US20030084630A1 - Perimeter walls - Google Patents

Perimeter walls Download PDF

Info

Publication number
US20030084630A1
US20030084630A1 US10/272,281 US27228102A US2003084630A1 US 20030084630 A1 US20030084630 A1 US 20030084630A1 US 27228102 A US27228102 A US 27228102A US 2003084630 A1 US2003084630 A1 US 2003084630A1
Authority
US
United States
Prior art keywords
perimeter
load bearing
foundation
level
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US10/272,281
Inventor
Peter Shotton
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cementation Foundations Skanska Ltd
Original Assignee
Cementation Foundations Skanska Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to GB0124991A priority Critical patent/GB0124991D0/en
Priority to GB0124991.1 priority
Application filed by Cementation Foundations Skanska Ltd filed Critical Cementation Foundations Skanska Ltd
Assigned to CEMENTATION FOUNDATION SKANSKA LIMITED reassignment CEMENTATION FOUNDATION SKANSKA LIMITED ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: SHOTTON, PETER GILBERT
Publication of US20030084630A1 publication Critical patent/US20030084630A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure

Abstract

The present application describes methods and apparatus for installing a load bearing pile 1 which is installed in the line of a perimeter wall, in particular to a perimeter wall consisting of a series of diaphragm wall panels. In this way substantial concentrated vertical loads can be carried in the line of a perimeter or retaining wall, in particular

Description

  • The present invention relates to methods of forming a foundation structure and, in particular, to the construction of perimeter or retaining walls. [0001]
  • Most perimeter walls are designed essentially to act as earth or soil retaining structures, e.g. basement structures, storm water tanks and traffic underpasses etc. Often the retaining walls comprise a series of piles (such as bored, CFA or secant piles), diaphragm walls, sheet pile walls or ‘post & plank’ schemes. [0002]
  • In many instances the perimeter wall is also required to support vertical loads from the superstructure. Often the loads are relatively small and can therefore be carried on a single wall element. Alternatively, the loads can be accommodated by installing a relatively small capping beam, which serves to distribute the load over several wall elements (piles, panels, etc.). [0003]
  • In many instances there is a need to support heavy concentrated loads and in these circumstances it is usually necessary to: i) extend the depth of the perimeter walls; and/or ii) install a deep capping beam to distribute the load to several elements. [0004]
  • However, both of these approaches suffer from a number of disadvantages. Extending the depth of the perimeter wall is labour intensive and obviously requires a larger quantity of concrete, therefore adding considerable cost to the overall foundation construction. Installing a deep capping beam which serves to distribute the load to a number of elements requires considerable skill and can be difficult and time consuming. Furthermore, it may be necessary to support local structures in order to excavate for a deep capping beam. [0005]
  • Preferred embodiments of the present invention seek to provide a method whereby substantial concentrated vertical loads can be carried in the line of a perimeter or retaining wall which, advantageously, do not require the use of a capping beam or spreader beam to distribute the vertical loads onto several wall elements. Advantageously, the depth of the retaining wall can therefore be reduced. Additionally, in some circumstances, it may be possible to reduce the thickness of the retaining wall element. [0006]
  • The present invention therefore seeks to provide a method in which a load bearing pile is installed in the line of a perimeter wall. The method of the present invention is particularly applicable to a perimeter wall consisting of a series of diaphragm wall panels. [0007]
  • According to one aspect of the present invention there is provided a foundation structure comprising a load bearing element positioned between adjacent elements of a perimeter wall. [0008]
  • According to a second aspect of the present invention there is provided a method of constructing a perimeter wall, the method comprising the formation of at least one load bearing element in the ground between adjacent elements of the perimeter wall. [0009]
  • In one embodiment of the present invention diaphragm wall panels are constructed either side of the load bearing element. However, the present invention may also be applied to periemter walls constructed from a driven sheet wall or a secant pile wall formed from complementary “male” and “female” piles. [0010]
  • A steel reinforcement section provided along a longitudinal axis of the load bearing element serves to transmit the load of an above ground structure down to the toe of the load bearing element. [0011]
  • The foundation structure of the present invention is generally constructed by forming the load bearing element first and then constructing the adjacent elements of the perimeter wall either side. [0012]
  • Formation of the load bearing element may be by forming a hole in the ground to a depth below that of the proposed perimeter wall. The hole is then partially filled with concrete to a level just below the toe of the proposed perimeter wall and a reinforcement section is plunged into the concrete before it has hardened. Alternatively the section may be positioned within the hole and the concrete placed around the lower end thereof, within the lower part of the bore hole. Preferably, a suitable embedment length is used in order to accommodate the load to be transferred by the reinforcement section to the base of the pile. [0013]
  • Positioning of the reinforcement section is advantageously achieved by employing the use of a positioning frame having a means to adjust the plan position of the section at an upper and lower level. [0014]
  • The reinforcement section may comprise steel, pre-cast reinforced concrete, or a combination of steel and concrete. For perimeter walls which are to be constructed from diaphragm wall panels, an “I” shaped section has advantages since the width of the panels may complement either side of the I shape. [0015]
  • When the reinforcement section has been positioned, the bore is filled above the low level cast concrete with a backfill mixture of sand/cement, bentonite, mortar/grout. After the backfill has gained adequate strength (usually after 1 to 2 days), guide walls are constructed to define the proposed perimeter wall in the conventional manner. [0016]
  • The perimeter wall elements are then constructed on either side of the column section. The column section will preferably be slightly wider than the perimeter wall element excavating tool, and the tool will excavate any material in the ‘belly’ of the section. [0017]
  • In accordance with the present invention it is possible to install a load-bearing element (e.g. a column section) into a perimeter wall, which can support a concentrated load of 20,000 kN. In practice, with a suitably designed embedment detail, loads of 40,000 kN and even greater can be accommodated. [0018]
  • Conventionally perimeter walls are designed to span vertically, whether as a cantilever or between horizontal supports such as floor slabs. The thickness of the wall element depends on the soil properties and the length of vertical span. [0019]
  • An important advantage of the present invention is that it is possible to economise the design of the perimeter wall by the provision of a load bearing element in the line of the wall. For example, where the cantilever height, or distance between supports, is large, the wall elements between adjacent (main) piles can be designed to span horizontally. This reduces the stresses, and a thinner, more economical, wall can be designed. [0020]
  • In a similar manner, where the wall elements themselves are reinforced concrete piles, sheet piles or other discrete vertical elements, the horizontal support can be accommodated by, for example, a steel walling beam spanning between the vertical load-bearing elements. [0021]
  • The individual load bearing elements and the embedded sections can be designed to resist the external soil forces, and at the same time support substantial vertical loads as described herein.[0022]
  • For a better understanding of the present invention, and to show how the same may be carried into effect, reference will now be made, by way of example, to the accompanying drawings, in which: [0023]
  • FIGS. 1A to [0024] 1D illustrate the stages involved in a method of constructing a perimeter wall, according to an embodiment of the present invention;
  • FIG. 2 shows the formation of a load bearing column according to embodiments of the present invention; [0025]
  • FIG. 3 shows the construction of a perimeter wall element on a first side of the load bearing column depicted in FIG. 2; [0026]
  • FIG. 4 shows the construction of a perimeter wall element on the other side of the load bearing column depicted in FIG. 2; [0027]
  • FIGS. 5A and 5B illustrate the stages involved in a method of constructing a perimeter wall, according to a further embodiment of the present invention; and [0028]
  • FIGS. 6A to [0029] 6C illustrate the stages involved in a method of constructing a perimeter wall, according to a further embodiment of the present invention.
  • FIG. 1A illustrates the first stage in the construction of a perimeter wall embodying the present invention and shows a plan view of a large diameter bored pile [0030] 1, having a reinforcement element 2 in the form of a steel I section column, positioned along its central longitudinal axis. The areas 3 and 4 either side of the pile column 1 indicate the line of the proposed perimeter wall. The dimensions of the I section are advantageously chosen to complement the thickness of the future perimeter wall elements.
  • FIG. 2 shows in more detail the construction of the pile column shown in FIG. 1A. A hole of appropriate size is formed in the ground and concrete [0031] 5 is pumped or poured into the bore up to a level 7 just below the lower level 8 of the proposed perimeter wall. The section 2 is plunged into the wet concrete to a predetermined depth and the plan position of the column is adjusted at an upper and lower level using a positioning frame having an upper and lower steering module. The bore is then filled with a mortar grout 6 up to a level at or near ground level. The resultant column will serve to carry a load 10, from an above ground structure, down into the base of the pile 5.
  • FIG. 1B shows the next stage of the construction in which guide walls [0032] 11 and 12 have been formed at an appropriate distance apart and above the load bearing column.
  • In FIG. 1C, area [0033] 4 between the guide walls 11 and 12 has been excavated so as to provide a cavity in the ground into which a cementious fluid will be pumped or poured in order to form a diaphragm wall panel. A stop end 13 (shown in FIG. 1D) is positioned within the cavity so as to comprise the end of the diaphragm wall panel. A reinforcing cage 14 is usually placed within the excavated area before filling with concrete to form the panel 15 (shown in FIG. 1D).
  • The construction of the first diaphragm wall panel is also illustrated by FIG. 3. The mortar grout substance which was used to form the upper part of the load bearing column has been excavated so that the concrete may be placed right up to the I section which is intended to protrude above the upper level of the perimeter wall. [0034]
  • In FIG. 1D and FIG. 4 the diaphragm wall panel [0035] 16 constructed on the other side of the load bearing column is shown. The resultant structure thus comprises a load bearing column which extends between two adjacent diaphragm wall panels and serves to transmit a load 10 down into the base of the pile in the ground.
  • FIGS. 5A and 5E illustrate the construction of a perimeter wall according to a further embodiment of the present invention. The load bearing element [0036] 20 is constructed as previously described, however the perimeter wall element comprises a sheet pile wall 21. The sheet piles, which may be interlocking or may be discrete elements in suitable ground conditions, will extend to the same level 8 to which the diaphragm wall 16 extended in FIG. 4.
  • After installation of the load bearing element [0037] 20, a pitching frame is erected along the proposed line of the sheet pile wall 21, and the sheet piles are then driven or vibrated to the required depth in the conventional manner. In suitable soil conditions it may be possible to install discrete sheet pile, i.e. without the need to inter-lock adjacent sheets.
  • FIGS. 6A, 6B and [0038] 6C illustrate the stages in the construction of a perimeter wall embodying the present invention in which a secant pile wall, comprising complementary male 26 and female 28 piles, is constructed either side of the load bearing element 23. Prior to the installation of the secant piles, guide walls 24 and 25 are formed and the mortar grout column of the load bearing element itself is partially excavated so as to complement adjacent secant pile 26 a and 26 b. The secant piles will extend to the same level 8 to which the diaphragm wall 16 extends in FIG. 4.
  • After installation of the load-bearing element [0039] 23, a secant pile wall is constructed in the conventional manner: a sequence of primary (or “male”) piles 26 and secondary (or “female”) piles 28 are formed which are counter-bored into the mortar grout column of the load bearing element 23.

Claims (12)

1. A foundation structure comprising a load bearing element positioned between adjacent elements of a perimeter wall.
2. A foundation element as claimed in claim 1, wherein the load bearing element extends from a level above that of the perimeter wall to a level below that of the perimeter wall.
3. A foundation element as claimed in claim 1 or 2, wherein the load bearing element comprises a concrete column having a reinforcement section provided along a longitudinal axis thereof.
4. A foundation element as claim in claim 3, wherein the reinforcement section comprises a steel “I” section.
6. A foundation element as claimed in claim 1 or 2, wherein the elements of the perimeter wall comprise diaphragm wall panels.
7. A foundation element as claimed in claim 1 or 2, wherein the elements of the perimeter wall comprise sheet piles.
8. A foundation element as claimed in claim 7, wherein the sheet piles may be inter-locking or discrete elements.
9. A foundation element as claimed in claim 1 or 2, wherein the elements of the perimeter wall comprise complementary male and female piles.
10. A method of constructing a perimeter wall, the method comprising the formation of at least one load bearing element in the ground between adjacent elements of the perimeter wall.
11. A method as claimed in claim 10, wherein the method comprises the steps of:
i) forming the load bearing element in the plane of the proposed perimeter wall; and
ii) forming perimeter wall elements either side of the load bearing element.
12. A method as claimed in claim 10 or 11, wherein the load bearing element extends from a level above that of the perimeter wall to a level below that of the perimeter wall.
13. A method as claimed in any one of claims 10 or 11, wherein the load bearing element comprises a concrete column having a reinforcement section provided along a longitudinal axis thereof.
US10/272,281 2001-10-17 2002-10-17 Perimeter walls Abandoned US20030084630A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
GB0124991A GB0124991D0 (en) 2001-10-17 2001-10-17 Perimeter walls
GB0124991.1 2001-10-17

Publications (1)

Publication Number Publication Date
US20030084630A1 true US20030084630A1 (en) 2003-05-08

Family

ID=9924061

Family Applications (1)

Application Number Title Priority Date Filing Date
US10/272,281 Abandoned US20030084630A1 (en) 2001-10-17 2002-10-17 Perimeter walls

Country Status (2)

Country Link
US (1) US20030084630A1 (en)
GB (2) GB0124991D0 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20190136481A1 (en) * 2017-11-06 2019-05-09 Richard J. Gagliano Foundation integral construction components and support systems

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101532287B (en) * 2008-03-14 2011-07-13 上海市基础工程有限公司 Prefabricated concrete insertion block for controlling closure deformation of guide wall

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US819067A (en) * 1905-04-07 1906-05-01 William Hunter Metallic piling.
US850496A (en) * 1906-02-23 1907-04-16 Composite Pile Construction Company Sheet-piling.
US1617762A (en) * 1923-06-30 1927-02-15 William G Kiefer Column and guard
US2439606A (en) * 1946-04-12 1948-04-13 Hurt Joel Retaining sea wall
US3555830A (en) * 1969-01-27 1971-01-19 Pomeroy & Co Inc J H Concrete wall structure and method
US3728862A (en) * 1971-06-23 1973-04-24 Meredith Drilling Co Inc Shoring system and components therefor
US4055927A (en) * 1975-08-12 1977-11-01 Icos Corporation Of America Concrete walls and reinforcement cage therefor
US4804299A (en) * 1986-07-09 1989-02-14 United International, Inc. Retaining wall system
US5324469A (en) * 1992-08-26 1994-06-28 Insul Holz-Beton Systems, Inc. Method of making single wood concrete layer sound absorption panel
US5404685A (en) * 1992-08-31 1995-04-11 Collins; Dennis W. Polystyrene foamed plastic wall apparatus and method of construction
US5689927A (en) * 1997-01-22 1997-11-25 Knight, Sr.; Larry E. Concrete post usable with a sound barrier fence
US6371699B1 (en) * 1997-10-16 2002-04-16 Durisol Inc. Anchored retaining wall system
US6554544B1 (en) * 1999-02-10 2003-04-29 Barkasz Sandor Method to build a water seal, creep-line increasing cutoff

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6017898B2 (en) * 1980-09-05 1985-05-07 Tomoegumi Iron Works
JPS6128774B2 (en) * 1980-12-23 1986-07-02 Tomoegumi Iron Works
GB8602254D0 (en) * 1986-01-30 1986-03-05 Roxbury Ltd Supports for building structures
US6394703B1 (en) * 1999-04-26 2002-05-28 Cementations Foundations Skanska Limited Formation of capping beams for piles

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US819067A (en) * 1905-04-07 1906-05-01 William Hunter Metallic piling.
US850496A (en) * 1906-02-23 1907-04-16 Composite Pile Construction Company Sheet-piling.
US1617762A (en) * 1923-06-30 1927-02-15 William G Kiefer Column and guard
US2439606A (en) * 1946-04-12 1948-04-13 Hurt Joel Retaining sea wall
US3555830A (en) * 1969-01-27 1971-01-19 Pomeroy & Co Inc J H Concrete wall structure and method
US3728862A (en) * 1971-06-23 1973-04-24 Meredith Drilling Co Inc Shoring system and components therefor
US4055927A (en) * 1975-08-12 1977-11-01 Icos Corporation Of America Concrete walls and reinforcement cage therefor
US4804299A (en) * 1986-07-09 1989-02-14 United International, Inc. Retaining wall system
US5324469A (en) * 1992-08-26 1994-06-28 Insul Holz-Beton Systems, Inc. Method of making single wood concrete layer sound absorption panel
US5404685A (en) * 1992-08-31 1995-04-11 Collins; Dennis W. Polystyrene foamed plastic wall apparatus and method of construction
US5689927A (en) * 1997-01-22 1997-11-25 Knight, Sr.; Larry E. Concrete post usable with a sound barrier fence
US6371699B1 (en) * 1997-10-16 2002-04-16 Durisol Inc. Anchored retaining wall system
US6554544B1 (en) * 1999-02-10 2003-04-29 Barkasz Sandor Method to build a water seal, creep-line increasing cutoff

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20190136481A1 (en) * 2017-11-06 2019-05-09 Richard J. Gagliano Foundation integral construction components and support systems

Also Published As

Publication number Publication date
GB0124991D0 (en) 2001-12-05
GB2381014A (en) 2003-04-23
GB0223647D0 (en) 2002-11-20

Similar Documents

Publication Publication Date Title
US6719492B1 (en) Top arch overfilled system
US3184893A (en) Contact foundation method
CA2036832C (en) Pinned foundation system
US4290246A (en) Multi-purpose precast concrete panels, and methods of constructing concrete structures employing the same
US4887691A (en) Modular wall construction using posts and panels
US5528877A (en) Concrete building frame construction method
JP3828153B2 (en) Underground structure for constructing tunnels, underground passages, underground parking lots, etc., construction method thereof, and prefabricated member for the structure
US6503024B2 (en) Concrete foundation pierhead and method of lifting a foundation using a jack assembly
CN201125354Y (en) Steep hill road bed branch block reinforced structure
AU2014237379B2 (en) Precast concrete retaining wall
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
CN100489198C (en) Prestressed scaffolding system
US6503025B1 (en) Precast concrete beam element and methods of making and installing same
US3226933A (en) Sheeting wall system and method of constructing same
US6988337B1 (en) Means and method for constructing a fully precast top arch overfilled system
US6659692B1 (en) Apparatus and method for supporting a structure with a pier and helix
US6299386B1 (en) Method and apparatus for a shoring wall
US20030185634A1 (en) Synthetic deformed bars and retaining walls
WO2010019014A2 (en) Method for constructing a chair-type, self-supported earth retaining wall
CA2425811A1 (en) Modular wall system with footing form
CA1046297A (en) Precast element for the construction of trenched structures and the process related thereto
EP1123443B1 (en) Method for manufacturing a ground slab field and a ground slab field
KR100633796B1 (en) Connecting structure of mid supporting beam for temporary soil sheathing work
US7500807B2 (en) Method of construction using sheet piling sections
WO2007058463A1 (en) Apparatus for fixing a wale

Legal Events

Date Code Title Description
AS Assignment

Owner name: CEMENTATION FOUNDATION SKANSKA LIMITED, UNITED KIN

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SHOTTON, PETER GILBERT;REEL/FRAME:013780/0979

Effective date: 20021029

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION