KR102216972B1 - Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation - Google Patents

Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation Download PDF

Info

Publication number
KR102216972B1
KR102216972B1 KR1020190046172A KR20190046172A KR102216972B1 KR 102216972 B1 KR102216972 B1 KR 102216972B1 KR 1020190046172 A KR1020190046172 A KR 1020190046172A KR 20190046172 A KR20190046172 A KR 20190046172A KR 102216972 B1 KR102216972 B1 KR 102216972B1
Authority
KR
South Korea
Prior art keywords
foundation
concrete structure
pile
exposed
construction
Prior art date
Application number
KR1020190046172A
Other languages
Korean (ko)
Other versions
KR20200122850A (en
Inventor
박완서
김병준
조영욱
강순종
Original Assignee
삼성물산 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼성물산 주식회사 filed Critical 삼성물산 주식회사
Priority to KR1020190046172A priority Critical patent/KR102216972B1/en
Publication of KR20200122850A publication Critical patent/KR20200122850A/en
Application granted granted Critical
Publication of KR102216972B1 publication Critical patent/KR102216972B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable
    • E02D2450/106Membranes impermeable for liquids
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

본 발명은 건축물 기초의 시공 방법에 관한 것이다. 기초 콘크리트 구조물 시공 후 인근 지반의 굴착 공사가 진행되어 상기 기초 콘크리트 구조물 하부의 파일이 노출되는 경우, 기초파일 내력 저감 및 사면의 변위 발생 가능성에 따른 상부 골조 안전성 확보 등의 문제점에 대하여, 사전에 기초 콘크리트 구조물 하부의 굴착이 예상되는 구역을 파악한 뒤, 상기 구역 내 위치한 기초 콘크리트 구조물 시공 시 연결빔으로 다른 기초 콘크리트 구조물과 연결하고, 시공 단계별 해석을 통한 기초파일 설계와 사면 안정화 조치 등을 통하여 문제점을 해소할 수 있는 건축물 기초의 시공 방법에 관한 것이다. 이를 통해 사면 굴착 이후, 되메우기 작업과 무관하게 기초파일이 노출된 구역에 대해서도 상부 골조공사를 동시에 진행하여 공기 단축 및 비용 절감을 도모할 수 있다.The present invention relates to a method of constructing a foundation for a building. If the piles under the foundation concrete structure are exposed after the construction of the foundation concrete structure, if the piles under the foundation concrete structure are exposed, for problems such as reducing the strength of the foundation piles and securing the safety of the upper frame due to the possibility of displacement of slopes, After identifying the area where excavation is expected under the concrete structure, when constructing the foundation concrete structure located in the area, connect it with other foundation concrete structures with a connecting beam, and solve the problem through the foundation pile design and slope stabilization measures through construction step analysis. It relates to the construction method of the foundation of a building that can be solved. Through this, after the excavation of the slope, regardless of the backfilling operation, the upper frame construction can be simultaneously performed on the area where the foundation pile is exposed, thereby reducing construction time and cost.

Description

공사 중 인근 지반의 굴착으로 파일의 노출이 예상되는 구역의 기초 시공 방법{Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation }Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation}

본 발명은 건축물의 기초 시공방법에 관한 것이다. 건축물 기초의 지반고가 구역별로 상이하여 인접한 기초 구조물 사이에서 단차가 발생하는 경우, 인접 지반의 굴착 공사로 인해 부득이하게 기시공된 기초 구조물 하부의 파일이 노출될 수 있다. 이러한 상황에서 종래의 시공방법이 가지는 문제점을 해소하고, 파일이 노출된 상태로 기초 상부의 골조공사를 진행할 수 있도록 기초 구조물을 보강하는 시공방법에 관한 것이다.The present invention relates to a basic construction method of a building. When the ground height of the foundation of a building is different for each zone and a step occurs between adjacent foundation structures, the piles under the previously constructed foundation structure may inevitably be exposed due to excavation work on the adjacent ground. In this situation, it relates to a construction method of reinforcing a foundation structure so as to solve the problems of the conventional construction method, and to proceed with the frame construction of the upper part of the foundation with the pile exposed.

일반적인 건축물 시공에 있어서, 그 건축물의 기둥과 벽을 지지하고 기둥과 벽의 뒤틀림 응력에 의해 건축물에 균열이 발생하거나 건축물이 기울어지는 것을 방지하며, 건축물의 하중을 지반에 고르게 분산시키기 위해 기초 구조물 공사를 한다. 건축물의 기초공사는 건축물의 하중을 직접 전달받는 최저층 영역의 공사로써 최저층 하부에 기초 구조물을 시공하는데, 주로 파일과 콘크리트 구조체의 조합으로 구성된다.In general building construction, basic structure construction to support the columns and walls of the building, to prevent the building from cracking or tilting due to the torsion stress of the column and wall, and to evenly distribute the load of the building to the ground. Do it. The foundation work of a building is the construction of the lowest floor area that directly receives the load of the building, and the foundation structure is constructed under the lowest floor, mainly composed of a combination of piles and concrete structures.

파일은 지중에 관입되는 콘크리트 기둥으로 말할 수 있으며, 지상 구조물의 하중을 지반에 전달하는 역할을 하고, 관입 깊이는 지반의 성질 및 파일의 종류에 따라 설계하여 정해진다. The pile can be said to be a concrete column penetrating the ground, and it serves to transmit the load of the above-ground structure to the ground, and the penetration depth is determined by designing according to the nature of the ground and the type of pile.

종래에 일반적으로, 건축물 하중에 의한 지반 침하를 방지하고 단단한 지반을 조성하기 위해 파일을 지중에 시공하고, 시공된 파일 상부에 파일과 연결된 기초 콘크리트 구조물을 시공한다. 이와 같은 기초공사가 완성된 후 그 기초 콘크리트 구조물의 상부에 건축물의 뼈대를 이루는 골조공사가 진행되며 이때 기초 콘크리트 구조물은 상부 골조의 하중을 지반에 안정적으로 전달해야 하므로 지면에 안착되어 있어야 한다.Conventionally, in general, a pile is constructed in the ground to prevent ground subsidence due to a building load and to create a solid ground, and a foundation concrete structure connected to the pile is constructed on the top of the constructed pile. After such a foundation work is completed, the frame work that forms the frame of the building is carried out on the upper part of the base concrete structure. At this time, the base concrete structure must be seated on the ground because the load of the upper frame must be stably transmitted to the ground.

한편, 건축물의 지하층이 평면상 구역별로 깊이를 달리할 때는 서로 인접한 기초 콘크리트 구조물이 각각 지반고를 달리하여 단차가 발생할 수 있다. 이때 지반고가 더 낮은 기초 콘크리트 구조물의 시공을 위해 지반을 굴착하게 되면, 깊게 굴착할수록 사면이 넓게 형성되면서 기시공된 인접한 다른 기초 콘크리트 구조물 하부의 토사가 굴착될 수밖에 없는 상황이 발생한다.On the other hand, when the basement layer of a building has a different depth for each area on the plane, the level difference may occur due to the different ground heights of the foundation concrete structures adjacent to each other. At this time, when the ground is excavated for the construction of a foundation concrete structure with a lower ground height, the deeper the excavation is, the wider the slope is formed, resulting in a situation in which the soil under the previously constructed adjacent foundation concrete structure is inevitably excavated.

이와 같은 상황에서 인접한 기초 콘크리트 구조물 하부의 파일 상단이 지상으로 노출되며, 이때 노출된 파일의 내력 저감 및 굴착 사면의 변위 발생 가능성에 따른 상부 골조 안정성 확보 등의 문제가 발생하므로 상기 인접한 기초 콘크리트 구조물은 상부의 골조공사를 진행할 수 있을 만큼 안정적이지 않다.In such a situation, the top of the pile under the adjacent foundation concrete structure is exposed to the ground, and at this time, problems such as reducing the strength of the exposed pile and securing the stability of the upper frame according to the possibility of displacement of the excavation slope occur. It is not stable enough to proceed with the upper frame construction.

도 1의 (a) 내지 (g)는 상기와 같은 상황에서 종래의 일반적인 시공순서를 도시한다.1 (a) to (g) shows a conventional general construction procedure in the above-described situation.

도 1의 (d)를 참고하면, 기초 콘크리트 구조물(130)은 그 하부의 기초파일(121)이 지상으로 노출된 상태에 해당하여 상부의 골조 공사가 불가능하다. 따라서, 종래의 시공법은 도 1의 (e)와 같이 굴착 사면의 하단부에 콘크리트 벽체(140)를 시공하고, 도 1의 (f)와 같이 기초 콘크리트 구조물(130) 하부를 토사로 되메우기(150)하며, 그 이후에야 비로소 도 1의 (g)에 도시된 것처럼 상부의 골조공사(160)를 진행할 수 있었다.Referring to (d) of FIG. 1, the foundation concrete structure 130 corresponds to a state in which the foundation pile 121 of the lower part is exposed to the ground, so that the upper frame construction is impossible. Therefore, the conventional construction method constructs the concrete wall 140 at the lower end of the excavation slope as shown in FIG. 1(e), and backfills the lower part of the foundation concrete structure 130 with soil as shown in FIG. 1(f) (150) And, only after that it was possible to proceed with the upper frame construction 160 as shown in Figure 1 (g).

그러나 콘크리트 벽체의 규모가 클수록 철근 조립 및 콘크리트의 타설과 양생을 여러 차례 반복하고, 콘크리트 벽체가 상당한 강도를 확보할 때까지 토사 되메우기를 할 수도 없어, 기초 상부의 골조공사를 착수하기 전 상당한 공기가 지연되는 문제가 있다.However, as the size of the concrete wall increases, reinforcement assembly and concrete pouring and curing are repeated several times, and the soil cannot be backfilled until the concrete wall has secured considerable strength. There is a problem of delay.

등록특허 제10-1105883호(공고일자: 2012.01.16.)Registered Patent No. 10-1105883 (announcement date: 2012.01.16.) 등록특허 제10-1220811호(공고일자: 2013.01.11.)Registration Patent No. 10-1220811 (announcement date: 2013.01.11.) 공개특허 제10-2014-0067312호(공개일자: 2014.06.05.)Publication Patent No. 10-2014-0067312 (Publication date: 2014.06.05.)

본 발명은 이러한 종래기술의 문제점을 개선하기 위한 것으로, 건축물의 기초공사 과정에서 지반고가 서로 다른 인접한 기초 콘크리트 구조물 사이의 단차로 인해 기초파일이 노출된 기초 콘크리트 구조물이 있을 경우라도 그 기초 콘크리트 구조물의 상부에 골조공사를 진행할 수 있도록 기초공사의 공법을 개선하는 방법을 제공하는 데 그 목적이 있다.The present invention is to improve the problems of the prior art, even if there is a foundation concrete structure in which the foundation pile is exposed due to a step difference between adjacent foundation concrete structures having different ground heights during the foundation construction process of a building, Its purpose is to provide a method of improving the construction method of the foundation construction so that the upper frame construction can be carried out.

이러한 목적을 달성하기 위한 본 발명에 따른 기초 시공 방법은, (a) 기초 콘크리트 구조물 하부 토사 굴착으로 상기 기초 콘크리트 구조물의 기초파일이 노출될 것으로 예정되는 구역을 설정하는 제1단계와; (b) 제1단계 설정구역에 위치하는 기초파일을 시공하는 제2단계; (c) 제2단계에서 시공된 기초파일의 상단과 연결되는 기초 콘크리트 구조물을 시공하는 제3단계; (d) 제1단계 설정구역에 위치한 상기 기초 콘크리트 구조물을 인접한 다른 기초 콘크리트 구조물과 연결빔으로 연결하는 제4단계; (e) 제3단계에서 형성된 기초 콘크리트 구조물의 콘크리트 강도가 확보된 후, 제1단계 설정구역의 토사가 굴착되어 상기 기초 콘크리트 구조물 기초파일의 적어도 일부가 지상으로 노출되는 제5단계; (f) 제5단계 기초 콘크리트 구조물의 상부 골조공사를 진행하는 제6단계;를 포함하며, 상기의 기초 콘크리트 구조물은 상기 연결빔과 연결하기 위해 조인트가 매입되는 것을 특징으로 한다.The foundation construction method according to the present invention for achieving this object includes: (a) a first step of setting an area in which the foundation pile of the foundation concrete structure is expected to be exposed by earth and sand excavation under the foundation concrete structure; (b) a second step of constructing a foundation pile located in the first step setting area; (c) a third step of constructing a foundation concrete structure connected to the top of the foundation pile constructed in the second step; (d) a fourth step of connecting the base concrete structure located in the first step setting area to another adjacent base concrete structure with a connecting beam; (e) a fifth step in which at least a part of the foundation pile of the foundation concrete structure is exposed to the ground by excavating the soil in the first stage setting area after the concrete strength of the foundation concrete structure formed in the third stage is secured; (f) a sixth step of proceeding the upper frame construction of the fifth step of the basic concrete structure, wherein the basic concrete structure is characterized in that the joint is embedded in order to connect with the connecting beam.

바람직하게는, 제5단계와 제6단계 사이에 기초파일이 노출된 기초 콘크리트 구조물과 상기 기초파일 및 연결빔에 변위 측정계 및 응력 측정계를 설치하여 실시간 모니터링 시스템을 구축한다.Preferably, a real-time monitoring system is constructed by installing a displacement measuring system and a stress measuring system on the foundation concrete structure in which the foundation pile is exposed between the fifth and sixth stages, and the foundation pile and the connecting beam.

이를 통해 사면 굴착 이후, 되메우기 작업과 무관하게 기초파일이 노출된 구역에 대해서도 상부 골조공사를 동시에 진행하여 공기 단축 및 비용 절감을 도모할 수 있다.Through this, after the excavation of the slope, regardless of the backfilling operation, the upper frame construction can be simultaneously performed on the area where the foundation pile is exposed, thereby reducing construction time and cost.

본 발명에 따른 건축물 기초공사 방법에 따르면, 건축물 기초의 시공순서에 따라 부득이 일부 기초 콘크리트 구조물의 기초파일이 노출되는 상황이 발생하더라도 콘크리트 벽체 공사와 관계없이 상부에서 골조공사를 곧바로 진행할 수 있으므로 공사 기간을 단축하고 비용을 절감할 수 있다.According to the method for foundation construction of a building according to the present invention, even if a situation in which the foundation piles of some basic concrete structures are unavoidably exposed according to the construction order of the foundation of the building, the construction period can proceed immediately from the upper part regardless of the concrete wall construction. Can shorten and reduce costs.

도 1의 (a) 내지 (g)는 종래 일반적인 기초공사 시공순서를 간략히 보여주는 도면이다.
도 2의 (a) 내지 (f)는 본 발명의 실시예에 따른 기초공사 시공순서를 간략히 보여주는 도면이다.
도 3은 본 발명의 실시예에 따른 사면 보강 공법의 개념도이다.
도 4는 본 발명의 실시예에 따른 모니터링 시스템의 개념도이다.
도 5는 본 발명의 실시예에 따른 기초 콘크리트 구조물과 연결빔의 연결 부위 개념도이다.
(A) to (g) of Figure 1 is a view briefly showing the construction procedure of a conventional general foundation work.
Figure 2 (a) to (f) is a view briefly showing the construction procedure of the foundation according to the embodiment of the present invention.
3 is a conceptual diagram of a slope reinforcement method according to an embodiment of the present invention.
4 is a conceptual diagram of a monitoring system according to an embodiment of the present invention.
5 is a conceptual diagram illustrating a connection part between a basic concrete structure and a connecting beam according to an embodiment of the present invention.

본 발명의 개념에 따른 실시예들은 다양한 형태로 실시될 수 있다. 또한, 본 명세서에 설명된 실시예들에 한정되는 것으로 해석되어서는 아니 되며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경물, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다. Embodiments according to the concept of the present invention may be implemented in various forms. In addition, it should not be construed as being limited to the embodiments described in the present specification, and should be understood to include all changes, equivalents, and substitutes included in the spirit and scope of the present invention.

어떠한 구성요소가 다른 구성요소에 "연결되어"있다거나 "접속되어"있다고 언급된 때에는, 그 다른 구성요소에 직접적으로 연결되어 있거나 접속되어 있을 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떠한 구성요소가 다른 구성요소에 "직접 연결되어"있다거나 또는 "직접 접촉되어"있다고 언급된 때에는, 중간에 다른 구성요소가 존재하지 않는 것으로 이해되어야 할 것이다. 구성요소 간의 관계를 설명하기 위한 다른 표현들, 즉 "~사이에"와 "바로 ~사이에" 또는 "~에 인접하는"과 "~에 직접 인접하는" 등의 표현도 마찬가지로 해석되어야 한다. When a component is referred to as being "connected" or "connected" to another component, it should be understood that it may be directly connected or connected to the other component, but other components may exist in the middle. something to do. On the other hand, when a component is referred to as being "directly connected" or "directly in contact" with another component, it should be understood that there is no other component in the middle. Other expressions for describing the relationship between components, that is, expressions such as "between" and "directly between" or "adjacent to" and "directly adjacent to" should be interpreted as well.

본 명세서에서 사용하는 용어와 도면의 표현은 단지 특정한 실시예를 설명하기 위해 사용된 것으로서, 본 발명을 한정하려는 의도가 아니다. 단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한, 복수의 표현을 포함한다. The terms and expressions in the drawings used in the present specification are only used to describe specific embodiments, and are not intended to limit the present invention. Singular expressions include plural expressions unless the context clearly indicates otherwise.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예에 따른 건축물 기초공사 시공 방법에 대하여 구체적으로 설명한다.Hereinafter, a method of constructing a foundation for a building according to a preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 2의 (a) 내지 (f)는 본 발명의 실시예에 따른 기초공사 시공순서를 간략히 도시하는 도면이다. 2A to 2F are diagrams briefly showing the construction procedure of a foundation work according to an embodiment of the present invention.

도 2에 예시된 것과 같이, 본 발명의 건축물 기초의 시공 방법은, 기초 콘크리트 구조물 하부의 지반이 굴착되어 기초파일의 노출이 예상되는 구역의 건축물 기초공사에 있어서, (a) 기초 콘크리트 구조물 하부 토사 굴착으로 상기 기초 콘크리트 구조물의 기초파일이 노출될 것으로 예정되는 구역을 설정하는 제1단계; (b) 제1단계 설정구역에 위치하는 기초파일을 시공하는 제2단계; (c) 제2단계에서 시공된 기초파일의 상단과 연결되는 기초 콘크리트 구조물을 시공하는 제3단계; (d) 제1단계 설정구역에 위치한 상기 기초 콘크리트 구조물을 인접한 다른 기초 콘크리트 구조물과 연결빔으로 연결하는 제4단계; (e) 제3단계에서 형성된 기초 콘크리트 구조물의 콘크리트 강도가 확보된 후, 제1단계 설정구역의 토사가 굴착되어 상기 기초 콘크리트 구조물 하부 기초파일의 적어도 일부가 지상으로 노출되는 제5단계; 및 (f) 제5단계의 기초 콘크리트 구조물의 상부 골조공사를 진행하는 제6단계;를 포함하며, 이러한 기초 콘크리트 구조물은 상기 연결빔과 연결하기 위해 콘크리트 타설 전 조인트가 매입된 것을 특징으로 한다.As illustrated in FIG. 2, in the construction method of the foundation of the building of the present invention, in the foundation construction of a building in an area where the foundation pile is expected to be exposed due to excavation of the ground under the foundation concrete structure, (a) the soil under the foundation concrete structure A first step of setting an area in which the foundation pile of the foundation concrete structure is expected to be exposed by excavation; (b) a second step of constructing a foundation pile located in the first step setting area; (c) a third step of constructing a foundation concrete structure connected to the top of the foundation pile constructed in the second step; (d) a fourth step of connecting the base concrete structure located in the first step setting area to another adjacent base concrete structure with a connecting beam; (e) a fifth step in which at least a part of the foundation pile under the foundation concrete structure is exposed to the ground by excavating the soil in the first stage setting area after the concrete strength of the foundation concrete structure formed in the third stage is secured; And (f) a sixth step of proceeding the upper frame construction of the basic concrete structure of the fifth step; including, and the basic concrete structure is characterized in that the joint is embedded before concrete pouring to connect with the connecting beam.

이하, 각 공정에 대해 구체적으로 살펴본다.Hereinafter, each process will be described in detail.

도 2의 (a)를 참조하면, 제1단계는 현장 시공에 착수하기 전 건축물 기초 설계에 따라 가장 효율적인 시공순서와 굴착계획을 수립하는 단계이다. 넓은 지역 기초공사의 경우는 토사 굴착과 구조물 시공이 동시에 이루어지므로 공정간 간섭이 이루어지지 않도록 유의한다.Referring to Figure 2 (a), the first step is a step of establishing the most efficient construction sequence and excavation plan according to the foundation design of the building before starting the on-site construction. In the case of a large-area foundation work, be careful not to interfere between processes because the excavation of soil and the construction of the structure are performed simultaneously.

이러한 계획 과정에서 굴착 깊이의 차이로 인해 지면에 단차가 발생하는 구역을 파악할 수 있고, 공정상 기초 콘크리트 구조물(30)의 시공이 완료된 후 그 하부 토사의 굴착이 이루어져 기초 콘크리트 구조물 하부 기초파일(21)이 노출되는 상황을 예상할 수 있다. 즉, 굴착계획을 수립하는 과정에서 굴착예정면(11)을 파악하고 현장의 평면도 상에서 기초 콘크리트 구조물 하부 기초파일(21)의 노출이 예정된 구역을 설정할 수 있다.In this planning process, it is possible to identify the area where the level difference occurs on the ground due to the difference in the excavation depth, and after the construction of the foundation concrete structure 30 is completed in the process, excavation of the lower soil is performed, and the foundation pile 21 under the foundation concrete structure is completed. ) Can be expected. That is, in the process of establishing an excavation plan, it is possible to identify the planned excavation surface 11 and set the area in which the foundation pile 21 under the foundation concrete structure is scheduled to be exposed on the floor plan of the site.

도 2의 (b)를 참조하면, 제2단계는 지반에 기초파일(20)을 시공하는 단계이다. 기초파일은 건축물의 설계 하중에 따른 충분한 지지력을 얻을 수 있도록 적절한 개수와 시공 깊이가 산정된다. 기초파일의 종류와 시공 방법은 여러 가지가 있으며, 담당자는 비용과 공기를 최소화하는 관점에서 현장의 여건과 설계 검토 내용을 반영하여 최적의 선택을 할 것이다.2(b), the second step is a step of constructing the foundation pile 20 on the ground. The number of foundation piles and construction depth are calculated to obtain sufficient support according to the design load of the building. There are various types of foundation piles and construction methods, and the person in charge will make the optimal selection by reflecting the site conditions and design review contents from the viewpoint of minimizing cost and construction time.

일반적으로 파일 시공은 현장에서 콘크리트를 타설한 후 양생하는 방식(현장타설말뚝)과 기성품인 PHC파일(Pretensioned spun High strength Concrete Piles)을 항타 또는 천공하여 지중에 관입하는 방식이 있다. 본 실시예에서는 설계에 따라 어떠한 형태의 기초파일 시공도 가능하다.In general, there are two types of pile construction: a method of curing after pouring concrete at the site (laying on site piles) and a method of driving or drilling ready-made PHC piles (Pretensioned spun High strength Concrete Piles) to penetrate the ground. In this embodiment, it is possible to construct any type of foundation pile according to the design.

추후 굴착공사로 인해 노출이 예상되는 파일의 경우, 해당 파일의 휨모멘트 강도는 강할수록 좋으며 PHC파일은 유효 프리스트레스가 80 kg/㎠(B종) 이상의 것을 사용하는 것이 바람직하다. 그리고, 기초 콘크리트 구조물 하부 기초파일(21)의 경우에는 굴착 후에도 사면 하단으로부터 10m 이상 근입 되도록 설계하는 것이 바람직하다.In the case of piles that are expected to be exposed due to future excavation work, the stronger the bending moment strength of the pile is, the better, and it is preferable to use a PHC pile with an effective prestress of 80 kg/㎠ (Class B) or more. In addition, in the case of the foundation pile 21 under the foundation concrete structure, it is preferable to design it to be near the bottom of the slope by 10m or more even after excavation.

도 2의 (c)를 참조하면, 제3단계는 기초파일(20) 시공 후 기초 콘크리트 구조물(30)을 시공하는 단계이다. 이는 통상적인 방법의 콘크리트 구조물 시공으로써 파일의 두부를 정리하고, 기초 콘크리트 구조물(30)의 철근을 배근한 뒤, 거푸집을 설치하고 콘크리트를 타설하는 방식이다. 이때 도 2의 (d)에서 연결빔(40)과 연결되는 제4단계 고려하여 연결빔(40)과 연결되는 부분에 미리 조인트(42)를 매입한 뒤 콘크리트를 타설한다.Referring to (c) of FIG. 2, the third step is a step of constructing the foundation concrete structure 30 after the foundation pile 20 is constructed. This is a method of arranging the head of a pile by constructing a concrete structure according to a conventional method, reinforcing the reinforcing bars of the foundation concrete structure 30, installing a formwork, and pouring concrete. In this case, in consideration of the fourth step of connecting the connecting beam 40 in FIG. 2(d), the joint 42 is pre-embedded in the portion connected to the connecting beam 40 and then concrete is poured.

도 5를 참조하면, 본 발명의 실시예에 따른 기초 콘크리트 구조물(30)에 매입된 조인트(42)가 도시되어 있다. 상기 기초 콘크리트 구조물(30)에 매입되는 조인트(42)는 H빔을 사용할 수 있다. H빔 일단의 플랜지에 스터드 볼트를 체결한 뒤, 기초 콘크리트 구조물(30)에 매입시키고, 상기 H빔의 타단을 기초 콘크리트 구조물 외부로 노출한다. 노출된 부분은 연결빔(40)과 연결되는 부분에 해당한다. 조인트(42)가 기초 콘크리트 구조물(30)에 매입되는 길이는 구조 설계를 검토하여 정할 수 있을 것이다.5, a joint 42 embedded in the basic concrete structure 30 according to an embodiment of the present invention is shown. The joint 42 embedded in the basic concrete structure 30 may use an H beam. After fastening the stud bolt to the flange of one end of the H beam, it is embedded in the basic concrete structure 30, and the other end of the H beam is exposed to the outside of the basic concrete structure. The exposed part corresponds to a part connected to the connecting beam 40. The length at which the joint 42 is embedded in the basic concrete structure 30 may be determined by examining the structural design.

도 2의 (d)를 참조하면, 제4단계는 상기 기초 콘크리트 구조물(30)의 시공 후 설정구역(13) 내 위치한 상기 기초 콘크리트 구조물(30)을 인접한 다른 기초 콘크리트 구조물(31)과 연결빔(40)을 이용하여 연결하는 단계이다.Referring to (d) of FIG. 2, the fourth step is to connect the basic concrete structure 30 located in the setting area 13 after the construction of the basic concrete structure 30 to the adjacent other basic concrete structure 31 This is the step of connecting using (40).

현장의 공사는 여러 구역에서 동시다발적으로 이루어지므로 설정구역(13) 내 위치한 기초 구조물 외에 다른 구역도 설계 내용에 따라 독립한 다른 기초 콘크리트 구조물(31) 또는 기초 매트 콘크리트 구조물(32) 시공이 진행된다.Since construction on the site is performed simultaneously in several areas, construction of other basic concrete structures (31) or foundation mat concrete structures (32) that are independent in accordance with the design content in addition to the foundation structures located in the set area (13) is in progress. do.

상기의 다른 기초 콘크리트 구조물(31)은 설정구역(13) 내 위치하지 않은 매트형식 또는 독립 형식의 기초 구조물일 수 있으며, 설정구역(13) 내 위치하는 기초파일이 노출된 상태의 기초 콘크리트 구조물일 수도 있다.The other foundation concrete structure 31 above may be a mat type or independent type foundation structure that is not located in the setting area 13, and is a foundation concrete structure in a state where the foundation pile located in the setting area 13 is exposed. May be.

연결빔(40)의 길이, 단면형상, 좌굴계수 등의 규격과 연결빔(40)의 개수는 현장 여건과 설계검토를 통해 정해질 수 있다. 일례로, 연결빔(40)은 H빔을 사용할 수도 있으며, 도 5에 연결빔(40)과 조인트(42)가 체결된 연결부(43)의 모습이 도시되어 있다.The length, cross-sectional shape, buckling coefficient, etc. of the connecting beam 40 and the number of connecting beams 40 may be determined through site conditions and design review. As an example, the connecting beam 40 may use an H-beam, and FIG. 5 shows the connecting portion 43 to which the connecting beam 40 and the joint 42 are fastened.

본 발명의 실시예에 따르면, 기초 콘크리트 구조물(30)에 매입되는 조인트(42)와 연결빔(40)은 용접 또는 볼트에 의해 연결하거나, 작용하는 응력을 효율적으로 전달할 수 있는 다양한 방법으로 연결이 가능할 것이다.According to an embodiment of the present invention, the joint 42 and the connecting beam 40 embedded in the basic concrete structure 30 are connected by welding or bolts, or in various ways to efficiently transmit the applied stress. It will be possible.

도 2의 (e)를 참조하면, 제5단계는 연결빔(40)의 연결이 완료된 후 상기 기초 콘크리트 구조물(30)의 콘크리트 강도가 발현되면 굴착예정지역을 굴착하는 단계이다. 콘크리트 강도가 확보되어야 굴착 후에도 구조물의 변형을 최소화할 수 있으며, 필요한 강도는 현장 담당자의 판단 또는 설계 검토하여 정할 수 있다.Referring to (e) of Figure 2, the fifth step is a step of excavating an area to be excavated when the concrete strength of the basic concrete structure 30 is expressed after the connection of the connecting beam 40 is completed. When the strength of concrete is secured, deformation of the structure can be minimized even after excavation, and the required strength can be determined by judgment or design review by the person in charge of the site.

이 단계에서 상기 기초 콘크리트 구조물(30)의 하부 토사가 굴착되므로 상기 기초 콘크리트 구조물 하부 기초파일(21)이 외부로 노출된다.In this step, since the soil under the foundation concrete structure 30 is excavated, the foundation pile 21 under the foundation concrete structure is exposed to the outside.

한편, 굴착으로 인해 형성된 사면(14)은 기시공된 기초파일(20) 및 지하수의 침투를 고려하여 사면 안정 해석을 검토함이 바람직하며, 상기 기시공된 기초파일(20)의 안정성 또한 검토할 수 있다. 굴착 전이라고 하더라도 사면 안정 해석을 통해 안정한 사면(14)의 경사와 소단의 개수 등을 계획할 수 있다.On the other hand, for the slope 14 formed by excavation, it is preferable to review the slope stability analysis in consideration of the previously constructed foundation pile 20 and the penetration of groundwater, and the stability of the previously constructed foundation pile 20 should also be reviewed. I can. Even before excavation, the slope of the stable slope 14 and the number of benches can be planned through slope stability analysis.

형성된 사면(14)은 굴착 공간을 되메우기할 때까지 안정한 상태로 유지되어야 하므로 사면 안정화 작업이 필요하며, 일례로 도3에 도시된 것과 같이 사면 전체에 방수포(16)를 설치하여 외부의 교란을 차단하고 사면 하단부의 유실을 방지하기 위한 톤백(15) 설치가 가능하다. 이외에도 사면 안정화 목적의 여러 공법을 활용할 수 있다.Since the formed slope 14 must be maintained in a stable state until the excavation space is refilled, slope stabilization is required.For example, as shown in Fig. 3, a tarpaulin 16 is installed on the entire slope to block external disturbances. It is possible to install a tone bag 15 to prevent loss of the lower part of the slope. In addition, various construction methods for slope stabilization purposes can be used.

도 2의 (f)를 참조하면, 제6단계는 기초파일이 노출된 상태의 기초 구조물의 상부에서 골조공사가 진행되는 단계이다. 이 경우, 골조의 하중에 의한 외력으로 구조물의 변형이 올 가능성이 존재한다. 따라서, 구조물의 안전성을 담보하기 위해 실시간으로 외력에 의한 변형을 계측할 수 있는 시스템을 구축하는 것이 바람직하다.Referring to (f) of Figure 2, the sixth step is a step in which the frame work is performed on the top of the foundation structure in a state where the foundation pile is exposed. In this case, there is a possibility that the structure may be deformed due to external force caused by the load on the frame. Therefore, in order to ensure the safety of the structure, it is desirable to construct a system capable of measuring deformation due to external force in real time.

도 4를 참조하면, 본 발명의 실시예에 따른 계측기 설치 모습이 도시되어 있다. 계측은 상기 기초 콘크리트 구조물(30) 하부의 굴착된 공간을 되메우기할 때까지 이루어져야 한다. 상기 기초 콘크리트 구조물(30) 및 상기 기초 콘크리트 구조물 하부 기초파일(21)의 횡방향 변위를 측정해야 하며, 상기 기초 콘크리트 구조물(30)과 상기 기초 콘크리트 구조물 하부 기초파일(21)의 측면에 타겟(33)을 설치하고, 정기적으로 매주 2회 이상 측정하는 것이 바람직하다.Referring to FIG. 4, there is shown an installation of a measuring instrument according to an embodiment of the present invention. Measurement should be made until the excavated space under the foundation concrete structure 30 is backfilled. It is necessary to measure the lateral displacement of the foundation concrete structure 30 and the foundation pile 21 under the foundation concrete structure, and a target on the side of the foundation concrete structure 30 and the foundation pile 21 under the foundation concrete structure ( 33) is installed, and it is desirable to measure at least twice a week on a regular basis.

상기 기초 콘크리트 구조물 하부 기초파일(21)의 횡 방향 변형 측정을 위해 EL. Beam(22)을 이용할 수 있으며, 연결빔(40)의 경우에는 응력측정기(41)를 설치하여 연결빔(40)에서 받는 응력을 주기적으로 측정한다. 허용 가능한 변위 및 응력값은 설계 검토를 통해 정할 수 있고 변위 또는 응력이 허용 값을 초과한 경우 상부의 골조(60)공사를 중단하고 일련의 보강 작업을 통해 안전성을 확보해야 할 것이다. 보강 방법으로는 연결빔(40)의 개수를 추가하거나 굴착 구역 일부를 되메우는 방법을 고려해 볼 수 있다.EL. To measure the transverse deformation of the foundation pile (21) under the foundation concrete structure. A beam 22 can be used, and in the case of the connecting beam 40, a stress meter 41 is installed to periodically measure the stress received from the connecting beam 40. Allowable displacement and stress values can be determined through design review, and if displacement or stress exceeds the allowable values, the construction of the upper frame 60 should be stopped and safety should be secured through a series of reinforcement works. As a reinforcement method, a method of adding the number of connecting beams 40 or filling a part of the excavation area may be considered.

본 발명에 따른 실시예에 의한 공법 시행 시 지상층 공사에 따른 설계 하중이 고려될 것이며, 그에 따라 기초파일(20)의 최대 노출 가능한 길이 계산이 가능하다.When implementing the construction method according to the embodiment of the present invention, the design load according to the ground floor construction will be considered, and accordingly, the maximum exposure length of the foundation pile 20 can be calculated.

이상에서 설명한 본 발명은 전술한 실시예 및 첨부된 도면에 의해 한정되는 것이 아니다. 또한, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 여러 형태로 치환, 변형 및 변경 가능함은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 명백할 것이다.The present invention described above is not limited by the above-described embodiments and the accompanying drawings. In addition, it will be apparent to those of ordinary skill in the art that the present invention can be substituted, modified, and changed in various forms without departing from the technical spirit of the present invention.

10:지반
11:굴착예정면
12:굴착면
13:설정구역
14:사면
15:톤백
16:방수포
20:기초파일
21:기초 콘크리트 구조물 하부 기초파일
22:El. Beam
30:기초 콘크리트 구조물
31:다른 기초 콘크리트 구조물
32:기초 매트 콘크리트 구조물
33:타겟
40:연결빔
41:응력측정기
42:조인트
43:연결부
50:사면 하단부 구조물 공사
60:골조
110:지반
111:굴착예정면
112:굴착면
120:기초파일
121:기초 콘크리트 구조물 하부 기초파일
130:기초 콘크리트 구조물
131:다른 기초 콘크리트 구조물
132:기초 매트 콘크리트 구조물
140:콘크리트 벽체
150:되메우기
160:골조
170:다른 구역 구조물 공사
10: ground
11: To be excavated
12: Excavation surface
13: Setting area
14: Slope
15: Tone bag
16: waterproof cloth
20: Basic file
21: Foundation pile under the basic concrete structure
22:El. Beam
30: Basic concrete structure
31: other foundation concrete structures
32: foundation mat concrete structure
33: target
40: connecting beam
41: stress meter
42: joint
43: connection
50: Slope lower part structure construction
60: frame
110: ground
111: The surface to be excavated
112: Excavation surface
120: basic file
121: foundation pile under the basic concrete structure
130: basic concrete structure
131: other foundation concrete structures
132: Foundation mat concrete structure
140: concrete wall
150: backfill
160: frame
170: Construction of structures in other areas

Claims (4)

기초 콘크리트 구조물 하부의 지반이 굴착되어 기초파일의 노출이 예상되는 구역의 건축물 기초공사에 있어서,
(a) 기초 콘크리트 구조물 하부 토사 굴착으로 상기 기초 콘크리트 구조물의 기초파일이 노출될 것으로 예정되는 구역을 설정하는 제1단계;
(b) 제1단계 설정구역에 위치하는 기초파일을 시공하는 제2단계;
(c) 제2단계에서 시공된 기초파일의 상단과 연결되는 기초 콘크리트 구조물을 시공하는 제3단계;
(d) 제1단계 설정구역에 위치한 상기 기초 콘크리트 구조물을 인접한 다른 기초 콘크리트 구조물과 연결빔으로 연결하는 제4단계;
(e) 제3단계에서 형성된 기초 콘크리트 구조물의 콘크리트 강도가 확보된 후, 제1단계 설정구역의 토사가 굴착되어 상기 기초 콘크리트 구조물의 하부 기초파일의 적어도 일부가 지상으로 노출되는 제5단계; 및
(f) 제5단계의 기초 콘크리트 구조물의 상부 골조공사를 진행하는 제6단계;를 포함하며,
상기 기초파일은 현장타설말뚝 또는 PHC파일을 포함하고,
상기의 기초 콘크리트 구조물은 상기 연결빔과 연결하기 위해 콘크리트 타설 전 조인트가 매입된 것을 특징으로 하는 건축물 기초의 시공 방법.
In the building foundation work in the area where the foundation pile is expected to be exposed due to excavation of the ground under the foundation concrete structure,
(a) a first step of setting an area in which the foundation pile of the foundation concrete structure is expected to be exposed through earth and sand excavation under the foundation concrete structure;
(b) a second step of constructing a foundation pile located in the first step setting area;
(c) a third step of constructing a foundation concrete structure connected to the top of the foundation pile constructed in the second step;
(d) a fourth step of connecting the base concrete structure located in the first step setting area to another adjacent base concrete structure with a connecting beam;
(e) a fifth step in which at least a part of the lower foundation pile of the foundation concrete structure is exposed to the ground by excavating the soil in the first stage setting area after the concrete strength of the foundation concrete structure formed in the third stage is secured; And
(f) a sixth step of proceeding the upper frame construction of the foundation concrete structure of the fifth step; includes,
The foundation pile includes a cast-in-place pile or a PHC pile,
The construction method of the foundation of a building, characterized in that the joint is embedded before concrete pouring in the foundation concrete structure to connect with the connecting beam.
제1항에 있어서,
제2단계에서 기초파일 중 PHC파일은 유효 프리스트레스가 80kg/㎠이상인 PHC파일을 포함하는 건축물 기초의 시공 방법.
The method of claim 1,
The PHC pile among the foundation piles in the second step is a construction method of the foundation of a building including a PHC pile with an effective prestress of 80kg/㎠ or more.
제1항에 있어서,
제5단계 이후 굴착으로 형성된 사면 전 구역에 방수포를 설치하고 사면 하단부에 톤백을 설치하는 사면 안정화 단계를 포함하는 건축물 기초의 시공 방법.
The method of claim 1,
The construction method of the foundation of a building, including the step of stabilizing the slope of the slope of the fifth step and then installing a tarpaulin in all areas of the slope formed by excavation and installing a tone bag at the bottom of the slope.
제1항에 있어서,
제5단계에서 기초파일의 적어도 일부가 노출된 기초 콘크리트 구조물 및 상기 노출된 기초파일의 변위 측정을 위한 측정계를 설치하고, 제4단계의 연결빔에 응력 측정계를 설치하여 실시간 모니터링 시스템을 구축하는 단계를 포함하는 건축물 기초의 시공 방법.
The method of claim 1,
In step 5, installing a foundation concrete structure in which at least a part of the foundation pile is exposed and a measuring system for measuring the displacement of the exposed foundation pile, and installing a stress measurement system on the connecting beam in the fourth step to establish a real-time monitoring system Construction method of a building foundation comprising a.
KR1020190046172A 2019-04-19 2019-04-19 Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation KR102216972B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190046172A KR102216972B1 (en) 2019-04-19 2019-04-19 Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190046172A KR102216972B1 (en) 2019-04-19 2019-04-19 Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation

Publications (2)

Publication Number Publication Date
KR20200122850A KR20200122850A (en) 2020-10-28
KR102216972B1 true KR102216972B1 (en) 2021-02-19

Family

ID=73018579

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190046172A KR102216972B1 (en) 2019-04-19 2019-04-19 Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation

Country Status (1)

Country Link
KR (1) KR102216972B1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200255724Y1 (en) 2001-09-10 2001-12-13 (주)내경엔지니어링 Flow thwarting structure of rigid frame pier

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101221970B1 (en) * 2010-05-04 2013-01-15 양숙경 Construction Method for Basement Structure without Temporary Structure
KR101220811B1 (en) 2010-06-11 2013-01-11 김경훈 construction method for building and form
KR20110138940A (en) * 2010-06-22 2011-12-28 송기용 Method for foundation design using phc pile
KR101105883B1 (en) 2011-07-14 2012-01-16 서보산업 주식회사 Basic mat constructing method of high rise concrete structure
KR20140067312A (en) 2012-11-26 2014-06-05 준이앤씨(주) The concrete foundation construction method of building

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200255724Y1 (en) 2001-09-10 2001-12-13 (주)내경엔지니어링 Flow thwarting structure of rigid frame pier

Also Published As

Publication number Publication date
KR20200122850A (en) 2020-10-28

Similar Documents

Publication Publication Date Title
KR20090084509A (en) Precast concrete truss support structure and construction method thereof
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
JP2006316495A (en) Foundation structure of bridge pier and its construction method
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
KR102216972B1 (en) Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation
TWI790741B (en) Retaining wall and its construction method
KR102476068B1 (en) Retaining wall structure with multidirectional anchor fixtures and construction method thereof
KR100808977B1 (en) Connecting structure of corner supporting beam for temporary soil sheathing work
JP3958319B2 (en) Prestressed temporary construction method
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
KR20200026397A (en) Apparatus and method for arranging and holding head of bored pile by using horizontal means and holding means
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
CN214363595U (en) Construction elevator foundation
RU2390609C1 (en) Method for erection of slab-pile foundation
JP6461690B2 (en) Foundation structure and foundation construction method
JP3768220B2 (en) Pier structure and pier
KR101166127B1 (en) A method of construction for a bridge abutment using poor ground and a bridge abutment structureconstructed by the method
KR20090042395A (en) Retainning wall and its construction method
KR101058982B1 (en) Middle beam for earth retaining wall using phc pile and construction method of the same
JP2006188862A (en) Construction method of structure, and foundation structure used for the same
KR101255610B1 (en) Structure construction method and structure of use it
KR102560642B1 (en) Composite pile using micro pile and its construction method
JP7536396B2 (en) Methods for reinforcing the foundation footing of existing bridge piers
JP7263671B2 (en) pile foundation structure

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right