TWI632274B - Suspension reinforcement working stand and construction method utilized thereof - Google Patents

Suspension reinforcement working stand and construction method utilized thereof Download PDF

Info

Publication number
TWI632274B
TWI632274B TW105138959A TW105138959A TWI632274B TW I632274 B TWI632274 B TW I632274B TW 105138959 A TW105138959 A TW 105138959A TW 105138959 A TW105138959 A TW 105138959A TW I632274 B TWI632274 B TW I632274B
Authority
TW
Taiwan
Prior art keywords
steel
screw
sub
suspended
floor
Prior art date
Application number
TW105138959A
Other languages
Chinese (zh)
Other versions
TW201819738A (en
Inventor
林志聖
Original Assignee
互助營造股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 互助營造股份有限公司 filed Critical 互助營造股份有限公司
Priority to TW105138959A priority Critical patent/TWI632274B/en
Publication of TW201819738A publication Critical patent/TW201819738A/en
Application granted granted Critical
Publication of TWI632274B publication Critical patent/TWI632274B/en

Links

Abstract

本發明的懸吊式鋼筋工作架包含螺桿、吊件以及型鋼。螺桿係設置朝遠離樓板表面延伸。螺桿具有第一端及位於第一端相反側之第二端。吊件係設置於樓板並連接第一端。型鋼設置垂直於螺桿的延伸方向並固定於第二端。 The suspended steel work frame of the present invention comprises a screw, a hanger and a section steel. The screw system is arranged to extend away from the surface of the floor. The screw has a first end and a second end on the opposite side of the first end. The hanging piece is arranged on the floor and connected to the first end. The profile steel is disposed perpendicular to the direction in which the screw extends and is fixed to the second end.

Description

懸吊式鋼筋工作架及使用其之施工方法 Suspended steel work frame and construction method using same

本發明係關於一種鋼筋工作架;具體而言,本發明係關於一種懸吊式鋼筋工作架及使用懸吊式鋼筋工作架的施工方法。 The present invention relates to a steel bar work frame; in particular, the present invention relates to a suspended steel bar work frame and a construction method using the suspended steel bar work frame.

建築施工中,鋼筋綁紮的品質與結構穩定度密切相關。有一些結構體的形成過程需藉助支撐件的輔助。例如,在逆打工法中建設筏基時,使用角鐵或鋼筋工作架進行地梁鋼筋綁紮作業,將鋼筋工作架豎立於大底並利用鋼筋工作架支撐上層鋼筋。在完成鋼筋綁紮後,進行組模與澆置作業,連帶地將鋼筋工作架封在結構體內。換言之,現有的施工方式無法回收這些支撐件(以及與之配合的元件),如此將增加材料使用成本。有鑑於此,現有的鋼筋綁紮施工方式仍有待改進。 In building construction, the quality of steel bar binding is closely related to structural stability. Some structures are formed by the aid of a support. For example, when constructing a raft foundation in the reverse construction method, an angle iron or a steel work frame is used to perform the ground beam reinforcement tying operation, and the steel work frame is erected on the outsole and the upper reinforcement is supported by the steel work frame. After the completion of the steel bar tying, the group mold and the pouring operation are performed, and the steel bar work frame is sealed in the structure body. In other words, existing construction methods cannot recover these supports (and the components they are mated with), which will increase the cost of material use. In view of this, the existing construction method of steel bar lashing still needs to be improved.

本發明之一目的在於提供一種懸吊式鋼筋工作架,可回收使用以節省材料成本。 It is an object of the present invention to provide a suspended steel work frame that can be recycled for use in material cost savings.

本發明之另一目的在於提供一種懸吊式鋼筋工作架的施工 方法,配合逆打工法提高其施工效率。 Another object of the present invention is to provide a construction of a suspended steel work frame The method is combined with the reverse working method to improve the construction efficiency.

懸吊式鋼筋工作架包含螺桿、吊件以及型鋼。螺桿係設置朝遠離樓板表面延伸。螺桿具有第一端及位於第一端相反側之第二端。吊件係設置於樓板並連接第一端。型鋼設置垂直於螺桿的延伸方向並固定於第二端。於一實施例,懸吊式鋼筋工作架更包含伸縮器,且螺桿包含分離的第一子桿體與第二子桿體。伸縮器連接第一子桿體與第二子桿體,藉由伸縮器可調整兩個子桿體的相對距離,以改變螺桿的長度。 Suspended steel work frames contain screws, hangers and sections. The screw system is arranged to extend away from the surface of the floor. The screw has a first end and a second end on the opposite side of the first end. The hanging piece is arranged on the floor and connected to the first end. The profile steel is disposed perpendicular to the direction in which the screw extends and is fixed to the second end. In one embodiment, the suspended steel work frame further includes a retractor, and the screw includes a separated first sub-bar body and a second sub-rod body. The retractor connects the first sub-bar body and the second sub-bar body, and the relative distance between the two sub-bar bodies can be adjusted by the retractor to change the length of the screw.

地下層施工方法包含:於樓板吊掛懸吊式鋼筋工作架;於型鋼與開挖面之間的一預形成範圍綁紮鋼筋;於預形成範圍間澆置混凝土以形成結構體;俟結構體完成後,拆除懸吊式鋼筋工作架。 The underground layer construction method comprises: hanging a suspended steel work frame on the floor; tying the steel bar in a pre-formed range between the steel section and the excavation face; pouring concrete between the preformed ranges to form a structure; After that, remove the suspended steel work frame.

10‧‧‧懸吊式鋼筋工作架 10‧‧‧suspension steel work frame

20‧‧‧樓板 20‧‧‧ Floor

30‧‧‧開挖面 30‧‧‧Excavation surface

40‧‧‧懸臂梁 40‧‧‧Cantilever beam

42‧‧‧預留孔 42‧‧‧Reserved holes

50‧‧‧支撐牆體 50‧‧‧Support wall

60‧‧‧基礎版 60‧‧‧ Basic Edition

62‧‧‧地梁 62‧‧‧Ground beams

64‧‧‧頂版 64‧‧‧Top version

70‧‧‧模板 70‧‧‧ template

72‧‧‧角材 72‧‧‧ Anglewood

80‧‧‧鋼管 80‧‧ ‧ steel pipe

110‧‧‧螺桿 110‧‧‧ screw

111‧‧‧第一端 111‧‧‧ first end

112‧‧‧第二端 112‧‧‧ second end

121‧‧‧第一子桿體 121‧‧‧First sub-rod

122‧‧‧第二子桿體 122‧‧‧Second sub-bar

123‧‧‧第一調整端 123‧‧‧First adjustment end

124‧‧‧第二調整端 124‧‧‧second adjustment end

130‧‧‧吊件 130‧‧‧ hanging pieces

132‧‧‧中空區域 132‧‧‧ hollow area

150‧‧‧型鋼 150‧‧‧ steel

152‧‧‧安裝面 152‧‧‧Installation surface

154‧‧‧鎖孔 154‧‧‧Keyhole

156‧‧‧調整孔 156‧‧‧Adjustment hole

160‧‧‧螺帽 160‧‧‧ nuts

170‧‧‧伸縮器 170‧‧‧Steel

601‧‧‧上層筋 601‧‧‧Upper ribs

603‧‧‧箍筋 603‧‧‧ stirrups

605‧‧‧下層筋 605‧‧‧lower ribs

607‧‧‧版筋 607‧‧‧ ribs

609‧‧‧鋼筋 609‧‧ ‧ steel bars

a‧‧‧延伸方向 A‧‧‧ extending direction

b‧‧‧延伸方向 b‧‧‧Extension direction

c‧‧‧方向 C‧‧‧direction

圖1為本發明懸吊式鋼筋工作架之一實施例示意圖;圖2為吊件與螺桿組裝之實施例示意圖;圖3為型鋼與螺桿組裝之實施例示意圖;圖4為對應圖1的懸吊式鋼筋工作架設置於樓板的實施例示意圖;圖5為型鋼之另一實施例示意圖;圖6為本發明懸吊式鋼筋工作架之另一實施例示意圖;圖7為對應圖6的懸吊式鋼筋工作架設置於樓板的實施例示意圖;圖8為本發明地下層施工方法之一實施例流程圖;圖9為地下層施工方法包含懸吊式鋼筋工作架吊掛步驟的細部流程圖;圖10為地下層施工方法包含懸吊式鋼筋工作架吊掛步驟的另一實施例流程圖; 圖11為地下層施工方法包含結構體形成步驟的細部流程圖;圖12至圖20為本發明地下層施工方法形成結構體的施工示意圖;圖21為地下層施工方法包含結構體形成步驟的另一實施例流程圖;圖22至圖25為本發明地下層施工方法形成結構體的施工示意圖。 1 is a schematic view of an embodiment of a suspension type steel work frame according to the present invention; FIG. 2 is a schematic view showing an embodiment of the assembly of the hanging piece and the screw; FIG. 3 is a schematic view of an embodiment of the assembly of the steel and the screw; FIG. 5 is a schematic view of another embodiment of a steel frame according to another embodiment of the present invention; FIG. 6 is a schematic view of another embodiment of a suspended steel work frame according to the present invention; FIG. Schematic diagram of an embodiment of a hanging steel work frame disposed on a floor; FIG. 8 is a flow chart of an embodiment of a method for constructing a underground layer of the present invention; and FIG. 9 is a detailed flow chart of a method for hanging a suspended steel work frame in a method of underground layer construction Figure 10 is a flow chart showing another embodiment of the underground layer construction method including the suspension steel frame hanging step; 11 is a detailed flow chart of a method for forming a subterranean formation comprising a structure; FIG. 12 to FIG. 20 are schematic views showing a construction of a structure for forming a subterranean formation according to the present invention; and FIG. 21 is a schematic diagram of a method for forming a subterranean formation including a step of forming a structure. A flow chart of an embodiment; FIG. 22 to FIG. 25 are schematic views showing the construction of a structure formed by a subterranean layer construction method of the present invention.

本發明係提供一種懸吊式鋼筋工作架,可在逆打工法的結構體建設過程中(例如鋼筋綁紮作業)提供臨時的支撐,且可在結構體完成後回收利用。圖1為本發明懸吊式鋼筋工作架10之一實施例示意圖。如圖1所示,懸吊式鋼筋工作架10包含螺桿110、吊件130以及型鋼150。在圖1的實施例,螺桿110為一長條狀桿體,沿其軸向在空間中豎立的方式設置。螺桿110具有第一端111及位於第一端111相反側之第二端112。吊件130係連接螺桿110的第一端111。請配合參考圖2,圖2為吊件130與螺桿110組裝之實施例示意圖。如圖2所示,吊件130整體為柱狀,且內部具有中空區域132,例如可形成內牙作為接合之用。螺桿110的第一端111係伸入中空區域132,藉此達成螺桿110與吊件130的固定。 The invention provides a suspended steel work frame, which can provide temporary support during the construction process of the reverse construction method (for example, steel bar binding operation), and can be recycled after the structure is completed. 1 is a schematic view of an embodiment of a suspended steel work frame 10 of the present invention. As shown in FIG. 1, the suspended steel work frame 10 includes a screw 110, a hanger 130, and a profile 150. In the embodiment of Fig. 1, the screw 110 is an elongated rod body that is disposed erected in space along its axial direction. The screw 110 has a first end 111 and a second end 112 on the opposite side of the first end 111. The hanger 130 is coupled to the first end 111 of the screw 110. Please refer to FIG. 2, which is a schematic diagram of an embodiment of assembling the hanger 130 and the screw 110. As shown in Fig. 2, the hanger 130 is generally cylindrical and has a hollow region 132 therein, for example, an internal tooth can be formed for engagement. The first end 111 of the screw 110 extends into the hollow region 132, whereby the fixing of the screw 110 and the hanger 130 is achieved.

另一方面,型鋼150係固定於螺桿110的第二端112。請參考圖1與圖3。在圖1中係繪示正面一側的型鋼150。如圖1所示,型鋼150在空間中以水平的方式設置。相對於螺桿110,型鋼150係設置垂直於螺桿110的延伸方向(螺桿的軸向)。在圖3中係繪示背面一側的型鋼150。如圖3所示之型鋼150與螺桿110組裝之實施例,型鋼150具有安裝面152及形成於安裝面152的鎖孔154。於一實施例,懸吊式鋼筋工作架可包含螺帽160。如圖3所示,螺桿110之第二端112係自鎖孔154貫穿安裝面152,且螺帽160係自安裝面152的相反側鎖附第二端112。藉此達成螺桿110與 型鋼150的固定。 On the other hand, the profiled steel 150 is fixed to the second end 112 of the screw 110. Please refer to Figure 1 and Figure 3. In Fig. 1, the profiled steel 150 on the front side is shown. As shown in Fig. 1, the profiled steel 150 is disposed in a horizontal manner in space. With respect to the screw 110, the profile 150 is disposed perpendicular to the extending direction of the screw 110 (the axial direction of the screw). In Fig. 3, the profile steel 150 on the back side is shown. As an example of assembling the profiled steel 150 and the screw 110 as shown in FIG. 3, the profiled steel 150 has a mounting surface 152 and a keyhole 154 formed in the mounting surface 152. In one embodiment, the suspended steel work frame can include a nut 160. As shown in FIG. 3, the second end 112 of the screw 110 extends through the mounting surface 152 from the locking aperture 154, and the nut 160 is attached to the second end 112 from the opposite side of the mounting surface 152. Thereby achieving the screw 110 and Fixing of profile steel 150.

在其他實施例,螺桿與型鋼可採用其他固定方式,例如,螺桿靠近第二端的位置形成直徑略大於鎖孔的擴大部,且在擴大部與螺桿的其他部分採可分離的設計。當螺桿安裝於型鋼時,將螺桿伸入鎖孔,再自安裝面另一側組裝擴大部,以達成螺桿與型鋼的固定。需補充的是,型鋼為角鋼或槽鋼,其剖面形狀並不以圖3繪示的態樣為限。 In other embodiments, the screw and the section steel may be otherwise fixed, for example, the screw near the second end forms an enlarged portion that is slightly larger in diameter than the keyhole, and is detachably designed in the enlarged portion from the other portions of the screw. When the screw is installed on the steel profile, the screw is inserted into the lock hole, and the enlarged portion is assembled from the other side of the mounting surface to achieve the fixing of the screw and the steel. It should be added that the section steel is angle steel or channel steel, and its sectional shape is not limited to the state shown in FIG.

圖4為對應圖1的懸吊式鋼筋工作架10設置於樓板20的實施例示意圖。如圖4所示,懸吊式鋼筋工作架10係吊掛於樓板20,位於樓板20與開挖面30之間。前述吊件(圖未示)係設置於樓板20。舉例而言,在樓板20成型之前將吊件預埋於樓板20內部。螺桿110設置朝遠離樓板20表面延伸。螺桿110兩端分別連接吊件與型鋼150,組成懸吊式鋼筋工作架10。如圖4所示,可採用多個懸吊式鋼筋工作架10,每一型鋼150設置垂直於螺桿110的延伸方向,且各型鋼150彼此並列設置。例如,螺桿110具有延伸方向a,型鋼150沿延伸方向b設置,型鋼150排列的方向c係沿橫切型鋼150的延伸方向b並列設置。 4 is a schematic view showing an embodiment in which the suspended steel work frame 10 of FIG. 1 is disposed on the floor 20. As shown in FIG. 4, the suspended steel work frame 10 is suspended from the floor 20 and is located between the floor 20 and the excavation face 30. The aforementioned hanger (not shown) is provided on the floor panel 20. For example, the hanger is pre-buried inside the floor 20 before the floor 20 is formed. The screw 110 is disposed to extend away from the surface of the floor 20. The two ends of the screw 110 are respectively connected with a hanging piece and a steel 150 to form a suspended steel work frame 10. As shown in FIG. 4, a plurality of suspended steel work frames 10 may be employed, each of which is disposed perpendicular to the extending direction of the screw 110, and each of the steel bars 150 are juxtaposed to each other. For example, the screw 110 has an extending direction a, the steel 150 is disposed along the extending direction b, and the direction c in which the steel 150 is aligned is juxtaposed along the extending direction b of the transverse steel 150.

於一實施例,螺桿係成對設置於型鋼,例如型鋼的左右兩側各設置一支螺桿。在其它實施例,亦可視需求調整螺桿的設置方式,例如將螺桿固定於型鋼中間,型鋼兩側利用鋼繩與螺桿連接。 In one embodiment, the screw systems are disposed in pairs on a profiled steel, such as a screw on each of the left and right sides of the profiled steel. In other embodiments, the arrangement of the screw can also be adjusted according to requirements, for example, the screw is fixed in the middle of the steel, and the steel is connected to the screw by the steel wire on both sides.

懸吊式鋼筋工作架可對型鋼進行平整度的調整。例如於螺桿的第二端112,藉前述螺帽160(參考圖3),調整螺桿110伸入鎖孔154的深度。另外,型鋼亦可透過螺桿的第一端進行平整度的調整。例如改變螺桿第一端伸入吊件的深度。在其它實施例,可結合上述兩種方式進行平整度的調整。 The suspended steel work frame can adjust the flatness of the steel. For example, at the second end 112 of the screw, by the aforementioned nut 160 (refer to FIG. 3), the depth of the screw 110 extending into the lock hole 154 is adjusted. In addition, the profile steel can also be adjusted for flatness through the first end of the screw. For example, changing the depth at which the first end of the screw extends into the hanger. In other embodiments, the adjustment of the flatness can be performed in combination with the above two methods.

此外,螺桿設置於型鋼上的位置係可調整的。請參考圖5。 圖5為型鋼150之另一實施例示意圖。如圖5所示,型鋼150具有形成於安裝面152的調整孔156。調整孔156係沿型鋼150的延伸方向b分布於鎖孔154之一側。在圖5的實施例,型鋼150的一邊於安裝面152上形成兩個調整孔156,位於鎖孔154左右兩側。鎖孔154至兩側調整孔156的間距相等。類似地,型鋼150的另一邊(圖未示)亦可採相同配置。應理解,調整孔156設置的數量及間距不以此為限。藉此設計,可視施工現場的情形改變螺桿的位置。以前述將螺桿110成對設置於型鋼150的方式為例(參考圖4),型鋼150兩邊的螺桿110可藉調整孔156調整兩側螺桿之間寬度,增加使用上的彈性。 In addition, the position of the screw on the profile is adjustable. Please refer to Figure 5. FIG. 5 is a schematic view of another embodiment of a profiled steel 150. As shown in FIG. 5, the profiled steel 150 has an adjustment hole 156 formed in the mounting surface 152. The adjustment holes 156 are distributed on one side of the lock hole 154 along the extending direction b of the steel 150. In the embodiment of FIG. 5, one side of the profiled steel 150 defines two adjustment holes 156 on the mounting surface 152, which are located on the left and right sides of the lock hole 154. The pitch of the keyhole 154 to the two side adjustment holes 156 is equal. Similarly, the other side of the profiled steel 150 (not shown) may also be of the same configuration. It should be understood that the number and spacing of the adjustment holes 156 are not limited thereto. With this design, the position of the screw can be changed depending on the situation at the construction site. Taking the screw 110 in pairs in the form of the profiled steel 150 as described above (refer to FIG. 4), the screw 110 on both sides of the profiled steel 150 can adjust the width between the screws on both sides by the adjustment hole 156 to increase the elasticity of use.

圖6為本發明懸吊式鋼筋工作架10之另一實施例示意圖。如圖6所示,與前述實施例的差異在於,懸吊式鋼筋工作架10包含伸縮器170連接分離的螺桿110。具體而言,螺桿110為分離的長條狀桿體組件,包含第一子桿體121與第二子桿體122。第一子桿體121沿其軸向在空間中豎立的方式設置,且第二子桿體122沿平行第一子桿體的延伸方向排列。如圖6所示,第一子桿體121具有第一調整端123,第二子桿體122具有第二調整端124與第一調整端123相向設置。 FIG. 6 is a schematic view of another embodiment of the suspended steel work frame 10 of the present invention. As shown in FIG. 6, the difference from the foregoing embodiment is that the suspended rebar workbench 10 includes the retractor 170 to connect the separated screws 110. Specifically, the screw 110 is a separate elongated rod assembly including a first sub-rod 121 and a second sub-rod 122. The first sub-rods 121 are disposed in a manner that they are erected in space along the axial direction thereof, and the second sub-rods 122 are arranged in parallel with the extending direction of the first sub-rods. As shown in FIG. 6 , the first sub-rod 121 has a first adjustment end 123 , and the second sub-rod 122 has a second adjustment end 124 disposed opposite to the first adjustment end 123 .

如圖6所示,伸縮器170連接第一子桿體121與第二子桿體122,亦即,於第一調整端123和第二調整端124將兩個子桿體連接。第一調整端123與第二調整端124之間的距離隨第一子桿體121與第二子桿體122沿螺桿110的延伸方向移動而改變。例如,懸吊式鋼筋工作架10可自伸縮器170將部分的第一子桿體121移出伸縮器170外,此時第一調整端123遠離第二調整端124,第一子桿體121伸出於伸縮器170的長度增長,且吊件130到型鋼150的距離增加。藉此設計,可利用伸縮器170調整懸吊式鋼筋工作架10的整體吊掛長度。 As shown in FIG. 6, the retractor 170 connects the first sub-rod 121 and the second sub-bar 122, that is, the two sub-bars are connected to the first adjustment end 123 and the second adjustment end 124. The distance between the first adjustment end 123 and the second adjustment end 124 changes as the first sub-rod 121 and the second sub-bar 122 move in the extending direction of the screw 110. For example, the suspended steel work frame 10 can move a portion of the first sub-rod 121 out of the retractor 170 from the retractor 170. At this time, the first adjustment end 123 is away from the second adjustment end 124, and the first sub-rod 121 is extended. As the length of the retractor 170 increases, the distance from the hanger 130 to the profile 150 increases. With this design, the overall length of the suspension rebar work frame 10 can be adjusted by the retractor 170.

另外,在圖6的實施例,第一子桿體121相反於第一調整端123的一端係連接吊件130,而第二子桿體122相反於第二調整端124的一端係固定於型鋼。在其他實施例,懸吊式鋼筋工作架可設計為吊件和型鋼處具有相同的固定方式,使第一子桿體與第二子桿體可替換於不同設置位置。 In addition, in the embodiment of FIG. 6, the first sub-rod 121 is connected to the hanger 130 at one end opposite to the first adjustment end 123, and the second sub-bar 122 is fixed to the profile steel at one end opposite to the second adjustment end 124. . In other embodiments, the suspended steel work frame can be designed such that the hanger and the steel have the same fixing manner, so that the first and second sub-rods can be replaced with different positions.

整體而言,型鋼的平整度除了如前述可於吊件之一側或是型鋼之一側進行調整外,還可利用伸縮器來調整。舉例而言,利用伸縮器作為粗調,再利用吊件之一側或是型鋼之一側進行微調。藉此,懸吊式鋼筋工作架可視施工需求作不同程度的調整,以提高調校的精確性。 Overall, the flatness of the section steel can be adjusted by using a bellows, in addition to being adjustable on one side of the hanger or one side of the profile as previously described. For example, a retractor is used as a coarse adjustment, and one side of the hanger or one side of the profile is used for fine adjustment. Thereby, the suspended steel work frame can be adjusted to different degrees according to the construction requirements to improve the accuracy of the adjustment.

圖7為對應圖6的懸吊式鋼筋工作架10設置於樓板20的實施例示意圖。如圖7所示,懸吊式鋼筋工作架10係吊掛於樓板20。類似地,將吊件係設置於樓板20。第一子桿體121與第二子桿體122設置朝遠離樓板20表面延伸,且第一子桿體121係連接吊件。第二子桿體122沿平行第一子桿體121的延伸方向a排列,且以伸縮器170連接第一子桿體121與第二子桿體122。第二子桿體122相反於第一子桿體121的一端係固定於型鋼150,以組成懸吊式鋼筋工作架10。如圖6所示,可採用多個懸吊式鋼筋工作架10,每一型鋼150設置垂直於螺桿110的延伸方向a,且各型鋼150彼此並列設置。 FIG. 7 is a schematic view showing an embodiment in which the suspended steel work frame 10 of FIG. 6 is disposed on the floor 20. As shown in FIG. 7, the suspended steel work frame 10 is suspended from the floor 20. Similarly, the hanger system is placed on the floor panel 20. The first sub-rod 121 and the second sub-rod 122 are disposed to extend away from the surface of the floor 20, and the first sub-rod 121 is connected to the hanger. The second sub-rods 122 are arranged in parallel with the extending direction a of the first sub-rods 121, and the first sub-rods 121 and the second sub-rods 122 are connected by the expander 170. The second sub-rod 122 is fixed to the profiled steel 150 opposite to the end of the first sub-rod 121 to constitute the suspended rebar work frame 10. As shown in Fig. 6, a plurality of suspended rebar work frames 10 may be employed, each of which is disposed perpendicular to the direction a of extension of the screw 110, and each of the steel bars 150 is juxtaposed to each other.

圖8為本發明地下層施工方法之一實施例流程圖。如圖8所示,地下層施工方法包含步驟S10:於樓板吊掛懸吊式鋼筋工作架。在步驟S12係確認懸吊式鋼筋工作架的設置是否達預定需求。所述預定需求係指螺桿長度是否足夠,以及懸吊式鋼筋工作架的數量是否足夠,其數量會隨欲建設的結構體尺寸而改變。例如圖4所示,沿方向c設置有多個懸吊式鋼筋工作架。若未達預定需求,則繼續設置懸吊式鋼筋工作架。反之, 若已達預定需求,則進行步驟S20。 8 is a flow chart of an embodiment of a method for constructing a subterranean formation according to the present invention. As shown in FIG. 8, the underground layer construction method includes the step S10: hanging the suspended steel work frame on the floor. At step S12, it is confirmed whether the setting of the suspended rebar work frame reaches a predetermined demand. The predetermined demand refers to whether the length of the screw is sufficient, and whether the number of the suspended steel work stands is sufficient, and the number thereof varies depending on the size of the structure to be constructed. For example, as shown in FIG. 4, a plurality of suspended steel work frames are disposed along the direction c. If the required demand is not met, continue to set up the suspended steel work frame. on the contrary, If the predetermined demand has been reached, step S20 is performed.

在步驟S20:於預形成範圍綁紮鋼筋。所述預形成範圍係指欲建設的結構體的所在位置。具體而言,確認欲建設的結構體後,將懸吊式鋼筋工作架吊掛完成,接著於型鋼與開挖面之間的預形成範圍綁紮鋼筋。接著在步驟S30:澆置混凝土。於預形成範圍間澆置混凝土以形成結構體。接著在步驟S40:拆除該懸吊式鋼筋工作架。藉此,懸吊式鋼筋工作架可拆除回收至其他位置組裝使用,可節省材料成本。 In step S20: the reinforcing bars are tied in the preformed range. The pre-formed range refers to the location of the structure to be constructed. Specifically, after confirming the structure to be constructed, the suspended steel work frame is hung, and then the steel bars are tied in a pre-formed range between the steel and the excavation surface. Next, in step S30, concrete is poured. Concrete is placed between the preformed ranges to form a structure. Next at step S40: the suspended steel work frame is removed. In this way, the suspended steel work frame can be removed and recycled to other locations for assembly, which can save material costs.

圖9為地下層施工方法包含懸吊式鋼筋工作架吊掛步驟的細部流程圖。如圖9所示,在懸吊式鋼筋工作架設置階段,包含步驟S101、S103、S105、S107。在步驟S101:於樓板設置吊件。舉例而言,在樓板成型之前將吊件預埋於樓板內部。在步驟S103:設置螺桿朝遠離樓板表面延伸。螺桿沿其軸向在空間中豎立的方式設置。接著將螺桿兩端組合,在步驟S105:連接吊件與第一端。在步驟S107:設置型鋼,並固定型鋼與第二端。懸吊式鋼筋工作架設置完成後,接著上述步驟S12、S20、S30、S40,建設結構體,然後將懸吊式鋼筋工作架拆除回收。 Figure 9 is a detailed flow chart of the underground layer construction method including the hanging steel frame lifting step. As shown in Fig. 9, in the suspension type steel frame installation stage, steps S101, S103, S105, and S107 are included. In step S101, a hanging member is set on the floor. For example, the slings are pre-buried inside the slab before the slab is formed. In step S103, the setting screw is extended away from the surface of the floor. The screw is arranged in such a manner that its screw is erected in space in its axial direction. Next, the two ends of the screw are combined, and in step S105, the hanger and the first end are connected. In step S107, a profile steel is set and the steel section is fixed to the second end. After the suspension type steel work frame is set, the structural body is constructed by the above steps S12, S20, S30, and S40, and then the suspended steel work frame is removed and recovered.

於一實施例,螺桿係成對設置於型鋼。在型鋼與螺桿固定階段可進一步包含:將螺桿成對設置於型鋼。此外,可採用多個懸吊式鋼筋工作架,亦即,重覆上述步驟S101、S103、S105、S107組成多個懸吊式鋼筋工作架。每一型鋼的設置步驟可進一步包含:將型鋼彼此並列設置。 In one embodiment, the screw systems are disposed in pairs in a profiled steel. In the section of fixing the steel and the screw, the screw may further comprise: the screws are arranged in pairs on the steel. In addition, a plurality of suspended steel work frames can be used, that is, the above steps S101, S103, S105, and S107 are repeated to form a plurality of suspended steel work frames. The step of setting each steel section may further include: arranging the steel profiles in parallel with each other.

於一實施例,型鋼係固定於螺桿的第二端。在型鋼與螺桿固定階段可進一步包含:於安裝面形成鎖孔;將螺桿之第二端自鎖孔貫穿安裝面;以螺帽自安裝面的相反側鎖附第二端。在其他實施例,可於上述鎖孔之一側形成其他孔。在型鋼與螺桿固定階段可進一步包含:於安裝面形成至少一調整孔,調整孔係分布於鎖孔之一側。例如,沿型鋼的延伸方向 分布於鎖孔左右兩側。藉此設計,可視施工現場的情形改變螺桿固定於型鋼上的位置。 In one embodiment, the profile is attached to the second end of the screw. In the steel and screw fixing stage, the method further comprises: forming a locking hole on the mounting surface; inserting the second end of the screw from the locking hole through the mounting surface; and locking the second end from the opposite side of the mounting surface with the nut. In other embodiments, other holes may be formed on one side of the above-mentioned keyhole. In the steel and screw fixing stage, the method further includes: forming at least one adjusting hole on the mounting surface, and adjusting the hole system on one side of the locking hole. For example, along the direction of extension of the section steel Distributed on the left and right sides of the keyhole. With this design, the position of the screw fixed on the profile steel can be changed depending on the situation at the construction site.

圖10為地下層施工方法包含懸吊式鋼筋工作架吊掛步驟的另一實施例流程圖。螺桿為分離的長條狀桿體組件,並利用伸縮器連接。如圖10所示,在步驟S101:於樓板設置吊件。在懸吊式鋼筋工作架設置階段,更包含步驟S1031:設置第一子桿體和第二子桿體朝遠離樓板表面延伸。第一子桿體與第二子桿體。第一子桿體沿其軸向在空間中豎立的方式設置,且第二子桿體沿平行第一子桿體的延伸方向排列。第一子桿體具有第一調整端,第二子桿體具有第二調整端與第一調整端相向設置。 Figure 10 is a flow chart showing another embodiment of the underground layer construction method including the suspension steel frame hanging step. The screw is a separate elongated rod assembly and is connected by a retractor. As shown in FIG. 10, in step S101, a hanger is provided on the floor. In the suspension steel frame setting stage, the method further includes a step S1031: setting the first sub-bar body and the second sub-bar body to extend away from the floor surface. The first sub-bar body and the second sub-bar body. The first sub-rods are disposed in a manner that they are erected in space along the axial direction thereof, and the second sub-rods are arranged in parallel with the extending direction of the first sub-bars. The first sub-rod has a first adjustment end, and the second sub-rod has a second adjustment end disposed opposite to the first adjustment end.

在步驟S1033:以伸縮器連接第一子桿體與第二子桿體。於一實施例,第一子桿體相反於第一調整端的一端係連接吊件,而第二子桿體相反於第二調整端的一端係固定於型鋼。第一調整端與第二調整端之間則以伸縮器連接。懸吊式鋼筋工作架的整體長度可隨第一子桿體與第二子桿體沿螺桿的延伸方向移動而改變。例如,於伸縮器調整第一子桿體與第二子桿體彼此靠近,則懸吊式鋼筋工作架自樓板朝向下方開挖面的長度縮短,且型鋼的水平高度提高。 In step S1033, the first sub-bar body and the second sub-bar body are connected by a retractor. In one embodiment, one end of the first sub-rod opposite to the first adjustment end is connected to the hanger, and one end of the second sub-rod opposite to the second adjustment end is fixed to the steel. The first adjustment end and the second adjustment end are connected by a retractor. The overall length of the suspended rebar work frame may vary as the first sub-bar body and the second sub-rod body move in the direction in which the screw extends. For example, when the retractor adjusts the first sub-bar body and the second sub-bar body to be close to each other, the length of the suspended rebar work surface from the floor panel toward the lower excavation surface is shortened, and the level of the profile steel is increased.

如圖10所示,接著進行前述步驟S105、S107、以及步驟S12。當懸吊式鋼筋工作架之設置已達預定需求,則進行步驟S14。在步驟S14係確認型鋼是否平整。例如,以雷射裝置確認各型鋼的水平高度是否一致。若型鋼不平整,則進行步驟S109:調整第一子桿體與第二子桿體。例如,利用伸縮器調整螺桿的伸出量,使型鋼平整地設置。若型鋼係平整的,則接著進行步驟S20、S30、S40,建設結構體,然後將懸吊式鋼筋工作架拆除回收。 As shown in FIG. 10, the above steps S105, S107, and step S12 are performed. When the setting of the suspended steel work frame has reached the predetermined demand, step S14 is performed. At step S14, it is confirmed whether the steel is flat. For example, it is confirmed by a laser device whether the horizontal heights of the respective steel profiles are uniform. If the section steel is not flat, proceed to step S109 to adjust the first sub-bar body and the second sub-bar body. For example, the amount of protrusion of the screw is adjusted by a retractor to set the profile steel flat. If the profiled steel is flat, then steps S20, S30, and S40 are performed to construct the structure, and then the suspended steel bar work frame is removed and recovered.

圖11為地下層施工方法包含結構體形成步驟的細部流程 圖。圖11係繪示將懸吊式鋼筋工作架結合基礎結構建設的流程。所述地下層施工方法係於地下層開挖後,於上層之樓板與該樓板下方之開挖面之間的施工方法。換言之,懸吊式鋼筋工作架可配合逆打工法,在地下層中構築樓板時,將吊件設置於樓板(例如預先埋設於樓板中),待樓板下方開挖後進行懸吊式鋼筋工作架的吊掛作業。 Figure 11 is a detailed flow diagram of a method for forming a subterranean formation including a structure forming step Figure. Figure 11 is a flow chart showing the construction of a suspended steel work frame combined with an infrastructure. The underground layer construction method is a construction method between the upper floor slab and the excavation surface below the floor after the underground layer is excavated. In other words, the suspended steel work frame can be used in conjunction with the reverse work method. When constructing the floor in the basement, the hangers are placed on the floor (for example, pre-buried in the floor), and the suspended steel frame is placed after the excavation below the floor. Hanging work.

如圖11所示,懸吊式鋼筋工作架設置完成後(步驟S10~S12),接著進行建築結構體的作業。在步驟S201:於型鋼上設置複數上層筋。在步驟S203:於上層筋及開挖面之間設置複數箍筋。在步驟S205:設置複數下層筋。在步驟S207:設置複數版筋。 As shown in Fig. 11, after the suspension type steel work frame is installed (steps S10 to S12), the work of the building structure is performed. In step S201, a plurality of upper ribs are disposed on the steel section. In step S203, a plurality of stirrups are disposed between the upper layer rib and the excavation surface. In step S205: a plurality of lower layers are set. In step S207: a plurality of ribs are set.

請配合參考圖12~15的施工示意圖。如圖12所示,樓板20建設完成,於下方空間挖掘至開挖面30。於開挖面30澆置PC整理。於樓板20下方吊掛懸吊式鋼筋工作架10,包含前述螺桿110、伸縮器170、型鋼150等。在圖12中,係採用具有伸縮器170之懸吊式鋼筋工作架10,但不限於此。待懸吊式鋼筋工作架10設置完成,於型鋼150上設置複數上層筋601。例如,沿型鋼150排列的方向c設置上層筋601。 Please refer to the construction diagram of Figure 12~15. As shown in Fig. 12, the floor 20 is completed and excavated to the excavation surface 30 in the space below. The PC is placed on the excavation face 30 for finishing. A suspended steel work frame 10 is suspended below the floor 20, and includes the aforementioned screw 110, a retractor 170, a steel 150, and the like. In Fig. 12, a suspended steel work frame 10 having a retractor 170 is employed, but is not limited thereto. After the suspension steel frame 10 is set, a plurality of upper ribs 601 are disposed on the steel 150. For example, the upper layer rib 601 is disposed along the direction c in which the steel bars 150 are arranged.

如圖13所示,於上層筋601及開挖面30之間設置複數箍筋603。如圖14所示,於該些箍筋603接近開挖面30之一側設置複數下層筋605,以及如圖15所示,於箍筋603接近下層筋605之一側設置複數版筋607。藉此,在結構體預形成範圍的作業可利用上方的樓板配合本發明的懸吊式鋼筋工作架提供支撐。 As shown in FIG. 13, a plurality of stirrups 603 are disposed between the upper layer rib 601 and the excavation surface 30. As shown in FIG. 14, a plurality of lower ribs 605 are disposed on one side of the stirrup 603 near the excavation face 30, and as shown in FIG. 15, a plurality of ribs 607 are disposed on one side of the stirrup 603 near the lower rib 605. Thereby, the work in the pre-formation range of the structure can be supported by the upper floor slab together with the suspended steel work frame of the present invention.

回到圖11,建築結構體的作業接著進入澆置混凝土及後續回收懸吊式鋼筋工作架的流程。在步驟S301:澆置混凝土而形成基礎版。在步驟S303:澆置混凝土而形成地梁。在步驟S40:拆除該懸吊式鋼筋工作架。在步驟S50:澆置混凝土而形成頂版。 Returning to Figure 11, the operation of the building structure then proceeds to the process of pouring the concrete and subsequently recovering the suspended steel work frame. In step S301, concrete is poured to form a base plate. In step S303, concrete is poured to form a ground beam. At step S40: the suspended steel work frame is removed. At step S50: the concrete is poured to form a top plate.

請配合參考圖16~20的施工示意圖。如圖16所示,於版筋607(參考圖15)與開挖面30之間澆置混凝土而形成基礎版60。接著如圖17所示,在基礎版60上澆置混凝土而形成地梁62。具體而言,於上層筋601下方之預設高度至基礎版60之間澆置混凝土而形成地梁62。換言之,保留預設高度預防澆置作業濺污懸吊式鋼筋工作架10並預留拆除懸吊式鋼筋工作架10的空間。如圖18所示,將懸吊式鋼筋工作架10拆除回收。需補充的是,懸吊式鋼筋工作架10亦可在基礎版60完成後(圖16)拆除,並不以前述說明的順序為限。圖19至圖20係繪示與上層筋601連結的結構體施做過程。如圖19所示,在接近上層筋601所在平面設置複數鋼筋609。如圖20所示,澆置混凝土而形成頂版64。 Please refer to the construction diagram of Figure 16~20. As shown in Fig. 16, a concrete plate 60 is formed by pouring concrete between the plate rib 607 (refer to Fig. 15) and the excavation face 30. Next, as shown in FIG. 17, concrete is poured on the base plate 60 to form the ground beam 62. Specifically, the ground beam 62 is formed by pouring concrete between the preset height below the upper rib 601 to the base plate 60. In other words, the preset height is prevented to prevent the pouring operation from splashing the suspended steel work frame 10 and the space for removing the suspended steel work frame 10 is reserved. As shown in Fig. 18, the suspended steel work frame 10 is removed and recovered. It should be added that the suspended steel work frame 10 can also be removed after the completion of the basic plate 60 (Fig. 16), and is not limited to the order described above. 19 to 20 illustrate a structure applying process of the upper layer rib 601. As shown in FIG. 19, a plurality of reinforcing bars 609 are disposed near the plane of the upper layer rib 601. As shown in Fig. 20, concrete is poured to form a top plate 64.

圖21為地下層施工方法包含結構體形成步驟的另一實施例流程圖。圖21係繪示懸吊式鋼筋工作架設置範圍內有阻隔物以及將懸吊式鋼筋工作架運用於其它結構建設的流程。如圖21所示,吊件設置完成後(步驟S101),在步驟S1032:於懸臂梁模組設置預留孔,並設置螺桿朝遠離樓板表面延伸。在步驟S1034:將螺桿穿過預留孔。在步驟S105:連接吊件與第一端。在步驟S1072:將型鋼設置於懸臂梁模組相反於樓板的一側,並固定型鋼與第二端。在步驟S1074:螺桿與型鋼共同支撐懸臂梁模組,並於步驟S12判斷懸吊式鋼筋工作架的設置是否達成預定需求。 Figure 21 is a flow chart showing another embodiment of the method for forming a subterranean formation comprising a structure forming step. Figure 21 shows the flow of the barrier in the setting range of the suspended steel work frame and the construction of the suspended steel work frame for other structural construction. As shown in FIG. 21, after the installation of the hanger is completed (step S101), in step S1032, a reserved hole is provided in the cantilever beam module, and the screw is disposed to extend away from the surface of the floor. At step S1034, the screw is passed through the reserved hole. In step S105, the hanger is connected to the first end. In step S1072, the profile steel is placed on the side of the cantilever beam module opposite to the floor, and the steel and the second end are fixed. In step S1074, the screw and the profile steel jointly support the cantilever beam module, and in step S12, it is judged whether the setting of the suspended steel bar work frame reaches a predetermined demand.

請配合參考圖22~23的施工示意圖。如圖22所示,樓板20建設完成,於下方空間挖掘至開挖面30。樓板20與開挖面30之間欲設置懸吊式鋼筋工作架10的路線上存在阻隔物(懸臂梁),即虛線繪示處。虛線框示的範圍R表示懸臂梁尚未成型。例如,懸臂梁處於模組階段,架設好模板而尚未綁紮鋼筋與澆置混凝土。此時懸吊式鋼筋工作架10與懸臂梁模組於開挖面上投影重疊。例如,懸吊式鋼筋工作架10一側的螺桿110的延 伸方向上與懸臂梁干涉。於設置螺桿110前,可於懸臂梁模組內對應投影重疊之螺桿的位置設置預留孔42,並將投影重疊之螺桿110穿過預留孔42。接著將型鋼150設置於懸臂梁模組相反於樓板20的一側。如圖22所示,以螺桿110與型鋼150共同支撐懸臂梁模組。於一實施例,可另於型鋼與開挖面之間設置支撐裝置提供額外的支撐。例如於型鋼下方設置鋼管提供支撐,以及於組立於懸臂梁預形成範圍外的模板、角材下方設置鋼管提供支撐。如圖23所示,澆置後形成懸臂梁40。懸吊式鋼筋工作架10對懸臂梁40提供支撐,於懸臂梁澆置之後可繼續朝原來的開挖面下方空間進行挖掘作業。 Please refer to the construction diagrams of Figures 22~23. As shown in Fig. 22, the floor 20 is completed and excavated to the excavation face 30 in the space below. There is a barrier (cantilever beam) on the route between the floor 20 and the excavation face 30 where the suspended steel work frame 10 is to be placed, that is, a dotted line. The range R indicated by the dashed line indicates that the cantilever beam has not been formed. For example, the cantilever beam is in the module stage, the formwork is erected and the reinforcement and the concrete are not yet tied. At this time, the suspension type steel work frame 10 and the cantilever beam module are projected to overlap on the excavation surface. For example, the extension of the screw 110 on one side of the suspended steel work frame 10 Interference with the cantilever beam in the extension direction. Before the screw 110 is disposed, the reserved hole 42 may be disposed in the position of the screw corresponding to the projection overlap in the cantilever beam module, and the screw 110 with the projection overlap is passed through the reserved hole 42. The section 150 is then placed on the side of the cantilever beam module opposite the floor panel 20. As shown in FIG. 22, the cantilever beam module is supported by the screw 110 and the profiled steel 150. In an embodiment, additional support may be provided between the profiled steel and the excavation face to provide additional support. For example, a steel pipe is provided under the profile steel to provide support, and a steel pipe is provided under the angle plate formed outside the preformed range of the cantilever beam to provide support. As shown in Fig. 23, a cantilever beam 40 is formed after being placed. The suspended steel work frame 10 provides support for the cantilever beam 40, and after the cantilever beam is placed, the excavation work can be continued toward the space below the original excavation face.

回到圖21,懸吊式鋼筋工作架設置完成後可進一步利用懸吊式鋼筋工作架進行建築結構體的作業。在步驟S211:於支撐牆體預形成範圍綁紮鋼筋。在步驟S311:澆置混凝土而形成支撐牆體。待下方支撐牆體完成後,在步驟S40:拆除該懸吊式鋼筋工作架。 Returning to Fig. 21, after the suspension type steel work frame is set, the suspended structure work frame can be further used for the work of the building structure. In step S211, the reinforcing bars are tied in the preforming range of the supporting wall. In step S311, concrete is poured to form a support wall. After the lower support wall is completed, in step S40: the suspended steel work frame is removed.

請配合參考圖24~25的施工示意圖。類似地,在結構體預形成範圍的作業可利用上方的樓板配合本發明的懸吊式鋼筋工作架提供支撐。例如,在型鋼一側與下方開挖面(圖未示)之間綁紮鋼筋。如圖24所示,於懸臂梁40與開挖面之間澆置混凝土而形成支撐牆體50。待支撐牆體50成型後將懸吊式鋼筋工作架10拆除回收。如圖25所示,懸臂梁40下方的支撐牆體50完成後,繼續於懸臂梁40上方建築支撐牆體50。 Please refer to the construction diagram of Figure 24-25. Similarly, work in the pre-formed range of the structure can be supported by the upper slab in conjunction with the suspended rebar work frame of the present invention. For example, the reinforcing bars are tied between the side of the profiled steel and the undercut surface (not shown). As shown in Fig. 24, concrete is poured between the cantilever beam 40 and the excavation surface to form the support wall 50. After the wall 50 to be supported is formed, the suspended steel work frame 10 is removed and recovered. As shown in FIG. 25, after the support wall 50 below the cantilever beam 40 is completed, the building support wall 50 continues to be built over the cantilever beam 40.

綜上所述,本發明的懸吊式鋼筋工作架具多個可調整長度、設置位置的設計,提供使用上的彈性。利用本發明的懸吊式鋼筋工作架可在逆打工法中結構體成型之前亦可作為臨時的支撐平台,並且隨結構體完成,可回收懸吊式鋼筋工作架節省成本。此外,本發明的懸吊式鋼筋工作架亦可結合於逆打工法中,像是提供阻隔物成型前的支撐。 In summary, the suspension type steel work frame of the present invention has a plurality of designs with adjustable length and position, and provides flexibility in use. The suspended steel work frame of the present invention can also be used as a temporary support platform before the structural body is formed in the reverse working method, and the suspended steel work frame can be recovered to save costs with the completion of the structure. In addition, the suspended steel work frame of the present invention can also be incorporated into a reverse working method, such as providing support for the barrier prior to molding.

本發明已由上述相關實施例加以描述,然而上述實施例僅為實施本發明之範例。必需指出的是,已揭露之實施例並未限制本發明之範圍。相反地,包含於申請專利範圍之精神及範圍之修改及均等設置均包含於本發明之範圍內。 The present invention has been described by the above-described related embodiments, but the above embodiments are merely examples for implementing the present invention. It must be noted that the disclosed embodiments do not limit the scope of the invention. On the contrary, modifications and equivalents of the spirit and scope of the invention are included in the scope of the invention.

Claims (13)

一種懸吊式鋼筋工作架,吊掛於一樓板,該懸吊式鋼筋工作架包含:至少一螺桿,設置朝遠離該樓板表面延伸,該螺桿具有一第一端及位於該第一端相反側之一第二端;至少一吊件,設置於該樓板,且該吊件係連接該第一端;一型鋼,設置垂直於該螺桿的延伸方向並固定於該第二端;以及一伸縮器,該螺桿包含分離之一第一子桿體與一第二子桿體,該第一子桿體具有一第一調整端且該第二子桿體具有一第二調整端與該第一調整端相向設置,該伸縮器連接該第一子桿體與該第二子桿體,該第一調整端與該第二調整端之間的距離隨該第一子桿體與該第二子桿體沿該些螺桿的延伸方向移動而改變。 A suspended steel work frame suspended from a first floor panel, the suspended steel work frame comprising: at least one screw disposed to extend away from a surface of the floor, the screw having a first end and an opposite side of the first end a second end; at least one hanging member disposed on the floor, and the hanging member is connected to the first end; a profile steel disposed perpendicular to the extending direction of the screw and fixed to the second end; and a retractor The screw includes a first sub-bar body and a second sub-bar body, the first sub-rod body has a first adjustment end and the second sub-rod body has a second adjustment end and the first adjustment The ends are oppositely disposed, the retractor is connected to the first sub-bar body and the second sub-bar body, and the distance between the first adjustment end and the second adjustment end is along with the first sub-bar body and the second sub-bar The body changes along the direction in which the screws extend. 如請求項1所述之懸吊式鋼筋工作架,其中該螺桿係成對設置於該型鋼。 A suspended steel work frame according to claim 1, wherein the screw is disposed in pairs in the steel. 如請求項1所述之懸吊式鋼筋工作架,更包含一螺帽,該型鋼具有一安裝面及一鎖孔形成於該安裝面,該螺桿之該第二端係自該鎖孔貫穿該安裝面,且該螺帽係自該安裝面的相反側鎖附該第二端。 The suspension type steel work frame of claim 1, further comprising a nut having a mounting surface and a locking hole formed on the mounting surface, the second end of the screw penetrating from the locking hole a mounting surface, and the nut locks the second end from an opposite side of the mounting surface. 如請求項3所述之懸吊式鋼筋工作架,其中該型鋼具有一水平延伸方向且具有至少一調整孔形成於該安裝面,該調整孔係沿該水平延伸方向分布於該鎖孔之一側。 The suspended steel work frame of claim 3, wherein the steel has a horizontal extending direction and at least one adjusting hole is formed on the mounting surface, and the adjusting hole is distributed in the horizontal direction of the locking hole. side. 如請求項1所述之懸吊式鋼筋工作架,其中該型鋼為角鋼或槽鋼。 The suspended steel work frame of claim 1, wherein the steel is angle steel or channel steel. 一種地下層施工方法,係於地下層開挖後,於上層之一樓板與該樓板下方之一開挖面之間的施工方法,並使用至少一個如請求項1至5任一項所述之懸吊式鋼筋工作架,其中該螺桿包含分離之一第一子桿體與一第二子桿體,該第一子桿體具有一第一調整端且該第二子桿體具有一第二調整端與該第一調整端相向設置,該地下層施工方法包含下列步驟: 於該樓板吊掛該懸吊式鋼筋工作架;以一伸縮器連接該第一子桿體與該第二子桿體;沿該螺桿的延伸方向移動該第一子桿體與該第二子桿體,以調整該第一調整端與該第二調整端之間的距離;於該些型鋼與該開挖面之間的一預形成範圍綁紮鋼筋;於預形成範圍間澆置混凝土以形成一結構體;以及拆除該懸吊式鋼筋工作架。 A method for constructing a subterranean formation, which is a construction method between one of the upper floors and an excavation surface below the floor after excavation in the underground layer, and using at least one of claims 1 to 5 A suspended steel work frame, wherein the screw comprises a first first sub-bar body and a second sub-rod body, the first sub-rod body has a first adjustment end and the second sub-rod body has a second The adjustment end is disposed opposite to the first adjustment end, and the underground layer construction method comprises the following steps: Suspending the suspended steel work frame on the floor; connecting the first sub-bar body and the second sub-rod body with a retractor; moving the first sub-bar body and the second sub-subject along the extending direction of the screw a rod body for adjusting a distance between the first adjustment end and the second adjustment end; tying the steel bar to a pre-formed range between the steel profiles and the excavation surface; pouring concrete between the preformed ranges to form a structure; and removing the suspended steel work frame. 如請求項6所述之地下層施工方法,該懸吊式鋼筋工作架吊掛步驟更包含:於該樓板設置該吊件;設置該螺桿朝遠離該樓板表面延伸,該螺桿具有第一端及位於該第一端相反側之第二端;將該吊件與該第一端連接;以及設置該型鋼垂直於該螺桿的延伸方向,且固定該型鋼與該第二端。 The method for constructing a subterranean floor according to claim 6, wherein the hanging steel frame hanging step further comprises: providing the hanging member on the floor; the screw is disposed to extend away from the surface of the floor, the screw has a first end and a second end on the opposite side of the first end; connecting the hanger to the first end; and providing the profile perpendicular to the direction of extension of the screw and securing the profiled steel and the second end. 如請求項7所述之地下層施工方法,其中該樓板吊掛有複數個懸吊式鋼筋工作架,型鋼與螺桿固定步驟更包含:將該螺桿成對設置於每一型鋼;以及將每一型鋼彼此並列設置。 The method for constructing a subterranean floor according to claim 7, wherein the floor slab is suspended with a plurality of suspended steel work frames, and the step of fixing the steel and the screw further comprises: arranging the screws in pairs for each steel; and The steel profiles are arranged side by side. 如請求項7所述之地下層施工方法,其中該樓板與該開挖面之間具有一懸臂梁,該懸臂梁與該螺桿於該開挖面上投影重疊,該懸吊式鋼筋工作架吊掛步驟更包含:於該懸臂梁對應投影重疊之該螺桿的位置設置一預留孔;將投影重疊之該螺桿穿過該預留孔;將該型鋼設置於該懸臂梁相反於該樓板的一側;以及 以該螺桿與該型鋼共同支撐該懸臂梁。 The method of claim 7, wherein the slab has a cantilever beam between the slab and the excavation surface, and the cantilever beam and the screw overlap on the excavation surface, the suspended steel frame hoist The step of hanging further comprises: providing a reserved hole at a position of the screw corresponding to the projected overlap of the cantilever beam; passing the screw that projects the overlap through the reserved hole; and setting the profiled steel on the cantilever beam opposite to the floor plate Side; The cantilever beam is supported by the screw and the steel. 如請求項9所述之地下層施工方法,該結構體形成步驟更包含:於該懸臂梁與該開挖面之間澆置混凝土而形成一支撐牆體。 The method for forming a subterranean formation according to claim 9, wherein the step of forming the structure further comprises: pouring concrete between the cantilever beam and the excavation face to form a support wall. 如請求項7所述之地下層施工方法,其中該型鋼具有一安裝面,型鋼與螺桿固定步驟更包含:於該安裝面形成一鎖孔;將該螺桿之該第二端自該鎖孔貫穿該安裝面;以一螺帽自該安裝面的相反側鎖附該第二端。 The method for constructing a subterranean floor according to claim 7, wherein the steel has a mounting surface, and the step of fixing the steel and the screw further comprises: forming a locking hole on the mounting surface; the second end of the screw is penetrated from the locking hole The mounting surface; the second end is locked by a nut from an opposite side of the mounting surface. 如請求項11所述之地下層施工方法,其中該型鋼具有一水平延伸方向,型鋼與螺桿固定步驟更包含:於該安裝面形成至少一調整孔,該調整孔係沿該水平延伸方向分布於該鎖孔之一側。 The method for constructing a subterranean layer according to claim 11, wherein the steel has a horizontal extending direction, and the step of fixing the steel and the screw further comprises: forming at least one adjusting hole on the mounting surface, the adjusting hole being distributed along the horizontal extending direction One side of the keyhole. 如請求項6所述之地下層施工方法,該結構體形成步驟更包含:於該型鋼上設置複數上層筋;於該些上層筋及該開挖面之間設置複數箍筋;於該些箍筋接近該開挖面之一側設置複數下層筋;於該些箍筋接近該些下層筋之一側設置複數版筋;於該些版筋與該開挖面之間澆置混凝土而形成基礎版;以及於該上層筋下方之一預設高度至該基礎版之間澆置混凝土而形成地梁。 The method for forming a subterranean layer according to claim 6, wherein the step of forming the structure further comprises: providing a plurality of upper ribs on the steel; and providing a plurality of stirrups between the upper ribs and the excavation surface; a plurality of lower ribs are disposed on a side of the rib near the excavation surface; a plurality of ribs are disposed on a side of the ribs adjacent to the lower ribs; and a concrete is poured between the ribs and the excavation surface to form a foundation And forming a ground beam by pouring concrete between a predetermined height below the upper rib to the base plate.
TW105138959A 2016-11-25 2016-11-25 Suspension reinforcement working stand and construction method utilized thereof TWI632274B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW105138959A TWI632274B (en) 2016-11-25 2016-11-25 Suspension reinforcement working stand and construction method utilized thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW105138959A TWI632274B (en) 2016-11-25 2016-11-25 Suspension reinforcement working stand and construction method utilized thereof

Publications (2)

Publication Number Publication Date
TW201819738A TW201819738A (en) 2018-06-01
TWI632274B true TWI632274B (en) 2018-08-11

Family

ID=63258320

Family Applications (1)

Application Number Title Priority Date Filing Date
TW105138959A TWI632274B (en) 2016-11-25 2016-11-25 Suspension reinforcement working stand and construction method utilized thereof

Country Status (1)

Country Link
TW (1) TWI632274B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI741347B (en) * 2019-08-12 2021-10-01 林添福 Reverse construction method with upside down support and non-dismantling formwork system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758343A (en) * 2014-01-26 2014-04-30 中铁建工集团有限公司 Hanging type construction method and hanging device for reinforced concrete floor
US20140360814A1 (en) * 2011-10-20 2014-12-11 Giuseppe Panseri Equipment and method for demolishing a building
TWI478852B (en) * 2012-11-30 2015-04-01 Innolux Corp Aseismatic structure of suspension system equipment
CN205024709U (en) * 2015-09-30 2016-02-10 安徽马钢工程技术集团有限公司 Buried bolt's device is in advance suspended in midair on basis
CN104141383B (en) * 2014-07-16 2016-06-01 北京万兴建筑集团有限公司 A kind of Bailey beam pendent form support system and construction thereof
CN205502551U (en) * 2016-03-15 2016-08-24 中国建筑第六工程局有限公司 Platform is suspended in midair in high altitude large -span vestibule construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140360814A1 (en) * 2011-10-20 2014-12-11 Giuseppe Panseri Equipment and method for demolishing a building
TWI478852B (en) * 2012-11-30 2015-04-01 Innolux Corp Aseismatic structure of suspension system equipment
CN103758343A (en) * 2014-01-26 2014-04-30 中铁建工集团有限公司 Hanging type construction method and hanging device for reinforced concrete floor
CN104141383B (en) * 2014-07-16 2016-06-01 北京万兴建筑集团有限公司 A kind of Bailey beam pendent form support system and construction thereof
CN205024709U (en) * 2015-09-30 2016-02-10 安徽马钢工程技术集团有限公司 Buried bolt's device is in advance suspended in midair on basis
CN205502551U (en) * 2016-03-15 2016-08-24 中国建筑第六工程局有限公司 Platform is suspended in midair in high altitude large -span vestibule construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI741347B (en) * 2019-08-12 2021-10-01 林添福 Reverse construction method with upside down support and non-dismantling formwork system

Also Published As

Publication number Publication date
TW201819738A (en) 2018-06-01

Similar Documents

Publication Publication Date Title
US20060260238A1 (en) Refinement to the construction systems for structures in reinforced concrete or some other material of high-precision intergral modular forms
KR100893765B1 (en) Supporting structure of slab form
KR101668521B1 (en) A construction method of concrete
TWI632274B (en) Suspension reinforcement working stand and construction method utilized thereof
KR20200092593A (en) Concrete slab of bridge with precast cantilever slab and concrete slab of bridge construction method therefor
JP4516585B2 (en) Internal staircase for building and its construction method
KR102089758B1 (en) Formwork structure supported by column unit
JP6055212B2 (en) Reinforced earth wall construction method
KR20200107332A (en) The Simultaneous Construction Method for Wall and Slab of Building
JP4204603B2 (en) Construction method of concrete structure
EP1726728B1 (en) Method of erecting a partition wall integrated with a concrete floor
KR101992928B1 (en) Retaining wall buttress c0nstruction method witt front pannel re-bar and retaining wall therewith
RU2043470C1 (en) Method for erecting monolithic elements of a building, preferentially floor, and concrete form to implement it
JPH1129910A (en) Method for constructing concrete pier
KR20180131058A (en) Spacing masonry type Brick wall and construction method thereof
KR100612662B1 (en) Steel-frame assembly body production method of ferroconcrete infrastructure
JP2007217871A (en) Dry foundation and its construction method
JP2006226106A5 (en)
RU2415231C2 (en) Method to erect building from finished elements
JP6418870B2 (en) How to build an elevator pit
KR102121363B1 (en) Functional supporter and constructing method for a protrusion of construction structure using the same, and the construction structure constructed by the method
KR200342812Y1 (en) Hanging type formwork for non-supporting formwork system for top down construction
JP4872301B2 (en) Construction method of RC structure
JP7064898B2 (en) How to build a liquid barrier
KR20090022451A (en) The underground wall body gang form and will reach and construction method of the underground wall body which it uses