CN106869166A - A kind of fabricated construction method for pipe gallery - Google Patents

A kind of fabricated construction method for pipe gallery Download PDF

Info

Publication number
CN106869166A
CN106869166A CN201710111147.1A CN201710111147A CN106869166A CN 106869166 A CN106869166 A CN 106869166A CN 201710111147 A CN201710111147 A CN 201710111147A CN 106869166 A CN106869166 A CN 106869166A
Authority
CN
China
Prior art keywords
construction
template
processing
terrace
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710111147.1A
Other languages
Chinese (zh)
Inventor
吴建国
左军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710111147.1A priority Critical patent/CN106869166A/en
Publication of CN106869166A publication Critical patent/CN106869166A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Abstract

The invention discloses a kind of fabricated construction method for pipe gallery, including following construction procedure:Assembling members process field construction;Custom built forms processing, exterior sheathing are installed;Member reinforcing steel bar etc. is installed;Inner template etc. is installed;Concreting, maintenance, form removal;Component converse transportation, upset, installation;Remaining cast-in-place structural construction.It is an advantage of the invention that:By assembled assembling members independently of field fabrication, constructed with reference to field cast-in-place structure, to shorten the construction period.

Description

A kind of fabricated construction method for pipe gallery
Technical field
The present invention relates to a kind of underground city pipe gallery cast-in-place structural and precast assembly construction method, in particular, It is to be related to a kind of fabricated construction method for pipe gallery.
Background technology
At present, the city integrated piping lane of heavy excavation form construction mainly has following several construction methods:1. conventional method Cast-in-place structural is constructed, and progressively construction cushion coat, base plate, side wall, top board after excavation, all components are cast-in-place.Using cast-in-place structural Advantage is relatively low construction cost, and waterproof effect is preferably, but the duration is more long, is influenceed larger by weather, it is desirable to a fairly large number of work Industry personnel.2. precast assembly method, piping lane standard knot is segmented prefabricated, and piping lane standard knot is prefabricated in factory process, is transported after maintenance Installed to the handling of live crane, connected using tongue and groove between standard knot.Using precast assembly method construction advantage be construction speed compared with Hurry up, and be protected from weather influences, piping lane is prefabricated can be carried out with round-the-clock;Have the disadvantage that piping lane precast plant one-time investment is larger, and it is fixed Pallet quantitative requirement is more, cannot otherwise meet site operation schedule requirement.Tongue and groove and rubber should be used between piping lane standard knot Rubber sealing, water-stagnating effect is limited.3. by the piping lane fabricated construction technology of assembled-type house technical transform, using superimposed sheet generation For conventional mould as concrete formation instrument.The method advantage is to reduce shuttering work amount, accelerating construction progress, but superimposed sheet Be disposable input, it is impossible to secondary turnover, larger increased to cost, and superimposed sheet is needed by prefabrication, cost of transportation compared with It is high.
City integrated piping lane is general to be built in new planning downtown roads or old town transformation, heavy excavation+support form phase Than having unrivaled cost advantage in shield or underground excavation, but influence of the heavy excavation to neighboring buildings, road is larger, therefore Duration is general shorter, and when being constructed using cast-in-place form, duration pressure is very big, and cost, duration cannot balance, and easily cause mistake Control.And the newly-built prefabricated processing factory of piping lane is needed using precast assembly piping lane or is transported to scene from nonlocal processing factory, it is relatively costly, Feasibility is relatively low.
In this case it is desirable to the construction to city integrated piping lane proposes a kind of new burst assembled piping lane construction party Method, improves the construction speed of piping lane under conditions of not improving cost, reducing Pipe rack construction quality, by assembled assembly structure Part is constructed independently of field fabrication with reference to field cast-in-place structure, to shorten the construction period.
The content of the invention
The present invention in view of the shortcomings of the prior art, and provide it is a kind of by will take duration piping lane side wall most long it is prefabricated plus Work, rationally sets construction joint position, and side wall reinforcing bar, embedded part, template construction take long in solution cast-in-place piping lane construction in the past Defect, while putting forward a kind of fabricated construction method for pipe gallery of the construction quality of High lateral wall.
A kind of fabricated construction method for pipe gallery of the invention, including following construction procedure:
A kind of fabricated construction method for pipe gallery, it is characterised in that including following construction procedure:
Step one, assembling members processing field construction;According to construction period, calculate per tooling member quantity day by day, planning processing Scene is accumulated, and processing space is carried out smooth, and component processing district need to pour processing terrace(1), process terrace(1)Press polish twice is needed to smear It is flat, it is ensured that surface smoothness;Processing terrace(1)Length, width determine that standard knot can divide 10m according to member segments length One section is made;
Step 2, custom built forms processing, exterior sheathing are installed;First, according to piping lane base plate and the physical dimension of side wall, sizing is made Template, after template construct, in processing terrace(1)Upper installation component outboard template, install outboard template before need to terrace upper berth every From material, such as felt, plastic foil;
Step 3, member reinforcing steel bar etc. are installed;After outboard template is installed, piping lane side wall reinforcing bar and bottom are laid according to design drawing Plate, top board reserved joint bar, installation side wall built-in fitting, construction joint steel plate for sealing water(3), earthing pole is welded, reserve suspension ring(4);
Step 4, inner template etc. are installed;After the completion of working above, inner side template is installed, reinforces, concealment acceptance;
Step 5, concreting, maintenance, form removal;After concealment acceptance, concreting work is carried out, in time maintenance, during maintenance Between determined according to drawing and code requirement;
Step 6, component converse transportation, upset, installation;After the component conservation phase arrives, can be transported to scene carries out installment work, typically One standard segment length is 30m, and 6 prefabricated components are needed altogether;Preceding scene is installed and answers line setting, arranged component and put sideline, Prevent from lifting off normal;
Step 7, remaining cast-in-place structural construction;After prefabricated components are put in place, the structure construction of construction joint part is carried out.Base plate Used with the reinforcing bar of top board and be welded to connect;Base plate is constructed in two times with top board, base plate of first constructing, then sets up backplanes support system, Roof plate template is installed, concrete roof of constructing.
Typified form makes framework using square steel in the step 2, and wood-plastic board makes surface layer and is made.
The beneficial effects of the invention are as follows:(1), by the way that the duration piping lane side prefabricated processing of wall most long will be taken, rationally set Construction joint position, solves side wall reinforcing bar, embedded part, template construction during conventional cast-in-place piping lane is constructed and takes long defect, while carrying The construction quality of High lateral wall, reduces piping lane construction cost, fast and efficiently completes the construction work of Pipe rack.(2), will dress With formula assembling members independently of field fabrication, constructed with reference to field cast-in-place structure, to shorten the construction period.
Brief description of the drawings
Fig. 1 is prefabricated components making side view in the present invention.
Fig. 2 is prefabricated components rear and cast-in-place structural schematic diagram in place in the present invention.
In figure:Processing terrace(1), piping lane side wall prefabricated components(2), construction joint steel plate for sealing water(3), suspension ring(4), base plate (5), top board(6).
Specific embodiment
Below by specific embodiment, technical scheme is described in further detail, but the present invention is simultaneously It is not limited to embodiment.
A kind of fabricated construction method for pipe gallery of the invention, including following construction procedure:
1)Assembling members process field construction
First according to construction period, calculate per tooling member quantity day by day, plan processing space area, processing space is carried out smooth. Component processing district need to pour processing terrace(1), terrace need press polish twice it is floating, it is ensured that surface smoothness;Processing terrace(1)Length Degree, width determine that standard knot can divide 10m mono- section and be made according to member segments length.
2)Custom built forms processing, exterior sheathing are installed
Principle of the invention is exactly using piping lane side wall as piping lane side wall prefabricated components(2)It is processed, side wall was fallen making, Template demand can be reduced, while putting forward the embedded part flatness of High lateral wall construction, the perpendicularity of side wall reduces horizontal construction joint and applies The leakage is shaken phenomenon that man-hour easily occurs.
First, according to piping lane base plate and the physical dimension of side wall, typified form is made, typified form can use square steel system Make framework, wood-plastic board makes surface layer, or directly customization aluminum alloy mould plate coordinates support system.After template construct, in processing terrace (1)Upper installation component outboard template, need to be in terrace upper berth isolated material, such as felt, plastic foil before installation outboard template.
3)Member reinforcing steel bar etc. is installed
After outboard template is installed, piping lane side wall reinforcing bar and base plate, top board reserved joint bar, installation side wall are laid according to design drawing Built-in fitting, construction joint steel plate for sealing water(3), earthing pole is welded, reserve suspension ring(4).
4)Inner template etc. is installed
After the completion of working above, inner side template is installed, reinforces, concealment acceptance;
5)Concreting, maintenance, form removal
After concealment acceptance, concreting work is carried out, in time maintenance, curing time determines according to drawing and code requirement.
6)Component converse transportation, upset, installation
After the component conservation phase arrives, the scene that can be transported to carries out installment work, and a general standard segment length is 30m, and 6 are needed altogether Prefabricated components.Preceding scene is installed and answers line setting, arranged component and put sideline, prevent from lifting off normal.
7)Remaining cast-in-place structural construction
After prefabricated components are put in place, the structure construction of construction joint part is carried out.The reinforcing bar of base plate and top board is used and is welded to connect. Base plate(5)With top board(6)Construct in two times, base plate of first constructing(5), then backplanes support system is set up, roof plate template, construction are installed Concrete roof.
Embodiments of the invention are the foregoing is only, the scope of the claims of the invention is not thereby limited, it is every to utilize this hair Equivalent structure or equivalent flow conversion that bright description is made, or directly or indirectly it is used in other related technology necks Domain, is included within the scope of the present invention.

Claims (2)

1. a kind of fabricated construction method for pipe gallery, it is characterised in that including following construction procedure:
Step one, assembling members processing field construction;According to construction period, calculate per tooling member quantity day by day, planning processing Scene is accumulated, and processing space is carried out smooth, and component processing district need to pour processing terrace, and processing terrace needs press polish twice floating, it is ensured that Surface smoothness;Process the length of terrace, width and determine that standard knot can divide 10m mono- section and be made according to member segments length Make;
Step 2, custom built forms processing, exterior sheathing are installed;First, according to piping lane base plate and the physical dimension of side wall, sizing is made Template, after template construct, the installation component outboard template on processing terrace need to isolate material before installing outboard template on terrace upper berth Material, such as felt, plastic foil;
Step 3, member reinforcing steel bar etc. are installed;After outboard template is installed, piping lane side wall reinforcing bar and bottom are laid according to design drawing Plate, top board reserved joint bar, installation side wall built-in fitting, construction joint steel plate for sealing water weld earthing pole, reserve suspension ring;
Step 4, inner template etc. are installed;After the completion of working above, inner side template is installed, reinforces, concealment acceptance;
Step 5, concreting, maintenance, form removal;After concealment acceptance, concreting work is carried out, in time maintenance, during maintenance Between determined according to drawing and code requirement;
Step 6, component converse transportation, upset, installation;After the component conservation phase arrives, can be transported to scene carries out installment work, typically One standard segment length is 30m, and 6 prefabricated components are needed altogether;Preceding scene is installed and answers line setting, arranged component and put sideline, Prevent from lifting off normal;
Step 7, remaining cast-in-place structural construction;After prefabricated components are put in place, the structure construction of construction joint part is carried out;Base plate Used with the reinforcing bar of top board and be welded to connect;Base plate is constructed in two times with top board, base plate of first constructing, then sets up backplanes support system, Roof plate template is installed, concrete roof of constructing.
2. a kind of fabricated construction method for pipe gallery according to claim 1, it is characterised in that the step Typified form makes framework using square steel in rapid two, and wood-plastic board makes surface layer and is made.
CN201710111147.1A 2017-02-28 2017-02-28 A kind of fabricated construction method for pipe gallery Pending CN106869166A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710111147.1A CN106869166A (en) 2017-02-28 2017-02-28 A kind of fabricated construction method for pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710111147.1A CN106869166A (en) 2017-02-28 2017-02-28 A kind of fabricated construction method for pipe gallery

Publications (1)

Publication Number Publication Date
CN106869166A true CN106869166A (en) 2017-06-20

Family

ID=59169121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710111147.1A Pending CN106869166A (en) 2017-02-28 2017-02-28 A kind of fabricated construction method for pipe gallery

Country Status (1)

Country Link
CN (1) CN106869166A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374435A (en) * 2018-05-08 2018-08-07 杭州伟业建设集团有限公司 Underground pipe gallery construction method with rainwater cabin and combustion gas cabin
CN108547317A (en) * 2018-05-08 2018-09-18 中国二十冶集团有限公司 Pipe gallery abnormal formwork construction method
CN108726348A (en) * 2018-03-31 2018-11-02 浙江交工集团股份有限公司 A kind of prefabricated overturning and hoisting method of piping lane segment prostrate
CN109457728A (en) * 2018-11-16 2019-03-12 河北工程大学 A kind of steel reinforced concrete pipe gallery quickly builds construction method
CN109469103A (en) * 2019-01-16 2019-03-15 上海中森建筑与工程设计顾问有限公司 A kind of environment-friendly type fabricated assembly overall pipe gallery and its assembly method
CN109505310A (en) * 2019-01-16 2019-03-22 上海中森建筑与工程设计顾问有限公司 A kind of environment-friendly type fabricated assembly overall pipe gallery and its assembly method
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN110924447A (en) * 2019-11-22 2020-03-27 浙江大学 Novel waterproof structure for construction joint of comprehensive pipe gallery and construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100265397B1 (en) * 1998-04-03 2000-09-15 박병무 Precasted culvert which is grouted on the spot
CN105256838A (en) * 2015-11-06 2016-01-20 深圳华瀚管廊物业服务有限公司 Pipe gallery prefabricated members and prefabricated comprehensive pipe gallery
CN105780808A (en) * 2016-03-14 2016-07-20 青岛润国生态科技发展有限公司 Assembly type precast comprehensive pipe gallery
CN205474893U (en) * 2015-12-31 2016-08-17 安徽省交通控股集团有限公司 Four component double -hinged reinforced concrete box -type passage of assembled
CN205502217U (en) * 2016-03-03 2016-08-24 中煤建筑安装工程集团有限公司 Prefabricated corridor of prefabricated corridor component and air film ball storehouse reinforced concrete
KR20160103939A (en) * 2015-02-25 2016-09-02 대한이.이엔.씨(주) Eco-friendly precast concrete box structure
CN105926942A (en) * 2016-05-13 2016-09-07 江苏中南建筑产业集团有限责任公司 Construction method of combined aluminum/steel frame wood-plastic formwork system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100265397B1 (en) * 1998-04-03 2000-09-15 박병무 Precasted culvert which is grouted on the spot
KR20160103939A (en) * 2015-02-25 2016-09-02 대한이.이엔.씨(주) Eco-friendly precast concrete box structure
CN105256838A (en) * 2015-11-06 2016-01-20 深圳华瀚管廊物业服务有限公司 Pipe gallery prefabricated members and prefabricated comprehensive pipe gallery
CN205474893U (en) * 2015-12-31 2016-08-17 安徽省交通控股集团有限公司 Four component double -hinged reinforced concrete box -type passage of assembled
CN205502217U (en) * 2016-03-03 2016-08-24 中煤建筑安装工程集团有限公司 Prefabricated corridor of prefabricated corridor component and air film ball storehouse reinforced concrete
CN105780808A (en) * 2016-03-14 2016-07-20 青岛润国生态科技发展有限公司 Assembly type precast comprehensive pipe gallery
CN105926942A (en) * 2016-05-13 2016-09-07 江苏中南建筑产业集团有限责任公司 Construction method of combined aluminum/steel frame wood-plastic formwork system

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108726348A (en) * 2018-03-31 2018-11-02 浙江交工集团股份有限公司 A kind of prefabricated overturning and hoisting method of piping lane segment prostrate
CN108374435A (en) * 2018-05-08 2018-08-07 杭州伟业建设集团有限公司 Underground pipe gallery construction method with rainwater cabin and combustion gas cabin
CN108547317A (en) * 2018-05-08 2018-09-18 中国二十冶集团有限公司 Pipe gallery abnormal formwork construction method
CN109457728A (en) * 2018-11-16 2019-03-12 河北工程大学 A kind of steel reinforced concrete pipe gallery quickly builds construction method
CN109457728B (en) * 2018-11-16 2023-04-07 河北工程大学 Rapid construction method for section steel concrete comprehensive pipe gallery
CN109469103A (en) * 2019-01-16 2019-03-15 上海中森建筑与工程设计顾问有限公司 A kind of environment-friendly type fabricated assembly overall pipe gallery and its assembly method
CN109505310A (en) * 2019-01-16 2019-03-22 上海中森建筑与工程设计顾问有限公司 A kind of environment-friendly type fabricated assembly overall pipe gallery and its assembly method
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN109706953B (en) * 2019-01-21 2023-10-13 吉林建筑大学 Die for foundation slab of assembled concrete underground building and drawing die construction method
CN110924447A (en) * 2019-11-22 2020-03-27 浙江大学 Novel waterproof structure for construction joint of comprehensive pipe gallery and construction method

Similar Documents

Publication Publication Date Title
CN106869166A (en) A kind of fabricated construction method for pipe gallery
CN106869172B (en) In-situ deposited prefabricated split-mounting type subway underground station construction method
CN101403218B (en) Processing method for basement water-proof concrete construction joint
CN103015719B (en) Preliminary work for spudding steel concrete wastewater disposal basin monobloc cast technique
CN103205979B (en) Method for constructing large raft foundation under high temperature
CN102966114B (en) Tower crane foundation structure and construction method thereof
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN103821180A (en) Double-water stop structure for concrete expansion joint and manufacturing and construction method for double-water stop structure
CN101148932A (en) Thermal insulation waterproof roof covering gas-guiding drainage system and construction method thereof
CN103615076A (en) Concrete construction method for big-gradient sloping roof
CN204662742U (en) The movable surface construction structure of a kind of pitched roof
CN107605107A (en) A kind of method for controlling pitched roof concrete construction quality
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN206859272U (en) The interim block structure of outer wall of basement pouring after settlement
CN203856099U (en) Environment-friendly energy-saving cast-in-place heat-insulating windowed composite exterior wall system
CN106638544A (en) Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN203247838U (en) Fully-buried basement side wall post-pouring belt advance water stop formwork
CN110847466A (en) Splicing and reinforcing construction method for prefabricated laminated slab
CN103334771A (en) Concrete pouring method of side wall and joint of middle plate and vault by means of underground excavation reverse construction method
CN207934054U (en) A kind of prefabricated assembled raft foundation
CN109322332A (en) It is a kind of in advance to basis and post-cast strip method for waterproofing
CN205711786U (en) Big cross section porous overlength cast-in-place box culvert formwork system
CN210216499U (en) A bottom plate and side wall handing-over department waterproof construction for piping lane
CN104405046A (en) Processing process for wall expansion joint structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170620

WD01 Invention patent application deemed withdrawn after publication