KR20210155380A - A construction period shortening type topdown structure using the underground core wall column and the temporary pole for transmitting the structural load on the ground floor and construction period shortening type topdown construction method using the same - Google Patents

A construction period shortening type topdown structure using the underground core wall column and the temporary pole for transmitting the structural load on the ground floor and construction period shortening type topdown construction method using the same Download PDF

Info

Publication number
KR20210155380A
KR20210155380A KR1020210077447A KR20210077447A KR20210155380A KR 20210155380 A KR20210155380 A KR 20210155380A KR 1020210077447 A KR1020210077447 A KR 1020210077447A KR 20210077447 A KR20210077447 A KR 20210077447A KR 20210155380 A KR20210155380 A KR 20210155380A
Authority
KR
South Korea
Prior art keywords
temporary
core wall
construction
temporary pillar
floor
Prior art date
Application number
KR1020210077447A
Other languages
Korean (ko)
Inventor
임인식
이범택
한주옥
Original Assignee
임인식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 임인식 filed Critical 임인식
Publication of KR20210155380A publication Critical patent/KR20210155380A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

The present invention relates to a construction period shortening type reverse rudder structure using an underground core wall side reverse rudder column and a temporary column for transmitting a structural load on a ground floor and a construction period shortening reverse piercing method using the same. The present invention can provide the construction period shortening type reverse rudder structure using a joint structure of a core wall and a semi-buried temporary column, comprising: the temporary column erected adjacent to the core wall; and a connecting unit having one end unit joined to the temporary column and the other end unit fixed to the core wall, connecting the temporary column and the core wall to each other. The temporary column is installed before core wall construction, but a lower end part is buried in a basement floor. An upper part is joined to a horizontal member of a ground floor, and an upper end part is erected to extend to an upper part of a ceiling of the ground floor. According to the above, a construction period of building construction can be effectively shortened because construction of the ground floor can be started even before construction of a core of a first basement floor is completed.

Description

지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물 및 이를 이용한 공기단축형 역타공법{A CONSTRUCTION PERIOD SHORTENING TYPE TOPDOWN STRUCTURE USING THE UNDERGROUND CORE WALL COLUMN AND THE TEMPORARY POLE FOR TRANSMITTING THE STRUCTURAL LOAD ON THE GROUND FLOOR AND CONSTRUCTION PERIOD SHORTENING TYPE TOPDOWN CONSTRUCTION METHOD USING THE SAME}A CONSTRUCTION PERIOD SHORTENING TYPE TOPDOWN STRUCTURE USING THE UNDERGROUND CORE WALL COLUMN AND THE TEMPORARY POLE FOR TRANSMITTING THE STRUCTION PERIOD SHORTENING TYPE TOPDOWN STRUCTURE USING THE UNDERGROUND CORE WALL COLUMN AND THE TEMPORARY POLE FOR TRANSMITTING LOAD ON THE GROUND FLOOR AND CONSTRUCTION PERIOD SHORTENING TYPE TOPDOWN CONSTRUCTION METHOD USING THE SAME}

본 발명은 도심지 역타공법 적용시 굴토용 장비 및 자재를 적재하는 바닥인 시공층 슬래브를 완료한 이후 상부층 골조의 조기착수를 위한 코어벽체의 접합구조를 이용한 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물 및 이를 이용한 공기단축형 역타공법에 관한 것으로서, 보다 상세하게는 시공층 슬래브 하부층의 코어벽체가 시공될 위치에 설치된 역타 임시기둥과 지상층 코어벽체가 부담하는 골조 및 자중 전달용 가설기둥의 접합구조를 이용하여 시공층 바닥슬래브 직하부층의 코어벽체가 완료되기 전부터 지상층 골조공사를 할 수 있도록 하여 공사기간을 단축할 수 있는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물 및 이를 이용한 공기단축형 역타공법에 관한 것이다.The present invention relates to the underground core wall side reverse hammering temporary column and the above ground floor frame load using the joint structure of the core wall for the early start of the upper layer after completing the construction layer slab, which is the floor for loading excavation equipment and materials when applying the reverse drilling method in the downtown area It relates to an air-shortened reverse rudder structure using a temporary pole for transmission and a shortened air piercing method using the same, and more particularly, to a temporary reverse rudder column installed at the location where the core wall of the lower layer of the slab in the construction layer will be constructed, and a frame borne by the core wall of the ground floor and By using the joint structure of temporary columns for self-weight transfer, it is possible to shorten the construction period by enabling the above-ground framing work to be performed even before the core wall of the floor directly below the floor slab is completed, thereby reducing the construction period. It relates to an air shortening type reverse punching structure using a temporary post for transmission and a short air type reverse punching method using the same.

일반적으로 건축물의 축조 시 종래에는 가설흙막이 없이 굴토완료후 구조체를 축조하는 Open Cut 방식이나 지하외부 벽체(가설흙막이 또는 지중연속벽)을 선시공한후 수평 토압지지용 가설재(스트러트 및 Earth Anchor)의 설치와 굴토공사를 반복하면서 굴토 완료후 하부층에서 시작하여 상부층의 순서로 진행하여 순타공법과는 달리, 탑다운 공법은 건축물 시공이 상부에서 하부로의 방향으로도 가능하게 되었다.In general, when constructing a building, the open cut method of constructing the structure after excavation is completed without a temporary retaining membrane or the installation of a horizontal earth pressure support temporary material (strut and earth anchor) after pre-construction of an external underground wall (temporary retaining wall or underground continuous wall) After excavation is completed, the top-down construction method can be constructed in a direction from the top to the bottom, unlike the straight drilling method, which starts from the lower layer and proceeds in the order of the upper layer by repeating the excavation and excavation work.

여기서, 탑다운 공법이란 굴착공사 이전에 지하외부 벽체(가설흙막이 또는 지중연속벽)와 지하층 기둥 그리고 기둥을 지지하는 현장타설말뚝을 선행으로 시공한 후, 단계별로 지하층 슬래브와 굴토공사를 위에서 아래로 반복해 가면서 지하구조물을 형성하여 토압을 지지하는 공법이다. 이 공법은 기존의 순타공법으로는 계획하기 어려운 대단면, 대심도 굴착이나 인접 건물이 많은 도심지 구간에서 안정적으로 적용할 수 있으며, 바닥슬래브가 선 시공되기(시공층) 때문에 작업장의 조기확보가 가능하여 강우 및 강설시에도 시공할 수 있는 전천후 공법이라고 할 수 있다. Here, the top-down method refers to the construction of the external underground wall (temporary retaining wall or continuous underground wall), the underground column, and the cast-in-place pile supporting the column before excavation work, and then the basement slab and excavation work are carried out step by step from top to bottom. It is a construction method that supports earth pressure by repeatedly forming underground structures. This construction method can be stably applied to large-scale excavation, deep excavation, or downtown areas with many adjacent buildings, which are difficult to plan with the conventional drilling method. Therefore, it can be said that it is an all-weather construction method that can be installed even in rain and snow.

또한, 탑다운 공법은 지하공사와 지상공사가 병행하여 진행될 수 있기 때문에 공기를 공기를 단축하는 측면에서 유리할 수 있는데, 이는 지하층 굴토 및 골조공사가 진행되는 동안 필요한 시점에 지상층을 조기에 착수하여 지하와 지상층을 병행하여 진행할 수 있기 때문이다. 그리고 지상층 골조는 시공방법에 따라 코어선행 동시타설 외주부선행(또는 코어후행)으로 구분할 수 있으나, 반드시 기둥과 코어 그리고 바닥슬래브가 동시에 또는 순차적으로 시공되어야 한다.In addition, the top-down method can be advantageous in terms of shortening the construction period because the underground construction and the above-ground construction can be carried out in parallel. This is because it can proceed concurrently with the ground floor. In addition, the above-ground structure can be divided into core leading simultaneous casting, outer perimeter leading (or core trailing) depending on the construction method, but the columns, the core, and the floor slab must be constructed simultaneously or sequentially.

한편, 탑다운 공법은 굴착공사 이전에 지하외부 벽체와 지하층 기둥을 선행으로 시공한 후 단계별로 굴착과 지하층 슬래브 구조물을 형성할 수 있으나, 지하층 수직부재인 코어벽체는 역타 시 작업장 바닥슬래브와 그 하부층 슬래브가 완료된 이후에 1개층 정도가 시공될 수 있고 굴토공사 및 최하부층 바닥인 기초가 완료된 이후 일정 기간이 지난 이후에 코어벽체가 수직으로 연결되어 완성될 수 있으므로 이 기간동안의 하중전달을 위해 코어 벽체측에는 반드시 역타용 임시기둥이 필요하게 된다. On the other hand, in the top-down method, it is possible to construct the underground outer wall and the basement column in advance before excavation, and then excavate and form the basement slab structure step by step. About one floor can be constructed after the slab is completed, and the core wall can be vertically connected and completed after a certain period of time has elapsed after excavation work and the foundation, which is the lowest floor, is completed. Temporary poles for back-beating are absolutely necessary on the wall side.

그런데, 종래의 탑다운 방식은 대부분의 건축물이 지하 층수에 비해 지상 층수가 크기 때문에 지상층부의 시공을 최대한 빨리 시작하는 것이 건설공사의 공기 단축 측면에서 유리함에도 불구하고, 역타시 작업장 완료후 바로 지상층 골조공사를 착수하지 못하고 직하부층 코어벽체가 완성되어야 진행할 수 있어 공기단축이 어려운 문제점이 있었다. However, in the conventional top-down method, since most buildings have a larger number of above-ground floors compared to the number of underground floors, starting the construction of the above-ground part as soon as possible is advantageous in terms of shortening the construction period. There was a problem in that it was difficult to shorten the construction period because the frame work could not be started and the core wall directly below the floor had to be completed.

다시 말해, 지하층 시공에 탑다운 공법을 적용하여 지상층과 동시시공을 시작하기 위해서는 일반적으로 제일 먼저 역타시 작업장 완료후 직하부층에 코어벽체를 시공해야 한다. 이를 위해서는 먼저 작업장용 바닥슬래브를 시공하고 직하부 굴토후 또는 직하부층 바닥을 시공한 후 코어벽체를 1개층 시공하여야 하고, 이로부터 지상층 골조의 코어벽체를 연결하여 시공할 수 있게 된다. In other words, in order to apply the top-down method to the underground floor construction and start simultaneous construction with the above-ground floor, in general, first, the core wall should be installed on the lower floor after the work site is completed. To do this, first construct the floor slab for the workshop, and then construct one layer of the core wall after the excavation of the direct lower part or the floor of the lower layer directly below it.

등록특허공보 제10-1014796호 (2011.02.15 공고)Registered Patent Publication No. 10-1014796 (published on February 15, 2011)

본 발명은 지하층 시공에 탑다운 공법을 적용하는 경우, 하부층 코어벽체의 시공이 완료되지 않아도 지하층과 지상층 골조공사를 동시에 시작하여 건설공사의 공기를 단축할 수 있도록, 지상층 코어벽체의 하중이 지하층 코어벽체측 역타용 가설기둥으로 전달될 수 있도록 지상층 코어벽체에 설치되는 가설기둥의 접합구조를 이용한 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물 및 이를 이용한 공기단축형 역타공법을 제공하는 것을 목적으로 한다.In the present invention, when the top-down method is applied to the basement construction, the load of the above-ground core wall is reduced to reduce the construction period by starting the basement and above-ground framing work at the same time even if the construction of the lower-level core wall is not completed. Shortened air turning type using a junction structure of temporary columns installed on the above-ground core wall so that it can be transmitted to a wall-side reverse striking temporary column and a temporary reverse striking temporary column on the wall side of the basement floor and a temporary column for transmitting the frame load on the ground floor, and an air shortening type using the same The purpose is to provide a reverse punching method.

본 발명의 일 측면에 의하면, 본 발명은 코어 벽체에 인접하게 세워지는 가설기둥과; 일단부는 상기 가설기둥에 접합되고 타단부는 상기 코어 벽체에 정착되어, 상기 가설기둥과 상기 코어 벽체를 서로 연결시키는 연결부;를 포함하되, 상기 가설기둥은, 상기 코어 벽체 시공 전 설치되되 하단부는 지하층 바닥에 매립 설치되고, 상부는 지상층 수평부재와 접합되어 상단부가 지상층 천정 상부까지 연장되어 세워지는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물을 제공할 수 있다.According to one aspect of the present invention, the present invention is a temporary pillar erected adjacent to the core wall; One end is joined to the temporary pole and the other end is fixed to the core wall, and a connection part for connecting the temporary pole and the core wall to each other; includes, wherein the temporary pole is installed before the core wall construction, and the lower end is the basement floor Installed buried in the floor, the upper part is joined to the horizontal member of the ground floor, and the upper part is extended to the upper part of the ceiling of the ground floor and erected. can provide

여기서, 상기 가설기둥은, 절단 가능한 I빔 또는 H빔을 적용할 수 있다.Here, the temporary pillar, a cuttable I-beam or H-beam can be applied.

또한, 상기 연결부는, 일측이 상기 가설기둥에 접합되는 연결부재와, 일측은 상기 연결부재의 타측에 접합되고, 타측은 상기 코어 벽체에 정착되는 정착부재를 포함하여 구성될 수 있다.In addition, the connecting portion may include a connecting member having one side joined to the temporary pole, one side joined to the other side of the connecting member, and a fixing member fixed to the core wall at the other end.

이때, 상기 연결부재는, I빔, H빔, 평판 및 T바 중 선택된 어느 하나의 부재로 형성될 수 있다.In this case, the connecting member may be formed of any one member selected from an I-beam, an H-beam, a flat plate, and a T-bar.

또한, 상기 정착부재는, I빔, H빔 및 복수개의 스터드볼트들 중 중 선택된 어느 하나의 부재로 형성될 수 있다.Also, the fixing member may be formed of any one member selected from among an I-beam, an H-beam, and a plurality of stud bolts.

나아가, 상기 정착부재는, I빔 또는 H빔으로 형성되고, 상기 I빔 또는 H빔의 플랜지의 양측으로 복수개의 정착 스터드볼트들이 결합될 수 있다.Furthermore, the fixing member may be formed of an I-beam or an H-beam, and a plurality of fixing stud bolts may be coupled to both sides of a flange of the I-beam or the H-beam.

한편, 상기 연결부는, 일측이 상기 가설기둥에 접합되고, 타측은 상기 코어 벽체를 향하여 연장되어 상기 코어 벽체 내부에 정착되는 정착연결부재를 포함하여 구성될 수 있다.On the other hand, the connection part, one side is joined to the temporary pillar, the other side may be configured to include a fixing connection member extending toward the core wall is fixed inside the core wall.

여기에서, 상기 정착연결부재는, 복수개의 스터드볼트들을 포함하여 구성될 수 있다. Here, the fixing connection member may be configured to include a plurality of stud bolts.

한편, 상기 가설기둥은, 지상층 수평부재와 접합되는 상부 접합영역과, 상기 수평부재와 접합되지 않는 노출영역을 포함하여, 완공 전 상기 노출영역은 절단할 수 있다.On the other hand, the temporary pillar, including an upper junction area joined to the ground level horizontal member, and an exposed area not joined to the horizontal member, the exposed area can be cut before completion.

본 발명의 다른 측면에 의하면, 본 발명은 (a) 지하층 바닥에서 지상층 천정 상부까지 길이를 갖는 가설기둥을 준비하고, 상기 가설기둥을 지반을 천공하여 건축물의 코어 벽체가 설치될 위치에 인접하게 세워 설치하는 단계와; (b) 일측이 상기 가설기둥에 접합되고 타측이 상기 코어 벽체에 매립 정착되는 연결부를 상기 가설기둥에 접합하여 연결하는 단계와; (c) 상기 연결부가 매립되도록 상기 코어 벽체를 설치하는 단계와; (d) 상기 건축물의 완공 전 상기 가설기둥의 일부를 절단하여 마무리하는 단계;를 포함하는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타공법을 제공할 수 있다.According to another aspect of the present invention, the present invention (a) prepare a temporary post having a length from the floor of the basement to the upper part of the ceiling of the ground floor, and drill the temporary post in the ground to erect it adjacent to the location where the core wall of the building will be installed installing; (b) connecting a connection part having one side joined to the temporary pillar and the other side buried and fixed in the core wall by bonding to the temporary pillar; (c) installing the core wall so that the connection part is buried; (d) cutting and finishing a part of the temporary pillar before the completion of the building; providing an air shortening type reverse drilling method using the underground core wall side reverse striking temporary pillar and the ground floor frame load transmission temporary pillar, characterized in that it includes can do.

여기서, 상기 가설기둥은, 절단 가능한 I빔 또는 H빔을 적용하고, 상기 (d) 단계의 마무리는, 상기 가설기둥에서 상기 건축물의 수평부재와 접합되지 않는 상기 가설기둥의 노출영역을 절단하여 구성될 수 있다.Here, the temporary pillar is configured by applying a cuttable I-beam or H-beam, and finishing the step (d) by cutting the exposed area of the temporary pillar that is not joined to the horizontal member of the building in the temporary pillar. can be

한편 본 명세서에 개시된 기술에 관한 설명은 단지 구조적 내지 기능적 설명을 위한 실시예에 불과하므로, 개시된 기술의 권리범위는 본문에 설명된 실시예에 의하여 제한되는 것으로 해석되어서는 아니 된다. 즉, 실시예는 다양한 변경이 가능하고 여러 가지 형태를 가질 수 있으므로 개시된 기술의 권리범위는 기술적 사상을 실현할 수 있는 균등물들을 포함하는 것으로 이해되어야 한다. 또한, 개시된 기술에서 제시된 목적 또는 효과는 특정 실시예가 이를 전부 포함하여야 한다거나 그러한 효과만을 포함하여야 한다는 의미는 아니므로, 개시된 기술의 권리범위는 이에 의하여 제한되는 것으로 이해되어서는 아니 될 것이다.On the other hand, since the description of the technology disclosed in this specification is merely an embodiment for structural or functional description, the scope of the disclosed technology should not be construed as being limited by the embodiment described in the text. That is, since the embodiment may have various changes and may have various forms, it should be understood that the scope of the disclosed technology includes equivalents capable of realizing the technical idea. In addition, since the object or effect presented in the disclosed technology does not mean that a specific embodiment should include all of them or only such effects, it should not be understood that the scope of the disclosed technology is limited thereby.

또한 본 발명에서 서술되는 용어의 의미는 다음과 같이 이해되어야 할 것이다. "제1", "제2" 등의 용어는 하나의 구성요소를 다른 구성요소로부터 구별하기 위한 것으로, 이들 용어들에 의해 권리범위가 한정되어서는 아니 된다. 예를 들어, 제1 구성요소는 제2 구성요소로 명명될 수 있고, 유사하게 제2 구성요소로 제1 구성요소로 명명될 수 있다.In addition, the meaning of the terms described in the present invention should be understood as follows. Terms such as “first” and “second” are for distinguishing one component from another, and the scope of rights should not be limited by these terms. For example, a first component may be termed a second component, and similarly a second component may be termed a first component.

나아가 어떤 구성요소가 다른 구성요소에 "연결되어"있다고 언급된 때에는, 그 다른 구성요소에 직접적으로 연결될 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떤 구성요소가 다른 구성요소에 "직접 연결되어"있다고 언급된 때에는 중간에 다른 구성요소가 존재하지 않는 것으로 이해되어야 할 것이다. 한편, 구성요소들 간의 관계를 설명하는 다른 표현들, 즉 "~사이에"와 "~사이에" 또는 "~에 이웃하는"과 "~에 직접 이웃하는" 등도 마찬가지로 해석되어야 한다.Furthermore, when it is mentioned that a certain element is "connected" to another element, it may be directly connected to the other element, but it should be understood that other elements may exist in between. On the other hand, when it is mentioned that a certain element is "directly connected" to another element, it should be understood that the other element does not exist in the middle. On the other hand, other expressions describing the relationship between elements, that is, "between" and "between" or "neighboring to" and "directly adjacent to", etc., should be interpreted similarly.

단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한 복수의 표현을 포함하는 것으로 이해되어야 하고, "포함하다"또는 "가지다" 등의 용어는 설시된 특징, 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것이 존재함을 지정하려는 것이며, 하나 또는 그 이상의 다른 특징이나 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.The singular expression is to be understood to include the plural expression unless the context clearly dictates otherwise, and terms such as "comprises" or "have" refer to the specified feature, number, step, action, component, part or these It is intended to indicate that a combination exists, and it should be understood that it does not preclude the possibility of the existence or addition of one or more other features or numbers, steps, operations, components, parts, or combinations thereof.

본 발명에 따른 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물 및 이를 이용한 공기단축형 역타공법은 코어벽체와 인접하게 가설기둥과 연결부를 설치하고 이를 통해 지하 1층 코어의 시공이 완료되기 전부터 지상층의 시공을 시작할 수 있기 때문에 건축 공사의 공기를 효과적으로 단축시킬 수 있으며, 완공 후 가설기둥과 연결부의 일부가 건축물에 구조적인 지지역할을 할 수 있는 효과를 제공할 수 있다.According to the present invention, the air shortening type reverse rudder structure using the underground core wall side reverse striking temporary pillar and the above ground floor frame load transmission temporary pillar and the air shortening type reverse punching method using the same are installed adjacent to the core wall and a temporary pillar and a connection part, and through this, the first basement floor Because the construction of the ground floor can start before the construction of the core is completed, the construction period can be effectively shortened, and after completion, the temporary column and part of the connecting part can provide a structural support to the building. have.

도 1은 본 발명의 실시예에 따른 공기단축형 역타구조물의 구성을 나타내는 정면도이다.
도 2는 도 1의 "A"선에 의한 단면도이다.
도 3은 본 발명의 실시예에 따른 공기단축형 역타구조물이 복수층에 대하여 시공된 상태를 나타내는 정단면도이다.
도 4는 도 3의 "1"선에 대한 단면도이다.
도 5는 도 4의 "a"선에 대한 단면도이다.
도 6은 도 4의 "b"선에 대한 단면도이다.
도 7은 본 발명의 실시예에 따른 공기단축형 역타구조물에서 정착연결부가 설치된 다른 실시예를 나타내는 평면도이다.
도 8은 도 7의 "a"선에 대한 단면도이다.
도 9는 도 7의 "b"선에 대한 단면도이다.
도 10은 본 발명의 실시예에 따른 공기단축형 역타구조물이 복수층에 대하여 시공된 다른 실시예를 나타내는 정면도이다.
도 11 및 도 12는 본 발명의 실시예에 따른 공기단축형 역타구조물에서 가설기둥과 벽체 수평근의 상태를 나타내는 평면도이다.
1 is a front view showing the configuration of an air shortening type reverse rudder structure according to an embodiment of the present invention.
FIG. 2 is a cross-sectional view taken along line “A” of FIG. 1 .
3 is a front cross-sectional view showing a state in which the air shortening type reverse rudder structure according to an embodiment of the present invention is constructed for multiple layers.
FIG. 4 is a cross-sectional view taken along line “1” of FIG. 3 .
FIG. 5 is a cross-sectional view taken along line “a” of FIG. 4 .
6 is a cross-sectional view taken along line “b” of FIG. 4 .
7 is a plan view showing another embodiment in which the fixing connection part is installed in the air shortening type reverse rudder structure according to an embodiment of the present invention.
FIG. 8 is a cross-sectional view taken along line “a” of FIG. 7 .
9 is a cross-sectional view taken along line “b” of FIG. 7 .
10 is a front view showing another embodiment in which the air shortening type reverse rudder structure according to an embodiment of the present invention is constructed for a plurality of floors.
11 and 12 are plan views showing the state of temporary pillars and wall horizontal roots in the air shortening type reverse rudder structure according to an embodiment of the present invention.

이하에서는 본 발명에 대하여 보다 구체적으로 이해할 수 있도록 첨부된 도면을 참조한 바람직한 실시 예를 들어 설명하기로 한다. Hereinafter, a preferred embodiment will be described with reference to the accompanying drawings so that the present invention may be understood in more detail.

먼저, 본 발명의 실시예에 따른 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물(이하 '공기단축형 역타구조물'이라 한다)는, 지하층의 코어 시공이 완료되기 전부터 지상층의 시공을 시작할 수 있어 건축 공사의 전체 공기를 단축할 수 있어 경제적인 시공이 가능한 시공구조를 제공할 수 있다. First, according to an embodiment of the present invention, the air shortening type reverse striking structure (hereinafter referred to as 'air shortened type reverse striking structure') using the underground core wall side reverse striking temporary pillar and the above-ground structural load transmission temporary pillar is completed before the core construction of the basement floor is completed. Since the construction of the above-ground floor can be started from before, the overall construction period can be shortened, thereby providing an economical construction structure.

이를 위해, 본 발명의 공기단축형 역타구조물은, 도 1 및 도 2에 도시된 바와 같이 가설기둥(100)과, 연결부(200)를 포함하여 구성될 수 있다.To this end, the air shortened inverted structure of the present invention may be configured to include a temporary pillar 100 and a connecting portion 200 as shown in FIGS. 1 and 2 .

먼저, 가설기둥(100)은, 건축물의 평면 설계상에 있어 설치되는 코어 벽체(10)에 대하여 인접하게 세워진다. First, the temporary pillar 100 is erected adjacent to the core wall 10 installed in the plan design of the building.

이때, 가설기둥(100)은, 본 발명의 탑다운 시공에 있어서 지하층과 지상층의 코어 벽체(10)를 비롯한 수평부재(20)의 설치를 위한 기둥 역할을 하는 것으로, 후술되는 바와 같이 코어 벽체(10)와 수평부재(20)(슬래브, 보 등)의 시공 전 설치된 후 이들 코어 벽체(10)의 시공이 완료되기 전 일정 구역 절단될 수 있다. At this time, the temporary pillar 100 is to serve as a pillar for the installation of the horizontal member 20 including the core wall 10 of the basement and above-ground floors in the top-down construction of the present invention, and as will be described later, the core wall ( 10) and the horizontal member 20 (slabs, beams, etc.) can be cut in a certain area after installation before construction is completed and before construction of these core walls 10 is completed.

이 때문에, 가설기둥(100)은, 절단 가능한 I빔 또는 H빔이 적용되는 것이 바람직하며, 가설기둥(100) 부재의 단면적 또는 크기는 다양하게 변경 가능하다. For this reason, the temporary pillar 100 is preferably a cuttable I-beam or H-beam applied, and the cross-sectional area or size of the temporary pillar 100 member can be variously changed.

여기서, 가설기둥(100)은, 코어 벽체(10) 시공 전 설치되되 하단부는 지하층 바닥에 매립 설치되고, 상부는 지상층 수평부재(20)와 접합되어 상단부가 최소한 지상층 1층 천정 이상의 상부까지 연장되어 세워질 수 있다.Here, the temporary pillar 100 is installed before the core wall 10 construction, and the lower end is buried in the basement floor, and the upper part is joined to the ground level horizontal member 20 so that the upper end extends to at least the upper part of the first floor above the ceiling. can be built

한편, 가설기둥(100)은, 지상층 수평부재(20)와 접합되는 상부 접합영역과, 수평부재(20)와 접합되지 않는 노출영역을 포함할 수 있으며, 이중 노출영역은 완공 전 절단되어 마무리될 수 있다. 이에 대한 세부내용은 후술되는 시공방법에서 살펴보기로 한다. On the other hand, the temporary pillar 100 may include an upper junction area joined to the above ground level horizontal member 20 and an exposed area that is not joined to the horizontal member 20, and the double exposed area is to be cut and finished before completion. can The details of this will be looked at in the construction method to be described later.

연결부(200)는, 일단부는 가설기둥(100)에 접합되고 타단부는 코어 벽체(10)에 정착되어, 가설기둥(100)과 코어 벽체(10)를 서로 연결시키는 역할을 한다. The connection part 200, one end is joined to the temporary pillar 100 and the other end is fixed to the core wall 10, serves to connect the temporary pillar 100 and the core wall 10 to each other.

세부적으로, 연결부(200)는, 일측이 가설기둥(100)에 접합되는 연결부재(220)와, 일측은 연결부재(220)의 타측에 접합되고, 타측은 코어 벽체(10)에 정착되는 정착부재(210)를 포함하여 구성될 수 있다.In detail, the connection part 200 has a connection member 220 having one side bonded to the temporary pole 100 , and one side bonding to the other side of the connection member 220 , and the other side is fixed to the core wall 10 . The member 210 may be included.

이때, 연결부재(220)는, 전술한 가설기둥(100)과 마찬가지로 절단가능한 부재가 사용되는 것이 바람직하며, 세부적으로는 웨브가 가설기둥(100)에 접합되는 I빔, H빔, 평판 및 T바 중 선택된 어느 하나의 부재로 형성될 수 있다. 이때, 연결부재(220)는, At this time, the connecting member 220, like the above-mentioned temporary pillar 100, it is preferable that a cuttable member is used, in detail, the web is joined to the temporary pillar 100 I-beam, H-beam, flat plate and T It may be formed of any one member selected from among the bars. At this time, the connecting member 220,

정착부재(210)는, EC(Erection Column)에 해당하는 것으로 볼 수도 있으며, 이후 시공되는 코어 벽체(10) 내부에 위치하도록 코어 벽체(10)와 대응되는 위치에 배치될 수 있다.The fixing member 210 may be viewed as corresponding to an Erection Column (EC), and may be disposed at a position corresponding to the core wall 10 so as to be located inside the core wall 10 to be constructed thereafter.

정착부재(210)는, I빔, H빔 및 복수개의 스터드볼트들 중 중 선택된 어느 하나의 부재로 형성될 수 있다.The fixing member 210 may be formed of any one member selected from among an I-beam, an H-beam, and a plurality of stud bolts.

이때, 정착부재(210)는, I빔 또는 H빔(211)으로 형성된 경우, 코어 벽체(10) 내 견고한 정착을 위하여 I빔 또는 H빔의 플랜지의 양측으로 복수개의 정착 스터드볼트(212, 도 4 참조)들이 결합될 수 있다.At this time, when the fixing member 210 is formed of an I-beam or an H-beam 211, a plurality of fixing stud bolts 212, FIG. 4) can be combined.

정착부재(210)는, 도시된 바와 같이 소정 높이에서부터 상측 방향을 따라 배치될 수 있지만 이에 한정되는 것은 아니며, 도시 하지 않았지만 지면에 닿을 수도 있고 그 아래까지 연장될 수도 있다. The fixing member 210 may be disposed along the upward direction from a predetermined height as shown, but is not limited thereto, and although not shown, may contact the ground or extend below it.

한편, 상기와는 달리 연결부(200)는, 일측이 가설기둥(100)에 접합되고, 타측은 코어 벽체(10)를 향하여 연장되어 코어 벽체(10) 내부에 정착되는 정착연결부재(230)를 포함하여 구성될 수 있다.On the other hand, unlike the above connection part 200, one side is joined to the temporary post 100, the other side is extended toward the core wall 10, the fixing connection member 230 fixed inside the core wall 10. may be included.

이러한 경우 정착연결부재(230)는, 도시된 바와 같이 복수개의 스터드볼트들을 포함하여 구성될 수 있으며(도 7참조), 전술한 정착부재(210)와 연결부재(220)를 포함하는 실시예에서 연결부재(220)가 생략된 것으로도 볼 수 있다. In this case, the fixing connection member 230 may be configured to include a plurality of stud bolts as shown (see FIG. 7 ), and in the embodiment including the fixing member 210 and the connection member 220 described above It can also be seen that the connection member 220 is omitted.

이하에서는, 도면을 참조하여 본 발명의 공기단축형 역타구조물에 대하여 상세하게 살펴보기로 한다.Hereinafter, with reference to the drawings, it will be described in detail with respect to the air shortening type reverse rudder structure of the present invention.

도 3은 본 발명의 실시예에 따른 공기단축형 역타구조물을 개념적으로 나타내는 단면도이고, 도 4는 도 3의 "1" 선에 대한 단면도이고, 도 5는 도 4의 "a" 선에 대한 단면도이며, 도 6은 도 4의 "b"선에 대한 단면도이다. 도 7은 도 3의 "2" 부위에 대한 단면도이다.3 is a cross-sectional view conceptually illustrating an air shortening type inverse rudder structure according to an embodiment of the present invention, FIG. 4 is a cross-sectional view taken along line “1” in FIG. 3, and FIG. 5 is a cross-sectional view taken along line “a” in FIG. , FIG. 6 is a cross-sectional view taken along line “b” of FIG. 4 . FIG. 7 is a cross-sectional view of a region “2” of FIG. 3 .

먼저, 도 3은 건축물의 지상 1층, 2층, 3층에 대한 구조를 예시적으로 나타낸 것으로서, 도 4 및 도 5에 도시된 바와 같이 가설기둥(100)의 양측에는 수평부재(31,40,수평빔)과 교차하는 방향으로 연장하는 별도의 수평부재(30)가 접합될 수 있다. First, FIG. 3 exemplarily shows the structure for the first, second, and third floors of a building, and as shown in FIGS. 4 and 5 , on both sides of the temporary pillar 100 , the horizontal members 31 and 40 , horizontal beam) and a separate horizontal member 30 extending in the intersecting direction may be joined.

도 6은 이러한 수평 부재를 코어 벽체(10)에 정착하기 위한 구조를 나타내고 있으며, 도 7은 본 발명의 공기단축형 역타구조물에서 정착연결부가 가설기둥(100)에 직접 접합 연결된 경우를 나타낸 도면으로, 도 3과는 달리 연결부재(220)의 구성이 생략 가능하다. 6 shows a structure for fixing such a horizontal member to the core wall 10, and FIG. 7 is a view showing a case in which the fixing connection part is directly connected to the temporary post 100 in the air shortening type reverse rudder structure of the present invention. Unlike FIG. 3 , the configuration of the connecting member 220 may be omitted.

이러한 경우, 공기단축형 역타구조물은 가설기둥(100)의 상부로 갈수록 가설기둥(100)이 부담해야 하는 하중은 감소할 것이므로, 가설기둥(100)을 코어 벽체(10)에 접합하기 위한 자재의 양이 저층에 비해 감소될 수 있기 때문에 정착연결부로도 시공이 가능하다. In this case, in the case of the air shortened inverted structure, the load to be borne by the temporary pole 100 will decrease as it goes to the upper part of the temporary pole 100 , so the amount of material for joining the temporary pole 100 to the core wall 10 . Since it can be reduced compared to the lower floor, it can be constructed as a fixing connection part.

도 8 및 도 9는 도 3의 "2"선에 대한 단면을 상세하게 나타낸 도면으로, 상층부에 가설부재에 정착연결부재(230)로서 스터드볼트들이 접합되어 가설기둥(100)과 코어 벽체(10)에 매립 설치되며, 도 9에 도시된 바와 같이 다양한 형상의 보강철근이 배근될 수 있다. 여기서, 도 8의 해칭된 부분은 완공 전 절단될 노출영역을 나타낸 것으로서 가설기둥(100)과 연결부(200)의 노출부분이 절단되면 도 9에 나타난 바와 같이 된다.8 and 9 are views showing in detail a cross-section taken along the line "2" of FIG. 3, in which stud bolts are joined as a fixing connection member 230 to a temporary member in the upper layer, and the temporary pillar 100 and the core wall 10 ), and as shown in FIG. 9, reinforcing bars of various shapes can be reinforced. Here, the hatched portion of FIG. 8 represents an exposed area to be cut before completion, and when the exposed portion of the temporary pillar 100 and the connecting portion 200 is cut, it becomes as shown in FIG. 9 .

도 10은 본 발명의 공기단축형 역타구조물이 건축물에 다른 실시예로 시공된 구조를 예시적으로 나타낸 도면으로 건축물의 지하층에 대한 구조를 나타내고 있다. FIG. 10 is a view exemplarily showing a structure in which the air shortening type inverse rudder structure of the present invention is constructed in another embodiment on a building, and shows the structure of the basement of the building.

이를 살펴보면, 공기단축형 역타구조물은 정착부재(210)가 복수의 스터드볼트들로 구성되어 있으며, 연결부재(220)는 웨브가 가설기둥(100)에 접합된 T바 형태로 구성되며, 도 3에서와는 달리 가설기둥(100)의 상부로 갈수록 가설기둥(100)이 부담해야 하는 하중은 감소하는데, 이에 가설기둥(100)의 하부로 갈수록 코어 벽체(10)를 포함하여 건축물 자체의 내력 구조가 완성되어 가므로 가설기둥(100)이 부담해야 하는 하중은 고층에 비해 감소될 수 있으므로, 필요에 따라 가설기둥(100), 연결부재(220) 및 정착부재(210)의 형태 및 치수는 다양하게 변경될 수 있다.Looking at this, in the air shortening type reverse rudder structure, the fixing member 210 is composed of a plurality of stud bolts, and the connecting member 220 is composed of a T-bar shape in which the web is joined to the temporary post 100, and in FIG. On the other hand, the load to be borne by the temporary pole 100 decreases as it goes to the upper part of the temporary pole 100, and the load-bearing structure of the building itself, including the core wall 10, is completed as it goes to the lower part of the temporary pole 100. Therefore, the load to be borne by the temporary pillar 100 can be reduced compared to the high-rise, so the shape and dimensions of the temporary pillar 100, the connecting member 220 and the fixing member 210 can be variously changed as needed. can

도 11 및 도 12는 본 발명의 실시예에 따른 공기단축형 역타구조물에서 가설기둥(100)과 벽체 수평근의 상태를 나타내는 평면도이다. 도 11 및 도 12를 참조하면, 본 발명의 공기단축형 역타구조물은 가설기둥(100)과 코어 벽체(10)가 접합되는 위치에서 견고한 접합 및 불연속화되는 수평철근의 성능 보완을 위해 다양한 형태의 보강 철근 등이 부가적으로 추가될 수 있다.11 and 12 are plan views showing the state of the temporary pillar 100 and the wall horizontal root in the air shortening type reverse rudder structure according to an embodiment of the present invention. 11 and 12 , the air shortened reverse rudder structure of the present invention is reinforced in various forms to complement the performance of the horizontal reinforcing bars that are rigidly joined and discontinued at the location where the temporary column 100 and the core wall 10 are joined. Reinforcing bars and the like may be additionally added.

이하에서는, 본 발명의 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타공법(이하 '공기단축형 역타공법'이라 한다)에 대하여 살펴보기로 한다.Hereinafter, an air shortening type reverse punching method (hereinafter referred to as an 'air shortening type reverse punching method') using the underground core wall side reverse punching temporary pillar and the above ground floor frame load transmission temporary pillar of the present invention will be looked at.

먼저 이에 앞서 본 발명의 공기단축형 역타공법은, 일반적인 탑다운 공법에서는 가설기둥(100)을 이용하여 지하 1층의 코어를 먼저 시공하고 지하 1층 코어로부터 상하로 시공을 진행되므로, 가설기둥(100)은 지상 1층 바닥면 위로 대략 1 미터 정도의 여장만이 돌출되는데, 본 발명의 실시예에서는 이와 달리 가설기둥(100)이 최소한 1층 천정 이상의 높이까지 연장된다. 이에, 가설기둥(100)에 직접 수평빔을 연결하여 곧바로 지상 1층의 보 및 슬래브 설치를 시작하기 위한 것인데, 지상 1층의 높이에서는 아직 큰 하중을 부담할 필요가 없기 때문으로 이러한 시공이 가능하다.First of all, in the air shortening reverse drilling method of the present invention, in the general top-down construction method, the core of the first basement is first constructed using the temporary pillar 100 and the construction proceeds up and down from the first basement core, so the temporary pillar 100 ), only about 1 meter of women's clothing protrudes above the floor surface of the first floor above the ground. In contrast, in the embodiment of the present invention, the temporary pillar 100 extends to a height of at least the ceiling of the first floor. Therefore, this is to directly connect the horizontal beam to the temporary pillar 100 and start the installation of the beam and slab on the first floor, since there is no need to bear a large load yet at the height of the first floor. do.

본 발명의 공기단축형 역타공법은, 우선 건축물을 시공하기 위하여 통상의 흙막이 벽체 설치 작업한 후, 지하층 바닥에서 지상층 천정 상부까지 길이를 갖는 가설기둥(100)을 준비한다. 이때, 가설기둥(100)은 지하층 바닥에서 지정된 지상층의 천정 상부까지의 설정 길이로 공장 또는 현장에서 제작될 수 있으며, 도시된 바와 같이 3층 상부까지 연장되게 준비될 수 있다. In the air shortening reverse drilling method of the present invention, a temporary retaining wall 100 having a length from the floor of the basement floor to the upper part of the ceiling of the ground floor is prepared after a normal retaining wall installation work is first performed in order to construct a building. At this time, the temporary pillar 100 may be manufactured in a factory or on-site with a set length from the floor of the basement floor to the upper part of the ceiling of the specified ground floor, and may be prepared to extend to the upper part of the third floor as shown.

가설기둥(100)은 전술한 바와 같이 아래로는 지하층의 제일 낮은 층 아래까지 연장되고, 위로는 설계된 소정의 층까지 연장될 수 있다. 가령, 가설기둥(100)은 필요에 따라 지상 3층의 천정 높이까지 연장될 수 있으나 이에 한정되는 것은 아니며, 더 높은 층 또는 더 낮은 층까지 연장될 수도 있다. As described above, the temporary pillar 100 extends down to the lowest level of the basement, and may extend up to a predetermined level designed above. For example, the temporary pillar 100 may extend to the ceiling height of the third floor above the ground as needed, but is not limited thereto, and may extend to a higher or lower floor.

이렇게 가설기둥(100)이 준비되면, 코어 벽체(10)가 설치될 위치에 대하여 설정 이격거리로 인접한 가설기둥(100) 설치될 위치에 지반을 천공하여 가설기둥(100)을 세워 설치한다. When the temporary pillar 100 is prepared in this way, the temporary pillar 100 is erected and installed by drilling the ground at the location where the temporary pillar 100 adjacent to the location where the core wall 10 is to be installed by a set separation distance.

이때, 지반을 천공하는 작업에는 PRD(Percussion Rotary Drilling), RCD(Reverse Circulation Drilling) 등을 포함하여 다양한 방법이 사용될 수 있다. At this time, various methods may be used for drilling the ground, including percussion rotary drilling (PRD), reverse circulation drilling (RCD), and the like.

다음으로, 가설기둥(100)에 연결부(200)를 연결 설치한다. 이때, 연결부(200)는, 일측이 가설기둥(100)에 접합되고 타측이 코어 벽체(10)에 매립 정착되는 구성으로, 연결부재(220)와 정착부재(210)를 포함하는 구성 또는 연결부재(220)와 정착부재(210)가 일체로 형성된 정착연결부를 적용할 수 있다. Next, the connection part 200 is connected to the temporary pillar 100 and installed. At this time, the connection part 200 has a configuration in which one side is joined to the temporary pillar 100 and the other side is embedded and fixed in the core wall 10 , and a configuration or a connection member including a connection member 220 and a fixing member 210 . (220) and the fixing member 210 may be applied to the fixing connection formed integrally.

한편, 현장에서 연결부(200)의 접합 설치는, 전에 연결부재(220)와 정착부재(210)를 서로 접합시키거나 일체형으로 제작하고, 현장 시공에서는 가설기둥(100)에 이렇게 접합된 연결부(200)의 연결부재(220)를 접합하거나, 전술한 정착연결부재(230)를 접합하여 현장에서의 접합(용접)공정을 최소화할 수 있다. On the other hand, in the joint installation of the connection part 200 in the field, the connection member 220 and the fixing member 210 are bonded to each other before or manufactured in one piece, and in the on-site construction, the connection part 200 bonded to the temporary pillar 100 in this way ) of the connection member 220 or by bonding the above-described fixing connection member 230, the bonding (welding) process in the field can be minimized.

상기한 바에 따라 가설기둥(100)과 연결부(200)의 시공이 완료되면, 연결부(200)가 매립되도록 코어 벽체(10)를 설치한다. 여기서, 전술한 바와 같이 본 발명에서는 지상 1층의 보 및 슬래브 설치를 진행함과 동시에 지하 1층의 시공 역시 진행될 수 있으며, 이는 종래기술이 지하 1층의 코어가 온전히 시공된 다음에야 지상층의 시공이 시작될 수 있는 것과는 달리, 지하 1층의 코어가 완성되기 이전에 지상층의 작업을 시작할 수 있어 공기를 대폭적으로 단축시킬 수 있다. When the construction of the temporary pillar 100 and the connecting part 200 is completed according to the above, the core wall 10 is installed so that the connecting part 200 is buried. Here, as described above, in the present invention, the construction of the first basement floor can also be carried out while the beams and slabs on the first floor are installed in the present invention. Unlike this that can be started, work on the ground floor can be started before the core of the first basement floor is completed, which can significantly shorten the construction period.

즉, 본 발명의 공기단축형 역타공법은, 지상 1층 위의 높이에서 가설기둥(100)과 정착부재(210)가 함께 위로 연장될 수 있으며, 지상 1층의 시공이 시작되면서 지하층의 작업도 진행되므로, 어느 시점에서는 지하 1층 및 지상 1층의 코어가 완성되고, 코어가 위층으로 계속 이어져 나가게 된다. That is, in the air shortening reverse drilling method of the present invention, the temporary pillar 100 and the fixing member 210 can extend upward together at the height above the first floor, and the work of the basement floor is also progressed as the construction of the first floor begins. Therefore, at a certain point, the core of the first basement and first floor is completed, and the core continues to the upper floor.

또한, 설계된 특정 높이에서 코어가 정착 부재의 위치에 다다르게 되며, 정착부재(210) 주위에 콘크리트가 타설됨으로써 정착부재(210)는 코어 내부에 매립될 수 있으며, 코어 벽체(10) 내에는 구조 설계에 따라 각종 철근이 배근될 수 있음은 물론이다.In addition, the core reaches the position of the anchoring member at a specific designed height, and concrete is poured around the anchoring member 210 so that the anchoring member 210 can be embedded in the core, and the core wall 10 has a structural design It goes without saying that various reinforcing bars can be arranged depending on the situation.

코어 벽체(10) 시공 등 건축물의 완공이 다가오면, 건축물의 완공 전 가설기둥(100)의 일부를 절단하여 마무리할 수 있다. 이때, 가설기둥(100)은, 절단이 가능한 I빔 또는 H빔이 이용되기 때문에, 가설기둥(100)에서 건축물의 수평부재(20)(수평빔)와 접합되지 않는 가설기둥(100)의 노출영역을 절단할 수 있다. 여기서, 수평부재(20)는 건축물의 내력 구조의 일부를 구성하는 영구적 부재일 수도 있고, 일시적으로 가설되는 임시적 부재일 수도 있다.When the completion of the building such as the core wall 10 construction approaches, it may be finished by cutting a part of the temporary pillar 100 before the completion of the building. At this time, the temporary pillar 100 is, since a cuttable I-beam or H-beam is used, the temporary pillar 100 that is not joined to the horizontal member 20 (horizontal beam) of the building in the temporary pillar 100 is exposed. The area can be cut. Here, the horizontal member 20 may be a permanent member constituting a part of the load-bearing structure of the building, or may be a temporary member that is temporarily erected.

다시 말해, 가설기둥(100)과 연결부재(220) 중 수평빔이 접합된 위치에 대응하는 접합부분은 건축물의 내력 구조의 일부로 남을 수 있으며, 가설기둥(100)과 연결부재(220) 중 수평빔이 접합된 위치에 대응하는 부분 이외의 노출부분은 건축물의 완공 이전의 어느 시점에 절단되어 제거될 수도 있다.In other words, the joint portion corresponding to the position where the horizontal beam is joined among the temporary post 100 and the connecting member 220 may remain as a part of the load-bearing structure of the building, and horizontal among the temporary post 100 and the connecting member 220 . Exposed parts other than the part corresponding to the position where the beam is joined may be cut and removed at any point before the completion of the building.

나아가, 가설기둥(100)에는 수평빔이 접합될 수 있다. 이러한 수평빔은 실제 건축물의 하중을 부담하는 내력 부재로서 영구적으로 사용될 수 있다. 여기서, 수평빔은, 철골보를 적용할 수 있으며, 이와 같이 설치되는 철골보를 바탕으로 슬래브를 시공할 수 있고 건축물의 기타 내력 부재를 시공할 수 있다. Furthermore, a horizontal beam may be bonded to the temporary pillar 100 . This horizontal beam can be permanently used as a load-bearing member to bear the actual load of the building. Here, the horizontal beam can be applied to the cheolgolbo, it is possible to construct a slab based on the cheolgolbo installed in this way, and to construct other bearing members of the building.

또한, 건축물의 시공이 진행됨에 따라 특정 높이에서는 더 이상 가설기둥(100)에 의존하여 보 및 슬래브를 설치할 필요가 없어지며, 이미 완성된 코어 또는 영구 철골 부재 등에 의해 시공을 진행할 수 있다. In addition, as the construction of the building progresses, it is no longer necessary to install beams and slabs depending on the temporary pillars 100 at a specific height, and construction can be performed by already completed cores or permanent steel members.

본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 다른 실시예가 가능하다는 점을 이해할 것이다. 따라서 본 발명의 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.Although the present invention has been described with reference to the embodiment shown in the drawings, which is merely exemplary, it will be understood by those skilled in the art that various modifications and equivalent other embodiments are possible therefrom. Therefore, the true technical protection scope of the present invention should be determined by the technical spirit of the appended claims.

상기에서는 본 발명의 바람직한 실시예를 참조하여 설명하였지만, 해당 기술 분야의 숙련된 당업자는 하기의 특허 청구의 범위에 기재된 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변경시킬 수 있음을 이행할 수 있을 것이다.Although the above has been described with reference to preferred embodiments of the present invention, those skilled in the art can variously modify and change the present invention within the scope without departing from the spirit and scope of the present invention as set forth in the claims below. You can do what you can do.

10 : 코어 벽체 20,30,31,40 : 수평부재
100 : 가설기둥 200 : 연결부
210,211,212 : 정착부재 220,221,222,223 : 연결부재
230 : 정착연결부재
10: core wall 20, 30, 31, 40: horizontal member
100: temporary column 200: connection part
210,211,212: fixing member 220,221,222,223: connecting member
230: fixing connection member

Claims (6)

코어 벽체에 인접하게 세워지는 가설기둥;
일단부는 상기 가설기둥에 접합되고 타단부는 상기 코어 벽체에 정착되어, 상기 가설기둥과 상기 코어 벽체를 서로 연결시키는 연결부;를 포함하되,
상기 가설기둥은,
상기 코어 벽체 시공 전 설치되되 하단부는 지하층 바닥에 매립 설치되고, 상부는 지상층 수평부재와 접합되어 상단부가 지상층 천정 상부까지 연장되어 세워지는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물.
Temporary columns erected adjacent to the core wall;
One end is joined to the temporary post and the other end is fixed to the core wall, and a connecting part connecting the temporary post and the core wall to each other;
The temporary pillar is
It is installed before the core wall construction, and the lower part is buried in the basement floor, and the upper part is joined to the ground level horizontal member so that the upper end is extended to the upper part of the ground floor ceiling and erected. Air shortening type reverse rudder structure using temporary columns for dragons.
제 1 항에 있어서,
상기 가설기둥은,
절단 가능한 I빔 또는 H빔이 적용되는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물.
The method of claim 1,
The temporary pillar is
An air shortening type reverse rudder structure using an underground core wall side reverse rudder temporary column and a temporary pole for transmitting structural load on the ground floor, characterized in that a cutable I-beam or H-beam is applied.
제 2 항에 있어서,
상기 연결부는,
일측이 상기 가설기둥에 접합되는 연결부재와,
일측은 상기 연결부재의 타측에 접합되고, 타측은 상기 코어 벽체에 정착되는 정착부재를 포함하는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물.
3. The method of claim 2,
The connection part,
a connecting member having one side joined to the temporary pillar;
One side is joined to the other side of the connection member, and the other side comprises a fixing member fixed to the core wall.
제 3 항에 있어서,
상기 연결부재는,
I빔, H빔, 평판 및 T바 중 선택된 어느 하나의 부재로 형성되는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타구조물.
4. The method of claim 3,
The connecting member is
I-beam, H-beam, flat plate, and T-bar, characterized in that formed of any one member selected from the underground core wall side reverse rudder construction using a temporary pillar for load transmission of the above-ground skeletal structure.
지하층 바닥에서 지상층 천정 상부까지 길이를 갖는 가설기둥을 준비하고, 상기 가설기둥을 지반을 천공하여 건축물의 코어 벽체가 설치될 위치에 인접하게 세워 설치하는 단계(S110);
일측이 상기 가설기둥에 접합되고 타측이 상기 코어 벽체에 매립 정착되는 연결부를 상기 가설기둥에 접합하여 연결하는 단계(S120);
상기 연결부가 매립되도록 상기 코어 벽체를 설치하는 단계(S130);
상기 건축물의 완공 전 상기 가설기둥의 일부를 절단하여 마무리하는 단계(S140);를 포함하는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타공법.
Preparing a temporary pillar having a length from the floor of the basement to the upper part of the ceiling of the ground floor, drilling the temporary pillar in the ground to erect and install the temporary pillar adjacent to the location where the core wall of the building will be installed (S110);
connecting a connection part having one side joined to the temporary pillar and the other side buried and fixed in the core wall by bonding to the temporary pillar (S120);
installing the core wall so that the connection part is buried (S130);
A step (S140) of cutting and finishing a part of the temporary pillar before the construction of the building is completed. The air shortening type reverse drilling method using the underground core wall-side reverse striking temporary pillar and the above-ground structural load transmission temporary pillar, characterized in that it includes.
제 5 항에 있어서,
상기 연결부는,
일측이 상기 가설기둥에 접합되고, I빔, H빔, 평판 및 T바 중 선택된 어느 하나의 부재로 형성되는 연결부재와,
일측은 상기 연결부재의 타측에 접합되고, 타측은 상기 코어 벽체에 정착되며, I빔, H빔 및 복수개의 스터드볼트들 중 중 선택된 어느 하나의 부재로 형성되는 정착부재를 포함하는 것을 특징으로 하는 지하층 코어 벽체측 역타 가설기둥과 지상층 골조하중 전달용 가설기둥을 이용한 공기단축형 역타공법.
6. The method of claim 5,
The connection part,
A connecting member having one side joined to the temporary pole and formed of any one member selected from an I-beam, an H-beam, a flat plate, and a T-bar;
One side is joined to the other side of the connection member, the other side is fixed to the core wall, characterized in that it comprises a fixing member formed of any one member selected from among I-beam, H-beam, and a plurality of stud bolts A short-term reverse drilling method using the underground core wall side reverse piercing temporary pillar and the above-ground framing load transmission temporary pillar.
KR1020210077447A 2020-06-15 2021-06-15 A construction period shortening type topdown structure using the underground core wall column and the temporary pole for transmitting the structural load on the ground floor and construction period shortening type topdown construction method using the same KR20210155380A (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
KR20200072313 2020-06-15
KR1020200072312 2020-06-15
KR20200072312 2020-06-15
KR1020200072313 2020-06-15

Publications (1)

Publication Number Publication Date
KR20210155380A true KR20210155380A (en) 2021-12-22

Family

ID=79164406

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210077447A KR20210155380A (en) 2020-06-15 2021-06-15 A construction period shortening type topdown structure using the underground core wall column and the temporary pole for transmitting the structural load on the ground floor and construction period shortening type topdown construction method using the same

Country Status (1)

Country Link
KR (1) KR20210155380A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101014796B1 (en) 2008-03-03 2011-02-15 주식회사 한빛구조엔지니어링 Top-down underground construction method using prefabricated concrete column member as temporary bridge column

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101014796B1 (en) 2008-03-03 2011-02-15 주식회사 한빛구조엔지니어링 Top-down underground construction method using prefabricated concrete column member as temporary bridge column

Similar Documents

Publication Publication Date Title
US6920728B2 (en) Column and beam construction and method
CN109944250B (en) Foundation pit forward and backward combined construction method of non-permanent vertical supporting system
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101187170B1 (en) Application of under pinning method in remodeling
KR20190022132A (en) Top-down method using precast-concrete colum
KR101006411B1 (en) System and method for underground downward construction using concrete filled tube
JP2005105531A (en) Foundation structure of building and its construction method
JP2001349065A (en) Underground base isolating construction method for existing building
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
KR20210155380A (en) A construction period shortening type topdown structure using the underground core wall column and the temporary pole for transmitting the structural load on the ground floor and construction period shortening type topdown construction method using the same
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
KR20050113450A (en) Downward reinforced-concrete underground structure using temporary assistant columns
KR101485563B1 (en) The horizontal structural frame
JP2847447B2 (en) Reverse construction method
JP2003003690A (en) Base isolation building and method for base isolation of exisiting building
KR101251096B1 (en) A temporary skeleton system used a building with a shallow basement and a top down underground construction method using a temporary skeleton system
JP4449595B2 (en) Column-beam joint structure, method for constructing column-beam joint structure, method for constructing underground structure, and building
KR200451731Y1 (en) Concrete Filed Tube
JP2736542B2 (en) Construction method of underground structure omitting temporary materials
KR101762207B1 (en) The speed up construction method using hemispherical joint
JP7442268B2 (en) underground structure
KR101200993B1 (en) Precast concrete column material for permanent column pre-establishment method
JPH1113067A (en) Burying construction method for supplementary stud in reverse concreting construction method
JPH0657769A (en) Underground concrete structure and working method thereof

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E601 Decision to refuse application