CN114008270A - Reverse drilling underground vertical member construction method for alternate construction - Google Patents

Reverse drilling underground vertical member construction method for alternate construction Download PDF

Info

Publication number
CN114008270A
CN114008270A CN201980097932.3A CN201980097932A CN114008270A CN 114008270 A CN114008270 A CN 114008270A CN 201980097932 A CN201980097932 A CN 201980097932A CN 114008270 A CN114008270 A CN 114008270A
Authority
CN
China
Prior art keywords
underground
construction
constructed
layer
core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201980097932.3A
Other languages
Chinese (zh)
Inventor
梁京沃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of CN114008270A publication Critical patent/CN114008270A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/02—Foundation pits
    • E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00—Independent underground or underwater structures; Retaining walls
    • E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/06—Foundation trenches ditches or narrow shafts
    • E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083—Shoring struts
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00—Temporary installations or constructions
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00—Materials
    • E02D2300/0004—Synthetics
    • E02D2300/0018—Cement used as binder
    • E02D2300/002—Concrete
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00—Materials
    • E02D2300/0026—Metals
    • E02D2300/0029—Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明提供一种为缩短施工中地下骨架的周期,采用自上而下的反钻法,更具体地,涉及通过提供每隔一个地下垂直构件(核心部,柱子)向下安装,然后将剩余的垂直构件利用同时期施工的施工方法缩短整体施工工期。安装挡土墙和地下柱桩后,包括:开挖地下1层及施工地上一层底板的第一步;向下施工地下层板,同时期先施工地下1层核心部以支撑向上施工的底层核心部的第二步;每隔一个地下垂直构件向下施工的第三步;施工最底层地垫或地基后,同时期安装剩余的地下垂直构件的步骤,通过缩短地下垂直构件,可以提早开始后期的地上构筑和收尾工作,从而缩短整体工期。

Figure 201980097932

The present invention provides a top-down back-drilling method in order to shorten the period of the underground skeleton during construction, and more particularly, involves installing every other underground vertical member (core, column) downward, and then removing the remaining The vertical components of the building use the construction method of the same period of construction to shorten the overall construction period. After installing the retaining wall and underground column piles, it includes: the first step of excavating the first underground floor and the ground floor of the first floor above the ground; constructing the underground floor slab downward, and constructing the core part of the first underground floor at the same time to support the bottom floor constructed upward The second step of the core part; the third step of the downward construction of every other underground vertical member; the steps of installing the remaining underground vertical members at the same time after the construction of the lowest floor mat or foundation can be started earlier by shortening the underground vertical members Later on the ground construction and finishing work, thereby shortening the overall construction period.

Figure 201980097932

Description

Reverse drilling underground vertical member construction method for alternate construction
Technical Field
The present invention relates to a method of back drilling from the top down in order to shorten the period of an underground framework in construction, and more particularly, to a method of constructing underground vertical members and shortening the overall construction period by providing a construction method in which every other underground vertical member is installed downward and then constructing the vertical members of the remaining floors after installing a floor mat and a foundation.
Background
The reverse-perforation method (from top to bottom) is a method for shortening a construction period by constructing a frame on a ground floor and simultaneously constructing a frame on a ground floor.
The general sequence of the underground back drilling construction is to install retaining walls and columns, excavate each layer, construct slabs, and finally construct the lowest floor foundation or ground mat with a depth of 4 to 7 layers underground.
In the underground vertical member, a pile is constructed at the initial stage of construction, the core part of the underground layer is used for the frame work of the overground layer, and the other vertical members are installed by rolling (from the lower layer to the upper layer) after the foundation or the ground mat is poured.
In this case, the above-ground frame work is constructed simultaneously with the underground layer, but the number of layers to be raised before the foundation and the floor mat are constructed and the number of layers to be raised before the underground vertical members are completed are structurally limited. For example, the floor of the 8 th floor of the ground can be reached before the foundation and the floor mat are laid, the floor of the 15 th floor above the ground can be reached at most before the underground vertical member is completed, and construction restriction to the roof can be given without any restriction after the underground vertical member is completed.
Therefore, if the underground frame construction period is increased, the above-ground frame can be constructed only to 8 or 15 floors and then stopped to wait. On the contrary, if the construction of the underground frame is accelerated, the construction of the overground frame is also accelerated, so that the whole construction period is greatly influenced by the construction work of the underground layer.
Particularly, in the case of the above-ground frame, it takes about 6 to 7 days to construct one floor, and thus four or more floors are constructed in one month, and for the underground floors, it takes 1.5 or 2 months for each floor, and thus the construction speed of the underground floors is relatively slow.
The conventional top-down reverse punching method has the following problems.
The existing underground construction sequence includes retaining wall, pile, excavation and slab construction of each layer, foundation or floor mat construction of the lowest layer, and upward construction of underground vertical members.
At this time, the underground vertical member has a characteristic of being sequentially performed (construction from a lower layer to an upper layer) after the foundation or the floor mat is cast. The construction period of the underground vertical member is 20-25 days for one layer, and the construction period of the underground 6 layers is 4-5 months.
The underground vertical members are installed in order (from bottom to top) after placing the foundation or floor mat. Since the bottom layer can continue to rise after the underground vertical member is completed, the underground vertical member is a critical path for determining the construction period.
On the other hand, the construction speed of the above-ground structure is fast, the period per floor is 6 to 7 days, the completion of laying the ground floor mats (for example, 8 floors) and the underground vertical members (15 floors) is limited, and the construction stops at the inflection points of the 8 floors and the 15 floors, and the phenomenon of waiting for construction occurs.
During the construction of the underground vertical member, the continuous and smooth construction of each floor must be achieved without any lacked condition. Even if one floor is delayed, the construction of the floor is delayed. Therefore, the existing construction method requires continuous and smooth construction of the underground vertical member in a short time, and has high delay risk.
The back drilling method has the advantages that the bottom layer is constructed at the same time of constructing the underground layer, and the construction period is shortened. However, the construction speed of underground floors is limited by the structure that the ground floors cannot be raised to a level higher than a certain level, and thus the construction of underground floors greatly affects the air quality.
The related applications are as follows.
Application no/date 1020110024619(2011.03.18), applicant hanbit structural engineering limited, registration no/date 1012420170000(2013.03.05), the title of the invention is a parallel construction method of an above-ground and underground structure using a grid type lintel in a core tube and constructing an above-ground core tube first
Construction method
Application No. 1995-
Application No. 10-2003-0037296, application No. 6/10/2003, building structure of reinforced concrete structure and steel frame reinforced concrete structure mixed structure and method for simultaneous construction thereof
Application No. 10-2011-
Application numbers 10-2013-
Disclosure of Invention
Technical problem to be solved
The present invention has been made in view of the above problems, and it is an object of the present invention to provide a back drilling method that shortens a construction period of an underground vertical member, enables work of an above-ground framework to be continuously performed, and shortens the entire construction period.
Technical scheme
In order to accomplish the object, in the alternately constructed underground vertical member construction method according to the present invention, every other underground vertical member is alternately constructed downward, and thereafter, the remaining vertical members are dispersed among the previously constructed vertical members and simultaneously inserted.
Advantageous effects
According to the present invention, the following effects can be expected.
The construction period is shortened by pre-building a plurality of underground vertical members on the whole process table and excluding a main process line (critical path) which determines the construction period.
Through constructing every other vertical member underground, the buckling length of the column is shortened, more ground floors can be constructed, and the whole construction period is shortened.
If every other underground vertical member is installed, the rest upward construction can be carried out at the same time, so that the whole construction period is shortened.
Because the underground vertical member can be constructed as early as possible after the construction of the bottom plate of the corresponding floor, the construction delay margin is small, and the whole construction period can not be delayed.
By only constructing the reinforcement assemblies first and pouring concrete at the same time, the construction period can be further shortened.
After the existing ground mat is poured, the vertical member is installed on an underground 6 layer, and then an underground 5 layer, an underground 4 layer, an underground 3 layer and an underground 2 layer are sequentially installed. In the case of the existing 5-story construction in order, a total of 125 days is spent in the case of 25 days per story, but according to the present invention, before the mat is laid, the odd-numbered stories are completed, and after the mat is laid, the even-numbered stories, i.e., the 6-story underground, the 4-story underground and the two-story underground are constructed simultaneously, using only 25 days. As a result, 125 days are required after the conventional floor mat, but 25 days are required according to the present invention, and thus the result is shortened by 100 days. Therefore, the whole construction period is shortened by about 100 days.
According to the present invention, the office building of the 6 th floor below the ground and the 39 th floor above the ground shows an effect of shortening the period of about 3 months (about 8% of the total amount of air) from 39 months to 36 months.
The overall construction period of offices, office buildings and the like is reduced from the perspective of a construction company, construction management cost, site cost and other construction cost are reduced at the same time, and the economic effects of advanced sales, rent income and extra sales (accounting for 25 percent of annual sales) are higher from the perspective of an owner.
Drawings
Fig. 1 is a general flowchart of a construction method of every other constructed underground vertical member according to the present invention.
Fig. 2 to 3 are examples of process tables of a 39-story office building according to the construction method of every other constructed underground vertical members of the present invention.
Fig. 4 is an enlarged process chart of the process of the underground vertical structure of fig. 2 according to the present invention as described above.
Fig. 5 is a process table example of the latest starting point of every other constructed underground vertical member according to the present invention.
Fig. 6 is a comparative process table of the earliest and latest starting points of every other constructed underground vertical member according to the present invention.
Fig. 7 is a general flow chart for constructing an underground vertical member according to a conventional method.
Fig. 8 to 9 are examples of process tables of a 39-floor office building to which the conventional method is applied.
Fig. 10 is an enlarged process chart of the subterranean vertical member process of the prior art method of fig. 8.
Fig. 11 is a comparative process table comparing a prior art method and every other constructed underground vertical member according to the present invention.
Fig. 12 to 13 are a time table difference comparison table for each floor comparing the overall process table (fig. 8, 9) of the prior art method with the overall process table (fig. 2, 3) of every other constructed underground vertical member according to the present invention.
Fig. 14 is a process comparison chart comparing the overall process chart of the prior art method (fig. 8 and 9) with the overall process chart of every other constructed underground vertical member according to the present invention (fig. 2 and 3).
Detailed Description
The construction method of every other underground vertical member constructed by the back drilling method according to the present invention will be described in detail.
FIG. 1 is a general flow diagram of a method of constructing a subterranean vertical member for back drilling every other construction according to an embodiment of the present invention. The target project is SRC office building with 6 underground floors and 39 above ground floors.
Referring to fig. 1, in the construction method of the underground vertical member of the present embodiment, in the soil retaining construction step S10, a soil retaining wall is constructed on the underground floor based on the outer wall of the underground floor of the building, and a slurry wall, CIP, H-pile and ground plate are constructed.
In the underground pile construction step S20, pillars of the building are constructed in a counter-drilling method from the ground to the foundation and the floor mat to support the underground slabs, and PRDs and RCDs are constructed.
In a floor construction step S30, a floor is completed by excavating a ground floor using the pillars constructed in the step S20 and pouring steel beams, decks and concrete.
In the one-underground floor constructing step S40, the two-underground floor is excavated and the one-underground floor is completed like the first floor.
In the underground one-story vertical member (core, column) construction step S50, the underground 1-story to underground one-story completion core constructed in the step S40 is constructed with the core frame from the above-ground story up.
In the above-ground frame (first) construction step S60, the above-ground core section and the columns are completed from the columns from the core section of the next floor constructed in the above-described step S50. For example, if due to the structural conditions of the PRD document, a frame of 8 stories may be built before the floor mat is constructed, and in the above-ground-level frame (first) step, the frame is built to 8 stories.
In the underground second floor slab construction step S70, after the underground triple-story floor slab is excavated downward after the step S40, the underground second floor slab is constructed.
In the underground triple floor construction step S80, after the underground four floors are excavated downward after the S70 step, the underground triple floor is constructed.
In the construction step S90 of the underground 3-layered vertical member according to the feature of the present invention, the underground 3-layered floor panel constructed in the step S80 completes an underground 3-layered core part. After the one-underground-layer core section is constructed in the step S50, the two-underground-layer core section is not constructed, and the three-underground-layer core section is constructed every other layer, so that the construction can be performed in order, and the construction is convenient.
Conventionally, a core part of 3 underground layers is constructed in order from 6 underground layers after a mat is laid, and according to the present invention, a vertical member of 3 underground layers is constructed first every other layer after the core part of one underground layer, thereby shortening a construction period.
In the underground 4-layer ground floor construction step S100, after the underground 5-layer ground floor is excavated downward after the step S80, the underground four-layer ground floor is constructed.
In the underground 5-layer ground floor construction step S110, after the underground 6-layer ground floor is excavated downward after the step S100, the underground 5-layer ground floor is constructed.
In the underground 5-layer vertical member construction step S120 according to a feature of the present invention, the underground 5-layer floor slab constructed in the step S110 completes an underground 5-layer core part. After the construction of the underground 3-layer core unit is completed in step S90, the construction of the underground 4-layer core unit is omitted, and the construction of the underground 5-layer core unit can be performed for every other layer in order.
In the related art, the core part of the underground 5-story floor is constructed in order from the underground 6-story floor after the floor mat is cast, but according to the present invention, the vertical members of the underground 5-story floor are constructed every other floor after the core part of the underground 3-story floor is constructed, thereby shortening the construction period.
The underground 3-story vertical member construction step S90 and the underground 5-story vertical member construction step S120 are previously constructed in sequence for each story before laying the floor mat according to the features of the present invention, thereby shortening the construction period.
Then, in a foundation or floor mat construction step S130, after the final downward excavation after the step S110, a foundation and a floor mat are constructed. After the ground mat is constructed, the ground mat turns around, and the vertical members of the underground layer and the framework of the overground layer are constructed upwards at the same time. For example, the above-ground frame may be raised to 8 stories before the flooring is paved until 15 stories after the underground vertical members are completed, and the uppermost roof layer can be constructed after the underground vertical members are completed.
After the foundation and the floor mat are completed S140, underground vertical members (core, pillars) are constructed.
Among the underground vertical members, the underground 1 st floor (S50), the underground 1 st floor (S90), and the underground 5 th floor (S120) are previously constructed according to the present invention, and thus the remaining vertical members are the underground 6 th floor, the underground 4 th floor, and the underground 2 nd floor. In the present invention, when the remaining vertical members are constructed (underground 6, 4, 2), since the core part has been constructed above and below the corresponding floors, there are advantages and characteristics that the construction can be performed simultaneously (S150, S160, S170).
In the prior art, after the core part of the underground 6 layers is constructed, the underground 5 layers are constructed firstly, and then the underground 4 layers, the underground 3 layers and the underground 2 layers are constructed in sequence. However, according to the present invention, since the remaining vertical members (underground 6, 4, 2) can be constructed at the same time, only one construction period is required.
Therefore, before the floor mat is placed, the core parts of 2 layers of 3 layers and 5 layers of the ground are constructed firstly, after the floor mat is laid, the other vertical members (6, 4 and 2 layers) are installed at the same time, and the effect of pre-building 4 layers integrally is achieved. Therefore, when 25 days are required for the vertical member of one layer, 125 days are conventionally required, but according to the present invention, 25 days are required, thereby reducing the total construction period of 100 days.
When the underground vertical member is completed as described above S170, then the above-ground truss (secondary) may be started S180. For example, the above-ground framework (primary) may be constructed to 15 floors above the ground until the underground vertical members are completed, and after the underground vertical members are completed, the above-ground framework (secondary) S180 may be constructed without limitation from 16 floors to the top floor.
Fig. 2 to 3 are examples of process tables of every other constructed underground vertical member construction method according to the present invention.
Referring to fig. 2, the present embodiment is an office building with 6 floors below ground and 39 floors above ground, and is an SRC group, and the construction method is upside down. The start date was 2019, 1 month, 1 day.
Referring to the process table, the H-pile/CIP construction was performed at the earth retaining construction stage (job number 6 in the first row on the left side of the process table) for 80 days.
A plurality of piles are constructed on the underground layer by the 7-bead triangle in the engineering, and the construction period is 70 days.
After excavation of No. 8 engineering of the underground layer and No. 7 triangular engineering of No. 1 base plate bead are completed, 1 layer of steel beams are installed on the piles, and a deck and concrete are poured into the SRC building, wherein the construction period is 50 days.
The underground second layer excavation and underground first layer bottom plate construction (No. 9 project, lower drawing number) is that after the first layer bottom plate 8 is finished, the underground second layer is excavated downwards, then the underground first layer bottom plate 9 is constructed, and the construction period is 50 days.
When the next layer of panels 9 is completed, the core and pillars 22 of the next layer are constructed so that the construction can proceed to the ground. Therefore, the underground downward engineering and the bottom upward construction are performed simultaneously, which is generally called top-down construction.
When the core section 22 of the next floor is completed, continuous operation is possible from the floor second floor 25 to the eight floor 31. At this time, the loads from the eight storied buildings are all received by the bead triangles.
Since the 9-story floor 32 can be performed only when the cushion concrete 15 is constructed, the construction is stopped for about 4 months after the 8-story floor 31 is completed. According to the structure calculation, the bead triangle can only support the load of 8 layers 31 on the ground, so the 9 layers 32 can be started after the ground cushion is placed.
Alternatively, the construction of the floor level may begin from floor 2 after about 3 months, and the wait time between floors 8 and 9 may be minimized to continue the construction, or the construction to floor 8 may be slowly progressed.
After the underground first floor 9 is finished, the underground third floor is excavated, and then the underground second floor 10 is constructed, wherein the construction period is 50 days.
After the underground 2-layer bottom plate 10 is finished, 4 underground layers are excavated, an underground 3-layer bottom plate 11 is constructed, and the construction period is 50 days.
When the underground 3-layer panel 11 is completed, the underground 3-layer core 20 is first constructed according to the features of the present invention. In the conventional construction method, after the floor mat 15 is completed, the core 20 of the underground 3-layer is constructed from the underground 6-layer upward. Therefore, according to the present invention, the underground three-layer core unit 20 is constructed earlier than the conventional construction method, thereby shortening the construction period.
After the underground 1-level core unit 22 is constructed, the underground 2-level core unit 21 of the lower level is skipped, and the underground 3-level core unit 20 is constructed on every floor. The reason is that it is difficult to adopt counterattack construction by the core section 21 of the underground 2 layer immediately below after the construction of the underground 1 layer core section 22 because it is difficult to construct a connection section. Therefore, when the core part 20 of the underground 3-stories is constructed every other story after the core part 22 of the underground one-story is constructed, since the underground 2-stories as the upper story are empty, the underground 3-stories can be sequentially operated, and the construction is easy.
When every other layer of the subsurface one-layer core 22 and the subsurface three-layer core 20 is completed, the intermediate subsurface two-layer core 21 may be constructed by sandwiching.
And after the underground 3-layer bottom plate 11 is finished, continuing to construct downwards, and after 5 underground layers are excavated, constructing an underground 4-layer bottom plate 12, wherein the construction period is 50 days.
After the 4-layer underground bottom plate 12 is finished, the 5-layer underground bottom plate 13 is constructed after 6 underground layers are excavated, and the construction period is 50 days.
At this time, when the underground 5-layer floor 13 is completed, the underground 5-layer core section 18 is constructed according to the features of the present invention. In the conventional construction method, after the floor mat 15 is completed, the core 18 of the underground 5-layer is constructed in the order from the underground 6-layer upward. Therefore, according to the present invention, the core part 18 of the underground 5-story building has a feature of being constructed first as compared with the conventional construction method, and has an effect of shortening the overall construction period.
After the underground 3-layer core unit 20 is constructed, the underground 4-layer core unit 19 is skipped and the underground 5-layer core unit 18 is constructed every other layer. The reason is that after the underground 3-layer core section 20 is constructed, the underground 4-layer core section 19 of the next layer is constructed by counterattack, and it is difficult to construct the connection section. As in the case of the subsurface 3-layer core 20.
After the excavation of the underground 6 layers, the excavation 14 of the ground mat is performed, and then the foundation and the ground mat 15 are constructed.
When the floor mat 15 is completed, the floor may rise above the 9 th floor 32 as the floor mat 15 supports the load supported by the PRD.
On the other hand, the reason why the ground mat 15 is restricted from being constructed to the underground vertical members, and the ground layer can only be raised to 15 layers is that the underground layer is bent by PRD, and about 5 layers of PRD columns are exposed from 6 layers to 2 layers of the ground. However, according to the present invention, since odd-numbered floors have been constructed for every other floor, the PRD column is exposed only at the height of one floor, and since the buckling restriction is small, a new effect of constructing a higher floor according to the floor construction method is exhibited.
After completion of the floor mat 15, the remaining frameworks of the underground layer are the underground sixth core 17, the fourth underground core 19 and the underground second core 21. Since the subsurface 3-layer 20 and subsurface 5-layer core 18 have been completed in advance, the remaining three layers of cores may be constructed with sandwiching.
According to a feature of the present invention, since the core part of the odd-numbered layers is already constructed, the remaining three layers may be operated simultaneously or sequentially.
On the other hand, in the construction of the underground 2-layer core 21 and the underground 4-layer core 19, reinforcing bars are prefabricated and concrete is simultaneously poured after the floor mat 15 is placed to further improve productivity.
Therefore, the existing three-storey buildings need to be constructed in sequence, so that three storeys (about 75 days) are needed, and according to the characteristics of the invention, only one storey (25 days) is needed because the three storeys can be constructed at intervals, so that the effect of shortening two storeys is achieved.
According to the present invention, the core parts 20 of the underground 3-layer and the underground 5-layer are prefabricated alternately before the floor mat is constructed, and the construction period of two layers is shortened by alternately performing every other underground vertical member, and the core parts 17, 19, 21 of the remaining three layers are constructed simultaneously after the floor mat 15 is cast, thereby shortening the construction period of two layers and shortening the construction period of four layers in total. Since the core portion of the underground layer is a main line (Critical Path), the total air length is shortened.
Referring to fig. 3, a frame work from 5 to 39 floors above the ground and a finished work as a final work are shown. According to the calculation of the backstroke structure, the work can be started after 9 layers of bottom plates 32 are poured, and 16 layers of bottom plates 39 are a process table started after the underground vertical members are finished. From 16 th to 39 th, the frames are framed in a 6 day period, and the trimming work is generally carried out for one year. The decoration engineering comprises indoor decoration engineering, elevator engineering, temporary dismantling engineering such as an outer curtain wall and a tower crane, roofing engineering, landscaping engineering and the like.
Therefore, the entire construction period of a 39-story office building is 1, 106 days (about 36 months) if the underground vertical structure construction method according to the present invention is applied every other construction, as shown in operation 1 of fig. 2. Compared with the existing construction mode, the total construction period is shortened by about 3 months.
Fig. 4 is an enlarged process chart of the process of the underground vertical structure of fig. 2 according to the present invention as described above.
Referring to fig. 4, the vertical members of the odd-numbered layers (the underground 1-layer core 22, the underground 3-layer core 20, and the underground 5-layer core 18) among the underground vertical members are started after the completion of the floor of the corresponding layer, and the remaining vertical members of the even-numbered layers (the underground 6-layer core 17, the underground 4-layer core 19, and the underground 2-layer core 21) are constructed in parallel with the floor mat 15 at the same time after the casting.
The remaining even numbered vertical members 17, 19, 21 are characterized by being sandwiched and constructed simultaneously as every other odd numbered level has been installed.
Fig. 5 is a process table example of the latest starting point of every other constructed underground vertical member according to the present invention.
The latest construction time is a construction period in which construction can be performed at the latest without affecting subsequent processes. A later start or completion refers to a schedule that can be constructed latest without affecting subsequent flows.
Referring to fig. 5, the core unit 22 of the underground 1-layer is constructed for the above-ground works 25 to 25 after the completion of the floor of the underground 1-layer. It is then shown that the underground 3-layer core 20 can be constructed at the latest before the construction of the even-numbered underground vertical members 17, 19, 21.
Fig. 6 is a comparative process table of the earliest and latest starting points of every other constructed underground vertical member according to the present invention. Fig. 6 is a view for explaining which date or time in the work schedule the underground vertical structure is constructed due to the construction order determination.
Referring to fig. 6, operation numbers 16 to 21 denote fast processing (fig. 4), and operation numbers 23 to 28 denote slow processing (fig. 5). The core of the subsurface 3 layer may be compared by work number 20 at the early stage and work number 27 at the slow stage. That is, looking at the 20 th starting column, the underground 3 th layer can be started quickly in 1 st 2020, and can be started from 27 th in 5 th 15 th 2020. Of course, it may begin at any time between 1 month, day 1 and 5 months, day 15.
As described above, the concept and embodiment of the construction method of the underground vertical members according to every other construction of the present invention have been described with reference to fig. 1 to 6.
The construction concept and embodiment of the underground vertical member of the prior art method in the back-drilling method will be explained by using fig. 7 to 10.
Fig. 7 is a general flow chart for constructing an underground vertical member according to a conventional method.
Referring to fig. 7, after a retaining wall T10 is constructed outside a building, PRD or RCD piles T20 are constructed underground to form a rudder frame. Then, the site plates T30 to T100 are downwardly applied at the same time of excavating the underground trench. T100 after the underground 6 layers are excavated, and the foundation and the ground mat T110 are completed.
Then, the underground vertical members T130-170 are constructed in order from the underground 6 th floor T130 upward.
On the other hand, in the above ground level, after the core section T50 in the next ground level is completed, the above ground structure (primary) T60 is constructed. For example, up to floor 8 above ground until the mat is poured. After laying the mat, the upper frame is constructed (twice) from 9 to 15 floors above the ground (T180). After the underground vertical members (T130-170) are built, construction can be carried out from 16 layers above the ground without limitation.
In the existing back drilling method, after a floor mat is constructed from the ground to the lowest floor mat, the floor mat is turned around as a turning point, and underground vertical members are constructed upwards in sequence.
Therefore, the sequence of underground layers is long, and the underground construction period is long.
Fig. 8 to 9 are general process charts of the back-drilling method to which the conventional method is applied.
Referring to fig. 8, the conventional back drilling method is a reverse top-down construction method for an office building with 6 underground layers and 39 above ground layers, which is an SRC group. The start date was 2019, 1 month, 1 day. As in fig. 2. The reason why the existing construction method is applied to explain the progress is to check the difference between the construction order and the total construction period of the construction method according to the present invention.
Referring to the process table, the retaining wall construction stage (project No. 6 in the first column on the left side of the process table) is H-pile/CIP project, and the construction period is 80 days.
The bead triangle of the project 7 is constructed by a plurality of piles in an underground layer, and the construction period is 70 days.
In the No. 8 project, after the construction of the bead triangle No. 7 project is finished, underground 1-layer excavation and 1-layer bottom plate construction are carried out, in the SRC project, a first-floor steel beam is installed on a pile, a deck and concrete are poured, and the construction period is 50 days.
After the excavation of the underground 2 layers and the construction of the underground 1 layer bottom plate (project 9, hereinafter, referred to as a number) are completed, after the excavation of the underground 2 layers, the underground 1 layer is constructed, and the construction period is 50 days.
When the underground 1-ply floor 9 is completed, the underground one-ply core and the pillars 22 are constructed so that the construction can be performed to the above-ground floor. Thus, the subsurface and sub-surface upward construction is performed contemporaneously, which is commonly referred to as top-down construction.
When the subsurface 1-layer core 22 is completed, continuous operation is possible from the ground 2-layer panel 25 to the eight-layer panel 31. At this time, the loads to the eighth floor are all supported by the bead triangles.
Since the 9-story floor 32 can be performed only when the cushion concrete 15 is constructed, the construction is stopped for about 4 months after the 8-story floor 31 is completed. Since the bead gores can only support the load to floor 8 31, floor 9 can begin with the floor pad.
After the underground first floor 9 is finished, the underground third floor is excavated, and then the underground second floor 10 is constructed, wherein the construction period is 50 days.
After the underground 2-layer bottom plate 10 is finished, 4 underground layers are excavated, an underground 3-layer bottom plate 11 is constructed, and the construction period is 50 days.
When the underground 3-layer plate 11 is finished, the construction is continued downwards, and after the underground 5 layers are excavated, the construction of the underground 4-layer plate 12 is carried out for 50 days.
After the 4-layer underground bottom plate 12 is finished, the 5-layer underground bottom plate 13 is constructed after 6 underground layers are excavated, and the construction period is 50 days.
After the excavation of the underground 6 layers, the excavation 14 of the ground mat is performed, and then the foundation and the ground mat 15 are constructed. When the floor mat 15 is completed, the floor may rise above the 9 th floor 32 as the floor mat 15 supports the load supported by the PRD.
When the floor mat 15 is completed, the underground vertical members 17 to 21 are directly connected from the core 17 of the underground 6 floor to the core 21 of the underground 2 floor, which takes 25 to 30 days per floor. During this time, the sub-floor may be constructed from 9 courses 32 to 15 courses 38.
Referring to fig. 9, floors 10 to 39 and finishing work are shown. The 16-level floor 39 is a process table that is started after the completion of the underground vertical structures. From 16 stories to the top of the building, the underground stories are not limited at all, and are framed in a 6-day cycle, typically for one year finishing work.
Therefore, the total construction period of a 39-story office building is 1,194 days (about 39 months) as shown in operation 1 of fig. 8 if the underground vertical member construction method according to the present invention is applied every other construction.
The total air of 39 months is 3 months longer than the total air of 36 months according to the invention. The reason is that it takes much time to construct the underground vertical wall from the underground 6 to the underground 2 in sequence.
Fig. 10 is an enlarged process chart of the subterranean vertical member process of the prior art method of fig. 8. After the floor mat 15 was constructed with the underground vertical members, it was shown that the construction was performed in order from task number 17 to task number 21, and the construction period was 130 days, which took about 4.3 months.
Fig. 11 is a comparative process table comparing underground vertical structures of the prior art method and every other underground vertical structure constructed according to the present invention.
Referring to fig. 11, operation numbers 1 to 19 are process tables of the prior art method, operation numbers 20 to 38 are process tables of the present invention, and operation number 39 shows the difference between the prior art method and the process method of the present invention.
First, in the prior art method, the core of the underground 5-layer is constructed in sequence after the floor mat 10 is constructed, showing that 130 days are required, from operations 12 to 16.
On the other hand, according to the invention, from operations 31 to 35, only 30 days are required after the mat 29 has been constructed, indicating the lack of 100 days for the invention (39).
The reason is that the core 34 of the underground 3-layer and the core 32 of the underground 5-layer are constructed in advance, and the remaining 3- layer cores 31, 33, 35 are inserted simultaneously or at the same time after the floor mat 29 is constructed. After every other odd core part is constructed, the remaining even floors are constructed once, so that the existing method needs 5 times of construction finally, and the effect of shortening 100 days of 4 floors by only one construction is shown in the invention.
Fig. 12 to 13 are a time table difference comparison table for each floor comparing the overall process table (fig. 8, 9) of the prior art method with the overall process table (fig. 2, 3) of every other constructed underground vertical member according to the present invention.
Referring to fig. 12, the total air difference (job number 1) for both methods was 88 days, which was reduced from 36 months to about 39 months, about 3 months, and it can be seen that the total air was reduced by about 8%.
Underground excavation, reverse slab and ground mat construction 6-15) are the same.
The difference occurs in the underground vertical members because every other underground vertical member (core) is constructed downward according to the present invention while the remaining core is constructed.
The last column I is the value of the completion date for each floor (column E) of the prior method subtracted from the completion date for each floor (column H) according to the present invention.
The 88-day difference is fixed starting from 16 layers (39) above ground and continues until the construction is completed.
Referring to fig. 13, the progress difference (I completion date difference column) of 88 days from the above-ground 16 th floor (39)) is shown to continue until completion.
Fig. 14 is a graph comparing the S-curve form of the overall schedule of the prior method (fig. 8 and 9) with the overall schedule of every other constructed underground vertical structure according to the present invention (fig. 2 and 3) and fig. 12-13.
Referring to fig. 14, blue lines represent prior art methods and red lines represent methods of the present invention.
The work is started 1 month and 1 day in 19 years, and 6 months and 8 days (the lowest points in the figure) in 2020, 6 layers of ground mats are poured.
Then, the red line according to the present invention indicates that two layers are constructed every other layer, three layers are simultaneously constructed within one month, the underground vertical structure is completed, and then 16 layers are accessed.
On the other hand, the blue line is an existing construction method, indicating that it takes about 4.3 months for the underground vertical members of each floor to pass to 16 floors after the floor mat is constructed. From 16 layers and above, the two construction methods are the same.
As described above, the differences between the existing method and the method of the present invention are compared by the process table, the table, and the graph.
The following is a description of a case where a partial operation is performed differently in an embodiment of the present invention.
Under the condition of final excavation of the underground 5 layers, an underground core part is firstly constructed downwards on the underground 1 layer and the underground 3 layer, after the ground mat is finished, the underground 5 layer is constructed, and then the underground 4 layer and the underground 2 layer are constructed simultaneously. Thus, the remaining core is mounted twice after the mat.
In the case of final excavation of the underground 4 layers, the underground core part is first constructed downwards on the underground 1 layer and the underground 3 layers, and after the ground mat is completed, the underground 4 layers and the underground 2 layers can be constructed simultaneously. The concept is the same as that of the underground 6-story building.
Because the underground layer is not high, the two lowest layers (such as 5 underground layers and 6 underground layers) are dug at the same time, then ground mats are laid, and then an underground 5-layer bottom plate is constructed. In this case, the core part of the underground 6-layer and the floor of the underground 5-layer are simultaneously constructed, and then the core part of the underground 5-layer is constructed. Thus, the remaining core is mounted twice after the mat.
As described above, in the case of excavating two floors of odd-numbered floors or the lowest floor at the same time, some construction items involve sequentially constructing the remaining core portions twice after the completion of the floor mat. Therefore, according to an embodiment of the present invention, after every other core unit is completed, the remaining core units are mostly completed once, and in the local construction project, the remaining portion may be constructed twice.
The process table of the above embodiment is prepared by a program specializing in process table preparation, and date calculation is an accurate example. The conder diagram is a red bar graph in the milestone, and the key pass, which is the main line, represents the main task of determining total air. The blue bar graph represents work with float. Therefore, in order to shorten the air, the red line as the main line must be shortened. Connecting lines containing arrows connect the bar graphs of the milestone meter (relationships represent context between tasks).
In summary, according to the features of the present invention, it can be seen that there may be some derived sequential core structures depending on the features of the site, based on the idea of completing the core alternately every other time in order to shorten the construction period of the underground core which determines the overall construction period. However, unlike the existing construction method sequential core construction method, according to the idea of shortening the entire construction period by every other core construction method according to the present invention, the engineer engaged in construction work will clearly understand that the partially modified core construction method is included in the spirit of the present invention.
Sequence of vertical member construction method in case of the back-drilled underground 8 layers alternately constructed according to the embodiment of the present invention.
The construction sequence is as follows.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second layers of the ground
Pouring reinforced concrete (pouring plate) in the underground layer of the steel bridge deck
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Excavating 6 underground layers
Laying of underground 5-layer bottom plate
Underground 7-building excavation
Pouring 6 underground layers of bottom plates and 5 underground layers of core wall columns
Digging 8 underground layers and ground mats
7-layer underground pouring slab and 7-layer underground pouring core wall column
Paving 8 layers of underground floor mats
Core wall column installation of underground 8, 6, 4 and 4 of the rest (4 simultaneous construction)
Or 2 layers of core wall column construction (2 layers and 2 times of construction) which is remained after 2 layers of construction by adding 8 layers and one layer of underground
Or, 2 and 3 layers of core wall columns are constructed on each layer by adding 8 layers and one layer of underground, 2 layers are constructed after 1 time of 2 layers, and 3 times of 1 layer and 2 layers are constructed totally (2 layers are constructed for 1 time and 3 times of 1 layer and 2 times)
Or, after the core wall column of 8 underground layers is constructed, the rest 3 layers are constructed in a layering way (4 layers are constructed for 4 times in total)
And 4, pouring the rest layers of the ground mat in layers 1, 2, 3 and 4.
The following is a sequence of a vertical member construction method in the case of a reverse drilling underground 7 layers alternately constructed according to an embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Excavating 6 underground layers
Laying of underground 5-layer bottom plate
Underground 7-building excavating and excavating ground mat
Pouring 6 underground layers of bottom plates and 5 underground layers of core wall columns
Paving 7 layers of ground in the ground
In the underground 7, 6, 4 and 2 of the rest layers
After 7 layers and 1 layer of the ground (1 layer is selected from 4 layers or 2 layers of the ground) are added, 2 layers of 2 times of core wall column construction (2 layers of 2 times of construction) are remained after 2 layers of one-time construction
Or 2-layer construction of 7 layers and the rest 3 layers, and construction of the rest 1 layer (3 times of construction in total)
Or one layer is constructed once, and the construction is carried out for four times.
This is the sequence of the vertical member construction method in the case of the alternately constructed back-drilled underground 6 layers according to one embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Excavating 6 underground layers and ground mats
Laying underground 5-layer bottom plate
Pouring 6 underground layers of bottom plates and 5 underground layers of core wall columns
In the underground 6, 4 and 2 of the rest layers
The other 3 layers are constructed at the same time (1 time in total)
Or, after 6 underground layers are constructed, 4 underground layers and 2 underground layers are constructed at the same time (2 times in total)
Or constructing 6 underground layers and 4 underground layers at the same time and then constructing 2 underground layers (2 times in total)
One layer is constructed at a time, and the construction is carried out for 3 times (3 times of separated construction).
This is the sequence of the vertical member construction method in the case of the sub-surface 5 layers of the back-drilling method of alternating construction according to one embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers
Laying on 3 layers of underground
Excavating 5 underground layers and ground mats
Pouring of 4 underground layers of bottom plates and 3 underground layers of core wall columns
Laying underground 5-layer bottom plate
In the underground 5, 4, and 2 of the rest layers
Construction of 4 underground layers and 2 underground layers (2 times in total) at the same time after construction of 5 underground layers
Or constructing 4 underground layers after the 5 underground layers and the 2 underground layers are constructed at the same time (2 times in total)
The other 3 layers are constructed one layer at a time (3 times in total).
This is the sequence of the vertical member construction method in the case of the underground 4-layer of the back-drilling method of alternating construction according to one embodiment of the present invention.
Mud guard
Underground column (PRD, RDC, ACT column)
Excavating the first and second underground layers
Steel bridge floor underground 1 layer reinforced concrete pouring (slab pouring)
Excavating underground 3 layers
The bottom plate is poured to two layers of underground, the core wall post of one layer of underground
Excavating 4 underground layers and ground mats
Pouring 3 underground layers of bottom plates and 3 underground layers of core wall columns
Laying 4 underground layers of bottom plates
In the underground 5 or 2 of the rest layers
Construction of 4 underground layers and 2 underground layers at the same time (1 time in total)
The other 2 layers are constructed one layer at a time (3 times in total).
Industrial applicability of the invention
At present, most of the top-down construction is carried out in city center construction. For other various construction methods according to the present invention, a structural design room is first designed, and then a contractor manufactures steel frames and forms, and then construction is performed. Therefore, the present invention can be directly applied to the industry.

Claims (12)

1. A method for shortening a construction period by every other underground vertical member construction method, as construction of an underground vertical member in a building of an above-ground structure constructed upward in parallel with downward construction of the underground structure, comprising:
a first step of downward construction of excavation and a floor of an underground layer,
a second step of pre-constructing every other underground vertical member;
and a third step of constructing the remaining underground vertical members every other one period or two times after the second construction.
2. The method for shortening construction period by every other underground vertical structure construction method according to claim 1, wherein if the underground layer is 6 underground layers, the slab is constructed on the underground construction site, the core part is constructed on 1 underground layer, 3 underground layers and 5 underground layers at every other underground layer at the same time, the underground plywood is constructed on the underground layer at the same time, and then the core part is constructed on 6 underground layers, 4 underground layers and 2 underground layers.
3. The method for shortening construction period by every other underground vertical structure construction method according to claim 1, wherein if the underground layer is an underground 5-layer, the slab is constructed on the underground 1-layer and the underground 3-layer at every other layer at the same time while the slab is downwardly constructed, and then the underground 4-layer is constructed after the underground 5-layer core is constructed, and the underground 2-layer core is constructed at the same time as during the underground 5-layer and the underground 4-layer constructions.
4. The method for shortening a construction period by the construction method of every other underground vertical member as claimed in claim 1, wherein if the underground layer is 4 underground layers, the slab is constructed on the underground 1, 3 underground layers at every other layer at the same time, and then the core is constructed on the underground 4-layer core and the underground 2-layer at the same time, at the downward construction site.
5. The method for shortening construction period by every other underground vertical member construction method according to claim 1,
under the condition that the two layers of the lowest layer and the upper layer of the underground layer are excavated at the same time, the underground plate is constructed downwards, the core part is constructed in advance every other layer at the same time, a ground mat or a foundation is constructed, and the core part is constructed and the residual core part is constructed at the same time after the construction of the core part at the lowest layer and the bottom plate next to the upper layer is finished.
6. The method for shortening a construction period by the construction method of every other underground vertical member according to claims 1 to 5,
according to the placement operation of the floor mat, the core portion to be built in advance and the remaining core portion built simultaneously as the tail are constructed front and rear.
7. The method for shortening construction period by every other underground vertical member construction method according to claims 1 to 5, wherein the construction schedule of every other previously constructed respective core part is constructed within a range of an earliest construction Date (Early Start Date) from when the panel of the corresponding floor is completed and a latest completion Date (Late) completed before the Date of the post construction of the remaining core parts.
8. The method for shortening construction period by the construction method of every other underground vertical member as claimed in claims 1 to 5, wherein the underground vertical member comprises a column connected to a core or a floor.
9. The method for shortening construction period by every other underground vertical member construction method according to claim 1, wherein the every other underground vertical member is constructed with the underground plate being downwardly constructed, the core part or the pillar of the underground odd-numbered floor (or even-numbered) is constructed in advance at the same time, the vertical member of the core part or the pillar of the even-numbered (or odd-numbered) floor of the remaining floor is constructed at the same time or constructed twice according to the on-site conditions after the floor mat or the foundation is constructed.
10. The method for shortening construction period by every other underground vertical member construction method according to claim 1, wherein the subsequent construction of the remaining core part is a method of further including concrete placement as a subsequent process after installing the reinforcing bars of the remaining underground core part as much as possible.
11. A method for reducing construction time by every other underground vertical member construction method, comprising:
(a) constructing a temporary retaining wall underground by a conventional method;
(b) when constructing underground structure and ground structure, the step of constructing the bottom core part parallel to the underground structure and the up construction and installing by inserting the pillar from the ground vertically;
(c) excavating an overground layer and constructing a floor, and excavating an underground layer and constructing the floor;
(d) excavating the rest underground layers downwards in sequence and constructing the bottom, and simultaneously constructing an underground core part of one or more underground layers to support a bottom core part which is preferentially constructed upwards;
(e) a step of constructing an underground frame in a downward direction parallel to an upward direction of the above-ground core unit by preferentially constructing the above-ground core unit in an upward direction on the above-ground core unit constructed first;
(f) in the step of installing the underground frame downward, a step of constructing core parts on the underground layer first and then installing core parts every other;
(g) a step of forming a foundation part by completing the underground frame to the foundation part, and simultaneously or sequentially installing core parts of every other remaining layer constructed downward from the bottommost layer to the upward direction to the core part of the underground layer constructed first;
(h) the construction is completed through the residual frame work of the bottom layer, the final work and the ending work,
the underground core unit is constructed first or simultaneously in advance or within a predetermined range, so that the underground core unit is excluded from the main line critical path, and the overall construction period is shortened.
12. The method for shortening construction period by every other underground vertical structure constructing method according to claim 11, wherein the step of installing the core units in turn every other includes constructing core units of odd-numbered floors, and then core units of the remaining floors include core units of even-numbered floors, the core units of odd-numbered floors and the core units of even-numbered floors being converted according to a structure of the floor mat, and constructing core units of the lowest floor and the core units of the upper floor in turn according to characteristics of the floor.
CN201980097932.3A 2019-06-27 2019-06-27 Reverse drilling underground vertical member construction method for alternate construction Pending CN114008270A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/KR2019/007842 WO2020262735A1 (en) 2019-06-27 2019-06-27 Method for alternately constructing underground vertical members using top-down construction method

Publications (1)

Publication Number Publication Date
CN114008270A true CN114008270A (en) 2022-02-01

Family

ID=74060414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201980097932.3A Pending CN114008270A (en) 2019-06-27 2019-06-27 Reverse drilling underground vertical member construction method for alternate construction

Country Status (5)

Country Link
US (1) US20220243418A1 (en)
JP (1) JP2022554045A (en)
KR (1) KR20220024070A (en)
CN (1) CN114008270A (en)
WO (1) WO2020262735A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982484B (en) * 2021-03-04 2022-07-12 中国建筑第八工程局有限公司 Semi-synchronous sequential construction method for underground and overground structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05255943A (en) * 1991-09-13 1993-10-05 Takenaka Komuten Co Ltd Construction method for underground skeleton by slide down system
CN101736756A (en) * 2009-12-04 2010-06-16 上海市第二建筑有限公司 Method for constructing soft soil foundation reverse interlayer
KR101267565B1 (en) * 2012-02-13 2013-05-24 주식회사 한빛구조엔지니어링 Construction method of under-ground core part structure in top-down construction procedure
KR20130119226A (en) * 2012-04-23 2013-10-31 대림산업 주식회사 Construction method of core part in building
CN104234082A (en) * 2014-08-29 2014-12-24 中国电建集团华东勘测设计研究院有限公司 Jump-layer reversed construction method for deep foundation pit

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2757026B2 (en) * 1989-07-14 1998-05-25 株式会社竹中工務店 Reverse construction method of basement structure
KR20090090742A (en) * 2008-02-22 2009-08-26 삼성물산 주식회사 Bottom-up Underground Structure Construction Using Permanent Struts
JP6937205B2 (en) * 2017-09-21 2021-09-22 大成建設株式会社 How to build an underground structure
KR102320104B1 (en) * 2017-12-20 2021-11-02 양경옥 Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05255943A (en) * 1991-09-13 1993-10-05 Takenaka Komuten Co Ltd Construction method for underground skeleton by slide down system
CN101736756A (en) * 2009-12-04 2010-06-16 上海市第二建筑有限公司 Method for constructing soft soil foundation reverse interlayer
KR101267565B1 (en) * 2012-02-13 2013-05-24 주식회사 한빛구조엔지니어링 Construction method of under-ground core part structure in top-down construction procedure
KR20130119226A (en) * 2012-04-23 2013-10-31 대림산업 주식회사 Construction method of core part in building
CN104234082A (en) * 2014-08-29 2014-12-24 中国电建集团华东勘测设计研究院有限公司 Jump-layer reversed construction method for deep foundation pit

Also Published As

Publication number Publication date
US20220243418A1 (en) 2022-08-04
WO2020262735A1 (en) 2020-12-30
JP2022554045A (en) 2022-12-28
KR20220024070A (en) 2022-03-03

Similar Documents

Publication Publication Date Title
KR102588684B1 (en) Method for constructing basement vertical member of top-down method constructed alternately
AU2001263323A1 (en) Construction of high-rise building with large modular units
CN106703197B (en) A kind of large span multilayer anti-seismic frame structure system and its construction method
US12084854B2 (en) Top-down construction method for multi-storey basement with full steel structure
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
CN103790295B (en) Reinforced concrete stairs structure and construction method thereof
US20060156647A1 (en) Anti-seismic reinforcement and expansion mehtod for building and anti-seismically reinforced and expanded building
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
KR100694493B1 (en) Reverse casting method to use the temporary structure supported by brackets as a workbench
JP2009013641A (en) Seismic reinforcement structure
KR20220024070A (en) The underground vertical member construction method of the reverse perforation method, which is constructed alternately every other time
CN109736589B (en) A kind of construction method of lattice column force transmission member
KR20210000234A (en) Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project
KR102910761B1 (en) Structure construction method for apartment remodeling using climbing bracket
KR101026112B1 (en) Construction method of underground structures using mega structure
KR102864508B1 (en) A method of constructing underground and above-ground structures in parallel through ground-level core preconstruction using temporary columns with reinforcement plates embedded in the core wall
KR20250164066A (en) Construction method and apparatus of the core wall structure on the ground floor using steel column and girder inside the core wall in 1st basement in top down construction
KR100442548B1 (en) The simultaneous construction method of building having mixed structure of reinforced concrete construction and steel framed reinforced concrete structure
EP2669438A1 (en) Method for repairing of buildings
JPH05255943A (en) Construction method for underground skeleton by slide down system
KR20240068954A (en) Continuous construction method of the superstructure by adding spare piles to the lowest basement floor in the top-down construction project
KR20250061106A (en) Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures
JP6938197B2 (en) Construction method
CN118187508A (en) A method for renovating the storey height of an existing brick-concrete building
KR20050122763A (en) A deck supportframe and a construction methed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220201