JP4872301B2 - Construction method of RC structure - Google Patents

Construction method of RC structure Download PDF

Info

Publication number
JP4872301B2
JP4872301B2 JP2005294613A JP2005294613A JP4872301B2 JP 4872301 B2 JP4872301 B2 JP 4872301B2 JP 2005294613 A JP2005294613 A JP 2005294613A JP 2005294613 A JP2005294613 A JP 2005294613A JP 4872301 B2 JP4872301 B2 JP 4872301B2
Authority
JP
Japan
Prior art keywords
wall
formwork
concrete
column
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2005294613A
Other languages
Japanese (ja)
Other versions
JP2007100461A (en
Inventor
弘幸 大穂
直樹 杉村
豊吉 冨川
久雄 田中
巌 鶴谷
一郎 藤原
剛典 柴田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2005294613A priority Critical patent/JP4872301B2/en
Publication of JP2007100461A publication Critical patent/JP2007100461A/en
Application granted granted Critical
Publication of JP4872301B2 publication Critical patent/JP4872301B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

本発明はRC構造体の構築工法に関し、特に倉庫などのような階高の高いRC構造物の施工に適用される。   The present invention relates to a construction method for an RC structure, and is particularly applied to construction of an RC structure having a high floor such as a warehouse.

一般にRC構造物の柱、梁、外壁などの構造体の施工は、作業足場の組み立てから始まって各構造体の鉄筋の配筋、型枠の加工と組み立て、さらにコンクリートの打設、養生の順に行われ、特に柱と壁の施工は同時に行われる。   In general, the construction of structures such as columns, beams, and outer walls of RC structures begins with the assembly of work scaffolds, the reinforcement of each structure, the processing and assembly of the formwork, the placement of concrete, and the curing In particular, the construction of the columns and walls is done simultaneously.

また、コンクリートの養生後、型枠を解体撤去して構造体の施工が完了したら、各構造体に対して外装工事が行われ、一連の工事が完了した後、作業足場が解体して撤去される。
特開平5−79092号公報 特開平5−106276号公報
In addition, after the concrete is cured, the formwork is dismantled and the construction of the structure is completed.Exterior construction is then performed on each structure, and after a series of construction is completed, the work scaffold is dismantled and removed. The
JP-A-5-79092 JP-A-5-106276

しかし、倉庫などのような特に階高の高い建物の施工に際しては、作業足場の組み立て、各構造体の鉄筋の配筋、さらに型枠の組み立て等、多くの作業が高所作業となり、特に型枠と作業足場には多くの仮設材が使用されているため、その組み立てと解体作業は非常に危険を伴うものである。   However, when constructing a building with a particularly high floor, such as a warehouse, many tasks such as assembly of work scaffolds, rebar reinforcement for each structure, and assembly of formwork are performed at high places. Since many temporary materials are used for the frame and work platform, the assembly and disassembly work is very dangerous.

また、コンクリートの打設に際しても、高所からの打設を強いられるため、鉄筋のかぶり厚を確実に確保できないことがあり、またコンクリートの分離、コールドジョイント、ジャンカ、さらにはひび割れ等が発生して品質の低下を招きやすい等の課題があった。   Also, when placing concrete, it is forced to cast from a high place, so the cover thickness of the reinforcing bars may not be ensured reliably, and concrete separation, cold joints, jumpers, and cracks may occur. As a result, there is a problem that the quality is likely to deteriorate.

さらに、都心のように限られた敷地内に敷地一杯に建設される建物にあっては、周囲の建物が障害になって外装工事が非常に困難になる等の課題もあった。   Furthermore, in a building that is built on a limited site such as the center of the city, there are problems such as the surrounding buildings being obstructed and the exterior work becoming very difficult.

本発明は、以上の課題を解決するためになされたもので、特に倉庫などのような階高の高い建物を効率的に、低コストでかつ安全に構築できるRC構造体の構築工法を提供することを目的とする。   The present invention has been made to solve the above problems, and provides a construction method of an RC structure capable of constructing a high-floor building such as a warehouse efficiently, inexpensively and safely. For the purpose.

請求項1記載のRC構体の構築工法は、柱を先行施工した後、当該柱間の外壁、前記柱および外壁の直上に位置する梁および床スラブを施工するRC構造体の構築工法において、前記柱の柱筋を配筋し、当該柱筋の周囲に柱型枠を設置し、当該柱型枠のうち屋外側の柱型枠にハーフプレキャストコンクリート版からなる柱型枠を設置し、当該柱型枠内にコンクリートを打設して前記柱を構築し、次に当該柱間に仮設梁を架け渡し、前記外壁の壁筋を配筋し、当該壁筋の屋外側と屋内側に壁型枠を設置し、当該壁型枠のうち屋外側の壁型枠にハーフプレキャストコンクリート版からなる壁型枠を設置し、当該壁型枠内にコンクリートを打設して前記外壁を構築し、次に前記仮設梁の上に前記梁および床スラブの型枠を設置し、当該型枠内に梁筋とスラブ筋を配筋し、かつコンクリートを打設して前記梁と床スラブを構築することを特徴とするものである。 Construction method of RC structure of claim 1, wherein, after prior construction pillars, exterior wall between the pillars, in the construction method of the pillars and RC structures of applying the beam and the floor slab directly above the outer wall, the Arrange the column reinforcement of the column, install the column form around the column reinforcement, install the column form frame made of half precast concrete plate on the column form on the outdoor side of the column form frame, and Concrete is placed in the formwork to construct the pillars, then temporary beams are bridged between the pillars, the wall bars of the outer wall are arranged, and the wall molds are placed on the outdoor side and indoor side of the wall bars. Install a frame, install a wall mold made of half-precast concrete plate on the wall mold on the outdoor side of the wall mold , and place the concrete in the wall mold to construct the outer wall. The above-mentioned beam and floor slab formwork are installed on the temporary beam, The slab muscle was Haisuji, and is characterized in that to construct the beam and the floor slab by Da設concrete.

本発明は、特に外柱と外壁の屋外側の外型枠としてハーフプレキャストコンクリート(以下「PCF」という)版を用い、少なくとも当該外柱と外壁の屋外側の型枠と当該型枠を設置するための外部足場を省略して、階高の高いRC構造体の施工の効率化と省力化、さらに安全施工を可能にしたものである。   In particular, the present invention uses a half precast concrete (hereinafter referred to as “PCF”) plate as the outer formwork of the outer pillar and the outer wall on the outdoor side, and at least the outer pillar and the outer formwork of the outer wall and the formwork are installed. This eliminates the external scaffold for the purpose of making the RC structure with high floor height more efficient and labor-saving, and also enables safe construction.

ここで用いるPCF版は、プレキャストコンクリート版の内側に版全体にわたって複数の鉄筋(いわゆる「オムニヤ筋」)が所定間隔おきに突設され、後から打設されるコンクリートと一体のRC合成体を形成するコンクリート版である。仮設梁は、壁筋、壁型枠の外型枠、さらに直上階の梁と床スラブを構築するための型枠などを受ける支保工として利用するもので、H形鋼などの形鋼材を用いることができる。   The PCF plate used here has a plurality of reinforcing bars (so-called “Omni bars”) protruding from the inside of the precast concrete plate at predetermined intervals to form an RC composite that is integrated with the concrete to be placed later. It is a concrete plate to do. Temporary beams are used as support works to receive wall reinforcement, outer formwork of wall formwork, and formwork for building beams and floor slabs on the upper floor, and use shape steel materials such as H-section steel. be able to.

また、仮設梁は工事の進行に伴って上階に移動して(盛り変えて)使用することができ、工事完了後は撤去することができる。なお、柱を構築した後、当該柱間に外壁より先に本設の梁を施工し、当該梁を仮設梁として利用することもできる。   Temporary beams can be moved to the upper floor as the construction progresses (changed) and can be removed after the construction is completed. In addition, after constructing a pillar, it is also possible to construct a permanent beam before the outer wall between the columns and use the beam as a temporary beam.

請求項2記載のRC構体の構築工法は、請求項1記載のRC構体の構築工法において、壁筋の屋内側に壁型枠の屋内側を構成する内型枠を設置し、当該内型枠と外型枠との間にコンクリートを打設して外壁の下半分を構築し、次に当該内型枠を上方に移動し、当該内型枠と前記外型枠との間にコンクリートを打ち継いで前記外壁の上半分を構築することを特徴とするものである。 The construction method for an RC structure according to claim 2 is the construction method for an RC structure according to claim 1, wherein an inner form that constitutes the indoor side of the wall form is installed on the indoor side of the wall line, and the inner form and then Da設concrete between the outer molds to construct the lower half of the outer wall, then moves the inner die frame upward, out of the concrete between the inner formwork and the outer formwork The upper half of the outer wall is constructed as a joint.

本発明は、外壁の施工に際し、コンクリートを複数回に分けて打ち継いで外壁全体のコンクリートを打設することにより、高所作業に伴うコンクリートの分離、コールドジョイント、ジャンカの発生を未然に防止し、コンクリートの品質の向上を図ることができる。   The present invention prevents the occurrence of concrete separation, cold joints, and jumpers due to work at a high place by placing concrete in multiple times in the construction of the outer wall and casting the concrete over the entire outer wall. The quality of concrete can be improved.

請求項3記載のRC構造体の構築工法は、請求項1または2記載のRC構造体の構築工法において、PCF版に仕上げ材が施してあることを特徴とするものである。   A construction method for an RC structure according to claim 3 is the construction method for an RC structure according to claim 1 or 2, wherein a finishing material is applied to the PCF plate.

本発明は、特に敷地一杯に建物が構築され、周囲の建物が障害となって外装工事ができないような場合に適しており、この場合の仕上げとしては、例えばタイル、塗装、吹き付け等があり、特に限定されるものではない。   The present invention is particularly suitable for a case where a building is constructed over the entire site, and the surrounding buildings are obstructed and exterior construction cannot be performed. In this case, for example, tiles, painting, spraying, etc. It is not particularly limited.

本発明は、特に外柱と外壁の屋外側の外型枠としてPCF版を用いることにより、少なくとも当該外柱と外壁の屋外側の型枠と当該型枠を設置するための外部足場を省略できるため、階高の高いRC構造体の施工の効率化と省力化、さらに安全施工が可能である。   In particular, the present invention can omit at least the outer pillar and the outdoor formwork of the outer wall and the external scaffold for installing the formwork by using the PCF plate as the outer formwork of the outer pillar and the outer wall on the outdoor side. Therefore, it is possible to improve the efficiency and labor saving of the construction of the RC structure with a high floor, and to perform safe construction.

また、PCF版は外柱および外壁の構造体の一部となるため、所定のかぶり厚を確実に確保することができる。さらに、PCF版には予め仕上げ材を施すことにより、敷地一杯に構築され、周囲の建物が障害となって外装工事ができないような場合でも特に問題になることはない。   In addition, since the PCF plate becomes a part of the structure of the outer column and the outer wall, a predetermined cover thickness can be reliably ensured. Furthermore, the PCF plate is preliminarily provided with a finishing material, so that the entire site is constructed, and there is no particular problem even if the surrounding building is obstructed and exterior construction cannot be performed.

図1〜図12は、本発明のRC構造体の構築工法の一例を示し、以下その施工手順について説明する。   FIGS. 1-12 shows an example of the construction method of the RC structure of this invention, and the construction procedure is demonstrated below.

最初に、柱筋1を地組みする(図1参照)。柱筋1は複数の主筋1aとフープ筋(またはスパイラル筋)1bを、構築される柱の断面形状に合わせて矩形または円形のかご状に組み立てる。またその際、柱の側方に突出して後述する壁筋との継手となる差筋1c,1cを配筋し、またコンクリート打ち継ぎ部のラス(図省略)、コンクリート打設用の管(例えばスパイラル管(図省略))なども組み込む。   First, the column 1 is grounded (see FIG. 1). The column reinforcement 1 assembles a plurality of main reinforcements 1a and hoop reinforcements (or spiral reinforcements) 1b into a rectangular or circular cage shape according to the cross-sectional shape of the pillar to be constructed. Further, at that time, differential bars 1c and 1c that project to the side of the column and serve as joints with the wall bars described later are arranged, laths (not shown) of the concrete joints, and pipes for placing concrete (for example, Incorporate spiral tubes (not shown).

次に、地組みした柱筋1を予め墨出しした位置に建て込む。柱筋1を基礎の上に建て込むときは、各主筋1aの下端部を予め基礎の上に突設したアンカー筋と結合し、また先に建て込んだ直下階の柱筋の上に重ねて建て込むときは、各主筋1aの下端部を先に建て込んだ柱筋1の各主筋1aと結合して自立させる。   Next, the built-up column 1 is built in a position where ink is drawn in advance. When building the column reinforcement 1 on the foundation, the lower end of each main reinforcement 1a is combined with the anchor reinforcement projecting on the foundation in advance and superimposed on the column reinforcement on the floor immediately below. When erected, the lower ends of the main bars 1a are combined with the main bars 1a of the column bars 1 that have been built first to be independent.

次に、柱筋1の周囲に柱型枠2を設置する(図2参照)。その際、柱筋1の屋外側には、特にPCF版からなる外型枠2aを建て込む。また、外型枠2aと対峙する内側(屋内側)とその両側の三方に内型枠2bを設置する。   Next, a column mold 2 is installed around the column 1 (see FIG. 2). At that time, an outer mold 2a made of a PCF plate is installed on the outdoor side of the pillar 1. Further, the inner mold 2b is installed on the inner side (indoor side) facing the outer mold 2a and on three sides thereof.

ここで、外型枠2aとして用いられるPCF版は、当該PCF版の内側に版全体にわたって複数の鉄筋(いわゆる「オムニヤ筋」)が所定間隔おきに突設され、後から打設されるコンクリートと一体の合成体を形成するコンクリート版であり、また、当該外形枠2aは階高とほぼ同等の高さを有し、また柱筋1の径(横幅)より幅広に形成され、両サイドが柱筋1の差筋1cに添って柱筋1の側方に伸びて、後述する外壁の外型枠の一部になっている。   Here, the PCF plate used as the outer mold 2a is a concrete in which a plurality of reinforcing bars (so-called “omni bars”) are projected at predetermined intervals on the inside of the PCF plate, and are placed later. It is a concrete slab that forms an integral composite, and the outer frame 2a has a height substantially equal to the floor height, is wider than the diameter (lateral width) of the column 1 and both sides are pillars. It extends to the side of the columnar bar 1 along the differential bar 1c of the bar 1 and forms a part of the outer form of the outer wall described later.

また、外型枠2aの下端部にレベル調整ボルト(図省略)が取り付けられ、さらに下端部と両縁端部に当該下端部と縁端部を固定するファスナー(図省略)が取り付けられている。   Further, a level adjustment bolt (not shown) is attached to the lower end of the outer mold 2a, and a fastener (not shown) for fixing the lower end and the edge is attached to the lower end and both edge ends. .

このように形成された外型枠2aを基礎の上に建て込むときは、予め墨出しを行って建て込む位置を決め、また建て込んだ後下端部をファスナーによって基礎の上に固定する。また、外型枠2aを先に建て込んだ直下階の外型枠の上に重ねて建て込むときは、下端部を先に建て込んだ外型枠の上端部とファスナーによって結合する。   When the outer mold 2a formed in this way is built on the foundation, the position to be built is determined in advance and the lower end portion is fixed on the foundation with a fastener after the construction. When the outer mold 2a is built on the outer floor on the floor immediately below, the lower end of the outer mold 2a is joined to the upper end of the outer mold built in first by a fastener.

また、いずれの場合も、下端部を固定する前にレベル調整ボルトによってレベル調整を行うものとし、また、内側から斜めサポート(図省略)によって鉛直に支持する。   In any case, level adjustment is performed with a level adjustment bolt before the lower end is fixed, and it is supported vertically by an oblique support (not shown) from the inside.

内型枠2bは、従来のコンクリート工事で用いられている、合板などからなる型枠であり、単管パイプ等の端太材からなる支保工により締め付けて固定する。   The inner mold 2b is a mold made of plywood or the like used in conventional concrete work, and is fastened and fixed by a support work made of a thick end material such as a single pipe.

内型枠2aの組み立ては、高所作業車を利用して行うものとし、単管などからなる支保工材で締め付ける。   The inner mold 2a is assembled using an aerial work vehicle and is tightened with a support material made of a single pipe or the like.

次に、こうして組み立てた柱型枠2内にコンクリートを打設する。コンクリートの打設に際しては、柱筋1の中に予め組み込んだコンクリート打設用管を利用することにより、高所作業に伴うコンクリートの分離、コールドジョイント、ジャンカ等の発生を防止し、コンクリートの充填性の向上を図る。   Next, concrete is placed in the column form 2 assembled in this way. When placing concrete, by using a concrete placement pipe that is pre-installed in the column reinforcement 1, concrete separation, cold joints, jumpers, etc. due to work at heights are prevented, and concrete filling is performed. To improve performance.

なお、内型枠2bを少なくとも2回程度に分けて組み立て、上に移動(盛り代え)しながら、コンクリートを打設するようにすれば、高所作業に伴うコンクリートの分離等を防止でき、コンクリートの品質を高めることができる。   In addition, if the concrete is placed while assembling the inner mold 2b at least twice and moving it up (replacement), it will be possible to prevent the separation of the concrete due to the work at the height, Can improve the quality.

次に、柱のコンクリートが充分に硬化したら外型枠2aは残し、内型枠2bを解体して撤去する(図3参照)。これで、RC構造の柱3が構築されたことになる。   Next, when the concrete of the pillar is sufficiently cured, the outer mold 2a is left, and the inner mold 2b is disassembled and removed (see FIG. 3). Thus, the RC structure pillar 3 is constructed.

次に、こうして構築されたRC構造の柱3と柱3との間に仮設梁4を架け渡す(図5参照)。仮設梁4の設置に際しては、柱3の側部に架設梁4を受けるブラケット5を突設し(図4参照)、このブラケット5に仮設梁4の端部をそれぞれボルト接合する。   Next, the temporary beam 4 is bridged between the columns 3 and 3 of the RC structure thus constructed (see FIG. 5). When the temporary beam 4 is installed, a bracket 5 for receiving the installation beam 4 is protruded from the side of the column 3 (see FIG. 4), and the end of the temporary beam 4 is bolted to the bracket 5 respectively.

ブラケット5は、後から構築される本設梁(または床スラブ)のやや下側に取り付けるものとし、また柱筋1を地組する際に柱筋1内に予め組み込んでおいたインサートナット(図省略)を利用し、当該インサートナットに螺合される取付ボルト(図省略)によって取り付ける。   The bracket 5 is attached to a slightly lower side of a main beam (or a floor slab) to be constructed later, and an insert nut (in FIG. Use a mounting bolt (not shown) to be screwed onto the insert nut.

なお、仮設梁4にはH形鋼やI形鋼などの形鋼材を用い、またブラケット5の取り付けと仮設梁4の設置には高所作業車を利用する。   The temporary beam 4 is made of a section steel material such as H-shaped steel or I-shaped steel, and an aerial work vehicle is used for mounting the bracket 5 and installing the temporary beam 4.

次に、壁筋6を地組みする。壁筋6は複数の縦筋と横筋を矩形の格子状に組み立て、必要に応じて二重に組み立てる。壁筋6の縦筋には階高よりやや長めの鉄筋を用い、縦筋の上端部分をその上側に設置される直上階の壁筋との継手部とし、横幅は柱3,3間(柱スパン)の内法幅と略同じとする。また、柱3,3間のスパンが長いために横幅が大き過ぎるときは、必要に応じて複数に分割してもよい。   Next, the wall reinforcement 6 is assembled. The wall bars 6 are constructed by assembling a plurality of vertical bars and horizontal bars into a rectangular lattice shape, and assembling doubly if necessary. Reinforcing bars that are slightly longer than the floor height are used for the vertical bars of the wall bars 6, and the upper end of the vertical bars is the joint part with the wall bars on the upper floor installed on the upper side, and the horizontal width is between columns 3 and 3 (column It is almost the same as the internal width of the span. Moreover, when the width is too large because the span between the columns 3 and 3 is long, it may be divided into a plurality of parts as necessary.

なお、壁筋6の組み立てに際しては、地組ヤードに捨てコンクリートを打ち、その上に後述する外壁の外型枠に取り付けられたファスナー等の付属金物や開口部などの位置を墨出し、これらを避けて配筋作業を行うものとする。   When assembling the wall reinforcement 6, throw away concrete in the ground yard and mark the positions of the attachments such as fasteners and openings attached to the outer formwork of the outer wall, which will be described later, and the openings. Avoid bar arrangements.

次に、こうして地組した壁筋6を、隣接する柱3,3間の予め墨出しした位置に建て込む(図6参照)。壁筋6を基礎の上に建て込むときは、各縦筋の下端部を予め基礎の上に突設したアンカー筋と結合し、また先に建て込んだ直下階の壁筋6の上に重ねて建て込むときは、各縦筋の下端部を先に建て込んだ壁筋の各縦筋の上端部とそれぞれ結合する。   Next, the wall reinforcement 6 thus built is built in a position marked in advance between the adjacent columns 3 and 3 (see FIG. 6). When the wall reinforcement 6 is built on the foundation, the lower end of each vertical reinforcement is connected to the anchor reinforcement projecting on the foundation in advance, and it is overlaid on the wall reinforcement 6 on the floor immediately below. When erected, the lower end of each vertical bar is combined with the upper end of each vertical bar of the wall bar previously built.

また、いずれの場合にも、壁筋6の各横筋の両端部は柱3の側部に突設された差し筋1cと結合する。なお、壁筋6の吊り込みに際しては、吊り込む部分を番線などで適当に補強し、専用の吊り冶具によって吊り込む。   In either case, both end portions of each horizontal bar of the wall bar 6 are coupled to the insertion bar 1 c protruding from the side of the column 3. When the wall bars 6 are hung, the hung portion is appropriately reinforced with a wire or the like and hung with a dedicated hanging jig.

次に、壁筋6の両側に壁型枠7を設置する(図7,8参照)。壁型枠7の組み立てに際しては、屋外側にPCF版からなる外型枠7aを建て込む。また、外型枠7aと対峙する壁筋6の屋内側には内型枠7bを設置する。外型枠7aは、柱型枠2の外型枠2aと同様に階高とほぼ同じ高さに形成されている。また、外型枠7aの下端部にレベル調整ボルト(図省略)が取り付けられ、さらに下端部と両縁端部に当該下端部と縁端部をそれぞれ固定するファスナー(図省略)が取り付けられている。   Next, the wall formwork 7 is installed on both sides of the wall reinforcement 6 (see FIGS. 7 and 8). When the wall mold 7 is assembled, an outer mold 7a made of a PCF plate is built on the outdoor side. Further, the inner mold 7b is installed on the indoor side of the wall reinforcement 6 facing the outer mold 7a. The outer mold frame 7 a is formed at the same height as the floor height, like the outer mold frame 2 a of the column mold 2. Further, a level adjustment bolt (not shown) is attached to the lower end portion of the outer mold 7a, and a fastener (not shown) for fixing the lower end portion and the edge end portion is attached to the lower end portion and both edge ends. Yes.

外型枠7aを基礎の上に建て込むときは、予め墨出しを行って建て込む位置を決め、下端部を基礎の上にファスナーによって固定する。また、先に建て込んだ直下階の外型枠7aの上に重ねて建て込むときは、下端部を先に建て込んだ外型枠7aの上端部とファスナーによって結合する。   When the outer mold 7a is built on the foundation, the position to be built is determined in advance and the lower end is fixed on the foundation with a fastener. Further, when building on the outer floor form 7a on the immediately lower floor built in advance, the lower end part is joined to the upper end part of the outer form frame 7a built in first by a fastener.

また、いずれの場合も、下端部を固定する前にレベル調整ボルトによってレベル調整を行うものとし、また、両側の縁端部を隣接する外型枠7aの縁端部とファスナーによってそれぞれ固定し、さらに上端部を仮設梁4に仮固定し、そして内側に斜めサポート(図省略)を設置して鉛直に支持する。   In either case, the level adjustment bolt is used to adjust the level before fixing the lower end portion, and the edge portions on both sides are fixed with the edge portions of the adjacent outer mold 7a and fasteners, respectively, Further, the upper end is temporarily fixed to the temporary beam 4, and an oblique support (not shown) is installed on the inner side to support it vertically.

内型枠7bは、従来のコンクリート工事で用いられている、合板などからなる型枠であり、単管パイプ等の端太材からなる支保工により締め付けて固定する。   The inner mold 7b is a mold made of plywood or the like used in conventional concrete work, and is fastened and fixed by a supporting work made of a thick end material such as a single pipe.

また、内型枠7bは少なくとも2回程度に分けて組み立て、上に移動(盛り代え)しながら利用する。また、内型枠7bの組み立てと盛り代えは高所作業車を利用して行う。   Further, the inner mold frame 7b is assembled at least twice, and is used while being moved up (replaced). The assembly and replacement of the inner mold 7b are performed using an aerial work vehicle.

そして、第一段目の内型枠7bを設置したら外型枠7aと内型枠7bとの間にコンクリート11を打設し、十分に養生して外壁8の下半分を構築する。そして、コンクリート11が十分に硬化したら内型枠7bを上方に盛り代え(移動し)、残る上半分の外壁を構築する。こうして、先行施工された柱3,3間にRC構造の外壁8が柱3,3と一体的に構築されたことになる。   When the first-stage inner mold 7b is installed, the concrete 11 is placed between the outer mold 7a and the inner mold 7b, and the lower half of the outer wall 8 is constructed by sufficiently curing. When the concrete 11 is sufficiently cured, the inner mold 7b is replaced (moved) upward, and the remaining upper half outer wall is constructed. In this way, the outer wall 8 of the RC structure is constructed integrally with the columns 3 and 3 between the columns 3 and 3 that have been previously constructed.

なお、内型枠7bの盛り代えに際しては、内型枠7bの下端部を一回目のコンクリート11の打設によって構築された躯体の内側に数センチ程度重ねることにより目違いをなくす。   When replacing the inner mold 7b, the lower end of the inner mold 7b is overlapped by about several centimeters on the inner side of the frame constructed by the first placement of the concrete 11, thereby eliminating the mistake.

次に、こうして構築されたRC構造の柱3,3および外壁8の上に、当該柱3と外壁8の上に構築される直上階の梁および床スラブ9を構築する。施工に際しては、まず、仮設梁4を支保工にして梁および床スラブ9の型枠10を設置し(図10参照)、その上に梁筋とスラブ筋を配筋し、かつコンクリート11を打設する。そして、コンクリート11が十分に硬化したら型枠10を解体して撤去する。こうして、直上階の梁と床スラブ9が構築されたことになる。なお、仮設梁4は、梁と床スラブ9が構築された後、これらの型枠10と共に撤去する。   Next, on the columns 3 and 3 and the outer wall 8 of the RC structure thus constructed, the beam and floor slab 9 on the upper floor constructed on the columns 3 and the outer wall 8 are constructed. At the time of construction, first, the formwork 10 of the beam and the floor slab 9 is installed with the temporary beam 4 as a support (see FIG. 10), and the beam and slab reinforcement are arranged thereon, and the concrete 11 is placed. Set up. Then, when the concrete 11 is sufficiently cured, the mold 10 is disassembled and removed. In this way, the beam and floor slab 9 on the upper floor are constructed. The temporary beam 4 is removed together with the formwork 10 after the beam and the floor slab 9 are constructed.

以上の工程でRC構造体の一階分の柱3、外壁8および梁と床スラブ9が構築されたことになる。よって、この工程を上方に繰り返し行うことにより複数階のRC建物の構造体をきわめて効率的にかつ安全に構築することができる。   Through the above steps, the pillar 3, the outer wall 8, the beam and the floor slab 9 for the first floor of the RC structure are constructed. Therefore, by repeating this process upward, a multi-storey RC building structure can be constructed very efficiently and safely.

本発明は、倉庫などのような階高の高いRC構造の建物を構築する際に特に有効であるが、必ずしも階高の高いRC構造物に限定されることなく、階高の低いRC構造物に本発明を適用することも可能である。   The present invention is particularly effective when building a high-rise building with an RC structure such as a warehouse, but is not necessarily limited to an RC structure with a high floor height, and an RC structure with a low floor height. The present invention can also be applied to.

本発明の施工手順を示し、(a)は柱筋を建て込んだ状態の平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is a plan view of a state in which a column is built, and (b) is a front view thereof. 本発明の施工手順を示し、(a)は柱筋の周囲に柱の型枠を設置した状態の平面図、(b)はその正面図、(c)はその側面図である。The construction procedure of this invention is shown, (a) is a plan view of a state in which a column formwork is installed around the column reinforcement, (b) is a front view thereof, and (c) is a side view thereof. 本発明の施工手順を示し、(a)は構築されたRC構造の柱の平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is a top view of the column of the constructed RC structure, (b) is the front view. 本発明の施工手順を示し、(a)は構築された柱の側部にブラケットを突設した状態を示す平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is a plan view showing a state in which a bracket projects from the side of the constructed pillar, and (b) is a front view thereof. 本発明の施工手順を示し、(a)は構築された柱間に仮設梁を架け渡した状態を示す平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is a top view which shows the state which spanned the temporary beam between the constructed | assembled pillars, (b) is the front view. 本発明の施工手順を示し、(a)は構築された柱間に仮設梁を架け渡し、かつ壁筋を配筋した状態を示す平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is a plan view showing a state where temporary beams are bridged between constructed columns and wall bars are arranged, and (b) is a front view thereof. 本発明の施工手順を示し、(a)は構築された柱間に仮設梁を架け渡し、壁筋を配筋し、かつ屋外側にPCF版からなる外型枠を設置した状態を示す平面図、(b)はその正面図、(c)はその側面図である。The construction procedure of the present invention is shown, (a) is a plan view showing a state in which a temporary beam is bridged between constructed columns, wall bars are laid out, and an external form made of a PCF plate is installed on the outdoor side. (B) is the front view, (c) is the side view. 本発明の施工手順を示し、(a)は構築された柱間に仮設梁を架け渡し、壁筋を配筋し、かつ屋外側にPCF版からなる外型枠を、屋内側に一段目の内型枠を設置した状態を示す平面図、(b)はその正面図、(c)はその側面図である。The construction procedure of this invention is shown, (a) lays a temporary beam between the constructed pillars, arranges the wall bars, and forms the external formwork made of PCF plates on the outdoor side, and the first stage on the indoor side. The top view which shows the state which installed the inner formwork, (b) is the front view, (c) is the side view. 本発明の施工手順を示し、(a)は図8において外型枠と内型枠との間に第一段目のコンクリートを打設した状態を示す平面図、(b)はその正面図、(c)はその側面図である。The construction procedure of the present invention is shown, (a) is a plan view showing a state in which the first-stage concrete is placed between the outer mold frame and the inner mold frame in FIG. 8, (b) is a front view thereof, (c) is the side view. 本発明の施工手順を示し、(a)は構築されたRC構造の柱と外壁の上側に梁と床スラブを構築するための型枠を設置した状態を示す平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is the top view which shows the state which installed the formwork for constructing a beam and a floor slab on the upper side of the pillar and outer wall of the constructed RC structure, (b) is the front FIG. 本発明の施工手順を示し、(a)は仮設梁を撤去し、一体的に構築されたRC構造の柱と外壁を示す平面図、(b)はその正面図である。The construction procedure of this invention is shown, (a) is the top view which shows the pillar and outer wall of RC structure which removed the temporary beam and was constructed integrally, (b) is the front view. 図10(b)におけるイ−イ腺断面図である。FIG. 11 is a cross-sectional view of the ii gland in FIG.

符号の説明Explanation of symbols

1 柱筋
1a 主筋
1b フープ筋
1c 差し筋
2 柱型枠
2a 外型枠
2b 内型枠
3 RC構造の柱
4 仮設梁
5 ブラケット
6 壁筋
7 壁型枠
7a 外型枠
7b 内型枠
8 RC構造の壁
9 RC構造の梁および床スラブ
10 梁および床スラブの型枠
11 コンクリート
DESCRIPTION OF SYMBOLS 1 Column reinforcement 1a Main reinforcement 1b Hoop reinforcement 1c Insertion 2 Column formwork 2a Outer formwork 2b Inner formwork 3 RC structure pillar 4 Temporary beam 5 Bracket 6 Wall reinforcement 7 Wall formwork 7a Outer formwork 7b Inner formwork 8 RC Structural walls 9 RC structure beams and floor slabs 10 Beam and floor slab forms 11 Concrete

Claims (3)

柱を先行施工した後、当該柱間の外壁、前記柱および外壁の直上に位置する梁および床スラブを施工するRC構造体の構築工法において、前記柱の柱筋を配筋し、当該柱筋の周囲に柱型枠を設置し、当該柱型枠のうち屋外側の柱型枠にハーフプレキャストコンクリート版からなる柱型枠を設置し、当該柱型枠内にコンクリートを打設して前記柱を構築し、次に当該柱間に仮設梁を架け渡し、前記外壁の壁筋を配筋し、当該壁筋の屋外側と屋内側に壁型枠を設置し、当該壁型枠のうち屋外側の壁型枠にハーフプレキャストコンクリート版からなる壁型枠を設置し、当該壁型枠内にコンクリートを打設して前記外壁を構築し、次に前記仮設梁の上に前記梁および床スラブの型枠を設置し、当該型枠内に梁筋とスラブ筋を配筋し、かつコンクリートを打設して前記梁と床スラブを構築することを特徴とするRC構造体の構築工法。   In the construction method of the RC structure for constructing the outer wall between the columns, the beam located immediately above the columns and the floor slab, and the floor slab after the columns are preliminarily constructed, the column bars of the columns are arranged, A column formwork is installed around the column, and a column formwork made of a half precast concrete plate is installed on the columnar form on the outdoor side of the column formwork. Next, the temporary beam is bridged between the pillars, the wall bars of the outer wall are laid out, and the wall formwork is installed on the outdoor side and the indoor side of the wall line. A wall formwork made of a half precast concrete plate is installed on the outer wall formwork, concrete is placed in the wall formwork to construct the outer wall, and then the beam and floor slab are placed on the temporary beam. The formwork is installed, the beam and slab bars are placed in the formwork, and the concrete is placed. Construction Method of the RC structure, characterized by constructing the beam and the floor slab by pouring. 壁筋の屋内側に壁型枠の屋内側を構成する内型枠を設置し、当該内型枠と外型枠との間にコンクリートを打設して外壁の下半分を構築し、次に当該内型枠を上方に移動し、当該内型枠と前記外型枠との間にコンクリートを打ち継いで前記外壁の上半分を構築することを特徴とする請求項1記載のRC構造体の構築工法。 Install the inner formwork that constitutes the indoor side of the wall formwork on the indoor side of the wall reinforcement, and place concrete between the inner formwork and the outer formwork to construct the lower half of the outer wall, 2. The RC structure according to claim 1, wherein the upper half of the outer wall is constructed by moving the inner mold upward and passing over concrete between the inner mold and the outer mold. 3. Construction method. ハーフプレキャストコンクリート版に仕上げ材が施してあることを特徴とする請求項1または2記載のRC構造体の構築工法。   The construction method for an RC structure according to claim 1 or 2, wherein a finishing material is applied to the half precast concrete plate.
JP2005294613A 2005-10-07 2005-10-07 Construction method of RC structure Expired - Fee Related JP4872301B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005294613A JP4872301B2 (en) 2005-10-07 2005-10-07 Construction method of RC structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005294613A JP4872301B2 (en) 2005-10-07 2005-10-07 Construction method of RC structure

Publications (2)

Publication Number Publication Date
JP2007100461A JP2007100461A (en) 2007-04-19
JP4872301B2 true JP4872301B2 (en) 2012-02-08

Family

ID=38027662

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005294613A Expired - Fee Related JP4872301B2 (en) 2005-10-07 2005-10-07 Construction method of RC structure

Country Status (1)

Country Link
JP (1) JP4872301B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395766B (en) * 2020-04-22 2023-09-19 五冶集团上海有限公司 Method for simultaneously pouring and constructing column, beam and floor slab in high-temperature environment

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5312113A (en) * 1976-07-19 1978-02-03 Nippon Telegraph & Telephone Method of construction of rahmen structure
JPS6268946A (en) * 1985-09-24 1987-03-30 株式会社フジタ Beam construction method
JP3180246B2 (en) * 1997-07-16 2001-06-25 鹿島建設株式会社 Construction method and construction member for reinforced concrete structure
JP3948544B2 (en) * 1998-06-25 2007-07-25 株式会社フジタ Construction method of non-bearing walls of buildings using precast concrete panels

Also Published As

Publication number Publication date
JP2007100461A (en) 2007-04-19

Similar Documents

Publication Publication Date Title
US11814835B2 (en) Methods and apparatus for constructing multi-storey buildings
KR20130113315A (en) A building structure
KR20120096605A (en) Bracket support type downward construction system and method
JP5405337B2 (en) Construction method of railway RC ramen structure viaduct
JPH1030212A (en) Reinforced concrete structure and its construction method
JPH10266602A (en) Method for constructing building of plant, and module structure to be used for construction thereof
JP2010261270A (en) Composite structure and method for constructing composite structure building
KR100775359B1 (en) Concrete-mold assembly and construction method using the same
KR102269141B1 (en) Deck plate wall installation method using underground pavement
JP4872301B2 (en) Construction method of RC structure
KR100676193B1 (en) Steel-frame stair structure
JPH1129910A (en) Method for constructing concrete pier
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JPH0657710A (en) Construction of concrete main tower
JP2001311247A (en) Construction method for concrete structure
JPH1136229A (en) Construction method for reinforced concrete bridge pier
JPH08100464A (en) Joint structure and work execution method for structure using it
JP7389634B2 (en) Building construction method
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JP2578671B2 (en) Column and beam construction method
JPH0988348A (en) Method for constructing foundation beam
JP2008150820A (en) Wall concrete, and manufacturing method and construction method therefor
JP2972956B2 (en) Column and beam joining method and its structure
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JP2023175116A (en) Installation method of metal lath

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080703

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101130

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101220

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110426

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110513

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111025

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111107

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141202

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees