Detailed Description
The construction method of every other underground vertical member constructed by the back drilling method according to the present invention will be described in detail.
FIG. 1 is a general flow diagram of a method of constructing a subterranean vertical member for back drilling every other construction according to an embodiment of the present invention. The target project is SRC office building with 6 underground floors and 39 above ground floors.
Referring to fig. 1, in the construction method of the underground vertical member of the present embodiment, in the soil retaining construction step S10, a soil retaining wall is constructed on the underground floor based on the outer wall of the underground floor of the building, and a slurry wall, CIP, H-pile and ground plate are constructed.
In the underground pile construction step S20, pillars of the building are constructed in a counter-drilling method from the ground to the foundation and the floor mat to support the underground slabs, and PRDs and RCDs are constructed.
In a floor construction step S30, a floor is completed by excavating a ground floor using the pillars constructed in the step S20 and pouring steel beams, decks and concrete.
In the one-underground floor constructing step S40, the two-underground floor is excavated and the one-underground floor is completed like the first floor.
In the underground one-story vertical member (core, column) construction step S50, the underground 1-story to underground one-story completion core constructed in the step S40 is constructed with the core frame from the above-ground story up.
In the above-ground frame (first) construction step S60, the above-ground core section and the columns are completed from the columns from the core section of the next floor constructed in the above-described step S50. For example, if due to the structural conditions of the PRD document, a frame of 8 stories may be built before the floor mat is constructed, and in the above-ground-level frame (first) step, the frame is built to 8 stories.
In the underground second floor slab construction step S70, after the underground triple-story floor slab is excavated downward after the step S40, the underground second floor slab is constructed.
In the underground triple floor construction step S80, after the underground four floors are excavated downward after the S70 step, the underground triple floor is constructed.
In the construction step S90 of the underground 3-layered vertical member according to the feature of the present invention, the underground 3-layered floor panel constructed in the step S80 completes an underground 3-layered core part. After the one-underground-layer core section is constructed in the step S50, the two-underground-layer core section is not constructed, and the three-underground-layer core section is constructed every other layer, so that the construction can be performed in order, and the construction is convenient.
Conventionally, a core part of 3 underground layers is constructed in order from 6 underground layers after a mat is laid, and according to the present invention, a vertical member of 3 underground layers is constructed first every other layer after the core part of one underground layer, thereby shortening a construction period.
In the underground 4-layer ground floor construction step S100, after the underground 5-layer ground floor is excavated downward after the step S80, the underground four-layer ground floor is constructed.
In the underground 5-layer ground floor construction step S110, after the underground 6-layer ground floor is excavated downward after the step S100, the underground 5-layer ground floor is constructed.
In the underground 5-layer vertical member construction step S120 according to a feature of the present invention, the underground 5-layer floor slab constructed in the step S110 completes an underground 5-layer core part. After the construction of the underground 3-layer core unit is completed in step S90, the construction of the underground 4-layer core unit is omitted, and the construction of the underground 5-layer core unit can be performed for every other layer in order.
In the related art, the core part of the underground 5-story floor is constructed in order from the underground 6-story floor after the floor mat is cast, but according to the present invention, the vertical members of the underground 5-story floor are constructed every other floor after the core part of the underground 3-story floor is constructed, thereby shortening the construction period.
The underground 3-story vertical member construction step S90 and the underground 5-story vertical member construction step S120 are previously constructed in sequence for each story before laying the floor mat according to the features of the present invention, thereby shortening the construction period.
Then, in a foundation or floor mat construction step S130, after the final downward excavation after the step S110, a foundation and a floor mat are constructed. After the ground mat is constructed, the ground mat turns around, and the vertical members of the underground layer and the framework of the overground layer are constructed upwards at the same time. For example, the above-ground frame may be raised to 8 stories before the flooring is paved until 15 stories after the underground vertical members are completed, and the uppermost roof layer can be constructed after the underground vertical members are completed.
After the foundation and the floor mat are completed S140, underground vertical members (core, pillars) are constructed.
Among the underground vertical members, the underground 1 st floor (S50), the underground 1 st floor (S90), and the underground 5 th floor (S120) are previously constructed according to the present invention, and thus the remaining vertical members are the underground 6 th floor, the underground 4 th floor, and the underground 2 nd floor. In the present invention, when the remaining vertical members are constructed (underground 6, 4, 2), since the core part has been constructed above and below the corresponding floors, there are advantages and characteristics that the construction can be performed simultaneously (S150, S160, S170).
In the prior art, after the core part of the underground 6 layers is constructed, the underground 5 layers are constructed firstly, and then the underground 4 layers, the underground 3 layers and the underground 2 layers are constructed in sequence. However, according to the present invention, since the remaining vertical members (underground 6, 4, 2) can be constructed at the same time, only one construction period is required.
Therefore, before the floor mat is placed, the core parts of 2 layers of 3 layers and 5 layers of the ground are constructed firstly, after the floor mat is laid, the other vertical members (6, 4 and 2 layers) are installed at the same time, and the effect of pre-building 4 layers integrally is achieved. Therefore, when 25 days are required for the vertical member of one layer, 125 days are conventionally required, but according to the present invention, 25 days are required, thereby reducing the total construction period of 100 days.
When the underground vertical member is completed as described above S170, then the above-ground truss (secondary) may be started S180. For example, the above-ground framework (primary) may be constructed to 15 floors above the ground until the underground vertical members are completed, and after the underground vertical members are completed, the above-ground framework (secondary) S180 may be constructed without limitation from 16 floors to the top floor.
Fig. 2 to 3 are examples of process tables of every other constructed underground vertical member construction method according to the present invention.
Referring to fig. 2, the present embodiment is an office building with 6 floors below ground and 39 floors above ground, and is an SRC group, and the construction method is upside down. The start date was 2019, 1 month, 1 day.
Referring to the process table, the H-pile/CIP construction was performed at the earth retaining construction stage (job number 6 in the first row on the left side of the process table) for 80 days.
A plurality of piles are constructed on the underground layer by the 7-bead triangle in the engineering, and the construction period is 70 days.
After excavation of No. 8 engineering of the underground layer and No. 7 triangular engineering of No. 1 base plate bead are completed, 1 layer of steel beams are installed on the piles, and a deck and concrete are poured into the SRC building, wherein the construction period is 50 days.
The underground second layer excavation and underground first layer bottom plate construction (No. 9 project, lower drawing number) is that after the first layer bottom plate 8 is finished, the underground second layer is excavated downwards, then the underground first layer bottom plate 9 is constructed, and the construction period is 50 days.
When the next layer of panels 9 is completed, the core and pillars 22 of the next layer are constructed so that the construction can proceed to the ground. Therefore, the underground downward engineering and the bottom upward construction are performed simultaneously, which is generally called top-down construction.
When the core section 22 of the next floor is completed, continuous operation is possible from the floor second floor 25 to the eight floor 31. At this time, the loads from the eight storied buildings are all received by the bead triangles.
Since the 9-story floor 32 can be performed only when the cushion concrete 15 is constructed, the construction is stopped for about 4 months after the 8-story floor 31 is completed. According to the structure calculation, the bead triangle can only support the load of 8 layers 31 on the ground, so the 9 layers 32 can be started after the ground cushion is placed.
Alternatively, the construction of the floor level may begin from floor 2 after about 3 months, and the wait time between floors 8 and 9 may be minimized to continue the construction, or the construction to floor 8 may be slowly progressed.
After the underground first floor 9 is finished, the underground third floor is excavated, and then the underground second floor 10 is constructed, wherein the construction period is 50 days.
After the underground 2-layer bottom plate 10 is finished, 4 underground layers are excavated, an underground 3-layer bottom plate 11 is constructed, and the construction period is 50 days.
When the underground 3-layer panel 11 is completed, the underground 3-layer core 20 is first constructed according to the features of the present invention. In the conventional construction method, after the floor mat 15 is completed, the core 20 of the underground 3-layer is constructed from the underground 6-layer upward. Therefore, according to the present invention, the underground three-layer core unit 20 is constructed earlier than the conventional construction method, thereby shortening the construction period.
After the underground 1-level core unit 22 is constructed, the underground 2-level core unit 21 of the lower level is skipped, and the underground 3-level core unit 20 is constructed on every floor. The reason is that it is difficult to adopt counterattack construction by the core section 21 of the underground 2 layer immediately below after the construction of the underground 1 layer core section 22 because it is difficult to construct a connection section. Therefore, when the core part 20 of the underground 3-stories is constructed every other story after the core part 22 of the underground one-story is constructed, since the underground 2-stories as the upper story are empty, the underground 3-stories can be sequentially operated, and the construction is easy.
When every other layer of the subsurface one-layer core 22 and the subsurface three-layer core 20 is completed, the intermediate subsurface two-layer core 21 may be constructed by sandwiching.
And after the underground 3-layer bottom plate 11 is finished, continuing to construct downwards, and after 5 underground layers are excavated, constructing an underground 4-layer bottom plate 12, wherein the construction period is 50 days.
After the 4-layer underground bottom plate 12 is finished, the 5-layer underground bottom plate 13 is constructed after 6 underground layers are excavated, and the construction period is 50 days.
At this time, when the underground 5-layer floor 13 is completed, the underground 5-layer core section 18 is constructed according to the features of the present invention. In the conventional construction method, after the floor mat 15 is completed, the core 18 of the underground 5-layer is constructed in the order from the underground 6-layer upward. Therefore, according to the present invention, the core part 18 of the underground 5-story building has a feature of being constructed first as compared with the conventional construction method, and has an effect of shortening the overall construction period.
After the underground 3-layer core unit 20 is constructed, the underground 4-layer core unit 19 is skipped and the underground 5-layer core unit 18 is constructed every other layer. The reason is that after the underground 3-layer core section 20 is constructed, the underground 4-layer core section 19 of the next layer is constructed by counterattack, and it is difficult to construct the connection section. As in the case of the subsurface 3-layer core 20.
After the excavation of the underground 6 layers, the excavation 14 of the ground mat is performed, and then the foundation and the ground mat 15 are constructed.
When the floor mat 15 is completed, the floor may rise above the 9 th floor 32 as the floor mat 15 supports the load supported by the PRD.
On the other hand, the reason why the ground mat 15 is restricted from being constructed to the underground vertical members, and the ground layer can only be raised to 15 layers is that the underground layer is bent by PRD, and about 5 layers of PRD columns are exposed from 6 layers to 2 layers of the ground. However, according to the present invention, since odd-numbered floors have been constructed for every other floor, the PRD column is exposed only at the height of one floor, and since the buckling restriction is small, a new effect of constructing a higher floor according to the floor construction method is exhibited.
After completion of the floor mat 15, the remaining frameworks of the underground layer are the underground sixth core 17, the fourth underground core 19 and the underground second core 21. Since the subsurface 3-layer 20 and subsurface 5-layer core 18 have been completed in advance, the remaining three layers of cores may be constructed with sandwiching.
According to a feature of the present invention, since the core part of the odd-numbered layers is already constructed, the remaining three layers may be operated simultaneously or sequentially.
On the other hand, in the construction of the underground 2-layer core 21 and the underground 4-layer core 19, reinforcing bars are prefabricated and concrete is simultaneously poured after the floor mat 15 is placed to further improve productivity.
Therefore, the existing three-storey buildings need to be constructed in sequence, so that three storeys (about 75 days) are needed, and according to the characteristics of the invention, only one storey (25 days) is needed because the three storeys can be constructed at intervals, so that the effect of shortening two storeys is achieved.
According to the present invention, the core parts 20 of the underground 3-layer and the underground 5-layer are prefabricated alternately before the floor mat is constructed, and the construction period of two layers is shortened by alternately performing every other underground vertical member, and the core parts 17, 19, 21 of the remaining three layers are constructed simultaneously after the floor mat 15 is cast, thereby shortening the construction period of two layers and shortening the construction period of four layers in total. Since the core portion of the underground layer is a main line (Critical Path), the total air length is shortened.
Referring to fig. 3, a frame work from 5 to 39 floors above the ground and a finished work as a final work are shown. According to the calculation of the backstroke structure, the work can be started after 9 layers of bottom plates 32 are poured, and 16 layers of bottom plates 39 are a process table started after the underground vertical members are finished. From 16 th to 39 th, the frames are framed in a 6 day period, and the trimming work is generally carried out for one year. The decoration engineering comprises indoor decoration engineering, elevator engineering, temporary dismantling engineering such as an outer curtain wall and a tower crane, roofing engineering, landscaping engineering and the like.
Therefore, the entire construction period of a 39-story office building is 1, 106 days (about 36 months) if the underground vertical structure construction method according to the present invention is applied every other construction, as shown in operation 1 of fig. 2. Compared with the existing construction mode, the total construction period is shortened by about 3 months.
Fig. 4 is an enlarged process chart of the process of the underground vertical structure of fig. 2 according to the present invention as described above.
Referring to fig. 4, the vertical members of the odd-numbered layers (the underground 1-layer core 22, the underground 3-layer core 20, and the underground 5-layer core 18) among the underground vertical members are started after the completion of the floor of the corresponding layer, and the remaining vertical members of the even-numbered layers (the underground 6-layer core 17, the underground 4-layer core 19, and the underground 2-layer core 21) are constructed in parallel with the floor mat 15 at the same time after the casting.
The remaining even numbered vertical members 17, 19, 21 are characterized by being sandwiched and constructed simultaneously as every other odd numbered level has been installed.
Fig. 5 is a process table example of the latest starting point of every other constructed underground vertical member according to the present invention.
The latest construction time is a construction period in which construction can be performed at the latest without affecting subsequent processes. A later start or completion refers to a schedule that can be constructed latest without affecting subsequent flows.
Referring to fig. 5, the core unit 22 of the underground 1-layer is constructed for the above-ground works 25 to 25 after the completion of the floor of the underground 1-layer. It is then shown that the underground 3-layer core 20 can be constructed at the latest before the construction of the even-numbered underground vertical members 17, 19, 21.
Fig. 6 is a comparative process table of the earliest and latest starting points of every other constructed underground vertical member according to the present invention. Fig. 6 is a view for explaining which date or time in the work schedule the underground vertical structure is constructed due to the construction order determination.
Referring to fig. 6, operation numbers 16 to 21 denote fast processing (fig. 4), and operation numbers 23 to 28 denote slow processing (fig. 5). The core of the subsurface 3 layer may be compared by work number 20 at the early stage and work number 27 at the slow stage. That is, looking at the 20 th starting column, the underground 3 th layer can be started quickly in 1 st 2020, and can be started from 27 th in 5 th 15 th 2020. Of course, it may begin at any time between 1 month, day 1 and 5 months, day 15.
As described above, the concept and embodiment of the construction method of the underground vertical members according to every other construction of the present invention have been described with reference to fig. 1 to 6.
The construction concept and embodiment of the underground vertical member of the prior art method in the back-drilling method will be explained by using fig. 7 to 10.
Fig. 7 is a general flow chart for constructing an underground vertical member according to a conventional method.
Referring to fig. 7, after a retaining wall T10 is constructed outside a building, PRD or RCD piles T20 are constructed underground to form a rudder frame. Then, the site plates T30 to T100 are downwardly applied at the same time of excavating the underground trench. T100 after the underground 6 layers are excavated, and the foundation and the ground mat T110 are completed.
Then, the underground vertical members T130-170 are constructed in order from the underground 6 th floor T130 upward.
On the other hand, in the above ground level, after the core section T50 in the next ground level is completed, the above ground structure (primary) T60 is constructed. For example, up to floor 8 above ground until the mat is poured. After laying the mat, the upper frame is constructed (twice) from 9 to 15 floors above the ground (T180). After the underground vertical members (T130-170) are built, construction can be carried out from 16 layers above the ground without limitation.
In the existing back drilling method, after a floor mat is constructed from the ground to the lowest floor mat, the floor mat is turned around as a turning point, and underground vertical members are constructed upwards in sequence.
Therefore, the sequence of underground layers is long, and the underground construction period is long.
Fig. 8 to 9 are general process charts of the back-drilling method to which the conventional method is applied.
Referring to fig. 8, the conventional back drilling method is a reverse top-down construction method for an office building with 6 underground layers and 39 above ground layers, which is an SRC group. The start date was 2019, 1 month, 1 day. As in fig. 2. The reason why the existing construction method is applied to explain the progress is to check the difference between the construction order and the total construction period of the construction method according to the present invention.
Referring to the process table, the retaining wall construction stage (project No. 6 in the first column on the left side of the process table) is H-pile/CIP project, and the construction period is 80 days.
The bead triangle of the project 7 is constructed by a plurality of piles in an underground layer, and the construction period is 70 days.
In the No. 8 project, after the construction of the bead triangle No. 7 project is finished, underground 1-layer excavation and 1-layer bottom plate construction are carried out, in the SRC project, a first-floor steel beam is installed on a pile, a deck and concrete are poured, and the construction period is 50 days.
After the excavation of the underground 2 layers and the construction of the underground 1 layer bottom plate (project 9, hereinafter, referred to as a number) are completed, after the excavation of the underground 2 layers, the underground 1 layer is constructed, and the construction period is 50 days.
When the underground 1-ply floor 9 is completed, the underground one-ply core and the pillars 22 are constructed so that the construction can be performed to the above-ground floor. Thus, the subsurface and sub-surface upward construction is performed contemporaneously, which is commonly referred to as top-down construction.
When the subsurface 1-layer core 22 is completed, continuous operation is possible from the ground 2-layer panel 25 to the eight-layer panel 31. At this time, the loads to the eighth floor are all supported by the bead triangles.
Since the 9-story floor 32 can be performed only when the cushion concrete 15 is constructed, the construction is stopped for about 4 months after the 8-story floor 31 is completed. Since the bead gores can only support the load to floor 8 31, floor 9 can begin with the floor pad.
After the underground first floor 9 is finished, the underground third floor is excavated, and then the underground second floor 10 is constructed, wherein the construction period is 50 days.
After the underground 2-layer bottom plate 10 is finished, 4 underground layers are excavated, an underground 3-layer bottom plate 11 is constructed, and the construction period is 50 days.
When the underground 3-layer plate 11 is finished, the construction is continued downwards, and after the underground 5 layers are excavated, the construction of the underground 4-layer plate 12 is carried out for 50 days.
After the 4-layer underground bottom plate 12 is finished, the 5-layer underground bottom plate 13 is constructed after 6 underground layers are excavated, and the construction period is 50 days.
After the excavation of the underground 6 layers, the excavation 14 of the ground mat is performed, and then the foundation and the ground mat 15 are constructed. When the floor mat 15 is completed, the floor may rise above the 9 th floor 32 as the floor mat 15 supports the load supported by the PRD.
When the floor mat 15 is completed, the underground vertical members 17 to 21 are directly connected from the core 17 of the underground 6 floor to the core 21 of the underground 2 floor, which takes 25 to 30 days per floor. During this time, the sub-floor may be constructed from 9 courses 32 to 15 courses 38.
Referring to fig. 9, floors 10 to 39 and finishing work are shown. The 16-level floor 39 is a process table that is started after the completion of the underground vertical structures. From 16 stories to the top of the building, the underground stories are not limited at all, and are framed in a 6-day cycle, typically for one year finishing work.
Therefore, the total construction period of a 39-story office building is 1,194 days (about 39 months) as shown in operation 1 of fig. 8 if the underground vertical member construction method according to the present invention is applied every other construction.
The total air of 39 months is 3 months longer than the total air of 36 months according to the invention. The reason is that it takes much time to construct the underground vertical wall from the underground 6 to the underground 2 in sequence.
Fig. 10 is an enlarged process chart of the subterranean vertical member process of the prior art method of fig. 8. After the floor mat 15 was constructed with the underground vertical members, it was shown that the construction was performed in order from task number 17 to task number 21, and the construction period was 130 days, which took about 4.3 months.
Fig. 11 is a comparative process table comparing underground vertical structures of the prior art method and every other underground vertical structure constructed according to the present invention.
Referring to fig. 11, operation numbers 1 to 19 are process tables of the prior art method, operation numbers 20 to 38 are process tables of the present invention, and operation number 39 shows the difference between the prior art method and the process method of the present invention.
First, in the prior art method, the core of the underground 5-layer is constructed in sequence after the floor mat 10 is constructed, showing that 130 days are required, from operations 12 to 16.
On the other hand, according to the invention, from operations 31 to 35, only 30 days are required after the mat 29 has been constructed, indicating the lack of 100 days for the invention (39).
The reason is that the core 34 of the underground 3-layer and the core 32 of the underground 5-layer are constructed in advance, and the remaining 3- layer cores 31, 33, 35 are inserted simultaneously or at the same time after the floor mat 29 is constructed. After every other odd core part is constructed, the remaining even floors are constructed once, so that the existing method needs 5 times of construction finally, and the effect of shortening 100 days of 4 floors by only one construction is shown in the invention.
Fig. 12 to 13 are a time table difference comparison table for each floor comparing the overall process table (fig. 8, 9) of the prior art method with the overall process table (fig. 2, 3) of every other constructed underground vertical member according to the present invention.
Referring to fig. 12, the total air difference (job number 1) for both methods was 88 days, which was reduced from 36 months to about 39 months, about 3 months, and it can be seen that the total air was reduced by about 8%.
Underground excavation, reverse slab and ground mat construction 6-15) are the same.
The difference occurs in the underground vertical members because every other underground vertical member (core) is constructed downward according to the present invention while the remaining core is constructed.
The last column I is the value of the completion date for each floor (column E) of the prior method subtracted from the completion date for each floor (column H) according to the present invention.
The 88-day difference is fixed starting from 16 layers (39) above ground and continues until the construction is completed.
Referring to fig. 13, the progress difference (I completion date difference column) of 88 days from the above-ground 16 th floor (39)) is shown to continue until completion.
Fig. 14 is a graph comparing the S-curve form of the overall schedule of the prior method (fig. 8 and 9) with the overall schedule of every other constructed underground vertical structure according to the present invention (fig. 2 and 3) and fig. 12-13.
Referring to fig. 14, blue lines represent prior art methods and red lines represent methods of the present invention.
The work is started 1 month and 1 day in 19 years, and 6 months and 8 days (the lowest points in the figure) in 2020, 6 layers of ground mats are poured.
Then, the red line according to the present invention indicates that two layers are constructed every other layer, three layers are simultaneously constructed within one month, the underground vertical structure is completed, and then 16 layers are accessed.
On the other hand, the blue line is an existing construction method, indicating that it takes about 4.3 months for the underground vertical members of each floor to pass to 16 floors after the floor mat is constructed. From 16 layers and above, the two construction methods are the same.
As described above, the differences between the existing method and the method of the present invention are compared by the process table, the table, and the graph.
The following is a description of a case where a partial operation is performed differently in an embodiment of the present invention.
Under the condition of final excavation of the underground 5 layers, an underground core part is firstly constructed downwards on the underground 1 layer and the underground 3 layer, after the ground mat is finished, the underground 5 layer is constructed, and then the underground 4 layer and the underground 2 layer are constructed simultaneously. Thus, the remaining core is mounted twice after the mat.
In the case of final excavation of the underground 4 layers, the underground core part is first constructed downwards on the underground 1 layer and the underground 3 layers, and after the ground mat is completed, the underground 4 layers and the underground 2 layers can be constructed simultaneously. The concept is the same as that of the underground 6-story building.
Because the underground layer is not high, the two lowest layers (such as 5 underground layers and 6 underground layers) are dug at the same time, then ground mats are laid, and then an underground 5-layer bottom plate is constructed. In this case, the core part of the underground 6-layer and the floor of the underground 5-layer are simultaneously constructed, and then the core part of the underground 5-layer is constructed. Thus, the remaining core is mounted twice after the mat.
As described above, in the case of excavating two floors of odd-numbered floors or the lowest floor at the same time, some construction items involve sequentially constructing the remaining core portions twice after the completion of the floor mat. Therefore, according to an embodiment of the present invention, after every other core unit is completed, the remaining core units are mostly completed once, and in the local construction project, the remaining portion may be constructed twice.
The process table of the above embodiment is prepared by a program specializing in process table preparation, and date calculation is an accurate example. The conder diagram is a red bar graph in the milestone, and the key pass, which is the main line, represents the main task of determining total air. The blue bar graph represents work with float. Therefore, in order to shorten the air, the red line as the main line must be shortened. Connecting lines containing arrows connect the bar graphs of the milestone meter (relationships represent context between tasks).
In summary, according to the features of the present invention, it can be seen that there may be some derived sequential core structures depending on the features of the site, based on the idea of completing the core alternately every other time in order to shorten the construction period of the underground core which determines the overall construction period. However, unlike the existing construction method sequential core construction method, according to the idea of shortening the entire construction period by every other core construction method according to the present invention, the engineer engaged in construction work will clearly understand that the partially modified core construction method is included in the spirit of the present invention.
Sequence of vertical member construction method in case of the back-drilled underground 8 layers alternately constructed according to the embodiment of the present invention.
The construction sequence is as follows.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second layers of the ground
Pouring reinforced concrete (pouring plate) in the underground layer of the steel bridge deck
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Excavating 6 underground layers
Laying of underground 5-layer bottom plate
Underground 7-building excavation
Pouring 6 underground layers of bottom plates and 5 underground layers of core wall columns
Digging 8 underground layers and ground mats
7-layer underground pouring slab and 7-layer underground pouring core wall column
Paving 8 layers of underground floor mats
Core wall column installation of underground 8, 6, 4 and 4 of the rest (4 simultaneous construction)
Or 2 layers of core wall column construction (2 layers and 2 times of construction) which is remained after 2 layers of construction by adding 8 layers and one layer of underground
Or, 2 and 3 layers of core wall columns are constructed on each layer by adding 8 layers and one layer of underground, 2 layers are constructed after 1 time of 2 layers, and 3 times of 1 layer and 2 layers are constructed totally (2 layers are constructed for 1 time and 3 times of 1 layer and 2 times)
Or, after the core wall column of 8 underground layers is constructed, the rest 3 layers are constructed in a layering way (4 layers are constructed for 4 times in total)
And 4, pouring the rest layers of the ground mat in layers 1, 2, 3 and 4.
The following is a sequence of a vertical member construction method in the case of a reverse drilling underground 7 layers alternately constructed according to an embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Excavating 6 underground layers
Laying of underground 5-layer bottom plate
Underground 7-building excavating and excavating ground mat
Pouring 6 underground layers of bottom plates and 5 underground layers of core wall columns
Paving 7 layers of ground in the ground
In the underground 7, 6, 4 and 2 of the rest layers
After 7 layers and 1 layer of the ground (1 layer is selected from 4 layers or 2 layers of the ground) are added, 2 layers of 2 times of core wall column construction (2 layers of 2 times of construction) are remained after 2 layers of one-time construction
Or 2-layer construction of 7 layers and the rest 3 layers, and construction of the rest 1 layer (3 times of construction in total)
Or one layer is constructed once, and the construction is carried out for four times.
This is the sequence of the vertical member construction method in the case of the alternately constructed back-drilled underground 6 layers according to one embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Excavating 6 underground layers and ground mats
Laying underground 5-layer bottom plate
Pouring 6 underground layers of bottom plates and 5 underground layers of core wall columns
In the underground 6, 4 and 2 of the rest layers
The other 3 layers are constructed at the same time (1 time in total)
Or, after 6 underground layers are constructed, 4 underground layers and 2 underground layers are constructed at the same time (2 times in total)
Or constructing 6 underground layers and 4 underground layers at the same time and then constructing 2 underground layers (2 times in total)
One layer is constructed at a time, and the construction is carried out for 3 times (3 times of separated construction).
This is the sequence of the vertical member construction method in the case of the sub-surface 5 layers of the back-drilling method of alternating construction according to one embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers and ground mats
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Laying underground 5-layer bottom plate
In the underground 5, 4, and 2 of the rest layers
Construction of 4 underground layers and 2 underground layers (2 times in total) at the same time after construction of 5 underground layers
Or constructing 4 underground layers after the 5 underground layers and the 2 underground layers are constructed at the same time (2 times in total)
The other 3 layers are constructed one layer at a time (3 times in total).
This is the sequence of the vertical member construction method in the case of the underground 4-layer of the back-drilling method of alternating construction according to one embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers and ground mats
Pouring 3 underground layers of bottom plates and 3 underground layers of core wall columns
Laying 4 underground layers of bottom plates
In the underground 5 or 2 of the rest layers
Construction of 4 underground layers and 2 underground layers at the same time (1 time in total)
The other 2 layers are constructed one layer at a time (3 times in total).
Industrial applicability of the invention
At present, most of the top-down construction is carried out in city center construction. For other various construction methods according to the present invention, a structural design room is first designed, and then a contractor manufactures steel frames and forms, and then construction is performed. Therefore, the present invention can be directly applied to the industry.