KR20100100165A - Slab top-down method of underground construction - Google Patents

Slab top-down method of underground construction Download PDF

Info

Publication number
KR20100100165A
KR20100100165A KR1020090018889A KR20090018889A KR20100100165A KR 20100100165 A KR20100100165 A KR 20100100165A KR 1020090018889 A KR1020090018889 A KR 1020090018889A KR 20090018889 A KR20090018889 A KR 20090018889A KR 20100100165 A KR20100100165 A KR 20100100165A
Authority
KR
South Korea
Prior art keywords
slab
underground
fixing
ground
construction method
Prior art date
Application number
KR1020090018889A
Other languages
Korean (ko)
Other versions
KR101044441B1 (en
Inventor
이세환
이예리
Original Assignee
이세환
이예리
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이세환, 이예리 filed Critical 이세환
Priority to KR1020090018889A priority Critical patent/KR101044441B1/en
Publication of KR20100100165A publication Critical patent/KR20100100165A/en
Application granted granted Critical
Publication of KR101044441B1 publication Critical patent/KR101044441B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Abstract

PURPOSE: A reverse direction construction method of an underground structure is provided to reduce production times and costs by the formation of a slab on concrete. CONSTITUTION: A reverse direction construction method of an underground structure comprises following steps. An underground continuous wall is formed on an underground position where an underground outer wall will be formed, so that an underground outer line may be formed(S10). Multiple center piles are built in the surface divided by the underground continuous wall, so that a base frame of a post is formed(S20). Two or more slabs forming the bottom surface of each under layer are laminated to move along multiple center piles(S30).

Description

지하 구조물의 역방향 축조방법{Slab top-down method of underground construction}Slab top-down method of underground construction

본 발명은 지하 구조물의 축조방법에 관한 것으로, 더욱 상세하게는 지하 구조물을 상부에서 하부방향으로 축조하되, 다수의 슬래브를 상호 이격될 수 있도록 적층시켜 형성하고, 그 슬래브 하측을 필요 깊이만큼 굴착 후 적층된 슬래브를 하측으로 이동시킨 다음, 설치함에 따라 작업공정을 감소시킬 수 있고, 작업시간을 단축시키며, 공정의 감소에 의해 폐기물을 감소시킴은 물론, 비용을 감소시켜 작업의 효율성을 향상시킬 수 있는 지하 구조물의 역방향 축조방법에 관한 것이다.The present invention relates to a method for constructing an underground structure, and more particularly, the underground structure is constructed from the top to the bottom direction, and is formed by stacking a plurality of slabs to be spaced apart from each other, and excavating the lower side of the slab to a required depth. By moving the laminated slab downwards, the installation can reduce the work process, reduce the working time, reduce waste by reducing the process, and reduce the cost, thereby improving the work efficiency. The present invention relates to a reverse construction method of underground structures.

일반적으로, 지하층 축조 시 다양한 기술이 사용되고 있으나 이 중에서 흙막이벽 공법으로는 엄지말뚝 토류벽, Sheet Pile, 현장타설 콘크리트말뚝 (CIP cast in place pile), DW(diaphragm wall-일명 Slurry wall)공법이 있다.In general, various techniques are used in the construction of the basement, but among them, the earthquake wall method includes a thumb pile earth wall, a sheet pile, a cast-in-place concrete pile, and a diaphragm wall (aka slurry wall) method.

그리고 흙막이벽 지지공법에는 Earth Anchor(인장 앵커 지지방식), Strut 방식(압축 버팀대 지지방식), SPS공법(Permanent Structural Members As Temporary Strut ), IPS 공법, SLS 공법 등이 있고, 지하층 구조물의 거푸집 형식으로는 동바 리와 일반 거푸집, 메달기 형틀공법 및 Deck Plate등이 사용되고 있다.In addition, earth wall support methods include Earth Anchor (tension anchor support method), Strut method (compression brace support method), SPS method (Permanent Structural Members As Temporary Strut), IPS method, SLS method, etc. Foreground, general formwork, medal formwork and deck plate are used.

여기서 strut식 등의 흙막이벽 지지공법은 영구구조물이 축조되기 전 토압을 지지하기 위한 임시구조물로서 지하층의 터파기 공사 및 골조 공사 시 장애요인이 될 뿐 아니라 구조물 축조 후 해체되어야 하므로 공사비 증가와 골조품질 저하 및 공사기일 증가 등의 문제점을 발생시키는 요인이 된다.Here, the strut wall support method such as strut type is a temporary structure to support earth pressure before the permanent structure is constructed. It is not only an obstacle for the excavation and framing work in the basement layer, but also needs to be dismantled after the construction of the structure. It is a factor that causes problems such as deterioration and increase of construction date.

이와 같은 문제점을 해소하기 위해 역타설(Top-Down 방향)공법이 사용되는데, 이 역타설 공법은 지하의 영구구조물을 상부에서 하부방향으로, 소요위치에 축조하여 축조된 영구구조물로 지하외벽에 작용하는 수압 및 토압을 지지하는 공법이다.In order to solve this problem, the reverse casting method is used. The reverse casting method is a permanent structure constructed by constructing the underground permanent structure from the upper side to the lower direction and at the required position. It is a method of supporting hydraulic pressure and earth pressure.

이 역타설 공법은 영구구조물을 지하에 역타로 축조하기 위하여 지하의 밀폐된 공간 내에서 거푸집작업, 철근작업, 콘크리트 타설 작업 또는 철골조립 및 설치작업을 수행하여야 하며, 이러한 작업의 수행을 위해 자재의 운반, 작업조건 등에 의하여 크게 제약을 받아 생산성이 저하되는 문제점이 있다.In order to construct a permanent structure with a back ground, this reverse casting method must perform formwork, reinforcing work, concrete pouring work or steel frame assembly and installation work in a closed space underground. There is a problem in that productivity is greatly reduced due to transportation, working conditions, and the like.

또한 타설 된 콘크리트가 양생되어 소요강도를 확보하기 이전(통상 28일 소요)에는 하부로 굴착작업이 불가능하여 지하층 구축에 소요되는 공사비가 커지고 공사기간이 길어질 수밖에 없는 실정이었다.In addition, before the cast concrete was cured and secured the required strength (usually 28 days), the excavation work was impossible at the bottom, which required the construction cost to be increased and the construction period to be long.

최근에 개발된 SPS 공법은 건축물에 영구 사용되는 철골 및 기둥만으로 지하연속벽에 작용되는 토압 및 수압을 지지한다는 개념에서 출발하였으나, 지하구조물 중 철골보 및 기둥만으로 형성된 골조형식으로는 지하에서 작용하는 토압 및 수압에 대응하기에는 턱없이 부족하였다.Recently developed SPS method started from the concept of supporting the earth pressure and hydraulic pressure acting on the underground continuous wall only with steel frames and pillars permanently used in the building, but the earth pressure acting underground with the skeleton type formed only of steel beams and columns among the underground structures. And insufficiently to cope with hydraulic pressure.

이를 극복하기 위해 지하층 철골 설치 후 Deck Plate를 사용하여 슬래브를 타설함에 따라 구축된 슬래브에 의하여 토압 및 수압을 지지하고 있으나, 이 방식은 최초의 의도와는 전혀 다른 기술자에게 범용된 역타설 공법의 한 변형형태가 되었으며, 지하의 밀폐된 공간 내에서 철골조립작업, 현장용접작업, Deck Plate 설치작업, 철근배근 작업, 콘크리트 타설 작업 등을 하여야 하므로 많은 문제점이 발생된다.In order to overcome this problem, the earth pressure and water pressure are supported by the slab constructed by using the deck plate after installing the basement steel frame. It has become a deformed form, and many problems occur because steel frame assembly work, field welding work, deck plate installation work, reinforcement work, concrete placing work, etc. must be performed in an enclosed space underground.

이에 본 발명은 상기와 같은 문제점들을 해소하기 위해 안출된 것으로써, 역방향 공법으로 지하구조물을 축조하되, 각 층을 이루는 슬래브를 상호 분리 가능하도록 적층 형성하고, 상기 슬래브의 하측 지면을 일정깊이 굴착하여 슬래브를 이동 및 설치함에 따라 작업공정 및 시간이 감소된다.In order to solve the above problems, the present invention is to construct an underground structure by a reverse method, but to form a stack so that each layer of the slab can be separated from each other, and to excavate the lower ground of the slab to a certain depth Moving and installing the slab reduces the workflow and time.

특히, 슬래브를 별도의 거푸집이나 동바리 없이 지면 위에 타설된 거푸집용 버림 콘크리트 상에서 형성시킴에 따라 생산기간 및 생산비를 절감시킬 수 있다.In particular, it is possible to reduce the production period and production cost by forming the slab on the formwork cast-away concrete placed on the ground without a separate formwork or club.

또한 하향이동되어 각 층을 이루는 슬래브가 지하연속벽의 토압 및 수압을 지지할 수 있어 종래 별도의 가설재 및 철골골조 등의 보강부재의 사용을 생략할 수 있다.In addition, the slab constituting each layer is moved downward to support the earth pressure and water pressure of the continuous wall of the underground can be omitted the use of reinforcement members such as conventional temporary construction materials and steel frame.

그리고 슬래브의 일부를 자재, 토사 및 장비 반출입용 개구부를 형성하여 지면 굴착 시, 개방된 슬래브를 통해 굴착이 이루어짐에 따라 굴착이 용이하고, 종래 발생되는 소음 및 먼지 등의 발생을 감소시킬 수 있다.And by forming a part of the slab openings for carrying out materials, earth and sand equipment, when the ground is excavated, the excavation is easy as the excavation is made through the open slab, it is possible to reduce the occurrence of noise and dust conventionally generated.

이에 따라, 지하 구조물을 축조함에 있어서, 종래보다 공정 및 시간이 감소되고, 비용을 절감시킬 수 있기 때문에 작업 효율성을 향상시킬 수 있는 지하 구조물의 역방향 축조방법을 제공하는 것이 목적이다.Accordingly, in the construction of underground structures, it is an object to provide a reverse construction method of underground structures that can improve the work efficiency because the process and time can be reduced and the cost can be reduced than before.

상기 목적을 이루기 위한 본 발명은, 지하외벽이 형성될 지하위치에 지하연 속벽을 형성하여 지하 외곽라인을 형성하는 지하연속벽 형성단계, 상기 지하연속벽에 의해 구획된 지면에 다수의 센터파일(center pile)을 축조하여 기둥의 기본틀을 형성시키는 센터파일 축조단계, 각 지하층의 바닥면을 이루는 슬래브를 상기 다수의 센터파일을 따라 이동될 수 있도록 적어도 두 개 이상 적층 형성되는 적층 슬래브 형성단계, 및 상기 다수 개 적층된 슬래브를 하측으로 이동시키며, 각 슬래브가 각 층의 위치에 설치되되, 지면 굴착과 슬래브 하향이동 및 설치가 반복적으로 이루어지는 슬래브 설치단계를 포함하여 이루어진다.In order to achieve the above object, the present invention provides an underground continuous wall forming step of forming an underground outer line by forming an underground outer continuous wall at an underground location in which an underground outer wall is to be formed, and a plurality of center piles on the ground partitioned by the underground continuous wall ( a center pile construction step of forming a base frame of the pillar by constructing a center pile, a stacking slab forming step of stacking at least two slabs which form a bottom surface of each basement layer to be moved along the plurality of center piles; And moving the plurality of stacked slabs to the lower side, each slab is installed in the position of each layer, including the slab installation step is repeatedly carried out the ground excavation and slab downward movement and installation.

바람직하게, 상기 적층 슬래브 형성단계에서는, 형성하고자 하는 층의 개수에 따라 상기 슬래브의 형성 개수가 결정되고, 상기 각 슬래브 사이에는 박리부재에 의해 상호 분리 가능하도록 적층 형성된다.Preferably, in the laminated slab forming step, the number of formation of the slab is determined according to the number of layers to be formed, and is laminated between the slabs so as to be separated from each other by a peeling member.

그리고 상기 다수의 슬래브 중 최상단에 위치한 슬래브의 상면이 지면과 수평을 이루도록 지면을 하측으로 굴착 평탄작업을 한 후, 굴착된 지면 상에 거푸집용 버림 콘크리트를 타설하여 상기 다수의 슬래브를 형성시킨다.After the excavation and flattening of the ground downward so that the upper surface of the slab located at the top of the plurality of slabs horizontal with the ground, the cast concrete is cast on the excavated ground to form the plurality of slabs.

또한, 상기 박리부재는 박리제와 비닐 및 필름 중 선택된 어느 하나 이상이다.In addition, the release member is at least one selected from a release agent, vinyl and a film.

그리고 상기 센터파일이 관통되도록 슬래브에 고정공이 통공되고, 상기 고정공의 내측면 내부에는 보강프레임이 더 구비되되, 상기 보강프레임은 상단부와 하단부의 형상이 대칭되도록 형성된다.A fixing hole is passed through the slab so that the center pile is penetrated, and a reinforcing frame is further provided inside the inner surface of the fixing hole, and the reinforcing frame is formed so that the shape of the upper end and the lower end is symmetrical.

또한, 상기 슬래브의 내부에 인장철근이나 인장강선이 체크무늬 형상으로 배열된 쳐짐방지부재가 더 구비되어 다수의 센터파일에 고정된 상기 슬래브 중 어느 하나의 센서파일에서 분리되어 지지력이 손실될 경우, 상기 쳐짐방지부재가 인접한 다른 센터파일에 지지되어 쳐짐을 방지함에 따라 상기 슬래브의 붕괴를 방지한다.In addition, when the reinforcement member or the deflection prevention member is arranged in a checkered shape in the interior of the slab is separated from any one of the sensor pile of the slab fixed to a plurality of center piles when the support force is lost, The deflection prevention member is supported by another adjacent center pile to prevent the deflection of the slab.

그리고 상기 슬래브 설치단계는, 상기 슬래브 형성단계에서 형성된 다수의 슬래브 중 최상단에 위치한 슬래브를 상기 지하연속벽과 센터파일에 고정시키는 슬래브 고정단계, 상기 다수 개 형성된 슬래브의 하측 지면을 한 층 깊이 이상 굴착시키는 지면 굴착단계, 및 상기 슬래브 고정단계에서 고정되지 않은 다수의 슬래브 중 최상단의 슬래브가 상기 고정된 슬래브와 한 층 높이 간격으로 이격되도록 하측으로 이동되는 슬래브 이동단계를 포함하여 이루어지고, 상기 슬래브 고정단계와 지면 굴착단계 및 슬래브 이동단계가 반복된다.And the slab installation step, the slab fixing step for fixing the slab located at the top of the plurality of slabs formed in the slab forming step to the underground continuous wall and the center pile, excavating the lower ground of the plurality of formed slabs more than one layer deep Ground slab excavation step, and a slab movement step of moving the lower side of the slab that is not fixed in the slab fixing step is moved downwardly spaced at a height interval with the fixed slab, the slab fixed The step, the ground excavation step and the slab movement step are repeated.

또한, 상기 슬래브 고정단계에서, 상기 센터파일이 관통되는 슬래브 고정공의 내측면은 하측으로 갈수록 외측으로 경사지게 형성되고, 상기 센터파일에는 상기 고정공의 내측면과 대응되도록 외측면을 갖는 고정편이 구비되어 상호 끼워지며, 상기 슬래브의 가장자리는 상기 지하연속벽과 콘크리트에 의해 타설시킨다.In addition, in the slab fixing step, the inner surface of the slab fixing hole through which the center pile is penetrated is formed to be inclined outward toward the lower side, the center pile is provided with a fixing piece having an outer surface to correspond to the inner surface of the fixing hole. And the edges of the slab are cast by the underground continuous wall and concrete.

그리고 상기 슬래브의 고정공과 고정편 주변에 철근과 콘크리트 또는 그라우팅(Grouting) 등을 이용하여 더욱 견고하게 고정시킨다.And it is more firmly fixed using reinforcing bars and concrete or grouting around the fixing hole and the fixing piece of the slab.

또한, 상기 슬래브 고정단계에서, 상기 센터파일과 슬래브를 절곡된 센터고정플레이트를 이용하여 용접 등으로 고정시키되, 상기 슬래브의 상면과 하면 중 선택된 어느 하나 이상에 고정되고, 상기 센터고정플레이트가 구비된 센터파일의 외측은 콘크리트에 의해 고정된다.In the slab fixing step, the center pile and the slab are fixed by welding using a bent center fixing plate, which is fixed to at least one selected from an upper surface and a lower surface of the slab, and the center fixing plate is provided. The outside of the center pile is fixed by concrete.

그리고 상기 슬래브의 가장자리 측면에는 내설된 하나 이상의 철근이 외측으 로 돌출되거나 상기 내설된 철근과 연결되어 외측으로 돌출되는 고정볼트가 구비되고, 상기 철근이나 고정보트의 단부가 상기 연속벽과 닿은 후, 콘크리트 등에 의해 고정됨에 따라 상기 슬래브의 측면이 상기 연속벽과 고정된다.And the side of the edge of the slab is provided with a fixing bolt protruding outward or connected to the inner reinforcement of one or more reinforcement bar is provided, and the end of the reinforcing bar or high information contact the continuous wall, As fixed by concrete or the like, the side surface of the slab is fixed to the continuous wall.

또한, 상기 슬래브의 측단부에는 상단 또는 하단이 회전 가능하도록 연결된 측면고정플레이트가 더 구비되어 콘크리트 타설 시, 거푸집 역할을 한다.In addition, the side end portion of the slab is further provided with a side fixing plate connected to the top or the bottom so as to be rotatable, when casting concrete, serves as a formwork.

그리고 상기 지면 굴착단계는, 상기 형성된 슬래브의 일부를 개폐 가능하도록 형성하고, 상기 슬래브의 일부를 개방하여 그 하측 지면을 굴착한다.And the ground excavation step is formed to open and close a portion of the formed slab, and opens a portion of the slab to excavate the lower ground.

또한, 상기 슬래브 이동단계에서, 상기 적층된 슬라브와 굴착된 지면 사이에 기체에 의해 팽창 및 수축되는 구션부가 더 구비된다.In addition, in the slab movement step, there is further provided a section that is expanded and contracted by the gas between the laminated slab and the excavated ground.

상기한 바와 같이, 본 발명에 의한 지하 구조물의 역방향 축조방법에 의하면, 별도의 거푸집이 필요하지 않고, 품질관리가 용이하며, 작업공정의 단축에 의해 폐기물 발생이 감소되어 환경 친화적이고, 각 적층 슬래브 형성 시 외기에 노출되는 부위가 적어 동계 및 우기에도 작업이 가능하여 전천후 시공이 가능하다.As described above, according to the reverse construction method of the underground structure according to the present invention, there is no need for a separate formwork, quality control is easy, waste generation is reduced by shortening the work process, environmentally friendly, each laminated slab It is possible to work in winter and rainy season because there are few parts exposed to outside air at the time of formation, so all weather construction is possible.

또한 적층 슬래브 형성 시, 최하단부 슬래브가 지면에 의해 지지됨에 따라 각 슬래브를 연속적으로 신속하게 형성할 수 있으며, 하강된 슬래브가 지하연속벽에 작용되는 토압 및 수압을 지지함에 따라 별도의 흙막이 지지용 가설구조물이나 철골보 등의 축조를 생략할 수 있다.In addition, when the laminated slab is formed, each slab can be formed quickly and continuously as the bottom slab is supported by the ground, and a separate soil film supporting hypothesis is provided as the lowered slab supports the earth pressure and water pressure acting on the underground continuous wall. Construction of structures or steel golbo can be omitted.

이러한 하강된 슬래브에 의하여 지하구조물의 골조형식이 플랫 플레이 트(Flat Plate) 또는 플랫 슬래브(Flat Slab) 형식이 가능하고, 종래에 비해 층고가 감소되어 지하 굴착 토공물량이 적어지며, 지반이 암반일 경우 암반 터파기 물량이 최소화되므로, 종래보다 비용의 절감은 물론, 작업시간을 단축시킬 수 있어 작업 효율성을 향상시킬 수 있게 하는 매우 유용하고 효과적인 발명이다.Due to the lowered slab, the frame structure of the underground structure can be flat plate or flat slab type, and the height of the excavated earth excavation is reduced due to the reduced height compared to the conventional structure. In this case, since the amount of rock rupture is minimized, it is a very useful and effective invention that can reduce the cost and shorten the working time than before, thereby improving work efficiency.

이하, 본 발명의 바람직한 실시 예를 첨부된 도면을 참조하여 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

또한, 본 실시 예는 본 발명의 권리범위를 한정하는 것은 아니고 단지 예시로 제시된 것이며, 그 기술적 요지를 이탈하지 않는 범위 내에서 다양한 변경이 가능하다.In addition, the present embodiment is not intended to limit the scope of the present invention, but is presented by way of example only, and various modifications may be made without departing from the technical gist of the present invention.

도 1은 본 발명에 따른 지하 구조물의 역방향 축조방법의 순서도를 도시한 도면이고, 도 2는 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 설치단계의 순서도를 도시한 도면이며, 도 3은 본 발명에 따른 지하 구조물의 역방향 축조방법을 도시한 도면이고, 도 4는 본 발명에 따른 지하 구조물의 역방향 축조방법의 지면 굴착을 도시한 도면이며, 도 5는 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 설치 및 이동을 도시한 도면이고, 도 6은 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 고정방법을 도시한 도면이며, 도 7은 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 고정방법의 다른 실시 예를 도시한 도면이고, 도 8은 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 쳐짐방지부재를 도시한 도면이다.1 is a view showing a flow chart of the reverse construction method of the underground structure according to the present invention, Figure 2 is a view showing a flow chart of the slab installation step of the reverse construction method of the underground structure according to the invention, Figure 3 4 is a view showing a reverse construction method of the underground structure according to the invention, Figure 4 is a view showing the ground excavation of the reverse construction method of the underground structure according to the present invention, Figure 5 is a reverse construction method of the underground structure according to the present invention Figure 6 is a view showing the installation and movement of the slab, Figure 6 is a view showing a slab fixing method of the reverse construction method of the underground structure according to the present invention, Figure 7 is a slab fixing of the reverse construction method of the underground structure according to the present invention. 8 is a view showing another embodiment of the method, Figure 8 is a view showing a slab sag prevention member of the reverse construction method of the underground structure according to the invention All.

도면에서 도시한 바와 같이, 지하 구조물의 역방향 축조방법은 지하연속벽 형성단계(S10)와 센터파일 축조단계(S20), 적층 슬래브 형성단계(S30) 및 슬래브 설치단계(S40)로 구성된다.As shown in the figure, the reverse structure construction method of the underground structure is composed of the underground continuous wall forming step (S10), the center pile construction step (S20), the laminated slab forming step (S30) and the slab installation step (S40).

지하연속벽 형성단계(S10)는 지하외벽이 형성될 지하위치에 지하연속벽(100)을 형성하는 것으로, 지하 구조물의 기본 외벽을 형성하게 된다.Underground continuous wall forming step (S10) is to form a continuous underground wall 100 in the underground position where the basement outer wall is to be formed, thereby forming a basic outer wall of the underground structure.

그리고 센터파일 축조단계(S20)는 기둥이 축조될 위치인 각 지하연속벽(100) 사이의 지면 속에 다수의 센터파일(center pile: 200)을 일정간격으로 축조하게 된다.And the center pile construction step (S20) is to build a plurality of center piles (center pile: 200) at a predetermined interval in the ground between each underground continuous wall (100) where the column is to be constructed.

이때, 축조되는 센터파일(200)의 개수는 필요로 하는 슬래브(200)의 개수보다 더 축조하여 슬래브(300)를 지지하고, 슬래브(300) 하강 후 제거함에 따라 공간을 확보할 수 있다.In this case, the number of center piles 200 to be built is more than the number of slabs 200 required to support the slab 300, and the space can be secured by removing the slab 300 after descending.

적층 슬래브 형성단계(S30)는 각 지하층의 바닥면을 이루는 슬래브(300)를 다수의 센터파일(200)을 따라 이동될 수 있도록 적어도 두 개 이상 적층 형성되는 것으로, 형성하고자 하는 지하층의 개수에 따라 슬래브(300)의 개수가 결정된다.Stacking slab forming step (S30) is to be formed by stacking at least two slabs 300 forming the bottom surface of each basement layer to be moved along a plurality of center piles 200, according to the number of basement layers to be formed The number of slabs 300 is determined.

그리고 적층되는 각 슬래브(300) 사이에는 박리부재(400)에 의해 상호 분리 가능하도록 적층 형성되며, 각 슬래브(300)에는 센터파일(200)이 관통되도록 고정공(310)이 통공된다.And between each of the slab 300 to be stacked is formed to be separated from each other by the peeling member 400, each of the slab 300 through the fixing hole 310 to pass through the center pile 200.

이러한 박리부재(400)는 박리제와 비닐 및 필름 중 선택된 어느 하나 이상으로 사용되는 것으로, 각 슬래브(300)를 박리시킬 수 있는 것이면 사용가능하다.The peeling member 400 is used as any one or more selected from a release agent, vinyl and a film, and can be used as long as it can peel each slab 300.

또한 적층 슬래브 형성단계(S30)의 다수의 슬래브(300) 중 최상단에 위치한 슬래브(300)의 상면이 지면과 수평을 이루도록 지면을 하측으로 굴착 평탄작업한 후, 굴착된 지면 상에 거푸집용 버림 콘크리트를 타설하여 다수의 슬래브(300)를 형성시킨다.In addition, after excavating and flattening the ground to the lower side so that the upper surface of the slab 300 located at the top of the plurality of slabs 300 of the laminated slab forming step (S30) to be horizontal with the ground, discarded concrete for formwork on the excavated ground By pouring a plurality of slabs 300 to form.

다시 말해, 형성하고자 하는 슬래브(300)의 개수를 정하여 지면을 일정 깊이로 굴착한 다음 거푸집용 버림 콘크리트를 타설하고, 이 타설된 거푸집용 버림 콘크리트 상에서 각 슬래브(300)를 적층 형성하게 된다.In other words, the number of slabs 300 to be formed is determined and the ground is excavated to a predetermined depth, and then the cast-away concrete is poured, and each slab 300 is laminated on the cast-away concrete.

이와 같이 다수의 슬래브(300)를 형성하면, 슬래브(300)가 외기에 노출되는 부위가 적어 동계에도 작업이 가능한 전천후 시공이 가능함은 물론, 최하단부 슬래브(300)가 거푸집용 버림 콘크리트와 지면에 의해 지지됨에 따라 슬래브(300)가 콘크리트 강도를 획득하기 이전이라도 각 슬래브(300)를 연속으로 형성할 수 있게 된다.As such, when a plurality of slabs 300 are formed, the slab 300 is exposed to outside air so that all-weather construction is possible even in winter, and the lowermost slab 300 is formed by cast concrete and the ground. As it is supported, it is possible to form each slab 300 continuously even before the slab 300 obtains the concrete strength.

그리고 슬래브 설치단계(S40)에서는 형성된 다수 개의 슬래브(300)를 하측으로 이동시켜, 각 슬래브(300)를 각 층의 위치에 설치하는 것으로, 지면 굴착과 슬래브(300) 하향이동 및 설치가 반복적으로 이루어지게 된다.And in the slab installation step (S40) by moving a plurality of slabs 300 formed to the lower side, by installing each slab 300 in the position of each floor, ground excavation and slab 300 downward movement and installation repeatedly Will be done.

이러한 슬래브 설치단계(S40)는 도 2에서 도시한 바와 같이, 슬래브 고정단계(S41)와 지면 굴착단계(S42) 및 슬래브 이동단계(S43)로 구성되며, 슬래브 고정단계(S41)와 지면 굴착단계(S42) 및 슬래브 이동단계(S43)가 반복된다.This slab installation step (S40), as shown in Figure 2, consisting of a slab fixing step (S41) and the ground excavation step (S42) and the slab moving step (S43), the slab fixing step (S41) and the ground excavation step (S42) and the slab movement step (S43) are repeated.

도 3 내지 도 7에서 도시한 바와 같이, 슬래브 고정단계(S41)는 슬래브 형성단계(S30)에서 형성된 다수의 슬래브(300) 중 최상단에 위치한 슬래브(300)를 지하연속벽(100)과 센터파일(200)에 고정시키게 된다.3 to 7, the slab fixing step (S41) is the slab 300 located at the top of the plurality of slabs (300) formed in the slab forming step (S30), the underground continuous wall 100 and the center pile It will be fixed to (200).

그리고 지면 굴착단계(S42)에서는 다수 개 형성된 슬래브(300)의 하측 지면을 한 층 깊이 이상 굴착시키는 것이고, 슬래브 이동단계(S43)에서는 슬래브 고정단계(S41)에서 고정되지 않은 다수의 슬래브(300) 중 최상단의 슬래브(300)가 고정된 슬래브(300)와 한 층 높이 간격으로 이격되도록 하측으로 이동시키게 된다.And in the ground excavation step (S42) is to excavate the bottom surface of the slab 300 formed a plurality of more than one layer depth, in the slab movement step (S43) a plurality of slabs 300 not fixed in the slab fixing step (S41) The uppermost slab 300 is moved downward so as to be spaced apart from the fixed slab 300 by one layer height interval.

하측으로 이동된 적층 슬래브(300)는 다시, 슬래브 고정단계(S41)를 거쳐 최상측의 슬래브(300)가 지하연속벽(100)과 센터파일(200)에 고정된 후, 지면 굴착단계(S42) 및 슬래브 이동단계(S43)를 다시 거치게 된다.Laminated slab 300 moved to the lower side again, after the slab fixing step (S41) of the uppermost slab 300 is fixed to the underground continuous wall 100 and the center pile 200, the ground excavation step (S42) ) And the slab moving step (S43) again.

이때, 슬래브 고정단계(S41)에서는 센터파일(200)이 관통되는 슬래브 고정공(310)의 내측면은 하측으로 갈수록 외측으로 경사지게 형성되고, 센터파일(200)에는 고정공(310)의 내측면과 대응되도록 경사진 외측면을 갖는 고정편(600)이 구비되어 상호 끼워짐에 따라 고정되는 것으로, 도 8에 도시한 바와 같다.At this time, in the slab fixing step (S41), the inner surface of the slab fixing hole 310 through which the center pile 200 penetrates is formed to be inclined outward toward the lower side, and the inner side of the fixing hole 310 in the center pile 200. A fixing piece 600 having an inclined outer surface to be inclined with each other is provided and fixed as being fitted together, as shown in FIG. 8.

이는, 종래 굴착 후 각 슬래브(300)를 형성하는 공정 시 사용되던 별도의 보강부재들의 사용을 생략할 수 있어 시간을 단축하고, 비용을 절감시킬 수 있는 것이다.This is because it can omit the use of a separate reinforcing member used in the process of forming each slab 300 after the conventional excavation, it is possible to shorten time and reduce costs.

그리고 도 9에서 도시한 바와 같이, 슬래브(300)의 고정은 도 8의 고정공(310)과 고정편(600)이 적용된 상태에서 철근(610) 및 콘크리트 또는 그라우팅(Grouting) 등에 의해 고정공(310)과 고정편(600) 사이 및 주변이 더욱 견고하게 고정될 수 있다.And, as shown in Figure 9, the fixing of the slab 300 is fixed by the reinforcing bars 610 and concrete or grouting in the state in which the fixing hole 310 and the fixing piece 600 of Figure 8 is applied ( Between 310 and the fixing piece 600 may be more firmly fixed.

또한 슬래브(300)의 가장자리부는 지하연속벽(100)과 콘크리트에 의해 타설되어 고정됨이 바람직하다.In addition, it is preferable that the edge portion of the slab 300 is fixed by being poured by the underground continuous wall 100 and concrete.

이때, 슬래브(300)의 고정공(310)이 통공되고, 고정공(310)의 내측면 내부에는 보강프레임(320)이 더 구비되되, 보강프레임(320)은 상단부와 하단부의 형상이 대칭되도록 형성된다.At this time, the fixing hole 310 of the slab 300 is passed through, the inner side of the fixing hole 310 is further provided with a reinforcement frame 320, the reinforcement frame 320 so that the shape of the upper end and the lower end is symmetrical Is formed.

다시 말해, 보강프레임(320)은 'ㄷ' 이나 'H' 및 'I' 등과 같은 형상으로 이루어지는 것으로, 상단부와 하단부가 대칭이면 어떤 형상이던 가능하다.In other words, the reinforcement frame 320 is formed of a shape such as 'c' or 'H' and 'I', and may be any shape if the upper and lower portions are symmetrical.

이 보강프레임(320)은 슬래브(300)의 고정공(310) 주변을 보강해 주는 것으로, 슬래브(300)를 센터파일(200)에 더욱 견고하게 고정시킬 수 있도록 보강하게 된다.The reinforcement frame 320 is to reinforce the periphery of the fixing hole 310 of the slab 300, it will be reinforced so that the slab 300 can be more firmly fixed to the center pile (200).

한편, 도 10에서 도시한 바와 같이, 슬래브 고정단계(S41)에서는 절곡된 센터고정플레이트(700)를 이용하여 센터파일(200)에 슬래브(300)를 용접 등으로 고정시킬 수 있으며, 이 센터고정플레이트(700)는 슬래브(300)의 상면과 하면 중 선택된 어느 하나 이상에 고정되어 센터파일(200)과 슬래브(300)를 고정시킬 수 있다.Meanwhile, as shown in FIG. 10, in the slab fixing step S41, the slab 300 may be fixed to the center pile 200 by welding, using the bent center fixing plate 700, and the center fixing may be performed. The plate 700 may be fixed to at least one selected from the upper and lower surfaces of the slab 300 to fix the center pile 200 and the slab 300.

이 센터고정플레이트(700)는 센터파일(200)과 슬래브(300)의 연결부를 따라 구비되며, 별도의 고정핀 등에 의해 추가적으로 더 고정될 수 있으며, 센터고정플레이트(700)가 구비된 센터파일(200)의 외측은 콘크리트를 타설하여 마무리함이 바람직하다.The center fixing plate 700 is provided along the connection portion of the center pile 200 and the slab 300, and may be further fixed by a separate fixing pin, and the center pile provided with the center fixing plate 700 ( The outside of 200 is preferably finished by pouring concrete.

또한 도 11에서 도시한 바와 같이, 슬래브(300)의 가장자리 측면에는 내설된 하나 이상의 철근(340)이 외측으로 돌출되거나 내설된 철근(340)과 연결되어 외측으로 돌출되는 고정볼트(350)가 구비된다.In addition, as shown in Figure 11, the edge side of the slab 300 is provided with one or more reinforcing bars 340 is protruding outwardly or is connected to the reinforcing bars 340 is provided with a fixing bolt 350 protruding outwards do.

이 철근(340)이나 고정볼트(350)의 단부가 지하연속벽(100)과 닿은 후, 콘크 리트 등에 의해 타설되어 고정됨에 따라 슬래브(300)의 측면이 지하연속벽(100)과 고정된다.After the end of the reinforcing bar 340 or the fixing bolt 350 is in contact with the underground continuous wall 100, the side of the slab 300 is fixed with the underground continuous wall 100 as it is poured and fixed by concrete or the like.

그리고 도 12에서 도시한 바와 같이, 슬래브(300)의 측단부에는 상단 또는 하단이 회전 가능하도록 연결된 측면고정플레이트(710)가 더 구비되어 콘크리트 타설 시, 거푸집 역할을 함이 바람직하다.And, as shown in Figure 12, the side end portion of the slab 300 is further provided with a side fixing plate 710 is connected to the top or the bottom so as to be rotatable, when pouring concrete, it is preferable to serve as a formwork.

또한 슬래브(300)는 도 13에 도시한 바와 같이, 그 내부에 인장철근이나 인장강선이 체크무늬 형상으로 배열된 쳐짐방지부재(800)가 더 구비된다.In addition, as shown in FIG. 13, the slab 300 is further provided with a deflection preventing member 800 in which the tensile reinforcing bar or tensile steel wire is arranged in a checkered shape.

이 쳐짐방지부재(800)는 다수의 센터파일(200)에 고정된 슬래브(300) 중 어느 하나의 센터파일(200)에서 슬래브(300)가 분리되어 지지력이 손실될 경우, 쳐짐방지부재(800)가 인접한 다른 센터파일(200)에 지지되어 쳐짐을 방지함에 따라 슬래브(300)의 붕괴를 방지하게 된다.The sag prevention member 800 is a sag prevention member 800 when the slab 300 is separated from any one of the slab 300 fixed to the plurality of center piles 200 and the bearing force is lost. ) Is supported by another adjacent center pile 200 to prevent sagging of the slab 300.

한편, 슬래브(300)의 일부에는 자재, 토사 및 장비 반출입용 개구부(330)가 일부에 형성되며, 지면 굴착단계(S42)에서 이 슬래브(300)의 개구부(330)를 통해 굴착작업이 이루어지게 된다.On the other hand, a part of the slab 300 is formed in the opening portion 330 for the material, soil and equipment in and out, and the excavation work is made through the opening 330 of the slab 300 in the ground excavation step (S42). do.

이러한 슬래브(300)의 개구부(330)를 통해 굴착작업이 이루어지면, 종래 굴착 시 발생되는 먼지 등이 공기 중으로 확산됨에 따라 주변을 오염시키는 것을 방지할 수 있어 환경 친화적인 굴착작업을 할 수 있다.When the excavation work is performed through the opening 330 of the slab 300, the dust generated during the conventional excavation may be prevented from being polluted as it is diffused into the air, thereby enabling environmentally friendly excavation work.

그리고 슬래브 이동단계(S43)에서는 별도의 슬래브 하강장치(500)에 의해 슬래브(300)가 하측으로 이동되는 것으로, 슬래브 하강장치(500)는 슬래브(300)를 하 측으로 용이하게 이동시킬 수 있는 것이면 제한되지 않고 사용될 수 있다.And in the slab movement step (S43) that the slab 300 is moved to the lower side by a separate slab lowering device 500, the slab lowering device 500 if the slab 300 can be easily moved to the lower side It can be used without limitation.

이러한 슬래브 하강장치(500)는 본 발명에서는 센터파일(200)의 길이방향을 따라 슬래브(300)를 이동시는 장치를 사용함이 바람직하다.In the present invention, the slab lowering device 500 is preferably used to move the slab 300 along the longitudinal direction of the center pile 200.

한편, 도 14에서 도시한 바와 같이, 적층된 슬라브 중 최하측의 슬래브(300)와 굴착된 지면 사이에 기체에 의해 팽창 및 수축되는 쿠션부(510)가 더 구비되어 슬라브(300)의 하강속도를 조절하고, 슬래브(300)가 일측으로 기울어지는 것을 방지할 수 있다.On the other hand, as shown in Figure 14, between the lower slab 300 of the stacked slabs and the excavated ground is further provided with a cushion portion 510 which is expanded and contracted by the gas is the descending speed of the slab 300 To adjust the, it is possible to prevent the slab 300 is inclined to one side.

이 쿠션부(510)는 공기를 이용하여 팽창 및 수축시킴이 바람직하며, 슬래브(300) 하측 전체에 설치될 수도 있고, 하중이 집중되는 부분에 분산되어 구비될 수도 있다. The cushion unit 510 is preferably expanded and contracted using air, and may be installed in the entire lower side of the slab 300 or may be provided in a part where load is concentrated.

이와 같은 지하 구조물의 역방향 축조방법은 종래보다 공정을 감소시키고, 시간을 단축시킬 수 있어 비용을 감소시키는 등의 종래 문제점을 해결할 수 있어 혁신적인 지하 구조물의 축조방법을 제공할 수 있다.Such a reverse construction method of the underground structure can solve the conventional problems such as reducing the process and the time can be reduced compared to the conventional cost can provide an innovative underground structure construction method.

도 1은 본 발명에 따른 지하 구조물의 역방향 축조방법의 순서도를 도시한 도면이고,1 is a view showing a flow chart of the reverse construction method of the underground structure according to the present invention,

도 2는 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 설치단계의 순서도를 도시한 도면이며,Figure 2 is a view showing a flow chart of the slab installation step of the reverse construction method of the underground structure according to the present invention,

도 3은 본 발명에 따른 지하 구조물의 역방향 축조방법을 도시한 도면이고,3 is a view showing a reverse construction method of the underground structure according to the present invention,

도 4는 본 발명에 따른 지하 구조물의 역방향 축조방법의 지면 굴착을 도시한 도면이며,4 is a view showing the ground excavation of the reverse construction method of the underground structure according to the present invention,

도 5는 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 설치 및 이동을 도시한 도면이고,5 is a view showing the slab installation and movement of the reverse construction method of the underground structure according to the present invention,

도 6은 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 고정방법을 도시한 도면이며,6 is a view showing a slab fixing method of the reverse construction method of the underground structure according to the present invention,

도 7은 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 고정방법의 다른 실시 예를 도시한 도면이고,7 is a view showing another embodiment of the slab fixing method of the reverse construction method of the underground structure according to the present invention,

도 8은 본 발명에 따른 지하 구조물의 역방향 축조방법의 슬래브 쳐짐방지부재를 도시한 도면이다.8 is a view showing a slab sag prevention member of the reverse construction method of the underground structure according to the present invention.

< 도면의 주요 부분에 대한 부호의 설명 ><Description of Symbols for Main Parts of Drawings>

100 : 지하연속벽 200 : 센터파일100: continuous continuous wall 200: center pile

300 : 슬래브 310 : 고정공300: slab 310: fixing hole

400 : 박리부재 500 : 슬래브 하강장치400: peeling member 500: slab lowering device

600 : 고정편 610 : 철근600: fixed piece 610: rebar

800 : 쳐짐방지부재800: sag prevention member

Claims (14)

지하외벽이 형성될 지하위치에 지하연속벽을 형성하여 지하 외곽라인을 형성하는 지하연속벽 형성단계;An underground continuous wall forming step of forming an underground outer line by forming an underground continuous wall in an underground position where an underground outer wall is to be formed; 상기 지하연속벽에 의해 구획된 지면에 다수의 센터파일(center pile)을 축조하여 기둥의 기본틀을 형성시키는 센터파일 축조단계;Center pile construction step of forming a plurality of center pile (center pile) on the ground partitioned by the underground continuous wall to form the base frame of the pillar; 각 지하층의 바닥면을 이루는 슬래브를 상기 다수의 센터파일을 따라 이동될 수 있도록 적어도 두 개 이상 적층 형성되는 적층 슬래브 형성단계; 및A laminated slab forming step of stacking at least two slabs forming a bottom surface of each basement layer so as to be moved along the plurality of center piles; And 상기 다수 개 적층된 슬래브를 하측으로 이동시키며, 각 슬래브가 각 층의 위치에 설치되되, 지면 굴착과 슬래브 하향이동 및 설치가 반복적으로 이루어지는 슬래브 설치단계를 포함하여 이루어지는 지하 구조물의 역방향 축조방법.Moving the plurality of stacked slabs to the lower side, each slab is installed at the position of each layer, the ground construction method of the underground structure comprising a slab installation step of repeatedly excavation and downward movement and installation of the ground. 제1항에 있어서, 상기 적층 슬래브 형성단계에서는,The method of claim 1, wherein in the forming of the laminated slab, 형성하고자 하는 층의 개수에 따라 상기 슬래브의 형성 개수가 결정되고, 상기 각 슬래브 사이에는 박리부재에 의해 상호 분리 가능하도록 적층 형성되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.The number of formation of the slab is determined according to the number of layers to be formed, the reverse construction method of the underground structure, characterized in that the lamination is formed between each slab by the separation member to be separated from each other. 제2항에 있어서,The method of claim 2, 상기 다수의 슬래브 중 최상단에 위치한 슬래브의 상면이 지면과 수평을 이루도록 지면을 하측으로 굴착 평탄작업을 한 후, 굴착된 지면 상에 거푸집용 버림 콘크리트를 타설하여 상기 다수의 슬래브를 형성시키는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.After excavating and flattening the ground downward so that the upper surface of the slab located at the top of the plurality of slabs horizontal to the ground, and then cast the formwork for cast concrete on the excavated ground to form the plurality of slabs Reverse construction method of underground structure. 제2항에 있어서,The method of claim 2, 상기 박리부재는 박리제와 비닐 및 필름 중 선택된 어느 하나 이상인 것을 특징으로 하는 지하 구조물의 역방향 축조방법.The peeling member is a reverse construction method of the underground structure, characterized in that any one or more selected from the release agent, vinyl and film. 제2항에 있어서,The method of claim 2, 상기 센터파일이 관통되도록 슬래브에 고정공이 통공되고, 상기 고정공의 내측면 내부에는 보강프레임이 더 구비되되, 상기 보강프레임은 상단부와 하단부의 형상이 대칭되도록 형성되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.A fixing hole is passed through the slab so that the center pile is penetrated, and a reinforcing frame is further provided inside the inner surface of the fixing hole, and the reinforcing frame is formed such that the upper and lower ends thereof are symmetrically formed. Construction method. 제2항에 있어서,The method of claim 2, 상기 슬래브의 내부에 인장철근이나 인장강선이 체크무늬 형상으로 배열된 쳐짐방지부재가 더 구비되어 다수의 센터파일에 고정된 상기 슬래브 중 어느 하나 의 센서파일에서 분리되어 지지력이 손실될 경우, 상기 쳐짐방지부재가 인접한 다른 센터파일에 지지되어 쳐짐을 방지함에 따라 상기 슬래브의 붕괴를 방지하는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.The slab is further provided with a deflection preventing member in which the reinforcing bars or the tensile steel wires are arranged in a checkered shape in the slab. A method for constructing a reverse structure of an underground structure, characterized by preventing the slab from collapsing as the preventing member is supported by another adjacent center pile to prevent sagging. 제1항에 있어서, 상기 슬래브 설치단계는,According to claim 1, The slab installation step, 상기 슬래브 형성단계에서 형성된 다수의 슬래브 중 최상단에 위치한 슬래브를 상기 지하연속벽과 센터파일에 고정시키는 슬래브 고정단계;A slab fixing step of fixing the slab located at the top of the plurality of slabs formed in the slab forming step to the underground continuous wall and the center pile; 상기 다수 개 형성된 슬래브의 하측 지면을 한 층 깊이 이상 굴착시키는 지면 굴착단계; 및A ground excavation step of digging the lower ground of the plurality of formed slabs more than one layer deep; And 상기 슬래브 고정단계에서 고정되지 않은 다수의 슬래브 중 최상단의 슬래브가 상기 고정된 슬래브와 한 층 높이 간격으로 이격되도록 하측으로 이동되는 슬래브 이동단계를 포함하여 이루어지고,Including the slab movement step of moving the lower side of the slab that is not fixed in the slab fixing step is moved downwardly spaced at a height interval with the fixed slab, 상기 슬래브 고정단계와 지면 굴착단계 및 슬래브 이동단계가 반복되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.Reverse construction method of the underground structure, characterized in that the slab fixing step, the ground excavation step and the slab movement step is repeated. 제7항에 있어서, 상기 슬래브 고정단계에서,The method of claim 7, wherein in the slab fixing step, 상기 센터파일이 관통되는 슬래브 고정공의 내측면은 하측으로 갈수록 외측으로 경사지게 형성되고, 상기 센터파일에는 상기 고정공의 내측면과 대응되도록 외측면을 갖는 고정편이 구비되어 상호 끼워지며,The inner surface of the slab fixing hole through which the center pile is penetrated is formed to be inclined outward toward the lower side, the center pile is provided with a fixing piece having an outer surface to correspond to the inner surface of the fixing hole, 상기 슬래브의 가장자리는 상기 지하연속벽과 콘크리트에 의해 타설되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.The edge of the slab is the reverse construction method of the underground structure, characterized in that the pouring by the underground continuous wall and concrete. 제8항에 있어서,The method of claim 8, 상기 슬래브의 고정공과 고정편 주변에 철근과 콘크리트 또는 그라우팅(Grouting) 등을 이용하여 더욱 견고하게 고정시키는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.Reverse construction method of the underground structure, characterized in that more securely fixed using reinforcing bars and concrete or grouting around the fixing hole and the fixing piece of the slab. 제7항에 있어서, 상기 슬래브 고정단계에서,The method of claim 7, wherein in the slab fixing step, 상기 센터파일과 슬래브를 절곡된 센터고정플레이트를 이용하여 용접 등으로 고정시키되, 상기 슬래브의 상면과 하면 중 선택된 어느 하나 이상에 고정되고,The center pile and the slab are fixed by welding using a bent center fixing plate, and fixed to any one or more selected from the upper and lower surfaces of the slab, 상기 센터고정플레이트가 구비된 센터파일의 외측은 콘크리트에 의해 고정되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.The reverse construction method of the underground structure, characterized in that the outer side of the center pile provided with the center fixing plate is fixed by concrete. 제8항 또는 제10항에 있어서,The method of claim 8 or 10, 상기 슬래브의 가장자리 측면에는 내설된 하나 이상의 철근이 외측으로 돌출 되거나 상기 내설된 철근과 연결되어 외측으로 돌출되는 고정볼트가 구비되고,The side of the edge of the slab is provided with a fixing bolt protruding outward or connected to the one or more reinforcing steel bar is protruded outward, 상기 철근이나 고정보트의 단부가 상기 연속벽과 닿은 후, 콘크리트 등에 의해 고정됨에 따라 상기 슬래브의 측면이 상기 연속벽과 고정되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.And the side of the slab is fixed to the continuous wall as the end of the reinforcing bar or the high information contact with the continuous wall, and is fixed by concrete or the like. 제11항에 있어서,The method of claim 11, 상기 슬래브의 측단부에는 상단 또는 하단이 회전 가능하도록 연결된 측면고정플레이트가 더 구비되어 콘크리트 타설 시, 거푸집 역할을 하는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.The side end portion of the slab is provided with a side fixing plate connected to the top or the bottom so as to be rotatable further when building concrete, reverse construction method of the underground structure, characterized in that serves as a formwork. 제7항에 있어서, 상기 지면 굴착단계는,The method of claim 7, wherein the ground excavation step, 상기 형성된 슬래브의 일부를 개폐 가능하도록 형성하고, 상기 슬래브의 일부를 개방하여 그 하측 지면을 굴착하는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.And forming a part of the formed slab so as to be openable and open, and opening a part of the slab to excavate a lower surface thereof. 제7항에 있어서, 상기 슬래브 이동단계에서,The method of claim 7, wherein in the slab movement step, 상기 적층된 슬라브와 굴착된 지면 사이에 기체에 의해 팽창 및 수축되는 쿠션부가 더 구비되는 것을 특징으로 하는 지하 구조물의 역방향 축조방법.And a cushion part further expanded and contracted by a gas between the stacked slabs and the excavated ground.
KR1020090018889A 2009-03-05 2009-03-05 Slab top-down method of underground construction KR101044441B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090018889A KR101044441B1 (en) 2009-03-05 2009-03-05 Slab top-down method of underground construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090018889A KR101044441B1 (en) 2009-03-05 2009-03-05 Slab top-down method of underground construction

Publications (2)

Publication Number Publication Date
KR20100100165A true KR20100100165A (en) 2010-09-15
KR101044441B1 KR101044441B1 (en) 2011-06-27

Family

ID=43006274

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090018889A KR101044441B1 (en) 2009-03-05 2009-03-05 Slab top-down method of underground construction

Country Status (1)

Country Link
KR (1) KR101044441B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741714A (en) * 2013-12-09 2014-04-23 中国建筑第二工程局有限公司 Construction method for full cover-excavation reverse method of underground engineering
CN109371957A (en) * 2018-12-04 2019-02-22 广东建诚监理咨询有限公司 Braced wall and two wall combined structure of structural wall
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
RU190322U1 (en) * 2019-01-10 2019-06-26 Федеральное государственное автономное образовательное учреждение высшего образования "Крымский федеральный университет имени В.И. Вернадского" Device for the construction of multi-storey underground structures
CN110485461A (en) * 2019-07-26 2019-11-22 上海建工二建集团有限公司 A kind of drop board construction method of underground structure
KR20220119549A (en) 2021-02-21 2022-08-30 아주자동차대학 산학협력단 LED Lane Guidance System And Method Thereof
KR20230122862A (en) 2022-02-15 2023-08-22 주식회사 산흥이지 Light reflection fee and LED to flash the crosswalk safety mark

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180078615A (en) * 2016-12-30 2018-07-10 주식회사 구들택 High Strength Concrete nuts and manufacturing methods

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2536249B2 (en) 1990-07-10 1996-09-18 鹿島建設株式会社 Lift-down underground structure construction method
JPH07324343A (en) * 1994-05-31 1995-12-12 Toda Constr Co Ltd Construction method for constructing underground skeleton
JP2897663B2 (en) * 1994-12-13 1999-05-31 株式会社大林組 How to build underground structures
JP3589329B2 (en) 1996-03-01 2004-11-17 鹿島建設株式会社 Construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741714A (en) * 2013-12-09 2014-04-23 中国建筑第二工程局有限公司 Construction method for full cover-excavation reverse method of underground engineering
CN103741714B (en) * 2013-12-09 2016-09-14 中国建筑第二工程局有限公司 Underground engineering full sheltered reverse excavation construction method
CN109371957A (en) * 2018-12-04 2019-02-22 广东建诚监理咨询有限公司 Braced wall and two wall combined structure of structural wall
RU190322U1 (en) * 2019-01-10 2019-06-26 Федеральное государственное автономное образовательное учреждение высшего образования "Крымский федеральный университет имени В.И. Вернадского" Device for the construction of multi-storey underground structures
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN109706953B (en) * 2019-01-21 2023-10-13 吉林建筑大学 Die for foundation slab of assembled concrete underground building and drawing die construction method
CN110485461A (en) * 2019-07-26 2019-11-22 上海建工二建集团有限公司 A kind of drop board construction method of underground structure
KR20220119549A (en) 2021-02-21 2022-08-30 아주자동차대학 산학협력단 LED Lane Guidance System And Method Thereof
KR20230122862A (en) 2022-02-15 2023-08-22 주식회사 산흥이지 Light reflection fee and LED to flash the crosswalk safety mark

Also Published As

Publication number Publication date
KR101044441B1 (en) 2011-06-27

Similar Documents

Publication Publication Date Title
KR101044441B1 (en) Slab top-down method of underground construction
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR100967497B1 (en) Method for constructing an underground structure
KR101341679B1 (en) Device for constructing an underground structure and method thereof
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR20090094971A (en) Under ground top-down method
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
KR101587062B1 (en) Steel composite underground earth retaining wall structure and it&#39;s construction method
JP5228862B2 (en) Underground structure, construction method of underground structure
KR20200122037A (en) The construction method using a exterio wall of undergound structure
JP2017172308A (en) Integrated foundation and integrated foundation construction method
KR100967496B1 (en) Device for constructing an underground structure
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
JP3641227B2 (en) Construction method of underground structure
KR101106799B1 (en) Construction method of Top-down concrete slab
JP6418683B2 (en) Temporary support method
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP5201719B2 (en) Column construction method and column structure
JP3160485U (en) Deep foundation foundation pile reinforcement bar construction
JP6534026B2 (en) Seismic isolation building and its construction method

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140619

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150617

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160620

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170622

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20180620

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190620

Year of fee payment: 9