KR0150304B1 - A method of simultaneously constructing frameworks for floors and basements of a building - Google Patents
A method of simultaneously constructing frameworks for floors and basements of a buildingInfo
- Publication number
- KR0150304B1 KR0150304B1 KR1019950003110A KR19950003110A KR0150304B1 KR 0150304 B1 KR0150304 B1 KR 0150304B1 KR 1019950003110 A KR1019950003110 A KR 1019950003110A KR 19950003110 A KR19950003110 A KR 19950003110A KR 0150304 B1 KR0150304 B1 KR 0150304B1
- Authority
- KR
- South Korea
- Prior art keywords
- construction
- floor
- frame
- ground
- basement
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본 발명은 건축 구조물의 골조 시공 방법에 관한 것으로, 소정이 지하층과 지상층으로 된 건축구조물의 골조를 철골철근콘크리트 구조로 시공함에 있어서, 지하토공사를 완료한 후 철골 및 데크 플레이트(deck plate)공사를 적어도 지상 2층 정도 이상까지 진행하고, 또한 골조 공사를 적어도 지하층 1개층 정도를 완료한 시점에서, 진행중인 철골 및 데크 플레이트(deck plate)공사 또는 지하층의 골조 공사를 계속 동일한 방식으로 상부층으로 진행해 나가는 한편, 지상층의 골조공사도 지상 1층 기둥부터 순차적으로 동시에 병행 추진함으로써, 골조공사 공기를 단축시켜 줄 뿐만 아니라 자원 가동 효율을 증대시켜 주는 것이다.The present invention relates to a method for constructing a structure of a building structure, in which the construction of a frame of a building structure consisting of a basement layer and a ground layer as a steel reinforcement concrete structure, after completion of the earthworks, a steel frame and deck plate (deck plate) construction At least two floors above ground and at least one basement level are completed, the ongoing construction of steel frame and deck plate or frame construction of the basement floor continues to the upper floor in the same way. In addition, the construction of the ground floor frame is also carried out simultaneously from the ground floor pillars in order to shorten the frame construction air and increase the efficiency of resource operation.
Description
제1도 (a)는 본 발명에 따른 공법의 개략적인 공정도.Figure 1 (a) is a schematic process diagram of the process according to the invention.
(b)는 본 발명에 따른 공법의 공정 단계별 시공상태도.(b) is a construction state step by step of the process according to the invention.
제2도 (a)는 공중가설 작업대의 설치 상태를 도시한 평면도.2 (a) is a plan view showing the installation state of the aerial work platform.
(b)는 공중가설 작업대의 단면도,(b) is a cross-section of a public work bench,
(c)는 공중가설 작업대가 설치된 공사 현장의 현장 사진,(c) a photograph of the site of the construction site where the public work platform is installed,
제3도 (a)는 보조 철근의 설치 상태를 나타낸 사진,3 (a) is a photograph showing the installation state of the auxiliary rebar,
(b)는 1층 기둥 하부 거푸집(8) 설치 상태를 나타낸 사진,(b) is a photograph showing the installation of the formwork (8) below the first-floor column,
(c)는 철근 및 거푸집 설치가 완료된 상태의 1층 기둥 하부의 종단면도,(c) is a longitudinal cross-sectional view of the lower part of the first-floor column with the rebar and formwork installed,
(d)는 철근 및 거푸집 설치가 완료된 상태의 1층 기둥 하부의 실제 시공 상태의 사진(d) is a picture of the actual construction state of the lower part of the first-floor column with the rebar and formwork installed.
제4도 (a)는 본 발명에 따른 공법의 골조 공사 진행 단계도,Figure 4 (a) is a frame construction progress step of the construction method according to the invention,
(b)는 본 발명의 시공 방법에 따라 시공 중인 건물의 현장 전경을 나타낸 사진,(b) is a photograph showing the site view of the building under construction in accordance with the construction method of the present invention,
제5도 (a)는 종래의 순타공법의 개략적인 공정도,5 (a) is a schematic process diagram of a conventional netting method,
(b)는 종래의 순타공법의 공정 단계별 시공 상태도,(b) is a construction state diagram for each step of the conventional net perforation method,
제6도 (a)는 종래의 역타공법의 개략적인 공정도,6 (a) is a schematic process diagram of a conventional reverse drilling method,
(b)는 종래의 역타공법의 공정단계별 시공상태도이다.(b) is a construction state diagram for each process step of the conventional reverse drilling method.
* 도면의 주요 부분에 대한 부호의 설명* Explanation of symbols for the main parts of the drawings
1 : 공중 가설 작업대 2 : 철골 기둥1: aerial temporary workbench 2: steel column
3 : 거어더(girder) 4 : 빔 브라켓3: girder 4: beam bracket
5, 5a : 단관 파이브 6 : 패널5, 5a: single tube five 6: panel
7 : 보조철근 8 : 1층기둥 하부거푸집7: auxiliary reinforcing bar 8: 1st floor pillar
9 : 주근 10 : 후프9: freckle 10: hoop
11 : 버팀대 12 : 타이 와이어11: brace 12: tie wire
A : 1층 기둥 하부 끝단위치 B : 1층 바닥슬라브 윗면 위치A: End position of 1st floor pillar B: Top position of 1st floor floor slab
본 발명은 건축 구조물의 골조 시공방법에 관한 것으로, 특히 고층 건축물의 시공시 지하층과 지상층 또는 하부층과 상부층의 2지점에서 골조공사를 동시에 병행 추진함으로써 골조공사 공기를 단축시켜 줄 뿐만 아니라 자원가동 효율을 증대시켜 주는 건축 구조물의 골조 시공방법에 관한 것이다.The present invention relates to a frame construction method of a building structure, and in particular, in the construction of high-rise buildings by simultaneously pushing the frame construction at the two points of the basement floor and ground floor or lower floor and the upper floor at the same time to shorten the frame construction air as well as improve the efficiency of resource operation It relates to a frame construction method of building structures to increase.
일반적으로 건축구조물은 기초공사, 골조공사, 마감공사를 거쳐 완성되는데. 이중 골조공사가 건축물의 시공비용 및 공기에 있어서 가장 비중있는 공사라 할 것인 바, 즉 골조공사의 경제성 및 효율성 여하에 따라 시공비의 고저 또는 공기의 장단이 결정적으로 좌우되는 것이다. 특히 건축공사의 공기에 있어서, 골조공사는 크리티칼 패쓰(critical path)에 해당되는 아주 중요한 요소로서, 건축물이 고층화될수록 그 중요성은 더욱 커지게 된다.In general, building structures are completed through foundation work, framing work, and finishing work. The double frame construction is the most important work in the construction cost and air of the building, that is, the height of the construction cost or the long and short of the construction cost is critically determined by the economic efficiency and efficiency of the frame construction. In particular, in the air of construction, framing is a very important element that corresponds to a critical path, and the more important the building becomes, the more important it becomes.
이와 같은 골조공사는 철골 또는 철근 조립과 콘크리트 타설이 주공정으로서, 골조자체가 자중을 스스로 지지해야 하기 때문에 건축물의 하층에서부터 상층으로 올라가면서 시공하는 것이 원칙이고 순리이다. 즉 골조공사를 추진하는 방법은, 기초, 지하층, 지상층, 지붕층의 순서로 진행하는 것이 일반적인데. 이러한 공법은 통상 순타공법(順打工法)으로 칭하는 것으로 지금까지 주로 사용되어 왔던 공법이다. 이러한 순타공법의 개략적인 공정도를 제5도에 (a)에 나타내었는데, 도시된 바와 같이, 지하토공사를 완료하고, 철골공사를 어느 정도 진행한 후 이와 동시에(때로는 철골공사 완료후)지하구체공사를 진행하여 완료하며, 계속해서 지상구체공사를 진행하는 공법이다. 이 공법을 더욱 이해하기 쉽도록 하기 위해, 공정단계별 시공상태를 개략적으로 도시한 것이 제5도의 (b)이다.In this framework, steel frame or reinforcing steel assembly and concrete casting are the main processes. Since the frame itself must support its own weight, it is a principle and aptitude to construct it from the lower floor to the upper floor of the building. In other words, it is common to proceed with the frame construction in the order of foundation, basement, ground and roof. Such a method is usually called a net working method and has been mainly used. A schematic process diagram of the netting method is shown in (a) in FIG. 5, as shown in FIG. 5, after the underground work is completed, the steelwork is carried out to some extent, and at the same time (sometimes after the completion of the steel work) It is a construction method to complete and proceed with the ground concrete construction. In order to make this process easier to understand, FIG. 5 (b) schematically shows the construction state for each process step.
한편, 통상의 골조공사에 있어서 지하층 공사는 층당 공기가 통상 1개월 정도로 길뿐만 아니라 지하 스트러트(strut)의 간섭 및 양생문제로 작업진행이 단속적이고, 지상층 공사는 층당 공사 물량이 소량으로서 층당 공기가 통상 1주일 정도로 짧은 반면 장비나 인력 등의 자원가동효율이 저조하며, 지붕층 공사는 수순상 최후에 진행해야 하는 공사이다.On the other hand, in the general frame construction, the underground floor construction is not only long, but the air per floor is usually about 1 month, and the work progress is intermittent due to the interference and curing problems of the underground struts. Although it is usually short for one week, the efficiency of resource operation such as equipment and manpower is low, and the roof layer construction is the last to be completed in the sequence.
따라서, 지하층의 최하층으로부터 상부층으로 순서대로 층층이 시공해 나가는 상기와 같은 종래의 순타공법에서는, 전체적으로 공사기간의 장기화가 불가피하게 되고, 또한 지하층과 지상층의 공사물량 차이 및 지하층의 작업 단속성으로 인해, 자원의 가동 효율이 지극히 저조하게 되는 문제가 본질적으로 내재되어 있다.Therefore, in the above-mentioned conventional netting method, in which the layers are constructed in order from the lowermost floor of the basement to the upper floor, prolongation of the construction period becomes inevitable as a whole, and also due to the difference in the construction volume of the basement and the ground floor and the work interruption of the basement floor, There is an inherent problem of extremely low resource efficiency.
이와 같은 순타공법의 문제점을 어느 정도 해결해 주는 공법으로 역타공법(top-down공법)이 있는데, 이를 상기 순타공법과 대비되도록 동일한 방식으로 제6도 (a) 및 (b)에 도시하였다. 도면상으로도 쉽게 알 수 있는 바와 같이, 이 역타공법은 지상 1층 바닥 골조 공사를 한 후, 지하토공사, 지하구체공사 및 지상구체공사를 거의 동시에 병행하여 시공하는 공법이다. 이와 같은 역타공법은 공기를 단축시키고 자원가동효율을 어느 정도 높여 주는 장점이 있는 반면, 오히려 파생되는 단점이 많아 잘 사용이 되지 않는 바, 즉 지하 흙막이 공사가 반드시 슬러리 월(slully wall)공법이어야 하는 제약이 있고, 지하공사에 있어서 작업환경이 불량하고 수직도 관리가 곤란하여 상당한 애로가 있으며, 전체적으로 공사원가의 상당한 상승이 불가피한 문제점이 있는 것이다.As a method for solving the problem of the net punching method to some extent, there is a back-down method (top-down method), which is shown in Figure 6 (a) and (b) in the same manner as compared to the net punching method. As can be easily seen from the drawing, this reverse perforation method is a method of constructing a ground frame construction on the ground floor, and then simultaneously performing underground earthworks, underground concrete works, and ground concrete works in parallel. This reverse drilling method has the advantage of shortening the air and increasing the efficiency of resource operation to some extent, but it is rather difficult to use because there are many disadvantages derived from it. That is, the underground wall construction must be a slurry wall method. There are limitations, and in the underground construction, the working environment is poor and the verticality management is difficult, and there is a considerable difficulty, and the overall increase in construction costs is inevitable.
이에 본 발명은 상기한 바와 같은 종래의 골조 시공방법의 문제점을 해결하기 위한 것으로, 상기 역타공법과 같이 별도의 공사비용을 추가로 발생시키거나 공법의 적용에 일정한 제한이 있는 문제점이 없으면서도, 자원가동효율을 높여 주고 공기는 현저히 단축시켜 주며, 따라서 전체적으로는 공사비용을 상당히 절감시켜 주는 건축 구조물의 골조 시공방법을 제공하는데 그 목적이 있다.Accordingly, the present invention is to solve the problems of the conventional frame construction method as described above, without additional problems such as generating a separate construction cost or a certain limitation in the application of the construction method, such as the reverse drilling method, resources Its purpose is to provide a method of framing construction of building structures that increases operational efficiency and significantly shortens air, thus significantly reducing construction costs as a whole.
상기와 같은 목적을 달성하기 위한 본 발명에 따른 건축 구조물의 골조 시공방법은 , 소정의 지하층과 지상층으로 된 건축구조물의 골조를 철골철근 콘크리트 구조로 시공함에 있어서, 지하토공사를 완료한 후 철골 및 데크 플레이트(deck plate)공사를 적어도 지상 2층 정도 이상까지 진행하고, 또한 골조공사를 적어도 지하층 1개층 정도를 완료한 시점에서, 진행중인 철골 및 데크 플레이트(deck plate)공사 또는 지하층의 골조공사를 계속 동일한 방식으로 상부층으로 진행해 나가는 한편, 건축물의 전체 층 중 중간부층에 해당하는 지상 1층 기둥부터 순차적으로 지상층의 골조공사도 동시에 병행 추진해 나가되, 지상 1층의 골조공사는, 지상 1층 철골부의 거어더(girder)를 따라 빔브라켓 및 단관 파이프 등을 이용하여 공중 가설 작업대를 설치하고, 1층 기둥의 주근 및 후프 철근이 흘러내리는 것을 방지하기 위해 1층 기둥 철골에 보조 철근을 용접으로 고정하여 이 보조철근에 철근이 지지되도록 배근해 주며, 타설할 콘크리트를 하부에서 지지해 주기 위해 1층 기둥하단부에 하면 거푸집을 콘크리트가 새지 않도록 긴밀히 설치한 후, 통상의 방법에 의해 철근조립, 거푸집 설치 및 콘크리트 타설 등을 함으로써 완료하고, 지상 2층 이후의 골조공사는 통상의 방식으로 진행하는 것을 특징으로 한다.Frame construction method of the building structure according to the present invention for achieving the above object, in the construction of the frame of the building structure consisting of a predetermined basement layer and the ground layer in a steel reinforced concrete structure, after completion of the underground earthwork steel and deck When the construction of the deck plate has been carried out to at least 2 stories above the ground and the framework has been completed at least 1 basement level, the construction of the steel frame and deck plate or the basement of the basement under construction is the same. While proceeding to the upper floor in the manner, while simultaneously proceeding with the construction of the ground floor at the same time from the first floor of the ground, which corresponds to the middle floor of the entire floor of the building, the frame construction of the first floor above the ground, Along the girder, install a temporary construction work platform using beam brackets and short pipes. In order to prevent the reinforcing bar and hoop reinforcement, the auxiliary reinforcing bar is fixed to the first floor column by welding so that the reinforcing bar is supported to the secondary reinforcing bar. After the formwork is closely installed so that the concrete does not leak, it is completed by reinforcing the assembly of the formwork, the formwork and concrete pouring, etc. according to a conventional method, and the framework after the second floor above ground is characterized in that proceeding in the usual way.
상술한 바와 같이 구성된 건축구조물의 골조 시공방법은 본 발명에서 종래의 공법과 유사한 명명 방식으로 이단타공법(二段打工法) 혹은 더블 압(double up)공법으로 명명하였는데, 상기와 같이 구성된 본 공법에서는, 지하층 골조 공사와 지상층 골조공사를 동시에 병행 추진하게 되므로, 이를 순차적으로 진행하는 종래의 공법에 비해 공기가 현저히 단축되고, 또한 작업의 불연속이 없이 연속적으로 진행되기 때문에 적절한 작업량을 계속 확보할 수 있으므로 투입인력을 효율적으로 관리할 수 있을 뿐만 아니라. 장비의 1회 투입으로 레미콘의 지상 및 지하 동시타설이 가능한 점 등 장비의 가동 효율이 증대되는 잇점이 있게 된다.Frame construction method of the building structure configured as described above was named in the present invention a two-stage method or a double up method in a similar naming method as the conventional method, this construction method configured as described above Since, at the same time, the basement structure and ground layer frame construction are simultaneously promoted simultaneously, the air is significantly shortened compared to the conventional construction method which proceeds sequentially, and the continuous work can be continuously performed without discontinuity of work, so that an appropriate amount of work can be continuously secured. Not only can you effectively manage your workforce. One-time operation of the equipment has the advantage that the operation efficiency of the equipment can be increased, such as allowing the concrete and ground to be poured simultaneously.
한편, 지하층 골조 공사를 계속하여 마지막으로 지상 1층 기둥 하부와 연결 처리할 때, 이 연결부에 레미콘을 밀실하게 충전시켜 주기 곤란한 문제가 있는데, 이를 해결하기 위해 1층 기둥의 콘크리트 타설시 기둥 하단을 1층바닥 슬라브의 상면과 하면 사이에 위치되도록 형성해 줌으로써, 추후 1층 바닥 슬라브를 타설하게 될 때 적절한 다짐만으로도 밀실한 충전이 충분히 이루어지게 할 수 있다.On the other hand, when continuing the basement frame construction and finally connecting to the lower ground pillars, there is a problem that it is difficult to tightly fill the ready-mixed concrete in this connection. By forming the first floor floor slab to be located between the upper surface and the lower surface, it is possible to ensure a sufficient filling with the proper compaction when placing the first floor floor slab in the future.
이하 본 발명을 첨부된 도면을 참조하여 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.
제1도는 종래의 공법을 도시한 제5도 및 제6도와 대비하여 용이하게 이해할 수 있도록 하기 위해 본 발명에 따른 골조의 시공방법을 개념적으로 도시한 것으로 제1도 (a)는 본 발명에 따른 공법의 개략적인 공정도이고, 제1도 (b)는 본 발명에 따른 공법의 공정단계별 시공상태를 개략적으로 도시한 것인데, 도시한 바와 같이 본 발명에 따른 골조의 시공방법은, 소정의 지하층과 지상층으로 이루어지는 건축구조물에서 그 골조를 철골 철근 콘크리트 구조로 시공함에 있어서, 철골공사를 어느 정도 진행한 후 지상구체공사와 지하구체공사를 동시에 진행하는 방식, 즉 지상골조공사와 지하골조공사를 어느 시점에서 병행 추진하는 시공방법이다.FIG. 1 conceptually illustrates a method for constructing a frame according to the present invention in order to make it easier to understand in comparison with FIGS. 5 and 6 showing a conventional method. FIG. Figure 1 is a schematic process diagram of the construction method, Figure 1 (b) is a schematic diagram showing the construction state of each process step of the construction method according to the present invention, as shown, the construction method of the frame according to the present invention, a predetermined basement layer and ground layer When constructing the frame from the structural structure of steel frame with reinforced concrete structure, after the steel frame work to some extent, the ground concrete work and the underground concrete work are carried out simultaneously, that is, the ground frame work and the underground frame work at some point It is the construction method to push in parallel.
그러나, 철골 및 데크 플레이트를 조립한 후 콘크리트 타설 등의 구체공사를 진행하는 골조공사에서, 지상골조공사는 지하골조공사가 전혀 이루어지지 않은 상태에서는 착수할 수 없으므로, 어느 정도의 골조공사를 진행한 시점에서 지상골조공사를 병행해 줄 수 있다. 이러한 병행 시점은 지하토공사를 완료한 후 철골 및 데크 플레이트(deck plate)공사를 적어도 지상 2층, 바람직하기로는 3-4층 정도까지 진행한 시점, 또 지하층의 기초공사 및 적어도 지하 1개층 정도의 골조공사는 완료한 시점 이후가 되어야 하는데, 전자의 시점은 철골이 조립되어야 콘크리트 타설이 가능하므로 당연한 이치이고, 후자의 시점은 철골구조가 어느 정도 안정된 상태에서 시공함으로써 이후의 시공부하에 충분히 견딜 수 있도록 하기 위함이다.However, in the construction of concrete structures such as concrete placing after assembling steel frame and deck plate, the ground frame construction cannot be undertaken without the underground frame construction. At this point, the ground frame construction can be done in parallel. This parallel point is the time when the construction of the steel frame and deck plate after the completion of the subterranean earthwork to at least two floors above the ground, preferably about 3-4 floors, the basement of the basement floor and at least one underground floor The frame construction should be after the completion point. The former point is natural because the steel can be assembled before the concrete can be placed. The latter point is sufficient to withstand the subsequent construction load by constructing the steel structure to a certain level. To make it work.
또한, 단순히 공기를 단축하고자 하는 목적만으로 골조공사를 병행 추진한다면, 지상골조공사를 병행 시작하는 층수를 꼭 1층을 할 필요가 없고, 오히려 상하 양 골조공사의 공사량을 반분하는 층으로 하는 것이 바람직하겠지만, 일반적으로 지하층의 한층당 공기는 지상층의 한층당 공기의 4배 정도가 되므로, 1층에서부터 지상골조 공사를 병행 시작하여도 상하의 양 공기는 통산 비슷하게 될 뿐만 아니라, 또한 병행 시작층의 골조 공사에서는 공중가설 작업대 등을 별도로 설치해야 하기 때문에 여러 가지 작업의 편의를 고려하고 공사의 안전성 등을 고려해 볼 때, 본 발명에서와 같이 지상골조 공사를 1층에서부터 시작하는 것이 가장 바람직 한 것이다.In addition, if the construction is to be carried out in parallel for the purpose of simply shortening the air, it is not necessary to have the first floor for the number of floors that start the ground frame construction in parallel, but rather, it is desirable to set the floor to half the construction volume of the upper and lower frames. However, in general, the air per floor of the basement floor is about four times the air per floor of the ground floor, so even if the ground frame construction starts from the first floor, the upper and lower air will not only be similar, but also the frame construction of the parallel starting floor. Since it is necessary to install a separate construction work platform, etc. In consideration of the convenience of various work and considering the safety of construction, it is most preferable to start the ground frame construction from the first floor as in the present invention.
한편, 지하층 및 지상층 골조공사를 병행하는 시점 이후의 공정에서 여타의 공사는 동일한 방식으로 그대로 진행하면 되지만, 지상 1층의 골조공사에서는 그 아래층의 기둥 및 슬라브 등의 골조가 아직 완성되지 않은 상태이기 때문에, 별도의 공중가설 작업대가 필요하게 되고, 또한 1층 기둥의 거푸집 설치 및 철근조립시 철근이나 타설된 콘크리트가 아래로 흘러내리지 않도록 하기 위해 특이한 구성이 필요하게 된다.On the other hand, in the process after the time when the basement and the ground-floor construction work together, other constructions can be carried out in the same way, but in the construction of the ground-floor construction of the ground floor, the framework of the pillars and slabs of the lower floor is not yet completed. Because of this, a separate aerial work platform is required, and a unique configuration is required to prevent the reinforcing bars or poured concrete from flowing down when installing the formwork of the first-floor column and assembling the reinforcing bars.
상기한 공중 가설작업대 대용으로 종래에 통상 사용하는 방식과 같이, 지하층 하부로부터 기둥별로 단관 비계 혹은 틀비계를 설치해 줄 수도 있는데, 이러한 경우에는 과다한 자재 및 인력투입이 불가피하고, 가설작업대 이용시 기둥간 수평이동이 곤란하게 되는 등 작업 안전성이 크게 떨어지며, 지하골조 작업과 간섭이 일어나 작업이 불편하게 되는 등의 문제점이 발생되기 때문에, 본 발명의 목적상 전혀 바람직하지 않다.As an alternative to the above-mentioned public temporary work platform, a single pipe scaffold or frame scaffold may be installed for each column from the lower basement floor, and in this case, excessive input of materials and manpower is inevitable, It is not preferable at all for the purposes of the present invention because problems such as difficulty in movement are greatly reduced and problems such as interference with the underground frame work are caused and work is inconvenient.
이와 같은 문제가 발생되지 않도록 본 발명에서는 일례로 제2도에 도시한 바와 같은 공중가설 작업대를 설치해 주는데, 제2도 (a)는 공중가설 작업대의 설치상태를 도시한 평면도이고, 제2도 (b)는 공중가설 작업대의 단면도이며, 제2도 (c)는 공중가설 작업대가 설치된 실제 공사현장의 현장사진이다. 도시한 바와 같이, 본 발명에 따른 공중가설 작업대(1)는 지상 1층 철골기둥(2)간을 서로 통하도록 빔(beam) 또는 거어더(girder, 3)를 따라 설치되어 있는데, 거어더(3)의군데 군데 지점에 빔브라켓(4)을 이용하여 단관 파이프(5)를 고정, 조립하고 패널(6)을 깔아서 작업대의 수평부를 만들고, 이 수평부의 양 측단에 역시 단관 파이프(6a)를 수직으로 조립하여 작업대의 난간부를 형성하여서 된 것이다. 이러한 공중가설 작업대는 그 아래층에 의존함이 없이 독립적으로 공중에 지지되는 것으로 지하 골조공사와의 간섭문제 해결하고 기둥의 철근조립 및 거푸집 설치를 안전하게 해 줄 뿐만 아니라, 간단한 자재와 적은 인력으로 용이하게 시공할 수 있어 별도의 추가비용을 별로 발생시키지 않는다.In order to prevent such a problem from occurring, the present invention provides an aerial construction work bench as shown in FIG. 2 as an example. FIG. 2 (a) is a plan view showing the installation state of the aerial work bench, and FIG. b) is a cross-sectional view of the construction work platform, and FIG. 2 (c) is a photograph of the actual construction site where the construction work platform is installed. As shown, the aerial work bench 1 according to the present invention is installed along a beam or girder 3 so as to pass through each other between the first-floor steel pillars 2 above the girder. 3) Fix and assemble the short pipe pipe 5 using beam brackets 4 at several places, and install the horizontal part of the workbench by laying the panel 6, and connect the short pipe pipe 6a at both ends of the horizontal part. It is made by vertically assembling the railing of the workbench. These aerial work platforms are independently supported by the air without relying on the lower floors to solve interference problems with underground structures, secure the reinforcing bars and formwork of columns, and make it easy with simple materials and less manpower. It can be constructed so that it does not incur additional additional costs.
또한, 1층의 아래부분 기둥이 아직 콘크리트가 타설되지 않은 철골상태로 되어 있기 때문에, 종래의 순타공법에서와 같은 방식으로 철근을 조립하거나 거푸집을 설치해서는 철근 및 콘크리트가 아래로 흘러내리게 되어 시공을 할 수 없게 되는데, 이를 방지하기 위해 1층 기둥의 철근 및 거푸집을 특별히 강구하여 설치해 주어야 하는데, 이의 설치상태는 예시적으로 제3도에 도시된 바와 같다.In addition, since the lower pillar of the first floor is in a steel frame in which concrete is not yet poured, the reinforcing bars and concrete will flow down by assembling the reinforcing bars or installing the formwork in the same manner as in the conventional net drilling method. In order to prevent this, the reinforcing bars and formwork of the first-floor column should be specially installed and installed, as shown in FIG. 3.
제3도 (a)는 보조철근의 설치상태를 나타낸 사진인데, 1층기둥 철골(2)에 보조철근(7)을 용접하여 튼튼하게 고정시키고, 여기에 후프철근 및 주근이 지지되도록 배근하여 줌으로써 철근이 흘러내리는 현상을 방지해 줄 수 있게 되는 것이다. 제 3도(b)는 1층기둥 하부 거푸집(8) 설치 상태를 나타낸 사진인데, 타설된 콘크리트를 아래에서 지지해 줄 수 있도록 종래와는 달리 기둥의 하면에도 1층바닥면의 거어더를 지지점으로하여 각재와 패널로 거푸집을 형성해 주는데. 이때 기둥의 주근(9) 부위는 절개해서 주근조립시 아래로 돌출될 수 있도록 해 준다.Figure 3 (a) is a photograph showing the installation state of the secondary reinforcement, by welding the secondary reinforcement (7) to the first-tier column steel frame (2) to be firmly fixed, by giving the hoop reinforcement and the main reinforcement here This will prevent the rebar from falling down. Figure 3 (b) is a picture showing the installation of the lower formwork (8) of the first floor pillar, unlike the prior art to support the pour concrete from the bottom of the column to support the bottom of the first floor girder By forming the formwork with lumber and panels. At this time, the main root (9) of the column is cut to allow the protruding down when the main root assembly.
제3도 (c)는 철근 및 거푸집 설치가 완료된 상태의 1층 기둥 하부의 종단면도이고, 제 3도 (d)는 이의 실제 시공상태의 사진이다. 도시된 바와 같이 철골(2) 둘레에 주근(9) 및 후프(10) 등의 철근을 조립하고, 그 측면 및 하면에 각재 및 패널을 이용하여 거푸집(8)을 설치한 상태로 되어 있고, 고정용 고리 또는 밀림방지용 앵글(미도시)을 이용하여 주변의 거어더에 미끄러지지 않도록 설치된 버팀대(11) 및 타이 와이어(tie wire, 12)에 의해 기둥 거푸집이 주변의 거어더에 긴결 지지됨으로써 기둥의 수직도가 안정적으로 유지되고 있으며, 또한 향후 지하부와의 이음을 위해 기둥의 주근(9)이 겹침 길이 이상의 길이만큼 아래로 돌출되도록 배근되어 있다.FIG. 3 (c) is a longitudinal cross-sectional view of the lower part of the one-story column when the reinforcing bars and formwork are installed, and FIG. 3 (d) is a photograph of its actual construction state. As shown in the figure, the reinforcing bars such as the main bar 9 and the hoop 10 are assembled around the steel frame 2, and the formwork 8 is installed on the side surfaces and the lower surfaces by using the materials and panels. The pillar formwork is tightly supported on the surrounding girder by the brace 11 and the tie wire 12 which are installed so as not to slip on the surrounding girder by using a ring or a rolling prevention angle (not shown). The road is kept stable, and further, the main root 9 of the column is projected to protrude downward by the length of the overlap length for future joint with the underground.
또한, 지하층 골조 공사를 계속하여 마지막으로 양 골조를 서로 연결 처리할 때, 1층 바닥 슬라브를 타설시 적절한 다짐만으로도 연결부에 틈새가 없이 레미콘의 밀실한 충전이 용이하게 이루어지게 하기 위해, 1층 기둥의 콘크리트 타설시 기둥 하부 끝단 위치(A)를 추후 타설할 1층바닥 슬라브의 윗면 위치(B)보다 아래에, 바람직하기로는 5cm 정도의 아래에 위치되도록 형성시켜 주면 좋다.In addition, when continuing the basement frame construction and finally connecting both frames together, the first-floor column can be easily filled with the ready-mixed concrete without gaps in the connecting part, even with proper compaction when placing the first-floor floor slab. In the case of concrete pouring, the lower end position (A) of the pillar may be formed to be located below the upper surface position (B) of the first floor floor slab to be poured later, preferably about 5 cm below.
또한 지하층의 골조작업은 지상1층 골조 작업 중 낙하물에 의해 간섭 또는 방해를 받을 수 있으므로, 1층의 바닥부분에 낙하물방지망(미도시)을 설치하여 이를 방지해 줄 수 있고, 일단 1층 천정슬라브가 완성이 되면 이 슬라브가 낙하물방지망을 대체하는 역할을 하게 되어 이후로는 낙하물방지망이 별도로 필요없게 된다.In addition, the frame work of the basement floor may be interfered with or interfered with by falling objects during the frame work on the ground floor, and thus, by installing a drop prevention net (not shown) on the bottom part of the first floor, the first floor ceiling slab may be prevented. When the slab is completed, the slab plays a role of replacing the fall prevention net, and thereafter, the fall prevention net is not necessary separately.
이상과 같이 공중가설 작업대, 1층기둥의 철근 및 거푸집 등을 설치하여 1층 골조 공사를 완료한 후에는, 통상의 순타공법에서 사용하는 방법으로 제4도 (a)에 도시된 바와 같이, 골조공사를 지하 및 지상 양 방향에서 층층이 상부로 진행에 나가면 되는 것이다. 제4도 (b)는 본 발명에 따른 시공방법으로 시공중인 건물의 현장전경을 참고적으로 나타낸 사진으로서, 지상층의 골조는 지상 1층 기둥부터 7층 바닥까지 완료된 상태이고, 지하부는 도시되어 있지는 않지만, 지하 2층까지 콘크리트 타설이 완료된 상태를 나타내고 있는데, 이로부터 지상층 및 지하층의 골조공사는 거의 비슷한 시기에 완료될 수 있음을 알 수 있다.After completing the construction of the first-floor frame by installing the aerial work bench, the reinforcing bar and the formwork of the first-floor column as described above, as shown in FIG. The construction is to proceed to the upper floor in both the basement and ground direction. Figure 4 (b) is a photograph showing the site view of the building under construction by the construction method according to the present invention for reference, the framework of the ground floor is completed from the ground floor pillars to the seventh floor, the basement is not shown However, concrete pouring to the second basement level is shown, and it can be seen from this that frame construction of the ground floor and the basement floor can be completed at about the same time.
한편, 본 발명의 공법은 이상의 설명으로부터도 쉽게 알 수 있는 바와 같이, 소정의 지하층과 지상층으로 이루어진 건축구조물 중에서 그 골조가 철골철근콘크리트 구조로 된 구조에 적용할 수 있는 공법이다. 이러한 구조의 건축물 중에서, 기둥의 철근콘크리트 부분에 응력부담이 없도록 설계된 경우(내화 피복용인 경우)에는 통상 아무런 문제점이 없이 그대로 본 발명의 공법을 적용 가능하나, 기둥의 철근 콘크리트 부분에 응력부담이 있도록 설계된 경우에는 시공부하에 적절히 대응할 수 있도록 철골부재를 보완 또는 조정할 필요가 있다. 이 후자의 경우는 적절하게 철골부재 단면을 조정하거나 보강재를 설치하여 용이하게 해결해 줄 수 있고, 또한 시공시에는 적재하중이 거의 실리지 않아 구조적으로 여유가 있는 경우가 대부분이므로, 본 발명에 따른 공법은 실질적으로 상당히 폭넓게 적용가능한 것이다.On the other hand, the construction method of the present invention, as can be easily seen from the above description, is a construction method that can be applied to the structure of the steel frame reinforced concrete structure of the building structure consisting of a predetermined basement and ground layer. In the structure of such a structure, if the reinforced concrete portion of the column is designed so that there is no stress burden (for fireproof coating), it is possible to apply the method of the present invention without any problem as usual, but to have a stress burden on the reinforced concrete portion of the column If it is designed, it is necessary to supplement or adjust the steel member so as to respond appropriately to the construction load. This latter case can be easily solved by appropriately adjusting the cross-section of the steel member or installing a reinforcing material, and in most cases, there is almost no structural load due to little loading load during construction. In fact, it is quite widely applicable.
이상에서 상세히 설명한 바와 같이 구성되는 본 발명에 따른 골조 시공 방법의 효과는 다음과 같다.Effects of the frame construction method according to the present invention configured as described in detail above are as follows.
첫째, 공기 단축의 효과이다. 지하층 골조공사와 지상층 골조공사를 거의 동시에 병행 추진하는 공정에 따른 당연한 귀결인데, 전체 골조공사 기간은 종래의 순타공법에 비해 상당히 단축될 수 있으며, 고층 빌딩일수록 그 효과는 더욱 커짐은 물론이다. 또한 본 발명에 의한 공법에서는 종래의 역타공법에서와 같은 추가적인 비용의 부담이 없는 잇점이 있다.First is the effect of air shortening. It is a natural consequence of the process of simultaneously promoting the basement frame construction and the ground structure at the same time, the overall frame construction period can be significantly shortened compared to the conventional netting method, the higher the building, the greater the effect is, of course. In addition, the method according to the present invention has the advantage that there is no additional cost burden as in the conventional reverse punching method.
둘째, 인력 및 장비 등의 자원 가동효율의 증대이다. 즉, 전체적으로 작업이 단속됨이 없어 연속적으로 진행되기 때문에 적절한 작업량을 계속 확보할 수 있으므로 투입인력을 효율적으로 관리할 수 있는 바, 따라서 종래와 같은 지하층 작업의 단속성으로 인한 속칭 데마찌 현상이 발생될 우려가 없다. 또한, 장비의 1회 투입으로 레미콘을 지상 및 지하층에 동시에 타설할 수 있으므로 장비의 가동효율이 증대되는 등의 잇점이 있게 되는 것이다.Second, resource utilization efficiency of human resources and equipment is increased. In other words, since the work is not interrupted as a whole and proceeds continuously, it is possible to continuously secure an appropriate amount of work so that the manpower can be efficiently managed. Therefore, the phenomenon known as Demachi occurs due to the intermittent work of the underground work. There is no fear of becoming. In addition, since the ready-mixed concrete can be placed on the ground and the basement at the same time, the operation efficiency of the equipment is increased.
셋째, 현장의 안전관리가 용이하다. 고층건물의 시공시 상부의 낙하물에 의한 재해 발생을 막기 위해 통상 낙하물방지망을 설치해 주는데, 본 발명의 공법에서는 일단 1층 천정슬라브가 완성이 되면 이후부터는 이 슬라브가 견고한 낙하물 방지망 기능을 수행하게 되므로, 시공의 안전성이 높아지게 되어 안전 관리상 매우 유익한 잇점이 있는 것이다.Third, the site's safety management is easy. In order to prevent the occurrence of disasters caused by falling objects in the upper part of the construction of high-rise building, the fall prevention net is usually installed, in the method of the present invention, once the first floor ceiling slab is completed, since the slab performs the function of the solid fall prevention net from then on, The safety of construction is increased, which is very beneficial in safety management.
넷째, 야적공간 확보가 가능하다. 통상 공사에 필요한 자재 등은 공사 현장에 일정량 적재해야 놓고 필요시 적시에 사용할 수 있도록 하는데, 종래에는 이를 위한 별도의 공간 또는 창고 등이 필요하였는데, 본 발명에서는 1층 천장슬라브(2층바닥)가 조기에 시공되므로, 이곳을 필요한 자재 적재 공간으로 활용할 수 있는 잇점이 있다. 특히 이점은 부지가 협소한 도심지 공사에서는 더욱 그 효과가 크다.Fourth, it is possible to secure yard spaces. Ordinary materials required for construction, such as a certain amount to be loaded on the construction site to be used in a timely manner if necessary, conventionally required a separate space or warehouse for this, in the present invention, the first floor ceiling slab (two floor floor) is Since it is constructed early, there is an advantage in using this as a necessary material loading space. This is especially true in urban construction where the site is narrow.
다섯째, 민원 부담이 대폭 경감된다. 공기 단축에 따른 당연한 귀결이지만, 환경 민원이나, 도심지 공사에서 특히 심한 교통 민원 등을 조기에 해결해 줄 수 있다.Fifth, the burden of complaints will be greatly reduced. Natural consequences of shortening the air, but can be resolved early, such as environmental complaints, and particularly severe traffic complaints in urban construction.
여섯째, 역타공법에 비해 적용 범위가 넓다. 종래의 역타공법은 지하토공사의 흙막이 공법을 슬러리 월 공법으로 해야 되는 제한이 있지만, 본 발명에서는 이러한 제한이 없으며, 또한 철골철근 콘크리트 구조이면 거의 제한 없이 폭넓게 적용가능하다.Sixth, the application range is wider than the reverse punching method. The conventional reverse drilling method has a limitation that the earthwork construction method of the underground soil construction as a slurry month method, but there is no such limitation in the present invention, and if the steel reinforced concrete structure can be widely applied without any limitation.
본 발명에 의한 공법을 시험적으로 적용해 본 결과, 이상과 같은 여러 가지 효과로 인해 다음의 도표와 같이 실제 공기의 단축은 물론 공사비용의 절감 효과가 있었다. (아래 도표는 건축면적 192.68평, 건물규모 지하5층 지상 12층인 경우임)Experimental application of the method according to the present invention, as a result of the above various effects, as shown in the following table, there was an effect of reducing the actual air as well as the construction cost. (The chart below is for building area of 192.68 pyeong, building scale of 5 basement levels and 12 ground levels
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019950003110A KR0150304B1 (en) | 1995-02-18 | 1995-02-18 | A method of simultaneously constructing frameworks for floors and basements of a building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019950003110A KR0150304B1 (en) | 1995-02-18 | 1995-02-18 | A method of simultaneously constructing frameworks for floors and basements of a building |
Publications (2)
Publication Number | Publication Date |
---|---|
KR960031732A KR960031732A (en) | 1996-09-17 |
KR0150304B1 true KR0150304B1 (en) | 1998-10-15 |
Family
ID=19408348
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019950003110A KR0150304B1 (en) | 1995-02-18 | 1995-02-18 | A method of simultaneously constructing frameworks for floors and basements of a building |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR0150304B1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101247638B1 (en) * | 2011-07-26 | 2013-04-01 | 삼성물산 주식회사 | Complex Frame System for Building and Building Construction Method Using the Same |
KR101395196B1 (en) * | 2012-11-29 | 2014-05-16 | 삼성물산 주식회사 | Fast-up method for construction duration reduction of high-rise buildings with transfer floor |
KR20210134532A (en) | 2017-12-20 | 2021-11-10 | 양경옥 | Method for constructing basement vertical member of top-down method constructed alternately |
-
1995
- 1995-02-18 KR KR1019950003110A patent/KR0150304B1/en not_active IP Right Cessation
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101247638B1 (en) * | 2011-07-26 | 2013-04-01 | 삼성물산 주식회사 | Complex Frame System for Building and Building Construction Method Using the Same |
KR101395196B1 (en) * | 2012-11-29 | 2014-05-16 | 삼성물산 주식회사 | Fast-up method for construction duration reduction of high-rise buildings with transfer floor |
KR20210134532A (en) | 2017-12-20 | 2021-11-10 | 양경옥 | Method for constructing basement vertical member of top-down method constructed alternately |
KR20210134533A (en) | 2017-12-20 | 2021-11-10 | 양경옥 | Method for constructing basement vertical member of top-down method constructed alternately |
Also Published As
Publication number | Publication date |
---|---|
KR960031732A (en) | 1996-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10260224B1 (en) | Simplified precast concrete system with rapid assembly formwork | |
KR101630235B1 (en) | Precast truss wall structure and construction method of underground structure using thereof | |
US5528877A (en) | Concrete building frame construction method | |
KR100951097B1 (en) | Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket | |
CN109339229B (en) | Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor | |
US4528793A (en) | Method of constructing precast concrete building with ductile concrete frame | |
AU754130B1 (en) | Building structural element | |
CN104831928B (en) | High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method | |
KR0150304B1 (en) | A method of simultaneously constructing frameworks for floors and basements of a building | |
KR0171873B1 (en) | Constructive method of a high building | |
CN114635503A (en) | Fair-faced concrete wall flexibly connected with concrete frame column and construction method | |
JP7134133B2 (en) | Bridge railing construction method | |
KR20060023915A (en) | Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports | |
JPH0361810B2 (en) | ||
JP2817591B2 (en) | Construction method of steel reinforced concrete building | |
JP6710064B2 (en) | Seismic isolation retrofit construction method and building construction | |
CN109736589B (en) | Construction method of lattice column force transmission component | |
JPH0988348A (en) | Method for constructing foundation beam | |
JPH0598653A (en) | Steel pipe concrete pillar in underground inverter construction method | |
KR20010097524A (en) | Hybrid precast concrete structure and the method of the same | |
JPH0337603B2 (en) | ||
RU2617813C2 (en) | The method of erection of prefabricated multi-storey reinforced concrete frame of a building | |
JP2024521265A (en) | Building Foundations | |
Nadeem | Formwork Construction Techniques | |
JPS6073916A (en) | Construction method for underground floor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130604 Year of fee payment: 16 |
|
FPAY | Annual fee payment |
Payment date: 20140514 Year of fee payment: 17 |
|
EXPY | Expiration of term |