SU1097795A1 - Method of working steep coal seam by hydraulic excavation - Google Patents

Method of working steep coal seam by hydraulic excavation Download PDF

Info

Publication number
SU1097795A1
SU1097795A1 SU813296669A SU3296669A SU1097795A1 SU 1097795 A1 SU1097795 A1 SU 1097795A1 SU 813296669 A SU813296669 A SU 813296669A SU 3296669 A SU3296669 A SU 3296669A SU 1097795 A1 SU1097795 A1 SU 1097795A1
Authority
SU
USSR - Soviet Union
Prior art keywords
layer
floor
procedure
artificial
completed
Prior art date
Application number
SU813296669A
Other languages
Russian (ru)
Inventor
Всеволод Васильевич Журавлев
Борис Яковлевич Экбер
Мирон Никанорович Маркус
Original Assignee
Ордена Октябрьской Революции И Ордена Трудового Красного Знамени Институт Горного Дела Им.А.А.Скочинского
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ордена Октябрьской Революции И Ордена Трудового Красного Знамени Институт Горного Дела Им.А.А.Скочинского filed Critical Ордена Октябрьской Революции И Ордена Трудового Красного Знамени Институт Горного Дела Им.А.А.Скочинского
Priority to SU813296669A priority Critical patent/SU1097795A1/en
Application granted granted Critical
Publication of SU1097795A1 publication Critical patent/SU1097795A1/en

Links

Abstract

СПОСОБ РАЗРАБОТКИ КРУТЫХ , УГОЛЬНЫХ ПЛАСТОВ ПРИ ЩЦРОДОБЫЧЕ, включающий проведение подэтажных выработок и базисных бремсбергов, последовательную отработку подэтажей сверху вниз с гидроотбойкой в забое и возведение искусственных целиков в каждом подэтаже путем подачи твердеющего материала в вьфаботанное пространство с вышерасположенной подэтажной выработки, о т л и ч а ющ и и с   тем, что, с целью повышени  безопасности работ и снижени  потерь угл  за счет обеспечени  изол ции технологического процесса гидроотбойки в забое от одновременно осуществл емого технологического процесса возведени  искусственного целика, каждый последующий подэтаж отрабатывают под защитой с одной стороны искусственного целика, возведенного на вьпперасположенном подэтаже на всем его прот жении, и с другой стороны - щита-опалубки и 3 искусственного целика, возводимого в обрабатываемом подэтаже путем монтажа в каждом подэтаже щита-опалубки , передвижки ее вслед за забоем и подачи за щит-опалубку твердеющего материала, причем в процессе возведени  искусственного целика в нем оставл ют сквозную полость, сообщающуюс  с базисным бремсбергом. . ч vl елTHE METHOD OF DEVELOPING TIGHT, COAL STRAYS UNDER SHCHTRODODYBYCHE, which includes carrying out subsurface workings and basic brambergs, successively working the sublevels from top to bottom with hydrotreatment in the bottomhole and erecting artificial pillars in each sub-floor by drawing a layer of hardening material in a pattern, and I completed a single layer of a layer of a layer of a layer of a layer of a layer of a layer of a layer, laid out the surface of the layer and laid erection in the subfloor by drawing the hardening material into the surface and struck the surface and struck the body and struck the surface and struck the body and created the surface and completed the procedure and completed the procedure and completed the procedure and completed the procedure and completed the procedure by completing the procedure and creating the same procedure. and with the fact that, in order to increase the safety of work and reduce coal losses by providing isolation of the hydrotreatment process in the bottomhole from one At the temporarily carried out technological process of erection of an artificial pillar, each subsequent basement is worked out under protection from one side of the artificial pillar erected on the upper substage along its entire stretch, and on the other hand to a formwork shield and 3 artificial pillars erected in the sub-floor being processed by mounting in each substage of the formwork shield, moving it after the slaughter and filing hardening material for the formwork shield, while in the process of erecting an artificial pillar in it is dissolved through cavity communicating with the base apex. . h vl ate

Description

Изобретение относитс  к горной промышленности и предназначено дл  разработки крутых угольных пластов с помощью гидромеханизации и с закл кой выработанного пространства. Известен способ разработки круты угольньгх пластов при гидродобыче, включающий проведение подэтажных го ных вьфаботок из базисных бремсберг и гидроотбойку угл  в подэтажах 1 Недостатками такого способа  вл ютс  значительные потери и разубоживание угл  из-за пересьшани  обрушенных боковых пород в зону гидроотбойки угл , сложна  схема проветривани  забо . Известен способ разработки круты угольных пластов при гидродобыче, включающий проведение подэтажных вы работок и базисных бремсбергов, последовательную отработку подэтаже сверху вниз с гидроотбойкой в забое и возведение искусственных целиков каждом подэтаже путем подачи твердеющего материала в выработанное пространство с вышерасположенной подэтажной выработки 2. Однако данный способ характеризуетс  недостаточной безопасностью рйбот и значительными потер ми угл  Целью изобретени   вл етс  повышение безопасности работ и снижение потерь угл  за счет обеспечени  изол ции технологического процесса гидроотбойки в забое от одновременно осуществл емого технологического процесса возведени  иск.усственного целика. Поставленна  цель достигаетс  тем, что согласно способу разработки крутых угольньгх пластов при гидр добыче , включающему проведение подэтажных выработок и базисных бремсбергов, последовательную отработку подэтажей сверху вниз с гидро отбойкой в забое и возведение искусственных целиков в каждом подэта же путем подачи твердеющего материа ла в выработанное пространство с вьш1ерасположенной подэтажной выработки , каждый последующий подэтаж отрабатывают под защитой с одной стороны искусственного целика, возведенного на вьшерасположенном подэтаже на всем его прот жении, и с другой стороны - щита-опалубки и искусственного целика, возводимого в отрабатываемом подэтаже путем мон тажа в каждом подэтаже щита-опалуб KHJ передвижки ее вслед за забоем и подачи за и ит-опалубку твердеющего материала, причем в процессе возведени  искусственного целика в нем оставл ют сквозную.полость, сообщающуюс  с базисным бремсбергом. Способ осуществл етс  следующим образом. Выемочное поле вскрьшают этажными квершлагами транспортными, вентил ционными и базисными бремсбергами . От одного из базисных бремсбергов проход т подэтажные выработки . По пласту могут быть пройдены и выемочные этажные штреки. Затем у другого базисного бремсберга в каждом подэтаже монтируют щитопалубку . Щит-опалубка может представл ть собой, например, объемный каркас из профильного металла в форме пр моугольного треугольника в боковом сечении. Вертикальна  сторона каркаса со стороны выработанного пространства покрыта ограждающим полотном, не схватывающимс  с твердеющей смесью. Со стороны почвы вынимаемого подэтажа и лежачего бока пласта щит-опалубка снабжена полозь ми, а со стороны вис чего бока пласта - уплотн ющими элементами , например в виде надувных пневматических конструкций, воздух из которых при передвижке щита опалубки выпускаетс . Объемный каркас щита-опалубки может быть выполнен облегченньм из расчета воспри ти  лишь нагрузки возводимого искусственного целика. Со стороны выработанного прост-, ранства каркас щита-опалубки снабаетс  надувньм багатоноТу, которьй в поперечном сечении при заполнении его воздухом воспроизводит форму оперечного сечени  вентил ционнозакладочной подэтажной выработки. При гидроотбойке угл  в подэтаже с помощью гидромонитора щит-опалубку перемещают лебедками, установленными на оконтуривающих подэтажных выработках, вслед за подвиганием забо . Щит может передвигатьс  и о принципу шагающей крепи. При передвижке щита-опалубки на прин тое рассто ние, исход  из онкретных условий возведени  исусственного целика, щит распирают (герметизируют) при помощи уплотн ющих элементов путем нагнетани  в пневматические конструкции сжатого воздуха, одновременно подают сжатый воздух и в пневмобаплон, который своим концом находитс  в полости затвер евшего искусственного целика, после чего по вентил ционно-закладочной прдэтажной выработке подаю за щит-опалубку твердеющую.смесь и заполн ют ею выработанное простран ство до уровн  почвы подэтажной выработки . После затвердевани  в смеси за щитом-опалубкой сжатый воздух из пневмоконструкций выпускают и возобновл ют передвижку щита-опапубки вслед за подвиганием забо . При зтом в искусственном целике образуетс  полость. Затем цикл работ в подэтаже повтор етс .The invention relates to the mining industry and is intended for the development of steep coal seams by means of hydromechanization and with the development of open space. There is a method of developing steep coal seams during hydraulic mining, which includes carrying out sublevel bottom lifts from basic bramsberg and coal hydrofluorization in sublevels 1 . There is a method of developing steep coal seams during hydraulic mining, which includes carrying out subsurface excavations and basic bremsberg, sequential mining of the sub-floor from top to bottom with hydrotreatment in the bottom, and erection of artificial pillars in each substage by feeding hardening material into the developed space from the upstream subsurface mine 2. However, this method characterizes insufficient safety of air and significant coal losses. The aim of the invention is to increase the safety of work and reduce carbon losses by providing insulation gidrootboyki technological process at the bottom of simultaneously carried emogo upmixing process isk.usstvennogo pillar. The goal is achieved by the fact that, according to the method of developing steep coal seams with hydr mining, including the conduct of sublevel workings and basic bremsbergov, sequential mining of sub-floors from top to bottom with hydroblowing in the face and building artificial pillars in each sub-part by feeding hardening material into the worked space each sub-floor development, each successive sub-floor is worked out under the protection from one side of an artificial pillar built on the top on the whole, and on the other hand, a formwork shield and an artificial pillar erected in the developed substage by mounting it in each substage of the KHJ formwork shield, moving it after the slaughter and filing for it and formwork of hardening material, and in the process of erecting an artificial pillar, a through cavity is left in it, which communicates with the basic bremsberg. The method is carried out as follows. The field is covered with transport, ventilation and basic brassbergs. From one of the base bramsberg pass t sublevel workings. Reservoirs can be traversed along the seam. Then, another baseboard in each sub-floor mounter is mounted. The formwork panel can be, for example, a three-dimensional profile metal frame in the shape of a rectangular triangle in lateral section. The vertical side of the frame from the side of the worked-out space is covered with a barrier sheet that does not adhere to the hardening mixture. On the soil side of the removed substage and the recumbent side of the reservoir, the formwork board is provided with runners, and on the side of which the sides of the reservoir are provided with sealing elements, for example, in the form of inflatable pneumatic structures, the air from which is released when the formwork shield is moved. The volumetric frame of the formwork panel can be made lighter on the basis of perceiving only the load of the artificial pillar being built. From the side of the developed space, the casing of the formwork shield is supplied with inflatable bagatonote, which in cross section when filled with air, reproduces the shape of the cross section of the ventilation-laying sub-floor mine. When the coal is hydrotreated in a substage, using a jetting system, the formwork shield is moved by winches installed on the contouring subsurface workings, following the advance of the bottom. The shield can also be moved on the principle of walking support. When shifting the formwork board to a given distance, based on the specific conditions for the construction of the artificial pillar, the shield is burst (sealed) with the help of sealing elements by forcing compressed air into the pneumatic structures, and at the same time compressed air is fed into the cavity of the hardened artificial pillar, after which, through the ventilation-stowing floor construction, I apply a hardening mixture for the formwork shield and fill it with the developed space to the level of the soil of the subnet working out. After solidification in the mixture behind the formwork shield, the compressed air from the pneumonstructions is released and the shifting of the formwork shield is resumed following the advance of the bottom. With this, a cavity is formed in the artificial pillar. The cycle of work in the sub-frame is then repeated.

Дл  более равномерной добычи угл  из выемочного пол  в нем могут находитьс  несколько одновременно . действукмцйх забоев (на нескольких подэтажах). В этом случае процессы выемки и возведени  искусственного целика чередуют.For more uniform extraction of coal from the excavated floor there may be several at a time. Actuation faces (on several floors). In this case, the processes of excavation and erection of an artificial pillar alternate.

Предлагаемый способ разработки позвол ет повысить по сравнению с прототипом безопасность работ в поДэтаже за счет содержани  в более благопри тных услови х подэтажных выработок и наличи  запасных выходов обеспечить .проветривание горных выработок за счет общешахтной депрессии и практически полностью устранить потери угл  в выемочном . поле.The proposed development method makes it possible to increase the safety of work in the pore in comparison with the prototype due to the maintenance of subsurface workings in more favorable conditions and the availability of emergency exits to ensure the ventilation of mine workings due to general depression and almost completely eliminate the loss of coal in the excavation. field.

Claims (1)

СПОСОБ РАЗРАБОТКИ КРУТЫХ , УГОЛЬНЫХ ПЛАСТОВ ПРИ ГИДРОДОБЫЧЕ, включающий проведение подэтажных 4 выработок и базисных бремсбергов, последовательную отработку подэтажей сверху вниз с гидроотбойкой в забое и возведение искусственных целиков в каждом подэтаже путем подачи твердеющего материала в выработанное пространство с вышерасположенной подэтажной выработки, отличающийся тем, что, с целью повышения безопасности работ и снижения потерь угля за счет обеспечения изоляции технологического процесса гидроотбойки в забое от одновременно осуществляемого технологического процесса возведения искусственного целика, каждый последующий подэтаж отрабатывают под защитой с одной стороны искусственного целика, возведенного на вышерасположенном подэтаже на всем его протяжении, и с другой стороны - щита-опалубки и искусственного целика, возводимого в обрабатываемом подэтаже путем монтажа в каждом подэтаже щита-опалубки, передвижки ее вслед за забоем и подачи за щит-опалубку твердеющего материала, причем в процессе возведения искусственного целика в нем оставляют сквозную полость, сообщающуюся с базисным бремсбергом.METHOD FOR THE DEVELOPMENT OF STEEP, COAL LAYERS DURING HYDRO-MINING, including carrying out 4 floor workings and basic Bremsbergs, sequential mining of top-floors from top to bottom with hydraulic breaking in the face and erection of artificial pillars in each sub-floor by feeding hardening material to the worked-out space underneath, , in order to improve the safety of work and reduce coal losses by ensuring the isolation of the technological process of hydraulic breakdown in the face from simultaneously the existing technological process of erecting an artificial pillar, each subsequent sub-floor is being worked out under the protection on one side of the artificial pillar, erected on the upper floor along its entire length, and on the other hand, the formwork panel and artificial pillar, erected in the processed sub-floor by mounting in each sub-floor of the shield formwork, moving it after the slaughter and feeding hardening material behind the formwork shield, moreover, in the process of erecting an artificial pillar, through strips are left in it communicating with the base Bremsberg.
SU813296669A 1981-06-01 1981-06-01 Method of working steep coal seam by hydraulic excavation SU1097795A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813296669A SU1097795A1 (en) 1981-06-01 1981-06-01 Method of working steep coal seam by hydraulic excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813296669A SU1097795A1 (en) 1981-06-01 1981-06-01 Method of working steep coal seam by hydraulic excavation

Publications (1)

Publication Number Publication Date
SU1097795A1 true SU1097795A1 (en) 1984-06-15

Family

ID=20961273

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813296669A SU1097795A1 (en) 1981-06-01 1981-06-01 Method of working steep coal seam by hydraulic excavation

Country Status (1)

Country Link
SU (1) SU1097795A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Зиберт X. Опыт гидромеханизации Добычи угл на гидрошахте. Ганза, Глюкауф, 1980, 18, с. 24-34. 2. Авторское свидетельство СССР № 781351, кл. Е 21 С 41/04, 1979 (прототип). *

Similar Documents

Publication Publication Date Title
RU2475647C2 (en) Mining method of thick steep ore bodies
CN105804748B (en) A kind of method of block mining Wall ore under open air transport system
RU2283431C1 (en) Method for thick steep mineral seam mining along with goaf filling
CN110778320A (en) Synchronous excavation supporting construction method for three-step inverted arch of weak surrounding rock tunnel
JP2008308835A (en) Construction method for sidewall pilot tunnel type tunnel and its structure
CN109056703A (en) A kind of construction method of assembled underground continuous wall
US4213653A (en) Method of mining of thick seam materials
US4174135A (en) Underground formed wall single-entry mining method
SU1097795A1 (en) Method of working steep coal seam by hydraulic excavation
CN109209484B (en) Auxiliary working face withdrawing method for withdrawing channel combined with paste prefabricated block
US4007966A (en) Single-entry mining development system
US2055876A (en) Tunneling
JP2000265777A (en) Transferable stage for repairing tunnel and tunnel repair method using the same
US4147452A (en) Method for constructing a rectangularly shaped tunnel
RU2263213C1 (en) Method for thick steeply inclined fire-hazardous bed mining with caving
JP3996597B2 (en) Open shield machine and open shield method using it
RU2254472C1 (en) Method for extraction of massive sloping potassium beds
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
RU2481473C1 (en) Method for layered development of kimberlitic pipe with backfilling
JPH0726877A (en) Construction method of underground structure
RU2276264C1 (en) Method for underground flat seam mining
RU2084631C1 (en) Method of hydraulic mining of steep thick seams with solid hardening gobbing
RU2083833C1 (en) Method for development of steep coal seams with backing worked-out area
SU1126696A1 (en) Method for underground working of mineral deposits
RU2068498C1 (en) Method of slant coal seams development