CN108560586A - Half prefabricated assembled pipe gallery and its construction method - Google Patents

Half prefabricated assembled pipe gallery and its construction method Download PDF

Info

Publication number
CN108560586A
CN108560586A CN201810551369.XA CN201810551369A CN108560586A CN 108560586 A CN108560586 A CN 108560586A CN 201810551369 A CN201810551369 A CN 201810551369A CN 108560586 A CN108560586 A CN 108560586A
Authority
CN
China
Prior art keywords
wallboard
layer
slot
waterproof
cupuliform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810551369.XA
Other languages
Chinese (zh)
Inventor
吴剑秋
王国欣
孙旻
周旻娴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201810551369.XA priority Critical patent/CN108560586A/en
Publication of CN108560586A publication Critical patent/CN108560586A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a kind of half prefabricated assembled pipe gallery and method, which includes:The bottom plate of cast-in-place formation corresponds to be provided with cupuliform slot at the position of wallboard thereon;Prefabricated piping lane segment, including integrally formed top plate and with top plate multiple wallboards connected vertically, the wallboard is inserted in corresponding cupuliform slot, is connected and fixed by cast-in-place linkage section between adjacent two piping lane segments;There is a setpoint distance in the top surface of the bitumastic layer being filled in the cupuliform slot, the bitumastic layer away from the notch of the cupuliform slot;And perfusion is formed in the waterproof concrete structure in the cupuliform slot, the waterproof concrete structure is located on the bitumastic layer, and the notch of the cupuliform slot is closed by the waterproof concrete structure.The present invention connects cast-in-place bottom plate and prefabricated wallboard using cup slot joint structure, and the bar splicing and binding avoided between prefabricated components and site concrete is constructed, and construction is simple improves construction efficiency.

Description

Half prefabricated assembled pipe gallery and its construction method
Technical field
The present invention relates to pipe gallery construction work field, a kind of half prefabricated assembled pipe gallery and its construction party are refered in particular to Method.
Background technology
With the continuous propulsion of Modernized City Construction, China's pipe gallery construction is also evolving.2015, the whole nation 69 Urban Underground pipe gallery construction scales about 1000km, 2016, the whole nation put into operation underground pipe gallery 2000km with On.Urban Underground pipe gallery construction has become one of the important content of following China's urban infrastructure construction.Traditional ground There are two types of modes for lower pipe gallery construction:One, field cast-in-place, two, prefabrication.
Cast-in-place pipe gallery easy construction, technology maturation, but since all operations are completed at the scene, side wall and top plate are equal Configuration template is wanted, and template has to remove after intensity is fully achieved in coagulation, long construction period, artificial demand is big, Situ wet operation heavy workload.Concrete cast in situs pollutes environment, is affected to surrounding enviroment.And on-site concrete is supported Guard strip part is poor, and the possibility that micro-crack occurs in concrete is big, is easy locally to leak, construction crack, side wall easily occurs in piping lane The problems such as entire crack.
Traditional complete prefabricated pipe gallery is spliced at the scene by the piping lane of precast segment, and splicing seams are more, edge joint position Waterproof requirement it is high, difficulty is big.Since prefabricated subsection weight is big, whole Transporting lifting is difficult, needs mass transit vehicle and big Type hanging device, construction cost are high.And precast segment piping lane is integral prefabricated in factory, mold is complicated, and low production efficiency is prefabricated It is of high cost.
Therefore how by cast-in-place construction and it is prefabricated be reasonably connected in construction technology, which kind of prefabricated wall beam taken The collocation form of column plate and cast-in-place part, and it is assembled to ensure that underground structure has good structural stability and water resistance Pipe gallery urgent problem to be solved.
Invention content
It is an object of the invention to overcome the deficiencies of existing technologies, a kind of half prefabricated assembled pipe gallery is provided and its is applied Work method, solves long construction period, situ wet operation heavy workload existing for cast-in-place pipe gallery and complete prefabricated pipe gallery is deposited Piece it is more, waterproof difficulty is big, construction cost is high etc. the problem of.
Realizing the technical solution of above-mentioned purpose is:
The present invention provides a kind of half prefabricated assembled pipe galleries, including:
The bottom plate of cast-in-place formation corresponds on the bottom plate and is provided with cupuliform slot, the slot of the cupuliform slot at the position of wallboard Mouth is arranged upward;
Prefabricated piping lane segment, including integrally formed top plate and with top plate multiple wallboards connected vertically, the piping lane Segment is inserted in corresponding cupuliform slot by the wallboard and is erected on the bottom plate, and the surface of the wallboard with it is corresponding Cupuliform slot internal face between be formed with gap, be connected and fixed by cast-in-place linkage section between adjacent two piping lane segments;
The bitumastic layer being filled in the gap, the top surface of the bitumastic layer is away from the slot of the cupuliform slot Mouth has a setpoint distance;And
Perfusion is formed in the waterproof concrete structure in the gap, and the waterproof concrete structure is located at the pitch agate On hoof lipid layer, and close by the waterproof concrete structure notch of the cupuliform slot.
The pipe gallery of the present invention is given full play to cast-in-place and pre- by pouring a part, a prefabrication part at the scene The advantage of system overcomes cast-in-place piping lane long construction period, high labor cost and complete prefabricated piping lane transport difficult, component seam waterproof poor The shortcomings that.The present invention connects cast-in-place bottom plate and prefabricated wallboard using cup slot joint structure, avoids prefabricated components and shows The bar splicing and binding poured between component are constructed, and prefabricated wallboard and bottom plate are linked to be entirety, cup by cup slot joint structure The cementation of fissures is carried out using bitumastic and water-proof concrete in shape slot, meets the waterproof requirement of Pipe rack, ensures structure safety. Bitumastic therein has preferable waterproof effect, which is filled in the bottom in gap, can be to wallboard Preferable package effect is played, the water on the outside of the wallboard of side is prevented to be entered in pipe gallery from the bottom of wallboard.Its In water-proof concrete play the role of reinforcement by connection to wallboard and bottom plate, it can be ensured that between wallboard and bottom plate it is effective securely Connection.
Half prefabricated assembled pipe gallery of the present invention further improvement lies in that, be also filled in the gap positioned at described Bituminous hemp fiber layer between waterproof concrete structure and the bitumastic layer or pitch spunyarn layer.
Half prefabricated assembled pipe gallery of the present invention further improvement lies in that, the bottom plate is arranged with base pad Layer, and base plate waterproofing is equipped between the bottom cushion and the bottom plate, the end of the base plate waterproofing flips up Be attached at the end side of the bottom plate and bending be attached at cupuliform slot positioned at end side cell wall top end face, and then stretch to described It fits in cupuliform slot and with the internal face of the cupuliform slot.
Half prefabricated assembled pipe gallery of the present invention further improvement lies in that, the wallboard includes the side wall positioned at side The outer surface of plate, the framed side wallboard is equipped with wallboard waterproof layer, and the bottom part of the wallboard waterproof layer is in corresponding cupuliform In slot.
Half prefabricated assembled pipe gallery of the present invention further improvement lies in that, the top plate and the cast-in-place linkage section it On be equipped with waterproof roofing layer, and the end pressing corresponding on the wallboard waterproof layer of the end of the waterproof roofing layer connects It connects.
The present invention also provides the construction methods of a kind of half prefabricated assembled pipe gallery, include the following steps:
The foundation pit of construction pipe gallery;
In the bottom of foundation ditch cast-in-place construction bottom plate, and in setting at the corresponding position for waiting for safe wallboard on the bottom plate Cupuliform slot, and the notch of the cupuliform slot is arranged upward;
Prefabricated piping lane segment is provided, the piping lane segment include integrally formed top plate and with the top plate vertical connection Multiple wallboards, the piping lane segment is inserted in by the wallboard in corresponding cupuliform slot by is erected on the bottom plate, And it is formed with gap between the surface of the wallboard and the internal face of corresponding cupuliform slot;
It will be connected and fixed by cast-in-place linkage section between two adjacent piping lane segments;
In in the gap filled bitumen matizhi formed bitumastic layer, and the top surface of the bitumastic layer away from The notch of the cupuliform slot has a setpoint distance;And
Waterproof concrete structure is formed in water-proof concrete is perfused in the gap, is sealed by the waterproof concrete structure Close the notch of the cupuliform slot.
The construction method of half prefabricated assembled pipe gallery of the present invention further improvement lies in that, perfusion water-proof concrete Further include before:
Pitch spunyarn layer is formed in the gap filling pitch spunyarn or filled bitumen flax silk forms Bituminous hemp fiber layer, and will Pitch spunyarn or the Bituminous hemp fiber compacting filled.
The construction method of half prefabricated assembled pipe gallery of the present invention further improvement lies in that, construct bottom plate before, also Including:
In the bottom of foundation pit construction bottom cushion;
It is laid with base plate waterproofing on the bottom cushion, the base plate waterproofing is coated to the end of the bottom plate upwards Side and be attached at the corresponding cupuliform slot positioned at end side cell wall top end face, and then the end of the base plate waterproofing is stretched into It fits in the cupuliform slot and with the internal face of the cupuliform slot.
The construction method of half prefabricated assembled pipe gallery of the present invention further improvement lies in that, the wallboard include be located at The framed side wallboard of side;
After the framed side wallboard is erected in corresponding cupuliform slot, it is anti-to be laid with wallboard in the outer surface of the framed side wallboard Water layer, and the bottom end of the wallboard waterproof layer is placed in corresponding cupuliform slot.
The construction method of half prefabricated assembled pipe gallery of the present invention further improvement lies in that, further include:
Waterproof roofing layer is laid on the top plate and the cast-in-place linkage section, and by the end of the waterproof roofing layer End pressing connection corresponding on the wallboard waterproof layer.
Description of the drawings
Fig. 1 is that piping lane segment is lifted in half prefabricated assembled pipe gallery of the invention to the structural schematic diagram of cast-in-place bottom plate.
Fig. 2 is that the piping lane segment in half prefabricated assembled pipe gallery of the invention is placed in the knot in the cupuliform slot of cast-in-place bottom plate Structure schematic diagram.
Fig. 3 is the side view of half prefabricated assembled pipe gallery of the invention.
Fig. 4 is the structural schematic diagram of the cup slot joint structure at the framed side wallboard of half prefabricated assembled pipe gallery of the invention.
Fig. 5 is the structural schematic diagram of the cup slot joint structure at the deadlight of half prefabricated assembled pipe gallery of the invention.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments.
Refering to fig. 1, the present invention provides a kind of half prefabricated assembled pipe gallery and its construction methods, using cup slot node The bar splicing between prefabricated components and site concrete and binding construction are avoided, cast-in-place piping lane and complete prefabricated piping lane are given full play to The advantage of the two overcomes long cast-in-place piping lane construction time, wet construction heavy workload and complete prefabricated piping lane low production efficiency, transport Small disadvantage is measured, environmental protection and energy saving, construction efficiency are high, and have excellent water resistance.The wallboard and top plate of the present invention is using whole The prefabricated form of body can be saved the time that integral cast-in-situ piping lane performs mould bases and support, and duration and cost are saved;Due to pre- Component bottom end processed is connect with cast-in-place bottom plate by cup slot, avoids bar splicing overlap joint and binding, site operation is simple, improves Construction efficiency.And the pipe gallery of the present invention uses the form of full packet waterproof, and it is anti-that closed annular is formed on the outside of Pipe rack Water-bound system, it is ensured that Pipe rack does not occur seeping water and drainage, ensure that Pipe rack water resistance.With reference to attached Figure illustrates half prefabricated assembled pipe gallery of the invention and its construction method.
Refering to fig. 1, it is shown that structural representation of the piping lane segment to cast-in-place bottom plate is lifted in half prefabricated assembled pipe gallery Figure.Refering to Fig. 3, it is shown that the side view of half prefabricated assembled pipe gallery of the present invention.Refering to Fig. 4, it is shown that the present invention half is pre- The structural schematic diagram of cup slot joint structure at the framed side wallboard of assembled pipe gallery processed.It is right with reference to Fig. 1, Fig. 3 and Fig. 4 Half prefabricated assembled pipe gallery of the present invention illustrates.
Shown in as shown in Figure 1, Figure 3 and Figure 4, half prefabricated assembled pipe gallery 20 of the invention includes bottom plate 21, piping lane segment 20a, cast-in-place linkage section 20b and cup slot joint structure 30, bottom plate 21 is cast-in-place bottom plate, and the position of wallboard 22 is corresponded on bottom plate 21 The place of setting is provided with cupuliform slot 31, and the notch of the cupuliform slot 31 is arranged upward.When pouring bottom plate 21, cup is integrally formed on bottom plate 21 Shape slot 31, the space of the cup type of the inside formation of cupuliform slot 31.Piping lane segment 20a is prefabricated components, by prefabricated enough multiple Piping lane segment 20a is spliced to form pipe gallery 20, and piping lane node 20a includes integrally formed top plate 23 and vertical with top plate 23 Multiple wallboards 22 of connection, piping lane segment 20a are inserted in corresponding cupuliform slot 31 by wallboard 22 and are erected on bottom plate 21, Coordinate shown in Fig. 2, when lifting piping lane segment 20a, the bottom of the wallboard 22 on the 20a of piping lane segment is inserted in corresponding cupuliform slot In 31.There are certain spacing between two adjacent piping lane segment 20a, and the cast-in-place linkage section 20b that constructs at the spacing, lead to Cast-in-place linkage section 20b is crossed to be connected and fixed two adjacent piping lane segment 20a.Cup slot joint structure 30 is used for 21 He of connecting bottom board Wallboard 22, this glass of slot joint structure 30 include cupuliform slot 31 on bottom plate 21, the bitumastic layer being filled in cupuliform slot 31 34 and waterproof concrete structure 35, wallboard 22 be inserted into cupuliform slot 31, and the internal face on the surface of wallboard 22 and cupuliform slot 31 Between be formed with gap 33, the surfaces externally and internally of the wallboard 22 is formed with gap between the internal face of corresponding cupuliform slot 31 33;Bitumastic layer 34 is filled in gap 33, and the top surface of the bitumastic layer 34 has one to set away from the notch of cupuliform slot 31 Set a distance;It is filled between the surface of the bitumastic layer 34 in gap 33 and framed side wallboard 221 and the internal face of cupuliform slot 31 It combines closely, since there is bitumastic higher cohesive strength, bitumastic layer 34 can also play connection wallboard 22 and bottom The effect of plate 21;The perfusion of waterproof concrete structure 35 is formed in gap 33, which is located at pitch agate hoof On lipid layer 34, and pass through the notch of the waterproof concrete structure 35 closing cupuliform slot 31.Waterproof concrete structure 35 is for adding Gu wallboard 22 and bottom plate 21, can ensure the safety of structure.
As the better embodiment of the present invention, as shown in figure 4, being also filled with positioned at water-proof concrete in gap 33 Bituminous hemp fiber layer 36 between structure 35 and bitumastic layer 34 or pitch spunyarn layer.Preferably, by bitumastic layer 34 Top surface be set to close to cupuliform slot 31 cell wall 311 center, the top surface of Bituminous hemp fiber layer 36 or pitch spunyarn layer is set to Close at the notch of cupuliform slot 31 so that have between the top surface and notch of the Bituminous hemp fiber layer 36 or pitch spunyarn layer it is certain between Away from the perfusion for waterproof concrete structure 35.Utilize bitumastic layer 34 and Bituminous hemp fiber layer 36 or pitch spunyarn layer Gap 33 in stuffing cup-shaped slot 31 can have higher waterproof effect, meet waterproof requirement.Bituminous hemp fiber layer 36 therein It is mixed to form, can be compacted flax silk in filling flax silk in gap, then the asphalt reperfusion into the flax silk by pitch and flax silk so that Bituminous hemp fiber is mixed to form Bituminous hemp fiber layer 36;Pitch spunyarn layer is mixed to form by pitch and spunyarn, in filling spunyarn in gap, Spunyarn is compacted, then the asphalt reperfusion into the spunyarn so that pitch spunyarn is mixed to form pitch spunyarn layer.
As another better embodiment of the present invention, as depicted in figs. 1 and 2, bottom plate 21 is arranged with bottom cushion 24, and be equipped with base plate waterproofing 251 between the bottom cushion 24 and bottom plate 21, the end of the base plate waterproofing 251 is to turning over Folding and sticking be set to bottom plate 21 end side and bending be attached at the cupuliform slot 31 positioned at end side cell wall 311 top end face 3111, in turn It extend into cupuliform slot 31 and fits with the internal face of cupuliform slot 31.Bottom plate 21 uses cast-in-place formation, when construction, first digs synthesis After foundation pit construction is good, in the bottom of foundation pit construction bottom cushion 24, it is anti-to be laid with bottom plate on bottom cushion 24 for the foundation pit of piping lane 20 Water layer 251, and the end of base plate waterproofing 251 is reserved into surplus to coat the part for the bottom plate constructed, then in bottom plate Cast-in-place bottom plate 21 is poured on waterproof layer 251, and in forming cupuliform slot 31 on bottom plate 21, it is strong to wait for that the concrete of bottom plate 21 reaches maintenance After degree, by the end side of the end bending cladding bottom plate 21 of base plate waterproofing 251, and cup is stretched into the end of base plate waterproofing 251 In shape slot 31, the bitumastic layer 34, Bituminous hemp fiber layer 36 or the pitch spunyarn layer that are subsequently perfused using cupuliform slot 31 and anti- Water coagulation soil 35 buries the end of the base plate waterproofing 251.
Further, as shown in Fig. 2, after bottom plate 21 reaches curing strength, piping lane segment 20a is lifted into bottom plate 21 On, wallboard 22 plugs in corresponding cupuliform slot 31, and wallboard 22 includes the middle wall positioned at the framed side wallboard 221 of side and positioned at middle part The outer surface of plate 222, framed side wallboard 221 is equipped with wallboard waterproof layer 252, and the bottom end of the wallboard waterproof layer 252 is located at corresponding cup In shape slot 31.The end of the wallboard waterproof layer 252 is enable to pass through the bitumastic layer 34 in cupuliform slot 31, Bituminous hemp fiber Layer 36 or pitch spunyarn layer and water-proof concrete 35 bury solid.Preferably, the end of base plate waterproofing 251 can be layed in The end of wallboard waterproof layer 252 is also bent and is layed in the bottom of cupuliform slot 31, and then wallboard is prevented by the bottom of cupuliform slot 31 The end of water layer 252 is a part of with the pressing of the end of base plate waterproofing 251 and is fixedly connected, thus by 252 He of wallboard waterproof layer Base plate waterproofing 251 connects integral waterproof construction, can improve waterproof effect.
By cast-in-place linkage section 20b connections between two adjacent framed side wallboards 221, so being laid with wallboard waterproof layer 252 When, wallboard waterproof layer 252 is covered on the cast-in-place linkage section 20b as wall, is covered in synthesis by wallboard waterproof layer 252 The side face of wall of piping lane 20, to playing good waterproof action at side wall.
Further, waterproof roofing layer 253, and waterproof roofing are equipped on top plate 23 and cast-in-place linkage section 20b The end end pressing connection corresponding on wallboard waterproof layer 252 of layer 253.To which the present invention passes through base plate waterproofing 251, wall Plate waterproof layer 252 and waterproof roofing layer 253 form the waterproof form wrapped entirely, and closing is formd in the outside of pipe gallery 20 Annular waterproof construction system, it can be ensured that there is not infiltration and the phenomenon that leak in pipe gallery, ensures the waterproof of pipe gallery Performance.
As the another better embodiment of the present invention, as shown in figure 3, waterproof concrete structure 35 includes being located at cupuliform slot Part in 31 and the part outside cupuliform slot 31, and the two parts are structure as a whole, when water-proof concrete is perfused, to cup Superfilled water-proof concrete in shape slot 31 so that waterproof concrete structure has part to protrude out the notch of annular groove 31 and form reinforcing Portion 351, reinforcing portion 351 are set between the top end face 3111 of the cell wall 311 of framed side wallboard 221 and annular groove 31, pass through reinforcing portion 351 Connect the top end face 3111 and framed side wallboard 221 of the cell wall 311.Preferably, the section of reinforcing portion 351 is triangular in shape, the reinforcing portion 351 a side is fitted and connected with framed side wallboard 221, and side rim portion is located on top end face 3111, partly with positioned at cupuliform slot 31 Interior waterproof concrete structure connects, and another side is obliquely arranged.Reinforcing portion 351 positioned at 221 both sides of framed side wallboard is in eight Font is arranged, and reinforcement effect is played to framed side wallboard 221.
As another better embodiment of the present invention, cup slot joint structure 30 further includes the bottom that pad is located at cupuliform slot 31 Modified asphalt felt 37 between wallboard 22 spreads modified asphalt felt 37 before wallboard 22 is inserted into cupuliform slot 31 Set on the bottom of cupuliform slot 31, to improve the effect of waterproof.
Preferably, when being laid with modified asphalt felt 37, the both ends of modified asphalt felt 37 are attached at cupuliform slot 31 On internal face.
Setting modified asphalt felt 37 can improve 21 junction of framed side wallboard 221 and bottom plate in asphalt reperfusion matizhi Waterproof effect, modified asphalt felt 37 itself have water-proof function, and its can be good at bitumastic layer 34 it is be bonded Together, closely knit waterproof construction is formed.
As the better embodiment another again of the present invention, the slot bottom width of cupuliform slot 31 is less than width of rebate.The cupuliform It is in inverted trapezoidal shape that space is formed by inside slot 31, and the width of notch is more than the width of slot bottom.When constructing cupuliform slot 31, the bottom of in Template is set up on plate bed course 24, baffle accordingly is set in the both sides of the two side walls 311 of cupuliform slot 31, so that side wall 311 It can pour to be formed together with bottom plate 21.The slot bottom of cupuliform slot 31 and the surface of bottom plate 21 are flush, and cupuliform slot 31 is located at bottom Two end sides of plate 21.
As the better embodiment another again of the present invention, as shown in Fig. 2, passing through cup between framed side wallboard 221 and bottom plate 21 Slot joint structure 30 connects, and constituting 30a by another glass of slot node in conjunction with shown in Fig. 5, between deadlight 222 and bottom plate 21 connects It connects, which includes the waterproof concrete structure 35 that cupuliform slot 31 is formed in perfusion in cupuliform slot 31, Because the waterproof requirement at deadlight 222 is not high, so after the deadlight 222 is inserted into cupuliform slot 31, it can be to the cupuliform slot 31 Interior perfusion water-proof concrete carries out the cementation of fissures to form waterproof concrete structure 35, and the top surface of the waterproof concrete structure 35 with The top surface of the cell wall 311 of cupuliform slot 31 flushes.In an installation before wallboard 222, modified drip is laid with prior to the bottom of cupuliform slot 31 Green malthoid 37, the modified asphalt felt 37 is between deadlight 222 and the slot bottom of cupuliform slot 31.
Half prefabricated assembled pipe gallery of the present invention has the beneficial effect that:
Using cupuliform slot connecting bottom board and wallboard, no-reinforcing-bar connection, site operation is simple and convenient, can improve construction effect Rate;
Bottom plate is cast-in-place, wallboard and top plate using integral prefabricated, eliminate integral cast-in-situ piping lane perform mould bases and support when Between, save duration and cost;
Base plate waterproofing, wallboard waterproof layer and waterproof roofing layer are set, forms the waterproof wrapped entirely and is formed, in integrated pipe The outside of corridor forms closed annular waterproof construction system, it is ensured that Pipe rack does not occur seeping water and drainage, guarantee integrate The water resistance of piping lane;
Gap between cupuliform slot and framed side wallboard is mixed using bitumastic, Bituminous hemp fiber or pitch spunyarn and waterproof The solidifying soil cementation of fissures, disclosure satisfy that the waterproof requirement of structure, ensure that the safety of structure.Framed side wallboard is located at the outermost of pipe gallery Side, with higher waterproof requirement, and framed side wallboard uses precast construction, when bottom plate uses cast-in-place structural, the two junction at For the important node of waterproof, the present invention is laid with modified asphalt felt prior to the bottom of cupuliform slot, as waterproof layer, is then inciting somebody to action Framed side wallboard is inserted into cupuliform slot, and the bottom of framed side wallboard erects on the modified asphalt felt as waterproof layer;In cupuliform slot For asphalt reperfusion matizhi to form bitumastic layer in the both sides of framed side wallboard, which is located at modified asphalt felt On, the two can good combination, improve waterproof effect, bitumastic layer closely be set to framed side wallboard surface, can Meet waterproof requirement;Still further, the present invention is provided with pitch spunyarn layer or Bituminous hemp fiber on bitumastic layer Layer, can further increase the waterproof effect at node;And the present invention use modified asphalt felt, bitumastic layer and The cost of pitch spunyarn layer or Bituminous hemp fiber layer is relatively low, can reduce construction cost, and also reduce difficulty of construction.Anti- water coagulation Soil structure not only has waterproof effect, additionally it is possible to play the role of reinforcing connection, can ensure between framed side wallboard and bottom plate Effectively firm connection.
The comprehensive pipe gallery structure of the present invention is conducive to popularization and application of the half prefabrication and assembly construction technology in underground engineering, is underground work Facilitation is played in the industrialization and industrialization of journey.
The present invention also provides the construction methods of a kind of half prefabricated assembled pipe gallery, are carried out below to the construction method Explanation.
The construction method of the half prefabricated assembled pipe gallery of the present invention, includes the following steps:
As depicted in figs. 1 and 2, the foundation pit of construction pipe gallery 20;Foundation pit slope is excavated, and dewatering construction base in hole can be coordinated Building enclosure in hole after excavation of foundation pit to designed elevation, then executes next step;
In bottom of foundation ditch cast-in-place construction bottom plate 21, and in being corresponded on bottom plate 21, cup is set at the position for waiting for safe wallboard 22 Shape slot 31, and the notch of cupuliform slot 31 is arranged upward;The cupuliform slot 31 include be erected on bottom plate 21 and with 21 1 bodily form of bottom plate At side wall 311, the cup type being enclosed between the bottom plate 21 between two side 311 and two side 311 inside cupuliform slot 31 is empty Between;
There is provided prefabricated piping lane segment 20a, piping lane segment 20a includes integrally formed top plate 23 and vertical with top plate 23 connects Piping lane segment 20a is inserted in by wallboard 22 in corresponding cupuliform slot 31 and is erected on bottom plate 21 by the multiple wallboards 22 connect, And it is formed with gap 33 between the surface of wallboard 22 and the internal face of corresponding cupuliform slot 31;Row can be used to hang piping lane segment 20a is lifted on bottom plate 21, then sets up skewed horizontal load, corrects prefabricated components installation site, the skewed horizontal load is as interim branch Support structure can remove the skewed horizontal load after wallboard 22 and cupuliform slot 31 fix.
In conjunction with shown in Fig. 3, it will be connected and fixed by cast-in-place linkage section 20b between two adjacent piping lane segment 20a;
In conjunction with shown in Fig. 4, bitumastic layer 34, and bitumastic layer are formed in filled bitumen matizhi in gap 33 Notch of 34 top surface away from cupuliform slot 31 has a setpoint distance;Bitumastic layer 34 and the framed side wallboard being filled in gap 33 It combines closely between 221 surface and the internal face of cupuliform slot 31, since bitumastic has higher cohesive strength, pitch agate Hoof lipid layer 34 can also play the role of connecting framed side wallboard 221 and bottom plate 21;
Waterproof concrete structure 35 is formed in perfusion water-proof concrete in gap 33, is closed by waterproof concrete structure 35 The notch of cupuliform slot 31.Waterproof concrete structure 35 can ensure the safety of structure for reinforcing framed side wallboard 221 and bottom plate 21 Property.
As the better embodiment of the present invention, further include before water-proof concrete is perfused:
Pitch spunyarn layer is formed in filled bitumen spunyarn in gap 33 or filled bitumen flax silk forms Bituminous hemp fiber layer 36, and The pitch spunyarn or Bituminous hemp fiber filled are compacted.
Preferably, the top surface of bitumastic layer 34 is set to the center close to the cell wall 311 of cupuliform slot 31, by pitch The top surface of flax silk layer 36 or pitch spunyarn layer is set to close at the notch of cupuliform slot 31 so that the Bituminous hemp fiber layer 36 or coal tar There is perfusion of certain spacing for waterproof concrete structure 35 between the top surface and notch of numb layer.Utilize bitumastic Gap 33 in layer 34 and Bituminous hemp fiber layer 36 or the stuffing cup-shaped slot of pitch spunyarn layer 31 can have higher waterproof effect, Meet waterproof requirement.Bituminous hemp fiber layer 36 therein is mixed to form by pitch and flax silk, can be in filling flax silk in gap, by flax silk Compacting, then the asphalt reperfusion into the flax silk so that Bituminous hemp fiber is mixed to form Bituminous hemp fiber layer 36;Pitch spunyarn layer by pitch and Spunyarn is mixed to form, and in filling spunyarn in gap, spunyarn is compacted, then the asphalt reperfusion into the spunyarn so that pitch spunyarn is mixed Conjunction forms pitch spunyarn layer.
As another better embodiment of the present invention, constructs before bottom plate 21, further include:
In the bottom of foundation pit construction bottom cushion 24;
It is laid with base plate waterproofing 251 on bottom cushion 24, base plate waterproofing 251 is coated to the end side of bottom plate 21 upwards And it is attached at the top end face 3111 of the cell wall 311 of the corresponding cupuliform slot 31 positioned at end side, and then by the end of base plate waterproofing 251 Portion stretches into cupuliform slot 31 and fits with the internal face of cupuliform slot 31.
When construction, after the foundation pit construction of pipe gallery 20 is good, in the bottom of foundation pit construction bottom cushion 24, in base pad It is laid with base plate waterproofing 251 on layer 24, and the end of base plate waterproofing 251 is reserved into surplus to coat the bottom plate constructed Part then pours cast-in-place bottom plate 21 on base plate waterproofing 251, and in forming cupuliform slot 31 on bottom plate 21, waits for bottom plate 21 After concrete reaches curing strength, by the end side of the end of base plate waterproofing 251 bending cladding bottom plate 21, and by base plate waterproofing 251 end is stretched into cupuliform slot 31, bitumastic layer 34, Bituminous hemp fiber layer 36 or the drip being subsequently perfused using cupuliform slot 31 Green spunyarn layer and water-proof concrete 35 bury the end of the base plate waterproofing 251.
Further, wallboard 22 includes the framed side wallboard 221 positioned at side;
After being erected on framed side wallboard 221 in corresponding cupuliform slot 31, it is anti-to be laid with wallboard in the outer surface of framed side wallboard 221 Water layer 252, and the bottom end of wallboard waterproof layer 252 is placed in corresponding cupuliform slot 31.So that the end of the wallboard waterproof layer 252 Portion can pass through bitumastic layer 34, Bituminous hemp fiber layer 36 or the pitch spunyarn layer and water-proof concrete 35 in cupuliform slot 31 Bury solid.Preferably, the end of base plate waterproofing 251 can be layed in the bottom of cupuliform slot 31, by wallboard waterproof layer 252 End also bends and is layed in the bottom of cupuliform slot 31, and then by the end of the end of wallboard waterproof layer 252 and base plate waterproofing 251 Pressing part in portion's is simultaneously fixedly connected, to which wallboard waterproof layer 252 and base plate waterproofing 251 to be connected to integral waterproof knot Structure can improve waterproof effect.
By cast-in-place linkage section 20b connections between two adjacent framed side wallboards 221, so being laid with wallboard waterproof layer 252 When, wallboard waterproof layer 252 is covered on the cast-in-place linkage section 20b as wall, is covered in synthesis by wallboard waterproof layer 252 The side face of wall of piping lane 20, to playing good waterproof action at side wall.
Further, further include:
It is laid with waterproof roofing layer 253 on top plate 23 and cast-in-place linkage section 20b, and by the end of waterproof roofing layer 253 End pressing connection corresponding on wallboard waterproof layer 252.
To which the present invention forms full packet by base plate waterproofing 251, wallboard waterproof layer 252 and waterproof roofing layer 253 Waterproof form, form closed annular waterproof construction system in the outside of pipe gallery 20, it can be ensured that pipe gallery is not There is the phenomenon that infiltration and leak, ensures the water resistance of pipe gallery.
After outside waterproofing layer is constructed, earthing is backfilled into foundation pit, that is, completes the construction of pipe gallery.
As the another better embodiment of the present invention, as shown in figure 4, when perfusion water-proof concrete, in cupuliform slot 31 Perfusion forms reinforcing portion 351 between the top end face 3111 and framed side wallboard 221 of cell wall 311, and framed side wallboard is connected by the reinforcing portion 351 221 and cell wall 311 top end face 3111.
Preferably, the top surface of bitumastic layer 34 is set to the center close to the cell wall 311 of cupuliform slot 31, by pitch The top surface of flax silk layer 36 or pitch spunyarn layer is set to close at the notch of cupuliform slot 31 so that the Bituminous hemp fiber layer 36 or coal tar There is perfusion of certain spacing for waterproof concrete structure 35 between the top surface and notch of numb layer.Utilize bitumastic Gap 33 in layer 34 and Bituminous hemp fiber layer 36 or the stuffing cup-shaped slot of pitch spunyarn layer 31 can have higher waterproof effect, Meet waterproof requirement.Bituminous hemp fiber layer 36 therein is mixed to form by pitch and flax silk, can be in filling flax silk in gap, by flax silk Compacting, then the asphalt reperfusion into the flax silk so that Bituminous hemp fiber is mixed to form Bituminous hemp fiber layer 36;Pitch spunyarn layer by pitch and Spunyarn is mixed to form, and in filling spunyarn in gap, spunyarn is compacted, then the asphalt reperfusion into the spunyarn so that pitch spunyarn is mixed Conjunction forms pitch spunyarn layer.
It is also wrapped before being erected on framed side wallboard 221 in cupuliform slot 31 as another better embodiment of the present invention It includes:
In being laid with modified asphalt felt 37 on the slot bottom of cupuliform slot 221, to improve the effect of waterproof.
Preferably, when being laid with modified asphalt felt 37, the both ends of modified asphalt felt 37 are attached at cupuliform slot 31 On internal face.
Setting modified asphalt felt 37 can improve 21 junction of framed side wallboard 221 and bottom plate in asphalt reperfusion matizhi Waterproof effect, modified asphalt felt 37 itself have water-proof function, and its can be good at bitumastic layer 34 it is be bonded Together, closely knit waterproof construction is formed.
As the better embodiment another again of the present invention, the slot bottom width of cupuliform slot 31 is less than the width of notch.It is applying When work cupuliform slot 31, in setting up template on bottom cushion 24, accordingly it is arranged in the both sides of the two side walls 311 of cupuliform slot 31 and keeps off Plate, so that side wall 311 can pour to be formed with bottom plate 21 together.The slot bottom of cupuliform slot 31 and the surface of bottom plate 21 are flush, And cupuliform slot 31 is located at two end sides of bottom plate 21.
As the better embodiment another again of the present invention, as shown in Fig. 2, passing through cup between framed side wallboard 221 and bottom plate 21 Slot joint structure 30 connects, and constituting 30a by another glass of slot node in conjunction with shown in Fig. 5, between deadlight 222 and bottom plate 21 connects It connects, which includes the waterproof concrete structure 35 that cupuliform slot 31 is formed in perfusion in cupuliform slot 31, Because the waterproof requirement at deadlight 222 is not high, so after the deadlight 222 is inserted into cupuliform slot 31, it can be to the cupuliform slot 31 Interior perfusion water-proof concrete carries out the cementation of fissures to form waterproof concrete structure 35, and the top surface of the waterproof concrete structure 35 with The top surface of the cell wall 311 of cupuliform slot 31 flushes.In an installation before wallboard 222, modified drip is laid with prior to the bottom of cupuliform slot 31 Green malthoid 37, the modified asphalt felt 37 is between deadlight 222 and the slot bottom of cupuliform slot 31.
The construction method of half prefabricated assembled pipe gallery of the present invention has the beneficial effect that:
Using cupuliform slot connecting bottom board and wallboard, no-reinforcing-bar connection, site operation is simple and convenient, can improve construction effect Rate;
Bottom plate is cast-in-place, wallboard and top plate using integral prefabricated, eliminate integral cast-in-situ piping lane perform mould bases and support when Between, save duration and cost;
Base plate waterproofing, wallboard waterproof layer and waterproof roofing layer are set, forms the waterproof wrapped entirely and is formed, in integrated pipe The outside of corridor forms closed annular waterproof construction system, it is ensured that Pipe rack does not occur seeping water and drainage, guarantee integrate The water resistance of piping lane;
Gap between cupuliform slot and framed side wallboard is mixed using bitumastic, Bituminous hemp fiber or pitch spunyarn and waterproof The solidifying soil cementation of fissures, disclosure satisfy that the waterproof requirement of structure, ensure that the safety of structure.Framed side wallboard is located at the outermost of pipe gallery Side, with higher waterproof requirement, and framed side wallboard uses precast construction, when bottom plate uses cast-in-place structural, the two junction at For the important node of waterproof, the present invention is laid with modified asphalt felt prior to the bottom of cupuliform slot, as waterproof layer, is then inciting somebody to action Framed side wallboard is inserted into cupuliform slot, and the bottom of framed side wallboard erects on the modified asphalt felt as waterproof layer;In cupuliform slot For asphalt reperfusion matizhi to form bitumastic layer in the both sides of framed side wallboard, which is located at modified asphalt felt On, the two can good combination, improve waterproof effect, bitumastic layer closely be set to framed side wallboard surface, can Meet waterproof requirement;Still further, the present invention is provided with pitch spunyarn layer or Bituminous hemp fiber on bitumastic layer Layer, can further increase the waterproof effect at node;And the present invention use modified asphalt felt, bitumastic layer and The cost of pitch spunyarn layer or Bituminous hemp fiber layer is relatively low, can reduce construction cost, and also reduce difficulty of construction.Anti- water coagulation Soil structure not only has waterproof effect, additionally it is possible to play the role of reinforcing connection, can ensure between framed side wallboard and bottom plate Effectively firm connection.
The construction method of the present invention is conducive to popularization and application of the half prefabrication and assembly construction technology in underground engineering, is underground engineering Facilitation is played in industrialization and industrialization.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this Invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (10)

1. a kind of half prefabricated assembled pipe gallery, which is characterized in that including:
The bottom plate of cast-in-place formation corresponds on the bottom plate and is provided with cupuliform slot, the notch court of the cupuliform slot at the position of wallboard Upper setting;
Prefabricated piping lane segment, including integrally formed top plate and with top plate multiple wallboards connected vertically, the piping lane segment It is inserted in corresponding cupuliform slot and is erected on the bottom plate by the wallboard, and the surface of the wallboard and corresponding cup It is formed with gap between the internal face of shape slot, is connected and fixed by cast-in-place linkage section between adjacent two piping lane segments;
The top surface of the bitumastic layer being filled in the gap, the bitumastic layer has away from the notch of the cupuliform slot One setpoint distance;And
Perfusion is formed in the waterproof concrete structure in the gap, and the waterproof concrete structure is located at the bitumastic On layer, and close by the waterproof concrete structure notch of the cupuliform slot.
2. half prefabricated assembled pipe gallery as described in claim 1, which is characterized in that be also filled with and be located in the gap Bituminous hemp fiber layer between the waterproof concrete structure and the bitumastic layer or pitch spunyarn layer.
3. half prefabricated assembled pipe gallery as described in claim 1, which is characterized in that the bottom plate is arranged with bottom plate Bed course, and base plate waterproofing is equipped between the bottom cushion and the bottom plate, the end of the base plate waterproofing is to turning over Folding and sticking is set to the end side of the bottom plate and bending be attached at the cupuliform slot positioned at end side cell wall top end face, and then stretch to institute It states in cupuliform slot and fits with the internal face of the cupuliform slot.
4. half prefabricated assembled pipe gallery as claimed in claim 3, which is characterized in that the wallboard includes being located at side The outer surface of framed side wallboard, the framed side wallboard is equipped with wallboard waterproof layer, and the bottom part of the wallboard waterproof layer is in corresponding In cupuliform slot.
5. half prefabricated assembled pipe gallery as claimed in claim 4, which is characterized in that the top plate and the cast-in-place connection Waterproof roofing layer, and the end pressing corresponding on the wallboard waterproof layer of the end of the waterproof roofing layer are equipped on section Connection.
6. a kind of construction method of half prefabricated assembled pipe gallery, which is characterized in that include the following steps:
The foundation pit of construction pipe gallery;
In the bottom of foundation ditch cast-in-place construction bottom plate, and in being corresponded on the bottom plate, cupuliform is set at the position for waiting for safe wallboard Slot, and the notch of the cupuliform slot is arranged upward;
There is provided prefabricated piping lane segment, the piping lane segment includes integrally formed top plate and connected vertically more with the top plate The piping lane segment is inserted in by the wallboard in corresponding cupuliform slot and is erected on the bottom plate by a wallboard, and institute It states and is formed with gap between the surface of wallboard and the internal face of corresponding cupuliform slot;
It will be connected and fixed by cast-in-place linkage section between two adjacent piping lane segments;
Bitumastic layer is formed in filled bitumen matizhi in the gap, and the top surface of the bitumastic layer is away from described The notch of cupuliform slot has a setpoint distance;And
Waterproof concrete structure is formed in water-proof concrete is perfused in the gap, institute is closed by the waterproof concrete structure State the notch of cupuliform slot.
7. the construction method of half prefabricated assembled pipe gallery as claimed in claim 6, which is characterized in that mixed in perfusion waterproof Further include before solidifying soil:
Pitch spunyarn layer is formed in the gap filling pitch spunyarn or filled bitumen flax silk forms Bituminous hemp fiber layer, and will be filled out Pitch spunyarn or the Bituminous hemp fiber compacting filled.
8. the construction method of half prefabricated assembled pipe gallery as claimed in claim 6, which is characterized in that construction bottom plate it Before, further include:
In the bottom of foundation pit construction bottom cushion;
It is laid with base plate waterproofing on the bottom cushion, the base plate waterproofing is coated into the end side of the bottom plate simultaneously upwards It is attached at the top end face of the cell wall of the corresponding cupuliform slot positioned at end side, and then the cup is stretched into the end of the base plate waterproofing It fits in shape slot and with the internal face of the cupuliform slot.
9. the construction method of half prefabricated assembled pipe gallery as claimed in claim 8, which is characterized in that the wallboard includes Framed side wallboard positioned at side;
After the framed side wallboard is erected in corresponding cupuliform slot, wallboard waterproof is laid in the outer surface of the framed side wallboard Layer, and the bottom end of the wallboard waterproof layer is placed in corresponding cupuliform slot.
10. the construction method of half prefabricated assembled pipe gallery as claimed in claim 9, which is characterized in that further include:
Waterproof roofing layer is laid on the top plate and the cast-in-place linkage section, and by the end of the waterproof roofing layer and institute State corresponding end pressing connection on wallboard waterproof layer.
CN201810551369.XA 2018-05-31 2018-05-31 Half prefabricated assembled pipe gallery and its construction method Pending CN108560586A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810551369.XA CN108560586A (en) 2018-05-31 2018-05-31 Half prefabricated assembled pipe gallery and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810551369.XA CN108560586A (en) 2018-05-31 2018-05-31 Half prefabricated assembled pipe gallery and its construction method

Publications (1)

Publication Number Publication Date
CN108560586A true CN108560586A (en) 2018-09-21

Family

ID=63552627

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810551369.XA Pending CN108560586A (en) 2018-05-31 2018-05-31 Half prefabricated assembled pipe gallery and its construction method

Country Status (1)

Country Link
CN (1) CN108560586A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667280A (en) * 2018-10-01 2019-04-23 南宁市城乡规划设计研究院 A kind of assembled piping lane and preparation method thereof that plateization is prefabricated
CN109680719A (en) * 2019-02-25 2019-04-26 北京市市政工程设计研究总院有限公司 A kind of jigsaw assembled pipe gallery and construction method
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN113668624A (en) * 2021-08-24 2021-11-19 中国建筑第八工程局有限公司 Device and method for testing waterproof performance of assembled comprehensive pipe rack node
CN113668623A (en) * 2021-08-24 2021-11-19 中国建筑第八工程局有限公司 Mechanical property test device and method for connection node of assembled cup groove

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101433344B1 (en) * 2014-04-30 2014-08-22 주식회사 케이씨산업개발 Method for constructing a culvet structure assembly
CN203924114U (en) * 2014-06-24 2014-11-05 刘小沙 Prefabricated pipe gallery
CN104674847A (en) * 2015-03-05 2015-06-03 东北大学 Novel assembling type precast concrete urban comprehensive pipe gallery and construction method thereof
CN204531213U (en) * 2015-01-14 2015-08-05 中国建筑第八工程局有限公司 Water-bound is draped over one's shoulders inside parapet of roofing
CN106013228A (en) * 2016-06-24 2016-10-12 中国建筑股份有限公司 Overlapping integral type prefabricated assembly structure for comprehensive pipe gallery and construction method thereof
CN208578067U (en) * 2018-05-31 2019-03-05 中国建筑第八工程局有限公司 Half prefabricated assembled pipe gallery

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101433344B1 (en) * 2014-04-30 2014-08-22 주식회사 케이씨산업개발 Method for constructing a culvet structure assembly
CN203924114U (en) * 2014-06-24 2014-11-05 刘小沙 Prefabricated pipe gallery
CN204531213U (en) * 2015-01-14 2015-08-05 中国建筑第八工程局有限公司 Water-bound is draped over one's shoulders inside parapet of roofing
CN104674847A (en) * 2015-03-05 2015-06-03 东北大学 Novel assembling type precast concrete urban comprehensive pipe gallery and construction method thereof
CN106013228A (en) * 2016-06-24 2016-10-12 中国建筑股份有限公司 Overlapping integral type prefabricated assembly structure for comprehensive pipe gallery and construction method thereof
CN208578067U (en) * 2018-05-31 2019-03-05 中国建筑第八工程局有限公司 Half prefabricated assembled pipe gallery

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667280A (en) * 2018-10-01 2019-04-23 南宁市城乡规划设计研究院 A kind of assembled piping lane and preparation method thereof that plateization is prefabricated
CN109706953A (en) * 2019-01-21 2019-05-03 吉林建筑大学 Mold and drawing-die construction method for assembly concrete hypogee sole plate
CN109706953B (en) * 2019-01-21 2023-10-13 吉林建筑大学 Die for foundation slab of assembled concrete underground building and drawing die construction method
CN109680719A (en) * 2019-02-25 2019-04-26 北京市市政工程设计研究总院有限公司 A kind of jigsaw assembled pipe gallery and construction method
CN113668624A (en) * 2021-08-24 2021-11-19 中国建筑第八工程局有限公司 Device and method for testing waterproof performance of assembled comprehensive pipe rack node
CN113668623A (en) * 2021-08-24 2021-11-19 中国建筑第八工程局有限公司 Mechanical property test device and method for connection node of assembled cup groove

Similar Documents

Publication Publication Date Title
CN108560586A (en) Half prefabricated assembled pipe gallery and its construction method
CN106013228B (en) A kind of overlapping monoblock type pipe gallery prefabricated assembly structural and its construction method
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN206052779U (en) A kind of prefabricated pipe gallery splicing structure
CN106284412B (en) A kind of prefabricated pipe gallery and construction method
CN205776348U (en) A kind of overlapping monoblock type pipe gallery prefabricated assembly structural
CN106988343A (en) A kind of town road pipeline protection structure and its construction method
CN204343339U (en) A kind of temporary support columns waterproof base plate
CN208280185U (en) A kind of post-cast strip advanced water-stopping construction
CN108560588A (en) Assembled pipe gallery and its construction method
CN110306595B (en) Co-building structure of electric power pipe gallery and flood control wall and construction method thereof
CN113668612A (en) Modular combined prefabricated electric power working well and construction method thereof
CN205444254U (en) Deformation joint structure
CN208578067U (en) Half prefabricated assembled pipe gallery
CN206052778U (en) A kind of steel and Combined concrete piping lane
CN215106098U (en) Prefabricated post connection structure
CN103669400A (en) Typical construction method for prefabricated tube bank
CN107268675A (en) Laying method and structure of combined multi-bin underground comprehensive pipe gallery
CN212129250U (en) Construction structure for additionally arranging collecting groove on post-cast strip of high-water-level foundation
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN209620049U (en) A kind of pin-connected panel anchor bolt frame girder construction
CN110359495A (en) Comprehensive pipe gallery structure seam construction and its construction method
CN110344441A (en) Sponge urban road designed with comprehensive pipe gallery and road construction method
CN210887303U (en) Coincide assembled utility tunnel structure
CN214116461U (en) Embankment ballast

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180921