TWI816594B - Architecture structure and method for constructing the same - Google Patents

Architecture structure and method for constructing the same Download PDF

Info

Publication number
TWI816594B
TWI816594B TW111141592A TW111141592A TWI816594B TW I816594 B TWI816594 B TW I816594B TW 111141592 A TW111141592 A TW 111141592A TW 111141592 A TW111141592 A TW 111141592A TW I816594 B TWI816594 B TW I816594B
Authority
TW
Taiwan
Prior art keywords
beam structure
steel bar
connector
connectors
kaifeng
Prior art date
Application number
TW111141592A
Other languages
Chinese (zh)
Other versions
TW202419719A (en
Inventor
尹衍樑
曹昌盛
王瑞禎
陳智軒
Original Assignee
潤弘精密工程事業股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 潤弘精密工程事業股份有限公司 filed Critical 潤弘精密工程事業股份有限公司
Priority to TW111141592A priority Critical patent/TWI816594B/en
Application granted granted Critical
Publication of TWI816594B publication Critical patent/TWI816594B/en
Publication of TW202419719A publication Critical patent/TW202419719A/en

Links

Abstract

The instant disclosure provides an architecture structure which includes a first and a second precast beam structures, and a number of mortar delivering pipes. A number of rebar couplers are embedded in the first precast beam structures, and a number of beam steels extends outward from an end surface of the second precast beam structure. Each of the rebar couplers includes: a first and a second openings, and a through hole. The first opening is fixed to a beam steel of the first precast beam structure, and the second opening is exposed to an end surface of the first precast beam structure and is configured to allow the insertion of one of the beam steels of the second precast beam structure. The through hole is adjacent to and communicate with the first opening and penetrates the outer wall of the rebar coupler. The mortar delivering pipes are embedded in the first precast beam structure and fluidly connected the through holes of the rebar couples and the exterior of the first precast beam structure.

Description

建築結構及其建造方法 Building structures and construction methods

本發明實施例關於提供一種建築結構及其建造方法。 Embodiments of the present invention provide a building structure and a construction method thereof.

常見的建築工法包括RC(鋼筋混凝土)結構、SC(鋼骨梁柱外面包覆混凝土做防火披覆使用)結構以及SRC(鋼骨鋼筋混凝土)結構等。RC(鋼筋混凝土)結構又可區分為現場澆置混凝土的傳統場鑄工法以及近年發展具有結構品質優異、施工安全迅速、營建成本經濟合理等優點的預鑄工法。預鑄工法係於預鑄廠或工地周邊,以標準化的作業流程及模組化的模具,施工鋼筋結構並澆置混凝土,快速大量生產精密的柱體、梁體、板體等的預鑄構件。藉由精確的搬運管理及組裝作業,將在預鑄廠內或工地周邊生產完成的預鑄構件於工地現場組合。藉此,工地現場中的工作量可以降低、減少人力及施工時間,進而有效縮短工期,並確保施工品質。此外,預鑄施工法亦可減少或避免在外牆鷹架上施工,大幅提高了施工安全性。 Common construction methods include RC (reinforced concrete) structure, SC (steel beams and columns covered with concrete for fire protection) structure, and SRC (steel reinforced concrete) structure. RC (reinforced concrete) structures can be divided into the traditional casting method of pouring concrete on site and the in-house construction method that has been developed in recent years and has the advantages of excellent structural quality, safe and rapid construction, and economical and reasonable construction costs. The Xuan construction method is based on the Xuan factory or around the construction site. It uses standardized operating procedures and modular molds to construct steel structures and pour concrete to quickly mass-produce precision columns, beams, plates, etc. Xuan components. . Through precise handling management and assembly operations, the Xuan components produced in the Xixuan factory or around the construction site are assembled on the construction site. In this way, the workload on the construction site can be reduced, manpower and construction time can be reduced, thereby effectively shortening the construction period and ensuring construction quality. In addition, the construction method can also reduce or avoid construction on the outer wall scaffolding, which greatly improves construction safety.

基於各種工法有其優缺點,混和式的建築工法也逐漸被採用。舉例而言,以預鑄柱工法搭配傳統場鑄工法建築住宅類型建案可發揮其各自的優缺點,其中利用預鑄柱工法施工建築物外圍的梁柱主結構,輔 以傳統場鑄工法施作建築物內圍較瑣碎的時工細節通常可以在品質、工時,以及成品各方面達到最佳的性價比。有鑑於此類建築物的發展,如何在利用最少施工步驟以達到最大產量且提供最佳品質的製造此類建築結構的方法,以及依此施工方法所完成的建築結構是業界所企盼的。 Since various construction methods have their own advantages and disadvantages, hybrid construction methods are gradually being adopted. For example, the construction of residential buildings using the cast-iron method and the traditional cast-iron construction method can bring into full play their respective advantages and disadvantages. Using traditional casting methods to construct the more trivial details of the interior of a building can usually achieve the best cost performance in terms of quality, working hours, and finished products. In view of the development of this type of building, how to use the minimum construction steps to achieve maximum output and provide the best quality methods for manufacturing such building structures, as well as the building structures completed according to this construction method, are what the industry is looking forward to.

本發明之一實施例提供一種建築結構,其包括:一第一預鑄梁結構及一第二預鑄梁結構,各自具有一端面,該二個端面相鄰設置並定義一間隙於其間,其中該第二預鑄梁結構之該端面包括複數個梁鋼筋向外延伸;複數個鋼筋續接器,埋設於該第一預鑄梁結構之該端面內,每一該複數個鋼筋續接器包括:一第一開口及一第二開口,分別位於其兩端,該等鋼筋續接器之該第一開口與該第一預鑄梁結構內之梁鋼筋之末端固接,該等鋼筋續接器之該第二開口暴露於該第第一預鑄梁結構之該端面,並經構形以允許該第二預鑄梁結構內之該複數個梁鋼筋插入其中;以及一第一貫穿孔,相鄰該第一開口,貫穿該鋼筋續接器之外壁,並與該第一開口連通;以及複數個漿料管線,埋設於該第一預鑄梁結構內,該複數個漿料管線流體連通該複數個鋼筋續接器之該複數個第一貫穿孔以及該第一預鑄梁結構之外部。 One embodiment of the present invention provides a building structure, which includes: a first ridge beam structure and a second ridge beam structure, each having an end face, the two end faces being arranged adjacently and defining a gap therebetween, wherein The end face of the second Kaifeng beam structure includes a plurality of beam steel bars extending outward; a plurality of steel bar connectors are embedded in the end face of the first Kaifeng beam structure, and each of the plurality of steel bar connectors includes : A first opening and a second opening, respectively located at both ends. The first opening of the steel bar connector is fixedly connected to the end of the beam steel bar in the first Jiaxuan beam structure. The steel bar connector is connected the second opening of the vessel is exposed to the end surface of the first Kaifeng beam structure and is configured to allow the plurality of beam steel bars within the second Kaifeng beam structure to be inserted therein; and a first through hole, Adjacent to the first opening, penetrates the outer wall of the steel connector and is connected to the first opening; and a plurality of slurry pipelines are buried in the first slurry beam structure, and the plurality of slurry pipelines are fluidly connected The plurality of first through-holes of the plurality of steel bar connectors and the outside of the first beam structure.

本發明之另一實施例提供一種建築結構之建造方法,其包括:一種建築方法,包括:提供一第一預鑄梁結構,包括複數個鋼筋續接器設置於其一端面,每一該複數個鋼筋續接器包括一第一開口及一第二開口,分別位於其兩端,該等鋼筋續接器之該第一開口與該第一預鑄梁結構內之梁鋼筋之末端固接,該等鋼筋續接器之該第二開口暴露於該第一預鑄梁結構之該端面,一第一貫穿孔相鄰該第一開口並貫穿該鋼筋續接器之外 壁以與該第一開口連通;以及複數個漿料管線,埋設於該第一預鑄梁結構內,該複數個漿料管線流體連通該複數個鋼筋續接器之複數個該第一貫穿孔以及該第一預鑄梁結構之外部;提供一第二預鑄梁結構,包括複數個梁鋼筋自其一端面向外延伸;吊裝該第二預鑄梁結構,以使該第二預鑄梁結構之複數個梁鋼筋伸入該第一預鑄梁結構內之該複數個鋼筋續接器之該複數個第二開口中;定位該第一預鑄梁結構以及該第二預鑄梁結構,以在該第一預鑄梁結構之該端面以及該第二預鑄梁結構之該端面之間提供一間隙;經由該複數個漿料管線其中之一者供應一砂漿材料至該複數個鋼筋續接器之一者,並使該砂漿材料經由該複數個鋼筋續接器之該者之該第二開口流入該間隙中,進而填充該砂漿材料至該複數個鋼筋續接器之其他者內。 Another embodiment of the present invention provides a construction method of a building structure, which includes: a construction method including: providing a first girder structure, including a plurality of steel bar connectors disposed on one end surface thereof, each of the plurality of Each steel bar connector includes a first opening and a second opening, respectively located at both ends thereof, and the first openings of the steel bar connectors are fixedly connected to the ends of the beam steel bars in the first gaixuan beam structure, The second openings of the steel bar connectors are exposed to the end surface of the first beam structure, and a first through hole is adjacent to the first opening and penetrates outside the steel bar connectors. The wall is connected to the first opening; and a plurality of slurry pipelines are buried in the first beam structure, and the plurality of slurry pipelines are fluidly connected to the plurality of first through holes of the plurality of steel connectors. and the exterior of the first Kaixuan beam structure; provide a second Kaixuan beam structure, including a plurality of beam steel bars extending outward from one end thereof; hoist the second Kaixuan beam structure so that the second Kaixuan beam structure The plurality of beam steel bars extend into the plurality of second openings of the plurality of steel bar connectors in the first Xiaoxuan beam structure; position the first Xiaoxuan beam structure and the second Xiaoxuan beam structure to A gap is provided between the end surface of the first Kaifeng beam structure and the end surface of the second Kaifeng beam structure; a mortar material is supplied to the plurality of steel bar splices through one of the plurality of slurry pipelines one of the devices, and the mortar material flows into the gap through the second opening of the plurality of steel bar connectors, and then the mortar material is filled into other of the plurality of steel bar connectors.

1:建築系統 1:Building system

9:垂直鋼筋 9:Vertical steel bars

10:外圍建築系統 10: Peripheral building system

11:預鑄角柱 11: 鐐鄄corner pillar

13:預鑄邊柱 13: 鐐鄄 border pillar

15:預鑄連接結構/第一預鑄連接結構 15: 鐐鄄connection structure/first 鐐鄄connection structure

15’:預鑄連接結構 15’: 鐐鄄connection structure

17:預鑄連接結構/第二預鑄連接結構 17: 鐐鄄connection structure/second 鐐鄄connection structure

17’:預鑄連接結構 17’: 鐐鄄connection structure

19:預鑄連接結構 19: 鐐鄄connection structure

20:預鑄梁結構 20: Xuan beam structure

21:梁鋼筋/第一梁鋼筋 21: Beam reinforcement/first beam reinforcement

25:預鑄梁結構 25: Xuan beam structure

30:場鑄接續結構 30: Field casting continuous structure

31:固定鋼筋續接器 31: Fixed steel bar connector

32:連接鋼筋 32:Connecting steel bars

34:箍筋 34: stirrups

35:可移動鋼筋續接器 35: Removable steel bar connector

40:內部建築系統 40:Internal building systems

41:內部柱結構 41: Internal column structure

42:內部梁結構 42: Internal beam structure

43:內部預鑄柱結構 43: Internal column structure

44:內部預鑄連接結構 44: Internal hook-and-loop connection structure

45:內部預鑄連接結構 45: Internal hook-and-loop connection structure

46:平台 46:Platform

47:平台 47:Platform

48:天井 48: Patio

49:天井 49: Patio

60:鋼筋續接器 60:Reinforcement bar connector

60a:鋼筋續接器 60a: Rebar connector

60’:上游鋼筋續接器 60’: Upstream steel bar connector

60a’:上游鋼筋續接器 60a’: upstream steel connector

61:第一開口 61:First opening

62:第二開口 62:Second opening

63:第一貫穿孔/貫穿孔 63: First through hole/through hole

64:第二貫穿孔/貫穿孔 64: Second through hole/through hole

70:漿料管線 70: Slurry pipeline

71:第一端 71:First end

72:第二端 72:Second end

91:裝飾面板 91: Decorative panel

92:密封元件 92:Sealing element

93:砂漿材料 93: Mortar material

94:塞子 94: stopper

95:傳輸管 95:Transmission tube

96:樓板連接件 96: Floor connectors

97:樓地板 97: Floor

111:頂表面 111:Top surface

112:續接結構 112: Continuation structure

131:頂表面 131:Top surface

132:續接結構 132: Continuation structure

150:第一預鑄連接頭 150: The first connector

151:第一預鑄梁結構 151:The first Xuan beam structure

151a:第一預鑄梁結構 151a: The first Qixuan beam structure

152:第一預鑄梁結構 152:The first Xuan beam structure

153:梁鋼筋 153:Beam reinforcement

154:梁鋼筋 154:Beam reinforcement

155:穿孔 155:Perforation

157:溝槽 157:Trench

170:第二預鑄連接頭 170: The second connector

171:第二預鑄梁結構 171:Second Haixuan beam structure

172:第二預鑄梁結構 172:Second Haixuan beam structure

173:梁鋼筋/第二梁鋼筋 173: Beam reinforcement/Second beam reinforcement

174:梁鋼筋 174:Beam reinforcement

175:穿孔 175:Perforation

179:梁鋼筋 179:Beam reinforcement

201:第一端 201:First end

202:第二端 202:Second end

440:內部預鑄連接頭 440: Internal connector

441:內部預鑄梁結構 441: Internal Xuan beam structure

442:內部預鑄梁結構 442: Internal Xuan beam structure

450:內部預鑄連接頭 450: Internal connector

451:內部預鑄梁結構 451: Internal Xuan beam structure

960:本體 960:Ontology

961:闊頭 961:Broadhead

962:連接頭 962: Connector

965:連接鋼筋 965:Connecting steel bars

971:混凝土 971:Concrete

1501:側表面 1501:Side surface

1502:側表面 1502:Side surface

1503:頂表面 1503:Top surface

1511:端面 1511:End face

1512:側表面 1512:Side surface

1513:上表面 1513: Upper surface

1532:錨定頭 1532:Anchor head

1542:錨定頭 1542:Anchor head

1701:側表面 1701:Side surface

1702:側表面 1702:Side surface

1703:側表面 1703:Side surface

1711:端面 1711: End face

1721:端面 1721: End face

1722:側表面 1722:Side surface

1723:上表面 1723: Upper surface

1721:端面 1721: End face

G:間隙 G: Gap

L1:距離 L1: distance

L2:長度 L2: length

L3:長度 L3: length

L4:長度 L4:Length

圖1展示本發明之一實施例中的建築結構之示意圖。 Figure 1 shows a schematic diagram of a building structure in one embodiment of the present invention.

圖2展示本發明上述實施例中的建築結構之製造方法之示意圖一。 Figure 2 shows a schematic diagram 1 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖3展示本發明上述實施例中的建築結構之製造方法之示意圖二。 Figure 3 shows a second schematic diagram of the manufacturing method of the building structure in the above embodiment of the present invention.

圖3A展示本發明上述實施例中的第一預鑄連接結構之部分結構之俯視圖。 FIG. 3A shows a top view of part of the first cage connection structure in the above embodiment of the present invention.

圖4展示本發明上述實施例中的建築結構之製造方法之示意圖三。 Figure 4 shows the third schematic diagram of the manufacturing method of the building structure in the above embodiment of the present invention.

圖5展示本發明上述實施例中的建築結構之製造方法之示意圖四。 Figure 5 shows a schematic diagram 4 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖6展示本發明上述實施例中的建築結構之製造方法之示意圖五。 Figure 6 shows a schematic diagram 5 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖7A展示本發明上述實施例中的建築結構之二個對接之預鑄梁結構之示意圖。 FIG. 7A shows a schematic diagram of two butt-jointed beam structures of the building structure in the above embodiment of the present invention.

圖7B展示本發明上述實施例中的建築結構之一預鑄梁結構在垂直預鑄梁結構之延伸方向上之斷面圖。 FIG. 7B shows a cross-sectional view of the Kaixuan beam structure in the extending direction of the vertical Kaixuan beam structure, one of the building structures in the above embodiment of the present invention.

圖7C展示本發明上述實施例中的建築結構之二個對接之預鑄梁結構在平行預鑄梁結構之延伸方向上之斷面圖。 7C shows a cross-sectional view of two butt-jointed Kaifeng beam structures of the building structure in the above embodiment of the present invention in the extending direction of the parallel Kaixuan beam structure.

圖7D-7I展示本發明上述實施例中的建築結構之二個預鑄梁結構之對接方法之示意圖。 7D-7I show schematic diagrams of the docking method of the two beam structures of the building structure in the above embodiment of the present invention.

圖7J展示本發明上述實施例中的建築結構之樓地板之製作方法之示意圖 Figure 7J shows a schematic diagram of the method for manufacturing the floor of the building structure in the above embodiment of the present invention.

圖8A-8G展示本發明另一實施例中的建築結構之二個預鑄梁結構之對接方法之示意圖。 8A-8G show schematic diagrams of the docking method of two beam structures of the building structure in another embodiment of the present invention.

圖9展示本發明上述實施例中的建築結構之製造方法之示意圖六。 Figure 9 shows a schematic diagram 6 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖10展示本發明上述實施例中的建築結構之製造方法之示意圖七。 Figure 10 shows a schematic seventh view of the manufacturing method of the building structure in the above embodiment of the present invention.

圖11展示本發明上述實施例中的建築結構之製造方法之示意圖八。 Figure 11 shows a schematic diagram 8 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖12展示本發明上述實施例中的建築結構之製造方法之示意圖九。 Figure 12 shows a schematic diagram 9 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖13展示本發明上述實施例中的建築結構之製造方法之示 意圖十。 Figure 13 shows the manufacturing method of the building structure in the above embodiment of the present invention. Intent ten.

圖14展示本發明上述實施例中的建築結構之製造方法之示意圖十一。 Figure 14 shows a schematic diagram 11 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖15展示本發明上述實施例中的建築結構之製造方法之示意圖十二。 Figure 15 shows a schematic diagram of the manufacturing method of the building structure in the above embodiment of the present invention.

圖16展示本發明上述實施例中的建築結構之製造方法之示意圖十三。 Figure 16 shows a schematic diagram 13 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖17展示本發明上述實施例中的建築結構之製造方法之示意圖十四。 Figure 17 shows a schematic diagram of the manufacturing method of the building structure in the above embodiment of the present invention.

圖18展示本發明上述實施例中的建築結構之製造方法之示意圖十五。 Figure 18 shows a schematic diagram 15 of the manufacturing method of the building structure in the above embodiment of the present invention.

圖19展示本發明另一實施例中的建築結構之一平面示意圖。 Figure 19 shows a schematic plan view of a building structure in another embodiment of the present invention.

圖20展示本發明之又一實施例中的建築結構之一平面示意圖。 Figure 20 shows a schematic plan view of a building structure in yet another embodiment of the present invention.

為更清楚了解本創作之特徵、內容與優點及其所能達成之功效,茲將本創作配合附圖,並以實施例之表達形式詳細說明如下,而其中所使用之圖式,其主旨僅為示意及輔助說明書之用,故不應就所附之圖式的比例與配置關係解讀、侷限本創作的申請專利範圍。 In order to have a clearer understanding of the characteristics, content and advantages of this invention and the effects it can achieve, this invention is described in detail below in conjunction with the accompanying drawings and in the form of embodiments. The purpose of the diagrams used is only They are for illustration and auxiliary description purposes, so the proportions and configuration relationships of the attached drawings should not be interpreted to limit the patentable scope of this creation.

本揭露中的用語「一」或「一種」係用以敘述本創作之元件及成分。此術語僅為了敘述方便及給予本創作之基本觀念。此敘述應被理解為包括一種或至少一種,且除非明顯地另有所指,表示單數時亦包括 複數。於申請專利範圍中和「包含」一詞一起使用時,該用語「一」可意謂一個或超過一個。此外,本揭露中的用語「或」其意同「及/或」。 The term "a" or "an" in this disclosure is used to describe the components and components of the invention. This terminology is only for convenience of description and to give the basic concept of this creation. The recitation shall be understood to include one or at least one and, unless expressly stated otherwise, the singular also includes plural. When used with the word "comprising" in a patent application, the term "a" can mean one or more than one. In addition, the word "or" used in this disclosure means the same as "and/or".

除非另外規定,否則諸如「上方」、「下方」、「向上」、「左邊」、「右邊」、「向下」、「本體」、「底座」、「垂直」、「水平」、「側」、「較高」、「下部」、「上部」、「上方」、「下面」等空間描述係關於圖中所展示之方向加以指示。應理解,本揭露中所使用之空間描述僅出於說明之目的,且本揭露中所描述之結構之實際實施可以任何相對方向在空間上配置,此限制條件不會改變本發明實施例之優點。舉例來說,在一些實施例之描述中,提供「在」另一元件「上」之一元件可涵蓋前一元件直接在後一元件上(例如,與後一元件實體接觸)的狀況以及一或複數個介入元件位於前一元件與後一元件之間的狀況。 Unless otherwise specified, terms such as "above", "below", "up", "left", "right", "down", "body", "base", "vertical", "horizontal", "side" Spatial descriptions such as "higher", "lower", "upper", "above", and "below" indicate the direction shown in the figure. It should be understood that the spatial description used in this disclosure is for illustrative purposes only, and actual implementations of the structures described in this disclosure may be spatially configured in any relative orientation. This limitation does not change the advantages of the embodiments of the present invention. . For example, in the description of some embodiments, providing that one element is "on" another element may cover situations where the former element is directly on (e.g., in physical contact with) the latter element, as well as when an element is "on" the latter element. Or a situation where multiple intervening components are located between the previous component and the following component.

如本揭露中所使用,術語「大致」、「實質上」、「實質的」及「約」用以描述及考慮微小之變化。當與事件或情形結合使用時,該等術語可意指事件或情形明確發生之情況以及事件或情形極近似於發生之情況。 As used in this disclosure, the terms "substantially," "substantially," "substantially," and "approximately" are used to describe and account for minor changes. When used in connection with an event or circumstance, these terms may mean both a definite occurrence of the event or circumstance and a close approximation of the occurrence of the event or circumstance.

本揭露以下內容中,包括「預鑄」之元件名稱(例如:預鑄角柱、預鑄邊柱、預鑄連接結構、預鑄梁結構等)所對應之結構係採用「預鑄工法」製造之建築結構,其係於預鑄廠或工地周邊,以標準化的作業流程及模組化的模具,施工鋼筋結構,例如鋼筋籠,構築模板並澆置混凝土,快速大量生產高精密度且高品質均一性的柱體、梁體、板體等的結構體構件。隨後,於工地現場中藉由精確的搬運管理及組裝作業,將生產完成之結構體構件於工地現場組合。另一方面,包括「場鑄」之元件名稱 (例如:場鑄接續結構等)所對應之結構係採用傳統「場鑄工法」之建築結構,其係於工地現場施工鋼筋結構、構築模板並澆置混凝土所完成之結構。 In the following content of this disclosure, the structure corresponding to the component name of "鐐鄄" (for example: 鐐鄄 corner column, 鐐鄄 side column, 鐐鄄 connection structure, 鐐鄄 beam structure, etc.) is manufactured using the "鐐鄄 construction method" Building structures, which are located in the Xixuan factory or around the construction site, use standardized operating procedures and modular molds to construct steel structures, such as steel cages, build formwork and pour concrete, to produce rapid mass production with high precision and high uniformity. Structural components such as columns, beams, plates, etc. Subsequently, through precise handling management and assembly operations, the completed structural components are assembled at the construction site. On the other hand, the component name including "field casting" (For example: field-cast continuous structure, etc.) The corresponding structure is a building structure that adopts the traditional "field-casting method". It is a structure completed by constructing a steel structure, building formwork and pouring concrete on the construction site.

根據本發明之一實施例,本發明之建築系統之單一樓層的外圍建築系統係採梁柱預鑄結構,內部建築系統之部分結構可採梁柱預鑄結構或以傳統場鑄工法製造。外圍建築系統包括多個預鑄角柱、多個預鑄邊柱、多個預鑄連接結構、至少一預鑄梁結構、及至少一場鑄接續結構。內部建築系統則可選擇地包括一或多個預鑄梁柱結構並以傳統場鑄工法製造剩餘之梁柱結構,或是所有梁柱結構皆以傳統場鑄工法製造。 According to an embodiment of the present invention, the single-story outer building system of the building system of the present invention adopts a beam-column-joint structure, and part of the structure of the internal building system can adopt a beam-column-joint structure or be manufactured by traditional casting methods. The peripheral building system includes a plurality of 鐐鄄 corner columns, a plurality of 鐐鄄 side columns, a plurality of 鐐鄄 connection structures, at least one 鐐鄄 beam structure, and at least one cast continuous structure. The internal building system can optionally include one or more beam and column structures and use traditional field casting methods to fabricate the remaining beam and column structures, or all beam and column structures can be fabricated using traditional field casting methods.

圖1展示之本發明之一實施例中的建築系統1之示意圖。建築系統1之單一樓層之外圍建築系統10包括複數個預鑄柱(例如:四個預鑄角柱11、八個預鑄邊柱13)、四個第一預鑄連接結構15、八個第二預鑄連接結構17、二個預鑄梁結構20、及二個場鑄接續結構30。建築系統1之內部建築系統40則是部分採梁柱預鑄結構,並以傳統場鑄工法製造剩餘之梁柱結構,其中包括二個內部柱結構41、多個內部梁結構42、二個內部預鑄柱結構43及二個內部預鑄連接結構44、45。 Figure 1 shows a schematic diagram of a building system 1 in an embodiment of the present invention. The outer building system 10 of a single floor of the building system 1 includes a plurality of 鐐鄄 pillars (for example: four 鐐鄄 corner columns 11, eight 鐐鐄 side columns 13), four first 鐐鄄 connecting structures 15, and eight second The connecting structure 17, two beam structures 20, and two casting connection structures 30. The internal building system 40 of the building system 1 is partially made of a beam-column structure, and the remaining beam-column structure is manufactured using traditional field casting methods, including two internal column structures 41, multiple internal beam structures 42, and two internal beam structures. The 鐐鄄 pillar structure 43 and the two internal 鐐鄄 connection structures 44 and 45.

根據本揭露之部分實施例,建築系統1之施工方法說明如下:建築系統1之施工方法包括定位外圍建築系統10之預鑄柱結構及內部建築系統40之預鑄柱結構。舉例而言,在圖1所展示之實施例中,在對建築系統1之各樓層進行建造時,首先將該樓層之外圍建築系統10之四個預鑄角柱11放置於建築系統1之角隅,並將該樓層之外圍建築系統10之二個預鑄邊柱13放置於每二個預鑄角柱11之間。並且,將該樓層 之內部建築系統40之二個內部預鑄柱結構43排列於該等預鑄角柱11及預鑄邊柱13所包圍之區域內。預鑄角柱11、預鑄邊柱13及內部預鑄柱結構43可各自具有建築系統1之單一樓層之高度,並藉由吊車(圖未示)垂直吊放於工地現場。在其他實施例中,預鑄角柱11、預鑄邊柱13及內部預鑄柱結構43可定位於已完成建造之下方樓層之預鑄連接結構之上。關於預鑄角柱、預鑄邊柱及內部預鑄柱結構與預鑄連接結構之連接方法請參見2022年10月17日申請之中華民國發明專利申請案第111139260號,該案之全部內容以引用方式併入本揭露中。 According to some embodiments of the present disclosure, the construction method of the building system 1 is described as follows: the construction method of the building system 1 includes positioning the column structure of the peripheral building system 10 and the column structure of the internal building system 40 . For example, in the embodiment shown in FIG. 1 , when constructing each floor of the building system 1 , firstly, the four corner columns 11 of the peripheral building system 10 of the floor are placed at the corners of the building system 1 , and place the two side columns 13 of the peripheral building system 10 of the floor between every two corner columns 11. And, put this floor The two internal column structures 43 of the internal building system 40 are arranged in the area surrounded by the corner columns 11 and the side columns 13 . The corner columns 11, the side columns 13 and the internal column structure 43 can each have the height of a single floor of the building system 1, and can be vertically suspended on the construction site by a crane (not shown). In other embodiments, the corner posts 11 , side posts 13 and internal post structure 43 may be positioned on top of the completed connection structure of the floor below. Regarding the connection method of the 鐐鄄 corner columns, 鐐鄄 side columns and the internal 鐐鄄 column structure and the 鐐鐄 connection structure, please refer to the Republic of China Invention Patent Application No. 111139260 filed on October 17, 2022. The entire content of the case is quoted. methods are incorporated into this disclosure.

如圖2所示,預鑄角柱11包括管狀的複數個續接結構112垂直埋設於其中。續接結構112之一端部暴露於預鑄角柱11之頂表面111並經構形以允許垂直鋼筋9插入其中並與其接合。相似地,預鑄邊柱13包括管狀的複數個續接結構132垂直埋設於其中。續接結構132之一端部暴露於預鑄邊柱13之頂表面131並經構形以允許垂直鋼筋9(未展示於圖2)插入其中並與其接合。 As shown in FIG. 2 , the corner column 11 includes a plurality of tubular continuous structures 112 vertically embedded therein. One end of the continuation structure 112 is exposed to the top surface 111 of the corner post 11 and is configured to allow vertical steel bars 9 to be inserted therein and engaged therewith. Similarly, the side pillar 13 includes a plurality of tubular continuous structures 132 vertically embedded therein. One end of the continuation structure 132 is exposed to the top surface 131 of the side column 13 and is configured to allow vertical steel bars 9 (not shown in Figure 2) to be inserted therein and engaged therewith.

在預鑄柱結構定位完成後,建築系統1之施工方法更包括將預鑄連接結構固定設置於對應之預鑄柱結構之上,並在水平方向上對預鑄連接結構進行耦接。舉例而言,如圖3所示,該等預鑄連接結構中的第一預鑄連接結構15係藉由吊車(圖未示)吊放於預鑄角柱11之上。第一預鑄連接結構15包括一第一預鑄連接頭150及二個彼此大致垂直的預鑄梁結構151、152(下稱第一預鑄梁結構151、152)。第一預鑄連接頭150設置於預鑄角柱11上方,並經構形以其底部連接預鑄角柱11以及以其兩個相鄰側邊與該二個彼此大致垂直的第一預鑄梁結構151、152連接。複數個穿孔155垂直穿設第一預鑄連接頭150,當第一預鑄連接頭150吊放於預 鑄角柱11之上時,如圖3所示,垂直鋼筋9穿過穿孔155,並自第一預鑄連接頭150之頂表面1503突出向上延伸。 After the positioning of the Xixuan column structure is completed, the construction method of the building system 1 further includes fixing the Xixuan connection structure on the corresponding Xixuan column structure, and coupling the Xixuan connection structure in the horizontal direction. For example, as shown in FIG. 3 , the first one of the three connection structures 15 is suspended on the one corner column 11 by a crane (not shown). The first K-shaped connection structure 15 includes a first K-shaped connecting head 150 and two K-shaped beam structures 151 and 152 that are substantially perpendicular to each other (hereinafter referred to as the first K-shaped beam structures 151 and 152). The first connecting head 150 is disposed above the corner column 11 and is configured to connect its bottom to the corner column 11 and its two adjacent sides to the two first beam structures that are substantially perpendicular to each other. 151, 152 connections. A plurality of through holes 155 are vertically inserted into the first connector 150. When the first connector 150 is hung on the predetermined When the corner post 11 is cast, as shown in FIG. 3 , the vertical steel bars 9 pass through the through holes 155 and protrude upward from the top surface 1503 of the first hook connector 150 .

如圖2所示,垂直鋼筋9係在第一預鑄連接結構15吊放於預鑄角柱11之上之前即預先固定設置於預鑄角柱11之上,並在第一預鑄連接頭150經由吊放的下降過程中,使複數個垂直鋼筋9分別穿設複數個穿孔155。在一些實施例中,垂直鋼筋9係在第一預鑄連接結構15吊放於預鑄角柱11之上之後,方插入穿孔155內並與預鑄角柱11內之續接結構132接合。在一些實施例中,如圖3A所示,第一預鑄連接頭150包括複數個箍筋156用以圍束設置於穿孔155中的垂直鋼筋。 As shown in FIG. 2 , the vertical steel bars 9 are pre-fixed on the corner posts 11 before the first link structure 15 is hung on the corner posts 11 , and are passed through the first link connector 150 During the hanging and lowering process, a plurality of vertical steel bars 9 are penetrated through a plurality of perforations 155 respectively. In some embodiments, the vertical steel bars 9 are inserted into the through holes 155 and joined with the continuing structure 132 in the corner column 11 after the first connecting structure 15 is suspended on the corner column 11 . In some embodiments, as shown in FIG. 3A , the first stirrup connector 150 includes a plurality of stirrups 156 for surrounding vertical steel bars disposed in the through holes 155 .

如圖4所示,二個第一預鑄梁結構151、152分別連結第一預鑄連接頭150上相互垂直之二個側表面1501、1502。換言之,二個第一預鑄梁結構151、152分別自第一預鑄連接頭150之相互垂直之二個側表面1501、1502向外延伸。如圖3A所示,每一第一預鑄梁結構151、152分別具有複數個梁鋼筋153、154,其一端設置於第一預鑄連接頭150內並自第一預鑄連接頭150向外沿水平方向延伸。複數個梁鋼筋153、154位於第一預鑄連接頭150內之端部包含具較大寬度之錨定頭1532、1542。藉由錨定頭1532、1542之設置可增加梁鋼筋153、154與第一預鑄連接頭150之間的連結強度。第一預鑄梁結構151、152之梁鋼筋153、154在第一預鑄連接頭150中位於不同高度,彼此互不干涉。 As shown in FIG. 4 , the two first hook beam structures 151 and 152 are respectively connected to the two mutually perpendicular side surfaces 1501 and 1502 of the first hook connection 150 . In other words, the two first hinge beam structures 151 and 152 respectively extend outward from the two mutually perpendicular side surfaces 1501 and 1502 of the first hinge connection head 150 . As shown in FIG. 3A , each first Kaifeng beam structure 151 and 152 respectively has a plurality of beam steel bars 153 and 154, one end of which is disposed in the first Kawasaki connector 150 and extends outward from the first Kawasaki connector 150. Extend horizontally. The ends of the plurality of beam steel bars 153 and 154 located in the first joint 150 include anchor heads 1532 and 1542 with larger widths. Through the arrangement of the anchor heads 1532 and 1542, the connection strength between the beam steel bars 153 and 154 and the first hook connector 150 can be increased. The beam steel bars 153 and 154 of the first beam structures 151 and 152 are located at different heights in the first beam connector 150 and do not interfere with each other.

如圖3A所示,第一預鑄梁結構151之一端面1511係預先埋設有複數個鋼筋續接器60於其中。鋼筋續接器60為管狀且具有一第一開口62及一第二開口61,分別位於鋼筋續接器60之相對二端,並與鋼筋續接器60內部之中空通道連通。第一開口62與梁鋼筋153之末端1531固接。 第二開口61暴露於第一預鑄梁結構151之端面1511並經構形以允許另一梁結構之梁鋼筋(未展示於圖3A)插入其中並與其接合。如圖7E至圖7H所示,二個貫穿孔64、63(下稱第一貫穿孔64及第二貫穿孔63)分別相鄰第一開口62及第二開口61貫穿鋼筋續接器60之壁面,並經構形以連接用於輸送砂漿材料之漿料管線。關於漿料管線之供應方式將於下方關於圖7D至圖7I之描述中詳細說明。 As shown in FIG. 3A , a plurality of steel bar connectors 60 are pre-embedded in one end face 1511 of the first beam structure 151 . The steel bar connector 60 is tubular and has a first opening 62 and a second opening 61 , which are respectively located at two opposite ends of the steel bar connector 60 and connected with the hollow channel inside the steel bar connector 60 . The first opening 62 is fixedly connected to the end 1531 of the beam steel bar 153. The second opening 61 is exposed to the end surface 1511 of the first beam structure 151 and is configured to allow the beam reinforcement of another beam structure (not shown in Figure 3A) to be inserted therein and engaged therewith. As shown in FIGS. 7E to 7H , two through holes 64 and 63 (hereinafter referred to as the first through hole 64 and the second through hole 63 ) are respectively adjacent to the first opening 62 and the second opening 61 and penetrate through the steel bar connector 60 . Walls configured to connect slurry lines for transporting mortar materials. The supply method of the slurry pipeline will be explained in detail in the description of FIGS. 7D to 7I below.

繼續參照圖4,在第一預鑄連接結構15定位施工完成後,繼續第二預鑄連接結構17之定位施工。在一實施例中,第二預鑄連接結構17包括一第二預鑄連接頭170及二個預鑄梁結構171、172(下稱第二預鑄梁結構171、172)。第二預鑄連接頭170設置於預鑄邊柱13上方,並經構形以其底部連接預鑄邊柱13且以其兩相對側與二個彼此大致平行且對齊之第二預鑄梁結構171、172連接。換言之,二個第二預鑄梁結構171、172分別自第二預鑄連接頭170之相對之二個側表面1701、1702向外延伸。相似於第一預鑄梁結構151、152,第二預鑄梁結構171、172也分別具有複數個梁鋼筋(圖4僅展示第二預鑄梁結構172之梁鋼筋174),其一端設置於第二預鑄連接頭170內並自第二預鑄連接頭170向外沿水平方向延伸。第二預鑄梁結構171之梁鋼筋之末端係固定於位於端面1711之鋼筋續接器60中,且第二預鑄梁結構172之梁鋼筋174之末端自第二預鑄梁結構172之端面1721延伸而出。複數個穿孔175垂直穿設第二預鑄連接頭170。穿孔175經構形以允許垂直鋼筋(未展示於圖4)穿設,進而將第二預鑄連接頭170固定於預鑄邊柱13之上。第二預鑄連接結構17進一步包括複數個梁鋼筋179,其一端設置於第二預鑄連接頭170內並自第二預鑄連接頭170之側表面1703向外沿水平方向延伸。第二預鑄連接頭170之側表面1703面向 建築物內部,並位於側表面1701、1702之間。梁鋼筋179經構形以連接內部梁結構42(參圖1)。 Continuing to refer to FIG. 4 , after the positioning construction of the first connecting structure 15 is completed, the positioning construction of the second connecting structure 17 is continued. In one embodiment, the second K-shaped connection structure 17 includes a second K-shaped connecting head 170 and two K-shaped beam structures 171 and 172 (hereinafter referred to as the second K-shaped beam structures 171 and 172). The second hook connector 170 is disposed above the bracket 13 and is configured to connect its bottom to the bracket 13 and its two opposite sides to two second bracket structures that are substantially parallel and aligned with each other. 171, 172 connections. In other words, the two second clamp beam structures 171 and 172 respectively extend outward from the two opposite side surfaces 1701 and 1702 of the second clamp connection head 170 . Similar to the first Xiaoxuan beam structures 151 and 152, the second Xiaoxuan beam structures 171 and 172 also have a plurality of beam steel bars respectively (FIG. 4 only shows the beam steel bars 174 of the second Xiaoxuan beam structure 172), one end of which is provided at The second connector 170 extends outwardly from the second connector 170 in a horizontal direction. The end of the beam steel bar of the second Kaifeng beam structure 171 is fixed in the steel bar connector 60 located at the end face 1711, and the end of the beam steel bar 174 of the second Kaifeng beam structure 172 is from the end surface of the second Kaifeng beam structure 172 1721 extends out. A plurality of through holes 175 vertically penetrate the second connector 170 . The perforations 175 are configured to allow vertical steel bars (not shown in FIG. 4 ) to be passed through to secure the second hook connector 170 to the bracket 13 . The second connecting structure 17 further includes a plurality of beam steel bars 179 , one end of which is disposed in the second connecting head 170 and extends outward in the horizontal direction from the side surface 1703 of the second connecting head 170 . The side surface 1703 of the second connector 170 faces Inside the building and between side surfaces 1701, 1702. Beam reinforcement 179 is configured to connect the internal beam structure 42 (see Figure 1).

參照圖4-6,第二預鑄連接結構17與預鑄邊柱13定位並與第一預鑄連接結構15對接之施工步驟說明如下:首先,先將第二預鑄連接結構17吊放至預鑄邊柱13之頂表面130之上之一偏移位置。如圖4所示,在此偏移位置上,第二預鑄梁結構172之端面1721與第一預鑄梁結構151之端面1511間隔一既定距離,且第二預鑄連接頭170係與預鑄邊柱13之頂表面130偏移設置,使第二預鑄連接頭170未完全覆蓋預鑄邊柱13之頂表面130。接著,沿圖4之箭頭所示之方向,對第二預鑄連接結構17執行一橫向移動施工。在橫向移動施工中,第二預鑄連接結構17朝向第一預鑄連接結構15移動,使固定於第一預鑄梁結構151內之鋼筋續接器60套設第二預鑄梁結構172之梁鋼筋174,並使第二預鑄梁結構172之端面1721相鄰第一預鑄梁結構151之端面1511設置。在完成上述橫向移動之施工後,如圖5所示,第二預鑄連接頭170對齊預鑄邊柱13之頂表面130,且第二預鑄連接頭170完全覆蓋預鑄邊柱13之頂表面130。接著,如圖6所示,在第二預鑄連接頭170對齊預鑄邊柱13之頂表面130之後,將垂直鋼筋9插入第二預鑄連接頭170上之穿孔175內並使其與預鑄邊柱13內之續接結構132(參圖3)接合。 Referring to Figures 4-6, the construction steps for positioning the second 鐐鄄 connection structure 17 and the 鐐鄄 side column 13 and docking with the first 鐐鄄 connection structure 15 are as follows: First, hoist the second 鐐鄄 connection structure 17 to An offset position above the top surface 130 of the side pillar 13 . As shown in FIG. 4 , at this offset position, the end surface 1721 of the second Kaixuan beam structure 172 is separated from the end surface 1511 of the first Kaixuan beam structure 151 by a predetermined distance, and the second Kaixuan connector 170 is connected to the predetermined distance. The top surface 130 of the cast edge pillar 13 is offset, so that the second hook connector 170 does not completely cover the top surface 130 of the edge pillar 13 . Then, perform a lateral movement construction on the second hook connection structure 17 in the direction shown by the arrow in FIG. 4 . During the lateral movement construction, the second connecting structure 17 moves toward the first connecting structure 15 , so that the steel connector 60 fixed in the first connecting structure 151 is sleeved on the second connecting structure 172 The beam reinforcement 174 is installed, and the end surface 1721 of the second Kaifeng beam structure 172 is arranged adjacent to the end surface 1511 of the first Kaifeng beam structure 151 . After completing the construction of the above-mentioned lateral movement, as shown in Figure 5, the second Xiaoxuan connector 170 is aligned with the top surface 130 of the Xiaoxuan side column 13, and the second Xiaoxuan connector 170 completely covers the top of the Xiaoxuan side column 13. Surface 130. Next, as shown in FIG. 6 , after the second hook connector 170 is aligned with the top surface 130 of the bracket side column 13 , insert the vertical steel bar 9 into the through hole 175 on the second hook connector 170 and align it with the predetermined The continuous structure 132 (see Figure 3) in the cast side pillar 13 is connected.

在一實施例中,砂漿材料(圖未示)係填充於預鑄連接頭(例如:第一預鑄連接結構15、第二預鑄連接結構17)與預鑄柱(例如:預鑄角柱11、預鑄邊柱13)之間並且填充於垂直鋼筋9穿設之穿孔155或穿孔175之部分空間中,以固定預鑄連接頭、預鑄柱及垂直鋼筋。關於預鑄連接頭、預鑄柱及垂直鋼筋之連接方法請參見2022年6月30日申 請之中華民國發明專利申請案第111124472號,該案之全部內容以引用方式併入本揭露中。 In one embodiment, the mortar material (not shown) is filled in the connecting joints (for example, the first connecting structure 15 and the second connecting structure 17) and the supporting columns (such as the corner columns 11). , between the side columns 13) and filled in part of the space of the perforations 155 or the perforations 175 where the vertical steel bars 9 are penetrated to fix the joints, columns and vertical steel bars. For the connection methods of the 鐐鄄 connectors, 鐐鄄 pillars and vertical steel bars, please refer to the application on June 30, 2022 Please refer to the Republic of China Invention Patent Application No. 111124472, the entire contents of which are incorporated into this disclosure by reference.

在一實施例中,相鄰之預鑄梁結構之續接方法,參照圖7A-7C,說明如後。如圖7A-7C所示,複數個漿料管線70係埋設於第一預鑄梁結構151鄰近端面1511之區域,並經構形以供應砂漿材料至埋設於第一預鑄梁結構151內部之鋼筋續接器60,或是經構形以允許少部分多餘砂漿材料自埋設於第一預鑄梁結構151內部之鋼筋續接器60流出。如圖7B所示,每一漿料管線70具有一第一端71及一第二端72。漿料管線70之第一端71係連結於鋼筋續接器60。又,如圖7A所示,漿料管線70之第二端72係暴露於第一預鑄梁結構151之側表面1512與上表面1513之上,以允許一傳輸管連接或允許來自鋼筋續接器60之少部分多餘砂漿材料對外排出。 In one embodiment, the method for connecting adjacent beam structures is described below with reference to FIGS. 7A-7C. As shown in Figures 7A-7C, a plurality of slurry pipelines 70 are buried in the area adjacent to the end face 1511 of the first Kaifeng beam structure 151, and are configured to supply mortar materials to the areas buried inside the first Kaifeng beam structure 151. The steel bar connector 60 may be configured to allow a small amount of excess mortar material to flow out from the steel bar connector 60 embedded inside the first girder structure 151 . As shown in FIG. 7B , each slurry pipeline 70 has a first end 71 and a second end 72 . The first end 71 of the slurry pipeline 70 is connected to the steel bar connector 60 . Also, as shown in FIG. 7A , the second end 72 of the slurry pipeline 70 is exposed above the side surface 1512 and the upper surface 1513 of the first beam structure 151 to allow a transmission pipe to be connected or to allow the connection from the steel bar. A small part of the excess mortar material in the device 60 is discharged to the outside.

在一些實施例中,如圖7C所示,在鋼筋續接器60具有第一貫穿孔64及第二貫穿孔63之實施例中,鋼筋續接器60之第一貫穿孔64及第二貫穿孔63之每一者皆流體連接漿料管線70,以接收來自漿料管線70之砂漿材料或以自其內部排出砂漿材料至漿料管線70。因此,複數個漿料管線70的數量為鋼筋續接器60之第一貫穿孔64及第二貫穿孔63之數量之總和。漿料管線70可以具一定硬度以防止在第一預鑄梁結構151之混凝土定形期間受壓縮而變形但同時允許彎折之材料所製成。舉例而言,漿料管線70可由多層PVC塑膠軟管交疊設置而成。 In some embodiments, as shown in FIG. 7C , in the embodiment in which the steel bar connector 60 has a first through hole 64 and a second through hole 63 , the first through hole 64 and the second through hole 63 of the steel bar connector 60 are Each of the holes 63 is fluidly connected to the slurry line 70 to receive mortar material from the slurry line 70 or to discharge mortar material from its interior to the slurry line 70 . Therefore, the number of the plurality of slurry pipelines 70 is the sum of the numbers of the first through holes 64 and the second through holes 63 of the steel bar connector 60 . The slurry pipeline 70 may be made of a material that has a certain hardness to prevent compression and deformation during the setting of the concrete of the first beam structure 151 but allows bending at the same time. For example, the slurry pipeline 70 can be formed by overlapping multiple layers of PVC plastic hoses.

圖7D-7I展示建築系統1之第一預鑄連接結構15之第一預鑄梁結構151與第二預鑄連接結構17之第二預鑄梁結構172之續接方法之示意圖。如圖7D所示,第一預鑄梁結構151與第二預鑄梁結構172之續接方法包括將第一預鑄梁結構151之端面1511相鄰第二預鑄梁結構172之端面 1721設置,以定義一間隙G於其間。 7D-7I show schematic diagrams of the method of continuing the connection between the first beam structure 151 of the first beam connection structure 15 and the second beam structure 172 of the second beam connection structure 17 of the building system 1. As shown in FIG. 7D , the method of continuing the first Kaixuan beam structure 151 and the second Kaixuan beam structure 172 includes adjoining the end surface 1511 of the first Kaixuan beam structure 151 to the end surface of the second Kaixuan beam structure 172 1721 is set to define a gap G in between.

接著,如圖7D所示,將間隙G左右兩側及下方以一密封元件92密封。在此實施例中,密封元件92為一板模,其貼附於第一預鑄梁結構151及第二預鑄梁結構172之側表面及底表面以部分密封間隙G。在另一實施例中,密封元件92為封膜氣胎。封膜氣胎可在一未充氣之情況下放入間隙G的四周,接著再將氣體填充進入封膜氣胎,以部分密封間隙G。在又一實施例中,間隙G之上方並未為密封元件92所覆蓋。 Next, as shown in FIG. 7D , the left and right sides and the lower part of the gap G are sealed with a sealing element 92 . In this embodiment, the sealing element 92 is a mold plate, which is attached to the side surface and the bottom surface of the first rib structure 151 and the second rib structure 172 to partially seal the gap G. In another embodiment, the sealing element 92 is a membrane-sealed pneumatic tire. The sealed air tire can be placed around the gap G when it is not inflated, and then the gas is filled into the sealed air tire to partially seal the gap G. In yet another embodiment, the upper part of the gap G is not covered by the sealing element 92 .

接著,如圖7D、7E所示,經由灌漿管道70將一砂漿材料93(例如無收縮砂漿)填充至間隙G中。砂漿材料93可由一傳輸管95供應,其中傳輸管95可連接至第一預鑄梁結構151之側表面1512上排列於最下方之漿料管線70,以供應砂漿材料93至排列於第一預鑄梁結構151最下方且緊鄰側表面1512之鋼筋續接器60內部。並且,如圖7E所示,傳輸管95所連接之漿料管線70係流體連接至所述鋼筋續接器60之第一貫穿孔64。亦即,傳輸管95連接至鋼筋續接器60較為遠離間隙G之一側。為清楚說明,以下內容以「上游鋼筋續接器60’」稱此流體連接傳輸管95且排列於第一預鑄梁結構151最下方並緊鄰側表面1512(參圖7B)之鋼筋續接器。 Next, as shown in FIGS. 7D and 7E , a mortar material 93 (such as non-shrinkage mortar) is filled into the gap G through the grouting pipe 70 . The mortar material 93 can be supplied by a transmission pipe 95, wherein the transmission pipe 95 can be connected to the slurry pipeline 70 arranged at the bottom on the side surface 1512 of the first mortar beam structure 151, so as to supply the mortar material 93 to the slurry pipe 93 arranged at the first predetermined position. The cast beam structure 151 is at the bottom and is adjacent to the inside of the steel bar connector 60 on the side surface 1512 . Moreover, as shown in FIG. 7E , the slurry pipeline 70 connected to the transmission pipe 95 is fluidly connected to the first through hole 64 of the steel bar connector 60 . That is, the transmission pipe 95 is connected to the side of the steel bar connector 60 that is farther away from the gap G. For clarity of explanation, the following content refers to the fluid connection transmission pipe 95 as the "upstream steel bar connector 60'" and the steel bar connector arranged at the bottom of the first beam structure 151 and adjacent to the side surface 1512 (see Figure 7B) .

如圖7E所示,當傳輸管95供應砂漿材料93時,砂漿材料93自漿料管線70經由上游鋼筋續接器60’之第一貫穿孔64進入上游鋼筋續接器60’內部。隨著砂漿材料93持續供應,砂漿材料93在上游鋼筋續接器60’與梁鋼筋153之間的空隙向上流動、以及上游鋼筋續接器60’與梁鋼筋174之間的空隙流動,進而填滿上游鋼筋續接器60’之內部。當上游鋼筋續接器60’內部為砂漿材料93所填滿後,少量砂漿材料93自連接上游鋼筋續接器60’之第二貫穿孔63之漿料管線70排出,其餘砂漿材料93則經由連通至間 隙G之第二開口61自上游鋼筋續接器60’流出。 As shown in Figure 7E, when the transmission pipe 95 supplies the mortar material 93, the mortar material 93 enters the interior of the upstream steel bar connector 60' from the slurry pipeline 70 through the first through hole 64 of the upstream steel bar connector 60'. As the mortar material 93 continues to be supplied, the mortar material 93 flows upward in the gap between the upstream steel bar connector 60' and the beam steel bar 153, and flows in the gap between the upstream steel bar connector 60' and the beam steel bar 174, thereby filling Fill the interior of the upstream steel connector 60'. When the interior of the upstream steel bar connector 60' is filled with mortar material 93, a small amount of mortar material 93 is discharged from the slurry pipeline 70 connected to the second through hole 63 of the upstream steel bar connector 60', and the remaining mortar material 93 passes through Connected to the room The second opening 61 of the gap G flows out from the upstream steel bar connector 60'.

如圖7F所示,隨著砂漿材料93持續自傳輸管95供應至上游鋼筋續接器60’內並流向間隙G,由於間隙G為密封元件92所部分封閉,故砂漿材料93將經由其餘鋼筋續接器60之第二開口61進入至各個鋼筋續接器60內,並在該些鋼筋續接器60與梁鋼筋153之間的空隙向上流動、以及鋼筋續接器60與梁鋼筋174之間的空隙向上流動。並且,如圖7G所示,當個別鋼筋續接器60為砂漿材料93充分填充時,鋼筋續接器60內的砂漿材料93將自連結至對應之鋼筋續接器60之漿料管線70之第二端72排出第一預鑄梁結構151外部。在本實施例中,傳輸管95僅經由單一漿料管線70供應砂漿材料,因此施工人員可藉由觀察砂漿材料自各個漿料管線70流出之情況,進而確認砂漿材料在鋼筋續接器60之填充狀況。舉例而言,如圖7F及7G上方展示之箭頭所示,當砂漿材料自連結位於第一預鑄梁結構151上方之鋼筋續接器60之漿料管線70之第二端72流出時,即表示位於第一預鑄梁結構151最上方之鋼筋續接器60內部已充分填充砂漿材料。 As shown in Figure 7F, as the mortar material 93 continues to be supplied from the transmission pipe 95 into the upstream steel bar connector 60' and flows to the gap G, since the gap G is partially closed by the sealing element 92, the mortar material 93 will pass through the remaining steel bars. The second opening 61 of the connector 60 enters each steel bar connector 60 and flows upward in the gaps between the steel bar connectors 60 and the beam steel bars 153, and between the steel bar connectors 60 and the beam steel bars 174. The gaps between them flow upward. Moreover, as shown in FIG. 7G , when individual steel bar connectors 60 are fully filled with mortar material 93 , the mortar material 93 in the steel bar connector 60 will self-connect to the slurry pipeline 70 of the corresponding steel bar connector 60 . The second end 72 exits the first beam structure 151 . In this embodiment, the transmission pipe 95 only supplies mortar material through a single slurry pipeline 70 , so the construction personnel can confirm the mortar material between the steel connector 60 by observing the flow of the mortar material from each slurry pipeline 70 . Fill status. For example, as shown by the arrows shown above in Figures 7F and 7G, when the mortar material flows out from the second end 72 of the slurry pipeline 70 connected to the steel connector 60 located above the first beam structure 151, that is, It means that the inside of the steel connector 60 located at the top of the first beam structure 151 has been fully filled with mortar material.

在一實施例中,隨著砂漿材料依序自連接不同鋼筋續接器60之漿料管線70排出,但一或多個漿料管線70之第二端72未有砂漿材料排出時,此時可判定未有砂漿材料排出之漿料管線70所連接之鋼筋續接器60並未充分填充砂漿材料。此時,施工人員可進一步將傳輸管95插入該未有砂漿材料排出之漿料管線70,逐一朝可能未充分填充砂漿材料之鋼筋續接器60供應砂漿材料。在鋼筋續接器60具有第一貫穿孔64及第二貫穿孔63之實施例中,施工人員可以藉由觀察砂漿材料是否由連接相同鋼筋續接器60之另一漿料管線70排出,進而判斷該鋼筋續接器60是否已充分填充砂漿材料。 In one embodiment, as the mortar material is sequentially discharged from the slurry pipelines 70 connected to different steel bar connectors 60, but no mortar material is discharged from the second end 72 of one or more slurry pipelines 70, at this time It can be determined that the steel bar connector 60 connected to the slurry pipeline 70 where no mortar material is discharged is not fully filled with mortar material. At this time, the construction personnel can further insert the transmission pipe 95 into the slurry pipeline 70 where no mortar material is discharged, and supply mortar material one by one to the steel connectors 60 that may not be fully filled with mortar material. In the embodiment in which the steel bar connector 60 has the first through hole 64 and the second through hole 63, the construction personnel can observe whether the mortar material is discharged from another slurry pipeline 70 connected to the same steel bar connector 60, and thereby Determine whether the steel bar connector 60 has been fully filled with mortar material.

參照圖7H,在完成砂漿材料之填充程序後,第一預鑄梁結構151與第二預鑄梁結構172之續接方法進一步包括將多個塞子94插入漿料管線70暴露於第一預鑄梁結構151表面之第二端72,以防止砂漿材料在凝固前自鋼筋續接器60內流出。在一實施例中,塞子94是在所有鋼筋續接器60皆充分填充有砂將材料後才插入至漿料管線70之一端。在另一實施例中,塞子94是在確認個別鋼筋續接器60已充分填充有砂將材料時即插入至連結該鋼筋續接器60之漿料管線70之第二端72中。 Referring to FIG. 7H , after completing the filling process of the mortar material, the connection method of the first mortar beam structure 151 and the second mortar beam structure 172 further includes inserting a plurality of plugs 94 into the slurry pipeline 70 to expose the first mortar beam structure 151 to the second mortar beam structure 172 . The second end 72 on the surface of the beam structure 151 prevents the mortar material from flowing out of the steel connector 60 before solidification. In one embodiment, the plug 94 is inserted into one end of the slurry line 70 after all rebar connectors 60 are fully filled with sand material. In another embodiment, the plug 94 is inserted into the second end 72 of the slurry line 70 connecting the individual steel bar connector 60 when it is confirmed that the steel bar connector 60 has been fully filled with sand material.

如圖7H所示,第一預鑄梁結構151之端面1511之中心與第二預鑄梁結構172之端面1711之中心進一步包括複數個溝槽157(請同時參圖3)形成於其上。在砂漿材料93填充間隙G之過程中,部分砂漿材料93將流入溝槽157內。當砂漿材料93凝固後,位於溝槽157內之砂漿材料93形成朝第一預鑄梁結構151內部及第二預鑄梁結構172內部延伸之多個接合結構(剪力榫),其進步一增強第一預鑄梁結構151與第二預鑄梁結構172之續接強度。在一實施例中,溝槽157係以具有複數個凸塊之模具(圖未示)製成。為利於脫模,溝槽157(及模具之凸塊)具有梯形之橫向剖面。第一預鑄梁結構151之端面1511及第二預鑄梁結構172之端面1721同樣具有複數個溝槽形成於其上,為簡化內容在此不再重複說明。 As shown in FIG. 7H , the center of the end surface 1511 of the first yoke beam structure 151 and the center of the end surface 1711 of the second yoke beam structure 172 further include a plurality of grooves 157 (please also refer to FIG. 3 ) formed thereon. During the process of filling the gap G with the mortar material 93 , part of the mortar material 93 will flow into the groove 157 . After the mortar material 93 is solidified, the mortar material 93 located in the groove 157 forms a plurality of joint structures (shear tenons) extending toward the inside of the first Kaifeng beam structure 151 and the inside of the second Kaifeng beam structure 172, which progresses by one The connection strength between the first and second beam structures 151 and 172 is enhanced. In one embodiment, the groove 157 is made by a mold (not shown) with a plurality of bumps. To facilitate demolding, the groove 157 (and the bumps of the mold) has a trapezoidal transverse cross-section. The end surface 1511 of the first Kaifeng beam structure 151 and the end surface 1721 of the second Kaifeng beam structure 172 also have a plurality of grooves formed thereon. To simplify the content, the description will not be repeated here.

在砂漿材料充分填充鋼筋續接器後,第一預鑄梁結構151與第二預鑄梁結構172之續接方法進一步包括將塞子94移除,並貼附裝飾面板91(例如:石材)於第一預鑄梁結構151及第二預鑄梁結構172之外表面之上。裝飾面板91係設置於建築系統之最外圍,用於裝飾建築系統之外觀。在一實施例中,如圖7A所示,在第一預鑄梁結構151及第二預鑄梁結構172未填充砂漿材料前,第一預鑄梁結構151之上表面1513及第二預鑄梁 結構172之上表面1723之部分區域即預先貼附有裝飾面板91,但裝飾面板91未覆蓋設置有漿料管線70之第二端72之區域。並且,如圖7I所示,在第一預鑄梁結構151及第二預鑄梁結構172之間以及其鄰近區域填充砂漿材料後,第一預鑄梁結構151之上表面1513或第二預鑄梁結構172之上表面1723上設置有漿料管線70之第二端72之區域才進一步覆蓋有裝飾面板91。裝飾面板91可利用例如黏著劑之材料貼附於第一預鑄梁結構151或第二預鑄梁結構172之上。透過預先將大部分裝飾面板91貼附於預鑄結構之上,而僅在工地現場後貼部分區域之裝飾面板91之施作方法,可有效縮短工地現場之施工時間。 After the mortar material fully fills the steel connector, the splicing method of the first Kaifeng beam structure 151 and the second Kaifeng beam structure 172 further includes removing the plug 94 and attaching the decorative panel 91 (for example, stone) to the On the outer surfaces of the first and second beam structures 151 and 172 . The decorative panel 91 is arranged on the outermost periphery of the building system and is used to decorate the appearance of the building system. In one embodiment, as shown in FIG. 7A , before the first and second beam structures 151 and 172 are filled with mortar material, the upper surface 1513 of the first and second beam structures 151 and 172 are not filled with mortar material. Liang A decorative panel 91 is pre-attached to part of the upper surface 1723 of the structure 172 , but the decorative panel 91 does not cover the area where the second end 72 of the slurry pipeline 70 is located. Moreover, as shown in FIG. 7I , after the mortar material is filled between the first and second beam structures 151 and 172 and adjacent areas thereof, the upper surface 1513 of the first beam structure 151 or the second predetermined area is The area on the upper surface 1723 of the cast beam structure 172 where the second end 72 of the slurry pipeline 70 is disposed is further covered with a decorative panel 91 . The decorative panel 91 can be attached to the first beam structure 151 or the second beam structure 172 using materials such as adhesive. By attaching most of the decorative panels 91 to the structure in advance and only attaching some areas of the decorative panels 91 at the construction site, the construction time at the construction site can be effectively shortened.

應當理解的是,上述實施例中,用於連接梁結構之鋼筋續接器與梁鋼筋之設置位置係可彼此互換,並不侷限於上述實施例所述之樣態。舉例而言,第一預鑄梁結構151之端面1511可包括多個梁鋼筋向外沿水平方向延伸,而第二預鑄梁結構172之端面1721可包括多個預先設置之鋼筋續接器。第一預鑄梁結構151與第二預鑄梁結構172對接時,第二預鑄梁結構172之鋼筋續接器套設第一預鑄梁結構151之梁鋼筋,並藉由如圖7A-7I之方式填充砂漿材料,以固定第一預鑄梁結構151與第二預鑄梁結構172。 It should be understood that in the above-mentioned embodiments, the installation positions of the steel bar connectors and the beam steel bars used to connect the beam structures are interchangeable with each other and are not limited to the manner described in the above-mentioned embodiments. For example, the end surface 1511 of the first Kaifeng beam structure 151 may include a plurality of beam steel bars extending outward in a horizontal direction, and the end surface 1721 of the second Kaifeng beam structure 172 may include a plurality of pre-set steel bar connectors. When the first Kaohsiung beam structure 151 and the second Kaohsiung beam structure 172 are connected, the steel bar connector of the second Kaohsiung beam structure 172 is sleeved with the beam steel bars of the first Kaohsiung beam structure 151, and as shown in Figure 7A- The mortar material is filled in the method 7I to fix the first ridge beam structure 151 and the second ridge beam structure 172 .

在一些實施例中,預鑄連接頭之樑結構上包括預先埋設之複數個樓板連接件,以利樓板之製作。舉例而言,如圖7B所示,第一預鑄梁結構151內埋設有複數個樓板連接件96。每一樓板連接件96包括一本體960。本體960之一端設置有一闊頭961,且本體960之另一端設置有一連接頭962。闊頭961位於樓板連接件96遠離側表面1512之一側。闊頭961之寬度較本體960之寬度大,藉此增加本體960與第一預鑄梁結構151之連 接強度並避免樓板連接件96自第一預鑄梁結構151掉落。連接頭962形成於樓板連接件96設置闊頭961之相反端,且暴露於第一預鑄梁結構151之側表面1512。連接頭962可為一管狀結構,且包括內螺紋結構形成於其管狀結構之內表面。在一實施例中,如圖7B所示,多個連接頭962暴露於側表面1512之上並相鄰側表面1512與上表面1513之交界處設置,其中多對連接頭962在第一預鑄梁結構151之延伸方向上等距排列。其餘預鑄連接頭之樑結構中也可預先設置樓板連接件96。舉例而言,如圖7A所示,第二預鑄梁結構172同樣具有多對連接頭962暴露於側表面1722之上。 In some embodiments, the beam structure of the X-shaped connector includes a plurality of pre-embedded floor slab connectors to facilitate the production of the floor slab. For example, as shown in FIG. 7B , a plurality of floor connectors 96 are embedded in the first beam structure 151 . Each floor connector 96 includes a body 960 . One end of the body 960 is provided with a broad head 961, and the other end of the body 960 is provided with a connector 962. The broad head 961 is located on the side of the floor connector 96 away from the side surface 1512 . The width of the broad head 961 is larger than the width of the main body 960, thereby increasing the connection between the main body 960 and the first beam structure 151. The connection strength is improved and the floor connector 96 is prevented from falling from the first beam structure 151 . The connecting head 962 is formed at the opposite end of the broad head 961 of the floor connecting member 96 and is exposed to the side surface 1512 of the first beam structure 151 . The connector 962 may be a tubular structure and include an internal thread structure formed on the inner surface of the tubular structure. In one embodiment, as shown in FIG. 7B , a plurality of connectors 962 are exposed on the side surface 1512 and are disposed adjacent to the junction of the side surface 1512 and the upper surface 1513 , wherein a plurality of pairs of connectors 962 are located on the first surface 1512 . The beam structures 151 are arranged equidistantly in the extending direction. The floor connectors 96 can also be pre-set in the beam structures of the other connectors. For example, as shown in FIG. 7A , the second beam structure 172 also has a plurality of pairs of connectors 962 exposed on the side surface 1722 .

每一樓板連接件96進一步包括複數個連接鋼筋965。連接鋼筋965每一者之一端具有外螺紋,藉此與本體960之連接頭962之內螺紋嚙合使得連接鋼筋965與本體960連接。根據本發明之部分實施例,樓板製作時一樓地板之鋼筋(未圖式)與連接鋼筋965遠離本體960之一端進一步藉由適當之方式(例如:焊接)連接,並且,混凝土971係供應於圍繞連接鋼筋965與樓地板之鋼筋之模板(圖未示)內,以包覆於連接鋼筋965外部,進而形成每一樓層之樓地板97。 Each floor connector 96 further includes a plurality of connecting steel bars 965 . One end of each connecting steel bar 965 has an external thread, thereby engaging with the internal thread of the connecting head 962 of the body 960 so that the connecting steel bar 965 is connected to the body 960 . According to some embodiments of the present invention, when the floor slab is manufactured, the steel bars (not shown) of the first floor and the end of the connecting steel bar 965 away from the body 960 are further connected by an appropriate method (such as welding), and the concrete 971 is supplied to The formwork (not shown) surrounding the steel bars connecting the steel bars 965 and the floor is wrapped around the connecting steel bars 965 to form the floor 97 of each floor.

圖8A、8B展示本發明另一實施例中的建築系統之二個預鑄梁結構151a與172對接之示意圖。圖8A、8B之實施例與圖7A、7B之實施例之差異包括鋼筋續接器60以鋼筋續接器60a取代,其中每一鋼筋續接器60a省略設置相鄰第二開口61之貫穿孔63,僅包括相鄰第一開口62設置之貫穿孔64;並且,預鑄梁結構151a中省略設置連接貫穿孔63之漿料管線70。 8A and 8B show a schematic diagram of the docking of two beam structures 151a and 172 of the building system in another embodiment of the present invention. The difference between the embodiment of FIGS. 8A and 8B and the embodiment of FIGS. 7A and 7B includes that the steel bar connector 60 is replaced by a steel bar connector 60 a , wherein each steel bar connector 60 a omits the through hole adjacent to the second opening 61 . 63, only includes the through-hole 64 provided adjacent to the first opening 62; and, the slurry pipeline 70 connected to the through-hole 63 is omitted from the Xuan beam structure 151a.

在一實施例中,預鑄梁結構151a與172之續接方法,請參照圖8C-8G。首先,如圖8C所示,以一密封元件92密封形成於第一預鑄梁結 構151a之端面1511與第二預鑄梁結構172之端面1721之間的間隙G。接著,如圖8C、8D所示,經由灌漿管道70將一砂漿材料93(例如無收縮砂漿)填充至間隙G中。砂漿材料93可由一傳輸管95供應,其中傳輸管95可連接至第一預鑄梁結構151a之側表面1512上排列於最下方之漿料管線70,以供應砂漿材料93至排列於第一預鑄梁結構151a最下方且緊鄰側表面1512之鋼筋續接器60a內部。並且,如圖8D所示,傳輸管95所連接之漿料管線70係流體連接至所述鋼筋續接器60a之位於預鑄梁結構151a之測表面的一貫穿孔64。亦即,傳輸管95連接至鋼筋續接器60a較為遠離間隙G之一側。為清楚說明,以下內容以「上游鋼筋續接器60a’」稱此流體連接傳輸管95且排列於第一預鑄梁結構151a最下方並緊鄰側表面1512之鋼筋續接器。 In one embodiment, please refer to FIGS. 8C-8G for the method of connecting the beam structures 151a and 172. First, as shown in FIG. 8C , a sealing element 92 is used to seal the first bridge beam structure. The gap G between the end surface 1511 of the structure 151a and the end surface 1721 of the second beam structure 172. Next, as shown in FIGS. 8C and 8D , a mortar material 93 (for example, non-shrinkage mortar) is filled into the gap G through the grouting pipe 70 . The mortar material 93 can be supplied by a transmission pipe 95, wherein the transmission pipe 95 can be connected to the slurry pipeline 70 arranged at the bottom on the side surface 1512 of the first mortar beam structure 151a, so as to supply the mortar material 93 to the slurry pipe 93 arranged at the first predetermined position. The lowermost part of the cast beam structure 151a and the inside of the steel bar connector 60a is immediately adjacent to the side surface 1512. Moreover, as shown in FIG. 8D , the slurry pipeline 70 connected to the transmission pipe 95 is fluidly connected to a through hole 64 of the steel connector 60a located on the surface of the Xuan beam structure 151a. That is, the transmission pipe 95 is connected to the side of the steel bar connector 60a farther away from the gap G. For clarity of explanation, the following content will refer to the fluid connection transmission pipe 95 as the "upstream steel bar connector 60a'" and the steel bar connector arranged at the bottom of the first beam structure 151a and immediately adjacent to the side surface 1512.

如圖8D所示,當傳輸管95供應砂漿材料93時,砂漿材料93自漿料管線70經由上游鋼筋續接器60a’之貫穿孔64進入上游鋼筋續接器60a’內部。隨著砂漿材料93持續供應,砂漿材料93在上游鋼筋續接器60a’與梁鋼筋153之間的空隙上流動、以及上游鋼筋續接器60a’與梁鋼筋174之間的空隙流動,進而填滿上游鋼筋續接器60a’之內部。當上游鋼筋續接器60a’內部為砂漿材料93所填滿後,砂漿材料93經由連通至間隙G之第二開口61自上游鋼筋續接器60a’流出。 As shown in Figure 8D, when the transmission pipe 95 supplies the mortar material 93, the mortar material 93 enters the interior of the upstream steel bar connector 60a' from the slurry pipeline 70 through the through hole 64 of the upstream steel bar connector 60a'. As the mortar material 93 continues to be supplied, the mortar material 93 flows in the gap between the upstream steel bar connector 60a' and the beam steel bar 153, and in the gap between the upstream steel bar connector 60a' and the beam steel bar 174, thereby filling the gap. The interior of the upstream steel bar connector 60a' is completely filled. When the interior of the upstream steel bar connector 60a' is filled with the mortar material 93, the mortar material 93 flows out from the upstream steel bar connector 60a' through the second opening 61 connected to the gap G.

如圖8E所示,隨著砂漿材料93持續自傳輸管95供應至上游鋼筋續接器60a’內並流向間隙G,由於間隙G為密封元件92所部分封閉,故砂漿材料93將經由其餘鋼筋續接器60a之第二開口61進入至各個鋼筋續接器60a內,並在該些鋼筋續接器60a與梁鋼筋153之間的空隙向上流動、以及鋼筋續接器60a與梁鋼筋174之間的空隙向上流動。並且,如圖8E所示,當個別鋼筋續接器60a為砂漿材料93充分填充時,鋼筋續接器60a內的砂漿 材料93將自連結至對應之鋼筋續接器60a之漿料管線70之第二端72排出第一預鑄梁結構151a外部。在本實施例中,傳輸管95僅經由單一漿料管線70供應砂漿材料,因此施工人員可藉由觀察砂漿材料自各個漿料管線70流出之情況,進而確認砂漿材料在鋼筋續接器60a之填充狀況。舉例而言,如圖8E及8F上方展示之箭頭所示,當砂漿材料自連結位於第一預鑄梁結構151a上方之鋼筋續接器60a之漿料管線70之第二端72流出時,即表示位於第一預鑄梁結構151a最上方之鋼筋續接器60a內部已充分填充砂漿材料。 As shown in Figure 8E, as the mortar material 93 continues to be supplied from the transmission pipe 95 into the upstream steel bar connector 60a' and flows to the gap G, since the gap G is partially closed by the sealing element 92, the mortar material 93 will pass through the remaining steel bars. The second opening 61 of the connector 60a enters each steel bar connector 60a, and flows upward in the gaps between the steel bar connectors 60a and the beam steel bars 153, and between the steel bar connector 60a and the beam steel bars 174. The gaps between them flow upward. Moreover, as shown in Figure 8E, when the individual steel bar connector 60a is fully filled with the mortar material 93, the mortar in the steel bar connector 60a The material 93 will exit the first girder structure 151a from the second end 72 of the slurry line 70 connected to the corresponding rebar connector 60a. In this embodiment, the transmission pipe 95 only supplies mortar material through a single slurry pipeline 70 , so the construction personnel can observe the flow of the mortar material from each slurry pipeline 70 to confirm that the mortar material is between the steel bar connector 60 a Fill status. For example, as shown by the arrows shown at the top of Figures 8E and 8F, when the mortar material flows out from the second end 72 of the slurry pipeline 70 connected to the steel connector 60a above the first beam structure 151a, that is, It means that the inside of the steel connector 60a located at the top of the first beam structure 151a has been fully filled with mortar material.

在一實施例中,隨著砂漿材料依序自連接不同鋼筋續接器60a之漿料管線70排出,但一或多個漿料管線70之第二端72未有砂漿材料排出時,此時可判定未有砂漿材料排出之漿料管線70所連接之鋼筋續接器60a並未充分填充砂漿材料。此時,施工人員可進一步將傳輸管95插入該未有砂漿材料排出之漿料管線70,逐一朝可能未充分填充砂漿材料之鋼筋續接器60a供應砂漿材料。參照圖8G,在完成砂漿材料之填充程序後,第一預鑄梁結構151與第二預鑄梁結構172之續接方法進一步包括將多個塞子94插入漿料管線70暴露於第一預鑄梁結構151表面之第二端72,以防止砂漿材料在凝固前自鋼筋續接器60a內流出。 In one embodiment, as the mortar material is sequentially discharged from the slurry pipelines 70 connected to different steel bar connectors 60a, but no mortar material is discharged from the second end 72 of one or more slurry pipelines 70, at this time It can be determined that the steel connector 60a connected to the slurry pipeline 70 where no mortar material is discharged is not fully filled with mortar material. At this time, the construction personnel can further insert the transmission pipe 95 into the slurry pipeline 70 where no mortar material is discharged, and supply mortar material one by one to the steel connectors 60 a that may not be fully filled with mortar material. Referring to FIG. 8G , after completing the filling process of the mortar material, the connection method of the first mortar beam structure 151 and the second mortar beam structure 172 further includes inserting a plurality of plugs 94 into the slurry pipeline 70 to expose the first mortar beam structure 151 to the second mortar beam structure 172 . The second end 72 on the surface of the beam structure 151 prevents the mortar material from flowing out of the steel connector 60a before solidification.

繼續參照圖9,位於圖1下方之第一預鑄連接結構15及第二預鑄連接結構17同樣以如圖2-6之實施例所描述之方法分別定位於預鑄角柱11及預鑄邊柱13之上,並且以如圖7D-7I之實施例所描述之方法彼此進行對接。如圖10所示,由於位於建築系統單一側邊之第一預鑄連接結構15係先定位於預鑄角柱11之上,隨後二個第二預鑄連接結構17才定位於預鑄邊柱13之上,因此,二個第二預鑄連接結構17之間具有一緩衝空間,以允許圖10所示之右側之第二預鑄連接結構17被預先執行如圖4所展示之橫向 移動施工。接著,如圖10所示,建築系統1進一步包括一預鑄梁結構20及一場鑄接續結構30以連結相鄰之二個預鑄連接結構(例如:二個第二預鑄連接結構17)之梁結構。 Continuing to refer to FIG. 9 , the first connecting structure 15 and the second connecting structure 17 located at the bottom of FIG. 1 are also positioned on the corner pillar 11 and the edge of the connecting structure in the same manner as described in the embodiment of FIGS. 2-6 . on the pillar 13 and docked with each other in the manner described in the embodiment of Figures 7D-7I. As shown in Figure 10, since the first connecting structure 15 located on a single side of the building system is first positioned on the corner column 11, then the two second connecting structures 17 are positioned on the side columns 13. Therefore, there is a buffer space between the two second hook connection structures 17 to allow the second hook connection structure 17 on the right side shown in Figure 10 to be pre-executed horizontally as shown in Figure 4 Mobile construction. Next, as shown in FIG. 10 , the building system 1 further includes a Kaifeng beam structure 20 and a cast connection structure 30 to connect two adjacent Kaohsiung connection structures (for example, two second Kaohsiung connection structures 17 ). beam structure.

參照圖10,其係預鑄梁結構20及場鑄接續結構30放置於二個第二預鑄連接結構17之間之結構爆炸圖,並展示二個相鄰之預鑄連接結構17藉由預鑄梁結構20及場鑄接續結構30進行續接之方法。預鑄梁結構20大致具有長形之形狀,具有相對的第一端201以及第二端202,並包括複數個梁鋼筋21埋設於其中(參圖12)。梁鋼筋21係沿預鑄梁結構20之長度方向上延伸,且其一端自預鑄梁結構20之第二端202向外伸出。預鑄梁結構20之第一端201係預先埋設有複數個鋼筋續接器60於其中。鋼筋續接器60係經構形以將自第二預鑄連接結構17之第二預鑄梁結構171向外沿水平方向延伸之梁鋼筋173連結至預鑄梁結構20內之梁鋼筋21。為清楚描述之目的,以下說明中以梁鋼筋21稱做「第一梁鋼筋」,且梁鋼筋173稱做「第二梁鋼筋」。在一實施例中,預鑄梁結構20之本體的長度L2係小於所欲對接之二個相鄰之預鑄連接結構之端面之間隔距離L1。預鑄梁結構20之本體的長度L2係指預鑄梁結構20之第一端201至第一梁鋼筋21之自由端之距離。 Referring to Figure 10, it is an exploded view of the structure of the Kaifeng beam structure 20 and the casting connection structure 30 placed between two second Kaifeng connection structures 17, and shows that the two adjacent Kaifeng connection structures 17 are connected by pre-set Method for continuing the cast beam structure 20 and the field cast connection structure 30. The Qixuan beam structure 20 is generally in a long shape, has an opposite first end 201 and a second end 202, and includes a plurality of beam steel bars 21 embedded therein (see Figure 12). The beam steel bar 21 extends along the length direction of the Kaifeng beam structure 20, and one end thereof extends outward from the second end 202 of the Kaifeng beam structure 20. The first end 201 of the K-beam structure 20 is pre-embedded with a plurality of steel bar connectors 60 therein. The steel connector 60 is configured to connect the beam reinforcement 173 extending outwardly in the horizontal direction from the second Kawasaki beam structure 171 of the second Kawasaki connection structure 17 to the beam reinforcement 21 within the Kawasaki beam structure 20 . For the purpose of clear description, the beam reinforcement 21 is referred to as the "first beam reinforcement" and the beam reinforcement 173 is referred to as the "second beam reinforcement" in the following description. In one embodiment, the length L2 of the main body of the K-shaped beam structure 20 is less than the distance L1 between the end surfaces of two adjacent K-shaped beam connection structures to be connected. The length L2 of the main body of the Kaifeng beam structure 20 refers to the distance from the first end 201 of the Kaifeng beam structure 20 to the free end of the first beam steel bar 21.

預鑄梁結構20與二個相鄰之預鑄連接結構17之第一者(圖10右方之第二預鑄連接結構17)之對接方法說明如下:首先,將預鑄梁結構20吊放至二個第二預鑄連接結構17之二個第二預鑄梁結構171之間。接著,對預鑄梁結構20執行一橫向移動施工。在橫向移動過程中,預鑄梁結構20朝向預鑄連接結構17之第一者(圖10右方)移動,使預鑄梁結構20內之鋼筋續接器60套設於預鑄連接結構17之第一者(圖10右方)之第二梁鋼 筋173,並且使第二預鑄梁結構171之端面1711鄰接預鑄梁結構20之第一端201,如圖11所示。接著,執行相似於上述圖7D-7I中所描述之二個梁結構續接之方法,以完成預鑄連接結構17之第一者(圖10右方)與預鑄梁結構20之對接施工。 The docking method of the Yi-Xuan beam structure 20 and the first of the two adjacent Yi-Xuan connection structures 17 (the second Yi-Xuan connection structure 17 on the right side of Figure 10) is described as follows: First, hang the Yi-Xuan beam structure 20 to between the two second hook beam structures 171 of the two second hook connection structures 17 . Then, a lateral movement construction is performed on the Xuan beam structure 20 . During the lateral movement, the Yi-Xuan beam structure 20 moves toward the first one of the Yi-Xuan connection structures 17 (right side in Figure 10 ), so that the steel bar connector 60 in the Yi-Xuan beam structure 20 is sleeved on the Yi-Xuan connection structure 17 The second beam steel of the first one (right side of Figure 10) The ribs 173 are installed, and the end surface 1711 of the second Kaifeng beam structure 171 is adjacent to the first end 201 of the Kaifeng beam structure 20, as shown in Figure 11. Next, a method similar to the method of connecting the two beam structures described in FIGS. 7D to 7I is performed to complete the butt jointing construction of the first of the PIX connection structures 17 (right side of FIG. 10 ) and the PIX beam structure 20 .

如圖12所示,場鑄接續結構30係經構形以將預鑄梁結構20與預鑄連接結構17之第二者(圖10左方之第二預鑄連接結構17)進行對接。在一實施例中,場鑄接續結構30包括複數個固定鋼筋續接器31、複數個連接鋼筋32、複數個箍筋34、及複數個可移動鋼筋續接器35。固定鋼筋續接器31預先埋設於第二預鑄連接結構17之第二者(圖10左方)之端面。固定鋼筋續接器31之內壁面可包括螺紋結構,連接鋼筋32經由該螺紋結構連接至固定鋼筋續接器31。可移動鋼筋續接器35為管狀,並且經構形以可移動的方式套設於第一梁鋼筋21以及連接鋼筋32之上。複數個箍筋34套設於預鑄梁結構20之第一梁鋼筋21及可移動鋼筋續接器35外側,用以圍束第一梁鋼筋21。 As shown in FIG. 12 , the field cast connection structure 30 is configured to connect the K-shaped beam structure 20 with the second K-shaped connecting structure 17 (the second K-shaped connecting structure 17 on the left side of FIG. 10 ). In one embodiment, the cast-on-site splicing structure 30 includes a plurality of fixed steel bar connectors 31 , a plurality of connecting steel bars 32 , a plurality of stirrups 34 , and a plurality of movable steel bar connectors 35 . The fixed steel bar connector 31 is embedded in advance on the end surface of the second part (left side of Figure 10) of the second hook connection structure 17. The inner wall surface of the fixed steel bar connector 31 may include a threaded structure, and the connecting steel bar 32 is connected to the fixed steel bar connector 31 via the threaded structure. The movable steel bar connector 35 is tubular and configured to be movably sleeved on the first beam steel bar 21 and the connecting steel bar 32 . A plurality of stirrups 34 are set on the outside of the first beam steel bar 21 and the movable steel bar connector 35 of the Qixuan beam structure 20 to surround the first beam steel bar 21.

預鑄梁結構20經由場鑄接續結構30與預鑄連接結構17之第二者(圖10左方)之對接方法說明如下:首先,將場鑄接續結構30之可移動鋼筋續接器35與箍筋34套設於第一梁鋼筋21上。如圖10所示,場鑄接續結構30之可移動鋼筋續接器35與箍筋34係預先設置於預鑄梁結構20之第一梁鋼筋21上,並連同預鑄梁結構20一同吊放至二個相鄰之第二預鑄連接結構17之間。接著,如圖12所示,在預鑄梁結構20與二個相鄰之第二預鑄連接結構之17第一者(圖10右方)對接完成後,將連接鋼筋32連接至第二預鑄連接結構之17第二者(圖10左方)之固定鋼筋續接器31。接著,如圖13所示,移動可移動鋼筋續接器35,使其一端之開口套設於第一梁鋼筋21, 且其另一端之開口套設於連接鋼筋32。接著,供應砂漿材料至可移動鋼筋續接器35中,以使可移動鋼筋續接器35與第一梁鋼筋21及連接鋼筋32固接。接著,如圖14所示,移動箍筋34,使箍筋34均勻分布於第二預鑄連接結構之17第二者與預鑄梁結構20之間。最後,經由模板環繞場鑄接續結構30並澆置混凝土於其中,以形成混凝土結構覆蓋包覆包含箍筋34之場鑄接續結構30。混凝土結構可在當層樓之預鑄連接結構皆完成對接後,再包覆場鑄接續結構30。或者,混凝土結構可在移動箍筋34後即進行施作。關於形成混凝土結構之詳細方法將於後方關於圖19之實施例進一步說明。 The docking method of the Haixuan beam structure 20 and the second member of the Haixuan connection structure 17 (left side of Figure 10) via the field cast connection structure 30 is explained as follows: First, connect the movable steel bar connector 35 of the field cast connection structure 30 with The stirrups 34 are set on the first beam steel bars 21. As shown in Figure 10, the movable steel bar connector 35 and the stirrup 34 of the cast-in-place continuous structure 30 are pre-set on the first beam steel bar 21 of the Haixuan beam structure 20, and are hoisted together with the Haixuan beam structure 20. to between two adjacent second connecting structures 17. Next, as shown in Figure 12, after the docking between the 17-inch beam structure 20 and the first of the two adjacent second 17-inch connection structures (right side of Figure 10) is completed, the connecting steel bars 32 are connected to the second prefabricated beams. The second fixed steel bar connector 31 of the cast connection structure 17 (left side in Figure 10). Then, as shown in Figure 13, the movable steel bar connector 35 is moved so that the opening at one end thereof is sleeved on the first beam steel bar 21. And the opening at the other end is sleeved on the connecting steel bar 32 . Next, mortar material is supplied to the movable steel bar connector 35 so that the movable steel bar connector 35 is fixedly connected to the first beam steel bar 21 and the connecting steel bar 32 . Next, as shown in FIG. 14 , the stirrups 34 are moved so that the stirrups 34 are evenly distributed between the second one of the second link structures 17 and the link beam structure 20 . Finally, the cast-in-place continuous structure 30 is surrounded by the formwork and concrete is poured therein to form a concrete structure covering the cast-in-place continuous structure 30 including the stirrups 34 . The concrete structure can be covered with a cast-in-place continuous structure 30 after all the connecting structures of the floor are connected. Alternatively, the concrete structure may be constructed immediately after the stirrups 34 are moved. The detailed method of forming the concrete structure will be further described later with respect to the embodiment of FIG. 19 .

在建築系統1單邊之預鑄連接結構定位完成且對接後,接著透過類似的施工方式,將該樓層剩餘的預鑄連接結構進行定位並對接。如圖16所示,預鑄梁結構20及場鑄接續結構30形成於建築系統1上相對設置之側邊(下文稱左側邊及右側邊)上。建築系統1上垂直於所述左側邊及右側邊之另外二個側邊(下文稱前側邊與後側邊)並未有預鑄梁結構20及場鑄接續結構30設置。在一實施例中,在建造建築系統1之左側邊及右側邊的過程中,定位於二個預鑄角柱11之上的二個第一預鑄連接結構15係早於定位於二個預鑄邊柱預鑄邊柱13之上的二個第二預鑄連接結構17施工,在二個第二預鑄連接結構17之間施工需要現場施作的工程,例如陽台,之後進而使用預鑄梁結構20及場鑄接續結構30連接二個第二預鑄連接結構17。相對的,在建造建築系統1之前側邊與後側邊的過程中,省略設置預鑄梁結構20及場鑄接續結構30於其中。 After the positioning and docking of the unilateral connection structure of building system 1 is completed, the remaining connection structures of the floor will be positioned and connected through similar construction methods. As shown in FIG. 16 , the Xuan beam structure 20 and the field cast connection structure 30 are formed on opposite sides of the building system 1 (hereinafter referred to as the left side and the right side). The other two sides of the building system 1 that are perpendicular to the left side and the right side (hereinafter referred to as the front side and the rear side) are not provided with a beam structure 20 and a casting connection structure 30 . In one embodiment, during the construction of the left and right sides of the building system 1, the two first connecting structures 15 positioned on the two corner columns 11 are positioned earlier than the two first connecting structures 15. Construction of two second connecting structures 17 on the side columns and side columns 13, construction of projects that require on-site construction, such as balconies, between the two second connecting structures 17, and then using the connecting beams The structure 20 and the casting connection structure 30 connect the two second hook connection structures 17 . In contrast, in the process of constructing the front side and the rear side of the building system 1, the installation of the beam structure 20 and the field cast connection structure 30 therein is omitted.

然而應當理解的是,本揭露並不僅限於上述實施例,外圍建築系統可在單一側邊上設置有預鑄梁結構20及場鑄接續結構30,其餘側邊並未設置預鑄梁結構20及場鑄接續結構30。在其他實施例中,在如圖6 所示之左側邊之第一預鑄連接結構15與第二預鑄連接結構17完成對接後,沿一順時針方向依序對接其餘預鑄連接結構,最後才經由如圖10所示之預鑄梁結構20及場鑄接續結構30完成外圍建築系統10。 However, it should be understood that the present disclosure is not limited to the above embodiments. The peripheral building system may be provided with the Kaifeng beam structure 20 and the field cast connection structure 30 on a single side, and the Kaifeng beam structure 20 and the cast connection structure 30 are not provided on the other sides. Field casting continuation structure 30. In other embodiments, as shown in Figure 6 After the first connecting structure 15 and the second connecting structure 17 on the left side are docked, the other connecting structures are sequentially connected in a clockwise direction, and finally through the connecting structures as shown in Figure 10 The beam structure 20 and the field cast connection structure 30 complete the peripheral building system 10 .

在一實施例中,經由預鑄梁結構20及場鑄接續結構30進行對接之二個相鄰的預鑄連接結構(例如:二個第二預鑄連接結構17),其二個梁結構(例如:第二預鑄梁結構171、172)具有不同之長度。舉例而言,如圖11所示,二個第二預鑄梁結構中相鄰預鑄梁結構20或場鑄接續結構30之一者(例如:第二預鑄梁結構171)的長度,係小於另一者(例如:第二預鑄梁結構172)的長度。藉由縮小預鑄連接結構之長度,將有利於預鑄連接結構之運送,並降低預鑄連接結構之重量。 In one embodiment, two adjacent 鐐鄄 connection structures (for example: two second 鐐鄄 connection structures 17) are connected through the 鐐鄄 beam structure 20 and the field cast connection structure 30, and the two beam structures ( For example: the second beam structures 171, 172) have different lengths. For example, as shown in FIG. 11 , the length of one of the adjacent Kaixuan beam structures 20 or the cast-in-place continuous structure 30 (for example: the second Kaixuan beam structure 171 ) of the two second Kawasaki beam structures is Less than the length of the other one (for example: the second beam structure 172). By reducing the length of the K-shaped connection structure, the transportation of the K-shaped connection structure will be facilitated and the weight of the K-shaped connection structure will be reduced.

在完成建築系統1之外圍建築系統10之建造步驟後,建築系統1之施工方法進一步包括施工內部建築系統40之二個內部柱結構41。在一實施例中,二個內部柱結構41係設置於下一樓層之二個場鑄柱結構(圖未示)之上。在一實施例中,內部柱結構41是在預鑄角柱11、預鑄邊柱13及內部預鑄柱結構43之吊放作業之前、之後或期間於工地現場進行場鑄建造。 After completing the construction steps of the outer building system 10 of the building system 1, the construction method of the building system 1 further includes constructing the two inner column structures 41 of the inner building system 40. In one embodiment, the two internal column structures 41 are disposed above the two field cast column structures (not shown) on the next floor. In one embodiment, the internal column structure 41 is cast and constructed at the construction site before, after or during the hoisting operation of the corner columns 11 , side columns 13 and the internal column structure 43 .

如圖17所示,建築系統1之施工方法進一步包括定位二個內部預鑄連接結構44、45於二個內部預鑄柱結構43之上,其中內部預鑄連接結構44係早於內部預鑄連接結構45定位於內部預鑄柱結構43之上。如圖16所示,複數個垂直鋼筋9係在內部預鑄連接結構44吊放於內部預鑄柱結構43之上之前即預先固定於內部預鑄柱結構43之上,並在內部預鑄連接結構44經由吊裝的下降過程中,使複數個垂直鋼筋9分別穿過內部預鑄連接結構44內部之複數個穿孔。並且,在內部預鑄連接結構44吊放於內部預鑄柱 結構43之上之後,再執行如圖4所展示之橫向移動施工,將內部預鑄連接結構45定位於另一內部預鑄柱結構43並使其與內部預鑄連接結構44對接,如圖17所示。 As shown in Figure 17, the construction method of the building system 1 further includes positioning two internal hook-and-loop connection structures 44, 45 on two internal hook-and-loop column structures 43, wherein the internal hook-and-loop connection structure 44 is earlier than the internal hook-and-loop column structure 43. The connecting structure 45 is positioned above the inner pillar structure 43 . As shown in Figure 16 , a plurality of vertical steel bars 9 are pre-fixed on the internal support column structure 43 before the internal support connection structure 44 is suspended on the internal support structure 43, and are connected by the internal support structure 43. During the lowering process of the structure 44 through hoisting, a plurality of vertical steel bars 9 are passed through a plurality of perforations inside the internal hook connection structure 44 respectively. Moreover, the internal connecting structure 44 is hung on the internal supporting column. After the structure 43 is placed on top of the structure 43, the lateral movement construction shown in Figure 4 is performed to position the internal connecting structure 45 on another internal connecting column structure 43 and connect it with the internal connecting structure 44, as shown in Figure 17 shown.

如圖17所示,內部預鑄連接結構44包括一內部預鑄連接頭440及二個內部預鑄梁結構441、442。內部預鑄連接頭440設置於內部預鑄柱結構43之上方。二個內部預鑄梁結構441、442設置於內部預鑄連接頭440之二個垂直之相鄰側表面。複數個梁鋼筋自內部預鑄連接頭440未設置內部預鑄梁結構之側表面向外沿水平方向延伸。內部預鑄連接結構45包括一內部預鑄連接頭450及一內部預鑄梁結構。內部預鑄連接頭450設置於另一預鑄柱結構43之上方。內部預鑄梁結構451設置於內部預鑄連接頭450相鄰梁結構441之側表面。複數個梁鋼筋自內部預鑄連接頭450未設置內部預鑄梁結構之側表面向外沿水平方向延伸。 As shown in FIG. 17 , the internal hinge connection structure 44 includes an internal hinge connection head 440 and two internal hinge beam structures 441 and 442 . The internal connector 440 is disposed above the internal column structure 43 . Two internal yoke beam structures 441 and 442 are disposed on two vertical adjacent side surfaces of the inner yoke connector 440 . A plurality of beam steel bars extend outward in the horizontal direction from the side surface of the internal rib connector 440 where the internal rib structure is not provided. The internal hinge connection structure 45 includes an internal hinge connection head 450 and an internal hinge beam structure. The internal connector 450 is disposed above the other column structure 43 . The inner K-beam structure 451 is disposed on the side surface of the inner K-beam connector 450 adjacent to the beam structure 441 . A plurality of beam steel bars extend outward in the horizontal direction from the side surface of the inner rib connector 450 that is not provided with the internal rib structure.

如圖18所示,在完成建築系統1之內部預鑄連接頭440之定位後,則施工內部建築系統40之內部梁結構42。內部梁結構42係連結於二個相鄰內部柱結構41之二者之間。或者,內部梁結構42係連結於內部柱結構41與預鑄連接頭440、450之間。或者,內部梁結構42係連結於內部預鑄連接結構44、45與外圍建築系統10之第二預鑄連接結構17之間。 As shown in FIG. 18 , after the positioning of the internal latch connector 440 of the building system 1 is completed, the internal beam structure 42 of the internal building system 40 is constructed. The internal beam structure 42 is connected between two adjacent internal column structures 41 . Alternatively, the internal beam structure 42 is connected between the internal column structure 41 and the X-shaped connectors 440, 450. Alternatively, the inner beam structure 42 is connected between the inner rib connection structures 44, 45 and the second rib connection structure 17 of the peripheral building system 10.

建築系統1之外圍建築系統10先完成後才施工內部建築系統40,且內部建築系統40中之內部梁結構42係以場鑄方式施工,這樣的施工方式無須在建築系統1之外圍搭設施工架且可降低建築系統之建造成本,並增加建造程序上的靈活性。 The outer building system 10 of the building system 1 is completed first and then the inner building system 40 is constructed, and the internal beam structure 42 in the inner building system 40 is constructed by cast-in-place construction. This construction method does not require erecting a work frame outside the building system 1 It can also reduce the construction cost of building systems and increase the flexibility of construction procedures.

參照圖19,其展示建築系統1之一樓層之平面圖。在一實施例中,場鑄接續結構30係相鄰建築系統1之一對外敞開並向外延伸之平台 46設置。在施工場鑄接續結構30時,施工人員可站立於平台46移動並定位可移動鋼筋續接器35(圖14)及透過模板的設置以及澆置混凝土於其中以形成混凝土結構36,使其包覆場鑄接續結構30。由於施工人員沒有暴露於建築系統1外部之風險,故無須額外搭設施工架。又,如圖19所示,建築系統1包括二個天井48、49,其中天井48之面積較天井49之面積大。由於相鄰天井48之內部建築系統40包括部分預鑄樑結構(例如:如圖17所示之內部預鑄梁結構441、442、451),且位於天井48兩側需以場鑄方式施工之內部梁結構42係相鄰建築系統1之一對外敞開並向外延伸之平台47設置,故天井48內也可不必搭設施工架。另一方面,由於位於天井49兩側需以場鑄方式施工之內部梁結構42係相鄰建築系統1之一對外敞開之平台47設置,故天井49內也可不必搭設施工架。 Referring to Figure 19, a plan view of one floor of the building system 1 is shown. In one embodiment, the casting connection structure 30 is an open and outwardly extending platform of one of the adjacent building systems 1 46 settings. When casting the splice structure 30 at the construction site, the construction workers can stand on the platform 46 to move and position the movable steel splice 35 (Fig. 14) and form the concrete structure 36 through the setting of the formwork and pouring concrete into it to make it envelope. Covered field cast continuous structure 30. Since there is no risk of construction workers being exposed to the outside of the building system 1, there is no need to erect additional construction frames. Furthermore, as shown in FIG. 19 , the building system 1 includes two patios 48 and 49 , in which the area of the patio 48 is larger than the area of the patio 49 . Since the internal building system 40 of the adjacent patio 48 includes part of the beam structure (for example, the internal beam structures 441, 442, 451 as shown in Figure 17), and is located on both sides of the patio 48, it needs to be constructed by field casting. The internal beam structure 42 is provided on a platform 47 adjacent to one of the building systems 1 that opens to the outside and extends outward. Therefore, there is no need to build a construction frame in the patio 48. On the other hand, since the internal beam structures 42 located on both sides of the patio 49 that need to be constructed by cast-in-place construction are installed on an open platform 47 of the adjacent building system 1, there is no need to build a construction frame in the patio 49.

藉由上述配置,建築系統1在施工過程中可將施工架之使用量降至最低,進而減少建築系統1之建造成本並避免產生不必要之建築廢棄物。 Through the above configuration, the building system 1 can minimize the use of construction racks during the construction process, thereby reducing the construction cost of the building system 1 and avoiding the generation of unnecessary construction waste.

參照圖20,其展示建築系統1’之一樓層之平面圖。建築系統1與建築系統1’相同或相似之元件以相同符號表示,且其結構特徵將不再描述。建築系統1與建築系統1’之差異在於兩者的外圍建築系統的結構略有不同,其中如圖19及圖20所示,建築系統1’以預鑄連接結構15’、17’、19取代結構不同之建築系統1之預鑄連接結構15、17,且建築系統1’進一步包括多個預鑄樑結構25。預鑄連接結構15’係透過預鑄樑結構25與預鑄連接結構17’或預鑄連接結構19而連接。二個預鑄連接結構17’係經由預鑄梁結構20及場鑄接續結構30而連接。二個預鑄連接結構19係彼此直接耦接。在一實施例中,預鑄連接結構15’、17’、19及預鑄樑結構25係以相似於圖 2-6及圖7A-7I所揭露之方式彼此進行連接,預鑄連接結構17’係以相似於圖10-14所揭露之方式進行連接,為簡化說明在此即不再重複。 Referring to Figure 20, a plan view of one floor of the building system 1' is shown. Elements of the building system 1 that are identical or similar to those of the building system 1′ are represented by the same symbols, and their structural features will not be described again. The difference between building system 1 and building system 1' is that the structures of the peripheral building systems of the two are slightly different. As shown in Figure 19 and Figure 20, building system 1' is replaced by Qixuan connection structures 15', 17', and 19. The construction system 1 has different construction systems 1 with connecting structures 15 and 17, and the building system 1' further includes a plurality of construction beam structures 25. The Qixuan connection structure 15' is connected to the Qixuan connection structure 17' or the Qixuan connection structure 19 through the Qixuan beam structure 25. The two connecting structures 17′ are connected through the connecting beam structure 20 and the casting connection structure 30. The two connecting structures 19 are directly coupled to each other. In one embodiment, the hook connection structures 15', 17', 19 and the hook beam structure 25 are similar to those shown in the figure. 2-6 and FIGS. 7A-7I are connected to each other in a manner disclosed in FIGS. 2-6 and 7A-7I. The QQ connection structure 17' is connected in a manner similar to that disclosed in FIGS. 10-14, which will not be repeated here to simplify the description.

在一實施例中,建築系統1’之預鑄連接結構15’、17’、19上水平延伸之樑結構的長度係較建築系統1之預鑄連接結構15、17上水平延伸之樑結構的長度短,藉此增加預鑄連接結構15’、17’、19運送之便利性。在一實施例中,建築系統1’之預鑄連接結構15’之樑結構151’、152’分別具有長度L3、L4。長度L3、L4係至少大於1公尺,以使樑結構151’、152’與相鄰結構之對接位置係位於預鑄連接結構15’之塑鉸(plastic hinge)區之外,以強化預鑄連接結構15’之結構強度。 In one embodiment, the length of the horizontally extending beam structures on the connecting structures 15', 17', and 19 of the building system 1' is longer than the length of the horizontally extending beam structures on the connecting structures 15 and 17 of the building system 1. The length is short, thereby increasing the convenience of transportation of the connecting structures 15', 17', and 19. In one embodiment, the beam structures 151' and 152' of the lattice connection structure 15' of the building system 1' have lengths L3 and L4 respectively. The lengths L3 and L4 are at least greater than 1 meter, so that the docking positions of the beam structures 151', 152' and adjacent structures are located outside the plastic hinge area of the 15' connection structure to strengthen the 15' Structural strength of connecting structure 15'.

本揭露實施例提供一種建築系統其施工方法,其至少包括以下技術優點:(1)藉由預鑄工法施工外圍建築系統的大部分結構,僅在部分區塊使用場鑄接續結構,有助於建築系統之製造流程標準化,減少施工程序上可變因數,進而提升建築品質;(2)藉由預鑄結構的使用,增加建造速度並提升工地環境整潔;及(3)藉由將場鑄之施作地點設置於陽台等場域,避免施工架之使用,有助減少生產成本並降低環境衝擊。 Embodiments of the present disclosure provide a construction method of a building system, which at least includes the following technical advantages: (1) Most of the structures of the peripheral building system are constructed using the construction method, and only some areas are used to cast continuous structures, which is conducive to The standardization of the manufacturing process of the building system reduces the variable factors in the construction process, thereby improving the quality of the construction; (2) through the use of the ridge structure, increases the construction speed and improves the cleanliness of the construction site environment; and (3) by casting the site into The construction site is set up in areas such as balconies to avoid the use of construction racks, which helps reduce production costs and environmental impact.

以上所述之實施例僅係為說明本創作之技術思想及特點,其目的在使熟習此項技藝之人士能夠瞭解本創作之內容並據以實施,當不能以之限定本創作之專利範圍,依本創作所揭示之精神所作之均等變化或修飾,仍應涵蓋在本創作之專利範圍內。 The above-mentioned embodiments are only for illustrating the technical ideas and characteristics of this invention. Their purpose is to enable those familiar with this art to understand the content of this invention and implement it accordingly. They should not be used to limit the patent scope of this invention. Equivalent changes or modifications made in accordance with the spirit disclosed in this creation shall still be covered by the patent scope of this creation.

151:第一預鑄梁結構 151:The first Xuan beam structure

153:梁鋼筋 153:Beam reinforcement

157:溝槽 157:Trench

172:第二預鑄梁結構 172:Second Haixuan beam structure

174:梁鋼筋 174:Beam reinforcement

60:鋼筋續接器 60:Reinforcement bar connector

61:第二開口 61:Second opening

62:第一開口 62:First opening

63:第二貫穿孔/貫穿孔 63: Second through hole/through hole

64:第一貫穿孔/貫穿孔 64: First through hole/through hole

70:漿料管線 70: Slurry pipeline

92:密封元件 92:Sealing element

1511:端面 1511: End face

1513:上表面 1513: Upper surface

1721:端面 1721: End face

G:間隙 G: Gap

Claims (10)

一種建築結構,包括:一第一預鑄梁結構及一第二預鑄梁結構,各自具有一端面,該二個端面相鄰設置並定義一間隙於其間,其中該第二預鑄梁結構之該端面包括複數個梁鋼筋向外延伸;複數個鋼筋續接器,埋設於該第一預鑄梁結構之該端面內,每一該複數個鋼筋續接器包括:一第一開口及一第二開口,分別位於其兩端,該等鋼筋續接器之該第一開口與該第一預鑄梁結構內之梁鋼筋之末端固接,該等鋼筋續接器之該第二開口暴露於該第一預鑄梁結構之該端面,並經構形以允許該第二預鑄梁結構內之該複數個梁鋼筋插入其中;以及一第一貫穿孔,相鄰該第一開口,貫穿該鋼筋續接器之外壁,並與該第一開口連通;以及複數個漿料管線,埋設於該第一預鑄梁結構內,該複數個漿料管線流體連通該複數個鋼筋續接器之該複數個第一貫穿孔以及該第一預鑄梁結構之外部。 A building structure, including: a first Kaixuan beam structure and a second Kaixuan beam structure, each having an end face, the two end surfaces are adjacently arranged and define a gap therebetween, wherein the second Kaixuan beam structure The end face includes a plurality of beam steel bars extending outward; a plurality of steel bar connectors are embedded in the end face of the first Jiaxuan beam structure. Each of the plurality of steel bar connectors includes: a first opening and a first Two openings are respectively located at both ends. The first opening of the steel bar connectors is fixedly connected to the end of the beam steel bar in the first beam structure, and the second opening of the steel bar connectors is exposed to The end surface of the first Kaifeng beam structure is configured to allow the plurality of beam steel bars in the second Kaifeng beam structure to be inserted therein; and a first through hole adjacent to the first opening passes through the The outer wall of the steel bar connector is connected to the first opening; and a plurality of slurry pipelines are buried in the first beam structure, and the plurality of slurry pipelines are fluidly connected to the plurality of steel bar connectors. A plurality of first through holes and the outside of the first beam structure. 如請求項1所述之建築結構,其中每一該複數個鋼筋續接器進一步包括一第二貫穿孔,相鄰該第二開口,貫穿該鋼筋續接器之外壁,並與該第二開口連通,其中該複數個漿料管線流體連通該複數個鋼筋續接器之該複數個第二貫穿孔以及該第一預鑄梁結構之外部。 The building structure as claimed in claim 1, wherein each of the plurality of steel bar connectors further includes a second through hole adjacent to the second opening, penetrating through the outer wall of the steel bar connector, and connected with the second opening. Communicated, wherein the plurality of slurry pipelines are fluidly connected to the plurality of second through holes of the plurality of reinforcing bar connectors and the outside of the first beam structure. 如請求項1所述之建築結構,其中該第一預鑄梁結構以及該第二預鑄梁結構之該等端面包括複數個溝槽於其中,以供砂漿材料填充於其中,而形成複數個接合結構。 The building structure as described in claim 1, wherein the end surfaces of the first Kaifeng beam structure and the second Kaifeng beam structure include a plurality of grooves therein for mortar materials to be filled therein to form a plurality of grooves. joint structure. 如請求項1所述之建築結構,進一步包括一密封元件,該密封元件經構形以密封該間隙之左右兩側及下方。 The building structure of claim 1, further comprising a sealing element configured to seal the left and right sides and below of the gap. 如請求項1所述之建築結構,進一步包括:一第一預鑄柱;一第一預鑄連接頭,設置於該第一預鑄柱上方,並經配置以與該第一預鑄柱之頂表面相隔一間隙,該第一預鑄連接頭包含複數個穿孔垂直穿設其中並與該間隙連通;以及複數個第一垂直鋼筋,設置於該第一預鑄連接頭之該等穿孔中,並連接至該第一預鑄柱;其中該第一預鑄梁結構自該第一預鑄連接頭沿一水平方向延伸,且該第一預鑄連接頭包含另一第一預鑄梁結構沿與該第一預鑄梁結構大致垂直的一方向延伸。 The building structure as described in claim 1, further comprising: a first Xiuxuan column; a first Xiuxuan connector disposed above the first Xiuxuan column and configured to connect with the first Xiuxuan column The top surface is separated by a gap, and the first hook-and-loop connector includes a plurality of perforations vertically passing through it and communicating with the gap; and a plurality of first vertical steel bars are disposed in the perforations of the first hook-and-loop connector, and connected to the first Xiaoxuan column; wherein the first Xiaoxuan beam structure extends along a horizontal direction from the first Xiaoxuan connection joint, and the first Xiaoxuan connection joint includes another first Xiaoxuan beam structure along It extends in a direction substantially perpendicular to the first beam structure. 如請求項5所述之建築結構,進一步包括:一第二預鑄柱;一第二預鑄連接頭,設置於該第二預鑄柱上方,並經配置以與該第二預鑄柱之頂表面相隔一間隙,該第二預鑄連接頭包含複數個穿 孔垂直穿設其中並與該間隙連通;以及複數個第二垂直鋼筋,設置於該第二預鑄連接頭之該等穿孔中,並連接至該第二預鑄柱;其中該第二預鑄梁結構自該第二預鑄連接頭朝向該第一預鑄梁結構延伸,且該第二預鑄連接頭包含另一第二預鑄梁結構沿與該第二預鑄梁結構相反且大致平行的一方向延伸。 The building structure as described in claim 5, further comprising: a second Xiuxuan column; a second Xiuxuan connector disposed above the second Xiuxuan column and configured to connect with the second Xiuxuan column The top surface is separated by a gap, and the second connector includes a plurality of through-holes. Holes are vertically penetrated therein and connected with the gap; and a plurality of second vertical steel bars are provided in the through holes of the second 鐐鄄 connector and connected to the second 鐐鄄 pillar; wherein the second 鐐鄄 pillar The beam structure extends from the second Kawasaki connector toward the first Kawasaki beam structure, and the second Kawasaki connector includes another second Kawasaki beam structure along an edge opposite to and substantially parallel to the second Kawasaki beam structure extends in one direction. 如請求項1所述之建築結構,進一步包括:複數個樓板連接件,其中每一該複數個樓板連接件包含:一本體,其一端設置有一闊頭,並埋設於該第一預鑄梁結構以及該第二預鑄梁結構內,其另一端設置有一連接頭,該連接頭包含一內螺紋於其中;以及一連接鋼筋,其一端具有外螺紋,該連接鋼筋經由該外螺紋與該本體之該連接頭之該內螺紋嚙合使得該連接鋼筋與該本體連接,該連接鋼筋暴露於該第一預鑄梁結構以及該第二預鑄梁結構之一側表面,以供與一樓地板之鋼筋連接。 The building structure as described in claim 1, further comprising: a plurality of floor connectors, wherein each of the plurality of floor connectors includes: a body with a broad head provided at one end and buried in the first gaixuan beam structure And in the second Kaixuan beam structure, the other end is provided with a connector, the connector includes an internal thread; and a connecting steel bar has an external thread at one end, and the connecting steel bar is connected to the body through the external thread. The internal thread engagement of the connector allows the connecting steel bar to be connected to the body. The connecting steel bar is exposed on a side surface of the first Haixuan beam structure and the second Haixuan beam structure for connecting with the steel bars of the first floor floor. connection. 一種建築方法,包括:提供一第一預鑄梁結構,包括複數個鋼筋續接器設置於其一端面,每一該複數個鋼筋續接器包括一第一開口及一第二開口,分別位於其兩端,該等鋼筋續接器之該第一開口與該第一預鑄梁結構內之梁鋼筋之末端固接,該等鋼筋續接器之該第二開口暴露於該第一預鑄梁結構之該端面,一第一貫穿孔相鄰該第一開口並貫穿該鋼筋 續接器之外壁以與該第一開口連通;以及複數個漿料管線,埋設於該第一預鑄梁結構內,該複數個漿料管線流體連通該複數個鋼筋續接器之複數個該第一貫穿孔以及該第一預鑄梁結構之外部;提供一第二預鑄梁結構,包括複數個梁鋼筋自其一端面向外延伸;吊裝該第二預鑄梁結構,以使該第二預鑄梁結構之複數個梁鋼筋伸入該第一預鑄梁結構內之該複數個鋼筋續接器之該複數個第二開口中;定位該第一預鑄梁結構以及該第二預鑄梁結構,以在該第一預鑄梁結構之該端面以及該第二預鑄梁結構之該端面之間提供一間隙;經由該複數個漿料管線其中之一者供應一砂漿材料至該複數個鋼筋續接器之一者,並使該砂漿材料經由該複數個鋼筋續接器之該者之該第二開口流入該間隙中,進而填充該砂漿材料至該複數個鋼筋續接器之其他者內。 A construction method, including: providing a first girder structure, including a plurality of steel bar connectors arranged on one end surface, each of the plurality of steel bar connectors including a first opening and a second opening, respectively located at At both ends, the first openings of the steel bar connectors are fixedly connected to the ends of the beam steel bars in the first beam structure, and the second openings of the steel bar connectors are exposed to the first beam structure. On the end surface of the beam structure, a first through hole is adjacent to the first opening and penetrates the steel bar. The outer wall of the connector is connected to the first opening; and a plurality of slurry pipelines are buried in the first beam structure, and the plurality of slurry pipelines are fluidly connected to the plurality of steel connectors. The first through hole and the outside of the first Kaifeng beam structure; provide a second Kaifeng beam structure, including a plurality of beam steel bars extending outward from one end thereof; hoist the second Kaifeng beam structure so that the second Kaifeng beam structure is The plurality of beam steel bars of the Kaixuan beam structure extend into the plurality of second openings of the plurality of steel bar connectors in the first Kaixuan beam structure; positioning the first Kaixuan beam structure and the second Kaixuan beam structure a beam structure to provide a gap between the end face of the first beam structure and the end face of the second beam structure; supplying a mortar material to the plurality of slurry pipelines via one of the plurality of slurry pipelines One of the steel bar connectors, and the mortar material flows into the gap through the second opening of the plurality of steel bar connectors, and then fills the mortar material to other members of the plurality of steel bar connectors. Within. 如請求項8所述之方法,其中該第一預鑄梁結構以及該第二預鑄梁結構之該等端面包括複數個溝槽於其中,該方法更包括:填充該砂漿材料至該複數個溝槽中,以形成複數個接合結構。 The method of claim 8, wherein the end surfaces of the first Kaifeng beam structure and the second Kaifeng beam structure include a plurality of grooves therein, and the method further includes: filling the mortar material into the plurality of grooves. in the grooves to form a plurality of joint structures. 如請求項8所述之方法,進一步包括:提供複數個樓板連接件,其中每一該複數個樓板連接件包含:在其一端設置有一闊頭之一本體,以及連接至該本體之另一端之一連接鋼筋; 將該複數個樓板連接件的具有該闊頭之該端預先埋設於該第一預鑄梁結構以及該第二預鑄梁結構內;將該連接鋼筋暴露於該第一預鑄梁結構以及該第二預鑄梁結構之一側表面;以及將該連接鋼筋與樓地板的鋼筋連接。 The method of claim 8, further comprising: providing a plurality of floor connectors, wherein each of the plurality of floor connectors includes: a body provided with a broad head at one end, and a body connected to the other end of the body. One connecting steel bar; Preliminarily bury the ends of the plurality of floor connectors with the wide heads in the first Kaifeng beam structure and the second Kaifeng beam structure; expose the connecting steel bars to the first Kaifeng beam structure and the One side surface of the second beam structure; and connecting the connecting steel bar to the steel bar of the floor.
TW111141592A 2022-11-01 2022-11-01 Architecture structure and method for constructing the same TWI816594B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW111141592A TWI816594B (en) 2022-11-01 2022-11-01 Architecture structure and method for constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW111141592A TWI816594B (en) 2022-11-01 2022-11-01 Architecture structure and method for constructing the same

Publications (2)

Publication Number Publication Date
TWI816594B true TWI816594B (en) 2023-09-21
TW202419719A TW202419719A (en) 2024-05-16

Family

ID=88966360

Family Applications (1)

Application Number Title Priority Date Filing Date
TW111141592A TWI816594B (en) 2022-11-01 2022-11-01 Architecture structure and method for constructing the same

Country Status (1)

Country Link
TW (1) TWI816594B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM248822U (en) * 2004-01-14 2004-11-01 Runhorn Pretech Eng Co Ltd Semi-precast beam-column joint
US20130263551A1 (en) * 2007-04-02 2013-10-10 Barnet L. Liberman Modular Building Structures
TWI736482B (en) * 2020-12-03 2021-08-11 潤弘精密工程事業股份有限公司 Construction method of architectural structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM248822U (en) * 2004-01-14 2004-11-01 Runhorn Pretech Eng Co Ltd Semi-precast beam-column joint
US20130263551A1 (en) * 2007-04-02 2013-10-10 Barnet L. Liberman Modular Building Structures
TWI736482B (en) * 2020-12-03 2021-08-11 潤弘精密工程事業股份有限公司 Construction method of architectural structure

Similar Documents

Publication Publication Date Title
WO2019206193A1 (en) Prefabricated wall panel, connection structure thereof and construction method therefor
KR101867300B1 (en) Joining structure of prefabricated shear wall
TWI592546B (en) Architecture structure and its construction method
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN110268124B (en) Precast reinforced heavy concrete retaining wall
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
WO2022160388A1 (en) Fabricated concrete beam-column joint and construction method therefor
KR102079703B1 (en) Modular staircase and method of constructing the same
TW202223211A (en) Construction method of architectural structure
KR20140110490A (en) Half precast concrete column manufacturing method using prefabricated PC panels and constructing method using the same
KR101675441B1 (en) Integrated wall structure, form and manufacturing method for integrated wall structure
TWI816594B (en) Architecture structure and method for constructing the same
KR101395129B1 (en) Precast panel and slab construction method using the same
CN211143393U (en) Frame for preparing assembly type concrete core-filled wall and assembly type concrete core-filled wall
TWI816583B (en) Architecture system and method for constructing the same
KR101636471B1 (en) Reinforced concrete column structure
KR101315365B1 (en) Hybrid beam structure
AU2021107156A4 (en) Construction of a lift shaft or stair core
TWI808911B (en) Architecture system and method for constructing the same
TWI816580B (en) Beam-column structure and method for fabricating the same and architecture system having the same
TWI818874B (en) Beam-column structure and method for assembling the same
WO2017187452A1 (en) System for connecting a precast column to a precast beam and method therefor
TWI764765B (en) Architecture system and method of constructing the same
TW202403156A (en) Beam-column structure and method for assembling the same
KR100757710B1 (en) Dowel bar construction method for downward construction of underground structures