JPH074060A - Lift-up execution equipment for multistoried building - Google Patents

Lift-up execution equipment for multistoried building

Info

Publication number
JPH074060A
JPH074060A JP5142096A JP14209693A JPH074060A JP H074060 A JPH074060 A JP H074060A JP 5142096 A JP5142096 A JP 5142096A JP 14209693 A JP14209693 A JP 14209693A JP H074060 A JPH074060 A JP H074060A
Authority
JP
Japan
Prior art keywords
jacks
story
columns
building
lift
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5142096A
Other languages
Japanese (ja)
Inventor
Hiroshi Koiso
浩 小磯
Ryoji Matsuura
良治 松浦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dainippon Doboku Kk
Toyo Engineering Corp
Original Assignee
Dainippon Doboku Kk
Toyo Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dainippon Doboku Kk, Toyo Engineering Corp filed Critical Dainippon Doboku Kk
Priority to JP5142096A priority Critical patent/JPH074060A/en
Publication of JPH074060A publication Critical patent/JPH074060A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To eliminate the need for a temporary material, and to improve efficiency by constructing girders and columns corresponding to one story, pushing up the whole story by jacks, building girders and columns corresponding to another one story in a lower section and obliquely disposing the jacks at symmetric positions with respect to the column. CONSTITUTION:The upper story structure of a building composed of existing girders 1 and columns 2 is lifted up by expansion jacks 3. New columns 2 are extended in the lower space of the columns 2, and the front ends of piston rods 3B are removed from binding sections 5 and the expansion jacks 3 are shrunk. The upper story structure is retained at the position of lifting as it is by the bearing of the columns 2 to be extended of a lower story and temporary receiving jacks at that time, and falling is prevented by the bearing of auxiliary jacks 6 in the expansion jacks 3. The piston rods 3B of the shrunk jacks 3 are connected to the binding sections 5 of the extended columns 2, and the binding sections 5 are coupled by horizontal girders 1 and a floor is executed. Accordingly, execution corresponding to one story is completed, the jacks 3 are elongated synchronously again and a routing is repeated, and a new story is constructed to a lower section while pushing up an assembly completion story.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、ビルなどの建築物を地
上で一層ずつ施工してリフトアップしながら構築する技
術に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technique for constructing buildings such as buildings one by one on the ground and constructing them while lifting them up.

【0002】[0002]

【従来の技術】ビルなどの建築物を地上で一層ずつ構築
し、構築した部分をジャッキにより順次リフトアップし
ながらその下方に新たな層を構築するリフトアップ工法
が近年数多く提案されている。
2. Description of the Related Art In recent years, many lift-up construction methods have been proposed in which a building such as a building is constructed one by one on the ground, and the constructed portion is sequentially lifted up by a jack and a new layer is constructed under the construction.

【0003】[0003]

【発明の課題】これらの工法において、リフトアップの
ためのジャッキは一般に垂直方向に配設され、垂直荷重
のみを支持するように構成されていた。そして、地震や
風が及ぼす水平荷重については構築した層の梁や柱を筋
交いやワイヤロープなどの仮設材で支持することにより
対処していた。
In these construction methods, the lift-up jacks are generally arranged in a vertical direction and are designed to support only a vertical load. Then, the horizontal load caused by the earthquake and wind was dealt with by supporting the beams and columns of the constructed layer with braces and temporary materials such as wire ropes.

【0004】しかしながら、ジャッキの他にこれらの仮
設材を設けることとで作業空間が狭められ、特に資材の
運搬通路や作業機械の移動通路上に仮設材が存在する
と、建設作業の効率が低下するという問題があった。
However, by providing these temporary materials in addition to the jack, the working space is narrowed, and particularly when the temporary materials are present on the material transportation passage or the moving passage of the working machine, the construction work efficiency is reduced. There was a problem.

【0005】本発明は、上記問題点を解決すべくなされ
たもので、上記のような仮設材を使用せずに垂直水平両
方向の荷重を支持できる施工装置を提供することを目的
とする。
The present invention has been made to solve the above problems, and an object of the present invention is to provide a construction device capable of supporting loads in both vertical and horizontal directions without using the above-mentioned temporary material.

【0006】[0006]

【課題を達成するための手段】本発明は、多層建築物の
一層分の梁と柱を構築した後、ジャッキにより層全体を
押し上げてその下方に新たに一層分の梁と柱を構築する
ことにより、構築した層を順次上方へ押し上げながら多
層建築物を施工する多層建築物のリフトアップ施工装置
において、前記各柱に対してそれぞれ一対の押し上げ用
のジャッキを前記柱を中心とする対称位置に傾斜状態で
配設している。
SUMMARY OF THE INVENTION According to the present invention, after constructing a beam and a pillar for one layer of a multi-layer building, the whole layer is pushed up by a jack and a beam and a column for one layer are newly constructed under the beam. Thus, in a lift-up construction device for a multi-story building that constructs a multi-story building while sequentially pushing the constructed layers upward, a pair of jacks for uplifting each of the pillars at symmetrical positions about the pillar. It is arranged in an inclined state.

【0007】さらに、前記各一対のジャッキを、平面上
隣り合う柱間で互いに直交する向きに配設している。
Further, the pair of jacks are arranged in a direction orthogonal to each other between adjacent columns on a plane.

【0008】[0008]

【作用】ジャッキを傾斜状態で対称位置に配設すること
により、建築物に作用する垂直水平両方向の荷重を仮設
材を要さずにジャッキのみで支持することが可能にな
る。
By arranging the jacks in symmetrical positions in a tilted state, it becomes possible to support loads acting in the vertical and horizontal directions on the building only by the jacks without using temporary materials.

【0009】また、各一対のジャッキを隣り合う柱間で
互いに直交する向きに配設することにより、建築物に作
用するあらゆる方向からの水平荷重に等しく耐えること
ができる。
Further, by arranging each pair of jacks in a direction orthogonal to each other between the adjacent columns, it is possible to withstand even horizontal loads from all directions acting on the building.

【0010】[0010]

【実施例】図1〜図5に本発明の実施例を示す。1 to 5 show an embodiment of the present invention.

【0011】図1は施工中のビルの一部を示し、1は
梁、2は柱でそれぞれ鉄骨で構成され、梁1と柱2の結
合部5を一対の対称的に傾斜させた伸縮ジャッキ3(3
X,3Y)により支持される。
FIG. 1 shows a part of a building under construction, where 1 is a beam, 2 is a column, each of which is made of steel frame, and a pair of symmetrically inclined telescopic jacks are provided at the connecting portions 5 of the beam 1 and the column 2. 3 (3
X, 3Y).

【0012】伸縮ジャッキ3は基端を地上に設けた基礎
4にヒンジ結合するシリンダチューブ3Aと、シリンダ
チューブ3Aから伸縮自在に突出して先端を結合部5に
取り外し可能な状態でヒンジ結合するピストンロッド3
Bとを備え、ピストンロッド3Bの伸縮位置に応じてこ
れらのヒンジが回転変位することにより、一定範囲で傾
斜角度を変化させる。各伸縮ジャッキ3を自立させるた
めに、シリンダチューブ3Bと基礎4との間に各々一対
の補助ジャッキ6(6X,6Y)が傾斜状態で設けられ
る。
The telescopic jack 3 has a cylinder tube 3A whose base end is hingedly connected to a foundation 4 provided on the ground, and a piston rod which is elastically projecting from the cylinder tube 3A and whose tip is detachably hinged to the connecting portion 5. Three
B, and the hinges are rotationally displaced according to the expansion / contraction position of the piston rod 3B, thereby changing the inclination angle within a certain range. In order to make each telescopic jack 3 self-supporting, a pair of auxiliary jacks 6 (6X, 6Y) are provided in an inclined state between the cylinder tube 3B and the foundation 4.

【0013】梁1は図5に示すように格子状に配設さ
れ、これらの各交点に柱2が立設され、結合部5が設け
られる。伸縮ジャッキ3は柱2の施工位置ごとに2基ず
つ側方から眺めた状態で2等辺三角形をなすように柱2
を中心とする対称位置に配設される。各組の伸縮ジャッ
キ3は図5に示すように、平面上でビルの外周部分に配
置される柱2については、ビルの外周を構成する梁1の
下方に同列に配設され、ビルの内側においては前後左右
に隣接する柱2ごとに梁1に沿って互いに直交する向き
に配設される。なお、これらの伸縮ジャッキ3の伸縮は
マイクロコンピュータなどで構成されたコントローラに
より制御される。
As shown in FIG. 5, the beams 1 are arranged in a grid pattern, columns 2 are erected at their intersections, and connecting portions 5 are provided. The telescopic jacks 3 form two isosceles triangles when viewed from the side, two sets at each construction position of the columns 2
Are arranged symmetrically with respect to. As shown in FIG. 5, the telescopic jacks 3 of each set are arranged in the same row below the beams 1 forming the outer circumference of the building, with respect to the pillars 2 arranged on the outer circumference of the building on the plane. In the above, the columns 2 adjacent to each other in the front, rear, left, and right are arranged along the beam 1 in directions orthogonal to each other. The expansion / contraction of these expansion / contraction jacks 3 is controlled by a controller composed of a microcomputer or the like.

【0014】次に作用を説明する。Next, the operation will be described.

【0015】図1においては既に構築した梁1と柱2か
らなるビルの上層構造体が一斉に伸長させたすべての伸
縮ジャッキ3によりリフトアップされている。
In FIG. 1, the upper layer structure of the building, which is composed of the beam 1 and the pillar 2, which has already been constructed, is lifted up by all the telescopic jacks 3 which are extended all at once.

【0016】このリフトアップ状態で、図2に示すよう
に柱2の下方の空間に新たな柱2を継ぎ足す。リフトア
ップの高さは継ぎ足す柱2の高さより大きく設定され、
柱2を継ぎ足す際は、柱2と基礎4の間に仮受ジャッキ
7を挿入して高さを調整する。
In this lift-up state, a new column 2 is added to the space below the column 2 as shown in FIG. The height of the lift-up is set to be larger than the height of the additional pillar 2,
When the pillar 2 is replenished, the temporary receiving jack 7 is inserted between the pillar 2 and the foundation 4 to adjust the height.

【0017】すべての位置に柱2を継ぎ足した後、ピス
トンロッド3Bの先端を結合部5から取り外して、伸縮
ジャッキ3を収縮させる。この時、上層部分の梁1と柱
2は新たに継ぎ足した下層の柱2と仮受ジャッキ7に支
持されるので、伸縮ジャッキ3を収縮させても上層構造
体はそのまま上昇位置に留まる。また、伸縮ジャッキ3
は各一対の補助ジャッキ6によって支持されているの
で、結合部5から離しても倒れることはない。
After the columns 2 have been added to all positions, the tip of the piston rod 3B is removed from the connecting portion 5 and the telescopic jack 3 is contracted. At this time, the upper layer beam 1 and the column 2 are supported by the newly added lower layer column 2 and the temporary receiving jack 7, so that the upper layer structure remains at the raised position even when the expansion jack 3 is contracted. Also, the telescopic jack 3
Is supported by each pair of auxiliary jacks 6, so that it does not fall down even if it is separated from the coupling portion 5.

【0018】次に収縮させた伸縮ジャッキ3のピストン
ロッド3Bを図3に示すように継ぎ足した柱2の結合部
5に連結する。そして、この状態で図4に示すように各
結合部5を水平の梁1で連結し、さらに床の施工を行
う。
Next, the piston rod 3B of the contracted telescopic jack 3 is connected to the connecting portion 5 of the column 2 which is added as shown in FIG. Then, in this state, as shown in FIG. 4, the connecting portions 5 are connected by the horizontal beams 1, and the floor is further constructed.

【0019】これにより、1層分の施工が終了する。こ
の状態で伸縮ジャッキ3を再び同期的に伸長させれば図
1と同様の状態となるので、再び上記の作業工程を繰り
返してさらに下層部分の施工を行う。なお、伸縮ジャッ
キ3の伸長動作は補助ジャッキ6を伸縮自由(フリー)
な状態にして行う。
This completes the construction of one layer. If the telescopic jack 3 is again synchronously extended in this state, the same state as in FIG. 1 is obtained. Therefore, the above-described working process is repeated again to further construct the lower layer portion. In addition, the extension operation of the telescopic jack 3 allows the auxiliary jack 6 to freely expand and contract (free).
It is done in such a state.

【0020】このようにして、組み立て終わった層をリ
フトアップしながら、その下方に新たな層を施工するこ
とでビルの構造体を完成させる。
In this way, the structure of the building is completed by lifting up the assembled layer and constructing a new layer below it.

【0021】施工中の構造体には自重による垂直荷重だ
けでなく、地震や風による水平荷重が作用するが、伸縮
ジャッキ3は結合部5と基礎4の間に斜めに配設されて
いるため、これらの荷重は水平荷重を含めてすべて伸縮
ジャッキ3により支持される。すなわち、垂直荷重につ
いては全伸縮ジャッキ3が荷重を分担して支持し、水平
荷重については水平荷重により圧縮力を受ける伸縮ジャ
ッキ3が荷重を分担する。水平荷重を支持する伸縮ジャ
ッキ3の数は図5の左右または前後方向に水平荷重が作
用した場合にそれぞれ全体数の約4分の1になるが、構
造体に加わる水平荷重は垂直荷重の数分の1であるた
め、この程度の数の伸縮ジャッキ3でも支持力は十分に
得られる。
Not only the vertical load due to its own weight but also the horizontal load due to an earthquake or wind acts on the structure under construction, but since the expansion jack 3 is obliquely arranged between the joint portion 5 and the foundation 4. All of these loads including horizontal loads are supported by the telescopic jack 3. That is, for the vertical load, all the telescopic jacks 3 share and support the load, and for the horizontal load, the telescopic jack 3 that receives the compressive force by the horizontal load shares the load. The number of telescopic jacks 3 supporting a horizontal load is about one-fourth of the total number when a horizontal load is applied in the left-right direction or the front-back direction in FIG. 5, but the horizontal load applied to the structure is the number of vertical loads. Since it is one-half, a sufficient supporting force can be obtained even with this number of expansion / contraction jacks 3.

【0022】この場合に隣り合う柱2の間で、伸縮ジャ
ッキ3の平面上の向きが互いに直角をなすように配置し
たので、構造体の左右、前後のすべての方向からの水平
荷重に等しく耐えることができる。
In this case, since the extension jacks 3 are arranged so that the plane directions of the extension jacks 3 are perpendicular to each other between the adjacent pillars 2, the structure can withstand the horizontal loads from all the left, right, front and rear directions equally. be able to.

【0023】このように、伸縮ジャッキ3が水平方向の
支持力を持つことにより、水平荷重を支持するための筋
交いやワイヤロープなどの仮設材は不要となる。したが
って、伸縮ジャッキ3に加えてこれらの仮設材を配設す
る場合と比べて作業や機械の移動のための空間を大きく
確保することができ、構造体の組み立て作業を効率良く
行うことができる。また、これらの仮設材の配置に要す
る手間も不要となる。
As described above, since the telescopic jack 3 has a horizontal supporting force, a bracing for supporting a horizontal load and a temporary material such as a wire rope are unnecessary. Therefore, as compared with the case where these temporary members are provided in addition to the expansion jack 3, a large space for work and movement of the machine can be secured, and the work of assembling the structure can be efficiently performed. In addition, the labor required for arranging these temporary materials is also unnecessary.

【0024】[0024]

【発明の効果】以上のように本発明は、構築した層の押
し上げを行うジャッキを柱を中心とする対称位置に傾斜
状態で配設したので、施工中の建築物に加わる水平垂直
両方向の荷重をジャッキで支持することができる。この
ため、水平荷重を支持するために筋交いやワイヤロープ
などの仮設材を設ける必要がなく、その分作業空間や作
業機械の移動空間を大きく確保することができる。また
仮設材の配置に伴う手間も節約できる。したがって、リ
フトアップ工法による建築作業の効率を向上させる効果
がある。
As described above, according to the present invention, since the jacks for pushing up the constructed layer are arranged in a tilted state at symmetrical positions around the column, the load applied to the building under construction in both horizontal and vertical directions. Can be supported with a jack. Therefore, it is not necessary to provide a bracing member or a temporary material such as a wire rope to support the horizontal load, and a working space and a moving space for the working machine can be largely secured accordingly. In addition, it is possible to save the labor required for disposing the temporary material. Therefore, there is an effect that the efficiency of construction work by the lift-up method is improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例を示すリフトアップ施工装置の
側面図である。
FIG. 1 is a side view of a lift-up construction device showing an embodiment of the present invention.

【図2】柱の継ぎ足し作業中のリフト−アップ施工装置
の側面図である。
FIG. 2 is a side view of a lift-up construction device during a pillar replenishment work.

【図3】ジャッキ結合位置変更後のリフトアップ施工装
置の側面図である。
FIG. 3 is a side view of the lift-up construction device after changing the jack connection position.

【図4】梁施工中のリフトアップ施工装置の側面図であ
る。
FIG. 4 is a side view of a lift-up construction device during construction of a beam.

【図5】リフトアップ施工装置とビル構造体の平面図で
ある。
FIG. 5 is a plan view of a lift-up construction device and a building structure.

【符号の説明】[Explanation of symbols]

1 梁 2 柱 3 伸縮ジャッキ 1 beam 2 pillar 3 telescopic jack

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 多層建築物の一層分の梁と柱を構築した
後、ジャッキにより層全体を押し上げてその下方に新た
に一層分の梁と柱を構築することにより、構築した層を
順次上方へ押し上げながら多層建築物を施工する多層建
築物のリフトアップ施工装置において、前記各柱に対し
てそれぞれ一対の押し上げ用のジャッキを前記柱を中心
とする対称位置に傾斜状態で配設したことを特徴とする
多層建築物のリフトアップ施工装置。
1. After constructing a beam and a pillar for a single layer of a multi-story building, a jack is used to push up the entire layer and a new beam and a column for a new layer are constructed below the layer, so that the constructed layers are sequentially raised. In a multi-layer building lift-up construction device for constructing a multi-layer building while pushing it up, a pair of push-up jacks for each of the columns are arranged in a tilted state at symmetrical positions about the column. Lift-up construction equipment for multi-story buildings.
【請求項2】 前記各一対のジャッキは、平面上隣り合
う柱間で互いに直交する向きに配設される請求項1記載
の多層建築物のリフトアップ施工装置。
2. The lift-up construction apparatus for a multilayer building according to claim 1, wherein the pair of jacks are arranged in mutually orthogonal directions between adjacent columns on a plane.
JP5142096A 1993-06-14 1993-06-14 Lift-up execution equipment for multistoried building Pending JPH074060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5142096A JPH074060A (en) 1993-06-14 1993-06-14 Lift-up execution equipment for multistoried building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5142096A JPH074060A (en) 1993-06-14 1993-06-14 Lift-up execution equipment for multistoried building

Publications (1)

Publication Number Publication Date
JPH074060A true JPH074060A (en) 1995-01-10

Family

ID=15307339

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5142096A Pending JPH074060A (en) 1993-06-14 1993-06-14 Lift-up execution equipment for multistoried building

Country Status (1)

Country Link
JP (1) JPH074060A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777037A (en) * 2011-05-13 2012-11-14 中国建筑第八工程局有限公司 Simple and practical hoisting construction method of long-span steel girder
KR101326793B1 (en) * 2011-09-09 2013-11-11 주식회사 라이즈글로벌 Elevating work platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777037A (en) * 2011-05-13 2012-11-14 中国建筑第八工程局有限公司 Simple and practical hoisting construction method of long-span steel girder
KR101326793B1 (en) * 2011-09-09 2013-11-11 주식회사 라이즈글로벌 Elevating work platform

Similar Documents

Publication Publication Date Title
JP2927320B2 (en) How to assemble a large hanging boiler
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
JPH074060A (en) Lift-up execution equipment for multistoried building
JPH0547704B2 (en)
JP2618171B2 (en) Telescopic strut
JP3700950B2 (en) Support
JP3187618B2 (en) How to assemble beam reinforcement
JPH07331882A (en) Construction method for multi-storied suspension structure
JP2592980B2 (en) Construction method of steel frame material for high-rise structure
JP2903859B2 (en) Reinforcement structure of column in temporary beam system for building construction
JP6951079B2 (en) Building structure
JPH06101348A (en) Method for constructing tower
JPH10110500A (en) Dome roof construction and execution method thereof
JPH06185120A (en) Construction method for upper structure of roof, etc.
JP2704447B2 (en) Lift-up method using permanent columns
JPH0470468A (en) Transferable form timbering for floor slab execution
CN114575253A (en) Arch rib mounting system
JP2735707B2 (en) Dome construction method
JPH03197734A (en) Lift up method by replacement of scaffold body
JP2884398B2 (en) Construction method of building structure and lifting device of building structure
JPH06220956A (en) Method and apparatus for arrangement of meshed reinforcement
JPH05311749A (en) Construction method of building
JPH04333775A (en) Erection method for steel framed construction of low-rise building
JPH10140840A (en) Push-up device of steel frame structure
JPH1162244A (en) Skeleton construction frame, and method using the same

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees