RU2199633C2 - Process of erection of building with prestressed frame by method of rise of stories - Google Patents

Process of erection of building with prestressed frame by method of rise of stories Download PDF

Info

Publication number
RU2199633C2
RU2199633C2 RU2001112352/03A RU2001112352A RU2199633C2 RU 2199633 C2 RU2199633 C2 RU 2199633C2 RU 2001112352/03 A RU2001112352/03 A RU 2001112352/03A RU 2001112352 A RU2001112352 A RU 2001112352A RU 2199633 C2 RU2199633 C2 RU 2199633C2
Authority
RU
Russia
Prior art keywords
floor
frame
rise
erection
column
Prior art date
Application number
RU2001112352/03A
Other languages
Russian (ru)
Inventor
Н.А. Маркаров
Original Assignee
Государственное унитарное предприятие "Научно-исследовательский, проектно-конструкторский и технологический институт бетона и железобетона"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Государственное унитарное предприятие "Научно-исследовательский, проектно-конструкторский и технологический институт бетона и железобетона" filed Critical Государственное унитарное предприятие "Научно-исследовательский, проектно-конструкторский и технологический институт бетона и железобетона"
Priority to RU2001112352/03A priority Critical patent/RU2199633C2/en
Application granted granted Critical
Publication of RU2199633C2 publication Critical patent/RU2199633C2/en

Links

Images

Abstract

FIELD: construction industry, erection of buildings of frame system with rise of floors. SUBSTANCE: in correspondence with proposed process cross-piece with tie-rod is put on each column of frame cell, hydraulic jack with draw-in clamps. Floor is anchored in angles on bodies of hydraulic jacks and rise is conducted with fixing of each step of hydraulic jack by draw-in clamps. Floor is first lifted above level of planned position and arrangement of holes in columns for passage of stressed reinforcement, temporary supporting members are inserted into holes and floor is born against supporting members. After rise of floors in adjacent cells of frame supporting tables embracing column are mounted on columns, temporary supporting members are removed and floor is lowered on supporting table into planned position. Employment of temporary supporting members simplifies process of mounting and shortens time of erection of skeleton-type building which is technical result of invention. EFFECT: simplified mounting process and shortened time of erection of frame building. 4 dwg

Description

Изобретение относится к области строительства и может быть использовано при возведении зданий каркасной системы с подъемом перекрытий и др. конструкций. The invention relates to the field of construction and can be used in the construction of buildings of the frame system with the rise of floors and other structures.

Известен способ подъема этажей, включающий уcтановку на колонны пары траверс с тягами, гидродомкрата между ними, пары цанговых зажимов на каждой тяге, подвешивание конструкций этажа к траверсе с помощью тяг и поэтапный подъем конструкций с фиксацией каждого шага цанговыми зажимами [1]. A known method of raising floors, including installing on a column a pair of traverses with rods, a hydraulic jack between them, a pair of collet clamps on each rod, suspending floor structures to the traverse with rods and phased lifting structures with fixing each step with collet clamps [1].

Недостатком известного способа является сложность монтажа громоздкого оборудования на колонне. The disadvantage of this method is the complexity of mounting bulky equipment on a column.

Наиболее близким является способ возведения каркасного здания методом подъема этажей, включающий установку на каждую колонну ячейки каркаса траверсы с тягой и установленным на ней гидродомкратом с цанговыми зажимами, подвешивание перекрытия к корпусам гидродомкратов и поэтапный подъем перекрытий путем шагового перемещения гидродомкрата относительно тяги с фиксацией каждого шага гидродомкрата цанговыми зажимами до проектного положения перекрытия, с последующим опиранием их на смонтированные на колоннах в уровнях каждого этажа опорные столики. The closest is a method of erecting a frame building using the method of raising floors, including installing a traverse with a rod and a hydraulic jack with collet clamps on each column of the cell frame, suspending the ceiling to the body of the hydraulic jacks and phasing the floors by stepwise moving the hydraulic jack relative to the link with fixing each step of the hydraulic jack collet clamps to the design position of the floor, with their subsequent support on mounted on columns at the levels of each floor nye tables.

Недостатками известного способа является сложность последовательного подъема перекрытий в смежных ячейках предварительно-напряженного каркаса после монтажа опорных столиков, которые охватывают колонну. The disadvantages of this method is the difficulty of sequentially lifting the floors in adjacent cells of the prestressed frame after mounting the supporting tables that cover the column.

Техническая задача заключается в упрощении монтажных работ, снижении трудоемкости и сокращении сроков возведения здания за счет обеспечения последовательного поэтапного подъема перекрытий в смежных ячейках каркаса. The technical task is to simplify installation work, reduce the complexity and reduce the time of construction of the building by providing a consistent phased lifting of floors in adjacent cells of the frame.

Поставленная задача решается таким образом, что в способе возведения здания с предварительно-напряженным каркасом методом подъема этажей, включающем установку на каждую колонну ячейки каркаса траверсы с тягой и установленным на ней гидродомкратом с цанговыми зажимами, крепление перекрытия к корпусам гидродомкратов и поэтапный подъем перекрытий с фиксацией каждого шага гидродомкрата цанговыми зажимами до проектного положения, с последующим опиранием перекрытий на смонтированные на колоннах в уровнях каждого этажа опорные столики, согласно изобретению перекрытия поднимают последовательно в каждой ячейке сначала выше уровня проектного положения и расположения отверстий в колонне для пропуска напрягаемой арматуры, устанавливают в эти отверстия временные опорные элементы и опирают на них перекрытие, после чего монтируют на колоннах опорные столики, временные опорные элементы снимают и опускают перекрытие на опорные столики в проектное положение. The problem is solved in such a way that in the method of erecting a building with a prestressed carcass by the method of raising floors, including installing on each column of a cell of the carcass carcass with a rod and a hydraulic jack with collet clamps installed on it, attaching the ceiling to the body of the hydraulic jacks and phased lifting of the ceilings with fixation each step of the hydraulic jack with collet clamps to the design position, with the subsequent support of the ceilings on the supporting tables mounted on columns in the levels of each floor, with According to the invention, the floors are raised sequentially in each cell, first above the level of the design position and the location of the holes in the column for the passage of prestressed reinforcement, temporary support elements are installed in these holes and the floor is supported on them, then the support tables are mounted on the columns, the temporary support elements are removed and lowered overlap on the supporting tables in the design position.

Предлагаемый способ отличается от известного тем, что перекрытия поднимают последовательно в каждой ячейке сначала выше уровня проектного положения и расположения отверстий в колонне для пропуска напрягаемой арматуры, устанавливают в эти отверстия временные опорные элементы и опирают на них перекрытие, после чего монтируют на колоннах опорные столики, временные опорные элементы снимают и опускают перекрытие на опорные столики в проектное положение. The proposed method differs from the known one in that the floors are successively raised in each cell first above the design position and the location of the holes in the column for the passage of prestressed reinforcement, temporary support elements are installed in these holes and the ceiling is supported on them, after which support tables are mounted on the columns, temporary support elements remove and lower the floor to the support tables in the design position.

Такая последовательность операций подъема с использованием временных опорных элементов обеспечивает возможность свободного подъема перекрытий в смежных ячейках с последующим монтажом опорных столиков, охватывающих все сечение колонны с четырех сторон. Временные опорные элементы, выполненные в виде приваренных к штырю пластин, после подъема перекрытий на высоту выше расположения отверстий для пропуска напрягаемой арматуры, устанавливаемой после монтажа перекрытий, вставляют в отверстия колонн со стороны монтируемой ячейки и опирают на них перекрытие. Затем подъем перекрытий осуществляют в смежной ячейке аналогичными путем. После подъема перекрытий монтируют опорные столики на смежные ячейки и опускают на них перекрытия. This sequence of lifting operations using temporary supporting elements provides the possibility of free lifting of the ceilings in adjacent cells with the subsequent installation of supporting tables, covering the entire cross-section of the column from four sides. Temporary support elements, made in the form of plates welded to the pin, after raising the ceilings to a height above the location of the openings for the passage of prestressed reinforcement installed after the installation of the ceilings, are inserted into the holes of the columns from the side of the cell to be mounted and the ceiling is supported on them. Then the rise of the floors is carried out in an adjacent cell in a similar way. After raising the floors, the support tables are mounted on adjacent cells and the floors are lowered on them.

Способ поясняется чертежом, где на фиг.1 представлен узел монтажа перекрытия (1 этап - перекрытие опирается на временные опорные элементы); фиг. 2 - то же, что и на фиг.1 (этап 2 - перекрытие опирается на опорные столики в проектном положении); фиг.3, 4 - временные опорные элементы. The method is illustrated in the drawing, where figure 1 shows the installation of the floor (stage 1 - the ceiling is based on temporary support elements); FIG. 2 - the same as in figure 1 (stage 2 - the overlap is based on the supporting tables in the design position); figure 3, 4 - temporary support elements.

На торец каждой колонны 1 в ячейке каркаса устанавливают траверсу, к которой подвешивают на всю высоту колонны тягу с гидродомкратом. Перекрытия 2 крепят по углам инвентарными тягами к корпусам гидродомкратов и поднимают на высоту выше уровня расположения отверстий 3 в колонне 1 для пропуска напрягаемой арматуры. В отверстия 3 колонн 1 со стороны ячейки вставляют временные опорные элементы 4, состоящие из штыря 5 и пластины 6, и опирают на них перекрытие 2. Затем таким же образом поднимают и опирают на временный опорный элемент перекрытие в смежных ячейках каркаса. После этого монтируют опорный столик 7, охватывающий колонну 1, и опускают на него перекрытия 2 в смежных ячейках каркаса. A traverse is installed on the end of each column 1 in the cell of the frame, to which a rod with a hydraulic jack is suspended to the entire height of the column. Overlappings 2 are fixed at the corners with inventory rods to the hydraulic jack housings and raised to a height above the level of the holes 3 in the column 1 to pass the prestressed reinforcement. Temporary support elements 4, consisting of a pin 5 and a plate 6, are inserted into the openings 3 of the columns 1 from the cell side and the overlap 2 is supported on them. Then, the overlap in adjacent cells of the frame is lifted and supported on the temporary support element. After that, mount the supporting table 7, covering the column 1, and lower the overlap 2 in adjacent cells of the frame.

Источники информации
1. Саакян А. О. Возведение зданий и сооружений методом подъема. - М.: Стройиздат, 1982, с.266-270.
Sources of information
1. Sahakyan A. O. The construction of buildings and structures by lifting. - M.: Stroyizdat, 1982, p. 266-270.

2. Патент РФ 2131004, кл. Е 04 В 1/35, БИ 15, 1999 г. (прототип). 2. RF patent 2131004, cl. E 04 In 1/35, BI 15, 1999 (prototype).

Claims (1)

Способ возведения здания с предварительно-напряженным каркасом методом подъема этажей, включающий установку на каждую колонну ячейки каркаса траверсы с тягой и установленным на ней гидродомкратом с цанговыми зажимами, крепление перекрытия к корпусам гидродомкратов и поэтапный подъем перекрытий с фиксацией каждого шага гидродомкрата цанговыми зажимами до проектного положения с последующим опиранием перекрытий на смонтированные на колоннах в уровнях каждого этажа опорные столики, отличающийся тем, что перекрытия поднимают последовательно в каждой ячейке сначала выше уровня проектного положения и расположения отверстий в колонне для пропуска напрягаемой арматуры, устанавливают в эти отверстия временные опорные элементы и опирают на них перекрытие, после чего монтируют на колоннах опорные столики, временные опорные элементы снимают и опускают перекрытие на опорные столики в проектное положение. A method of erecting a building with a prestressed carcass by the method of raising floors, including installing a traverse with a rod and a hydraulic jack with collet clamps on each column of the cell carcass, attaching the ceiling to the body of the hydraulic jacks and phasing the ceilings with fixing each step of the hydraulic jack with collet clamps to the design position with the subsequent support of the ceilings on the supporting tables mounted on columns in the levels of each floor, characterized in that the ceilings raise the In each cell, first, above the design position and the location of the holes in the column for passing prestressed reinforcement, temporary support elements are installed in these holes and the floor is supported on them, after which support tables are mounted on the columns, temporary support elements are removed and the ceiling is lowered on the support tables in design position.
RU2001112352/03A 2001-05-10 2001-05-10 Process of erection of building with prestressed frame by method of rise of stories RU2199633C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2001112352/03A RU2199633C2 (en) 2001-05-10 2001-05-10 Process of erection of building with prestressed frame by method of rise of stories

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2001112352/03A RU2199633C2 (en) 2001-05-10 2001-05-10 Process of erection of building with prestressed frame by method of rise of stories

Publications (1)

Publication Number Publication Date
RU2199633C2 true RU2199633C2 (en) 2003-02-27

Family

ID=20249333

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2001112352/03A RU2199633C2 (en) 2001-05-10 2001-05-10 Process of erection of building with prestressed frame by method of rise of stories

Country Status (1)

Country Link
RU (1) RU2199633C2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517970A (en) * 2018-03-14 2018-09-11 江苏恒久钢构有限公司 A kind of large-span truss hanging method
CN114704108A (en) * 2022-04-29 2022-07-05 江苏鸿基节能新技术股份有限公司 Jacking device for building storey addition

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517970A (en) * 2018-03-14 2018-09-11 江苏恒久钢构有限公司 A kind of large-span truss hanging method
CN114704108A (en) * 2022-04-29 2022-07-05 江苏鸿基节能新技术股份有限公司 Jacking device for building storey addition
CN114704108B (en) * 2022-04-29 2024-03-01 江苏鸿基节能新技术股份有限公司 Jacking device for building storey-adding

Similar Documents

Publication Publication Date Title
EP0654571B1 (en) Zone module construction method of steel structure construction
US5839239A (en) Apparatus and method for building construction
US10745919B1 (en) Method and apparatus for installing a staircase assembly into a building
JP2010265727A (en) Method for demolishing building using floor climbing type tower crane
RU2199633C2 (en) Process of erection of building with prestressed frame by method of rise of stories
US4782634A (en) Building construction
JP2927320B2 (en) How to assemble a large hanging boiler
JP3732586B2 (en) Method and apparatus for constructing steel structure
US6808338B2 (en) Method and system for lifting of the massive constructions
RU2415231C2 (en) Method to erect building from finished elements
RU2233953C2 (en) Method for erecting building frame without girders by means of floor lifting
IT8224337A1 (en) Building construction method and device
JP2890341B2 (en) Method and apparatus for lifting up top-level frame for structure construction
KR101209408B1 (en) A prefabricated house construction device
SU1240852A1 (en) Process for erecting multistorey skeleton building by floor-lifting method
RU2656633C1 (en) Method of multi storage framework-monolithic building erection by the floors lifting method
JP3187618B2 (en) How to assemble beam reinforcement
JPH11131811A (en) Method for constructing building
JP3106270B2 (en) Pillars for lifting and joining structures and methods for lifting structures
RU2018610C1 (en) Shelter and method for its monitoring
RU2120006C1 (en) Method of rood hoisting (versions)
SU1717770A1 (en) Method of reconstruction of industrial building by increasing the spacing of its columns
JPH0791603A (en) Assembly parallel progressing method for large suspension type boiler
JPH074060A (en) Lift-up execution equipment for multistoried building
SU278076A1 (en) TIME. • '.VOAVYODShSh KAf "KACA AND STEP BUILDING

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20060511