Heat source or heat sink unit with thermal ground coupling Download PDFInfo
- Publication number
- US20050061472A1 US20050061472A1 US10/502,070 US50207004A US2005061472A1 US 20050061472 A1 US20050061472 A1 US 20050061472A1 US 50207004 A US50207004 A US 50207004A US 2005061472 A1 US2005061472 A1 US 2005061472A1
- Authority
- US
- United States
- Prior art keywords
- drive
- pipe
- ground
- probe
- probe shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24T—GEOTHERMAL COLLECTORS; GEOTHERMAL SYSTEMS
- F24T10/00—Geothermal collectors
- F24T10/10—Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground
- F24T10/13—Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground using tube assemblies suitable for insertion into boreholes in the ground, e.g. geothermal probes
- F24T10/15—Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground using tube assemblies suitable for insertion into boreholes in the ground, e.g. geothermal probes using bent tubes; using tubes assembled with connectors or with return headers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24T—GEOTHERMAL COLLECTORS; GEOTHERMAL SYSTEMS
- F24T10/00—Geothermal collectors
- F24T10/10—Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground
- F24T10/13—Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground using tube assemblies suitable for insertion into boreholes in the ground, e.g. geothermal probes
- F24T10/17—Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground using tube assemblies suitable for insertion into boreholes in the ground, e.g. geothermal probes using tubes closed at one end, i.e. return-type tubes
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/10—Geothermal energy
Definitions
- the present invention relates to a heat source or heat sink system with thermal ground coupling for near-surface recovery of thermal energy from the ground or for near-surface discharge of thermal energy into the ground, wherein the system comprises at least one ground probe arranged in the ground, wherein thermal energy can either be withdrawn from or discharged into the ground by means of a heat transfer fluid supplied through the ground probe, wherein each ground probe comprises a metallic probe shaft that is tight against the surrounding ground and consists of several drive-pipe segments driven into the ground, and wherein either an immersion pipe that is open at its lower end or a U-shaped pipe loop is arranged in the probe shaft for supplying or removing the heat transfer fluid.
- a first group of systems according to the known state-of-the-art is operated with an open circuit, wherein groundwater is collected from a groundwater conduit, is cooled or heated in a heat pump or another unit and is returned to the groundwater conduit.
- this heat recovery from or heat discharge into the groundwater is possible only if an appropriate groundwater conduit is available and if the quality of the groundwater is satisfactory.
- the collection and return of groundwater requires official approval which is granted only under specific conditions.
- panel collectors are already known, which are usually designed as horizontally arranged tube-register heat exchangers and are placed in the ground at a depth of approximately 1 m or slightly more. Such panel collectors require extensive earthworks, thus causing expensive installation; in addition, they can often not be used owing to local conditions.
- ground probes are known for the establishment of heat source systems. These known ground probes consist of a single or double pipe loop installed in a borehole that is drilled vertically into the ground. In general, the depth of the borehole is less than 100 m, but it may also exceed this value. Where sandy soil is concerned, the boreholes are usually drilled according to flush drilling method. In solid ground, use is mostly made of what is called the airlift drilling method with an in-hole hammer. This drilling method requires provision of a two-stage air compressor with a working pressure ranging up to 24 bar and an operating energy input of 200 kW and higher. Where unconsolidated rock is concerned, a protective piping is used for drilling, said protective piping being, in practice, for example typically 152 mm in diameter.
- a typical diameter of, for example, 128 mm is used for continuing the drilling process until the particular final depth required is reached.
- the pipe loop assembly must be inserted in the finished ground borehole. Thereafter, the remaining space between the pipe loop and the walls of the ground borehole must be progressively filled with filling material from bottom to top, said filling material in practice mostly being bentonite, i.e. a cement-clay mixture. This ensures that water-bearing layers are reliably and permanently sealed against each other and that the thermal contact required between the pipe loop and the ground is ensured. It is also obvious that the establishment of such a system is very complicated and, thus, expensive.
- the cutting of threads, the welding or the soldering are to disadvantage in that all of these processes result in local changes in the structure and hardness of the material of the probe shaft segments and, thus, in potential weak spots which may, sooner or later, be the starting point of cracks or breakages.
- the present invention aims at creating a system of the aforementioned type which obviates the drawbacks disclosed and which can, in particular, be established in an economical manner, which is particularly safe with regard to potential environmental impairments, which has a long service life, and which has a first-rate efficiency.
- each drive-pipe segment is made of ductile cast iron
- the drive-pipe segments are formed such that they can be fitted into each other at their ends
- each drive-pipe segment comprises a tapered outer perimeter at one of its ends and, at its other end, a sleeve provided with a stop shoulder and having a mating tapered inner perimeter, wherein their diameters and taper angles are dimensioned such that the drive-pipe segments, on being driven in, can be connected to each other in a force-closed and tight manner.
- each drive-pipe segment is formed of ductile cast iron.
- ductile cast iron differs from traditional gray cast iron in that the graphite is contained in ductile cast iron in the form of nodular graphite, so that the mechanical properties are changing; in particular, the strength and tenacity are increased.
- the chemical properties of ductile cast iron are also improved, in particular the corrosion resistance against pitting.
- the drive-pipe segments can, for example, be produced according to the centrifugal casting method, wherein it is practically possible to use 100-percent recycling material, i.e. steel scrap, this being both to economical and ecological advantage.
- the drive-pipe segments of ductile cast iron have such a mechanical resistance that they can be driven into the ground with considerable impact forces without suffering any damage.
- the invention provides that the drive-pipe segments are designed such that they can be fitted into each other at their ends. Large-scale screwed, soldered or welded connections which can be established and tested on the construction site only under the greatest difficulties are not required between the successive drive-pipe segments. This also facilitates the mechanical treatment of the ends of the drive-pipe segments during their production and also reduces the amount of work and the risk of faults on the construction site at the place where the drive-pipe segments are driven into the ground.
- each drive-pipe segment comprises a tapered outer perimeter at one of its ends and, at its other end, a sleeve having a mating tapered inner perimeter, wherein their taper angles are dimensioned such that the drive-pipe segments, solely by being driven in, can be connected to each other in a force-closed and tight manner.
- This embodiment of the drive-pipe segments ensures that the desired tightness and force-closed connection of the various drive-pipe segments to each other is obtained solely by the drive-in process. Special sealants are not required.
- Each sleeve is provided with a shoulder and, as regards the fitted part of the respectively other segment, is designed such that, after the sleeve has been expanded by a defined amount, the fitted segment comes to rest on this shoulder and then transfers the drive pulses, therein preventing the sleeve from being subjected to the stress of a further expansion to an impermissible extent. If the pulses or drive blows for driving in the drive-pipe segments are sufficiently strong, a friction weld ensuring the desired tightness and force-locking connection for very long operating times of the probe shaft is obtained in the region where two drive-pipe segments are connected to each other. Since it is not necessary to ensure that the individual drive-pipe segments are, at a later point, disconnected from each other without being destroyed, this non-detachable friction-welded connection is not of any technical disadvantage whatsoever.
- the probe shafts each comprise several drive-pipe segments driven into the ground, a particularly economical establishment of the system is ensured.
- This high economical efficiency is, in particular, achieved because the time and technical expenditures required for driving in the drive-pipe segments in order to form the probe shaft by means of appropriate devices, particularly by means of a commercially available hydraulic hammer, are less than those required for establishing a ground borehole; this applies, in particular, to energy expenditures which are reduced by at least 80 percent.
- the drive-pipe segments are designed such that, when being driven into the ground, they can absorb the impact forces developing without suffering any damage.
- the probe shaft is to advantage in that it is tight against the surrounding ground solely by being driven in, so that the heat transfer fluid is practically prevented from being flowing out of the probe shaft and into the ground, and this the more so since the drive-pipe segments forming the probe shaft have relatively thick walls because of the mechanical stability required. Therein, the tightness is maintained according to the life expectancy of the probe shafts, even over long periods of many decades.
- the system according to the invention permits to achieve a high efficiency because each probe shaft, after having been driven into the ground, is in a firm and close contact with the surrounding ground without special filling or contact materials having to be placed into the region of the outer perimeter of the probe shaft. This ensures a first-rate heat transfer from the ground into the probe shaft and vice versa, without particular measures being necessary. Since the probe shaft itself is metallic, its thermal conductivity is very high so that the resistance to the heat conduction out of the ground and into the heat transfer fluid flowing in the inner region of the probe shaft and vice versa is, altogether, very low.
- the system can be used both as a heat source for heating purposes and as a heat sink for cooling purposes.
- the system can, for cooling purposes, be used either at the natural temperature level or with interconnection of a reversely operated heat pump, i.e. a refrigeration unit. If a reversible heat pump is used, it is even possible to optionally and alternately select the heating or cooling mode. This application is to particular advantage, especially in southern hot climates of the earth or in regions with typical continental climate.
- the invention preferably proposes that the tapered outer perimeter of each drive-pipe segment is provided at the latter's forward end and that the sleeve with the stop shoulder of each drive-pipe segment is provided at the latter's backward end. This embodiment permits to achieve as low a motional resistance of the drive-pipe segments as possible when they are driven into the ground.
- a further contribution to a high economical efficiency is obtained by the fact that only an immersion pipe that is open at its lower end is required for supplying and removing the heat transfer fluid, wherein, preferably, the outer diameter of the immersion pipe is, furthermore, smaller than the inner diameter of the probe shaft and the length is slightly smaller than the length of the probe shaft.
- the second half of the flow path of the heat transfer fluid then extends through that part of the interior region of the probe shaft that is not occupied by the immersion pipe.
- a U-shaped pipe loop is arranged in the probe shaft in the stead of the immersion pipe for supplying and removing the heat transfer fluid, wherein it is, furthermore, preferably provided that the length of said pipe loop extending up to the latter's U-bend is slightly smaller than the length of the probe shaft and that the part of the interior region of the probe shaft that is not occupied by the pipe loop is filled with a thermally conductive filling material.
- This embodiment of the system according to the invention provides the advantage of a particularly high protection against an ingress of the heat transfer fluid into the ground in the environment of the probe shaft since, here, both the pipe loop and the probe shaft must become leaky before the heat transfer fluid can penetrate into the ground.
- this increased safety results in a slightly lower efficiency because, here, the resistances to the heat conduction from the ground into the heat transfer fluid and vice versa are, altogether, slightly higher.
- the first advancing drive-pipe segment of the probe shaft is, at its forward end, appropriately provided with or tightly connected to a probe tip. If the probe tip is tightly connected to the drive-pipe segment, this connection is appropriately established in the manner described above by tapered connection regions and their being friction-welded by drive impacts.
- the last drive-pipe segment of the probe shaft is, at its backward end, tightly connected to a connection cover attached after completion of the drive-in procedure, with an inflow line connection and a return flow line connection for the heat transfer fluid being arranged on said connection cover.
- the connection cover provides the necessary connections for the inflow and the return flow of the heat transfer fluid. Since it is to be placed subsequently, the cover does not disturb when the drive-pipe segments are driven in. Since, as a result, the cover does not have to absorb any drive forces, it can be of a light-weight design, and the usual connection methods are appropriate for attaching the cover to the last drive-pipe segment and for sealing the cover.
- the immersion pipe or the pipe loop is mounted only to or in the connection cover further contributes to advantageously low production efforts. Expensive and only difficultly accessible mounting means in the course of the probe shaft itself are not necessary here. Whether the immersion pipe or the pipe loop is exactly centered while extending through the probe shaft or whether it approaches the walls of the probe shaft to a higher or lesser degree is not of any noticeable importance either. Since the immersion pipe or the pipe loop is mounted to or in the connection cover, it is not yet positioned in the drive-pipe segments when these are driven in, so that neither the immersion pipe nor the pipe loop is disturbing or can be damaged in this step either. The immersion pipe or the pipe loop is inserted in the probe shaft only after the latter has been driven into the ground over the complete length provided.
- the immersion pipe or the pipe loop comprises an air vent or a vent valve at its upper end.
- the air vent or vent valve permits air to exit out of the immersion pipe or the pipe loop at the uppermost point of the probe shaft and to be removed with the returning heat transfer fluid. Thereafter, the air is, appropriately, finally separated in the known manner by means of an automatic ventilation device in the highest part of the system.
- the immersion pipe or the pipe loop consists of plastic material, preferably of polyethylene (PE) or polypropylene (PP).
- PE polyethylene
- PP polypropylene
- the material itself allows to achieve a first-rate thermal insulation value which keeps any undesired heat exchange between the inflowing and the returning heat transfer fluid inside the probe shaft at a very low level.
- the immersion pipe is also relatively light so that it practically does not cause any tensile forces to the connection cover in connection with its buoyant lift in the heat transfer fluid.
- the immersion pipe can be provided with an additional insulation, for example in the form of a mounted corrugated plastic pipe, wherein the intermediate space between the immersion pipe and the corrugated pipe is, appropriately, also filled with the fluid.
- the probe shaft is driven into the ground either in vertical direction or in an inclined direction preferably extending at an angle ranging from 15 to 75 degrees in relation to the vertical direction.
- the particular drive-in direction depends on local conditions. If the surface area available is adequate, an inclined drive-in direction should be preferred because this permits to achieve a greater heat collection area on the surface of the earth. In this manner, the amount of thermal energy required, for example for heating a residential building, can be obtained from the ground with a lesser number of probe shafts.
- the present invention relates, among others, to a system for near-surface recovery of geothermal energy, wherein this geothermal energy is generated by incoming solar radiation.
- the probe shaft extends at an inclined angle in relation to the vertical direction because, in this case, the area of the collection of the ground probe that is projected on the surface of the earth becomes greater than when the probe shaft only extends in vertical direction.
- An inclined course of the probe shaft or of an arrangement of probe shafts can be achieved by means of the drive-in method without any problems and, in particular, much more easier than the drilling of inclined boreholes, in particular if the angle in relation to the vertical direction is relatively large, for example more than 45 degrees.
- the probe shaft is driven into a borehole that has been predrilled into the ground, with the maximum depth of the borehole being as great as the length of the probe shaft and with the diameter of the borehole being smaller than the outer diameter of the probe shaft, this ensuring that the first-rate heat conduction contact between the ground and the probe shaft is achieved here as well.
- driving-in is facilitated to an essential degree.
- each drive-pipe segment ranges from 10 to 20 percent of the outer diameter of the drive-pipe segment.
- the walls of the drive-pipe segments are very thick in relation to their diameter; but, owing to the high thermal conductivity of the metal used to make the drive-pipe segments, this is not to disadvantage to the heat transfer from the ground into the heat transfer fluid in the inner region of the probe shaft or vice versa.
- each drive-pipe segment comprises an outer diameter approximately ranging from 80 to 200 mm and a wall thickness approximately ranging from 7 to 12 mm. If having the dimensions specified, the drive-pipe segments can still be driven into the ground with relatively low efforts and, thus, with accordingly relatively light-weight machines, so that such drive-pipe segments can be driven into the ground without any problems, even in built-up areas, without causing any risk to buildings in the environment.
- each drive-pipe segment approximately ranges from 4 to 6 m and is preferably 5 m, and that the total length of the probe shaft approximately ranges from 10 to 50 m and even more if this is permitted by actual ground conditions. If having these dimensions, the individual drive-pipe segments can still be handled by two workers and the current handling devices, this facilitating the work on site at the place where the drive-pipe segments are to be driven into the ground. Only two persons, that is an operator for an excavator with a hydraulic hammer and a person to hand over the pipe segments and to assist in fitting the particular new pipe segment, are required as personnel.
- the preferred total length of the probe shaft is as specified, it can, in practice, be expected in most of the cases that the drive-pipe segments of the probe shaft can still be driven in without any problems and at a relatively high drive speed.
- driving-in of the drive-pipe segments is usually facilitated by the drive-pipe segments being inserted in the ground not vertically, but at an inclined angle.
- the preferable heat transfer fluid is pure water, in particular without any antifreeze additive and in particular under a pressure of an order of approximately 10 bar. As a matter of principle, this excludes all groundwater and other environmental hazards; that is the reason why it is much easier to obtain official approvals and why these may even not be applicable at all.
- the heat transfer fluid may also be carbon dioxide, in particular under a pressure of an order of approximately 100 bar and more.
- the heat transfer fluid may also be carbon dioxide, in particular under a pressure of an order of approximately 100 bar and more.
- an appropriately pressure-tight cover can, without any difficulties, be provided at, in particular welded to, the upper end of the probe shafts. It is also possible to optimize the “heat-pipe” method by selecting a favorable drive angle of the probe shaft and to distinctly improve said method as compared with the presently usual vertical boreholes.
- the ductile cast iron preferably used to make the drive-pipe segments is corrosion-resistant to an essentially higher degree than the usual gray cast iron.
- each drive-pipe segment can, in addition, be provided with an anticorrosive layer on its external and/or internal surface. If saline water is present in the ground, for example near coasts, the probe shaft can be effectively protected against corrosion by means of an impressed current anode.
- the anticorrosion layer can, for example, be formed by galvanizing or by a plastic coating, preferably of polyurethane (PU), wherein the material used should be oxygen-diffusion-tight.
- PU polyurethane
- a further contribution to avoiding corrosion damages consists in using pipes for the piping of the remaining system and for its connection with a heating or cooling device, which are oxygen-diffusion-tight. By this, an introduction of oxygen into the heat transfer fluid, which might promote corrosion of the drive-pipe segments, is prevented.
- FIG. 1 is a schematic vertical sectional view of a heat recovery system with a single probe shaft in a condition where it is driven into the ground in vertical direction;
- FIG. 2 is a longitudinal sectional view of a section of a modified probe shaft
- FIG. 3 is a schematic vertical sectional view of a heat recovery system with two probe shafts driven into the ground at an inclined angle.
- the ground probe 1 consists of a probe shaft 2 that is composed of several drive-pipe segments 20 .
- the required number of drive-pipe segments 20 are initially driven successively into the ground 3 in a relatively small building pit 30 that has been prepared beforehand, for example by means of a hydraulic hammer mounted to an excavator arm or a carriage.
- the drive-pipe segment 20 that is the bottommost in the drawing is provided with a probe tip 23 in order to ensure that said drive-pipe segments 20 can be driven into the ground 3 with as low a resistance as possible and as easily and quickly as possible.
- the probe tip 23 is tightly connected to the forward end 21 of the lower drive-pipe segment 20 .
- a second drive-pipe segment 20 is fitted; thereafter, the first and second drive-pipe segments 20 are further driven into the ground 3 together.
- each drive-pipe segment 20 is provided with a tapered outer perimeter 21 ′.
- the backward end of each drive-pipe segment 20 and the rear side of the probe tip 23 are each provided with a sleeve 22 with a mating tapered inner perimeter 22 ′ or 23 ′.
- the taper angles of the outer perimeter 21 ′ and the inner perimeter 22 ′ or 23 ′ are selected and coordinated with each other such that the desired force-closed and tight connection is achieved solely by the drive blows or drive pulses executed while the drive-pipe segments 20 are driven in, wherein these occurring blows or pulses generate a friction-welded connection in the connection area.
- each sleeve 22 is provided with a shoulder 22 ′′ or 23 ′′ and, in connection with the fitted forward end 21 of the particular other segment 20 , is designed such that the fitted end 21 of the segment 20 comes to rest on this shoulder 22 ′′ or 23 ′′ after the sleeve 22 has been expanded by a defined amount and will then transfer the drive pulses without subjecting the sleeve 22 to stress in expansion direction to an impermissible extent.
- the drive-pipe segments 20 and the probe tip 23 are formed of ductile cast iron which has a particularly high strength and tenacity so that it can absorb the drive blows without suffering any damage and facilitates the desired friction-welded connection in the connection areas of the drive-pipe segments 20 when the latter are driven in.
- a connection cover 24 is placed onto the upper end of the upper drive-pipe segment 20 in a sealing manner and is secured with at least one locking screw 24 ′.
- the connection cover 24 comprises one inflow line connection 25 and one return flow line connection 27 for a heat transfer fluid.
- the heat transfer fluid is water to which an antifreeze agent, usually alcohol, is added as required.
- An immersion pipe 26 that is only mounted to the connection cover 24 and is, otherwise, extending freely through the hollow inner region 28 of the probe shaft 2 is connected to the inflow line connection 25 . Therein, the length of this immersion pipe 26 is only slightly smaller than the length of the probe shaft 2 .
- cold heat transfer fluid flows through the inflow line connection 25 into and through the immersion pipe 26 , until it reaches the lower end region of the probe shaft 2 .
- the heat transfer fluid exits out of the immersion pipe 26 and is now flowing from bottom to top through that part of the interior region 28 of the probe shaft 2 that is not occupied by the immersion pipe 26 .
- the heat transfer fluid absorbs thermal energy from the surrounding ground 3 , wherein the heat transfer fluid is heated as compared with its original temperature.
- the heated heat transfer fluid exits the probe shaft 2 through the return flow line connection 27 provided at the side of the connection cover 24 .
- the return flow line connected to the connection 27 is usually running to a heat pump in which the geothermal energy contained and transported in the heat transfer fluid is withdrawn and is utilized for heating purposes, for example for building or water heating purposes.
- the heat transfer fluid which exits the heat pump and whose temperature is now reduced is then supplied back to the inflow line connection 25 and through the immersion pipe 26 into the inner region 28 of the probe shaft 2 .
- this system represents a closed heat-transfer-fluid circuit.
- the heat transfer fluid will, in this case, be able to absorb a relatively great amount of thermal energy from the ground while it is dwelling in the probe shaft 2 , thus being subjected to a relatively great increase in temperature, this being favorable for the efficiency of the heat pump.
- the high fluid content of the ground probe which can, for example, be approximately 10 I/m in practice, becomes positively apparent. This results in typical times for a complete recirculation of the heat transfer fluid approximately ranging from 30 to 60 minutes.
- the probe shaft 2 Owing to its relatively great material thickness which it requires for being driven into the ground 3 , the probe shaft 2 is absolutely tight over very long operating times ranging up to many decades, so that any exit of the heat transfer fluid out of the probe shaft 2 and into the ground 3 is practically excluded. After having been driven into the ground 3 , the probe shaft 2 is closely embedded in said ground 3 so that, in connection with the first-rate thermal conductivity of the metallic wall of the probe shaft 2 , a high efficiency is achieved on heat transfer from the ground 3 into the heat transfer fluid in the hollow inner region 28 of the probe shaft 2 and vice versa.
- the inflow and return flow lines for the heat transfer fluid are also arranged in the ground 3 , wherein an arrangement below the frost limit, e.g. at a depth of approximately 1 m or deeper if necessary, is to reasonable advantage.
- a pipe loop 29 that is positioned in the probe shaft 2 in U-shaped form can alternatively be used for routing the heat transfer fluid.
- the U-bend 29 ′ is, appropriately, positioned near the lower end of the probe shaft 2 .
- the heat transfer fluid remains enclosed in the pipe loop 29 along its entire path through the pipe shaft 2 , being prevented from coming into an immediate contact with the probe shaft 2 .
- that part of the interior region 28 of the probe that is arranged around the pipe loop 29 is, therefore, filled with a thermally conducting filling material, for example water, which is then an essentially still fluid.
- a heat recovery system can comprise one or more probe shafts 2 . If several probe shafts 2 or ground probes 1 are used, as is schematically represented in FIG. 3 , said shafts or probes can be advantageously connected in series because of their low hydraulic resistance, wherein the length of the individual probe shafts 2 can be selected as desired. As a result, installation becomes markedly less expensive and a hydraulic calibration, which is always associated with energy losses, is not applicable. If necessary, however, it is, of course, also possible to connect a greater number of probe shafts 2 in parallel to each other or in a mixed arrangement.
- the several ground probes 1 are spaced apart from each other depending on the collection area of each individual ground probe 1 , wherein the size of the collection area depends on the thermal conductivity of the ground 3 in the particular case. It is also possible to drive the probe shafts 2 into the ground 3 at an inclined angle, as shown in FIG. 3 , instead of vertically as shown in FIG. 1 of the drawing. This is to advantage in many application cases because, in this case, a larger collection area for the thermal energy irradiated by the sun across the surface of the earth and into the ground 3 can be achieved per probe shaft 2 . With the direction of the probe increasingly deviating from the vertical direction, this will then allow an increasingly smaller probe spacing. With a specified amount of energy required, the upper ends of the probes 2 can then be arranged on a smaller total area, this saving space and installation cost.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Earth Drilling (AREA)
- Geophysics And Detection Of Objects (AREA)
- Investigating Or Analyzing Materials By The Use Of Magnetic Means (AREA)
- Water Treatment By Sorption (AREA)
- Electrical Discharge Machining, Electrochemical Machining, And Combined Machining (AREA)
- Structure Of Telephone Exchanges (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
- Other Air-Conditioning Systems (AREA)
- Cooling Or The Like Of Electrical Apparatus (AREA)
- Cooling Or The Like Of Semiconductors Or Solid State Devices (AREA)
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE10202261.5 | 2002-01-21 | ||
DE10202261A DE10202261A1 (de) | 2002-01-21 | 2002-01-21 | Wärmequellen- oder Wärmesenken-Anlage mit thermischer Erdankopplung |
PCT/EP2003/000470 WO2003060389A1 (fr) | 2002-01-21 | 2003-01-18 | Dispositif de source thermique ou dissipateur thermique comportant un couplage thermique a la terre |
Publications (1)
Publication Number | Publication Date |
---|---|
US20050061472A1 true US20050061472A1 (en) | 2005-03-24 |
Family
ID=7712738
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/502,070 Abandoned US20050061472A1 (en) | 2002-01-21 | 2003-01-18 | Heat source or heat sink unit with thermal ground coupling |
Country Status (10)
Country | Link |
---|---|
US (1) | US20050061472A1 (fr) |
EP (1) | EP1468226B1 (fr) |
AT (1) | ATE300023T1 (fr) |
BR (1) | BR0307036A (fr) |
CA (1) | CA2473369A1 (fr) |
DE (2) | DE10202261A1 (fr) |
DK (1) | DK1468226T3 (fr) |
ES (1) | ES2246476T3 (fr) |
PT (1) | PT1468226E (fr) |
WO (1) | WO2003060389A1 (fr) |
Cited By (41)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070068615A1 (en) * | 2005-09-23 | 2007-03-29 | Hon Hai Precision Industry Co., Ltd. | Method for manufacturing heat pipes |
US20080169084A1 (en) * | 2007-01-16 | 2008-07-17 | Bullivant Roger A | Geothermal energy system |
US20080202723A1 (en) * | 2007-02-27 | 2008-08-28 | Tracto-Technik Gmbh & Co. Kg | Method and apparatus for installing a borehole heat exchanger in the earth |
US20090165992A1 (en) * | 2007-12-31 | 2009-07-02 | Noble Geofurnace, Inc. | Geothermal heat exchange system and method |
US20100059198A1 (en) * | 2007-03-06 | 2010-03-11 | A&S Umwelttechnologie Ag | System for configuring earth probes |
US20100200192A1 (en) * | 2007-06-26 | 2010-08-12 | Climatisation Par Puits Canadiens | Buried vertical threaded exchanger for heating or cooling apparatus |
US20100218912A1 (en) * | 2008-04-07 | 2010-09-02 | Lane Lawless | Method, apparatus, header, and composition for ground heat exchange |
US20100236749A1 (en) * | 2009-03-23 | 2010-09-23 | John Stojanowski | Modular, stackable, geothermal block system |
US20100258266A1 (en) * | 2009-03-23 | 2010-10-14 | John Stojanowski | Modular, stackable, geothermal block heat exchange system with solar assist |
US20100270003A1 (en) * | 2009-04-27 | 2010-10-28 | Alberto Sarria | Two-concentric pipe system to heat fluids using the earth's interior thermal energy (deep) |
US20100288465A1 (en) * | 2007-07-06 | 2010-11-18 | Stewart James J | Geothermal energy system and method of operation |
US20100307734A1 (en) * | 2006-02-24 | 2010-12-09 | Scandinavian Energy Efficiency | Method and device for heating and cooling |
US20120097448A1 (en) * | 2009-03-10 | 2012-04-26 | Geo-Mole Limited | Percussion Mole |
WO2012140324A1 (fr) * | 2011-04-14 | 2012-10-18 | Runtech Systems Oy | Appareil permettant de mettre en œuvre un système de chaleur géothermique et procédé permettant d'exploiter celui-ci |
US20130020048A1 (en) * | 2010-04-01 | 2013-01-24 | SPS Energy GmbH | Device and method for recovering heat from the environment |
US20130087306A1 (en) * | 2011-10-09 | 2013-04-11 | Bernard Meredith Winn, JR. | Forced Insertion Concentric Ground-Coupled Heat Exchanger for Ground Source Heat Pumps |
EP2313708A4 (fr) * | 2008-06-13 | 2014-04-09 | Michael J Parrella | Systeme et procede de capture de chaleur geothermique provenant de l'interieur d'un puits fore afin de generer de l'electricite |
JP2014109180A (ja) * | 2012-12-04 | 2014-06-12 | Asahi Kasei Construction Materials Co Ltd | 熱交換用配管を備えた基礎杭、及びその埋設方法 |
JP2015021714A (ja) * | 2013-07-23 | 2015-02-02 | 北海バネ株式会社 | 地中熱ヒートポンプシステム用の地中熱交換器 |
JP2015121040A (ja) * | 2013-12-24 | 2015-07-02 | システム計測株式会社 | 場所打ち鋼管コンクリート杭 |
US9121630B1 (en) | 2008-04-07 | 2015-09-01 | Rygan Corp. | Method, apparatus, conduit, and composition for low thermal resistance ground heat exchange |
US9360236B2 (en) | 2008-06-16 | 2016-06-07 | Greenfield Master Ipco Limited | Thermal energy system and method of operation |
US9423158B2 (en) | 2008-08-05 | 2016-08-23 | Michael J. Parrella | System and method of maximizing heat transfer at the bottom of a well using heat conductive components and a predictive model |
US9897347B2 (en) | 2013-03-15 | 2018-02-20 | Thomas Scott Breidenbach | Screw-in geothermal heat exchanger systems and methods |
US9915247B2 (en) | 2007-07-06 | 2018-03-13 | Erda Master Ipco Limited | Geothermal energy system and method of operation |
US9933187B2 (en) | 2014-11-05 | 2018-04-03 | SaeHeum Song | System and method for geothermal heat exchange |
JP2018178529A (ja) * | 2017-04-13 | 2018-11-15 | ケミカルグラウト株式会社 | 凍結管及び凍結工法 |
CN109237840A (zh) * | 2017-05-11 | 2019-01-18 | 周兆弟 | 能源桩 |
US10309693B2 (en) | 2011-03-08 | 2019-06-04 | Erda Master Ipco Limited | Thermal energy system and method of operation |
US10345051B1 (en) * | 2012-06-11 | 2019-07-09 | Roy Dan Halloran | Ground source heat pump heat exchanger |
US20190257550A1 (en) * | 2016-09-23 | 2019-08-22 | Nordwind S.R.L. | Coaxial geothermal probe and method for making a coaxial geothermal probe |
US10871310B2 (en) * | 2016-10-26 | 2020-12-22 | Eco-Planner Co., Ltd. | Underground heat exchanger |
US20210071915A1 (en) * | 2018-08-23 | 2021-03-11 | Intertech Co., Ltd. | Underground heat exchange type cooling and heating system |
WO2021234516A1 (fr) | 2020-05-20 | 2021-11-25 | Namaya Ltd | Systèmes et procédés de construction d'ensembles d'entrée-sortie pour des installations de dessalement d'eau |
WO2021245485A1 (fr) | 2020-06-04 | 2021-12-09 | Namaya Ltd. | Ensembles systèmes et procédés de fonçage d'éléments préfabriqués présentant un agencement structuré |
US11536472B2 (en) * | 2018-07-30 | 2022-12-27 | John P. Ballegeer | Concentric pipe geothermal heat exchanger well head |
US11549725B2 (en) * | 2016-07-22 | 2023-01-10 | Nmbu | System for storing and retrieving thermal energy |
US11549726B2 (en) | 2017-03-07 | 2023-01-10 | E-Tube Sweden Ab | Flexible sealing tube and method for producing the same |
US20230047310A1 (en) * | 2021-08-12 | 2023-02-16 | Bernard J. Gochis | Piles providing support and geothermal heat exchange |
US11796225B2 (en) | 2012-10-18 | 2023-10-24 | American Piledriving Equipment, Inc. | Geoexchange systems including ground source heat exchangers and related methods |
US11906205B2 (en) * | 2018-02-12 | 2024-02-20 | Quantitative Heat Oy | Geothermal heat exchanger, geothermal heat arrangement and method for charging thermal energy into ground |
Families Citing this family (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1486741B1 (fr) * | 2003-06-13 | 2006-11-29 | Tiroler Röhren- und Metallwerke Aktiengesellschaft | Pieu pour énergie |
US7363769B2 (en) | 2005-03-09 | 2008-04-29 | Kelix Heat Transfer Systems, Llc | Electromagnetic signal transmission/reception tower and accompanying base station employing system of coaxial-flow heat exchanging structures installed in well bores to thermally control the environment housing electronic equipment within the base station |
WO2007070905A2 (fr) * | 2005-12-19 | 2007-06-28 | Atlas Copco Mai Gmbh | Echangeur de chaleur |
DE102006026531B3 (de) * | 2006-03-11 | 2007-09-20 | Strebe, Angelika | Erdsonde zur Wärmegewinnung |
WO2008106699A1 (fr) * | 2007-03-06 | 2008-09-12 | A & S Umwelttechnologie Ag | Installation de sonde terrestre |
DE102007013089A1 (de) | 2007-03-14 | 2008-09-25 | Dede, Christian, Dr. | Anordnung zur Gewinnung von oberflächennaher Erdwärme |
ES2561947T3 (es) * | 2007-09-08 | 2016-03-01 | Dynamic Blue Holding Gmbh | Circuito cerrado de transferencia de calor geotérmico |
DE102007054185B3 (de) * | 2007-11-14 | 2009-05-20 | Herold, Andreas, Dipl.-Ing. | Geothermiesonde und Verfahren zu deren Installation |
DE202008002342U1 (de) | 2008-02-19 | 2008-07-03 | Strebe, Jürgen | Solarsonde |
DE102008017675A1 (de) | 2008-04-08 | 2009-10-15 | Stephan Heckert | Kombination von Solarthermie mit der Nutzung von Erdwärme |
DE102008060068A1 (de) * | 2008-07-28 | 2010-02-04 | Clina Heiz- und Kühlelemente GmbH | Wärmeübertrager |
CA2639648C (fr) * | 2008-09-12 | 2019-12-31 | Alain Desmeules | Systeme et methode pour installation souterraine de boucle de canalisation geothermale et tete penetrant le sol connexe |
DE102008057495A1 (de) * | 2008-11-15 | 2010-05-20 | Stauss, Erich | Wärmespeicheranordnung |
US9291286B2 (en) | 2009-08-06 | 2016-03-22 | WCA Group LLC | Hollow drill rod for slurry application in a geothermal loop |
US8529156B2 (en) | 2009-08-06 | 2013-09-10 | True.Home Heating/Cooling, Inc. | Bit adapter and tube return for vertizontal geothermal loop |
US8256531B1 (en) | 2009-08-06 | 2012-09-04 | Williams Comfort Air, Inc. | Vertizontal geothermal loop and installation method |
DE102009040476A1 (de) * | 2009-09-08 | 2011-03-10 | Rheinisch-Westfälische Technische Hochschule Aachen | Geothermiesonde und Verfahren zu deren Betrieb |
US9587890B2 (en) * | 2009-11-05 | 2017-03-07 | Tai-Her Yang | Vertical fluid heat exchanger installed within natural thermal energy body |
ES2394578B1 (es) * | 2010-03-23 | 2013-08-19 | Grupo Rodio Kronsa S.L. | Pilote prefabricado hueco empalmable para cimentación. |
DE102018005394A1 (de) * | 2018-07-09 | 2020-01-09 | Enerpipe Gmbh | Wärmetauscher |
EP3748254B1 (fr) * | 2019-06-04 | 2021-11-03 | Peter Häusler | Dispositif d'échangeur de chaleur géothermique comprenant des poteaux d'échangeur de chaleur à visser |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3952802A (en) * | 1974-12-11 | 1976-04-27 | In Situ Technology, Inc. | Method and apparatus for in situ gasification of coal and the commercial products derived therefrom |
US4325228A (en) * | 1980-05-20 | 1982-04-20 | Wolf Herman B | Geothermal heating and cooling system |
US4392531A (en) * | 1981-10-09 | 1983-07-12 | Ippolito Joe J | Earth storage structural energy system and process for constructing a thermal storage well |
US4512156A (en) * | 1977-09-30 | 1985-04-23 | Kyoto Central Co. Ltd. | Geothermal energy conversion system |
US4574875A (en) * | 1983-12-05 | 1986-03-11 | Geo-Systems, Inc. | Heat exchanger for geothermal heating and cooling systems |
US4671351A (en) * | 1985-07-17 | 1987-06-09 | Vertech Treatment Systems, Inc. | Fluid treatment apparatus and heat exchanger |
US4808032A (en) * | 1986-05-30 | 1989-02-28 | Meyer & John Gmbh & Co. Tief- Und Rohrleitungsbau | Thrust pipe |
US4854372A (en) * | 1987-03-11 | 1989-08-08 | Fujikura Ltd. | Corrugated heat pipe |
US4930572A (en) * | 1988-09-14 | 1990-06-05 | Doshier John R | Heat pipe and aqua-thaw animal waterer |
US4995450A (en) * | 1989-08-18 | 1991-02-26 | G.P. Industries, Inc. | Heat pipe |
US5203173A (en) * | 1990-05-18 | 1993-04-20 | Diego Horton | Device for utilization of geothermal energy |
US5533356A (en) * | 1994-11-09 | 1996-07-09 | Phillips Petroleum Company | In-ground conduit system for geothermal applications |
US5560220A (en) * | 1995-09-01 | 1996-10-01 | Ecr Technologies, Inc. | Method for testing an earth tap heat exchanger and associated apparatus |
US5590715A (en) * | 1995-09-12 | 1997-01-07 | Amerman; Thomas R. | Underground heat exchange system |
US5623986A (en) * | 1995-09-19 | 1997-04-29 | Wiggs; B. Ryland | Advanced in-ground/in-water heat exchange unit |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2431004A1 (fr) * | 1978-07-12 | 1980-02-08 | Vignal Maurice | Procede pour la mise en place d'un echangeur thermique dans le sol |
LU81670A1 (de) * | 1979-09-10 | 1980-01-24 | Feist Artus | Verfahren zur erdwaermegewinnung und vorrichtung zur durchfuehrung dieses verfahrens |
DE7936659U1 (de) * | 1979-12-28 | 1980-10-23 | Molzner, Hermann-Dietrich, 2300 Kiel | Vorrichtung zum einbringen von stangenfoermigen waermetauschern in das erdreich |
DE4437124C2 (de) * | 1993-06-04 | 2003-11-20 | Vattenfall Europe Generation | Verwendung einer Sonde aus einer unten geschlossenen Doppelrohrtour |
DE9414813U1 (de) * | 1994-09-12 | 1994-11-10 | Tiroler Röhren- und Metallwerke AG, Hall in Tirol | Pfahl |
NL1010725C1 (nl) * | 1998-12-04 | 2000-06-06 | Berg A P Van Den Beheer Bv | Werkwijze voor het in de bodem aanbrengen van een bodemwarmtewisselaar, alsmede een bodemwarmtewisselaarsamenstel. |
DE20013561U1 (de) * | 2000-08-08 | 2000-11-23 | Krüger, Alexander, Dipl.-Ing., 08412 Leubnitz | Wärmetauscher als Tauchkollektor für Wärmepumpenanlagen |
-
2002
- 2002-01-21 DE DE10202261A patent/DE10202261A1/de not_active Withdrawn
-
2003
- 2003-01-18 BR BR0307036-0A patent/BR0307036A/pt not_active IP Right Cessation
- 2003-01-18 EP EP03729483A patent/EP1468226B1/fr not_active Expired - Lifetime
- 2003-01-18 AT AT03729483T patent/ATE300023T1/de not_active IP Right Cessation
- 2003-01-18 US US10/502,070 patent/US20050061472A1/en not_active Abandoned
- 2003-01-18 PT PT03729483T patent/PT1468226E/pt unknown
- 2003-01-18 WO PCT/EP2003/000470 patent/WO2003060389A1/fr active IP Right Grant
- 2003-01-18 DK DK03729483T patent/DK1468226T3/da active
- 2003-01-18 DE DE50300809T patent/DE50300809D1/de not_active Expired - Fee Related
- 2003-01-18 CA CA002473369A patent/CA2473369A1/fr not_active Abandoned
- 2003-01-18 ES ES03729483T patent/ES2246476T3/es not_active Expired - Lifetime
Patent Citations (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3952802A (en) * | 1974-12-11 | 1976-04-27 | In Situ Technology, Inc. | Method and apparatus for in situ gasification of coal and the commercial products derived therefrom |
US4512156A (en) * | 1977-09-30 | 1985-04-23 | Kyoto Central Co. Ltd. | Geothermal energy conversion system |
US4325228A (en) * | 1980-05-20 | 1982-04-20 | Wolf Herman B | Geothermal heating and cooling system |
US4392531A (en) * | 1981-10-09 | 1983-07-12 | Ippolito Joe J | Earth storage structural energy system and process for constructing a thermal storage well |
US4574875A (en) * | 1983-12-05 | 1986-03-11 | Geo-Systems, Inc. | Heat exchanger for geothermal heating and cooling systems |
US4671351A (en) * | 1985-07-17 | 1987-06-09 | Vertech Treatment Systems, Inc. | Fluid treatment apparatus and heat exchanger |
US4808032A (en) * | 1986-05-30 | 1989-02-28 | Meyer & John Gmbh & Co. Tief- Und Rohrleitungsbau | Thrust pipe |
US4858679A (en) * | 1987-03-11 | 1989-08-22 | Fujikura Ltd. | Corrugated heat pipe |
US4854372A (en) * | 1987-03-11 | 1989-08-08 | Fujikura Ltd. | Corrugated heat pipe |
US4930572A (en) * | 1988-09-14 | 1990-06-05 | Doshier John R | Heat pipe and aqua-thaw animal waterer |
US4995450A (en) * | 1989-08-18 | 1991-02-26 | G.P. Industries, Inc. | Heat pipe |
US5203173A (en) * | 1990-05-18 | 1993-04-20 | Diego Horton | Device for utilization of geothermal energy |
US5533356A (en) * | 1994-11-09 | 1996-07-09 | Phillips Petroleum Company | In-ground conduit system for geothermal applications |
US5560220A (en) * | 1995-09-01 | 1996-10-01 | Ecr Technologies, Inc. | Method for testing an earth tap heat exchanger and associated apparatus |
US5590715A (en) * | 1995-09-12 | 1997-01-07 | Amerman; Thomas R. | Underground heat exchange system |
US5623986A (en) * | 1995-09-19 | 1997-04-29 | Wiggs; B. Ryland | Advanced in-ground/in-water heat exchange unit |
Cited By (58)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070068615A1 (en) * | 2005-09-23 | 2007-03-29 | Hon Hai Precision Industry Co., Ltd. | Method for manufacturing heat pipes |
US9310103B2 (en) * | 2006-02-24 | 2016-04-12 | Scandinavian Energy Efficiency Co. Seec Ab | Method and device for heating and cooling |
US20100307734A1 (en) * | 2006-02-24 | 2010-12-09 | Scandinavian Energy Efficiency | Method and device for heating and cooling |
US20080169084A1 (en) * | 2007-01-16 | 2008-07-17 | Bullivant Roger A | Geothermal energy system |
GB2447123A (en) * | 2007-02-27 | 2008-09-03 | Tracto Technik | Method of Installing Borehole Heal Exchangers |
GB2447123B (en) * | 2007-02-27 | 2012-01-18 | Tracto Technik | Method of installing borehole heat exchangers in the earth and an apparatus |
US20080202723A1 (en) * | 2007-02-27 | 2008-08-28 | Tracto-Technik Gmbh & Co. Kg | Method and apparatus for installing a borehole heat exchanger in the earth |
US8016049B2 (en) | 2007-02-27 | 2011-09-13 | Tracto-Technik Gmbh & Co. Kg | Method and apparatus for installing a borehole heat exchanger in the earth |
US20100059198A1 (en) * | 2007-03-06 | 2010-03-11 | A&S Umwelttechnologie Ag | System for configuring earth probes |
US20100200192A1 (en) * | 2007-06-26 | 2010-08-12 | Climatisation Par Puits Canadiens | Buried vertical threaded exchanger for heating or cooling apparatus |
US9915247B2 (en) | 2007-07-06 | 2018-03-13 | Erda Master Ipco Limited | Geothermal energy system and method of operation |
US9556856B2 (en) * | 2007-07-06 | 2017-01-31 | Greenfield Master Ipco Limited | Geothermal energy system and method of operation |
US20100288465A1 (en) * | 2007-07-06 | 2010-11-18 | Stewart James J | Geothermal energy system and method of operation |
US20090165992A1 (en) * | 2007-12-31 | 2009-07-02 | Noble Geofurnace, Inc. | Geothermal heat exchange system and method |
US9121630B1 (en) | 2008-04-07 | 2015-09-01 | Rygan Corp. | Method, apparatus, conduit, and composition for low thermal resistance ground heat exchange |
US20100218912A1 (en) * | 2008-04-07 | 2010-09-02 | Lane Lawless | Method, apparatus, header, and composition for ground heat exchange |
US9816023B2 (en) * | 2008-04-07 | 2017-11-14 | Rygan Corp | Method, apparatus, header, and composition for ground heat exchange |
US10301528B1 (en) * | 2008-04-07 | 2019-05-28 | Rygan Corp. | Method, apparatus, header, and composition for ground heat exchange |
EP2313708A4 (fr) * | 2008-06-13 | 2014-04-09 | Michael J Parrella | Systeme et procede de capture de chaleur geothermique provenant de l'interieur d'un puits fore afin de generer de l'electricite |
US9404480B2 (en) | 2008-06-13 | 2016-08-02 | Pardev, Llc | System and method of capturing geothermal heat from within a drilled well to generate electricity |
AU2009258086B2 (en) * | 2008-06-13 | 2016-07-07 | Michael J. Parrella | System and method of capturing geothermal heat from within a drilled well to generate electricity |
US9360236B2 (en) | 2008-06-16 | 2016-06-07 | Greenfield Master Ipco Limited | Thermal energy system and method of operation |
US9423158B2 (en) | 2008-08-05 | 2016-08-23 | Michael J. Parrella | System and method of maximizing heat transfer at the bottom of a well using heat conductive components and a predictive model |
US20120097448A1 (en) * | 2009-03-10 | 2012-04-26 | Geo-Mole Limited | Percussion Mole |
US8936113B2 (en) * | 2009-03-10 | 2015-01-20 | Geo-Mole Limited | Percussion mole and method of geothermal heat exchange |
US20100236749A1 (en) * | 2009-03-23 | 2010-09-23 | John Stojanowski | Modular, stackable, geothermal block system |
US20100258266A1 (en) * | 2009-03-23 | 2010-10-14 | John Stojanowski | Modular, stackable, geothermal block heat exchange system with solar assist |
US8776867B2 (en) * | 2009-03-23 | 2014-07-15 | John Stojanowski | Modular, stackable, geothermal block heat exchange system with solar assist |
US8230900B2 (en) * | 2009-03-23 | 2012-07-31 | John Stojanowski | Modular, stackable, geothermal block system |
US20100270003A1 (en) * | 2009-04-27 | 2010-10-28 | Alberto Sarria | Two-concentric pipe system to heat fluids using the earth's interior thermal energy (deep) |
US8307896B2 (en) * | 2009-04-27 | 2012-11-13 | Alberto Sarria | Two-concentric pipe system to heat fluids using the earth's interior thermal energy (deep) |
US20130020048A1 (en) * | 2010-04-01 | 2013-01-24 | SPS Energy GmbH | Device and method for recovering heat from the environment |
US10309693B2 (en) | 2011-03-08 | 2019-06-04 | Erda Master Ipco Limited | Thermal energy system and method of operation |
US10921030B2 (en) | 2011-03-08 | 2021-02-16 | Erda Master Ipco Limited | Thermal energy system and method of operation |
WO2012140324A1 (fr) * | 2011-04-14 | 2012-10-18 | Runtech Systems Oy | Appareil permettant de mettre en œuvre un système de chaleur géothermique et procédé permettant d'exploiter celui-ci |
US20130087306A1 (en) * | 2011-10-09 | 2013-04-11 | Bernard Meredith Winn, JR. | Forced Insertion Concentric Ground-Coupled Heat Exchanger for Ground Source Heat Pumps |
US10345051B1 (en) * | 2012-06-11 | 2019-07-09 | Roy Dan Halloran | Ground source heat pump heat exchanger |
US11796225B2 (en) | 2012-10-18 | 2023-10-24 | American Piledriving Equipment, Inc. | Geoexchange systems including ground source heat exchangers and related methods |
JP2014109180A (ja) * | 2012-12-04 | 2014-06-12 | Asahi Kasei Construction Materials Co Ltd | 熱交換用配管を備えた基礎杭、及びその埋設方法 |
US9897347B2 (en) | 2013-03-15 | 2018-02-20 | Thomas Scott Breidenbach | Screw-in geothermal heat exchanger systems and methods |
US11892201B2 (en) | 2013-03-15 | 2024-02-06 | Thomas Scott Breidenbach | Installation apparatus/tool for tubular geothermal heat exchanger systems and methods |
JP2015021714A (ja) * | 2013-07-23 | 2015-02-02 | 北海バネ株式会社 | 地中熱ヒートポンプシステム用の地中熱交換器 |
JP2015121040A (ja) * | 2013-12-24 | 2015-07-02 | システム計測株式会社 | 場所打ち鋼管コンクリート杭 |
US9933187B2 (en) | 2014-11-05 | 2018-04-03 | SaeHeum Song | System and method for geothermal heat exchange |
US11549725B2 (en) * | 2016-07-22 | 2023-01-10 | Nmbu | System for storing and retrieving thermal energy |
US20190257550A1 (en) * | 2016-09-23 | 2019-08-22 | Nordwind S.R.L. | Coaxial geothermal probe and method for making a coaxial geothermal probe |
US10871310B2 (en) * | 2016-10-26 | 2020-12-22 | Eco-Planner Co., Ltd. | Underground heat exchanger |
US11549726B2 (en) | 2017-03-07 | 2023-01-10 | E-Tube Sweden Ab | Flexible sealing tube and method for producing the same |
JP2018178529A (ja) * | 2017-04-13 | 2018-11-15 | ケミカルグラウト株式会社 | 凍結管及び凍結工法 |
CN109237840A (zh) * | 2017-05-11 | 2019-01-18 | 周兆弟 | 能源桩 |
US11906205B2 (en) * | 2018-02-12 | 2024-02-20 | Quantitative Heat Oy | Geothermal heat exchanger, geothermal heat arrangement and method for charging thermal energy into ground |
US11536472B2 (en) * | 2018-07-30 | 2022-12-27 | John P. Ballegeer | Concentric pipe geothermal heat exchanger well head |
US20210071915A1 (en) * | 2018-08-23 | 2021-03-11 | Intertech Co., Ltd. | Underground heat exchange type cooling and heating system |
US11835268B2 (en) * | 2018-08-23 | 2023-12-05 | Intertech Co., Ltd. | Underground heat exchange type cooling and heating system |
WO2021234516A1 (fr) | 2020-05-20 | 2021-11-25 | Namaya Ltd | Systèmes et procédés de construction d'ensembles d'entrée-sortie pour des installations de dessalement d'eau |
WO2021245485A1 (fr) | 2020-06-04 | 2021-12-09 | Namaya Ltd. | Ensembles systèmes et procédés de fonçage d'éléments préfabriqués présentant un agencement structuré |
US20230047310A1 (en) * | 2021-08-12 | 2023-02-16 | Bernard J. Gochis | Piles providing support and geothermal heat exchange |
US11953237B2 (en) * | 2021-08-12 | 2024-04-09 | Bernard J. Gochis | Piles providing support and geothermal heat exchange |
Also Published As
Publication number | Publication date |
---|---|
EP1468226B1 (fr) | 2005-07-20 |
ES2246476T3 (es) | 2006-02-16 |
WO2003060389A1 (fr) | 2003-07-24 |
DK1468226T3 (da) | 2005-11-21 |
PT1468226E (pt) | 2005-11-30 |
BR0307036A (pt) | 2004-10-26 |
CA2473369A1 (fr) | 2003-07-24 |
ATE300023T1 (de) | 2005-08-15 |
EP1468226A1 (fr) | 2004-10-20 |
DE10202261A1 (de) | 2003-08-07 |
DE50300809D1 (de) | 2005-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20050061472A1 (en) | Heat source or heat sink unit with thermal ground coupling | |
CN104695964B (zh) | 地铁盾构隧道冰冻进洞方法 | |
WO2017024916A1 (fr) | Tuyau de transfert thermique encastré dans une colonne de tuyau préfabriquée et procédé d'encastrement | |
US7841383B2 (en) | Encasement assembly for installation of sub-surface refrigerant tubing in a direct exchange heating/cooling system | |
KR101425632B1 (ko) | 고심도용 지중 열교환기 코일관 웨이트장치 및 설치방법 | |
JP2004233031A (ja) | 回転圧入工法で埋設された中空管体による地中熱交換器およびそれを利用した高効率エネルギーシステム | |
CN205260038U (zh) | 盾构隧道端头箱型冻结壁加固结构 | |
CN107672155A (zh) | 一种用于管道修复的气压翻转设备及修复工艺 | |
JP4949358B2 (ja) | 地中埋設温度成層型蓄熱水槽 | |
KR100981527B1 (ko) | 고심도 수직밀폐형 지중 열교환기 장치 및 구성 방법 | |
CN111238085A (zh) | 基于土壤岩石交替出现地层的地源热泵地埋管施工方法 | |
RU2295608C2 (ru) | Способ установки сваи в многолетнемерзлом грунте (варианты) | |
CN107119672B (zh) | 端承能量桩及其系统 | |
CN101709577A (zh) | 一种冻土地基快速解冻方法 | |
JP2015190715A (ja) | 地中熱交換器用本体、地中熱交換器、地中熱交換システム及び施工方法 | |
CN115522531A (zh) | 一种基于冻结法的电梯井或集水坑的冻结系统和施工方法 | |
WO2008091173A1 (fr) | Procédé d'installation d'un pieu dans un pergélisol et variantes | |
CN210105867U (zh) | 一种盾构隧道端头冻土墙与地连墙联合加固结构 | |
JP2005273235A (ja) | 地中熱利用建物 | |
KR20190102433A (ko) | 자천공 동결관 | |
CN207047836U (zh) | 端承能量桩及其系统 | |
AU2006348699B2 (en) | Encasement assembly for installation of sub-surface refrigerant tubing in a direct exchange heating/cooling system | |
CN104863596A (zh) | X形冻结管及其在冻结施工中的应用方法 | |
CN217274912U (zh) | 一种埋管换热系统及含有其的室内供暖制冷系统、路面除冰降温系统 | |
JP7219857B2 (ja) | 同心軸多層構造地中熱交換器設置用機材、同心軸多層構造地中熱交換器及び地中熱交換器設置方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: WATERKOTTE WARMEPUMPEN GMBH, GERMANY Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:WATERKOTTE, KLEMENS;REEL/FRAME:015978/0684 Effective date: 20040818 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO PAY ISSUE FEE |