JP7536396B2 - Methods for reinforcing the foundation footing of existing bridge piers - Google Patents

Methods for reinforcing the foundation footing of existing bridge piers Download PDF

Info

Publication number
JP7536396B2
JP7536396B2 JP2020108551A JP2020108551A JP7536396B2 JP 7536396 B2 JP7536396 B2 JP 7536396B2 JP 2020108551 A JP2020108551 A JP 2020108551A JP 2020108551 A JP2020108551 A JP 2020108551A JP 7536396 B2 JP7536396 B2 JP 7536396B2
Authority
JP
Japan
Prior art keywords
pier
foundation footing
plate portion
reinforcing
reinforcement structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020108551A
Other languages
Japanese (ja)
Other versions
JP2022006375A (en
Inventor
雄介 井出
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2020108551A priority Critical patent/JP7536396B2/en
Publication of JP2022006375A publication Critical patent/JP2022006375A/en
Application granted granted Critical
Publication of JP7536396B2 publication Critical patent/JP7536396B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Description

本発明は、既設橋脚における基礎フーチングの補強方法に関する。 This invention relates to a method for reinforcing foundation footings in existing bridge piers.

橋脚の基礎は、地盤の支持力を増すため、水平方向に拡張されて、基礎フーチングをなし、基礎フーチングは、適切な支持層まで延びる複数の基礎杭の頭部と一体化している。 To increase the bearing capacity of the ground, the foundation of the pier is extended horizontally to form a foundation footing, which is integrated with the heads of multiple foundation piles that extend to an appropriate bearing layer.

既設橋脚の耐震補強のための補強方法としては、特許文献1に記載の方法が知られている。これは、既設橋脚の基礎フーチングの周囲に杭を増設し、増設杭の頭部に打設した増設コンクリートと基礎フーチングとをPC鋼材で結合、あるいは、増設杭の頭部どうしを基礎フーチングの上面にわたした連結材で緊結する。 The method described in Patent Document 1 is known as a method for strengthening the earthquake resistance of existing bridge piers. This involves adding piles around the foundation footing of the existing bridge pier, and connecting the additional concrete poured into the heads of the additional piles to the foundation footing with PC steel, or fastening the heads of the additional piles together with connecting materials that are placed over the top surface of the foundation footing.

特開平03-286028号公報Japanese Patent Application Publication No. 03-286028

しかしながら、特許文献1に記載のような増し杭工法は、大掛かりなものとなり、工期及び工費の増大を招く他、施工ヤードが広くなる。 However, the pile addition method described in Patent Document 1 is large-scale, which increases the construction period and costs, and requires a large construction yard.

また、既設橋脚の耐震補強において、施工しやすさという観点から、橋脚耐力向上(増厚等)が一般的に行われているが、橋脚の耐力を向上させると、設定想定荷重より大きな地震を受けた場合に、橋脚から基礎に伝達される地震力も大きくなり、基礎が先に損傷する恐れがある。 In addition, when strengthening the earthquake resistance of existing bridge piers, it is common to improve the pier's strength (by increasing its thickness, etc.) from the perspective of ease of construction. However, if the pier's strength is improved, in the event of an earthquake larger than the set expected load, the seismic force transmitted from the pier to the foundation will also increase, and there is a risk that the foundation will be damaged first.

そこで、基礎フーチングの耐震補強が検討された。具体的には、フーチングの降伏は、主に、橋脚頭部に水平方向に地震力が作用した場合に、橋脚に曲げモーメントを生じ、基礎フーチング内の下側鉄筋に過大な引張力が作用することによる、下側鉄筋の降伏であることから、次の(1)~(4)のような補強案が検討された。しかし、それぞれ問題点がある。 Therefore, seismic reinforcement of the foundation footing was considered. Specifically, yielding of the footing occurs mainly when a horizontal seismic force acts on the head of the pier, generating a bending moment in the pier, which causes excessive tensile force to act on the lower reinforcing bars in the foundation footing, causing the lower reinforcing bars to yield. Therefore, the following reinforcement plans (1) to (4) were considered. However, each plan has its own problems.

(1)フーチング側面から下側鉄筋を後施工で追加
フーチング側面の掘削が必要な上、フーチングの側面から全長にわたってアンカーを打つことになり、アンカーの設置も大変である。
(2)フーチング上面の増厚
下側鉄筋の有効高が増加するが、鉄筋量は増やせないので、必要増厚が過大となる。
(3)フーチング下面の増厚
フーチング下面を掘削する必要があり、大掛かりとなる。
(4)PC鋼材によるプレストレス導入
杭に拘束されるため、圧縮力がかからない恐れがあり、効果が不明確である。
(1) Adding the lower rebar from the side of the footing through post-construction. This requires excavation of the side of the footing, and also requires driving anchors into the ground along the entire length from the side of the footing, making the installation of the anchors difficult.
(2) Increasing the thickness of the top surface of the footing The effective height of the lower reinforcing bars will increase, but the amount of reinforcing bars cannot be increased, so the required thickness will be excessive.
(3) Increasing the thickness of the underside of the footing This will require excavation of the underside of the footing, which will be a major undertaking.
(4) Prestressing using PC steel: Since the piles are restrained, there is a risk that compressive force will not be applied, and the effectiveness of this method is unclear.

本発明は、このような実状に鑑みてなされたもので、比較的簡単な工事で、既設橋脚の基礎フーチングを必要十分に補強することができる、基礎フーチング補強方法を提供することを課題とする。 The present invention was made in consideration of these circumstances, and aims to provide a foundation footing reinforcement method that can sufficiently reinforce the foundation footing of an existing bridge pier with relatively simple construction work.

本発明に係る既設橋脚の基礎フーチング補強方法は、
既設橋脚の周囲の地盤を基礎フーチングの上面が露出するまで掘削する掘削工程と、
前記掘削により露出させた橋脚側面及び基礎フーチング上面にそれぞれアンカー筋を設置するアンカー筋設置工程と、
前記橋脚側面と前記基礎フーチング上面とのなす角部に、前記橋脚側面に接合する第1の接合面と前記基礎フーチング上面に接合する第2の接合面とを含む補強構造体を設置して、前記アンカー筋により一体化させる補強構造体設置工程と、
前記補強構造体を覆うように前記掘削した箇所を埋戻す埋戻し工程と、
を含むことを特徴とする。
The method for reinforcing the foundation footing of an existing bridge pier according to the present invention comprises the steps of:
an excavation process for excavating the ground around the existing pier until the top surface of the foundation footing is exposed;
An anchor installation process in which anchors are installed on the pier side surface and the foundation footing top surface exposed by the excavation;
A reinforcement structure installation process in which a reinforcement structure including a first joint surface that joins to the pier side surface and a second joint surface that joins to the foundation footing upper surface is installed at the corner between the pier side surface and the foundation footing upper surface, and integrated with the anchor reinforcement;
A backfilling process of backfilling the excavated area so as to cover the reinforcement structure;
The present invention is characterized by comprising:

ここにおいて、前記補強構造体として、鋼製補強構造体を用いることできる。
この場合、前記補強構造体設置工程は、前記補強構造体として、前記橋脚側面に押し当てて接合する垂直板部と、前記基礎フーチング上面に押し当てて接合する水平板部とを含む、鋼製補強構造体を用い、前記橋脚側面と前記基礎フーチング上面とのなす角部に、前記鋼製補強構造体を配置して、前記アンカー筋により固定する鋼製補強構造体設置工程となる。前記垂直板部と前記水平板部とには、それぞれ、前記アンカー筋を貫通させる取付孔が形成されており、前記垂直板部の取付孔は、前記水平板部を前記基礎フーチング上面に押し当てる方向に長い長孔であり、前記水平板部の取付孔は、前記垂直板部を前記橋脚側面に押し当てる方向に長い長孔である
Here, the reinforcing structure may be a steel reinforcing structure.
In this case, the reinforcement structure installation step is a steel reinforcement structure installation step in which a steel reinforcement structure including a vertical plate portion pressed against and joined to the side surface of the pier and a horizontal plate portion pressed against and joined to the upper surface of the foundation footing is used as the reinforcement structure, the steel reinforcement structure is placed at the corner between the side surface of the pier and the upper surface of the foundation footing, and fixed with the anchor bars. The vertical plate portion and the horizontal plate portion each have a mounting hole through which the anchor bars pass, and the mounting hole of the vertical plate portion is a long hole that is long in the direction in which the horizontal plate portion is pressed against the upper surface of the foundation footing, and the mounting hole of the horizontal plate portion is a long hole that is long in the direction in which the vertical plate portion is pressed against the side surface of the pier .

本発明によれば、橋脚側面と基礎フーチング上面とのなす角部に補強構造体を設置して一体化させることにより、剛域が拡大し、片持スパン低減により曲げモーメントが減少し、地震力によって基礎フーチング内の下側鉄筋に作用する引張力が減少することから、十分な耐震補強を実現することができる。
また、掘削は基礎フーチング上面まで行えばよく、工費及び工期の低減を図ることができる。
According to the present invention, by installing and integrating a reinforcing structure at the corner between the side of the pier and the top surface of the foundation footing, the rigidity area is expanded, the bending moment is reduced by reducing the cantilever span, and the tensile force acting on the lower reinforcing bars in the foundation footing due to seismic forces is reduced, thereby achieving sufficient earthquake resistance reinforcement.
Furthermore, excavation only needs to be carried out up to the top surface of the foundation footing, which reduces construction costs and time.

本発明の第1実施形態として示す基礎フーチング補強方法の工程図A process diagram of a foundation footing reinforcement method shown as the first embodiment of the present invention. 図1(c)の平面図Plan view of FIG. ハンチコンクリート追加の効果を示す図A diagram showing the effect of adding corbel concrete 本発明の第2実施形態として示す基礎フーチング補強方法の工程図A process diagram of a foundation footing reinforcement method shown as a second embodiment of the present invention. 図4(c)の平面図Plan view of FIG. 鋼製補強構造体の斜視図Perspective view of steel reinforcement structure

以下に、本発明の実施の形態について、図面に基づいて詳細に説明する。
図1は本発明の第1実施形態として示す基礎フーチング補強方法の工程図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
FIG. 1 is a process diagram of a foundation footing reinforcing method according to a first embodiment of the present invention.

図1(a)を参照し、橋脚1は、RC(鉄筋コンクリート)製で、供用中の既設の橋梁の一部をなし、図外の頭部(支承部)を介して橋梁の橋桁を支持している。 Referring to Figure 1(a), pier 1 is made of reinforced concrete (RC) and forms part of an existing bridge in service, supporting the bridge girder via a head (bearing part) not shown in the figure.

橋脚1の基礎は、地盤の支持力を増すために、水平方向に延在して、所定厚の基礎フーチング2をなしている。
橋脚1の基礎はまた、複数の基礎杭3を備え、これらの基礎杭3は、その頭部で基礎フーチング2と一体化されて、基礎フーチング2の底面から適切な支持層まで延びている。
The foundation of the pier 1 extends horizontally to form a foundation footing 2 of a predetermined thickness in order to increase the bearing capacity of the ground.
The foundation of the pier 1 also comprises a number of foundation piles 3 which are integral with the foundation footing 2 at their heads and extend from the bottom of the foundation footing 2 to a suitable bearing layer.

かかる橋脚(既設橋脚)1における基礎フーチング2の補強方法を図1(a)~(c)の工程図により説明する。 The method for reinforcing the foundation footing 2 of such a pier (existing pier) 1 is explained using the process diagrams in Figures 1(a) to (c).

図1(a)は掘削工程及び表面はつり工程を示している。
掘削工程では、橋脚1の周囲の地盤Gを基礎フーチング2の上面2aが露出するまで掘削する。掘削深さは基礎フーチング2の設置深さにより異なるが、概ね1~5m程度である。掘削深さによっては掘削部を囲むように山留壁を構築してから、その内部を掘削する。周囲に十分な余裕がある場合は、緩傾斜の法面を設けることで、山留壁は不要となる。
FIG. 1(a) shows the drilling process and the surface chipping process.
In the excavation process, the ground G around the pier 1 is excavated until the top surface 2a of the foundation footing 2 is exposed. The excavation depth varies depending on the installation depth of the foundation footing 2, but is generally about 1 to 5 m. Depending on the excavation depth, a retaining wall is constructed to surround the excavated area, and then the inside is excavated. If there is sufficient space around, a gently sloping slope can be provided, making the retaining wall unnecessary.

掘削工程後は、表面はつり工程に移行する。
表面はつり工程では、掘削により露出させた橋脚側面1a及び基礎フーチング上面2a(厳密には、これらのうち後述するハンチコンクリートの打設範囲;図示H)を、チッピングによる打撃あるいはウォータジェットなどにより、はつる(斫る)。これは、後述するハンチコンクリートとの打継ぎ部の密着性を向上させるために、表面に1mm程度の凹凸をつける、表面荒し処理(目荒し)である。
After the excavation process, the surface moves to the chipping process.
In the surface chipping process, the pier side surface 1a and the foundation footing top surface 2a exposed by excavation (strictly speaking, the area where the haunch concrete will be poured, which will be described later; H in the figure) are chipped (chipped) by impact with a chipping hammer or water jet, etc. This is a surface roughening process (roughening) that creates irregularities of about 1 mm on the surface in order to improve the adhesion of the joint with the haunch concrete, which will be described later.

図1(b)はアンカー筋設置工程を示している。
アンカー筋設置工程では、掘削により露出させた橋脚側面1a及び基礎フーチング上面2a(厳密には、これらのうち後述するハンチコンクリートの打設範囲)に、それぞれ、複数のアンカー筋(定着用の継手)4を設置する。
FIG. 1(b) shows the anchor installation process.
In the anchor bar installation process, a number of anchor bars (joints for fixing) 4 are installed on each of the pier side surface 1a and the foundation footing upper surface 2a (strictly speaking, the area where haunch concrete will be poured, which will be described later) that have been exposed by excavation.

アンカー筋4の設置に際しては、先ず、橋脚側面1a及び基礎フーチング上面2aのアンカー筋設置予定位置を削孔する。すなわち、橋脚側面1aには横方向に(あるいは斜め下向きの傾斜をつけて)削孔し、基礎フーチング上面2aには鉛直方向に削孔する。 When installing the anchor bars 4, first drill holes at the planned locations for installing the anchor bars on the pier side surface 1a and the top surface 2a of the foundation footing. That is, holes are drilled horizontally (or at a downward incline) on the pier side surface 1a, and vertically on the top surface 2a of the foundation footing.

削孔後、削孔内にセメントミルクを注入し、セメントミルクが注入された削孔内にアンカー筋4の一端部を挿入して、一体化させる。これにより、橋脚側面1a及び基礎フーチング上面2aからアンカー筋4の他端部を突出させる。 After drilling the holes, cement milk is poured into the holes, and one end of the anchor bar 4 is inserted into the holes into which the cement milk has been poured, and the two are integrated together. This causes the other end of the anchor bar 4 to protrude from the pier side surface 1a and the top surface 2a of the foundation footing.

図1(c)はハンチコンクリート打設工程及び埋戻し工程を示している。
ハンチコンクリート打設工程では、橋脚側面1aと基礎フーチング上面2aとのなす角部に、橋脚側面1a及び基礎フーチング上面2aから突出するアンカー筋4を巻込んで、少なくともハンチ状にコンクリートを場所打ちする。
FIG. 1(c) shows the process of pouring haunch concrete and backfilling.
In the haunch concrete pouring process, the anchor bars 4 protruding from the pier side surface 1a and the foundation footing upper surface 2a are wrapped around the corner formed by the pier side surface 1a and the foundation footing upper surface 2a, and concrete is poured in place in at least a haunch shape.

「少なくともハンチ状」というのは、基本的には、角部にハンチ状、すなわち、側方から見て略三角形状にコンクリートを打設すればよいが、三角形状を包含していれば、余分とはなるが、四角形状などでもよいことを意味している。 "At least haunch-shaped" basically means that the concrete should be poured into the corner in a haunch shape, i.e., in a roughly triangular shape when viewed from the side, but as long as it includes a triangular shape, it can also be a square shape, although this is redundant.

なお、コンクリート打設に先立って、打設領域に配筋(ハンチ筋の設置)を行うようにしてもよい。 In addition, reinforcement (installation of haunch reinforcement) may be performed in the pouring area prior to pouring the concrete.

このようにして、橋脚側面1aと基礎フーチング上面2aとのなす角部に、橋脚側面1aに接合する第1の接合面と基礎フーチング上面2aに接合する第2の接合面とを含む補強構造体として、ハンチコンクリート5が構築される。 In this way, the haunch concrete 5 is constructed as a reinforcing structure at the corner between the pier side surface 1a and the foundation footing upper surface 2a, including a first joint surface that joins to the pier side surface 1a and a second joint surface that joins to the foundation footing upper surface 2a.

図2は図1(c)の平面図である。ハンチコンクリート5は、4つの橋脚側面1aを囲むように、頭四角錐形状をなしている。 Fig. 2 is a plan view of Fig. 1(c). The haunch concrete 5 has a truncated quadrangular pyramid shape so as to surround the four pier side surfaces 1a.

なお、ハンチコンクリート打設工程は、コンクリート打設前になされる型枠設置工程と、コンクリート打設後に型枠を除去する脱型工程とを含む。 The haunch concrete pouring process includes a formwork installation process that is performed before pouring the concrete, and a formwork removal process that removes the formwork after pouring the concrete.

ハンチコンクリート打設工程後は、埋戻し工程に移行する。
埋戻し工程では、補強構造体としてのハンチコンクリート5を覆うように、前記掘削工程で掘削した箇所を元の地盤Gのラインまで埋戻す。
After the haunch concrete pouring process, the backfilling process begins.
In the backfilling step, the area excavated in the excavation step is backfilled up to the original ground G line so as to cover the haunch concrete 5 as the reinforcing structure.

図3はハンチコンクリート追加の効果を示す図であり、橋脚1の頭部に図示矢印Fの方向の水平な地震力が作用した場合に、基礎フーチング2に生じるひび割れ(ずれ)の解析結果を示している。 Figure 3 shows the effect of adding haunch concrete, and shows the analysis results of cracks (shifts) that occur in the foundation footing 2 when a horizontal seismic force acts on the head of the pier 1 in the direction of the arrow F shown.

橋脚1の頭部に図示矢印Fの方向に地震力が作用した場合、橋脚1に曲げモーメントを生じ、基礎フーチング2の図で右側の下側鉄筋位置に大きな引張力を生じるが、図3(a)のハンチ無しの場合に比べ、図3(b)のハンチ有りの場合は、ひび割れ(ずれ)の範囲を大幅に低減することができる。 When an earthquake force acts on the head of pier 1 in the direction of arrow F, a bending moment is generated in pier 1, and a large tensile force is generated at the lower rebar position on the right side of the foundation footing 2 in the diagram. However, compared to the case without haunch in Figure 3(a), the area of cracks (displacement) can be significantly reduced in the case with haunch in Figure 3(b).

このように、橋脚側面1aと基礎フーチング上面2aとのなす角部に補強構造体(ハンチコンクリート5)を設置して一体化させることにより、剛域が拡大し、片持スパン低減により曲げモーメントが減少し、地震力によって基礎フーチング2内の下側鉄筋に作用する引張力が減少することから、十分な耐震補強を実現することができる。 In this way, by installing and integrating a reinforcing structure (haunch concrete 5) at the corner between the pier side surface 1a and the foundation footing top surface 2a, the rigidity area is expanded, the bending moment is reduced by reducing the cantilever span, and the tensile force acting on the lower rebar in the foundation footing 2 due to seismic forces is reduced, thereby achieving sufficient seismic reinforcement.

言い換えれば、剛域設定で照査断面位置が杭に近くなり、片持ちスパン低減により曲げモーメントの減少を図ることができる。また、照査断面位置での部材厚増加により下側鉄筋に対する引張応力を減少させることができる。更に、せん断照査位置が杭に近くなることにより、せん断スパン比の影響で、せん断耐力を増加させることができる。 In other words, by setting the rigid zone, the inspection section position is brought closer to the piles, and the bending moment can be reduced by reducing the cantilever span. Also, by increasing the thickness of the member at the inspection section position, the tensile stress on the lower rebar can be reduced. Furthermore, by bringing the shear inspection position closer to the piles, the shear strength can be increased due to the effect of the shear span ratio.

図4は本発明の第2実施形態として示す基礎フーチング補強方法の工程図である。
図4(a)は掘削工程を示している。
掘削工程では、図1(a)と同様に、橋脚1の周囲の地盤Gを基礎フーチング2の上面2aが露出するまで掘削する。
掘削工程後は、表面はつり処理を行うことなく、アンカー筋設置工程に移行する。
FIG. 4 is a process diagram of a foundation footing reinforcing method according to a second embodiment of the present invention.
FIG. 4(a) shows the drilling process.
In the excavation step, similarly to FIG. 1(a), the ground G around the pier 1 is excavated until the upper surface 2a of the foundation footing 2 is exposed.
After the excavation process, the surface is not subjected to chipping treatment and the process moves to the anchor reinforcement installation process.

図4(b)はアンカー筋設置工程を示している。アンカー筋設置工程では、図1(b)と同様に、掘削により露出させた橋脚側面1a及び基礎フーチング上面2a(厳密には、これらのうち後述する鋼製補強構造体の設置範囲)に、それぞれ、複数のアンカー筋(アンカーボルト)4を設置する。 Figure 4 (b) shows the anchor bar installation process. In the anchor bar installation process, similar to Figure 1 (b), multiple anchor bars (anchor bolts) 4 are installed on the pier side surface 1a and the foundation footing top surface 2a exposed by excavation (strictly speaking, the installation area of the steel reinforcement structure described later).

図4(c)は鋼製補強構造体設置工程及び埋戻し工程を示している。
鋼製補強構造体設置工程では、橋脚側面1aと基礎フーチング上面2aとのなす角部に、鋼製補強構造体6を配置して、アンカー筋4により固定する。
FIG. 4(c) shows the steel reinforcement structure installation process and backfilling process.
In the steel reinforcement structure installation process, a steel reinforcement structure 6 is placed at the corner between the pier side surface 1 a and the foundation footing upper surface 2 a and fixed in place with anchor bars 4 .

鋼製補強構造体6は、図4(c)の他、図5(図4(c)の平面図)及び図6(鋼製補強構造体6の斜視図)に示されるように、板金製で、橋脚側面1aに接合する垂直板部6aと、基礎フーチング上面2aに接合する水平板部6bと、垂直板部6aと水平板部6bとの間に配置されて、これらをリブ状につなぐ複数の三角形状の補強板部6cと、を含んで構成される。 As shown in Fig. 4(c), as well as Fig. 5 (plan view of Fig. 4(c)) and Fig. 6 (perspective view of steel reinforcement structure 6), the steel reinforcement structure 6 is made of sheet metal and comprises a vertical plate portion 6a joined to the pier side surface 1a, a horizontal plate portion 6b joined to the foundation footing upper surface 2a, and a number of triangular reinforcing plate portions 6c arranged between the vertical plate portion 6a and the horizontal plate portion 6b and connecting them in the form of ribs.

鋼製補強構造体6はまた、垂直板部6a及び水平板部6bに、橋脚側面1a及び基礎フーチング上面2aから突出するアンカー筋4を貫通させる取付孔7を有している。 The steel reinforcement structure 6 also has mounting holes 7 on the vertical plate portion 6a and horizontal plate portion 6b through which the anchor bars 4 protruding from the pier side surface 1a and the foundation footing top surface 2a pass.

従って、鋼製補強構造体設置工程では、鋼製補強構造体6の垂直板部(第1の接合面)6aを橋脚側面1aに押し当てて、橋脚側面1aから突出するアンカー筋4を垂直板部6aの取付孔7に挿入し、当該アンカー筋4の端部にロックナット8を螺合して締付け固定する。 Therefore, in the steel reinforcement structure installation process, the vertical plate portion (first joint surface) 6a of the steel reinforcement structure 6 is pressed against the pier side surface 1a, the anchor bar 4 protruding from the pier side surface 1a is inserted into the mounting hole 7 of the vertical plate portion 6a, and the lock nut 8 is screwed onto the end of the anchor bar 4 to tighten and fix it in place.

同時に、鋼製補強構造体6の水平板部(第2の接合面)6bを基礎フーチング上面2aに押し当てて、基礎フーチング上面2aから突出するアンカー筋4を水平板部6bの取付孔7に挿入し、当該アンカー筋4の端部にロックナット8を螺合して締付け固定する。 At the same time, the horizontal plate portion (second joint surface) 6b of the steel reinforcement structure 6 is pressed against the upper surface 2a of the foundation footing, the anchor bar 4 protruding from the upper surface 2a of the foundation footing is inserted into the mounting hole 7 of the horizontal plate portion 6b, and the lock nut 8 is screwed onto the end of the anchor bar 4 to tighten and fix it in place.

このときの取付けを容易にするため、垂直板部6aの取付孔7又は水平板部6bの取付孔7の少なくとも一方について、長孔としておくとよい。この場合、垂直板部6aの取付孔7については上下方向(水平板部6bを押し当てる方向)に長い長孔とし、水平板部6bの取付孔7については左右方向(垂直板部6aを押し当てる方向)に長い長孔とする。 To facilitate this installation, it is advisable to make at least one of the mounting holes 7 in the vertical plate portion 6a or the horizontal plate portion 6b a long hole. In this case, the mounting hole 7 in the vertical plate portion 6a is a long hole that is long in the up-down direction (the direction in which the horizontal plate portion 6b is pressed against it), and the mounting hole 7 in the horizontal plate portion 6b is a long hole that is long in the left-right direction (the direction in which the vertical plate portion 6a is pressed against it).

このようにして、橋脚側面1aと基礎フーチング上面2aとのなす角部に、橋脚側面1aに接合する第1の接合面(垂直板部6a)と基礎フーチング上面2aに接合する第2の接合面(水平板部6b)とを含む補強構造体として、鋼製補強構造体6が設置される。 In this way, a steel reinforcement structure 6 is installed at the corner between the pier side surface 1a and the foundation footing upper surface 2a as a reinforcement structure including a first joint surface (vertical plate portion 6a) that joins to the pier side surface 1a and a second joint surface (horizontal plate portion 6b) that joins to the foundation footing upper surface 2a.

なお、鋼製補強構造体6は、図5からわかるように、橋脚1の4つの側面1aのそれぞれに設置され、4個用いられる。 As can be seen from Figure 5, four steel reinforcement structures 6 are used, one on each of the four sides 1a of the pier 1.

鋼製補強構造体設置工程後は、埋戻し工程に移行する。
埋戻し工程では、補強構造体としての鋼製補強構造体6を覆うように、前記掘削工程で掘削した箇所を元の地盤Gのラインまで埋戻す。
After the steel reinforcement structure installation process, the backfilling process begins.
In the backfilling process, the area excavated in the excavation process is backfilled up to the original ground G line so as to cover the steel reinforcing structure 6 as the reinforcing structure.

このようなハンチ状の鋼製補強構造体6を用いても、ハンチコンクリート5と同様な効果を得ることができる。 Even if such a haunch-shaped steel reinforcement structure 6 is used, the same effect can be obtained as with haunch concrete 5.

補強構造体としては、この他、場所打ちコンクリートに代えて、プレキャストコンクリート製の補強構造体を用いることもできる。 In addition, instead of cast-in-place concrete, a precast concrete reinforcement structure can also be used.

示の実施形態はあくまで本発明を概略的に例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。
なお、出願当初の請求項は以下の通りであった。
[請求項1]
既設橋脚における基礎フーチングの補強方法であって、
前記既設橋脚の周囲の地盤を前記基礎フーチングの上面が露出するまで掘削する掘削工程と、
前記掘削により露出させた橋脚側面及び基礎フーチング上面にそれぞれアンカー筋を設置するアンカー筋設置工程と、
前記橋脚側面と前記基礎フーチング上面とのなす角部に、前記橋脚側面に接合する第1の接合面と前記基礎フーチング上面に接合する第2の接合面とを含む補強構造体を設置して、前記アンカー筋により一体化させる補強構造体設置工程と、
前記補強構造体を覆うように前記掘削した箇所を埋戻す埋戻し工程と、
を含む、既設橋脚の基礎フーチング補強方法。
[請求項2]
前記補強構造体設置工程は、前記橋脚側面及び前記基礎フーチング上面に前記アンカー筋を巻込んで、少なくともハンチ状にコンクリートを場所打ちし、場所打ちコンクリートによって前記補強構造体を構築するコンクリート打設工程であることを特徴とする、請求項1記載の既設橋脚の基礎フーチング補強方法。
[請求項3
前記掘削工程後、前記コンクリート打設工程前に、前記掘削により露出させた橋脚側面及び基礎フーチング上面のコンクリート表面をはつる、表面はつり工程を更に含むことを特徴とする、請求項2記載の既設橋脚の基礎フーチング補強方法。
[請求項4]
前記補強構造体設置工程は、前記補強構造体として、前記橋脚側面に接合する垂直板部と、前記基礎フーチング上面に接合する水平板部とを含む、鋼製補強構造体を用い、
前記橋脚側面と前記基礎フーチング上面とのなす角部に、前記鋼製補強構造体を配置して、前記アンカー筋により固定する鋼製補強構造体設置工程であることを特徴とする、請求項1記載の既設橋脚の基礎フーチング補強方法。
[請求項5]
前記鋼製補強構造体は、前記垂直板部と前記水平板部との間に配置されて、これらをリブ状につなぐ複数の補強板部を更に含むことを特徴とする、請求項4記載の既設橋脚の基礎フーチング補強方法。
It goes without saying that the illustrated embodiments are merely schematic examples of the present invention, and that the present invention encompasses various modifications and variations that may be made by those skilled in the art within the scope of the claims, in addition to those directly shown in the described embodiments.
The claims as originally filed were as follows:
[Claim 1]
A method for reinforcing a foundation footing in an existing bridge pier, comprising:
An excavation process of excavating the ground around the existing pier until the top surface of the foundation footing is exposed;
An anchor installation process in which anchors are installed on the pier side surface and the foundation footing top surface exposed by the excavation;
A reinforcement structure installation process in which a reinforcement structure including a first joint surface that joins to the pier side surface and a second joint surface that joins to the foundation footing upper surface is installed at the corner between the pier side surface and the foundation footing upper surface, and integrated with the anchor reinforcement;
A backfilling process of backfilling the excavated area so as to cover the reinforcement structure;
A method for reinforcing the foundation footing of an existing bridge pier, including:
[Claim 2]
2. The method for reinforcing a foundation footing of an existing pier according to claim 1, wherein the reinforcing structure installation step is a concrete pouring step of wrapping the anchor bars around the side surface of the pier and the top surface of the foundation footing, pouring concrete into at least a haunch shape, and constructing the reinforcing structure by pouring concrete into the place.
[Claim 3 ]
The method for reinforcing a foundation footing of an existing pier according to claim 2, further comprising a surface chipping step of chipping the concrete surfaces of the pier side surface and the top surface of the foundation footing exposed by the excavation after the excavation step and before the concrete pouring step.
[Claim 4]
The reinforcement structure installation step uses a steel reinforcement structure including a vertical plate portion joined to the side surface of the pier and a horizontal plate portion joined to the upper surface of the foundation footing as the reinforcement structure,
2. The method for reinforcing the foundation footing of an existing pier according to claim 1, further comprising a steel reinforcing structure installation step of placing the steel reinforcing structure at the corner between the side surface of the pier and the top surface of the foundation footing and fixing it with the anchor bars.
[Claim 5]
The method for reinforcing the foundation footing of an existing bridge pier according to claim 4, characterized in that the steel reinforcing structure further includes a plurality of reinforcing plate portions arranged between the vertical plate portion and the horizontal plate portion and connecting them in the form of ribs.

1 橋脚(既設橋脚)
1a 橋脚側面
2 基礎フーチング
2a 基礎フーチング上面
3 基礎杭
4 アンカー筋
5 ハンチコンクリート(補強構造体)
6 鋼製補強構造体
6a 垂直板部
6b 水平板部
6c 補強板部
7 取付孔
8 ロックナット
1. Pier (existing pier)
1a Pier side surface 2 Foundation footing 2a Foundation footing top surface 3 Foundation pile 4 Anchor bar 5 Haunch concrete (reinforced structure)
6 Steel reinforcement structure 6a Vertical plate portion 6b Horizontal plate portion 6c Reinforcement plate portion 7 Mounting hole 8 Lock nut

Claims (2)

既設橋脚における基礎フーチングの補強方法であって、
前記既設橋脚の周囲の地盤を前記基礎フーチングの上面が露出するまで掘削する掘削工程と、
前記掘削により露出させた橋脚側面及び基礎フーチング上面にそれぞれアンカー筋を設置するアンカー筋設置工程と、
前記橋脚側面と前記基礎フーチング上面とのなす角部に、前記橋脚側面に接合する第1の接合面と前記基礎フーチング上面に接合する第2の接合面とを含む補強構造体を設置して、前記アンカー筋により一体化させる補強構造体設置工程と、
前記補強構造体を覆うように前記掘削した箇所を埋戻す埋戻し工程と、
を含み、
前記補強構造体設置工程は、前記補強構造体として、前記橋脚側面に押し当てて接合する垂直板部と、前記基礎フーチング上面に押し当てて接合する水平板部とを含む、鋼製補強構造体を用い、
前記橋脚側面と前記基礎フーチング上面とのなす角部に、前記鋼製補強構造体を配置して、前記アンカー筋により固定する鋼製補強構造体設置工程であり、
前記垂直板部と前記水平板部とには、それぞれ、前記アンカー筋を貫通させる取付孔が形成されており、
前記垂直板部の取付孔は、前記水平板部を前記基礎フーチング上面に押し当てる方向に長い長孔であり、
前記水平板部の取付孔は、前記垂直板部を前記橋脚側面に押し当てる方向に長い長孔である、既設橋脚の基礎フーチング補強方法。
A method for reinforcing a foundation footing in an existing bridge pier, comprising:
An excavation process of excavating the ground around the existing pier until the top surface of the foundation footing is exposed;
An anchor installation process in which anchors are installed on the pier side surface and the foundation footing top surface exposed by the excavation;
A reinforcement structure installation process in which a reinforcement structure including a first joint surface that joins to the pier side surface and a second joint surface that joins to the foundation footing upper surface is installed at the corner between the pier side surface and the foundation footing upper surface, and integrated with the anchor reinforcement;
A backfilling process of backfilling the excavated area so as to cover the reinforcement structure;
Including,
The reinforcement structure installation step uses a steel reinforcement structure including a vertical plate portion pressed against and joined to the side surface of the pier and a horizontal plate portion pressed against and joined to the upper surface of the foundation footing,
A steel reinforcement structure installation process in which the steel reinforcement structure is placed at the corner between the pier side surface and the foundation footing top surface and fixed by the anchor reinforcement;
The vertical plate portion and the horizontal plate portion each have a mounting hole through which the anchor bar passes,
The mounting hole of the vertical plate portion is a long hole that is long in a direction in which the horizontal plate portion is pressed against the upper surface of the foundation footing,
A method for reinforcing the foundation footing of an existing pier, wherein the mounting hole of the horizontal plate portion is a long hole that is long in the direction in which the vertical plate portion is pressed against the side surface of the pier.
前記鋼製補強構造体は、前記垂直板部と前記水平板部との間に配置されて、これらをリブ状につなぐ複数の補強板部を更に含む、請求項1に記載の既設橋脚の基礎フーチング補強方法。 The method for reinforcing a foundation footing of an existing bridge pier according to claim 1 , wherein the steel reinforcing structure further includes a plurality of reinforcing plate portions arranged between the vertical plate portion and the horizontal plate portion and connecting them in the form of ribs.
JP2020108551A 2020-06-24 2020-06-24 Methods for reinforcing the foundation footing of existing bridge piers Active JP7536396B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020108551A JP7536396B2 (en) 2020-06-24 2020-06-24 Methods for reinforcing the foundation footing of existing bridge piers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020108551A JP7536396B2 (en) 2020-06-24 2020-06-24 Methods for reinforcing the foundation footing of existing bridge piers

Publications (2)

Publication Number Publication Date
JP2022006375A JP2022006375A (en) 2022-01-13
JP7536396B2 true JP7536396B2 (en) 2024-08-20

Family

ID=80110228

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020108551A Active JP7536396B2 (en) 2020-06-24 2020-06-24 Methods for reinforcing the foundation footing of existing bridge piers

Country Status (1)

Country Link
JP (1) JP7536396B2 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011246981A (en) 2010-05-27 2011-12-08 Nippon Steel Corp Foundation reinforcement method of structure
JP2013096176A (en) 2011-11-02 2013-05-20 Sumitomo Mitsui Construction Co Ltd Reinforcement structure of existing foundation
US20160097179A1 (en) 2014-10-07 2016-04-07 Allan P. Henderson Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2979114B2 (en) * 1995-08-21 1999-11-15 鹿島建設株式会社 Existing foundation structure reinforcement method
JPH09324408A (en) * 1996-06-06 1997-12-16 Kunitomi Kk Underwater construction method of bridge pier or the like
JPH10331437A (en) * 1997-05-28 1998-12-15 Taisei Corp Seismic reinforcement structure of existing columns and beams

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011246981A (en) 2010-05-27 2011-12-08 Nippon Steel Corp Foundation reinforcement method of structure
JP2013096176A (en) 2011-11-02 2013-05-20 Sumitomo Mitsui Construction Co Ltd Reinforcement structure of existing foundation
US20160097179A1 (en) 2014-10-07 2016-04-07 Allan P. Henderson Retrofit reinforcing structure addition and method for wind turbine concrete gravity spread foundations and the like

Also Published As

Publication number Publication date
JP2022006375A (en) 2022-01-13

Similar Documents

Publication Publication Date Title
KR100743832B1 (en) Construction method of bridge using preflex girder and integral shift
JP2000248526A (en) Pier structure and its construction method
JP7017541B2 (en) Improvement structure and improvement method of existing sheet pile type quay
KR101051978B1 (en) Basement structure construction method using PC member
KR102560642B1 (en) Composite pile using micro pile and its construction method
KR101341260B1 (en) Method of reinforcing existing concrete footing structure using micropile
JP3780816B2 (en) Seismic isolation method for existing buildings
KR100657655B1 (en) Prefab pile for ground stability method
KR101198286B1 (en) Non-wale strut system for top-down construction and top-down construction method thereby
JP7536396B2 (en) Methods for reinforcing the foundation footing of existing bridge piers
KR100922121B1 (en) Combined structure of composite pile and expansion foundation composed of concrete pile
JP7028728B2 (en) Joint structure of foundation pile and foundation slab
JP5852475B2 (en) Pile foundation reconstruction method
JP3768220B2 (en) Pier structure and pier
KR102398605B1 (en) Construction method of seismic retrofit system using pc panel
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JPH1077644A (en) Earthquake resisting pile foundation construction method
JP3963326B2 (en) Seismic reinforcement structure for bridge pier and its construction method
KR101483865B1 (en) Construction Method of Underground Structure using Composite Wale
JPS63280153A (en) Underground inverted lining method
JP2005325603A (en) Construction method of foundation and support structure of concrete foundation in reverse casting method
JP3849234B2 (en) Reinforced concrete underground outer wall construction method
JP6000414B2 (en) Pile foundation reconstruction method and pile foundation structure
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP6895740B2 (en) Horizontal force restraint structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230201

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231011

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231205

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231225

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20240402

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240514

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20240521

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240806

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240806

R150 Certificate of patent or registration of utility model

Ref document number: 7536396

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150