KR101106799B1 - Construction method of Top-down concrete slab - Google Patents

Construction method of Top-down concrete slab Download PDF

Info

Publication number
KR101106799B1
KR101106799B1 KR1020090025157A KR20090025157A KR101106799B1 KR 101106799 B1 KR101106799 B1 KR 101106799B1 KR 1020090025157 A KR1020090025157 A KR 1020090025157A KR 20090025157 A KR20090025157 A KR 20090025157A KR 101106799 B1 KR101106799 B1 KR 101106799B1
Authority
KR
South Korea
Prior art keywords
slab
frame
support
lowering
concrete
Prior art date
Application number
KR1020090025157A
Other languages
Korean (ko)
Other versions
KR20100106882A (en
Inventor
박창규
Original Assignee
박창규
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박창규 filed Critical 박창규
Priority to KR1020090025157A priority Critical patent/KR101106799B1/en
Publication of KR20100106882A publication Critical patent/KR20100106882A/en
Application granted granted Critical
Publication of KR101106799B1 publication Critical patent/KR101106799B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Abstract

본 발명은 탑 다운 콘크리트 슬래브 시공방법에 관한 것으로서, 지하층 기둥을 선 시공한 후 단계별로 지하층 슬래브와 토공사를 위에서 아래로 반복해 가면서 지하구조물을 형성하는 탑 다운 시공방법에 있어서, 1층 보 하부까지 터파기 공사를 하고, 보 하강틀 및 1층 보 형틀을 설치하여 서포트에 의해 지지한 다음, 슬래브 하강틀 및 슬래브 형틀을 설치하여 서포트에 의해 지지시키는 제1공정과; 상기 보 하강틀과 슬래브 하강틀에 인양구를 설치하고 철근을 배근한 후 콘크리트를 타설하여 1층 보 및 슬래브를 형성하는 제2공정과; 상기 제2공정에서의 콘크리트가 양생된 후, 상기 서포트를 해체하고 지하 1층 이하의 깊이로 터파기 공사를 하고, 상기 보 하강틀을 인양구에 의해 하강시켜서 지하 1층 보 형틀을 설치하여 서포트에 의해 지지하고, 상기 슬래브 하강틀 및 슬래브 형틀을 하강시켜서 지하 1층 슬래브 형틀을 설치하여 서포트에 의해 지지시키는 제3공정과; 상기 보 하강틀과 슬래브 하강틀에 인양구를 설치하고 철근을 배근한 후 콘크리트를 타설하여 지하 1층 보 및 슬래브를 형성하는 제4공정과; 상기 제4공정에서의 콘크리트가 양생된 후, 원하는 지하층까지 상기 제3공정과 제4공정을 반복하면서 지하층을 단계적으로 형성하는 공정을 포함하여 이루어지는 것을 특징으로 한다.

Figure R1020090025157

보, 슬래브, 하강틀, 형틀, 서포트, 현수부재

The present invention relates to a method of constructing a top-down concrete slab, and more particularly, to a top-down construction method for constructing an underground structure while repeatedly laying a basement slab and an earth- A first step of installing a beam lowering frame and a single-layer beam frame and supporting the beam by a support, then installing and supporting the slab lowering frame and the slab frame by a support; A second step of installing a lifting platform on the beam lowering frame and the slab lowering frame, placing a reinforcing bar and casting concrete to form a single-layer beam and a slab; After the concrete in the second step is cured, the support is disassembled and the trench construction is carried out to a depth of not more than one layer below the foundation, and the beam lowering frame is lowered by a lifting section to form a one- A third step of lowering the slab-lifting frame and the slab-lifting frame so that the slab-lifting frame and the slab-lifting frame are supported by a support; A fourth step of installing a lifting platform on the beam lowering frame and the slab lowering frame, placing a reinforcing bar and placing concrete thereon to form a 1-story underground beam and a slab; And a step of forming the basement layer step by step by repeating the third and fourth steps up to the desired basement layer after the concrete in the fourth step is cured.

Figure R1020090025157

Beam, slab, lowering frame, mold, support, suspending member

Description

탑 다운 콘크리트 슬래브 시공방법{Construction method of Top-down concrete slab}BACKGROUND OF THE INVENTION Field of the Invention The present invention relates to a method of constructing a top-down concrete slab,

본 발명은 탑 다운 방식의 콘크리트 슬래브 시공방법에 관한 것으로서, 더욱 상세하게는 지하의 각 층을 단계적으로 상부층에서 하부층으로 완성해 가는 탑 다운 공법에 있어서, 한 개 층의 형틀을 상측에 연결된 현수부재에 의해 현수시킨 상태에서 설치하여 시공하고, 그 형틀을 다시 하부층으로 이동시켜서 연속적인 시공이 이루어지도록 함으로써 시공기간 및 시공비용을 절감할 수 있도록 된 탑 다운 콘크리트 슬래브 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a top-down concrete slab, and more particularly, to a method of constructing a concrete slab of a top-down type, The present invention relates to a method of constructing a top down concrete slab in which a construction period and a construction cost can be reduced by allowing the continuous construction to be performed by moving the form to a lower layer.

건축 구조물의 시공에 있어서, 근래에는 탑 다운 방식의 시공방법이 많이 적용되고 있는데, 탑 다운 시공방법은 일반적으로 도 1에서와 같이 굴착공사 이전에 지하외부 벽체(slurry wall:W)와 지하층 기둥(bored pile:P)을 선시공한 후, 단계별로 지하층 슬래브와 토공사를 위에서 아래로 반복해 가면서 지하 구조물을 형성하는 공법으로서 도 1에 그 시공예가 도시되어 있다.In the construction of a building structure, a top-down construction method is applied in recent years. In general, as shown in FIG. 1, a top-down construction method generally includes a slurry wall (W) bored pile: P), and then constructing an underground structure while repeating the steps of the basement slab and earthworks from top to bottom, is shown in Fig.

이러한 탑 다운 방법은 기존의 오픈 컷(open cut) 공법으로 계획하기 어려운 대단면, 대심도 굴착이나 인접 건물이 많은 도심지 구간에서 안정적으로 적용할 수 있으며, 1층 바닥이 선시공되기 때문에 작업장의 조기 확보가 가능하여 강우 및 강설시에도 시공할 수 있는 전천후 공법이고, 지상과 지하가 동시에 진행될 수 있으므로 일정 규모 이상의 건물에서는 공기 단축의 효과도 기대할 수 있어서 널리 사용되고 있다.This top-down method can be applied stably in the large-area, large-scale excavation that is difficult to plan by the existing open cut method, or in the urban area with many adjacent buildings. Since the first floor floor is caught, And it can be applied to rainfall and snowfall. It is widely used because it can expect the effect of shortening of air in buildings over a certain scale because ground and underground can be operated at the same time.

이러한 탑 다운 공법은 형틀을 지지하는 형태에 따라 여러 방법으로 나뉘는데, 굴토지반을 평탄하게 한 후 슬래브 형틀을 설치하거나 버림콘크리트를 타설하여 슬래브 철근을 시공하는 S.O.G공법, 굴토지반을 평탄하게 다지거나 버림콘크리트를 타설한 후 서포트를 설치하지 않고 바로 거더와 빔의 형틀을 설치하는 B.O.G공법, 일반 오픈 컷 공법에서와 마찬가지로 서포트를 사용하여 형틀을 지지하는 서포트 공법, 대형 형틀을 초기에 제작하여 현수식으로 매달아서 단계적으로 골조공사를 진행하는 N.S.T.D공법 등이 있다.The top-down method is divided into several methods depending on the form supporting the formwork. SOG method in which slabs are flattened and then slabs are laid or concrete is put in place to construct the slab reinforcement, BOG method that installs girder and beam mold without installing support after pouring or throwing concrete, support method which supports support frame by using support as same as general open cut method, And the NSTD method, which is constructed by stepping up the structure with hanging from the formula.

상기 S.O.G공법은 굴착깊이를 최소화할 수 있어서 연속벽의 안전성과 R.C.D파일의 좌굴 방지에도 효과적이며 공기 단축이나 작업능률 향상에도 효과가 있으나 초기 장비 작업공간 확보를 위한 토공 반출구 작업기간이 별도로 필요하며, 하부 지층이 견고할 경우에는 적용이 어려운 문제가 있다.The SOG method is effective for minimizing the depth of excavation and also for preventing the stability of the continuous wall and buckling of the RCD file. It also has the effect of shortening the air space and improving the work efficiency. However, , And it is difficult to apply it when the lower layer is rigid.

B.O.G공법은 별도의 서포트가 필요하지 않으므로 단순구체공사에 소요되는 공사기간은 단축될 수 있으나, 하부층 공사시 토공 반입구의 초기 굴착에 소요되는 기간이 별도로 필요하며 대지가 좁을 경우에는 매층마다 굴토장비가 반입, 반출되어야 하는 번거로움이 발생한다.Since the BOG method does not require any additional support, the construction period required for the simple concrete construction can be shortened. However, the period required for the initial excavation of the earthwork entrance at the lower floor construction is required separately. It is troublesome to carry in and out.

서포트 공법은 하부층 굴토공사를 진행하기 위해서 슬래브의 형틀 및 서포트 를 해체하여 상부층으로 인양해야 하므로 이에 따른 공사기간과 비용이 추가로 발생할 수 있으며, 상부층 슬래브가 충분히 양생되지 않은 상태에서 무리하게 적재 및 장비의 이동 등으로 구조체의 균열을 유발시킬 수도 있고, 또한 연속벽과 R.C.D파일의 노출 길이가 커짐으로 인하여 연속벽의 강성이 증대되어야 하는 등의 문제가 있었다.In the support method, it is necessary to disassemble the formwork and the support of the slab in order to carry out the excavation of the lower-level excavation earth, so that the construction period and cost may be further increased. And the rigidity of the continuous wall must be increased due to an increase in exposure length of the continuous wall and the RCD file.

N.S.T.D공법은 공개특허공보 특1999-012858호에 그 기술이 제시된 바 있으며, 이 공법은 슬래브 상부에 매달린 형틀 서포트 틀을 활용하기 때문에 하단부 서포트 및 기타 장애물이 없고, 슬래브 양생과는 별도로 지하 굴토 공사를 진행할 수 있는 공법으로서 공사기간을 단축할 수 있고, 콘크리트의 품질이 향상될 수 있으며, 연약지반에도 효과적으로 적용될 수 있다. 따라서 이러한 N.S.T.D공법이 근래에 널리 사용되고 있으나, 대형의 형틀을 초기에 제작하여 사용하기 때문에 그에 따른 초기의 투입비용과 제작기간이 소요되어 지하가 일정 층 수 이상이 되어야 경제성이 있으며, 각 층이 동일한 평면구조를 가지지 않으면 적용이 어려운 문제가 있었다.The NSTD method is disclosed in Japanese Patent Laid-Open Publication No. 1999-012858. Since this method utilizes a mold support frame suspended above the slab, there is no lower support and other obstacles, and an underground construction work is performed separately from the slab curing As the construction method can proceed, the construction period can be shortened, the quality of the concrete can be improved, and it can be effectively applied to the soft ground. Therefore, although the NSTD method is widely used in recent years, since the large molds are initially manufactured and used, the initial charging cost and the manufacturing period are required. Therefore, it is economical that the number of the underground is more than a certain number of layers. If it does not have a planar structure, it is difficult to apply.

또한, 형틀 공정과 철근 공정의 일체 진행이 불가하여 공사기간이 지연되고, 보 하부 수평잡기 및 단차부 작업 그리고 터파기 작업 등에 많은 어려움이 있었으며, 보, 옹벽 이음철근에 의해 해체가 어렵고, 보 위치의 변경시 적용이 곤란한 등의 여러 문제점이 있었다.In addition, it is impossible to proceed with the mold process and the rebar process, so that the construction period is delayed, and there is a lot of difficulty in leveling the beam lower, stepping work and tearing work, and it is difficult to dismantle by the beam, It is difficult to apply the method to the change of the position.

이러한 여러 탑 다운 공법들의 문제점들을 개선하고자 제안된 기술 중에 상기 N.S.T.D공법과 마찬가지로 형틀을 현가하는 방식이면서 각 지하층 마다 독립된 형틀을 제작하여 사용하는 방법으로서 선 발명특허 제10-821663호가 본 발명자에 의해 제안된 바 있는데, 이 방법은 종래의 시공방법에 비하여 시공기간을 획기적으로 단축시킬 수 있는 효과를 제공하였다. 그러나, 각 지하층 마다 별도의 형틀을 제작하여 설치하여야 하는 관계로 형틀이나 기타 자재의 해체, 정리 및 반출에 따른 작업기간과 인력이 많이 투입되어야 하고, 이에 따라 비용과 시간의 소모가 많은 문제점이 있었다.To improve the problems of these various top-down techniques, among the proposed techniques, as in the case of the NSTD method, there is proposed a method in which an independent mold is manufactured and used for each underground layer, This method has provided an effect of drastically shortening the construction period as compared with the conventional construction method. However, due to the fact that separate molds must be manufactured and installed in each underground floor, a lot of work time and manpower required for disassembling, arranging, and unloading of the molds and other materials must be applied, .

본 발명은 상기한 문제점을 해결하기 위하여 발명한 것으로서, 그 목적은 형틀 등의 자재를 최소화하여 전체적인 시공경비를 대폭 절감할 수 있으면서 작업이 간편하게 이루어질 수 있는 탑 다운 콘크리트 슬래브 시공방법을 제공하기 위한 것이다.It is an object of the present invention to provide a method of constructing a top down concrete slab, which can simplify the work while minimizing the overall construction cost by minimizing the material such as a mold .

본 발명의 다른 목적은, 형틀을 지지하기 위한 구성물이 간단하여 작업이 간편하고 연속적인 재 사용이 가능하여 비용이 저렴하며, 터파기 작업이 유리하고, 해체 및 철거 작업 또한 매우 용이하게 이루어질 수 있도록 된 탑 다운 콘크리트 슬래브 시공방법을 제공하는 것이다.It is another object of the present invention to provide a mold for supporting a mold, which is simple and easy to operate and can be reused continuously, so that a cost is low, a tearing operation is advantageous, And to provide a method of constructing a top-down concrete slab.

본 발명의 탑 다운 콘크리트 슬래브 시공방법은, 지하층 기둥을 선 시공한 후 단계별로 지하층 슬래브와 토공사를 위에서 아래로 반복해 가면서 지하구조물을 형성하는 탑 다운 시공방법에 있어서, 1층 보 하부까지 터파기 공사를 하고, 보 하강틀 및 1층 보 형틀을 설치하여 서포트에 의해 지지한 다음, 슬래브 하강틀 및 슬래브 형틀을 설치하여 서포트에 의해 지지시키는 제1공정과;The method of constructing a tower-down concrete slab according to the present invention is a tower-down construction method for constructing an underground structure while repeatedly repeating a basement slab and earthworks from top to bottom, step by step, A first step of installing a beam lowering frame and a single-layer beam frame and supporting the beam by a support, then installing a slab lowering frame and a slab frame, and supporting the beam by a support;

상기 보 하강틀과 슬래브 하강틀에 인양구를 설치하고 철근을 배근한 후 콘크리트를 타설하여 1층 보 및 슬래브를 형성하는 제2공정과;A second step of installing a lifting platform on the beam lowering frame and the slab lowering frame, placing a reinforcing bar and casting concrete to form a single-layer beam and a slab;

상기 제2공정에서의 콘크리트가 양생된 후, 상기 서포트를 해체하고 지하 1층 이하의 깊이로 터파기 공사를 하고, 상기 보 하강틀을 인양구에 의해 하강시켜 서 지하 1층 보형틀을 설치하여 서포트에 의해 지지하고, 상기 슬래브 하강틀 및 슬래브 형틀을 하강시켜서 지하 1층 슬래브 형틀을 설치하여 서포트에 의해 지지시키는 제3공정과;After the concrete in the second step is cured, the support is disassembled and a trench construction is carried out to a depth of not more than one layer below the foundation, and the beam lowering frame is lowered by a lifting frame, A third step in which the slab lowering frame and the slab frame are supported by a support so that a slab frame of one basement level is installed and supported by a support;

상기 보 하강틀과 슬래브 하강틀에 인양구를 설치하고 철근을 배근한 후 콘크리트를 타설하여 지하 1층 보 및 슬래브를 형성하는 제4공정과;A fourth step of installing a lifting platform on the beam lowering frame and the slab lowering frame, placing a reinforcing bar and placing concrete thereon to form a 1-story underground beam and a slab;

상기 제4공정에서의 콘크리트가 양생된 후, 원하는 지하층까지 상기 제3공정과 제4공정을 반복하면서 지하층을 단계적으로 형성하는 공정을 포함하여 이루어지는 특징이 있다.And a step of forming the basement layer step by step while repeating the third and fourth steps up to the desired basement layer after the concrete in the fourth step is cured.

상기 보 하강틀과 슬래브 하강틀 및 보 형틀과 슬래브 형틀은 다수 개로 분리 구성되어 각각 독립적으로 하강 및 형틀 작업이 이루어질 수 있다.The beam lowering frame, the slab lowering frame, the beam frame, and the slab frame may be separated into a plurality of blocks, and the frames may be independently lowered and formed.

여기서 상기의 각 공정의 구분은 이해를 돕기 위한 형식적인 것으로서 실제로는 정확하게 구분됨이 없이 연속적인 공정으로 이루어질 수 있다.Here, the division of each of the above processes is a formal one for the purpose of understanding, and it can be realized by a continuous process without being actually divided correctly.

상기 인양구는 철근이나 와이어 또는 볼트를 이용할 수 있으며, 1층 또는 각 작업층의 상층에서 삼각지주 및 체인블럭에 의해 지지된 상태로 하강시킬 수 있다.The lifting rods can be reinforcing bars, wires or bolts, and can be lowered in a state of being supported by a triangular support and a chain block in one layer or in an upper layer of each working layer.

그리고, 상기 4공정에서 인양구의 설치시에는 인양구가 통과하는 부위에 관을 매설하여 보 하강틀 및 슬래브 하강틀의 하강 작업이 가능한 공간을 확보하게 된다.In addition, when the lifting sphere is installed in the step 4, a tube is buried in a portion through which the lifting mouth passes, thereby securing a space in which the beam lowering frame and the slab lowering frame can be lowered.

상기 슬래브 형틀은 데크로 대신하여 설치할 수도 있으며, 호리빔으로 슬래브 형틀을 지지하거나 또는 데크를 설치하여 콘크리트를 타설할 수 있는 것이다.The slab formwork may be provided in place of a deck, or a slab formwork may be supported by a hori- ze beam or a deck may be installed to pour concrete.

이와 같이 본 발명은 슬래브의 형성시 하나의 형틀을 이용하여 여러 층의 시공이 가능하여 시공기간과 시공비용을 대폭 절감할 수 있으면서, 보 형틀 및 슬래브 형틀이 다수 개로 분리되어 각각의 제작 및 설치 작업이 간편하게 이루어질 수 있는 효과를 제공한다.In the present invention, it is possible to construct a slab with a plurality of layers by using one frame, thereby greatly reducing the construction period and the construction cost, while separating the frame and the slab frame into a plurality of blocks, Thereby providing an effect that can be easily achieved.

또한, 본 발명에 따르면, 형틀 등의 자재를 최소화하여 형틀의 전용도를 높이면서 완료된 후의 자재의 해체, 철거 및 정리가 간편하게 이루어질 수 있는 효과를 제공하게 된다.In addition, according to the present invention, it is possible to minimize the material such as a mold, thereby enhancing the degree of exclusive use of the mold, and simplifying the disassembly, demolition, and arrangement of the finished material.

본 발명에 따른 시공이 이루어지기 전에 일반적으로 선행되는 공사로서 지하 연속벽 공사(slurry wall)와 보드 파일(bored pile/R.C.D) 공사를 하게 된다.Prior to the construction according to the present invention, a slurry wall and a bored pile / R.C.D. construction are generally performed as a preceding construction.

지하 연속벽(W) 공사는 지중에 도랑을 굴착하고 철근망을 건입한 후 콘크리트를 타설함으로써 구조물을 안전하게 연속적으로 시공할 수 있도록 하는 것이며, 가시설 흙막이 벽체로서의 역할과 더불어 건물구조체(지하외벽)로서의 역할을 갖는 것이다.The underground continuous wall (W) works to excavate the ditch in the ground and install the concrete after the reinforcing net is inserted, so that the structure can be safely and continuously constructed. In addition to its role as a temporary earth retaining wall, It has a role.

보드 파일 공사는 기둥을 이루는 위치를 굴착하여 여기에 기둥철골(P)을 삽입한 후 기둥철골의 하부에 철근 콘크리트를 주입하여 지반에 견고하게 고정시키는 작업으로서 건물의 주요 철골 기둥을 이루게 되며, 차후 진행하는 슬래브 설치작업의 주요 기준 및 지지기반이 된다.The construction of the board pile is to drill the position of the column, to insert the column steel (P) into it, to inject the reinforced concrete into the lower part of the column steel, to firmly fix it to the ground and to form the main steel column of the building It is the main criterion and support base for ongoing slab installation work.

도 2는 본 발명에 따른 시공시에 보 형틀 및 슬래브 형틀이 배치되는 형태를 일례로 나타낸 평면도이고, 도 3 내지 도 8은 본 발명에 따른 시공방법에 따라 순 차적인 시공이 이루어지는 단계를 일실시예로서 나타낸 설치 상태도이다.FIG. 2 is a plan view showing an example in which a bottle frame and a slab frame are disposed at the time of construction according to the present invention, and FIGS. 3 to 8 illustrate a step in which a sequential construction is performed according to a construction method according to the present invention. Fig.

도면에서 동일 명칭부분에 대해서는 동일 부호를 적용한다.In the drawings, the same reference numerals are applied to the same names.

우선 도 2의 평면도에서 도시한 바와 같이 각 층을 형성하는 슬래브를 여러 개의 보(b) 및 슬래브(s) 부분으로 구획하게 되며, 구획된 각 부분마다 현수부재가 설치될 포인트(m)를 정하게 된다.First, as shown in the plan view of FIG. 2, the slab forming each layer is divided into a plurality of beams b and slabs s, and a point m at which the suspension member is installed is defined for each partitioned part do.

처음의 공정에서는 도면에 도시되지 않았지만 연속벽이나 철골기둥이 설치되어 있는 상태에서 진행하게 되며, 우선 지상 1층의 보 하부까지 터파기 공사가 이루어지고, 여기에 보 및 슬래브의 하강틀과 형틀이 설치되는데, 도 3은 보 하강틀의 설치 초기 상태를 보여준다.In the first step, although not shown in the drawings, a continuous wall or a steel column is installed, and the earthquake first proceeds to the lower part of the ground, and the lowering frame and the slab of the beam and slab FIG. 3 shows the initial state of the beam lowering frame.

도 3에 도시된 바와 같이, 구획된 대로 다수의 보 하강틀(1)을 배치하게 되는데, 상기 보 하강틀(1)은 보 멍에(4)와 이 보 멍에(4)를 받쳐주는 금속형강(6)으로 이루어져 있고, 보 하강틀(1)의 윗면에는 보 형틀을 구성하는 보 밑판(7)이 설치되어 있다.As shown in FIG. 3, a plurality of beam lowering frames 1 are arranged as they are partitioned. The beam lowering frames 1 include a beam 4 and a metal frame (not shown) supporting the beam 4 6, and a beam bottom plate 7 constituting a beam frame is provided on the upper surface of the beam lowering frame 1.

그리고, 상기 금속형강(6)은 "C형강"을 맞대어 그 중간에 현수부재(h)가 통과되도록 되어 있으며, 이 현수부재(h)의 하단과 상단은 나사부(8)가 형성되어 있어서, 현수부재(h)의 상단과 하단에 와셔(9)를 조립하여 상단은 상기 보 밑판(7)을 결속하고, 하단은 상기 금속형강(6)의 하측에 지지되도록 하면서, 상단과 하단의 더 돌출된 상기 나사부(8)에 또 다른 현수부재를 너트에 의해 연결되도록 되어 있다.The metal section 6 has a "C-shaped steel" and a hanging member h is passed through the hole. The lower end and the upper end of the hanging member h are formed with a thread 8, The washer 9 is assembled to the upper and lower ends of the member h so that the upper end binds the lower plate 7 and the lower end thereof is supported on the lower side of the metal section 6, And another suspending member is connected to the threaded portion 8 by a nut.

상기 현수부재(h)는 철근이나 와이어, 볼트 및 로프 등을 적용할 수 있으며, 이러한 현수부재를 연결할 수 있는 구조는 그 형태가 다양하게 실시될 수 있으며, 어떠한 형태를 적용하여도 무방하다.The suspension member h may be a reinforcing bar, a wire, a bolt, a rope, or the like, and the structure capable of connecting the suspension member may be variously shaped, and any shape may be applied.

도 4는 보 형틀의 설치 상태를 구체적으로 보여주고 있는데, 이에 도시된 바와 같이, 상기 보 하강틀(1)의 위에서 보 형틀(11)이 설치되어 보(b)를 형성하도록 되고, 상기 보 형틀(11)의 양 외측에서 상기 현수부재(h)가 설치되며, 상기 현수부재(h)가 통과하기 위한 공간을 확보하기 위하여 주름관(14)이 매입되도록 설치되고 이 주름관(14)을 상기 현수부재(h)가 통과되도록 한다.4 is a perspective view showing a state of the bicycle frame. As shown in FIG. 4, the bicycle frame 11 is provided at the top of the bicycle frame 1 to form the bike b, The hung member h is installed on the outer side of the hung member 11 and the bell pipe 14 is installed so as to secure a space for the hung member h to pass therethrough, (h).

도 5는 상기 보 하강틀(1) 및 보 형틀(11)이 서포트(15)에 의해 지지되도록 설치된 상태를 나타내며, 여기에 슬래브 하강틀(2) 및 슬래브 형틀(12)이 서포트(15)에 의해 지지되도록 함께 설치된 상태가 도 6에 도시되어 있다.5 shows a state in which the beam lowering frame 1 and the beam forming frame 11 are supported by the support 15 and the slab lowering frame 2 and the slab frame 12 are supported by the support 15 6 are shown together.

상기 슬래브 하강틀(2) 및 슬래브 형틀(12)은 보 하강틀(1) 및 보 형틀(11)의 설치 구조와 동일한 단면구성으로 되어 있으며, 역시 동일한 작업을 거치게 된다.The slab lowering frame 2 and the slab frame 12 have the same sectional structure as the installation structure of the beam lowering frame 1 and the blanking frame 11, and the same operation is performed.

상기 서포트(15)는 소위 "동바리"라고 하며, 도면에서는 중간이 나사 조립되어 분리될 수 있는 것으로 선택되어 있으며, 일체형으로 적용될 수도 있다.The support 15 is referred to as a so-called "shore ", and in the drawing, the middle is selected to be assembled by screwing, and can be applied integrally.

또한, 상기 서포트(15)에 의해 각 보 하강틀(1)과 슬래브 하강틀(2)을 지지할 때, 서포트(15)의 하단이 지면에 그대로 설치될 수도 있으나, 지면 상태에 따라 지지하는 강도가 다를 수 있으므로, 지면에 패널(16)을 필요에 따라 한 개 또는 다수 개를 깔고, 그 위에 상기 서포트(15)를 설치할 수 있으며, 필요에 따라 상기 패널(16)의 위에 각목(17)을 더 얹고 이 각목(17) 위에 상기 서포트(15)를 설치할 수 있다.The lower end of the support 15 may be installed on the ground as it is when the support beams 15 and the slab lowering frames 2 are supported by the support 15, One or more panels 16 may be laid on the ground as required and the support 15 may be provided on the panel 16. The panels 17 may be provided on the panel 16, And the support 15 can be installed on the tree 17.

다음의 공정에서는 상기와 같이 보 형틀(11) 및 슬래브 형틀(12)이 설치된 상태에서 철근을 배양하고 콘크리트를 타설하여 지상 1층을 형성하게 되는데, 도 7은 이렇게 지상 1층의 콘크리트를 타설한 상태를 도시하고 있다.In the next step, the reinforcing bars are cultivated in the state that the bottle frame 11 and the slab frame 12 are installed as described above, and concrete is laid to form one ground layer. Fig. 7 shows a concrete structure Respectively.

이 상태에서 콘크리트의 양생이 이루어지게 되고, 양생이 완료되면, 다음의 공정으로서 지하의 터파기 작업 후 각 형틀의 하강 작업이 이루어지게 되는데, 그 전에 터파기 작업을 위해 상기 보 하강틀(1) 및 슬래브 하강틀(2)을 지지하는 서포트(15)를 처리하게 되는데, 각 서포트(15)들을 모두 분리하여 정리한 다음 터파기 작업을 할 수도 있으며, 다르게는 도 8과 같이 서포트(15)의 중간을 절곡하여 접어올린 다음 서포트(15)의 하단을 보 하강틀(1) 및 슬래브 하강틀(2)의 일단에 매달아 두고, 터파기 작업이 완료되면 보 하강틀(1) 및 슬래브 하강틀(2)과 함께 하강시켜서 그대로 연속적인 작업을 할 수 있다.In this state, the concrete is cured. When the curing is completed, the lowering work of each of the molds is performed after the subterranean trenching work as the next step. Before that, And the support 15 supporting the slab lowering frame 2 may be processed. Alternatively, the support 15 may be separated from the supports 15 and then subjected to a tearing operation. Alternatively, as shown in FIG. 8, The lower end of the support 15 is hung on one end of the beam lowering frame 1 and the slab lowering frame 2 so that the beam lowering frame 1 and the slab lowering frame 2 2), so that continuous operation can be performed.

즉, 서포트(15)의 상단부는 보 하강틀(1) 또는 슬래브 하강틀(2)의 밑면에 못으로 고정하여 사용하게 되며, 서포트(15)의 상단에 근접한 어느 일단이 분리되어 절곡부(20)를 이루고, 이 절곡부(20)는 서로 요철 형상으로 끼워진 상태에서 핀(21)으로 연결되어 있으며, 이 핀(21)을 중심으로 회전 절곡이 가능하도록 되어 있다.That is, the upper end of the support 15 is fixed to the bottom of the beam lowering frame 1 or the slab lowering frame 2 with a nail, and one end near the upper end of the support 15 is separated, The bent portion 20 is connected to the pin 21 in a state of being fitted in a concavo-convex shape, and is capable of rotationally bending about the pin 21.

다르게는, 상기 서포트(15)의 상단부분에 경첩(도면에 도시안됨)을 부착하여 이 경첩에 의해 절곡부를 형성할 수도 있다.Alternatively, a hinge (not shown) may be attached to the upper end of the support 15 to form the bent portion by the hinge.

따라서, 하층의 터파기 작업을 진행하고자 하면, 상기 서포트(15)의 절곡 부(20)를 절곡시켜서 서포트(15)의 하단을 보 하강틀(1) 또는 슬래브 하강틀(2)에 끈으로 매달아 두게 된다.The support 15 is bent at the bent portion 20 of the support 15 so that the lower end of the support 15 is fastened to the beam lowering frame 1 or the slab lowering frame 2 with a strap I will.

상기 서포트(15)를 매달기 위하여 보 하강틀(1) 또는 슬래브 하강틀(2)의 밑면에는 끈을 묶을 수 있는 돌기나 구멍(22)이 다수 형성될 수 있을 것이다.A plurality of protrusions or holes 22 may be formed on the underside of the beam lowering frame 1 or the slab lowering frame 2 to suspend the support 15.

도 9는 보 하강틀(1)을 하강시키는 상태를 도시한 것이며, 도 10은 하강된 보 하강틀(1)에 지하 1층의 보 형틀(11)이 설치된 상태를 나타낸다.Fig. 9 shows a state in which the beam lowering frame 1 is lowered, and Fig. 10 shows a state in which the lower beam lowering frame 1 is provided with a bolt 11 having a single basement.

도 9 및 도 10을 참조하면, 지상 1층의 지면에 삼각지주(31)와 체인블럭(32)을 설치하여 상기 현수부재(h)를 인양하여 하강시키게 되며, 하강된 보 하강틀(1)에 지하 1층의 보 형틀(11)을 설치한 후 서포트(15)에 의해 지지시킨다.9 and 10, a triangular support 31 and a chain block 32 are installed on one ground level to lift the suspending member h to descend, and the lowered beam lowering frame 1, A bolt 11 of a basement 1 is installed on the support frame 15 and then supported by a support 15.

이어서, 마찬가지의 방법으로 지상 1층의 슬래브 하강틀(2)과 슬래브 형틀(12)을 하강시켜서 도 11에서와 같이 지하 1층의 전체적인 형틀을 갖추게 되고, 여기에 지하 1층의 콘크리트 타설 및 양생이 이루어지게 된다.Subsequently, the slab lowering frame 2 and the slab frame 12 are lowered in the same manner as in the first embodiment, so that the whole form frame of the first basement is provided as shown in Fig. 11, and the concrete pouring and curing .

계속하여 지하 층의 보 및 슬래브 공사를 상기와 같은 지하 1층의 시공방식으로 반복적으로 진행하게 되며, 최종 지하층의 콘크리트 양생이 완료되면, 상기 보 하강틀(1)과 보 형틀(11) 및 슬래브 하강틀(2)과 슬래브 형틀(12)을 분리 해체하여 제거하게 되며, 현수부재(h)를 인양하기 위하여 설치된 주름관(14) 부분의 마무리 공사를 하게 된다.Subsequently, the beam and slab construction of the underground layer are repeatedly carried out by the construction method of the underground one layer as described above. When the concrete curing of the final underground layer is completed, the beam lowering frame 1, the bolt- The lowering frame 2 and the slab formwork 12 are separated and removed so as to finish the part of the corrugated pipe 14 installed to lift the suspension member h.

한편, 본원 시공방법에서는 보 하강틀(1)에 설치되는 보 형틀(11)에서 측면의 형틀은 각 층 마다 별도로 시공될 수 있는데, 이는 보 하강틀(1)과 보 형틀(11)의 하강시 보 형틀(11)의 측면이 슬래브 형틀(12)과의 접촉으로 인해 분리 작업이 번거로울 수 있어서 별도의 조립이 오히려 편리할 수 있기 때문이며, 구조에 따라서는 보 형틀(11)의 측면 부분도 함께 하강시킬 수도 있다.On the other hand, in the construction method of the present invention, the side molds can be separately constructed for each layer in the bottle mold 11 installed in the beam lowering frame 1. This is because when the beam lowering frame 1 and the bottle mold 11 are lowered This is because the side surface of the bolt hole 11 may be troublesome in the separation operation due to the contact with the slab formwork 12, so that it is more convenient to separate the bolt hole 11 from the side surface of the bolt hole 11, .

이상의 실시예에서 살펴본 바와 같이 본 발명에 따르면, 각 지하층의 슬래브를 일개 층의 보와 슬래브의 하강틀을 연속적으로 하강시키면서 시공할 수 있어서 간편한 시공이 이루어질 수 있고, 자재를 줄여서 비용 및 인력을 절감할 수 있음을 알 수 있다.As described above, according to the present invention, the slabs of the respective basement layers can be constructed while continuously lowering the lowering frame of one layer of beams and slabs, so that the construction can be carried out easily, and the cost and manpower can be reduced by reducing the material It can be seen that

그리고, 실시예에서는 연속벽과 철골기둥이 먼저 설치된 상태에서 슬래브 공사가 진행되었으나, 연속벽은 경우에 따라 선 시공되지 않을 수도 있다.In the embodiment, the slab construction proceeds while the continuous wall and the steel column are installed in advance, but the continuous wall may not be installed in some cases.

또한, 상기의 실시예에서는 슬래브 형틀을 사용하는 것으로 설명하였으나, 형틀 대신에 데크를 적용하여 실시할 수도 있을 것이다.In the above embodiment, the slab form frame is used, but the deck may be applied instead of the form frame.

이상에서 설명하고 도시한 바와 같은 본 발명은 상기의 실시예에 한정하는 취지는 아니며, 본 발명의 요지를 벗어나지 않는 범위 내에서 여러 형태의 실시가 가능하다. 예를 들면, 보와 슬래브의 구획은 건축물의 구조에 따라 임의적인 선택이 이루어질 수 있고, 서포트의 구조나 하강틀 및 형틀의 자체적인 구조는 필요에 따라 선택될 수 있을 것이다.The present invention as described and illustrated above is not intended to be limited to the above-described embodiments, and various modes of practice are possible without departing from the gist of the present invention. For example, the sections of beams and slabs can be arbitrarily selected according to the structure of the building, and the structure of the supports, the lowering frame and the structure of the frame itself can be selected as needed.

도 1은 일반적인 탑 다운 시공방법을 나타낸 단면도1 is a cross-sectional view showing a general top-

도 2는 본 발명에 따른 시공시에 보 형틀 및 슬래브 형틀이 배치되는 형태를 일례로 나타낸 평면도FIG. 2 is a plan view showing an example in which a bottle frame and a slab frame are arranged at the time of construction according to the present invention.

도 3 , 도 5, 도 6, 도 7, 도 9, 도 10 및 도 11은 본 발명에 따른 시공의 일례를 단계적으로 나타낸 시공 상태도Figs. 3, 5, 6, 7, 9, 10 and 11 are diagrams showing a construction state stepwise showing an example of construction according to the present invention

도 4는 본 발명에 따른 보 형틀의 설치 상태 단면도Fig. 4 is a sectional view of the bottle-shaped frame according to the present invention

도 8은 본 발명에 따른 서포트를 접어 올린 상태도8 shows a state in which the support according to the present invention is folded up

※ 도면의 주요 부분에 대한 부호의 설명 ※[Description of Reference Numerals]

b : 보 s : 슬래브b: Measure: Slab

m : 포인트 m: points

1 : 보 하강틀 2 : 슬래브 하강틀1: beam lowering frame 2: slab lowering frame

4 : 보 멍에 6 : 금속형강4: yoke 6: metal section steel

7 : 보 밑판 8 : 나사부7: beam bottom plate 8:

9 : 와셔 11 : 보 형틀9: Washer 11: Beam frame

12 : 슬래브 형틀 14 : 주름관12: a slab form frame 14: a corrugated pipe

15 : 서포트 16 : 패널15: Support 16: Panel

17 : 각목 20 : 절곡부17: Shape 20: Bending section

21 : 핀 22 : 구멍21: pin 22: hole

31 : 삼각지주 32 : 체인블럭31: triangular support 32: chain block

Claims (4)

지하층 기둥을 선 시공한 후 단계별로 지하층 슬래브와 토공사를 위에서 아래로 반복해 가면서 지하구조물을 형성하는 탑 다운 콘크리트 슬래브 시공방법에 있어서,A method of constructing a top-down concrete slab in which an underground structure is formed by repeating a basement slab and earthworks from top to bottom, 1층 보 하부까지 터파기 공사를 하고, 보 하강틀 및 1층 보 형틀을 설치하여 서포트에 의해 지지한 다음, 슬래브 하강틀 및 슬래브 형틀을 설치하여 서포트에 의해 지지시키는 제1공정과;A first step of performing a trench construction to the lower portion of the first story beam, installing a beam descending frame and a first-stage beam frame, supporting the same by a support, and then supporting the slab descending frame and the slab frame by a support; 상기 보 하강틀과 슬래브 하강틀에 인양구를 설치하고 철근을 배근한 후 콘크리트를 타설하여 1층 보 및 슬래브를 형성하는 제2공정과;A second step of installing a lifting platform on the beam lowering frame and the slab lowering frame, placing a reinforcing bar and casting concrete to form a single-layer beam and a slab; 상기 제2공정에서의 콘크리트가 양생된 후, 상기 서포트를 해체하고 지하 1층 이하의 깊이로 터파기 공사를 하고, 상기 보 하강틀을 인양구에 의해 하강시켜서 지하 1층 보 형틀을 설치하여 서포트에 의해 지지하고, 상기 슬래브 하강틀 및 슬래브 형틀을 하강시켜서 지하 1층 슬래브 형틀을 설치하여 서포트에 의해 지지시키는 제3공정과;After the concrete in the second step is cured, the support is disassembled and the trench construction is carried out to a depth of not more than one layer below the foundation, and the beam lowering frame is lowered by a lifting section to form a one- A third step of lowering the slab-lifting frame and the slab-lifting frame so that the slab-lifting frame and the slab-lifting frame are supported by a support; 상기 보 하강틀과 슬래브 하강틀에 인양구를 설치하고 철근을 배근한 후 콘크리트를 타설하여 지하 1층 보 및 슬래브를 형성하는 제4공정과;A fourth step of installing a lifting platform on the beam lowering frame and the slab lowering frame, placing a reinforcing bar and placing concrete thereon to form a 1-story underground beam and a slab; 상기 제4공정에서의 콘크리트가 양생된 후, 원하는 지하층까지 상기 제3공정과 제4공정을 반복하면서 지하층을 단계적으로 형성하는 공정을 포함하여 이루어지는 것을 특징으로 하는 탑 다운 콘크리트 슬래브 시공방법.And a step of forming the basement layer step by step by repeating the third step and the fourth step to a desired basement layer after the concrete in the fourth step is cured. 제 1 항에 있어서,The method according to claim 1, 상기 보 하강틀과 슬래브 하강틀 및 보 형틀과 슬래브 형틀은 다수개로 분리 구성되어 각각 독립적으로 하강 및 형틀작업이 이루어지도록 된 것을 특징으로 하는 탑 다운 콘크리트 슬래브 시공방법.Wherein the beam lowering frame, the slab lowering frame, the beam frame, and the slab frame are divided into a plurality of blocks, and the lowering frame and the slab frame are independently formed. 제 1 항에 있어서,The method according to claim 1, 상기 서포트의 하단을 지지하기 위하여 지면에 패널이나 각목을 깔고 그 위에 상기 서포트를 설치하는 것을 특징으로 하는 탑 다운 콘크리트 슬래브 시공방법.Wherein the support is laid over a panel or a tree on the ground to support the lower end of the support. 제 1 항에 있어서,The method according to claim 1, 상기 서포트는 중간에 절곡부가 형성되어 있어서 콘크리트 양생이 완료된 후 하층의 터파기 작업 전에 상기 절곡부를 절곡시켜서 서포트의 하단을 상기 보 하강틀이나 슬래브 하강틀의 하단에 끈으로 매달아 두고, 터파기 작업이 완료되면 상기 보 하강틀 또는 슬래브 하강틀과 함께 하강시켜서 그대로 재 사용이 이루어지도록 된 것을 특징으로 하는 탑 다운 콘크리트 슬래브 시공방법.After the concrete curing is completed, the support is bent in the middle so that the bent portion is bent before the tearing operation of the lower layer, so that the lower end of the support is suspended by the string at the lower end of the beam lowering frame or the slab lowering frame, And when it is completed, it is lowered together with the beam-lowering frame or the slab-lowering frame, and is reused as it is.
KR1020090025157A 2009-03-24 2009-03-24 Construction method of Top-down concrete slab KR101106799B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090025157A KR101106799B1 (en) 2009-03-24 2009-03-24 Construction method of Top-down concrete slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090025157A KR101106799B1 (en) 2009-03-24 2009-03-24 Construction method of Top-down concrete slab

Publications (2)

Publication Number Publication Date
KR20100106882A KR20100106882A (en) 2010-10-04
KR101106799B1 true KR101106799B1 (en) 2012-01-19

Family

ID=43128895

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090025157A KR101106799B1 (en) 2009-03-24 2009-03-24 Construction method of Top-down concrete slab

Country Status (1)

Country Link
KR (1) KR101106799B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924608B (en) * 2014-04-18 2016-05-04 中交第一公路工程局有限公司 A kind of detachable end steel jacket box device that has
CN112160760B (en) * 2020-09-12 2022-07-22 中铁隧道局集团有限公司 Construction method for coping with accumulated slag in large-diameter slurry shield cabin

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000018037A (en) * 2000-01-05 2000-04-06 박정진 Hanging form system
KR100261775B1 (en) 1997-07-31 2000-07-15 박형국 Method for non-supporting formwork for top_down construction and anchorage, coupler, supporting frame and hydraulic lift
KR100484512B1 (en) 2002-11-12 2005-04-20 (주)거혁건설 The constructing and dismantling method of concrete forms constructed for wall and slab
KR100821663B1 (en) 2005-11-25 2008-04-11 근보건설주식회사 Construction method of Top-down concrete slab

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100261775B1 (en) 1997-07-31 2000-07-15 박형국 Method for non-supporting formwork for top_down construction and anchorage, coupler, supporting frame and hydraulic lift
KR20000018037A (en) * 2000-01-05 2000-04-06 박정진 Hanging form system
KR100484512B1 (en) 2002-11-12 2005-04-20 (주)거혁건설 The constructing and dismantling method of concrete forms constructed for wall and slab
KR100821663B1 (en) 2005-11-25 2008-04-11 근보건설주식회사 Construction method of Top-down concrete slab

Also Published As

Publication number Publication date
KR20100106882A (en) 2010-10-04

Similar Documents

Publication Publication Date Title
KR101341679B1 (en) Device for constructing an underground structure and method thereof
KR100821663B1 (en) Construction method of Top-down concrete slab
KR20100100165A (en) Slab top-down method of underground construction
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101401057B1 (en) Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed
KR101329443B1 (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
KR20090090742A (en) Bottom-up construction method of underground structure using permanent strut
KR20060096706A (en) Deck suspension top-down method of sub-structure
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
KR101106799B1 (en) Construction method of Top-down concrete slab
KR101358471B1 (en) architecture using a complex steel pile
KR200385376Y1 (en) Form system for construction of underground slab
JP4211491B2 (en) Method for constructing wall structure with permanent anchor, wall structure constructed by this method
JP2006299660A (en) Temporary receiving construction method and temporary receiving structure
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
KR101249660B1 (en) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure
KR200390421Y1 (en) Top-down substructure by deck suspension
JP3644606B2 (en) Installation method of formwork support in reverse placement method
JP3208100U (en) Scaffolding device for construction of underground structures
KR100679986B1 (en) Structure for plastic slab deck system and Downward construction method using the same
JP5850528B2 (en) Structure with ramen frame
KR100593203B1 (en) a deck supportframe and a construction methed

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150107

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170111

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180209

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190425

Year of fee payment: 8