KR20100132222A - Reinforce unit for grouting and grouting reinforce method using the same - Google Patents

Reinforce unit for grouting and grouting reinforce method using the same Download PDF

Info

Publication number
KR20100132222A
KR20100132222A KR1020090050932A KR20090050932A KR20100132222A KR 20100132222 A KR20100132222 A KR 20100132222A KR 1020090050932 A KR1020090050932 A KR 1020090050932A KR 20090050932 A KR20090050932 A KR 20090050932A KR 20100132222 A KR20100132222 A KR 20100132222A
Authority
KR
South Korea
Prior art keywords
grouting
reinforcing
unit
reinforcing member
tunnel
Prior art date
Application number
KR1020090050932A
Other languages
Korean (ko)
Other versions
KR101079075B1 (en
Inventor
박재현
Original Assignee
박재현
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박재현 filed Critical 박재현
Priority to KR1020090050932A priority Critical patent/KR101079075B1/en
Publication of KR20100132222A publication Critical patent/KR20100132222A/en
Application granted granted Critical
Publication of KR101079075B1 publication Critical patent/KR101079075B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/028Devices or accesories for injecting a grouting liquid in a bore-hole
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0093Accessories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE: A reinforcing unit for grouting and a grouting reinforcing method using the same are provided to maintain continuous prestress in a part in which a reinforcing member and a compression joint module are installed even if compressive force is lost. CONSTITUTION: A reinforcing unit for grouting comprises two or more reinforcing members(10,20) and compression joint modules(110). The reinforcing members are inserted into boring holes. The compression joint modules are located between the reinforcing members. Compressive force is applied to the compression joint modules after a grouting work is completed.

Description

그라우팅용 보강유닛 및 이를 이용한 그라우팅 보강방법{Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same}Reinforcement unit for grouting and grouting reinforcement method using the same {Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same}

본 발명은 그라우팅 공법과 관련된 것으로서, 보다 상세하게는 지반에 대해 상시 압축력을 제공할 수 있도록 한 그라우팅 보강유닛 및 이를 이용한 그라우팅 방법에 관한 것이다.The present invention relates to a grouting method, and more particularly, to a grouting reinforcement unit and a grouting method using the same to provide a constant compressive force on the ground.

일반적으로, 그라우팅(grouting)이라 함은 토목공사에서 누수방지나 토질안정 등의 목적으로 지반 내부에 시멘트 등과 같은 소정의 그라우팅재를 주입하여 지반을 안정화시키는 것을 말한다.In general, grouting refers to stabilizing the ground by injecting a predetermined grouting material such as cement into the ground for the purpose of preventing leakage or stabilizing soil in civil works.

산업화의 발달에 따라 도로의 건설이나 단지 조성 등의 목적으로 터널의 굴착이나 급경사지의 개발이 불가피한 실정인데, 이를 위해서는 시공의 안정성 및 경제성, 환경보전성 등을 충족시키기 위한 안정화 대책이 요구되고 있다.With the development of industrialization, the excavation of tunnels and the development of steep slopes are inevitable for the purpose of construction of roads and complexes, and stabilization measures are required to satisfy construction stability, economic feasibility, and environmental preservation.

특히, 철도나 자동차 도로 등의 건설을 위한 터널의 굴착 시에는 지반의 상황이나 용수에 의해 시공이 곤란해지거나 지보효과가 저하되는 경우 안전하고 효율적인 터널시공을 위한 보강 공법이 요구된다.In particular, in the excavation of tunnels for the construction of railroads or automobile roads, reinforcing methods for safe and efficient tunnel construction are required when construction is difficult due to ground conditions or water or the support effect is reduced.

이를 위해, 터널의 굴착면에 강관을 이용하여 보강을 행하는 그라우팅 공법 이 널리 이용되고 있는데, 상기 그라우팅 공법은 터널 등의 굴착면에 일정 각도의 경사각을 갖도록 천공홀을 천공한 후, 그 내부에 다수 개의 강관을 삽입하고, 상기 천공홀에 그라우팅재를 주입하여 상기 천공홀 및 강관 사이의 공간부에 그라우팅재가 경화되면서 주변지반을 보강하도록 하게 된다.To this end, a grouting method for reinforcing using a steel pipe on an excavation surface of a tunnel is widely used. The grouting method is used to drill a hole to have a predetermined angle of inclination on an excavation surface such as a tunnel, and then a plurality of grouting methods. The two steel pipes are inserted, and the grouting material is injected into the drilling holes to reinforce the surrounding ground while the grouting material is cured in the space portion between the drilling holes and the steel pipes.

즉, 상기 그라우팅 공법은 천공홀 주변의 빈 공간에 그라우팅재가 얼마나 견고하고 균일하게 투입되느냐에 따라 그 보강성능의 효율성이 결정되는 것이다.That is, in the grouting method, the efficiency of the reinforcing performance is determined according to how firmly and uniformly the grouting material is injected into the empty space around the hole.

이에, 그라우팅 공법의 효율성을 높이기 위하여 다양한 구조의 강관이 개발되어 보강작업 시에 사용되고 있다.In order to increase the efficiency of the grouting method, steel pipes of various structures have been developed and used in reinforcement work.

도 1 및 도 2는 종래 일반적인 그라우팅 공법을 나타낸 도면이며, 터널의 상측 지반에 그라우팅 공법이 적용되는 것을 일예로 설명한다.1 and 2 are views showing a conventional general grouting method, it will be described as an example that the grouting method is applied to the upper ground of the tunnel.

먼저, 도 1에 도시된 바와 같이, 터널의 시공 시 터널 상측 지반의 보강을 위하여 지반 상측으로부터 시공될 터널 내측으로 다수개의 천공홀(1)을 천공한 후, 상기 천공홀(1) 각각에 강관(2)을 삽입한다.First, as shown in FIG. 1, when the tunnel is constructed, a plurality of drilling holes 1 are drilled from the upper side of the tunnel to the inside of the tunnel to be reinforced to the ground above the tunnel, and then steel pipes are formed in each of the drilling holes 1. Insert (2).

그리고, 도 2에 도시된 것처럼, 상기 천공홀(1)과 강관(2) 사이의 공간부에 파이프(8) 등을 통하여 그라우팅재를 충진시키고 경화시킴으로써 지반을 보강하게 된다.As shown in FIG. 2, the ground is reinforced by filling and curing the grouting material through the pipe 8 or the like in the space between the drilling hole 1 and the steel pipe 2.

이때, 소정 압력으로 그라우팅재를 주입하는 가압 그라우팅을 하는 경우에는 상기 천공홀(1) 주위의 미세한 틈(5)까지 그라우팅재가 삽입된 후 경화되어 보다 안정적인 지반보강이 가능하여 지게 된다.At this time, in the case of pressurized grouting to inject the grouting material at a predetermined pressure, the grouting material is inserted to the fine gap 5 around the perforation hole 1 and then hardened to allow more stable ground reinforcement.

또한, 경우에 따라서는, 상기 강관에 인장력을 가한 후에 그라우팅함으로써 그라우팅이 경화작업까지 완료된 경우 지반에 상하로 압축력이 작용하도록 하여 보다 강화된 보강작업도 한다.In addition, in some cases, when the grouting is completed until the hardening operation by applying the tensile force to the steel pipe, the compressive force acts up and down on the ground to further strengthen the reinforcement work.

그런데, 상기 종래 그라우팅 공법의 경우에는, 강관 중의 일부가 끊어지는 경우 강관 전체에 걸쳐 있던 프리스트레스가 모두 풀리게 되므로 해당 강관 전체가 압축력을 통하여 지반을 보강하는 구조를 이루는 데에는 취약해지는 문제점이 있었다.By the way, in the conventional grouting method, when some of the steel pipes are broken, all the prestresses of the steel pipes are released, so that the entire steel pipe has a problem in forming a structure that reinforces the ground through the compressive force.

또한, 그라우팅 작업이 완료된 후에 터널을 시공 시에는 터널 내면의 형성 작업 시 터널 내측까지 위치된 강관까지 동시에 커팅하는 작업을 거쳐야 한다.In addition, when the tunnel is constructed after the grouting work is completed, the work to simultaneously cut to the steel pipe located up to the inside of the tunnel during the formation of the tunnel inner surface.

그런데, 강철 재질의 종전 그라우팅용 강관의 경우는 그 강도가 강하여 터널 내면의 시공작업을 하는 경우에 장비의 손상을 가져오는 등의 문제점이 있었다.However, in the case of the conventional grouting steel pipe made of steel, there is a problem in that the strength thereof is strong, resulting in damage to the equipment in the case of construction work on the inner surface of the tunnel.

본 발명은 상술한 종래의 문제점 및 제결점을 해결하기 위하여 안출된 것으로서, 본 발명의 목적은 다음과 같다.The present invention has been made to solve the above-mentioned problems and disadvantages, the object of the present invention is as follows.

첫째, 하나의 그라우팅 보강유닛에 있어서도 압축력이 보강유닛의 일정 영역별로 분산되어 걸리도록 하는데 그 목적이 있다.First, even in one grouting reinforcing unit, the purpose is to compress the compressive force by a predetermined area of the reinforcing unit.

둘째, 천공홀 내 상기와 같이 분산되어 압축력이 걸리는 보강유닛의 설치가 용이하게 이루어지도록 하는데 그 목적이 있다.Second, the purpose is to facilitate the installation of the reinforcement unit is distributed as described above in the drilling hole is applied to the compressive force.

셋째, 그라우팅 작업이 완료된 후에 천공홀을 관통삽입하여 터널 내측면 부위까지 위치된 보강유닛의 커팅 및 절삭 등의 작업 시에 작업공구의 파손을 방지하면서, 원활한 작업이 가능하도록 하는데 그 목적이 있다.Thirdly, after grouting is completed, the penetrating hole is inserted to prevent a breakdown of the work tool during cutting and cutting of the reinforcing unit located up to the inner side of the tunnel, thereby enabling smooth operation.

상기한 목적을 달성하기 위하여, 본 발명은 지반에 형성시킨 천공홀을 이용 그라우팅 작업을 하기 위한 보강유닛에 있어서, 상기 천공홀에 삽입되는 적어도 두 개 이상의 보강부재 및 상기 각각의 스틸보강부재 사이에 위치되어 그라우팅 작업이 완료된 후에 상기 스틸보강부재 사이에 압축력이 작용하도록 연결되는 압축연결모듈을 포함하여 구성되는 그라우팅용 보강유닛을 제공한다.In order to achieve the above object, the present invention is a reinforcing unit for grouting work using a punched hole formed in the ground, between at least two reinforcing members and the respective steel reinforcing members inserted into the punching hole It provides a reinforcing unit for grouting comprising a compression connection module is positioned so that the compression force is applied between the steel reinforcing member after the grouting operation is completed.

여기서, 상기 천공홀에 먼저 삽입되는 보강부재는 GRP재질로 이루어진 보강부재일 수 있다.Here, the reinforcing member inserted into the drilling hole may be a reinforcing member made of a GRP material.

그리고, 상기 압축연결모듈은 상기 보강부재의 길이방향을 기준으로 양측으 로 각각 상기 보강부재의 일단이 길이방향을 따라 슬라이딩 이동 가능하게 연결되는 외부케이스와 상기 보강부재의 일단부가 연결됨과 동시에 상기 외부케이스 내측에 상기 보강부재와 함께 슬라이딩 이동 가능하게 구비되는 커플러 및 상기 외부케이스 내측에 구비되어 상기 보강부재를 길이방향 외측으로 잡아당긴 경우 상기 보강부재가 다시 원래의 위치로 돌아가는 복원력을 가하는 탄성부재를 포함하여 구성될 수 있다.The compression connection module has an outer case in which one end of the reinforcing member is slidably moved along the longitudinal direction and the one end of the reinforcing member is connected to both sides of the reinforcing member in a longitudinal direction. A coupler provided to be slidably movable together with the reinforcing member inside the case and an elastic member provided inside the outer case to pull out the reinforcing member in the longitudinal direction to apply a restoring force to return to the original position. It can be configured to include.

한편, 상기 탄성부재는 코일 스프링으로 형성되며, 상기 한 쌍의 커플러 사이에 구비됨과 동시에 코일 스프링의 일측과 타측이 각각 상기 커플러에 고정될 수 있다.On the other hand, the elastic member is formed of a coil spring, and provided between the pair of couplers and at the same time one side and the other side of the coil spring can be fixed to the coupler.

그리고, 상기 탄성부재는 코일스프링으로 형성되며, 상기 커플러와 상기 외부케이스 사이에 구비될 수 있다.In addition, the elastic member is formed of a coil spring, it may be provided between the coupler and the outer case.

또한, 상기 외부케이스는 상기 천공홀의 내측에 고정되도록 상기 외부케이스 외측으로 고정편을 더 포함하여 구성될 수 있다.In addition, the outer case may be configured to further include a fixing piece to the outside of the outer case to be fixed to the inside of the drilling hole.

그리고, 상기 고정편은 상기 외부케이스에 회전 가능하게 힌지결합되고, 상기 고정편과 외부케이스 사이에는 상기 고정편에 외력을 작용하지 않는 경우 천공홀 내측에 맞닿도록 상기 고정편이 회전/이동하도록 하는 탄성부를 더 구비할 수 있다.And, the fixing piece is hinged rotatably to the outer case, elasticity to rotate / move the fixing piece so as to abut the inner side of the drilling hole when no external force is applied to the fixing piece between the fixing piece and the outer case It may be further provided.

한편, 본 발명은 그라우팅 보강유닛을 이용하여 행하는 그라우팅 방법에 있어서, 지반에 천공홀을 천공하는 단계, 상기 천공홀에 급결 그라우팅재를 충진하는 단계, 상기 급결 그라우팅재가 충진된 천공홀에 상기 그라우팅 보강유닛을 삽입하 는 단계, 상기 그라우팅 보강유닛이 삽입된 천공홀에 그라우팅재를 삽입하는 단계 및 상기 천공홀에 삽입된 그라우팅 보강유닛에 있어서 지면 외측에 위치된 보강유닛을 잡아당겨 고정시키는 단계를 포함하여 이루어진 그라우팅 방법을 제공한다.On the other hand, the present invention is a grouting method performed by using a grouting reinforcing unit, the step of drilling a hole in the ground, the step of filling a quick grouting material in the drilling hole, the grouting reinforcement in the drill hole filled with the quick grouting material Inserting the unit, inserting the grouting material into the boring hole into which the grouting reinforcing unit is inserted, and pulling and fixing the reinforcing unit located outside the ground in the grouting reinforcing unit inserted into the boring hole. It provides a grouting method made by.

그리고, 본 발명은 청구항 1 내지 청구항 7항 중 어느 한 항에 기재된 그라우팅 보강유닛을 이용하여 행하는 그라우팅 방법에 있어서, 터널을 가시공하는 단계와, 상기 가시공된 터널의 내측으로부터 지면 측으로 천공홀을 천공하는 단계와, 상기 천공홀에 일단부에는 GRP보강부재가 구비되며 그 외 부분에는 다수개의 스틸보강부재가 연결된 상태의 그라우팅 보강유닛을 상기 GRP보강부재가 터널 내측을 향한 상태를 이루도록 삽입하는 단계와, 상기 그라우팅 보강유닛이 삽입된 천공홀에 그라우팅재를 삽입하는 단계 및 상기 천공홀에 삽입된 그라우팅 보강유닛에 있어서 터널 내측에 위치된 GRP보강부재를 잡아당겨 고정시키는 단계를 포함하여 이루어진 그라우팅 보강방법을 제공한다.In addition, the present invention provides a grouting method using the grouting reinforcing unit according to any one of claims 1 to 7, comprising the steps of visually drilling a tunnel, and drilling a hole in the ground from the inside of the visible tunnel. Drilling and inserting a grouting reinforcing unit having a GRP reinforcing member connected to a plurality of steel reinforcing members at one end of the drilling hole so that the GRP reinforcing member is formed toward the inside of the tunnel; And a grouting material inserted into the boring hole into which the grouting reinforcing unit is inserted, and pulling and fixing the GRP reinforcing member located inside the tunnel in the grouting reinforcing unit inserted into the boring hole. Provide a method.

상기와 같이 구성된 본 발명 그라우팅 보강유닛 및 이를 이용한 그라우팅 보강방법의 효과에 대하여 설명하면 다음과 같다.Referring to the effects of the present invention grouting reinforcing unit configured as described above and the grouting reinforcement method using the same as follows.

첫째, 그라우팅용 보강유닛을 위한 보강부재를 다단으로 형성하고, 각각의 보강부재 사이에 압축력을 가하도록 하는 압축연결모듈을 설치함으로써, 일부 보강부재에 있어서의 프리스트레스 즉 압축력이 손실되더라도 다른 보강부재 및 압축연결모듈이 설치된 부위는 계속적인 프리스트레스를 유지할 수 있도록 하는 효과가 있다.First, by forming a reinforcing member for the grouting reinforcing unit in multiple stages and installing a compression connection module for applying a compressive force between each reinforcing member, the other reinforcing member and the prestressing, that is, the compressive force is lost in some reinforcing members and The area where the compression connection module is installed has the effect of maintaining continuous prestress.

둘째, 터널 내측으로 삽입되는 보강부재는 유리섬유재질의 GRP보강부재로 구성되도록 하여, 터널 내측면을 시공 시에 장비의 파손 등을 방지하면서 유연하게 터널 내측의 시공을 할 수 있는 효과가 있다.Second, the reinforcing member inserted into the tunnel is configured to be made of a glass fiber GRP reinforcing member, there is an effect that can be flexibly installed inside the tunnel while preventing the damage of the equipment when the tunnel inner surface is installed.

셋째, 보강부재가 연결되는 부위마다 앵커모듈을 구비하도록 하여 천공홀의 임의의 위치마다 압축연결모듈을 고정시켜 각 구간마다의 보강부재에 압축력이 유지되도록 하는데 안정적인 구조를 취할 수 있게 되는 효과가 있다.Third, the anchor module is provided at each part where the reinforcing member is connected, thereby fixing the compression connection module at any position of the drilling hole, so that the compressive force can be maintained in the reinforcing member of each section.

이하 첨부된 도면들을 참조하여 본 발명의 바람직한 실시예들을 상세하게 설명하지만, 본 발명이 실시예들에 의해 제한되거나 한정되는 것은 아니다. 참고로, 이하 설명에서는 구성 및 기능이 거의 동일하여 동일하게 취급될 수 있는 요소는 동일한 참조번호로 특정될 수 있다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to the like elements throughout. Note that, in the following description, components that are substantially the same in structure and function and can be handled identically can be identified by the same reference numerals.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 일 실시예에 따른 구조를 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings illustrating a structure according to a preferred embodiment of the present invention.

도 3은 본 발명의 일 실시예에 따른 그라우팅 보강유닛을 나타낸 단면도이다.Figure 3 is a cross-sectional view showing a grouting reinforcement unit according to an embodiment of the present invention.

도시된 것처럼, 본 발명의 일 실시예에 따른 그라우팅 보강유닛(100)은 지반에 천공된 다수개의 천공홀 각각에 삽입되며 길이방향을 따라서 다수개가 나뉘어진 형태로 연결되는 보강부재(10,20)를 포함하여 구성된다.As shown, the grouting reinforcement unit 100 according to an embodiment of the present invention is inserted into each of the plurality of perforation holes drilled in the ground and the reinforcement members 10 and 20 connected in a plurality of divided form along the longitudinal direction It is configured to include.

이때, 상기 보강부재(10,20)는 각각 소정의 길이를 가지는 봉형상으로 이루어지며, 스틸재질로 이루어진 스틸보강부재(10)와 GRP(Glass Reinforced Plastic) 재질로 이루어진 GRP보강부재(20)가 사용된다.At this time, the reinforcing members 10 and 20 are each made of a rod-shaped having a predetermined length, the steel reinforcing member 10 made of a steel material and the GRP reinforcing member 20 made of Glass Reinforced Plastic (GRP) material is Used.

일반적으로 사면보강을 위해서는 상기 스틸재질의 스틸보강부재가 다수개 연결된 형태의 그라우팅용 보강유닛이 사용되며, 터널의 시공 시에는 터널 내측 주위로는 상기 GRP보강부재(20)가 적용된 그라우팅용 보강유닛이 사용되며 이하에서 보다 상세히 설명한다.In general, a grouting reinforcing unit is used to reinforce slopes in which a plurality of steel reinforcing members of the steel material are connected, and when the tunnel is constructed, a grouting reinforcing unit to which the GRP reinforcing member 20 is applied is installed around the inside of the tunnel. This is used and described in more detail below.

첨부된 도 3에서는 터널 시공을 위하여 GRP보강부재가 적용되는 그라우팅용 보강유닛을 나타낸 도면으로서, 이하에서는 터널 시공을 위한 그라우팅용 보강유닛을 위주로 설명한다.3 is a view showing a grouting reinforcing unit to which a GRP reinforcing member is applied for tunnel construction, hereinafter, a grouting reinforcing unit for tunnel construction will be described.

도시된 바와 같이, 터널의 시공 시에는 시공되는 터널의 상측 지반으로부터 하부의 시공되는 터널이 위치된 쪽으로 GRP보강부재(20)가 위치되며, 그 이외의 부분은 스틸보강부재(10)가 다수개 연결되어 구성되는 보강유닛(100)이 사용된다,As shown, when the tunnel is constructed, the GRP reinforcing member 20 is positioned from the upper ground of the tunnel to be installed toward the lower construction tunnel, and other portions of the tunnel are provided with a plurality of steel reinforcing members 10. Reinforcement unit 100 is used to be connected,

이를 위해, 미리 시공되는 터널의 위치 및 모양에 따라서 상기 천공홀 각각의 천공작업이 이루어지게 되야 함은 물론이다.To this end, it is a matter of course that the drilling operation of each of the drilling holes to be made according to the position and shape of the tunnel to be constructed in advance.

그리고, 상기 스틸보강부재(10)는 다수개가 연결된 형태를 이루며 각각의 스틸보강부재(10) 또는 상기 GRP보강부재(20)와 스틸보강부재(10)는 모두 압축연결모듈(110)에 의하여 연결되는 형태를 이룬다.In addition, the steel reinforcing member 10 has a form in which a plurality is connected, each steel reinforcing member 10 or the GRP reinforcing member 20 and the steel reinforcing member 10 are all connected by a compression connection module 110. To form.

상기 압축연결모듈(110)은 각각 상기 스틸보강부재(10) 또는 GRP보강부재(20)의 일단부가 연결되는 커플러(121,122) 및 상기 보강부재(10,20)의 설치가 완료된 후에 상기 두 개의 커플러(121,122) 사이를 연결하도록 설치되는 탄성부재(130)를 포함하여 구성된다.The compression connection module 110 is the coupler (121, 122) and one end of the reinforcing member (10, 20) is connected to one end of the steel reinforcing member 10 or GRP reinforcing member 20, respectively, after the two couplers are completed It is configured to include an elastic member 130 is installed to connect between (121, 122).

여기서, 상기 탄성부재(130)는 코일스프링이 사용된다.Here, the coil spring is used as the elastic member 130.

그리고, 상기 커플러(121,122)와 상기 각각의 보강부재(10,20)가 결합되는 방법은 억지끼움 또는 기타 결합부재를 이용하는 방식 등 여러 형태가 적용가능하다.The coupler 121 and 122 and the respective reinforcing members 10 and 20 may be coupled in various ways such as by using interference fit or other coupling members.

도 3에서는 그 중 일 형태만을 나타낸 것으로서 상기 커플러(121,122)에는 암나사부가 형성되고, 상기 스틸보강부재(10) 및 GRP보강부재(20)의 일단부에는 숫나사부가 형성되도록 하여 나사회전방식에 의하여 결합되는 형태를 도시한 것이다.In FIG. 3, only one form is shown, and a female screw part is formed at the coupler 121 and 122, and a male screw part is formed at one end of the steel reinforcing member 10 and the GRP reinforcing member 20 to be coupled by a screw rotation method. It is shown the form.

한편, 상기 보강부재의 길이방향을 기준으로 양측으로 각각 상기 보강부재 및 커플러가 결합된 후 보강부재의 길이방향을 따라 슬라이딩 이동이 가능하도록 하는 외부케이스(111)가 구비된다.On the other hand, after the reinforcing member and the coupler is coupled to both sides based on the longitudinal direction of the reinforcing member is provided with an outer case 111 to enable sliding movement along the longitudinal direction of the reinforcing member.

즉, 상기 외부케이스(111) 내측으로 상기 커플러(121,122)가 슬라이딩 이동이 가능하게 설치되며, 상기 외부케이스(111) 내측 상기 커플러(121,122) 사이로 상기 코일 스프링(130)의 일측과 타측이 각각 상기 커플러(121,122)에 결합되도록 구성된다.That is, the couplers 121 and 122 may be slidably moved into the outer case 111, and one side and the other side of the coil spring 130 may be disposed between the coupler 121 and 122 inside the outer case 111, respectively. It is configured to be coupled to the coupler (121, 122).

한편, 상기 압축연결모듈(110)은 상기 커플러(121,122) 및 탄성부재(130)가 천공홀 내부에 삽입된 후에 천공홀의 내측면에 일정위치에서 고정이 되도록 앵커모듈(101)을 포함하여 구성되는데, 여기서 상기 외부케이스(111) 자체가 앵커모듈(101)의 일부를 구성하게 된다.On the other hand, the compression connection module 110 is configured to include an anchor module 101 to be fixed at a predetermined position on the inner surface of the drilling hole after the coupler (121, 122) and the elastic member 130 is inserted into the drilling hole. Here, the outer case 111 itself constitutes a part of the anchor module 101.

그리고, 상기 외부케이스(111) 외측으로는 상기 외부케이스(111)에 천공홀의 내면 측에 맞닿도록 회전 가능하게 지지되는 고정편(112)이 구비된다.The outer case 111 is provided with a fixing piece 112 rotatably supported by the outer case 111 so as to be in contact with the inner surface side of the drilling hole.

도 3에서, 상기 고정편(112)은 상기 외부케이스(111)에 힌지(118)방식의 결합구조로 회전 가능하게 연결된 모습을 나타낸 것이다. In Figure 3, the fixing piece 112 is shown to be rotatably connected to the coupling structure of the hinge 118 method to the outer case 111.

이때, 상기 고정편(112)과 상기 외부케이스(111) 사이에는 스프링(115)이 구비되며, 상기 스프링(115)을 가압한 형태로 가압밴드(150)가 상기 고정편(115)을 감싸는 형태로 위치된다.At this time, a spring 115 is provided between the fixing piece 112 and the outer case 111, and the pressing band 150 surrounds the fixing piece 115 in a form in which the spring 115 is pressed. Is located.

자세히 도시되어 있지는 않지만, 상기 고정편(112)은 상기 외부케이스(111)의 둘레부를 따라서 복수개가 구비됨이 바람직하다.Although not shown in detail, the fixing piece 112 is preferably provided with a plurality along the circumference of the outer case 111.

이렇게 구성되어, 상기 가압밴드(150)를 이탈시키면 상기 고정편(112)이 스프링(115)의 복원력에 의하여 외측으로 벌어지게 된다.In this manner, when the pressing band 150 is separated, the fixing piece 112 is opened to the outside by the restoring force of the spring 115.

이 경우, 상기 고정편(112) 자체를 탄성을 지니는 물질로 구성하여별도의 스프링이 없이 상기 외부케이스(111)의 외부에 설치될 수도 있다.In this case, the fixing piece 112 itself may be made of a material having elasticity and may be installed outside the outer case 111 without a separate spring.

상기와 같이 구성된 본 발명 그라우팅 보강유닛을 이용한 그라우팅 보강방법을 첨부된 도 4 내지 도 8을 참조하여 설명하면 다음과 같다.The grouting reinforcement method using the present invention grouting reinforcement unit configured as described above will be described with reference to FIGS. 4 to 8.

첨부된 도면 중 도 4는 터널의 시공을 위하여 지반 상측에 천공홀이 천공된 모습을 개략적으로 나타낸 단면도이고, 도 5 내지 도 7은 본 발명에 따른 그라우팅 보강방법을 순서대로 나타낸 도면들이며, 도 8은 본 발명에 따른 그라우팅 보강공법을 나타낸 순서도이다.4 is a cross-sectional view schematically showing a hole in the upper ground for the construction of the tunnel, Figures 5 to 7 are views showing the grouting reinforcement method according to the present invention in order, Figure 8 Is a flowchart showing a grouting reinforcement method according to the present invention.

먼저, 첨부된 도 4에 도시된 바와 같이, 시공되는 터널의 상측으로부터 미리 설계된 터널 내측 부분에까지 다다르도록 상기 다수개의 천공홀(H)을 시공하는 단계를 수행한다(S10).First, as shown in FIG. 4, the construction of the plurality of drilling holes H is performed to reach a pre-designed tunnel inner part from the upper side of the tunnel to be constructed (S10).

이때, 상기 천공홀(H)은 터널이 길이방향은 물론 양 폭을 따라서 다수개의 열을 이루며 천공작업이 진행되면, 차후 시공되는 터널의 내측으로 본 발명 그라우팅 보강유닛의 일부 특히 GRP보강부재가 돌출이 가능할 정도로 천공작업이 수행된다.At this time, the drilling hole (H) is a tunnel is formed in a plurality of rows along the width as well as the longitudinal direction when the drilling operation is progressed, in particular the GRP reinforcing member of the grouting reinforcement unit of the present invention protrudes into the tunnel to be constructed later The drilling operation is carried out to this extent possible.

다음으로는, 상기 천공된 천공홀(H)에 있어서 터널이 위치된 쪽으로 즉, 상기 천공홀(H)의 선단부 일부를 레진 또는 급결그라우팅재로 충진한다(S20).Next, in the drilled hole H, the tunnel is located, that is, a portion of the tip portion of the drilled hole H is filled with a resin or a quick grouting material (S20).

여기서, 상기 레진 또는 급결그라우팅재는 빠른 시간 안에 굳어지는 재질로 이루어지며, 충진되는 깊이는 상기 그라우팅 보강유닛(100)의 GRP보강부재(20)가 일부 삽입될 정도의 깊이로 충진된다(S20).Here, the resin or the fastening grouting material is made of a material that is hardened in a fast time, the filling depth is filled to a depth enough to insert a part of the GRP reinforcing member 20 of the grouting reinforcing unit 100 (S20).

다음으로는, 상기와 같이 레진 또는 급결그라우팅재가 충진된 천공홀(H) 내측으로 상기 그라우팅 보강유닛(100)을 선단부가 GRP 보강부재(20)가 되도록 한 후 삽입하는 단계를 수행한다(S30).Next, the step of inserting the grouting reinforcing unit 100 into the GRP reinforcing member 20 to the inside of the drilling hole (H) filled with the resin or the quick grouting material as described above (S30). .

이때, 상기 그라우팅 보강유닛(100)은 천공홀의 깊이에 따라서 미리 다수개의 GRP보강부재(20)와 스틸보강부재(10)를 압축연결모듈(110)을 이용하여 조립하여 놓게 되며, 특히 터널 내측으로는 상기 GRP보강부재(20)가 일부 돌출되도록 함과 동시에 지반 상측으로도 상기 스틸보강부재(10)가 일부 돌출될 정도의 길이로 조립시킨다.At this time, the grouting reinforcing unit 100 is assembled in advance by using the compression connection module 110 a plurality of GRP reinforcing member 20 and the steel reinforcing member 10 according to the depth of the drilling hole, in particular in the tunnel While the GRP reinforcing member 20 is partially protruded, the steel reinforcing member 10 is assembled to a length such that the steel reinforcing member 10 partially protrudes from the ground.

그리고 나서, 상기 충진시킨 레진 또는 급결 그라우팅재가 굳어짐에 따라서 상기 그라우팅 보강유닛(100)의 선단부 즉 GRP보강부재(20)가 상기 천공홀 내측에 고정된 상태를 이루게 되면, 지면상측으로 일부 돌출되게 설치된 스틸보강부재(10) 를 외부로 잡아당겨 상기 그라우팅 보강유닛(100) 전체에 걸쳐서 인장력이 작용하는 상태를 이루도록 한다(S40).Then, when the filled resin or the fastening grouting material is hardened, the front end portion of the grout reinforcing unit 100, that is, the GRP reinforcing member 20 is fixed to the inside of the drilling hole, is installed to partially protrude to the ground side. Pull the steel reinforcing member 10 to the outside to achieve a state in which the tensile force acts throughout the grouting reinforcement unit (100) (S40).

이렇게 되면, 상기 그라우팅 보강유닛(100)의 각각의 보강부재 사이에 구비되는 압축연결모듈(101)의 코일스프링(130) 각각에 모두 인장력이 작용하여 그라우팅 보강유닛 전체적으로는 그 길이가 일부 늘어난 상태를 이루게 된다.In this case, a tensile force acts on each of the coil springs 130 of the compression connection module 101 provided between the respective reinforcing members of the grouting reinforcing unit 100 so that the length of the whole grouting reinforcing unit is partially increased. Is achieved.

다음으로는, 상기 가압밴드(150)를 이탈시켜 고정편(112)을 이용하여 상기 외부케이스(111)를 상기 천공홀(H) 내부의 일정 위치마다 고정된 상태를 유지하는 작업을 수행한다(S50).Next, the pressing band 150 is separated to perform the operation of keeping the outer case 111 fixed at a predetermined position inside the drilling hole H by using the fixing piece 112 ( S50).

그리고 나서, 상기 천공홀(H) 내부에는 최종적으로 일반 그라우팅재를 충진하고, 최외곽에 위치하는 스틸보강부재(10)를 고정 캡 또는 고정볼트 등을 이용하여 지면에 고정시키는 작업을 수행한다.Then, the perforated hole (H) is finally filled with a general grouting material, and performs the operation of fixing the steel reinforcing member 10 located at the outermost to the ground using a fixing cap or fixing bolts.

상기와 같은 과정을 통하여 그라우팅 보강유닛의 설치작업 및 그라우팅 보강작업까지 모두 완료되면, 상기 천공홀(H) 내부의 그라우팅 보강유닛(100)은 그 길이방향을 따라서는 각각의 스프링(130)이 위치된 구간별로 압축력이 작용하는 상태를 이루게 된다.When the installation and grouting reinforcement work of the grouting reinforcement unit is completed through the above process, the grouting reinforcement unit 100 inside the drilling hole (H) is positioned with each spring 130 along its length direction. Compression force acts for each section.

더불어, 상기 그라우팅 보강유닛(100) 주위로 그라우팅재가 경화된 경우 지반 또한 상하로 압축력이 작용하는 상태를 이루게 되므로, 시공되는 터널 상측이 상부와 하부가 서로 압축된 상태를 이루므로 안정된 구조를 유지하게 된다.In addition, when the grouting material is hardened around the grouting reinforcing unit 100, the ground also forms a state in which the compressive force acts up and down, and thus the upper and lower tunnels are constructed to maintain a stable structure. do.

특히, 본 발명에 따르면 상기 압축연결모듈(110)이 구비된 위치를 기준으로 하여 일정 구간별로 압축력이 작용하게 된다. 즉, 일부 보강부재 또는 압축연결모 듈이 시간이 지남에 따라서 녹이 슬거나 파손하게 되는 일이 발생하게 되더라도, 해당 보강부재 또는 압축연결모듈이 위치된 부분에 해당하는 지반이 취약해질 뿐, 다른 압축력이 작용하고 있는 보강부재나 압축연결모듈이 구비된 구간은 압축력이 계속 작용하는 상태를 유지하게 되므로 전체적으로 종전보다 안정된 지반구조를 유지할 수 있게 된다.Particularly, according to the present invention, the compressive force acts for each section based on the position where the compression connection module 110 is provided. In other words, even if some reinforcing members or compression connection module is rusted or damaged over time, the ground corresponding to the portion where the reinforcement member or compression connection module is located becomes weak, other compression force The section provided with the reinforcing member or the compression connection module is in operation to maintain a state in which the compressive force continues to act as a whole it is possible to maintain a more stable ground structure than before.

한편, 시공되고자 할 터널의 내면이 형성되는 부위에는 유리강화 합성섬유 재질인 GRP보강부재(20)가 위치되므로, 터널의 모양을 형성하고 터널 내면을 형성하기 위한 커팅 및 절삭 작업을 하는 경우 그 작업이 종전의 스틸재질의 보강부재의 경우보다 쉽게 이루어진다.On the other hand, since the GRP reinforcing member 20, which is made of glass-reinforced synthetic fiber, is located at the site where the inner surface of the tunnel to be constructed is formed, the work when cutting and cutting to form the tunnel shape and the inner surface of the tunnel are performed. This is easier than in the case of the conventional steel reinforcement member.

즉, 상기 GRP보강부재(20)는 강한 압축력 및 인장력을 지니어 상하방향으로의 보강은 충분히 이루어지는데 반해, 전단력이 상당히 취약한 특성을 지니고 있음으로 인하여, 터널의 내측 공사 시에는 전단력이 작용하여 쉽게 깨지게 되지만, 터널이 시공된 후에는 주로 상하방향으로의 힘만을 받게 되어 보강부재로서의 역할은 충분히 수행할 수 있게 된다. That is, the GRP reinforcing member 20 has a strong compressive force and a tensile force in the vertical direction of the reinforcement is sufficiently made, while the shear force has a characteristic that is quite weak, because the shear force acts during the inner construction of the tunnel easily Although broken, after the tunnel is constructed, only the force in the vertical direction is mainly applied, so that the role of the reinforcing member can be sufficiently performed.

첨부된 도 9는 상기 압축연결모듈에 있어서, 일종의 앵커모듈을 구성하는 외부케이스의 다른 실시예를 나타낸 도면이다.9 is a view showing another embodiment of the outer case constituting a kind of anchor module in the compression connection module.

도시된 것처럼, 본 발명의 다른 실시예에 있어서 상기 앵커모듈(201)에 있어서 상기 외부케이스(211)는 천공홀의 길이방향을 따라서 양측 모든 방향에 고정되는 형태로 두 쌍의 고정편(212)이 구비될 수 있다.As shown, the outer case 211 in the anchor module 201 in another embodiment of the present invention is a pair of fixing pieces 212 in a form that is fixed in both directions along the longitudinal direction of the drilling hole It may be provided.

즉, 이와 같은 구성된 고정편(212)을 구비한 외부케이스(211)는 상기 고정 편(212)이 천공홀(H) 내부에 길이방향을 따라서 상부의 지반 방향 측으로 외부케이스가 이동되는 것을 방지함은 물론 하부에 위치되는 터널방향 측으로 외부케이스가 이동되는 것 또한 보다 확실히 방지할 수 있게 된다.That is, the outer case 211 having the fixing piece 212 configured as described above prevents the fixing piece 212 from being moved to the ground side of the upper portion along the longitudinal direction in the drilling hole H. Of course, it is also possible to more surely prevent the outer case is moved to the tunnel direction side located at the bottom.

한편, 첨부된 도면 10은 본 발명 그라우팅 보강유닛에 있어서 압축연결모듈의 다른 실시예를 도시한 것이다.On the other hand, the accompanying Figure 10 shows another embodiment of the compression connection module in the grouting reinforcement unit of the present invention.

즉, 기 서술한 본 발명의 일 실시예에서는, 도 3에 도시된 바와 같이, 일측 보강부재에 연결된 커플러(121)와 타측 보강부재에 연결된 커플러(122) 사이에 탄성부재인 코일 스프링(130)이 구성되도록 도시 및 설명되어 있으나, 도 10에서는 상기 외부케이스(111)의 내측면과 커플러(121) 사이에 코일스프링(130)이 설치되도록 한 것이다.That is, in one embodiment of the present invention described above, as shown in Figure 3, between the coupler 121 connected to one reinforcement member and the coupler 122 connected to the other reinforcement member coil spring 130 as an elastic member Although illustrated and described to be configured, in FIG. 10, the coil spring 130 is installed between the inner surface of the outer case 111 and the coupler 121.

이 경우에도, 상기 천공홀(H) 내부에 보강유닛을 설치한 후, 지반 상측의 스틸보강부재(10)를 잡아당기고 고정편(112)을 통한 고정작업 및 그라우팅 작업을 실시한 후 그라우팅 보강작업이 완료되면, 보강유닛 전체적으로는 압축력이 작용하는 상태를 이루게 된다.In this case, after the reinforcing unit is installed in the drilling hole H, the grouting reinforcing work is performed after pulling the steel reinforcing member 10 on the upper side of the ground and fixing and grouting the work through the fixing piece 112. Upon completion, the reinforcing unit as a whole achieves a state in which the compression force acts.

또한, 각각의 구간별로 압축력이 작용함도 본 발명의 일실시예와 같다. 이때, 상기 첨부된 도 10에서는 상기 압축연결모듈(210)에 있어서 외부케이스(111) 내측으로 상부에 위치된 커플러(121)와 외부케이스(111) 사이에만 코일스프링(130)이 구비된 것만 도시되어 있으나, 하부에 위치된 커플러(122)와 외부케이스(111) 사이에 코일스프링(130)이 설치되어도 같은 효과가 나타나게 되며, 양측 커플러(121,122) 각각과 상기 외부케이스(111) 사이에 코일스프링이 설치되어도 마찬가 지임은 물론이다.In addition, the compression force acting for each section is also the same as the embodiment of the present invention. 10, only the coil spring 130 is provided between the coupler 121 and the outer case 111 positioned at the upper side of the outer case 111 in the compression connection module 210. Although the coil spring 130 is installed between the coupler 122 and the outer case 111 positioned at the lower side, the same effect is obtained, and the coil spring is formed between each of the couplers 121 and 122 and the outer case 111. Of course, even if it is installed.

상기 서술한 본 발명의 다양한 실시예들에 따른 그라우팅용 보강유닛은 첨부된 도 11에 도시된 바와 같이 사면에도 적용이 가능하다.Grouting reinforcing unit according to various embodiments of the present invention described above is applicable to the slope as shown in Figure 11 attached.

이 경우에든 GRP보강부재가 사용되지 않고, 전체 보강유닛이 모두스틸보강부재로 이루어지도록 함이 바람직할 것이다.In this case, the GRP reinforcing member is not used, and it may be desirable that the entire reinforcing unit is made of all steel reinforcing members.

나아가, 본 발명은 첨부된 도 12 내지 도 15에서와 같은 또 다른 실시예에 따른 그라우팅 보강방법도 적용 가능하다.Furthermore, the present invention is also applicable to the grouting reinforcement method according to another embodiment as shown in Figure 12 to 15 attached.

이하, 본 발명의 다른 실시예에 따른 그라우팅 보강방법을 보다 자세히 설명하면 다음과 같다,Hereinafter, the grouting reinforcement method according to another embodiment of the present invention in more detail as follows.

첨부된 도 12 내지 도 15는 터널의 내측으로부터 그라우팅 보강유닛을 적용하는 그라우팅 보강방법을 나타낸 도면이다.12 to 15 are a view showing a grouting reinforcement method applying the grouting reinforcement unit from the inside of the tunnel.

먼저, 첨부된 도 12에서와 같이, 가터널을 시공한다.First, as shown in FIG. 12, a garnet is constructed.

여기서, 상기 가터널은 예를 들면 전체가 왕복 4차선으로 이루어지는 터널을 시공 시에 미리 왕복 2차선 정도의 터널을 시공하는 것을 말한다.Here, the said tunnel refers to constructing a tunnel of about two lanes in advance and the like, for example, when constructing a tunnel consisting entirely of four lanes of reciprocation.

즉, 상기 가터널이라 함은 전체 완성된 터널의 시공을 하기 전에 미리 일부 내경의 터널만을 시공하는 것으로서, 장비 등의 이송 등을 하기 위한 일종의 파일럿터널을 의미한다.In other words, the term "garnet tunnel" means to construct only a tunnel having a partial inner diameter before the construction of the entire completed tunnel, and refers to a kind of pilot tunnel for transporting equipment and the like.

상기에서와 같이, 가터널을 시공한 후에, 첨부된 도 13에 도시된 것처럼, 천공홀(H)을 천공하고 그라우팅용 보강유닛(100)을 상기 천공홀(H)에 삽입 설치한다.As described above, after the construction of the tunnel, as shown in the accompanying FIG. 13, the drilling hole (H) is drilled and the grouting reinforcing unit 100 is inserted into the drilling hole (H).

이때, 상기 그라우팅용 보강유닛(100)은 터널 내면(7)을 향하여 GRP보강부 재(20)가 위치되도록 삽입 설치된다.At this time, the grouting reinforcing unit 100 is inserted and installed so that the GRP reinforcing portion 20 is located toward the tunnel inner surface 7.

나아가, 도 14에서 점선으로 표시된 부분이 최종 굴착하고자 하는 터널의 내면(8)에 해당한다면, 상기 가터널의 내면(7)과 최종 굴착되는 터널의 내면(8) 사이에 GRP보강부재(8)가 위치되도록 한다.Furthermore, if the portion indicated by the dashed line in FIG. 14 corresponds to the inner surface 8 of the tunnel to be finally excavated, the GRP reinforcing member 8 between the inner surface 7 of the tunnel and the inner surface 8 of the tunnel to be finally excavated. To be located.

여기서, 상기 그라우팅용 보강유닛(100)을 설치하는 경우에, 상술한 실시예에서와 같이, 상기 천공홀 내부에 미리 급결 그라우팅재 등을 충진한 후 상기 그라우팅 보강유닛(100)을 삽입하여 고정시킬 수 있다.Here, in the case of installing the reinforcing unit 100 for grouting, as shown in the above-described embodiment, the grouting reinforcing unit 100 is inserted and fixed after filling the quenching grouting material, etc. in advance in the drilling hole. Can be.

그리고, 터널 내측으로 외부 돌출된 GRP보강부재(20)를 당겨 인장력을 가한 후에 그라우팅재를 삽입하고, 상기 천공홀(H) 내부에 일정위치마다 앵커모듈(100)을 이용 그라우팅용 보강유닛(100)이 고정되도록 한다.Then, after pulling out the GRP reinforcing member 20 protruding into the tunnel and applying a tensile force, the grouting material is inserted, and the grouting reinforcement unit 100 uses the anchor module 100 at predetermined positions in the drilling hole H. ) To be fixed.

상기와 같은 과정을 거쳐 천공홀 내부에 그라우팅용 보강유닛을 고정시키는 작업이 완료되면, 완성시킬 터널에 해당할 정도로 굴착하는 작업이 더 진행된다.When the work for fixing the grouting reinforcing unit in the drilling hole is completed through the process as described above, the work is carried out to the extent enough to correspond to the tunnel to be completed.

즉, 도 14에 도시된 점선 부근(8)에 이르기까지 굴착작업이 수행된다.That is, the excavation work is performed up to the vicinity of the dotted line 8 shown in FIG.

굴착이 완료된 터널을 나타낸 도면은 도 15에 도시된 바와 같다.The tunnel showing the excavation is completed as shown in FIG.

즉, 상술한 바와 같이 터널 내측으로부터 그라우팅 보강유닛을 이용 보강작업을 행하게 되는 경우에도 터널의 내면을 조금 더 절삭하거나 또는 마무리 다듬질 등을 하는 경우에는 터널 내측에는 유리섬유재질의 GRP보강유닛(20)이 설치되어 있으므로, 작업이 쉬워지게 되고 장비의 파손을 방지하게 됨은 상술한 실시예와 같다.That is, even when the reinforcing operation is performed using the grouting reinforcing unit from the inside of the tunnel as described above, when cutting the inner surface of the tunnel a little more or finishing finishing, etc., the GRP reinforcing unit 20 of the glass fiber material is formed inside the tunnel. Since it is provided, the work becomes easy and the damage of the equipment is prevented as in the above-described embodiment.

그리고, 이와 같은 그라우팅 보강방법도 첨부된 도 10에 도시된 바와 같이, 본 발명의 다른 실시예에 따른 압축연결모듈(210)이 사용된 그라우팅 보강유닛을 적용할 수도 있음은 물론이다.And, such a grouting reinforcement method is also shown in FIG. 10, of course, can be applied to the grouting reinforcement unit used compression connection module 210 according to another embodiment of the present invention.

이상과 같이 본 발명에 따른 바람직한 실시예를 살펴보았으며, 앞서 설명된 실시예 이외에도 본 발명이 그 취지나 범주에서 벗어남이 없이 다른 특정 형태로 구체화 될 수 있다는 사실은 해당 기술에 통상의 지식을 가진 이들에게는 자명한 것이다. 그러므로, 상술된 실시예는 제한적인 것이 아니라 예시적인 것으로 여겨져야 하고, 이에 따라 본 발명은 상술한 설명에 한정되지 않고 첨부된 청구항의 범주 및 그 동등 범위 내에서 변경될 수도 있다.As described above, the preferred embodiments of the present invention have been described, and the fact that the present invention can be embodied in other specific forms in addition to the above-described embodiments without departing from the spirit or scope thereof has ordinary skill in the art. It is obvious to them. Therefore, the above-described embodiments should be regarded as illustrative rather than restrictive, and thus, the present invention is not limited to the above description and may be modified within the scope of the appended claims and their equivalents.

예를 들면, 상기 앵커모듈은 이해 및 설명의 편의를 위하여 간단한 형태를 예로 들어 도시 및 설명하고 있으나, 본 발명과 마찬가지의 효과를 내는 같은 원리의 다른 앵커모듈이 사용될 수도 있을 것이다.For example, the anchor module is illustrated and described by way of example in order to facilitate understanding and explanation, but other anchor modules of the same principle that produce the same effect as the present invention may be used.

도 1은 종래 기술에 따른 그라우팅 보강공법이 시행되는 터널을 개략적으로 나타낸 단면도;1 is a cross-sectional view schematically showing a tunnel in which the grouting reinforcement method according to the prior art is implemented;

도 2는 종래 기술에 따른 그라우팅 보강공법이 시행되는 모습을 설명하기 위한 확대도;Figure 2 is an enlarged view for explaining how the grouting reinforcement method according to the prior art is implemented;

도 3은 본 발명의 일 실시예에 따른 그라우팅 보강유닛을 나타낸 도면;3 is a view showing a grouting reinforcing unit according to an embodiment of the present invention;

도 4는 터널의 시공을 위하여 지반 상측에 천공홀이 천공된 모습을 개략적으로 나타낸 단면도;Figure 4 is a schematic cross-sectional view showing a drilled hole in the upper ground for the construction of the tunnel;

도 5 내지 도 7은 본 발명의 일 실시예에 따른 그라우팅 보강유닛을 이용 그라우팅 보강공법이 행하여지는 과정을 순서대로 나타낸 도면들;5 to 7 are views showing a sequence in which a grouting reinforcement method is performed using a grouting reinforcing unit according to an embodiment of the present invention;

도 8은 본 발명에 따른 그라우팅 보강공법을 나타낸 순서도;8 is a flow chart showing a grouting reinforcement method according to the invention;

도 9는 본 발명에 있어서 앵커모듈의 다른 실시예를 개략적으로 나타낸 도면;9 is a view schematically showing another embodiment of an anchor module in the present invention;

도 10은 본 발명의 다른 실시예에 따른 그라우팅 보강유닛을 나타낸 단면도; 10 is a cross-sectional view showing a grouting reinforcing unit according to another embodiment of the present invention;

도 11은 사면구조의 지형에 본 발명 그라우팅 보강유닛을 적용한 모습을 나타낸 도면; 및11 is a view showing a state in which the present invention grouting reinforcement unit is applied to the topography of the slope structure; And

도 12 내지 도 15는 본 발명의 또 다른 실시예에 따른 그라우팅 보강유닛이 적용된 터널구조를 나타낸 단면도이다.12 to 15 are cross-sectional views showing a tunnel structure to which the grouting reinforcement unit is applied according to another embodiment of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10,20: 보강부재 100: 그라우팅 보강유닛10,20: reinforcing member 100: grouting reinforcing unit

101: 앵커모듈 110: 압축연결모듈101: anchor module 110: compression connection module

111: 외부케이스 112: 고정편111: outer case 112: fixing piece

115: 스프링 121,122: 커플러115: spring 121,122: coupler

130: 코일스프링 150: 가압밴드130: coil spring 150: pressure band

Claims (12)

지반에 형성시킨 천공홀을 이용 그라우팅 작업을 하기 위한 보강유닛에 있어서,In the reinforcing unit for grouting work using the drilled hole formed in the ground, 상기 천공홀에 삽입되는 적어도 두 개 이상의 보강부재; 및At least two reinforcing members inserted into the drilling holes; And 상기 각각의 보강부재 사이에 위치되어 그라우팅 작업이 완료된 후에 상기 보강부재 사이에 압축력이 작용하도록 연결되는 압축연결모듈;A compression connection module positioned between each of the reinforcing members and connected to the compressive force between the reinforcing members after the grouting operation is completed; 을 포함하여 구성되는 그라우팅용 보강유닛.Grouting reinforcement unit comprising a. 제1항에 있어서,The method of claim 1, 상기 천공홀에 최선으로 삽입되도록 연결되는 GRP(Glass Reinforced Plastic)보강부재를 더 포함한 것을 특징으로 하는 그라우팅용 보강유닛.Grouting reinforcement unit characterized in that it further comprises a GRP (Glass Reinforced Plastic) reinforcing member connected to be inserted into the drilling hole best. 제1항에 있어서,The method of claim 1, 상기 압축연결모듈은,The compression connection module, 상기 보강부재의 길이방향을 기준으로 양측으로 각각 상기 보강부재의 일단이 길이방향을 따라 슬라이딩 이동 가능하게 연결되는 외부케이스; An outer case to which one end of the reinforcing member is slidably moved along the length direction to both sides with respect to the longitudinal direction of the reinforcing member; 상기 보강부재의 일단부가 연결됨과 동시에 상기 외부케이스 내측에 상기 보강부재와 함께 슬라이딩 이동 가능하게 구비되는 커플러; 및A coupler coupled to one end of the reinforcing member and slidably movable together with the reinforcing member inside the outer case; And 상기 외부케이스 내측에 구비되어 상기 보강부재를 길이방향 외측으로 잡아 당긴 경우 상기 보강부재가 다시 원래의 위치로 돌아가는 복원력을 가하는 탄성부재;An elastic member provided inside the outer case to apply a restoring force to return the reinforcing member to its original position when the reinforcing member is pulled outward in the longitudinal direction; 를 포함하여 구성되는 것을 특징으로 하는 그라우팅용 보강유닛.Grouting reinforcement unit, characterized in that comprises a. 제3항에 있어서,The method of claim 3, 상기 탄성부재는 코일 스프링으로 형성되며,The elastic member is formed of a coil spring, 상기 한 쌍의 커플러 사이에 구비됨과 동시에 코일 스프링의 일측과 타측이 각각 상기 커플러에 고정된 것을 특징으로 하는 그라우팅용 보강유닛.Grouting reinforcement unit, characterized in that provided between the pair of couplers and at the same time one side and the other side of the coil spring is fixed to the coupler. 제3항에 있어서,The method of claim 3, 상기 탄성부재는 코일스프링으로 형성되며,The elastic member is formed of a coil spring, 상기 커플러와 상기 외부케이스 사이에 구비된 것을 특징으로 하는 그라우팅용 보강유닛.Grouting reinforcement unit, characterized in that provided between the coupler and the outer case. 제3항에 있어서,The method of claim 3, 상기 외부케이스는,The outer case, 상기 천공홀의 내측에 고정되도록 상기 외부케이스 외측으로 고정편을 더 포함하여 구성된 것을 특징으로 하는 그라우팅용 보강유닛.Grouting reinforcement unit, characterized in that it further comprises a fixing piece to the outside of the outer case to be fixed to the inside of the drilling hole. 제6항에 있어서,The method of claim 6, 상기 고정편은,The fixing piece, 상기 외부케이스에 회전 가능하게 힌지결합되고,Rotatably hinged to the outer case, 상기 고정편과 외부케이스 사이에는 상기 고정편에 외력을 작용하지 않는 경우 천공홀 내측에 맞닿도록 상기 고정편이 회전 이동하도록 하는 탄성부를 더 구비하는 것을 특징으로 하는 그라우팅용 보강유닛.Grouting reinforcing unit between the fixing piece and the outer case further comprises an elastic portion for rotating the fixing piece to abut on the inner side of the hole when the external force is not applied to the fixing piece. 제2항에 있어서,The method of claim 2, 상기 천공홀에 최선으로 삽입되는 GRP(Glass Reinforced Plastic)보강부재와 상기 스틸보강부재는 상기 압축연결유닛에 의하여 연결되는 것을 특징으로 하는 그라우팅용 보강유닛.GRP (Glass Reinforced Plastic) reinforcing member and the steel reinforcing member that is best inserted into the drilling hole is connected by the compression connecting unit. 청구항 1 내지 청구항 8항 중 어느 한 항에 기재된 그라우팅 보강유닛을 이용하여 행하는 그라우팅 방법에 있어서,In the grouting method performed using the grouting reinforcing unit according to any one of claims 1 to 8, 지반에 천공홀을 천공하는 단계;Drilling a hole in the ground; 상기 천공홀에 급결 그라우팅재를 충진하는 단계;Filling a fastening grouting material into the drilling hole; 상기 급결 그라우팅재가 충진된 천공홀에 상기 그라우팅 보강유닛을 삽입하는 단계;Inserting the grouting reinforcing unit into the drilling hole filled with the quick grouting material; 상기 그라우팅 보강유닛이 삽입된 천공홀에 그라우팅재를 삽입하는 단계; 및Inserting a grouting material into the drilling hole into which the grouting reinforcing unit is inserted; And 상기 천공홀에 삽입된 그라우팅 보강유닛에 있어서 지면 외측에 위치된 보강유닛을 잡아당겨 고정시키는 단계;Pulling and fixing the reinforcing unit positioned outside the ground in the grouting reinforcing unit inserted into the drilling hole; 를 포함하여 이루어진 그라우팅 보강방법.Grouting reinforcement method comprising a. 제9항에 있어서,10. The method of claim 9, 상기 고정편을 이용하여 천공홀 내측에 고정시키는 단계를 더 포함하여 구성된 것을 특징으로 하는 그라우팅 보강방법.Grouting reinforcement method characterized in that it further comprises the step of fixing to the inside of the drilling hole using the fixing piece. 청구항 1 내지 청구항 8항 중 어느 한 항에 기재된 그라우팅 보강유닛을 이용하여 행하는 그라우팅 방법에 있어서,In the grouting method performed using the grouting reinforcing unit according to any one of claims 1 to 8, 터널을 가시공하는 단계;Burrowing the tunnel; 상기 가시공된 터널의 내측으로부터 지면 측으로 천공홀을 천공하는 단계;Drilling a drilling hole from an inner side of the visible tunnel to a ground side; 상기 천공홀에 일단부에는 GRP보강부재가 구비되며 그 외 부분에는 다수개의 스틸보강부재가 연결된 상태의 그라우팅 보강유닛을 상기 GRP보강부재가 터널 내측을 향한 상태를 이루도록 삽입하는 단계;Inserting a grout reinforcing unit having a GRP reinforcing member connected to a plurality of steel reinforcing members at one end of the perforation hole, and a plurality of steel reinforcing members connected to the GRP reinforcing member toward the inside of the tunnel; 상기 그라우팅 보강유닛이 삽입된 천공홀에 그라우팅재를 삽입하는 단계; 및Inserting a grouting material into the drilling hole into which the grouting reinforcing unit is inserted; And 상기 천공홀에 삽입된 그라우팅 보강유닛에 있어서 터널 내측에 위치된 GRP보강부재를 잡아당겨 고정시키는 단계;Pulling and fixing the GRP reinforcing member located inside the tunnel in the grouting reinforcing unit inserted into the drilling hole; 를 포함하여 이루어진 그라우팅 보강방법.Grouting reinforcement method comprising a. 제11항에 있어서,The method of claim 11, 상기 고정편을 이용하여 천공홀 내측에 고정시키는 단계를 더 포함하여 구성 된 것을 특징으로 하는 그라우팅 보강방법.Grouting reinforcement method characterized in that it further comprises the step of fixing to the inside of the drilling hole using the fixing piece.
KR1020090050932A 2009-06-09 2009-06-09 Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same KR101079075B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090050932A KR101079075B1 (en) 2009-06-09 2009-06-09 Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090050932A KR101079075B1 (en) 2009-06-09 2009-06-09 Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same

Publications (2)

Publication Number Publication Date
KR20100132222A true KR20100132222A (en) 2010-12-17
KR101079075B1 KR101079075B1 (en) 2011-11-02

Family

ID=43507942

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090050932A KR101079075B1 (en) 2009-06-09 2009-06-09 Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same

Country Status (1)

Country Link
KR (1) KR101079075B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536283A (en) * 2012-02-24 2012-07-04 安徽理工大学 Retractable constant force yielding anchor bolt for dynamical pressure soft rock lane
CN105863695A (en) * 2016-05-03 2016-08-17 许国安 Sectional and modular combined anchor rod capable of resisting large deformation and impact and assembling method of combined anchor rod
CN110470269A (en) * 2019-08-21 2019-11-19 山东大学 Reinforcing laneway prediction scheme is comprehensive to determine method
KR102604502B1 (en) * 2023-07-17 2023-11-20 이광영 Improved Support Material Interference steel pipe and construction method using the same
KR102604497B1 (en) * 2023-07-17 2023-11-20 이광영 Simultaneous Injection Coking Type steel pipe and construction method using the same

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002294702A (en) * 2001-03-29 2002-10-09 Sanshin Corp Coupling construction between casing packer device for ground anchor and tension member
KR200359013Y1 (en) 2004-05-07 2004-08-21 (주) 코리아에스이 Ground Anchor having Reinforcement for Grouting Concrete
JP2006299546A (en) 2005-04-18 2006-11-02 Usei Sho Rock bolt

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536283A (en) * 2012-02-24 2012-07-04 安徽理工大学 Retractable constant force yielding anchor bolt for dynamical pressure soft rock lane
CN102536283B (en) * 2012-02-24 2014-03-05 安徽理工大学 Retractable constant force yielding anchor bolt for dynamical pressure soft rock lane
CN105863695A (en) * 2016-05-03 2016-08-17 许国安 Sectional and modular combined anchor rod capable of resisting large deformation and impact and assembling method of combined anchor rod
CN105863695B (en) * 2016-05-03 2017-11-03 许国安 A kind of anti-large deformation of sectional modular and shock resistance assembled bolt and its assemble method
CN110470269A (en) * 2019-08-21 2019-11-19 山东大学 Reinforcing laneway prediction scheme is comprehensive to determine method
CN110470269B (en) * 2019-08-21 2021-04-16 山东大学 Comprehensive determination method for roadway reinforcement plan
KR102604502B1 (en) * 2023-07-17 2023-11-20 이광영 Improved Support Material Interference steel pipe and construction method using the same
KR102604497B1 (en) * 2023-07-17 2023-11-20 이광영 Simultaneous Injection Coking Type steel pipe and construction method using the same

Also Published As

Publication number Publication date
KR101079075B1 (en) 2011-11-02

Similar Documents

Publication Publication Date Title
KR101079075B1 (en) Reinforce Unit For Grouting And Grouting Reinforce Method Using The Same
KR101605028B1 (en) Structure of Permanent Anchor
KR20170102397A (en) The Tunnel construction method to use retangular pipe
KR101781475B1 (en) Reinforcing member for ground and timbering method using the same thing
KR101402267B1 (en) Close juxtaposition tunnel pillar reinforcement structure and its construction methods
KR100971147B1 (en) Reinforce unit for grouting and soil nailing reinforce method using the same
KR100937237B1 (en) Multiple soil-nailing ground reinforcement apparatus and multiple soil-nailing method
KR101023477B1 (en) Pressed grouting soil nailing body
KR101048628B1 (en) Upper sealing cover and lower sealing cover for soli nailing unit, soil nailing unit having the same and soil nailing reinforce method using the same
KR101236765B1 (en) Method for placing adhesive filling into the expanded drill hole to increase bearing capacity of piles and tention members and apparatus therefor
JP6872231B2 (en) Reinforcement structure of rock slope with long-term durability and its construction method
KR102478561B1 (en) Connector with insertion groove for wale and strut of earth retaining wall
KR101029320B1 (en) Rock bolt and fixation method the rock bolt
KR101665516B1 (en) Construction method of duel tunnel using composite capable of bidirectional tensioning, pressure casting and tiebolting, and its duel tunnel
KR20130029906A (en) An expanding device of frictional force
JP2016020569A (en) Concrete box body used for open shield method
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR101161214B1 (en) Reinforcement means for soft land and slope reinforcement methode using the same
KR101864857B1 (en) Construction method of foundation pile with reinforced casing structure
KR101460180B1 (en) Nail connectors for soil nailing method
KR101165692B1 (en) Multipurpose anchor and construction method thereof
KR101293237B1 (en) Apparatus of fixing cover for ground anchor
KR100951872B1 (en) The ground reinforcement apparatus and ground reinforcement method
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
JP6254657B1 (en) Flexible joint structure of concrete box

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141010

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20151028

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161028

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee