 9 ) is compared with the overall process table of the underground vertical members alternately constructed according to the present invention ( FIGS. 2 and 3 ) in an S-Curve form.
  • FIG. 1 is an overall flow chart of the method for alternately constructing underground vertical members using a top-down construction method according to an embodiment of the present invention.
  • a target project to be executed is an SRC office building with 6 underground levels and 39 above-ground levels.
  • the earth retaining wall is constructed in the underground level based on an outer wall of the underground level of the building, and a slurry wall, a CIP, an H-pile, an earth plate, and the like are constructed.
  • pillars of the building are constructed from the above ground to the foundation and the mat to support a slab of the underground level in the top-down construction method, and a PRD and a RCD are constructed.
  • the first level slab is completed by excavating the first underground level and placing a steel beam, a deck plate, and concrete using the pillars constructed in the step S 20 .
  • the second underground level is excavated and the first underground level slab is completed as in the first above-ground level.
  • the first underground level core parts are completed from the first underground level slab constructed in the step S 40 , and a core part frame can be constructed upward to the above-ground level.
  • the core parts and the pillars of the above-ground level are completed from the core parts and the pillars of the first underground level constructed in the step S 50 .
  • the frame can be constructed up to the 8th above-ground level before the mat construction under a structural condition of a PRD file
  • the frame in the construction step of the frame (primary) of the above-ground level, the frame is constructed up to the 8th above-ground level.
  • the second underground level slab construction step S 70 the second underground level slab is constructed after excavating the third underground level downward following the step S 40 .
  • the third underground level slab is constructed after excavating the 4th underground level downward following the step S 70 .
  • the third underground level core part is completed from the third underground level slab constructed in the step S 80 .
  • the construction can be done in a sequence, thereby making construction easy.
  • the third underground level core part is constructed in a sequence from the 6th underground level after the mat has been placed, but according to the present invention, the third underground level vertical member is first alternately constructed after the first underground level core part is constructed, and thereby the construction period is shortened.
  • the 4th underground level slab is constructed after excavating the 5th underground level downward following the step S 80 .
  • the 5th underground level slab is constructed after excavating the 6th underground level downward following the step S 100 .
  • the 5th underground level core part is completed from the 5th underground level slab is constructed in the step S 110 .
  • the construction can be done in a sequence.
  • the 5th underground level core part is constructed in a sequence from the 6th underground level after the mat has been placed, but according to the present invention, the 5th underground level vertical member is first alternately constructed after the third underground level core part is constructed, and thereby the construction period is shortened.
  • the third underground vertical member construction step S 90 and the 5th underground vertical member construction step S 120 are the method for alternately pre-constructing in a sequence before placing of the mat according to the features of the present invention, and thereby the construction period is shortened.
  • the foundation and the mat are constructed after the final excavation downward following the step S 110 .
  • the construction is turned again and the underground level vertical member and the above-ground level frame are constructed during the same time period.
  • the above-ground level frame can go up to the 8th above-ground level before the mat construction, the construction up to the 15th level can be performed until the construction of the underground level vertical members are completed, and the construction up to the roof level, which is the top level, is carried out after the underground level vertical members are completed.
  • the first underground level vertical member (S 50 ), the third underground level vertical member (S 90 ), and the 5th underground level vertical member (S 120 ) were alternately pre-constructed according to the present invention, so the remaining vertical members are in the 6th underground level, the 4th underground level, and the second underground level.
  • the remaining vertical members (6th underground level, 4th underground level, and second underground level) since the core part has already been constructed above and below the corresponding level, it has an advantage and a feature that the construction can be carried out at a time (S 150 , S 160 , and S 170 ).
  • the 5th underground level core part is constructed, and then the 4th underground level core part, the third underground level core part, and the second underground level core part has to be constructed in order.
  • the remaining vertical members (6th underground level, 4th underground level, and second underground level) can be constructed during the same time period, only one level construction period is required.
  • the core pars of two levels of the third underground level and the 5th underground level are first constructed, the mat is placed, and then the remaining vertical members (6th underground level, 4th underground level, and second underground level) are constructed during the same time period, so that an effect that the pre-construction of a total of 4 levels is carried out is provided. Therefore, in the prior art, in a case where it takes 25 days for the construction of the vertical member of one level, it takes 125 days, but according to the present invention, it takes 25 days, and thereby the total construction period of 100 days is reduced.
  • construction of the above-ground level frame (secondary) can be started.
  • the above-ground level frame (primary) can be constructed up to the 15th above-ground level until the underground level vertical members are completed, and after the underground level vertical members are completed, the above-ground level frames (secondary) (S 180 ) from the 16th above-ground level to the top above-ground level (roof) can be constructed without restrictions.
  • FIGS. 2 to 3 are an overall process tables of the method for alternately constructing underground vertical members using a top-down construction method in accordance with an embodiment of the present invention.
  • the present embodiment is carried out in an office building with 6 underground levels and 39 above-ground levels, and has an SRC structure, and using top-down construction method.
  • the construction start date is Jan. 1, 2019.
  • H-pile/CIP is constructed in the earth retaining wall construction stage (work No. 6 in the first column on the left of the process table), and the work period is 80 days.
  • PRD of work No. 7 is provided to construct a number of pillar posts in the underground level, and the construction period is 70 days.
  • Excavation of the first underground level and first level slab of work No. 8 are SRC construction in which the first level floor steel beams are constructed on posts, and the deck plate and concrete are placed when the PRD construction of work No. 7 is completed, and the construction period is 50 days.
  • Excavation of the second underground level and construction of the first underground level slab (work No. 9, hereinafter, indicated by only the number) are construction in which the second underground level is excavated downward when the first level slab (No. 8) is completed, and then the first underground level slab (No. 9) is constructed, and the construction period is 50 days.
  • the first underground level core part and the pillar (No. 22) are constructed so that the construction can proceed to the above-ground level.
  • the underground level downward construction and the above-ground level upward construction are simultaneously carried out, and this is generally referred to as top-down construction.
  • the construction of the 9th above-ground level (No. 32) can proceed only when the mat concrete (No. 15) is constructed, the construction is stopped for about 4 months after the construction of the 8th above-ground level (No. 31) is completed. According to a structural calculation, since the PRD can only support the load up to the 8th above-ground level (No. 31), the construction of the 9th above-ground level (No. 32) can be started after the mat is placed.
  • the construction of the above-ground levels from the second above-ground level can be started about 3 months late, and the waiting period of the construction between the 8th and 9th above-ground levels can be minimized to continuously construct or proceed slowly up to the 8th above-ground level.
  • the second underground level slab (No. 10) is constructed after the third underground level is excavated downward, and the construction period is 50 days.
  • the third underground level slab (No. 11) is constructed after the 4th underground level is excavated, and the construction period is 50 days.
  • the third underground level core part (No. 20) is first constructed according to the features of the present invention.
  • the third underground level core part (No. 20) is constructed upward from the 6th underground level after the mat (No. 15) is completed. Therefore, according to the present invention, the three underground level core part (No. 20) is constructed first compared to the existing construction method, and thereby the construction period is shortened.
  • the second underground level core part (No. 21) is skipped and the third underground level core part (No. 20) is alternately constructed.
  • the reason is that it is difficult to construct a connection part if the second underground level core part (No. 21), which is immediately below the first underground level, is constructed in the top-down construction method after the construction of the first underground level core part (No. 22). Therefore, if the third underground level core part (No. 20) is alternately constructed after the first underground level core part (No. 22) is constructed, since the second underground level, which is the upper level of the third underground level, is empty, the third underground level can be constructed in a sequence, so that the construction is easy.
  • the second underground level core part (No. 21) disposed between them can be constructed by sandwiching therebetween.
  • the 5th underground level slab (No. 13) is constructed after the 6th underground level is excavated, and the construction period is 50 days.
  • the 5th underground level core part (No. 18) is first constructed according to the features of the present invention.
  • the 5th underground level core part (No. 18) is constructed upward in order from the 6th underground level after the mat 15 is completed. Therefore, according to the present invention, the 5th underground level core part (No. 18) has the feature of being constructed first compared to the existing construction method, and thereby the overall construction period is shortened.
  • the 4th underground level core part (No. 19) is skipped and the 5th underground level core part (No. 18) is alternately constructed.
  • the reason is that the construction of the connection part is difficult to construct the 4th underground level core part (No. 19), which is immediately below the third underground level, using the top-down construction method after the third underground level core part (No. 20) is constructed. This is the same as the case of the third underground level core part (No. 20).
  • the mat excavation (No. 14) is carried out, and then the foundation and the mat (No. 15) are constructed.
  • the mat 15 supports the load that has been supported by the PRD, so that the above-ground level can go up to the 9th level (No. 32) or more.
  • the reason for limiting that the above-ground level can only go up to the 15th level until the completion of the underground vertical member after the construction of the mat (No. 15) is the buckling of the underground level PRD, and the PRD pillars from the 6th underground level to the second underground level are exposed for about 5 levels.
  • the PRD pillar is exposed for the height of only one level, so that there is little buckling restriction. Therefore, depending on the above-ground level construction method, a new effect of capable of constructing higher above-ground levels is exhibited.
  • the number of the remaining frames in the underground levels now is three, that is, the 6th underground level core part (No. 17), the 4th underground level core part (No. 19), and the second underground level core part (No. 21). Since the third underground level core part (No. 20) and the 5th underground level core part (No. 18) have been alternately completed in advance, the core parts of the remaining three levels may be constructed by sandwiching therebetween.
  • the remaining three levels can be worked simultaneously, at the same period, or in sequence.
  • the construction period of two levels is shortened by simultaneously constructing the underground level vertical members and pre-constructing the third underground level core part (No. 20) and the 5th underground level core part (No. 18) before the mat construction, and the core parts (Nos. 17, 19, and 21) of the remaining three levels are constructed at once after the mat (No. 15) is excavated to shorten the construction period of two levels, thereby having the effect of shortening the construction period of a total of four levels. Since the underground level core part is the main construction line (critical path), the total construction period is shortened.
  • the final work that is the finishing work
  • the final work is displayed along with the frame construction from the 5th above-ground level to the 39th above-ground level.
  • a process table is created in which the 9th above-ground level slab (No. 32) can be started after the mat is placed, and the 16th above-ground level slab (No. 39) is started after all of the underground vertical members are completed.
  • the finishing construction includes interior decoration construction, elevator construction, dismantling of temporary construction such as external curtain wall and tower crane, roof construction, landscaping construction, and the like after the roof frame is completed.
  • the total construction period of the office building with the 39 levels takes 1,106 days (about 36 months) as illustrated in the work No. 1 in FIG. 2 when applying the method for alternately constructing underground vertical members using a top-down construction method according to the present invention.
  • the total construction period is shortened by about 3 months compared to the existing construction method.
  • FIG. 4 is an enlarged process table of the underground vertical member process of FIG. 2 .
  • the construction of the odd-numbered underground level vertical members (the first underground level core part (No. 22), the third underground level core part (No. 20), and the 5th underground level core part (No. 18)) among the underground level vertical members are started after the corresponding level slabs are completed.
  • the construction of the remaining even-numbered vertical members (the 6th underground level core part (No. 17), the 4th underground level core part (No. 19), the second underground level core part (No. 21)) of 3 levels are carried out at the same period in parallel after the mat 15 is placed.
  • the remaining even-numbered level vertical members (Nos. 17, 19, and 21) have features that can be constructed during the same time period by sandwiching therebetween since the odd-numbered levels have already been alternately constructed.
  • FIG. 5 is an example of the process table of the latest start point of the underground vertical members that are alternately pre-constructed according to the present invention.
  • the latest start point refers to the work schedule that can be constructed the latest without affecting the subsequent process.
  • start (finish) time means a schedule that can be constructed the latest without affecting the subsequent process.
  • the first underground level core part (No. 22) is constructed after completion of the first underground level slab for the above-ground level construction (No. 25-).
  • the three underground level core part (No. 20) can be constructed the latest before the even-numbered underground vertical members (Nos. 17, 19, and 21) are constructed.
  • FIG. 6 is a comparison process table of the earliest start point and the latest start point of the underground vertical members which are alternately constructed according to the present invention.
  • FIG. 6 is provided for explaining the contents of the construction which is carried out at which date or time point in the process table because the construction order of the vertical members is determined.
  • work Nos. 16 to 21 indicate an early process ( FIG. 4 ), and work Nos. 23 to 28 indicate a late process ( FIG. 5 ).
  • the third underground level core part can be compared through the early work No. 20 and the late work No. 27.
  • the construction of the third underground level can be started quickly on Jan. 1, 2020, and can be started on May 15, 2020 in No. 27.
  • the construction thereof can be started at any time between Jan. 1 and May 15, 2020.
  • FIG. 7 is an overall flow chart of the underground vertical member construction method of the conventional construction method using the top-down construction method.
  • the PRD or RCD posts (T 20 ) are constructed underground in order to form frames using the top-down construction method. After that, the underground slabs are constructed downward while excavating the underground levels (T 30 to T 100 ). After excavating the 6th underground level (T 100 ), the foundation and the mat (T 110 ) are completed.
  • the underground vertical members (T 130 to T 170 ) are constructed upward in a sequence from the 6th underground level (T 130 ).
  • the above-ground frame (primary) (T 60 ) is constructed.
  • the construction up to the 8th above-ground level slab is carried out until the mat is placed.
  • the above-ground level frames (secondary) (T 180 ) from the 9th to 15th above-ground levels are constructed.
  • the underground vertical members (T 130 to T 170 ) are completed, it can be constructed without restrictions from the 16th above-ground level.
  • the order of the underground levels is long, and the underground construction period is long.
  • FIGS. 8 and 9 are overall process tables of the top-down construction method to which the conventional construction method is applied.
  • the building is an office building with 6 underground levels and 39 above-ground levels, and has an SRC structure, and using the existing reverse construction method of a top-down construction method.
  • the construction start date is Jan. 1, 2019.
  • the configuration of FIG. 8 is similar to that of FIG. 2 .
  • the reason for explaining the process table by applying the existing construction method is to examine a difference in the construction sequence and the total construction period with the construction method according to the present invention.
  • the earth retaining wall construction step (work No. 6 in the first column on the left of the process table) is H-pile/CIP work and the construction period is 80 days.
  • the PRD of work No. 7 is provided to construct a number of pillar posts in the underground levels, and the construction period is 70 days.
  • Excavation of the first underground level and the first level slab construction of Work No. 8 are SRC work that installs the first level steel beams on the posts and places the deck plate and concrete when PRD work of work No. 7 is completed, and the construction period is 50 days.
  • the core part and the pillar (No. 22) of the first underground level are constructed so that the construction can proceed to the above-ground levels. Therefore, the underground level downward construction and the above-ground level upward construction are simultaneously carried out, and this is generally referred to as a top-down construction.
  • the first underground level core part (No. 22) When the first underground level core part (No. 22) is completed, it can work continuously from the second above-ground level slab (No. 25) to the 8th above-ground level slab (No. 31). At this time, the load on the above-ground levels up to the 8th level is supported by the PRD.
  • the 9 level slab (No. 32) can be constructed only when the mat concrete (No. 15) has to be placed, the construction is stopped for about 4 months after the 8th above-ground level (No. 31) is completed. Since the PRD can only support the load up to the 8th above-ground level (No. 31), it is possible to undertake the 9th above-ground level (No. 32) after the mat is placed.
  • the second underground level slab (No. 10) is constructed after the third underground level is excavated downward, and the construction period is 50 days.
  • the third underground level slab (No. 11) is constructed after the 4th underground level is excavated, and the construction period is 50 days.
  • the 5th underground level slab (No. 13) is constructed after the 6th underground level is excavated, and the construction period is 50 days.
  • the foundation or mat (No. 15) is constructed after the mat (No. 14) is excavated.
  • the mat (No. 15) supports the load which has been supported by the PRD, so that the above-ground level can go up to the 9th level (No. 32) or more.
  • the underground vertical members (Nos. 17 to 21) are continuously and directly constructed from the 6th underground level core part (No. 17) to the second underground level core part (No. 21), and it takes 25 to 30 days per level.
  • the above-ground level can be constructed from the 9th level (No. 32) to the 15th level (No. 38).
  • the 10th to 39th above-ground levels and finishing construction are indicated.
  • the process table is created in which the construction of the 16th above-ground level slab (No. 39) is started when all the underground vertical members are completed. From the 16th level to the top level, the construction of the frames is carried out in a cycle of 6 days without any restrictions on the underground levels, and the general finishing construction is applied for one year.
  • the total construction period of the office building with the 39 levels takes 1,194 days (about 39 months) as illustrated in work No. 1 of FIG. 8 .
  • the total construction period of 39 months is longer by months than the total construction period of 36 months according to the present invention.
  • the reason is that it takes a lot of time to construct the underground vertical walls in a sequence from the 6th underground level to the second underground level.
  • FIG. 10 is an enlarged process table of the underground vertical member process of the conventional construction method of FIG. 8 . It illustrates that the underground vertical members are constructed in a sequence from work No. 17 to work No. 21 after the construction of the mat (No. 15), and the construction period is 130 days, that is, it takes about 4.3 months.
  • FIG. 11 is a comparison process table in which the process of the underground vertical members alternately constructed according to the present invention is compared with the conventional construction method.
  • work No. 1 to work No 19 are the process tables of the conventional construction method
  • work No. 20 to work No 38 are the process tables according to the present invention
  • work No. 39 is a difference in construction period between the conventional construction method and the construction method of the present invention.
  • the third underground level core part (No. 34) and the 5th underground level core part (No. 32) are previously constructed, and the remaining three level core parts (Nos. 31, 33, and 35) can be constructed by inserting each other simultaneously or at the same time point (at the same period) after the construction of the mat 29 .
  • the remaining even-numbered level core parts are constructed at once.
  • the conventional construction method requires construction of 5 times.
  • the effect of shortening 100 days of 4 levels with construction of only one time is exhibited
  • FIGS. 12 and 13 are comparison tables of a schedule difference in which the overall process tables ( FIGS. 8 and 9 ) of the conventional construction method are compared with the overall process tables ( FIGS. 2 and 3 ) of the underground vertical members alternately constructed according to the present invention.
  • the total construction period difference (work No. 1) in the two construction methods is 88 days of about 3 months, that is, it takes about 39 months in the conventional construction method and 36 months in the construction method of the present invention, and it can be seen that about 8% of the total construction period is shortened.
  • the underground excavation, the top-down slab, and mat construction (Nos. 6 to 15) are the same in the construction period in both construction methods.
  • the underground vertical members and according to the present invention, the underground vertical members (core parts) are alternately constructed downward, and the construction of the remaining core parts is carried out at the same time.
  • the last column (I) is a value obtained by subtracting the completion date for each level (column E) of the existing construction method from the completion date for each level (column H) according to the present invention.
  • FIG. 13 illustrates that the schedule difference (completion date difference column (I)) of 88 days continues from the 16th above-ground level (No. 39) until the completion of the construction.
  • FIG. 14 is a process comparison graph in which the overall process tables ( FIGS. 8 and 9 ) of the conventional construction method are compared with the overall process tables ( FIGS. 2 and 3 ) of the underground vertical members alternately constructed according to the present invention by indicating in an S-Curve form from FIGS. 12 and 13 which are arranged in tables.
  • a blue line indicates the existing construction method
  • a red line indicates the construction method of the present invention.
  • Construction is started on Jan. 1, 1999, and the 6th underground level mat is placed on Jun. 8, 2020 (lowest point in the graph).
  • the red line according to the present invention indicates that two levels are already alternately constructed, and three levels are constructed during the same time period in one month to complete the underground vertical members, and then lead to the 16th level.
  • the blue line according to the conventional construction method indicates that it takes about 4.3 months to construct the underground vertical member for each level after the mat construction, and then leads to the 16th level. From the 16th level and above, the two construction methods are the same.
  • the underground core parts are first constructed downwards on the first and third underground levels, and after the mat is completed, the 5th underground level is constructed, and then the 4th and second underground levels may be constructed during the same time period. Therefore, after the mat construction, the remaining core parts are constructed twice.
  • the underground core parts are first constructed downward on the first and third underground levels, and after the mat is completed, the 4th and second underground level core parts can be constructed during the same time period. It is the same concept as the construction of the 6 underground levels.
  • the lowest two levels for example, the 5th and 6th underground levels
  • the mat be completed, and then the 5th underground level slab be constructed.
  • the 5th underground level core part is constructed. Therefore, after the mat construction, the remaining core parts are constructed twice.
  • the remaining core parts are constructed twice in a sequence after the mat is completed. Therefore, according to one embodiment of the present invention, after alternately completing the core parts, there are many cases where the remaining core parts are completed at once, and in some construction, a case of constructing the remaining parts twice is derived.
  • the process table of the above embodiment is an example in which the date calculation is accurate because it is prepared by a program specializing in process table preparation.
  • the Kant chart which is a red bar chart in the process table, represents a major operation that determines the total construction period as a critical path of the major progress line.
  • the blue bar chart represents an operation with float in the number of temporal flexible dates. Therefore, in order to shorten the construction period, the red line, which is the main construction line, has to be shortened.
  • a connection line (relationship) including arrows connecting the bar charts in the process table indicates the preceding and subsequent relationship between works.
  • the construction sequence is as follows.
  • the remaining levels are 4 levels, and the 4 levels are placed by dividing into 1 time, 2 time, 3 time, and 4 time.
  • the followings are the sequence of the method for alternately constructing vertical members using a top-down construction method in a case of 7 underground levels according to an embodiment of the present invention.
  • the followings are the sequence of the method for alternately constructing vertical members using a top-down construction method in a case of 6 underground levels according to an embodiment of the present invention.
  • Construction of 3 levels one level by one level for total 3 times construction by dividing into 3 times.
  • the followings are the sequence of the method for alternately constructing vertical members using a top-down construction method in a case of 5 underground levels according to an embodiment of the present invention.
  • the followings are the sequence of the method for alternately constructing vertical members using a top-down construction method in a case of 4 underground levels according to an embodiment of the present invention.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
US17/623,168 2019-06-27 2019-06-27 Method for alternately constructing underground vertical members using top-down construction method Pending US20220243418A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/KR2019/007842 WO2020262735A1 (ko) 2019-06-27 2019-06-27 하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 공사방법

Publications (1)

Publication Number Publication Date
US20220243418A1 true US20220243418A1 (en) 2022-08-04

Family

ID=74060414

Family Applications (1)

Application Number Title Priority Date Filing Date
US17/623,168 Pending US20220243418A1 (en) 2019-06-27 2019-06-27 Method for alternately constructing underground vertical members using top-down construction method

Country Status (5)

Country Link
US (1) US20220243418A1 (zh)
JP (1) JP2022554045A (zh)
KR (1) KR20220024070A (zh)
CN (1) CN114008270A (zh)
WO (1) WO2020262735A1 (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982484B (zh) * 2021-03-04 2022-07-12 中国建筑第八工程局有限公司 地下地上结构半同步顺作施工方法

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05255943A (ja) * 1991-09-13 1993-10-05 Takenaka Komuten Co Ltd スライドダウン方式による地下躯体の構築工法
KR20090090742A (ko) * 2008-02-22 2009-08-26 삼성물산 주식회사 영구 스트럿을 이용한 상향식 지하구조물 구축공법
CN101736756B (zh) * 2009-12-04 2011-06-22 上海市第二建筑有限公司 软土地基逆作隔层施工方法
KR101267565B1 (ko) * 2012-02-13 2013-05-24 주식회사 한빛구조엔지니어링 지하 역타 시공시 코어부 구조물 시공 방법
KR101327785B1 (ko) * 2012-04-23 2013-11-11 대림산업 주식회사 건물의 코어부 역타시공방법
CN104234082A (zh) * 2014-08-29 2014-12-24 中国电建集团华东勘测设计研究院有限公司 深基坑跃层逆作施工方法
KR102320104B1 (ko) * 2017-12-20 2021-11-02 양경옥 하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 공사방법

Also Published As

Publication number Publication date
WO2020262735A1 (ko) 2020-12-30
CN114008270A (zh) 2022-02-01
JP2022554045A (ja) 2022-12-28
KR20220024070A (ko) 2022-03-03

Similar Documents

Publication Publication Date Title
KR102588684B1 (ko) 하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 시공 방법
US20220243418A1 (en) Method for alternately constructing underground vertical members using top-down construction method
JP6339923B2 (ja) 建築物躯体の構築方法
KR101267565B1 (ko) 지하 역타 시공시 코어부 구조물 시공 방법
CN106013450A (zh) 核心筒跳层施工方法
Abdelrazaq Design and construction planning of the Burj Khalifa, Dubai, UAE
JP2000273946A (ja) 鉄筋コンクリート構造物の組立て方法
JP2016199957A (ja) 先行床工法
JP6710064B2 (ja) 免震レトロフィットにおける建物の取り合い部分の施工方法と建物
KR20210000234A (ko) 하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 공사방법
KR100442548B1 (ko) 철근콘크리트구조와 철골철근콘크리트구조의 혼합구조를 갖는 건축구조물의 동시시공방법
JP3187618B2 (ja) 梁鉄筋の組み立て方法
US20240133175A1 (en) Top-down construction method for multi-storey basement with full steel structure
JP4005259B2 (ja) 柱および梁の構築方法
KR20240068954A (ko) 탑다운 역타공사에서의 지하 최하층에 예비말뚝 시공을 통한 지상층 연속 공사방법
JP2009180058A (ja) 立体駐車場の施工方法
JP3364426B2 (ja) 柱の構築方法
Undara et al. EXPLORATION OF AVAILABLE OFFSITE CONSTRUCTION METHODS IN INDIAN CITIES FOR COST AND TIME SAVINGS IN HOUSING CONSTRUCTION
JP4057169B2 (ja) 建築物の構築方法
RU2617813C2 (ru) Способ возведения сборного многоэтажного железобетонного каркаса здания с предварительным напряжением
JP2023108327A (ja) 地下構造部を有する建物の建て替え方法
JP2023016370A (ja) 構造物の施工方法
CN114263275A (zh) 高层装配式钢结构-核心筒同层施工工法
JPH03197734A (ja) 足場躯体の盛替えによるリフトアップ工法
JPH01121425A (ja) 多層建物の柱・梁仕口構造

Legal Events

Date Code Title Description
STPP Information on status: patent application and granting procedure in general

Free format text: DOCKETED NEW CASE - READY FOR EXAMINATION

STPP Information on status: patent application and granting procedure in general

Free format text: NON FINAL ACTION MAILED