KR20220024070A - The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time - Google Patents

The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time Download PDF

Info

Publication number
KR20220024070A
KR20220024070A KR1020217041259A KR20217041259A KR20220024070A KR 20220024070 A KR20220024070 A KR 20220024070A KR 1020217041259 A KR1020217041259 A KR 1020217041259A KR 20217041259 A KR20217041259 A KR 20217041259A KR 20220024070 A KR20220024070 A KR 20220024070A
Authority
KR
South Korea
Prior art keywords
basement
floor
construction
constructed
core part
Prior art date
Application number
KR1020217041259A
Other languages
Korean (ko)
Inventor
양경옥
Original Assignee
양경옥
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양경옥 filed Critical 양경옥
Publication of KR20220024070A publication Critical patent/KR20220024070A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

본 발명은 건설공사 지하층 역타공법 탑다운에서의 지하 골조공사 기간을 단축하기 위한 것으로, 지하 수직부재(코어부, 기둥)를 하나 걸러 번갈아 가면서 아래층으로 시공하며 이후에는 남은 수직부재를 동시에 시공하는 공사방법을 제공하여 공사기간을 단축할 수 있도록 한다.
흙막이를 설치하고 지하 기둥말뚝을 시공한 후, 지하 1층 터파기 및 지상 1층 바닥을 시공하는 제1단계 ;
지하층 슬라브를 아래층으로 시공하면서 상향 시공되는 지상층 코어부를 지지하기 위하여 지하 1개층 코어부를 먼저 시공하는 제2단계 ;
지하 수직부재를 하나 걸러 번갈아 가며 하향으로 시공하는 제3단계 ;
최하층 매트 또는 기초를 시공한 후, 남은 잔여층 지하 부직부재를 동시에 시공하는 단계 ;
로 이루어져 지하 수직부재를 단축함으로써 이후의 지상 골조 및 마감공사를 조기에 착수할 수 있게 되어 전체 공사기간을 단축하는 것을 특징으로 한다.
The present invention is to shorten the period of underground framing construction in the top-down of the basement level reverse perforation method of construction work, and the construction of underground vertical members (core part, column) alternately every other one to the lower floor, and then to construct the remaining vertical members at the same time method to shorten the construction period.
After installing the retaining wall and installing the underground pillar piles, the first step of excavating the first basement floor and constructing the first floor floor above the ground;
a second step of constructing the first basement core in order to support the above-ground core to be constructed upward while constructing the basement slab as a lower floor;
A third step of constructing the underground vertical members alternately downward;
After constructing the lowest floor mat or foundation, simultaneously constructing the remaining basement nonwoven member;
It is characterized in that by shortening the underground vertical member, it is possible to start the later above-ground framing and finishing work at an early stage, thereby shortening the overall construction period.

Description

하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 공사방법The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time

본 발명은 건설공사 역타공법 탑다운에서의 지하 골조공사 기간을 단축하기 위한 것으로, 더욱 상세하게는 지하 수직부재를 하나 걸러 번갈아 가면서 아래로 시공하고 이후 매트, 기초 시공 후에는 남은층의 수직부재를 동시에 일괄 시공하는 공사방법을 제공하여 지하 수직부재 및 전체 공사기간을 단축할 수 있도록 한다.The present invention is to shorten the period of underground framing construction in the reverse drilling method top-down construction work, and more specifically, construct an underground vertical member alternately every other time, and then install the vertical member of the remaining floor after the mat and foundation construction. At the same time, it is possible to shorten the underground vertical member and the overall construction period by providing a construction method for collective construction.

역타공법(탑다운, Top-down)은 지하층으로 골조공사를 형성해 내려가면서 동시에 지상층 골조공사를 시공하여 공사기간을 단축하는 공법이다.The reverse perforation method (top-down) is a method of shortening the construction period by constructing a framing work on the basement floor while simultaneously constructing a framing work on the ground floor.

일반적인 지하층 역타공법의 시공순서는 흙막이와 기둥을 설치하고 각 층 터파기를 한 후 슬라브를 시공해 내려가면서, 마지막으로 최하층 기초 또는 매트(mat)를 시공하며 지하 4층 내지 7층 깊이를 갖는다.The general order of construction of the basement level reverse drilling method is to install retaining walls and columns, excavate each floor, construct slabs, and finally construct the lowest floor foundation or mat, and have a depth of 4 to 7 floors underground.

지하 수직부재 중 말뚝 기둥은 공사초기에 시공되고 지상층 골조공사를 위하여 지하 1개층 코어부가 시공되고 나머지 수직부재는 기초 또는 매트 타설 후 순타(아래층부터 위층으로)로 시공된다.Among the vertical members in the basement, pile columns are constructed at the initial stage of construction, the core part of the first basement floor is constructed for the framing work of the ground floor, and the remaining vertical members are constructed by rolling (from the lower floor to the upper floor) after placing the foundation or mat.

이때 지상층 골조공사는 지하층과 동시에 시공되지만 기초, 매트 시공전까지 올라가는 층수와 이후 지하 수직부재의 완료시까지 올라가는 층수가 구조적으로 제한이 되어 있다. 예를 들면 기초, 매트 타설전까지는 지상 8층 슬라브까지만 가능하고 지하 수직부재가 완료되기 전까지는 지상 15층 슬라브까지만 가능하고 지하 수직부재가 완료된 이후에는 제한없이 옥상층까지 올라갈 수 있는 공사 제약 조건이 부여된다. At this time, although the above-ground framing work is constructed at the same time as the basement, the number of floors that rise before the foundation and mat construction and the number of floors that rise until the completion of the basement vertical member is structurally limited. For example, up to the 8th floor slabs are possible until the foundation and mat are placed, and the 15th floor slabs are allowed until the basement vertical members are completed. is granted

따라서 지하층 골조공사 기간이 증가하면 지상층 골조는 8층 또는 15층 까지만 시공하고 중단한 후 대기하여야 한다. 반대로 지하층 골조공사가 빨라지면 지상층 골조공사도 빨라져 전체 공사기간은 지하층 공사에 크게 영향을 크게 받는다.Therefore, if the period of basement frame construction increases, the above ground level frame should be constructed only up to the 8th or 15th floor, then stop and wait. Conversely, if the basement level construction is accelerated, the above ground level frame construction will also be accelerated, so the overall construction period is greatly affected by the underground floor construction work.

특히 지상층 골조는 기준층 1개층 시공에 6일 내지 7일 정도 소요되어 1개월에 4개층 이상을 시공하지만 지하층은 한 개층에 1.5개월 또는 2개월이 소요되어 지하층의 공사속도가 상대적으로 느리다.In particular, in the case of the ground floor, it takes about 6 to 7 days to construct one base floor, so more than four floors are constructed in a month, but for the basement floor, it takes 1.5 months or 2 months for one floor, so the construction speed of the basement is relatively slow.

이러한 종래의 역타공법 탑다운에서의 문제점은 다음과 같다.The problems in the conventional reverse punching method top-down are as follows.

종래의 지하 시공순서는 흙막이, 말뚝, 각층 하향 터파기 및 슬라브 시공, 최하층 기초 또는 매트 시공, 지하 수직부재의 상향의 순타시공으로 진행된다.The conventional underground construction sequence consists of retaining walls, piles, digging and slab construction on each floor, foundation or mat construction on the lowest floor, and upward construction of underground vertical members.

여기서 지하 수직부재는 기초 또는 매트 타설 후 순타(아래층에서 위층으로 시공)로 진행되는 특징을 가진다. 지하 수직부재의 공사기간은 1개층 시공에 20일 내지 25일이 소요되고 지하 6층인 경우 4개월 내지 5개월이 소요된다.Here, the underground vertical member has the characteristic that it proceeds in a sequence (construction from the lower floor to the upper floor) after the foundation or the mat is poured. The construction period of the underground vertical member takes 20 to 25 days for one floor and 4 to 5 months for the sixth basement.

지하 수직부재는 기초 또는 매트 타설 후 순타(아래에서 위로)로 시공한다. 지하 수직부재가 완성된 이후 지상층이 계속 올라갈 수 있으므로 지하 수직부재는 공사기간을 결정하는 크리티컬 패스(주공정선, critical path)이다.Underground vertical members are installed by rolling (bottom to top) after placing the foundation or mat. Since the ground floor can continue to rise after the underground vertical member is completed, the underground vertical member is a critical path that determines the construction period.

한편 지상층 골조는 층당 싸이클이 6~7일 정도로 공사속도가 빠른 반면 지하층 매트 타설 시점(예들 들어 지상 8층)과 지하 수직부재 완성 시점(지상 15층)까지 올라갈 수 있는 층수가 제한되어 있어 지상 8층과 지상 15층의 변곡점에서 공사중단 및 공사대기가 발생하게 된다.On the other hand, the construction speed of the above-ground structure is fast, with a cycle of 6-7 days per floor, while the number of floors that can be climbed up to the time of placing the basement floor mat (eg, the 8th floor above the ground) and the completion of the underground vertical member (15th floor above the ground) is limited. At the inflection point of the first floor and the 15th floor, construction stops and construction waiting occurs.

지하 수직부재 공사 기간중에는 각 층 공사가 여유없이 연속적으로 원활하게 이루어져야 한다는 조건을 달성해야 한다. 만약 한개 층이라도 지연이 발생하는 경우, 지상층 공사는 그만큼 지연되게 된다. 따라서 지하 수직부재를 연속적으로 단기간에 원활하게 시공해야 하는 기존의 공법은 공기지연 리스크가 매우 크다.During the underground vertical member construction period, the condition that the construction of each floor should be carried out continuously and smoothly without any leeway must be achieved. If even one floor is delayed, the ground floor construction will be delayed by that much. Therefore, the existing construction method, which requires continuous and smooth construction of underground vertical members in a short period of time, has a very high risk of delay.

역타공법은 지하층을 시공하면서 동시에 지상층을 시공하여 공사기간을 단축하는 장점이 있다. 그러나 지하층 공사속도에 따라 지상층이 일정 층수 이상 올라갈 수 없는 구조적인 제약 조건에 따라 공기가 지하 골조공사에 크게 영향을 받고 있는 실정이다.The reverse drilling method has the advantage of shortening the construction period by constructing the ground floor while constructing the basement floor. However, depending on the construction speed of the basement, the air quality is greatly affected by the construction of the basement due to the structural constraint that the above-ground floor cannot go up to more than a certain number of floors.

관련출원은 다음과 같다.The related applications are as follows.

출원번호/일자 1020110024619 (2011.03.18), 출원인 주식회사 한빛구조엔지니어링, 등록번호/일자 1012420170000 (2013.03.05), 발명의 명칭 코어내부 격자형 인방보와 우선시공되는 지상층 코어부를 이용한 지상 및 지하구조물 병행Application No./Date 1020110024619 (2011.03.18), Applicant Hanbit Structural Engineering Co., Ltd., Registration No./Date 1012420170000 (2013.03.05), Title of Invention Parallel above-ground and underground structures using lattice-type lintel beams inside the core and the priority-constructed above-ground core

구축공법, construction method,

출원번호 특1995-0003110, 출원일자 1995년02월18일, 건축구조물의 지상층 및 지하층 골조의 병행 시공방법Application No. 1995-0003110, Application date February 18, 1995, Method of parallel construction of above-ground and basement structures of building structures

출원번호 10-2003-0037296, 출원일자 2003년06월10일, 철근콘크리트구조와 철골철근콘크리트구조의 혼합구조를갖는 건축구조물 및 그의 동시시공방법Application No. 10-2003-0037296, filing date June 10, 2003, Building structure having a mixed structure of reinforced concrete structure and steel frame reinforced concrete structure and method for simultaneous construction thereof

출원번호 10-2011-0087835, 출원일자 2011년08월31일, 등록번호 10-1101182, 등록일자 2011년12월26일, 지하구조물의 역타공법Application No. 10-2011-0087835, Application Date August 31, 2011, Registration No. 10-1101182, Registration Date December 26, 2011, Reverse perforation method of underground structures

출원번호 10-2013-0004918, 출원일자 2013년01월16일, 등록번호 10-1426511, 등록일자 2014년07월29일, 건물의 지하구조물 축조 시 사용되는 가설 골조시스템과 이를 이용한 역타공법Application No. 10-2013-0004918, Application Date January 16, 2013, Registration No. 10-1426511, Registration Date July 29, 2014, Temporary frame system used in the construction of underground structures of buildings and reverse drilling method using the same

본 발명은 상기와 같은 종래 기술에 따른 문제점을 해결하기 위하여 창안된 것으로서, 역타공법에서 지하 수직부재의 공사기간을 단축하여 지상층 골조공사를 연속적으로 진행할 수 있도록 한다.이에 따라 전체 공사기간을 단축하도록 한다.The present invention was devised to solve the problems of the prior art as described above, and shortens the construction period of the underground vertical member in the reverse perforation method so that the above-ground framing work can be continuously carried out. Accordingly, to shorten the overall construction period do.

상기한 목적을 달성하고 상술한 종래기술의 문제점을 해결하기 위하여, 본 발명에 따른 하나 걸러 번갈아 시공되는 지하 수직부재 공사방법은 지하 수직부재를 하나 걸러 번갈아 하향으로 시공하고, 이후에는 잔여 수직부재를 상기 앞서 시공된 수직부재 사이로 분산하여 동시에 끼워서 시공한다.In order to achieve the above object and solve the problems of the prior art, the underground vertical member construction method alternately constructed according to the present invention constructs every other underground vertical member downward alternately, and thereafter, the remaining vertical members Distributed between the previously constructed vertical members and installed at the same time.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

전체 공정표상에서 다수의 지하 수직부재를 선시공하여 공사기간을 결정하는 주공정선(크리티컬 패스, Criticla path)상에서 배제하므로써 공사기간이 단축된다.The construction period is shortened by pre-constructing a number of underground vertical members on the entire process table and excluding them from the critical path, which determines the construction period.

지하 수직부재를 하나 걸러 시공하므로 기둥의 좌굴길이가 짧아져 보다 많은 지상층을 시공할 수 있어 전체 공사기간이 단축된다.By constructing every other vertical member under the ground, the buckling length of the column is shortened and more ground floors can be constructed, thereby shortening the overall construction period.

지하 수직부재를 하나 걸러 시공하면, 상향으로 시공되는 잔여분을 동시에 각각 시공할 수 있어 전체 공사기간이 단축된다.If every other underground vertical member is constructed, the remainder of the upward construction can be constructed at the same time, thereby shortening the overall construction period.

지하 수직부재를 해당층 슬라브 시공 후 조기에 시공할 수 있어 공사지연이 발생할 여지가 적어 전체 공사기간을 지연시키지 않게 된다.Since the underground vertical member can be constructed early after the construction of the slab for the corresponding floor, there is little room for construction delay and thus the entire construction period is not delayed.

철근조립만을 먼저 시공하고 콘크리트는 동시에 일괄 타설하여 공사기간을 더욱 단축할 수 있다.The construction period can be further shortened by constructing only the rebar assembly first and pouring the concrete at the same time.

종래에는 매트 타설후 지하 6층을 수직부재를 시공한 후 지하 5층, 지하 4층, 지하 3층, 지하 2층의 순서로 순타로 시공하였다. 이에 따라 종래에는 순타로 5개층을 시공하는데 층당 25일인 경우 총 125일이 소요되었으나 본 발명에 따르면 홀수층은 매트 타설전에 이미 완료하였으며 매트 타설 후에는 짝수층인 지하 6층, 지하 4층, 지하 2층을 동시에 시공하여 25일만 소요된다. 그 결과 종래에는 매트 타설 후 125일 소요되었으나 본 발명에 따르면 25일이 소요되므로 결과적으로 100일이 단축된다. 이에 따라 전체 공사기간도 약 100정도 단축된다.Conventionally, after placing the mat, the vertical member was installed on the 6th basement floor, and then the 5th basement floor, the 4th basement floor, the 3rd basement floor, and the 2nd basement floor were installed sequentially in that order. Accordingly, conventionally, it took a total of 125 days to construct 5 floors in Sunta-ro, but 25 days per floor. It takes only 25 days to construct the layers at the same time. As a result, in the prior art, it took 125 days after placing the mat, but according to the present invention, it takes 25 days, so 100 days are shortened as a result. As a result, the overall construction period is shortened by about 100.

본 발명에 따르면 지하 6층, 지상 39층 오피스 빌딩에서 39개월 대비 36개월로 약 3개월(전체공기의 8% 정도)의 공기단축 효과를 나타낸다.According to the present invention, in an office building with 6 floors underground and 39 floors above ground, it shows an effect of shortening the period of about 3 months (about 8% of the total air) from 39 months to 36 months.

오피스, 오피스텔 등에서의 전체 공사 기간의 단축은 건설사 측면에서의 공사관리비, 현장경비 등의 공사비 절감과 함께 건물주 측면에서의 조기 분양, 임대료 수입, 매출 추가 발생(년 매출의 25%) 등 높은 경제적 효과를 갖는다. The reduction of the overall construction period in offices and officetels has high economic effects such as reduction of construction costs such as construction management costs and field expenses from the construction company side, and early sales, rental income, and additional sales (25% of annual sales) from the building owner’s side. has

도 1은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재 시공방법의 전체 흐름도.
도 2 내지 도 3은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재 시공방법의 39층 오피스 건물의 공정표의 일예.
도 4는 상기 도 2의 본 발명에 따른 지하 수직부재 공정의 확대공정표.
도 5는 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 가장 늦은 착수시점의 공정표의 일예.
도 6은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 가장 빠른 착수시점과 가장 늦은 착수시점의 비교 공정표.
도 7은 종래 기존공법의 지하 수직부재 시공방법의 전체 흐름도.
도 8 내지 도 9는 종래 기존 공법을 적용한 39층 오피스 건물의 공정표의 일예.
도 10은 상기 도 8의 종래 기존공법의 지하 수직부재 공정의 확대공정표.
도 11은 종래 기존공법과 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 공정을 비교한 비교공정표.
도 12내지 도 13은 종래 기존공법의 전체공정표(도 8,9)와 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 전체공정표(도 2,3)을 일정차이를 각 층 별로 비교한 일정차이 비교표.
도 14는 종래 기존공법의 전체공정표(도 8,9)와 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 전체공정표(도 2,3)을 S-Curve 형태로 비교한 공정비교 그래프.
1 is an overall flow chart of the underground vertical member construction method to be constructed every other one according to the present invention.
2 to 3 are an example of a process table of a 39-story office building of the underground vertical member construction method to be constructed every other one according to the present invention.
Figure 4 is an enlarged process table of the underground vertical member process according to the present invention of Figure 2;
Figure 5 is an example of the process table of the latest starting point of the underground vertical member to be constructed every other according to the present invention.
Figure 6 is a comparative process table of the earliest starting point and the latest starting point of the underground vertical member constructed every other one according to the present invention.
7 is an overall flowchart of a method of constructing an underground vertical member of a conventional conventional method.
8 to 9 are an example of a process table of a 39-story office building to which the conventional method is applied.
Figure 10 is an enlarged process table of the underground vertical member process of the conventional conventional method of Figure 8.
11 is a comparative process table comparing the process of the underground vertical member constructed every other one according to the present invention with the conventional conventional construction method.
12 to 13 are a comparison of the schedule difference for each floor by comparing the schedule difference between the overall process table of the conventional conventional method ( FIGS. 8 and 9 ) and the overall process table of the underground vertical member constructed every other one according to the present invention ( FIGS. 2 and 3 ). comparison table.
14 is a process comparison graph comparing the overall process table of the conventional conventional method ( FIGS. 8 and 9 ) and the overall process table of the underground vertical member constructed every other one according to the present invention ( FIGS. 2 and 3 ) in an S-Curve form.

발명의 실시를 위한 최선의 형태Best mode for carrying out the invention

이하, 본 발명에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하층 수직부재 시공방법을 상세히 설명한다.Hereinafter, the construction method of the basement vertical member of the reverse drilling method alternately constructed according to the present invention will be described in detail.

도 1은 본 발명의 일실시예에 따른 하나 걸러 시공되는 역타공법의 지하 수직부재 시공방법의 전체 흐름도이다. 실시 대상 프로젝트는 지하 6층, 지상 39층의 SRC 오피스 빌딩이다.1 is an overall flow chart of the underground vertical member construction method of the reverse perforation method constructed every other one according to an embodiment of the present invention. The target project is an SRC office building with 6 stories below the ground and 39 above.

도 1을 참조하면, 본 실시예에 따른 지하 수직부재의 시공방법은 흙막이 시공단계(S10)에서는 건물 지하층 외벽을 기준으로 지하에 흙막이를 시공하며 슬러리 월, CIP, H-Pile 및 토류판 등이 시공된다.Referring to FIG. 1, in the construction method of the underground vertical member according to this embodiment, in the retaining construction step (S10), the retaining wall is constructed in the basement based on the outer wall of the basement floor of the building, and the slurry wall, CIP, H-Pile, and earth plate are constructed. do.

지하 말뚝 시공단계(S20)에서는 역타공법에서 지하층 슬라브를 지지하기 위하여 건물의 기둥을 지상에서 기초와 매트까지 시공하며, PRD, RCD가 시공된다.In the underground pile construction step (S20), the pillars of the building are constructed from the ground to the foundation and the mat to support the basement slab in the reverse drilling method, and PRD and RCD are constructed.

1층 슬라브 시공단계(S30)에서는 지하 1층을 터파기하고 상기 (S20)단계에서 시공한 기둥을 이용하여 철골보, 데크플레이트 및 콘크리트를 타설하여 1층 슬라브를 완성한다.In the first-floor slab construction step (S30), the first-floor slab is completed by excavating the first underground floor and pouring the steel beam, deck plate and concrete using the column constructed in the step (S20).

지하 1층 슬라브 시공단계(S40)에서는 지하 2층을 터파기하고 1층과 마찬가지로 지하 1층 슬라브를 완성한다.In the first basement slab construction step (S40), the second basement is excavated and the slab of the first basement is completed as in the first floor.

지하 1층 수직부재(코어부, 기둥) 시공단계(S50)에서는 상기(S40) 단계에서 시공한 지하 1층 슬라브로부터 지하 1층 코어부를 완성하여 지상층으로 코어부 골조가 상향 시공될 수 있도록 한다.In the first basement vertical member (core part, column) construction step (S50), the core part of the first basement level is completed from the first basement floor slab constructed in the step (S40) so that the core part frame can be constructed upwards to the above-ground floor.

지상층 골조(1차) 시공단계(S60)에서는 상기 (S50)단계에서 시공한 지하 1층 코어부, 기둥으로 부터 지상층 코어부와 기둥을 완성한다. 예를 들어 PRD 파일의 구조조건상 매트 시공전까지 지상 8층까지만 골조를 시공할 수 있다면, 상기 지상층 골조(1차) 단계에서는 지상 8층까지 골조를 시공한다.In the above-ground frame (first) construction step (S60), the above-ground core part and the pillar are completed from the first basement core part and the column constructed in the step (S50). For example, if it is possible to construct a frame up to the 8th floor before the mat construction due to the structural condition of the PRD file, in the above-ground level framing (1st) step, the frame is constructed up to the 8th floor above the ground.

지하 2층 슬라브 시공단계(S70)에서는 상기 (S40)단계에 이어 하향으로 지하 3층 터파기를 한 후 지하 2층 슬라브를 시공한다.In the second basement slab construction step (S70), after excavating the third basement floor downward following the step (S40), the second basement slab is constructed.

지하 3층 슬라브 시공단계(S80)에서는 상기 (S70)단계에 이어 하향으로 지하 4층 터파기를 한 후 지하 3층 슬라브를 시공한다.In the 3rd basement slab construction step (S80), after excavating the 4th basement floor downward following the (S70) step, the 3rd basement slab is constructed.

본 발명의 특징에 따른 지하 3층 수직부재 시공단계(S90)에서는 상기(S80) 단계에서 시공한 지하 3층 슬라브로부터 지하 3층 코어부를 완성한다. 상기 (S50)단계에서 지하 1층 코어부를 시공한 후 지하 2층 코어부 시공을 생략하고 한 층 걸러 지하 3층 코어부를 시공하면 순타로 시공할 수 있어 시공이 용이하다. In the construction step (S90) of the vertical member on the 3rd basement level according to the characteristics of the present invention, the core part on the 3rd basement level is completed from the 3rd basement floor slab constructed in the step (S80). If, after constructing the first basement core part in step (S50), construction of the second basement core part is omitted, and the third basement core part is constructed every other floor, the construction can be done in a straight line, which facilitates construction.

종래에는 지하 3층 코어부는 매트 타설 후 지하 6층부터 순타로 시공하였으나, 본 발명에 따라 지하 3층 수직부재는 지하 1층 코어부 시공 후 한 층 걸로 먼저 시공하므로써 공사기간을 단축하는 효과를 갖는다.Conventionally, the core part of the 3rd basement floor was constructed sequentially from the 6th floor after the mat was placed, but according to the present invention, the vertical member of the 3rd basement floor is first constructed one floor after the core part of the basement 1st floor has been constructed, thereby shortening the construction period.

지하 4층 슬라브 시공단계(S100)에서는 상기(S80) 단계에 이어 하향으로 지하 5층 터파기를 한 후 지하 4층 슬라브를 시공한다.In the 4th basement slab construction step (S100), after excavating the 5th basement floor downward following the step (S80), the 4th basement slab is constructed.

지하 5층 슬라브 시공단계(S110)에서는 상기(S100) 단계에 이어 하향으로 지하 6층 터파기를 한 후 지하 5층 슬라브를 시공한다.In the 5th basement slab construction step (S110), after excavating the 6th basement floor downward following the step (S100), the 5th basement slab is constructed.

본 발명에 특징에 따른 지하 5층 수직부재 시공단계(S120)에서는 상기(S110) 단계에서 시공한 지하 5층 슬라브로부터 지하 5층 코어부를 완성한다. 상기 (S90)단계에서 지하 3층 코어부를 시공한 후 지하 4층 코어부 시공을 생략하고 한 층 걸러 지하 5층 코어부를 시공하면 순타로 시공할 수 있다. In the 5th basement vertical member construction step (S120) according to the characteristics of the present invention, the core part of the 5th basement is completed from the 5th basement slab constructed in the step (S110). After constructing the core part on the 3rd basement level in the step (S90), the construction of the core part on the 4th basement level is omitted and the core part on the 5th basement floor is constructed every other floor.

종래에는 지하 5층 코어부는 매트 타설 후 지하 6층부터 순타로 시공하였으나, 본 발명에 따라 지하 5층 수직부재는 지하 3층 코어부 시공 후 한 층 걸로 먼저 시공하므로써 공사기간이 단축되는 특징을 갖는다.Conventionally, the 5th basement core part was constructed sequentially from the 6th basement floor after the mat was poured, but according to the present invention, the 5th basement vertical member is constructed one floor first after the core part of the 3rd basement floor according to the present invention, thereby shortening the construction period.

지하 3층 수직부재 시공단계(S90)와 지하 5층 수직부재 시공단계(S120)는 본 발명의 특징에 따라 매트 타설전에 순타로 한층 걸러 미리 시공하는 방법으로서 공사기간을 단축한다.The 3rd basement vertical member construction step (S90) and the 5th basement vertical member construction step (S120) are a method of pre-constructing every other layer before placing the mat according to the characteristics of the present invention, thereby shortening the construction period.

이후 기초 또는 매트(Mat) 시공단계(S130)에서는 상기 (S110)단계에 이어 하향으로 최종 터파기를 한 후 기초, 매트를 시공한다. 매트가 시공되면, 이제 유턴하여 상향으로 지하층 수직부재와 지상층 골조를 동시에 시공한다. 예를 들어 매트 시공전까지는 지상 골조는 8층까지 올릴 수 있고, 지하 수직부재 완성시까지는 15층까지 시공할 수 있으며 지하 수직부재 완료 후에는 최상층인 지붕층까지 시공할 수 있다.After that, in the foundation or mat construction step (S130), after the final excavation downward following the step (S110), the foundation and the mat are constructed. After the mat is installed, now make a U-turn and construct the basement vertical member and the above-ground frame at the same time. For example, the above-ground frame can be raised up to the 8th floor before mat construction, up to the 15th floor until the basement vertical member is completed, and up to the roof layer, which is the top floor, after the basement vertical member is completed.

기초, 매트가 완성되면(S140), 이제 지하 수직부재(코어부, 기둥)를 시공한다.When the foundation and the mat are completed (S140), now the underground vertical member (core part, column) is constructed.

지하 수직부재중 지하 1층(S50), 지하 3층(S90), 지하 5층(S120)는 본 발명에 따라 하나 걸러 미리 시공하였으므로 남은 수직부재는 지하 6층, 지하 4층, 지하 2층이다. 본 발명에서는 상기 잔여 수직부재(지하 6층, 지하 4층, 지하 2층)를 시공하는데 있어 해당층의 상하로 코어부가 이미 시공되어 있으므로 동시에 일시에 시공할 수 있는 장점과 특징을 갖는다(S150, S160, S170). Of the vertical members in the basement, the first basement floor (S50), the third basement floor (S90), and the fifth basement floor (S120) were pre-constructed according to the present invention, so the remaining vertical members are the 6th basement floor, the 4th basement floor, and the second basement floor. In the present invention, in constructing the remaining vertical members (6th basement floor, 4th basement floor, and 2nd basement floor), since the core part has already been constructed above and below the corresponding floor, it has the advantage and feature that it can be constructed at the same time (S150, S160, S170).

종래에는 지하 6층 코어부를 시공한 후, 지하 5층을 시공하고 이어서 지하 4층, 지하 3층, 지하 2층 순으로 순서대로 시공해야 했다. 그러나 본 발명에 따르면, 잔여 수직부재(지하 6층, 지하 4층, 지하 2층)를 동시에 시공할 수 있으므로 1개층을 시공하는 기간만 소요된다.Conventionally, after the core part of the 6th basement was constructed, the 5th basement floor was constructed, and then the 4th basement floor, the 3rd basement floor, and the 2nd basement floor were to be constructed in that order. However, according to the present invention, since the remaining vertical members (the 6th basement floor, the 4th basement floor, and the 2nd basement floor) can be simultaneously constructed, only one floor construction period is required.

이에 따라 매트 타설전에는 지하 3층, 지하 5층의 2개 층의 코어부를 먼저 시공하고, 매트 타설후에는 잔여 수직부재(지하6, 4, 2층)를 동시에 시공하므로 종합적으로 4개층을 미리 시공하는 효과를 갖는다. 따라서 1개층 수직부재에 25일이 소요되는 경우, 종래에는 125일이 소요되었으나, 본 발명에 따르면 25일이 소요되어 100일의 전체 공사기간 단축효과를 갖는다. Accordingly, the core of the 3rd basement and 5th basement floors are first installed before the mat is placed, and the remaining vertical members (6th, 4th, and 2nd floors) are installed at the same time after the mat is placed. has the effect of Therefore, when it takes 25 days for one-story vertical member, it takes 125 days in the prior art, but according to the present invention, it takes 25 days, thereby reducing the total construction period of 100 days.

이상과 같이 지하 수직부재가 완성되면(S170), 다음으로 지상층 골조(2차)(S180)이 시작될 수 있다. 예를 들면 지상층 골조(1차)는 지하 수직부재가 완성되기 전까지는 지상 15층까지 시공할 수 있고, 지하 부직부재 완성 이후에는 지상층 골조(2차)(S180)로서 지상 16층부터 최상층(지붕)까지 제약없이 시공할 수 있다.When the underground vertical member is completed as described above (S170), then the above-ground floor framing (secondary) (S180) can be started. For example, the above-ground frame (primary) can be constructed up to the 15th floor above the ground until the underground vertical member is completed, and after the basement non-woven member is completed, the above-ground frame (secondary) (S180) from the 16th floor to the top floor (roof) ) can be constructed without restrictions.

도 2 내지 도 3은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 시공방법의 전체 공정표이다.2 to 3 are overall process tables of the underground vertical member construction method of the reverse drilling method alternately constructed every other according to an embodiment of the present invention.

도 2를 참조하면, 본 실시예는 지하 6층, 지상 39층 오피스 빌딩이며, SRC조, 역타 탑다운 공법이다. 착공일은 2019년 1월 1일이다. Referring to FIG. 2, this embodiment is an office building with 6 stories below the ground and 39 above the ground, and is an SRC group, reverse top-down construction method. The start date is January 1, 2019.

공정표를 참조하면 흙막이 시공단계(공정표상의 왼쪽 첫번째 칼럼의 작업번호 6번)에서는 H-pile / CIP가 시공되며 작업기간은 80일이다. Referring to the process table, H-pile / CIP is constructed in the retaining construction stage (work number 6 in the first column on the left of the process table) and the work period is 80 days.

7번 작업 PRD는 지하층에 다수의 말뚝 기둥을 시공하는 것이며 기간은 70일이다.The 7th PRD is to construct a number of pile columns in the basement, and the period is 70 days.

8번 작업 지하 1층 터파기 및 1층 슬라브는 7번 작업 PRD공사가 완료되면 말뚝에 1층 바닥 철골보를 시공하고 데크 플레이트 및 콘크리트를 타설하는 SRC 공사이며 기간은 50일이다.Work No. 8 Excavation of the basement 1st floor and slab on the 1st floor is an SRC construction that constructs the 1st floor steel beams on piles and pours the deck plates and concrete when the PRD work of No. 7 work is completed. The duration is 50 days.

작업 지하 2층 터파기 및 지하 1층 슬라브 시공(9번 작업, 이하 번호로 표시)은 1층 슬라브(8)가 완료되면 하향으로 지하 2층 터파기를 한 후 지하 1층 슬라브(9)를 시공하는 것이며 기간은 50일이다.In the case of excavating the 2nd basement floor and constructing the 1st basement slab (work 9, indicated by the number below), when the 1st floor slab (8) is completed, dig the 2nd basement floor downward and then construct the 1st basement slab (9) and the period is 50 days.

지하 1층 슬라브(9)가 완성되면, 지하 1층 코어부와 기둥(22)을 시공하여 지상층으로 공사를 진행할 수 있도록 한다. 이에 따라 지하층 하향공사와 지상층 상향공사가 동시에 진행되며, 이를 일반적으로 탑다운(Top-down) 공사라고 한다.When the first basement slab 9 is completed, the first basement core part and the pillar 22 are constructed so that the construction can proceed to the above-ground floor. As a result, both the basement and ground floor upward construction are carried out at the same time, and this is generally referred to as top-down construction.

지하 1층 코어부(22)가 완성되면, 지상 2층 슬라브(25)부터 지상 8층 슬라브(31)까지 연속적으로 작업할 수 있다. 이 때 8층까지의 지상층 하중은 PRD가 받는다. When the first basement core part 22 is completed, it is possible to continuously work from the second-floor slab 25 to the eighth-floor slab 31 above the ground. At this time, the load on the ground floor up to the 8th floor is received by the PRD.

9층 슬라브(32)는 매트 콘크리트(15)가 시공되어야 진행할 수 있으므로, 8층(31) 완료 후 약 4개월간 공사가 중지된다. 구조계산에 따라 PRD가 지상 8층(31)까지의 하중만 지탱할 수 있기 때문에 매트 타설 이후에 9층(32)을 착수할 수 있다.Since the 9-story slab 32 can proceed only when the mat concrete 15 is installed, the construction is stopped for about 4 months after the 8-story 31 is completed. According to the structural calculation, since the PRD can only support the load up to the 8th floor (31) above the ground, the 9th floor (32) can be started after the mat is placed.

아니면 2층부터의 지상층 공사를 약 3개월 정도 늦게 착수하여 8층과 9층사이의 공사대기 기간을 최소화하여 연속적으로 시공하거나 8층까지의 공사를 천천히 진행할 수 있다. Alternatively, the construction of the ground floor from the 2nd floor can be started about 3 months later and the waiting period between the 8th and 9th floors can be minimized to continue construction or proceed slowly to the 8th floor.

상기 지하 1층 슬라브(9)가 완성되면, 다음으로 지하 3층 터파기를 하향으로 한 후 지하 2층 슬라브(10)를 시공하며 기간은 50일이다.When the first basement slab 9 is completed, the second basement slab 10 is constructed after digging the third basement floor downward, and the period is 50 days.

지하 2층 슬라브(10)가 완성되면, 다음으로 지하 4층 터파기를 한 후 지하 3층 슬라브(11)를 시공하며 기간은 50일이다. When the 2nd basement slab 10 is completed, then the 4th basement level is excavated and then the 3rd basement level slab 11 is constructed, and the period is 50 days.

지하 3층 슬라브(11)가 완성되면, 본 발명의 특징에 따라 지하 3층 코어부(20)를 먼저 시공한다. 기존의 공법은 지하 3층 코어부(20)는 매트(15) 완료 후 지하 6층부터 상향으로 시공하고 있다. 따라서 본 발명에 따라 지하 3층 코어부(20)는 기존 공법에 비해 먼저 시공하며, 그에 따라 공사기간이 단축되는 효과가 있다. When the 3rd basement slab 11 is completed, the 3rd basement core part 20 is first constructed according to the characteristics of the present invention. In the existing construction method, the 3rd basement floor core 20 is being constructed upward from the 6th basement floor after the mat 15 is completed. Therefore, according to the present invention, the underground three-story core 20 is constructed first compared to the existing construction method, and thus the construction period is shortened.

지하 1층 코어부(22)를 시공한 후, 그 아래층의 지하 2층 코어부(21)를 건너뛰어 한 층 걸러 지하 3층 코어부(20)를 시공한다. 그 사유는 지하 1층 코어부(22) 시공 후 바로 아래층인 지하 2층 코어부(21)를 역타로 시공하는 것은 연결부의 시공이 어렵기 때문이다. 따라서 지하 1층 코어부(22) 시공 후 지하 3층 코어부(20)를 한 층 걸러 시공하면 위층인 지하 2층이 비어 있기 때문에 지하 3층을 순타로 작업할 수 있어 시공이 용이하다는 특징을 갖는다.After the first basement core part 22 is constructed, the third basement core part 20 is constructed every other floor by skipping the second basement core part 21 of the lower floor. The reason is that it is difficult to construct the connection part by reverse hitting the core part 21 on the second basement floor, which is immediately below after the construction of the core part 22 on the first basement floor. Therefore, if the core part 20 on the 3rd basement is constructed every other floor after the construction of the core part 22 on the 1st basement level, since the 2nd basement, which is the upper floor, is empty, the 3rd basement floor can be worked sequentially, so construction is easy. .

지하 1층 코어부(22)와 지하 3층 코어부(20)가 한층 걸러 완성되면, 그 사이에 있는 지하 2층 코어부(21)은 그 사이에 끼워서 시공할 수 있다.When the core part 22 on the first basement level and the core part 20 on the third basement level are completed every other layer, the core part 21 on the second basement floor in between can be constructed by sandwiching them.

지하 3층 슬라브(11)가 완성되면, 계속 하향으로 공사를 진행하며 지하 5층 터파기를 한 후 지하 4층 슬라브(12)를 시공하며 기간은 50일이다.When the 3rd basement slab 11 is completed, the construction continues downward, excavating the 5th basement, and then constructing the 4th basement slab 12, and the period is 50 days.

지하 4층 슬라브(12)가 완성되면, 지하 6층 터파기를 한 후 지하 5층 슬라브(13)를 시공하며 기간은 50일이다.When the 4th basement slab 12 is completed, the 5th basement slab 13 is constructed after excavating the 6th basement, and the period is 50 days.

이때 지하 5층 슬라브(13)가 완성되면, 본 발명의 특징에 따라 지하 5층 코어부(18)를 먼저 시공한다. 기존공법은 지하 5층 코어부(18)는 매트(15) 완료 후 지하 6층부터 순서대로 상향으로 시공하고 있다. 따라서 본 발명에 따라 지하 5층 코어부(18)는 기존공법에 비해 먼저 시공하는 특징을 가지며, 전체 공사기간이 단축되는 효과를 발휘한다.At this time, when the 5th basement slab 13 is completed, the 5th basement core part 18 is first constructed according to the characteristics of the present invention. In the existing method, the 5th basement floor core 18 is being constructed upward in order from the 6th basement floor after the mat 15 is completed. Therefore, according to the present invention, the 5th basement core portion 18 has the characteristic of being constructed first compared to the existing construction method, and exhibits the effect of shortening the overall construction period.

지하 3층 코어부(20)를 시공한 후, 그 아래층의 지하 4층 코어부(19)를 건너뛰어 한 층 걸러 지하 5층 코어부(18)를 시공한다. 그 사유는 지하 3층 코어부(20) 시공 후 바로 아래층인 지하 4층 코어부(19)를 역타로 시공하는 것은 연결부의 시공이 어렵기 때문이다. 상기 지하 3층 코어부(20)의 경우와 같다.After constructing the core part 20 on the 3rd basement level, the core part 18 on the 5th basement floor is constructed every other floor by skipping the core part 19 on the 4th basement floor below it. The reason is that the construction of the connection part is difficult to construct the core part 19 on the 4th basement floor, which is immediately below, by reverse hitting after the construction of the core part 20 on the 3rd basement level. It is the same as the case of the core part 20 on the third basement floor.

지하 6층 터파기 이후에는 매트 터파기(14)를 한 후 기초, 매트(15)를 시공한다. After excavating the 6th basement floor, after excavating the mat (14), the foundation and the mat (15) are constructed.

매트(15)가 완성되면, PRD가 지탱하던 하중을 매트(15)가 지지하므로 지상층은 9층(32)이상으로 올라갈 수 있다. When the mat 15 is completed, the mat 15 supports the load that the PRD was supporting, so that the ground floor can go up to the 9th floor 32 or more.

한편 매트(15) 시공 후 지하 수직부재의 완성시까지 지상층을 15층 까지만 올릴 수 있도록 제한하는 이유는 지하층 PRD의 좌굴이며 지하 6층부터 지하 2층까지 PRD기둥이 5개층 정도 노출되어 있기 때문이다. 그러나 본 발명에 따르면, 한 층 걸러 홀수층이 이미 시공되어 있으므로 한 개층 높이만 PRD기둥이 노출되어 있어 좌굴 제약이 적으므로 지상층 공사방법에 따라 보다 높은 지상층을 시공할 수 있는 새로운 효과를 발휘한다.On the other hand, the reason that the ground floor can only be raised to the 15th floor after the construction of the mat 15 until the completion of the underground vertical member is because the PRD in the basement is buckling and the PRD columns from the 6th basement to the 2nd floor are exposed. . However, according to the present invention, since the odd-numbered floors have already been constructed for every other floor, the PRD column is exposed at the height of only one floor, so there is little buckling restriction.

매트(15) 완료 이후 이제 지하층에서 남은 골조는 지하 6층 코어부(17), 지하 4층 코어부(19), 지하 2층 코어부(21) 3개이다. 한층 걸러 미리 지하 3층(20), 지하 5층 코어부(18)가 완성되었으므로, 남은 3개층 코어부는 그 사이 사이에 끼워서 시공하면 된다.After the mat (15) is completed, the remaining frameworks in the basement are the 6th basement core 17, the 4th basement core 19, and the 2nd basement core 21. Since the 3rd basement level 20 and the 5th basement level core part 18 have been completed every other layer in advance, the core part of the remaining 3 floors can be constructed by sandwiching them between them.

본 발명의 특징에 따라 홀수층 코어부가 이미 시공되어 있으므로 남은 3개층은 동시 또는 같은 시기나 또는 순서대로 작업할 수 있다. According to a feature of the present invention, since the odd-numbered layer core has already been constructed, the remaining three layers can be worked simultaneously or at the same time or in sequence.

한편 지하 2층 코어부(21)과 지하 4층 코어부(19)의 시공에 있어서 철근을 미리 시공하고, 콘크리트는 매트(15) 타설 이후에 동시에 타설하여 추가로 생산성을 높일 수도 있다.On the other hand, in the construction of the second basement core part 21 and the fourth basement core part 19, reinforcing bars are pre-constructed, and concrete is poured simultaneously after the mat 15 is poured to further increase productivity.

따라서 종래에는 3개층을 순타로 순서대로 시공해야 했으므로 3개층(약 75일)이 소요되었으나, 본 발명의 특징에 따라 남은 3개층을 하나 걸러 같은 시기에 동시에 시공할 수 있으므로 1개층(25일)의 기간만 소요되어 2개층을 단축하는 효과를 갖는다. Therefore, in the prior art, three floors (about 75 days) were required because three floors had to be constructed in sequential order. It takes only a period of time and has the effect of shortening two floors.

본 발명에 따라 지하 수직부재를 하나 걸러 번갈아 매트 시공전에 지하 3층 코어부(20)와 지하 5층(18)을 미리 시공하여 2개층의 공사기간을 단축하였고, 매트(15) 타설후에는 남은 3개층의 코어부(17, 19, 21)을 일시에 시공하여 2개층 기간을 단축하여, 총 4개층의 공사기간 단축효과를 갖는다. 지하층 코어부는 주공정선(크리티컬 패스, Critical Path)이므로 전체 공기가 단축된다.According to the present invention, the construction period of two floors was shortened by pre-constructing the 3rd basement level core part 20 and the 5th basement floor 18 before the mat construction by alternately removing one underground vertical member, and after placing the mat 15, the remaining By constructing the core parts 17, 19, and 21 of three floors at once, the period of two floors is shortened, which has the effect of shortening the construction period of a total of four floors. Since the core part of the basement floor is the main line (Critical Path), the total air length is shortened.

도 3을 참조하면, 지상 5층부터 39층까지의 골조공사와 함께 마지막 작업인 마감공사가 표시되어 있다. 역타 구조계산에 따라, 9층 슬라브(32)는 매트 타설 후 시작할 수 있고, 16층 슬라브(39)는 지하 수직부재가 모두 완료되고 착수하는 것으로 공정표가 작성되어 있다. 16층부터는 최상층 39층까지는 6일 싸이클로 골조가 진행되고 마감공사는 일반적인 1년을 적용하였다. 마감공사에는 지붕 골조 완료 후 실내 인테리어 공사, 엘리베이터 공사, 외부 커튼월, 타워크레인 등의 가설공사 해체, 옥상공사, 조경공사 등이 포함된다.Referring to FIG. 3 , the final work, the finishing work, along with the frame work from the 5th to the 39th floor is displayed. According to the reverse structural calculation, the 9-story slab 32 can be started after the mat is poured, and the 16-story slab 39 is completed with all of the underground vertical members and the process table is prepared. From the 16th floor to the 39th floor of the top floor, framing was carried out in a cycle of 6 days, and the general finishing work was applied for one year. The finishing work includes interior decoration work, elevator work, temporary dismantling of external curtain walls and tower cranes, etc., roof work, landscaping work, etc.

따라서 39층 오피스 빌딩의 전체 공사기간은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재 공법을 적용하면 도 2의 1번 작업에 나타난 바와 같이 1,106일(약 36개월)이 소요된다. 이는 기존의 공법에 비해 전체 공사기간이 약 3개월이 단축된 것이다.Therefore, the total construction period of the 39-story office building takes 1,106 days (about 36 months) as shown in the first operation of FIG. Compared to the previous construction method, the total construction period was shortened by about 3 months.

도 4는 상기 도 2의 지하 수직부재 공정의 확대공정표이다.4 is an enlarged process table of the underground vertical member process of FIG. 2 .

도 4를 참조하면, 지하 수직부재중 홀수층의 수직부재(지하 1층 코어부(22), 지하 3층 코어부(20), 지하 5층 코어부(18))가 해당층의 슬라브가 완성된 후 착수하는 것을 나타내고 있다. 나머지 잔여 짝수층의 수직부재(지하 6층 코어부(17), 지하 4층 코어부(19), 지하 2층 코어부(21)) 3개층은 매트(15) 타설 후 같은 시기에 병행하여 시공되는 것을 나타내고 있다.Referring to FIG. 4, the vertical members of the odd-numbered floors among the underground vertical members (the first basement core part 22, the third basement core part 20, the fifth basement core part 18) are the slabs of the corresponding floors are completed. It indicates starting later. The remaining three floors of the remaining even-numbered vertical members (the 6th basement core 17, the 4th basement core 19, the 2nd basement core 21) are installed in parallel at the same time after the mat 15 is poured. indicates to be

상기 잔여 짝수층의 수직부재(17, 19, 21)은 하나 걸러 이미 홀수층이 시공되어 있으므로 그 사이 사이에 끼워서 동시에 시공할 수 있는 특징을 갖는다.The remaining even-numbered vertical members (17, 19, 21) have a feature that, since every other odd-numbered layer has already been installed, they can be sandwiched between them and constructed at the same time.

도 5는 본 발명에 따른 하나 걸러 선시공 되는 지하 수직부재의 가장 늦은 착수시점의 공정표의 일예이다. 5 is an example of the schedule of the latest starting point of the underground vertical member to be pre-constructed every other according to the present invention.

가장 늦은 착수시점이란 후속공정에 영향을 주지않고 가장 늦게 시공할 수 있는 작업일정을 말한다. 가장 늦은 착수시점 또는 완료시점(As late as possible start, finish)은 후속공정에 영향을 미치지 않고 가장 늦게 시공할 수 있는 일정을 의미한다. The latest start time refers to the work schedule that can be constructed the latest without affecting the subsequent process. As late as possible start, finish refers to the schedule that can be constructed the latest without affecting the subsequent process.

도 5를 참조하면, 지하 1층 코어부(22)는 지상층 공사(25~)를 위하여 지하 1층 슬라브 완성 후 시공되어 있다. 다음으로 지하 3층 코어부(20)는 짝수층 지하 수직부재(17, 19, 21)가 시공되기 이전에 가장 늦게 시공될 수 있음을 나타내고 있다. Referring to FIG. 5 , the first basement core part 22 is constructed after completion of the first basement slab for the above-ground floor construction (25~). Next, it indicates that the three-story basement core 20 can be constructed the latest before the even-numbered basement vertical members 17, 19, and 21 are constructed.

도 6은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 가장 빠른 착수시점과 가장 늦은 착수시점의 비교 공정표이다. 도 6은 지하 수직부재의 시공순서가 정해졌으므로 공정표상에서 어떤 날짜 또는 어느 시점에 시공을 하느냐에 관한 내용을 설명하는 것이다.6 is a comparative process table of the earliest starting point and the latest starting point of the underground vertical member constructed every other one according to the present invention. 6 is to explain the contents of the construction at which date or time in the process table because the construction order of the vertical member is determined.

도 6을 참조하면, 작업번호 16부터 21까지는 빠른 공정(도 4)을 나타내고, 작업번호 23부터 28까지는 늦은 공정(도 5)을 나타내고 있다. 지하 3층 코어부는 빠른 작업 20번과 늦은 작업 27번을 통해 비교할 수 있다. 즉 지하 3층은 20번에서 착수칼럼을 보면 2020년 1월 1일 빠르게 착수할 수 있고, 27번에서 2020년 5월 15일 착수할 수 있다. 물론 1월 1일과 5월 15일 사이 그 중간에도 아무 때나 착수할 수 있다.Referring to FIG. 6 , operation numbers 16 to 21 indicate a fast process ( FIG. 4 ), and operation numbers 23 to 28 indicate a slow process ( FIG. 5 ). The core part of the 3rd basement floor can be compared through the early work No. 20 and the slow work No. 27. In other words, if you look at the start column in No. 20, the 3rd basement floor can be started quickly on January 1, 2020, and can be started on May 15, 2020 from No. 27. Of course, you can start at any time between January 1st and May 15th.

이상과 같이, 도 1부터 도 6까지 본 발명에 따른 하나 걸러 시공되는 지하 수직부재 공사방법의 사상과 실시예를 설명하였다.As described above, the idea and embodiment of the underground vertical member construction method constructed every other one according to the present invention from FIGS. 1 to 6 has been described.

다음은 도 7부터 도 10까지 역타공법에서 종래 기존공법의 지하 수직부재 시공개념과 실시예를 설명한다.The following describes the construction concept and embodiment of the underground vertical member of the conventional conventional method in the reverse drilling method from FIGS. 7 to 10 .

도 7은 역타공법에서 종래 기존공법의 지하 수직부재 시공방법의 전체 흐름도이다.7 is an overall flowchart of the underground vertical member construction method of the conventional conventional method in the reverse drilling method.

도 7을 참조하면, 건물 외곽으로 흙막이(T10)를 시공한 후, 역타 골조를 형성하기 위하여 지하에 PRD 또는 RCD 말뚝(T20)을 시공한다. 이후 지하 터파기를 하면서 지하 슬라브를 하향으로 시공해간다(T30~T100). 지하 6층 터파기 이후(T100), 기초와 매트(T110)를 완성한다. Referring to FIG. 7 , after the retaining wall (T10) is constructed on the outside of the building, a PRD or RCD pile (T20) is constructed underground to form a reversed frame. After that, the underground slab is constructed downward while excavating the underground trench (T30~T100). After excavating the basement 6th floor (T100), complete the foundation and mat (T110).

이후 지하 수직부재(T130~170)는 지하 6층(T130)부터 순차적으로 상향으로 시공한다. Thereafter, the underground vertical members (T130-170) are sequentially constructed upward from the 6th basement floor (T130).

한편 지상층은 지하 1층 코어부(T50)를 완성한 후 지상층 골조 (1차)(T60)를 시공한다. 예를 들어 매트 타설전까지는 지사 8층 슬라브까지 시공한다. 매트 타설 후에는 지상 9층부터 15층까지 지상층 골조(2차)(T180)를 시공한다. 지하 수직부재(T130~170)가 완성되면, 지상 16층부터 제약없이 시공할 수 있다.On the other hand, for the above-ground layer, after the core part (T50) of the first basement is completed, the above-ground frame (1st) (T60) is constructed. For example, up to the 8th floor slab of the branch is installed until the mat is poured. After placing the mat, construct the above ground level frame (secondary) (T180) from the 9th to 15th floors above the ground. When the underground vertical member (T130 ~ 170) is completed, it can be constructed without restrictions from the 16th floor above the ground.

종래의 역타공법은 지상부터 최하층인 매트까지 하향으로 시공한 후, 매트를 반환점으로 하여 유턴하여 상향으로 지하 수직부재를 순타로 시공한다.In the conventional reverse drilling method, after the construction is done downward from the ground to the lowest floor, the mat is used as a turning point to U-turn and the underground vertical members are sequentially constructed upwards.

따라서 지하층의 순서가 길어 지하 공사기간이 많이 소요되는 특징이 있다.Therefore, the sequence of the basement floors is long and the underground construction period is long.

도 8 내지 도 9는 기존의 공법을 적용한 역타공법의 전체 공정표이다.8 to 9 are overall process tables of the reverse punching method to which the conventional method is applied.

도 8을 참조하면, 기존의 역타공법은 지하 6층, 지상 39층 오피스 빌딩이며, SRC조, 역타 탑다운 공법이다. 착공일은 2019년 1월 1일이다. 도 2와 동일하다. 기존의 공법을 적용하여 공정표를 설명하는 이유는 본 발명에 의한 공사방법과의 공사순서 차이와 전체 공사기간의 차이를 살펴보기 위함이다.Referring to FIG. 8 , the conventional reverse punching method is an office building with 6 stories below the ground and 39 stories above the ground, and it is an SRC group, reverse tapping top-down construction method. The start date is January 1, 2019. It is the same as FIG. The reason for explaining the schedule by applying the existing construction method is to examine the difference between the construction sequence and the total construction period with the construction method according to the present invention.

공정표를 참조하면 흙막이 시공단계(공정표상의 왼쪽 첫번째 칼럼의 작업번호 6번)는 H-pile / CIP 작업이며 기간은 80일이다. Referring to the process table, the retaining construction stage (work number 6 in the first column on the left of the process table) is H-pile / CIP work, and the duration is 80 days.

7번 작업 PRD는 지하층에 다수의 말뚝 기둥을 시공하는 것이며 기간은 70일이다.The 7th PRD is to construct a number of pile columns in the basement, and the period is 70 days.

8번 작업 지하 1층 터파기 및 1층 슬라브 시공은 7번 작업 PRD공사가 완료되면 말뚝에 1층 바닥 철골보를 설치하고 데크 플레이트 및 콘크리트를 타설하는 SRC 작업이며 기간은 50일이다.Work No. 8 excavation of the first basement floor and slab construction of the first floor is an SRC work of installing the first floor steel beams on the piles and pouring the deck plate and concrete when the PRD work of No. 7 work is completed, and the duration is 50 days.

작업 지하 2층 터파기 및 지하 1층 슬라브 시공(9번 작업, 이하 번호로 표시)은 1층 슬라브(8)가 완료되면 하향으로 지하 2층 터파기를 한 후 지하 1층 슬라브를 시공하며 기간은 50일이다.In the case of excavation of the 2nd basement floor and construction of the 1st basement slab (work 9, indicated by the number below), when the 1st floor slab (8) is completed, excavate the 2nd basement floor downward and then construct the 1st basement slab. 50 days.

지하 1층 슬라브(9)가 완성되면, 지하 1층 코어부와 기둥(22)을 시공하여 지상층으로 공사를 진행할 수 있도록 한다. 이에 따라 지하층 하향공사와 지상층 상향공사가 동시에 진행되며, 이를 일반적으로 탑다운(Top-down) 공사라고 한다.When the first basement slab 9 is completed, the first basement core part and the pillar 22 are constructed so that the construction can proceed to the above-ground floor. As a result, both the basement and ground floor upward construction are carried out at the same time, and this is generally referred to as top-down construction.

지하 1층 코어부(22)가 완료되면, 지상 2층 슬라브(25)부터 지상 8층 슬라브(31)까지 연속적으로 작업할 수 있다. 이 때 8층까지의 지상층 하중은 PRD가 지지한다.When the first basement core part 22 is completed, it is possible to continuously work from the second-floor slab 25 to the eighth-floor slab 31 above the ground. At this time, the load on the ground floor up to the 8th floor is supported by the PRD.

9층 슬라브(32)는 매트 콘크리트(15)가 타설되어야 시공할 수 있으므로, 8층(31) 완료 후 약 4개월간 공사가 중지된다. PRD가 지상 8층(31)까지의 하중만 지탱할 수 있기 때문에 매트 타설 이후에 9층(32)을 착수할 수 있다.Since the 9-story slab 32 can be constructed only when the mat concrete 15 is poured, the construction is stopped for about 4 months after the 8th-floor 31 is completed. Since the PRD can only support the load up to the 8th floor (31) above the ground, it is possible to undertake the 9th floor (32) after placing the mat.

상기 지하 1층 슬라브(9)가 완성되면, 다음으로 지하 3층 터파기를 하향으로 한 후 지하 2층 슬라브(10)를 시공하며 기간은 50일이다.When the first basement slab 9 is completed, the second basement slab 10 is constructed after digging the third basement floor downward, and the period is 50 days.

지하 2층 슬라브(10)가 완성되면, 다음으로 지하 4층 터파기를 하향으로 한 후 지하 3층 슬라브(11)를 시공하며 기간은 50일이다. When the second basement slab 10 is completed, then the third basement slab 11 is constructed after digging down the fourth basement level, and the period is 50 days.

지하 3층 슬라브(11)가 완성되면, 또한 계속 하향으로 공사를 진행하는데, 지하 5층 터파기를 한 후 지하 4층 슬라브(12)를 시공하며 기간은 50일이다.When the 3rd basement slab 11 is completed, the construction continues downward, and after excavating the 5th basement, the 4th basement slab 12 is constructed, and the period is 50 days.

지하 4층 슬라브(12)가 완성되면, 지하 6층 터파기를 한 후 지하 5층 슬라브(13)를 시공하며 기간은 50일이다.When the 4th basement slab 12 is completed, the 5th basement slab 13 is constructed after excavating the 6th basement, and the period is 50 days.

지하 6층 터파기 이후에는 매트 터파기(14)를 한 후 기초 또는 매트(15)를 시공한다. 매트(15)가 완료되면, PRD가 지탱하던 하중을 매트(15)가 지지하므로 지상층은 9층(32)이상으로 올라갈 수 있다. After excavating the 6th basement floor, after excavating the mat 14, the foundation or the mat 15 is constructed. When the mat 15 is completed, the mat 15 supports the load that the PRD was supporting, so that the ground floor can go up to the 9th floor 32 or more.

매트(15)가 완료되면, 지하 수직부재(17부터 21)를 지하 6층 코어부(17)부터 지하 2층 코어부(21)까지 연속적으로 직결로 시공하며, 층당 25일 내지 30일이 소요된다. 이 기간 중 지상층은 9층(32)부터 15층(38)까지 시공할 수 있다.When the mat 15 is completed, the underground vertical members 17 to 21 are continuously directly connected from the core part 17 on the 6th basement level to the core part 21 on the 2nd basement floor, and it takes 25 to 30 days per floor. do. During this period, the ground floor can be constructed from the 9th floor (32) to the 15th floor (38).

도 9를 참조하면, 지상 10층부터 39층 및 마감공사가 표시되어 있다. 16층 슬라브(39)는 지하 수직부재가 모두 완료되고 착수하는 것으로 공정표가 작성되어 있다. 16층부터는 지하층 제약없이 최상층까지 6일 싸이클로 골조가 진행되고 마감공사는 일반적인 1년을 적용하였다. Referring to FIG. 9 , the 10th to 39th floors above the ground and finishing work are displayed. The 16-story slab 39 has a process table written that all underground vertical members are completed and started. From the 16th floor to the top floor without any restrictions on the basement, framing is carried out in a cycle of 6 days, and the general finishing work is applied for one year.

따라서 39층 오피스 빌딩의 전체 공사기간은 본 발명에 따른 하나 걸러 시공되는 지하 수직부재 공법을 적용하면 도 8의 1번 작업에 나타난 바와 같이 1,194일(약 39개월)이 소요된다.Therefore, the entire construction period of the 39-story office building takes 1,194 days (about 39 months) as shown in the first operation of FIG.

상기 39개월의 전체공기는 본 발명에 따른 전체공기 36개월 비해 3개월의 더 길다. 그 사유는 지하 수직벽체를 지하 6층부터 지하 2층까지 순타로 순서대로 시공하면서 많은 시간을 소요하기 때문이다.The total air of 39 months is longer by 3 months compared to the total air of 36 months according to the present invention. The reason is that it takes a lot of time to construct the underground vertical walls sequentially from the 6th basement to the 2nd basement level.

도 10은 상기 도 8의 종래 기존공법의 지하 수직부재 공정의 확대공정표이다. 지하 수직부재가 매트(15) 시공이후, 작업번호 17부터 작업번호 21까지 순차적으로 순타로 시공되고 있음을 나타내고 있으며, 기간은 130일이며 약 4.3개월이 소요된다.10 is an enlarged process table of the underground vertical member process of the conventional conventional method of FIG. It shows that the underground vertical member is being constructed sequentially from operation number 17 to operation number 21 after the construction of the mat 15, and the period is 130 days and takes about 4.3 months.

도 11은 종래 기존공법의 지하 수직부재 공정과 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 공정을 비교한 비교공정표이다.11 is a comparative process table comparing the process of the underground vertical member constructed every other one according to the present invention with the process of the underground vertical member of the conventional conventional method.

도 11을 참조하면, 작업번호 1부터 19까지는 종래공법의 공정표이며, 작업번호 20부터 38까지는 본 발명에 따른 공정표이며, 작업번호 39는 종래공법과 본 발명 공법간의 공사기간의 차이를 나타낸다.Referring to FIG. 11, operation numbers 1 to 19 are the process tables of the conventional method, operation numbers 20 to 38 are the process tables according to the present invention, and operation number 39 shows the difference in the construction period between the conventional method and the method of the present invention.

먼저 종래공법에서 작업 12부터 16까지 지하 5개층의 코어부는 매트(10) 시공 이후 순차적으로 시공되어 130일이 소요됨을 나타내고 있다. First, in the prior art method, from 12 to 16, the core part of the five basement floors is sequentially constructed after the mat 10 construction, indicating that it takes 130 days.

반면 본 발명에 따르면, 작업 31부터 35까지는 매트(29) 시공 이후, 30일만이 소요되어 본 발명이 100일이 짧음을 표시한다(39).On the other hand, according to the present invention, from operations 31 to 35, only 30 days are required after the mat 29 construction, indicating that the present invention is short of 100 days (39).

그 사유는 지하 3층 코어부(34)와 지하 5층 코어부(32)를 미리 시공하였고, 매트(29) 시공 이후에 남은 3개층 코어부(31, 33, 35)를 동시 또는 같은 시점에 각각 끼워 넣어 시공할 수 있기 때문이다. 홀수층 코어부를 하나 걸러 시공한 후, 남은 짝수층을 한꺼번에 시공하여 결과적으로 종래공법은 5회 시공이 필요하나, 본 발명에서는 단 1회 에 해당하는 시공으로 4개층의 100일을 단축하는 효과를 발휘한다.The reason is that the core part 34 on the 3rd basement level and the core part 32 on the 5th basement floor were previously constructed, and the remaining three-story core parts 31, 33, 35 after the mat 29 were installed at the same time or at the same time. This is because each can be inserted and constructed. After constructing every other odd-numbered core part, the remaining even-numbered layers are constructed at once. As a result, the conventional method requires 5 constructions, but in the present invention, the effect of shortening 100 days of 4 floors with only one construction perform

도 12내지 도 13은 종래 기존공법의 전체공정표(도 8, 9)와 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 전체공정표(도 2, 3)을 층별로 일정차이를 비교한 일정비교표이다.12 to 13 are schedule comparison tables comparing the schedule difference for each floor of the overall process table of the conventional conventional method ( FIGS. 8 and 9 ) and the overall process table of the underground vertical member constructed every other one according to the present invention ( FIGS. 2 and 3 ). .

도 12를 참조하면, 두 공법에 의한 전체공기 차이(작업번호 1)는 약 39개월 대비 36개월로써 88일이며 이는 약 3개월이며 전체공기의 약 8%가 단축됨을 알 수 있다.12, it can be seen that the total air difference (operation number 1) by the two methods is 88 days, which is 36 months compared to about 39 months, which is about 3 months, and about 8% of the total air is shortened.

지하 터파기 및 역타 슬라브, 매트 시공(6~15)부분은 두 공법에서 동일하다.The underground excavation, reverse slab, and mat construction (6~15) parts are the same in both methods.

지하 수직부재에서부터 차이가 발생하며, 본 발명에 따라 지하 수직부재(코어부)를 하나 걸러 번갈아 하향 시공하고, 남은 잔여 코어부를 동시에 시공함에 기인한다.The difference occurs from the underground vertical member, and it is due to the construction of every other underground vertical member (core part) downward in accordance with the present invention, and the construction of the remaining core part at the same time.

마지막 칼럼(I)은 본 발명에 따른 층별 완료일(H칼럼)에서 기존공법의 층별 완료일(E칼럼)을 마이너스한 값이다. The last column (I) is a value minus the completion date for each floor (column E) of the existing method from the completion date for each floor (column H) according to the present invention.

지상 16층(39) 부터는 88일의 차이가 고정되어 공사준공시까지 지속된다.From the 16th floor (39) above the ground, the difference of 88 days is fixed and continues until construction is completed.

도 13을 참조하면 지상 16층(39)부터 88일의 일정차이(I 완료일 차이 칼럼)가 준공시까지 이어짐을 나타내고 있다. Referring to FIG. 13 , it is shown that a schedule difference of 88 days from the 16th floor 39 (I completion date difference column) continues until completion.

도 14는 종래 기존공법의 전체공정표(도 8,9)와 본 발명에 따른 하나 걸러 시공되는 지하 수직부재의 전체공정표(도 2,3)와 이를 표로 정리한 도 12~13을 S-Curve 형태로 나타내어 비교한 공정 비교 그래프이다.14 is an S-Curve form of the overall process table of the conventional conventional method ( FIGS. 8 and 9 ) and the overall process table of the underground vertical member constructed every other one according to the present invention ( FIGS. 2 and 3 ) and FIGS. 12-13 organized in a table It is a comparative process comparison graph represented by .

도 14를 참조하면, 파란 선은 기존공법, 붉은 선은 본 발명의 공법을 나타낸다. Referring to FIG. 14 , the blue line indicates the existing method, and the red line indicates the method of the present invention.

19년 1월 1일 착공하여 지하 6층 매트는 2020년 6월 8일 타설한다(그래프 최하점).Construction began on January 1, 19, and the 6th basement floor mat was poured on June 8, 2020 (lowest point in the graph).

이후 본 발명에 따른 붉은 선은 하나 걸러 이미 2개층을 시공하고, 한번의 1개월에 3개층을 동시에 시공하여 지하 수직부재를 완성한 후 16층으로 이어짐을 나타내고 있다.Afterwards, the red line according to the present invention indicates that two floors have already been constructed every other one, and three floors are simultaneously constructed in one month to complete the basement vertical member and then lead to the 16th floor.

반면 종래 기존공법인 파란선은 매트 시공이후 층별로 지하 수직부재를 약 4.3개월에 걸려 시공한 후 16층으로 이어짐을 나타내고 있다. 16층 이상부터는 두 공법은 동일하다.On the other hand, the blue line, which is the conventional method of construction, indicates that it takes about 4.3 months to construct the basement vertical member for each floor after the mat construction, and then leads to the 16th floor. From the 16th floor and above, the two construction methods are the same.

이상과 같이 기존공법과 본 발명의 공법차이를 공정표와 표 및 그래프를 통하여 비교하였다.As described above, the difference between the existing method and the method of the present invention was compared through the process table, table, and graph.

다음은 본 발명의 실시예에서 일부 작업이 다르게 진행되는 경우에 대한 설명이다. The following is a description of a case in which some operations are performed differently in an embodiment of the present invention.

최종 터파기가 지하 5층인 경우의 공사에서는 지하 코어부가 지하 1층과 지하 3층이 먼저 하향으로 시공되고 매트 완료 이후에는 지하 5층을 시공한 후, 지하 4층과 지하 2층은 동시에 병행하여 시공될 수 있다. 따라서 매트이후 잔여 코어부는 2회에 걸쳐 시공된다.In the case of the final excavation of the 5th basement level, the basement core part is first constructed downwards on the 1st and 3rd basement floors, and after the mat is completed, the 5th basement floor is constructed, and then the 4th basement and 2nd basement floors are simultaneously constructed can be Therefore, after the mat, the remaining core part is installed twice.

최종 터파기가 지하 4층인 경우의 공사에서는 지하 코어부가 지하 1층과 지하 3층이 먼저 하향으로 시공되고 매트 완료 이후에는 지하 4층과 지하 2층 코어부를 동시에 시공할 수 있다. 지하 6층 규모 공사와 동일한 개념이다.In the case of the final excavation of the 4th basement floor, the basement core part is constructed downwards first on the 1st basement floor and the 3rd basement floor, and after the mat is completed, the 4th basement floor and the 2nd basement core part can be constructed at the same time. It is the same concept as the 6-story underground construction.

지하 최하층의 층고가 높지 않아 최하층 2개층(예를 들어 지하 5층과 지하 6층)을 동시에 터파기 한 후, 매트를 완료하고 이후에 지하 5층 슬라브를 시공하는 경우가 있다. 이 때에는 지하 6층 코어부와 지하 5층 슬라브를 동시에 시공한 후, 지하 5층 코어부를 시공한다. 따라서 매트이후 잔여 코어부는 2회에 걸쳐 시공된다.Since the floor height of the basement floor is not high, there are cases where the bottom two floors (for example, the 5th floor and the 6th floor) are dug at the same time, then the mat is completed and then the 5th basement slab is installed. In this case, after constructing the 6th basement slab and the 5th basement slab at the same time, construct the 5th basement core part. Therefore, after the mat, the remaining core part is installed twice.

이상과 같이 지하 층수가 홀수층이나 최하층을 2개층을 동시에 터파기 하는 경우에 있어서는 매트 완료 이후 잔여 코어부를 2회에 걸쳐 순차적으로 시공하는 경우가 일부 공사에서 발생한다. 따라서 본 발명의 일실시에 따르면 하나 걸러 코어부를 완성한 후 잔여 코어부를 한번에 완료하는 경우가 대부분이고 일부 공사에서는 잔여부를 2회에 걸쳐 시공하는 경우가 파생된다.As described above, in the case of excavating two floors with an odd number of floors or the lowest floor at the same time, some construction projects involve sequentially constructing the remaining core part twice after mat completion. Therefore, according to one embodiment of the present invention, after completing every other core part, the remaining core part is mostly completed at once, and in some constructions, the case of constructing the remaining part twice is derived.

상기 실시예의 공정표는 공정표 작성 전문 프로그램으로 작성되어 날짜 계산이 정확한 예이다. 공정표에서 붉은색 바챠트인 칸트 챠트는 주공정선 크리티컬 패스로서 전체 공기를 결정하는 주요한 작업을 나타낸다. 파란색 바챠트는 여유일수 플로트(float)가 있는 작업을 의미한다. 따라서 공기를 단축하기 위해서는 주공정선인 붉은색을 단축하여야 한다. 공정표의 바챠트를 사이를 연결하는 화살표를 포함하는 연결선(Relationship은 작업간의 선행 후행 관계를 나타낸다. The step table of the above embodiment is an example in which the date calculation is accurate since it is prepared by a program specializing in step table preparation. The Kant chart, which is a red bar chart in the milestone, represents a major operation that determines the total air as a critical pass of the major line. Blue bar charts indicate jobs with floats. Therefore, in order to shorten the air, the red line, which is the main line, must be shortened. A connection line including arrows connecting the bar charts of the milestone table (Relationship indicates the preceding and following relationship between tasks).

이상과 같이 본 발명의 특징에 따르면, 전체 공사기간을 결정하는 지하 코어부의 공기를 단축하기 위하여 하나 걸러 번갈아 코어부를 완성하는 사상을 기본으로 현장의 특성에 따라 일부 파생적인 순차적인 코어부 시공이 있을 수 있음을 알 수 있다. 그러나 기존공사방법인 순차적인 코어부 시공방법과는 달리 본 발명에 따른 하나 걸러 시공하는 코어부 시공방법을 통해 전체 공사기간을 단축하는 사상을 바탕으로 일부 수정되는 코어부 시공방법은 본 발명의 사상에 포함되는 것임을 건설공사를 업으로 하는 기술자들은 명백히 알 수 있을 것이다.As described above, according to the characteristics of the present invention, there may be some derivative sequential core part construction depending on the characteristics of the site based on the idea of alternately completing the core part every other to shorten the construction period of the underground core part, which determines the overall construction period. It can be seen that However, unlike the sequential core part construction method, which is the existing construction method, the core part construction method partially modified based on the idea of shortening the entire construction period through the every other core part construction method according to the present invention is the spirit of the present invention. Engineers in the construction industry will be able to clearly see that it is included in the

발명의 실시를 위한 형태Modes for carrying out the invention

본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 8층인 경우의 수직부재 시공방법의 순서이다.This is the order of the vertical member construction method in the case of the 8th basement floor of the reverse perforation method alternately constructed according to an embodiment of the present invention.

시공순서는 다음과 같다.The construction sequence is as follows.

흙막이mudguard

지하기둥(PRD, RDC, ACT column)Underground column (PRD, RDC, ACT column)

지하1층 및 지하2층 터파기Digging the 1st and 2nd basement floors

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Reinforced concrete pouring on the 1st basement floor of the steel frame deck (slab pouring)

지하3층 터파기3rd floor digging

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement floor slab pouring, 1st basement floor core wall column installation

지하4층 터파기4th basement floor digging

지하3층 슬라브 타설3rd basement floor slab casting

지하5층 터파기Digging the 5th basement floor

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4th basement floor slab pouring, 3rd basement floor core wall column installation

지하6층 터파기digging the 6th floor

지하5층 슬라브 타설5th basement floor slab casting

지하7층 터파기7th floor digging

지하6층 슬라브 타설, 지하5층 코어월 기둥 타설6th basement floor slab pouring, 5th basement floor core wall column installation

지하8층 터파기 및 매트 터파기Digging the 8th basement floor and excavating the mat

지하7층 슬라브 타설, 지하7층 코어월 기둥 타설 7th basement floor slab pouring, 7th basement floor core wall column installation

지하8층 바닥 매트 타설8th basement floor mat

잔여층인 지하8층, 지하6층, 지하4층, 지하4층 코어월 기둥 타설 (4개층 동시시공)Remaining 8th basement, 6th basement, 4th basement, and 4th basement core wall pillars installed (4 floors simultaneous construction)

또는 지하8층 및 한개층 추가하여 2개층 1차 시공 후 남은 2개층 2차 코어월 기둥 시공(2개층 2회 시공)Or 2nd floor 2nd core wall column construction remaining after the 1st 2nd floor construction by adding 8 basement floors and 1st floor (2nd 2nd floor construction)

또는 지하8층 및 한개층 추가하여 2개층 1차 시공 후 남은 2개층을 한개층씩 2차 3차로 코어월 기둥 시공(2개층 1회, 1개층 2회 총 3회 시공)Alternatively, after the first construction of 2 floors by adding 8 basement floors and one floor, the core wall pillar construction is performed on the remaining 2 floors one by one in the second and third phases (2 floors 1 time, 1 floor 2 times total 3 times)

또는 지하8층 코어월 기둥 시공 후 남은 3개층을 한개층씩 시공 (4개층을 총4회 시공)Alternatively, construct the remaining 3 floors one by one after the core wall pillar construction on the 8th basement floor (4 floors in total 4 times)

매트 타설이후에는 남은 층은 4개층이며 1회, 2회, 3회, 4회에 분할하여 타설한다.After the mat is poured, the remaining layers are 4 layers, and pour it in 1, 2, 3, and 4 divisions.

다음은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 7층인 경우의 수직부재 시공방법의 순서이다.The following is the sequence of the vertical member construction method in the case of the 7th basement floor of the reverse perforation method alternately constructed according to an embodiment of the present invention.

흙막이mudguard

지하기둥(PRD, RDC, ACT column)Underground column (PRD, RDC, ACT column)

지하1층 및 지하2층 터파기Digging the 1st and 2nd basement floors

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Reinforced concrete pouring on the 1st basement floor of the steel frame deck (slab pouring)

지하3층 터파기3rd floor digging

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement floor slab pouring, 1st basement floor core wall column installation

지하4층 터파기4th basement floor digging

지하3층 슬라브 타설3rd basement floor slab casting

지하5층 터파기Digging the 5th basement floor

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4th basement floor slab pouring, 3rd basement floor core wall column installation

지하6층 터파기digging the 6th floor

지하5층 슬라브 타설5th basement floor slab casting

지하7층 터파기 및 매트 터파기Digging the 7th basement floor and excavating the mat

지하6층 슬라브 타설, 지하5층 코어월 기둥 타설6th basement floor slab pouring, 5th basement floor core wall column installation

지하7층 바닥 매트 타설Pouring floor mat on the 7th basement floor

잔여층인 지하 7층, 지하6층, 지하4층, 지하2층에서On the remaining floors, 7th basement, 6th basement, 4th basement, and 2nd basement

지하7층 및 한개층 추가(지하 4층 또는 지하 2층 중에서 택1)하여 2개층 1차 시공 후 남은 2개층 2차 코어월 기둥 시공(2개층 2회 시공)Add 7 basement floors and one floor (choose 1 from 4 basement floors or 2 basement floors)

또는 지하7층, 잔여 3개층에서 2개층 2차 시공, 나머지 잔여 1개층 시공 (총 3회 분할 시공)Or 2nd floor construction from the 7th basement floor and 3 remaining floors, construction of the remaining 1st floor (3 divided constructions in total)

또는 한개층씩 시공하여 총 4회 시공한다.Alternatively, install one layer at a time and install a total of 4 times.

본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 6층인 경우의 수직부재 시공방법의 순서이다.This is the sequence of the vertical member construction method in the case of the basement 6th floor of the reverse drilling method alternately constructed according to an embodiment of the present invention.

흙막이mudguard

지하기둥(PRD, RDC, ACT column)Underground column (PRD, RDC, ACT column)

지하1층 및 지하2층 터파기Digging the 1st and 2nd basement floors

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Reinforced concrete pouring on the 1st basement floor of the steel frame deck (slab pouring)

지하3층 터파기3rd floor digging

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement floor slab pouring, 1st basement floor core wall column installation

지하4층 터파기4th basement floor digging

지하3층 슬라브 타설3rd basement floor slab casting

지하5층 터파기Digging the 5th basement floor

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4th basement floor slab pouring, 3rd basement floor core wall column installation

지하6층 터파기 및 매트 터파기Excavation of basement 6th floor and excavation of mat

지하5층 슬라브 타설 5th basement floor slab casting

지하6층 바닥 매트 타설, 지하5층 코어월 기둥 타설 Pouring floor mat on the 6th basement floor, pouring the core wall column on the 5th basement floor

잔여층인 지하6층, 지하4층, 지하2층에서On the remaining floors, the 6th, 4th, and 2nd basement floors,

잔여 3개층으로 동시에 시공(총1회)Construction on the remaining 3 floors at the same time (1 time in total)

또는 지하6층 시공 후 지하4층과 지하2층을 동시시공 (총2회)Alternatively, after constructing the 6th basement floor, simultaneously construct the 4th and 2nd basement floors (2 times in total)

또는 지하6층과 지하4층을 동시 시공 후 지하2층을 시공 (총2회)Or construct the 2nd basement floor after simultaneously constructing the 6th and 4th floors (2 times in total)

한개층씩 시공하여 총 3회 시공(총3회 분할시공)한다.Construct one layer at a time and construct a total of 3 times (3 divided constructions in total).

본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 5층인 경우의 수직부재 시공방법의 순서이다.This is the sequence of the vertical member construction method in the case of the 5th basement floor of the reverse drilling method alternately constructed according to an embodiment of the present invention.

흙막이mudguard

지하기둥(PRD, RDC, ACT column)Underground column (PRD, RDC, ACT column)

지하1층 및 지하2층 터파기Digging the 1st and 2nd basement floors

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Reinforced concrete pouring on the 1st basement floor of the steel frame deck (slab pouring)

지하3층 터파기3rd floor digging

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement floor slab pouring, 1st basement floor core wall column installation

지하4층 터파기4th basement floor digging

지하3층 슬라브 타설3rd basement floor slab casting

지하5층 터파기 및 매트 터파기Digging the 5th basement floor and excavating the mat

지하4층 슬라브 타설, 지하3층 코어월 기둥 타설4th basement floor slab pouring, 3rd basement floor core wall column installation

지하5층 바닥 매트 타설5th basement floor mat

잔여층인 지하5층, 지하4층, 지하2층에서On the remaining floors, the 5th, 4th, and 2nd basement floors,

지하 5층 시공후 지하 4층과 지하2층을 동시시공(총2회)Simultaneous construction of the 4th and 2nd floors after the construction of the 5th basement (2 times in total)

또는 지하 5층과 지하2층 동시시공후 지하 4층을 시공(총2회)Alternatively, construct the 5th basement floor and the 2nd basement floor at the same time and then construct the 4th basement floor (2 times in total)

잔여 3개층으로 한개층씩 시공(총3회)한다.The remaining 3 layers are constructed one layer at a time (3 times in total).

다음은 본 발명의 일실시예에 따른 하나 걸러 번갈아 시공되는 역타공법의 지하 4층인 경우의 수직부재 시공방법의 순서이다.The following is the sequence of the vertical member construction method in the case of the fourth basement floor of the reverse perforation method alternately constructed according to an embodiment of the present invention.

흙막이mudguard

지하기둥(PRD, RDC, ACT column)Underground column (PRD, RDC, ACT column)

지하1층 및 지하2층 터파기Digging the 1st and 2nd basement floors

지하1층 철골 데크 철근 콘크리트 타설(슬라브 타설)Reinforced concrete pouring on the 1st basement floor of the steel frame deck (slab pouring)

지하3층 터파기3rd floor digging

지하2층 슬라브 타설, 지하1층 코어월 기둥 타설2nd basement floor slab pouring, 1st basement floor core wall column installation

지하4층 터파기 및 매트 터파기Digging the 4th basement floor and excavating the mat

지하3층 슬라브 타설, 지하3층 코어월 기둥 타설3rd basement floor slab pouring, 3rd basement floor core wall column installation

지하4층 바닥 매트 타설4th basement floor mat

잔여층인 지하4층, 지하2층에서On the remaining floors, the 4th and 2nd basement floors,

지하 4층과 지하2층을 동시시공(총1회)Simultaneous construction of the 4th basement floor and the 2nd basement floor (1 time in total)

잔여 2개층을 한개층씩 시공(총2회)한다.Construct the remaining 2 layers one layer at a time (2 times in total).

현재 탑다운 공사는 도심지 공사에서 대부분 시공되고 있다. 본 발명에 따른 하나걸러 시공방법에 관하여 먼저 구조설계사무소에서 설계를 한후 시공사가 철골 및 형틀을 제작한 후 시공하면 된다. 따라서 본 발명은 산업상 바로 적용이 가능하다.Currently, most of the top-down construction is being carried out in downtown construction. With respect to the every other construction method according to the present invention, it is necessary to first design at the structural design office, and then construct the steel frame and formwork and then construct it. Therefore, the present invention can be directly applied industrially.

Claims (12)

지하구조물의 하향시공과 병행하여 상향시공되는 지상층 골조를 시공하는 건물의 지하 수직부재의 시공에 있어서,
터파기와 지하층 슬라브를 하향으로 시공하는 제1단계;
지하 수직부재를 하나 걸러 선행시공하는 제2단계;
상기 제2단계 시공 후 남은 잔여 지하 수직부재를 하나 걸러 동시에 또는 2회에 걸쳐 시공하는 제3단계;
로 이루어져 하나 걸러 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
In the construction of an underground vertical member of a building that constructs an above-ground structure that is constructed upward in parallel with the downward construction of an underground structure,
The first step of constructing the excavation and the basement slab downward;
A second step of prior construction of every other underground vertical member;
a third step of constructing every other remaining underground vertical member after the second step construction, either at the same time or twice;
A method of shortening the construction period through the construction method of every other underground vertical member, characterized in that it is constructed every other time.
제1항에 있어서,
상기 지하층이 지하 6층인 경우,
지하 슬라브를 하향 시공하면서 하나 걸러 지하 1층, 지하 3층, 지하 5층 코어부를 선행 시공하고 이후 지하 6층, 지하 4층, 지하 2층의 코어부를 동시에 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
According to claim 1,
When the basement floor is the 6th floor,
One underground vertical member characterized in that the core part of the 1st basement, 3rd basement, and 5th floor is pre-constructed in advance while constructing the basement slab downwards, and then the core part of the 6th basement, 4th basement, and 2nd floor are simultaneously constructed. A method of shortening the construction period through the filter construction method.
제1항에 있어서,
상기 지하층이 지하 5층인 경우,
지하 슬라브를 하향 시공하면서 하나 걸러 지하 1층, 지하 3층 코어부를 선행 시공하고 이후 지하 5층 코어부를 시공한 후 지하 4층를 시공하되, 지하 2층 코어부는 지하 5층과 지하 4층 시공기간 동안에 병행하여 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
According to claim 1,
When the basement floor is the 5th floor,
While constructing the basement slab downward, pre-construct every other 1st basement and 3rd basement core part, and then construct the 5th basement core part and then construct the 4th basement level, but the 2nd basement core part is installed during the construction period of the 5th and 4th basement floors. A method of shortening the construction period through the construction method of every other vertical member underground, characterized in that the construction is carried out in parallel.
제1항에 있어서,
상기 지하층이 지하 4층인 경우,
지하 슬라브를 하향 시공하면서 하나 걸러 지하 1층, 지하 3층 코어부를 선행 시공하고 이후 지하 4층 코어부와 지하 2층의 코어부를 동시에 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
According to claim 1,
When the basement floor is the fourth basement floor,
Air through the construction method for every other vertical member in the basement, characterized in that, while constructing the basement slab downward, the core part on the first basement floor and the third basement floor is pre-constructed every other time, and then the core part on the 4th basement floor and the core part on the 2nd basement floor are simultaneously constructed. shortening method.
제1항에 있어서,
상기 지하층의 최하층과 그 상층 부분인 2개층을 동시에 터파기 하는 경우,
지하 슬라브를 하향 시공하면서 하나 걸러 코어부를 선행 시공하고 매트 또는 기초를 시공하고, 최하층 코어부와 직상층 슬라브를 시공한 후, 잔여 코어부를 동시에 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
According to claim 1,
In the case of excavating the lowermost floor of the basement and the upper two floors at the same time,
While constructing the underground slab downward, every other core part is pre-constructed, the mat or foundation is constructed, the lowest core part and the slab of the immediately above floor are constructed, and then the remaining core part is constructed at the same time. Air shortening method.
제1항 내지 제5항에 있어서,
상기 하나 걸러 선행 시공되는 코어부와 이후 후행으로 동시에 시공되는 잔여 코어부는 매트 타설 작업을 기준으로 선행과 후행으로 구분되어 시공되는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
6. The method of claim 1 to 5,
The method for shortening the construction period through the construction method for every other vertical member in the basement, characterized in that the core part to be constructed in advance every other and the remaining core part to be constructed simultaneously afterward are divided into preceding and following based on the mat pouring operation.
제1항 내지 제5항에 있어서,
상기 하나 걸러 선행 시공되는 각각의 코어부의 공사 일정은
해당층의 슬라브 완성 후 시작하는 가능한한 가장 빠른 착수일(Early Start Date)과 잔여 코어부를 후행으로 시공하는 시점 이전에 완료하는 가장 늦은 완료일(Late Finish Date)의 범위내에서 시공되는 것임을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
6. The method of claim 1 to 5,
The construction schedule of each core part, which is constructed in advance of every other above, is
It is characterized in that construction is carried out within the range of the earliest possible start date that starts after the completion of the slab of the corresponding floor and the latest finish date that is completed before the time when the remaining core part is constructed as a trailing point. A method of shortening the construction period through the construction method of every other vertical member in the basement.
제1항 내지 제5항에 있어서,
상기 지하 수직부재는 코어부 또는 지상층으로 연결되는 기둥을 포함하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
6. The method of claim 1 to 5,
The underground vertical member is an air shortening method through the construction method for every other underground vertical member, characterized in that it includes a pillar connected to the core portion or the above-ground floor.
제1항에 있어서,
상기 하나 걸러 시공되는 지하 수직부재는
지하 슬라브를 하향 시공하면서, 지하 홀수층(또는 짝수층)의 코어부 또는 기둥을 선행 시공하고 매트 또는 기초 시공 후에는 잔여층인 짝수층(또는 홀수층)의 코어부 또는 기둥의 수직부재를 일시에 또는 현장여건에 따라 2회에 걸쳐 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
According to claim 1,
The underground vertical member constructed every other one above is
While constructing the basement slab downward, the core part or column of the underground odd-numbered (or even-numbered) floor is pre-constructed. A method of shortening the construction period through the construction method of every other vertical member in the basement, characterized in that the construction is carried out twice depending on the site or site conditions.
제1항에 있어서,
상기 잔여 코어부를 후속으로 일시에 시공하는 것은,
지하 잔여 코어부의 철근을 가능한한 먼저 설치한 후, 후속공정인 콘크리트를 같은 시점에 타설하는 방법을 더 포함하여 시공하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
According to claim 1,
The subsequent construction of the remaining core part at once is,
A method of shortening the construction period through the construction method for every other vertical member in the basement, characterized in that after installing the reinforcing bar of the remaining underground core part as much as possible first, and then constructing it further including a method of pouring concrete at the same time, which is a subsequent process.
(a) 통상의 방법에 의해서 지중에 가설 흙막이 벽체를 구축하는 단계 ;
(b) 지하구조물 및 지상구조물을 시공할 때, 지하구조물의 하향시공과 병행하여 상향시공되는 지상층 코어부 및 기둥으로부터 기둥을 지상으로부터 수직으로 박아 설치하는 단계;
(c) 지상 1층을 굴토하고 바닥부를 시공한 후, 지하 1층을 굴토하고 바닥부를 시공하는 단계;
(d) 나머지 지하 각층을 하향방향으로 순서대로 굴토하고 바닥부를 시공함과 동시에 우선적으로 상향시공되는 지상층 코어부를 지지하기 위하여 지하1개층 또는 지하 복수개층의 지하층 코어부를 먼저 시공하는 단계;
(e) 상기 먼저 시공되는 지하층 코어부 상부에 지상층 코어부를 상부방향으로 우선적으로 시공하면서, 이와 병행하여 지하층 골조를 하향방향으로 설치하는 단계;
(f) 상기 지하층 골조를 하향방향으로 설치하는 단계에서 상기 지하1개층 코어부를 먼저 시공하고 이후 하나 걸러 코어부를 뒤따라 설치하는 단계;
(g) 상기 지하층 골조가 기초부분까지 완료된 이후에는 기초부를 형성하고, 최하층부터 상부방향으로 하나 걸러 하향시공하는 남은 층의 코어부를 동시에 또는 순차적으로 상기 우선시공한 지하층 코어부까지 설치하는 단계;
(h) 지상층 잔여 골조공사와 마지막 작업인 마감공사를 통해 공사준공을 시공하는 단계를 포함하며,
상기 지하 코어부는 가능한한 일정 가능 범위내에서 먼저 시공되거나 동시에 시공되어 주공정선 크리티컬 패스로 부터 배제하여 전체 공사기간을 단축하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
(a) constructing a temporary retaining wall in the ground by a conventional method;
(b) installing the underground structure and the above-ground structure by driving the pillars vertically from the ground from the above-ground core and pillars constructed upward in parallel with the downward construction of the underground structure;
(c) excavating the first floor above the ground and constructing the floor, excavating the first basement and constructing the floor;
(d) excavating the remaining basement floors in order in the downward direction and constructing the floor part and at the same time constructing the basement core part of one basement floor or a plurality of basement floors first to support the above-ground core part which is preferentially constructed upward;
(e) preferentially constructing the above-ground core in the upper direction on the upper part of the basement core to be constructed first, and installing the basement frame in the downward direction in parallel with this;
(f) in the step of installing the basement frame in the downward direction, first constructing the core part of the first basement floor, and then installing the core part after every other one;
(g) after the basement frame is completed to the foundation part, forming the foundation, and installing the core part of the remaining floor to be constructed downwardly every other one from the lowest floor to the upper floor, simultaneously or sequentially, to the core part of the basement that was first constructed;
(h) including the steps of constructing the construction completion through the remaining framing work of the ground floor and the final work, the finishing work,
The underground core part is constructed first or at the same time as possible within a certain possible range, so that the construction period is shortened by excluding it from the critical path of the main line.
제11항에 있어서,
상기 하나 걸러 코어부를 뒤따라 설치하는 단계는 홀수층 코어부를 시공하는 것을 포함하며, 이후 남은층의 코어부는 짝수층의 코어부를 포함하며, 상기 홀수층과 짝수층 코어부는 매트 공사를 기준으로 전환되며, 현장특성에 따라 최하층 코어부와 그 상층 코어부는 순차적으로 시공되는 경우를 포함하는 것을 특징으로 하는 지하 수직부재 하나 걸러 시공방법을 통한 공기단축방법.
12. The method of claim 11,
The step of installing the core part after every other includes constructing the core part of the odd-numbered layer, the core part of the remaining layer includes the core part of the even-numbered layer, and the odd-numbered layer and the even-numbered layer core part are converted based on the mat construction, A method of shortening the construction period through the construction method of every other vertical member in the basement, characterized in that it includes the case where the lowermost core part and the upper core part are sequentially constructed according to site characteristics.
KR1020217041259A 2019-06-27 2019-06-27 The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time KR20220024070A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/KR2019/007842 WO2020262735A1 (en) 2019-06-27 2019-06-27 Method for alternately constructing underground vertical members using top-down construction method

Publications (1)

Publication Number Publication Date
KR20220024070A true KR20220024070A (en) 2022-03-03

Family

ID=74060414

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020217041259A KR20220024070A (en) 2019-06-27 2019-06-27 The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time

Country Status (5)

Country Link
US (1) US20220243418A1 (en)
JP (1) JP2022554045A (en)
KR (1) KR20220024070A (en)
CN (1) CN114008270A (en)
WO (1) WO2020262735A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982484B (en) * 2021-03-04 2022-07-12 中国建筑第八工程局有限公司 Semi-synchronous sequential construction method for underground and overground structure

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2757026B2 (en) * 1989-07-14 1998-05-25 株式会社竹中工務店 Reverse construction method of basement structure
JPH05255943A (en) * 1991-09-13 1993-10-05 Takenaka Komuten Co Ltd Construction method for underground skeleton by slide down system
KR20090090742A (en) * 2008-02-22 2009-08-26 삼성물산 주식회사 Bottom-up construction method of underground structure using permanent strut
CN101736756B (en) * 2009-12-04 2011-06-22 上海市第二建筑有限公司 Method for constructing soft soil foundation reverse interlayer
KR101267565B1 (en) * 2012-02-13 2013-05-24 주식회사 한빛구조엔지니어링 Construction method of under-ground core part structure in top-down construction procedure
KR101327785B1 (en) * 2012-04-23 2013-11-11 대림산업 주식회사 Construction Method of Core Part in Building
CN104234082A (en) * 2014-08-29 2014-12-24 中国电建集团华东勘测设计研究院有限公司 Jump-layer reversed construction method for deep foundation pit
JP6937205B2 (en) * 2017-09-21 2021-09-22 大成建設株式会社 How to build an underground structure
KR102320104B1 (en) * 2017-12-20 2021-11-02 양경옥 Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project

Also Published As

Publication number Publication date
WO2020262735A1 (en) 2020-12-30
US20220243418A1 (en) 2022-08-04
JP2022554045A (en) 2022-12-28
CN114008270A (en) 2022-02-01

Similar Documents

Publication Publication Date Title
KR102588684B1 (en) Method for constructing basement vertical member of top-down method constructed alternately
KR102301605B1 (en) A Method of Bottom-up Removal of Underground Structures
JP2015025292A (en) Building construction method and building
CN105178358B (en) Vertical supporting system for reverse construction method and construction method of vertical supporting system
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
KR102290076B1 (en) The construction method using a exterio wall of undergound structure
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
KR20220024070A (en) The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time
KR101310677B1 (en) Top down method using precast composite retaining wall and raker in slope
CN114134931B (en) Reverse construction method for developing basement structure of existing building
KR20240144025A (en) Method of constructing underground vertical members using Top Down Construction Method of alternating construction one by one
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
US12084854B2 (en) Top-down construction method for multi-storey basement with full steel structure
KR20240069939A (en) Construction Method of Ground Floor Core Construction according to Start of Semi-Basement Core at 1st Basement Floor in Top-Down Construction
JPS61109827A (en) Construction of basement
KR101026112B1 (en) The construction method of underground structure using mega-structure
KR20240068954A (en) Continuous construction method of the superstructure by adding spare piles to the lowest basement floor in the top-down construction project
KR100593203B1 (en) a deck supportframe and a construction methed
JPH05255943A (en) Construction method for underground skeleton by slide down system
JP7462475B2 (en) How to build a building
KR0150304B1 (en) A method of simultaneously constructing frameworks for floors and basements of a building
CN109736589B (en) Construction method of lattice column force transmission component
KR20240138893A (en) Structure construction method for apartment remodeling using climbing bracket
JP4005259B2 (en) How to build columns and beams