PE20141630A1 - Metodo para formar un muro de contencion y muro de contencion correspondiente - Google Patents

Metodo para formar un muro de contencion y muro de contencion correspondiente

Info

Publication number
PE20141630A1
PE20141630A1 PE2014000426A PE2014000426A PE20141630A1 PE 20141630 A1 PE20141630 A1 PE 20141630A1 PE 2014000426 A PE2014000426 A PE 2014000426A PE 2014000426 A PE2014000426 A PE 2014000426A PE 20141630 A1 PE20141630 A1 PE 20141630A1
Authority
PE
Peru
Prior art keywords
retaining wall
wall
earth
area
forming
Prior art date
Application number
PE2014000426A
Other languages
English (en)
Inventor
Maurice Garzon
Lavih Garzon
Original Assignee
Lavih Garzon
Maurice Garzon
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lavih Garzon, Maurice Garzon filed Critical Lavih Garzon
Publication of PE20141630A1 publication Critical patent/PE20141630A1/es

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/26Compacting soil locally before forming foundations; Construction of foundation structures by forcing binding substances into gravel fillings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil

Abstract

SE REFIERE A UN METODO PARA FORMAR UN MURO DE CONTENCION CEMENTICIO, EL CUAL COMPRENDE: A) DEFINIR SOBRE UNA SUPERFICIE DE TIERRA UN TRAZADO DEL MURO A SER FORMADO, EL TRAZADO DELIMITANDO UN AREA DE TIERRA A SER EXCAVADA; B) COMPACTAR EL AREA, DENSIFICANDO LA TIERRA DEBAJO Y ADYACENTE AL AREA; C) EXCAVAR LA TIERRA DESDE EL AREA COMPACTADA EN LA ETAPA (B) HASTA UNA PROFUNDIDAD INICIAL, CREANDO UNA CAVIDAD DE MURO QUE COMPRENDE UNA SUPERFICIE DE FONDO Y SUPERFICIES LATERALES; D) COMPACTAR LA SUPERFICIE DE FONDO DE LA CAVIDAD DE MURO Y POSTERIORMENTE EXCAVAR LA TIERRA DESDE LA SUPERFICIE DE FONDO COMPACTADA; E) REPETIR EL PASO (D) HASTA QUE SE ALCANCE UNA PROFUNDIDAD FINAL DE LA CAVIDAD DE MURO; Y F) LLENAR EN PARTE LA CAVIDAD DE MURO CON UN MATERIAL CEMENTICIO PARA FORMAR EL MURO DE CONTENCION
PE2014000426A 2011-09-27 2012-09-27 Metodo para formar un muro de contencion y muro de contencion correspondiente PE20141630A1 (es)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US201161539547P 2011-09-27 2011-09-27
US201261611085P 2012-03-15 2012-03-15

Publications (1)

Publication Number Publication Date
PE20141630A1 true PE20141630A1 (es) 2014-11-06

Family

ID=47994077

Family Applications (1)

Application Number Title Priority Date Filing Date
PE2014000426A PE20141630A1 (es) 2011-09-27 2012-09-27 Metodo para formar un muro de contencion y muro de contencion correspondiente

Country Status (18)

Country Link
US (1) US8898996B2 (es)
EP (1) EP2761098B1 (es)
JP (1) JP6166264B2 (es)
KR (1) KR20140075767A (es)
CN (1) CN103958780B (es)
AP (1) AP2014007534A0 (es)
AU (1) AU2012315417B2 (es)
BR (1) BR112014006774A2 (es)
CA (1) CA2806224C (es)
CL (1) CL2014000733A1 (es)
CO (1) CO6990684A2 (es)
CR (1) CR20140139A (es)
EA (1) EA027027B1 (es)
IL (1) IL231651B (es)
MX (1) MX349515B (es)
PE (1) PE20141630A1 (es)
PH (1) PH12014500697B1 (es)
WO (1) WO2013044386A1 (es)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9328472B2 (en) * 2013-08-07 2016-05-03 R&B Leasing, Llc System and method for determining optimal design conditions for structures incorporating geosynthetically confined soils
US11519152B2 (en) 2018-12-14 2022-12-06 Levee Lock, LLC System and method for installing a membrane-lined buried wall
US10753061B2 (en) 2018-12-14 2020-08-25 Levee Lock, LLC Membrane-lined wall
US10501908B1 (en) 2018-12-14 2019-12-10 Levee Lock, LLC Membrane-lined wall
CN110144908B (zh) * 2019-05-09 2024-03-22 中铁二院工程集团有限责任公司 一种深层注浆加固滑坡构造的构筑方法
RU2725716C9 (ru) * 2019-12-23 2020-09-03 Федеральное государственное бюджетное образовательное учреждение высшего образования "Казанский государственный архитектурно-строительный университет" (КазГАСУ) Способ возведения армированной бетонной стены на 3d-принтере
CN111291492B (zh) * 2020-02-20 2023-01-13 中铁二院工程集团有限责任公司 一种提升既有衡重式挡墙抗滑、抗倾覆安全性的方法
CN112325735B (zh) * 2020-11-05 2021-08-03 吉林大学 一种苗床土块三维空间分布可视化的测量装置和方法
CN112627796B (zh) * 2020-12-22 2022-09-16 五矿盐湖有限公司 一种采卤渠系统的施工方法
CN112873506B (zh) * 2021-01-13 2022-10-21 中建一局集团第三建筑有限公司 一种预制式装配化生态挡墙边肋柱及其施工方法
CN113235970B (zh) * 2021-06-09 2022-07-29 广州市鲁班建筑科技集团股份有限公司 一种对古墓室四周进行分离的结构及其施工方法
US11761161B2 (en) * 2021-07-22 2023-09-19 Precast Concrete Concepts, LLC. Retaining wall extension systems and methods
CN114282393B (zh) * 2022-01-07 2023-05-02 中铁二十三局集团有限公司 一种装配式挡土墙稳定性计算方法

Family Cites Families (44)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1650827A (en) 1927-01-27 1927-11-29 Clyde N Friz Method of compacting earth
US2298837A (en) * 1941-03-22 1942-10-13 James B Oswald Concrete foundation wall form
DE1634603A1 (de) * 1967-08-09 1970-09-17 Franz Schruellkamp Bauunterneh Verfahren zur Herstellung von unterhalb des Erdbodens liegenden Aussenwaenden aus bewaehrtem Beton,insbesondere bei Grenzbebauung oder zur Aussenseite des Bauwerks hin beschraenktem Arbeitsraum
US3898844A (en) 1971-09-24 1975-08-12 Louis Menard Method of compacting made-up ground and natural soil of mediocre quality
AU526267B2 (en) * 1978-07-13 1982-12-23 Freyssinet International (Stup) Reinforced earth structures
US4504176A (en) * 1982-06-02 1985-03-12 Byggnads-& Industriservice Ab Binab Method for compacting compactable soils by vibration
US4557634A (en) * 1983-01-11 1985-12-10 Henri Vidal Wall structure and method of construction
US5139369A (en) * 1985-09-12 1992-08-18 Jaecklin Felix Paul Wall with gravity support structure, building element and method for construction thereof
EP0393032A4 (en) * 1987-06-12 1991-05-08 Foundation Technology (Aust) Pty. Ltd. Reinforcement for continuously-cast concrete walls
US4818142A (en) 1987-11-13 1989-04-04 Cochran James C Method and apparatus for constructing a walled pool excavation
JPH02164937A (ja) 1988-12-16 1990-06-25 Shimizu Corp 抗土圧壁
DE69003892T2 (de) * 1989-07-10 1994-05-11 Trevi Spa Verfahren zur Ausführung von geraden oder kreisförmigen monolitischen Strukturwänden und Maschine zur Durchführung eines solchen Verfahrens.
US4974349A (en) * 1989-11-02 1990-12-04 Robert Timmons Backhoe compactor apparatus
JPH06173223A (ja) 1991-04-01 1994-06-21 Hirose Giken Kk 吸音板
JPH04336117A (ja) 1991-05-10 1992-11-24 Ebine Gisuke 山留め安定工法
US5193324A (en) 1992-03-12 1993-03-16 Fellows Richard R Concrete beam reinforcement system
US5537788A (en) * 1992-08-28 1996-07-23 Jte, Inc. System and method for widening a highway and supporting a sound wall
JPH0681354A (ja) 1992-09-04 1994-03-22 Kajima Corp 地下構造躯体の構築方法
JPH06173214A (ja) 1992-12-07 1994-06-21 Nippon Steel Corp 鉄道用踏切
JPH06228947A (ja) * 1993-02-01 1994-08-16 Taisei Corp 廃棄物埋立地盤における山止め壁の構築方法
JP2543327B2 (ja) * 1994-04-22 1996-10-16 憲士 中山 擁壁構造及び擁壁構築工法
JPH10131175A (ja) 1996-10-31 1998-05-19 Tenox Corp 山留め壁及びその構築方法
JPH10298973A (ja) * 1997-04-23 1998-11-10 Shimizu Corp 地中連続壁
US6089792A (en) * 1997-12-19 2000-07-18 Khamis; Suheil R. Reinforced retaining wall
JP3669247B2 (ja) 2000-02-17 2005-07-06 大成建設株式会社 軟弱砂質土地盤の山留めアンカー方法
JP2004092097A (ja) * 2002-08-30 2004-03-25 Jfe Civil Engineering & Construction Corp 打設材打設方法
FR2860811A1 (fr) * 2003-10-13 2005-04-15 Freyssinet Int Stup Ouvrage en sol renforce et procede pour sa construction
JP4020858B2 (ja) 2003-11-21 2007-12-12 株式会社福田組 地下構造物の製造方法
JP2005207144A (ja) 2004-01-23 2005-08-04 Takenaka Komuten Co Ltd 連続壁形成方法
JP2006037527A (ja) * 2004-07-28 2006-02-09 Mitsubishi Kagaku Sanshi Corp 軽量盛土およびその施工方法
JP4612356B2 (ja) * 2004-08-17 2011-01-12 株式会社クラハラ のり面の造成方法
CA2501773C (en) * 2005-03-22 2012-06-19 Ecoroads Inc. Method of site preparation in environmentally sensitive areas
US7114887B1 (en) 2005-11-14 2006-10-03 Earth Reinforcement Technologies, Llc Modular block anchoring techniques
CN1837506B (zh) * 2006-04-12 2012-02-15 上海市政工程设计研究总院 一种在运营中的隧道上方开挖箱形结构的施工方法
GB2437960B (en) * 2006-05-08 2008-08-13 Aqs Holdings Ltd Ground engineering method
US20070286688A1 (en) * 2006-06-08 2007-12-13 Bradley David A Retaining wall having modular panels
FR2913436B1 (fr) * 2007-03-05 2009-05-29 Terre Armee Internationale Soc Ouvrage en sol renforce et elements de renfort pour sa construction
JP4853429B2 (ja) * 2007-08-29 2012-01-11 株式会社大林組 覆工板の支持構造、覆工板の支持方法
CN101139838B (zh) 2007-10-15 2010-09-01 上海市隧道工程轨道交通设计研究院 高承压水地区超深基坑的施工方法
KR100866162B1 (ko) 2008-08-14 2008-10-30 이재호 의자형 자립식 흙막이벽의 시공방법
CN101806055B (zh) * 2009-02-13 2011-09-21 梁闽 真空预压联合刚性桩复合地基加固方法
US20100303555A1 (en) * 2009-06-02 2010-12-02 Allan John Herse Concrete block for wall, walls having such blocks, and methods
CN101718099B (zh) * 2009-11-14 2011-08-31 欧阳甘霖 静压地下连续墙自动成墙装置及方法
AU2010364506B2 (en) * 2010-11-26 2017-03-02 Terre Armee Internationale Facing element with integrated compressibility

Also Published As

Publication number Publication date
CR20140139A (es) 2014-06-06
EA027027B1 (ru) 2017-06-30
EP2761098A4 (en) 2015-05-27
BR112014006774A2 (pt) 2017-03-28
WO2013044386A1 (en) 2013-04-04
MX2014003484A (es) 2015-02-18
JP2014531539A (ja) 2014-11-27
CN103958780B (zh) 2017-08-25
EP2761098B1 (en) 2016-06-01
IL231651B (en) 2018-02-28
US20140215959A1 (en) 2014-08-07
EP2761098A1 (en) 2014-08-06
US8898996B2 (en) 2014-12-02
EA201490691A1 (ru) 2014-08-29
AU2012315417B2 (en) 2015-09-10
CN103958780A (zh) 2014-07-30
CO6990684A2 (es) 2014-07-10
PH12014500697B1 (en) 2014-05-12
CA2806224C (en) 2014-03-18
CA2806224A1 (en) 2013-03-27
JP6166264B2 (ja) 2017-07-19
KR20140075767A (ko) 2014-06-19
AP2014007534A0 (en) 2014-03-31
CL2014000733A1 (es) 2014-10-10
MX349515B (es) 2017-08-02
AU2012315417A1 (en) 2013-05-09
IL231651A0 (en) 2014-05-28

Similar Documents

Publication Publication Date Title
PE20141630A1 (es) Metodo para formar un muro de contencion y muro de contencion correspondiente
PH12018550061A1 (en) Method for forming a stable foundation ground
CO2021003362A2 (es) Método de consolidación de la lechada para pilote prefabricado con guía de revestimiento de pozo completo y pilote prefabricado para ello
GB2537317A (en) Soil and rock grouting using a hydrajetting tool
PH12017501665A1 (en) Hard road construction method for natural groundwater recharge
MX2019015001A (es) Muelle de combinacion.
CO7550088A1 (es) Sistema de desplazamiento de fluido empleando una bomba gerotor
AU2014393189A1 (en) Method for filling open stope with aeolian sand in shallow coal seam in western desertified mining areas
CL2015000769A1 (es) Método para producir una estructura reforzada en el suelo.
AR095105A1 (es) Métodos para producir lechadas de cemento resistentes a la migración de fluidos
LT2014085A (lt) Teleskopinės klojinių sistemos įrenginys taškinėms iškasoms kasti ir jo panaudojimo būdas
KR20180084293A (ko) 매입말뚝 구조체 및 그 시공 방법
CR20160148A (es) Métodos y aparatos para la compactación de tierra y materiales granulares
EA201600052A1 (ru) Способ сооружения сваи с уширением
TN2014000125A1 (en) Method for forming a retaining wall, and corresponding retaining wall
AR098356A1 (es) Procedimiento de fracturación de rocas
UA52255U (ru) Способ рекультивации земель
CR20160011A (es) Procedimiento para ampliación y estabilización de terrenos planos en zonas de topografía accidentada
UA86637U (ru) Способ возведения насыпи на болотных грунтах
UA97150C2 (ru) Способ рекультивации земель
UA111289C2 (uk) Спосіб засипки відробленого глибокого кар'єру
UA90151U (ru) Способ усиления железобетонного основания пола
CL2011000082A1 (es) Metodo constructivo estructural para viviendas economicas de geometria simple o formas compactas, de un solo nivel, que combina tierra apisonada con la tecnica del post-tensado que comprende engrosar y reforzar las esquinas del muro con un tablon de madera de 45º para generar una esquina triangulo; sistema constructivo estructural.
UA103342U (uk) Спосіб зведення монолітних фундаментів мілкого закладання по принципу "ластівчина хвоста"
RU2013116307A (ru) Способ проведения крутой траншеи

Legal Events

Date Code Title Description
FG Grant, registration