JPS6073916A - Construction method for underground floor - Google Patents

Construction method for underground floor

Info

Publication number
JPS6073916A
JPS6073916A JP58145667A JP14566783A JPS6073916A JP S6073916 A JPS6073916 A JP S6073916A JP 58145667 A JP58145667 A JP 58145667A JP 14566783 A JP14566783 A JP 14566783A JP S6073916 A JPS6073916 A JP S6073916A
Authority
JP
Japan
Prior art keywords
floor
floor slab
guide rails
beams
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP58145667A
Other languages
Japanese (ja)
Inventor
Takeo Uchida
内田 武男
Seitaro Ebi
成太郎 海老
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP58145667A priority Critical patent/JPS6073916A/en
Publication of JPS6073916A publication Critical patent/JPS6073916A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To perform efficient building of an underground floor and to place concrete without the use of a construction joint at the underground floor, by a method wherein a structure center pillar having guide rails is erected in a hole bored in a ground, and beam materials are slidably engaged with guide rails. CONSTITUTION:A structure cetner pillar 3 having guide rails 6 is erected in a hole bored in a ground. After a second floor beam material 7 is secured to the portion, projecting from a ground, of the structure center pillar 3, beam materials (a) and (b) are slidably engaged with the guide rails 6, the adjoining beam materials (a) and (b) at the same floor are coupled together by means of an angle brace material 8, and floor plates are placed thereon to assemble a floor slab material. After the already-assembled floor slab for an underlaying floor is lowered along the guide rails 6, a next floor slab material is assembled. Further, after the floor slab materials for from a lowermost floor to a first floor are temporarily secured, in order, in a staged manner, the floor slab materials are secured to the structure center pillar 3, in order, from the floor slab material for an upper floor, and concrete is placed, in order, from an upper floor to a lower floor.

Description

【発明の詳細な説明】 本発明は地下階の構築工法に関する。[Detailed description of the invention] The present invention relates to a construction method for a basement floor.

従来の逆打ち工法線、通常の地下階構築工法に比べ、特
に地下階の構築工期が増大する欠点があった。その大き
な原因としては次の3点が挙げられる。
Compared to the conventional reverse construction method and the normal basement floor construction method, this method had the disadvantage of increasing the construction period, especially for the basement floor. There are three main reasons for this:

0) 梁を含む1wiス2プを構築した後、地下階を構
築していること。そのため、地下階の構築作業が、殆ん
ど1階スラブ下方での地下作業となり、資材の搬入、搬
出、取り込み作業が煩雑とならざるを得なかった0 (ロ) 梁下刃の約1.0Mから1.5Mの部分に打継
ぎ部を設けていること。そのため、この部分の型枠及び
鉄筋の組立作業と止水処理に多くの手間と時間を費やし
ていた。
0) After constructing the 1wisp including beams, the basement floor is constructed. As a result, most of the construction work for the basement floor was done underground below the first floor slab, and the loading, unloading, and importing of materials had to be complicated. A joining part shall be provided between 0M and 1.5M. Therefore, a lot of time and effort was spent on assembling the formwork and reinforcing bars in this area, and on water-stopping treatments.

〔う コンクリートを打設し、所定コンクリート強度に
達するまで養生期間を設けていたこと0その後、その階
の下部の掘削作9t−再開するため、工期を浪費してい
た。
[U] Concrete was poured and a curing period was allowed until the specified concrete strength was reached. After that, the excavation work at the bottom of that floor had to be restarted, which wasted construction time.

本発明は上記の欠点に鑑み、地下階を従来の逆打ち工法
よりも極めて簡単かつ能率的に構築でき、。
In view of the above-mentioned drawbacks, the present invention enables the construction of a basement floor much more easily and efficiently than the conventional reverse construction method.

また構築工期の短縮化を図るとともに、施工階スラブの
上端と直上階スラブの下端との間を、打継ぎ部を設ける
ことなく一度にコンクリート打設できる地下階の構築工
法を提供することを目的とするO 本発明によれば、この目的は、カイトレールを有する構
真柱を地中孔内に立設し、相対向する画描真柱の地上突
出部に2@梁材を架構固着した後、上記ガイドレールに
梁材を滑合させて同一階の直交し隣接する梁材同士を連
結するとともにそれらの上に床板を設置して床版材を組
み立て、地盤の掘削作朶の進行にともない、既に組み立
てた下方階の床版板をガイドレールに沿りて下降させた
後、当該階の床版材を組み立て、最下階よシ1階までの
床版材を構真柱に固着することなく順次段差的に吊持又
は仮固定し、所定架構位置に達しな上方階の床版材よシ
順次構真柱に固着するとともへ、上方階より下方階へと
順次所定部位のコンクリートを打設することによって達
成される。
In addition to shortening the construction period, the objective is to provide a construction method for basement floors that allows concrete to be poured at one time between the upper end of the construction floor slab and the lower end of the floor slab immediately above, without creating a joint. O According to the present invention, this purpose is to erect a structural pillar with a kite rail in an underground hole, and fix the frame beam material to the above-ground protrusion of the opposing drawing pillar. After that, the beams are slid onto the guide rails to connect the orthogonal and adjacent beams on the same floor, and the floor plates are installed on top of them to assemble the floor slabs and the ground excavation work progresses. Therefore, after lowering the already assembled floor slabs on the lower floor along the guide rails, we assembled the floor slabs on the relevant floor and fixed the floor slabs from the lowest floor to the first floor to the structural pillars. The floor slabs on the upper floors are fixed to the structural pillars in sequence, and the concrete is suspended or temporarily fixed in stages from the upper floors to the lower floors. This is achieved by pouring.

以下に本発明の一実施例を詳細に説明する。An embodiment of the present invention will be described in detail below.

第1図において、予め山留め壁°材11に設置しておき
、次に示すfll〜(4)の作業手順に従って構真柱を
立設するとともに2階梁材を架構する。
In FIG. 1, the retaining wall material 11 has been installed in advance, and the structural pillars are erected and the second floor beam materials are constructed according to the following work procedure (4).

(1)、所定位置にそれぞれ掘削された所定深さの孔2
内に所定長さの構真柱3を挿入して地上において仮固定
治具4によって仮固定し・この状態で各掘削孔2内にコ
ンクリートを打設して各構真柱3の下端部を固定する。
(1), holes 2 of a predetermined depth each drilled at a predetermined location
A structural pillar 3 of a predetermined length is inserted into the hole and temporarily fixed on the ground using a temporary fixing jig 4. In this state, concrete is poured into each excavated hole 2 to secure the lower end of each structural pillar 3. Fix it.

なお、構真柱3として、本例では、第7図に示すように
角パイプ状柱材を用い、その内部にコンクリート5′を
充填している。
In this example, as the structural pillar 3, a square pipe-shaped pillar material is used, as shown in FIG. 7, and the inside thereof is filled with concrete 5'.

構真柱3の各側面には、そのほぼ全長にそれぞれ2本の
ガイドレール6.6が平行に突設されている。
On each side of the structure pillar 3, two guide rails 6.6 are provided extending in parallel over almost the entire length thereof.

(2)、相対向する画描真柱3.3の地上突出部に1第
1.7図に示すように1対の2階梁相7,7を平行に架
構固着する。
(2) As shown in FIG. 1.7, a pair of second-story beams 7, 7 are fixed in parallel to the above-ground protruding parts of the facing pillars 3.3.

表お、このとき、ガイドレール6.6の上端部に切欠部
6’、6’を形成し、ここにおいて2階梁材7.7の端
縁を構真柱3の側面に溶接して、両2階梁拐7,7の間
隔(内法寸法)をガイドレール6.6の間隔とはは等し
くしておくこと、及びガイドレール6.6の内面と2階
梁材7,7の内面を平滑にしておくことが望ましい。
At this time, notches 6', 6' are formed at the upper end of the guide rail 6.6, and the edge of the second floor beam 7.7 is welded to the side surface of the structural column 3. The distance between the two second floor beams 7, 7 (inner dimensions) must be the same as the distance between the guide rails 6.6, and the inner surface of the guide rail 6.6 and the inner surface of the second floor beams 7, 7. It is desirable to keep it smooth.

また、2階梁拐7,7をこのように構真柱3に固着する
ことは、機能性(特に、後述する梁材の滑合作業時の施
工性と安全性、2階床板設置後の前記2者の両立、構真
柱頭部の位置決め・水平方向の剛性)を向上させるため
で、2va梁材には、みそ形鋼を用いるが最も望ましい
が、工形J H形鋼、L形銅などの他の形鋼でもよい。
In addition, fixing the second floor beams 7, 7 to the structural pillars 3 in this way is important for functionality (in particular, workability and safety during the sliding work of beam materials, which will be described later), and In order to achieve both of the above two requirements, as well as to improve the positioning of the structural column head and horizontal rigidity, it is most preferable to use miso section steel for the 2VA beam material. Other shaped steels such as

(3)、仮固定治具4を取シ外す。(3) Remove the temporary fixing jig 4.

かくして、相対向する構真柱3.3の上端部は2va梁
材7,7によって一定の間隔に保持されるもので、この
後、次の(4)〜(イ)の順序で梁材の滑合下降、梁材
の連結・組み立て、その吊持及び下降、コンクリート打
設作業を行う。
In this way, the upper ends of the structural pillars 3.3 facing each other are held at a constant distance by the 2VA beams 7, 7, and after this, the beams are attached in the following order (4) to (a). Performs sliding and lowering, connecting and assembling beams, lifting and lowering them, and concrete pouring work.

なお、本例では、最下階から1階までのいずれの諧の梁
材についても、第7図に示すように耐力壁に隣接する梁
材aにはH形fl11を用い、それ以外の梁材すには、
2本のみそ形N b1* byをフィラープレートb、
を介し分離可能にボルト接合;、た合成梁材を用いる場
合を想定している。
In this example, for all beams from the bottom floor to the first floor, H-shaped fl11 is used for the beam a adjacent to the load-bearing wall, and the other beams are For the timber,
Two miso-shaped N b1* by filler plate b,
It is assumed that composite beams are used that are separably bolted together.

(4)、掘削作朶を開始し、所定の深さまで掘削された
場所から、第2図に示すように梁材a、bを地上におい
てクレーン等で吊持しながら、面構真柱3゜3のガイド
レール6.6に上端よシ滑合させ、これらガイドレール
6,6に沿って下降させて1対の2@梁材7,70間を
通過させる。
(4) Start excavation work, and from the place excavated to a predetermined depth, as shown in Figure 2, while suspending beams a and b on the ground with a crane etc., The upper end is slidably fitted onto the guide rails 6, 6 of No. 3, and is lowered along these guide rails 6, 6 to pass between the pair of beam members 7, 70 of No. 2.

(5)、滑合通過させた梁@’a、bのうち互いに直交
し隣接する梁材同士を、火打材8によって強固に連結し
て格子状に組む。
(5) Among the beams @'a and b that have been slid together and are mutually orthogonal and adjacent to each other, the beams are firmly connected by flint 8 and assembled in a lattice shape.

(6)、格子組梁材上にm@床板91に設置する(以下
床版材と記す)とともに、第7.8図に示すように梁@
a及びbの端部に、ガイドレール6.6の外側面と摺接
する摺動補助板9,9をボルト接合して最下階・(・本
例では地下3階)の床版材B、を組み立て、例えばチェ
ーンブロック10のチェーン10′によりて2i梁材7
の下刃に仮吊持しておく。
(6), install the m@ floor plate 91 on the lattice beam (hereinafter referred to as floor slab material), and as shown in Fig. 7.8,
Sliding auxiliary plates 9, 9 that are in sliding contact with the outer surfaces of the guide rails 6.6 are bolted to the ends of a and b to create the floor slab material B for the lowest floor (in this example, the third basement floor). For example, use the chain 10' of the chain block 10 to connect the 2i beam 7.
Temporarily hang it on the lower blade.

(力、掘削作業がさらに進行した後、第3図に示すよ・
うに最下階用床版材B、の上方において上記(4)〜(
6)と同じ作業手順で地下2階用床版材B、を組み立て
、同様にチェーンブロック10のチェーン10’で2階
梁材7の下方に吊持するとともに、仮受は治具11で構
真柱3に仮固定する。すなわち、第7図に示すように、
仮受は治具11をボルトを用いてガイドレール6.6に
取り付けるとともに1この仮受は治具11上に梁材a又
はbt乗載してボルトで仮固定する。その後、チェーン
ブロック10を取シ替え、最下階用床版材B、を地下2
階用床版材B、の下方に吊持する。
(After further excavation work, as shown in Figure 3)
Above (4) to () above the bottom floor slab material B,
Assemble the floor slab material B for the second basement floor using the same procedure as in step 6), suspend it below the second floor beam material 7 using the chain 10' of the chain block 10, and use the jig 11 for temporary support. Temporarily fix it to the true pillar 3. That is, as shown in Figure 7,
For the temporary support, the jig 11 is attached to the guide rail 6.6 using bolts, and the beam material a or b is mounted on the jig 11 and temporarily fixed with bolts. After that, the chain block 10 was replaced, and the floor slab material B for the lowest floor was installed in the basement 2.
It is suspended below the floor slab material B.

寿お、梁材a、bを仮固定するのは、上記のように既に
架構固着した2階梁材7,7と相俟って、架構中の両槽
真柱3.3相互の動きを拘束し、その中途部分での捩れ
やそシを防止するためである。
The purpose of temporarily fixing the beams a and b is to prevent the movement of the two tank pillars 3 and 3 in the frame together with the second floor beams 7 and 7 that have already been fixed to the frame as described above. This is to prevent twisting or unraveling in the middle portion.

+81. TiA接した場所において上記と同様に最下
階用床版材B、/を組み立て、その梁材を仮受は治具1
1で仮固定する。なお、床版材B、とB、/とは、合成
梁材すのb8とす、とを分離して別個に組み立てる。
+81. Assemble the floor slab materials B and / for the bottom floor in the same way as above at the place where the TiA contacts, and use jig 1 to temporarily hold the beam materials.
Temporarily fix at 1. In addition, the floor slab materials B, and B, / are assembled separately by separating the composite beam materials b8 and .

(9)、山留め壁材1と構真柱3の間に第1段用復起し
材12.及び切梁材131を設置す石。
(9) First-stage backing material 12 between the retaining wall material 1 and the structural pillar 3. and stones for installing struts 131.

む0)、チェーンブロック10を操作し、最下階用床版
材B3をガイドレール6.6に沿って所定位置まで下降
させる。
0), operate the chain block 10 to lower the floor slab material B3 for the lowest floor to a predetermined position along the guide rail 6.6.

al)、第4図に示すように、最下階川床版材B、t−
仮受は治具、11によって所定位置に仮固定するととも
に、第2段用腹蔵し材12.及び切梁材13.の一部を
設置する。
al), as shown in Fig. 4, the bottom floor river bed slab material B, t-
The temporary support is temporarily fixed in a predetermined position with a jig 11, and a second stage holding material 12. and strut material 13. Install a part of the

(1:!1. 地下1階用床版材B1を組み立て、仮受
は治具11によって所定位置に仮固定する。
(1:!1. Assemble the floor slab material B1 for the first basement floor, and temporarily fix the temporary support in the predetermined position using the jig 11.

G31. 地下2階用床版材B、を、仮受は治具lll
数取外した後、所定位置まで下降させる。
G31. Temporarily hold the floor slab material B for the second basement floor using a jig.
After removing several parts, lower it to the specified position.

0滲、防接した場所において、地下2階用床版材Bfを
組み立て、仮受は治具11によって所定粒+!′Ij:
に仮固定した後、最下階用床版材Bi ’k 7151
定位置まで下降させる。
Assemble the floor slab material Bf for the second basement floor in a place with zero leakage and shielding, and temporarily hold it with the specified grain +! using jig 11. 'Ij:
After temporarily fixing the floor slab material for the bottom floor Bi'k 7151
Lower it to the fixed position.

051、掘削作業の進行にともない、最下階川床版材B
□地下2階用床版拐Bx−地下1v?用床版材B、につ
いて上記のような下降、仮固定作築を順次行い、1階用
床版材F、(第5図)を組み立てるとともに第3段用復
起し材12.及び切梁材13□を設置する。隣接した場
所においても同様にして地下IWj用床板床版材及び1
階用床版材FIを組み立てる。
051, As the excavation work progresses, the bottom floor riverbed slab material B
□ Floor slab for basement 2nd floor Bx-basement 1v? The above-mentioned lowering and temporary fixing of the floor slab material B are carried out in sequence, and the first floor floor slab material F (Fig. 5) is assembled, and the third stage raising material 12. and install 13□ struts. In the same way, the floor slab material for underground IWJ and 1.
Assemble floor slab material FI.

Qo、1階梁材の滑合が終了した場Biより2階スラブ
コンクリート14を打設する。
Qo, the second floor slab concrete 14 is poured from Bi when the sliding joint of the first floor beams is completed.

(L?)−19’r定の架構位置に達した1階用困1阪
材F、及びF?の梁材a及びb (b、とb1再びボル
ト接合する)を構真柱3に溶接固着した後、これら床版
材FleF8上にスラブコンクリート15を打設する。
(L?)-19'R The first floor 1st floor timbers F and F? have reached the fixed frame position. After the beams a and b (b and b1 are bolted again) are welded and fixed to the structural pillars 3, slab concrete 15 is placed on these floor slabs FleF8.

この間、下方階の床版材については、上記の作業手1直
に従って仮固定及び下降作業を行う。
During this time, the floor slab materials on the lower floors will be temporarily fixed and lowered according to the first shift described above.

081、7)r定の架相位傷9に達した地下1階用床版
@B、。
081, 7) Floor slab for the first basement floor @B, which has reached r constant frame phase flaw 9.

BEについて、1階の場合と同様の作業を行う。For BE, perform the same work as for the first floor.

Ql、スラブコンクリート15カニFFt定のコンクリ
ート強度に達したなC)杖、第6図に示すように1階と
地下1階の間において、柱16.梁17.耐力壁18の
鉄筋、型枠を組み立て、1F#のスラブの所定位置に設
けられた貫通孔よりコンクリートを流る0 (至)、地下1階床版材B1+]lRと地下i階梁材B
、、B4のl■において上記と同様の作業を行う。最下
階では、梁材a、bを1?ll真柱3に溶接した仮、耐
力盤19のコンクリートを打設し、次に柱、耐力壁、梁
Ql, the concrete strength of the slab concrete 15 crab FFt has been reached. Beam 17. Assemble the reinforcing bars and formwork for the load-bearing wall 18, and pour the concrete through the through holes provided in the predetermined positions of the slab on the 1st floor.
,, Do the same work as above in l■ of B4. On the bottom floor, set beams a and b to 1? ll Concreting the temporary load-bearing plate 19 welded to the true pillar 3, then the column, load-bearing wall, and beam.

スラブのコンクリートを打設する0 以上の通シ、格子状に組み立てられた梁′@(床版材)
の仮固定によって土圧を支持しなめcら、掘削を進め、
床版材を所定位置まで下降させた後、用足部位のコンク
リートを打設すれば、掘削工事を中断させることなく、
複雑な打継ぎ部を不用とした地下階を構築することがで
きる。
0 or more through holes for pouring slab concrete, beams assembled in a grid pattern (floor slab material)
The earth pressure was supported by temporary fixation, and the excavation continued.
After lowering the floor slab material to the specified position, concrete for the footing area can be poured without interrupting the excavation work.
It is possible to construct a basement floor that does not require complicated joints.

本実施例において、構真柱3として角ノくイフ゛状柱材
を用い、その内部にコンクリート5′を充填した形態と
したのは、スラブの全平面寸法(建物の地下部分の平面
寸法にほぼ等しい)を藍大藪い場合を想定し、各階につ
いて梁材a、bt−多数躬1(複数の格子組)とし、各
階別側にしかも上、下階段差的に下降、溶接固着する方
法を採ったため、土cc at 9工亡引今汁削でけ、
ヒ、下階のi材[K段差が生じていることKよシ、構真
柱3に曲けや剪断力が働く。このため、S真柱3に社曲
げ耐力及び剪断耐力が徴求されることを考慮したもので
ある。
In this example, square shaped pillars are used as the structural pillars 3, and the concrete 5' is filled inside them because the overall planar dimension of the slab (approximately Assuming a case where the beams are the same (equal), the beams are made of A, BT and 1 (multiple lattice sets) for each floor, and the upper and lower stairs are lowered differentially and fixed by welding on each floor. As a result, the construction of the earth cc at 9th construction was completed.
hi, I material on the lower floor [K There is a step. For this reason, it is taken into consideration that the S true pillar 3 is required to have bending strength and shear strength.

なお、スラブの全平面寸法が小さい場合には、梁材a、
bを1組連結(1個の格子組)した方法でも構築性可能
である。なお、この場合、最下階の床版材の下降時には
、安全のため、掘削作業は一時中断(従来工法に比べて
その時間は極めて短い)することが望ましい。
In addition, if the overall planar dimensions of the slab are small, beam materials a,
Construction is also possible by connecting one set of b (one lattice set). In this case, for safety reasons, it is desirable to temporarily suspend the excavation work (the time required is extremely short compared to conventional construction methods) when lowering the floor slab material on the lowest floor.

また、梁材a、bの端部に摺動用補助板9.910付け
て格子組梁材(床版材)全下降させる方法を採ったのは
、直上階、直下階の格子組梁材を仮受は治具11により
て構真柱3に仮固定して構真柱3を拘束しているといえ
ども、土圧が伝達された状態(構真柱に曲げやそシが生
じる)で格子組梁材を下降させると、梁材の端面と構真
柱の側面が摺れ合い、溶接用開先の表面状態が不良とな
るため、摺動用補助板9,9とガイドレール6゜6とを
摺れ合せて梁材の端面と構真柱の側面との直接接触を回
避するためである。
In addition, the method of attaching sliding auxiliary plates 9.910 to the ends of beams a and b and lowering the lattice beams (floor slabs) completely is because the lattice beams on the floors directly above and below are Even though the temporary support is temporarily fixed to the structural pillar 3 using the jig 11 and the structural pillar 3 is restrained, the temporary support is in a state where earth pressure is transmitted (bending or distortion occurs in the structural pillar). When the lattice beam is lowered, the end face of the beam and the side surface of the structural column will rub against each other, making the surface condition of the welding groove poor. This is to avoid direct contact between the end face of the beam material and the side surface of the structural column by sliding the ends together.

また、格子組梁材相互の接合部となる梁材すに、2本の
みぞ形態bisb!をフィラープレートbsを介し分離
可能にボルト接合する合成梁材の形態を採ったのは、土
圧が伝達されている状態において、下降時には、分離さ
せたみそ形mbtmbt同士の衝突、摺れ合いによる作
業性低下を回避する一万、所定架構位置に達した後の接
合時には、その接合作業(特にフィラーグレートの挟設
作業)を容易にし、しかも接合後には、構造体としての
所定性能が得られること全考慮したためである。
In addition, the beams that form the joints between the lattice beams have two grooves bisb! The reason why we adopted the form of a composite beam material that is separably bolted together via a filler plate bs is that when earth pressure is being transmitted, the separated miso-shaped mbtmbt collide and slide against each other when descending. 10,000 to avoid deterioration in work efficiency, when joining after reaching the specified frame position, it facilitates the joining work (especially the work of sandwiching the filler grates), and furthermore, after joining, the specified performance as a structure can be obtained. This is because we have taken everything into consideration.

また、格子組梁材上に潤製床板9を設置した床版拐を用
いたのは、安全な作業床及び下方階(掘削面も含む)か
ら見た場合は防護天井を碌保するためであり、しかも床
版材を所定位置に固着し、スラブコンクリートの打設・
硬化後、上方階の梁コンクリートの自重が支えられる支
持床とするためである。なお、土庄に対して、格子組梁
材の材軸方向の許容圧縮応力が不足する場合、銅製床板
の代わシにプレキャストコンクリート製床板を用いたシ
、外周所定部位をコンクリートで覆っ九(プレキャスト
コンクリート化)梁材を用いれば、より大きな土圧に対
応でき、しかもコンクリートを打設する部位が少なくな
るため、工期をさらに短縮することができる。
In addition, the reason why we used a floor slab with Jun-made floor plates 9 installed on the lattice beams was to ensure a safe working floor and a protective ceiling when viewed from the lower floor (including the excavation surface). Yes, and it also fixes the floor slab material in place, making it easy to place and place slab concrete.
This is to create a supporting floor that can support the weight of the concrete beams on the upper floors after hardening. If the allowable compressive stress in the axial direction of the lattice beams is insufficient for Tonosho, precast concrete floor plates may be used instead of copper floor plates, or precast concrete may be used to cover designated areas of the periphery with concrete. By using beams, it is possible to cope with greater earth pressure, and there are fewer places to pour concrete, which further shortens the construction period.

本発明の工法による効果を以下に列記する。The effects of the construction method of the present invention are listed below.

■ 床版材又は格子組梁材が切梁材の用をなすため、従
来工法において地下階内部に貫通していた切梁材が不用
となシ、その設置及び解体にともなう仮設費の低減や工
期の短縮が図れる。
■ Because the floor slab material or lattice beam material serves as the strut material, the strut material that penetrates into the basement floor in conventional construction methods is no longer required, reducing temporary construction costs associated with installation and dismantling. Construction period can be shortened.

■ 施工階スラブの上端と直上階スラブの下端との間を
一度にコンクリート打設でき、各梁の下方(約1.0M
−15M)に打継ぎ部が生じないモルタルの注入)の工
事簀の低減及び工期の短縮が図れる。
■ Concrete can be placed between the top end of the construction floor slab and the bottom end of the floor slab directly above it at once, and the area below each beam (approximately 1.0M
-15M) can be used to reduce the amount of work required and shorten the construction period.

■ 各階のスラブのコンクリートを打設し、所定コンク
リート強度に達した後、梁、柱1、耐力壁の配筋及び型
枠の組み立てが行えるため、地上階における通常の作梨
形態、支保形態と#1は同様になシ、梁、往、耐力壁の
構築作−梨は単純化され、しかもそれらのコンクリート
打設作業は、財上階スラブに設けられた貫通孔から直接
投入できるため、作業安全・a tit、 eめて向上
する。
■ After pouring concrete for each floor slab and reaching the specified concrete strength, reinforcement for beams, columns 1, load-bearing walls, and formwork can be assembled. #1 similarly simplifies the construction of pears, beams, and load-bearing walls, and moreover, the concrete pouring work can be done directly through the through-hole provided in the upper floor slab, making the work easier. Improve safety, atit, and safety.

■ 最下階より1階までの床版材を段差的に下降させ、
P5「定架構位會に達した上方階のものより順次梠真柱
に固着するため、(イ)梁、柱、耐力壁の配筋及び型枠
組立作業、←)床版材の仮固定、下降、固着作業、(ハ
)掘削作業の3秒類の作業は、同時にかつ安全に並行し
て行うことができ(床版材が介在するため、上下重複作
業とはならない)、シかも床版材の組立作業は地上で行
える念め、上記3釉の作業は動線と重複することもなく
、地下階構築の全体工期を大幅に短縮することができる
■ The floor slab material from the bottom floor to the first floor is lowered in steps,
P5: In order to secure the upper floors to the pillars in order from the upper floors that have reached the fixed frame position, (a) Reinforcement and formwork assembly work for beams, columns, and load-bearing walls, ←) Temporary fixing of floor slab materials, The three-second work of lowering, anchoring work, and (c) excavation work can be performed simultaneously and safely in parallel (because the floor slab material is involved, there will be no overlap between upper and lower operations), and it may be possible to Since the assembly work of the materials can be carried out above ground, the work for the three glazes mentioned above does not overlap with the flow line, making it possible to significantly shorten the overall construction period for the basement floor construction.

【図面の簡単な説明】[Brief explanation of drawings]

第1〜6図は本発明の一実施例の施工順序を示す説明図
、第7,8図は構真柱と梁材の関係を示す斜視図及び平
面図である。 6・・・ガイドレール、3・・・構真柱、2・・・掘削
孔、7・・・2階梁材、a、b・・・梁材、9・・・床
板、B□Bt e B1 e R#瀉+ B!l BI
sF?・・・床版@0 特許出願人 株式会社間 組 代理人 弁理士 原 1) 信 F” ココ5 111 手続補正書 昭和59年11月8日 特許庁長官 志 賀 学 殿 1、事件の表示 特願昭58−145667号 2、 発明の名称 地下階の構築工法 3、補正をする者 事件との関係 特許出願人 株式会社 間 組 4、代理人 ■105東京都港区新橋−丁目18番11号−松ビル自
 発 6、補正の対象 明細書の発明の詳細な説明の欄。 !11 明細書第6頁第9行の「ガイドレール」を「ガ
イドレール」と補正する。 (2)同書第9頁第10行の「F2」をrFl ’Jと
補正する。
1 to 6 are explanatory diagrams showing the construction order of an embodiment of the present invention, and FIGS. 7 and 8 are a perspective view and a plan view showing the relationship between the structural pillar and the beam material. 6... Guide rail, 3... Structure pillar, 2... Excavation hole, 7... Second floor beam material, a, b... Beam material, 9... Floor plate, B□Bt e B1 e R# 瀉+ B! l BI
sF? ...Floorplate @0 Patent Applicant Maza Co., Ltd. Agent Patent Attorney Hara 1) Shin F” Coco 5 111 Procedural Amendment November 8, 1980 Commissioner of the Japan Patent Office Manabu Shiga 1, Special indication of the case Application No. 58-145667 2, Name of the invention Construction method for underground floors 3, Relationship with the case of the person making the amendment Patent applicant Co., Ltd. Hazama Gumi 4, Agent ■ 105 Shinbashi-18-11, Minato-ku, Tokyo - Matsu Building Co., Ltd. 6, Detailed description of the invention in the specification subject to amendment. !11 Amend "guide rail" in line 9 of page 6 of the specification to "guide rail." (2) "F2" on page 9, line 10 of the same book is corrected to rFl'J.

Claims (1)

【特許請求の範囲】[Claims] L ガイドレールを有する構真柱を地中掘削孔内に立設
し、相対向する両槽真柱の地上突出部に2階梁材を架構
固着した後、上記ガイドレールに梁材を滑合させて同一
階の直交し隣接する梁材同士を連結するとともにそれら
の上に床板を設置して床版材を組み立て、地盤の掘削作
業の進行に伴ない、既に組み立てた下方階の床版材をガ
イドレールに沿って下降させた後、当該階の床版材を組
み立て、最下階よ91階までの床版材を構真柱に固着す
ることなく順次段差的に吊持又は仮固定し、所定架構位
置に達した上方階の床版材より順次構真柱Kb’J着す
るととも罠、上方階よシ下方階へと順次コンクリート打
設することを特徴とする地下階の構築工法。
L: After installing a structural column with a guide rail in the underground excavation hole and fixing the second-floor beam material to the above-ground protrusion of the opposing tank main column, the beam material is slid onto the guide rail. Then, the orthogonal and adjacent beams on the same floor are connected to each other, and floor plates are installed on top of them to assemble the floor slabs.As the ground excavation work progresses, the floor slabs of the already assembled lower floors are After lowering the floor slabs along the guide rails, the floor slabs for the relevant floors are assembled, and the floor slabs from the lowest floor to the 91st floor are suspended or temporarily fixed in stages without being fixed to the structural pillars. A construction method for a basement floor, which is characterized in that concrete is poured sequentially from the floor slab material of the upper floor that has reached a predetermined frame position to the structural column Kb'J, and then from the upper floor to the lower floor.
JP58145667A 1983-08-11 1983-08-11 Construction method for underground floor Pending JPS6073916A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58145667A JPS6073916A (en) 1983-08-11 1983-08-11 Construction method for underground floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58145667A JPS6073916A (en) 1983-08-11 1983-08-11 Construction method for underground floor

Publications (1)

Publication Number Publication Date
JPS6073916A true JPS6073916A (en) 1985-04-26

Family

ID=15390297

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58145667A Pending JPS6073916A (en) 1983-08-11 1983-08-11 Construction method for underground floor

Country Status (1)

Country Link
JP (1) JPS6073916A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01322045A (en) * 1988-06-24 1989-12-27 Shimizu Corp Construction of basement
JPH0594342U (en) * 1992-05-22 1993-12-24 清水建設株式会社 Structure of the true pillar
EP1488046A1 (en) * 2002-03-07 2004-12-22 Paul Blazevic Method of construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01322045A (en) * 1988-06-24 1989-12-27 Shimizu Corp Construction of basement
JPH0594342U (en) * 1992-05-22 1993-12-24 清水建設株式会社 Structure of the true pillar
EP1488046A1 (en) * 2002-03-07 2004-12-22 Paul Blazevic Method of construction
EP1488046A4 (en) * 2002-03-07 2005-11-23 Paul Blazevic Method of construction
CN100443673C (en) * 2002-03-07 2008-12-17 P·布拉热维奇 Method of construction

Similar Documents

Publication Publication Date Title
JP6448817B2 (en) PC truss wall structure and construction method thereof
KR100927344B1 (en) Construction method for connecting underground structure and underground structure using connection structure for underground construction
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
JP4164857B2 (en) Reconstruction method using existing underground structure
KR100605514B1 (en) Bracket support type downward construction system and construction method using the same
KR20110052360A (en) Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab
JP6855296B2 (en) Building foundation structure and its construction method
KR200383309Y1 (en) Form system for construction of underground slab
JPS6073916A (en) Construction method for underground floor
CN115387378A (en) Semi-pillarless assembly type station based on simply supported superposed side walls and floorslabs and method thereof
JP2020060000A (en) Skeleton construction method
JP4024448B2 (en) Seismic isolation method for existing buildings
JP2002206209A (en) Bridge having upper-lower section integral structure and its execution method
JP2016044494A (en) Construction method of foundation
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
JPS6137692Y2 (en)
JPH07107360B2 (en) Station construction method using multi-connection shield method
JP4024449B2 (en) Seismic isolation method for existing buildings
JPH0657710A (en) Construction of concrete main tower
JPH0361810B2 (en)
JPH11140892A (en) Method for excavating ground and method for constructing underground structure using the same
JP7152383B2 (en) Structural column base structure and column base fixing method
KR0150304B1 (en) A method of simultaneously constructing frameworks for floors and basements of a building
JP2817591B2 (en) Construction method of steel reinforced concrete building
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam