CN109706953B - Die for foundation slab of assembled concrete underground building and drawing die construction method - Google Patents

Die for foundation slab of assembled concrete underground building and drawing die construction method Download PDF

Info

Publication number
CN109706953B
CN109706953B CN201910051764.6A CN201910051764A CN109706953B CN 109706953 B CN109706953 B CN 109706953B CN 201910051764 A CN201910051764 A CN 201910051764A CN 109706953 B CN109706953 B CN 109706953B
Authority
CN
China
Prior art keywords
concrete
drawing die
foundation slab
guide rail
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910051764.6A
Other languages
Chinese (zh)
Other versions
CN109706953A (en
Inventor
孟凡林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Ronghuida Construction Engineering Co ltd
Original Assignee
Jilin Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Jianzhu University filed Critical Jilin Jianzhu University
Priority to CN201910051764.6A priority Critical patent/CN109706953B/en
Publication of CN109706953A publication Critical patent/CN109706953A/en
Application granted granted Critical
Publication of CN109706953B publication Critical patent/CN109706953B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The die for the foundation slab of the assembled concrete underground building and the drawing die construction method belong to the technical field of building engineering, the foundation slab of the assembled concrete underground building is constructed by adopting a drawing die method, a drawing die platform is a steel die plate capable of being drawn horizontally and moved, the inner contour of the drawing die platform is the same as the outer contour of the foundation slab, and the drawing die platform comprises a concrete hopper, vibrating holes, bearing wheels, guide wheels, a rubber sealing plate, a supporting structure and a forming die plate; the weight of the horizontal drawing die table is transmitted to the guide rail through the bearing wheel, is transmitted to the bearing pile through the guide rail and finally is transmitted to the foundation; the guide wheels are used for ensuring that the travelling route of the horizontal drawing die table is not deviated; the rubber sealing plates clamp the inverted T-shaped steel below the guide rail from two sides, so that the concrete is ensured not to leak slurry at the track position. By adopting the construction method, the construction of the foundation slab of the assembled concrete underground building has the advantages of good quality, high speed and low cost.

Description

Die for foundation slab of assembled concrete underground building and drawing die construction method
Technical Field
The invention belongs to the technical field of constructional engineering, relates to the construction of concrete underground buildings, and in particular relates to a drawing die construction method for an assembled concrete underground building foundation slab.
Background
The existing construction method of the foundation slab of the assembled concrete underground building mainly comprises the following two modes:
the first is a traditional common construction method, similar to the traditional foundation construction method of an assembled concrete single-layer industrial factory building, a mode of formwork supporting, steel bar binding and concrete beating is adopted, an installation groove of an upper vertical component is prepared on a foundation slab of an assembled concrete underground building, and the invention patent application specification CN201810551369.X discloses a semi-prefabricated assembled comprehensive pipe gallery and a construction method, wherein the comprehensive pipe gallery comprises: a cup-shaped groove is arranged on the cast-in-situ formed bottom plate at the position corresponding to the wallboard; the prefabricated pipe gallery section comprises an integrally formed top plate and a plurality of wallboards vertically connected with the top plate, wherein the wallboards are inserted into corresponding cup-shaped grooves, and two adjacent pipe gallery sections are fixedly connected through a cast-in-situ connecting section; the pitch mastic layer is filled in the cup-shaped groove, and the top surface of the pitch mastic layer is at a set distance from the notch of the cup-shaped groove; and pouring a waterproof concrete structure formed in the cup-shaped groove, wherein the waterproof concrete structure is positioned on the asphalt mastic layer and is used for sealing the notch of the cup-shaped groove. The invention adopts the cup groove node structure to connect the cast-in-situ bottom plate and the prefabricated wall plate, avoids the overlap joint and binding construction of the reinforcing steel bars between the prefabricated component and the cast-in-situ component, has simple construction and improves the construction efficiency. However, the method is not innovative, and the construction precision and the appearance quality are not ideal.
Secondly, the construction method of full prefabrication prepares the assembled concrete underground building foundation slab in a factory mode, installs the foundation slab on site, then grouting the bottom of the foundation slab to finish the construction of the foundation slab, and has good construction quality, high precision and clean appearance. However, the method has low efficiency and high manufacturing cost, and the grouting quality is difficult to ensure.
The existing construction method of the foundation slab of the assembled concrete underground building has the problems of unsatisfactory construction precision and appearance quality, low efficiency, high manufacturing cost, difficult quality assurance and the like, and a new technical scheme needs to be provided.
Disclosure of Invention
The technical problems to be solved by the invention are as follows: the die and the drawing die construction method for the foundation slab of the assembled concrete underground building are provided, and the foundation slab of the assembled concrete underground building is constructed by adopting a flat drawing die method, so that the construction quality is good, the speed is high and the cost is low; the method is particularly suitable for construction and construction of the bottom plate of the assembled concrete underground building, including construction of projects such as concrete underground pipe gallery, subway station line, tunnel and the like.
The die for the foundation slab of the assembled concrete underground building comprises a guide rail and a horizontal drawing die platform;
the guide rail is a steel pipe, and inverted T-shaped steel is arranged at the lower part of the steel pipe;
the horizontal drawing die table comprises a concrete hopper, vibrating holes, bearing wheels, guide wheels, a rubber sealing plate, a supporting structure and a forming die plate, wherein the inner contour of the forming die plate is consistent with the outer contour of the foundation slab; the concrete hopper is arranged at the highest point of the design height of the foundation slab; the vibrating holes are arranged in more than two and are positioned between the concrete hoppers to penetrate through the forming templates; the bearing wheels are arranged at the upper part of the guide rail; the guide wheels are arranged on two sides of the guide rail; the rubber sealing plate is arranged at the bottom of the horizontal drawing die table penetrated by the inverted T-shaped steel, and the rubber sealing plate clamps the inverted T-shaped steel arranged at the lower part of the guide rail from two sides.
The drawing die construction method for the foundation slab of the assembled concrete underground building, which is applied to the die for the foundation slab of the assembled concrete underground building, comprises the following steps in sequence;
step one, preparation for construction
After the foundation pit is excavated according to the conventional means, constructing a bearing pile and pouring a concrete cushion according to the design requirements, wherein the bearing pile comprises a steel pile and a concrete pile, a connecting steel plate is arranged at the pile top of the bearing pile, a guide rail is arranged at the top of the bearing pile by adopting a welding or bolting method, and the steel bars of the foundation slab of the assembled concrete underground building are bound;
step two, preparing and installing a horizontal drawing die table
The support structure of the horizontal drawing die table, the forming template and the concrete hopper are prepared from profile steel and a steel plate, more than two vibrating holes are reserved between the concrete hoppers, and the vibrating holes are prepared from steel pipes; the installation sequence of the horizontal drawing die table is that bearing wheels are installed on the upper part of a guide rail, guide wheels are installed on two sides of the guide rail, and rubber sealing plates clamp inverted T-shaped steel arranged on the lower part of the guide rail from two sides;
step three, constructing assembled concrete underground building foundation slab by horizontal drawing die method
Pouring the concrete of the foundation slab of the assembled concrete underground building through a concrete hopper, wherein the slump of the concrete is 0.5-10 mm, and vibrating and compacting the concrete through the concrete hopper and the vibrating holes; translating the horizontal drawing die table along the guide rail, and pouring the concrete of the foundation slab of the assembled concrete underground building of the next working section until all concrete pouring is completed;
step four, removing the horizontal drawing die table
And (3) after all concrete pouring in the step three is completed, removing the horizontal drawing die table, and cleaning for later use.
Through the design scheme, the invention has the following beneficial effects: the die and the drawing die construction method are used for constructing the foundation slab of the assembled concrete underground building, the method of adopting a flat drawing die is adopted for constructing the foundation slab of the assembled concrete underground building, the flat drawing die table is a steel die plate capable of being horizontally drawn and moved, the inner contour of the flat drawing die table is the same as the outer contour of the foundation slab, and the die comprises a concrete hopper, vibrating holes, bearing wheels, guide wheels, a rubber sealing plate, a supporting structure and a forming die plate; the weight of the horizontal drawing die table is transmitted to the guide rail through the bearing wheel, is transmitted to the bearing pile through the guide rail and finally is transmitted to the foundation; the guide wheels are used for ensuring that the travelling route of the horizontal drawing die table is not deviated; the rubber sealing plates clamp the inverted T-shaped steel below the guide rail from two sides, so that the concrete is ensured not to leak slurry at the track position; by adopting the construction method, the construction of the foundation slab of the assembled concrete underground building has the advantages of good quality, high speed and low cost.
Drawings
The invention is further described with reference to the drawings and detailed description which follow:
fig. 1 is a schematic cross-sectional view of a load-bearing pile arrangement according to the present invention.
Fig. 2 is a schematic cross-sectional view of a load bearing pile and rail arrangement of the present invention.
FIG. 3 is a schematic cross-sectional view of the concrete hopper and vibrating aperture location of the flat drawing bench of the present invention.
Fig. 4 is an enlarged partial schematic view of a cross-section of an arrangement of the load bearing wheel, guide wheel and rubber seal plate of the present invention.
FIG. 5 is a schematic longitudinal section of the horizontal drawing die table of the present invention.
Fig. 6 is an enlarged partial schematic view of a longitudinal section of the bearing and guide wheel arrangement of the present invention. .
FIG. 7 is a schematic cross-sectional view of a flat drawing die table according to the present invention.
FIG. 8 is a schematic cross-sectional view of the foundation slab of the present invention after construction.
FIG. 9 is a schematic cross-sectional view of the assembled upper structure of the foundation slab of the present invention.
In the figure, the pile is 1-bearing pile, 2-guide rail, 3-flat drawing die table, 4-concrete hopper, 5-vibrating hole, 6-bearing wheel, 7-guide wheel, 8-rubber sealing plate and 9-foundation slab.
Description of the embodiments
A mould for assembled concrete underground construction foundation slab, characterized by: as shown in fig. 1 to 7, the slide rail comprises a guide rail 2 and a flat drawing die table 3;
the guide rail 2 is made of steel pipes, and the bottom of the guide rail is welded with inverted T-shaped steel;
the horizontal drawing die table 3 is a steel die plate capable of horizontally drawing and moving, and comprises a concrete hopper 4, a vibrating hole 5, a bearing wheel 6, a guide wheel 7, a rubber sealing plate 8, a supporting structure and a forming die plate thereof, wherein the inner contours of the supporting structure and the forming die plate are consistent with the outer contour of a foundation slab 9; the concrete hopper 4 is used for pouring concrete to the foundation slab 9 and is arranged at a position corresponding to the highest point of the foundation slab 9; the vibrating holes 5 are positioned between the concrete hoppers 4 and are made of steel pipes, and two or more than two vibrating holes are uniformly distributed; the bearing wheels 6 are arranged on the guide rail 2 and are made of steel materials and are used for transmitting the gravity of the horizontal drawing die table 3 to the guide rail 2 and supporting the horizontal drawing die table 3; the guide wheels 7 are arranged on two sides of the guide rail 2 and are made of steel materials, and play a role in horizontal positioning and translational guiding when the die platform is translated; the rubber sealing plate 8 is prepared from a rubber plate, is arranged on a template of the horizontal drawing die table 3, clamps inverted T-shaped steel below the guide rail 2 from two sides, and plays a role in sealing during horizontal drawing movement;
the foundation slab 9 is a concrete slab which is prepared by adopting the horizontal drawing die table 3 and is used for an assembled concrete underground building.
A drawing die construction method for an assembled concrete underground building foundation slab is characterized in that: comprising the following steps, which are sequentially carried out,
step one, preparation for construction
After the foundation pit is excavated according to the conventional means, as shown in fig. 1 and 2, constructing a bearing pile 1 and pouring a concrete cushion according to the design requirements, wherein the bearing pile 1 comprises a profile steel pile and a concrete pile, the pile top of the bearing pile 1 is provided with a connecting steel plate, the top of the bearing pile 1 is provided with a guide rail 2 in a welding or bolt connection mode, and the steel bars of an assembled concrete underground building foundation slab 9 are bound;
step two, preparing and installing a horizontal drawing die table 3
As shown in fig. 3 to 7, the support structure and the forming template of the horizontal drawing die table 3 are prepared by adopting profile steel and steel plates, and the horizontal drawing die table further comprises a concrete hopper 4 for pouring concrete, a vibrating hole 5 for vibrating the concrete, a bearing wheel 6, a guide wheel 7 and a rubber sealing plate 8; after the reinforcement of the foundation slab 9 of the assembled concrete underground building prepared by the construction in the step one is completed, installing a horizontal drawing die table 3, placing a bearing wheel 6 on a guide rail 2, placing guide wheels 7 on two sides of the guide rail 2, and clamping inverted T-shaped steel below the guide rail 2 by a rubber sealing plate 8 from two sides;
step three, constructing assembled concrete underground building foundation slab by horizontal drawing die method
As shown in fig. 3 to 7, after the horizontal drawing bench 3 in the second step is installed, pouring the assembled concrete underground building foundation slab 9 concrete through the concrete hopper 4, wherein the slump of the concrete is 0.5mm to 10mm, and vibrating and compacting the concrete through the concrete hopper 4 and the vibrating holes 5; translating the horizontal drawing die table 3 along the guide rail 2, and pouring the concrete of the foundation slab 9 of the assembled concrete underground building of the next working section until the whole concrete pouring is completed;
step four, removing the horizontal drawing die table 3
As shown in fig. 8, after all concrete pouring is completed, the horizontal drawing die table 3 is removed and cleaned for later use.
To this end, as shown in fig. 8, the drawing die construction method for the foundation slab of the fabricated concrete underground building is completed; after the foundation bed 9 reaches the design strength, as shown in fig. 9, the structure of the upper part of the foundation bed 9 of the fabricated concrete underground building can be installed.

Claims (2)

1. A mould for assembled concrete underground construction foundation slab, characterized by: comprises a guide rail (2) and a flat drawing die table (3);
the guide rail (2) is a steel pipe, and inverted T-shaped steel is arranged at the lower part of the steel pipe;
the horizontal drawing die table (3) comprises a concrete hopper (4), vibrating holes (5), bearing wheels (6), guide wheels (7), a rubber sealing plate (8), a supporting structure and a forming die plate, wherein the inner contour of the forming die plate is consistent with the outer contour of the foundation slab (9); the concrete hopper (4) is arranged at the highest point of the design height of the foundation slab (9); the vibrating holes (5) are arranged in more than two and are positioned between the concrete hoppers (4) to penetrate through the forming templates; the bearing wheels (6) are arranged at the upper part of the guide rail (2); the guide wheels (7) are arranged on two sides of the guide rail (2); the rubber sealing plate (8) is arranged at the bottom of the horizontal drawing die table (3) penetrated by the inverted T-shaped steel, and the rubber sealing plate (8) clamps the inverted T-shaped steel arranged at the lower part of the guide rail from two sides.
2. A drawing die construction method for an assembled concrete underground building foundation slab is characterized in that: use of the mould for the foundation slab of a fabricated concrete underground construction of claim 1, comprising the following steps, and the following steps are performed in sequence;
step one, preparation for construction
After excavation of a foundation pit is completed according to conventional means, constructing a bearing pile (1) and pouring a concrete cushion according to design requirements, wherein the bearing pile (1) comprises a profile steel pile and a concrete pile, a connecting steel plate is arranged at the pile top of the bearing pile (1), a guide rail (2) is arranged at the top of the bearing pile (1) by adopting a welding or bolting method, and steel bars of an assembled concrete underground building foundation slab (9) are bound;
step two, preparing and installing a flat drawing die table (3)
The support structure of the horizontal drawing die table (3), the forming die plate and the concrete hopper (4) are prepared by adopting profile steel and steel plates, more than two vibrating holes (5) are reserved between the concrete hoppers (4), and the vibrating holes (5) are prepared by adopting steel pipes; the installation sequence of the horizontal drawing die table (3) is that a bearing wheel (6) is installed on the upper part of the guide rail (2), guide wheels (7) are installed on two sides of the guide rail (2), and rubber sealing plates (8) clamp inverted T-shaped steel arranged on the lower part of the guide rail (2) from two sides;
step three, constructing assembled concrete underground building foundation slab by horizontal drawing die method
Pouring the concrete of an assembled concrete underground building foundation slab (9) through a concrete hopper (4), wherein the slump of the concrete is 0.5-10 mm, and vibrating and compacting the concrete through the concrete hopper (4) and a vibrating hole (5); translating the horizontal drawing die table (3) along the guide rail (2), and pouring the concrete of the foundation slab (9) of the assembled concrete underground building of the next working section until all concrete pouring is completed;
step four, removing the flat drawing bench (3)
And (3) removing the horizontal drawing die table (3) after all concrete in the step (III) is poured, and cleaning for later use.
CN201910051764.6A 2019-01-21 2019-01-21 Die for foundation slab of assembled concrete underground building and drawing die construction method Active CN109706953B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910051764.6A CN109706953B (en) 2019-01-21 2019-01-21 Die for foundation slab of assembled concrete underground building and drawing die construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910051764.6A CN109706953B (en) 2019-01-21 2019-01-21 Die for foundation slab of assembled concrete underground building and drawing die construction method

Publications (2)

Publication Number Publication Date
CN109706953A CN109706953A (en) 2019-05-03
CN109706953B true CN109706953B (en) 2023-10-13

Family

ID=66261491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910051764.6A Active CN109706953B (en) 2019-01-21 2019-01-21 Die for foundation slab of assembled concrete underground building and drawing die construction method

Country Status (1)

Country Link
CN (1) CN109706953B (en)

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09324431A (en) * 1996-06-05 1997-12-16 Home Sera:Kk Construction method of basement
RU2151298C1 (en) * 1998-12-10 2000-06-20 Общество с ограниченной ответственностью "Крот инжиниринг" Device for lining underground structure with cast-in-situ structure
KR20100100165A (en) * 2009-03-05 2010-09-15 이세환 Slab top-down method of underground construction
CN102434171A (en) * 2011-11-17 2012-05-02 广汉金达隧道机械有限公司 Tunnel bottom concrete side-slipping lining construction method and side-slipping needle beam bottom board trolley
CN103174156A (en) * 2013-04-10 2013-06-26 大连宜华建设集团有限公司 Independent basic construction inner template device with cup opening smaller than 600*600 mm<2> and construction method thereof
KR20140008067A (en) * 2012-07-10 2014-01-21 한국철도기술연구원 Low depth tunnel construction method using variable mould system
CN204783054U (en) * 2015-07-08 2015-11-18 中国长江三峡集团公司 Tunnel invert concrete lining's sliding template
CN205822221U (en) * 2016-07-06 2016-12-21 河南五建第二建筑安装有限公司 Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure
CN106638183A (en) * 2016-10-26 2017-05-10 中铁五局集团有限公司 Urban rail transit assembly board type high precision rail base cast-in-place construction method
CN106869166A (en) * 2017-02-28 2017-06-20 中国十七冶集团有限公司 A kind of fabricated construction method for pipe gallery
CN107059920A (en) * 2017-03-23 2017-08-18 海门市帕源路桥建设有限公司 Loess formation piping lane construction technology
CN207277108U (en) * 2017-10-09 2018-04-27 安徽省新路建设工程集团有限责任公司 Vertical type is without slope light ecological embankment structure
CN108560586A (en) * 2018-05-31 2018-09-21 中国建筑第八工程局有限公司 Half prefabricated assembled pipe gallery and its construction method
CN209652963U (en) * 2019-01-21 2019-11-19 吉林建筑大学 Mold for assembly concrete hypogee sole plate

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09324431A (en) * 1996-06-05 1997-12-16 Home Sera:Kk Construction method of basement
RU2151298C1 (en) * 1998-12-10 2000-06-20 Общество с ограниченной ответственностью "Крот инжиниринг" Device for lining underground structure with cast-in-situ structure
KR20100100165A (en) * 2009-03-05 2010-09-15 이세환 Slab top-down method of underground construction
CN102434171A (en) * 2011-11-17 2012-05-02 广汉金达隧道机械有限公司 Tunnel bottom concrete side-slipping lining construction method and side-slipping needle beam bottom board trolley
KR20140008067A (en) * 2012-07-10 2014-01-21 한국철도기술연구원 Low depth tunnel construction method using variable mould system
CN103174156A (en) * 2013-04-10 2013-06-26 大连宜华建设集团有限公司 Independent basic construction inner template device with cup opening smaller than 600*600 mm<2> and construction method thereof
CN204783054U (en) * 2015-07-08 2015-11-18 中国长江三峡集团公司 Tunnel invert concrete lining's sliding template
CN205822221U (en) * 2016-07-06 2016-12-21 河南五建第二建筑安装有限公司 Base isolation system advanced water-stop post-pouring zone steel bar concrete foundation slab structure
CN106638183A (en) * 2016-10-26 2017-05-10 中铁五局集团有限公司 Urban rail transit assembly board type high precision rail base cast-in-place construction method
CN106869166A (en) * 2017-02-28 2017-06-20 中国十七冶集团有限公司 A kind of fabricated construction method for pipe gallery
CN107059920A (en) * 2017-03-23 2017-08-18 海门市帕源路桥建设有限公司 Loess formation piping lane construction technology
CN207277108U (en) * 2017-10-09 2018-04-27 安徽省新路建设工程集团有限责任公司 Vertical type is without slope light ecological embankment structure
CN108560586A (en) * 2018-05-31 2018-09-21 中国建筑第八工程局有限公司 Half prefabricated assembled pipe gallery and its construction method
CN209652963U (en) * 2019-01-21 2019-11-19 吉林建筑大学 Mold for assembly concrete hypogee sole plate

Also Published As

Publication number Publication date
CN109706953A (en) 2019-05-03

Similar Documents

Publication Publication Date Title
CN104533456A (en) Super-large section chamber reinforced concrete modelling construction method
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN210086295U (en) Compound assembled underground structure
CN112502186A (en) Building space structure integrated assembly type subway station structure
CN108951840B (en) Method for constructing arc-shaped outer wall of basement based on single-side formwork support of shaped support
CN110761808A (en) Large-section loess tunnel supporting system and supporting construction method
CN110670722A (en) Implementation method of beam-column connecting node of fabricated building
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN210369032U (en) Socket type precast concrete assembled retaining wall unit and assembled retaining wall thereof
CN110725302B (en) Construction method of prefabricated cast-in-place combined underground diaphragm wall
CN111576236A (en) Method for mounting integral type prefabricated bridge deck auxiliary structure
CN109706953B (en) Die for foundation slab of assembled concrete underground building and drawing die construction method
CN109267578B (en) Inclined plane plain concrete structure and construction method thereof
CN209652963U (en) Mold for assembly concrete hypogee sole plate
CN116378428A (en) Construction method of longitudinal rib superimposed shear wall structure wall
CN111271078A (en) Construction method for assembling sectional longitudinal translation in prefabricated tunnel lining structure tunnel
CN111577345B (en) Construction method and construction system for multilayer anti-seepage tunnel bottom structure
CN110671132B (en) Deep loess tunnel deformation control construction structure and method based on sleeve arch
CN212978682U (en) Concrete precast slab structure for building convenient to pour
CN211038656U (en) Large-section loess tunnel supporting system
CN210151784U (en) Integration template piping lane
CN111622264A (en) Underground pipe gallery automatic control creeping formwork system and operation method thereof
CN111535361A (en) Assembled rail top air duct structure of underground station and construction method thereof
CN211340823U (en) Supporting system for prefabricated hollow plate used for bearing platform and ground beam side mold
CN113931459B (en) Construction method of hollow PVC ribbed wall in tall and big space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240108

Address after: 831100 Shop 2-3, Commercial Building 2, Hope Home Community, Intersection of Mancheng Road and Guihua Road, Jimusar County, Changji Hui Autonomous Prefecture, Xinjiang Uygur Autonomous Region

Patentee after: Xinjiang Ronghuida Construction Engineering Co.,Ltd.

Address before: 130118 No. 5088 Xincheng Street, Changchun City, Jilin Province

Patentee before: JILIN JIANZHU University